punjab irrigation agriculture investment project – new khanki

28
Social Monitoring Report Project Number: 37231-033 September 2015 PAK: Punjab Irrigation Agriculture Investment Project New Khanki Barrage Project Loan 2841 Internal Resettlement Monitoring Report Prepared by the Project Management Office (PMO) for Punjab Barrages, Irrigation Department, Punjab for the Asian Development Bank (ADB). The social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Upload: khangminh22

Post on 25-Apr-2023

0 views

Category:

Documents


0 download

TRANSCRIPT

Social Monitoring Report Project Number: 37231-033 September 2015

PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841

Internal Resettlement Monitoring Report Prepared by the Project Management Office (PMO) for Punjab Barrages, Irrigation Department, Punjab for the Asian Development Bank (ADB).

The social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

GOVERNMENT OF THE PUNJAB

IRRIGATION DEPARTMENT

New Khanki Barrage Project (NKBP)

ADB Loan No. 2841-PAK

Internal Resettlement Monitoring Report

For

Quarter July – September, 2015

PROJECT MANAGEMENT OFFICE (PMO) FOR PUNJAB BARRAGES,

IRRIGATION DEPARTMENT CANAL BANK

MUSTAFABAD, LAHORE

NKBP Internal Resettlement Monitoring Report

1 PMO For Punjab Barrages

New Khanki Barrage Project (NKBP)

Internal Resettlement Monitoring Report for the Quarter July-September, 2015

1. LAND ACQUISITION AND RESETTLEMENT PLAN (LARP)

The project is category B for i volu tary resettle e t a d category C for i dige ous people. Draft Land Acquisition and Resettlement Plan (LARP) for New Khanki Barrage was prepared and

submitted to ADB for approval. ADB cleared the draft LARP on July 07, 2012. LARP was revised/

updated and cleared by ADB in Feb 2014. Land Acquisition is in progress according to requirement

of Land Acquisition Act 1894. A total of 8.6 acres of land was required for construction of Head

Regulator and Head Reach of the new LCC. Section 4 and section 5 of Land Acquisition Act for 8.6

acres of land were notified and published in the Punjab Gazette on August 07, 2012 and January 21,

2013 respectively. In the Punjab Gazette on August 07, 2012 and January 21, 2013 respectively. Land

price was assessed, and the EA released the total amount Rs. 9.925 million to the Revenue

Department, Government of the Punjab.

However, due to change in engineering design it was found that only 4.58 acres out of 8.6 acres of

land was required along with a new piece of land 1 acre, 6 kanal, 3 marlas, and 4.5 Sarsai. Due to

this change, process of land acquisition was re-initiated. The section 4 & 5 of land Acquisition Act

1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July

29, 2015 respectively.

Again due to change in engineering design of LCC Lead Channel, the procedure for acquiring 5 kanal,

10 Marla of private land from one landowner (Mr. Farooq Akbar Cheema) is still in process.

Compensation rates have been re-calculated to reflect current values and procedures. The

landowner has received partial payment for crop losses and structures. Compensation payment for

the trees and remaining structures is expected to be completed by December 2015.

The five affected families which are residing at the Dera of land owner remained on same site but

their new accommodation is being built by the landowner on his remaining land. Their livelihoods

remain unaffected. These households have received their relocation allowance (Pak Rupees

5,000/household) and cash assistance for vulnerable households (Pak Rupees72, 000/-household).

Alternative accommodation for the 15 no. of the affected families of Irrigation staff is also being

constructed. Funds for the remaining compensation activities are available. All compensation

payments (structure and 6.625 acres land) and relocation of the affected households will be

completed by June 2016.

LARP implementation activities for Tranche-2 relates to LCC Lead Channel (component) of New

Khanki Barrage Project. Internal Resettlement Monitoring of all relevant activities is the

responsibility of PMO (Environment and Social Unit (ESU). Internal Monitoring Reports in the shape

NKBP Internal Resettlement Monitoring Report

2 PMO For Punjab Barrages

of QPR are being regularly submitted to the Bank. The PMO is in the process of engaging an

independent resettlement monitor (IM) to cover all tranches of the MFF. The IM will be mobilized

by December 2015 and is expected to submit its first external resettlement monitoring report by

January 2016

Tranche-2 also has an operational Grievance Redressal Mechanism that covers all types of

grievances of NKBP, including resettlement. Complaint register is also being maintained by the

Consultants to record community concerns and their solutions. Out of 27 complaints, 15 complaints

have been resolved while 12 complaints are yet to be resolved. The detail of complaints is given in

Annex-A. ESU / PMO for Punjab Barrages in busy in Implementation of LARP since 2012.

