escalation estimating principles and methods

Upload: basit-anwar

Post on 07-Jul-2018

218 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/19/2019 Escalation Estimating Principles and Methods

    1/16

    Lecture 5-1CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET© Dr. Farrukh Arif, Assistant Professor, NED UET

    CE-591- Cost Engineeringand Control

    ESCALATION ESTIMATINGPRINCIPLES AND

    METHODS USING INDICES

    Lecture 5-2CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Introduction Recommended practice (RP) of AACE

    Defines basic principles and methodological buildingblocks for estimating escalation costs using

    −forecasted price

    −or cost indices

    Escalation estimating is an element of both the costestimating and risk management processes

    RP is focused on quantification, not on escalationtreatment

  • 8/19/2019 Escalation Estimating Principles and Methods

    2/16

    Lecture 5-3CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Outline

    Background

    General Principles and Methods

    General Principles

    Basic Escalation Cost EstimateRelationship Using Indices

    Price and other Econometric Indices

    Pricing Versus Costs

    Price Index Forecasts

    Addressing Costs Over Time (CashFlow)

    Addressing Cost Account Detail

    Matching Indices to Cost Accounts(Weighting Indices)

    Adjusted or Composite Indices

    Using Price Indices to NormalizeHistorical Project Costs

    Escalation on Contingency

    Escalation Uncertainty andProbabilistic Methods

    Lag and “Sticky Prices”

    Accuracy

    Lecture 5-4CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Background

    Escalation is a provision in costs or prices for changes intechnical, economic and market conditions over time.

    Increases with the volatility and uncertainty of Economy

    Can have a tremendous impact on estimates, bids,profitability

    A common source of claims and disputes if not addressed

    explicitly Escalation as defined here excludes contingency and

    currency exchange impacts, but includes inflation

    Inflation is generally defined as the overarching effect onprices of excess money supply

  • 8/19/2019 Escalation Estimating Principles and Methods

    3/16

    Lecture 5-5CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Background

    Some of the drivers of escalation, in addition to inflation include

    −Changes in market conditions,

    −Technology,

    −Regulation,

    −General industry or regional-wide productivity and

    −Other economic factors that generally affect an economic sector orsegment.

    Technology and regulation changes covered by escalation are generalevolutionary changes in design tools or regulations not immediately

    impacting the project Major technology changes or regulations that directly or immediately

    impact the project would be covered in contingency or reserves

    Lecture 5-6CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Background

    Escalation does not include changes in cost or priceresulting from potential changes in company or projectspecific strategies, actions, risk events or other changes

    Those pricing risks should be addressed by contingencyestimates.

    Segregating escalation from exchange rate impacts ismore challenging because both are driven by economicfactors

    This RP deals only with quantification not the escalationtreatment

  • 8/19/2019 Escalation Estimating Principles and Methods

    4/16

    Lecture 5-7CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Basic Escalation Cost Estimate Relationship

    Using Indices

    Methods covered in this RP require input from economistsas appropriate

    Such as measured or forecast cost and prices, usuallyexpressed with a relative index

    Convert the base year cost to a value of 1.00 or 100 andexpress the costs in all other years relative to that base

    Escalation cost is the escalated cost minus the base costas shown below

    Lecture 5-8CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Basic Escalation Cost Estimate RelationshipUsing Indices

      Example

    An item costing $100 in the base year (index = 1.00) and a forecast index of1.15 for the year of payment, the escalation cost is as follows:

    = $100 · [1.15/1.00 −1] = $100 · 0.15 = $15

    The target date can be in the past or future depending upon the purpose ofthe estimate

    The time period that you have indices for can vary; however, reliable cost andindex data are rarely available for periods more frequent than monthly

    Quarterly or annual periods are more commonly used

    When dealing with economics evaluation, the terms “nominal” versus “real”cost may arise in discussions

    Real costs are more or less synonymous with the “base” estimate

    Nominal cost with escalated costs

  • 8/19/2019 Escalation Estimating Principles and Methods

    5/16

    Lecture 5-9CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Price and other Econometric Indices

