electrical design and rates document

25
 #$%&' $ ()* *(#'+%,)-'  #$%#&% '()$ &*( +)$'() ' ,-.,'

Upload: kantha

Post on 26-Feb-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 1/25

 

#$%&' $ ()* *(#'+%,)-'

  #$%#&%'()$ &*( +)$'() '

,-.,'

Page 2: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 2/25

Page 3: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 3/25

  #$%&

#''()'*#+#*(,%-./012/3%-4)5/6478947#

pROJ  Ts

#5:#

;# <=>?  $%& '&' # '()*:3@A=03,'#

9B

#C626DE60

#7899# F# :# :#4

=GG #*0%H3-235G#CI J#

+,-./-*/

#*0.1,*23,40.

#501,

#&6786#

17  JAN

  2 12

KL6#MN/5-O50O#,%-./012/3%-

#,%./

#4# 7897MJ#PL32L#506#5QQG325EG6#P3/L#6RR62/#R0%D#SGM#T5-150 #

7897#3.#.6-/#L606P3/L#R%0# %10#3-R%0D5/3%-#5-O#-626..50 #52/3%-:#

  # 9:;9<#<=)>+#?;<#+)=(@=<@

#5;(+)<95)A;(

#5;+)+#

KL6#N/5-O50O

# ,%./.

# .L5GG# E6#1.6O#%-G #R%0#-6P#2%-./012/3%-#P%0U.#5/#Q0%H3-26.# .3-26#/L6#

V%0UD6-#)62%H60 #)5/F#5-O#/L6#SH60L65O#)62%H60

# )5/6

#R%0#/L6#Q0%H3-26.#506#2%DQ1/6O#

%-#/L6#R%GG%P3-W#E5.3.:#

(BC#50.1,*23,40.1D

# X8Y

#%R

#/L6#P%0U

#3.

#O%-6#E #/L6#Q03H5/6#2%-/052/%0.#5-O#/L6#E5G5-26#

78Y

# E

#/L6

# ,'Z#O3062/#G5E%10:#

#$%&

+B* 43B#50..B3,40.1D# B8Y#%R#P%0U#E #/L6#*03H5/6#,%-/052/%0.#

98Y #%R#P%0U.#E #/L6#,'Z#O3062/#G5E%10#

S-# /L3.

# E5.3.

# /L6# R%GG%P3-W# G5E%10# 05/6.# +# %H60L65O# 062%H60 # 05/6.# 506#1.6O# R%0# /L6#

25G21G5/3%-#%R#N/5-O50O#,%./.:#

E-FG

#H-I02*#<B30 B*#<-,B#

#'

# (BC

#50.1,*23,40.#J0*K1#

44G

# +B* 43B#50..B3,40.

#C0*K1#

EIFG; B*LB-/#<B30 B*M

#<-,B#

4G# (BC#50.1,*23,40.#J0*K1#

44G# +B* 43B#50..B3,40.#J0*K1#

<1G#687N&#OB*#P-I02*#L02*#

<1G#8QRN&#OB*

#P-I02*

#L02*#

<1G#88SN&

#OB*

# P-I02*#L02*#

<1G#8TSN&#OB*# P-I02*#L02*#

6G# H=:;9<

#U

#;%><V>=@#<>5;%><W

#<=)>+

#?;<#;)V><

#5>:

#J;<X+#

<%0#5GG

#%/L60#[%E.

#6\26Q/#-6P#2%-./012/3%-#P%0U.#/L6 #R%GG%P3-W#05/6.#.L%1GO#E6#5QQG36O:#

H-I02*#<B30 B*M

#<-,B

# &# <1G#6T6N&

#OB*

#P-I02*#L02*#

; B*LB-/#<B30 B*#<-,B# &# <1G#8TSN&#OB*#P-I02*#L02*#

Page 4: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 4/25

  #$%&' %( #)$%*#+*&+$)

,-.-) /012334/0567)&582)9/6)+ :;)< :)50=)>?5@5

)#2AB@5>

  #

)C4023)

$% %

 &'(  )* #)%&+, ( %-.(/ /'+%%  0( )1 &'2(( 3'+/( 4)./&25 4&-).6 78(.  -1 +

  #$%&'

 3'+/(

%-.(  -/  2(95(/&(: 5.:(2  &' ( ;<=> ?<= )2  @+A+ B(,5A+>  <7= *-%C 32)8-:(  +  D'2((

?'+/( %-.(

  EF%G>

 H+/3

  +.: $=<

 <).:54&)2I

  +& &'(

 4).4(//-).+2G 2+&(/ ,-8(. 0( %)* 6

D'-/

  <).4(//-).+2G J+&(  -/

)/0C7)5DDC415EC2

 & ) &'( ;<=>  ?<= +.: @+A+ B(,5A+

)F/E3)

15.:(:  0G &'( ,)8(2 .A(.& 6

D'2(( ?'+/(  EF%GI

).G@

  K J/6  L>MNO>MMM6MMPK

D'2((

  ()* '  EH+/3I

  LQA  K J/6  L>LRS>MMM6MMPK

D'26(( ?'+/( E$=<I LQA  K J/6  L>LOO>MMM6MMPK

T. &'-/ 0+/-/>  <7=

 *-%%

  -.452  +. +::-&-).+% <)/&  )1  J/6 UR>MMM6MMPK 3(2 QA )1 #

)HIC7;)

H+/3  +.: $= < <).:54&) 2I %-.(/  -. )2:(2 &) 32)8-:( V  3'+/( 1((:(2/ 5.:(2 &'( ?<=>

;<=  +.: @+A+ B(,5A+ W)0/6  D'-/  +::-&-).+% (X3(.:-&52(

  *-%%

 0( A(& 12) A /G/&(A

$5,A(.&+&-). F5.:/6

Y)*(8(2  -.

  4+/(

  )1  05%Q / 533% G 4) ./5 A(2/ > 32)3(2&G :(8(%)3(2/  +.:

) 5CC

  )&'(2

<)AA(24-+% 7/&+0%-/'A(.&/ +4&5+% 4)./&254&-). 2+&(/ /'+%% 0( +33%-4+0%( +/ 1)%%)*/6

Z-.,%(

  ?'+/(  EF [I LQA  K  J/6 N\N>MMM6MMPK

D'2(( ?'+/(  EF%GI LQA  K J/6

) .>LOL>MMM6MMPK

D'2(( ?'+/(  EH+/3I  LQA  K J/6) .