The Implementation Schedule of LARP is given below:

Sr.

No.

Action Time Line Responsibility To date Status

1 Establishment of PMO - PID PMO is already in place at

Lahore.

2 Setting-up the ESU. In place

PMO ESU is already in place.

3 Setting-up the LIU at Khanki 30 June, 2012

PMO Notified

4 Establish Grievance Redress Cell. 30 Sep, 2012 PMO Notified.

5 Submission of draft LARP to ADB 30 June, 2012 PMO Submitted

6 Approval of LARP 15 June, 2012 ADB Cleared

7 Urdu translation and disclosure of

LARP

05 July, 2012 PD/ ESU Also paste at website

8 Formation of DPs Consultation

Committees (2 Nos.)

30 Jun 2012 LIU Formed and notified.

9 Deployment of Supervisory

Consultants

30 Sep. 2012 PMO Deployed

10 Deployment of Social & Environment 31 Dec 2012 PMO Deployed

11 Employment to DPs/ locals (age of

economic group)

June 2013 to

March 2017

Contractor/

Consultants/PMO

A list of willing and

potential DPs/ locals is

included in LARP. Also

NKBP Internal Resettlement Monitoring Report

3 PMO For Punjab Barrages

given to DESCON

(Contractor) for action.

12 IMR submission before handing over

Barrage site for construction

31 Oct, 2012 PMO Done

13 NTP for Barrage - ADB Done

14 Construction of Link LCC 30 Jun. 2016 Contractor/ PMO To be completed upto 30

Jun, 2016.

Land Acquisition

15 Section-4 Notification Dec. 2015 LAC Due to new / revised

drawing of LCC in

September 2015

16 Section-5 Notification January-2016 LAC --

17 Land Acquisition Process through

Private Negotiation

-- -- Not Applicable

18 LARP Updation Oct. 2015 Consultant Discussed with ADB

representatives on

October 07, 2015.

19 Payment to DPs (Partial Payment) July 2015 Land owner/ PMO 50% payment has

released to land owner,

while remaining 50% will

be paid after relocation

of his agricultural wage

labourers at alternate

location at nearby place.

20 Relocation of Farming labourers Dec., 2015 Land owner/Agri.

Labourers PMO

-

21 Final payment to land owner after

confirmation by IM that labourers

have been relocated and paid as in

LARP.

May 2016 PMO -

22 Possession/ Transfer of Land May 2016 LAC/ PMO -

23 Relocation/ Construction of Staff

Colony

Dec. 2015 PMO -

24 Relocation/ shifting of PID staff Dec. 2015 Residents/ PMO -

25 Construction of Community Lined

Watercourses

30 Jun 2016 Contractor/ PMO -

NKBP Internal Resettlement Monitoring Report

4 PMO For Punjab Barrages

26 Construction of Lined Public

Watercourse

30 Jun 2016 Contractor/ PMO -

27 Construction of High Level Channel 30 June 2016 Contractor/ PMO -

28 Date of contract award (expected) 30 Sept.,

2012

PMO -

29 Full Implementation of LARP Dec. 2016 PMO -

30 IMR confirming LARP implementation Dec. 2016 IM Specialist/

PMO

-

31 Commencement of civil works Subject to

ADB approval

for NTP.

ADB Subject to ADB approval

on the satisfactory

implementation of LARP.

32 Redress of Community Complaints Continuous

activity

GRC/ PMO Ongoing activity till

project completion.

Total amount under LARP is Rs. 18.05 Million. Out of which, Rs. 9.925 Million has already been paid

to the Revenue Department for land Acquisition. Rupees 2.864 million have been paid to the six no.

of affected families as compensation amount for their structures. The detail is given in Annex-B

2. ADJUSTMENT MADE IN THE COMPENSATION RATE DURING UPDATING OF LARP

The LARP of New Khanki Barrage was approved in 2012. Again, it was updated and approved in

2014. The adjustment was made in compensation rates of the land after certification by the Revenue

Department, Government of Punjab.

