PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 1 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
I. FUNCTION OF THE DEPARTMENT
The Technical Services Department (TSD) is in charge of the formulation and
recommendation of policies, systems and techniques for the effective implementation of
developmental projects and the repair, rehabilitation and improvement of existing
facilities and utilities; preparation of preliminary appraisal and feasibility studies of
project proposals to determine infrastructure projects proposed for implementation;
preparation, review and validation of engineering, architectural and technical plans for
proposed infrastructure projects; supervision, monitoring and evaluation of the
construction/rehabilitation, repair activities undertaken by private contractors or by
administration on duly approved projects; provision of technical assistance to operating
units on matters involving technical plan preparation and related concerns; and
preparation of the annual work plans in coordination with other units for inclusion of
same in the over-all expenditure program of the Agency.
II. DEFINITION OF TERMS AND ABBREBIATIONS
A. DEFINITION OF TERMS
The following terms and definition shall apply in this manual:
1. Construction Supervision = is the process of ensuring that the project is built in
accordance with the requirements of the contract documents, approved plans,
specifications, building codes, building code standards and applicable local codes
and ordinances.
2. Preliminary Project Evaluation = an initial step wherein moderate to
large projects are evaluated before development applications are filed.
3. Infrastructure Assessment Study = a process/method which involves the
evaluation or estimation of a basic physical and organizational structures and
facilities (e.g., buildings, roads, and power supplies) needed for the operation of
enterprise.
4. Field Survey = a research activity undertaken at the specific project location
where survey methodologies and techniques are applied in the a) collection of
primary and secondary data using questionnaires, b) gathering hydrographic and
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 2 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
topographic data using engineering equipment, and c) conduct of observations
on the actual unloading and trading activities of fishermen and fish traders.
5. Project Identification = is the process of identifying the potential site for the
establishment of fishery post-harvest facilities: such as fish port, ice plant, cold
storage.
6. Pre-Feasibility Study = is the initial design stage of a project which establishes the
fishery resource situation in the project area, the functional design, project site
selection, architectural and physical layout of specific projects, preliminary design
and cost estimates, and the economic, financial and environmental impact
analyses required for project evaluation.
7. Regional Fish Port Complex = is a port compound equipped with facilities such as
breakwater, landing quay, market hall, refrigeration facilities such as ice plants
and cold storages, processing facilities, slipway or dry-docking facilities, fishing
gear mending area, and related facilities devoted for the landing and
distribution/marketing of fish and fishery products.
8. Municipal Fish Port = refers to smaller fish ports equipped with basic fish
landing and trading facilities catering to sustenance fishermen
9. Preliminary Engineering Design = one of the stages of project development where
basic analysis and design planning are translated into specific conceptual
engineering plans, specifications and budgetary cost estimates of a project.
10. Budgetary Cost Estimate = is a detailed approximation of the preliminary/initial
engineering design of the project and is used to source funds for the
construction/implementation of the proposed project.
11. Detailed Engineering Design/Study = is the phase where the approved concept
design is refined, and plans, specifications, and estimates are created. It describes
all the main component of the projects, their dimensions, sections, and elevations.
The output also include 2D and 3D models, P & ID's, cost build up estimates,
procurement plans, operational flows etc.
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 3 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
12. Detailed Project Cost Estimate = is the process of determining the total cost of the
project by analysing the type and quantity of construction materials, price of the
materials required by the scope of the project, labor requirement for all the items
of work and their costs which is then used to compare with the bids to compete
for a contract award.
13. Program of Work = refers to the reference point of the contract for how work will
be carried out in a certain way and by certain dates.
14. Specifications of Materials = refers to a set of documented requirements to be
satisfied by materials, design, product, or service.
