initial environmental examination report
TRANSCRIPT
Initial Environmental Examination Report ________________________________________
Project Number: 47021-002
Loan Number: 3239
PAK: Federally Administered Tribal Areas Water Resources
Development Project
Initial Environmental Examination Report for Tor Dara and Tarkhokas Weirs,
District Khyber
Prepared by Project Management Unit, Government of Khyber Pakhtunkhwa, Pakistan
For the Asian Development Bank
Date received by ADB: June 2020
NOTES
(i) The fiscal year (FY) of the Government of the Islamic Republic of Pakistan and its
agencies ends on 30 June.
(ii) In this report “$” refer to US dollars.
This initial environmental examination report is a document of the borrower. The views expressed
herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation
of or reference to a particular territory or geographic area in this document, the Asian
Development Bank does not intend to make any judgments as to the legal or other status of any
territory or area.
FEDERALLY ADMINISTERED TRIBAL AREAS
WATER RESOURCES DEVELOPMENT PROJECT
PMU FWRDP
Project Management Unit FATA Water Resources Development Project P&D Department KP
INITIAL ENVIRONMENTAL EXAMINATION (IEE)
TOR DARA & TARKHO KAS WEIRS
(KHYBER DISTRICT) March, 2020
House # 3, Street # 1, Near Board Bazar, Tajabad, Peshawar, Khyber Pakhtunkhwa, Pakistan. Tel: +92 91 5601635 - 6 Fax: +92 91 5840807 E-mail: [email protected]
FATA WATER RESOURCES DEVELOPMENT PROJECT CONSULTANTS
Initial Environmental Examination:
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
i | T O C
TABLE OF CONTENTS
Sr. No. Description ................................................................................................. Page No.
List of Abbreviations ................................................................................................................ ii
EXECUTIVE SUMMARY ......................................................................................................... i
INTRODUCTION.................................................................................................................... 9
General .................................................................................................................... 9
Project Background ................................................................................................. 9
Project Consultants .................................................................................................10
Purpose of This Initial Environmental Examination (IEE) ........................................10
IEE Methodology ....................................................................................................10
Study Area ..............................................................................................................11
Baseline Survey Methodology ................................................................................11
Impact Assessment Methodology ...........................................................................13
Report Format ........................................................................................................14
Project Categorization ............................................................................................15
IEE Team ...............................................................................................................15
POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK ................................................... 16
General ...................................................................................................................16
National Policy and Legal Framework .....................................................................16
The Khyber Pakhtunkhwa Environmental Protection Act, 2014 ..............................16
Regulations for Environmental Assessment, Pakistan EPA ....................................17
Regulatory Clearances, EPA ..................................................................................18
Guidelines for Environmental Assessment, Pakistan EPA ......................................18
Pakistan Environmental Protection Agency Review of IEE and EIA Regulations, (2000)…. ..............................................................................................................................18
National Environmental Quality Standards (NEQS) ................................................18
Comparative Analysis of the National and International Standards .........................19
ADB’s Safeguard Policy Statement (SPS), 2009 ....................................................25
Project Categorization ............................................................................................26
Other Environment Related Legislations .................................................................27
PROJECT DESCRIPTION ................................................................................................... 30
Project Features .....................................................................................................30
Project Location ......................................................................................................36
Project Objectives ...................................................................................................36
Construction Planning .............................................................................................36
Stage-I ....................................................................................................................37
Stage- II ..................................................................................................................37
Initial Environmental Examination:
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
ii | T O C
Sub Projects Implementation ..................................................................................42
Executing Agency ...................................................................................................42
Design Consultant ..................................................................................................42
Provincial Development Working Party ...................................................................42
Terms of Partnership ..............................................................................................43
Operation and Maintenance ....................................................................................43
DESCRIPTION OF ENVIRONMENT .................................................................................... 44
General ...................................................................................................................44
Baseline Survey Methodology ................................................................................44
Study Area ..............................................................................................................46
Physical Environment .............................................................................................46
Topography ............................................................................................................46
Climate ...................................................................................................................47
Hydrology ...............................................................................................................48
Regional Geology ...................................................................................................49
Geology of the Sub Project Area .............................................................................49
Soil .........................................................................................................................50
Seismology .............................................................................................................50
Ambient Air Quality and Noise ................................................................................52
Water Resources ....................................................................................................56
Water Quality ..........................................................................................................57
Biological Environment ...........................................................................................59
Land use and Land Cover.......................................................................................59
Flora .......................................................................................................................62
Fauna .....................................................................................................................65
Avifauna .................................................................................................................66
Protected areas / National sanctuaries ...................................................................67
Fisheries .................................................................................................................67
Socio-Economic Environment .................................................................................67
Administrative Set Up .............................................................................................68
Demographic Profile ...............................................................................................68
Population ..............................................................................................................69
Family Size .............................................................................................................69
Dwelling ..................................................................................................................69
Language ...............................................................................................................70
The Family System .................................................................................................70
Livestock ................................................................................................................70
Conflicts Resolution Mechanism .............................................................................71
Religious Beliefs .....................................................................................................72
Water Supply and Sanitation ..................................................................................72
Poverty ...................................................................................................................73
Initial Environmental Examination:
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
iii | T O C
Health facilities .......................................................................................................74
Social Organization .................................................................................................74
Agriculture ..............................................................................................................74
Education ...............................................................................................................75
Food .......................................................................................................................76
Dress and Ornaments .............................................................................................77
Economic Features .................................................................................................77
Mining .....................................................................................................................77
Roads .....................................................................................................................78
Telephone Facilities ................................................................................................78
Sites of Historical Significance ................................................................................78
Gender Issues ........................................................................................................80
PROJECT ALTERNATIVES ................................................................................................. 82
ENVIRONMENTAL IMPACT ASSESSMENT AND MITIGATION MEASURES .................... 87
Impact Assessment - Overview ...............................................................................87
Impact Area ............................................................................................................87
Excavation ..............................................................................................................91
Waste Generation and Disposal .............................................................................92
Labour camps, storage and approach roads ...........................................................92
Soil pollution due to fuel and oil spillage from construction machinery ....................93
Agriculture Land Damage .......................................................................................94
Impact of taking borrow material from earth borrow site ..........................................94
Construction material leftovers................................................................................95
Impacts on Hydrology and Water Resources ..........................................................95
Contamination of surface water due to washing ......................................................95
Drinking water Supply for Contractor’s Staff............................................................96
Municipal waste disposed into the stream ...............................................................96
Impact on Air Quality and Noise Pollution ...............................................................96
Dust from construction and smoke from plants and equipment ...............................96
Noise from use of old/and or out-dated machinery ..................................................97
Dust Emission from stone quarrying and transportation ..........................................97
Impact on Biological Resources ..............................................................................97
Impacts on Socioeconomic, Cultural and Archaeological Issues .............................98
Tribal Tension and Rivalries ...................................................................................98
Impact on Civic Infrastructure ............................................................................... 100
Initial Environmental Examination:
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
iv | T O C
Community safety risks due to accidental or natural hazards ................................ 100
Health and safety of labour at construction site ..................................................... 100
Soil pollution due to excessive application of pesticides and fertilizers.................. 101
ENVIRONMENTAL MANAGEMENT PLAN (EMP) ............................................................. 103
General ................................................................................................................. 103
Mitigation Measures .............................................................................................. 103
Residual Impact .................................................................................................... 104
Institutional Arrangements .................................................................................... 104
Management Responsibilities ............................................................................... 104
Monitoring Activities .............................................................................................. 125
Project Enhancement Plans .................................................................................. 126
Restoration Plan ................................................................................................... 126
Reports ................................................................................................................. 126
Training Schedule ................................................................................................. 127
EMP Estimated Budget for Implementation .......................................................... 128
Third Party Monitoring .......................................................................................... 129
PUBLIC CONSULTATION ................................................................................................. 131
General ................................................................................................................. 131
Identification of Stakeholders ................................................................................ 132
Methodology ......................................................................................................... 133
Agenda of Consultative Session ........................................................................... 135
Local Farmer Views .............................................................................................. 135
Consultation with Other Stakeholders and Their Response .................................. 136
GRIEVANCE REDRESS MECHANISM ............................................................................. 139
General ................................................................................................................. 139
Objectives of Grievance Redress Mechanism ....................................................... 139
Awareness of GRM ............................................................................................... 140
Implementation of GRM ........................................................................................ 141
CONCLUSION, FINDINGS AND RECOMMENDATIONS .................................................. 144
Findings and Recommendations ........................................................................... 144
Conclusion ............................................................................................................ 144
Initial Environmental Examination:
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
v | T O C
List of Annexures
ANNEX-I Rapid Environmental Assessment Checklist ....................................................... 146
ANNEX – II Environmental Testing .................................................................................... 149
ANNEX III - National Environmental Quality Standards (NEQS) ......................................... 157
ANNEX – IV Governor Notifications on Wetlands and Wild Life in FATA ............................ 163
ANNEX-V Table of Content Environmental Compliance Monitoring ................................... 167
ANNEX – VI Photo Log ...................................................................................................... 169
ANNEX-VII WHO Standards .............................................................................................. 172
Initial Environmental Examination:
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
vi | T O C
List of Tables & Figures
Table 2.1 Comparison of International and local Air Quality Standards ....................................20
Table 2.2: Comparison of International and local for Noise-Limit in dB(A) Leq .........................21
Table 2.3 Comparison of International and local Standards for Drinking Water ........................22
Table 2.4 (a) Criteria for Irrigation Water ..................................................................................23
Table 2.4 (b) Conditions of Water Use and Irrigation Water Quality .........................................25
Table 2.4. Environmental Guidelines and Legislations .............................................................27
Table 3.1: Salient Features of Tor Dara Sub Project ................................................................30
Table 3.2: Salient Features of Tarkho Kas Sub Project ............................................................31
Figure 3.1: Sub Projects Location Map ....................................................................................33
Figure 3.2: Satellite Image of Tor Dara Sub Project Area .........................................................34
Figure 3.3: Satellite Image of Tarkho Kas Sub Project Area .....................................................35
Table 3.3: Weirs Location GPS Coordinates ............................................................................36
Table 3.4: Diversion Weirs Works and Quantities ....................................................................37
Figure 3.6: Diversion Weir Layout Plan Tor Dara .....................................................................39
Figure 3.7: Diversion Weir Layout Plan Tarkho Kas .................................................................40
Table 3.5: Personnel Requirement ...........................................................................................41
Table 3.6: Equipment Requirements ........................................................................................41
Figure 4.2: Tectonic Map of Pakistan .......................................................................................51
Table 4.1: Ambient Air Quality and Noise of Sub Projects Area ...............................................53
Figure 4.3 Environmental Testing and Sampling Map Tor Dara ...............................................54
Table 4.4: Water Quality of Tor Dara Sub Project ....................................................................57
Table 4.5: Water Quality of Tarkho Kas Sub Project ................................................................58
Figure 4.5: Land use Map ........................................................................................................61
Table 4.6: Common Trees Species in Project Area ..................................................................63
Table 4.7: Common Grasses Species in the Area.....................................................................64
Table 4.8: Common Shrub Species in the Project Area ............................................................64
Table 4.9: Fauna of the Project Area ........................................................................................65
Table 4.10: Avifauna of the Project Area...................................................................................66
Table 4.11: Population Details of Khyber District .....................................................................69
Table 4.12: No. of Functional Govt. Schools and Enrolment in Khyber (2014-15) ....................76
Figure 5.1 Impact Area .............................................................................................................88
Table 5.1 Screening of Environmental Impacts; Construction and Operation Stages ...............89
Table 6.1: Environmental Management (Mitigation) Plan (Construction & Operation) ............ 108
Table 6.2 Environmental Monitoring ....................................................................................... 125
Table 6.3: Distribution of Reports ........................................................................................... 127
Table 6.4: Estimated Budget for Environmental Management ................................................ 128
Table 6.5: Estimated Budget Environmental Monitoring ......................................................... 128
Figure 7.1: Identification of Stakeholders ............................................................................... 133
Table 7.3: List of Community Consultation Participants .......................................................... 137
Figure 7.2: Community Consultation Meetings ....................................................................... 138
Figure 8.1: Proposed GRM .................................................................................................... 143
Initial Environmental Examination:
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
| T O C
Units Conversion Tables
Length Units
Millimeters Centimeters Meters Kilometers Inches Feet Yards Miles
mm Cm M Km In ft yd mi
1 0.1 0.001 0.000001 0.03937 0.003281 0.001094 6.21e-07
10 1 0.01 0.00001 0.393701 0.032808 0.010936 0.000006 1000 100 1 0.001 39.37008 3.28084 1.093613 0.000621
1000000 100000 1000 1 39370.08 3280.84 1093.613 0.621371 25.4 2.54 0.0254 0.000025 1 0.083333 0.027778 0.000016 304.8 30.48 0.3048 0.000305 12 1 0.333333 0.000189 914.4 91.44 0.9144 0.000914 36 3 1 0.000568
1609344 160934.4 1609.344 1.609344 63360 5280 1760 1
Area Units
Millimeter Square
Centimeter Square
Meter square
Inch square
Foot square
Yard square
mm2
cm2
m2 in2 ft
2 yd
2
1 0.01 0.000001 0.00155 0.000011 0.000001
100 1 0.0001 0.155 0.001076 0.00012
1000000 10000 1 1550.003 10.76391 1.19599
645.16 6.4516 0.000645 1 0.006944 0.000772
92903 929.0304 0.092903 144 1 0.111111
836127 8361.274 0.836127 1296 9 1
Volume Units
Centimeter cube
Meter cube
Liter Inch cub
Foot
US gallons
Imperial
US barrel (oil)
cm3
m3 Ltr in3
ft3
US gal Imp. gal US brl
1 0.000001 0.001 0.061024 0.000035 0.000264 0.00022 0.000006
1000000 1 1000 61024 35 264 220 6.29 1000 0.001 1 61 0.035 0.264201 0.22 0.00629 16.4 0.000016 0.01638 1 0.000579 0.004329 0.003605 0.000103
28317 0.028317 28.3168 1728 1 7.481333 6.229712 0.178127 3785 0.003785 3.79 231 0.13 1 0.832701 0.02381 4545 0.004545 4.55 277 0.16 1.20 1 0.028593
158970 0.15897 159 9701 6 42 35 1
Mass Units
Grams Kilograms Metric tonnes Short ton Long ton Pounds Ounces
g Kg Tonne Shton Lton lb Oz
1 0.001 0.000001 0.000001 9.84e-07 0.002205 0.035273 1000 1 0.001 0.001102 0.000984 2.204586 35.27337
1000000 1000 1 1.102293 0.984252 2204.586 35273.37
907200 907.2 0.9072 1 0.892913 2000 32000
1016000 1016 1.016 1.119929 1 2239.859 35837.74 453.6 0.4536 0.000454 0.0005 0.000446 1 16
28 0.02835 0.000028 0.000031 0.000028 0.0625 1
Initial Environmental Examination:
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
i | T O C
Volumetric Liquid Flow Units
Liter/second Liter/minute Meter
cube/hour Foot
cube/minute Foot
cube/hour US
gallons/minute US barrels
(oil)/day
L/sec L/min M3/hr ft
3/min ft
3/hr gal/min US brl/d
1 60 3.6 2.119093 127.1197 15.85037 543.4783 0.016666 1 0.06 0.035317 2.118577 0.264162 9.057609 0.277778 16.6667 1 0.588637 35.31102 4.40288 150.9661
0.4719 28.31513 1.69884 1 60 7.479791 256.4674 0.007867 0.472015 0.02832 0.01667 1 0.124689 4.275326 0.06309 3.785551 0.227124 0.133694 8.019983 1 34.28804 0.00184 0.110404 0.006624 0.003899 0.2339 0.029165 1
Temperature Conversion Formulas
Degree Celsius (°C) (°F - 32) x 5/9
(K - 273.15)
Degree Fahrenheit (°F) (°C x 9/5) + 32
(1.8 x K) - 459.67
Kelvin (K) (°C + 273.15)
(°F + 459.67) ÷ 1.8
Currency Exchange Table
US Dollar Pakistani Rupees
01 154.99
Exchange Rate as of 13 February, 2020
Initial Environmental Examination:
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
ii | T O C
List of Abbreviations
AC Assistant Commissioner
ADB Asian Development Bank
AMSL Above Mean Sea Level
CO Community Organization
CCA Culturable Command Area
CSC Construction Supervision Consultant
DC Deputy Commissioner
DG Director General
EIA Environmental Impact Assessment
ESMU Environmental and Social Management Unit
EMMP Environmental Management and Monitoring Plan
EMP Environment Management Plan
EPA Environment Protection Agency
FRDP FATA Rural Development Project
FWRDP FATA Water Resources Development Project
FATA Federally Administered Tribal Areas
FGD Focus Group Discussions
GIS Geographic Information System
GoP Government of Pakistan
GRC Grievance Redress Committee
GRM Grievance Redress Mechanism
HSE Health, Safety and Environment
IA Implementing Agency
IEE Initial Environmental Examination
IUCN International Union for Conservation of Nature
KP Khyber Pakhtunkhwa
MMT Main Mantle Thrust
NEQS National Environmental Quality Standards
NSDWQ National Standards for Drinking Water Quality
NGO Non-Governmental Organization
NOC No Objection Certificate
PCC Plain Cement Concrete
PD Project Director
PEPA Pakistan Environmental Protection Act
PEPC Pakistan Environmental Protection Council
PIU Project Implementation Unit
PMU Project Management Unit
PPTA Project Preparatory Technical Assistance
RCC Reinforced Cement Concrete
RE Resident Engineer
SDS Safety Data Sheet
SPS Safeguard Policy Statement
SSEMP Site Specific Environmental Management Plan
ToP Terms of Partnership
ToR Terms of Reference
WWF World Wide Fund for Nature
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
i | Executive Summary
EXECUTIVE SUMMARY
1. Introduction
This environmental study was undertaken in accordance with Khyber
Pakhtunkhwa Environmental Protection Act, 2014 and ADB`s Safeguards Policy
Statement (SPS), 2009 requirement and recommendations.
The study Terms of References (TOR) requires that an assessment of the
environmental impacts of the sub projects (i.e. IEE or EIA), preparation of the
environmental management and monitoring plans (EMMPs), inclusion of costs
for implementing recommended mitigation measures, and any capacity
strengthening measures in the project development costs.
Federally Administered Tribal Areas (FATA) Water Resources Development
Project (FWRDP) will be operational in the provincial tribal territories at the
western borders of Pakistan with Afghanistan. It focuses on increasing irrigation
supplies in three Tribal Districts, namely Mohmand, Khyber and Bajaur, to
increase crop production and harvest water sustainably. The project is being
proposed as a result of the Water Assessment Study executed under the
completed ADB supported FATA Rural Development Project of former FATA
Secretariat. The study identified 40 watersheds where the groundwater aquifers
are depleting at a high rate, even under average weather conditions due to
unplanned water extraction for irrigation and other associated purposes. It
recommends shifting from groundwater to surface water, which remains totally
unutilized, and identified potential sites for small reservoirs and diversion weirs
in the 40 watersheds of Mohmand, Khyber and Bajaur Tribal Districts of Khyber
Pakhtunkhwa (KP).
With above background, ADB financed a Project Preparatory Technical
Assistance, TA 8409-PAK (PPTA) for FATA Water Resources Development
Project in preparing a project for financing consideration by ADB through FATA
support implemented the PPTA during 2013-2014, in which a team of national
consultants prepared a feasibility study for a water resources project for erstwhile
FATA. Based on the findings of the PPTA and on the request of Government of
Pakistan, ADB approved, on 15th December 2014, the Federally Administered
Tribal Areas Water Resources Development Project (Project) contributing $42.97
million from ADB’s Special Funds. The Government will contribute $4.93 million as counterpart fund. The ADB and Government of Pakistan signed the legal
agreement on 17th April 2015 and declared the loan effective on 7th August 2015.
The Project implementation period ends on 31th March 2020 and loan accounts
will close on 30th September 2020.
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
ii | Executive Summary
Since the sub projects are categorized as a category B projects as per ADB’s Safeguards Policy Statement 2009, an Initial Environmental Examination (IEE)
exercise is done for sub projects.
2. Project Location
The Tor Dara and Tarkho Kas weir sub projects are proposed on Tor Dara nullah
and Mato nullah which are tributaries of Bara River and are located at a distance
of 100 Km and 79 Km respectively from Jamrud Khyber District Head Quarter.
The weirs location coordinates are provided in the table below:
Proposed Weirs Longitude Latitude
Tor Dara Weir 70.772° E 33.909° N
Tarkho Kas Weir 70.837° E 33.918° N
3. Environmental Issues
The main features of the sub projects include construction of weirs, irrigation
channels, retaining walls, fall structures, road culverts and drainage culverts, on-
farm water management works, improvement of ware sheds through forestation
and development of cultivable command area of 183 ha. This will cause some
disturbance due to construction activities within the RoW at site and the allied
sites involving borrow material, camp area, material and machinery yard and
necessary facilities for the staff and labor to be engaged for the execution of the
sub projects.
4. Policy Legal and Administrative Framework
This report represents in accordance to Khyber Pakhtunkhwa Environmental
Protection Act, 2014 and the Asian Development Bank’s Safeguard Policy Statement (SPS) 2009 requires that environmental considerations be
incorporated into ADB’s funded project to ensure that the project will have minimal environmental impacts and be environmentally sound. Occupational
health & safety of the local population should also be addressed as well as the
project workers as stated in SPS 2009. Because these sub projects fall in the
jurisdiction of Provincial EPA, therefore an approval from the KP EPA will be
required.
5. Project Description
Tor Dara Weir and Natu Khel Weir are proposed to collect water from Tor Dara
Nullah and its tributary and to convey the available flows to the command area
laying at both right and left side of Tor Dara Nullah. Gross command area is 96
ha and Cultivable Command Area is 93 ha, which is proposed to be irrigated at
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
iii | Executive Summary
cropping intensity of 100 % with the design discharge of 22.90 lit/sec and 6.45
lit/sec for Tor Dara and Natu Khel Weir respectively.
The project cost of Tor Dara weirs is estimated as Rs. 93.804 million and is
anticipated to take 12 months period to complete. The results of the economic
analysis show that the sub project is economically viable (EIRR 12.03 %). The
financial analysis also indicates the safe investment with FIRR as 10.23 %.
Tarkho Kas Weir is proposed to collect water from Matu Nullah and carry it to
the command area. Cultivable Command Area of 90 ha will be irrigated at
cropping intensity of 100 % and design discharge of 28.9 lit/sec. Total length of
irrigation network is 5290 m.
The project cost of Tarkho Kas weir is estimated Rs. 64.577 million and
anticipated to take 12 months period to complete. The results of the economic
analysis show that the project is economically viable (EIRR 12.23 %). The
financial analysis also indicates the safe investment with FIRR as 10.33 %.
6. Project Alternatives
Project alternatives have been considered with consideration of their ability to
match immediate demand and then keep pace with emerging demand while
ensuring capture of available yield in the stream. Technically there is no other
source of water or place at Tarkho Kas diverting water for irrigation purposes.
However, different siting alternatives including construction of small concrete
gravity dam were studied for Tor Dara sub project which were discarded on
technical and social basis.
The sub project area is considered as poor from an economic perspective.
Subsistence farming is the economic mainstay. Water availability is scarce in
area hence the proposed project will contribute positively to the project area.
Therefore, no project option is not viable option.
Various technical alternatives including conventional weir were also considered
and the most viable option Tyrolean weir was adopted.
7. Environmental and Social Baseline
The purpose of this chapter is to establish the baseline conditions for the
physical, biological and the social aspects of the environment of the sub projects
area. The data were collected of the study area from field surveys, desk studies
and visits to the Government Departments, other relevant agencies, and
discussions with the main stakeholders of the area.
8. Physical Environment
Khyber District is one of the eight newly merged districts in KP. It ranges from
the Tirah valley down to Peshawar. It borders Nangarhar Province of
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
iv | Executive Summary
Afghanistan to the west, Orakzai Tribal District to the south, Kurram Tribal
District to south west and Peshawar to the east.
The topography of this area is prevailingly hilly, with rugged barren mountainous
terrain, including narrow strips of bottom valleys and sub valleys. An interesting
feature in the topography is a mountain spur from the Kunar range, which,
curving eastwards culminates in the well-known peak of Koh-i-Mor, which is
visible from the Peshawar valley.
Agriculture is limited in the region due to rocky soils, steep slopes, lack of
suitable land and limited water supply. Scanty shrub vegetation along slopes
and other areas are used as grazing and fuel wood gathering. The sub projects
area has forest cover of 61.9%, sparse forest is 10.7%, range land is 16.0%
while barren land is 11.4%.
Tor Dara and Matu nullah / stream, where the sub projects will be constructed
are left side tributaries of Bara River. The sub projects area falls in the temperate
and warm climatic zone associated with 600-800 mm of annual precipitation.
Soil of the area are loam, non-calcareous, non-saline and non-sodic in nature.
Soil pH is slightly alkaline. The soils are low in organic matter and nitrogen
contents, medium in phosphorus while sufficient in potassium contents.
The sub projects area experiences two rain seasons: winter and summer. Water
supply is from rainfall, snow melt and groundwater during the dry periods. The
source of water supply in the sub projects area is springs. Both the drinking
water and stream water is fit for drinking and irrigation respectively with
exception of turbidity which is exceeding the NEQS.
The ambient air quality and noise testing results reveals that the air quality and
noise of the area is within the permissible limits of NEQS.
9. Biological Environment
Ecologically, this area falls within the main group of Dry Subtropical Broad-
leaved Forest. The sub–group is Monotheca Scrubs. Generally, the vegetation
is thorny evergreen shrubs, which are capable of developing into small trees,
even under harsh climatic conditions and social pressure (heavy grazing
/browsing).
The main tree species are Querons ilex ( Kharpata Cherai), Olia europea
(Khomunor Khowand), Morus alba (Tooth), Olea cuspidate (wild olive), Salix
(Wula), Juglans regia (Akhrot), Punicis grantsum (Anar), Amygdalus persica
(Mandatas), Pyrus pyrifolia (Nashpati)..
Similarly, there are no evidences of any animal species apart from the common
cats, dogs, wild boars, brown monkey and jackals etc.
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
v | Executive Summary
Avifauna of the area is highly diversified and colorful, which is widely dispersed
in gardens, cultivated fields, streams and hill slopes. No threatened or
endangered species were observed in the sub projects area, as per IUCN red
list classification of 2017.
10. Socio-Economic and Cultural Aspects
Khyber Tribal District is bordered with Afghanistan, Peshawar city and the
Kurram and Orakzai Tribal Districts. The total area of the District is 2,5761
square kilometers, with 0.8% of the total area of the district being forest. The
Khyber Tribal District consists of four tehsils; Bara, Landi Kotal, Jamrud and
Mullagori.
Until 2018, it was an agency of Federally Administered Tribal Areas, with merger
of FATA with Khyber Pakhtunkhwa, it became a district. The 25th amendment
received assent from President of Pakistan on 31 May 2018, after which FATA
was officially merged with Khyber Pakhtunkhwa.
The Khyber Tribal District had a unique governance status in the past, whereby
all land is owned by tribes inhabiting the areas since generations. No revenue
record of lands is available or maintained.
The communities of the sub projects area lead their lives under strict tribal code
and cultural practices. The traditional tribal governance structure of local Maliks
(tribal chiefs), Jirga (committee of tribal elders) is in place. The main ethnic
groups in the Khyber District are Pashtuns. The four main tribes of Khyber
District are; Afridis, Shinwaris, Mollagoris, and Shilmanis.
The population of the district, according to the 2017 census is 986,9732 with an
average annual growth rate 3.15. The sub projects sites are situated in the
remote area of Tirah valley in Tehsil Bara. Afridis are the main tribe of the sub
projects area and are further sub divided into Koki Khel/Abdal Khel and Qambar
Khel sub tribes.
The people in the sub projects area are not widely educated. They migrate to
down districts in search of jobs or any other labour. The former FATA region has
historically remained amongst the poorest parts of Pakistan. There are serious
disparities in service provision as compared to the rest of the country. The
absence of visible progress and the perceived lack of interest by both sub-
national and federal governments in redressing the disparities have
consequently deteriorated citizens’ trust in the ability of government institutions
1 "DISTRICT AND TEHSIL LEVEL POPULATION SUMMARY WITH REGION BREAKUP [PDF]" (PDF). www.pbscensus.gov.pk. 2018-01-03. Retrieved 2018-03-25. 2http://www.pbs.gov.pk/sites/default/files/DISTRICT_WISE_CENSUS_RESULTS_CENSUS_2017.pdf
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
vi | Executive Summary
to meet the basic needs of the population. The militancy crisis in KP and former
FATA is a key contributor to stagnant growth and high unemployment.
Tribal identity along with gender and age are the key factors in determining
power and influence. The identity of women is drawn from that of their male
relative as next of kin–father, brothers or husband. Women had no significant
role in decision-making, even if decisions directly affect their lives.
11. Public Consultation
The public consultation process with various stakeholders has been carried out
to create awareness, information dissemination and to involve them in the
designing, planning and execution of sub projects. The viewpoints of the
stakeholders have been taken into account and their concerns and suggestions
for possible improvements have been included where appropriate.
During the field survey, significant efforts were made to identify the possible
categories of stakeholders. Stakeholders at site were notified villagers, local
residents, government officials, shop owners, public representative, NGO’s and
general public. All those stake holders had different types of stakes according to
their professions.
Tribal society is dominated by men with final say in the affairs of all members
of the family. Women, by comparison, play a subservient role and observe
strict purdah (veiling). They are for the most part restricted to performing
household work, and are excluded from decision-making both on the domestic
front and at the community level. Keeping in mind the above background,
women of the subproject area were not consulted.
The people of the area were briefed about the both negative and positive
impacts of the subproject during construction. They responded that the
negative impacts like noise and dust are very minor and temporary issues as
compared to the positive impacts, which will help them to improve their
socioeconomic conditions.
12. Environmental Impact Assessment and Mitigation Measures
The Initial Environmental Examination (IEE) study has revealed that the sub
projects are not likely to have any severe negative impacts on the environment
and people of the area. All the potential impacts which have been identified
during the present assessment are associated with the construction stage of the
subproject, and minor to moderate in severity; and can easily be avoided
(through good design and construction planning) or mitigated (through proper
implementation of the EMP).
No acquisition of permanent land will be involved. There is no such adverse
environmental impact of the sub projects but the construction-related impacts
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
vii | Executive Summary
such as air pollution, noise and use of community resources can be well
managed through proper implementation of the mitigation measures, which
have been identified in this report. Also, there is no environmentally sensitive
area in the vicinity of the sub projects area.
Women headed households has not been identified and no indigenous people
impacts are involved in the proposed sub projects. The other social issues like
safety of general public and workers, security problems, risk of communicable
diseases, vector borne diseases etc. are of temporary nature.
On the other hand, the subproject will create job opportunities particularly for the
local population during construction stage and extremely beneficial for the uplift
of socio-economic condition of the local population through irrigated agriculture
i.e. development of 183 ha culturable land.
13. Environmental Management Plan
Environmental Management Plan (EMP) is produced as a complementary part
of Detailed Design and is a free- standing document. It ensures incorporation of
the relevant environmental factors into the overall sub projects design and will
identify linkages to other safeguard policies relating to the project.
