dhaka and western zone transmission grid expansion project
TRANSCRIPT
Resettlement Plan Document Stage: Updated Project Number: 51137-003 July 2022
Bangladesh: Dhaka and Western Zone Transmission Grid Expansion Project
Volume 3: 230 kV Goplaganj to Shibchar Transmission Line
Prepared by the EQMS Consulting Limited for the Asian Development Bank. This is an updated version of the draft originally posted in July 2019 available on https://www.adb.org/projects/documents/ban-51137-003-rp
This updated resettlement plan is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
EQMS Consulting Limited www.eqms.com.bd
Power Grid Company of Bangladesh Limited
Ministry of Power Energy and Mineral
Resources
Government of the People’s Republic of Bangladesh
JULY 2022
Dhaka and Western Zone Transmission
Grid Expansion Project (DWZTGEP)
Updated Resettlement Plan
Volume 3: 230kv Goplaganj to Shibchar Transmission Line
DOCUMENT DETAILS
Document Title Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion
Project (DWZTGEP)
Document Type Draft Report
Project Ref. No. EQMS #2091210503
Date 07-30-2022
Author Md Mosabbir Hossain
Client Name PGCB
Country Bangladesh
DISTRIBUTION LIST
Hardcopy Softcopy CDs Other form
✓ ✓ × ×
DOCUMENT HISTORY
Version Date Description Reviewed by Approved by
V-1 07-30-2022 Issue for Client Review Md. Abdul Halim,
Principal
Consultant
Kazi Farhed
Iqubal, ED
SIGNATURE PAGE
30 July 2022
Resettlement Plan for Dhaka and Western Zone
Transmission Grid Expansion Project (DWZTGEP)
Reviewed by:
Name: Md. Abdul Halim
Title: Principal Consultant
Approved by:
Name: Kazi Farhed Iqubal
Title: Executive Director
EQMS Consulting Limited
House #53, Road #4, Block - C, Banani, Dhaka
Country: Bangladesh
[email protected] | www.eqms.com.bd
This report has been prepared and reviewed by EQMS Consulting Limited with all responsible skill, care, and diligence within the
terms of the contract with the client, incorporating our General Terms and Conditions of Business and taking account of the
resources devoted to it by agreement with the client.
We disclaim any responsibility to the client and others in respect of any matters outside the scope of the above.
This report is confidential to the client and we accept no responsibility of whatsoever nature to third parties to whom this report,
or any part thereof, is made known. Any such party relies on the report at their own risk.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited i PGCB.
ABBREVATION
ADB : Asian Development Bank
APs : Affected Persons
ARIPA : Acquisition and Requisition of Immovable Property Act (2017)
ARIPO : Acquisition and Requisition of Immovable Property Ordinance (1982)
CCL : Cash Compensation under the Law
CLAC : Central Land Allocation Committee
CPR : Common Property Resources
DC : Deputy Commissioner
DWZTGEP : Dhaka and Western Zone Transmission Grid Expansion Project
DPD : Deputy Project Director
ESU : Environmental and Social Unit
GoB : Government of Bangladesh
GRC : Grievance Redress Committee
GRM : Grievance Redress Mechanism
IEM : Independent External Monitor
IoL : Inventory of Losses
JVS : Joint Verification Survey
km r : kilometer
kV : kilovolt
LGRC : Local Grievance Redress Committee
LILO : Line-in-Line-Out
MPEMR : Ministry of Power, Energy and Mineral Resources
PAVC : Property Assessment and Valuation Committee
PGCB : Power Grid Company of Bangladesh
PMU : Project Management Unit
PVS : Property Valuation Survey
RoW : Right-of-Way
RP : Resettlement Plan
R&R : Rehabilitation and Restoration
SPS : Safeguard Policy Statement (ADB 2009)
Tk : Bangladesh Taka
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited ii PGCB.