    Escalation is driven by economic trends

    The primary econometric measures of price change over time (i.e., escalation)used by economists are price indices

    Economists usually measure price levels using market surveys

    −Survey of the price charged by producers (Producer price index,PPI)

    −Prices paid by consumers (Consumer price index, CPI)

    Other econometric indices

    −employment cost indices, average hourly earnings, etc.), capital spending, laborproductivity

    Primary sources of Historical price/indices

    −U.S. Bureau of Labor Statistics (BLS), Eurostat or Statistics Canada

    Lecture 5-10CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Price and other Econometric Indices

    Using Consumer Price Index (CPI) as index for escalationestimation is not an effective practice for accurateescalation

    The consumer targeted by the CPI reflects a personwhose spending patterns and market generally have littlerelevance to capital project ending or markets

    The only time that the CPI works well is when the  only escalation occurring is inflation 

  • 8/19/2019 Escalation Estimating Principles and Methods

    6/16

    Lecture 5-11CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Pricing Versus Costs

    The prices paid by (or cost to) a consumer may differ from the supplier’s costs

    Supplier prices charged to the consumer include markups for their overheadand profit, contingency and other premiums

    Understanding these distinctions is important in escalation estimating becauseit affects the

    “As an example of the subtleties of indices, consider the employment cost index (ECI)from the BLS, which is commonly used to track the cost or price of labor. The ECI measures changes in wages and compensation paid to a given type of worker. This may fairly track the costs to an employer for that worker. However, consider the price that a contractor employer will charge a customer for contract services. That price will include not only trends in wages, but trends in markups and premiums that the contractor will add to their bid or invoice. In a volatile market, the markups generally will 

    not follow the same trend as wages. Therefore, the ECI may work for the contractor estimator who is estimating their internal escalation costs, but not for the customer’s estimator who is estimating the price they will have to pay for the contracted labor services. selection and use of indices “ 

    Lecture 5-12CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Price Index Forecasts

    Economists study historical trends and build econometric modelsthat forecast future price index values, generally at an aggregatelevel

    The models of price change for specific goods or services areusually tied to macroeconomic models

    Some economists rely less on models and more on expert opinion,market surveys

    Some companies tend to rely more on the forecasts of theirprocurement and contracting specialists who have some level ofinsight as to the specific market of their company

  • 8/19/2019 Escalation Estimating Principles and Methods

    7/16

    Lecture 5-13CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Price Index Forecasts

    Estimators must recognize that most economists are notexperts in specific capital project costs or sub-markets

    Estimators and economists must work together to find anadjusted combination of indices that can serve as proxies forelements of project or product costs

    Most government agencies do not prepare long-term forecastsof detailed indices

    Lecture 5-14CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Addressing Costs Over Time (Cash Flow)

    The basic escalation cost estimating relationship (CER)presented at the start of the RP assumes spending on oneitem in one point of time such as for purchasing a discreteitem

    Spending is usually spread out over time for manyaccounts such as labor or bulk materials

    For this RP, we will use the phrase cash flow to representspending distributed over time

  • 8/19/2019 Escalation Estimating Principles and Methods

    8/16

    Lecture 5-15CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Addressing Costs Over Time (Cash Flow)

    Figure 1 illustrates three primary methods for addressingcosts incurred over time

    Lecture 5-16CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Addressing Costs Over Time (Cash Flow)

      Mid-point spending method: This 

    method sets the single target date as the mid-point between the start and end 

    of spending on the subject cost 

    account. This is the simplest approach and requires no knowledge of the 

    actual spending pattern. It is most amenable for Class 5 and 4 base cost 

    estimates for which cost and schedule 

    information is limited. It is not very reliable if either cash flow or index 

    trends are inconsistent over time.