The EMP defines roles and responsibilities for the implementation of mitigation
measures in order to minimize or control negative impacts of construction and
operational of the project, as well as defining a framework and responsibilities
for the monitoring of each mitigation measure. The EMP shall implemented
throughout the construction period by the contractor. The EMP shall be
supplemented by Site Specific Environmental Management Plan (SSEMP) to be
prepared by the contractor upon mobilization. Based on the preliminary
assessment, key mitigation measures recommended under this Environmental
Management Plan (EMP), the Contractor will submit the Site-Specific
Environmental Management Plan (SSEMP) to the CSC and PMU for approval
at least ten (10) days prior to commencement of any physical works. Overall
responsibility for Environmental Management and Monitoring will rest with the
Project Management Unit (PMU) which is headed by a Project Director (PD) and
assisted by the CSC.
14. Conclusion and Recommendations
The assessment of potential impacts of the proposed Tor Dara and Tarkho Kas
weir sub projects reveals that these sub projects will generate only minor to
moderate adverse environmental impacts. These adverse impacts will be mostly
confined to the construction works and will be temporary in nature. The predicted
adverse impacts will be minimized and reduced by timely execution of the
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
viii | Executive Summary
prescribed mitigation measures and will be continually monitored by
implementing and updating the EMP.
The overall finding is that the beneficial gains provided by irrigation sub projects
will by far exceed the negative impacts – most of them being short-termed and
without major interference to both the bio-physical and human environment. It is
emphasized that the success of the EMP depends on the respective line
agencies and institutions identified as key players in the implementation of the
EMP. The timely and complete inclusion of the EMP’s compliance clauses with
allocated cost in the Contractor bidding documents is mandatory to ensure the
successful implementation of all environmental safeguard measures.
As the sub projects are exclusively an irrigation system, all identified adverse
environmental impacts during the rehabilitation and improvement works of the
sub projects will be of minor nature, easily to be mitigated by adequate
implementation of the Environmental Management and Monitoring Plans. Entire
command of the sub projects components does not include any environmentally
sensitive areas. The final conclusion is that, the sub projects are environmentally
safe and socially acceptable.
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
9 | Initial Environmental Examination
INTRODUCTION
General
1. The environmental study is undertaken in accordance with Khyber Pakhtunkhwa
Environmental Protection (Amendment) Act 2014 and Asian Development Bank`s
(ADB) Environment Safeguards Policy Statement (SPS), 2009 requirement and
recommendations.
2. The study Terms of References (TOR) requires that an assessment of the
environmental impacts of the sub projects (i.e. IEE or EIA), preparation of the
environmental management plan (EMP), inclusion of costs for implementing
recommended mitigation measures, and any capacity strengthening measures in
the project development costs.
Project Background
3. The merged districts of Khyber Pakhtunkhwa (KP) have scarcity of land and water
resources. In spite of the land scarcity, the people are agriculturalist and livestock
herders by occupation and practice agriculture. Encouraged by the salutary
effects of schemes in water sector, the Khyber Pakhtunkhwa Planning &
Development Department has proposed to harvest the flood water in the streams
by constructing small dams to bring more areas under irrigation and to recharge
aquifer for supplementing groundwater reserve. Therefore, main focus in recent
years has been the construction of dams to conserve water in order to expand
and intensify irrigated agriculture. The irrigated agriculture has evolved over many
centuries and today, despite the decades of civil strife, there are still thousands of
hectares being irrigated by traditional systems, which are managed, operated and
maintained by communities with little or no involvement of the government.
However, there is considerable opportunity for increasing agricultural production
by construction of major infrastructure works, like construction of small dams,
diversion weirs, lining of water courses and increasing awareness about latest
farm practices and cropping patterns which are beyond the technical and financial
capacity of the farming communities.
4. FATA Water Resources Development Project (FWRDP) will be operational in the
tribal territories at the western borders of Pakistan with Afghanistan. It focuses on
increasing irrigation supplies in three tribal districts, namely Mohmand, Khyber
and Bajaur, to increase crop production and harvest water sustainability. The
project is being proposed as a result of the Water Assessment Study executed
under the completed ADB supported FATA Rural Development Project of former
FATA Secretariat. The study identified 40 watersheds where the groundwater
aquifers are depleting at a high rate, even under average weather conditions due
to unplanned water extraction for irrigation and other associated purposes. It
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
10 | Initial Environmental Examination
recommends shifting from groundwater to surface water, which remains totally
unutilized, and identified potential sites for small reservoirs and diversion weirs in
the 40 watersheds of Mohmand, Khyber and Bajaur Tribal Districts of KP.
5. With above background, ADB financed a Project Preparatory Technical
Assistance, TA 8409-PAK (PPTA) for FATA Water Resources Development
Project in preparing a project for financing consideration by ADB through former
FATA Secretariat support implemented the PPTA during 2013-2014, in which a
team of national consultants prepared a feasibility study for a water resources
project for erstwhile FATA. Based on the findings of the PPTA and on the request
of Government of Pakistan, ADB approved, on 15th December 2014, the Federally
Administered Tribal Areas Water Resources Development Project (Project)
contributing $42.97 million from ADB’s Special Funds. The Government will contribute $4.93 million as counterpart fund. The ADB and Government of
Pakistan signed the legal agreement on 17th April 2015 and declared the loan
effective on 7th August 2015. The Project implementation period ends on 31th
March 2020 and loan accounts will close on 30th September 2020.
6. The Tor Dara and Tarkho Kas weir sub projects are proposed on Tor Dara and
Matto Nullah/ Khwars respectively which are tributaries of Bara River and are
located at a distance of 95 km from Jamrud Khyber District Head Quarter. As per
site observation there is perennial flow exist in the Nullah/Khwar/stream.
Project Consultants
7. The Proponent / client, FATA Water Resources Development Project, former
FATA Secretariat entered into a formal contract in October, 2016 with design and
supervision consultants for the project with joint venture, led by BAK Consulting
Engineers, AGES Consultants and Rehman Habib Consultants.
Purpose of This Initial Environmental Examination (IEE)
8. The purpose of the IEE is:
• Establish preconstruction environmental baseline of the subproject for
construction and operation phases impacts evaluation.
• Predict positive and adverse impacts.
• Find ways to minimize/manage adverse impacts.
• Enhance positive effects.
IEE Methodology
9. In the present study, standard methods were followed for Environmental and
Social Impact Assessment. All the methods were structured for collection and
organization of environmental baseline data and identification of environmental
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
11 | Initial Environmental Examination
impacts using different survey tools and discussions with different stakeholders.
The information, thus gathered, has been analyzed and presented in the form of
a number of visual formats for easy interpretation and decision making.
10. The baseline data was developed and analyzed to identify potential environmental
impacts of the sub projects. A Rapid Environmental Assessment (REA) Checklist
(Annex-I) methodology was adopted to identify the high-risk activities and suggest
their mitigation measures. Where possible, eliminating the risk by altering the
scope or method of execution of work was preferred rather than minimizing the
risk with control measures.
11. The Social Assessment (SA) has been conducted to evaluate the sub projects
potential positive and adverse effects on the affected people and to examine sub
projects alternatives where adverse effects may be significant. The width, depth
and type of analysis in the social assessment are proportional to the nature of the
sub projects and scale of its potential effects, positive or adverse, on the affected
people.
Study Area
12. The study area related to IEE of the project comprised the following areas and
features / aspects:
i. Primary impacts zone, where the proposed sub projects components,
including “the area of weir, along the alignment of the proposed irrigation system, Contractor’s camp and construction material storage area.
ii. The secondary impact zone is the command area of the sub projects, where
beneficial impacts are anticipated as with the availability of water, the
cultivated area will be increased and cropping pattern will be changed as
well as intensified.
Baseline Survey Methodology
13. A survey was carried out in the sub projects area for field studies including
physical, biological and social impact assessment in April and May, 2019. The
visit was made to the project area to understand the terrain, environment and
social issues, and vegetation of the study area. During the visit, the preliminary
interpreted data were tested and necessary corrections made after proper ground-
truthing. The physiographic features on the satellite imagery appearing in different
tones and textures were used to correlate image elements and ground features
for accurate identification.
14. The purpose of the site visits was to familiarize with the physical, biological and
socioeconomic environment of the proposed project area and the areas in the
vicinity. Critical areas with respect to environmental and social concerns were
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
12 | Initial Environmental Examination
identified and assessment of positive as well as adverse impacts of the project on
the environment was done. A summary of the main activities undertaken during
the visit has been enlisted below:
i. Collected information and required data from the project area for
preparation of Initial Environmental Examination (IEE) report.
ii. Identified site-specific issues of microenvironment of the proposed
project.
iii. Information obtained regarding existing infrastructure in and around
the project area.
iv. Requirements of necessary mitigation measures to be integrated
into the overall plan were identified.
v. Consultations were held with the population settled in the vicinity of
the project.
vi. Survey of nearby environmental sensitive receptors was carried out.
vii. Interviews with the locals for the presence and relative abundance
of various animal species within each locality were also taken for
firsthand information.
viii. Data collection was carried out on habitat condition, animal
presence by direct sighting and indirect evidences.
15. Spatial data base on the physiographic features was prepared based on the
various data sources including survey map of the sub projects and topographic
sheets. These data were extracted and presented in accordance with the standard
IEE methodology used for such studies.
16. The section on climatology has been taken from the Project Hydrology Report
made by project hydrologists.
17. The regional geology and seismo-tectonics of the region are discussed based on
the various available data sources and reports. Particularly, the discussion on
project geology has been based on the data available in the Project Geology
Report and field observations made in selective pockets of different project
affected sites.
18. Land use and land cover mapping was carried out by standard methods of
analysis of remotely sensed data followed by ground truthing.
19. Forest types and plant species were recorded during the field visits and the floristic
data for the catchment were sourced from the published literature. Based on the
field data and available literature, frequency, density and cover of each species
were calculated.
20. Ecological status of species was identified as per IUCN Red list, 2017 and other
available literature.
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
13 | Initial Environmental Examination
21. In order to collect the information on the fauna (mammals, avifauna, herpetofauna)
in the area, primary as well as secondary sources were utilized.
22. The environmental testing (air, noise and water) at about 10 m distance from main
proposed construction site has been carried out to determine the baseline
conditions of the area (Annex-II).
Impact Assessment Methodology
23. Prediction of impacts has been based on a broad matrix group ‘ecosystem’ constituted by physical and biological components. The vulnerability of an
ecosystem to various impacts resulting from an activity or multiple activities was
identified and accordingly impacts predicted. The main theme of the ecosystem
approach in visualizing impacts on various sets of environmental data revolves
around the idea that natural processes and patterns are likely to be affected under
impacts of a developmental activity.
24. In natural ecosystems, the impacts would surely change the existing state of
equilibrium. In managed ecosystems and human societies, impacts could be of
positive as well as adverse consequence. Similarly, in case of natural ecosystems,
likelihood of adverse impacts could be seen in terms of direct and/or indirect,
temporary or permanent impacts.
25. In the absence of long-term data availability on various environmental variables
and also the paucity of studies on their likely responses to changes under
developmental activities, it is difficult to predict impacts with a high degree of
exactness and certainty. For example, it will not be possible to predict impacts of
such a developmental activity on the behavioral patterns of animal and bird
populations except for the fact that their habitats may come under stress. In that
sense these predictive impacts could be said to have a limitation.
26. The potential impacts at various stages of the project were predicted, identified
and assessed according to their category of impact. They were classified as
negligent, moderate or high. Each category is defined as under;
Negligible: No or minimum impact
Moderate: Potential impact but can be mitigated (Site Specific)
High: significant adverse environmental impacts that are irreversible, diverse, or
unprecedented
27. The moderate to high impacts were further described and mitigation measures
were suggested accordingly.
28. The mitigation measures and environmental monitoring have been worked out in
the light of environmental impacts assessed. Interviews, field visits/surveys,
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
14 | Initial Environmental Examination
scoping sessions with officials/notables and concerned stakeholders were also
made for the accomplishment of the study.
Report Format
Chapter A: Introduction consists of the background; project needs and
objectives. It also explains the methodologies adopted for
carrying out different environmental and socio-economic
studies.
Chapter B: The legal and institutional framework section provides in
detail, an overview of the government laws and rules that
apply to regulate and control the environmental impacts due
to project implementation, operation and maintenance,
together with the relevant guidelines, legislation and policies
concerning the project.
Chapter C: It provides details of the project components and study of
different project alternatives. This chapter also includes, route
selection studies to select most viable route with maximum
socio-economic benefits with minimum environmental
adverse impacts.
Chapter D: It describes the baseline conditions like physical, biological
and socioeconomic, and surrounding area people. It also
provides information about the existing amenities like
education, health, infrastructure, cultural heritage, water
supply/availability, electricity, etc. in the area.
Chapter E: It describes the different alternative options studied for placing
the weir axis and type including No Project Option. Different
options were considered and evaluated on the basis of
technical, economic, social and environmental parameters. It
also provides the justification of current weir axis.
Chapter F: It provides the project impacts, both positive and
negative/adverse, on the land, land-based assets,
infrastructure, crops, forest and fruit trees, existing amenities,
sewage, waste material generation etc. due to the
construction of the project. This section also deals with the
mitigation of the adverse impacts identified in the shape of the
compensation, rehabilitation, capacity building, provision of
livelihood resources and other needed amenities etc.
Chapter G: This chapter ensures that healthy and friendly environment is
created during the construction, operation and maintenance of
the project by adopting effective Environmental Management
Plan (EMP).
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
15 | Initial Environmental Examination
Chapter H: This chapter deals with consultation with different
stakeholders of the project as well as the study area.
Chapter I: This chapter covers the Grievance Redress Mechanism from
stakeholders and general public, and also includes required
actions taken on any issue raised by them during construction
or operational phases of the project.
Chapter J: It summaries the positive and adverse impacts, mitigation
measures of the adverse impacts and main recommendations
based on the studies carried out and
discussions/consultations with the affected persons, other
stakeholders and notables of the project area.
Project Categorization
29. According to ADB Safeguard Policy Statement 2009, projects are to be
categorized into three environmental categories; A, B, or C. All the anticipated
adverse environmental impacts of the project can be mitigated, are of temporary
nature and localized, except a few adverse impacts which are long term and will
be managed/minimized through implementation of the Environmental
Management Plan. The REA Checklist defines these sub project in category “B” as per ADB’s guidelines for project categorization.
IEE Team
30. The IEE team for Tor Dara and Tarkho Kas weir sub projects consists of the
following.
➢ Mr. Shabir Ahmad Khan Environment Specialist
➢ Mr. Ihsan Afridi Environmentalist
➢ Mr. Farhan Environmentalist
➢ Mr. Ibad Ullah Sociologist
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
16 | Initial Environmental Examination
POLICY, LEGAL AND ADMINISTRATIVE FRAMEWORK
General
31. This section provides an overview of the policy framework and national legislation
that applies to the proposed sub-project. The project is expected to comply with
all national legislation relating to environment in Pakistan and ADB`s Environment
Safeguards Policy Statement (SPS) 2009.
National Policy and Legal Framework
32. National Environmental Policy (NEP) is the primary policy of Government of
Pakistan addressing environmental issues. The broad Goal of NEP is, “to protect, conserve and restore Pakistan’s environment in order to improve the quality of life
of the citizens through sustainable development”. The NEP identifies a set of sectorial and cross-sectoral guidelines to achieve its goal of sustainable
development. It also suggests various policy instruments to overcome the
environmental problems throughout the country.
33. Prior to the adoption of the 18th Constitutional Amendment, the Pakistan
Environmental Protection Act (PEPA) 1997 was the governing law for
environmental conservation in the country. Under PEPA 1997, the Pakistan
Environmental Protection Council (PEPC) and Pakistan Environmental Protection
Agency (EPA) were primarily responsible for administering PEPA 1997. After the
adoption of the 18th Constitutional Amendment in 2011, the subject of environment
was devolved and the provinces have been empowered for environmental
protection and conservation.
The Khyber Pakhtunkhwa Environmental Protection Act, 2014
34. The Khyber Pakhtunkhwa Environmental Protection Act, 2014 is the basic
legislative tool empowering the provincial government to frame regulations for the
protection of the environment. The act is applicable to a broad range of issues and
extends to air, water, soil and noise pollution, as well as to the handling of
hazardous substance. The key features of the law which are directly related to the
proposed project area are:
Section-11: Prohibition of certain discharges or emissions:
(1) "Subject to the provisions of this Act and the rules & regulations made there
under no person shall discharge or emit or allow the discharge or emission
of any effluent or waste or air pollution or noise in an amount, concentration
or level which is in excess of the National Environmental Quality Standards.”
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
17 | Initial Environmental Examination
Section-13: Initial Environmental Examination and Environmental Impact
Assessment:
(1) "No proponent of a project shall commence construction or operation unless
he has filed with the Federal Agency an Initial Environmental Examination (IEE)
or, where the project is likely to cause an adverse environmental effect, an
Environmental Impact Assessment (EIA), and has obtained from the Federal
Agency approval in respect thereof".
Section-14 and 15: Prohibition of Import of Hazardous Waste and Handling
of Hazardous Substances:
No person shall carry, import, bring, transport or deliver hazardous waste or
cause to carry, import, bring, transport or delivery of hazardous waste into the
territorial jurisdiction of the Province of the Khyber Pakhtunkhwa.
Subject to the provisions of this Act, no person shall generate, collect, consign,
transport, treat, dispose of, store, handle, deal in and use or import any
hazardous substance except:
(a) under a license issued by the Agency and in such manner, as may be
prescribed; or
(b) in accordance with the provisions of any other law for the time being in force,
or of any International Treaty, Convention, Protocol, Code, Standard, Agreement
or other instrument to which Pakistan or the Province of the Khyber Pakhtunkhwa
is a party.
Regulations for Environmental Assessment, Pakistan EPA
35. Under Section 12 of the Pakistan Environmental Protection Act 1997 and section
13 of Khyber Pakhtunkhwa Environmental Protection (Amendment) Act 2014, a
project falling under any category specified in Schedule I (SRO 339, 10/2000)
requires the proponent to file an Initial Environment Examination (IEE) report with
concerned provincial or federal Environmental Protection Agency (EPA). Projects
falling under any category specified in schedule II, the proponent shall submit an
EIA with the Provincial or federal Agency, in this case Khyber Pakhtunkhwa
Environmental Protection Agency (KP-EPA) Peshawar as the sub projects are
located in KP within 10 working days of IEE or EIA having been deposited, the
concerned agency will confirm that the document submitted is complete for the
purpose of review. During this time should the empowered agency require the
proponent for revision, clearly citing those aspects that need further discussion
the proponent will carry out necessary revision. Subsequently, the concerned
agency will make every effort to complete the process for an IEE review within 45
days and an EIA within 90 days of filing and issue a “No-Objection Certificate” to the project proponent.
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
18 | Initial Environmental Examination
Regulatory Clearances, EPA
36. In accordance with regulatory requirements, an IEE/EIA satisfying the
requirements of the Khyber Pakhtunkhwa Environmental Protection Act is to be
submitted to KP Environment Protection Agency for review and approval, and
subsequent issuance of NOC before the commencement of construction.
Guidelines for Environmental Assessment, Pakistan EPA
37. The Pak-EPA has published a set of environmental guidelines for conducting
environmental assessments and the environmental management of different
types of development projects. The guidelines that are relevant to the proposed
sub-project are listed below:
• Guidelines for the Preparation and Review of Environmental Reports, Pakistan, EPA1997;
• Guidelines for Public Consultations; Pakistan EPA May 1997;
Pakistan Environmental Protection Agency Review of IEE and EIA
Regulations, (2000)
38. The Regulation classifies projects on the basis of expected degree of adverse
environmental impacts and lists them in two separate schedules. Schedule I lists
projects that may not have significant environmental impacts and therefore require
an IEE. Schedule II lists projects of potentially significant environmental impacts
requiring preparation of an EIA. The Regulations also require that all projects
located in environmentally sensitive areas require preparation of an EIA. It also
lists projects not requiring either an EIA or an IEE.
National Environmental Quality Standards (NEQS)
39. The National Environmental Quality Standards (NEQS) were first promulgated in
1993 and have been amended in 1995 and 2000. They have been revised and
the latest NEQS were issued in 2010.These standards are also correlating with
the International Regulation. The following standards that are specified in the
NEQS are relevant to the proposed sub projects.
• NEQS for Ambient Air – November, 2010 state the maximum allowable
concentration of air pollutants
• NEQS for Drinking Water Quality – 2010 describe the drinking water
properties by outlining the defined physical and chemical parameters.
• NEQS for vehicle exhaust –2000 maximum allowable concentration of
pollutants (02 parameters) in gaseous emissions from vehicle exhaust and
noise emission from vehicles
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
19 | Initial Environmental Examination
• NEQS for Noise – November 2010 states the maximum allowable limit of
noise arising from vehicles in decibels (dB) separately for day and night
times.
• NEQS for Waste Effluents –2000 states the Maximum allowable
concentration of pollutants (32 parameters) in municipal and liquid
industrial effluents discharged to inland waters, sewage treatment facilities
and the sea.
• These standards apply to the gaseous emissions and liquid effluents
discharged by, campsites and construction machinery. The standards for
vehicles will apply only during the construction phase of the Sub Projects.
Standards for ambient air quality have also been prescribed. (Reference
Annex III for NEQS).
Comparative Analysis of the National and International Standards
40. A comparison of applicable local and international guidelines for air quality has
been provided in Table 2.1 In general, the NEQS standards for air quality are most
stringent in comparison to USEPA, WHO and the World Bank standards. The only
exception is the TSP parameter for the annual mean where the World Bank
standard (100 ug/m3) is more stringent than the NEQS standard (360 ug/m3).
Apart from this one exception, the NEQS standards will also be used for the
proposed project.
41. Similar to the standards for air quality, the comparison of noise standards provided
in Table 2.2 clearly shows that NEQS standards for noise in case of commercial
areas are more stringent in comparison to the World Bank/IFC standards. In case
of night time standards for the residential areas, the IFC/WHO standards are more
stringent as compared to Pak NEQS. Apart from this one exception, the NEQS
will be used for the proposed project.
42. A comparison of National Standards for Drinking Water Quality (NSDWQ),
Pakistan and World Health Organization (WHO) are given in Table 2.3. Maximum
Allowable limits of all of the contaminates are almost same except for Lead &
Arsenic. The NSDWQ will be used for the proposed project.
43. Guidelines of Irrigation water quality for Pakistan (proposed by WWF 2007) is
provided in Table 2.4 (a) & (b) to consider for this project.
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
20 | Initial Environmental Examination
Table 2.1 Comparison of International and local Air Quality Standards
Pollutants
USEPA3 WHO4 World Bank5 Pak. NEQS
Avg. Time
Standard Avg. Time
Standard Avg. Time
Standard Avg. Time
Standard
SO2 1 hr
3hrs
Primary- 75 ppb
Secondary- 0.5 ppm (1,300 μg/m³)
24-hour mean
20 μg/m3
Annual Mean
125 (Interim target-1)
50 (Interim target-2)
20 (guideline)
Annual Average
80 ug/m3
10-minute mean
500 μg/m3
24 hrs 120
ug/m3
10 minutes
500 ug/m3
CO
1 hr
8 hrs
Primary 35 ppm
(40 mg/m³)
Primary 9 ppm
(10 mg/m³)
8 hrs
10 mg/m3
(8.7 ppm)
- -
8 hrs 5 mg/m3
40 mg/m3 1 hr 10
mg/m3
1 hr
NO2 Annual Mean
Primary & Secondary- 0.053 ppm
(100 μg/m³)
annual mean
1-hour mean
40 μg/m3
200 μg/m3
Annual Mean
40 (guideline)
200 (guideline)
Annual Average
40 ug/m3
24 hrs 80 ug/m3
O3
1 hr
8 hrs
Primary & Secondary- 0.12 ppm
(235 μg/m³)
Primary &
Secondary- 0.070 ppm
(140 μg/m³)
- - 1 hr 130
ug/m3 8 hrs mean
100 μg/m3
TSP 24 hrs 260 ug/m3 24 hrs 150-230 ug/m3
Annual Mean
100 ug/m3 Annual Mean
360 ug/m3
24 hrs 500 ug/m3 24 hrs 500
ug/m3
PM10 24 hrs annual mean
20 μg/m3
1 year
Annual Mean
120 ug/m3
3 Source- https://en.wikipedia.org/wiki/National_Ambient_Air_Quality_Standards retrieved on 15th January, 2018. 4 Source-http://www.who.int/mediacentre/factsheets/fs313/en/ retrieved on 15th January, 2018. 5 Source-IFC Environmental, Health, and Safety Guidelines-GENERAL EHS GUIDELINES: ENVIRONMENTAL AIR EMISSIONS AND AMBIENT AIR QUALITY, April 2007.
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
21 | Initial Environmental Examination
Pollutants
USEPA3 WHO4 World Bank5 Pak. NEQS
Avg. Time
Standard Avg. Time
Standard Avg. Time
Standard Avg. Time
Standard
150 μg/m³
Primary and
Secondary
24-hour mean
50
μg/m3
24 hours
70 (Interim target-1) 50 (Interim target-2) 30 (Interim target-3)
20 (guideline)
150 (Interim target-1) 100 (Interim target-2) 75 (Interim target-3)
50 (guideline)
24 hrs 150
ug/m3
PM2.5
-Annual
Annual
24 hrs
-Primary 12 μg/m³
Secondary 15 μg/m³
Primary & Secondary 35 μg/m³
annual mean
24-hour mean
10 μg/m3
25 μg/m3
- -
Annual Average
15 ug/m3
24 hrs 35 ug/m3
1 hr 15 ug/m3
Note: I ug/m3 = 0.002ppm
Table 2.2: Comparison of International and local for Noise-Limit in dB(A) Leq
NEQS (Effective form July, 2012) IFC & WHO
S.No Category of
Area/Zone
Day time Night time Receptor Day time
(7-00:22-
00)
Night time
(22:00-7:00)
1 Residential Area (A) 55 55 Residential;
institutional;
educational6
55 45
2 Commercial Area (B) 65 45 Industrial;
commercial
70 70
3 Industrial Area (C) 75 65
6 For acceptable indoor noise levels for residential, institutional, and educational settings refer to WHO (1999).
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
22 | Initial Environmental Examination
4 Silence Zone (D) 50 45
Table 2.3 Comparison of International and local Standards for Drinking Water
Sr. No.
Parameter Unit WHO
Guidelines
National Standards for Drinking Water
Quality
Biological Analysis
1. Total Coliform No./100ml 0/100 ml 0
2. E. Coli No./100ml 0/100 ml 0
3. Fecal E. Coli No./100ml 0/100 ml 0
Chemical Analysis
4. pH - 6.5 – 8.5 6.5 – 8.5
5. Temperature 0C - -
6. Color TCU <15 <15
7. Taste …. Not Objectionable Not Objectionable
8. Odour ouE/m³ Not Objectionable Not Objectionable
9. Turbidity NTU <5 <5
10. Electrical Conductivity
µS NA NA
11. Total Hardness mg/l <500 <500
12. TDS mg/l <1000 <1000
13. TSS mg/l NA NA
14. Ammonia mg/l NA NA
15. Arsenic mg/l 0.01 <0.05
16. Iron mg/l NA NA
17. Aluminum mg/l - <0.2
18. Sodium mg/l NA NA
19. Chloride mg/l NA NA
20. Sulphate mg/l 0.01 <0.05
21. Fluoride mg/l <1.5 <1.5
22. Nitrate mg/l <50 <50
23. Nitrite mg/l 3 3
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
23 | Initial Environmental Examination
Sr. No.
Parameter Unit WHO
Guidelines
National Standards for Drinking Water
Quality
24. Cadmium mg/l 0.003 0.01
25. Chromium mg/l 0.05 <0.05
26. Copper mg/l 2.0 2.0
27. Manganese mg/l 0.5 <0.5
28. Nickel mg/l 0.02 <0.02
29. Lead mg/l 0.01 <0.05
30. Zinc mg/l 3.0 5.0
NA: Not Applicable
Table 2.4 (a) Criteria for Irrigation Water7
Explanation:
This class applies to the surface waters that are primarily used for agricultural irrigation.
SUBSTANCE OR
CONDITION
UNIT RECOMMENDED VALUE REMARKS
Sa
linity
Solids (TDS)
mg/L 1000
The values depend on various factors; can be relaxed. See table 2.4 (b) for details.
EC at 25 °C dS/m 1.5
SAR 5
RSC me/L 1.25
Boron mg/L 1.0
Chloride mg/L 100
pH Units 6.5 - 8.4
BOD mg/L 8.0
Dissolved Oxygen (D.O) mg/L >4.0
Coliform bacteria (fecal) No./100mL 1000
Aluminium mg/L 5.0
7 National Surface Water Classification Criteria & Irrigation Water Quality Guidelines for Pakistan Proposed by WWF - Pakistan through consultations with stakeholders Source: http://mocc.gov.pk/moclc/userfiles1/file/MOC/National%20Environment%20Quality%20Standards/National%20Surface%20Water%20Classification%20Criteria.pdf
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
24 | Initial Environmental Examination
Arsenic mg/L 0.10
Beryllium mg/L 0.10
Cadmium mg/L 0.01
Chromium mg/L 0.01
Cobalt mg/L 0.05
Copper mg/L 0.20
Cyanide mg/L 1.0
Fluoride mg/L 1.0
Iron mg/L 5.0
Lead mg/L 0.1 Livestock
Lithium mg/L 2.5
Manganese mg/L 0.20
Mercury mg/L 0.01 Livestock
Molybdenum mg/L 0.01
Nickel mg/L 0.20
Selenium mg/L 0.02
Vanadium mg/L 0.10
Zinc mg/L 2.0
Toxic substances and organic pollutants
The water should not contain toxic substances and other organic compounds in quantities that can accumulate in the soils to such a level as to result in the uptake by the crop and thus may be detrimental to public health or impair the quality of water for use in agriculture and livestock watering.
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
25 | Initial Environmental Examination
Table 2.4 (b) Conditions of Water Use and Irrigation Water Quality
Water Quality Guidelines Condition of Use
Water Quality Parameter Guideline Value
Salinity TDS or EC 2000mg/L or 3.0 dS/m Coarse textured soils
SAR 10
RSC 2.5 me/L
Salinity TDS or EC 1500 mg/L or 23 dS/m Medium textured soils
SAR 8
RSC 2.3 me/L
Salinity TDS or EC 1000 mg/L or 1.5 dS/m Fine textured soils
SAR 8
RSC 1.25 me/L
ADB’s Safeguard Policy Statement (SPS), 2009
44. The Asian Development Bank’s Safeguard Policy Statement (SPS) 2009 requires that environmental considerations be incorporated into all ADB funded projects to
ensure that the project will have minimal environmental impacts and is
environmentally sound. Health & safety aspects for the project workers and the
local population should also be addressed as stated in SPS.
45. All loans and investments are subject to categorization to determine
environmental assessment requirements. Categorization is to be undertaken
using Rapid Environmental Assessment (REA) checklists, consisting of questions
relating to (i) the sensitivity and vulnerability of environmental resources in sub
Projects area, and (ii) the potential for the sub projects to cause significant adverse
environmental impacts. Projects are classified into one of the following
environmental categories:
46. Category A: A project is classified as category A if it is likely to have significant
adverse environmental impacts that are irreversible, diverse or unprecedented.