15. Tender Documents = refers to the documents issued by the agency as the basis for
bids, furnishing all information necessary for a prospective bidder to prepare a
bid for the Goods, Infrastructure Projects and/or Consulting Services required by
the agency
16. Approved Budget for the Contract = refers to the budget for the contract duly
approved by the HoPE, as provided for in the General Appropriations Act,
continuing, and automatic appropriations, in the case of national government
agencies ; the corporate budget for the contract approved by the Board of
Directors, pursuant to Executive Order (E.O). No. 518, s. 1979, in the case of
GOCCs1.
17. Developmental Projects = refers the construction, improvement, rehabilitation,
demolition, repair, restoration or maintenance of municipal fish ports, ice plant
and cold storages and other related construction projects of the agency.
18. Variation Orders = refers to the increase/decrease in quantities, including
introduction of new items that are not included in the original contract or
reclassification of work items that are either due to change of plans, design or
alignment to suit the actual filed conditions resulting in disparity between the
preconstruction plans used for purposes of bidding and the "as staked plans" or
construction drawings prepared after a joint survey by the contractor and the
agency after award of the contract 1.
1 The 2016 Revised Implementing Rules and Regulations of RA No. 9184
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 4 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
19. Work Suspension = refers to the temporary stoppage of work wholly or partly by
written order for such period as may be deemed necessary, due to force majeure
or any fortuitous events or for failure on the part of the contractor to correct bad
conditions which are unsafe for workers or for the general public, to carry out
valid orders given by the agency or to perform any provisions of the contract, or
due to adjustment of plans to suit field conditions as found necessary during
construction 1.
20. Contract Time Extension = refers to the phase where the completion date of the
has not been met maybe due to additional work, or occurrence of other special
circumstances and/or major calamities such as exceptionally destructive
typhoons, floods and earthquakes, and epidemics, and for causes such as non-
delivery on time of materials, working drawings, non-acquisition of permit to
enter private properties within the right-of- way resulting in complete
paralyzation of construction activities, general labor strikes, and peace and order
problems, and other meritorious causes as determined/certified by the concerned
Government units and approved by the procuring entity.
21. Environmental Compliance Certificate = refers to the document issued by the
Department of Environment and Natural Resources - Environmental Management
Bureau that allows the project to proceed to the next stage of project planning,
which is the acquisition of approvals from other government agencies and LGU’s,
after which the project can start implementation.
22. Certificate of Non-Coverage = refers to the document issued by DENR stating that
the proposed project is not covered by the Philippine Environmental Impact
Assessment System, therefore, the proponent is not required to secure an ECC
prior to implementation or commencement of operation.
23. Architectural and Engineering Design = is the combined application
of architectural and engineering principles and technology to building and non-
building design and construction.
24. Documentary Requirements = are PFDA’s mandatory documents that must be
complied or submitted by the proponent before the project procurement.
25. Project Development Officer = a technical personnel responsible in or who carry
out the activities involved in the conduct of 1) project identifications, 2) Pre-
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 5 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
Feasibility Studies, and 3) other reportorial requirements, of fishery-related post-
harvest projects
26. Civil Engineer = a technical personnel who 1) Designs and estimates all
components of proposed projects; 2) Conducts engineering surveys of proposed
projects and inspects projects during its construction stage; 3) Prepares Plans,
technical specifications, accomplishment Reports, Variation Orders, Time
Extension and other documents necessary for the projects.
27. Electrical Engineer = a technical personnel who 1) Prepares Designs and
estimates of technical documents of electrical aspects of proposed projects; 2)
Inspects the construction of electrical aspects of on-going projects; Assist in the
conduct of engineering surveys of proposed projects and inspects projects during
its construction stage;
28. Mechanical Engineer = a technical personnel who 1) Prepares Designs and
estimates of technical documents of mechanical aspects of proposed projects; 2)
Inspects the construction of mechanical aspects of on-going projects; Assist in the
conduct of engineering surveys of proposed projects and inspects projects during
its construction stage;
29. Agricultural Engineer = a technical personnel who 1) Designs and estimates all
components of proposed projects; 2) Conducts engineering surveys of proposed
projects and inspects projects during its construction stage; 3) Prepares Plans,
technical specifications, accomplishment Reports, Variation Orders, Time
Extension and other documents necessary for the projects.
