eskdalemuir route to a...
TRANSCRIPT
Presentation Outline
Wind turbines
Eskdalemuir Array and Importance
2005 Report to EWG
Budget as it stands
Recent discoveries
Route to a solution
Who We Are
Xi Engineering Consultants Ltd. formed in 2011 by spinning the
Vibration & Engineering Solutions team out of Reactec Ltd.
Our focus is noise and vibration. We have provided solutions to
many sectors including:
Onshore wind and offshore wind
Tidal stream turbines
Semiconductor industries
Health and occupational safety
Construction, buildings and planning
Marine vessels and boats
Physics of Wind turbine vibrations
Multiple drivers for vibration
Wind Profile
Random fluctuations in wind
Blade pass pressure fluctuations
Rotor imbalance
Drive train imbalances
Gear meshing frequencies
Electromagnetic resonances
Turbine Vibration Modes
2 4 6 8 10 12 14 16 18 200
0.001
0.002
0.003
0.004
0.005
0.006
0.007
0.008
0.009
0.01
Frequency (Hz)
z -
velo
city a
mp (
mm
s-1
)
1st Bending tower
2n
d B
endin
g
tow
er
A
2n
d B
endin
g t
ow
er
B
Tors
ion
Bla
de B
Bla
de C
Bla
de D
Breathing
Axial
High order breathing
Forced
Eskdalemuir Seismic Array (EKA) and Eskdalemuir
Unique MoD resource with unparalleled capabilities for forensic seismology
And
A region of significant wind resource for potential onshore developments
Eskdalemuir Seismic Array
9
The seismometer array at Eskdalemuir (EKA) has two arms, each of ten seismometers.
EKA became operational on the 19th May 1962.
Well Calibrated Station
Pre-dates Primary Status
Only site in the UK
Eskdalemuir Seismic Array
10
The array has recorded signals associated with about 400 nuclear explosions (up to 15,000 km away from EKA).
Kazakhstan 5,250km , 100t Chemical Pakistan 6,196km, Nuclear
Main seismic signals of interest are P waves with a frequency passsband of 0.5 – 8Hz
THERE MUST BE NO RISK TO SAFEGUARDING THE ARRAY
11
Seismic Budget defined in 2005
Based on the work of Schofield (2001) in which seismic measurements near the Stateline wind farm, Washington, USA were taken. Vestas V47
Previous work and current EKA safeguards
Variable Comment Value
r Distance of wind farm from EKA
P Power of turbines in target wind farm
N Number of turbines in target wind farm
Constants
A0 Source term - Amplitude of reference wind farm 24 nm
rref Distance of reference wind farm from measurement site 1000 m
Pref Power of turbines at reference farm 0.66 MW
Nref Number of turbines at reference wind farm 399
f Frequency of mid-point of band pass 4.5 Hz
Q Non-geometry attenuation constant 50
v Velocity of ground vibration 2000 m/s
Algorithm used to predict the amplitude of ground vibrations produced by a wind farm is then given as:
Previous work and current EKA safeguards
Agreed rationale of doubling median background noise = 0.336nm
Based on ground attenuation i.e. Ground characteristics and distance to array (80km statutory consultation zone reduced to 50km radius)
Based on interacting waveforms (10 +10 = ~14 turbines)
Based on utilisation of turbines (beneficial to developers)
Study was performed at Dun Law wind farm to verify the source term
Calculated at 4.5 Hz as this was deemed to be frequency with low noise and signals observed from wind turbines
2005 budget and current EKA safeguards
MOD perspective
2005 Model is fit for purpose
Budget Managed on a first come first served basis
Budget has been reached - MOD have periodically released the Budget tables which consist
of;
Table 1 – Developments up to the Seismic Ground Vibration Threshold ~950MW
Table 2 – MOD objections ~ 690MW
Table 3 – Withdrawn Applications ~ 150MW
No proven mitigation
Multiple Public Inquiries
2011 study was conducted on an 2.5MW machine
Discovery that Dunlaw data was processed in velocity
Geology not the same at Stateline and Eskdalemuir
When processed in displacement the largest peaks attributable to turbines is not in 4-5Hz
range
Therefore a review of the current budget tool accounting for the frequency pass band of
interest is required.