These impacts may affect an area larger than the sites or facilities subject to
physical works. An Environmental Impact Assessment (EIA) is required.
47. Category B: A project is classified as category B if its potential adverse
environmental impacts are less adverse than those of category “A” projects. These impacts are site-specific, few, if any of them are irreversible, and in most
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
26 | Initial Environmental Examination
cases mitigation measures can be designed more readily than for category “A” projects. An Initial Environmental Examination (IEE) is required.
48. Category C: A project is classified as category C if it is likely to have minimal or
no adverse environmental impacts. No environmental assessment is required
although environmental implications need to be reviewed.
49. Category FI: A project is classified as category FI if it involves investment of ADB
funds to or through a financial intermediary (FI).
Access to Information Policy (AIP) 2018
50. ADB’s new Access to Information Policy (AIP), reflects the ADB’s ongoing commitment to transparency, accountability, and participation by stakeholders.
The policy contains principles and exceptions to information sharing with external
stakeholders, led by a new overarching principle of “clear, timely, and appropriate disclosure.”
ADB’s Accountability Mechanism Policy 2012
51. The objectives of the Accountability Mechanism is providing an independent and
effective forum for people adversely affected by ADB-assisted projects to voice
their concerns and seek solutions to their problems, and to request compliance
review of the alleged noncompliance by ADB with its operational policies and
procedures that may have caused, or is likely to cause, them direct and material
harm. The Accountability Mechanism is a “last resort” mechanism.
B.13 Project Categorization
52. As per the Rapid Environmental Assessment (REA) checklist of ADB
(Attached as Annex-II), the subproject is classified as Category B, which requires
an IEE study to be conducted. Thus, a detailed and comprehensive IEE study,
including the EMP, has been prepared
53.Under Section 12 of the Pakistan Environmental Protection Act 1997 and
section 13 of Khyber Pakhtunkhwa Environmental Protection Act 2014, a project
falling under any category specified in Schedule I (SRO 339, 10/2000) requires
the proponent to file an Initial Environment Examination (IEE) report with
concerned provincial or federal Environmental Protection Agency (EPA). Projects
falling under any category specified in schedule II, the proponent shall submit an
EIA with the Provincial or Federal Agency, in this case Khyber Pakhtunkhwa
Environmental Protection Agency (KP-EPA) Peshawar, as the project is located
in KP. Within 10 working days of IEE or EIA having been deposited, the concerned
agency will confirm that the document submitted is complete for the purpose of
review. During this time should the empowered agency require the proponent for
revision, clearly citing those aspects that need further discussion the proponent
will carry out necessary revision. Subsequently, the concerned agency will make
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
27 | Initial Environmental Examination
every effort to complete the process for an IEE review within 45 days and an EIA
within 90 days of filing and issue a “No-Objection Certificate” to the project proponent.
54.These sub projects fall under schedule-I of the Pakistan Environmental
Protection Agency (Review of IEE & EIA) Regulations, 2000 in water
management, dams, irrigation and flood protection heading which states that
dams and reservoirs with storage volume less than 50 million cubic meters of
surface area less than 8 square kilometers require an IEE.
IEE/EIA Regulations 2000, Schedule I IEE Required
Dams and reservoirs with storage volume less than 50 million cubic meters or surface area less than 8 square kilometers
Yes
Irrigation and drainage projects serving less than 15,000 hectares Yes
B.13 Other Environment Related Legislations
55 The Table 2.4 provides all others legislations, guidelines, conventions and
corporate requirements.
Table 2.4. Environmental Guidelines and Legislations
Legislation/Guideline Description
The Forest Act (1927) The Act empowers the provincial forest departments to declare any
forest area as reserved or protected. It empowers the provincial
forest departments to prohibit the clearing of forest for cultivation,
grazing, hunting, removing forest produce, quarrying and felling,
lopping and topping of trees, branches in reserved and protected
forests
The Antiquities Act
(1975)
It ensures the protection of Pakistan’s cultural resources. The Act defines “antiquities” as ancient products of human activity, historical sites, or sites of anthropological or cultural interest, national
monuments, etc. The Act is designed to protect these antiquities
from destruction, theft, negligence, unlawful excavation, trade, and
export. The law prohibits new construction in the proximity of a
protected antiquity and empowers the GOP to prohibit excavation
in any area that may contain articles of archaeological significance.
Under the Act, the project proponents are obligated to ensure that
no activity is undertaken in the proximity of a protected antiquity,
report to the Department of Archaeology, GOP, any archaeological
discovery made during the course of the project.
Pakistan Penal Code
(1860)
It authorizes fines, imprisonment or both for voluntary corruption or
fouling of public springs or reservoirs so as to make them less fit for
ordinary use.
The Public Health
(Emergency Provision)
Act 1954 read with
These two laws cover the presentation and spread of human
diseases, safeguarding the public health and providing and
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
28 | Initial Environmental Examination
Legislation/Guideline Description
West Pakistan
Epidemic Control Act
1958
maintaining adequate medical services and other services essential
to the health of the communities in the project area.
NATIONAL ENVIRONMENTAL AND CONSERVATION STRATEGIES
National Conservation
Strategy
Before the approval of NEP, the National Conservation Strategy
(NCS) was considered as the Government’s primary policy document on national environmental issues. At the moment, this
strategy just exists as a national conservation program. The NCS
identifies 14 core areas including conservation of biodiversity,
pollution prevention and abatement, soil and water conservation
and preservation of cultural heritage and recommends immediate
attention to these core areas.
Biodiversity Action
Plan
The plan recognizes IEE/EIA as an effective tool for identifying and
assessing the effects of a proposed operation on biodiversity.
Environment and
Conservation
There is a well-established framework for environmental
management in Pakistan. The Ministry of Environment deals with
environment and biological resources. Within the ministry, the NCS
unit established in 1992 is responsible for overseeing the
implementation of the strategy. Two organizations, the Pakistan
Environmental Protection Council (PEPC) and the Pak EPA are
primarily responsible for administering the provisions of the PEPA,
1997. The PEPC oversees the functioning of the Pak EPA. Its
members include representatives of the government, industry, non-
governmental organizations and the private sector. The Pak EPA is
required to ensure compliance with the NEQS, establish monitoring
and evaluation systems, and both identify the need to and institution
of legislations whenever necessary. It is thus the primary
implementing agency in the hierarchy. The Provincial
Environmental Protection Agencies are formed by the respective
provinces.
ADB’s ENVIRONMENTAL GUIDELINES
Safeguard Policy
Statement (SPS), 2009
ADB’s Safeguard Policy Statement (SPS), 2009 provides guidelines for environmental assessments of development projects.
These guidelines help prospective projects identify impacts they will
have on various environmental receptors. The guidelines call for
carrying out EIAs or IEEs of projects based on severity of their
impacts.
INTERNATIONAL CONVENTIONS
The Convention on
Conservation of
Migratory Species of
Wild Animals (1981.21)
The Convention requires countries to take action to avoid
endangering migratory species. The term "migratory species" refers
to the species of wild animals, a significant proportion of whose
members cyclically and predictably cross one or more national
jurisdictional boundaries. The parties are also required to promote
or cooperate with other countries in matters of research on
migratory species. There are no endangered species of plant life or
animal life in the vicinity of the Project.
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
29 | Initial Environmental Examination
Legislation/Guideline Description
Convention on
International Trade in
Endangered Species of
Wild Fauna and Flora
(1973)
The convention requires Pakistan to impose strict regulation
(including penalization, confiscation of the specimen) regarding
trade of all species threatened with extinction or that may become
so, in order not to endanger their survival further.
International Union for
Conservation of Nature
and Natural Resources
Red List (2000)
Lists wildlife species experiencing various levels of threats
internationally. Some of the species indicated in the IUCN red list
are also present in the wetlands of Pakistan.
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
30 | Initial Environmental Examination
PROJECT DESCRIPTION
Project Features
52. The Tor Dara weir sub project has two weirs one on the main Tor Dara Nullah and
the other on its small tributary near village Natu Khel in Tirah Valley, District
Khyber and is located at a distance of 100 km from Peshawar.
53. During various visits at site the hydrological observation was made and found the
perennial flow in a range of 5-8 cusecs. The last site visit was made on (19-06-
2019) and approximately 5 cusecs of flows was observed on Tor Dara nullah and
0.30 cusecs was observed in its tributary.
54. Tor Dara Weir and Natu Khel Weirs are proposed to collect water from Tor Dara
Nullah and its tributary to convey the available flows to the command area laying
at both right and left side of Tor Dara Nullah. Gross command area is 96 hectares
and cultivable command area is 93 hectares which is proposed to be irrigated at
cropping intensity of 100 % with the design discharge of 22.90 lit/sec and 6.45
lit/sec for Tor Dara and Natu Khel Weir respectively.
55. The main features of the project include construction of weirs, irrigation channels,
retaining walls, fall structures, road culverts and drainage culverts, on-farm water
management works and improvement of ware sheds through forestation. The
project cost is estimated as Rs. 93.804 million and is anticipated to take 12 months
period to complete. The results of the economic analysis show that the sub project
is economically viable (EIRR 12.03%). The financial analysis also indicates the
safe investment with FIRR as 10.23%.
Table 3.1: Salient Features of Tor Dara Sub Project
Catchment Area 35.66 km2
No. of Weirs 02
Type of Weir Tyrolean Type
50 Year Return Flood
• Tor Dara Weir 180 Cumecs
• Natu Khel Weir 13 Cumecs
Gross Command Area 96 ha
Total Culturable Command Area 93 ha
Irrigation Intensity
100%
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
31 | Initial Environmental Examination
Irrigation discharge required
• Channel – 01 (Tor Dara Weir) 22.90 Lit/sec
• Channel – 02 (Natu Khel Weir) 6.45 Lit/sec
Irrigation Channels Type PCC Rectangular
Length of Channel 01 (Tor Dara Weir) 4640 m
Length of Channel 02 (Natu Khel Weir) 1660 m
Length of Water Courses 4092 m
Project Cost Rs. 93.804 Million
Construction Period 12 Months
EIRR 12.03 %
FIRR 10.23 %
56. The Tarkho Kas Weir sub-project is proposed on Matu Nullah near village
Naghara in Tirah vallay in District Khyber and is located at a distance of 79 km
from Jamrud Khyber District head quarter. As per site observation there is
perennial flow exist in the Nullah.
57. Tarkho Kas Weir is proposed to collect water from Matu Nullah and convey it to
the command area. Cultivable command area of 90 ha will be irrigated at cropping
intensity of 100 % and design discharge of 28.9 lit/sec. Total length of irrigation
network is 5290 m.
58. The project cost is estimated Rs. 64.577 million and anticipated to take 12 months
period to complete. The results of the economic analysis show that the project is
economically viable (EIRR 12.23 %). The financial analysis also indicates the safe
investment with FIRR as 10.33 %.
Table 3.2: Salient Features of Tarkho Kas Sub Project
Catchment Area 14.75 km2
Design Flood 104 cumecs
Total Culturable Command Area 90 ha
Irrigated Area 36 ha
Barani Area 54 ha
Irrigation Intensity 100%
FATA Water Resources Development Project Tor Dara & Tarkho Kas Weir Sub Projects
32 | Initial Environmental Examination
Irrigation discharge required 28.9 lit/sec
Channels Type PCC Trapezoidal
Pre-Cast Parabolic Channel
Length of Channel 01 1843 m
Length of Channel 02 1345 m
Length of Channel 03 1940 m
Length of Water Courses 4550 m
Project Cost Rs. 64.577 Million
Construction Period 12 months
EIRR 12.23 %
FIRR 10.33 %
59. Tor Dara and Tarkho Kas weir sub projects on account of its construction volume
would not require elaborate arrangements for construction of labor camps.
Keeping in mind the quantum of work, no large size camp would be required as
non-technical labour is to be engaged would be of local origin. Storage sheds for
construction materials would be constructed in the vicinity of weir construction site.
The contractor will make his own arrangements for the technical staff and details
will be provided in the SSEMP.
60. All the land required for different sub projects components is community owned
barren land, which would be provided voluntarily; no land base infrastructure will
be affected during construction as well as operational phases of the sub projects.
The permanent land for sub projects components such as weir, water channels,
offices, etc. as well as temporary land will be taken on lease if required. The
amount of lease is part of project civil cost and is not added in Environmental
Management Cost (details in Chapter G) to avoid duplication of cost.
61. The location of the project is shown in Figure 3.1 and layout plan over satellite
image in Figure 3.2 and 3.3:
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
33 | Initial Environmental Examination
Figure 3.1: Sub Projects Location Map
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
34 | Initial Environmental Examination
Figure 3.2: Satellite Image of Tor Dara Sub Project Area
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
35 | Initial Environmental Examination
Figure 3.3: Satellite Image of Tarkho Kas Sub Project Area
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
36 | Initial Environmental Examination
Project Location
Khyber merged District, KP was the tribal area in the former Federally
Administered Tribal Areas of Pakistan created in 1873. It ranges from the Tirah
valley down to Peshawar. It borders Nangarhar Province of Afghanistan in the
west, Orakzai Tribal District in the south, Kurram merged District in south west
and Peshawar district in the east. Jamrud is headquarter of the Khyber merged
District. Khyber District lies between latitude 33˚ 43' to 34˚ 21' and longitude 71˚ 27' to 71˚ 32'. The Khyber District is drained by tributaries of the Kabul and Bara
rivers. It covers an area of 2,576 km2.The Tor Dara (two weirs i.e. Tor Dara main
weir and Natu khel weir under one subproject) and Tarkho Kas weir sub projects
are proposed on Tor Dara nullah and Mato nullah which are tributaries of Bara
River and are located at a distance of 100 Km and 79 Km respectively from
Jamrud Khyber District Head Quarter.
62. The weirs location coordinates are provided in the table below;
Table 3.3: Weirs Location GPS Coordinates
Proposed Weirs Longitude Latitude
Tor Dara Weir 70.772° E 33.909° N
Tarkho Kas Weir 70.837° E 33.918° N
Project Objectives
63. The main objective of the sub projects is to construct a low height Tyrolean weir
and irrigation channels that will irrigate Culturable Command Area (CCA) of
approximately 183 ha downstream of the subprojects. The present cropping
intensity is 0 to 38% in rainfed and irrigated agricultural lands respectively. It is
estimated that a reasonable quantity of water from the weirs will meet the irrigation
demand of lands in the command area. Regular and dependable irrigation water
availability with the construction of the sub projects will greatly increase cropping
intensity by 100% and production in the currently partially irrigated command area.
Due to timely and regulated water supplies there will be substantial improvement
in agriculture production. Provision of irrigation water with the construction of the
weirs, will transform the below subsistence level rain-fed farming lands into
productive irrigated agriculture.
Construction Planning
64. The main components of Tor Dara and Tarkho Kas weirs irrigation sub projects
include the:
i. Geotechnical Investigation
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
37 | Initial Environmental Examination
ii. Foundation preparation
iii. Diversion Weir.
iv. Stilling Basin at the downstream.
v. Irrigation system.
vi. On-Farm Water Management Works
65. These components are proposed to be constructed in two stages. The
geotechnical investigation will be carried out first, while construction of civil works
will be carried out after design review. The stage wise break-up of components for
construction purposes is briefly described below:
Stage-I
Preparation of Foundation for Weirs
66. The foundation preparation will involve excavation in stream/khwar bed and
abutments, which mostly constitute of shingle gravel and weathered rock
formation. The detail of excavation involved has provided in Table 3.4 below.
Table 3.4: Diversion Weirs Works and Quantities
Item # Description Unit Tor Dara Weirs
Quantity Tarkho Kas Weir
Quantity
1 Excavation
cu. m 2827.38 1778.56
2 Structural backfill cu. m 219.46 142.47
3 Re-handling of gravel work or excavated rock
cu. m 438.92 284.94
4 Cement Concrete Work cu. m 868.31 976.65
5 Erecting & removing formwork to concrete in any shape / position (Vertical)
sq. m 1334.17 1,032.01
6 Supply & fabricate M.S. reinforcement for cement concrete (Hot rolled deformed bars Grade 60)
Tonne 34.84 46.80
7 Providing and laying stone pitching/filling, dry hand packed in pitching & aprons
cu. m 41.32 593.25
Stage- II
Main Weir Body
67. The diversion weir has been located at the location keeping in view the minimum
possible width of the nullah and the ease of construction to the contractor. It has
been considered during project sites selection that change in nullah regime should
be avoided with the construction of weir. The wing walls of proposed weirs are
properly embedded in the side hills/embankments to fix the flow regime at the weir
top permanently. The area beyond weir’s side wall will be consolidated by
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
38 | Initial Environmental Examination
providing protection/backfill up to side wall height for trenches produced for the
construction of weir or by flood before the construction of weir.
68. For the diversion of irrigation discharge tyrolean intake is adopted at these
locations. The diversion weir comprises an overflow sections for flood routing and
a depressed tyrolean section to divert the flow for irrigation.
69. The oblique arrangement of the trash rack prevents it from being clogged by bed
load or floating materials, resultantly, the intake from being obstructed.
70. In order to ensure the diversion of design discharge when there is blockage of the
rack due wedging of stones or leaves and branches trap in the rack, length of the
rack has kept 20 % more than its required length. Inclination angle (15 deg) of the
rack with horizontal plane has been kept in the direction of flow. The clear spacing
of rack bars have been kept 10 mm, hence only the particle with less than 10 mm
size could get into the embedded channel which would be settled down in
collection sump.
71. Construction of the weir body is proposed to commence from left and right
abutment and intake pipe would be placed near abutment in the weir. Construction
of Irrigation channel and outlet structure will be taken up as parallel activities of
this stage.
Stilling Basin
72. Terminal structures to weir are provided to safely deliver the excess discharge to
the downstream. The hydraulic jump stilling basin is one of the typical types of
energy dissipaters, which has been adopted for the projects. At downstream of
the stilling basin, riprap has been proposed to protect the structure from scouring.
73. Due to low velocity and weak hydraulic jump formation type-I stilling Basin has
been adopted for all the weirs.
74. Construction of stilling basin will be started after construction of outlet structures.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
39 | Initial Environmental Examination
Figure 3.6: Diversion Weir Layout Plan Tor Dara
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
40 | Initial Environmental Examination
Figure 3.7: Diversion Weir Layout Plan Tarkho Kas
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
41 | Initial Environmental Examination
Irrigation System
75. Once the main irrigation channel has been completed, the beneficiaries will be
provided with design and layout of field channels falling within the proposed weir
project. The activity would be mostly carried out by the beneficiaries as part of
their labor and land contribution.
On-Farm Water Management Works
76. All irrigation projects are designed focusing the command area, targeting the
community of that command and management of this water on farm level.
Controlling the conveyance losses by an efficient conveyance system and the best
possible irrigation application method is always the main aim of such projects.
Typical precast water course x-section, farm outlet, drainage culverts, foot bridge
etc. are part of these activities.
77. The command area activities mostly initiated when main structure (Weir) is
completed and work on main conveyance structure starts. However, the land
development can be started when work on main structure is near to completion.
The personnel and equipment required for the execution of one subproject is
given in the tables below, also the same personnel and equipment will be used
for the second subproject.
Table 3.5: Personnel Requirement
Sr. No Position Nos
1 Project Manager / Project Engineer 01
2 Construction Supervisor 02
3 Site Engineer 01
4 Environmentalist 01
5 Health and Safety Officer 01
6 Surveyor 02
7 Quantity Surveyor 01
8 Site Inspector (Environment) 01
9 Skilled Labor 05
Table 3.6: Equipment Requirements
Sr. No Equipment/Machinery Type Nos
1 Front End Loader 01
2 Excavator 01
3 Dumper 02
4 Water Tanker 02
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
42 | Initial Environmental Examination
5 Mixer 01
6 Generator 02
7 Tractor along with Trolley 01
Commissioning of Weirs
77. The weirs and its associated structures i.e. main irrigation channels and minor
distribution channels will be commissioned on completion of stage-II works and
by starting the perennial flow diversion.
Sub Projects Implementation
78. The sub projects implementation would be carried out in accordance with Project
Administration Manual (PAM) framed under FWRDP PPTA by Asian Development
Bank. The sub projects construction would be completed in twelve (12) months.
Executing Agency
79. The Khyber Pakhtunkhwa Planning & Development Department will be the
executing agency. A Project Management Unit (PMU) will be established in the
Planning and Development Department (P&D Department) of the Merged Areas
Secretariat. Project implementing agencies include the Directorate of Irrigation,
which will be responsible for the improved irrigation infrastructure and on-farm
water management components with the latter effort supported by the Department
of Agriculture. The Department of Forests will be responsible for the watershed
management component.
Design Consultant
80. The design and residency supervision of the subproject would be carried out by
FWRDP design consultants. The consultants will carry out screening of the
subproject as per selection criteria. Accordingly, feasibility study of the subproject
fulfilling the selection criteria would be framed.
Provincial Development Working Party
81. The Provincial Development Working Party (PDWP) would approve the feasible
sub projects of FWRDP. The PDWP would be delegated special powers to
approve FWRDP sub projects costing more than the threshold approval limit of
PDWP. The sub project will also be implemented in cooperation with local
community organizations (COs) established under the FRDP and will be key
partners in the new project. The COs will enter into Terms of Partnership (TOPs)
with the Khyber Pakhtunkhwa Planning & Development Department for the
preparation and implementation of all sub-projects to be financed under the
project. Such TOPs were already signed with COs for the 3 pilot sub projects, and
are the model to be followed for subsequent sub projects. The COs also would be
responsible for maintenance of completed sub projects under the main project.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
43 | Initial Environmental Examination
Prior to the commencement of each proposed sub project, the Khyber
Pakhtunkhwa Planning & Development Department and the relevant Community
Organization will have entered into a Terms of Partnership (“TOP”) setting forth, among other relevant terms, the details of the preparation and implementation of
such sub project (including information on any land to be voluntarily contributed
by the community for such sub projects) and subsequent operation and
maintenance of the facilities financed under such sub project, which such TOP will
have been approved by the Deputy Commissioner.
Terms of Partnership
82. TOP for a sub project involving the construction of a weir or irrigation channel will
stipulate that the relevant Community Organization will be responsible for
operation and maintenance of such weir or irrigation channel from such
Community Organization’s own funds, provided, that, any major repairs to such
facilities shall be carried out by, and at the expense of, the Merged Areas
Secretariat, through its Irrigation Department.
Operation and Maintenance
83. The sub projects have been designed to minimize manual operation to a minimum
but the main canal can be regulated for flows through vertical steel gate.
84. The beneficiaries have signed Terms of Partnership (TOP) with the local
authorities of Khyber Tribal District and Irrigation Directorate. The TOP clearly
states the roles and responsibilities of each stake holder. Most of the O & M
activities at secondary and tertiary level would be carried out by the beneficiaries
through Village Organizations/COs.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
44 | Initial Environmental Examination
DESCRIPTION OF ENVIRONMENT
General
85. The purpose of this chapter is to establish baseline conditions for the
physical, biological and social aspects of the environment of project area.
The data were collected from field surveys, desk studies and visits to the
government departments, other relevant agencies, and discussions with the
main stakeholders of the area. The purpose of the baseline study is to fulfill
the following objectives.
a. To get the data about the physical, biological and socio-
economic environment of the project area
b. To understand the current situation of the area
comprehensively, and
c. To rationalize the decisions according to the ground realities.
86. Information sources for this IEE also include:
i. Water Assessment Study & Management Plan, Bajaur, Khyber and Mohmand, published by ADB and FATA Secretariat, produced under the ADB FATA Rural Development Project (FRDP)
ii. Forest Atlas of Pakistan
iii. GIS Database developed by the PPTA GIS Specialist
iv. Primary Surveys conducted under PPTA by Environment Specialist
v. Hydraulic Design Feasibilities conducted under PPTA by Hydraulic Design Specialist and
vi. Agriculture and Geological Studies conducted under PPTA by Agricultural Specialist and Geologist
87. The main environmental conditions, likely to be affected due to project
execution are:
a. Physical Environment
b. Biological Environment
c. Socio-economic Environment
Baseline Survey Methodology
88. A survey was carried out in the project area for field studies including
physical, biological and social impact assessment in March and April, 2019.
The visit was made to the project area to understand the terrain, environment
and social issues, and vegetation of the study area. During the visit, the
preliminary interpreted data were tested and necessary corrections made
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
45 | Initial Environmental Examination
after proper ground-truthing. The physiographic features on the satellite
imagery appearing in different tones and textures were used to correlate
image elements and ground features for accurate identification.
89. The purpose of the site visits was to familiarize with the physical, biological
and socioeconomic environment of the proposed project area and the areas
in the vicinity. Critical areas with respect to environmental and social
concerns were identified and assessment of positive as well as adverse
impacts of the project on the environment was done. A summary of the main
activities undertaken during the visit have been enlisted below:
i. Collected information and required data from the project area
for preparation of Initial Environmental Examination report.
ii. Identified site-specific issues of microenvironment of the
proposed project.
iii. Information obtained regarding existing infrastructure in and
around the project area.
iv. Requirements of necessary mitigation measures to be
integrated into the overall plan were identified.
v. Consultations with the population settled in the vicinity of the
project.
vi. Survey of nearby environmental sensitive receptors.
vii. Interviews with the locals for the presence and relative
abundance of various animal species within each locality were
also taken to have firsthand information.
viii. Data collection was carried out on habitat condition, animal
presence by direct sighting and indirect evidences.
90. Spatial data base on the physiographic features was prepared based on the
various data sources including survey map of the project and topographic
sheets. These data were extracted and presented in accordance with the
standard IEE methodology used for such studies.
91. The section on climatology has been taken from the Project Hydrology Report
made by project hydrologists.
92. The regional geology and seismo-tectonics of the region are discussed based
on the various available data sources and reports. Particularly, the discussion
on project geology has been based on the data available in the project
Geology Report and field observations made in selective pockets of different
project affected sites.
93. Land use and land cover mapping was carried out by standard methods of
analysis of remotely sensed data followed by ground truthing.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
46 | Initial Environmental Examination
94. Forest types and plant species were recorded during the field visits and the
floristic data for the catchment were sourced from the published literature.
Based on the field data and available literature, frequency, density and cover
of each species were calculated.
95. Ecological status of species was identified as per IUCN Red list, 2017 and
other available literature.
96. In order to collect the information on the fauna (mammals, avifauna,
herpetofauna) in the area, primary as well as secondary sources were
utilized.
97. The environmental testing (air, noise and water) at about 10 m distance from
main proposed construction site has been carried out to determine the
baseline conditions of the area.
Study Area
98. The studied area for this IEE was broadly the Khyber merged District and
more specifically the Tor Dara and Tarkho Kas settlements.
99. The required information/ data of a baseline study were classified into two
main categories i.e. Primary data and Secondary data. The primary data was
collected directly from the concerned communities and direct observation,
secondary data was the information gathered through secondary sources
such as census report, research publications, topographic sheets, other
published data related to the project such as wildlife, livestock, fishery,
forestry, agriculture, horticulture, climate etc.
100. The project Area of influence (AoI) is referred to all those areas in the region
within 0.5 km from the sub project corridor and which may be affected directly
or indirectly by the sub project activities.
101. For the purpose of this IEE, detailed deliberations were held with relevant
stakeholders from the state, civil society and academia.
102. As a result, an effort was made to establish a baseline or state of environment
for the study area, with a focus on sub-project site location. Having stated the
above, there are still limitations to the accuracy and authenticity, since in
numerous cases, sources for data are singular and cannot be cross verified
due to paucity of reliable sources.
Physical Environment
Topography
103. Khyber Merged District was a tribal area in the erstwhile Federally
Administered Tribal Areas region of Pakistan. It is one of the eight newly
merged tribal District in Khyber Pakhtunkhwa Province. It ranges from
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
47 | Initial Environmental Examination
the Tirah valley down to Peshawar. It borders Nangarhar of Afghanistan
Province to the west, Orakzai Tribal District to the south, Kurram Tribal
District to south west and Peshawar to the east. An interesting feature in the
topography is a mountain spur from the Kunar range, which, curving
eastwards culminates in the well-known peak of Koh-i-Mor, which is visible
from the Peshawar valley. The topography of this pass is prevailingly hilly,
with rugged barren mountainous terrain, including narrow strips of bottom
valleys and sub valleys. The primary ecological factors which determine the
plant communities/association in this eco–zone are, rainfall & temperature,
topography and soil and elevation.
Climate
104. The sub projects area falls in the warm and temperate climatic zone
associated with 600-800 mm of annual precipitation. There are two distinct
rainy seasons in the Area: winter (December through March) and summer
(June- September).
105. Meteorological stations within sub projects area do not exist. Nearest
meteorological stations are Peshawar (77 km East from project site), Kohat
(76 km South East), Parachinar (59 km West) and Fort Lockhart (46 km
South). All other stations except Parachinar, Kohat and Fort Lockhart are not
representing the climate zone of the sub projects area and located far from
sub projects area, hence not used for the project area assessment studies.
Fort Lockhart average annual rainfall is almost double than estimated from
isohyetal map and gridded data set for the project area, hence dropped from
studies.
106. The sub projects area has a climate with cold winters and mild summers.
During summer months there is great fluctuation in diurnal temperature in the
open and in the shade of hilly areas. In the winter at higher elevations the
area may experience snow from late December to mid-March.
107. The mean maximum temperature during the hottest months of June and July
are 30.9 °C and 30.1 °C respectively. January and February are the coldest
months with minimum temperature of about -4.4 °C and -2.3 °C8.
108. The nearest meteorological station to the sub projects area is Parachinar.
The mean monthly with minimum and maximum temperature for Parachinar
representing the sub projects area is provided in Figure 4.1 below.
8 Hydrological studies Feasibility Reports (Data Source: Monthly Climate Normal of Pakistan (1981-2010), Pakistan Met. Department Karachi, Jan, 2013)
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
48 | Initial Environmental Examination
Figure 4.1 Monthly Mean Temperature of Parachinar 9
Hydrology
109. Surface flow was not gauged in the past therefore, no flow record exists within
watershed of proposed weir site. Perennial flow exists at proposed weir site.
Flow measurements have been carried out through conventional method at
Tor Dara weir site. About (1.5 – 2.0 cusec) flow was observed during
December, 2018 while 141-226 liter/sec (5-8 cusec) flow was
observed/measured during March-April, 2019 at weir site. The last site visit
was made on (19-06-2019) and approximately 5 cusecs of flows was
observed on Tor Dara nullah and 0.30 cusecs was observed on tributary of
Tor Dara nullah.
110. At Tarkho Kas 43.07 liters/sec (1.52 cusec) was observed/measured during
March 2019. One cusecs of discharge were estimated during low flow season
that is in the month of January at weir site.
111. The qualitative statement of the available flows would have been worded
differently had there been any reliable records of their measurement. These
types of streams have their own ifs and buts and one could not ascertain the
9 Data Source: Monthly Climate Normal of Pakistan (1981-2010), Pakistan Met. Department Karachi, Jan, 2013
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
49 | Initial Environmental Examination
perennial flow from a single or a couple of site visits. The scheme has been
devised based on the flows experienced during the site visits.