The rates are still applicable up till now. The adjustment made in the compensation is given

at Annex-C.

3. EMPLOYMENT FOR THE AFFECTED HOUSEHOLDS IN PROJECT RELATED JOBS

Two types of affected families are residing at LCC Lead Channel. First are Irrigation Department

Employees and they are already serving in Irrigation Department. Second are the land owner and his

agriculture laborers, those are cultivating crops. They also remained busy in construction of houses

for shifting in newly built houses. The Contractor is ready to accommodate the affected families for

jobs as and when they demand. ESU, PMO Punjab Barrages requested to the Consultants to ask

the Contractor to provide jobs under the project. As per recommendation of the Engineer, the

Contractor trace each of the person included in the list, the list of the potential persons of affected

NKBP Internal Resettlement Monitoring Report

5 PMO For Punjab Barrages

families requiring jobs under the project. The Contractor offered them an appropriate employment.

Out of 16 affected persons, only 3 residents of Irrigation Colony were willing for jobs with the

Contractor and the Contractor hired their services. The status of employment of affected families is

given in Annex-D. The Contractor also offered jobs to the family members of employees of Irrigation

Department of Khanki Division. Out of 26 applications, 20 family members of Irrigation staff were

offered jobs and the Contractor hired their services under the Project. The detail is given in Annex-E

Regarding employment to the unskilled labor of the local area, the status of skilled and un-skilled

labor employment for the month of July, August and September 2015 is given in Annex-F, G and H

which is 64%, 60% and 58 % respectively for the unskilled labor for the project area.

4. RELOCATION OF AFFECTED HOUSEHOLDS AND THEIR CURRENT LIVING

CONDITION

Total Twenty One (21) affected families (AFs) are to be dislocated from LCC Lead Channel

component of New Khanki Barrage Project. In first phase, land owner and his five (05) Agri-laborers

are to be relocated and an amount of Pak Rupees 2.864 million has been paid to the six (06) no. of

affected families as the compensation amount for their structure and other assets. Fifteen (15) no. of

affected families are the Irrigation Department Employees. Construction of new residences for these

families is in progress and after completion / handing over to Irrigation Department, they will be

shifted accordingly. Status of current living condition of all affected household is as under:

Case No.1

Mr. Farooq Akbar Cheema is only the land owner fall in category of affected families. His land, trees

and residential structures etc. were affected due to construction of LCC Lead Channel under NKBP.

A compensation payment of amounting to Pak Rs. 1,570,362 was paid for crops, tube well borehole,

hand pump and structures. His current status of land and structure after dismantling can be viewed

as under:

NKBP Internal Resettlement Monitoring Report

6 PMO For Punjab Barrages

Mr. Farooq Akbar Cheema (Land owner) is standing on his land and structures after dismantling in the back

ground.

Case No.2

Mr. Muhammad Anwar is the agri-laborer of Mr. Farooq Akbar Cheema. He is residing at the Dera of

land owner and now he will be relocated to the newly constructed house by the land owner. He has

received an amount of Rs. 77,000/- as compensation / poverty allowance and relocation allowance.

His current status is as under:

Mr. Muhammad Anwar is standing in front of his house

NKBP Internal Resettlement Monitoring Report

7 PMO For Punjab Barrages

Case No.3

Mr. Amanat Ali is the agri-laborer of Mr. Farooq Akbar Cheema. He is residing at the Dera of land

owner and now he will be relocated to the newly constructed house by the land owner. He has

received an amount of Rs. 77,000/- as compensation /poverty allowance and relocation allowance.

His current status is as under:

Mr. Amanat Ali is standing in front of his existing residence

Case No.4

Mr. Manzoor Hussain is the agri-laborer of the Mr. Farooq Akbar Cheema. He built the residential

structure at the Dera of land owner. He has received amounting to Rs. 986,100/- as compensation

for his structures, one (01) No. of hand pump, poverty allowance and relocation allowance.

