subsea production system (sps) control modelling - utpedia

78
Subsea Production System (SPS) Control Modelling by Mohd Muslim bin Abd Koha Dissertation in partial fulfilment of The requirements for the Bachelor of Engineering (Hons) (Mechanical Engineering) September 2013 Universiti Teknologi PETRONAS Bandar Seri Iskandar 31750 Tronoh Perak Darul Ridzuan

Upload: khangminh22

Post on 30-Mar-2023

0 views

Category:

Documents


0 download

TRANSCRIPT

Subsea Production System (SPS) Control Modelling

by

Mohd Muslim bin Abd Koha

Dissertation in partial fulfilment of

The requirements for the

Bachelor of Engineering (Hons)

(Mechanical Engineering)

September 2013

Universiti Teknologi PETRONAS

Bandar Seri Iskandar

31750 Tronoh

Perak Darul Ridzuan

CERTIFICATION OF APPROVAL

Subsea Production System (SPS) Control Modelling

by

Mohd Muslim bin Abd Koha

A project dissertation submitted to the

Mechanical Engineering Programme

Universiti Teknologi PETRONAS

in partial fulfilment of the requirement for the

BACHELOR OF ENGINEERING (Hons)

(MECHANICAL ENGINEERING)

Approved by,

(AP Dr Fakhruldin b Mohd Hashim)

UNIVERSITI TEKNOLOGI PETRONAS

TRONOH, PERAK

SEPTEMBER 2013

CERTIFICATION OF ORIGINALITY

This is to certify that I am responsible for the work submitted in this project, that the

original work is my own except as specified in the references and acknowledgements, and

that the original work contained herein have not been undertaken or done by unspecified

sources or persons.

MOHD MUSLIM B ABD KOHA

ABSTRACT

The motivations of this project work are to develop a simulation model for a direct

hydraulic control system, find the effect of changing key parameters to the system’s

response time, and also to demonstrate Emergency Shut Down (ESD) feature which is a

requirement for the subsea production control systems (SPCS). The methodology of this

project involves selecting a control system to be studied which is a direct hydraulic control

system, gathering technical details and data regarding the control system and components

that constitute the control system, and translating the technical details and concepts into

acceptable simulation forms in the simulation’s software. This project used SimulationX

to simulate the developed model. The developed model consist of a hydraulic power unit,

a topside control panel, hydraulic lines, a subsea control module and two actuator valves.

The Cadlao oil field has been selected as the case study and simulation models were built

according to the Cadlao field’s SPCS. The simulated model is validated by comparing the

Cadlao’s performance curves and the acquired results. The simulation is done by varying

3 parameters which are umbilical length, umbilical diameter, and actuator size. Each

parameter is tested to study its influences on the signal time and shift time. To find the

effect of umbilical length on the signal time, umbilical lengths of 6000 ft, 12000 ft, and

18000 ft have been used. Time taken are 47 s, 110 s, and 195 s respectively. For the

simulation using different umbilical diameters, 0.15 inch, 0.35 inch and 0.50 inch have

been used. Time taken to fully pressurize the umbilical are 111 s, 39 s and 48 s

respectively. For the second part, to find the effect of varying parameters on shift time,

three parameters are changed (umbilical length, umbilical diameter and actuator

diameter). 6000 ft, 12000 ft and 18000 ft umbilical lengths have been used and the

recorded shift times are 13 s, 21 s and 31 s respectively. For the simulation using different

umbilical diameters, 0.15 in, 0.35 in and 0.50 in have been used and the recorded shift

times are 113 s, 19 s and 13 s respectively. Lastly, sensitivity analysis is done using three

different piston diameters. Diameters of 6 in, 9 in and 12 in have been used and the

recorded shift times are 28 s, 36 s and 56 s respectively. Lastly, emergency shut-down

simulated showed that the actuator is able to return to fail safe condition in 33 s.

ACKNOWLEDGEMENT

Firstly, I would like to express my deepest appreciation and gratitude to my supervisor,

AP Dr Fakhruldin bin Mohd Hashim, who has been guiding me throughout this project.

Without his consistent supervisions, concerns and supports, this particular project would

not has been as complete as it is today.

I am also indebted to the final year project’s coordinator, Dr Azmi Abd Wahab for his

time and commitments in arranging various seminars to provide support and knowledge

to assist me in doing this project. I am also would like to thank my final year project poster

and oral presentation’s evaluator, AP. Ir. Dr. Mohd Amin Bin Abd Majid, and my oral

presentation’s examiner, Dr. Mark Ovinis for his time and willingness to assess my

project.

Special thanks to my beloved family who has been supporting and encourage me in

completing this final year project. Lastly, I also would like to thank all the individuals that

have helped me in many ways in doing this project. Thank you.

TABLE OF CONTENT

TABLE OF CONTENT ..................................................................................................... 1

LIST OF FIGURES .......................................................................................................... ii

LIST OF TABLES ............................................................................................................ iv

ABBREVIATIONS .......................................................................................................... iv

CHAPTER 1 ...................................................................................................................... 1

1.1 BACKGROUND STUDY ................................................................ 1

1.2 PROBLEM STATEMENT ............................................................... 4

1.3 OBJECTIVES ................................................................................... 4

1.4 SCOPE OF PROJECT ....................................................................... 4

CHAPTER 2 ...................................................................................................................... 6

2.1 SUBSEA PRODUCTION CONTROL SYSTEM ............................ 6

2.2 DIRECT HYDRAULIC CONTROL SYSTEM ............................... 8

2.2.1 Hydraulic Power Unit (HPU) ......................................................... 9

2.2.2 Topside Umbilical Termination Unit (TUTU) ............................. 10

2.2.3 Subsea Control Module (SCM) .................................................... 11

2.2.4 Umbilical ...................................................................................... 12

2.2.5 Valve Actuator ............................................................................. 14

2.3 ARTICLES REVIEWED ................................................................ 16

2.4 LITERATURE SUMMARY ........................................................... 20

2.5 AGITO SIMULATIONX ................................................................ 22

CHAPTER 3 .................................................................................................................... 25

3.1 WORKFLOW ................................................................................. 25

3.2 PROJECT ACTIVITIES ................................................................. 27

3.3 CASE STUDY ................................................................................ 27

3.4 MODEL CONCEPTUALIZATION ............................................... 31

3.5 MODEL TRANSLATION .............................................................. 33

3.5.1 Hydraulic Power Unit Model ....................................................... 33

3.5.2 Topside Umbilical Termination Unit (TUTU) Model.................. 34

3.5.3 Hydraulic Lines Model ................................................................. 35

3.5.4 Subsea Control Module Model ..................................................... 37

3.5.5 Subsea Actuator Valve Model ...................................................... 38

3.6 OVERALL MODEL ....................................................................... 39

3.7 MODEL VALIDATION ................................................................. 41

CHAPTER 4 .................................................................................................................... 44

4.1 SYSTEM BEHAVIOUR ................................................................. 45

4.1.1 Gate Valve .................................................................................... 45

4.1.2 Umbilical ...................................................................................... 47

4.2 SIGNAL TIME ................................................................................ 48

4.2.1 Umbilical’s Bulk Modulus Effect ................................................ 48

4.2.2 Umbilical’s Length Effect ............................................................ 49

4.2.3 Umbilical’s Inner Diameter Effect ............................................... 50

4.3 SHIFT TIME ................................................................................... 52

4.3.1 Umbilical’s Length Effect ............................................................ 52

4.3.2 Umbilical’s Inner Diameter Effect ............................................... 53

4.3.3 Actuator’s Size Effect .................................................................. 54

4.4 EMERGENCY SHUT DOWN (ESD) ............................................ 55

CHAPTER 5 .................................................................................................................... 58

5.1 CONCLUSION ............................................................................... 58

5.2 RECOMMENDATION ................................................................... 60

REFERENCES ................................................................................................................. 61

APPENDICES ................................................................................................................. 64

ii

LIST OF FIGURES

Figure 1: Global oil consumption [1] ................................................................................. 1

Figure 2: Offshore production from 1970 to 2020 [1] ....................................................... 2

Figure 3: World subsea hardware market [1] ..................................................................... 2

Figure 4: Direct hydraulic control system [7] .................................................................... 8

Figure 5: Hydraulic power unit [7] .................................................................................. 10

Figure 6: TUTU [8] .......................................................................................................... 10

Figure 7: Typical subsea control module [10] ................................................................. 12

Figure 8: Direct hydraulic umbilical [12] ........................................................................ 13

Figure 9: Hydraulic control line criteria [4] ..................................................................... 14

Figure 10: Subsea production valves on X-mas tree [14] ................................................ 15

Figure 11: Illustrations of a typical gate valve in closed and open position [13] ............ 15

Figure 12: Typical volumetric curve for 1" line (2000 ft. length) [4] .............................. 16