112. Daily rainfall data for metrological stations Parachinar & Kohat for the period
of 1961-2017 & 1970-2017 have been collected from Pakistan Metrological
Department. Historic annual isohyetal maps for period of 1951-80, 1971-
2000, 1955-2000, 1981-2010 indicates that mean annual rainfall in the
project area ranges from 600-800 mm.
113. The estimation of water availability has also been carried out indirectly by Soil
Conservation Services Curve Number (SCS) method. To be on a
conservative site perennial flow of 1.5 cusec (42.50 lit./sec) and 1.2 cusec
(34.0 lit./sec) are added in rainfall-runoff estimated flow for Tor Dara and
Tarkho Kas sub projects respectively. Curve number of 51, 70 and 85 for
AMC-I, AMC-II and AMC-III conditions are used. As project area lies in
between gauging station of Parachinar and Kohat. Parachinar & Kohat
rainfall data is representing the project area rainfall, water availability is
estimated without any adjustment / correction factor for daily rainfall record10.
Regional Geology
114. The Khyber emerged District, KP in which these weirs have been proposed
lies in the region which is close to the collision zone of the Indian and
Eurasian Plates; the collision process started in the late Eocene to Early
Oligocene with the formation of Himalayan Ranges and this process is still
going on. Relative to Eurasia, the Indian Plate is still moving northward at a
rate of about 4 cm/yr. The subduction of the Indian Plate beneath the
Eurasian Plate has resulted in folding and thrusting of the upper crustal layers
near the collisional boundary. The thrusting has been depicted from north to
south in the shape of Main Karakoram Thrust (MKT), Main Mantle Thrust
(MMT) and Salt Range Thrust (SRT).
Geology of the Sub Project Area
115. The topography of the project area having rugged and hilly terrain with low to
moderate relief. The both scheme of project are proposed on the stream
having perennial flow with the slope gradient of about 2-3% on average in the
nullah bed. The flow pattern is generally dendritic though at places trellis
pattern can be observed. Geologically the project area has got consolidated
deposits of sedimentary and metamorphic origin comprising slates, phylites,
schist, quartzite, shale marl and Lime stone. Folding and shearing is quite
common due to tectonic forces. The rock body is mostly covered by
unconsolidated material. The unconsolidated deposits comprise Recent to
10 Hydrological studies Feasibility Report
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
50 | Initial Environmental Examination
sub-Recent gravel, sand, silt and clay mixed with gravel of mostly of
metamorphic and sedimentary origin.
116. The rock unit found at weir site belong to Landikotal Slates in contact with
slightly metamorphosed shale and quartzite. The formation is composed
predominantly of greenish gray to yellowish gray slates and phyllites intruded
by dykes & sills. At few places slate is calcareous11.
Soil
117. Soil of the area are loam, non-calcareous, non-saline and non-sodic in
nature. Soil pH is slightly alkaline. The soils are low in organic matter and
nitrogen contents, medium in phosphorus while sufficient in potassium
contents.
118. Judicious use of farmyard manure and inorganic fertilizers is required to
improve soil physical conditions, soil fertility and crop yields.
Seismology
119. Figure 4.2 shows the tectonic map of the area. The project area falls in minor
to moderate seismic zone. Formations in the study area are highly folded and
faulted due to tectonic movement. A large variety of rocks occur together in
a very disturbed manner. The country rocks are diorites, granite phyllites and
amphibolites with limestone, schist and phyllites.
11 Geological Studies Section of Feasibility Reports
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
51 | Initial Environmental Examination
Figure 4.2: Tectonic Map of Pakistan12
12 Source: Pakistan Meteorological Department
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
52 | Initial Environmental Examination
Ambient Air Quality and Noise
120. Sources of air and noise pollution around the sub-project area are minimal.
The area is predominantly rural, with no major industrial setups. The NEQS
for noise in residential areas is 55 dB (A) in the day time and 45 dB (A) at
night. Traffic is low, with heavy traffic being minimal. The ambient air quality
and noise at site was conducted at a 10 m distance from the main sub
projects axis as most of the construction activities will be done here while the
residential area is at distance of more than 500 m where the impact of all the
construction activities will be minimum. The sampling location (Figure 4.3 &
4.4) were selected keeping in view;
(a) the sensitive receptors and
(b) magnitude of construction activities.
121. These locations will be helpful for construction phase impacts monitoring and
comparison of the results with the baseline situation. The result (Table 4.1)
reveals that the air quality and noise of the sub projects area is within the
permissible limits of NEQS.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
53 | Initial Environmental Examination
Table 4.1: Ambient Air Quality and Noise of Sub Projects Area
Sr. No.
Parameter UoM Results Tor Dara
Results Tarkho Kas
NEQS IFC Method
1 Carbon Monoxide (CO)
mg/m3 2.9 1.6 5 - NDIR
2 Sulfur Dioxide (SO2)
µg/m3 21 19 120 125 UV Fluorescent
3 Nitrogen Oxide (NO)
µg/m3 11.4 13.8 40 - Chemiluminescence
4 Nitrogen Dioxide (NO2)
µg/m3 18 11 80 - Chemiluminescence
5 Combined Oxides of Nitrogen (NOx)
µg/m3 29.4 24.8 Chemiluminescence
6 PM10 µg/m3 18 40 150 150 Beta- Attenuation
7 PM2.5 µg/m3 11 23 35 Beta- Attenuation
8 Suspended Particulate Matter (SPM)
µg/m3 117 258 500 Gravimetric Sampling
9 Noise Entrance Point
dB(A) 47.9 48.4 55 55 ASTM E-1124
10 Noise Center Point
dB(A) 50.6 51.9 55 55 ASTM E-1124
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
54 | Initial Environmental Examination
Figure 4.3 Environmental Testing and Sampling Map Tor Dara
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
55 | Initial Environmental Examination
Figure 4.4 Environmental Testing and Sampling Map Tarkho Kas
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
56 | Initial Environmental Examination
Water Resources
Surface Water
122. The following major rivers flow through the Khyber Tribal District:
123. Kabul River originates from Chitral, and enters Afghanistan at Arandu,
making a semi-circle around Kabul City reaches in the vicinity of Jalalabad
where it is called Kunar River. Of late, Government of Afghanistan has
planned a multipurpose dam at Kama village near Jalalabad. The proposed
Kama dam is expected to irrigate about 40,486 ha in Kunar province. The
proposed Kama dam will reduce the flows in Kabul River by 15%. The
construction of proposed Munda dam on Swat River which is a tributary of
Kabul River will mitigate the effects of 15% reduction of flows in Kabul River
due to Kama dam in Afghanistan. Kabul River re-enters Pakistan in
Mohmand District and after traversing a few kilometers it turns into a
boundary river between Mohmand and Khyber Districts.
124. Bara River originates in the southeast of Khyber District from Rajgal and
Malik Din Khel watersheds. It drains into the Kabul River near Nissata, after
passing through the settled areas. There are three canals off-taking from the
river, within and outside Khyber District.
125. Drainage pattern plays key role in the ground water system. The perennial
nullahs on which the weirs are proposed are flowing near the command area.
The Nullahs are flowing from North to South. The Nullah originates in the
Northern Mountains further joining the Bara River which finally leaves the
district.
Ground Water
126. The sub projects area experiences two rain seasons: winter and summer.
Water supply is from rainfall, snow melt, and groundwater during the dry
periods. Springs are the major sources of drinking water. Since there is no
open well/dug well and tube well in the proposed command area therefore
depth to ground water table could not be measured.
127. Ground water flows always follow the surface topography of an area. In the
sub project area, the topographic trend is from West to Southeast. Whereas
topographic trends of the left side are from North to Southwest. Ground water
movement are always perpendicular to the ground water elevation contours.
In the instant case ground water table map and ground elevation contour map
cannot be generated due to non-availability of ground water points.
128. Rain and Snowfall is the main source of recharge in the command area. The
command area of the sub project area is situated on the recharge boundary
of the Sub Watershed Khyber-9 (K 9) located on the left bank of Bara River,
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
57 | Initial Environmental Examination
moreover connected to the snow-covered mountains of Tirah, presumably
recharge to the system is not an issue.
Water Quality
129. The surface water samples 10 m upstream of weir axis and drinking water
samples from nearest settlements (Figure 4.3) of the subproject area were
collected and analyzed in the Laboratory. The result reveals that the water is
fit for irrigation and drinking with exception of turbidity which makes it
aesthetically unpleasant. The turbidity is due to snow melting which result in
soil erosion from the nullah banks in the catchment area. This requires proper
physical treatment e.g. slow or rapid sand filtration before consumption. All
other chemical and biological parameters are in accordance with NEQS and
WHO standards. The results are given in Table 4.4 and 4.5.
Table 4.4: Water Quality of Tor Dara Sub Project
Sr. No
Parameters UoM Methods NEQS WHO Results Surface Water
Results Drinking
Water
1 Color TCU Sensory evaluation
< 15 < 15 Colorless Colorless
2 Odor - Sensory evaluation
Unobjectionable Unobjectionable UO UO
3 Taste - Sensory evaluation
Unobjectionable Unobjectionable UO UO
4 EC uS/cm Alpha, 21th Edition
< 1000 <1000 701 190
5 pH - Alpha, 21th Edition
6.5-8.5 6.5-8.5 7.7 7.8
6 Turbidity NTU Alpha, 21th Edition
<5 <5 5.6 3.2
7 Alkalinity mg/l Alpha, 21th Edition
-- < 500 6.58 1.59
8 Bicarbonate mg/l Alpha, 21th Edition
-- -- 329.02 79.76
9 Calcium mg/l Alpha, 21th Edition
-- -- 99.70 39.88
10 Carbonate mg/l Alpha, 21th Edition
-- -- BDL BDL
11 Chloride mg/l Alpha, 21th Edition
250 250 17.44 12.46
12 Hardness mg/l Alpha, 21th Edition
500 500 398.81 99.70
13 Magnesium mg/l Alpha, 21th Edition
-- -- 36.34 0
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
58 | Initial Environmental Examination
14 Potassium mg/l Alpha, 21th Edition
-- -- 1.69 1.39
15 Sodium mg/l Alpha, 21th Edition
-- -- 14.95 4.98
16 Sulphate mg/l Alpha, 21th Edition
-- 250 42.47 7.47
17 TDS mg/l Alpha, 21th Edition
1000 1000 419.75 119.34
18 Nitrate mg/l Alpha, 21th Edition
10 50 2.29 1.19
19 Total Coliform
CFU Alpha, 21th Edition
0 CFU/100 ml 0 CFU/100 ml 0 0
20 E.Coli CFU Alpha, 21th Edition
-ve 0 CFU/100 ml 0 0
Table 4.5: Water Quality of Tarkho Kas Sub Project
Sr. No
Parameters UoM Methods NEQS WHO Results Surface Water
Results Drinking
Water
1 Color TCU Sensory evaluation
< 15 < 15 Colorless Colorless
2 Odor - Sensory evaluation
Unobjectionable Unobjectionable UO UO
3 Taste - Sensory evaluation
Unobjectionable Unobjectionable UO UO
4 EC uS/cm Alpha, 21th Edition
< 1000 <1000 387 368
5 pH - Alpha, 21th Edition
6.5-8.5 6.5-8.5 8.1 8.1
6 Turbidity NTU Alpha, 21th Edition
<5 <5 76.2 47.8
7 Alkalinity mg/l Alpha, 21th Edition
-- < 500 3.19 3.58
8 Bicarbonate mg/l Alpha, 21th Edition
-- -- 159.52 179.46
9 Calcium mg/l Alpha, 21th Edition
-- -- 27.91 15.95
10 Carbonate mg/l Alpha, 21th Edition
-- -- BDL BDL
11 Chloride mg/l Alpha, 21th Edition
250 250 14.95 19.94
12 Hardness mg/l Alpha, 21th Edition
500 500 199.40 199.40
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
59 | Initial Environmental Examination
13 Magnesium mg/l Alpha, 21th Edition
-- -- 31.40 38.68
14 Potassium mg/l Alpha, 21th Edition
-- -- 1.79 1.49
15 Sodium mg/l Alpha, 21th Edition
-- -- 9.97 8.97
16 Sulphate mg/l Alpha, 21th Edition
-- 250 16.85 17.94
17 TDS mg/l Alpha, 21th Edition
1000 1000 208.38 220.34
18 Nitrate mg/l Alpha, 21th Edition
10 50 2.29 2.29
19 Total Coliform
CFU Alpha, 21th Edition
0 CFU/100 ml 0 CFU/100 ml NT 0
20 E.Coli CFU Alpha, 21th Edition
-ve 0 CFU/100 ml NT 0
Biological Environment
130. The natural environment of the project area has undergone severe
degradation due to intensive use of ground water resources, miss
management of watershed resources, over grazing of range lands and
uncontrolled cutting of forest trees13. The agriculture, irrigation, forest range,
and forestry interventions in terms of tree plantation in the project area will
restore the lost eco-systems.
Land use and Land Cover
131. The data pertaining to land use are required to understand that how much
area at present is put directly under different crops. Culturable area,
cultivated and unculturable areas are also known to see the extent of
increase in cropped area, which may be achieved with the provision of project
conditions. Similarly, culturable waste and forest, if any, are also taken into
considerations. The statistics regarding the present land use in the study area
are presented in Table 4.6.
Table 4.6: Land Use Statistics of Project Area14
District Khyber Area in Hectares
Total Reported Area 257676
Cultivated Area 24153
(i) Net Sown 17388
13 PC-I Proforma for FATA Water Resources Development Project (FWRDP)
14 Source: Development Statistics of FATA 2012-13 to 2015-16
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
60 | Initial Environmental Examination
District Khyber Area in Hectares
(ii) Current Fallow 6765
Cropped Area 21815
Un-Cultivated Area 235454
(i) Culturable Waste 51010
(ii) Forest 2050
(iii) Not Available for Cultivation 182374
132. Agriculture is limited in the region due to rocky soils, steep slopes, lack of
suitable land and limited water supply. Scanty shrub vegetation along slopes
and other areas are used as grazing and fuel wood gathering. The sub
projects area has forest cover of 61.9%, sparse forest is 10.7%, range land
is 16.0% while barren land is 11.4%. Land use and land cover of the sub
projects are depicted in figure below:
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
61 | Initial Environmental Examination
Figure 4.5: Land use Map
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
62 | Initial Environmental Examination
Flora
133. The forests being an
integral part of rural
economy provide critical
ecological services.
Healthy forest cover helps
water retention, control
flash floods and soil
erosion, provides a habitat
for flora and fauna and
contributes to a clean
environment. Due to more
dependence of the rural
population on the available scanty forest resource, the environmental
services provided by natural ecosystems have also diminished. The water
retention capacity of the soil has fallen; the area suffers both from flash floods
and long period of drought.
134. The total area of the District is 2,576 square kilometers, with 0.8% of the total
area of the district being forest15. Ecologically, this area falls within the main
group of Dry Subtropical Broad-leaved Forest 16 . The sub–group is
Monotheca Scrubs. Generally, the vegetation is thorny evergreen shrubs,
which are capable of developing into small trees, even under harsh climatic
conditions and social pressure (heavy grazing /browsing).
135. The main tree species are Querons Ilex ( Kharpata Cherai), Olia europea
(Khomunor Khowand), Morus alba (Tooth), Olea cuspidate (wild olive), Salix
(Wula ), Juglans regia (Akhrot), Punicis grantsum (Anar), Amygdalus persica
(Mandatas), Pyrus pyrifolia (Nashpati).
136. The common grasses are Heteropogon, Cymopogon, Saccharum clumps
(munja). The ground vegetation makes appearance after the spring rains in
the month of January and February. Some of the tree species, which have
been planted by the forest department and local community are, eucalyptus,
bakian, mulberry, shisham and poplar.
137. No endangered species have been reported in the project area by the locals.
Sub projects area are free of forest cover. Overall natural vegetation,
including shrubs, bushes and grasses can be aptly termed as potential
rangelands which provide grazing habitat for livestock. Following are some
species of trees and shrubs found in the sub project area:
15 Important Agency/FR wise Socio-Economic Indicators of FATA, BoS P&D FATA 16 (Forest Types of Pakistan by Champion, Seth and Khattak, 1965)
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
63 | Initial Environmental Examination
Table 4.6: Common Trees Species in Project Area
Local Name Botanical Name IUCN Status
Local Status Picture
Cherai Kharpata Querons ilex NE Common
Khomunor Khowand
Olia europea NE Common
Zeeton (wild olive)
Olea europaea subsp. cuspidata
DD Rare
Tooth Morus alba LC Common
Wula Salix LC Rare
Toot (Mulberry) Morus LC Common
Bakain (dhraik) Melia azedarach LC Common
Oghuz /Akhrot Juglans regia LC Common
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
64 | Initial Environmental Examination
NE: Not Evaluated; LC: Least Concern DD: Data Deficient as per IUCN Red List, 2017.
Table 4.7: Common Grasses Species in the Area
Common Name
Botanical Name IUCN Status Picture
baruwa grass (munja)
Saccharum clumps
NE
Suryalla ghass
Heteropogon contortus
NE
lemon grass Cymbopogon LC
NE: Not Evaluated; LC: Least Concern as per IUCN Red List,2017.
Table 4.8: Common Shrub Species in the Project Area
Local / Common Name
Botanical Name IUCN Staus
Picture
Baikar Adhatoda vasica
Justicia adhatoda
NE
Ak Calotropis spp NE
Vena Rhazya spp NE
Khatumaal Rumex hastatus NE
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
65 | Initial Environmental Examination
Local / Common Name
Botanical Name IUCN Staus
Picture
Granda Carrisa spp NE
Karir Capparis spp NE
Karkanrha Zizyphus nummularia
NE
*NE: Not Evaluated; LC: Least Concern as per IUCN Red List, 2017.
Fauna
138. No baselines on wild mammals,
birds and fish species are
available for erstwhile FATA. No
comprehensive survey has ever
been conducted in the territories
by any line department or NGO.
For the purpose of this IEE, a
primary survey was conducted by
project environmentalist during
January, 2019 to ascertain the
distribution of species, and to collect evidence of any sightings in consultation
with local residents, the following animals have potential to be in the area:
Table 4.9: Fauna of the Project Area
S No. Common Name Scientific Name 1 Mammals i) Jackals Canis aureus (LC)
ii) Foxes SSP. Vulpes (LC)
iii) Field rats Rattus norvegicus (LC)
iv) Hare Lepus nigricollis (LC)
v) Porcupine Hystrix indica (LC)
vi) Hedge Hog Erinaceinae (LC)
vii) Wild cat Felis chaus (LC)
viii) Wild Boar Sus scrofa (LC)
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
66 | Initial Environmental Examination
ix) Brown Monkey Ateles hybridus (LC)
2 Reptiles
i) Rat eating snake Colubrinae (NE)
ii) House gecko Hemidactylus frenatus (LC)
3 Amphibians i) Common Toads Bufo bufo (LC)
4 Others i) Scorpions Scorpiones (NE)
ii) Spiders Araneae (NE)
*LC: Least Concern NE: Not Evaluated NT; Near Threatened as per IUCN Red list, 2017.
Avifauna
139. Avifauna of the area is highly diversified and colorful, which is widely
dispersed in gardens, cultivated fields, streams and hill slopes. Common
species are given in Table 4.10.
Table 4.10: Avifauna of the Project Area
S.NO Common Name Scientific Name 1 Tawny Eagle Aquila rapax (LC)
2 Long Legged Buzzard Buteo rufinus (LC)
3 Sparrow Hawk Accipiter nisus (LC)
4 Rose Finch Carpodacus erythrinus (LC)
5 Indian Blue Robin Luscinia brunnea (LC)
6 Red Headed Bunting Emberiza bruniceps (LC)
7 Crested Bunting Melophus lathami (LC)
8 Grey Tit Melaniparus afer (LC)
9 Blue Throated Fly Catcher Cyornis rubeculoides (LC)
10 White Throated Dipper Cinclus cinclus (LC)
11 Green Warbler Phylloscopus nitidus (LC)
12 Himalayan Tree Creeper Certhia himalayana (LC)
13 Magpie Robin Copsychus saularis (LC)
14 Rosy Pastor Pastor roseus (LC)
15 Common Babbler Turdoides caudata (LC)
16 Rufous Backed Shrike Lanius schach (LC)
17 Hoopoe Upupa epops (LC)
18 Red Vented Bulbul Pycnonotus cafer (LC)
19 White Cheeked Bulbul Pycnonotus leucotis (LC)
20 Grey Partridge Perdix perdix (LC)
21 See See Partridge Ammoperdix griseogularis (LC)
22 Grey Lag Goose Anser anser (LC)
23 Wigeon Mareca penelope (LC)
24 Pintail Anas acuta (LC)
25 Mallard Anas platyrhynchos (LC)
26 Grey Heron Ardea cinerea (LC)
27 Black Winged Stilt Himantopus himantopus (LC) 28 Great Egret Ardea alba (LC)
29 Flamingo Phoenicopterus roseus (LC)
30 Sand Plover Charadrius mongolus (LC)
31 Curlew Numenius phaeopus (LC)
32 Red-Wattled Lapwing Vanellus indicus (LC)
33 Little Ringed Plover Charadrius dubius (LC)
34 Yellow Wagtail Motacilla flava (LC)
35 Night Heron Nycticorax nycticorax (LC)
36 Little Egret Egretta garzetta (LC)
37 White Breasted King Fisher Halcyon smyrnensis (LC)
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
67 | Initial Environmental Examination
140. The hotspots for these birds and waterfowls are irrigation dams, khwars, river
beds and banks.
141. Any human-wildlife interface is very rare in the sub projects area, as most
faunal species are likely to have shifted their niche to higher altitude due to
significant anthropogenic footprint in the area.
142. No threatened or endangered species were observed in the sub projects
area, as per IUCN red list classification of 2017.
Protected areas / National sanctuaries
143. After merger of Tribal district with KP the wildlife and forest laws are extended
to the district. In past there were no wildlife or forest laws enacted for
erstwhile FATA. However, more recently, Governor KP has issued a
notification, declaring all wetlands in the former FATA as Community Game
Reserves. Hunting shall only be allowed with joint agreement of local
communities and local authorities. Moreover, a separate notification has also
been issued declaring trade in body parts (pelt, skin, stuffed bodies, trophies,
etc.) of all wild fauna including migratory birds as illegal. Both of these are
attached as Annex IV.
Fisheries
144. No fish was observed during the present study in the Khwar/stream.
Socio-Economic Environment
145. Khyber Tribal District is the most famous district amongst seven others in the
erstwhile Federally Administered Tribal Areas (FATA). Khyber Tribal District
derives its name from the famous Khyber Pass, which has served as a
historical trade route, connecting the Asian sub-continent with the rest of
Central Asia, via Afghanistan. Because of its geographical location, the
district has a history dating back thousands of years. The Khyber Pass has
been used by the Aryans in 1600 B.C., the Persians in 600 B.C., Alexander
in 326 B.C. and subsequently, by Changez Khan, Taimurlang, the Mehmood
of Ghazni and the Mughals.
146. Khyber Tribal District is bordered with Afghanistan, Peshawar city and the
Kurram and Orakzai Tribal Districts The total area of the District is 2,576
square kilometers, with 8.22% of the total area of the District being forest.
The Khyber Tribal District consists of three tehsils; Bara, Landi Kotel and
Jamrud. Khyber Tribal District has a barren and rugged mountainous terrain.
It consists mostly of hilly tracks and mountains, with narrow strips of valleys.
It is the meeting place of a series of ranges, such as the Koh-e-Safaid, an
off-shoot of the mighty Hindukush Mountains. Lacha Ghar, Karagah Ghar,
Surghar, Tor Ghar, Morgah and Kalauch; are some of the mountains located
in the district.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
68 | Initial Environmental Examination
Administrative Set Up
147. Under the Constitution, erstwhile FATA is included among the territories of
Pakistan (Article 1). It was administered by Governor of the KP in his capacity
as an agent to the President of Pakistan, under the overall supervision of the
Ministry of States and Frontier Regions in Islamabad. The KP Governor
Secretariat played a coordinating role for interaction between the federal and
provincial governments and the Merged Area Secretariat.
148. The 25th Constitutional amendment like 18th Constitutional amendment which
resulted in abolition of concurrent list and devolved 47 subjects to provinces,
is a paradigm shift where under Federally Administered Tribal Areas (FATA)
stand integrated with and merged in the province of Khyber Pakhtunkhwa.
149. The executive authority previously exercised by the Governor Khyber
Pakhtunkhwa in respect of FATA under Article 247 of the constitution has
been done away with. Now being part of the province, the executive authority
is shifted to the Chief Minister and his cabinet. The Merged Areas have no
longer special status or dispensation. All provincial laws shall equally be
applicable to these areas and on mainstreaming of erstwhile FATA due
representation (about 16 general seats) shall be given in the Provincial
Assembly.
150. The colonial legacy in the form of political administration under the unbridled
powers of Political Agent is no longer there. The office is re- named as Deputy
Commissioner and Assistant Commissioner. Similarly, the Century old FCR
is no more in the field and replaced with Interim Governance Regulation. The
tribal people will have fundamental rights guaranteed by the Constitution and
of which they were deprived till now. The introduction and presence of
criminal and judicial system will ensure their fundamental rights like other
citizens of rest of the Country.
Demographic Profile
151. Erstwhile FATA had a unique governance status in the recent past, whereby
all land is owned by tribes inhabiting the areas since generations. Any
physical activity hence carried out needs the agreement of the locals, as well
as land donation by them. Since it is an egalitarian society, chances of elite
capture are minimum and major decisions are taken by Jirga, the tribal
administrative and management body.
152. The Malik (chief/elder) serves as an intermediary between the tribe and the
political administration, in exchange for a regular allowance with which to
meet social and leadership obligations. The more weapons at a Malik’s
disposal and the more men he can command to bear arms when needed, the
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
69 | Initial Environmental Examination
greater is his stature within the tribe. The jirga plays an important part in tribal
society as a traditional mechanism for conflict resolution.
153. Tribal people are accustomed to managing their own resources and solving
disputes without outside intervention. They act collectively to assist others in
the group and help fulfill social obligations. Marriages and deaths, for
example, draw support from all members of the tribe, as do everyday
activities such as harvesting and threshing, laying and clearing irrigation
channels, carrying out flood protection, maintaining paths, cutting grass, and
constructing hujras (meeting places), mosques or other buildings.
Population
154. The population of the district, according to the 2017 census is 986,973
persons, out of which 51% are males and 49% are female. Average
household size is around 8.84 persons per family with an average annual
growth rate of 3.15.
155. The subproject site is situated in west of Jamrud tehsil. Afridis are the main
tribe of the sub projects area and are further sub divided into Koki Khel Abdal
Khel and Qambar Khel sub tribes.
Table 4.11: Population Details of Khyber District 17
Households Population 2017
Male Female Sex Ratio
Population 1998
1998-2017 Average Annual Growth Rate
111,558 986,973 505,475 481,487 104.98 546,730 3.15
Family Size
156. The average household consists of 9 individuals. The male and female ratio
is 105 males to 100 females18.
Dwelling
157. Mostly the houses are made of mud throughout the District. The houses are
called Qila that is fortresses, which encompasses a number of houses inside.
A house generally consists of two or three rooms with a verandah in the rear
17http://www.pbscensus.gov.pk/sites/default/files/DISTRICT_WISE_CENSUS_RESULTS_CEN
SUS_2017.pdf 18 FRDP Inception Report, Important Agency/FR wise Socioeconomic Indicators of FATA 2012
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
70 | Initial Environmental Examination
and front. Joint family system is in vogue in the District. Every cluster of
houses has a common sitting place called Hujra where the male members
daily meet, discuss and share views on variety of local, national and inter-
national issues with each other’s. It is a common place and is also used as a
guest room. The young spend winter nights in Hujra and arrange for
themselves music programs or food dishes as a pass time activity. It is an
important part of Pakhtoon culture, which is unfortunately changing with the
modern times as people have begun to prefer using personal guest-room.
158. Majority of the houses (100%) of the sub projects area have ordinary
construction (Kutcha structure) with timber roof and mud mortar, whereas
moderate standard buildings with cement masonry (pacca structure) and dry-
stone masonry (semi-pacca structure) were not reported.
Language
159. Pashto is the main language of the area, with a softer form spoken in the
north and a harder dialect in the south.
The Family System
160. Majority households are compound type where one or extended families19
are living. Both Joint and nuclear family systems20 exist in the compounds.
The area of the house and number of persons living in a house is irrelevant
in the context of tribal society. The household data shows that a middle-sized
compound is housed with 25 persons as one extended family. Another same
sized compound is housed with 3 small sized families. The construction
material used for the compound is an indicator of economic status of the
occupants.
161. Men are the dominant force in the household, with final say in the affairs of
all members of the family. Women, by comparison, play a subservient role
and observe strict purdah (veiling). Although divorces or separations are
extremely rare in tribal households, a husband is free to take on additional
wives.
Livestock
162. Livestock not only provides milk, meat, eggs for daily human consumption
but also provides hides/skins and wool/hair and bones/blood for industrial
products and manure /urine for soil fertilization. Livestock is also a source of
rural transport and draft power in Agricultural farming and provides an easy
source of income to majority of the rural population.
19 a family which extends beyond the nuclear family to include grandparents and other relatives. 20 A nuclear family, elementary family or conjugal family is a family group consisting of two parents and their children (one or more).
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
71 | Initial Environmental Examination
163. The erstwhile FATA, being mostly dry hilly terrain, has little land for crops
production whereas sizeable land is available for grazing. The land-less and
small holders (more than 85% of farmers) are mostly dependent on Livestock
production. Livestock provides employment to 50% of the population either
directly or indirectly. About 80% of the income of trans-hum ant families
accrues from Livestock.
164. There is a good enough network of Veterinary Institutions in erstwhile FATA
established since years, providing Veterinary services to the poor Livestock
Farmers; but due to meager amount of operational funds, lack of access to
appropriate know how the SDS is not up to the required level.
Conflicts Resolution Mechanism
165. Erstwhile FATA region is traditionally based on the principle of close
association by tribe or kinship. The people of erstwhile FATA have long been
accustomed to witnessing violent conflict between the members of different
tribes and clans. Inter- or intra-tribe conflict may range from minor family
disputes that create tensions and uncertainty to full-blown armed clashes that
result in irreparable losses. While for many generations the people have
managed to build their lives in this climate of instability, today there is growing
awareness that internecine conflict of this sort is a waste of resources and a
major obstacle in the way of development.
166. The tribal elder (Malik) often serve as an intermediary between people and
the local administrative structures for identifying the priorities. The tribal
council of elders (Jirga) is the main mechanism for decision making on behalf
of the local population and is also considered the key entity for conflict
resolution and providing judgment for punitive actions. The Jirga is essentially
the only mechanism for out-of-court settlements over enmities that span
generations. The tribe’s identity is the key to how local communities exercise
their right to and ownership of natural resources and other assets. The tribal
identity as depicted through the Malik and Jirga is therefore essential for
access and use of resources and is often seen as the only safety net available
to poorer segments of the population. This intricate community system has
survived for centuries with adequate legitimacy by the local authorities as well
as acceptance by local communities as it continues to exert its influence on
communal life. In more recent times, some development projects21 working
in the tribal District have invested in forming local community-based groups
and indigenous organizations that have cooperated with the local Jirga as
well as the political administration for implementing their programs.
