punjab irrigation agriculture investment project – new khanki
TRANSCRIPT
Social Monitoring Report Project Number: 37231-033 September 2015
PAK: Punjab Irrigation Agriculture Investment Project – New Khanki Barrage Project Loan 2841
Internal Resettlement Monitoring Report Prepared by the Project Management Office (PMO) for Punjab Barrages, Irrigation Department, Punjab for the Asian Development Bank (ADB).
The social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
GOVERNMENT OF THE PUNJAB
IRRIGATION DEPARTMENT
New Khanki Barrage Project (NKBP)
ADB Loan No. 2841-PAK
Internal Resettlement Monitoring Report
For
Quarter July – September, 2015
PROJECT MANAGEMENT OFFICE (PMO) FOR PUNJAB BARRAGES,
IRRIGATION DEPARTMENT CANAL BANK
MUSTAFABAD, LAHORE
NKBP Internal Resettlement Monitoring Report
1 PMO For Punjab Barrages
New Khanki Barrage Project (NKBP)
Internal Resettlement Monitoring Report for the Quarter July-September, 2015
1. LAND ACQUISITION AND RESETTLEMENT PLAN (LARP)
The project is category B for i volu tary resettle e t a d category C for i dige ous people. Draft Land Acquisition and Resettlement Plan (LARP) for New Khanki Barrage was prepared and
submitted to ADB for approval. ADB cleared the draft LARP on July 07, 2012. LARP was revised/
updated and cleared by ADB in Feb 2014. Land Acquisition is in progress according to requirement
of Land Acquisition Act 1894. A total of 8.6 acres of land was required for construction of Head
Regulator and Head Reach of the new LCC. Section 4 and section 5 of Land Acquisition Act for 8.6
acres of land were notified and published in the Punjab Gazette on August 07, 2012 and January 21,
2013 respectively. In the Punjab Gazette on August 07, 2012 and January 21, 2013 respectively. Land
price was assessed, and the EA released the total amount Rs. 9.925 million to the Revenue
Department, Government of the Punjab.
However, due to change in engineering design it was found that only 4.58 acres out of 8.6 acres of
land was required along with a new piece of land 1 acre, 6 kanal, 3 marlas, and 4.5 Sarsai. Due to
this change, process of land acquisition was re-initiated. The section 4 & 5 of land Acquisition Act
1894 for additional land was notified and published in the Punjab Gazette on July 11, 2014 and July
29, 2015 respectively.
Again due to change in engineering design of LCC Lead Channel, the procedure for acquiring 5 kanal,
10 Marla of private land from one landowner (Mr. Farooq Akbar Cheema) is still in process.
Compensation rates have been re-calculated to reflect current values and procedures. The
landowner has received partial payment for crop losses and structures. Compensation payment for
the trees and remaining structures is expected to be completed by December 2015.
The five affected families which are residing at the Dera of land owner remained on same site but
their new accommodation is being built by the landowner on his remaining land. Their livelihoods
remain unaffected. These households have received their relocation allowance (Pak Rupees
5,000/household) and cash assistance for vulnerable households (Pak Rupees72, 000/-household).
Alternative accommodation for the 15 no. of the affected families of Irrigation staff is also being
constructed. Funds for the remaining compensation activities are available. All compensation
payments (structure and 6.625 acres land) and relocation of the affected households will be
completed by June 2016.
LARP implementation activities for Tranche-2 relates to LCC Lead Channel (component) of New
Khanki Barrage Project. Internal Resettlement Monitoring of all relevant activities is the
responsibility of PMO (Environment and Social Unit (ESU). Internal Monitoring Reports in the shape
NKBP Internal Resettlement Monitoring Report
2 PMO For Punjab Barrages
of QPR are being regularly submitted to the Bank. The PMO is in the process of engaging an
independent resettlement monitor (IM) to cover all tranches of the MFF. The IM will be mobilized
by December 2015 and is expected to submit its first external resettlement monitoring report by
January 2016
Tranche-2 also has an operational Grievance Redressal Mechanism that covers all types of
grievances of NKBP, including resettlement. Complaint register is also being maintained by the
Consultants to record community concerns and their solutions. Out of 27 complaints, 15 complaints
have been resolved while 12 complaints are yet to be resolved. The detail of complaints is given in
Annex-A. ESU / PMO for Punjab Barrages in busy in Implementation of LARP since 2012.