6]]\>MMM6MMPK

,-J-)$26K412) /002184/03)

,-J-.-) ,L*)$60AC2)<M532)$26K412) /002184/03)

H5N

 

)$40AC2)DM532)326K412) 1/002184/0)=4385012)BD)8/)OL@)

$ 4)AA). 4'+2,(

  )1 J/6

 LR>MMM6MMPK

  *-%%  0(

 +33%-4+0%(

  1)2

 /-.,%( 3' +/ (

/(28-4( 4)..(4&-)./ *-&'-.

  R M A

  12)A

  &' (

  :-/&2-05&-). .( &* )2Q

-22(/3(4&-8(  )1 &'(  :-/&+.4( 12)A  &'( :-/&2-05&-). .(&*)2Q6 Y)* (8 (2) 5)

&)%(2+.4(  ) 1 - A -/  +%%)*(:  -.  )2:(2  &)

  #$%#&

  :-/35&(/ *-&' 32)/3(4&-8(

45/ &)A (2/ )8(2 RM A 12)A &'( .(+2(/& 3)%( )1 &'( :-/&2-05&-). .(& *)2 Q6

HEN)-$40AC2) <M532)326K412)1/002184/0 :-/&+.4( 0(G). :)OL@)

D)&+% 4)/& 4)./-/&/  )1 + 1-X(: 4)/& +.: + 8+2-+0%( 4)/&6

F-X(: <)/&

  -/ J/6

  LR>MMM6MMPK #+2-+0%( 4)/&

  -/ J/6

  UOM6MMPK

) D26) 2K267)

@2826)40)2P1233)/9

 RMA 6

Page 5: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 5/25

3.2.2. 30A /60A , Three Phase Service Connections

A i l  30A and 60A  t h r e e p h a s e s e r v i c e c o n n e c ti o n s  to  I ndus t r ia l , Commerc ia l

a n d G e n e r a l p u r p o s e i n s t a l l a t i o n s s h o u l d  be  s upp l i ed t h r o ug h Mo u l d ed ca s e

C i r c u i t

  B r e a k e r s M C C B ) .  No  s e r v i ce cu t - o u t s s ha l l  be  used  in  these

i n s t a l l a t i on s .

3.3. Other charges

O t h e r C h a r g e s  fo r  m i s c e l l a n e o u s s e r v ic e s  are  i n c l u d e d  in the  S t anda r d

C o n s t r u r t i o n C o s t s -

  2012.

Value Added  Tax VAT) is not chargeable. There for all estimates issued for new line and

substation construction works shou ld not be included with VAT componen t over and

above the Standard Cost Estimates.

1)  G M , CEB

2)  A G M {R2)

(3} A G M (R4)

4)

  A G M (R l )

5)  A G M (R3)

6)  DG M (C C ) R l , R2, R3 R4

7)

  DG M ( P D )

 R l ,

 R2, R3 R4

8)  D G M (Pr. H M ) R l ,  l  i  R4

9)  D G M (REP P r o c u r e m e n t )

10) A F M  D i s t r i b u t i o n )  R l , R2, R3 R4 -

f.i.pl.

f.i.pl.

f.Lpl.

f.i.pl.

f.i.pl.

P l ea s e a r r ang e  to  d i s t r i b u t e a m o n g  the

r e l e va n t  b r a n c h e s

  in

 you r re g ion.

fj pl

f.i.pl.

f.i.pl.

f.i.pl.

Page 6: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 6/25

STANDARD CONSTRUCTION COST - 2012

1 . LV NEW

 LINES/CONVERSIONS/COMBINED RUNS

All  the distribution feeders shall be of 3 phase construction. The maximum length of any

distribution feeder

 with

 Fly

  7/3.4

 mm) conductor shall not exceed 1.8 km

 from

 the respective

distribution substation.

a ,

  LV

 New

 Construction

 -  Cost per km.

Following rates

 are

 only applicable for

 LV

 lines funded

 through

 the

 Decentralized Budget

and

  Provincial

  Council  Budget  and all the LV lines shall be of three 3) phase

construction.

FLY-7/3.40mm

WASP-7/4.39mm ABC

7/.134  inches

7/.173 inches

70x3+50mm2

3 Ph. 3 Ph.

COST Rs.

1,086,000.00

1.154,000.00

1.166,000.00

Following rates are applicable for Bulk suppliers, Property developers, etc.. and all other

 third

parties.

FLY-7/3.40mm

3 Ph.

WASP-7/4.39mm

3 Ph.

COST Rs.

1.161.000.00 1,229,000.00

Note:-

The cost of construction of  ph. Fly  7/3.40mm) LV line for third parties shall be Rs. 898.000.00

b LV

 Line

 Conversion - Cost per km.

FLY7/3.40mm

WASP7M.39mm

CONDUCTOR

7/.134

 Inches)

7/.173

 Inches)

CONDUCTOR

1PH/3PH.

2

 PH/3 PH.

Changing Conductor

  3PH.

Fly/Wasp

COST

 Rs.

344.000.00 245,000.00

528.000.00

41

Ceylon

 Electricity

 Board

1

Standard Construclion

 Rates-2012

Page 7: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 7/25

c . Combined

 run of LV

 Line

 on

 existing

 MV

 Line

Foliowing rates are only applicable

 for

 LV lines funded through

 the

 Decentralized

 Budget

and

 Provincial

 Council

 Budget.

CONDUCTOR

FLY-7/3.40mm

3

 Ph.

WASP-7/4.39mm

3 Ph.

ABC

3Ph.4Wire

Combined  Runon11kV/33

kV

 line cost in

 Rs.

636,000.00

713.000.00

684,000.00

d ^Combined

 run of

 LV Line

 on

 Nev/

 MV

 Line

Followiing rates

 are

 only applicable

 for

 LV

 lines funded

 through

 the

 Decentralized

 Budget

and

 Provincial

 Council

 Budget.

CONDUCTOR

FLY-7/3.40mm

3

 Ph.

WASP-7/4.39mm

3 Ph.

ABC

3Ph.4Wire

Combined Run

 on 11kV/33

kV

 line cost

  in

  Rs.

399.000.00

475,OCO.0O

579,000.00

Note.

Span

 of MV

 lines

 are

 reduced

 to the

 span required

 for

 LV. Therefore

 no LV

 poles introduced in

between MV

 Poles.