NKBP Internal Resettlement Monitoring Report

8 PMO For Punjab Barrages

Mr. Manzoor Hussain is standing near his dismantled house

Case No.5

Mr. Anayat Muhammad is the argi-laborer of Mr. Farooq Akbar Cheema. He was residing at the Dera

of land owner and now he will be relocated to the newly constructed house by the land owner. He

has received an amount of Rs. 77,000/- as compensation /poverty allowance and relocation

allowance. His current status is as under:

Mr. Anayat Muhammad is standing near his dismantled house

NKBP Internal Resettlement Monitoring Report

9 PMO For Punjab Barrages

Case No.6

Mr. Muhammad Ramzan is the agri-laborer of Mr. Farooq Akbar Cheema. He was residing at the

Dera of land owner and he will be relocated to the newly constructed house by the land owner. He

has received an amount of Rs. 77,000/- as compensation /poverty allowance and relocation

allowance. His current status is as under:

Mr. Muhammad Ramzan is standing near his dismantled house

Case No.7

Mr. Abdul Hameed (Guage Reader) is employee of the Irrigation Department and he is residing at

RoW of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony

Khanki and he will get Rs. 5,000/- as relocation / shifting allowance.

Case No. 7. Mr. Abdul Hameed (Guage Reader) with his family at existing residence.

NKBP Internal Resettlement Monitoring Report

10 PMO For Punjab Barrages

Case No.8

Mr. Muhammad Mansha (Beldar) is employee of the Irrigation Department and he is residing at RoW

of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony Khanki

and he will get Rs. 5,000/- as relocation / shifting allowance.

Case No.8. Mr. Muhammad Mansha (Beldar) with his family at his existing residence.

Case No.9

Mr. Ghulam Abbas (Chowkidar) is employee of the Irrigation Department and he is residing at RoW

of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony Khanki

and he will get Rs. 5,000/- as relocation / shifting allowance

Case No. 9. Mr. Ghulam Abbas (Chowkidar) with family at his existing residence.

NKBP Internal Resettlement Monitoring Report

11 PMO For Punjab Barrages

Case No.10

Mr. Faisal Mehmood (Naib Qasid) is employee of the Irrigation Department and he is residing at

RoW of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony

Khanki and he will get Rs. 5,000/- as relocation / shifting allowance.

Case No. 10. Mr. Faisal Mehmood (Naib Qasid) is standing at his existing residence.

Case No.11

Mr. Muhammad Akram (Regulation Beldar) is employee of the Irrigation Department and he is

residing at RoW of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in

Canal Colony Khanki and he will get Rs. 5,000/- as relocation / shifting allowance.

Case No. 11. Mr. Muhammad Akram (Regulation Beldar) with family at his existing residence.

NKBP Internal Resettlement Monitoring Report

12 PMO For Punjab Barrages

Case No.12

Mr. Muhammad Riaz (Boatman) is employee of the Irrigation Department and he is residing at RoW

of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony Khanki

and he will get Rs. 5,000/- as relocation / shifting allowance.

Case No. 12. Mr. Muhammad Riaz (Boatman) with family at his existing residence.

Case No.13

Mr. Liaqat Ali (Regulation Beldar) is employee of the Irrigation Department and he is residing at RoW

of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony Khanki

and he will get Rs. 5,000/- as relocation / shifting allowance.

Case No.13. Mr. Liaqat Ali (Regulation Beldar) with family at his existing residence.

NKBP Internal Resettlement Monitoring Report

13 PMO For Punjab Barrages

Case No.14

Mr. Walayat Hussain (Head Boatman) is employee of the Irrigation Department and he is residing at

RoW of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony

Khanki and he will get Rs. 5,000/- as relocation / shifting allowance.

Case No. 14. Mr. Walayat Hussain (Head Boatman) with family at his existing residence.

Case No.15

Mr. Muhammad Shabbir (Beldar) is employee of the Irrigation Department and he is residing at RoW

of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony Khanki

and he will get Rs. 5,000/- as relocation / shifting allowance.

Case No. 15. Mr. Muhammad Shabbir (Beldar) standing in front of his existing residence

NKBP Internal Resettlement Monitoring Report

14 PMO For Punjab Barrages

Case No.16

Mr. Muhammad Mushtaq (Beldar) is employee of the Irrigation Department and he is residing at

RoW of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony

Khanki and he will get Rs. 5,000/- as relocation / shifting allowance.

Case No. 16. Mr. Muhammad Mushtaq(Beldar) standing in front of his existing residence

Case No.17

Mr. Ashraf Masih (Sweeper) is employee of the Irrigation Department and he is residing at RoW of

LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony Khanki

and he will get Rs. 5,000/- as relocation / shifting allowance.