Recent Developments
Recent Developments
Power spectral density in decibels(dB) from Kelhope 1 site about 2.3 km from Dun Law wind farm. Seismic
ground vibration PSD in dB relative to velocity power in units of (m/s)2/Hz (green spectrum) and dB
relative to displacement power in units of m2/Hz (red spectrum)
Reformed EWG
Proposed study in two stages.
The purpose of Stage 0 is twofold;
1. Provide the EWG with information to determine whether it is worthwhile pursuing the
substantive Stage 1 research envisages in technical proposal Appendix A
2. Provide Valuable input to the drafting of the scope of the substantive Research in Stage
1
Stage 1 Study - Quantify the wind turbine SGV
source-term
Validation of data sets and algorithms analysed/verified/developed in Stage 0
Consider wind direction and wind speed.
Compare Craig results with Dun Law (26 times 660KW turbines) SGV data acquired in 2004, and data
presented in the Schofield (2000) report from analysis of Stateline wind farm data.
Remove background noise
Assess site effects, statistical properties of SGV data (Craig/Dun Law), and the relationship with
physical parameters of wind turbines (e.g., rated-power, tower height, blade diameter).
Develop an analytic model, based on physics as much as possible, to predict SGV from wind turbines
with robust treatment of uncertainty.
Consider whether the “utilisation” factor (currently 60% in the Styles Model) needs revisiting
Safeguarding management model/software tool.
End July stage 0 reporting – is their likely to be additional budget?
As yet undefined Stage 1 to follow
Current estimates indicate that the science may be resolved by early 2014
Policy to follow
Getting there
Contact
21
Dr Mark-Paul Buckingham
Xi Engineering Consultants
www.Xiengineering.com
0131 247 7580
*Patent granted, Europe, US,
No risk to safeguarding
Xi (then Reactec) developed a mitigation technology as understood safeguarding required for the EKA
© Copyright 2013 © Copyright 2013
The Aviation Challenge
• Introduction.
• UK Airspace - a Finite Resource.
• Impact Upon Primary Surveillance Radar.
• MOD Perspectives.
• Conclusion.
© Copyright 2013 © Copyright 2013
UK Airspace - Construct
• UK Airspace - 1964/Today.
• Controlled Airspace.
• Non-controlled Airspace.
© Copyright 2013 © Copyright 2013
Non-controlled Airspace Users
Image Copyrights: airbus.com, MOD, civilaviation.co.uk, frogwell.com, aircardets.org, BBC, The Met Office
© Copyright 2013 © Copyright 2013
MOD - Low Flying
• Political and operational landscape.
• The UK Military Low Flying System.
• Balancing the requirement for operational low
flying.
• Quality versus quantity.
• To object or not object; that is the question.
© MOD
© Copyright 2013 © Copyright 2013
Unlocking Capacity
Potential Ways Forward:
• Greater Cross-Government Co-operation….
• Mitigation Solution Development…
• A “Secondary” Way…
© Copyright 2013 © Copyright 2013
Conclusion
• UK Airspace - a Finite Resource.
• The Impact Upon Primary Surveillance Radar.
• MOD Perspectives.
© Copyright 2013
Mark A Van Vogt MA MRAeS FInstLM MCMI
Aviation/ATM Principal
07794085211
SP Transmission
Delivering Infrastructure for Renewables
Colin Taylor
Head of Transmission Programmes
Large Increase in offshore & onshore wind generation
Base case investment delivers MWs and boundary capacity in line with Gone Green scenario
Increased import capacity will further enhance security of supply for Scotland
Flexibility to fund investment over and above Gone Green if required
Delivering Energy Policy
Majority of 275kV network over 40 years old
£1.3bn (~ 65%) of investment provides connections & capacity for wind generation
Strong Incentives for Delivery - By 2020 we will:
Increase transmission capacity to England to 6.6GW (now 2.8GW)
– a further 2.GW+ (ECHVDC) triggered by submission to Ofgem
Connect a further 2.5 GW of wind generation (total of 4.4GW ) to align with Gone Green
scenario - revenue driver to fund up to 7GW if required
15% of our substation assets renewed
Replaced over 800 circuit km of overhead line
– modern transformers and conductors increase transfer capability
£0.8bn (~ 35% )of investment needed to modernise the network by 2020
Significant sections of 132kV network over 60 years old
Investment Plan based on nationally agreed central scenario (Gone Green)
RIIO-T1 Overview
Meeting the Delivery Challenge
Using the latest technologies • Getting the most out of existing assets
• Installation of shunt and series capacitors
• Use of advanced inter-tripping technologies to facilitate higher transfers
• HVDC “bootstraps”
Market • Developing the capacity and capability of the supplier base
• Attracting new suppliers
• Changing the contractual model
People • Developing existing staff and recruiting staff with the necessary skills
• Significant graduate and apprentice programmes to grow our own workforce
• Increase in staff focused on transmission activities since 2011 of circa 200
Stakeholders • Government communities and landowners
• Strong focus on consents with Scottish Government
• Close liaison between SO and TOs
• More flexible approach to land rights, encourage engagement from developer at
early stage
Denny North Substation
• All project consents achieved in April 2012
• Overhead line enabling works progressing to schedule
• Substation platform works at Denny North well advanced
• SHETL circuits to be commissioned late 2015
• Project complete end 2016
• Platform dimensions – 62,500 m2
• Peat excavated from site 100,000 m3 (70% deposited around
the site and 30% removed from site)
• Clay excavated from site 80,000 m3 (all of it is stored on site,
treated with lime to make it suitable for re-use on site and
used as part of the substation base).