The Implementation Schedule of LARP is given below:
Sr.
No.
Action Time Line Responsibility To date Status
1 Establishment of PMO - PID PMO is already in place at
Lahore.
2 Setting-up the ESU. In place
PMO ESU is already in place.
3 Setting-up the LIU at Khanki 30 June, 2012
PMO Notified
4 Establish Grievance Redress Cell. 30 Sep, 2012 PMO Notified.
5 Submission of draft LARP to ADB 30 June, 2012 PMO Submitted
6 Approval of LARP 15 June, 2012 ADB Cleared
7 Urdu translation and disclosure of
LARP
05 July, 2012 PD/ ESU Also paste at website
8 Formation of DPs Consultation
Committees (2 Nos.)
30 Jun 2012 LIU Formed and notified.
9 Deployment of Supervisory
Consultants
30 Sep. 2012 PMO Deployed
10 Deployment of Social & Environment 31 Dec 2012 PMO Deployed
11 Employment to DPs/ locals (age of
economic group)
June 2013 to
March 2017
Contractor/
Consultants/PMO
A list of willing and
potential DPs/ locals is
included in LARP. Also
NKBP Internal Resettlement Monitoring Report
3 PMO For Punjab Barrages
given to DESCON
(Contractor) for action.
12 IMR submission before handing over
Barrage site for construction
31 Oct, 2012 PMO Done
13 NTP for Barrage - ADB Done
14 Construction of Link LCC 30 Jun. 2016 Contractor/ PMO To be completed upto 30
Jun, 2016.
Land Acquisition
15 Section-4 Notification Dec. 2015 LAC Due to new / revised
drawing of LCC in
September 2015
16 Section-5 Notification January-2016 LAC --
17 Land Acquisition Process through
Private Negotiation
-- -- Not Applicable
18 LARP Updation Oct. 2015 Consultant Discussed with ADB
representatives on
October 07, 2015.
19 Payment to DPs (Partial Payment) July 2015 Land owner/ PMO 50% payment has
released to land owner,
while remaining 50% will
be paid after relocation
of his agricultural wage
labourers at alternate
location at nearby place.
20 Relocation of Farming labourers Dec., 2015 Land owner/Agri.
Labourers PMO
-
21 Final payment to land owner after
confirmation by IM that labourers
have been relocated and paid as in
LARP.
May 2016 PMO -
22 Possession/ Transfer of Land May 2016 LAC/ PMO -
23 Relocation/ Construction of Staff
Colony
Dec. 2015 PMO -
24 Relocation/ shifting of PID staff Dec. 2015 Residents/ PMO -
25 Construction of Community Lined
Watercourses
30 Jun 2016 Contractor/ PMO -
NKBP Internal Resettlement Monitoring Report
4 PMO For Punjab Barrages
26 Construction of Lined Public
Watercourse
30 Jun 2016 Contractor/ PMO -
27 Construction of High Level Channel 30 June 2016 Contractor/ PMO -
28 Date of contract award (expected) 30 Sept.,
2012
PMO -
29 Full Implementation of LARP Dec. 2016 PMO -
30 IMR confirming LARP implementation Dec. 2016 IM Specialist/
PMO
-
31 Commencement of civil works Subject to
ADB approval
for NTP.
ADB Subject to ADB approval
on the satisfactory
implementation of LARP.
32 Redress of Community Complaints Continuous
activity
GRC/ PMO Ongoing activity till
project completion.
Total amount under LARP is Rs. 18.05 Million. Out of which, Rs. 9.925 Million has already been paid
to the Revenue Department for land Acquisition. Rupees 2.864 million have been paid to the six no.
of affected families as compensation amount for their structures. The detail is given in Annex-B
2. ADJUSTMENT MADE IN THE COMPENSATION RATE DURING UPDATING OF LARP
The LARP of New Khanki Barrage was approved in 2012. Again, it was updated and approved in
2014. The adjustment was made in compensation rates of the land after certification by the Revenue
Department, Government of Punjab.
The rates are still applicable up till now. The adjustment made in the compensation is given
at Annex-C.