  • 8/19/2019 Escalation Estimating Principles and Methods

    9/16

    Lecture 5-17CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Addressing Costs Over Time (Cash Flow)

      Median spending method: This method 

    sets the single target date as the 

    median date of the cash flow distribution (i.e., half the spending is 

    before and half after this date). This requires some knowledge of the 

    spending pattern even if just to know if it has an early or late bias (i.e., before 

    or after the mid-point). It is most 

    amenable for Class 5 and 4 base estimates for which cost and schedule 

    information is limited. While it addresses asymmetric spending 

    patterns, it is still not very reliable if 

    index trends are inconsistent over time.

    Lecture 5-18CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Addressing Costs Over Time (Cash Flow)

      Period spending method: this method breaks the spending into time increments, typically by month, quarter or year depending on the typical duration of the spending (i.e., monthly estimates are usually not justified for projects of many years duration). For each time increment of spending for each account, the simple method in the previous section is applied with the target date for the increment as the mid-point of the incremental period. Alternatively, the percent index change for each period can be applied 

    cumulatively to derive the target year index.For example, if you are estimating costs in year 0  (index=1.00), and the spending willbe in year 3, and prices increase 5 percentper year, the price index for year 3 is 1.05 x1.05 x 1.05 = 1.16 (i.e., escalation for thatitem is 16%).

  • 8/19/2019 Escalation Estimating Principles and Methods

    10/16

    Lecture 5-19CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Addressing Cost Account Detail

    The basic escalation CER and cash flow treatments canbe applied to any level of detail of cost breakdown fromoverall cost, to very detailed cost accounts

    However, neither a single account value nor an extremelydetailed account breakdown is recommended for a project

    Users should establish accounts that meet the followingprinciples

    −Use accounts/indices that address differential price trends

    between accounts.−Use accounts/indices that address levels of detail for variousestimate classes.

    Lecture 5-20CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Addressing Cost Account Detail

    At the highest level, material, office and field labor costaccounts typically have different price trends and need to besegregated

    Further breakdowns of material are equipment (generally bymajor types), steel, concrete, piping, etc

    For buildings and infrastructure work, this corresponds roughlyto the Masterformat division accounts excluding the process

    equipment subgroup For capital projects, breakdowns by work breakdown (e.g.,

    area/unit/system, CSI Uniformat, etc.) can be used

    However, more index weighting will be required in thisarrangement

  • 8/19/2019 Escalation Estimating Principles and Methods

    11/16

    Lecture 5-21CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Matching Indices to Cost

    Accounts (Weighting Indices) It is a challenge to determine the best way to apply disaggregated

    indices to aggregated or overall project, product or service costs forwhich no single reliable aggregated forecast index is available

    There are separate indices for each of the major resources that go intoor make up a project’s cost structure

    The estimator must create weighted composite indices to apply to anestimate category based on the composition of the estimate categoryrelative to the items represented by the indices

    Lecture 5-22CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Matching Indices to CostAccounts (Weighting Indices)

      For Example

    A typical process plant has significant pipe material costs. Most of thepiping material cost, as estimated, is for pipe spools from a fabricator.The spool price includes the cost for pipe, fittings and shop laborcosts. The available disaggregated indices do not cover spool prices;therefore, the estimator must create an aggregate or “proxy” index forshop-fabricated pipe that includes a weighted mix of pipe costs, fittingcosts and shop labor as shown in the following example:

  • 8/19/2019 Escalation Estimating Principles and Methods

    12/16

    Lecture 5-23CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Matching Indices to Cost

    Accounts (Weighting Indices) The following criteria will help the user select and develop price indices for use

    in escalation estimating: Indices should

    Use or be based on industry or government sources that are generallyrecognized as reliable and are readily available.

    Be generally applicable to the subject industry in the primary regions where acompany performs or will perform capital projects, maintenance andoperations or manufacturing.

    Be specific to the major cost types found on all the company’s projects orproducts.

    Be easy to update, modify and maintain as an ongoing reference source.