Following rates are

 applicable

 for

 Bulk suppliers, Property

 developers,

 and

 other

 third

 parties.

e Combined

 run of LV

 Line

 on

 existing

 MV

 Line

CONDUCTOR

FLY-7/3.40mm

3

 Ph.

WASP-7/4.39mm

3 Ph.

ABC

3Ph 4Wire

Combined

 Run

 on

11kV/33kV

 line cost

  in Rs.

711,000.00

788,000.00

759.000.00

The above costs include the cost

 of

 additional intermediate LV poles

  8.3m)

 required

 to

 support

 th

LV feeder. However standard practice

 is to plant

 MV poles 10m

 or

 11m) and construct

 the

 line

 oi

LV

 span.

 The difference in cost has to be borne by the

 CEB. 

J

Ceylon Electricity Board

2

Standard Construction Ratcs-2

Page 8: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 8/25

f Combined  run of LV Line on New MV Line

CONDUCTOR

FLY-7/3.40mm

3 Ph.

WASP-7/4.39mm

3 Ph.

ABC

3Ph.4Wire

Combined

 Run on11l

^V

/33

kV  line cost in Rs.

474,000.00

550,000.00

654,000.00

Note.  , .

Span of MV lines are reduced to the span required for LV. Therefore no LV poles introduced in

between

 MV Poles.

2 . AERIAL BUNDLED CONDUCTORS LV

 LINE,

a . ABC LV Line Cost per km.

CONCRETE POLE

ABC Conductor

70x3 50mm2

70x3 50 1

  #$

COST Rs.

1.241

.000.00

1,437

 000.00

COST Rs.  For the Second Circuit)

738.000.00

Tcylun

 Electricity Board

3

Standard Construction

 Ratcs 201

Page 9: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 9/25

3 . MV

 LINE -  COST PER

 km

  These rates are only applicable for Pole Line Constructions)

Since LV span 45m) used in MV constmction it may be economical to use

 10.0 m

  RC or PS) pole |

in MV construction. PS  11 .Om) poles may be used in special construction where clearance can not 1

be maintained by 10.0 m poles, eg. Road crossings, urban areas)  f

11kV

kV

CODE

7

/ 4.09mm

RACOON

37

/2

.79

LYNX

19

/3.76mm

ELM

7M

.09mm

RACOON

37

/2

.79

LYNX

19

/3.76mm

ELM

Single

 Crcuit

on

 10m

 pole

Cost Rs.

2,056,000.00 2,306.000.00

Single

 Crcuit

on

 11m

 Pole

Cost Rs.

2,247,000.00 3.155,000.00

2.846.000.00

2,437,000.00 3.339,000.00 3.019,000.00

Single

 Crcuit

on

 13m

 Pole

Cost Rs.

2,34.5,000.00

3,604,000.00 3.482,000.00 2.556,000.00 3.841,000.00

3,508,000.00

Double

Crcuit on

13m Pole

Cost Rs.

5.968.000.00 5,287.000.00

6.376,000.00

5.773,000.00

Al

 values are in Rupees.

4)  COST FOR OUTDOOR

 TYP

DISTRIBUTION SUBSTATIONS.

kVA 100 160 250

11kV/ LTRs.

1,299,000.00 1,492,000.00

1,788.000.00

33kV LT Rs.

1,392.000.00

1.573.000.00

1,839,000.00

The above costs include for followings: , |

i)  Three Nos. Pin Insulators, Tension Insulator Sets on line side) and all other material costs.

ii

Two Sets of Fuse Switch Disconnectors 3ph. Unit with neutral Lnk) on LV side for two

feeders.

ill).  PVC Tail Wres 80 meters long) from the TF LV Terminal to Fuse Switch Disconnectors for

the two LV Feeders.

iv)

 

Connection Camps Crimp

 Type

  Sockets at the LV Terminal of the Transformer, Fuse

Switch Disconnectors and Bimetallic Camps at the LV feeders).

v) Substation metering set with metal enclosure.

vi) Concrete Earthing Blocks  Four  numbers) including earth rods, Exothennic Welding

materials, compression connectors. Earth mesh and 25m of 50 mm PVC Sheattied

conductors. ,

Therefore the costs for the above items need not be added to the Standard Costs when a quotation

for a Distribution Substation is prepared.

Ceylon Eicaricity  Board

4

Standard Conslruciion

 Rates 201

Page 10: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 10/25

d),  OST OF OUT-DOOR SUBSTATIONS (BULK SUPPLY)

716

,000

100 160 250 400 630

800

1000

716

,000

1,187,000

1,418.000 1,802,000

2,222,000 3.032,000

3,622,000

4,169,000

Ri.

707

.000

1,282,000

1,502.000 1,821,000

2,428.000

3,259,000

3,748.000

4,383,000

Thfl

 above schedule Includes the cost of the followng items;

1}

  Bulk Supply Meter Sets.

I) Current Transformers

H

MCCBs.

Crimp type Sockets {at the Transformer LV Temiinals and MCCBs)

V .

  PVC insulated Cu Cables (10mdistance,fromTransformerLVTerminals to the MCCB)

V

Bulk Supply Meter Box.

vl 4 Nos. of Concrete Earthing System with 50 mm Cables (30m) with compression lugs,

Earth rods and Exothermic materials

In IhQ event additional PVC Cables are required, the cost of such cables shall be added to the above

standard construction costs wthout adding extra labour and overhead costs.

The consumer

 shall

 provde the Transfomier Pinth and Meter Cubicle for Housing Bulk Supply Meter Box &

MCCB.  (Transfonner plinth and the meter cubicle could either be a combined type or separate type as

roquired.)

6 .  COST OF

 AUGMENTATION

 OF OUTDOOR

 DISTRIBUTON

 SUBSTATIONS (11kV LV 33kV LV)

XISTIN TRANSFORMER KVA 63 100

160

RATING  OF  AUGMENTED

SS TRANSFORMER KVA

100

IlkV

187.000.00

100

33kV

160 11kV

439,000.00 279,000.00

160 33kV 208,000.00

250

IlkV

716.000.00 573,000.00

394,000.00

250

33kV

511,000.00

354.000.00

NOTE:  The above Standard Costs are computed allowng for a rebate (100%) on the existing

Transformer based on

 2011

 prices.

This

 cost includes the cost for augmentation of transformer, labour, transport, contingency and overhead,

charges.

If the available fuse switch cut-outs are not in working condition they shall be replaced and the cost of such

items shall be met from the maintenance vote.