Case No. 17. Mr. Ashraf Masih(Sweeper), standing in front of his existing residence.

NKBP Internal Resettlement Monitoring Report

15 PMO For Punjab Barrages

Case No.18

Mr. Amanat Ali (Painter) is employee of the Irrigation Department and he is residing at RoW of LCC

Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony Khanki and he

will get Rs. 5,000/- as relocation / shifting allowance.

Case No. 18. Amanat Ali (Painter) standing in front of his existing residence.

Case No.19

Mr. Sibt Ul Hassan (Sub Engineer) is employee of the Irrigation Department and he is residing at

RoW of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony

Khanki and he will get Rs. 5,000/- as relocation / shifting allowance.

Case No. 19. Sibt Ul Hassan (Sub Engineer) is standing in front of his existing residence

NKBP Internal Resettlement Monitoring Report

16 PMO For Punjab Barrages

Case No.20

Mr. Rana Ayub ((Sub Engineer)) is employee of the Irrigation Department and he is residing at RoW

of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony Khanki

and he will get Rs. 5,000/- as relocation / shifting allowance.

Case No. 20. Rana Ayub (Sub Engineer)is standing in front of his existing residence

Case No.21

Mr. Muhammad Shabir (Sub Engineer) is employee of the Irrigation Department and he is residing at

RoW of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony

Khanki and he will get Rs. 5,000/- as relocation / shifting allowance.

Case No. 21. Muhammad Shabir (Sub Engineer) is standing in front of his existing residence.