30. Environmental Specialist = a technical personnel who 1) responsible in securing
the required environmental clearances (from the DENR) of municipal and
regional fish port, ice plant, and cold storage projects of the agency, 2) ensures
compliance and implementation of approved Environmental Management Plan of
fish ports and other fishery-related infrastructure facilities
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 6 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
B. ABBREVIATIONS AND ACRONYMS
1. PFDA = Philippine Fisheries Development Authority
2. TSD = Technical Services Department
3. PPED = Project Planning and Engineering Division
4. CMD = Construction Management Division
5. FSD = Facilities and Services Division
6. PDO = Project Development Officer
7. CE = Civil Engineer
8. EE = Electrical Engineer
9. ME = Mechanical Engineer
10. AgEng = Agricultural Engineer
11. IAS = Infrastructure Assessment Study
12. PRE-FS = Pre-Feasibility Study
13. DE/S = Detailed Engineering Study
14. CPM = Critical Path Method
15. POW = Program of Works
16. ABC = Approved Budget for the Contract
17. LGU = Local Government Unit
18. RFPC = Regional Fish Port Complex
19. MFP = Municipal Fish Port
20. IP = Ice Plant
21. CS = Cold Storage
22. ECC = Environmental Compliance Certificate
23. CNC = Certificate of Non-coverage
24. HoPE = Head of Procuring Entity
25. GAA = General Appropriations Act
26. GOCC = Government Owned Controlled Corporation
27. VO = Variation Order
28. FSD = Finance Services Department
29. CPMISD = Corporate Planning and Management Information Systems
Department
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 7 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
30. BAC = Bids and Awards Committee
31. DBM = Department of Budget and Management
32. DENR = Department of Budget and Management
33. EMB = Environmental Management Bureau
34. DA = Department of Agriculture
35. GCG = Good Governance Commission for Government Owned and
Controlled Corporation
36. NEDA = National Economic and Development Authority
37. BFAR = Bureau of Fisheries and Aquatic Resources
III. RESPONSIBILITIES OF THE TSD
The Department is composed of three (3) Divisions namely: Project Planning and
Engineering Division, Construction Management Division, and Facilities and Services
Division.
A. PROJECT PLANNING AND ENGINEERING DIVISION (PPED)
1. Main tasks of the PPED are the following:
a. Prepares infrastructure assessment and pre-feasibility studies to determine and validate the need/demand for identified projects, as well as verify the magnitude, cost and financial/socio-economic viability of such projects
b. Reviews and prepares further studies on project proposals from government and non-government agencies and the private sector to determine compliance with duly approved guidelines for the establishment of post-harvest projects
c. Validates and undertakes the cost-benefit analysis of proposed plans, programs and activities (specifically the proposed capital investment projects) submitted by the operating units for inclusion in the Agency’s Annual and Medium-term plans
d. Coordinates with other units/agencies on the preparation of guidelines and/or
criteria for the establishment of fish ports, ice plants and cold storages, and
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 8 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
other post-harvest projects nationwide; prepares designs, plans, technical
specifications and cost estimates of the civil works, electro-mechanical works
and the sanitary and architectural aspects of the proposed developmental
projects; develops and recommends appropriate project schemes and
reviews/ verifies the technical aspects of the project proposals submitted by
the operating units and private consultancy firms;
e. Undertakes engineering field surveys and investigations including
hydrographic and topographic surveys, among others; reviews and evaluates
engineering work programs and submits periodic accomplishment reports on
all infrastructure projects.
2. Organizational Structure of PPED
Division Chief
Project Planning
Project Develoment Officer III
Project Develoment Officer II
Project Develoment Officer I
Clerk III & Utility Worker II
Engineering
Engineering Assistant
Engineer II
Engineer III
Engineer IV
Dept.