1 TABLE OF CONTENTS
ABBREVATION ........................................................................................................................................ i
LIST OF FIGURES ................................................................................................................................. iv
LIST OF TABLES .................................................................................................................................... v
GLOSSARY ............................................................................................................................................. i
EXECUTIVE SUMMARY ........................................................................................................................iii
1 PROJECT DESCRIPTION ............................................................................................................ 1
1.1 Background ........................................................................................................................ 1
1.2 Project Location ................................................................................................................. 1
1.3 Project Components .......................................................................................................... 3
1.4 Sub-project Descriptions .................................................................................................... 4
1.5 Objective of the RP ............................................................................................................ 4
1.6 Measures to Minimize Impact ............................................................................................ 5
1.7 Methodology for Up-dating and Preparation of RP ............................................................ 5
1.8 Eligibility Cut-of Date .......................................................................................................... 6
2 SCOPE OF LAND REQUIREMENT FOR THE sub-PROJECT and resettlement ........................ 7
2.1 Introduction ........................................................................................................................ 7
2.2 Transmission Towers ......................................................................................................... 7
2.3 Impact on Land .................................................................................................................. 8
2.3.1 Land Requirement for Tower Foundation ............................................................. 8
2.3.2 Land Requirement of Service Area for Tower Construction ................................. 8
2.4 Impact on Crops ................................................................................................................. 9
2.4.1 Impact on Crops within Tower Foundation and Service area ............................... 9
2.5 Impact on Crops within Clearing Width for Transmission Lines ...................................... 10
2.6 Impact on Built Structures ................................................................................................ 11
2.7 Impact on Trees ............................................................................................................... 11
2.8 Measure Adopted to Mitigate Impacts ............................................................................. 12
2.9 Summary of Impacts ........................................................................................................ 12
3 SOCIOECONOMIC INFORMATION AND PROFILE.................................................................. 13
3.1 Introduction ...................................................................................................................... 13
3.2 Demographic Profile of Affected HHs .............................................................................. 13
3.3 Sex Profile of Affected Populations ................................................................................. 13
3.4 Marital Status ................................................................................................................... 14
3.5 Age and Sex Distribution of Affected Population ............................................................. 15
3.6 Level of Education of PAPs ............................................................................................. 15
3.7 Primary Occupation of PAHs ........................................................................................... 16
3.8 Religion of PAHs .............................................................................................................. 16
3.9 Income of Affected HH ..................................................................................................... 16
3.10 Energy Use of PAHs ........................................................................................................ 17
3.11 Fuel Source of PAHs ....................................................................................................... 17
3.12 Water Source of AHs ....................................................................................................... 18
3.13 Sanitation Facilities of Ahs ............................................................................................... 19
3.14 Health and Services ......................................................................................................... 19
3.15 Role of Women and Gender Issues ................................................................................. 19
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited iii PGCB.
3.16 Indigenous Peoples ......................................................................................................... 20
4 INFORMATION DISCLOUSER, CONSULTATION, AND PARTICIPATION .............................. 21
4.1 Consultation ..................................................................................................................... 21
4.1.1 Participation through Focus Group Discussion .................................................. 21
4.2 Outcome of the FGDs discussion .................................................................................... 24
4.3 Information Disclosure ..................................................................................................... 24
4.4 Continued Consultation and Participation ........................................................................ 25
5 GRIEVANCE REDRESS MECHANISM ...................................................................................... 26
6 POLICY AND LEGAL FREMAWORK ......................................................................................... 29
6.1 Introduction ...................................................................................................................... 29
6.2 Legal Framework for Land Acquisition in Bangladesh .................................................... 29
6.3 Valuation of Assets and Property Compensation ............................................................ 30
6.4 The Electricity Act, 2018 .................................................................................................. 30
6.5 ADB’s Safeguard Policy Statement (SPS) 2009 ............................................................. 32
6.6 Involuntary Resettlement Safeguard Principles Applicable to Project ............................. 35
7 ENTITLEMENTS, ASSISTANCE AND BENEFITS ..................................................................... 37
7.1 Entitlement Matrix ............................................................................................................ 37
8 INCOME RESTORATION ........................................................................................................... 34
9 BUDGET AND FINANCING PLAN ............................................................................................. 36
9.1 Cost Estimation for Land of Tower Footing ..................................................................... 36
9.2 Cost Estimation for Crops ................................................................................................ 36
9.3 Cost Estimation for Trees of Tower Foundation Area ..................................................... 37
9.4 Cost Estimation for Trees& Bamboos of ROW ................................................................ 37
9.5 Resettlement budget (Summary) ..................................................................................... 39
10 INSTITUTIONAL ARRANGEMENTS ............................................................................................ 1
10.1 Role of the Project Director in Managing Land Acquisition and Resettlement .................. 2
10.2 Environment and Social Unit (ESU) ................................................................................... 2
10.3 Role of Implementing NGO ................................................................................................ 4
10.4 Property Assessment and Valuation Committee (PAVC) .................................................. 4
11 MONITORING AND REPORTING ................................................................................................ 6
11.1 Internal Monitoring ............................................................................................................. 6
11.2 External Monitoring ............................................................................................................ 8
12 IMPLEMENTATION SCHEDULE ................................................................................................ 10
Appendix A: Photograph of Social Survey ............................................................................................ 13
Appendix B: Photographs of FGDs ....................................................................................................... 14
Appendix C: Attendance of FGDs ......................................................................................................... 15
Appendix D: List of Land owners .......................................................................................................... 18
Appendix E: Survey Questionnaire ....................................................................................................... 21
Appendix F Details of Budget ............................................................................................................... 26
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited iv PGCB.