NKBP Internal Resettlement Monitoring Report

17 PMO For Punjab Barrages

Status of Settlement of Complaints Annex –A

Sr# Date Complainant Location Sort of Complain Status

1 10/2/14 Imtiaz Ahmed

Lundpur

/complete

address

Demand for Culverts at

Chanawan Road Resolved

2 1/1/15 Zubair Ahmad Burj Cheema

Demand for Culverts/186+36

and 192+32 /Chanawan

Road

Resolved

3 10/1/15 Mansoor Warraich Thatthi Baloch

Demand for

Culverts134+71/Chanawan

Road

Resolved

4 5/1/14 Khizar Hayat Thatthi Baloch

Demand for

Culverts/115+70Chanawan

Road

Resolved

5 10/12/14 Naseem Hussain Thatthi Baloch

Demand for

Culverts/84+93/Chanawan

Road

Resolved

6 15/12/14 Master Shafqat Ali Faqiranwali

Demand for

Culverts/56+37/Chanawana

Road

Resolved

7 14/10/14 Farooq Akbar

Cheema LCC

Increase the rate of land

/LCC In Process

8 26/12/14 Dr. Azhar Iqbal

Cheema Kot Jaffar

Small Bridge /Gunayanwala

to Kot Jaffar Road In Process

9 1/12/14 Rana Muhammad

Khan Burj Dhalla

Demand for

Culverts/19+200/ Chanawan

Road 21+150

In Process

10 Repeated

App

Dr. Azhar Iqbal

Cheema Kot Jaffar No 8 Applicaton Repeated. Resolved

11 12/4/15 Ghulam Sarwar

Cheema Burj Cheema

Demand for

Culverts/Chanawan Road Resolved

12 21/05/15 Head Mistress

Girls School Khanki Play Ground/ Khanki In Process

13 16/5/15 Ghulam Rasool Ratowali /Jamil

Town

Cemented Ramp & Soling

/LMB Road In Process

14 21/5/15 Farooq Akbar

Cheema Kot Imam Bux

Drainage of flood

water/Chanawan Road In Process

15 14/5/15 Umer Hayat Burj Dhalla Demand for

Culverts/Chanawan Road In Process

NKBP Internal Resettlement Monitoring Report

18 PMO For Punjab Barrages

16 8/6/15 Hafiz SaifUllah

Chatta Kot Ratta

Speed Breaker/ Footpath

/Chanawan Road In Process

17 9/6/15 Muhammad

Aslam Randhawa Kor Ratta Outlet /Chanawan Road In Process

18 8/6/15 Haji Amjad Pervaiz

Randhawa Kor Ratta

Repair the old bridge

/Chanawan Road In Process

19 7/6/15 Pervaiz Iqbal

Bhatti Kot Ratta

Repair the old

bridge/Chanawan Road In Process

20 9/6/15 XEN Irrigation Khanki Boundary wall / Play

Ground/Irrigation Colony

Approved by

PMO

21 6/4/15 Master Nasir

Mahmood Kot Ratta

Change the location of

culvert/Chanawan Road Resolved

22 11/4/15 Waqas Chatta

Advocate Lundpur Court Case /Chanawan Road Resolved

23 9/7/15 SDO Headworks Khanki Breakage of High Level

Channel Resolved

24 7/7/15 Umer Hayat Burj Dhalla Hurdle on Chanawan Road In Process

25 14/7/15 Farooq Akbar

Cheema Khanki

Drainage of Rain water from

crops Resolved

26 22/7/15 Amanat Ali Khanki Standing Rain Water in

Colony Resolved

27 28/7/15 SDO Headworks Khanki Breakage of High Level

Channel Resolved

NKBP Internal Resettlement Monitoring Report

19 PMO For Punjab Barrages

Annex –B

Implementation of LARP for New Khanki Barrage as of September

2015

Contract No. 2841-PAK

Sr.

No Contract No.

Status of

Preparatio

n, vetting

and

approval of

RP

No. of

AFs

Paym

ent

Due

Total

AFs

paid

Amou

nt

Paid

%

Implement

ation

%

Amount

Paid

Remarks

1 2841-PAK

LARP for LCC

Lead Channel

Component

(under NKBP)

Draft LARP

of LCC Lead

Channel

was

prepared

and

approved in

2012. Later

on LARP

was

revised,

updated

and cleared

by ADB in

Feb, 2014

21 15.41

8

6 2.864 29% 18.57 Cost of 6.625

@ 1,200,000 is

amounting to

Rs. 7,950,000

while PMO has

deposited Rs.

9.925 (million)

to the

Revenue

Department

for payment to

the land

owner

NKBP Internal Resettlement Monitoring Report

20 PMO For Punjab Barrages

Adjustment made in Compensation Rates in LARP July, 2014

Annex - C

Sr. No. Description Unit

Unit Rate of LARP

2012

Unit Rate of updated LARP

2014 Remarks

A) Mouza -Wise Acquisition of Private Land

I) Khanki Acres 0.474 (Rs. Million)

1.2 (Rs. Million)

The rates of 2012

were not applicable in 2014 so, after Consultation with

Revenue and Agriculture

Department, rate for land and crop

compensation were updated,

while rates for structures and,

other i.e. Tree compensation

and livelihood assistance are still

applicable in 2015-16.

Therefore, there is no much changes

recognized for D, E, F and G up till now.

B) Land Acquisition Compulsory Surcharge (15%)

- - -

C) Crop Compensation

Rabi Acres 32,236 42,000

Kharif Acres

54,373 82,000

D) Residential Structures (Houses) Sq. ft. Rs.675/sqft Rs.675/sqft

- i) Pacca structure Sq. ft. - -

- ii) Semi-Pacca structures - Sq. ft. - -

- iii) Katcha/ thatched shed - Sq. ft. - -

E) Others - - -

i) Cattle Yard Sq. ft. Rs.675/sqft Rs.675/sqft

ii) Borehole of a tube well / drilling

No 148000/

bore 148000/ bore

iii) Hand pump No 0.01 0.01

Cost of W/C 1 community ,Private

Meters 1445/m 1445/m

F) Tree Compensation

Fruit Trees No 4208.33 4208.33

Timber wood trees

No 1663.16 1663.16

G) Livelihood Assistance - -

- Livelihood assistance to vulnerable families

- - -

a) impassion cash assistance /allowance equivalent to 6 months OPL adjustment amount , i.e.(Rs. 12000)

DFs 0.072 0.072

b) Relocation assistance Rs. 5000/- to be paid all the DPs requiring to move out of the ROW or Land acquired for the Project

DFs 0.005 0.005

NKBP Internal Resettlement Monitoring Report

21 PMO For Punjab Barrages

Annex-D

1- List of Potential Persons of Displaced Families (DFs) Requiring Jobs under the

Project

Sr.