3. EMPLOYMENT FOR THE AFFECTED HOUSEHOLDS IN PROJECT RELATED JOBS
Two types of affected families are residing at LCC Lead Channel. First are Irrigation Department
Employees and they are already serving in Irrigation Department. Second are the land owner and his
agriculture laborers, those are cultivating crops. They also remained busy in construction of houses
for shifting in newly built houses. The Contractor is ready to accommodate the affected families for
jobs as and when they demand. ESU, PMO Punjab Barrages requested to the Consultants to ask
the Contractor to provide jobs under the project. As per recommendation of the Engineer, the
Contractor trace each of the person included in the list, the list of the potential persons of affected
NKBP Internal Resettlement Monitoring Report
5 PMO For Punjab Barrages
families requiring jobs under the project. The Contractor offered them an appropriate employment.
Out of 16 affected persons, only 3 residents of Irrigation Colony were willing for jobs with the
Contractor and the Contractor hired their services. The status of employment of affected families is
given in Annex-D. The Contractor also offered jobs to the family members of employees of Irrigation
Department of Khanki Division. Out of 26 applications, 20 family members of Irrigation staff were
offered jobs and the Contractor hired their services under the Project. The detail is given in Annex-E
Regarding employment to the unskilled labor of the local area, the status of skilled and un-skilled
labor employment for the month of July, August and September 2015 is given in Annex-F, G and H
which is 64%, 60% and 58 % respectively for the unskilled labor for the project area.
4. RELOCATION OF AFFECTED HOUSEHOLDS AND THEIR CURRENT LIVING
CONDITION
Total Twenty One (21) affected families (AFs) are to be dislocated from LCC Lead Channel
component of New Khanki Barrage Project. In first phase, land owner and his five (05) Agri-laborers
are to be relocated and an amount of Pak Rupees 2.864 million has been paid to the six (06) no. of
affected families as the compensation amount for their structure and other assets. Fifteen (15) no. of
affected families are the Irrigation Department Employees. Construction of new residences for these
families is in progress and after completion / handing over to Irrigation Department, they will be
shifted accordingly. Status of current living condition of all affected household is as under:
Case No.1
Mr. Farooq Akbar Cheema is only the land owner fall in category of affected families. His land, trees
and residential structures etc. were affected due to construction of LCC Lead Channel under NKBP.
A compensation payment of amounting to Pak Rs. 1,570,362 was paid for crops, tube well borehole,
hand pump and structures. His current status of land and structure after dismantling can be viewed
as under:
NKBP Internal Resettlement Monitoring Report
6 PMO For Punjab Barrages
Mr. Farooq Akbar Cheema (Land owner) is standing on his land and structures after dismantling in the back
ground.
Case No.2
Mr. Muhammad Anwar is the agri-laborer of Mr. Farooq Akbar Cheema. He is residing at the Dera of
land owner and now he will be relocated to the newly constructed house by the land owner. He has
received an amount of Rs. 77,000/- as compensation / poverty allowance and relocation allowance.
His current status is as under:
Mr. Muhammad Anwar is standing in front of his house
NKBP Internal Resettlement Monitoring Report
7 PMO For Punjab Barrages
Case No.3
Mr. Amanat Ali is the agri-laborer of Mr. Farooq Akbar Cheema. He is residing at the Dera of land
owner and now he will be relocated to the newly constructed house by the land owner. He has
received an amount of Rs. 77,000/- as compensation /poverty allowance and relocation allowance.
His current status is as under:
Mr. Amanat Ali is standing in front of his existing residence
Case No.4
Mr. Manzoor Hussain is the agri-laborer of the Mr. Farooq Akbar Cheema. He built the residential
structure at the Dera of land owner. He has received amounting to Rs. 986,100/- as compensation
for his structures, one (01) No. of hand pump, poverty allowance and relocation allowance.
NKBP Internal Resettlement Monitoring Report
8 PMO For Punjab Barrages
Mr. Manzoor Hussain is standing near his dismantled house
Case No.5
Mr. Anayat Muhammad is the argi-laborer of Mr. Farooq Akbar Cheema. He was residing at the Dera
of land owner and now he will be relocated to the newly constructed house by the land owner. He
has received an amount of Rs. 77,000/- as compensation /poverty allowance and relocation
allowance. His current status is as under:
Mr. Anayat Muhammad is standing near his dismantled house
NKBP Internal Resettlement Monitoring Report
9 PMO For Punjab Barrages
Case No.6
Mr. Muhammad Ramzan is the agri-laborer of Mr. Farooq Akbar Cheema. He was residing at the
Dera of land owner and he will be relocated to the newly constructed house by the land owner. He
has received an amount of Rs. 77,000/- as compensation /poverty allowance and relocation
allowance. His current status is as under:
Mr. Muhammad Ramzan is standing near his dismantled house
Case No.7
Mr. Abdul Hameed (Guage Reader) is employee of the Irrigation Department and he is residing at
RoW of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony
Khanki and he will get Rs. 5,000/- as relocation / shifting allowance.