LIST OF FIGURES
Figure 1-1 Districts Covered by the Project ............................................................................................ 2
Figure 1-2 Guplaganj to Shibchar Transmission Line ............................................................................. 3
Figure 1-3 Subprojects under Component 1 ........................................................................................... 4
Figure 3-1 Sex Profile of the affected population .................................................................................. 14
Figure 3-2 Marital Status of the PAPs ................................................................................................... 14
Figure 3-3 Age- Distribution of PAPs in the project area ...................................................................... 15
Figure 3-4 Monthly Income of the AHHs ............................................................................................... 17
Figure 3-5 Fuel Source of PAHs ........................................................................................................... 18
Figure 3-6 Source of drinking water by household number .................................................................. 18
Figure 3-7 Sanitation Facilities of AHs .................................................................................................. 19
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited v PGCB.
LIST OF TABLES
Table 2-1 Number and Type of Transmission Towers ............................................................................ 7
Table 2-2: Land Requirement for Tower Foundation and four tower footings ........................................ 8
Table 2-3 Upazila wise Land Requirement of Service Area for Gopalganj-Shibchar sub-project .......... 9
Table 2-4 District wise land required for ROW and Estimated Damaged Crops .................................. 11
Table 2-5: Trees Affected by the Gopalganj-Shibchar230 kv Sub-project ........................................... 11
Table 2-6: Number of Affected Bamboos .............................................................................................. 12
Table -: Summary of Impacts by the Gopalganj-Shibchar 230 kv Sub-projectError! Bookmark not
defined.
Table 3-1 General Profile of Affected Population ................................................................................. 13
Table 3-2 Level of Education of PAPs .................................................................................................. 15
Table 3-3 Occupation of PAH ............................................................................................................... 16
Table 4-1 Locations and the Number of Participants at Public and Women’s Consultation ................ 21
Table 4-2 Summary of Issue discussed and response from FGD ........................................................ 22
Table 6-1 Key Features of the Electricity Act, 2018 .............................................................................. 31
Table 6-2 A Compliance Review of the Legal Framework of Bangladesh and the Safeguard Principles
of the ADB Safeguard Policy Statement of 2009 .......................................................................... 34
Table 8-1 Livelihood and Income Restoration Plan .............................................................................. 34
Table 9-1 Upazila wise land and cost estimation for tower footing ....................................................... 36
Table 9-2: Crops compensation value for Tower foundation service area and ROW .......................... 37
Table 9-3 Cost Estimation for Trees and Bamboos of ROW Clearance .............................................. 37
Table 10-1 Tasks and Responsibilities of ESU ....................................................................................... 3
Table 10-2 Membership of PAVC ........................................................................................................... 5
Table 11-1 Monitoring Indicators ............................................................................................................ 6
Table 11-2 Reference for the External Social Monitoring Expert ............................................................ 8
Table 12-1 Implementation Schedule ................................................................................................... 11
Table 12-2 Estimated Budget for Tower Footing .................................................................................. 26
Table 12-3 Estimated Budget for Crops ................................................................................................ 27
Table 12-4 : Estimated Budget for Trees .............................................................................................. 29
Table 12-5 Tower to Tower Trees ......................................................................................................... 31
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited i PGCB.
GLOSSARY
Affected Person (AP)
Individuals who are affected by the project through land acquisition,
relocation or loss of incomes, including any person, affected
households (AHs), firms or private institutions who, on account of
changes that result from the project will have their (i) standard of living
adversely affected; (ii) right, title, or interest in any house, land
(including residential, commercial, agricultural, forest, and/or grazing
land), water resources, or any other moveable or fixed assets
acquired, possessed, restricted, or otherwise adversely affected, in
full or in part, permanently or temporarily; and/or (iii) business,
occupation, place of work or residence, or habitat adversely affected,
with physical or economic displacement.
Assistance Support, rehabilitation and restoration measures extended in cash
and/or kind over and above the compensation for lost assets.
Compensation
Payment in cash or kind for an asset to be acquired or affected by
project at replacement cost based on current market value.
Cut-Off-Date
The date after which eligibility for compensation or resettlement
assistance (as the case may be) will not be considered. The final date
of census is considered as eligibility cut-off-date. This is recognized
as the social cut-off date. The legal cut-off date will be the date on
which the DC issues section 4 notice under ARIPA 2017 indicating the
intention of land acquisition.