Shunt Capacitors – MSDCN Units
• Increase Scotland-England transfer capability
without building new lines
• Units completed at Elvanfoot & Windyhill
substations will increase export capability from
2.8GW to circa 3.1GW
Capacitors
Reactors
Resistors
• Units under construction at Moffat and Longannet
will further increase export capability to 3.3GW
Moffat Substation
• New substation energised Q3 2013
• MSCDN completed end 2014
• Series compensation unit completed end 2015 as part
of 4.4 GW upgrade
• Major new 400kV substation
• Connects to Scotland-England interconnector
• Renewables generation collector substation
• Will contain MSCDN and series compensation equipment
OHL Modernisation
• Modernisation of XV Route (Strathaven/Kilmarnock South 400kV)
• Driven by condition of line
• Conductor replacement with modern equivalent increases capacity
by circa 40%
• Conductor works complete end 2013
Key Activities and Challenges for 2013
• RIIO-T1 provides a robust framework for investment
delivery
– stable mechanism to fund investment
– strong incentives on output delivery
• We have made the most of our “fast-track year”
– recruitment, market development, engineering
– good progress on project delivery
– major focus on consents
• We are committed to continuous improvement in our
engagement with all stakeholders
– TOs, SO, DNOs
– Government at all levels
– Developers
In Conclusion
Delivering Energy Policy Objectives
2
GB TRANSMISSION WIRES OWNERSHIP
SHE Tx
SP Tx
National Grid
Electricity Transmission
NETSO
OFTO
OFTO
OFTO
OFTO
OFTO
EXISTING
NETWORK
WESTE
RN
ISLES
Sky
e
ORKN
EY
Dounrea
y Thurs
o
Ullapoo
l
Foyers
Beau
ly Keit
h Peterhe
ad
ABERDEE
N
Blackhillo
ck
Kintor
e
Elgi
n
Fraserbur
gh
DUNDE
E
Tealin
g
PERT
H
Fort
William
Oba
n
Arra
n
Mul
l
Tire
e
Col
l
Isla
y
Jura
Kirkwa
ll
Storno
way
Shi
n
Grudie
Bridge
Erroch
ty
Campbelto
wn
F. Augustus
Killin
Dunoo
n
Inverara
y
But
e
Boat of Garten
Dunbeath
Tarland
Macdu
ff
Braco
Port
Ann
Carradale
Cassle
y
Cruach
an
Alness
Bonnybri
dge Windyhill
Afri
c
Nair
n
SHETLA
ND
Lerwi
ck
Key:
132kV circuit
275kV circuit
400kV circuit
M:\planning\_Transmission Development\DIAGRAMS AND GEOGRAPHICS\110425-2020-Transmission Reinforcement Strategy-Mahesh Dayal.ppt
• 1200 Contractors/Consultants
presently directly employed
• Open4business Initiative
• HVDC cable supply and
vessel constraints
• Overhead Line Framework
• Substation framework now
awarded
Supply Chain
• 250 SHE Transmission Staff – recruiting an
additional 60
• 1200 Contractors/Consultants
• 25 Overhead Line Apprenticeships per year
• 5 Technical Staff Trainees
• 5 Graduates
Resources / Skills