week 3-schedule management
TRANSCRIPT
Schedule Managem
ent2
Creating a Schedule
Schedule Management
3Project Update
Last week we defined the scope which will be adjusted as we go through the course.
This week we focus on the dependencies and building the schedule. Going back to our Kitchen analogy, we have to install the base cabinets before we install the counters. Oh yeah, we had to install the floor before the base cabinets
Your assignment will be creating a schedule for our overall project; the key take away from the class is learning how to estimate and understand the dependencies.
The expectation is that you will learn and experience that the decisions made at one phase of a project impact others; then we learn how to handle the change.
Schedule Managem
ent4
Process Groups /Knowledge Areas
Initiation Planning Execution Monitoring & Controlling
Closing
Integration Develop Charter
Develop Prelim scope statement
Develop project management plan
Direct and manage project execution
Monitor and control project work
Integrated change control
Close project
Scope Scope planning Scope definition Create WBS
Scope verification Scope Control
Time Activity Definition Activity Sequencing Activity Resource Est. Activity Duration Est. Schedule
Development
Schedule Control
Cost Cost Estimating Cost budgeting
Cost Control
Quality Quality planning Perform quality assurance
Perform Quality Control
Human Resource Human Resource planning
Acquire project team
Develop project team
Manage project Team
Communications Communication planning
Information distribution
Performance reporting
Manage Stakeholders
Risks Risk management planning
Risk identification Qualitative Risk Anal Quantitative Risk Anal. Risk Response Plan
Risk monitoring & Control
Procurement Plan purchases & acquisitions
Plan Contracting
Request Settler responses
Select Sellers
Contract Admin. Contract Closure
Stakeholder Management
• Identify stakeholders and determine their expectations, influence and impact
Determine roles and responsibilities
Plan communication and stakeholder engagement
Request changes Manage stakeholder
engagement and expectations
Take action to control the project
Influence the factors that cause changes
Inform stakeholders of the results of change requests
Schedule Management
5Estimating
Most projects have issues with estimation because some people are optimistic and some are pessimistic.
You will not know which estimate is accurate unless you had prior substantiating evidence Guess what, you will do this poorly throughout the class – However, you will
learn how to estimate better in the future because you will know the questions to ask or thoughts to eliminate; “OH I SHOULD HAVE THOUGHT OF THAT!
When you estimate for this class plan out how many “billable” hours it will take to complete the task. This will create the baseline – then you will measure what it actually took! This will help you in the future and be frustrating now; however, this is a
free environment to learn vs. the work world. Grading is focused on your thought process not the accuracy of the estimate.
Schedule Management
6Variation in task duration
Why do estimates vary greatly: Skill levels – are you learning something new while performing the work
Potential rework Unexpected events
Personal illness Efficiency of worker’s time
How good are you at managing time Mistakes and misunderstandings
Oops I thought…. Common cause variation (duration is a random value)
Schedule Management
7How to estimate
Similarity to other activities Historical data Expert advice Delphi Technique Three-point technique (aka PERT; what you will most likely use for
this class) Wide-band Delphi Technique
Just think it is easy to estimate for someone else when you are not doing the work!! How many times have we said that should take 10 minutes; yet it takes 2 hours.
In the work world, take time to really think on the estimate so that you can meet commitments.
Schedule Management
8PERT: Estimating Activity Duration The actual duration of any activity is uncertain. Any activity can be later than it can be early (the fundamental law of Project
Management). To save ourselves a lot of math, we estimate activity durations with the
PERT Method: Each activity is assigned three durations:
Shortest expected duration (S) Most likely duration (M) Longest expected duration (L)
The expected duration for each activity is:(S + 4M + L) ∕ 6
Example: M = 4 weeks, S = 3 weeks, L= 8 weeks Expected duration
= (3 + (4×4) + 8) ∕ 6 weeks= 27 ∕ 6 weeks= 4½ weeks
Schedule Management
9Estimates and now the schedule
As a team you have: Created estimates on all the tasks defined in the WBS Thought about your personal schedules and how
much time you plan to commit to the class Added up all those times to figure out how much
“project” time you will do each week (excluding textbook reading, reading these great charts, discussion questions, etc…)
Remember we estimated with hours. The constraints on the project are the hours you commit each week and what you can accomplish
Schedule Management
10Activity-Based Schedulingfrom the WBS
Project
Subproject
Schedule Activities appear on the schedule. They are decomposed from Work Packages. Each is a discrete piece of work, linked to others by logical relationships (dependencies).