Case No. 7. Mr. Abdul Hameed (Guage Reader) with his family at existing residence.
NKBP Internal Resettlement Monitoring Report
10 PMO For Punjab Barrages
Case No.8
Mr. Muhammad Mansha (Beldar) is employee of the Irrigation Department and he is residing at RoW
of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony Khanki
and he will get Rs. 5,000/- as relocation / shifting allowance.
Case No.8. Mr. Muhammad Mansha (Beldar) with his family at his existing residence.
Case No.9
Mr. Ghulam Abbas (Chowkidar) is employee of the Irrigation Department and he is residing at RoW
of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony Khanki
and he will get Rs. 5,000/- as relocation / shifting allowance
Case No. 9. Mr. Ghulam Abbas (Chowkidar) with family at his existing residence.
NKBP Internal Resettlement Monitoring Report
11 PMO For Punjab Barrages
Case No.10
Mr. Faisal Mehmood (Naib Qasid) is employee of the Irrigation Department and he is residing at
RoW of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony
Khanki and he will get Rs. 5,000/- as relocation / shifting allowance.
Case No. 10. Mr. Faisal Mehmood (Naib Qasid) is standing at his existing residence.
Case No.11
Mr. Muhammad Akram (Regulation Beldar) is employee of the Irrigation Department and he is
residing at RoW of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in
Canal Colony Khanki and he will get Rs. 5,000/- as relocation / shifting allowance.
Case No. 11. Mr. Muhammad Akram (Regulation Beldar) with family at his existing residence.
NKBP Internal Resettlement Monitoring Report
12 PMO For Punjab Barrages
Case No.12
Mr. Muhammad Riaz (Boatman) is employee of the Irrigation Department and he is residing at RoW
of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony Khanki
and he will get Rs. 5,000/- as relocation / shifting allowance.
Case No. 12. Mr. Muhammad Riaz (Boatman) with family at his existing residence.
Case No.13
Mr. Liaqat Ali (Regulation Beldar) is employee of the Irrigation Department and he is residing at RoW
of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony Khanki
and he will get Rs. 5,000/- as relocation / shifting allowance.
Case No.13. Mr. Liaqat Ali (Regulation Beldar) with family at his existing residence.
NKBP Internal Resettlement Monitoring Report
13 PMO For Punjab Barrages
Case No.14
Mr. Walayat Hussain (Head Boatman) is employee of the Irrigation Department and he is residing at
RoW of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony
Khanki and he will get Rs. 5,000/- as relocation / shifting allowance.
Case No. 14. Mr. Walayat Hussain (Head Boatman) with family at his existing residence.
Case No.15
Mr. Muhammad Shabbir (Beldar) is employee of the Irrigation Department and he is residing at RoW
of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony Khanki
and he will get Rs. 5,000/- as relocation / shifting allowance.
Case No. 15. Mr. Muhammad Shabbir (Beldar) standing in front of his existing residence
NKBP Internal Resettlement Monitoring Report
14 PMO For Punjab Barrages
Case No.16
Mr. Muhammad Mushtaq (Beldar) is employee of the Irrigation Department and he is residing at
RoW of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony
Khanki and he will get Rs. 5,000/- as relocation / shifting allowance.
Case No. 16. Mr. Muhammad Mushtaq(Beldar) standing in front of his existing residence
Case No.17
Mr. Ashraf Masih (Sweeper) is employee of the Irrigation Department and he is residing at RoW of
LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony Khanki
and he will get Rs. 5,000/- as relocation / shifting allowance.
Case No. 17. Mr. Ashraf Masih(Sweeper), standing in front of his existing residence.