21 For example, the ADB supported the FATA Rural Development Project in Khyber, Bajaur and
Mohmand agencies that implemented the project interventions through Community Organizations for delivering services including drinking water supply schemes; irrigation and small dams; natural resource management e.g. raising forest nurseries; etc.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
72 | Initial Environmental Examination
Religious Beliefs
167. A primary survey was conducted as part of the Social Feasibility Study
carried out for the subproject in April, 2019. All the respondents of the Social
Assessment Primary Survey, reported to be Muslim. People generally have
conservative outlook on life and are particular in observance of religious
ceremonies. Majority of the respondents normally offers prayers and keep
fasts during the month of Ramzan. Religious extremism was in full swing for
last few years, but the situation is relatively better now. Majority of the
population belong to Sunni sect of Islam. They believe in Hanafi interpretation
of Shariah. Majority has a religious disposition and practice Islam according
to its fundamental principles. Inheritance is divided according to the Islamic
principles and daughters are given their property right accordingly.
Water Supply and Sanitation
168. Springs, streams, rivers and perennial watercourses serve as the primary
source of water for drinking and domestic use. In mountainous areas, where
natural surface and ground sources are not available, people rely on rain-
water ponds. In the plains where surface water is scarce, shallow wells allow
the people to meet their basic requirements. A combination of factors,
including the large-scale movement of displaced persons from neighboring
Afghanistan, has adversely affected forest reserves which are critical for
watershed protection. The depletion of forest resources has reduced the
water retention capacity of the soil, while ecological and climatic conditions
have led to the low recharge of groundwater sources. As a result, many
springs, streams and perennial watercourses have dried up, forcing people
to turn to deep groundwater sources. Official records for 2014–15 show that
60.0422 per cent of the population is covered by water supply schemes,
mainly through community tanks and taps. Just 27 per cent of supply through
these schemes consists of individual residential connections. Some 85 per
cent of public-sector schemes rely on groundwater, while the remaining use
surface sources23. The majority of groundwater schemes consist of tube
wells, while dug wells and infiltration galleries using electric or diesel pumps
are few in number. The normal water table in most parts of erstwhile FATA is
between 91.44 and 152.4 meters. Surface schemes are gravity-based, using
slopes and gradients to carry water to distribution points. Sources developed
by the works and services department are analyzed for physical and chemical
properties alone, and these results show that the water is fit for human
consumption.
22 Source: Important Agency/FR wise Socio-Economic Indicators of FATA 2016 FATA Secretariat 23 Environmental and Social Assessment (ESA); Rural Livelihood and Community Infrastructure
Project, FATA Secretariat.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
73 | Initial Environmental Examination
169. Traditionally, settlements in the tribal areas have always been widely
dispersed. For reasons of security, meanwhile, communities have generally
preferred to build their houses on mounds and hill-tops. In such areas, the
drainage of rainwater and domestic wastewater was never a problem.
Perhaps as a result, most communities failed to pay much attention to
sanitation infrastructure. But as the population has grown and settlements
have expanded, this arrangement is no longer safe or practicable.
170. The physical growth of settlements without any provision for basic sanitation
is degrading the living environment and polluting water sources. Commerce,
trade and business activities, and related services, add to the congestion.
Today, the lack of adequate sanitation infrastructure poses a serious health
hazard. Children, women and the elderly are particularly vulnerable.
171. Results from the primary social survey of the subproject show that 15 per
cent of houses have “separate” latrines without flush system, 85 per cent
have no access to latrines and use open fields. Overall, it appears that the
population has no access to adequate sanitation in the form of toilets,
sewerage, drainage and solid waste disposal.
Poverty
172. The erstwhile FATA region has historically remained amongst the poorest
parts of Pakistan. There are serious disparities in service provision as
compared to the rest of the country. The absence of visible progress and the
perceived lack of interest by both sub-national and federal governments in
redressing the disparities have consequently deteriorated citizens’ trust in the
ability of government institutions to meet the basic needs of the population.
The general lack of basic services and weak institutional capacity to provide
these have been recognized as drivers of crisis creating conducive
environment for opportunistic militant groups whose economic incentives for
potential recruits greatly outweighed the alternatives available to the people
for their livelihoods.
173. The militancy crisis in KP and erstwhile FATA is a key contributor to stagnant
growth and high unemployment. The ranks of the unemployed have risen
with the intensification of the crisis in 2009/10, and even are likely to continue
rising. These conditions have created a conducive environment for
opportunistic militant groups whose economic incentives for potential recruits
greatly outweigh alternative available options. Many are dependent on the
black economy, drug trafficking and criminal activity for survival.
174. Official statistics on rural income and poverty in the area are quite weak.
Factors underlying the region's poverty include (i) historical, political, and
social isolation; (ii) a legal system reliant on executive and judicial authority
administered through civil servants preferring to maintain the status quo; (iii)
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
74 | Initial Environmental Examination
poor quality and coverage of institutions responsible for the provision of basic
services; (iv) social practices that preclude women’s participation in economic life; and (v) lack of effective institutions for skill training to enable
the labor force to shift from low to high-productivity sectors.
175. Poverty has to some extent made the population vulnerable to extremist
tendencies and criminality. In the absence of viable options to earn a living,
the lure of illicit activities such as smuggling (consumer goods, weapons) and
drug trafficking is as difficult to resist as the call of extremist elements.
Health facilities
176. Health indicators for District
are incomplete and, in many
cases, only estimates are
available. These highlight the
poor state of the health care
system. Health facilities in
project area are inadequate.
District Headquarter Hospital
(Landikotal), Type-D hospital
(Jamrud) and Dogra hospital
(Bara) are main hospitals.
Other than that, there are a
number of private doctors and Hakeems present in the area.
177. Access to health services is severely limited, with 26 dispensaries, 04 T.B
clinic/hospital, 13 Basic Health Units (BHU), 02 Mother Child Health Centers
(MCHs) and 17 Community Health Centers reported in the year 2016 in
District Khyber24.
Social Organization
178. Society is structured on kinship basis in the Project area. Most of the
decisions are made at the household level. The rich and influential people
are accepted as community leaders, especially in collective welfare and
development of the area. Also, the traditional leader in the village is the
“Malik”, the elder who commands respect in the community.
Agriculture
179. Only 8.6 per cent of the total geographic area of Khyber Tribal District is
cultivated, with another two percent recorded as fallow, accounting for
roughly half of all potentially cultivable land. A little over 4.3 percent of the
cultivated area is irrigated, while the remaining farmland relies exclusively on
24 Source: Directorate of Health Services, Merged Area Secretariat, Peshawar
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
75 | Initial Environmental Examination
rainfall. In irrigated areas, water is provided through a combination of delivery
systems, including tube wells, dug wells, lift pumps and traditional communal
canals.
180. The total cultivated area of Khyber Tribal District is about 24,153 hectares,
whilst uncultivated land is 233,523 hectares, with 2050 hectares as forest
area. The total cropped area is 24,148 hectares25.
181. At present no agriculture is being carried out and whole of the command area
shows a barren picture and
there is nothing in the fields.
The information about the
project area revealed that
due to the absence of the
local community, there is no
agriculture for the last many
years. The information also
revealed that in past the
inhabitants of the area were
engaged in agriculture.
182. After the people of the area may return in the near future, they will again
engage themselves in agriculture activities for earning their livelihoods.
Therefore, assured supply of irrigation water through construction of
permanent structure, these areas could be as good for crop production as
normal agriculturally developed areas. It will also help in changing cropping
pattern of the area gradually spreading over a period of 5–6 years or even
more. Eventually the cropping intensity will also be increased.
Education
183. Bearing in mind that Khyber district has a traditional society, with low
economic development and limited facilities, education is not a priority for
them. The prevailing security situation over the last few years has retarded
the pace of growth in education sector. The number of functional Govt.
Schools and enrolment of boys and girls are provided in the Table 4.12 shows
a negative picture of the situation.
25 Source: FATA Development Statistics, 2015-16
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
76 | Initial Environmental Examination
Table 4.12: No. of Functional Govt. Schools and Enrolment in Khyber (2014-
15) 26
Educational Institutes No. of Schools Enrolment
Total Boys Girls Total Boys Girls
Primary Schools 327 198 128 59188 33827 25361
Middle Schools 26 14 12 1782 1301 481
High Schools 27 23 4 6441 5428 1013
Higher Secondary School 4 2 2 2118 1446 627
Govt. Degree College 4 3 1 3346 3076 270
Technical School 2 2 - 231 231 -
184. Entries to education in Khyber district normally starts from primary level and
children of age five years and above are entitled to be formally enrolled. The
overall literacy rate in Khyber district for both sexes was 49.40%, which is far
less than the national average of 58% (2013-14). Similarly, the adult literacy
rate in the region is 28% as against the national average of 75%.
185. The development statistics show a marked gender gap in literacy ratio as
male adult literacy ratio in Khyber district stands at 76. 30% compared to just
16.60% female literacy rate. Primary level net enrolment rate for boys and
girls is 52.1% compared to 65% across Pakistan.
186. Females are particularly unable to access middle and secondary schools.
These schools are far away from the population or the majority of hamlets.
Female mobility is restricted in Khyber district due to cultural limitations.
Transport facilities are often not available, while the road network is non-
existent or badly constructed. These are the major factors hampering access
to middle and secondary education for girls.
187. A primary school for boys is present in the subproject area which is non-
functional due to non-availability of staff.
Food
188. Simplicity is the haul-mark of the food of the people of the area. Rice is a
staple dish especially for dinners. Maize bread with local vegetable Saag and
Lassi is offered to guest as a seasonal specialty in summer.
26 Source: Directorate of Education, FATA, Peshawar
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
77 | Initial Environmental Examination
Dress and Ornaments
189. People wear the traditional Pakhtoon dress of Shalwar Kameez and head-
wear. Generally, the people wear handmade Dir caps while notables wear
Pugri and Kula, but this tradition is gradually fading out. Women folk wear
Shalwar Kameez generally use black printed cloth and Chadder/veil and for
Purdah they use Burkas (veil).
190. Their working and festival dresses are all the same with the exception that
they wear new dress on festival. In winter season a chadar or woolen blanket
is used by the males. While in the case of females their dress remains the
same.
191. Women use ornaments such as Bangles, Bracelets, Pazeb, Karah, Nath,
Golden rings and earrings.
Economic Features
192. Historically, and particularly during the Soviet invasion of Afghanistan
beginning in 1979, the region was a major center for opium production &
trafficking and weapons sale. Today, the transit trade with Afghanistan is a
major source of employment for the local population. The economy operates
on an informal basis and is undocumented, since few laws providing for the
regulation of economic activity have been extended to the tribal areas.
193. The people of the subproject area are not widely educated. They migrate to
down districts in search of jobs or any other labor. Government services are
a cherished source of livelihood for many. Agricultural farming (25%), small
scale business (08%) and working on daily wages basis (55%) are also major
providers of job and sources employment in the subproject area. About 02%
of the employed population which is predominantly male works as migrant
workers in Gulf countries while just less than 10% of the population is
reported as employed in other provinces of Pakistan.27
Mining
194. The mineral deposits in Khyber Tribal District include Soapstone, limestone,
dolomite, ciliate, silica sand, barite, mica, graphite and marble. Mullagori
marble is one of the largest deposits in the world. Soapstone is the second
largest mineral found in the area.
195. Extensive deposits of marble are found at several places in Khyber district.
The marble is associated with the calcareous rocks in the Mullagori area. The
marble is processed in different green and black colors. The marble is
processed in different marble factories in KP, and in other parts of the
country.
27 Primary Social Survey of the Sub Project, 2019.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
78 | Initial Environmental Examination
Roads
196. According Socio-Economic Indicators of FATA 2016, total coverage extends
to 662.96 kilometers of blacktop and another 218.74 kilometers of shingle
roads in the year 201628. The sub projects area is accessible through all-
weather road.
Telephone Facilities
197. Landline telephone facilities are not available while Cellular networks are
available with limited network in the subproject area.
Sites of Historical Significance
198. The prime attraction in this
region is the Khyber Pass
situated some 5 kilometers to
the west from Jamrud. It runs
to a length of about 40
kilometers up to Torkham
check post at the Pak-Afghan
border. For centuries this pass
has been witnessing
numerous kings, generals and
preachers passing through it.
Khyber is associated with
numerous events in history, which have brought about momentous changes
in the annals of mankind. It is a collection of mountain ranges, barren and
crazily piled hills; forts of steel and rock stop every vantage point and naked
road.
199. Baab-i-Khyber, the gateway to Khyber, has been constructed at the
entrance of the historic Khyber Pass near Jamrud. The platform, for visiting
dignitaries and containing
useful and authenticated
information which present in a
nutshell, the historical
background of the pass, the
secrets of its magical charm
and strategic importance, have
also been constructed.
200. Jamrud Fort is visible from a
distance like an old battleship.
Looking ruggedly majestic with
28 Important Agency/FR Wise Socio-Economic Indicators of FATA 2016, FATA Secretariat.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
79 | Initial Environmental Examination
its jumble of towers and loop hole walls, the fort contains the grave of its
builder, the famous Sikh General Hari Singh Nalwa, who died here in action
against the forces of the Amir of Kabul in 1837 AD. The fort; coarsely
constructed of stone daubed with mud plaster, was built by the Sikhs in 1823
on the site of an earlier fort. The modern stone arch spanning the road dates
from 1964.
201. Near the narrowest point of
the pass, about 15 Km from
Jamrud is Ali Masjid and a
large fort and a British
cemetery. The valley walls
bear insignia of British
regiments that have served
here. In the cemetery here
are the graves of British
soldiers killed in the Second
Afghan War of 1879. This
was the famous battle of Ali
Masjid. Regimental insignia
are carved and painted on to the rock faces at several places along the road,
with the Gordon Highlanders, the South Wales Borderers, and the Royal
Sussex, Cheshire and Dorset regiments standing in one doughty group. After
the gorge, the pass opens out into a wide fertile valley dotted with Pashtun
villages. True to form, however, these villages look more like forts, with high,
crenellated mud walls running between watch-towers pierced with narrow
gun slits.
202. Ali Masjid Fort is located at
the narrowest portion of the
Khyber Pass, through which
only a loaded mule or Camel
could pass till as late as the
mid nineteenth century. The
fort was built by the British in
1890. The ruins of a Buddhist
Stupa can also be seen in the
area. There is also a mosque
and a shrine in the memory of
Hazrat Ali (RA), who visited
this place according to a local
tradition. There is also a huge boulder which carries the marks of a hand
believed to be that of Hazrat Ali (RA). Even Khyber was named after the
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
80 | Initial Environmental Examination
Khyber of Arabia, where Hazrat Ali (RA) accomplished a great deed of
valour.
203. Shpola Stupa, a Buddhist ruin
dating from the second to the
fifth centuries AD, stands to the
right of the road and above the
railway at the village of Zarai,
25 kilometers (16 miles) from
Jamrud. The Stupa has a high
hemispherical dome resting on
a three-tiered square base.
Some beautiful Gandharan
sculptures were found here
when the site was excavated at
the beginning of this century.
Some of the finds are now in the Peshawar Museum. The side of the Stupa
lacing the road has been restored.
204. On a hilltop to the left of Torkham is the ruined Kafir Fort, a Hindu relic of the
ninth century AD. On this ridge in 1919, the British and Afghans fought one
of the last engagements of the Third Afghan War. The top of the hill is now
Afghan territory, with a commanding view down on Pakistani installations and
forts.
205. No sites have been reported around the sub projects site of any cultural and
historical significance.
Gender Issues
206. Tribal society is dominated by men. Cultural tradition, social practices and
low female literacy have left women in a vulnerable position. They are for the
most part restricted to performing household work, and are excluded from
decision-making both on the domestic front and at the community level.
Women’s access to education and health care is limited because such services are not available close to home.
207. The male domination in total population is consistent. Although the women
about ½ of the population but they are not visible in public life of the villages
due to strict purdah/veil system. The FGDs confirmed that women’s role in the tribal system is limited to unpaid housekeeping and very small-scale
productive activities at household level and they are not involved in any
economic activity
208. Women in the area play a dominant role in running the household, rearing
and guiding children, managing household finances, and providing much of
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
81 | Initial Environmental Examination
the labor for agriculture and animal husbandry. They do not normally have a
public role, particularly in interactions with the broader society.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
82 | Initial Environmental Examination
PROJECT ALTERNATIVES
No Project Option
209. Project alternatives have been considered with consideration of their ability
to match immediate demand and then keep pace with emerging demand
while ensuring capture of available yield in the stream. With an increased
awareness of the scarcity of water as a resource, short-term supplies may be
achieved through demand management strategies, water use efficiency,
combined with research and development programs that reduce
consumption.
210. Agricultural demand has the potential to be met through the take up of
currently unutilized, or under-utilized, water resources.
211. The use of groundwater within the area is limited to primarily stock and
domestic purposes and supplies to small towns and is not considered to be
a feasible alternative supply to the Project
212. Inability to support the Project increases inherent risk of supply from a single
source. The primary objective of the Project is to increase the agricultural
production. The ‘no project’ option has the potential to inhibit increase in the crop production. Limiting agricultural production in particular has the potential
to adversely impact the area economy with large-scale agricultural
development potentially seeking alternative locations interstate due to this
water supply constraint. With the implementation of project leading to
increase in agricultural yields and production, the additional generating
benefits are:
• Additional revenues directly from the project output.
• Crop diversification: The introduction of irrigation enables farmers to
diversify their crops based on local market’s demand and export.
• Employment opportunities: During the construction phase there will be
improved employment opportunities for local people and new comers.
• The project will provide water for cultivation of crops, irrigated fodder
development, domestic purpose, livestock etc.
• Food security further improved: In this case, the proposed small-scale
diversion weir irrigation will have a paramount importance in further
improving the overall living conditions of the people residing in and
around the project environment and will play its own role in alleviating
food shortage.
• Improved forage varieties provided and increased.
• Animal productivity and production.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
83 | Initial Environmental Examination
• Increase the opportunities for plant establishment of nursery sites and
forest seedling production.
• Forest tree plantation.
213. Water availability is scarce in area hence the proposed project will contribute
positively to the project area. The no project option is not viable option.
Project Siting Alternatives
214. Based on topography, command area, available flow and site visits,
alternative arrangements for project formulation have been done for a simple,
sustainable and suitable project layout. The perennial flow of the khwar may
be diverted for irrigation by means of weir construction. During the site visit
of the project, the whole stretch of the khwar was inspected for suitable weir
location. Entire stretch of the khwar was inspected at upstream and
downstream for exploration of other possible weir locations so as to irrigate
entire command area available along the banks of khwar. Technically there
is no other source of water or place diverting water for irrigation purposes in
Tarkho Kas however the following siting alternatives were considered for Tor
Dara sub project.
Alternative-1: Concrete Gravity Dam at Tor Dara
215. Initially the Tor Dara khwar/ nullah was studied for construction of concrete
gravity small dam and a narrow gorge was found at a distance of
approximately 2 Km upstream of the currently proposed weir but the
topography of the nullah at this place was found very steep slope where the
formation of reservoir with 15 m high dam was not possible and hence this
option was discarded on technical basis.
Alternative-2: Construction of Weir Upstream
216. It was proposed that a weir should be constructed at the above-mentioned
site initially selected for construction of small dam which will irrigate both the
command areas available on the left and right side of the nullah. The
available flow was not enough to irrigate both the command areas.
Furthermore, water mills and Micro Hydro Power plants (MHPs) were located
downstream where no water will be available for them to operate which will
result in social issues. Hence this option was also discarded on technical and
social basis.
Alternative-3: Proposed Tor Dara Weirs
217. The Tor Dara sub project comprises of two weir one at the main Tor Dara
Nullah named as Tor Dara Weir and other at the tributary of Tor Dara Nullah
named as Natu Khel Weir. At both the proposed weir sites the previous
abandoned irrigation system signs are available which helped in planning
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
84 | Initial Environmental Examination
irrigation channels in hard rock vertical cliffs available at both banks of Tor
Dara Nullah.
218. The location of the weir has been fixed by considering the natural conditions,
the project purpose, command area and construction difficulties including
topography and geology. The detailed considerations for the selection of weir
site are as follows.
• Suitability of the weir structure type;
• Geological and topographic conditions;
• Technically most suitable site to command the irrigable area; and
• Minimum environmental degradation.
219. By considering the above-mentioned parameters the weir sites have been
proposed near Natu Khel village which is situated approximately 04 km at
upstream on Tor Dara Nullah from Main Tirah-Miadan Road in District
Khyber. Both the weirs axis have been proposed on the location where
perennial flow was visually observed and the available command area could
easily be irrigated without creating any social issues.
220. The diversion weir has been fixed at the location keeping in view the width of
the Nullah, elevation of the weir axis with respect to the command area and
the ease of construction to the contractor. It has been considered during
project site selection that change in Nullah regime should be avoided up to
maximum possible extent with the construction of weir. The width of Nullah
flood plan at proposed weir location is about 30m, while active perennial and
low flood creek is only 10m wide, therefore weir has been proposed in the
active creek portion of Nullah which is 10m wide. The wing walls of proposed
weir is properly embedded in the side hill to fix the flow regime at the weir top
permanently at right side while at left side plum concrete protection wall is
proposed at both upstream and downstream side to protect the low height
adjacent fields.
Technological Alternatives
221. Tor Dara Nullah and tributary of Tor Dara Nullah have an average bed slopes
of 0.028 m/m at upstream and d/s of proposed weirs axis which will result
high flow velocity during floods and will bring coarse sediments. A
conventional weir at proposed location will cause sediment deposition at
upstream, which necessitates the flushing arrangements by means of
providing Bottom outlets or undersluice section.
222. For the diversion of irrigation discharge Tyrolean intake type of structure is
proposed and the outlet is at right side of the weir. The overall diversion weir
comprises an overflow sections for flood routing, a depressed Tyrolean
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
85 | Initial Environmental Examination
section to divert the flow for irrigation, Wing walls at both side for proper flow
channelization and plum concrete protection wall at left side both upstream
and downstream of weir.
223. The Delivery Box Channel/Conduit is proposed to align at right side of Tor
Dara nullah protected with plum concrete protection wall up to collection
sump 01 proposed at RD 0+100m. A free flow spillway is proposed at
collection sump 01 to off-load the additional flows. From sump 01 power
channel will emanates and run at longitudinal slope of 1:250m and dissipates
in sump 02 where water will be distributed between MHP and for irrigation.
After sump 02 irrigation channel will start and run upto RD 4+160m with
1:250m longitudinal slope and end at the end of proposed command area of
Tora Dara weir.
224. Tyrolean intake weir is the most appropriate diversion arrangement for the
perennial streams. A Tyrolean section is slightly deeper portion provided in
main weir, it consists trash rack at bottom and embedded channel beneath.
The length of rack is provided according to design discharge to be diverted.
Bars of the rack are laid parallel to flow and inclined in the direction of flow.
The flow passing over the rack, is collected in the embedded channel to the
limit of its capacity.
225. The embedded channel has 1.5% bed slope to convey the sediments laden
discharge outside through conveyance box channel connected at its end.
After removal of coarse sand and pebbles from diverted discharge at main
sump comparatively clean water will be delivered into the conveyance system
to irrigate command area.
226. The oblique arrangement of the trash rack prevents it from being clogged by
bed load or floating materials, resultantly, the intake from being obstructed.
227. In order to ensure the diversion of design discharge when there is blockage
of the rack due wedging of stones or leaves and branches trap in the rack,
length of the rack has kept 20 % more than its required length. Inclination
angle of the rack with horizontal plane has been kept 15 degree in the
direction of flow. The spacing of rack bars have been kept 10mm, hence only
the particle with less than 10mm size could get into the embedded channel
and box channel. The particle with more than 10mm will slip down the weir
over trash rack to the cistern of weir.
228. Therefore, based on simple and sediment free operation a low height
Tyrolean weir has been proposed for the Tor Dara weirs sub project.
Selection of the Tyrolean type weir has been accomplished on following
bases:
• Self-operated system;
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
86 | Initial Environmental Examination
• Insured diversion of water during minimum flow season;
• Self-creation of upstream channelization and minimize silt deposition
at upstream of intake;
• Ease in construction; and
• Cost effectiveness.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
87 | Initial Environmental Examination
ENVIRONMENTAL IMPACT ASSESSMENT AND MITIGATION
MEASURES
Impact Assessment - Overview
229. The environment assessment study has disclosed that the sub projects are
not likely to have any severe negative impacts on the environment and
people of the area. All the potential impacts which have been identified during
the present assessment are associated with the construction stage, are minor
to moderate in severity; and can easily be avoided (through good design and
construction planning) or mitigated (through proper implementation of the
EMP). On the other hand, the sub projects will be beneficial particularly for
the local population on creation of job opportunities and extremely beneficial
for irrigation. Significant indicators of the project are mentioned below:
▪ Construction of irrigation system in virgin lands tends to change water and
land use patterns that might have potential of severe, long term
permanent impacts (positive) on the environmental settings of that area.
▪ Construction activities in general could lead to interference with local
community life.
▪ Most beneficial impacts associated with the improved channel condition,
management and efficient and equitable water distribution are of long-
term in nature.
▪ After completion of the construction works, the improved canal water
supplies will contribute to increased cropping intensity resulting into
increased use of agricultural inputs like fertilizers and pesticides which
may cause limited adverse impacts and need to be addressed.
▪ The improved water supplies will boost the agriculture and improve the
living standard of the community in the project area.
▪ The sub projects will also help to regulate the groundwater abstraction to
neutralize the lowering trend.
▪ The sub projects will also provide unskilled jobs during the construction
phase and a limited number of jobs in operations. This will be a bonus for
the people of the area, many of who are used to having to travel down
country for employment.
Impact Area
230. The subproject impact areas mainly involve weir and construction areas. The
vegetation cover of the catchment is good. The weir sites are however
located in and around shrub lands, hence no felling of trees is involved.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
88 | Initial Environmental Examination
Figure 5.1 Impact Area
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
89 | Initial Environmental Examination
231. Table 5.1 considers the potential impacts at various stages of the project, and
assesses the category of the impact, classifying them as negligent, moderate
or high. Each category is defined as under:
Negligible: No or minimum impact
Moderate: Potential impact but can be mitigated (Site Specific)
High: significant adverse environmental impacts which are irreversible,
diverse, or unprecedented
232. The section further goes on to explain the table, by describing those impacts
that have moderate to high impact, but can be mitigated.
Table 5.1 Screening of Environmental Impacts; Construction and Operation
Stages
Potential Environmental Impacts Project Stage Impact Categorization (N=Negligible, M=Moderate, H=High)
1. Land resources
1.1 Excavation Construction M
1.2 Waste generation and disposal Construction N
1.3 Labor camps, storage, approach roads Construction M
1.4 Soil pollution due to fuel and oil spillage (related to construction machinery)
Construction M
1.5 Agriculture land damage Construction N
1.6 Earth Borrow Site Construction M
1.7 Installation of cement mixing plants Construction N
1.8 changes in Soil Characteristics due to labour camps, and machinery yards
Construction N
1.9 Leaching of soil nutrients and changes in soil characteristics
Operation N
1.10 Soil pollution due to excessive application of fertilizers and pesticides
Operation M
1.11 Construction Material Leftover Construction & Operation
N
2. Hydrology and Water Resources
2.1 Contamination of surface water due to washing (machinery and other related materials)
Construction M
2.2 Drinking water supply Construction M
2.3 Municipal waste disposed into the stream Construction M
2.4 Water quality & sedimentation load Operation M
2.7 Excessive use of irrigation water for cultivating high delta crops
Operation M
2.8 Contamination of water due to farm runoff Operation N
3. Air Quality and Noise Pollution
3.1 Dust and smoke and other pollutants from plants and equipment
Construction M
3.2 Smoke from burning of waste or firewood Construction N
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
90 | Initial Environmental Examination
3.3 Noise control from use of old and/or outdated machinery
Construction M
3.4 Dust Emission from Stone quarrying and transportation
Construction M
4. Biological Resources
4.1 Damage to flora and fauna Construction N
4.2 Habitat fragmentation Operation N
4.3 Aquatic Life Construction and Operation
N
5. Socioeconomic and Cultural Issues
5.1 Tribal tensions and rivalries All stages M
5.2 Impact on civic infrastructure (education, health, roads, water supply, electricity)
Construction N
5.3 Community safety risks due to both accidental and natural hazards
Construction and Operation
M
5.4 Health and safety of labor and employees at construction site
Construction H
5.5 Aesthetic/scenic value Operation N 5.6 Employment of alien labor Construction N
Negligible: No or minimum impact, Moderate: Potential impact but can be mitigated, (Site
specific) High: significant adverse environmental impacts that are irreversible, diverse, or
unprecedented
Pre Construction Stage
Assure Compliance with Relevant Construction Field Legislation
233. There are certain laws and regulations in the country before undertaking any
construction work of developmental project. Therefore, No Objection
Certificates (NOCs) will be required as legal complications may lead to delay
in sub projects construction.
Mitigation
• Acquire construction permit/ Environmental Approval/ NOC from local
authorities.
• Preparation SSEMPs for each site and get them approved by the
Consultant/PMU with endorsement of ADB, before the construction
works start.
• Provide water management guidelines if subprojects are executed
near surface watercourse.
Development of Strategies
234. Some strategies need to be developed prior to the construction of the project
as problems may arise due to non-compliance. It will help the project staff to
carry out the construction and of the sub projects in organized manner. This
will be highly beneficial in long terms.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
91 | Initial Environmental Examination
235. An Operation Environmental Action Plan (OEAP) needs to be prepared
demonstrating the manner in which the Contractor/Operator will comply with
the requirements of management plans proposed in EMP/SSEMP.
236. The following strategies and procedures will be developed prior to the
commencement of Project operations:
• Project specific security and public access control strategy;
• Project specific waste management strategy
• Project specific air and noise control strategy;
• Project specific traffic control strategy;
Construction Stage Impacts
Excavation
237. Being located in a hilly terrain, the weirs will require excavation for alignment
of abutments and land leveling. The quantity of excavated material at Tor
Dara and Tarkho Kas weirs is 2827.38 m3 and 1778 m3 respectively. Such
physical work has the propensity to alter the landscape, due to cutting of trees
and/or leveling mounds and hills, and also create dust pollution. In case of
these weirs, the sites do not have extensive vegetation in terms of trees.
238. Any excavation work during the construction activities, whether permanent or
temporary, may lead to loss of soil. Erosion of soil can also occur from
removal of vegetation cover, runoff from unprotected excavated areas, etc.
Excavations on slopes would also decrease its stability. It is expected that
minor level of short-term risk is associated with the type of construction
activities that are likely to take place. The current land formation is fairly
stable therefore no major impact is associated with regards to slope stability.