Displaced Person
(DP)
Displaced persons are those who are physically displaced (relocation,
loss of residential land, or loss of shelter) and/or economically
displaced (loss of land, assets, access to assets, income sources, or
means of livelihoods) as a result of (i) involuntary acquisition of land,
or (ii) involuntary restrictions on land use.
Entitlements The range of measures comprising cash or kind compensation,
relocation cost, income restoration assistance, transfer assistance,
income substitution and business restoration, which are due to
Affected Households, depending on the type and degree/nature of
their losses, to restore their social and economic base.
Eminent Domain The regulatory authority of the government to obtain land for public
purpose/interest or use as described in ARIPA 2017 of Bangladesh.
The principle of eminent domain and the land acquisition laws referred
to will be applied to acquire the land required for the proposed
substations.
Inventory of Loses The record (inventory) of the affected or lost properties and assets
identified during census survey which is used as the basis for
preparation of the Resettlement Plan.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited ii PGCB.
Non-titled Those who have no recognizable rights or claims to the land that they
are occupying as per the national laws and includes people using
private or public land without permission, permit or grant i.e. those
people without legal title to land and/or structures occupied or used by
them.
Poverty Line The upper poverty line for the project region is based on the
Bangladesh Bureau of Statistics (BBS) 2011 survey which was Tk
1,125.3 per capita. Adopting national BBS inflation rates (11.5% for
2011, 6.2% for 2012, 7.5% for 2013, 7.0% for 2014, 6.2% for 2015,
5.7% for 2016 & 2017 and 6% for 2018), the upper poverty line has
been updated to Tk 1,927.69 per month per capita (i.e. Tk 8,481.83
per household/month, for an average household size of 4.4 in
Bangladesh as per the BBS data 2011). Considering the monthly
household income of Tk 8,481.83 for an average household size of
4.42 (as per the census survey, 2018), Tk 8,520 has been adopted as
the poverty line for the project area. Based on this Tk 8,520x12=Tk
102,240 is calculated as the annual poverty line and with a rounded-
off figure of Tk 102,000 is counted as poverty line in the resettlement
plan.
Relocation Rebuilding and re-establishing of private residential dwellings and
businesses in a new location
Replacement Cost
The calculation of full replacement cost will be based on the following
elements: (i) fair market value; (ii) transaction costs; (iii) interest
accrued, (iv) transitional and restoration costs; and (v) other
applicable payments, if any. Furthermore, replacement cost of the
land, structures, trees and crops affected had been assessed during
consultations conducted with APs, and information elicited through a
rapid market survey conducted with key stakeholders in the land
market and other relevant government departments such as forest,
agriculture, marketing and public works. In calculating the
replacement cost, depreciation of built structures and other assets will
not be considered.
Rehabilitation & Restoration
The restoration of income, livelihoods, and re-establishment of
sociocultural system
Significantly Affected
Households
Households who will be i) physically displaced or ii) lose more than
ten percent or more of their productive assets.
Vulnerable Households
Those households which are (i) living below the official poverty line;(ii)
women headed households living below the official poverty line; (iii)
headed by elderly over 70 years or disabled persons; and (iv) without
legal title to land and to become landless due to land acquisition. The
vulnerable status is finally determined subject to the impacts based on
social survey.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited iii PGCB.
EXECUTIVE SUMMARY
This Resettlement Action Plan has been updated which was prepared and approved by the Asian
Development Bank (ADB). The update includes changing the number of the towers and the in the
transmission lines. The consultants conducted census and IOL survey of the locations and conducted
meetings with the different stakeholders. Based on the census and IOL survey and the consultation
meetings this RP has been updated.
A. The Project
The Power Grid Company of Bangladesh Ltd. (PGCB), with financial support from theADB, has been
implementing a project named “Dhaka Western Zone Transmission Grid Expansion Project (DWZTGEP) to meet the increasing electricity demand in Bangladesh. This will involve grid
enhancement and strengthening work.
Total length of the Gopalganj-Shibchar transmission line is 25.1 km, and a total of 58 tower will be
constructed according to the original RP, however PGCB approved 53 towers for construction till date.
As per field survey, no physical displacement is required in the tower footing construction area. The
proposed transmission lines will pass mostly through agricultural fields and will not require displacement
of the houses due to the transmission lines.
Basically, land will be required at 4 legs of the tower base (Foundation work), which is estimated to be
in the range of 0.56 square meter (sqm) per tower. In the project, a total of 58 no. towers will be erected,
of which 17 angle & 41 suspension towers. Accordingly, for the erection of 58 towers total loss of land
in the legs is estimated to be about 0.0081 Acres. Further, an area estimated of 11.03 acres will be
required for stacking materials during the construction period as service area. As of to the tune of
248.1746 Acres (25.1km alignment with 40-meter width) will also be getting affected temporarily during
stringing of the transmission lines.