No Name Father's Name

Father's

Designation

Age

(Years) Education Remarks

1

Mr. Muhammad

Nadeem Abdul Hameed Gurge Reader 21 Middle Out of Country

2

Mr. Muhammad

Sufian

Muhammad

Mansha Baildar 21 Middle Out of Country

3 Mr. Akhtar Ali

Muhammad

Mansha Baildar 21 Matric Out of Country

4 Mr. Paris Ali Walayat Hussain

Head Boat

Man 24 Middle Not Willing

5 Mr. Rahat Ali Walayat Hussain

Head Boat

Man 27 Middle

Hired

in year 2014-15

6

Ms. Rizwana

(female) W/O Pans Ali

Head Boat

Man 26

Intermedia

te Not Required

7 Mr. Waseem Akram

Muhammad

Akram Baildar 28 Middle

Hired

in year 2014-15

8 Mr. Husnan Akram

Muhammad

Akram Baildar 23 Middle

Hired

in year 2014-15

9 Mr. Ahsan Ullah Liaqat Ali Baildar 24 Middle Out of Country

10

Mr. Shafkat

Mushtaq Mustaq Ahmad

Head Boat

Man 21 Matric Not Willing

11

Mr. Mubasher

Sarfraz Malik Sarfraz Sub Engineer 22 M.Com Not Willing

2- Potential Persons available for Job from 5 Vulnerable DFs at Dera Farooq Akbar

Cheema, Village Khanki

Sr.

No Name Father's Name

Father's

Designation

Age

(Years) Education Remarks

1

Mr. Muhammad

Mustafa

Muanzoor

Hussain

Agricultural-

Labourer 25 Illiterate

Called for joining

but not joined

yet

2

Mr. Muhammad

Sarwar

Muhammad

Anayat

Agricultural-

Labourer 25 Illiterate

Called for joining

but not joined

yet

3 Mr. Ali Raza

Muhammad

Akram

Agricultural-

Labourer 23 Illiterate Migrate

4

Mr. Muhammad

Ramzan

Muhammad

Anayat

Agricultural-

Labourer 35 Illiterate Migrate

5

Mr. Ghulam

Murtaza Amanat Ali

Agricultural-

Labourer 21 Illiterate Migrate

NKBP Internal Resettlement Monitoring Report

22 PMO For Punjab Barrages

Application of employees sons of khanki division

Irrigation Department for Employment in DESCON

Annex-E

Sr. No Name of

Applicant Father's Name

Father's

Designation

Post Applied

For Remarks

1 Waseem Akram Muhammad

Akram Signaler Helper Hired

2 Salman Niaz Muhammad Niaz Security Guard Safty Helper

3 Muhammad

Afzaal Muhammad Riaz Boatman Helper Hired

4 Faisal Iqbal Muhammad

Ashraf

Regulation

Jamadar Helper Hired

5 Muqarrab Ali Muhammad

Ashraf Guage Reader Helper Hired

6 Muhammad

Rehan Ghulam Rabbani Oil Man Helper Hired

7 Atif Raza Muhammad

Abbas Baildar Helper Hired

8 Shah Nawaz Manzoor Hussain Baildar Helper Hired

9 Zaman Ali Nasrullah Khan Regulation

Baildar Helper Hired

10 Zubair Hussain Muhammad

Anwar Naib Qasid Helper Hired

11 Waqar Ali Late Muhammad

Aslam

Regulation

Baildar Helper Hired

NKBP Internal Resettlement Monitoring Report

23 PMO For Punjab Barrages

12 Muhammad Asim Muhammad

Inayat

Regulation

Baildar Messon

13 Qasir Shahzad Manzoor Hussain Baildar Driver Hired

14 Saeed Anwar Muhammad

Anwar Junior Clerk Office Boy Hired

15 Rahat Ali Muhammad

Walayat Hussain Head Boat Man Helper Hired

16 Umar Farooq Muhammad

Azam

Regulation

Baildar Helper Hired

17 Amjad Farooq Manzoor Hussain Baildar Helper Hired

18 Shahzad Ali Manzoor Hussain Baildar Helper Hired

19 Shawal Ali Liaqat Ali Regulation

Baildar

Generator

Mechanic

20 Kaleem Ullah Irshad Ahmad

Butt Boatman Office Boy

21 Muhammad Bilal Muhammad

Younas

Regulation

Baildar Helper Hired

22 Irshad Masih Ashraf Masih Sweeper Sweeper

23 Husnain Akram Muhammad

Akram

Regulation

Baildar Safty helper Hired

24 Jazib Ali Irshad Ahmad

Butt Boatman Survey Helper Hired

25 Muhammad

Javed Muhammad Khan Bulock Man Helper Hired

26 Bilal Ahmad Muhammad Fazal Naib Qasid Helper

NKBP Internal Resettlement Monitoring Report

24 PMO For Punjab Barrages

Employment Status for the Month of July, 2015 Annex - F

Sr.