5

Ce y lon E l c d r i c i t y Boa r d S tandar d Cons t r u c t i on Ra tc s 2 0 1 2

Page 11: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 11/25

7 .

COST OF

 AUGMENTATION

 OF

 OUTDOOR

 BULK SUPPLY  SUBSTATIONS

 {11KV LV

 33KV LV)

EXSTNG

TRANSFORMER KVA

63 100 160 250 400

630 800

RATNG OF

AUGMENTED

SUBSTATON

TF KVA

100 11kV

266,000

100

33kV

231.000

160

IlkV

497,000 302.000

160

33kV

449.000 272,000

250

11kV 854.000 660.000 453,000

250

33kV

773.000 596.000 413,000

400

41kV

1.301,000 1.107,000

900,000 568.000

400

33kV

• 1.379.000

1.202.000

1.018.000

738.000

630

IlkV

i

 2.111.000

1.917,000 1,709.000 1.378.000

993.000

630

33kV

2.210.000

2.033.000

1,849.000 1.569.000

979.000

800

11kV 2.701.000

2.507,000 2.300,000

1.968.000

1.583.000

896,000

800

33kV

2.749.000 2,572.000 2,388.000

2.108.000

1.518,000

799,000

1000

11kV

3.252.000

3.057.000

2,850,000

2.519.000

2.134.000

1,446,000

916.000

1000

33kV 3.321.000

3.145.000

2.961.000

2.681.000

2,091.000

1,371.000

930,000

Al Values are in Rupees

NOTE: The above Standard Costs are computed allowing for a rebate

  100

  ) on the existing

 Transformer.

MCCB and

 Cables,

 based on

 2011

 prices  except in the case of augmenting 63kVA Substation).

The cost

 of

 meter sets

 shall

 be charged only

 if

 there

 is no Bulk Supply meter set at present.

The costs of New MCCBs, Connecting sockets, PVC Tail Wres/ Cables, labour and overheads are

included in the above Standard Costs.

I

Standard Construction Ratcs 2012i

C e y l o n

  E l e c t r i c i t y Boa r d

Page 12: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 12/25

8).

  COST OF mSTALUTON OF

 MV SPUR

 LINE TAPPING WITH

 EXPULSION FUSES

 ON DOUBLE

POLE STRUCTURE

I)

 

1lkV -  Rs.

 222,500.00

II)

 

33kV

  - Rs.

 235.000.00

0).

  COST OF INSTALLATON OF LOAD

 BREAK

  SWTCHED

 V ITH

 LOAD INTERRUPTERS ON

DOUBLE POLE STRUCTURE

Air insulated  SF6 MANUAL SF6 Remote Operation

i)

 

11 kV -  Rs.

 580,500.00 682,000.00

  Rs.

 1.636,000.00

ii)

 

33kV

  -

  Rs.

 662.500.00  1.016,000.00  Rs. 1,989,500.00

10)  COST OF INSTALUTION OF

 AUTO-RECLOSERS

Wth

 Remote Operation.

I). 11kV - Rs.

 1.541.000.00

ii)

  33kV

  -  Rs. 2,022,000.00

11)  COST OF INSTALLATON OF

 MV

 METERING EQUIPMENT

i)  11kV - Rs. 1.029.500.00

ii)

 

33kV  - Rs.

 1,884,000.00

12) 

COST OF INSTALLATON OF GUARD

Cradle

 Guard

 20m. Spa wltli

 wdth

 3m

1.  11 kV-Rs. 85,000.00  .

2.  33 kV-Rs. 95.000.00

•   Poles are not included in the Item 12.

7

Ceylon Electricity Board  Standard Construction

 Raics 2012

Page 13: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 13/25

STANDARD CONSTRUCTON

 COST

 -

  2 12

13 .  SERVCE CONNECTONS

a).

  Overhead

 Servce

 Connections

1 Single Phase Up to 50m

  ^

Type  '

  Fxed Cofet

  . ' '

30A  • •

  Rs.

 15.000.00

2 Single Phase Beyond  50m and

 the maxmum

 distance

 of servce

 wre

 should

 not

 exceed

110m

Type

  '

  Fxed Cost Variable Cost Remarks

•i

30A  .

  Rs.

 15,000.00

  Rs, 760.00/meter

  Variable cost

 is

for

  the

 length

 in

excess of

 50m

Note: - Variable cost

 calculation is

 for

 the length in

 excess of

 50m.

Eg. for

 55m  15,000.00+

  55-50) x

 76 = 15,000.00+5

 x

 76 =18.800.00

3 Three

 Phase Domestic/ industrial/ Commerciat

 General

 Purpose

The maxmum distance

 of

 servce

 wre should not

 exceed

 110m.

30A

  Rs.

 18,000.00

  Rs. 640.00/meter

60A

  Rs.

 19,300.00

  Rs 715.00/meter

Meter Enclosure

 and MCCB

 should

 be installed at all three

 phase connections.

4

Single

 phase to Three

 Phase conversion.

From Sngle Phase To Three Phase Fxed Cost Variable Cost

30A  30A

  Rs.

 16,500.00  Rs. 560.00/meter

30A  60A

  Rs.

 17,400.00  Rs. 690.00/meter

Note:

 Above

 rate

  it  applicable

 only for

 the

 conversion  of servce

  wre.

 If Conversion  of bare

conductors

  ABC is

 required

 it

 should

 be carried

 as per

 the

 conversion rates.

Cey lon Elec tr ic i ty Board

Standard Construction  Rates 2012

Page 14: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 14/25

(Applied for Colombo Cty and Kandy Cty Under ground networks

 only)

Loop Services -  from an existing 30A service only.

SINGLE PHASE SERVICE '

Permitted No. of Loops

15A

  Rs.

 4,250.00

  1

THREE PHASE SERVICES -

  from

 existing 30A/ 60A service

Permitted No. of Loops

From-30A Service

15A  Rs.

  18,000.00

  Rs

 350.00

  . 2 .

30A  Rs.  18,000.00 Rs.375.00  ,

 

The fixed costs include the cost of MCCB or MCB, Meter Box, 5 m length of service wire  D-brackets

required on Consumer' s side.

Variable Costs. '

Variable costs include the cost of the service

 wire

 and line material such as poles, D-brackets, Stays. Struts

otc, as applicable.  .