B. Impacts Identified by the Project
The project will require procumbent of private land for the tower footing. The project will have also
impact on tress and crops. No structures will be affected during the construction period as well.
C. Socioeconomic Information
The socio-economic profile is 71 HHs comprising 333 people will be affected by the project with average
HH size 4.7. The overall male female ratio of the project area is 100:112.98 (the national ratio is
100:99.68) which implies that the project area is different from the corresponding national condition with
a higher female population.
There are no indigenous people’s settlements in the affected area of the project. Therefore, no permanent or temporary and direct or indirect impacts on indigenous people’s communities are anticipated.
The survey find that primary and secondary level enrolment is high in the project area. It also indicates
that higher education rate is high among female population. Among 333 people 103 are educated in
primary level which is highest number in this area for educational attainment.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited iv PGCB.
Agricultural is the primary occupation in the project area. Women are usually doing unpaid household
work for their family. Study finds that 19.8% were involve with agriculture and 0.3% services as highest
and lowest level of income.
Electricity is the main source of lighting for 100% grid connected households Firewood is the main
source of energy used by most of the households (41%) for cooking and boiling purposes followed by
8.6% using liquefied petroleum gas, particularly by people living closer to urban areas. Kerosene is
used by 11.0%.
The major source of drinking water is tube-well where about 68% population use tube-wells water.
About 38% and 15% of households use non-water-sealed and water sealed sanitary latrine facility,
respectively rest use non-sanitary latrine.
No major chronic illnesses are reported from the subproject affected areas. However, incidence of water
borne diseases and skin ailments were frequently reported during consultations.
D. Information Disclosure, Consultation and Participation
A total of 07 consultation meetings were held during updated of the RP. Consultations were held with
the different stakeholders such as local leaders, farmers, businessman, service holder, housewives,
day laborers, etc. In the consultation meetings, discussions held on the project description, the scope
of the project, social safeguard issues, probable impacts and mitigation measures about the project,
Gender-Based Violence risks of the project etc. Professionals of EQMS participated in the consultation
meeting and responded to the questions of the participants. By the consultation meetings, the identified
positive and negative impacts are pointed out below.
• Electricity service would enhance
• Different local business would emerge
• Local employment would increase
• Irrigation system would develop by supplying uninterrupted electricity.
• Economic activities would be much better
• Income and livelihood opportunities would increase due to project intervention.
• The standard of living will be developed.
• Cultivation will not be possible with a tractor under electric towers.
• Land under the transmission line will be less valuable
• Construction of multi-storied building under the transmission lines will be restricted
E. Grievance Redress Mechanism
Through public consultations, PAPs were informed about their right to lodge and resolve any
grievance/complaints they may have regarding social & resettlement issues. Gender-Based Violence
(GBV) related risks were also discussed in the consultation meetings.
The RP implementing agency will assist the Project Director in identifying service provider organizations
in the project area. The GRM will record all GBV related complaints and pass them on to the service
provider. The GRM will document whether the complaint is project induced or not. If the complaint is
related to the project the GRM will track the complaint and keep updates through monthly progress
reports. If not, the GRM will not track the complaint.
Grievances will be settled with full representation in GRCs constituted by the representatives from the
PGCB, RAP implementing agency, local government institutions (LGI) and the PAPs. The PAPs will
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited v PGCB.
call upon the support of the IA to assist them in presenting their grievances to the GRCs. The GRCs
will review grievances involving compensation and resettlement assistances, livelihood restoration.
Grievances will be redressed within four weeks from the date of lodging the complaints.
Table: Hierarchy of GRMs
Level Members at Different Levels & Time Frame
Field Level • Project officers appointed by PGCB (Time frame is two weeks)
Local Community Level
• Executive engineer of the project;
• Contractor or his representative;
• A male and a female member of the concerned Union;
• A representative of the aggrieved party (the representative should be a female if
the aggrieved party is a female). (Time frame is two weeks)
PMU Level
• Project Director of the relevant subproject;
• Resettlement Specialist of the environmental and social unit;
• Team Leader of the contractor;
• The one responsible for land acquisition;
• A representative of the aggrieved party;
• A representative of the civil society. (Time frame is one month)
F. Policy and Legal Framework
The government does not have a national policy on involuntary resettlement. The law of eminent domain
is applied for the acquisition of land for infrastructure projects of public interest. The legal and policy
framework for land acquisition and involuntary resettlement for the project will be based on: (i) the
recently enacted Acquisition and Requisition of Immovable Property Act (ARIPA) 2017 (ii) the Electricity
Act of 2018; and (iv) ADB's Safeguards Policy Statement (SPS), 2009, which applies to all ADB financed
and/or administered projects, regardless of the country of where the project is located or the financing
modality (i.e., loan, a grant, or other means).