No. Project Area

DESCON Sub-Contractor Total

Remarks Skilled

Un-

Skilled Total Skilled

Un-

Skilled Total Skilled

Un-

Skilled Total

1 Gujranwala 130 160 290 50 42 92 180 202 382

Three

PAPs’ sons are

serving

with the

Contract

or while

other are

not

willing to

do the

job on

the

project

2 Hafizabad 25 8 33 40 26 66 65 34 99

3 Chiniot 3 0 3 - - - 3 0 3

4 Sheikhupur

a 18 10 28 - - - 18 10 28

5 Nankana 18 0 18 - - - 18 0 18

6 Faisalabad 42 14 56 - - - 42 14 56

7 Jhang 24 12 36 - - - 24 12 36

8 Toba Tek

Singh 16 11 27 - - - 16 11 27

9

Gujrat

(Barrage

adjoining

villages

140 16 156 28 58 86 168 74 242

Total 416 231 647 118 126 244 534 357 891

9 % age 73.50% 57.32% 66.77

% 66.67% 80.77%

73.72

% 72% 64% 68%

10 Other

Districts 150 172 322 59 30 89 209 202 411

Total District 566 403 969 177 156 333 743 559 1302

64 % unskilled is used during the month of JULY-2015

NKBP Internal Resettlement Monitoring Report

25 PMO For Punjab Barrages

New Khanki Barrage Project (NKBP) Annex -G

Employment Status for the Month of August 2015

Sr.

No. Project Area

DESCON Sub-Contractor Total

Remarks

Skilled Un-

Skilled Total Skilled

Un-

Skilled Total Skilled

Un-

Skilled Total

1 Gujranwala 128 142 270 48 37 85 176 179 355

Three PAPs

sons are

solving with

the Contractor

while other are

not willing to

do the job on

the project

2 Hafizabad 25 8 33 38 21 59 63 29 92

3 Chiniot 3 0 3 - - - 3 0 3

4 Sheikhupura 18 10 28 - - - 18 10 28

5 Nankana 18 0 18 - - - 18 0 18

6 Faisalabad 40 12 52 - - - 40 12 52

7 Jhang 23 10 33 - - - 23 10 33

8 Toba Tek

Singh 14 11 25 - - - 14 11 25

9

Gujrat

(Barrage

adjoining

villages

138 16 154 22 48 70 160 64 224

Total 407 209 616 108 106 214 515 315 830

9 % age 72.16% 53.45% 64.50% 66.26% 80.30% 73.28% 71% 60% 66%

10 Other

Districts 157 182 339 55 26 81 212 208 420

Total District 564 391 955 163 132 295 727 523 1250

NKBP Internal Resettlement Monitoring Report

26 PMO For Punjab Barrages

New Khanki Barrage Project (NKBP) Annex -H

Employment Status for the Month of September 2015

Sr.

No. Project Area

DESCON Sub-Contractor Total

Remarks Skilled

Un-

Skilled Total Skilled

Un-

Skilled Total Skilled

Un-

Skilled Total

1 Gujranwala 130 142 272 48 37 85 178 179 357

Three PAPs

sons are

solving

with the

Contractor

while other

are not

willing to

do the job

on the

project

2 Hafizabad 25 8 33 38 21 59 63 29 92

3 Chiniot

3 0 3 - - - 3 0 3

4 Sheikhupura 18 10 28 - - - 18 10 28

5 Nankana

18 0 18 - - - 18 0 18

6 Faisalabad 40 12 52 - - - 40 12 52

7 Jhang

23 10 33 - - - 23 10 33

8 Toba Tek

Singh 15 11 26 - - - 15 11 26

9

Gujrat

(Barrage

adjoining

villages

138 16 154 22 48 70 180 44 224

Total

410 209 619 108 106 214 538 295 833

9 % age

72.31% 53.45% 64.61% 55.17% 72.88% 64.02% 67% 58% 64%

10 Other

Districts 157 182 339 104 32 136 261 214 475

Total District

567 391 958 212 138 350 799 509 1308