A suitable service bracket shall be provided and installed by the consumer.

eylon lilcctricity

 Board

9

Standard Construciion Ratcs-2012

Page 15: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 15/25

b). Sen/ice Connection to Welding Plants, Metal Crushers, Saw Mil's etc.

In providing service connections to installations having equipment such as welding

  plant,

  Metal Crushers,

Saw

 Mills etc., which could have adverse effects on the other consumers connected to the existing feeder. A

separate feeder has to be constructed and a capital cost has to be charged as per the table given below, in

addition to the cost of the normal service connection provided   from   the separate feeder. This is not

applicable to the norma 30A/60A suppliers where such equipment is not

 used.

A  SEPARATE  BUNDLE CONDUCTOR

  LINE (3x70mm2 + 1 x 50mm2) MAY BE DRAWN  IN

 PARALLEL

'WITH THE

 EXISTING

 DISTRIBUTION LINE WHEN

 PROVIDING

 SERVICE CONNECTIONS TO

 WELDING

PLANTS, METAL CRUSHERS. SAW MILLS

 ETC.

01 The above service connections should not be given from  normal consumer distribution  lines.

02 ** The distance

 limits

 for 3 phase, 30A and 60A connections is applicable as per the construction

standards ie. 800m and 400m respectively from  the T/F.

03 A capital cost of the new line has to be shared by the consumers in addition to the sen/ice

connection charges.

04 When providing the connection to the First Consumer,  CEB has to bare the balance cost of the

feeder as the consumer  will  pay only his share as given in the table below. The balance

expenditure may be charged to the

 System

 Augmentation

 Fun^ls.

05 The capita cost for different categories of the service connections is given in the table below.

06 If service connection can not be given due to distance

  limits

  or voltage drop,

  that

 has to be

referred to the Planning Engineer to study and make an appropriate System Augmentation

proposal.

07

The costs indicated below are valid only for the feeder section constructed on the existing pole^

parallel to an existing feeder. If it is required to install poles to get the connection off the existing

feeder or extend the existing feeder the   length from  the T-off  or the

  point

 of extension to ih(

consumer

 point

 shall be charged under the relevant service connection rates. .

Capital Costs

Size  of the  service

connection

60A 3  phase

30A3phase

30A1  phase

Allowable distance

from  the Substation

400m 800m

1000m

No.

 of service connection

(allowable)

2

4

4

Capital  cost per service

connection to be charged

from  the consumer

Rs.100,000.00

Rs.100,000.00

Rs.75,000.00

Note:  This is only a puide line to prepare the cost estimates. These limits could be changed '

considering the voltage drops, consumer  growth  etc only on personal approval  of  t

Provincial DbMM on case by case basis.

Ceylon

 Electricity

 Board

10

Standard  Construction Rate:;-

Page 16: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 16/25

Quidollnos for Preparation of Estimates.

Mo>iuromont of the Servce Connection Length.

Thd IftfVCO

 Connoclion

 Length is

 the Horizontal Dstance

 (Ground

 Dstance) fron- the Pole to the

llfViCi BfiCket at the consumer's premises. No. allowance shall be added for the Sag or Down

HOWOVO

 lengths of Servce

 Wre

 shall be issued on the

 basis

 of

 actual

 length required to construct

thS

  #$%&'#

 Connection

 including

 Sag

 and the  Down

 Run

(&)*+ cost charged

 from

 the Consumer includes the cost of the length of servce Wre required for

,-. -/ the  Down

 Run

II).  Insulated Wres for Three Phase Servce Connections

Three

 Phase Servce Connection shall

 be connected

 wth

i)

 .

  On Fat

 Twin

 Core Servce

 Main

 Wre

 (Black

 and

  Gray

 for

 two

  Phases) and

ii)

 .

  One normal Single Phase Servce

 Main

 Wre

 (Insulated

 Conductor for third phase

[Brown] and

  other Conductor

 [Sheathed, Blue]

 for neutral).

If

 there

 is a shortage of Fat

 Twin

 Core Servce

 Main Wre,

 Sngle Core Insulated Wre may

III .  Last Span

In all  categories of service connections the last span shall generally  not exceed 30m,

however

 in

 special circumstances

 it

 may be appropriate to change the last span slightly wth

the approval

 of the

  Engineer concemed.

Iv). Servce Connection length exceeding 110m  -

When the Servce length exceeds  110m, up  to 110m  Standard Constaiction Cost for Servce

Connection shall be used. For the balance length, Standard Construction Cost for LV Lnes

(as

 indicated below)

 shall be used for estimation purposes, but

 it is to be

  noted that the total

bare alumnum conductor

 line

 length shall

 not

  exceed

 1.8km  from the

  distribution substation.

i). Constmction cost per

 km.

  using FLY Conductor

ii).

  Construction cost per

 km

  using ABC conductor

  4 wres)

  ;

 Rs.1,  241,000.00

v). Servce Connections for Consumers beyond 1 8km

 from

 the

 Distribution

 Substation

Dstribution feeders shall not be_extended beyond

 I.Bkm from

 the distribution substation to provde

Service connection utilizng bare aluminum conductors.

  In

 the

 event

 servce connections are to be

provded

 from

 the feeder terminal point (1.8km

 from

 the

 dist.

 sub.) separate insulated servce main

wires shall be used for each consumer up to a maxmum distance of 110m.  No bare conductors

shall be used to provde such service connections.  . . .

be used.

(7/3.40mm) (7/.134 in)

1

 Phase

3

 Phases

: Rs.898.000.00

:Rs.1.161.000.00

00

l i n E l c d r i c i t y Boa r d

Standard Cons lr uc t ion Ra ies -2012

Page 17: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 17/25

14 .

  Under Ground Service Connection.

15

 Amp.

30

 Amp.

60

 Amp.

#

UNDERGROUND SERVICE SINGLE PHASE

a). Fxed cost for

 3

 way joint box

Rs.37.800.00 Rs.  #,800.00

b). Variable cost 16mm2/2C

 Al.

 Cable

  per

 meter

ength

Rs.3,200.00 Rs.3,200.00

2.

SHIFTING SERVICE  U.G.) SINGLE PHASE

Details

 estimate*should be prepared.

3

Tiree Phase 30

  A

  From

  LV

  underground

distributor

Termination Kit.

 $%&'( %)(

 4C,  $%%&

Consumer contribution for mini feeder pillers.