Figure 13: Leakage hydraulic control system [16] .......................................................... 19

Figure 14: Simplified SPARSC design [17] .................................................................... 20

Figure 15: SimulationX GUI Overview [20] ................................................................... 23

Figure 16: Elements in subsea library [20] ...................................................................... 24

Figure 17: Flow Chart of the Project................................................................................ 26

Figure 18: Cadlao Oil Field [23] ...................................................................................... 28

Figure 19: Schematic of test arrangement [21] ................................................................ 29

Figure 20: Effect of valve volume and hose size to shift time [21] ................................. 30

Figure 21: Effect of hose length and hose diameter to the signal response time [21] ..... 30

Figure 22: Model conceptualization................................................................................. 31

Figure 23: Signal time and shift time [21] ....................................................................... 32

Figure 24: Overall response time expected behaviour [21] ............................................. 33

Figure 25: HPU Model [20] ............................................................................................. 34

Figure 26: HPU model and parameters ............................................................................ 34

Figure 27: TUTU model and parameters ......................................................................... 35

Figure 28: Distributed Line Model [13] ........................................................................... 35

iii

Figure 29: Umbilical's parameter definition [20] ............................................................. 36

Figure 30: Umbilical’s parameters [20] ........................................................................... 36

Figure 31: Umbilical model [20] ..................................................................................... 36

Figure 32: SCM schematic diagram ................................................................................. 37

Figure 33: SCM modelled in SimulationX ...................................................................... 37

Figure 34: Main parameters for the check valve .............................................................. 38

Figure 35: Actuator definition and parts [20] .................................................................. 38

Figure 36: Actuator model and parameters ...................................................................... 39

Figure 37: Overall simulation model ............................................................................... 40

Figure 38: Fluid properties [24] ....................................................................................... 42

Figure 39: Umbilical parameters [25] .............................................................................. 43

Figure 40: Gate valve behaviour during opening and closing ......................................... 45

Figure 41: Pressure drop when operating second actuator............................................... 46

Figure 42: Umbilical hose pressurization ........................................................................ 47

Figure 43: Umbilical pressurization time for different bulk modulus ............................. 48

Figure 44: umbilical pressurization at different length .................................................... 49

Figure 45: Umbilical pressurization at different diameter ............................................... 50

Figure 46: Cadlao response time for umbilical at different length and diameter [21] ..... 51

Figure 47: Shift time for different umbilical length ......................................................... 53

Figure 48: Effect of varying hose diameter...................................................................... 54

Figure 49: Effect of actuator size on shift time ................................................................ 55

Figure 50: Gate valve time to return to safe state ............................................................ 56

Figure 51: correction on spring force and preload force on spring .................................. 57

iv

LIST OF TABLES

Table 1: Advantages and disadvantages of subsea system ................................................ 3

Table 2: Control system selection criteria ........................................................................ 17

Table 3: Summary of literature review ............................................................................ 21

Table 4: Function of areas in SimulationX GUI .............................................................. 23

Table 5: Data used in Cadlao field [21] ........................................................................... 28

Table 6: HPU configurations ........................................................................................... 41

Table 7: Umbilical configurations ................................................................................... 41

Table 8: Actuator configurations ..................................................................................... 42

Table 9: Effect of varying bulk modulus of hose pressurization ..................................... 49

Table 10 : Effect of varying umbilical length to pressurization time .............................. 49

Table 11: Effect of varying umbilical diameter on pressurization ................................... 50

Table 12: Time taken to fully open actuator valve using different hose length ............... 53

Table 13: Recorded time for piston to fully shift to the other end ................................... 54

Table 14: Recorded shift time for different piston diameter ............................................ 55

ABBREVIATIONS

CAPEX Capital Expenditures

CIU Chemical Injection Unit

DCV Directional Control Valve

DHSV Down Hole Safety Valve

HIPPS High Integrity Pressure Protection System

HPU Hydraulic Power Unit

OPEC Organization of the Petroleum Exporting Countries

SCM Subsea Control Module

SDU Subsea Distribution Unit

v

SEM Subsea Electronic Module

SPCS Subsea Production Control System

SPCU Subsea Power and Communication Unit

SPS Subsea Production System

SRM Subsea Router Module

UTA Umbilical Termination Assembly

XT X-mas Tree

1

CHAPTER 1

INTRODUCTION

1.1 BACKGROUND STUDY

Nowadays, oil and gas exploration have moved toward deeper water region due to increase

in demand for more oil and gas energy. It also due to depletion in shallow water oil

reserves. Figure 1 shows forecast global oil consumption from 1965 until 2035.

Figure 1: Global oil consumption [1]

With overall OPEC (Organization of the Petroleum Exporting Countries) oil production

is declining, the key drivers of growth in oil production are the US and Canada.

Exploration and production (E&P) expenditure growth is growing slowly but still healthy

(Barcap report 8.8% in 2012 vs. 10% forecast. 7% forecast for 2013). Although E&P

expenditure is not increasing as rapidly as expected, report on SUT by Liam Kelleher state

2

that current predictions that total E&P expenditure is expected to increase from US$600

billion in 2012 to US$644 billion in 2013. Along with increase in offshore spending,

subsea hardware is predicted to have an overall CAPEX of US$135 billion spread over

the next five years (representing a 14% increase from previous five years) [2]. Figure 2

present the deep-water production statistic and Figure 3 present the world subsea hardware

market.

Figure 2: Offshore production from 1970 to 2020 [1]

Figure 3: World subsea hardware market [1]

3

Subsea production system is a combination of subsystems that have their own roles aiming

to assist in bring out hydrocarbon from reservoir to the surface and stores at a topside

facility or at a distance facility. The main subsystem are [3]:

Subsea well heads and x-mas tree equipments

Production control system

Umbilicals

Intervention system

Subsea structures and piping systems

Subsea flow lines

Table 1: Advantages and disadvantages of subsea system

Advantages Disadvantages

Eliminate or reduce CAPEX of the

platform Complex hardwares

Cost burden transferred from CAPEX to

OPEX Inaccessible for maintenance and repair

Construction cycle is conducive to fast-

track projects Intervention is expensive and complex

Suitable to phased projects

The brain of the subsea production system is the production control system which control

all the subsystems that comprise the SPS for the aim of producing hydrocarbon. Subsea

production control system (SPCS) is used to control subsea control valves installed on

subsea equipments located on seabed. SPCS is also used to provide information of the

subsea equipment’s status. In term of safety, SPCS is required to detect adverse conditions

and effect its own automatic shut-down to prevent accident or broken equipment [4].

SPCS is designed according to standards regulated by industry, national and international

agencies including the operation, design and testing of the system. System is subjected to

strict quality reviews such as failure modes, effects and critical analysis.

4

1.2 PROBLEM STATEMENT

As oil field moving toward deeper region, as shallow water reserves have mostly depleted,

operator requires new technologies to be implemented to cope with new challenges faced

in this region. To understand new technology capabilities, beside physical experiment on

model, which will consume a lot of time and very costly, developer nowadays are using

simulation software to virtually test their proposed solution. By simulation, system can be

virtually tested in various operation conditions and verified the system capability to run

in the field. This will increase the confidence in the system. Despite that, many other

alternative solutions also can be tested and each solution can be compared to find the most

dependable one. For example, the effect of varying dimension of umbilical or different

actuator size can be analysed and their impact to system performance can be acquired

quickly. The need for simulation is heightened as umbilical is the most expensive

component in subsea system, and if wrongly dimensioned, it can result in major time and

cost overruns. Therefore, various alternative solutions of umbilical can be tested through

simulation in order to select the best solution.

1.3 OBJECTIVES

The objectives of this project are:

1. To develop simulation model for a direct hydraulic control system.

2. Investigate model’s signal time and shift time under varying parameters.

3. Investigate model behaviour under emergency situation.

1.4 SCOPE OF PROJECT

The scope of the study covers the following:

1. Study on a various subsea control system and select a system for modelling and

simulation.

2. Develop a simulation model focusing on the critical components in subsea

production control system (hydraulic power unit, umbilical, subsea control

5

module, and actuator) that operates the subsea gate valves and effectively

illustrates the gate valves operations on controlling an oil or gas flow.

3. SPCS model is simulated using real operating field data acquired from patents.

4. Behaviours of the developed umbilical and gate valves are studied and their effects

on the system’s response time aer shown through performance curves.

5. Emergency shut-down feature included in model is simulated to show system

behaviour under emergency situation.

6. Cadlao oil field is selected as the case study for this project and the developed

simulation model is validated by comparing the performance curves of the Cadlao

field and the acquired results.