NKBP Internal Resettlement Monitoring Report
15 PMO For Punjab Barrages
Case No.18
Mr. Amanat Ali (Painter) is employee of the Irrigation Department and he is residing at RoW of LCC
Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony Khanki and he
will get Rs. 5,000/- as relocation / shifting allowance.
Case No. 18. Amanat Ali (Painter) standing in front of his existing residence.
Case No.19
Mr. Sibt Ul Hassan (Sub Engineer) is employee of the Irrigation Department and he is residing at
RoW of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony
Khanki and he will get Rs. 5,000/- as relocation / shifting allowance.
Case No. 19. Sibt Ul Hassan (Sub Engineer) is standing in front of his existing residence
NKBP Internal Resettlement Monitoring Report
16 PMO For Punjab Barrages
Case No.20
Mr. Rana Ayub ((Sub Engineer)) is employee of the Irrigation Department and he is residing at RoW
of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony Khanki
and he will get Rs. 5,000/- as relocation / shifting allowance.
Case No. 20. Rana Ayub (Sub Engineer)is standing in front of his existing residence
Case No.21
Mr. Muhammad Shabir (Sub Engineer) is employee of the Irrigation Department and he is residing at
RoW of LCC Lead Chanel of NKBP. He will be relocated to newly allotted building in Canal Colony
Khanki and he will get Rs. 5,000/- as relocation / shifting allowance.
Case No. 21. Muhammad Shabir (Sub Engineer) is standing in front of his existing residence.
NKBP Internal Resettlement Monitoring Report
17 PMO For Punjab Barrages
Status of Settlement of Complaints Annex –A
Sr# Date Complainant Location Sort of Complain Status
1 10/2/14 Imtiaz Ahmed
Lundpur
/complete
address
Demand for Culverts at
Chanawan Road Resolved
2 1/1/15 Zubair Ahmad Burj Cheema
Demand for Culverts/186+36
and 192+32 /Chanawan
Road
Resolved
3 10/1/15 Mansoor Warraich Thatthi Baloch
Demand for
Culverts134+71/Chanawan
Road
Resolved
4 5/1/14 Khizar Hayat Thatthi Baloch
Demand for
Culverts/115+70Chanawan
Road
Resolved
5 10/12/14 Naseem Hussain Thatthi Baloch
Demand for
Culverts/84+93/Chanawan
Road
Resolved
6 15/12/14 Master Shafqat Ali Faqiranwali
Demand for
Culverts/56+37/Chanawana
Road
Resolved
7 14/10/14 Farooq Akbar
Cheema LCC
Increase the rate of land
/LCC In Process
8 26/12/14 Dr. Azhar Iqbal
Cheema Kot Jaffar
Small Bridge /Gunayanwala
to Kot Jaffar Road In Process
9 1/12/14 Rana Muhammad
Khan Burj Dhalla
Demand for
Culverts/19+200/ Chanawan
Road 21+150
In Process
10 Repeated
App
Dr. Azhar Iqbal
Cheema Kot Jaffar No 8 Applicaton Repeated. Resolved
11 12/4/15 Ghulam Sarwar
Cheema Burj Cheema
Demand for
Culverts/Chanawan Road Resolved
12 21/05/15 Head Mistress
Girls School Khanki Play Ground/ Khanki In Process
13 16/5/15 Ghulam Rasool Ratowali /Jamil
Town
Cemented Ramp & Soling
/LMB Road In Process
14 21/5/15 Farooq Akbar
Cheema Kot Imam Bux
Drainage of flood
water/Chanawan Road In Process
15 14/5/15 Umer Hayat Burj Dhalla Demand for
Culverts/Chanawan Road In Process
NKBP Internal Resettlement Monitoring Report
18 PMO For Punjab Barrages
16 8/6/15 Hafiz SaifUllah
Chatta Kot Ratta
Speed Breaker/ Footpath
/Chanawan Road In Process
17 9/6/15 Muhammad
Aslam Randhawa Kor Ratta Outlet /Chanawan Road In Process
18 8/6/15 Haji Amjad Pervaiz
Randhawa Kor Ratta
Repair the old bridge
/Chanawan Road In Process
19 7/6/15 Pervaiz Iqbal
Bhatti Kot Ratta
Repair the old
bridge/Chanawan Road In Process
20 9/6/15 XEN Irrigation Khanki Boundary wall / Play
Ground/Irrigation Colony
Approved by
PMO
21 6/4/15 Master Nasir
Mahmood Kot Ratta
Change the location of
culvert/Chanawan Road Resolved
22 11/4/15 Waqas Chatta
Advocate Lundpur Court Case /Chanawan Road Resolved
23 9/7/15 SDO Headworks Khanki Breakage of High Level
Channel Resolved
24 7/7/15 Umer Hayat Burj Dhalla Hurdle on Chanawan Road In Process
25 14/7/15 Farooq Akbar
Cheema Khanki
Drainage of Rain water from
crops Resolved
26 22/7/15 Amanat Ali Khanki Standing Rain Water in
Colony Resolved
27 28/7/15 SDO Headworks Khanki Breakage of High Level
Channel Resolved
NKBP Internal Resettlement Monitoring Report
19 PMO For Punjab Barrages
Annex –B
Implementation of LARP for New Khanki Barrage as of September
2015
Contract No. 2841-PAK
Sr.
