Download - Presentasi Orientasi n Early QCC
-
8/9/2019 Presentasi Orientasi n Early QCC
1/36
-
8/9/2019 Presentasi Orientasi n Early QCC
2/36
PROFIL JOBSITE BIMO
-
8/9/2019 Presentasi Orientasi n Early QCC
3/36
pt mining services - bimo
-
8/9/2019 Presentasi Orientasi n Early QCC
4/36
BINUNGAN MINING OPERATION
ENGINEERING
PRODUKSI
PLANT
LOGISTIK
SHE
FA
HCGA
BIMO
-
8/9/2019 Presentasi Orientasi n Early QCC
5/36
STRUKTUR ORGANISASIJOBSITE BIMO
Christian Cahyana H.
Project Manager
Muh. Hawari
EngineeringSection Head
Sub Section
Yoseph Danang
ProductionSection Head
Sub Section
Edi Susanto
PlantSection Head
Sub Section
Achmad Aan N.
SHESection Head
Sub Section
M. Farouk
LogisticDeputy Section Head
Sub Section
Andre Ibnu A.
FAAct. Supervisor
Sub Section
Agus Nugroho
HCGASection Head
Sub Section
Dellyar Wildansyah
PDCA Officer
-
8/9/2019 Presentasi Orientasi n Early QCC
6/36
HCG SECTION
HCGA
Facilitiy &Service
Infrasctructure ITGA
Purchase
CSR(Customer Support
Relationship)
HCSupport
HCDevelopment
Man
Power
Recruit
ment
General
service
Sarana
Eksternal :
Goverment
Relarionship
Comunity
Development,Pengembangan
masyarakat lingkar
tambang
Internal :
Hubungan karyawan
(Serikat Pekerja)
dengan Management
Pengelolaan
sistem
telekomunik
asi dan
jaringan IT
Kebutuhan
Infrastruktur Pembelian
item
Man Power
Development
-
8/9/2019 Presentasi Orientasi n Early QCC
7/36
F SECTION
SectionHead
SupervisorGroupLeader
Admin
Pencatatan dan Pelaporan TransaksiKeuangan
Payment
Monitoring Deviasi Budget
Gross Profit (GP) Report
KEGIATAN
VendorLOG
HCGA
FA
Purchase
RequisitionPurchase
Order
Invoice
Invoice
Costumer
FA PROCESS
-
8/9/2019 Presentasi Orientasi n Early QCC
8/36
SHE SECTION
SHE
OperationTraining &
DevelopmentSystem & Development Environment
Pengadaan
APD
Accident
Recording,
Investigation,
& Analyze
Rambu K3L
Pelatihan K3LM Induksi
Safety Meeting, Safety Talk
Inspeksi harian, Inspeksi
gabungan
Hazard report
Safety Behaviour
Observation (SBO )
Pembuatan Mine Permit
dan Simper
Fasilitasi &
monitoring
pelaksanaan dan
pengelolaan limbah
B3
-
8/9/2019 Presentasi Orientasi n Early QCC
9/36
PLANT SECTION
PLANT
Track WheelSupport and
Facilities
Plant SiteDevelopment
Plant Safety
Plant EngineerMaintenance
Planning
MaMS
-
8/9/2019 Presentasi Orientasi n Early QCC
10/36
MAINTENANCE PROCESS
PredictiveMaintenace(SCHEDULED)
Program AnalisisPelumas (PAP)
Program Pemeriksaan
Unit (PPU)Program Pemeriksaan
Mesin (PPM)
Program PemeriksaanUndercarriage (PPU)
BackLog
PreventiveMaintenance
(SCHEDULED)
Periodic Maintenance(Periodic Inspection,Daily Check, Periodic
Service)MidLife
General Overhaul (GOH)
CorectiveMaintenance(UNSCHEDULED)
Repair & Adjusment
Breakdown Maintenance
Physical Availability
Mean Time Between Failure (MTBF)
Mean Time To Repair (MTTR)
Maintenance Ratio
KPI
-
8/9/2019 Presentasi Orientasi n Early QCC
11/36
LOGISTIC SECTION
Receiving &
Binning
Issueing &Packing
Stock taking
Rekonsiliasi
Housekeeping
Katalog
Analisa fast
moving item Setting ROP &
ROQ
Adjustment Stock
Analisa Slow
moving
BackLog
Part GOH &
MidLife
Mapping Supplier
Order Process
Requisition Quotation
Comparison
Purchase Order
(PO)
Receiving &
Binning FOG
RefuellingFOG Stock taking
FOG
Rekonsiliasi
FOG
Housekeeping
Parts Availability
Inventory Turn Ov er ( ITO)
Discreapancy
Lead Time Purchase Order (PO) CreateLead Time Supply Supplier
KPI
LOGISTIC
Inventory Warehouse Purchase FOG(Fuel, Oil, Grease)
SCMS
-
8/9/2019 Presentasi Orientasi n Early QCC
12/36
WAREHOUSE
INVENTORY Supplier
PURCHASING
All Site/Distric
PLANT
FOGSupplier/
Transportir
Storage
Pit Stop, Lub
Truck, Workshop
Equipment
Maintank/
Fuel Truk
MIT
LOGISTIC PROCESS
-
8/9/2019 Presentasi Orientasi n Early QCC
13/36
PRODUCTION SECTION
PRODUCTION
Pit ServiceMan PowerSupport &Equipment