6

CHAPTER 2

LITERATURE REVIEW

2.1 SUBSEA PRODUCTION CONTROL SYSTEM

With reference to API 17F, subsea production control system is defined as a control

system operating a subsea production system during operations [5]. Subsea Production

Control System (SPCS) manages the operation of subsea equipment located on the seabed

during various subsea functions execution. The control functions include:

1. Operates valves and chokes on subsea trees, manifold/templates, and pipelines

remotely from topside.

2. Receives and transmits the data between the topside and subsea equipment, which

helps engineers monitor the status of production.

3. Enable safe operation of subsea wells by enabling the operator to control the

opening and closing of valves and perform shut down operation during emergency.

Appendix I illustrates an overview of a subsea production control system. The control of

SPCS is done at the topside facility and transferred to seabed where the control function

is executed. It typically consists of three sections [6]:

1. Topside (surface control unit)

Comprises of a hydraulic power unit (HPU), electric power unit (EPU) and well

panel. The HPU can be on surface station on land or a work over rig platform.

2. Umbilical (control line)

Combination of electric cables, hoses or steel tubes, either on their own or in

combination (or with fibre optic cables), cabled together to increase flexibility and

mechanical strength. It is used to transfer electrical power and signals, hydraulic

7

power, and/or chemicals to the subsea components on the subsea production

system.

3. Subsea installations

Subsea installations include subsea control module (SCM), subsea distribution

systems (distribute chemical, electrical, and hydraulic from umbilical

termination), and subsea located sensors.

Satisfactory response time is an important factor that may affect system’s reliability and

safe of operation. As communication distance between topside production facilities and

subsea installations increases, total well that have to be controlled increases and water

depth become deeper, earlier control method using direct hydraulic control become less

feasible. As a result, more advanced and complex control method being developed. There

are several type of control system:

1. Direct Hydraulic Control System

2. Piloted Hydraulic Control System

3. Sequential Piloted Hydraulic Control System

4. Hard-wired Electrohydraulic Control System

5. Multiplexed Electrohydraulic Control System

Selection of fluids to be used should consider maximum operation temperature and

pressure that the fluid will be exposed to. Besides, compatibility of the fluid with system

components also have to be considered [5]. Two commonly used fluid for subsea

production system are high water content-based or synthetic hydrocarbon control fluids.

Mostly used fluid is high water content-based.

The characteristics of high water content-based fluid depend on the ethylene glycol

content (typically 10% to 40%), viscosity varies with temperature (normally 2-10oC). Due

to government regulations does not allow venting mineral-based oil into the sea, the

system that uses this type of fluid must be closed-loop system, which requires extra

conduit in the umbilical, thus making it more complex [6].

8

2.2 DIRECT HYDRAULIC CONTROL SYSTEM

Direct hydraulic control system operation is the relatively simple and straight forward

system in which HPU and control panel for each well to be controlled located on the

topside facility. The control panel consist of solenoid-operated control valve which control

the flow of the hydraulic fluid. When operator set the control valve on control panel to

open position, allowing pressurized fluid to pass through and transported to actuator

located on the X-mas tree via umbilical hose.

Figure 4: Direct hydraulic control system [7]

The system advantages are relatively simple control system, high reliability, ease of

service, and minimization of subsea components [6]. Regardless of the strengths of the

control system, it also has downsides such as complex hydraulic line as it has to contain

all the individual line for each subsea function. The size of the umbilical also increased.

Hence, cost also increased. Besides that, it has slow response time caused by the need to

TOPSIDE

SUBSEA

9

pressurize the fluid until it reached the pressure that enough to operate subsea actuator or

to perform other task. Slow response of the hydraulic fluid is influenced by the fluid’s

properties (e.g. bulk modulus, viscosity), characteristics of the umbilical (e.g. wall

roughness, elasticity) and compliance and volume of actuators. Due to slow response time,

this type of control system is limited to applications where the distance between the

topside facility and the operated subsea equipment is less than 3-4 km [6].

2.2.1 Hydraulic Power Unit (HPU)

By NORSOK Standard’s requirement, HPU shall supply regulated hydraulic fluid to the

subsea installation. Output fluid from the HPU shall as a minimum satisfy cleanliness

requirement of NAS 1638 class 6. Hydraulic system shall be designed 10% above the

maximum operating pressure. Maximum operating pressure should be 5% above normal

operating pressure. Typical operation pressures for Christmas tree and manifold functions

are 3000 psi and 9000 psi for down hole safety valves (DHSV) functions. The pressure

difference is dictated by the function of water depth and process pressures [6].

HPU functioned to supply fluid at correct pressure, flow rate and acceptable cleanliness

to remotely operated subsea valves through the umbilical. The reason for cleanliness is to

maintain the reliability of the system. Besides that, HPU also regulates supply pressure to

avoid overpressure or during insufficient hydraulic pressure. HPU normally installed on

the FPSO or platform or may be located onshore for subsea-to-beach tiebacks. Fluid is

supplied via the controls umbilical, the subsea hydraulic distribution system, and the

SCM’s to operate subsea valve actuators. The pressurized fluid provided by pump is

driven by an electric motor. There are many types of pump, but the most common type

uses accumulators that are charged by fix pumps. Redundancy for the motor pump sets

act as backups in case of pump failures or maintenance.

10

Figure 5: Hydraulic power unit [7]

2.2.2 Topside Umbilical Termination Unit (TUTU)

TUTU is the interface between the surface and subsea equipment. The function of TUTU

is to route hydraulic fluid from the HPU to the subsea umbilical. It provides hose coupling

points and an electrical junction box. Additionally, it houses block and bleed valves for

each hydraulic function.

Figure 6: TUTU [8]

11

2.2.3 Subsea Control Module (SCM)

SCM is the interface between the control lines and various end users such as actuators

located on trees and manifolds. SCM can be installed on a subsea tree, manifold template

and other components and it is packaged in a retrievable housings. SCM consists of many

components such as:

1. Electrohydraulic or hydraulic piloted DCV and other valves (check valves and

shuttle valves)

2. Sensors and transmitters

3. Filters

4. Accumulators

5. SEMs

Typical well control functions provided by SCM are [9]:

1. Actuation of fail-safe return production tree actuators and down hole safety valves

and other valves (e.g. shut-off valves, choke valves)

2. Provides data (e.g. pressure, temperature and flow rates) of subsea systems.

3. Monitoring position of chokes

4. Filters hydraulic fluid

5. Direct hydraulic fluid supply to respective lines to actuate valves

Directional control valves located on the SCM will directs fluid to or from actuators during

operation by controlling the spool position or orifice area.

12

Figure 7: Typical subsea control module [10]

2.2.4 Umbilical

Umbilical is a composite cable containing tension wires, hydraulic pipes, electrical power,

control and communication signals which is installed from host facility to subsea

installations [11]. The main functions of the umbilical are:

1. To deliver control fluids or electric control signals to control the functions of

subsea equipment (e.g. tree, valves, manifold)

2. To convey chemical during chemical injection to subsea trees or manifolds

3. To monitor pressures in well annulus

There are many types of umbilical and the choice of umbilicals can depend on the

application and type of system deployed. Figure 8 shows the umbilical used for direct

hydraulic control system.

13

Figure 8: Direct hydraulic umbilical [12]

Umbilical dimensions typically range up to 25.5 cm in diameter. The umbilical may be

very long, in some cases up to 20 km or more depending on the offset between the host

facility and the subsea equipment that it connecting to. To avoid any potential faults, the

umbilicals are fabricated in continuous length [6].

Due to long umbilical’s length, the flow resistance in the hydraulic line becomes

substantial and can affect the response time of the valve actuators in the system. The

ability of hoses to accumulate liquid can be a disadvantage in a system that requires rapid

bleeding of lines. However, this property can also turned into an advantage in systems

where large actuators are to be operated. Using hoses with high volumetric expansion can

be in some cases replace accumulators on the seabed.

The design of the hydraulic lines are important to the performance and operation of the

whole system. It is therefore important that model of the hose is accurate, and that it

includes the delays that are experienced in real operations [13]. There are many types of

umbilical available such as hybrid umbilical, thermoplastic, steel tube, optical fibre and

electrical power components. Figure 9 shows the criteria in selecting hydraulic lines. For

14

this report, 2 criteria of hydraulic line will be simulated to investigate the impact on the

system response time which are the length of control line and size of hose bore.

Figure 9: Hydraulic control line criteria [4]

2.2.5 Valve Actuator

Typically, linear actuators are used in the SPCS [13]. In subsea production system,

production valve is used to control oil and gas flow from wells. Wellhead Xmas tree is

installed on top of the wells comprises process control valves, where each process control

valve is provided with an actuator for the operation of the valves. Actuators can be

operated electrically or hydraulically but mostly for wellhead Xmas tree, hydraulic

actuator is used.