G. Entitlements, Assistance and Benefits
This section presents an entitlement matrix that provides for compensation and other R&R assistance
for different losses of the affected persons depending on the type and scope of the losses, its impact,
and status of ownership to the affected assets and the social and economic vulnerability of the affected
persons. The land procured for the project as well as the land, trees, and crops that would be affected
by impacts imposed on land use during the construction of the transmission towers and lines will be
compensated. Furthermore, the landowners will be allowed to continue to use the land falling within the
ROW of the transmission lines and under the transmission towers (except for planting of tall trees) after
the completion of construction work. In addition, since there are no land acquisitions for transmission
lines, people can still retain their ownership to the land, and use it for residential and cultivation purposes
provided the vertical clearance requirement is maintained.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited vi PGCB.
Table: Types of Losses and the Corresponding Entitlements in accordance with the policies
and legal framework of the government and ADB safeguard policies
Type of Loss Entitlements
Agricultural, fallow land, pond land,
and commercial land used for tower
footing
• Cash Compensation
Trees within the ROW of the
transmission lines
• Cash compensation at replacement cost and R & R
assistance
Any crops within the tower foundation
area and service area of the tower
footing
• Considering the assessed rate of DAE of a given
variety of crop, average seasonal production of the
cultivated land and the number of seasons lost to the
farmer
• Assistance for restoration of the land to its previous
state or better level.
Crops within the ROW of the
transmission lines
• Cash compensation recommended by PAVC based on
assessed rate of DAE for given variety of crop,
average seasonal production of the cultivated land and
the number of seasons lost to the farmer.
• Assistance for restoration of the land to its previous
state or better level
Vulnerable allowances • R&R assistance
Livelihood restoration allowances • R&R assistance
Unforeseen adverse impacts on
properties and livelihoods during
project construction
• Cash compensation at replacement cost
Unforeseen other impacts • Will be assessed and determined based on safeguards
principles and incorporated into the entitlement matrix
H. Income Restoration
The project will not cause permanent physical displacements and relocation of affected people.
Landowners will receive compensation from the project for the acquired land at replacement cost
together with additional compensation for affected standing trees, crops and fish stocks. Meanwhile,
leaseholders and sharecroppers will receive cash compensation for the loss of their crops and incomes.
Livelihood restoration grants will be provided to the significantly affected households to help them
restoring their livelihoods and incomes. Additional cash grants will also be provided to vulnerable
households to cope with their income losses during a transitional period and until their livelihoods are
reestablished. The project encourages the landowners to invest their compensation money diligently,
and for productive purposes such as buying alternate land for cultivations or initiating alternate
livelihoods so that they would not be impoverished by the loss of their land or face food insecurities in
their households. Project will also extend assistance to leaseholders and sharecroppers to find alternate
land for cultivations. The construction work of the transmission lines will temporarily affect the crops
cultivated within the clearing RoW as well as trees grown therein. It is estimated that 71 households
would be affected. Project will pay compensation for the affected crops for the duration of the
construction period and the trees that are to be removed from the RoW. Project will encourage APs to
use part of their compensation for re-planting the trees and will facilitate linkages with support agencies
that can assist the APs in replanting programs. Project will also reach agreements with construction
contractors to offer employment in construction work, specifically for households affected by the project.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited vii PGCB.
I. Budget and Financing Plan
The cost for the resettlement plan for this project has been estimated at the mouza rate for the land for
tower footing, DOF rate for trees, and DAE rate for the losses of standing crops. A total of BDT
59,558,673 is estimated for the project as the resettlement cost of land, crops, tress and unforeseen
other impacts.
J. Institutional Arrangement
PGCB will be the executing agency of the overall project. The executing agency will establish a Project
Management Unit (PMU) for the overall implementation and coordination of the project related activities.
The PMU with its Project Director (PD) appointed to be in-charge of different components of the Project
will be responsible for overall project planning and implementation, including procurement, accounting,
quality assurance, social and environmental issues, coordination with concerned agencies, supervising,
monitoring, and auditing. It is also the responsibility of PMU to report to ADB on the implementation of
the resettlement plan on a semiannual basis during construction and on annual basis during operation.
The PD will be assisted by two Deputy Project Directors (DPDs). PGCB has an environmental and
social unit (ESU) at its headquarters composed of a manager and two engineers with resettlement
experience.