No Contract No.
Status of
Preparatio
n, vetting
and
approval of
RP
No. of
AFs
Paym
ent
Due
Total
AFs
paid
Amou
nt
Paid
%
Implement
ation
%
Amount
Paid
Remarks
1 2841-PAK
LARP for LCC
Lead Channel
Component
(under NKBP)
Draft LARP
of LCC Lead
Channel
was
prepared
and
approved in
2012. Later
on LARP
was
revised,
updated
and cleared
by ADB in
Feb, 2014
21 15.41
8
6 2.864 29% 18.57 Cost of 6.625
@ 1,200,000 is
amounting to
Rs. 7,950,000
while PMO has
deposited Rs.
9.925 (million)
to the
Revenue
Department
for payment to
the land
owner
NKBP Internal Resettlement Monitoring Report
20 PMO For Punjab Barrages
Adjustment made in Compensation Rates in LARP July, 2014
Annex - C
Sr. No. Description Unit
Unit Rate of LARP
2012
Unit Rate of updated LARP
2014 Remarks
A) Mouza -Wise Acquisition of Private Land
I) Khanki Acres 0.474 (Rs. Million)
1.2 (Rs. Million)
The rates of 2012
were not applicable in 2014 so, after Consultation with
Revenue and Agriculture
Department, rate for land and crop
compensation were updated,
while rates for structures and,
other i.e. Tree compensation
and livelihood assistance are still
applicable in 2015-16.
Therefore, there is no much changes
recognized for D, E, F and G up till now.
B) Land Acquisition Compulsory Surcharge (15%)
- - -
C) Crop Compensation
Rabi Acres 32,236 42,000
Kharif Acres
54,373 82,000
D) Residential Structures (Houses) Sq. ft. Rs.675/sqft Rs.675/sqft
- i) Pacca structure Sq. ft. - -
- ii) Semi-Pacca structures - Sq. ft. - -
- iii) Katcha/ thatched shed - Sq. ft. - -
E) Others - - -
i) Cattle Yard Sq. ft. Rs.675/sqft Rs.675/sqft
ii) Borehole of a tube well / drilling
No 148000/
bore 148000/ bore
iii) Hand pump No 0.01 0.01
Cost of W/C 1 community ,Private
Meters 1445/m 1445/m
F) Tree Compensation
Fruit Trees No 4208.33 4208.33
Timber wood trees
No 1663.16 1663.16
G) Livelihood Assistance - -
- Livelihood assistance to vulnerable families
- - -
a) impassion cash assistance /allowance equivalent to 6 months OPL adjustment amount , i.e.(Rs. 12000)
DFs 0.072 0.072
b) Relocation assistance Rs. 5000/- to be paid all the DPs requiring to move out of the ROW or Land acquired for the Project
DFs 0.005 0.005
NKBP Internal Resettlement Monitoring Report
21 PMO For Punjab Barrages
Annex-D
1- List of Potential Persons of Displaced Families (DFs) Requiring Jobs under the
Project
Sr.