15

The switching of the actuator valves is by mean of hydraulic which uses spring-return

actuators. The maximum actuation pressures that occur during opening of valves that are

in closed, pressurised position, typically as follows [6]:

1. Tree valve open: 750-2200psig (50-140bar)

2. Tree valve closed: 600-1000psig (20-65bar)

3. Down hole safety valve open : 2500-9200psig (160-600bar)

4. Down hole safety valve closed: 500-4500psig (32-290bar)

Figure 10: Subsea production valves on X-mas tree [14]

Figure 11: Illustrations of a typical gate valve in closed and open position [13]

Annulus

Master

Valve Chemical Injection

Metering Valve

Production Master

Valve

SEABED

SUBSURFACE

WELLHEAD

Production Wing

Valve

Surface Controlled

Subsurface Safety Valve

16

2.3 ARTICLES REVIEWED

Subsea production control system has been crucial and the most interesting topic for

researchers. The need for new technology to be applied in the field drives researchers to

continually investigate potential technology that can be introduced to overcome

challenges found in the field.

Tony Pipe through his work, SPE 13399, has extensively outlined the hydraulic aspects

of subsea control system. Various system configurations and particular applications are

discussed. He did discussed about other type of control systems such as pilot hydraulic,

sequence hydraulic, electro hydraulic and multiplexed control system which are designed

as a solution to the problems faced in the oil field industry as shown in Table 2. He also

present the scenarios that lead to the solutions and considerations for the subsea system.

Factors to consider for fluid selection are included in the paper and he also mentioned

about the criteria that people in the industry normally try to maintain through the operation

(e.g. bacterial growth). For control lines, he is comparing between flexible hose and rigid

line. He states that majority of expansion experienced in the flexible hose happened during

low pressure range which can be eliminate by incorporating a pre-charge pressure of 500

– 1000 psi, which will greatly reduce the response time [4].

Figure 12: Typical volumetric curve for 1" line (2000 ft. length) [4]

17

In the end, he highlighted that the most important system characteristics that should be

considered. The characteristics are as the following [4]:

1. How quickly can a system be charged and ready for operation?

2. The time required to open or close valve actuators under normal condition.

3. How many valves can be operated before hydraulic pressure need to be re-charge?

4. What is the system leak rate likely to be?

5. What is the maximum leak rate that may be tolerated and still permit valve

operations?

All systems are likely to have leakage. In system that operates multiple valves, the leak

rate for each valve maybe small but as combined with all the leakage for all the valves,

total leakage will be multiplied. This is very important when sizing control lines and

accumulators [4].

Table 2: Control system selection criteria

System Distance

(km)

Response

time Subsea line Function supply

Direct hydraulic 5 Very slow Very large hose

bundle Control

Piloted hydraulic 5 Slow Very large hose

bundle Control

Sequential

hydraulic 8 Slow

Large hose

bundle Control

Electro hydraulic 10 Fast Large electro-

hydraulic cables

Control, data

limited analogue

inputs

Multiplexed

electro hydraulic 15 Fast

Small electro-

hydraulic cables

Control, data

analogue inputs,

pulse counts

Subsea hydraulic

power generation 30 fast

Small electric

cable

Control, data

analogue inputs,

pulse counts

Other researcher, Thomas Stavenes, in his Master thesis titled “Subsea Hydraulic Leakage

Detection and Diagnosis” discussed about numerous ways on detecting leakage. In the

thesis, he states that 98% leakage in hydraulic system were caused by directional control

valve (DCV) problems. The problems were caused by the long term seawater presence

18

due to the seawater ingress during installation. Besides that, hydraulic fluid caused

biodegradation that led to the DCV leakage. In other statement, he states that close circuit

system is more reliable than open circuit system due to seawater ingress and type of fluid

used (water based or mineral based) [15].

The following state-of-the-art leakage detection and diagnosis methods that can be used

for pipeline [15].

1. Line balance calculation (conservative of mass)

2. Real time transient model (simulation model)

3. Statistical analysis (by comparing historical data)

4. Pressure/flow monitoring

The author also mentioned about the current leakage detection and diagnosis efforts that

are used such GE Smart Centre which responsible to monitor and gather data from subsea

from around the world, and then interpret the data to gain knowledge for decision

purposes. Another technology used by FMC is Condition and Performance Maintenance

(CPM) which functioned to monitor systems including subsea control system. Data

collected from SCM and sensors are then processed for decision purposes [15].

Another work done a group of three inventors to detect leakage in subsea production

control system. In the patent, leakage detection is done by monitoring the valves

signatures during accumulator recharging. The pressure differential between two points

adjacent to subsea equipment (before and after component) should be zero for non-leaking

system. Figure 13 shows leaking hydraulic control system of an approximately 5 gpm

[16].

19

Figure 13: Leakage hydraulic control system [16]

Todays, exploration and production are moving toward deeper regions, and there are many

efforts in tackling new challenges arise. Developers are suggesting solutions to cope with

the new obstacles. One of the solution proposed is by using all electric subsea system.

There are many articles and patents discussing this technology. M. Theobald in his

research paper titled “Autonomous Control System (SPARCS) For Low Cost Subsea

Production Systems” describes a Subsea Powered Autonomous Remote Control System

(SPARCS) which is invented for controlling subsea infrastructures without the use of

electro-hydraulic control umbilicals. One of the benefits of using SPARCS is low cost

subsea developments. By using acoustic telemetry for communication between surface

facility and subsea infrastructures, this innovation is estimated to reduce overall costs by

£72.5million over a period of 10 years. Currently, the breaks even on capital outlay

compared with existing technology is when the total length of umbilical approximately

2.3km [17].

In another paper, M. Theobald addressed the benefits of using all electric subsea

production control systems [18]. The benefits including the cost saving in the capital

expenditures and the operational expenditures due to increase in system reliability,

availability and maintainability.

20

Figure 14: Simplified SPARSC design [17]

This technology has already been successfully implemented in K5F in the North Sea

operated by Total E&P Netherland BV, hence, becomes the world first field uses all-

electrical x-mas tree. The supply of the all-electric subsea production system was awarded

to Cameron. The field began production in September 2008 at initial rate of 45Mmscf/day

and increased up to 90Mmscf/day in few months later. With the advancement of the

technology, the exploration towards harsher and isolated region which impossible to

develop before this, will be feasible [19].

2.4 LITERATURE SUMMARY

Through literature review, few bench markings or key references have been taken as the

basis for developing simulation models for this project. The main points or bench

markings extracted from literature review are illustrated in Table 3.

21

Table 3: Summary of literature review

Author/s Year Title Finding

NORSOK

Standard 1995

Design Requirements:

Subsea Production

Systems

1. Control system main

components and functions

2. Emergency shut-down < 60s

(Work over control system)

3. Main components encompass a

SPCS

Technical

Committee

ISO/TC 67

2003 API Specification

17F

1. Rated working pressure for

hydraulic control components

(exclude SCSSV) = (10.3 MPa,

20.7 MPa, 34.5 MPa)

2. Subsea pipe, tubing and hoses <

6 mm nominal outside diameter

Baha Tulu Tanju,

Hailing An,

Karamchandani

2008 Subsea Control

System Diagnosis

Method used to detect leakage in

system.

Thomas Stavenes 2010

Subsea Hydraulic

Leakage Detection

and Diagnosis

Methods for leakage detection in

subsea system.

Jacek S Stecki 2003

Production Control

Systems – An

Introduction

1. Various type of control systems

is extensively discussed

including the main components

(HPU, umbilical, gate valve).

2. Advantages and disadvantages

of each system.

Tony Pipe 1982

Subsea Hydraulic

Power Generation

and Distribution for

Subsea Control

Systems

1. Criteria for selecting control

system components.

2. Concerns when operating

multiple valves.

3. Basic components in subsea

production control system.

M Theobald

2005

Benefits of All-

Electric Subsea

Production Control

Systems

1. Issues in existing subsea

developments.

2. Concerns when developing new

system.

3. Future technology to be

applied. 1993

Autonomous Control

System (SPARCS)

for Low Cost Subsea

Production Systems

22

2.5 AGITO SIMULATIONX

SimulationX is a program for modelling, computation, simulation, and reliability analysis

of components and systems in many areas of technological development. The

computational includes mechanics, fluid, control, electrical technology and magnetics are

represented by models which are found in the libraries. With the integrated models found

in SimulationX’s library, systems or models can be designed fast and efficiently with

validated standard elements. This include subsea hydraulic library which contain

commonly used elements.

Users also can create their own models without the need for setting up differential

equations, signal flow diagrams or transfer functions. Elements can be arranged and

connected graphically in order to resemble the physical structures of needed systems or

components. The variables such as the pressure, temperature, density are kept as simple

as possible and close to the technical device. Furthermore, it also can be manipulated to

comply with the experimental system’s parameters. An extensive fluid library offers a

great variety of predefined hydraulic fluids. However, users can easily modify the

predefine fluid as needed [20]. The working area of ITI SimulationX can be subdivided

into different windows and areas as illustrated in Figure 15.