Mitigation
239. Vegetation loss will be avoided as much as possible and limited to
demarcated construction area. Slope stabilization measures will be adopted
such as adequate vertical and horizontal drains, cross drainage etc. Slope
movements will be monitored around excavation work areas. Top six inches
soil should be protected through stockpiling before excavation and should be
placed back after completion of construction work. Excavated material shall
be preferably reused after approval of quality control engineer of CSC. Non-
reusable excavated material shall be safely dumped and leveled in barren
land with approval from Environment specialist of CSC and dumping. The
location of the dumping area should be selected in joint survey of contractor
and CSC and should be provided in SSEMP.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
92 | Initial Environmental Examination
Waste Generation and Disposal
240. During the construction phase, most of the waste generated will be related to
construction. Construction waste will involve debris due to cutting of stones,
residual RCC material, domestic waste and other associated waste from
construction site. Beside this waste from Kitchen etc. will also be generated
which is estimated to be less than 01 cubic meter. This is a medium negative
impact but can be mitigated.
Mitigation
241. To minimize environmental impacts and avoid any need for disposal of
earthwork materials or the importation and unnecessary storage of earth, the
project will maximize the reuse of excavated materials. All of the construction
activity will be contained inside construction area. Solid waste generation
should be reduced, reused and recycled. Any residual spoil will have to be
disposed in environment friendly manner, where it will be leveled and
landscaped.
242. Waste from the project construction area and office area shall be segregated
and collected by the Tehsil Municipal corporation for dumping at approved
Land fill site or if small amount than will be arranged natural gully uncultivable
land for dumping with approval from CSC Environment Specialist.
243. To be made contractor’s obligation through contract document, an SSEMP
will be prepared by the contractor and waste management plan will be a part
of it.
Labour camps, storage and approach roads
244. Due to availability of ample community owned barren land, location, material
yards, equipment yards and approach roads will not cause any serious
problem. Bearing in mind the quantum of work no large size labor camp will
be established as most of the non-technical labor engaged will be of local
origin and would not require housing. Therefore, this is a matter of moderate
significance and can be easily mitigated and managed through proper
mitigation measure.
Mitigation
245. The contractor will, in consultation with RE (CSC), resolve the exact location
of all these facilities within the barren land owned by the local community that
will be provided by the community temporarily and free of cost. The location
of these facilities will be at least 500 m away from the settlements. The
contractor will not locate and construct any facilities without the written
approval of the CSC.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
93 | Initial Environmental Examination
Soil pollution due to fuel and oil spillage from construction machinery
246. Leakage of oil from machinery and vehicles and the dumping of oil will
permanently create contamination along with allied physical, biological and
social losses. This can be mitigated through effective application of the
maximum spill regulations.
247. “Guidelines for Oil Spill Waste Minimization and Management issued by International Petroleum Industry Environmental Conservation Association29
are as follows: -
248. Soil contaminated by minor spills/ leakages (defined as leaks from
vehicles, machinery, equipment or storage containers such that the area and
depth of contaminated soil is less than 0.92903 sq. meter and 0.0762 meter
respectively) is to be scraped and disposed of accordingly in environmentally
friendly manner to ensure protection of water sources.
249. Moderate spills defined as spills of volume less than or equal to 200 liters is
to be contained and controlled using shovels, sands and native soil. These
equipment’s and materials are to be made available at camp sites during the
operation. The contaminated soil is to be excavated and stored in a burn area
lined with an impermeable base. Depending on the volume, the contaminated
soil is either disposed-off through by specialized treatment such as
bioremediation or through approved contractor.
250. Major spills (defined as spills of volume much greater than 200 liters) require
initiation of Emergency Response Procedures and Oil Spill Contingency
Plan. These spills are to be handled and controlled according to the Plan
and require special treatment such as bioremediation and through approved
contractors.
Mitigation
251. Strict rules will be imposed on workers and labors to ensure that no such
spills are caused. If the spills take place, it must be followed by treatment
prescribed above as per the degree of spill. An Oil Spill Management Plan
containing specific mitigation measures to be part of contractor site specific
environmental management plan are:
• Spill prevention trays will be provided and used at refueling locations
• On-site maintenance of construction vehicles and equipment will be
avoided, a vehicle maintenance area with impermeable floor will be
designated.
29 http://www.ipieca.org/resources/good-practice/oil-spill-waste-minimization-and-management/
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
94 | Initial Environmental Examination
• Regular inspections will be carried out to detect leakages in
construction vehicles and equipment.
• Fuels and lubricants will be stored in covered and dyked areas,
underlain with impervious lining.
• Spill control kit (shovels, plastic bags and absorbent materials) will be
available near fuel and oil storage areas.
• Contaminated soil will be removed from the site and disposed in a
manner to ensure protection of water sources
• Emergency plan for spill management will be prepared and inducted to
the staff for any incident of spill.
• The bottom of any soak pit or septic tank will be constructed at least
100 meters away from springs and water bores
• Record of spills and Volume of removed contaminated soil will be
maintained.
• Record of remedial measures taken will be maintained.
Agriculture Land Damage
252. Land leveling, excavation and construction of channels and distributary
channel may cause damage to agricultural land. In case of these sub
projects there will be no agricultural land damage as cultivated area is away
from the project site.
Mitigation
253. It is contractor’s obligation not to cause such damage and strictly follow the
design. Top six inches soil will be protected through stockpiling and land will
be restored to its previous condition after completion of construction works.
Impact of taking borrow material from earth borrow site
254. There is likelihood for obtaining the earth fill material for On-Farm Water
Management works. Excavation and cutting activities could cause adverse
environmental impacts including sliding, soil erosion and drainage on the
surrounding areas.
Mitigation
• No private land will be acquired for the borrow areas.
• The contractor will ensure that selected borrow areas on irrigation
land are clearly demarcated and approved by the engineer including
the allowed depth of the excavation before starting excavation.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
95 | Initial Environmental Examination
• The borrow areas will be leveled. The Contractor will not leave the
borrow pits in such a condition that they are unsuitably filled with rain
water and cause the problem for the community.
• If the borrow area is near to the settlements, then it should be fenced
completely.
• If agriculture land needs to be used as borrowing area, then the
Contractor will adopt the following methods during the digging
process.
• Fix the location of excavation.
• Remove thirty centimeters of the top soil and keep it on reserved site
for re-spreading in the field.
• Excavate up to one-meter depth.
• Maintain the slope as far as possible.
• Place the top soil back during the restoration process.
• Pay compensation for any damages/ crop losses.
255. Following the above criteria, after identification and approval by the
Engineers, the Contractor will mark borrow areas location in his Site-Specific
Environmental Management Plan (SSEMP).
Construction material leftovers
256. Construction material leftover may likely happen after the closure of
temporary construction sites. This might have short term and minimal
insignificant impact on the project area.
Mitigation
• All shivers and material that remain after the closure of temporary
construction sites are to be removed from the location and re-
used/re-cycled where possible.
• All remains are to be disposed of in a manner that will not be harmful
to environment.
Impacts on Hydrology and Water Resources
Contamination of surface water due to washing
257. There is a tendency to wash construction machinery and equipment using
the stream water, eventually draining the same into the stream.
Contaminants like motor oil, diesel and other such materials pollute the water
body in the short run, causing harm to aquatic life, and affecting the overall
water quality.
Mitigation
258. Contractor will demarcate a washing area for all sorts of washing activities,
with running water facility connected to a dedicated drain flowing into the
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
96 | Initial Environmental Examination
septic tanks. There would be restriction on servicing/ washing of vehicles and
equipment at site.
Drinking water Supply for Contractor’s Staff
259. Since the site and adjacent area is away from settlements, there is no
connection available to a water supply scheme. There are springs in the
catchment of the weir, but they can be far off. Stream water will need to be
tested and used for drinking purposes.
Mitigation
260. Contractor, under the guidance of Environment Specialist of CSC, will get
stream water tested for chemical and biological contaminants, and assist in
providing filtration to make water drinkable. There are numerous cost-
effective water treatment models available in order to mitigate chemical
and/or biological contamination. Sand filtration, Chlorination, UV treatment
and oxidation are a few such methods.
Municipal waste disposed into the stream
261. Municipal waste generated due to human activity is a concern if it is disposed
and drained into the stream.
Mitigation
262. Solid waste bins will be placed at labor eating and resting areas. Latrines and
washing areas with septic tanks will be erected by the contractor at the
construction site. Waste from the project construction area and office area
shall be segregated and collected by the Tehsil Municipal corporation for
dumping at approved land fill site or if small amount then a natural gully or
uncultivable land will be arranged for dumping with approval from CSC
Environment Specialist.
Impact on Air Quality and Noise Pollution
Dust from construction and smoke from plants and equipment
263. Due to nature of the construction, involving excavation, land leveling and
clearing, a lot of dust will be produced. Heavy machinery will be used to carry
out these activities which will result in vehicular emissions as well as other
exhaust fumes.
264. Dust or other pollution from stored material is also inevitable, moderately
significant and can be mitigated.
Mitigation
265. Contractor’s contractual obligation will include keeping the dust and smoke
within permissible level by using machinery which is well maintained and with
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
97 | Initial Environmental Examination
low noise land all Kutcha roads and paths will be sprinkled with water after
regular intervals.
266. The contractor must avoid/ control the dust and smoke by carefully storing
and distributing the construction material so as to cause minimum dust which
again should be within the acceptable limits.
Noise from use of old/and or out-dated machinery
267. Old and poorly maintained machinery generates higher decibels of noise and
cause noise pollution for workers in the close vicinity of heavy machinery.
Mitigation
268. Contractor’s contractual obligation is to use new, well maintained and low
noise machinery preferably during day time. The drivers, operators and
workers working on or near the heavy machinery must be provided ear plugs.
269. The contractor will ensure use of newer, well maintained machinery that
creates minimum noise and emissions, as per National Environmental
Quality Standards (NEQS 2000). Environment Specialist of CSC will ensure
that this clause is added to the biding and contract document. Night time
construction activities will be strictly discouraged, and may only be carried
out in exceptional cases, with prior permission of Resident Engineer. Noise
monitoring will be carried out near sensitive receptors on a monthly basis.
The NEQS for noise residential areas is 55 dB (A) in the day time and 45 dB
(A) at night. It is recommended that noise levels close to sensitive receptors
do not exceed 55 dB (A) during the day time as required by the NEQS.
Dust Emission from stone quarrying and transportation
270. This will not cause any impact on the immediate project area except that the
vehicles carrying the stone shall exert additional traffic load on the roads
leading to the project. Crushed stone will fall on roads.
Mitigation
271. Contractor shall use the road network carefully and repair any damages
immediately. During transportation, covering of vehicle with sheet will be
done. Unloading of vehicles will be done on designated sites.
Impact on Biological Resources
272. No major change is expected in the habitat of the natural flora or fauna. No
tree will be cut for the project construction. Small readjustment of place may
be made by some birds and rodents. Similarly, negligible impact on aquatic
life is anticipated.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
98 | Initial Environmental Examination
Mitigation
273. Environment Specialist of CSC together with the line departments will
ascertain the status of the site area in terms of occurrence of wildlife species,
flora and aquatic life. And in accordance, recommend a watch and ward
system that will be based on partnership between communities, wildlife,
forest & fisheries departments and political administration. Each partner’s roles will be specified at the onset, and responsibilities assigned. Till the
completion of the survey, contractor will ensure no extraction takes place
from the surrounding vegetation for fuel wood or hunting of any birds by the
labor employed. If such a case is witnessed, it will be brought to the notice of
the project management as well as the concerned Assistant Commissioner.
274. Contractor’s obligation to strictly respect the limits of construction site. Cutting of trees will be strictly prohibited and if no alternate is available plantation of
trees will be done in case any tree is cut for project activities. Tree cutting will
be restored by planting four trees against each tree cut.
275. As per Environmental Safeguard policy of the project, sufficient amount has
been allocated for tree plantation for better environment. For this purpose,
Watershed Management Specialist in consultation with District Forest Officer
(DFO) will prepare a tree plantation plan by Watershed Management
Specialist in consultation with District Forest Officer including the type of
species, location for plantation and other necessary information. This plan
will also compensate any unlikely tree cutting involved during project
implementation. Selection of borrow area with least vegetation cover. Soft
start for allowing time to reptiles to move away from the project site
Restriction and prohibition on hunting, shooting, trapping, and poaching of
wild species. No night time activity will be carried out. Photographs of the
project area will be taken at pre and post project stage.
Impacts on Socioeconomic, Cultural and Archaeological Issues
Tribal Tension and Rivalries
276. Since the subproject will benefit a certain number of beneficiaries and their
agricultural land, a tendency of rivalry exists which can cause tensions
amongst neighboring tribal households. Although terms of partnership have
been signed with the intended beneficiaries, the risk will still remain.
277. Other socio economic cultural and archaeological impacts can be:
• Disturbance to existing services: education, health, electricity,
water supply or signboards.
• Aggravation of any disputes on land ownership.
• Any need for land acquisition.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
99 | Initial Environmental Examination
• Access to other construction materials.
• Adverse effects on known archaeological sites.
• Dealing with chance finds.
• Problems to Health and Safety of labour and employees on
construction work and provision of safety equipment to workers
on site.
• Employment of locals on the project.
• Possibility of spread of HIV/AIDS amongst the project labour
and adjoining population.
• Rise in prices of essential commodities.
• Gender Issues.
• Recreational facilities for public.
• Any spots of religious significance e.g. Mosques, Tombs and
Shrines etc.
• Discovery of Antiquities
Mitigation
278. For matters pertaining to social obligation and benefits of the communities, if
needed, a social Framework Agreement shall be signed by the RE with
communities to ensure their participation and full satisfaction in matters
pertaining to them. All matters where contractor is involved, these should be
made as his contractual obligations.
279. Project Team along with the Social Organizers of Project Implementation Unit
(PIU) will ensure continuous liaison with the communities throughout the
construction phase of the project, so as to identify any incident or cause of
dispute/grievance in time. Relevant political authorities will be kept abreast
of the progress, as well as any such issue if in making.
280. If, during the execution of the activities or excavation, any material is
discovered onsite, which may be considered of historical or cultural interest,
such as evidence of prior settlements, native or historical activities, evidence
of any existence on a site, which may be of cultural significance, all work shall
stop and the supervising contracting officer shall be notified immediately. The
area in which the material was discovered shall be marked and the evidence
preserved for examination. The contractor is required to develop Chance
Find Procedure as part of the SSEMP.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
100 | Initial Environmental Examination
Impact on Civic Infrastructure
281. Construction activities cause additional wear and tear of roads and cross
drainage. Such situation can arise through carelessness of the heavy
machinery drivers / operators. A considerable damage to paths, roads and
drainages structures may occur if the drivers/operators are not made aware,
trained and bound to be careful. It is a concern of minor significance but can
be mitigated through care and regulation.
Mitigation
282. Contractor’s contractual obligations to impose strict control over operators
and drivers of all types of vehicles/machinery. Awareness may be given to
them. The position of infrastructure and underground installation should be
precisely located to avoid any damage. Should the damage take place, the
contractor must contractually be bound to carry out repair immediately.
Community safety risks due to accidental or natural hazards
283. Although there are no settlements near the construction site, but there is
always some risk involved with construction activities. Also, since the area is
prone to natural hazards including floods, earthquakes and drought, the
construction team will pay heed to this risk as well.
Mitigation
284. The contractor will ensure proper signage and fencing in order to limit public
access to the construction site. Access will be strictly restricted specially
during activities such excavation. Construction site will have a first aid facility
with certain staff trained to handle emergencies. The design of the weir has
been tested for a 50 years flood return period, but at the same time, an
emergency response plan will be prepared by subproject contractor’s SSEMP in order to respond to any hazard caused naturally or otherwise.
Health and safety of labour at construction site
285. Since the project is being constructed at a remote site in the tribal areas,
safety of labor will be of prime concern. In addition, adequate measures
related to Health, Safety and Environment (HSE) will have to be provided for
the labor employed.
Mitigation
286. The contractor will ensure that proper HSE protocols are in place, including
protective gear, drinking water, sanitation, energy supply and overall safety
for the labor. Evacuation plans in case of fire or any other accidents will also
be prepared, and drills carried out to ensure the labor is aware of responding
to such a situation.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
101 | Initial Environmental Examination
Operation Stage Impacts
287. Various operational activities will invariably create environmental
disturbances, which may have impacts on the people working in the area
nearby communities and flora and fauna. Such impacts include the
following:
Soil pollution due to excessive application of pesticides and fertilizers
288. Pesticides and herbicides are applied to agricultural land, during operational
phase, to control pests that disrupt crop production. Soil contamination can
occur when pesticides persist and accumulate in soils, which can alter
microbial processes, increase plant uptake of the chemical, and also cause
toxicity to soil organisms. Pesticide leaching occurs when pesticides mix
with water and move through the soil, ultimately contaminating
groundwater. The amount of leaching is correlated with particular soil type
and pesticide characteristics and the degree of rainfall and irrigation.
289. Only a fraction of the nitrogen-based fertilizers is converted to produce and
other plant matter. The remainder accumulates in the soil or lost as runoff.
High application rates of nitrogen-containing fertilizers combined with the
high water-solubility of nitrate leads to increased runoff into surface water
as well as leaching into groundwater, thereby causing groundwater
pollution. The excessive use of nitrogen-containing fertilizers (be they
synthetic or natural) is particularly damaging, as much of the nitrogen that
is not taken up by plants is transformed into nitrate which is easily leached.
Mitigation
290. Agriculture Directorate shall introduce agriculture extension programs
targeting use of Integrated Pest Management (IPM), green manure, and
limiting use of pesticides/ fertilizers to required levels only, and will target
farmer communities to inform and train them. In general, the farmer use
mostly the farm yard manure or green manure. The pesticide use is also
rare, because of less vegetables and fruit production.
Use of additional irrigation water for cultivating high delta crops
291. With additional guaranteed supply of irrigation water, there is strong
likelihood that the farmers will cultivate high delta crops. Such practices will
not be sustainable in longer term, since the water diversion capacity is
dependent limit the irrigation capacity of the weir. In such a situation, high
water demand crops will consume maximum share of irrigation water
supply, and leave the farmers unattended for future cropping seasons.
Water balance models for the area will need to take heed of this factor, and
cropping pattern will have to be developed.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
102 | Initial Environmental Examination
Mitigation
292. Cultivation of high delta crops will be strictly discouraged keeping in mind
the appropriate use of the water for maximum are under cropping, and the
water balance model30 . Cropping pattern in accordance with the water
balance model will be suggested and promoted with the help of the
Agriculture Department.
Monitoring Programmes
293. The following monitoring programmes will be developed prior to the
commencement of project operations;
• Landslide monitoring
• Water quality monitoring
• Watershed and flood telemetry monitoring
Training/ Educational programmes
294. The following educational programmes will be developed prior to the
commencement of project operations;
• Employee induction programme on environmental awareness
• Employee code of conduct
• Health and Safety training programme
30 Water balance models were prepared as part of the Water Assessment Study and Management
Plan, 2010
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
103 | Initial Environmental Examination
ENVIRONMENTAL MANAGEMENT PLAN (EMP)
General
295. This EMP document is produced as a complementary part of Detailed
Design, as a free-standing document. It ensures incorporation of the relevant
environmental factors into the overall project design and will identify linkages
to other safeguard policies relating to the project.
Mitigation Measures
296. Based on the preliminary assessment, key mitigation measures
recommended under this Environmental Management Plan (EMP) are listed
as follows:
a. Identify and locate on project plans any sensitive natural resources
in the project area including but not limited to patches of natural
habitat, bird colonies, and wet lands, unique plant communities etc.
(consult with local nature protection authorities).
b. Identify local access routes through and around cultivated land and
pasture.
c. Minimize requirements for temporary or permanent alteration of
lands.
d. Provide zones for preliminary accumulation of wastes that will
cause no damage to the vegetation cover and other components
of the environment.
e. Transport and disposal of construction concrete rubble, debris and
spoils in approved paths and landfills/ dumpsites.
f. Delineate access roads/ work areas carefully and prevent their
expansion.
g. Rehabilitate access roads and work areas after work completion
(scratch soil with special engine, put fertile topsoil in place, etc.).
h. Use closed/covered trucks for transportation of construction
materials.
i. Clean the surrounding area from dust by water sprinkling, removal
of excess materials and cleaning of sites upon completion of
activities.
j. Restoration to original conditions of landscape after completion of
construction and rehabilitation works.
k. Arrange necessary preservation measures (establish protection
zones, by-pass these areas during transportation and other).
l. Cease the works at once, historical and cultural monuments are
encountered during earthworks and provide relevant information to
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
104 | Initial Environmental Examination
the State Agency for Historical and Cultural Monuments
Protection.
m. Conduct mid-term and end-of-project inspections to the sites
during construction works.
297. The parameters, mitigation, monitoring and responsibility will be discussed in
detail in the EMP.
Residual Impact
298. Residual impacts are defined as those impacts that remain following the
implementation of the mitigation measures proposed. Residual impacts refer
to those environmental effects predicted to remain after the application of
mitigation outlined in this IEE. The predicted residual effects are considered
for each project phase (construction, post construction, pre-operations and
operation, as per the Impact screening presented in Table 5.1, the
significance has been determined for each residual adverse effect.
Institutional Arrangements
Management Responsibilities
299. The Khyber Pakhtunkhwa Planning & Development Department is the
project’s executing agency (EA). It established a Project Management Unit (PMU). The PMU will be responsible for;
(i) sub-project preparation including feasibility studies;
(ii) monitoring implementation of all project activities;
(iii) undertaking all procurement activities;
(iv) coordinating and monitor the required civil works and project
facilities;
(v) undertaking financial accounting and reporting; and
(vi) ensuring the project is implemented in compliance with ADB
Safeguard policies and procedures.
300. Project Implementation Units (PIU) are established in each of the three Tribal
Districts for execution of the project at district level. The three PIUs will have
core staff comprised of a project manager assisted by account and
administration officer, monitoring and evaluation coordinator, and social
organizers. Project implementing agencies include the Directorate of
Irrigation, which will be responsible for the improved irrigation infrastructure
and on-farm water management components with the latter effort supported
by the Department of Agriculture, and the Department of Forests, which will
be responsible for the watershed management component. The IAs will
coordinate with the PMU and PIUs to ensure project activities are reflected
in their annual work plans, along with requisite financial and human
resources.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
105 | Initial Environmental Examination
Environment and Social Management Unit
301. For an effective compliance of an EMP, roles and responsibilities need to be
defined at the onset, with relevant professionals hired as project team
members at the executing or implementing agency (EAs/IAs) levels.
Moreover, these professionals are to be placed in the project hierarchy in
such a way whereby they cannot be influenced by the operational teams
(engineers, procurement, contractors, etc.) in order to lessen their
compliance monitoring responsibilities.
302. For the Project, an Environmental and Social Management Unit (ESMU) is
proposed to be set up within the Project Director’s (PD) Office at the E/IA
level, with direct reporting line to the PD. An Environment Specialist and a
Social Development Specialist will need be engaged as be a part of the
ESMU so as to ensure compliance to both parts of the EMP.
303. The responsibilities of ESMU will be the following, but not limited to:
o Ensure effective compliance of EMP as per ADB Safeguards
Policy requirements
o Provide technical assistance to the Project Team, in matters
related to EMP in particular, and to environmental and social
safeguards as a whole
o Put in place reporting mechanism and monitoring regimes of
project staff as well as contractors
o Ensure that EMP related clauses specifically, and environment
related clauses in general, are part of all the tender/bid/RFP
documents.
o Ensure that EMP implementation costs are made part of BoQs
o Provide technical input to the various training programs
proposed as a part of the EMP.
o Ensure that all regulatory clearances (e.g. clearance from KP-
EPA) have been obtained before starting civil works for the
subproject.
o Conduct on site spot checks to monitor the compliance level,
as well as for any outstanding issue not being covered by the
EMP.
o Regularly report to PD as well as ADB and EPA on progress
related to EMP Compliance and
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
106 | Initial Environmental Examination
o Immediately report any unanticipated environmental impact to
ADB.
The Consultant
304. The Construction Supervision Consultant (CSC) will ensure the
implementation and regular monitoring of the EMP in true letter and spirit
during execution of the civil works and shall submit periodic reports to ESMU
of IA regarding the EMP implementation status. The Consultant will engage
qualified Environmental Specialist and Social Specialist who will be
responsible for EMP implementation and reporting any non-compliance to
the Engineer of the Project and the ESMU.
a. The Contractor
305. The contractor will be responsible for on-site implementation of the EMP of
the sub-project environmental protection liabilities. They will be responsible
for compliance of EMP provisions under contractual obligations. The
contractor will train their crew/ staff in implementation of the EMP though
capacity building interventions.
306. The EMP will be an integral part of the contract document. The bid should
include a detailed environmental mitigation budget as part of the engineering
costs of the respective works. Contractor will engage social and
environmental managers to realize the above requirements.
307. A site-specific environmental management plan (SSEMP) will be prepared
and submitted to CSC by the contractor at least 10 days before the
commencement of civil work.
308. Civil work will not be commenced on site before the approval of the SSEMP
by the CSC and its endorsement by ADB.
b. Environmental Management Plan
309. The mitigation plan, being a key component of EMP includes measures to
mitigate potential negative impacts and enhance its positive impacts during
the construction phase of the sub-project. The contractor is responsible for
implementation of EMP with the co-operation of executing and implementing
agencies, client staff, social and environmental consultants and local
community of the project.
310. The Environmental Management Plan, shown in Table 6.1, which also covers
monitoring, will therefore form the basis of the environmental and social
protection measures implemented by ESMU and Engineering, Procurement
and Construction (EPC) contractor that will be employed. The implementation
of the EMP ensures that environmental, health, safety (EHS) and social
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
107 | Initial Environmental Examination
performance is in accordance with National (PAK-EPA) and International
(ADB Safeguard Policies) standards and best practice.
311. The Table 6.1 depicts the environmental management plan for the impacts
along with mitigation plan, as well as the institutional responsibility.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
108 | Initial Environmental Examination
Table 6.1: Environmental Management (Mitigation) Plan (Construction & Operation)
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
ImplementationResponsibility
Supervision Responsibility
Pre-Construction Stage
Assure compliance with relevant construction field legislation.
Legal complications and delay in project
• Acquire construction permit/ Environmental NOC from local authorities.
• Preparation of SSEMPs for each site and get them approved by the Consultant/PMU with the consent of ADB, before the construction works start.
• Provide Water management guidelines if subprojects are executed near surface watercourse.
Before the construction of the project activities.
Number of reported non-compliances
Minimization and continued improvement in number of reported non-compliances
EPC Contractor
ESMU/ Consultant
Development of Strategies.
Problems arising due to non-compliance
• An ‘Operation Environmental Action Plan’ (OEAP) needs to be prepared demonstrating the manner in which the Contractor/Operator will comply with the requirements of management plans proposed in EMP/SSEMP.
• The following strategies and procedures will be developed prior to the commencement of Project operations:
• Project specific security and public access control strategy;
Pre-Operations Implementation Operation Environmental Action Plan’ (OEAP)
Beneficial in long terms with the implementation of Operation Environmental Action Plan’ (OEAP)
ESMU PMU & ADB
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
109 | Initial Environmental Examination
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
ImplementationResponsibility
Supervision Responsibility
• Project specific waste management strategy
• Project specific air and noise control strategy;
• Project specific traffic control strategy;
Construction Stage Impacts Impacts on Land Resources Excavation • Noise &
Vibration • HSE issues
• Vegetation loss will be avoided as much as possible and limited to demarcated construction area.
• Slope stabilization measures will be adopted such as adequate vertical and horizontal drains, cross drainage etc.
• Slope movements will be monitored around excavation work areas.
• Top six inches soil should be protected through stockpiling before excavation and should be placed back after completion of construction work.
• Excavated material shall preferably be reused after approval of quality control engineer of CSC.
• Non-reusable excavated material shall be safely dumped and leveled in
During Construction
• Implementation of SSEMP before start of works
• Annual reports and documentation of safety inspection
• Workforce /Community complaints
Not Significant (Minimal) Target = zero Threshold 1, with agreed mitigation
EPC Contractor
ESMU/CSC
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
110 | Initial Environmental Examination
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
ImplementationResponsibility
Supervision Responsibility
barren land with approval from Environment specialist of CSC and dumping.
• The location of the dumping area should be selected in joint survey of contractor and CSC and should be provided in SSEMP..
Waste Management
• Waste Pollution
• To minimize environmental impacts and avoid any need for disposal of earthwork materials or the importation and unnecessary storage of earth, the project will maximize the reuse of excavated materials.
• All of the construction activity will be contained inside construction area.
• Solid waste generation should be reduced reused and recycled.
• Any residual spoil will have to be disposed in environment friendly manner, where it will be leveled and landscaped. The dumping sites must be approved by CSC environment specialist.
• To be made contractor’s obligation through contract
During construction stage
• EPC’s Site officer and EHS officer in place
• SSEMP including Waste Management Plan
• Zero Complaints from Community & Workers
• Internal auditing and reporting by EPC
Not Significant (Minimal)
EPC Contractor
ESMU/CSC
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
111 | Initial Environmental Examination
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
ImplementationResponsibility
Supervision Responsibility
document, as an SSEMP will be prepared by the contractor and waste management plan will be a part of it.
Labor camps and material storage
• Cultural & Social issues
• Water & Sanitation issues
• The contractor will, in consultation with RE, resolve the exact location of all these facilities within the barren land owned by the local community that will be provided by the community temporarily and free of cost.
• The location of these facilities will be at least 500 m away from the settlements.
• The contractor will not locate and construct any facilities without the written approval of the CSC.
During construction
• Monthly Reports (EPC)
• Supervision by Consultant
• EHS officer implementing SSEMP Information Events for work force
Not Significant (Minimal)
Contractor ESMU/CSC
Soil pollution due to oils and lubricants / equipment poor maintenance and repairs / refueling at the construction site.
• Soil pollution • Water
pollution
• Strict rules will be imposed on workers and labors to ensure that no such spills are caused.
• If the spills take place, it must be followed by treatment prescribed above as per the degree of spill.
• An Oil Spill Management Plan containing specific mitigation measures to be part of contractor site
Because the area can be subject to un seasonal heavy rain plan before and during construction (cut and fill, land reclamation etc.) while considering the climatic conditions.
Spill contingency plan is available at site Properly paved/cemented mechanical workshop No water bodies near the working area Staff Training over oil spillage
Not Significant (Minimal)
Contractor ESMU/CSC
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
112 | Initial Environmental Examination
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
ImplementationResponsibility
Supervision Responsibility
specific environmental management plan are:
• Spill prevention trays will be provided and used at refueling locations
• On-site maintenance of construction vehicles and equipment will be avoided, a vehicle maintenance area with impermeable floor will be designated.
• Regular inspections will be carried out to detect leakages in construction vehicles and equipment.
• Fuels and lubricants will be stored in covered and dyked areas, underlain with impervious lining.
• Spill control kit (shovels, plastic bags and absorbent materials) will be available near fuel and oil storage areas.
• Contaminated soil will be removed from the site and disposed in a manner to ensure protection of water sources
• Emergency plan for spill management will be prepared and inducted to the staff for any incident of spill.
All the vehicles and machinery seals are intact Containers are available for used oil
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
113 | Initial Environmental Examination
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
ImplementationResponsibility
Supervision Responsibility
• The bottom of any soak pit or septic tank will be constructed at least 100 meters away from springs and water bores
• Record of spills and Volume of removed contaminated soil will be maintained.
• Record of remedial measures taken will be maintained.
Heavy Machinery near agricultural land
• Agriculture Land Damage
• It is contractor’s obligation not to cause such damage and strictly follow the design.