Deliverables and/or Project Phases
Work Package
Work Package Work PackageSchedule Activity
Schedule Activity Schedule Activity Schedule Activity Schedule Activity
Schedule Management
11Schedule Activities & Scope of Work
A Schedule Activity is:a discrete scheduled component of work, with Estimated duration Estimated cost Estimated resource requirements
Each Schedule Activity has a Scope of Work: A description in sufficient detail to ensure that project team
members understand what is to be accomplished. The scope of work of each activity defines what work is to be
completed.
Schedule Management
12Schedule Development
Part of the Planning process Analyzes:
Activity sequences and dependencies Activity durations Resource requirements
Produces a Project Schedule Requires:
Activity Duration Estimates Activity Resource Requirements
Schedule Management
13The Schedule:Much More than a List of Dates
The Project Schedule defines: When a project will be complete
(completion date) The intermediate steps along the way
(milestones) The sequence of work activities
(GANTT chart) The interdependence of work activities
(network diagram) Work activities which cannot be delayed
(critical path) Planned start and finish dates for each activity
Schedule Management
14The GANTT Chart
Also called a bar chart. Originated by Henry Laurence Gantt in or before 1910. Shows activities, milestones, durations, and dates. Each activity takes up one row. Each activity refers to the WBS.
Schedule Management
16Why Are Bar Charts not Enough?
GANTT Chart Shows tasks & durations. Does not show dependencies s
Network Diagram Activities on Nodes Dependencies on arrows Activity Durations
Time
ScheduleActivities
F
B
D
A
C
EIf task D completes three days
late, what happens to the project?
A (3)
Start D (2)
B (7) F (2)
E (2)C (3)
End
Schedule Management
17Critical Path
A path through a Network Diagram is a sequence of activities connecting the start and finish.What are the paths through the Network Diagram below?
The critical path in a Network Diagram is the shortest time a project can take from start to finish.
This is also the longest path through the Network Diagram.
Schedule Management
18Critical Path Example
A (3)
Start D (2)
(7) F (2)
E (2)C (3)
End
What is the critical path through the Network Diagram below?
How long is the critical path? BF=9How long will the project take? 9 weeks
Activity durations are in weeks.
Schedule Management
19Network Diagram Exercise
a) Sketch out a Network Diagram (PERT Chart) based upon the following activity durations and dependencies:1. Design
1.1. Design Product 15 Days None1.2. Obtain Approval for Design 5 Days 1.1
2. Development2.1. Hardware
2.1.1. Evaluate & Select Vendors 4 days 12.1.2. Procure Hardware 3 days 2.1.12.1.3. Test Hardware 10 days 2.1.2
2.2. Software2.2.1. Design Software 15 days 12.2.2. Write Software 25 days 2.2.12.2.3. Test Software 9 days 2.2.2
2.3. Integration2.3.1. Integrate Hardware & Software 20 days 2.1, 2.2
3. Site Implementation3.1. Prepare Site 4 days 13.2. Site Installation 5 days 2, 3.1
b) Identify the critical path on your Network Diagram.c) Estimate the Project Duration.
Schedule Management
20Float
An activity on the critical path has no float. An activity not on the critical path may be started at any time
within a certain interval. This interval is the float for that task.
Time
ScheduleActivities
F
B
D
A
C
E
Starting every task as late as possible is seldom the best
strategy.Why?
Schedule Management
21Lengthening the Critical Path
Allocating Resources to activities can lengthen the critical path, due to: Availability Suitability Less than 100% utilization
Time
Activities
F
B
D
A
C
E
Time
Ahmed
Brenda
Chris
F
B
D
A
C
E
GANTT Chart Resource Bar Chart
Vacation
Training
Schedule Management
22Shortening the Critical Path
Fast Tracking starts one activity before a predecessor is complete (at more risk).
Crashing the Project shortens tasks on the critical path by allocating more resources to them (at more cost). Doubling the staff does not halve the time!
Time
Ahmed
Brenda
Chris
F
B
D
A
C
E
Crashed Project
Vacation
Training
Time
Ahmed
Brenda
Chris
Delia
F
B D
A
C
E
Vacation
Training
B
Schedule Management
23Now what?
We have an estimate on each task We have a network diagram of the tasks and we
know the dependencies We know how much time the team will spend on the
project each week Now commit to the tasks that will be done each
week; this will be your baseline Teams will exceed their estimates or might be
pleasantly surprised that their estimate was right Throughout this course think about how you would estimate
better in the future or what you did to a solid estimate
Schedule Management
24Lessons Learned
Now that you put together a schedule, can you get to all the scope defined from last week?
You now need to explain to the customer what can and cannot be done based on this week’s lesson
Imagine if you were talking to a customer last week – would you have thought all that work was able to be done in the semester?
Now we are seeing how decisions from the prior week interrelate with other processes.