No Name Father's Name
Father's
Designation
Age
(Years) Education Remarks
1
Mr. Muhammad
Nadeem Abdul Hameed Gurge Reader 21 Middle Out of Country
2
Mr. Muhammad
Sufian
Muhammad
Mansha Baildar 21 Middle Out of Country
3 Mr. Akhtar Ali
Muhammad
Mansha Baildar 21 Matric Out of Country
4 Mr. Paris Ali Walayat Hussain
Head Boat
Man 24 Middle Not Willing
5 Mr. Rahat Ali Walayat Hussain
Head Boat
Man 27 Middle
Hired
in year 2014-15
6
Ms. Rizwana
(female) W/O Pans Ali
Head Boat
Man 26
Intermedia
te Not Required
7 Mr. Waseem Akram
Muhammad
Akram Baildar 28 Middle
Hired
in year 2014-15
8 Mr. Husnan Akram
Muhammad
Akram Baildar 23 Middle
Hired
in year 2014-15
9 Mr. Ahsan Ullah Liaqat Ali Baildar 24 Middle Out of Country
10
Mr. Shafkat
Mushtaq Mustaq Ahmad
Head Boat
Man 21 Matric Not Willing
11
Mr. Mubasher
Sarfraz Malik Sarfraz Sub Engineer 22 M.Com Not Willing
2- Potential Persons available for Job from 5 Vulnerable DFs at Dera Farooq Akbar
Cheema, Village Khanki
Sr.
No Name Father's Name
Father's
Designation
Age
(Years) Education Remarks
1
Mr. Muhammad
Mustafa
Muanzoor
Hussain
Agricultural-
Labourer 25 Illiterate
Called for joining
but not joined
yet
2
Mr. Muhammad
Sarwar
Muhammad
Anayat
Agricultural-
Labourer 25 Illiterate
Called for joining
but not joined
yet
3 Mr. Ali Raza
Muhammad
Akram
Agricultural-
Labourer 23 Illiterate Migrate
4
Mr. Muhammad
Ramzan
Muhammad
Anayat
Agricultural-
Labourer 35 Illiterate Migrate
5
Mr. Ghulam
Murtaza Amanat Ali
Agricultural-
Labourer 21 Illiterate Migrate
NKBP Internal Resettlement Monitoring Report
22 PMO For Punjab Barrages
Application of employees sons of khanki division
Irrigation Department for Employment in DESCON
Annex-E
Sr. No Name of
Applicant Father's Name
Father's
Designation
Post Applied
For Remarks
1 Waseem Akram Muhammad
Akram Signaler Helper Hired
2 Salman Niaz Muhammad Niaz Security Guard Safty Helper
3 Muhammad
Afzaal Muhammad Riaz Boatman Helper Hired
4 Faisal Iqbal Muhammad
Ashraf
Regulation
Jamadar Helper Hired
5 Muqarrab Ali Muhammad
Ashraf Guage Reader Helper Hired
6 Muhammad
Rehan Ghulam Rabbani Oil Man Helper Hired
7 Atif Raza Muhammad
Abbas Baildar Helper Hired
8 Shah Nawaz Manzoor Hussain Baildar Helper Hired
9 Zaman Ali Nasrullah Khan Regulation
Baildar Helper Hired
10 Zubair Hussain Muhammad
Anwar Naib Qasid Helper Hired
11 Waqar Ali Late Muhammad
Aslam
Regulation
Baildar Helper Hired
NKBP Internal Resettlement Monitoring Report
23 PMO For Punjab Barrages
12 Muhammad Asim Muhammad
Inayat
Regulation
Baildar Messon
13 Qasir Shahzad Manzoor Hussain Baildar Driver Hired
14 Saeed Anwar Muhammad
Anwar Junior Clerk Office Boy Hired
15 Rahat Ali Muhammad
Walayat Hussain Head Boat Man Helper Hired
16 Umar Farooq Muhammad
Azam
Regulation
Baildar Helper Hired
17 Amjad Farooq Manzoor Hussain Baildar Helper Hired
18 Shahzad Ali Manzoor Hussain Baildar Helper Hired
19 Shawal Ali Liaqat Ali Regulation
Baildar
Generator
Mechanic
20 Kaleem Ullah Irshad Ahmad
Butt Boatman Office Boy
21 Muhammad Bilal Muhammad
Younas
Regulation
Baildar Helper Hired
22 Irshad Masih Ashraf Masih Sweeper Sweeper
23 Husnain Akram Muhammad
Akram
Regulation
Baildar Safty helper Hired
24 Jazib Ali Irshad Ahmad
Butt Boatman Survey Helper Hired
25 Muhammad
Javed Muhammad Khan Bulock Man Helper Hired
26 Bilal Ahmad Muhammad Fazal Naib Qasid Helper
NKBP Internal Resettlement Monitoring Report
24 PMO For Punjab Barrages
Employment Status for the Month of July, 2015 Annex - F
Sr.