23

Figure 15: SimulationX GUI Overview [20]

Table 4: Function of areas in SimulationX GUI

Menu bar Allow access to all tools and commands

of SimulationX

Task pane List frequently used command and can be

called directly from here

Library bar Serves for selection, management and

editing of elements types

Model view

SimulationX support 4 types of views

(diagram view, 3D view, text view and

documentation view)

Result window To display result curves

Result window manager Facilitates the central management of the

result windows of all opened models

Model explorer Offers access to properties of the

components of a simulation model

Output area Output area messages, tracing outputs,

warnings and error messages are logged

24

Subsea library included in this software help in modelling the SPCS for this project. The

subsea library consist of several elements as can be seen in Figure 16 below.

Figure 16: Elements in subsea library [20]

25

CHAPTER 3

METHODOLOGY

3.1 WORKFLOW

This project work aims to investigate the effect of varying length and diameter of

umbilical, and size of actuator to the model’s signal time and shift time. Firstly, simulation

model have to be developed. In this chapter, work flow of this project is elaborated. For

this project, direct hydraulic control system have been chosen to be modelled. The reasons

for choosing direct hydraulic control system are:

1. Direct hydraulic control system is the simplest control system. Therefore it will

not generate complex simulation model as the components included are hydraulic

power unit, control panel, umbilical, subsea control module, and actuator.

2. Direct hydraulic control system is the most common control system. For this

reason, huge range of aids can be found to assist model development.

3. Can be a stepping stone in understanding newer and complicated control system

such as electro-hydraulic control system.

4. As the case study selected for this project used a direct hydraulic control system,

therefore, simulation model is developed based on the real system for the

validation purposes.

Modelling and simulation of SPCS involves observing the system, noting various

components that building it, developing an acceptable representation of the system for

further study and experimentation virtually to understand its behaviours, interaction

between components and evaluate the operations of the system. With proper analysis,

suggestions can be made for further improvement of the system.

26

In order to make sure project’s plans executed properly, process flow is created and

followed. This also helped in identifying the main concerns and aims for this project and

determine the steps to be taken if problems occur. Figure 17 illustrates the project flow

chart.

Figure 17: Flow Chart of the Project

27

3.2 PROJECT ACTIVITIES

Project Gantt chart can be seen in appendices section. It is the list of all the activities done

throughout this project.

3.3 CASE STUDY

SPE 12001 by W.S. Manuel and J.E. Hall has been acquired and selected for further study

[21]. The report on Cadlao oil field located in Philippines shows the performances of the

field using a direct hydraulic control system. The experimental testing in the SPE 12001

report was simulated in 29 different operating conditions and data and results from this

report is crucial for this project especially in validating the developed simulation model.

Due to time constrain only a few of the tests will be used to validate simulation model.

The offshore 20 m depth Cadlao oil field located 400km southwest of Manila in the

offshore North West Palawan, Philippines was discovered in 1977 by Amoco. The field

is then developed in 1981 and produced about 11.235 mmbbls of light oil (47o API) from

two wells by natural flow. Its production stopped in 1991 due to high operating costs and

low oil prices. Two reports showed that the remaining oil reserves is around 6 mmbbls

(most likely) and 4 mmbbls (proven) [22]. Redevelopment of the field by Blade Petroleum

Limited that act as the operator with share of 80% of equity interest in the field and

VenturOil Philippines Inc. has the 20% of the equity interest.

The reasons why Cadlao oil field has been chosen as case study are:

All the required parameters for this project is well presented in the report by W.S.

Manuel and J.E. Hall and therefore making the simulation possible.

The testing results conducted at Cameron Iron Works plant in Berwick, Louisiana

are also included in the report. Hence, validation of developed control system is

possible by comparing the performance curves of the field and the acquired results

from model.

28

Figure 18: Cadlao Oil Field [23]

The schematic of test arrangement that Cameron Iron Works used is shown in Figure 19

and data used are shown in Table 5.

Table 5: Data used in Cadlao field [21]

Umbilical Length 6000 ft (1830 m)

4 hoses ½ inch inner diameter @ 3500 psig

3 hoses ¼ inch inner diameter @ 5000 psig

valve 4 inch piston diameter

Estimated operating time for ½ inch hose 60 – 90 seconds

Fluid 10% Cameron 590 in water at 45 – 55 oF

(SG=1.072, viscosity@100oF=3.78 cSt)

29

Figure 19: Schematic of test arrangement [21]

The reason for presenting the schematic diagram and the data is to show that the simulation

model developed is based on the system’s configuration used by the Cameron Iron Works.

The real data are used in simulating the developed model and validation done by

comparing results acquired with the actual results.

Figure 20 shows the effect of varying hose size (diameter) and valve volume (diameter)

to the shift time and Figure 21 illustrates the effect hose length and hose diameter to the

signal response time for Cadlao field’s control system.

30

Figure 20: Effect of valve volume and hose size to shift time [21]

Figure 21: Effect of hose length and hose diameter to the signal response time [21]

6000 feet 12000 feet

18000 feet

31

3.4 MODEL CONCEPTUALIZATION

Before simulation models are constructed in simulation software, it is important to

understand the system first and construct a conceptual framework that describes the

system in order to give a better insight on critical components in the system. By

understanding the concept of the system and components inside it, this will help to avoid

miss-place or missing in critical components in simulation model afterward. Figure 22

below illustrates the components that have been selected for modelling.

Figure 22: Model conceptualization

32

Despite satisfactory operational characteristics, control system also need to have

acceptable response time in order to ensure its reliability and safe operational. Response

time is the combination of signal time and shift time.

Signal time is the time required for the pressure wave to travel down the control line

connecting topside facilities and subsea equipment and for the pressure to build up (or

decay) to the level necessary for the valve actuator to start to shift. Figure 23 below shows

the signal behaviour if the line was blocked at the gate valve actuator.

Shift time is the time required for the valve gate to travel from one end to the other [21].

Figure 23: Signal time and shift time [21]

33

Figure 24: Overall response time expected behaviour [21]

3.5 MODEL TRANSLATION

After the conceptual framework that describes the system is identified, next stage is to

translate the concept into acceptable simulation forms in simulation software which is

SimulationX. Elements to be modelled are HPU, TUTU (DCV), Umbilical, SCM (DCV)

and gate valve actuators. Several other elements such as piping and local resistances also

included to account for losses that are experienced in real practices.

3.5.1 Hydraulic Power Unit Model

During modelling stage, HPU is modelled as shown in Figure 25. Based on literature

review, HPU is required to provide a clean and pressurized hydraulic fluid for actuation

of the actuators. For modelling, HPU model includes two pumps, a tank, an accumulator,

a pressure regulator, and two check valves. The two pumps included are duty pump and

standby pump. Standby pump only starts when the pressure of the system drop below the

pre-set pressure which is 310 bar, and both pump stop when fluid supplied have reached

the pre-set pressure which 510 bar. To simplify the model, only major components with

minimal redundancy included in the model. The limitations also applied based on the

SimulationX capabilities. The developed model is based on the following assumption:

34

1. The model does not take contaminations in the fluid into account and therefore

dividing filter between reservoirs shall not be used.

Figure 25: HPU Model [20]

For this simulation, the HPU is already defined in the SimulationX’s library. The HPU

model and parameters needed are as in Figure 26.

Figure 26: HPU model and parameters

3.5.2 Topside Umbilical Termination Unit (TUTU) Model

As describe in Chapter 2, TUTU is used to route hydraulic fluid from HPU to the subsea

umbilical. In SimulationX, TUTU is represented as 2 ways, 3 ports directional control

valve (DCV) which allows or terminates hydraulic fluid flow.

35

Figure 27: TUTU model and parameters

3.5.3 Hydraulic Lines Model

Hydraulic line or umbilical is one of the most important components in hydraulic control

system. It is used to transport pressurized fluid from topside to subsea equipment and vice

versa. The umbilical properties such as elasticity and flow resistance of the umbilical will

affect the system response time. For system that requires fast bleeding time, this could be

a great disadvantage but as for operating big actuators, high expansion hoses will be an

advantage. Therefore, it is important to model the umbilicals accurately.

Umbilicals have been modelled using distributed line model. For this method, the spatial

distribution of the fluid flow along the length of the umbilical is considered. Therefore,

all flow and fluid variables (e.g. pressure, flow, density, compressibility) are not only a

function of time, but also a function of space. With the modelling of fluid behaviours in

hydraulic lines, we can include the time delays during operation accurately, which are

experienced in real practice.

Figure 28: Distributed Line Model [13]

36

Figure 29 shows the definition of each parameter for umbilical and Figure 30 shows the

properties box where parameters can be set. Figure 31 is the graphical model of umbilical.