• Top six inches soil will be protected through stockpiling and land will be restored to its previous condition after completion of construction works.
Construction and post construction
• Monthly Reports (EPC)
• Supervision by Consultant
• EHS officer implementing SSEMP
Information Events for work force
Not Significant (Minimal)
Contractor ESMU/CSC
Earth borrow • Land owner problems
• Levelling of land after borrowing
• Issues to the local community
• Compensation difficulties
• No private land will be acquired for the borrow areas.
• The Contractor will ensure that selected borrow areas on irrigation land are clearly demarcated and approved by the engineer including the allowed depth of the excavation before starting excavation.
• The borrow areas will be leveled. The Contractor will
Construction and post construction
Top soil management Government approved site Approval for any other site by RE and Government Borrow area management generated and implemented Agreement in case of private land owner
Minor \Reduced
Contractor ESMU/CSC
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
114 | Initial Environmental Examination
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
ImplementationResponsibility
Supervision Responsibility
not leave the borrow pits in such a condition that they are unsuitably filled with rain water and cause the problem for the community.
• If the borrow area is near to the settlements, then it should be fenced completely.
• If agriculture land needs to be used as borrowing area, then the Contractor will adopt the following methods during the digging process.
• Fix the location of excavation.
• Remove thirty centimeters of the top soil and keep it on reserved site for re-spreading in the field.
• Excavate up to one-meter depth.
• Maintain the slope as far as possible.
• Place the top soil back during the restoration
• Pay compensation for any damages/ crop losses.
Grievance redress Mechanism Leveling of Borrow Area
Construction material leftovers and site restoration
Waste generation due to closure of site
Occupation of usable land.
• All shivers and material that remain after the closure of temporary construction sites are to be removed from the location
Completion of Construction
• Site Inspection • Implementation
of Environmental Enhancement Program
Not Significant (Minimal) Short term during construction phase Beneficial in long terms with the implementation of Environmental Enhancement Program
Contractor ESMU/CSC
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
115 | Initial Environmental Examination
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
ImplementationResponsibility
Supervision Responsibility
and re-used/re-cycled where possible.
• All remains are to be disposed of in a manner that will not be harmful to environment.
Impacts on Hydrology and Water Resources
Washing of Vehicle and equipment in the stream
• Contamination of Surface water
• Contractor will demarcate a washing area for all sorts of washing activities, with running water facility connected to a dedicated drain flowing into the septic tanks. There would be restriction on servicing/ washing of vehicles and equipment at site.
During Construction
• Documentation of audit and remedial actions where necessary
• Grievance’s record (Target=0, Threshold 1 with agreed mitigation)
Not Significant (Minimal) Short term during construction phase
Contractor ESMU/CSC
Drinking Water supply
• Water borne diseases & other water related issues
• Contractor, under the guidance of Environment Specialist of CSC, will get spring water tested for chemical and biological contaminants, and assist in providing filtration to make water drinkable.
• There are numerous cost-effective water treatment models available in order to mitigate chemical and/or biological contamination. Sand filtration, Chlorination, UV treatment and oxidation are a few such methods.
Before construction and during the project activities.
• Documentation of audit and remedial actions where necessary
• Grievance’s record (Target=0, Threshold 1 with agreed mitigation)
Not Significant (Minimal)
Contractor ESMU/CSC
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
116 | Initial Environmental Examination
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
ImplementationResponsibility
Supervision Responsibility
Municipal solid and liquid Waste Generation
• Nuisance and Soil Pollution, diseases due to dumping
• Solid waste bins will be placed at labor eating and resting areas.
• Latrines and washing areas with septic tanks will be erected by the contractor at the construction site.
• Waste from the project construction area and office area shall be segregated and collected by the Tehsil Municipal corporation for dumping at approved land fill site or if small amount then a natural gully or uncultivable land for dumping will be arranged with approval from CSC Environment Specialist.
• All these provisions will be incorporated in site Contractor Site Specific EMP for construction. Prior utilization, all the landfill sites or disposal sites will be approved by CSC Environment Specialist
During construction
• Implementation of SSEMP
• Site auditing • Grievance’s
record (Target=0, Threshold 1 with agreed mitigation)
Not Significant (Minimal)
Contractor ESMU/CSC
Impacts on Air Quality and Noise Pollution
Dust/smoke Emission from plants and equipment
• Air pollution • Lung
Diseases
• Contractor’s contractual obligation will include keeping the dust and smoke within permissible
During Construction. Water sprinkling to be done on
• Water sprinkling Records
• Monthly reports EPC
Not Significant (Minimal)
Contractor ESMU/CSC
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
117 | Initial Environmental Examination
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
ImplementationResponsibility
Supervision Responsibility
level by using machinery, which is well maintained and with low noise.
• Land, all katcha roads and paths will be sprinkled with water after regular intervals.
• The contractor must avoid/ control the dust and smoke by carefully storing and distributing the construction material so as to cause minimum dust which again should be within the acceptable limits.
regular/daily basis.
• Site Inspection and Audits
• Monthly Monitoring Reports by EPA certified Laboratory
Operation of heavy mechanization and generators.
Noise pollution
and vibration
• Contractor’s contractual obligation is to use new, well maintained and low noise machinery preferably during day time.
• The drivers, operators and workers working on or near the heavy machinery must be provided with ear plugs. The contractor will ensure use of newer, well maintained machinery that creates minimum noise and emissions, as per National Environmental Quality Standards (NEQS 2000)
• Environment Specialist of CSC will ensure that this
During Construction stage
• EPC Site Manager and EHS Officer in Place
• Audit and Inspection record of heavy mechanization and generators.
• Monthly Noise level Monitoring Reports by EPA certified Laboratory
• No. of Grievance’s (Target=0)
Not Significant (Minimal)
Contractor ESMU/CSC
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
118 | Initial Environmental Examination
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
ImplementationResponsibility
Supervision Responsibility
clause is added to the bidding and contract document.
• Night time construction activities will be strictly discouraged, and may only be carried out in exceptional cases, with prior permission of Resident Engineer.
• Noise monitoring will be carried out near sensitive receptors on a quarterly basis.
• The NEQS for noise in residential areas is 55 dB (A) in the day-time and 45 dB (A) at night. It is recommended that noise levels close to sensitive receptors do not exceed 55 dB (A) during the day time as required by the NEQS.
Stone quarrying and Transportation of material
• Dust Emission and lungs diseases.
• Contractor shall use the road network carefully and repair any damages immediately.
• During transportation, covering of vehicle with sheet will be done.
• Unloading of vehicles will be done on designated sites.
During construction.
• Recording of violations and corrective measures
• Performance of Regular Driver Training (target 100% participation of drivers)
• Instruction and Information
Not Significant (Minimal)
Contractor ESMU/CSC
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
119 | Initial Environmental Examination
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
ImplementationResponsibility
Supervision Responsibility
Events for workforce
• No. of accidents (Target=0)
Impacts on Biological Resources
Multiple project activities
• Damage to Flora and Fauna
• Impact on aquatic life
• Environment Specialist together with FATA line departments will ascertain the status of the site area in terms of occurrence of wildlife species, flora and fisheries. And in accordance, recommend a watch and ward system that will be based on partnership between communities, wildlife, forest & fisheries departments and political administration. Each partner’s roles will be specified at the onset, and responsibilities assigned.
• Till the completion of the survey, contractor will ensure no extraction takes place from the surrounding vegetation for fuel wood or hunting of any birds by the labor employed.
• If such a case is witnessed, it will be brought to the notice of the project management as
Rerouting and site identification during design stage and other matters during construction of relevant activities
• EPC internal monitoring and monthly reports
• Site auditing • Photographic
record of pre and post project
• Implementation of Environmental Enhancement Program
Not Significant (Minimal) during construction phase Beneficial in long terms with the implementation of Environmental Enhancement Program
Contractor ESMU/CSC
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
120 | Initial Environmental Examination
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
ImplementationResponsibility
Supervision Responsibility
well as the concerned Authorities.
• Contractor’s obligation is to strictly respect the limits of construction site.
• Cutting of trees will be strictly prohibited and if no alternate is available plantation of trees will be done in case any tree is cut for project activities.
• Tree cutting will be restored by planting four trees against each tree cut.
• Borrow areas with least vegetation cover will be selected.
• The project will have a soft start for allowing time to reptiles to move away from the project site.
• There will be restriction and prohibition on hunting, shooting, trapping, and poaching of wild species.
• No night time activity will be carried out.
• Photographs of the project area will be taken at pre and post project stage.
Impacts on Socioeconomic and Cultural Issues Project Activities
• Tribal tensions and rivalries
• For matters pertaining to social obligation and benefits of the communities, if needed, a
Before and During construction
• Continued Community Consultation Records
Not Significant (Minimal)
Contractor ESMU/CSC
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
121 | Initial Environmental Examination
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
ImplementationResponsibility
Supervision Responsibility
social Framework Agreement shall be signed by the RE with communities to ensure their participation and full satisfaction in matters pertaining to them. All matters where contractor is involved, these should be made as his contractual obligations.
• Project Team along with the Social Development Specialist will ensure continuous liaison with the communities throughout the construction phase of the project, so as to identify any such incident in time. Relevant political authorities will be kept abreast of the progress, as well as any such issue if in making.
• If, during the execution of the activities or excavation, any material is discovered onsite, which may be considered of historical or cultural interest, such as evidence of prior settlements, native or historical activities, evidence of any existence on a site, which may be of cultural significance, all
• Implementation of Community Liaison Plan by EPC
• No. Of Grievance’s (Target=0)
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
122 | Initial Environmental Examination
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
ImplementationResponsibility
Supervision Responsibility
work shall stop and the supervising contracting officer shall be notified immediately. The area in which the material was discovered shall be marked and the evidence preserved for examination.
• The contractor is required to develop Chance Find Procedure as part of the SSEMP.
Excavation activities
Impact on the existing civil infrastructure and facilities, especially underground installations (water supply and sewerage pipeline etc.) which cause obstacles in the provision of services to consumers
• Precisely situate the position of infrastructure and underground installations at the local works in cooperation with the relevant institutions at all levels of authority.
• Close liaison with local relevant authorities
• Should the damage take place, the contractor must contractually be bound to carry out repair immediately.
Before the construction of the dam and all other structures, the APs should be given sufficient time and compensation to satisfy them.
• Continued Community Consultation Records
• No. Of Grievance’s (Target=0)
• Monthly Reports on Information activities and response from community
• Liaison Records with local relevant authorities
Not Significant (Minimal)
Contractor CS Consultant / EMU in cooperation with concerned Department. I-e, Public Health etc.
Multiple project activities related to HSE
• Risk of injuries at work
• The contractor will ensure that proper HSE protocols are in place, including protective gear, drinking water, sanitation, energy supply and overall safety for the labor.
Prior to commencement and during construction
• Site Inspection • Monthly EPC
Reports • PPEs issuance
records • Health and
safety Plans in
Not Significant (Minimal)
Contractor ESMU/CSC
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
123 | Initial Environmental Examination
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
ImplementationResponsibility
Supervision Responsibility
• Evacuation plans in case of fire or any other accidents will also be prepared, and drills carried out to ensure the labor is aware of responding to such a situation.
• A detailed HSE Plan will be formulated in SSEMP.
Place and Implemented
• Implementation of Construction Site Organization Plan
Operation Stage Impacts and Maintenance (O&M)
Water
Availability and
Post
construction
use of
pesticides and
Fertilizers
• Soil pollution due to excessive application of fertilizers and pesticides
• Agriculture Directorate shall introduce Agriculture extension programs targeting use of Integrated Pest Management (IPM), green manure, and limiting use of pesticides/ fertilizers to required levels only will target farmer communities to inform and train them. In general, in erstwhile FATA area the farmer uses mostly the Farm yard manure or green manure. The pesticide use is also rare, because of less vegetables and fruit production.
Post Construction
• Agriculture extension program developed before completion of construction
Minor Agriculture Directorate
PMU
• Use of irrigation water for cultivating high delta crops
• Cultivation of high delta crops will be strictly discouraged.
• Cropping pattern in accordance with the water balance model will be suggested and promoted.
Post construction
Agriculture extension program developed before completion of construction
Not Significant (Minimal)
Agriculture Directorate
PMU
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
124 | Initial Environmental Examination
Activity Problem / Impact Mitigation Measures Timing to Implement MM
Performance Indicator
Residual Impact Negligible: No or minimum adverse impact Moderate: Site specific Potential impact but can be mitigated High: significant adverse environmental impacts that are irreversible, diverse, or unprecedented
ImplementationResponsibility
Supervision Responsibility
Monitoring programmes
Mitigation plan implementation cannot be gauged
The following monitoring programmes will be developed prior to the commencement of Project operations: • Landslide monitoring; • Water quality monitoring • Watershed and flood
telemetry monitoring
Operational stage
Site Inspection Monitoring Reports
Beneficial in long terms with the implementation of Operation Environmental Action Plan’ (OEAP)
Irrigation Department
PMU
Training/ educational programmes.
Effect on employees` efficiency during project
The following educational programmes will be developed prior to the commencement of Project operations: • Employee induction
programme on environmental awareness;
• Employee code of conduct; • Health and Safety training
programme
Operational stage
Implementation of Training Events and Programs
Highly Beneficial Irrigation Department
PMU
MM: Mitigation Measures
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
125 | Initial Environmental Examination
Monitoring Activities
312. For each of the environmental components, the monitoring plan specifies the
parameters to be monitored; location of the monitoring sites and duration of
monitoring. The monitoring plan also specifies the applicable standards,
implementation and supervising responsibilities.
313. In addition to the critical locations selected during design stage, the
environmental monitoring will also be done at the construction camp site and
any other plant site as determined relevant during rehabilitation works stage.
Performance Indicators
314. A key aspect of monitoring is defining relevant indicators. A Performance
Indicator is a measurable value that demonstrates how effectively the EMP
is achieving its key objectives, evaluated against the criteria defined in
environmental management Plan.
Table 6.2 Environmental Monitoring31
Sr. No. Test Frequency Parameters Location of Monitoring
Number of samples
1 Water Quality
Quarterly pH
Color
Odor
Electrical Conductivity
Turbidity
Alkalinity
Bicarbonate
Carbonate
Calcium
Sodium
Potassium
Hardness
Sulphate
Nitrates
TDS
Total Coliforms & E-Coli
Surface water sample to be collected 10 m downstream of the weir.
Drinking water sample from Labor camp
02 (surface and Ground water)
2 Air Quality
Quarterly for one hour at construction site
Carbon Monoxide (CO)
Sulfur Dioxide (SO2)
Nitrogen Oxide (NO)
10 m from the main construction site
01
31 Environmental Monitoring Plan is given for one sub project only and the same will be applicable
for each sub project
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
126 | Initial Environmental Examination
Oxides of Nitrogen (NOx)
PM10
Suspended Particulate Matter (SPM)
3 Noise Quality
Quarterly for one hour at construction site
Quarterly and whenever required in an emergency or exceeding the NEQS limits
10 m from construction site
02
Project Enhancement Plans
Restoration Plan
315. If during construction, further material is required or contractor needs to
borrow material from any other site, then the contractor can acquire private
land in accordance with the lease agreement with the land owner.
Photographic record will be kept before and after the land use as borrowing
area. The contractor will not leave borrowing pit in such a condition that they
are unusable and could be filled with rain water and provide breeding place
for mosquitoes or cause any health and safety issues. Agricultural land
should be restored such that it can be re-used for agricultural purpose. The
topsoil of agricultural land, if used as borrow area, the top soil up to 6 inches
should be removed and kept separate on site for its re-spread back on the
leveled borrow area. Then the site area should be leveled for placing the
topsoil back.
Reports
316. The Environmental Specialist of the Construction Supervision Consultant
(CSC) shall produce periodical reports as well as inspection notes based
upon the visits to the subproject site. The contractor will submit weekly
checklist report to CSC on the basis of which CSC will prepare monthly report
and submit to PMU. Similarly, CSC will prepare Bi-annual report and submit
to PMU.
317. This information shall make a basis for Project Management Unit (PMU) for
their further reporting or visiting the site. All reports shall be location based
and activity specific. The reports shall especially identify areas of contractor’s noncompliance with the EMP and provide guiding remarks on actions to be
taken. The significance of the non-compliance shall also be noted. Copies of
these reports shall be sent to the Resident Engineer (RE) who shall forward
them to the team leader, Head PMU and the contractor for their action(s).
The RE will include in routine reports a summary status of activities relating
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
127 | Initial Environmental Examination
to the EMP. Supplemental reports on issues should also be prepared when
required.
318. The consultant’s environmental team will produce daily, monthly reports, as well as a final report of the project based on the information collected. The
Table of Contents (TOC) of Monthly Environmental Progress Report (MEPR)
is annexed as Annex-V. The list of distribution reports is given in Table 6.3.
Table 6.3: Distribution of Reports
Training Schedule
319. Environmental training will form part of the Environment Management Plan.
The training will be conducted for all personnel involved in the project works.
The key objective of training program is to ensure that the requirements of
the EMP are clearly understood and followed throughout the implementation
of the sub projects. The trainings to the staff will help in communicating
environmental related restrictions specified in the EMP. The contractors will
be primarily responsible for providing environmental training to all project
personnel on potential environmental issues of the Sub Projects.
Responsibility of trainings related to public safety lies with PIU. In addition to
the training specified in the training log, special/ additional trainings will be
provided during the sub projects activity.
Report Prepared by Reviewed by Distribution
Weekly
Checklist
Contractor’s HSE/Environment officer
Contractor`s Environment
Officer and Consultant’s Environment Specialist
Resident Engineer
Monthly Environment team of the
Design & Construction
Supervision Consultants
PMU`s Environment
Specialist
Project Director
Effects
Monitoring
Environment team of the
Design & Construction
Supervision Consultants
PMU`s Environment
Specialist
Project Director
Change
Management
Environment team of the
Design & Construction
Supervision Consultants
PMU`s Environment
Specialist
Project Director
Semi-annual Environment team of the
Design & Construction
Supervision Consultants
PMU`s Environment
Specialist
ADB through Project
Director
Final Environment team of the
Design & Construction
Supervision Consultants
Reviewed by ESMU of
ESMU
ADB through Project
Director
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
128 | Initial Environmental Examination
EMP Estimated Budget for Implementation
320. Contractor will be responsible for the implementation of environmental
mitigation plan. Most of the mitigation measures are covered in the
engineering costs of the respective works. The following EMP Cost reflected
in Table 6.4 deem to covered in the engineering cost, the contractor will not
claim this amount as a direct cost, while the environmental monitoring cost32
(Table 6.5) to be claimed as a direct cost, when to be carried out at site.
The appointment of Environment Health & Safety (EHS) staff is already
included in the contractor Employees/personnel requirement. The
afforestation cost will be covered as part of Watershed Management
component for the sub projects catchment area.
Table 6.4: Estimated Budget for Environmental Management
Serial No. Description Amount in Pak Rs
1 PPEs 1,00,000
2 Safety Banners & Sign boards 25,000
3 Medical facility at site 1,00,000
4 Water sprinkling 2,00,000
5 Fire protection equipment’s 50,000
6 HSE Training 1,00,000
7 Misc. (Unforeseen) 75,000
Total Amount 650,000
Table 6.5: Estimated Budget Environmental Monitoring
Item No Item Description
Parameters Frequency Rate (Rs)
As per Contract Amount
Quantity Amount
1 Air Testing at site
1. Carbon Monoxide (CO)
2. Sulfur Dioxide (SO2)
3. Nitric Oxide (NO)
4. Nitrogen Dioxide (NO2)
5. PM10 6. PM2.5
Quarterly for one hour at construction
site
8000 4/year 32000
2 Noise Testing at
site
1. Noise Quarterly for one hour at construction
site
500 8/year 4000
32 Note: All the budgets are calculated in 2019 for one sub project only without any escalation rates and taxes. Actual budget will be provided by the Contractor at the time of implementation and will be applicable for each subproject.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
129 | Initial Environmental Examination
3 Water Testing in
Lab
1. Total Coli form
2. E. coli 3. pH 4. Total
Dissolved solids (TDS)
5. Total Hardness as CaCO3
6. Sodium 7. Potassium 8. Sulphate 9. Chloride 10. Alkalinity 11. Color 12. Odor 13. Taste 14. Nitrogen-
Nitrates 15. TSS
Quarterly 11000 8/year 88000
Total 1,24,000
Contingency Cost @5%
6200
Grand Total 130,200
Third Party Monitoring
321. The purpose of third-party monitoring is to ensure that the project is
implemented with a due concern for environmental and social safeguards
according to ADB’s Safeguards Policy Statement (SPS) 2009, and specifically to ensure that these issues are adequately addressed in
compliance with the approved EIA/IEE reports and Environment
Management Plan (EMP). The third-party monitoring consultant will check /
validate these reports during the construction phase of the project and also
the Project Completion Report and report to ADB
322. As per TOR of the Contract the Third-Party Consultant will perform the
following key tasks.
i. Review the sub-project's environmental performance to ensure that it
complies with the national environmental legislation, requirements
under Pakistan Environmental Protection Act, ADB's environmental
safeguards as stipulated in Safeguard Policy Statement (SPS) and
relevant environmental documents (IEE, EIA, Site specific EMP,
Environmental Assessment and Review Framework);
ii. Monitor and participate in selected sub-projects' design and
construction stage consultations;
iii. Monitor the performance of consultants in delivering the services and
the performance of EA/PMU/PIUs and IAs in delivering their roles and
responsibilities so that the project stays compliant with ADB
environmental safeguards;
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
130 | Initial Environmental Examination
iv. Monitor on sample basis EMP compliance at a construction site;
v. In the case of unpredicted environmental impacts occurring during
project implementation, provide guidance on the preparation of a
corrective action plan, and monitor its implementation;
vi. Support the PMU in information sharing and disclosure of
environmental safeguard documents, training on environmental
management, and health and safety aspects to project staff;
vii. If required, participate in the ADB project review missions to assist in
due diligence reviews and analyses; and
viii. Identify implementation capacities gaps, recommend improvements
and troubleshooting to address bottlenecks and emerging issues that
affect project management;
323. The Consultant will deliver (a) third party monitoring detailed plan in
consultation with the EA, PMU, PIU and IAs; (b) biannual external
environment safeguards monitoring report; and (c) collate and provide input
to the final TA report. The Consultant will report to ADB Project Team Lead
in PRM Islamabad.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
131 | Initial Environmental Examination
PUBLIC CONSULTATION
General
324. Public Consultation is a process to disclose project information to the local
communities and other concerned stakeholders and record feedback regarding
the proposed subproject and preference. It brings new ideas and information in a
dynamic and integrated way. It also educates the community towards type and
objectives of the subproject and persuades them to be rational to participate in the
sub project activities.
325. The public consultation process was commenced in the initial feasibility stages
(prior to construction) in order to disclose the project information to the
stakeholders. The stakeholders involved in the process, were the population likely
to be impacted, the village leaders and relevant departments.
326. Prior to the implementation of the subproject, consultations have been carried out
to support this EMMP. The focus of attention has been the population near the
subproject area that may be affected by the subproject. The level of engagement
varied from the stakeholder to stakeholder with some registering no major
comment but it is noted that none registered any outright opposition to subproject.
327. The disclosure of the subproject intervention and subsequent consultation with
stakeholders is imperative for the environmental assessment and mitigation of
impacts. Public consultation can also provide a conduit for the improvement of the
subproject implementation to better serve the stakeholders. In this EMMP, the
consultation process was performed to achieve the objective of ADB Safe guard’s policy statement 2009.
328. The main objectives of public participation and consultation are to achieve the
following:
• Ensure public and community participation in the subproject environmental
policy objectives and decision making.
• Ensure public confidence in the administration of the environment by
demonstrating the role of government to enforce the environmental
stewardship of government agencies and organs, corporate citizens and
elite organizations;
• Grant the citizenry access to environmental information and data, thereby
promoting the quality of environmental management and compliance
monitoring.
• Provide key project information and create awareness among various
stakeholders about the project intervention;
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
132 | Initial Environmental Examination
• Have interaction for primary and secondary data collection with project
affectees and other stakeholders;
• Begin establishing communication and an evolving mechanism for the
resolution of social and environmental problems at local and project level;
• Involve project stakeholders in an inclusive manner; and
• Receive feedback from primary stakeholders on mitigation and
enhancement measures for environmental and social impacts.
329. Community engagement provides a valuable link between the stakeholders of the
subproject and serves by;
• Enabling the community to be better informed
• Reducing the level of possible misconception/ misinterpretation or
deception
• Ensuring commitment and greater ownership of the final decision by the
community
• Strengthening relationships between project cycle and the community
• Encouraging the community to put forward ideas
• Assembling better understanding of local needs
• Helping to identify issues which may not otherwise have been considered
Identification of Stakeholders
330. Stakeholders are persons or groups who are directly or indirectly affected by a
project as well as those who may have interests in a project and/or the ability to
influence its outcome, either positively or negatively. Stakeholders of the
subproject include locally affected communities, local government authorities, and
civil society organizations, groups with special interests, the academic community,
or businesses. (Figure 7.1).
331. During the field survey, different stakeholders identified, were the villagers, local
residents, government officials, farmers, public representative, NGO’s and general public. All those stakeholders had different types of stakes according to
their professions.
332. Two types of the stakeholders were identified: the primary stakeholders, who
would be directly affected by the subproject; and the secondary stakeholders, who
would be indirectly affected by the subproject.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
133 | Initial Environmental Examination
Figure 7.1: Identification of Stakeholders
333. These stakeholders were contacted by the Construction Supervision Consultants
(CSC) in August, 2019. Their views and reservations/ concerns about the
subprojects were taken into consideration. Construction Supervision Consultants
also interacted with the community-based organizations that can support the
community during the execution of the subprojects.
334. Tribal society is dominated by men with final say in the affairs of all members of
the family. Women, by comparison, play a subservient role and observe strict
purdah (veiling). They are for the most part restricted to performing household
work, and are excluded from decision-making both on the domestic front and at
the community level. Due to cultural background, women of the subproject area
were not consulted.
Methodology
335. To carry out stakeholder consultations, the survey team adopted a strategic and
flexible approach, where influential were earlier briefed and taken into confidence
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
134 | Initial Environmental Examination
for holding community level meetings. This was followed by candid meetings with
residents and small group meetings with locals.
336. A number of comprehensive consultations were carried out with the subproject
stakeholders at various locations during the preparation of environmental and
social impact assessment. The consultation and scoping sessions were designed
specifically to provide subproject information to the public. These sessions were
informal so as to encourage friendly social environment in which participants may
feel comfortable in raising questions, expressing their opinion and concerns about
the subproject besides seeking clarification regarding their concerns. The focus
group discussions were instrumental in the process, whereas one-to- one
meetings were also held with the institutions.
337. During the field visit we observed that most of the infrastructure are damaged or
destroyed during war against militancy. The local communities displaced from the
subproject area after launching of the military operation against militancy/
extremism. The people of the subproject area are not yet returned to their homes.
Therefore, no public consultation was carried out with the community of Tarkho
Kas subproject area. Information was collected about physical infrastructure in the
subproject area through security forces deployed there and the extent to which it
could be affected by the subproject intervention. As people of the area were not
consulted at feasibility stage however every possible effort has been done to
design the subproject in socially acceptable manner. After their return to
subproject area they will be consulted and changes would be done according to
their needs and want.
338. The subproject survey was carried out to cover socio-economic condition of the
area and to assess the farmer community’s demands and difficulties with the
consideration of the following protocols:
339. The meeting was freely formatted so as to avoid any uneasiness of local farmers
and to provide them maximum freedom of speech.
• Survey team has highlighted the potential benefits of project
implementation and noticing any aspects which would need to be covered
in greater detail during execution stage.
• Discussions were also made regarding the proposed rehabilitation of
irrigation system and feedback /suggestions based on historical knowledge
of area were recorded.
• Preliminary assessment of community’s willingness was assessed to contribute to project implementation in the form of local labor with the Civil
Works Contractor.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
135 | Initial Environmental Examination
Agenda of Consultative Session
340. The agenda for the consultative session with local farmers was prepared after
investigating all existing irrigation infrastructure in the area. Similarly, an informal
interview guide was used to obtain views of key informants on the issues of
irrigation in the project area. Data obtained helped the facilitator in drafting and
adopting the following agenda for the community meetings.
➢ To assess the apprehensions and aspirations of the local farmers
regarding improvements to the existing irrigation infrastructure;
➢ To assess indigenous knowledge of potential improvements in
irrigation system
➢ Knowledge and experience of any similar works undertaken by
government agencies, NGOs and other technical institutions.
Local Farmer Views
341. The local farmers openly expressed their views that farmers understood fully that
improved and ensured surface water supply is the only way to improve agriculture
and rural livelihood. The improved surface water supplies will contribute to
minimize reliance on ground water abstraction thus, resulting into improved
income and regulated ground water regime. The peoples told that the tail end
users will not receive water, as experience of surrounding irrigated area. Farmers
termed the uncertain and unreliable supply of the canal water. No one has directly
or indirectly indicated any negative feelings towards the proposed intervention.
342. Relations between farmers and Irrigation Department officers are generally poor.
Rural farmers have little trust in government generally and in the Irrigation
Department in particular. Therefore, the proposed weir will be supervised by the
farmer community. The irrigation Department will arrange only the major repair in
future.
343. When asked whether a Farmers’ Organization (FO) would be useful or not,
respondent answers were largely in favor (90%). Farmers want FOs to share the
resolution of issues like water theft, cementing of watercourse etc., agricultural
issues (e.g. marketing) and credit etc.
344. The participants were in complete agreement about the benefits of the project and
expressed full support to the project. Qualitative assessment during the field
survey indicates that the community is willing to contribute to sub-project
implementation by working as unskilled labor. The preference is to work during
the agricultural off-season. Training in labor-based construction works will be
needed in order to implement the project efficiently. This will also result in
necessary basic skills transfer for future maintenance of the scheme.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
136 | Initial Environmental Examination
Consultation with Other Stakeholders and Their Response
345. The potential stakeholders were inhabitants, field staff of Irrigation Department
and other relevant departments working in the Sub Projects area. During the
consultation, maximum information about the Sub Projects were shared. A list of
Government official consulted is enlisted in Table 7.2 and local
Notables/beneficiaries farmers are in Table 7.3.
346. All the stakeholders including the local community were consulted about the
proposed subproject. Salient features of the subproject and requirement of ADB
SPS were discussed. Sub project does not require land acquisition and no
resettlement of the people is involved. There is no major issue related to the RoW
of the sub projects, which was provided by Irrigation Department. Public
consultation was also made with the local people residing in the adjacent and
surveyed villages in the sub projects area. The discussion was focused on the
impacts of the proposed sub projects.
347. The people were pleased to know about the proposed subproject. They
appreciated the efforts of taking-up the subproject for providing benefits to the
public.