Manager
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 9 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
3. Process Flow of work
a. Project Identification
i. Project Proposals submitted by Local Government Units or endorsed by
other government agencies
(1) PDO requests submission of the accomplished TSD Survey Form Sets
A & B and other documents
(2) PDO prepares preliminary project evaluation report upon receipt of
documentary requirements
(3) PDO submits evaluation report with recommendation to Top
Management for approval
(4) PDO sends letter to the proponent and inform them of the result of the
evaluation /recommendation on the proposed project
ii. Infrastructure Assessment Study (IAS)
(1) PDO conducts Infrastructure Assessment Survey to identify potential
site and determine fishery post-harvest facilities needed in the area;
(2) PDO prepares IAS report and submits the report with
recommendation to Top Management for approval
b. Pre-Feasibility Study
i. PDO conducts Validation Survey at the City/Municipality identified to be
potential for establishment of fishery post-harvest facilities to validate the
need/demand for identified projects; identify site/location of the proposed
project, verify the types of facilities and their size/magnitude, cost and
financial/socio-economic viability of such projects
(1) Gathers secondary data from the different offices of the locality;
(2) Conducts FGD with the various industry stakeholders in the area, such
as: fish producers/commercial & municipal fishermen, fishpond and
cage operators, and fish producers associations
(3) Conducts one on one interview with stakeholders using various types
of Survey Forms/Questionnaires:
ii. CE/EE/ME/Arch. conduct Engineering Surveys – hydrographic and
topographic surveys – at the site/s identified and proposed/recommended
by the LGU for the project
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 10 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
iii. CE/EE/ME/Arch. prepares preliminary site development plan/drawings,
program of works or budgetary cost estimate, financial plan, work plan of
proposed project
iv. PDO packaged the Pre-feasibility Study report and prepares transmittal
memorandum submitting the report to the Top Management for approval
c. Detailed Engineering Study
i. CE/Arch. prepares architectural plan and specification of the proposed
project
(1) Site development plan which include perspective, elevation, sections,
landscaping, traffic circulation
(2) Floor plans, elevations, sections, schedule of door and windows,
finishing works of building facilities
ii. CE prepares civil and structural plan and specification of the proposed
project
(1) Site development plan which include embankment, retaining walls,
revetment, sheet pile design, pier design, causeway design, perimeter
fence details, sidewalks, curbs and gutter, concrete pavement, slabs,
quay wall, stairlanding, banca landing, access road
(2) Foundation layout: footing, footing tie beam and column details;
flooring/roof framing plan; beams, slab, parapet wall details. stair
details, CHB wall layout and details of building facilities
iii. CE/SE prepares sanitary or plumbing plan and specification of the
proposed project
(1) Site development plan which include general notes, legends, outside
fresh water supply layout, outside sewerage layout, outside storm
drainage layout, outfall layout & detail, manhole, gutter type canal,
open canal, screening tank, holding tank, , cistern, elevated water tank
details
(2) Fresh water supply layout, sewerage and downspout layout, septic
vault & catch basin details, plumbing isometric of building facilities
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 11 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
iv. EE prepares electrical plan and specification of the proposed project
(1) Site development plan which include general notes, legends, , outside
power distribution layout, street & causeway/pier lighting layout
(2) Single line/riser diagram, load schedules, lighting and power layout,
lighting fixture details of building facilities
v. ME prepares mechanical plan and specification of the proposed project
which include equipment sizing, layout and details, equipment
foundation details/plans, process flow diagram, schedule of pipes and
fittings, piping layout
vi. CE/EE/ME/Arch. prepares Program of Works – Detailed cost estimate,
CPM and Terms of Reference of proposed project
vii. CE/EE/ME/Arch. packaged Detailed Engineering Plans and POW for
submission to Top Management for Approval
viii. CE/EE/ME/Arch. endorses the duly approved Detailed Engineering Plans
and Program of Works to the Bids and Awards Committee for inclusion in
the agenda to procurement
d. Other Unit Activities
i. Developmental Projects for Funding
(1) PDO prepares long-lists of projects identified for possible inclusion in
the agency’s budget proposal for the succeeding year for submission
to Top Management for approval and prioritization
> Identifies the projects from the list of Pre-FS, IAS, Preliminary
Evaluation, endorsement of LGUs and other government agencies
(2) PDO endorses the approved short list of projects to the CPMISD and
FSD
(3) PDO accomplishes various DBM Budget forms and submit the same to
the FSD for consolidation
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 12 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
(4) PDO prepares other documents as maybe required by the DBM and
coordinates its submission to the DBM with the CPMISD and FSD
ii. Project Procurement
(1) CE/EE/ME/Arch. submits Tender Documents of projects included in
the BACs agenda to the procurement/bidding process.