No. Project Area
DESCON Sub-Contractor Total
Remarks Skilled
Un-
Skilled Total Skilled
Un-
Skilled Total Skilled
Un-
Skilled Total
1 Gujranwala 130 160 290 50 42 92 180 202 382
Three
PAPs’ sons are
serving
with the
Contract
or while
other are
not
willing to
do the
job on
the
project
2 Hafizabad 25 8 33 40 26 66 65 34 99
3 Chiniot 3 0 3 - - - 3 0 3
4 Sheikhupur
a 18 10 28 - - - 18 10 28
5 Nankana 18 0 18 - - - 18 0 18
6 Faisalabad 42 14 56 - - - 42 14 56
7 Jhang 24 12 36 - - - 24 12 36
8 Toba Tek
Singh 16 11 27 - - - 16 11 27
9
Gujrat
(Barrage
adjoining
villages
140 16 156 28 58 86 168 74 242
Total 416 231 647 118 126 244 534 357 891
9 % age 73.50% 57.32% 66.77
% 66.67% 80.77%
73.72
% 72% 64% 68%
10 Other
Districts 150 172 322 59 30 89 209 202 411
Total District 566 403 969 177 156 333 743 559 1302
64 % unskilled is used during the month of JULY-2015
NKBP Internal Resettlement Monitoring Report
25 PMO For Punjab Barrages
New Khanki Barrage Project (NKBP) Annex -G
Employment Status for the Month of August 2015
Sr.
No. Project Area
DESCON Sub-Contractor Total
Remarks
Skilled Un-
Skilled Total Skilled
Un-
Skilled Total Skilled
Un-
Skilled Total
1 Gujranwala 128 142 270 48 37 85 176 179 355
Three PAPs
sons are
solving with
the Contractor
while other are
not willing to
do the job on
the project
2 Hafizabad 25 8 33 38 21 59 63 29 92
3 Chiniot 3 0 3 - - - 3 0 3
4 Sheikhupura 18 10 28 - - - 18 10 28
5 Nankana 18 0 18 - - - 18 0 18
6 Faisalabad 40 12 52 - - - 40 12 52
7 Jhang 23 10 33 - - - 23 10 33
8 Toba Tek
Singh 14 11 25 - - - 14 11 25
9
Gujrat
(Barrage
adjoining
villages
138 16 154 22 48 70 160 64 224
Total 407 209 616 108 106 214 515 315 830
9 % age 72.16% 53.45% 64.50% 66.26% 80.30% 73.28% 71% 60% 66%
10 Other
Districts 157 182 339 55 26 81 212 208 420
Total District 564 391 955 163 132 295 727 523 1250
NKBP Internal Resettlement Monitoring Report
26 PMO For Punjab Barrages
New Khanki Barrage Project (NKBP) Annex -H
Employment Status for the Month of September 2015
Sr.
No. Project Area
DESCON Sub-Contractor Total
Remarks Skilled
Un-
Skilled Total Skilled
Un-
Skilled Total Skilled
Un-
Skilled Total
1 Gujranwala 130 142 272 48 37 85 178 179 357
Three PAPs
sons are
solving
with the
Contractor
while other
are not
willing to
do the job
on the
project
2 Hafizabad 25 8 33 38 21 59 63 29 92
3 Chiniot
3 0 3 - - - 3 0 3
4 Sheikhupura 18 10 28 - - - 18 10 28
5 Nankana
18 0 18 - - - 18 0 18
6 Faisalabad 40 12 52 - - - 40 12 52
7 Jhang
23 10 33 - - - 23 10 33
8 Toba Tek
Singh 15 11 26 - - - 15 11 26
9
Gujrat
(Barrage
adjoining
villages
138 16 154 22 48 70 180 44 224
Total
410 209 619 108 106 214 538 295 833
9 % age
72.31% 53.45% 64.61% 55.17% 72.88% 64.02% 67% 58% 64%
10 Other
Districts 157 182 339 104 32 136 261 214 475
Total District
567 391 958 212 138 350 799 509 1308