K. Monitoring and Reporting
PGCB will have the overall responsibility for monitoring the project processes, outputs, outcomes and
impacts in periodic intervals. The project will be monitored both internally and externally as required by
ADB’s SPS 2009 for projects classified for A category. The executing agency will establish the necessary institutional arrangements required for monitoring of the implementation of the resettlement
plan. The project director who will be responsible for the overall project management and coordination
will appoint competent staff to carry out the internal monitoring activities. Semiannual reports will be
submitted to ADB and disclosed on the ADB website.
An External Monitoring Agency (EMA), independent of the project, with prior experience in resettlement
and rehabilitation of development induced displacement has been engaged to carry out external M&E
and for reporting on the implementation of the RP. The EMA will carry out quarterly, annual, mid-term
and final evaluation and recommend necessary changes to the PMU. The scope of external monitoring
will cover compliance monitoring and social impact evaluation of RP implementation.
L. Implementation Schedule
A time bound implementation schedule for the RP has been prepared and it is synchronized with project
construction schedule. The RP implementation is expected to be completed within 36 Months. The
overall schedule of implementation is based on the principle that resettlement benefits are paid to
project affected households before they are displaced and civil engineering works takes off.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 1 PGCB.
1 PROJECT DESCRIPTION
1.1 Background
1. This draft resettlement plan is prepared for the proposed Dhaka and Western Zone
Transmission Grid Expansion Project (DWZTGEP, hereafter 'the project') which focuses on expanding
the transmission system to deliver electricity to load centers in Dhaka and western Bangladesh. This
draft resettlement plan is developed based on several assumptions and preliminary engineering
designs. The detailed and final engineering designs are yet to be completed. RAP implementing NGO
(EQMS, hereafter “INGO”) will conduct a full census of all affected persons and prepare a corresponding
inventory of losses based on final designs.
2. To sustain the country's economic momentum, the government has prepared the Power
System Master Plan 2016 to increase power generation capacity, as well as improve and extend the
power transmission and distribution network, with the aim of achieving universal access to electricity by
2021. Further, Bangladesh's Seventh Five Year Plan envisages an integrated development strategy for
the Greater Dhaka area and west zone encompassing Dhaka, Khulna, and Barishal. The government
has a national target of electricity for all achieved by 2021 from 91% in 2018. Per capita electricity
consumption is expected to increase from 336 kWh in 2018 to 514 kWh by 2020
3. PGCB, a state-owned enterprise, is the sole company responsible for power transmission in
the country. Development of transmission and distribution system in line with generation capacity
additions have been identified as a key element of the power sector strategy in the Seventh Five-Year
Plan, FY2016 - FY2020. Transmission system expansions are required to cater the increasing demand
in existing and new load centers. PGCB is the executing agency (EA) of the project. The project will be
funded by the Asian Development Bank (ADB) with a regular loan of $300 million, a loan of $200 million
by the Asian Infrastructure Investment Bank (AIIB), and a $750,000 grant provided by People's Republic
of China Poverty Reduction and Regional Cooperation Fund (PRC Fund) which is administered by ADB.
The balance will be financed by the government and PGCB. ADB and AIIB will finance the transmission
system in Greater Dhaka and western region, and the installation of the ERP system. PRC Fund will
support a pilot drone inspection center within the operation and maintenance department of PGCB with
some gender equality element. The project implementation period is 4 years and 9 months starting from
October 2019.
1.2 Project Location
4. The project area comprises five (5) administrative divisions and 20 districts as depicted in below
Figure 1-1 Khulna and Barishal Divisions, and the Faridpur, Madaripur and Gopalganj Districts of
Dhaka Division, all located south of Padma River, can be grouped as Southwest Bangladesh, while
Rajshahi and Rangpur Divisions bordered by Padma and Jamuna Rivers can be grouped as Northwest
Bangladesh. Merger of Southwest and Northwest Bangladesh forms the Western Zone.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 2 PGCB.
Figure 1-1 Districts Covered by the Project
5. The project will support the electricity distribution network of Dhaka Electricity Supply Company
Limited (DESCO), one of the agencies responsible for electricity distribution in Dhaka and Narayongonj
districts. Electricity demand in DESCO distribution area is expected to grow up to 2,600 MW and 5,100
MW by 2025 and 2030 respectively. The project will also address severe low voltage problem in the
Western districts of Northwest Bangladesh such as Naogaon, Dinajpur, Nilphamari and Lalmonirhat,
which are also the major grain cultivation zones having high electricity demand for irrigation purposes.