(2) CE/EE/ME/Arch. attends to queries of the bidders concerning the
plans and cost estimates and other relevant issues raised during the
conduct of pre-bid conference
iii. Reportorial Requirement
(1) PDO prepares various reports required by other government agencies
such as NEDA Regional offices, BFAR-Regional offices, DBM, DA, GCG,
and other government agencies
(2) CE/EE/ME/Arch. prepares various reports pertaining to project
implementation required by other government and non-government
entities
B. CONSTRUCTION MANAGEMENT DIVISION
1. Main tasks of the CMD are the following:
a. Supervises the over-all construction of projects either by contract or by administration and ensures proper adherence to plans, specifications, work schedules and safety and health program as provided for in the contract;
b. Oversees the testing of materials and geo-technical investigation conducted by the Contractors;
c. Recommends payments of work accomplishments;
d. Assists the OSD on the turn-over of completed projects to the end-users;
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 13 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
2. Organizational Structure of CMD
3. Process Flow of work
a. Project Engineer/Inspector conducts pre-construction conference with the Project Contractor
b. Project Engineer/Inspector and Contractor conducts joint site inspection, layout and staking
c. Project Engineer/Inspector coordinates with concerned LGUs and other government agencies relevant issues on project construction
d. Project Engineer/Inspector conducts periodic project inspection and give on-site instruction to the contractor, whenever necessary
e. Project Engineer/Inspector conducts technical meeting to discuss progress of construction and observations
f. Project Engineer/Inspector evaluates and prepares Variation Order/Contract Time Extension/Work Suspension Order upon approval by the Top Management of the Contractor’s request
g. Upon receipt of Contractor’s request, Project Engineers/Inspector prepares Progress Billing
Division Chief
Engineer IV
Engineer III
Engineer II
Clerk III & Utility Worker II
Dept.
Manager
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 14 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
h. Project Engineer/Inspector conducts punch listing activity upon report of substantial work completion by the contractor
i. Project Engineer/Inspector conducts final inspection upon receipt of request by the Contractor
j. Project Engineer/Inspector prepares Certificate of Project Completion and Acceptance duly conformed by the Contractor to be signed by the Project Management and Top Management
k. Project Engineer/Inspector prepares Certificate of Turn-over to be signed by the Top Management and Acceptance to be signed by the proponent
l. Project Engineer/Inspector coordinates with the OSD, FSD, and Project Management the preparation of Journal Entry Voucher documentary requirements
C. FACILITIES AND SERVICES DIVISION (FSD)
1. Main tasks of the FSD are the following:
a. Oversees the repair/rehabilitation, improvement and major maintenance works of all regional fish port complex (RFPC) facilities (ice plants and cold storages, waste water treatment plant, waste water treatment facilities and other electro-mechanical facilities);
b. Assists the operating units in the formulation and evaluation of operating and maintenance procedures for port facilities/utilities;
c. Evaluates the operational performance of refrigeration facilities, water and wastewater treatment plants and power sub-stations at the regional fish ports;
d. Recommends measures to improve/upgrade existing facilities for efficient performance;
e. Assists the regional fish ports in addressing their environmental concerns;
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 15 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
f. Secures the necessary Environmental Compliance Certificates (ECCs) of infrastructure projects, and monitors compliance with the Environmental Management Plan (EMP) and other applicable laws in the implementation of developmental projects and operation of port facilities.