Figure 29: Umbilical's parameter definition [20]

Figure 30: Umbilical’s parameters [20]

Figure 31: Umbilical model [20]

37

3.5.4 Subsea Control Module Model

SCM is modelled with one 2 positions, 3 ways directional control valve. The opening and

closing of the DCV is controlled by signal that have been set. During open position, the

pressure from the HPU is supplied to actuator through the DCV. In close position, the

pressure supply port is closed and fluid is vented to the sea through an exhaust port. A

check valve has been included to make sure one way flow from the actuators to the sea.

Figure 32: SCM schematic diagram

The SCM modelled includes a check valve, vent to sea, two DCVs and a bladder

compensator as illustrated in Figure 33.

Figure 33: SCM modelled in SimulationX

Check valve

38

The parameters of each element that builds the SCM also need to be defined similarly

with previous elements. Figure 34 shows the main specifications needed for the check

valve.

Figure 34: Main parameters for the check valve

3.5.5 Subsea Actuator Valve Model

Subsea actuator modelled in SimulationX is based on spring-return. In case of loss of

hydraulic pressures or equipment failures, the gate valve will return to initial state which

is closed position (normally closed actuator) to prevent situations become worse. The

pressure inside the open chamber must overcome the forces exerted by the spring and pre-

loaded force in order to move the piston.

Figure 35: Actuator definition and parts [20]

39

Each element that building the actuator (e.g. piston, spring, friction) can be modelled

separately but for this report, model which available in the SimulationX’s library has been

used. Figure 36 shows the model and parameters needed for actuator in SimulationX.

Figure 36: Actuator model and parameters

3.6 OVERALL MODEL

By combining all the elements included in model conceptualization, the overall simulation

configuration is shown in Figure 37. The model is developed based on the system used

for the Cadlao field. Additional components included in the simulation model are

representing the connections between each component.

40

Figure 37: Overall simulation model

Actuator

Control

Panel Umbilical

Actuator

Vent to

sea

HPU

SCM

41

3.7 MODEL VALIDATION

Validation of the simulation model build is important to ensure the model assumptions are

correct, complete and consistent. Additionally, validation is also done to prove that the

simulation model developed is acceptable and can be used to represent the actual system,

and will able to behave similarly to the real system. To validate the model, the simulation

model used variables from Cadlao field as recorded in Table 6, 7, and 8. Additional

variables are taken from the default values available in the SimulationX. The reason why

default values are used because SimulationX’s specialization is in subsea modelling.

Therefore all the default values in the SimulationX are the typical dimensions for subsea

applications. Another reasons is, due to time constrain. Specification sheets from online

source does not provide enough parameters and mostly only provide the working pressures

and maximum working pressures. To get full specifications, request have to be made to

the manufacturers which will need more time. The parameters used are as in the following

tables:

Table 6: HPU configurations

Pumps

Duty pump flow-rate 10 litres/min

Standby pump flow-rate 10 litres/min

Accumulator

Volume 250 litres

External gas volume 250 litres

Pressure regulator

Set pressure 3500 psi

Return line check valve

Cracking pressure 2 bar

Full opening pressure 3 bar

Table 7: Umbilical configurations

Geometry

Inner diameter 0.15 in 0.35 in 0.50 in

Length from sea surface to sea bed 6000 ft 12000 ft 18000 ft

Bulk modulus 700 Mpa

42

Table 8: Actuator configurations

Design data

Shape of piston area Ring shaped

Piston diameter 4 inch

Stroke length 203 mm

Piston mass 50 kg

Spring definition and pressures

Spring force preload 30 kN

Spring force compressed 45 kN

As the hydraulic fluid used in the Cadlao field’s system, Cameron 590, is not available in

SimulationX, Castrol Transaqua HT has been selected as hydraulic fluid the simulation

model as the properties of Castrol Transaqua HT are similar to the Cameron 590 which is

used in the Cadlao field. The properties of the fluid are shown in Figure 38.

Figure 38: Fluid properties [24]

Additional data for umbilical are needed as the data presented in the SPE 12001 are

insufficient for simulation. Specification sheets from manufacturer’s sites are acquired to

find an umbilical with the same or similar properties to the umbilical used in Cadlao field.

When selecting the most suitable umbilical, several factors have been put into

consideration such as fluid compatibleness, temperature rating, and pressure rating. In the

end, umbilical type 2040H has been selected as it poses similar properties to the umbilical

used in Cadlao field.

43

Figure 39: Umbilical parameters [25]

44

CHAPTER 4

RESULT AND DISCUSSION

This chapter presents the simulation results obtained. Firstly, the system is verified by

simulating the simulation model using parameters from the Cadlao oil field to show

whether the model behave accordingly or not. Performance curves of Cadlao field are then

compared to the acquired curves from simulation.

After the model have been validated, simulation model is simulated using different

operating conditions. Due to time constrain in developing simulation model, only

parameters of the umbilical and actuator are changed for this project simulation.

Additional simulation test on the effect of umbilical’s bulk modulus also included. The

aims for simulation testing are to study the effect of changing these parameters on the

system performance. The simulation system is simulated using three conditions as the

following:

1. Varying umbilical length

2. Varying umbilical inner diameter

3. Varying valve piston actuator size

An Emergency Shut Down (ESD) simulation done to show how quick the system can

recover to its initial safe position after the hydraulic supply from the topside is terminated.

This feature is included in control system because it is considered critical in determining

the reliability and boost confidence in the control system. ESD also a requirement for

SPCS.

45

The results obtained are compared to case study’s results showed similar behaviours and

getting an exact results are not possible mainly due to lack of data. Only critical data such

as working pressures and hose lengths are presented in the reference paper. At the same

time, when developing simulation model, many other parameters are still need to be set.

Therefore, assumptions made by author influence the acquired results.

4.1 SYSTEM BEHAVIOUR

4.1.1 Gate Valve

Before proceed to the simulation testing using different parameters, validation has to be

done first. For the validation purpose, developed simulation model is simulated using

default values which are used in Cadlao field. The results acquired from simulation are

then compared to the results of Cadlao field. Figure 40 below are simulated using 3500

psi (241.3 bar) regulated pressure, 6000 ft. long hose, ½ inch diameter hose and 4 inches

actuator’s piston diameter.

Figure 40: Gate valve behaviour during opening and closing

From the graph, we can see that the actuator start to shift at t = 22 s at a minimum

differential pressures of approximately 130 bar, and fully extended at t = 35 s. Therefore,

46

shift time is 13 s. The Cadlao field’s shift time recorded was 25 s, a disparity of 12 s are

observed. The difference is due to the insufficient data provided for the case study

especially for actuator. Assumpations and calculations have been made to predict the

appropriate values for the missing dimensions. The system seem to experience

disturbances during pressure build up but the system has completely actuating the gate

valve.

Pressure variation will be experienced during operation and if the variation is too high,

opened valves might start to close and consequently, unwanted shut down might happen.

To study the pressure drop in the system, the SCMs in the developed simulation model is

set to move to open position at different time. First, gate valve #1 is actuated and at t = 50

s, the SCM #2 moved to open position allowing hydraulic fluid pass through and actuates

the actuator #2. Observation on the pressure variation experienced in the system during

actuation of actuator #2 is made and analysed to study the pressure drop during actuation

of actuator #2.

Figure 41: Pressure drop when operating second actuator

From Figure 41, we can notice that gate valve #2 operation at t = 50 s caused a pressure

drop of approximately 610 psi (42 bar). As DCV #2 opened, fluid that was compressed in

actuator #1 moved to fill up empty space in actuator #2. As a result, pressure drop is

47

experienced in the system. If the pressure drop is too great, the opened actuator #1 might

start to close, but for this system, pressure did not fall below the reset pressure of DCV

#1. In real practices, operator usually used subsea accumulator or increase the hose size

to reduce the effect of pressure drop but consequently, the time needed for umbilical

pressurization and bleed it when shutting down will be affected.

4.1.2 Umbilical

This test is conducted to assess the time needed for the umbilical to stabilize after the

surface HPU energized and supplies the fluid power to the subsea umbilical. The graph

acquired by closing the two DCVs located at the end of the umbilical on the sea bed.

Figure 42 illustrates the performance of a 6000 foot long and ½ inch diameter umbilical

with a regulated pressure at 3500 psi (241.3 bar).

Figure 42: Umbilical hose pressurization

From the graph (Figure 42), we can observe that the umbilical requires approximately 47

seconds to reach steady state at 3571 psi (246.2 bar), which is slightly higher than the

regulated pressure due to water depth of Cadlao field (20 m). The value is important

especially when there are plans to expand the system afterward.

48

4.2 SIGNAL TIME

4.2.1 Umbilical’s Bulk Modulus Effect

Bulk modulus of the umbilical also play an important role in the umbilical pressurization

because it is a measure of the umbilical’s resistance to the uniform compression. It affects

the umbilical pressurization and bleed time. Most importantly, response time of gate

valves will varies depending on the bulk modulus. Figure 43 shows the time needed for

the pressurization of an umbilical at different values of bulk modulus.