Total

 Fxed Cost for*30A,

  *+,

.(Termination kit,

 1/5

 of

mini

 feeder piller,  labour, transport and overfiead)

54,900.00

Variable cost for

  *-

 30A for 16mm2  XLPE, At. Cable

per meter

3,600.00

4

Three

  Phase 60  A  From  LV  underground

distributor

a For 35 mm XLPE.AI.

 Cable

Tennination kit $%&'( LT, 4C  . mm

Consumer contribution for mini feeder pillers.

Total  Fxed cost  for 60A,  *-/  with  .  001  Al.

cable.(Termination kit, 1/4  of mini feeder

 piller,

 labour

transport and

 overhead)

61,200.00

Variable cost  for  *-(  60A in  .  001/ $%&'( AL

Cable

 per meter

3,600.00

b For

 70 mm2

, XLPE, AL Cable

Termination kit

 $%&'( LT,

 4C 70

 001

Consumer contribution for

 mini

 feeder pillers.

Total  Fxed cost  for  60A,  *-/ For 70 mm  Al.

cable.{Termination kit.

 

/4 of

 mini

 feeder piller,  labour

transport and

 overhead)

65,300.00

Variable cost

 for

  *-/ 60A

 for

 70 mm? $%&'(

 Al.

Cable

 per meter

4,400.00

c For

 95 mm2

 XLPE, AL Cable

Termination kit

 $%23'( LT

 4C 95 mm?

Consumer contribution for mini feeder pillers

Total  Fxed cost

  for

  60 

*-

 with

  95

 mm?

 Al.

cable.(Termination kit, 1.14 of mini feeder piller,  labour

transport and overhead)

71.300.00

Variable cost for

  *-(

 60A for 4. 05-1 $%&6( 4C, Al.

cable

 per meter

4,500.00

2

Ceyon

 Electricity Board Slandard

 Construction

 Ratcs-20i2

Page 18: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 18/25

7. SHIFTNG

 SERVICE

  U.G.)

 THREE PHASE

Detail estimate should

 be

 prepared.

8.

SINGLE PHASE

 LOOP

 SERVICE

a)

 .

 Fxed Cost

b) Variable Cost

Rs. 4.250.00

Rs.

 300/meter

9.

THREE PHASE

 LOOP

 SERVICE

a)

 .

 Fxed Cost

b) Variable cost

Rs. 18,000.00

Rs. 350/meer

Rs.18,000.00

Rs.375/meter

olicy for recovering cost n new three phase connection

When a

 three

 phase servce is

 given from

 the UG network {Oher than

 15 A.

 3P servce

 from

 an exsting

cable at the

 building) followng capital costs (Mini feeder pillar and associated items)

 are

 charged from.

consumers

 as

 follows.

  s

Capital

 Cost Remarks

a)

 30A 3ph

 connection

 from

 exsting UG network  Rs.

 27,300.00 15

 of the total cost of MFP

b) 60A 3ph connection

 from

 exsting UG network  Rs. 34.100.00

 

of the tola cost of MFP

MFP - Mini

 Feeder Fller

When

 provding the connection to the first consumer, the balance expenditure may

 be

 charged to the System

Augmentation

 Vote

Cey lon Elec tr ic i ty Board

3

Standard ConsU uct io n Ratcs 2012

Page 19: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 19/25

STANDARD  RATE  FOR  CHANGING

 OVER

TO THE

 TIME

 OF DAY

 TARIFF

1 Consumer

 metered

 at

 Medium Voltage

The existing single rate meter is to be replaced with  Programmable 3 phase 3 wire

meter

 free

 of charge Fixing charge

 and

 the

 transport are

 to be charged

 on

 actual

on Electricity Board

14

Standard Construction Raict; 20

Page 20: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 20/25

16)

  OTHER CHARGES

Oher charges for

 miscellaneous

 servces

No

Types of Charge

Charge

  Rs)

1. Dsconnection

 at the

 customers request

800.00

2.

Reconnection

 at the

 customers request

800.00

3.

Reconnection after

 a

 statutory disconnection

800.00

4. Testing of an energy or energy demand meter

 (230/400

 V)

800.00

5.

Testing of an  energy  or  energy demand meter and associated

equipment {230/400 V)

8,500.00

6. Testing of an energy or energy demand meter associated equipment

(used at voltages higher than

 230/400

 V)

8,500.00

7. Installation testing -

CCE

8.

Changing

 an

 account'name and/or

 the

 tariff category

250.00

9.

Changing

 an

 energy or energy demand meter

Free of charge for changng

defective meters. For other

cases

 CCE

 shall

 apply.

10.

Provsion

 of

 temporary electricity supply

CCE

11.

Augmentation

 of

 an

 exsting electricity supply

CCE

12.

Shifting

 of poles/ lines/ transfomer/any other

 electrical

 plant

'

  CCE

13.

Cearing of

 way leaves

CCE

  based on

compensation charges

decided

  by Dvsional

Secretaies

  and cost of

removng way leaves.

14.

Issuing

 a

 clearance report

Free

 of charge

15.

issuing

 a duplicate bill

Free

 of

 charge

16.

Provsion of net metering facility

CCE

17.

Grid interconnection

 of generation

 facility

CCE

18.

Delays in Payment

 -

  Bulk Supply Consumers

According

 to the government

 gazette

 on

  Tariffs and Charges

published in 24.10.2008 Section 15 cause~ 3

(i) After 15 days period, a monthly interest of 2% wll be

charged to the

 bill from

 the

 16*

day of

 bill

 issue

 from

 the

,

  consumer.

i

A monthly interest

 of

 2%

 wll

be charged to the bill.

(ii) If consumer

 fail to

 pay the

 bill

 and interest thereon wthin 3

,

 day of issuing liie bill, supply

 wll

 be disconnected by issuinc

disconnectic:  order. Reconnection of the supply wll be

given

Upon ihe payment of 2%

,interes( on the outstanding

amount until the day of

reconnection together wtfi

Reconnection processing

fee and Outstanding

amount.

15

#$%&'($%)*+)*,#' - %&& .' /,0&1021' %&34*0*%&506 3789:8'

Page 21: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 21/25

19.

Delays

 in

 Payment -

 Ordinary

 Supply Consumers

According

 to

 the government gazette

 on

 "Tariffs and Charges

published in 24.10.2008"  Section 15 clause 4

(i)  After 30days period, if a disconnection order is issued a

monthly interest of

 2

wll be charged on the outstanding

amount effective

 from

 the date of issuing the

 bill

 from

 the

consumer.