    Lecture 5-24CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Adjusted or Composite Indices

    A challenge to using indices is dealing with the fact thatthey do not track micro-economic trends, markups, and soon

    This is because contractor’s prices include markups,premiums, productivity factors

    Estimators and other team members (e.g., procurementlead) must add their knowledge for adjusting the indices tomicroeconomic conditions

  • 8/19/2019 Escalation Estimating Principles and Methods

    13/16

    Lecture 5-25CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Adjusted or Composite Indices

    One method is to start with a base index that is independent of micro-market trends (e.g., an ECI from the BLS), and then use an index ofcapital spending (a proxy of market conditions) in the micro-market tomodify the base index

    This approach is based on two rational hypotheses−1) a given market’s pricing will be correlated to the extent that demand is more orless than the supply in that market, and

    −2) supply will be more or less inelastic in the short term (period of interest toprojects) for items that require significant investment of time and/or resources tocreate (e.g., skilled labor, major equipment, etc). Fortunately, economists do track

    and forecast capital spending in many markets

    The general form of the index adjustment can be expressed asfollows:

    Lecture 5-26CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Adjusted or Composite Indices

      Example

    Consider the prior unadjusted example given of an item costing $100in the base year (index = 1.00) and a forecast index of 1.15 for theyear of payment. The unadjusted escalation cost is as follows:

    = $100 · [1.15/1.00 − 1] = $100 · 0.15 = $15

    If the capital expenditure spending level index was 1.00 in the base year,

    and 1.25 for the year of the payment, and the exponent was 0.5, the

    adjusted escalation cost is as follows= $100 · [1.15/1.00 · (1.25/1.00)0.5 − 1]

    = $100 · [1.15 · 1.12 − 1)

    = $100 · [1.29 − 1)

    = $29

  • 8/19/2019 Escalation Estimating Principles and Methods

    14/16

    Lecture 5-27CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Escalation on Contingency

    Contingency, by AACE’s definition, is a cost expected tobe spent

    It is logical to apply escalation to contingency like anyother estimated cost account

    The weighted index for contingency will typically reflect theweighting of cost accounts for the project as a whole

    Lecture 5-28CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Exchange Rate Interaction

    This RP recommends segregating escalation and exchange rateimpacts for projects with resources priced in currencies other than the“base” currency

    However, perfectly clean segregation is not possible because bothescalation and exchange rates are driven by economic conditions

    The optimal approach using segregation is to estimate escalation onan item using a price index that reflects the price trend for that item inthe location where it is sourced

    For example, if a base estimate was reported for a Canadian project inCanadian dollars at current exchange, but an item was to be boughtfrom the US using US dollars, use a US-based price index for thatitem. Then, estimate the $US/$CAN exchange rate impact separately.

  • 8/19/2019 Escalation Estimating Principles and Methods

    15/16

    Lecture 5-29CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Exchange Rate Interaction

      Example

    Given:

    Price index from US reference source today is 1.10 and 1.32 at plannedpurchase date

    Exchange rate is 0.85 $US per $CAN today and 1.02 at plannedpurchase date

    Then:

    Escalation: ($100 price in $CAN) x (1.32/1.10-1)

    = $100 x 0.20 = 20 $CANExchange: ($100 price in $CAN) x (0.85/1.02-1)

    = $100 x -0.17 = $17CAN

    Lecture 5-30CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    Miscellaneous Points Probabilistic Estimation: One method of obtaining a range is to apply

    Monte-Carlo simulation to the estimate model. In this approach, theuncertain index, factors and timing inputs are substituted withdistributions.

    Lag and “Sticky Prices” : Another uncertainty in escalation estimating,particularly as it regards consideration of market swings, is thatsuppliers do not immediately change their bidding and pricing levels orstrategies in lock-step with underlying trends in commodity, wages and

    other costs to them

    Accuracy: Estimators are cautioned not to expect too much accuracyfrom cost indexes and escalation estimates. The indices areapproximations intended to represent the average trends for a largegroup of projects in a broad region

  • 8/19/2019 Escalation Estimating Principles and Methods

    16/16

    Lecture 5-31CE-591 Cost Engineering and Control 

    © Dr. Farrukh Arif, Assistant Professor, NED UET

    End of Lecture