Figure 43: Umbilical pressurization time for different bulk modulus

From the graph, we can observed that 700 MPa bulk modulus yield the quickest

pressurization which is approximately 47 seconds, followed by 500 MPa and the longest

pressurization experienced by hose line with 300 MPa of bulk modulus. Hence, the lower

the modulus, the more volume the umbilical can occupy, and longer time needed for

pressurization. In some cases, high expansion hydraulic hoses can act as accumulators to

reduce fluctuation in line and also used for actuating large actuator valve. The time taken

for each bulk modulus is recorded in Table 9.

0.5 inch diameter

3500 psi regulated pressure

49

Table 9: Effect of varying bulk modulus of hose pressurization

Bulk Modulus (MPa) Time (seconds)

700 47

500 63

300 100

4.2.2 Umbilical’s Length Effect

Simulation done on umbilical at different lengths to study the effect of varying the lengths

of an umbilical line to the pressurization time. The results are shown in Figure 44. As the

fluid compressed in the umbilical hose, longer hose needs more fluid to fill up the spaces

in the umbilical line. As a result, time needed for fluid to travel to the end of the umbilical

increased as the length increased. Therefore, longer pressurization period is experienced.

Figure 44: umbilical pressurization at different length

Time taken for each length is recorded in Table 10 below.

Table 10 : Effect of varying umbilical length to pressurization time

Length (foot) Time (seconds)

6000 47

12000 110

18000 195

47 s

50

4.2.3 Umbilical’s Inner Diameter Effect

For this simulation, the effect of an umbilical’s inner diameter is studied. As the inner

diameter of an umbilical increased, more fluid is needed to fill up the umbilical before the

pressurization can start. As a result, longer time is required to pressurize larger umbilical.

In other word, the time for the pressure to build up to the level necessary for actuator to

start to shift will also increase. The effect of umbilical’s inner diameter to the signal time

can be seen through Figure 45.

Figure 45: Umbilical pressurization at different diameter

From the graphs, 0.35 inch hose diameter yield the quickest signal time followed by 0.5

inch hose diameter, then 0.15 inch hose diameter, and lastly umbilical hose with 0.10 inch

of diameter as can be seen in the Table 11.

Table 11: Effect of varying umbilical diameter on pressurization

Diameter (inch) Time (seconds)

0.15 111

0.35 39

0.50 47

Smaller size (0.15 in) will experience high pressure loss. By Darcy-Weisbach equation,

the umbilical diameter is inversely proportional to the friction loss [26]. The velocity also

51

higher in 0.15 inch compared to 0.35 inch and 0.50 inch umbilical. Higher velocity will

caused higher friction as stated by the Darcy-Weisbach equation. Therefore, the 0.15 inch

internal diameter umbilical requires the longest time to be fully pressurized. Comparing

0.35 inch with the 0.50 inch hose, as both simulation used the same flow rate, the time

taken to fill up larger hose will increase. Therefore, the time required to fully pressurize

the umbilical for 0.35 inch hose is shorter.

Figure 46: Cadlao response time for umbilical at different length and diameter [21]

For validation, the performance curves of the Cadlao field are compared with the acquired

results obtained through simulations. The developed model yields similar response time

curves as the Cadlao field. For the hose length of 6000 ft ½ inch, the response time for

Cadlao field is approximately 50 seconds, while the response time from the simulation is

47 seconds, a disparity of 3 seconds. For 12000 ft length and ½ inch hose, the response

time for Cadlao is roughly around 132 seconds, while response time acquired through

simulation yielded 110 seconds, a disparity of 22 seconds. Lastly, response time for 18000

ft length and ½ inch diameter hose for Cadlao is greater than 180 seconds, while the

52

simulation yield more or less 195 seconds. From all the simulations done, a disparity of

less than 30% between the acquired results and Cadlao field’s response time. Therefore,

the simulation model is valid to represent the system used in Cadlao field.

The simulation is not exactly yield an exact result as from the Cadlao field, but the system

behave as predicted and similar to the actual system. The main reason for this is due to

the incomplete data. Therefore, assumptions are made to predict the values for the missing

variables based on calculations and from the specification sheets found online.

4.3 SHIFT TIME

Second objective for this project is to find the effect of varying parameters to the system’s

signal time and shift time. The simulations to study the effect of varying parameters to the

signal time are done in the previous section (Section 4.2). For this section, the effect of

varying the parameters to the system’s shift time is studied. The simulations are done by

using different values for these properties:

1. Umbilical length

2. Umbilical size

3. Actuator size

4.3.1 Umbilical’s Length Effect

The simulation are done using three lengths, which are 6000 ft, 12000 ft, and 18000 ft.

The results obtained are shown in Figure 48. From the results, it is observed that as the

length increased, the shift time also increased. Analytically, the reason for the pattern is

due to the fact that longer time is needed for the fluid to travel in longer umbilical. As the

velocity of fluid stays the same, hydraulic fluid will need more time to reach the end of

the umbilical located on sea bed. Pressure builds up slowly in longer length umbilical.

Therefore, time taken to build up the pressure to a level sufficient to overcome the forces

acting the stem area is increased.

53

Figure 47: Shift time for different umbilical length

Table 12: Time taken to fully open actuator valve using different hose length

Length (ft.) Time to fully open (s)

6000 13

12000 21

18000 31

4.3.2 Umbilical’s Inner Diameter Effect

This simulation done to study the effect of varying umbilical’s inner diameter to the

system’s shift time. Diameters used are 0.15 inch, 0.35 inch, and 0.50 inch. The time taken

for the piston to travel to open position is illustrated in Figure 48.

54

Figure 48: Effect of varying hose diameter

Table 13: Recorded time for piston to fully shift to the other end

Diameter (inch) Time to fully shift (s)

0.15 113

0.35 19

0.50 13

From the results, we can observed that 0.15 inch inner diameter umbilical yields the

longest time for the actuator to be fully opened. The reason for this behaviour is, only

small amount of hydraulic fluid can be transferred at a time and huge pressure losses are

experienced in a smaller umbilical’s diameter. As a conclusion, The bigger the diameter,

the shorter the shift time experienced.

4.3.3 Actuator’s Size Effect

To show the effect of varying actuator’ piston diameter on the shift time, different sizes

have been used which are 6 inches, 9 inches and 12 inches. The results are shown in Figure

49.

55

Figure 49: Effect of actuator size on shift time

Table 14: Recorded shift time for different piston diameter

Valve piston diameter (in) Time taken to fully open (s)

6 28

9 36

12 56

From the results (Table 14), the shortest time recorded is 28 seconds, simulated using 6

inches actuator’s diameter, followed by 9 inches actuator (36 seconds) and the longest

time recorded is 56 seconds when using 12 inches piston diameter. A smaller piston will

results in a smaller volume of the actuator. Therefore, the time needed to fill up the

actuator’s cylinder is shorter as compared to the bigger size actuator. Thus, we can

conclude that the bigger the size of the cylinder, the longer time required for hydraulic

fluid to fill up the actuator’s cylinder.

4.4 EMERGENCY SHUT DOWN (ESD)

Lastly, simulation on emergency shut-down is done to demonstrate how the system

behaves during accidents or hardware failures. For this simulation, the header valve

located on the surface facility is closed during operation resulting in termination of the

56

hydraulic supply. During the simulation of the emergency shut-down, hydraulic fluid

supplied by the HPU is vented back to the tank. This simulation done to predict the time

needed for the actuator valve to return to its fail safe position, and block the flow of

hydrocarbon in the wellhead, in order to prevent any further dangerous occurrences or

further lost. The graph below (Figure 50) shows the actuator’s behaviours during

emergency situation.

Figure 50: Gate valve time to return to safe state

For this system, gate valve take too long to return to its initial state. This is due to the

insufficient spring force on the actuator which cannot overcome forces exerted by the

hydraulic fluid in the umbilical hose. This unforeseen event could have led to disaster if

the system were to put into operation before simulation is thoroughly done.

To solve the problem, spring force and preload force are altered. The new values was then

simulated to confirm the gate valve position. After few trial and errors, the graphs plotted

shows that the valve fully returned to its safe position in 37 seconds. This value can still

be reduced by increasing the spring force and preload force, but higher spring force means

that higher force is required to open the actuator valve during production. Hence,

Hydraulic supply cut-off @ t=65s

57

increased in the opening time of gate valve will be experienced. Regardless of that, the

ESD was successfully simulated and gate valve was fully closed in 33 seconds.