(ii) If supply is disconnected, Reconnection of the supply wt

be given

  ,

A monthy interest

 of 2

wll

be charged on the

outstanding amount.

Upon the payment of 2%

interest on the outstanding

amount {calculated for half

the period of

  bill

  is beng

outstanding) together

  wth

Reconnection processing

fee and outstanding

  bill

amount

20.

Repair

 of

 damages to Servce connection

 wre

Responsibility

 of removng way leaves along the

 path

 of

 servce

connection wre  rests

 wth

  the consumer. Cost of repair to

servce wre damaged due to non-removng of way leaves is to

be

 charged from

 the

 respective consumers.

CCE

CCE

  - Case by Case Estimation by the Lcensee based on Standard Constmction Cost -

  2012

 and Price

Lst

 of

 Materials

 2012

 issued by

  CEB.

Ceylon

 £l« tricity Board

6

Standard

 Construction

 Rates 2012

Page 22: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 22/25

P ROV IS ION  O F

 E L E C T R l C r r Y  SUPPLY

 T O

 H I G H

 RISE BUIL DING S

(i)  - If  the .power reqoireinent  is  3 0 100 A m p . or less,  in  the

  case

  of areas where the

distribution system is underground an d 3 0,60 A m p. or less i n the

 case

 of areas where

-•- the .distribution  system is overhead and if it is technically possible to provide the

: power connection fro m the existing L T  distribution  system, the Area Engineer shaU

. : give

  tiie

  quotation to the prospective applicant based on

  tiie

  standard rates subject to

other conditions. If the capadiy of the substation  is re qu ired to be increased

 tiie cost

 of

; augmentation shou ld also be recovered along

 with

  the

 cost

  of service-cormectioiu

(ii) If the pow er' requir eme nt (contract demand) of  fee bu ild in g cannot be provided from

'• ti^e  existin g L V net wo rk then substation capacity a nd the location of the new

substation has to be decided by Co mm ercia l Engineer (Heavy Supply) of the Provin ce.

The tota l electddty pow er requiremen t of the bu ild in g shou ld be assessed- by the

; 1  Provincial Plann ing Com mittee based on the information gathered by the Com mercial

Engineer

 fr om the

 buHding

 owner.,

  Planning

 Committee should comprise of

  D G M

  of

the P rovin ce,

  Planning

Erigiheer  of 'the

 ProviiKC

  Chie f Erigin ee: (Cbmmerdal) a nd

Comm ercial Engineer (Heavy Supply) : :

(iii)  Comm ercial Engineer (Heavy Supply) should advice

  with

  the owner of  th>3 building

and  pro vi de a design for a suitable LT switchgear a nd distribution pane l to

accommodate  var ious power connections (service connection) to various flo or s/

apartments i n the high-rise  building. The LT panel has to be provided by

  thfi

 owner, of

,

 the

 bm ld ih g at a suitable location

 wi th

 adequate

  security.. It

 is advisable to locate these

\ panels in the sub station cub ical itself or i n a separate roo m in the ground floor of the

1  , building and

  install

  al l m eters'in the L T  distribution paneL

  A l l

  consumers

  shaU

 br ing

ftieir lo ad w ires up to the paneL Cost of cabling to the LT switchgear and d istribution

panel a nd meter panel has to be calcula ted and added to the

 cost

 of substation.  . .

; iv)

  The qu ota tion for pr ov id in g electricity supply to the h ig h rise bu ildi ng has to be

prepared.con sidering the length of requ ired H I spur line (or HT Cable).and cost  of

substation

  (Indoor substation where applicable) as i n the

 case

 of buBc sup ply .-

(v). Thepxesent  Comrnerdal Policy an d method of  cost sh aring for  giving connections i n

Co lombo Qty

  shall

 be adopted i n Ka nd y  Dehiwala a nd M t

  Lavinia Munf-cipal

 Areas

as weE, whe rq there area undergrou nd distribution systems. 

(vi) Pr ov is io n of service connections to various floors or apartn.ents i n the high-rise

' j • • bm ldin gs; Quotation for service connections/ power connections  shall be issued to the

prospective occupa nts/ bui ldin g own er

  by

  die Ar ea Engineer. Depending

  on

  the

power requirement of  each applicant flie type  of  the connection (whether ordinary or

balk) h as  to be decided .

Page 23: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 23/25

F. P R O V I S I O N

  O F

 EOECnaCrry

  ST JP PL Y T O L A N D D E V E L O P E R S  (AUCnON

  L A N D S ) . . ,

. . . .  r - : ^ ;

:

  t~X.^.

-I 

••

  p •

The 'Commercial Engiiaeer (Heavy

 Supply)

 shall assess the power requirement

.of the developed I-iid  assuming thataLL blocks of developed land will have

houses

  except

  roads  and xeservatioDS for common purposes such as play

grounds etc

  Commercial

 Engineer may compute electriciiy demand per house

hold orr the following basis.

-  Category

Peak Load

 of the

Installation

 (kW)

 ,LDpk

1.

[

 Small Honse  •  -

• •  .035 . .--

Honses whirh are  in. urban areas

and.  in arid around nrbah coundl

T r r n - ^

  (MedinTTTHousey ^

 •

  '

.0.75 > •

3- ..

Houses in the .Developed T  : nds  ia.

\y area s.;

 fT

 arge House)

7

  ^ .

Houses

  to*

 bmld

 ih'De ^o pe d Lands in

 the areas

 o&er.than

  MnnicipsI Lbiiite

 and Urban

Coimdl .areas shall be-considered  as  small or medium isize/-considering  the  geography,

-Simomdingand'roadcdnditianof thelocali^

  . ' - .

••

  y\

Calcolatiou'of  gpTOup demandj

, =

 .  •*

  - • :•, '-~ .

ThebDtalloadof agrdup.ofnnos-housesrw

  • . .

  -

;

  TotiLLoad

  . ;

  XDEk

 X ji X

 C ^ -

  ^ ' ,  • • . . .

 Where.,

  ,

  •

 ;

  -UDptis

 the-peakloiadbfaninstallati

  . . ' '.

 Total'load•='.^0.75kV^pb:haii^eXl5  nok

• \ CbincidentfactDrsare given,belowior.vaiioiis  gfottpsof  H o t i s e s J ' - ' . • •

- Jiln  • of

 •

.Houses-  .

.1-3.

4 -~ .

• 5 . - .6 .-_ .