348. The stakeholders were asked about the likely impacts of the proposed sub
projects during construction/ execution phases. Most of the people have
knowledge about the sub projects. The people of the area were briefed about the
both negative and positive impacts of the sub projects. They responded that the
negative impacts like noise and dust are very minor and temporary issues as
compared to the positive impacts which will help them to improve their
socioeconomic conditions. They said that the project will greatly help in the
rehabilitation of the Temporarily Displaced Persons (TDPs) as most of the
irrigation channels are damaged. The project will also help us in providing
temporary employment opportunities. People of the area were demanding some
basic facilities like drinking water supply, electricity, Schools and Basic Health
Units (BHU) etc. however they were told that the project focuses only on improving
irrigation and efficient use of water resources. They also demanded for flood
protection wall. Their concerns were noted and were shared with the line
department and their queries about the sub projects were answered to their
satisfaction. Suggestions were also sought from the locals for incorporating
mitigation measures in the EMP.
Table 7.2: List of Government Official Contacted
Sr. No Name Designation Contact No Department
1 Nasrat
Shaheen
Agricultural
officer 091 2211998 Agriculture
2 Abdurahman XEN 03009065647 Irrigation
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
137 | Initial Environmental Examination
Table 7.3: List of Community Consultation Participants33
S/No. Name CNIC No. Cell No.
1. Shahid Ullah 21202-1544029-9 03063976038
2. Mir Sadiq 21202-7310201-7 03325578131
3. Ihsan Gul 21202-5694699-5 03015915115
4. Shams Ul Haq ____________ 03348703867
5. Zarghoon Jan 21202-9060309-3 03359111567
6. Amirooz Khan 21202-7377162-1 03009866668
7. Khan Shah 21202-9659371-5 03038875951
8. Naqibullah 21202-3564422-5 03027353566
9. Dost Muhammad ____________ 03025775155
10. Shabir Ahmad 21202-4142162-7 03099218905
11. Muhammad Idrees 21202-4109284-7 03005984343
12. Muhammad Ali Jan 21202-1303773-7 03077133335
13. Aziz Khan 21202-5703520-1 03349023508
14. Asad Ullah 21202-3251359-7 03077170345
15. Muhammad Alam Khan 21202-8281315-5 03063976038
33 The consultation was only done with the community of Tor Dara sub project and no community is available for consultation at
Tarkho kas as the TDPs not yet returned to their native villages after military operation. Both the projects are of same nature and
closely located.
3 Fazal Ilahi DFO 091 9213830
03009034468 Forest
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
138 | Initial Environmental Examination
16. Aman Ullah 21202-9242043-5 03342344445
17. Kashmir Khan ____________ 03065933377
Figure 7.2: Community Consultation Meetings
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
139 | Initial Environmental Examination
GRIEVANCE REDRESS MECHANISM
General
349. A Grievance Redress Mechanism (GRM), consistent with the requirements of
ADB safeguard policies will be established to prevent and redress community
concerns, reduce risks, and assist the project to maximize social and
environmental benefits, in addition to serving as a platform to resolve grievances.
For this purpose, a Public Complaint Centre with Public Complaint Committee will
be established in all concerned agencies where the project activities are in
progress. Generally, all project staff, management staff involved in the project,
and government administrators will take on grievance handling as a responsibility.
The GRM members should be qualified, experienced, and competent personnel
who can win the respect and confidence of the affected communities. Criteria for
selecting members of GRM could include the following knowledge of the project,
its objectives, and outcomes; technical knowledge and expertise, e.g., irrigation,
engineering, environmental, geological; understanding of the social, economic,
and cultural environments and the dynamics of the communities; capacity to
absorb the issues dealt with and to contribute actively to decision-making
processes; social recognition and standing; and an equitable representation of the
community.
350. The following committee members are being proposed for Public Complaint
Centers at concerned districts where project activities are being undertaken:
1. Chairperson, Project Director-FWRDP.
2. Member, community elder/Malak, Religious leader.
3. Member, Social Development Officer/ Resettlement officer - FWRDP.
4. Member, Environment Officer - FWRDP
5. Member from Village Organization (one for Executive Body and one for
General Body)
6. Member, PIU (Project Manager, Monitoring officer and Social organizer)
7. Member from Contractor/Environment Specialist/Manager
8. Member District Administration Representative
9. Member from Line Department
Objectives of Grievance Redress Mechanism
351. The main objective of establishing GRM is to resolve problems in an efficient,
timely and cost-effective manner in a cordial environment with the participation of
all stakeholders including affected parties. The GRM, it shall describe the options
available to the project for grievance redress. Any environmental or social impacts
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
140 | Initial Environmental Examination
that would be adversely affecting the general public in the project area should be
resolved through the GRM.
352. The PIU shall indicate how these would be disseminated and accessible to
affected parties in a way that should be clear and understandable to the
Implementing Agency (IA) also. The Grievance Redress Mechanism should also
have an in-built monitoring mechanism to check on responsiveness to complaints
or grievances lodged. The different forms of receiving the complaints should be
clearly described together with the different stages of going through the process.
In addition, the redress mechanism shall indicate alternatives, in case the
proposed mechanism, for any reason, does not respond to all grievances and
complaints. GRM should be able to provide benefits to both the project and
affected parties by setting up following objectives,
• Provide a forum for redressing grievance and disputes at the lowest level.
• To build up productive relationship among the all stakeholders including
affected parties.
• Provide access to affected parties to negotiate and influence the decisions and
policies of the project which might affect them adversely.
• Mitigate or prevent adverse impacts of the project on communities and
produces appropriate corrective or preventive action.
• To harmonize both project and affected parties activities.
• Open channels for effective communication, including the identification of new
social and environmental issues of concern arising from the project:
• Be accessible to diverse members of community, including more vulnerable
groups such as women and youth
• Provide opportunities for confidentialities and privacy for complainants to be
honored where this is seen as important
Awareness of GRM
353. GRM should be widely publicized among stakeholder groups such as the affected
communities, government agencies, and community organizations. Lack of
knowledge about GRM results in people not approaching and using it, and they
eventually lose the importance and the validity of the purpose for which they were
created. People should also be informed about their options, depending on the
types of complaints, but should not be encouraged to submit false claims. Criteria
for eligibility need to be communicated. An effective awareness campaign should
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
141 | Initial Environmental Examination
be launched to give publicity to the roles and functions of the GRM and should
include the following components:
• How complaints can be reported in the GRM and to whom, e.g., phone, postal
address and email addresses, of the GRM as well as information that should
be included in a complaint; procedures and time frames for initiating and
concluding the grievance redress process; boundaries and limits of GRMs in
handling grievances; and roles of different agencies such as project
implementers and funding agencies.
354. A variety of methods can be adopted for communicating information to the
relevant stakeholders:
• Display of posters in public places such as in government offices, project
offices, community centers, etc.; distribution of brochures;
• P.O BOX number should be established to receive the grievance of the
affected community through mail.
• Community-based organizations; and print and electronic media, including
radio.
Implementation of GRM
Stage 1:
355. When a grievance arises, (social & environmental /or any other) the affected
person may contact directly with the contractor/operator and the project manager
to resolve the issue of concern, if the issue is successfully resolved, no further
follow up is required.
Stage 2:
356. If solution is not found the affected person/s will submit an oral or written complaint
to the Public Complaint Centre (PCC) by themselves. In case of an oral complaint
the PCC must make a written record. For every complaint PCC must investigate
the complaint, assess its eligibility and identify an appropriate solution. It will
provide a clear response in five working days to the complainant. The PCC will
instruct the contractor to take corrective action. It will than review the contractor’s
response and undertake additional monitoring. During the complaint investigation,
the PCC will work in close consultation with the contractors and the supervising
engineer (during construction). The contractor during construction and the IA
during operation should convey the outcome to the PCC within seven working
days.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
142 | Initial Environmental Examination
Stage 3:
357. If no solution can be identified by the PCC or if the complainant is not satisfied
with the suggested solutions under stage 2, the PCC will organize within two
weeks a multi stakeholders meeting under the auspices of the irrigation
department, where all relevant stakeholders (i.e. the complainant, IA,
contractor/operator, relevant local government offices) will be invited. The meeting
should result in solution acceptable to all, and identify responsibilities and action
plan.
358. The contractor during construction and IA during operation should implement the
agreed upon redress solution and convey the outcome to the PCC within seven
working days.
Stage 4;
359. If the multi stakeholder hearing process is not successful, the PCC will inform the
project steering committee (PSC), A Project Steering Committee headed by
additional Chief Secretary, Planning and Development Department (P&DD) KP,
will provide policy guidelines for smooth running of the project activities, the
Members of PSC include the Secretary, P&DD, KP, Secretary finance KP,
Secretary Irrigation KP, Secretary Agriculture KP, Secretary Forest KP, Director
General Projects, Merged Areas , Representative of Planning & Development
Division Government of Pakistan, Islamabad, Deputy Commissioner of Khyber,
Bajaur, Mohmand Districts, representatives of all concerned line departments and
representative of ADB, PRM Islamabad. The Project Director will participate as
PSC Member cum Secretary. The PSC will meet at least twice a year or more
frequently, whenever issues requiring resolution are submitted for its
consideration. The PSC will organize special meetings to address the problem
and identify its solution.
Stage 5:
360. If the affected people are still not satisfied with the reply in stage 4, he or she can
go through local Jirga and or judicial proceedings.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
143 | Initial Environmental Examination
Stage 1
Yes
No
Stage 2
Yes
No
Stage 3
Yes
No
Stage 4
Yes
No
Stage 5
Figure 8.1: Proposed GRM
Assessment and action taken directly by the
contractor/operator and the project manager
Grievance Resolved
Grievance
Resolved
Registration of Grievance through PO BOX 023
Public Complaint Centre (PCC)
Multi stakeholders meeting under the auspices of
the irrigation department
Project Steering Committee (PSC)
Grievance
Resolved
Local Jirga and or Judicial Proceedings Grievance
Settled
Grievance
Resolved
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
144 | Initial Environmental Examination
CONCLUSION, FINDINGS AND RECOMMENDATIONS
Findings and Recommendations
361. The assessment of potential impacts of the proposed Tor Dara and Tarkho Kas
sub projects reveals that these sub projects will generate only minor to moderate
adverse environmental impacts. These adverse impacts will be mostly confined to
the construction works and will be temporary in nature. The predicted adverse
impacts will be minimized and reduced by implementing the prescribed mitigation
measures and will be continually monitored by implementing and updating the
EMP.
362. The overall finding is that the beneficial gains provided by irrigation sub projects
will by far exceed the negative impacts – most of them being short-termed and
without major interference to both the bio-physical and human environment. All
mitigation measures proposed in the Environmental Management Plan are
deemed to be appropriate. The Environmental Monitoring Plan represents the
basic verification tool for ensuring the effectiveness of the proposed measures.
363. It is emphasized that the success of the EMP depends on the respective line
agencies and institutions identified as key players in the implementation of the
EMP. The timely and complete inclusion of the EMP’s compliance clauses in the Contractor documents is mandatory to ensure the success of all environmental
safeguard measures.
Conclusion
364. As the sub projects are exclusively an irrigation system, all identified adverse
environmental impacts during the rehabilitation and improvement works of the
project will be of minor to moderate in nature, easily to be mitigated by adequate
implementation of the Environmental Management and Monitoring Plans. Entire
command of the sub projects components does not include any environmentally
sensitive areas. The measures taken to adequately mitigate negative impact in
the construction phase will be the most important task. Implementation of
proposed mitigation measures are deemed to be sufficient for negating the
potentially identified impacts. The supervision of the mitigation measures provided
in the contractor’s documents is the key for completing this project in an
environmentally sound manner.
365. The final conclusion is that, the sub projects are environmentally safe and socially
acceptable project.
366. A few, essentially minor, negative residual impacts identified in the Impact
Assessment during the feasibility study design are all unavoidable and there are
no technically or economically feasible alternatives which would remove them
altogether.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
145 | Initial Environmental Examination
ANNEXURES
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
146 | Initial Environmental Examination
ANNEX-I Rapid Environmental Assessment Checklist
The projects are screened through Rapid Environmental Assessment (REA) checklist
to determine environmental categorization. The environmental and social rapid
screening depicts that:
(i) the subproject will not require any land acquisition;
(ii) the subproject will not involve any involuntary resettlement; and
(iii) the subproject does not fall in any protected area.
Screening Questions Yes No Remarks
A PROJECT SITING
IS THE PROJECT AREA ADJACENT TO OR WITHIN ANY
OF THE FOLLOWING ENVIRONMENTALLY SENSITIVE
AREAS?
▪ PROTECTED AREA
▪ WETLAND
▪ MANGROVE
▪ ESTUARINE
▪ BUFFER ZONE OF PROTECTED AREA
▪ SPECIAL AREA FOR PROTECTING BIODIVERSITY
B POTENTIAL ENVIRONMENTAL IMPACTS
WILL THE PROJECT CAUSE…
▪ loss of precious ecological values (e.g. result of encroachment into forests/swamplands or historical/cultural buildings/areas, disruption of hydrology of natural waterways, regional flooding, and drainage hazards)?
▪ conflicts in water supply rights and related social conflicts?
▪ impediments to movements of people and animals?
▪ potential ecological problems due to increased soil erosion and siltation, leading to decreased stream capacity?
▪ Insufficient drainage leading to salinity intrusion
▪ Over pumping of groundwater, leading to salinization and ground subsidence?
Use of surface water have no effect on salinization, as the area has no salinity/alkalinity problem. No pumping of water will be required.
▪ Impairment of downstream water quality and therefore, impairment of downstream beneficial uses of water?
▪ Dislocation or involuntary resettlement of people?
No dislocation or involuntary resettlement of people will occur
▪ Disproportionate impacts on the poor, women and children, Indigenous Peoples or other vulnerable groups?
▪ Potential social conflicts arising from land tenure and land use issues?
No land acquisition will be required
▪ Soil erosion before compaction and lining of canals? N.A
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
147 | Initial Environmental Examination
Screening Questions Yes No Remarks
▪ Noise from construction equipment?
It will be managed through mitigation measures and will be documented in EMP
▪ dust during construction?
It has moderate Impact for labors during construction, but It will be managed by water sprinkling and wet earth. Dust generated will be managed through sound planning and good management practices with implementation of EMP
▪ Waterlogging and soil salinization due to inadequate drainage and farm management?
▪ Leaching of soil nutrients and changes in soil characteristics due to excessive application of irrigation water?
▪ Reduction of downstream water supply during peak seasons?
▪ Soil pollution, polluted farm runoff and groundwater, and public health risks due to excessive application of fertilizers and pesticides?
▪ Soil erosion (furrow, surface)?
▪ Scouring of canals?
▪ Clogging of canals by sediments?
▪ Clogging of canals by weeds?
▪ Seawater intrusion into downstream freshwater systems?
▪ Introduction of increase in incidence of waterborne or water related diseases?
▪ Dangers to a safe and healthy working environment due to physical, chemical and biological hazards during project construction and operation?
The subproject does not have usage of any hazardous chemicals during construction. However, health and safety measures for laborers will be taken to implement HSE Plan that will be developed and documented in EMP
▪ Large population influx during project construction and operation that causes increased burden on social infrastructure and services (such as water supply and sanitation systems)?
Local people will be employed as much as possible from close by villages/ towns and the same will be documented in EMP
▪ Social conflicts if workers from other regions or countries are hired?
Priority will be given to local for employment and the same will be documented in EMP
▪ Risks to community health and safety due to the transport, storage, and use and/or disposal of materials such as explosives, fuel and other chemicals during construction and operation?
Risk may likely lead to a very minimum and short time for community during construction time, however, Health and safety Plan and Emergency response procedures will be prepared and implemented. The same will be documented in EMP.
▪ Community safety risks due to both accidental and natural hazards, especially where the structural elements or components of the project (e.g., irrigation dams) are accessible to members of the affected community or where their failure could result in injury to the community throughout project construction, operation and decommissioning?
Safety measures for community will be taken to avoid any risk and consequence. It will be documented in EMP. However, it has major positive impact, because the construction of the new weir will save community/infrastructure from flood threat if any.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
148 | Initial Environmental Examination
Climate Change and Disaster Risk Questions The following questions are not for environmental categorization. They are included in this checklist to help identify potential climate and disaster risks.
Yes No Remarks
• Is the Project area subject to hazards such as earthquakes, floods, landslides, tropical cyclone winds, storm surges, tsunami or volcanic eruptions and climate changes?
▪ Could changes in temperature, precipitation, or extreme events patterns over the Project lifespan affect technical or financial sustainability (e.g., increased glacial melt affect delivery volumes of irrigated water; sea level rise increases salinity gradient such that source water cannot be used for some or all of the year)?
▪ Are there any demographic or socio-economic aspects of the Project area that are already vulnerable (e.g., high incidence of marginalized populations, rural-urban migrants, illegal settlements, ethnic minorities, women or children)?
▪ Could the Project potentially increase the climate or disaster vulnerability of the surrounding area (e.g., by diverting water in rivers that further increases salinity upstream, or encouraging settlement in earthquake zones)?
Note: Hazards are potentially damaging physical events.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
149 | Initial Environmental Examination
ANNEX – II Environmental Testing
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
150 | Initial Environmental Examination
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
151 | Initial Environmental Examination
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
152 | Initial Environmental Examination
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
153 | Initial Environmental Examination
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
154 | Initial Environmental Examination
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
155 | Initial Environmental Examination
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
156 | Initial Environmental Examination
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
157 | Initial Environmental Examination
ANNEX III - National Environmental Quality Standards (NEQS)
Table 1: Effluent Discharge Standards (NEQS 2000) Applicable to the Works
Sr. No. Determinant NEQS
1 Temperature 40 OC =≤3 deg. 2 pH 6 – 9
3 BOD5 80 mg/l
4 Chemical Oxygen Demand (COD) 150 mg/l
5 Total Suspended Solid (TSS) 200 mg/l
6 Total Dissolved Solids 3500 mg/l
7 Grease and Oil 10 mg/l
8 Phenolic compounds (as phenol) 0.1 mg/l
9 Ammonia 40 mg/l
10 Chlorine 1.0 mg/l
11 Chloride 1000.0 mg/l
12 Sulphate 600 mg/l
13 Manganese 1.5 mg/l
14 Fluoride 10 mg/l
15 Cyanide (as CN’) total 1.0 mg/l
16 An-ionic detergents (as MB As) 20 mg/l
17 Sulphide (S-2) 1.0 mg/l
18 Pesticides 0.15 mg/l
19 Cadmium 0.1 mg/l
20 Chromium trivalent and hexavalent 1.0 mg/l
21 Copper 1.0 mg/l
22 Lead 0.5 mg/l
23 Mercury 0.01 mg/l
24 Selenium 0.5 mg/l
25 Nickel 1.0 mg/l
26 Silver 1.0 mg/l
27 Total Toxic metals 2.0 mg/l
28 Zinc 5.0 mg/l
29 Arsenic 1.0 mg/l
30 Barium 1.5 mg/l
31 Iron 8.0 mg/l
32 Boron 6.0 mg/l
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
158 | Initial Environmental Examination
Table 2: National Environmental Quality Standards (NEQS) for Gaseous Emission
(mg/Nm3, Unless Otherwise Defined)
Sr.
No. Parameter Source of Emission
Existing
Standards
Revised
Standards
1 2 3 4 5
1. Smoke Smoke Opacity not to exceed 40% or 2
Ringlemann Scale
40% or 2
Ringlemann
Scale or
equivalent smoke
number
2.
Particulate
Matter
(I)
(a) Boilers and Furnaces
(i) Oil fired
(ii) Coal fired
(iii) Cement Kilns
(b) Grinding, crushing, clinker
coolers and Related processes,
Metallurgical Processes,
converter, blast furnaces and
cupolas.
300
500
200
500
300
500
200
500
3. Hydrogen
Chloride Any 400 400
4. Chlorine Any 150 150
5. Hydrogen
Fluoride Any 150 150
6. Hydrogen
Sulphide Any 10 10
7. Sulphur Oxide (2) (3)
Sulfuric acid/ Sulphonic acid
plants
Other plants except power
plants operating on oil and coal
400
1700
8. Carbon
Monoxide Any 800 800
9. Lead Any 50 50
10. Mercury Any 10 10
11. Cadmium Any 20 20
12. Arsenic Any 20 20
13. Copper Any 50 50
14. Antimony Any 20 20
15. Zinc Any 200 200
16.
Oxides of
Nitrogen
(3)
Nitric acid manufacturing unit.
Other plants except power
plants operating on oil or coal:
Gas fired
Oil fired
Coal fired
400
-
-
400
600
1200
Explanations:-
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
159 | Initial Environmental Examination
1. Based on the assumption that the size of the particulate is 10 micron or more.
2. Based on 1 percent sulphur content in fuel. Higher content of Sulphur will case standards to be pro-rated.
3. In respect of emissions of sulphur dioxide Nitrogen oxides, the power plants operating on oil and coal as fuel shall in addition to National Environmental Quality Standards (NEQS) specified above, comply with the following standards.
Table 3: National Environmental Quality Standards (NEQS, 2009) for Vehicular
Emission
Sr.
No. Parameter
Standard (Maximum
permissible Limit) Measuring Method Applicability
1 Smoke
40% or 2 on the
Ringlemann Scale during
engine acceleration
mode.
To be compared with
Ringlemann Chart at a distance
of 6 meters or more
Immediate effect
2
Carbon
Monoxide
(CO)
6%
Under idling condition: Non-
dispersive infrared detection
through gas analyzer.
3 Noise 85 dB(A) Sound Meter at 7.5 meters from
the source
Table 4: National Environmental Quality Standards (NEQS, 2010) for Noise
Sr.
No.
Category of Area /
Zone
Effective from 1st July,
2010
Effective from 1st July,
2013
Limit in dB (A) Leq*
Daytime Night-time Daytime Night-time
1 Residential Area (A) 65 50 55 45
2 Commercial Area (B) 70 60 65 55
3 Industrial Area (C) 80 75 75 65
4 Silence Zone (D) 55 45 50 45
Note:
1. Daytime hours: 6:00 a.m. to 10:00 p.m.
2. Night-time hours: 10:00 p.m. to 6:00 a.m.
3. Silence Zone: Zones which are declared as such by the competent authority. An area comprising not less than 100 meters round hospitals, educational institutions and courts.
4. Mixed categories of areas may be decided as one of the four above mentioned categories by the competent authority.
*dB (A) Leq: Time weighted average of the level of sound in scale “A” which is relatable to human hearing.
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
160 | Initial Environmental Examination
Table 5: National Environmental Quality Standards (NEQS, 2010) for Drinking
Water
Sr.
No. Properties/Parameters
Standard Values for
Pakistan WHO Standards Remarks
BACTERIAL
1
All water is intended for
drinking (E.Coli or
Thermotolerant Coliform
bacteria)
Must not be
detectable in any
100ml sample
Must not be
detectable in any
100ml sample
Most Asian Countries
also follow WHO
Standards
2
Treated water entering the
distribution system (E.Coli
or Thermotolerant
Coliform and total Coliform
bacteria)
Must not be
detectable in any
100ml sample
Must not be
detectable in any
100ml sample
Most Asian Countries
also follow WHO
Standards
3
Treated water entering the
distribution system (E.Coli
or Thermotolerant
Coliform and total Coliform
bacteria)
Must not be
detectable in any
100ml sample. In
case of large
supplies, where
sufficient samples
are examined, must
not be present in
95% of the samples
taken throughout
any 12-month
period.
Must not be
detectable in any
100ml sample. In
case of large
supplies, where
sufficient samples
are examined,
must not be
present in 95% of
the samples taken
throughout any 12-
month period.
Most Asian Countries
also follow WHO
Standards
PHYSICAL
4 Colour ≤15 TCU ≤15 TCU
5 Taste
Non
Objectionable/
Acceptable
Non
Objectionable/
Acceptable
6 Odour
Non
Objectionable/
Acceptable
Non
Objectionable/
Acceptable
7 Turbidity <5 NTU <5 NTU
8 Total hardness as CaCO3 <500mg/l ---
9 TDS <1000 <1000
10 pH 6.5-8.5 6.5-8.5
RADIOACTIVE
11 Alpha Emitters bq/L or pCi 0.1 0.1
12 Beta Emitters 01 01
CHEMICAL
Essential Inorganics mg/litre mg/litre
13 Aluminum (Al) mg/l ≤0.2 0.02
14 Antimony (Sb) ≤0.005 0.02
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
161 | Initial Environmental Examination
Sr.
No. Properties/Parameters
Standard Values for
Pakistan WHO Standards Remarks
15 Arsenic (As) ≤0.05 0.01
Standard for Pakistan
similar to most Asian
developing Countries
16 Barium (Ba) 0.7 0.7
17 Boron (B) 0.3 0.3
18 Cadmium (Cd) 0.01 0.003
Standard for Pakistan
similar to most Asian
developing Countries
19 Chloride (Cl) <250 250
20 Chromium (Cr) ≤0.05 0.05
21 Copper (Cu) 2 2
Toxic Inorganics mg/litre mg/litre
22 Cyanide (CN) ≤0.05 0.07
Standard for Pakistan
similar to most Asian
developing Countries
23 Fluoride (F) ≤1.5 1.5
24 Lead (Pb) ≤0.05 0.01
Standard for Pakistan
similar to most Asian
developing Countries
25 Manganese (Mn) ≤0.5 0.5
26 Mercury (Hg) ≤0.001 0.001
27 Nickel (Ni) ≤0.02 0.02
28 Nitrate (NO3) ≤50 50
29 Nitrite (NO2) ≤3 3
30 Selenium (Se) 0.01 0.01
31 Residual Chlorine
0.2-0.5 at
consumer end 0.5-
1.5 at source
---
32 Zinc (Zn) 5.0 3
Standard for Pakistan
similar to most Asian
developing Countries
Organics
33 Pesticides
mg/L ---
PSQCA No. 4629-
2004, Page No.4,
Table No. 3, Serial
No. 20-58 may be
consulted
Annex-II
34 Phenolic Compounds (as
Phenols) mg/L --- ≤0.002
35
Poly nuclear aromatic
hydrocarbons (as PAH)
g/L
0.01 (By GC/MS
method)
***PSQCA: Pakistan Standards Quality Control Authority
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
162 | Initial Environmental Examination
Table 6: National Environmental Quality Standards (NEQS, 2010) for Ambient Air
Pollutants Time-weighted
average
Concentration in Ambient Air Method of
Measurement Effective from
1st July 2010
Effective from
1st January 2013
Sulphur
Dioxide (SO2)
Annual Average* 80µg/m3 80µg/m3 Ultraviolet
Fluorescence Method 24 hours** 120µg/m3 120µg/m3
Oxides of
Nitrogen as
(NO)
Annual Average* 40µg/m3 40µg/m3 Gas Phase
Chemiluminescence 24 hours** 40µg/m3 40µg/m3
Oxides of
Nitrogen as
(NO2)
Annual Average* 40µg/m3 40µg/m3 Gas Phase
Chemiluminescence 24 hours** 80µg/m3 80µg/m3
Ozone (O3) 1 hour 180µg/m3 130µg/m3 Non disperse UV
absorption method
Suspended
Particulate
Matter (SPM)
Annual Average* 400µg/m3 360µg/m3
High Volume
Sampling, (Average
flow rate not less than
1.1m3/minute)
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
163 | Initial Environmental Examination
ANNEX – IV Governor Notifications on Wetlands and Wild Life in FATA
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
164 | Initial Environmental Examination
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
165 | Initial Environmental Examination
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
166 | Initial Environmental Examination
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
167 | Initial Environmental Examination
ANNEX-V Table of Content Environmental Compliance Monitoring
Monthly Progress Report
CONTENTS OF MONTHLY ENVIRONMENTAL MONITORING REPORT
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
168 | Initial Environmental Examination
CONTENTS
Part I Introduction ..................................................................................................................
Description of the Subprojects…………………………………………….…………….…………….
Environmental Monitoring………….……………………………………………………..……………
Part II Environmental Monitoring ..........................................................................................
Environmental Monitoring Summary.........................................................................................
Environmental Trainings………………………………………………………………………………..
Noise and Vibration ..................................................................................................................
Water Quality ...........................................................................................................................
Air Quality ................................................................................................................................
Flora and Fauna Monitoring .....................................................................................................
Fuel Consumption ....................................................................................................................
Water Consumption .................................................................................................................
Solid Waste Management ……………………………………………………………………………
Part III Environmental Management ......................................................................................
Site Inspections and Audits ......................................................................................................
Non-Compliances Notices, Corrective Action Plans .................................................................
Table
Table-I Oustanding Issues .......................................................................................................
Conclusion ……………………………………………………………………………………………..
Annexure
Weekly Monitoring Checklist
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
169 | Initial Environmental Examination
ANNEX – VI Photo Log
Tor Dara Command Area
Tor Dara Weir Site
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
170 | Initial Environmental Examination
Natu Khel Weir
Tarkho Kas Weir
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
171 | Initial Environmental Examination
Tarkho Kas Command Area
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
172 | Initial Environmental Examination
ANNEX-VII WHO Standards
Ambient Air Quality Standards
Average(24 hrs) CO NOx SO2 PM10 PM2.5
µg/m3 µg/m3 µg/m3 µg/m3 µg/m3
NEQS 10 80 120 250 35
IFC - - 125 150 75
Noise Levels (For Residential Areas)
Day Time Avg Night Time Avg
NEQS Limits 55 45
IFC/WHO Limit 55 45
Drinking Water Standards
Sr.
No. Parameter Unit
WHO
Guidelines NSDWQ Method
4. Total Coliform No./100ml 0/100 ml 0 Culture
5. E. Coli No./100ml 0/100 ml 0 Culture
6. Fecal E. Coli No./100ml 0/100 ml 0 Culture
7. pH - 6.5 – 8.5 6.5 – 8.5 Field Test- ExStik EC500
8. Temperature 0C - - Field Test-
9. Color TCU <15 <15 US EPA 110.1
10. Taste …. Not Objectionable Not Taste Panel
11. Odour ouE/m³ Not Objectionable Not Dilution
12. Turbidity NTU <5 <5 US EPA 160.1
13. Electrical Conductivity µS NA NA Field Test-
14. Total Hardness mg/l <500 NA US EPA 130.2
FATA Water Resources Development Tor Dara & Tarkho Kas Weir Sub Projects
173 | Initial Environmental Examination
Sr.
No. Parameter Unit
WHO
Guidelines NSDWQ Method
15. TDS mg/l <1000 <1000 US EPA 160.1
16. TSS mg/l NA NA Filtration
17. Ammonia mg/l NA NA US EPA 200.8
18. Arsenic mg/l 0.01 <0.05 US EPA 200.8
19. Iron mg/l NA NA US EPA 200.8
20. Aluminum mg/l - <0.2 US EPA 200.8
21. Sodium mg/l NA NA US EPA 200.8
22. Chloride mg/l NA NA SMEW
23. Sulphate mg/l 0.01 <0.05 SW-846 Test Method 9035
24. Fluoride mg/l <1.5 <1.5 US EPA 340.1
25. Nitrate mg/l <50 <50 US EPA 352.1
26. Nitrite mg/l 3 3 US EPA 354.1
27. Cadmium mg/l 0.003 0.01 US EPA 200.8
28. Chromium mg/l 0.05 <0.05 US EPA 200.8
29. Copper mg/l 2.0 2.0 US EPA 200.8
30. Manganese mg/l 0.5 <0.5 US EPA 200.8
31. Nickel mg/l 0.02 <0.02 US EPA 200.8
32. Lead mg/l 0.01 <0.05 US EPA 200.8
33. Zinc mg/l 3.0 5.0 US EPA 200.8