Figure 51: correction on spring force and preload force on spring

58

CHAPTER 5

CONCLUSION AND RECOMENDATION

5.1 CONCLUSION

As the conclusion, simulation offers great help in analysing the subsea production control

system. All the components in a system can be tested in various ways to analyse their

integrities and behaviours. The influence of a component to the overall system’s

performance can be studied and appropriate actions can be taken to improve the system.

This is important for newly designed system. Before putting the system into operation, the

system can be virtually tested first to increase confidence or to understand the operation

of the system.

For this project, the first objective is successfully achieved as illustrated in Figure 37

which is to develop a simulation model for a direct hydraulic control system. Several

guidelines and steps have been strictly followed in order to design a model for the direct

hydraulic control system. Simulation model is build based on the model used in the case

study for this project, which is Cadlao field. While studying the case study, literature

review is done on the direct control system and various components in the system are

identified. After the critical components are recognized, further study done to understand

the concepts and functions of each component. At the same time, the conceptualized

components are translated to acceptable form in the simulation software. During this stage,

simulation model developed are constantly tested and simulated to verify whether the

developed model can be simulated properly or not. During this stage, the configurations

of the system are frequently changed. After the developed model is verified and all main

components that build a direct hydraulic control system are included, real field data are

59

used to simulate the developed system and validation is done during this stage. After

validation is completed and the developed model is proved to behave similar to the real

system in Cadlao field, simulations are continued to study the effect of varying parameters

to the shift time and signal time, which is the second objective for this project work.

To achieve second objective for this project work, the developed model is simulated using

different values for three main parameters in the system, which are the umbilical length,

umbilical inner diameter, and actuator size. The simulation are successfully done and the

effect of varying the parameters are analysed and discussed in the previous chapter, which

is Chapter 4. The conclusions made about the effect of the varying parameters to the

system’s signal time and shift time are as the following:

1. Pressure drop is experienced when operating neighbouring actuators. Therefore, a

thorough consideration is needed when designing the operation of the system.

2. Delay is experienced when a function is initiated at the topside and executed at the

seabed. Careful contemplations for the system’s design will help in reducing the

effect of the delay.

3. Subsea production control system’s signal time is directly proportional to the

umbilical length, and is inversely proportional to umbilical inner diameter.

4. Subsea production control system’s shift time is directly proportional to umbilical

length and inner diameter, but inversely proportional to the actuator size

(diameter).

Lastly, the third objective is also successfully accomplished which is to demonstrate the

emergency shut down (ESD) feature which is a requirement for subsea control system.

The ESD simulation showed that the personnel on the topside facility are exposed to risk

within the 33 seconds recorded in Figure 51. Quicker fail safe time is preferred for the

subsea system in order to reduce or eliminate the risk but the period is still acceptable as

the requirement for ESD for work over control system is less than 60s [27]. If this

developed model is used in real field, there should be a plan and set of actions to be done

during the emergency shut down. The time for the actuator to return to its fail safe position

should be used to plan appropriate actions that can be done during emergency. The steps

60

or actions taken will decide the life of the personnel on the surface platform. Hopefully,

the tragedy of Piper Alpha which caused 167 personnel died will not happened again as

proper actions planned to make sure everything is in control during the 33 s.

5.2 RECOMMENDATION

Simulation model developed showed similar behaviour to system in Cadlao field.

Regardless of that, there are few things that, in my opinion, can be done to improve the

outcomes of this project. My recommendations are as follows:

1. SimulationX should include recommendation on how to solve an error during

simulation. This will help beginners such as myself to troubleshoot error quicker.

As for now, only the cause of error is shown, and length calculation or

consideration have to be made to find the problematic parameter or component.

2. Other factors should be investigated rather than umbilical size and length, and

actuator size as it is already done in this project. Other parameters can be used for

future works such as bulk modulus and water depth.

3. Future works should model and simulate newer control system such as multiplexed

control system so that alternative solution can be suggested to improvise current

limitations in the system.

4. As all the operators are aiming for low cost and reliable system, all-electric subsea

systems are introduced. Future works may include studying the all-electric subsea

control system which seem to have huge potentials and can be further improved.

61

REFERENCES

[1] J. Westwood, "Go Bookee," [Online]. Available: http://www.gobookee.net/.

[Accessed 15 October 2013].

[2] L. Kelleher, "Report on SUT London Evening Meeting," Society for Underwater

technology, London, 2013.

[3] NORSOK Standardisation Work Group, "Design Requirement: Subsea Production

Control Systems," Norsok Standard, January 1995.

[4] T. Pipe, "Subsea Hydraulic Power Generation and Distribution for Subsea Control

Systems," in European Petroleum Conference, London, October 1982.

[5] Technical Committee ISO/TC 67, "Specification for Subsea Production Control

System - API 17F," API Publishing Services, Washington, 2003.

[6] J. S. Stecki, "Production Control Systems - An Introduction," Monash University,

2003.

[7] Y. Bai and Q. Bai, Subsea Engineering Handbook, USA: Gulf Professional

Publishing, 2010.

[8] FMC Technologies, "FMC Technologies," FMC Technologies, [Online].

Available:

http://www.fmctechnologies.com/SubseaSystems/Technologies/SubseaProduction

Systems/ControlSystems/Topsides/TUTA.aspx. [Accessed 2013 December 15].

[9] K. William C.Parks and H. J.Douglas Smith, "Subsea Control Module". United

States of America Patent 6,161,618, 9 December 2000.

[10] Advanced Technology Department, Deepwater Reference Book, 2000, p. 86.

[11] H. Devold, Oil and Gas Production Handbook: An Introduction to Oil and Gas

Production, Oslo: ABB, 2010.

[12] A. Husby and R. Morgan, Subsea - Building Blocks, Det Norske Veritas AS, 2011.

[13] R. Lien, "News/articles," [Online]. Available: http://www.agito.no. [Accessed 14 6

2012].

62

[14] S. A. M. Rusok, "Requesting Details For Icon Control System," 16 July 2013.

[Online]. Available: [email protected].

[15] T. Stavenes, "Subsea Hydraulic Leakage Detection and Diagnosis," Norwegian

University of Science and Technology, Trondheim, 2010.

[16] b. T. Tanju, H. An and Karamchandani, "Subsea Control System Diagnosis". US

Patent 7,895,001 B2, 23 December 2008.

[17] M. Theobald, "Autonomous Control System (SPARCS) For Low Cost Subsea

Production Systems," in Advances in Underwater Technology, Ocean Science and

Offshore Engineering, Netherlands, Kluwer Academic Publishers, 1993, pp. 125-

148.

[18] M. Theobald, "Benefits of All-Electric Subsea Production Control Systems," in

Offshore Technology Conference, Texas, 2005.

[19] Offshore Technology.com, "K5F Gas Field, Netherlands," [Online]. Available:

http://www.offshore-technology.com/projects/k5f/. [Accessed 20 December 2013].

[20] K. Brenan, User Manual SimulationX, Dresden: ITI GmbH, 2011.

[21] W. Manuel, "Response Time Testing for Subsea Control in the Cadlao Field," in

Annual Technical Conference and Exhibition, San Francisco, 1983.

[22] Raisama Energy Limited, "energy-pedia news," 2 July 2012. [Online]. Available:

http://www.energy-pedia.com/news/philippines/new-150903. [Accessed 12

Disember 2013].

[23] Blade Petroleum Limited, "Blade Petroleum," Blade Petroleum Limited. [Online].

[24] RE Trading AS, "Subsea Fluids," [Online]. Available:

http://www.ertrading.no/subsea-fluids. [Accessed 12 Disember 2013].

[25] Fluid Control, "Fluid Control AS," [Online]. Available:

http://www.fluidcontrol.no/fluid-control. [Accessed 2 December 2013].

[26] C. A. Chung, Simulation Modeling Handbook: A Practical Approach, United States

of America: CRC Press, 2004.

[27] NORSOK Standardisation Work Group, "Design Requirements : Subsea

Production Systems," 1995.

63

[28] A. Akers, M. Grassman and R. Smith, Hydraulic Power System Analysis, US:

Taylor & Francis Group, 2006.

[29] FMC Technologies, "Subsea Control Systems," FMC Technologies.

[30] W. Bolton, Mechatronics: A Multidisciplinary Approach, Great Britain: Pearson

Education Limited, 2008.

[31] J. R. Daines, Fluid Power: Hydraulics and Pneumatics, Illinois: G-W Publisher,

2009.

[32] A. Maria, "Introduction To Modeling And Simulation," in Simulation Conference,

Binghamton, 1997.

[33] W. D. K. Averill M. Law, Simulation Modeling and Analysis, United States of

America: McGraw-Hill Companies, Inc, 2000.

[34] O. K. Aziz, "Subsea Production Systems Control Modelling," Tronoh, 2013.

64

APPENDICES

Appendix I: Typical subsea production system (Courtesy of FMC)

65

Appendix II: FYP I Gantt Chart

66

Appendix III: FYP II Gantt Chart

67