2. Organizational Structure of FSD
3. Process Flow of Work
a. Technical Assistance to RFPC and MFP/IP/CS
i. ME/EE gathers, consolidates and evaluates the technical data for the proposed project;
ii. ME/EE conducts site investigation and ocular inspection, perform testing and engineering surveys, if applicable
iii. EE prepares electrical plan and specification of the proposed project (1) Site development plan which include general notes, legends, , outside
power distribution layout, street & causeway/pier lighting layout
(2) Single line/riser diagram, load schedules, lighting and power layout,
lighting fixture details of building facilities
Division Chief
Engineer IV
Engineer III
Engineer II
Engineer I
Environment Specialist
Clerk III
Dept.
Manager
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 16 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
iv. ME prepares mechanical plan and specification of the proposed project which include equipment sizing, layout and details, equipment foundation details/plans, process flow diagram, schedule of pipes and fittings, piping layout
v. ME/EE submits recommendation to Top Management for approval
b. Review of RFPC-initiated rehabilitation/improvement Projects i. ME/EE review and evaluates technical plans on the proposed project
submitted by the RFPC management ii. ME/EE prepares evaluation report and
(1) submits endorsement/recommendation to Top Management for
approval, if the technical data are found to be acceptable, or
(2) transmit the evaluation report to the concerned RFPCs, if adjustment
in the technical plans is necessary
(3) Once revised, endorsement/recommendation will be submitted to
Top Management for approval
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 17 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
IV. FLOW CHART
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 18 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
-
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 19 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
1
PRE-FEASIBILITY STUDY PREPARATION
(Pre- FS Report)
START
Conduct of Validation and Engineering Survey A
STOP
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 20 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
-
—
-
- -
- -
- -
- -
- -
- –
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 21 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 22 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
-
-
-
-
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 23 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
Conducts joint site inspection, layout and
sta ing with the Contractor
Conducts technical meeting to discuss pro
gress of construction and observations
Prepares Certi icate of urn-over to be
signed by the op Management and Ac
ceptance to be signed by the proponent
Coordinates with the D, F D, and Project
Management the preparation of ournal
Entry oucher documentary requirements
Evaluates and prepares ariation rder/
ime E tension/ ime uspension upon
approval by the op Management of the
Contractor s request
Coordinates with concerned LGUs and oth
er govt agencies the relevant issues on
project construction
Upon receipt of Contractor s request, Pro
ject Engineers/Inspector prepares Pro
gress illing
Conducts pre-construction conference with
the Contractor
Conducts periodic project inspection and
give on-site instruction to the contractor,
whenever necessary
Conducts punch listing activity upon report
of substantial wor completion by the con
tractor
Conducts inal inspection upon receipt of
request by the Contractor
Prepares Certi icate of Project Completion
and Acceptance duly conformed by the
Contractor to be signed by the Project Man
agement and op Management
-
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 24 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 25 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 26 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
REVIEW OF RFPC-INITIATED PROJECTS
PHILIPPINE FISHERIES DEVELOPMENT AUTHORITY
PCA Annex Building, Elliptical Road, Diliman, Quezon City
Code PFDA-ISO-SOI-005
Version No. 1
STANDARD OPERATIONAL INSTRUCTIONS TECHNICAL SERVICES DEPARTMENT
Effectivity February 1, 2019
Page No. Page 27 of 27
This document is an UNCONTROLLED COPY unless stamped as CONTROLLED COPY duly signed by the QMR .
REVIEW OF RFPC-INITIATED PROJECTS