PitDrilling &Blasting
OB removal &
coal getting
Mengawasi
proses loading
dan hauling di
lapangan
Mengatur dan
mengontrol
proses
pengeboran
dan peledakan
Menganalisa
hasil ledakan
Cost blasting
Land Clearing
Top Soil
Removal Penyiapan
pekerjaan
Rehabilitasi
Tambang/
Disposal
Penerangan
Tambang
(Lighting)
Dewatering
Road
Maintenance
WMP
Maintenance
Roster Man
Power
Koordinasi
ketersediaan
alat dan
operator
UA (Uti l ity Avai labi l i ty)
Mencapai Target Produksi OB dan CoalKPI
-
8/9/2019 Presentasi Orientasi n Early QCC
14/36
DESIGN
ENGINEERING
LAND CLEARING
ROM/CPP
SOIL REMOVALSTOCK
SOIL
EKSPOSE
BATUBARA
DISPOSAL MANAGEMENT
OVERBUDEN
RIPPING
COVERING SOIL
BLASTING
IN PIT
DUMPOUT PIT
DUMP
COAL GETTING
COAL
CLEANING
PIT
DEWATERING
DUST CONTROL
ROAD
MAINTENANCE
PRODUCTION PROCESS
COAL HAULING
-
8/9/2019 Presentasi Orientasi n Early QCC
15/36
ENGINEERING SECTION
ENGINEERING
Mine Survey
Surveyor
Mine Plan
Pit Control
Project Control
Minimasi Slippery Time
Meningkatkan Cycle Speed
Fuel Ratio
Cost Subcont
Blasting Recovery
Deviasi Join Survey
KPI
-
8/9/2019 Presentasi Orientasi n Early QCC
16/36
-
8/9/2019 Presentasi Orientasi n Early QCC
17/36
CUSTOMER
PRODUCTION
GENERAL
SUPPORT
MANPOWER &
INFRASTUKTUR
LONG TERM SHORT TERM
PLANNING &SCHEDULLING
SURVEYING
PLANNING &SCHEDULLING
SURVEY
PIT CONTROL
PROJECT
CONTROL
MONITORING& CONTROL
INVOICING
DESIGN
ENGINEERING PROCESS
-
8/9/2019 Presentasi Orientasi n Early QCC
18/36
-
8/9/2019 Presentasi Orientasi n Early QCC
19/36
Pit Control
tivities
MONITORINGKESESUAIAN FLEETTERHADAP PLAN
MONITORINGPEKERJAAN PITSERVICE
PENGECEKAN DISPOSAL
SETTING FLEET& JOBPENDING SHIFT 2
MENYIAPKAN FORECASTBATUBARA
PERENCANAAN LOKASI
PENGEBORAN DANPELEDAKAN
PEMBUATAN REPORTRCM & GMP
DAILY TECHNICALMEETING
-
8/9/2019 Presentasi Orientasi n Early QCC
20/36
THE
PROJECT
-
8/9/2019 Presentasi Orientasi n Early QCC
21/36
Tema : Cycle Speed
Job Site BIMO
2012
-
8/9/2019 Presentasi Orientasi n Early QCC
22/36
Cycle Speed; kecepatan yang dihasilkandalam satu siklus Loader-Hauler (km/jam)
Cycle Time; waktu satu siklus Loader-Hauler
(menit)
TRAVEL TIME; WAKTU YANG DIBUTUHKAN HAULERUNTUK MENEMPUH JALAN DARI FRONT LOADING
SAMPAI DUMPING POINT(MENIT)
Cycle Time rendah, Cycle Speed tinggi,
ProduktiVitas tinggi.
-
8/9/2019 Presentasi Orientasi n Early QCC
23/36
Variabel yang mempengaruhi Cycle Speed
Working Geometry
Manuver unit Loadingmaupun Hauling
Material Blasting
Kondisi material blasting berpengaruh pada kinerja unit
Hauling maupun Loading
Road Condition Performance unit Hauling saat travelling
Hauling Distance
Semakin dekat jarak, semakin sulit hauler mencapai steady
speed-nya
Disposal Management Kondisi dan geometri disposal
-
8/9/2019 Presentasi Orientasi n Early QCC
24/36
Contoh Perhitungan Cycle Speed
-
8/9/2019 Presentasi Orientasi n Early QCC
25/36
Nilai Cycle Speedjobsite bimoJanuari September 2012
-
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
18.00
20.00
JAN FEB MAR APR MEI JUN JUL AGS SEP
AKTUAL
TABLE
Rata-rata pencapaian selama bulan Januari sampai September 2012 adalah 73,1 %
-
8/9/2019 Presentasi Orientasi n Early QCC
26/36
Masalah Foto StratifikasiPerformance operator Man
Jalan bergelombang Material
Manuver unit kurang
optimal
Methode
Jalan berdebu Enviro
-
8/9/2019 Presentasi Orientasi n Early QCC
27/36
Material Man
Methode Enviro
DIAGRAMFISHBONE
Jalan berdebu
Dust Suppresion
kurang optimal
Manuver Unit
Working geometry
Material pembentuk
jalan kurang baik
Material penyusun
jalan tercampur
lumpur
Performance
operator
Operator tidurterlalu larut
-
8/9/2019 Presentasi Orientasi n Early QCC
28/36
PROJECT SCOPE
Ruang lingkup yang diimplementasikan pada Projectiniadalah Cycle Speed pada kegiatan Loading-Haulingdi Pit
H4Ext.