-7   ^ T

S;.._ -•

10   ^r

• l l - - -

r l :

•14 -

-G ) indigent

Factor

.1.00

0.93 0.86 0.79

QJ

.0.69 0 65 0,63 0.61

0-55

• 54

053

No  - -of ;17

.19

20-

21

22- -

24 25 29

  .•

  30- 34 •

35 .. 40

50 &

Houses: \

to

to

-

  to

to to .

Above

18-

23

28

33

'39 - 4?

\'

Coihddet

052 051

05- •0.49

a43

0.47 0.46 0:45

0.44 0.43

0.42

0.40)

.

 Factor

i.

  i

  -

  I.-

  # $#

Page 24: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 24/25

(ii)  Once group  dem an d i s computed thfen capacity of the substatLcn and its location

shou ld be de cide d, tak ing the nearest standard substation, capa dly

(in)

•^i^i  r J .

-

De sig n the jn te m a l overhead electricity distr ibu tioh system of the land to cater" the

Icjng- term pQwer  xeqmxement

  (assume

  each bl oc k of la n d contains a hoi.'se). and

enabling all tiie houses, to get a service coimection'"without us in g a pole.

Quotation tb the Deve loped

  Land

  should include.

(a) BaU 'costof the'm tem alLT

(b)  Full

 cost

 of the H X

 spur

 line reqoi rem ^^ .

'(c)-  •  Apportioned

  cost  of'the

  substation accord ing, to the ratio of contract demand

and capacity of the:substationi..Balance

 costhas

  to be

 borne by_CEB.

 The

 cost

 of

subs tation is the substation for

 K E schemes

 hked in

 this, document

; :(y)  ••  If the-pawef.fe^iiremCTt"(gr^ demaiid) of the Dev^'oped'-Iahd c ould be met from

.' / the e x is fe g X V distribution^^  cost,  internal of L V distributibn ^s tem

shall

  P  rhartredfrom-the

  annHrant'.

  • • • • • •

. T

  If  the prospective"retai

.corisTnn^

  and

  60

  Arnp?)" .are £tnated'witSiit

 tfre^^

.'.--•existing LT network (that; is \ w thin 1.8 kmlirnit) • Su pp ly "should be given as usuaL Anjrthing

outside witt require a separ atee^ /

•J

Page 25: Electrical Design and Rates Document

7/25/2019 Electrical Design and Rates Document

http://slidepdf.com/reader/full/electrical-design-and-rates-document 25/25

P O L I C Y O N N E W S E R V I C E C O N N E C T I O N S

T y p e

  of S u p p l y

tiiifii. -. : .

i .sU

S UPL I E S OV E R ; 1 M V A

Colombo  C i ty

Generally supplied and. metered at.

 11-

 kV..

Co sto f alt IT kV works associated-w itti the

supply up to the mete ring point

normaliy be  • paid by the custom er.

However,

  if augm entation of

  Grid

 -

Substation  or Pri ma ry Substation, is

nece ssar y. to prov ide' requested-; supply.;

theri a propo rtionate co st as g iven

  be low

  to

bep aid by the customer. . . - •

Proportionate co st - . .

• Cost of Augmentation X Contract Demand

. Standard incr eas e

  in:

 capac i ty .

Outstatloris'

Supplied & metered

at 33 kv. or .11 k v.

Costing is similar to

Colombo'City.

2.A

S U P P L I E S - L E S S T H A N O R .

E Q U t V A L E I s f T T Q i t M V A . . ' •

AND MOR&THAN-10Q KVA- ' - .

(100 KVA

 -•

 1.5Q: K V A AM F.- -3 0)

 -

To-be

  always on a cost sharing ba sis . Co st to

be shared ' . '

 between.  .

 c u s t o m e r . a n d C E B .

Custo rn'ersh arew ouidb e -; , ' . •

; C11-

1 0 0 K V A S U P P U E 5

:.BUU<(tSQ^np-:^30 ).^.^ .; •

tOOKVASUPfeY-FOR

.  RETAlLDlSTRIBLmON

• UIK

  f 100 :AMP^3g i i : - ' - : : -

7 d K V A - S U P p ' f e s - ' F O R - •

.RETAILDtSTRIBUnON

  T ...

' - ' S UP P L I E S AS6>^5^ KVA

 AND0PTO7a-KVA-'-

 

.'Lusiorper

  u6n&cCt   Dems iha7 '~~ 7 . " "T " ;  " * ~ " " T

Next.step.6f std,Cap.

  o f

  S/S

  a b o v e ,

  contract

Demand-

  J - - .

/ .

.

 Capitai.

 charge for suppl ies les s than

  o r  equaf-

 100kyA.and,morE

  Ihari 7Q

 kVA

would be  • •

• ;CbsLof4Qq:^^ .

; W k W C o n t r a c t D e m a n d . :••  •• .-

If th e . ' customer

reguii eme'nt-

  .more

than,

  or- equ al to

;capac ity- '- .'

  . of

-standard: • .S/S on

C E B '

  does

  . not.

Tntent;-   -

  --..utlisirig

;si3are

'capadty theh

:custorTier.:''

 •.'•should

.beatr.the

  fijil

  cost of

SIS:} and ----HT/LT

;;iihes   ~  c V; ;

f

• 

1

T Y P E O F L T S t J P P L I E S •-

S E R V I C E

 C O N N E C n O N S -

Customers i f f 'm eet 'the - cost: '6f -service- ca bl e

ftumthe dis tri bu tor /iio we yer l ike Irr oiitstat ions,'

.

 CEB.

 wH- lay brg ger ca b le diistrit)ut6r_.for_.future.

expansiori/dev^opmenL

  ' T y p e

  of Con nectio ns

'

  :3CrA

^30

, - '

'••30

 A 30

 Loop

'

  soA-ierLoop

  •

, .ISA 30^

.15 A 30

  Loop

i.5A.10. '•

: : l 5 A ' i 0 L o o p

Tax. ' of

  i

  bundle

conductors..with no

ex t ra ' - - cos t t o

custom ei^ irr -urban-

and

  . d'evelbp ing

areas .

  Type- . - . o f

conriections-'.. .

-l>-

  6 0 X 3 0

  ". -

It )  3 Q ' A ' 3 0 . - .

1 1 1 ) 3 C F A ' 3 0 L O O P

1V ) 3O : A i : 0 t l bo p

3aA.i0 •

V1)): 1 5 A 3 0 .