Data historis yang digunakan sebagai acuan adalah data
Cycle Speed dari bulan Januari sampai September 2012
-
8/9/2019 Presentasi Orientasi n Early QCC
29/36
Terima kasih ....
-
8/9/2019 Presentasi Orientasi n Early QCC
30/36
-
8/9/2019 Presentasi Orientasi n Early QCC
31/36
STRUKTUR ORGANISASI FA
Supervisor
Finance & AdminSection Finance & Admin
Head : (vacant)
Finance Clerk
Andre Aulia, (ACT) Nisna Rafika
Group Leader
Finance & Admin
Maria Ulfa
-
8/9/2019 Presentasi Orientasi n Early QCC
32/36
STRUKTUR ORGANISASI SHE
Section SHE
Head : Achmad Aan N.
Supervisor SHE
Vacant
Group Leader SHE
1. Operation :
Hendrikus
2. Training & Development :
Dian Karitri W3. System & Development :
Prasetyo Joko Pranoto
4. Environment System
Hasyim Murdiyanto
SHE Clerk
Evi Kafatul J
Plant SHE (Reps)
Suparno
SHE Field Support
Isnawan
-
8/9/2019 Presentasi Orientasi n Early QCC
33/36
STRUKTUR ORGANISASI LOGISTIK
Group Leader FOG
Sudiyanto, Karni Chandra
Group Leader Inventory
Group Leader Warehouse
vacant
Section Logistic
Head : M. Farouk (act. Dpty)
M. Erwin
Group Leader Purchasing
Rukly Febriana
Supervisor Logistic
vacant
Admin FOG
Driver FOG
Purchasing Clerk
Purchasing Clerk
Receiving & Binning Clerk
Issuing & Packing Clerk
Inventory Control
Cataloguer
-
8/9/2019 Presentasi Orientasi n Early QCC
34/36
STRUKTUR ORGANISASI PLANT
Planner Maintenance
Track Type : Rizqi Kurniawan
Wheel Type : Hery Sofianto
Support & Facility
PTA : Vacant
Supervisor Plant
1. Track Type :
Aris Totok P.2. Wheel Type :
Solichin
3. Support & Faci lity :
Rokani
SectionPlant
Head : Edi Susanto
Instructor Plant
Anjas A, Indra S
Officer Plant Site Development
Vacant
Officer Plant Engineering
Rhandyawan, Budi NUgraha
Supervisor Maintenance Planning
Mulato
Group Leader Plant
1. Track Type :
Yanto, Totok PC
2. Wheel Type :
Bertha, JusmanS, Wair
3. Support & Faci lity :
- Support : Siswanto,
,Erwin R.H, Tri Sulistiono
- Fabrication : DedikE.
- Component Rebuild :
Vacant
- Tire : Eko M., Eka S.
Plant Safety
Suparno
-
8/9/2019 Presentasi Orientasi n Early QCC
35/36
STRUKTUR ORGANISASI PRODUKSI
Section Production
Head : Yosep DanangS
Dept : Daniel Yosa
Supervisor Production
Iqbal A,
Bidron P, Made Adi S
Supervisor Drill & Blast
Edy Sayoga
Supervisor Man Power
Support & Equipment
Syahriel
Group Leader Man Power
Support & Equipment
L. Maksimus, Zaini
Group Leader Pit Service
Damianus Sion, Anzar
Supervisor Pit Service
PormanSilalahi
Group Leader Production
Hendy G, Heri S, Ervin M, Ilmawan K,
Hanafi, M. Basuki, Ifan,
Esra M, Yohanes L
DPP : Julius A, Bambang F, Anggun H,
Robiansyah, Rio Prasmoro
Group Leader Drill & Blast
Abdurahman,
Taupikkurahman,
Agus S
Operator Pump
Operator A2B
Operator DT
Field Support
Checker.Dump Man
Operator Drilling
Operator Forklift
Field Support Checker
Drill & Blast
-
8/9/2019 Presentasi Orientasi n Early QCC
36/36
STRUKTUR ORGANISASI ENGINEERING
CDP
Group Leader Mine Planning
Fazlan Alfarizy, Nur Isa H,
Gito MP
Group Leader Survey
Fahrujiansyah
Supervisor Engineering
Erikson T
Group Leader Project Control
Sultan
Section Engineering
Sec. Head : M. Hawari
Depty. Budi Gangsar
Supervisor Project Control
Rian Satra