Electricity demand in Western Bangladesh is expected to grow up to 3,500 MW and 5,400 MW by 2025
and 2030 respectively. Below Figure 1-2 shows the transmission line of Gopalganj to Shibchar sub-
project.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 3 PGCB.
Figure 1-2 Guplaganj to Shibchar Transmission Line
1.3 Project Components
6. The project consists of three main components as described below.
Component 1 –Transmission System Development in Greater Dhaka includes: i) construction of 400
kV, 230 kV and 132 kV transmission lines with respective cumulative line lengths of 22 km, 9 km, and
9 km; and ii) construction of 400/230 kV and 230/132 kV substations with respective cumulative
capacities of 3,750 MVA and 700 MVA. As shown in Figure 1-3, except for Kaliganj (Gazipur) substation
and related transmission lines, all other subprojects are located within the boundaries of DESCO service
area, which falls inside the densest district of the country. Given this situation, finding suitable corridors
for construction of overhead transmission lines is difficult. As such, the proposed 230 kV and 132 kV
transmission lines of Component 1 will be underground cables except in narrow river crossing areas.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 4 PGCB.
Figure 1-3 Subprojects under Component 1
Component 2 – Transmission System Development in Western Zone comprises: i) construction of 230
kV and 132 kV transmission lines with their respective cumulative lengths of 135 km and 233 km; ii)
construction of 230/132 kV, 230/33 kV and 132/33 kV substations with their respective cumulative
capacities of 750 MVA, 240 MVA and 2,080 MVA, and iv) construction of twenty 132 kV bay extensions
at 9 existing substations.
Component 3 – Institutional Capacity Development of PGCB includes: (i) implementation of Enterprise
Resource Planning (ERP) system, and (ii) establishment of a Drone Inspection Center within the
operation and maintenance department of PGCB with some gender equality elements.
1.4 Sub-project Descriptions
7. Gopalganj-Shibchar Transmission line located in the south-western region of Bangladesh and
crossed two districts namely Gopalganj and Madaripur. The transmission line started at Moksudpur of
Gopalganj district and ended at Shibchar of Madaripur districts. Total length of this 230 kV transmission
line is 25.1km. The Gopalganj-Shibchar transmission line have a total of 64 transmission towers
including 21 Angle Towers, rest of the towers are suspension towers. It is to be mentioned here that, till
to date PGCB approved all 53 towers for constructions. However, the updated resettlement plan is
presented social impacts and mitigation measure of 64 towers required for 230 kV Goplaganj to
Shibchar transmission line.
1.5 Objective of the RP
8. This RP is an updated version of the previously approved resettlement plan. The RP for
Gopalganj-Shibchar sub-project is based on the preliminary engineering design prepared during project
preparation.
9. This RP applies to full or part, permanent or temporary physical displacement (relocation, loss
of agricultural and residential land, or loss of shelter) and economic displacement (loss of land, assets,
access to assets, income sources, or means of livelihoods) resulting from dislocation of any
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 5 PGCB.
shops/businesses due to any project. In the establishment of the proposed water transmission line, a
resettlement plan is prepared. The RP presents:
▪ Types and extents of losses including agricultural land and sources of income and livelihood.
▪ Socio-economic conditions of APs of project area.
▪ Principles and legal framework applicable for mitigating losses.
▪ The Entitlement Matrix.
▪ Outcome of Community Consultation and Focus Group Discussion.
▪ Livelihood and Income Restoration Program.
▪ Schedule of RP implementation.
▪ RP implementing budget.
▪ Monitoring and Evaluation.
1.6 Measures to Minimize Impact
10. To reduce impact on livelihood due to physical displacement from land, extensive and elaborate
consultation were held with APs to understand their views and expectations. The following key efforts
were undertaken:
▪ Extensive consultations were conducted with the affected population and their views incorporated in the RP.
▪ Provisions for cash compensation of acquired land, affected structures, trees and other assets at current market price.
▪ The LIRP will be carried out to assist the APs to develop new activities and to explore better income sources.
1.7 Methodology for Up-dating and Preparation of RP
11. Series of discussions were conducted with the affected persons, Resettlement Specialist,
Project Director of DWZTGEP and relevant stakeholders for preparation of the RP.
12. A Census and SES conducted through questionnaire and checklist for collecting data from the
project (Gopalganj-Shibchar) for preparing the RP. All instruments, study tools were developed in
Bengali and pre-tested for finalizing and submitted to PMU for approval.
13. All the field staff was trained for one day for creating a responsive environment with APs,
maintaining confidentiality, communication skill and how to present the tools/instruments and recording
their responses. The field enumerators were assigned in pairs in different location of the project area
pockets for data collection purpose.
14. Survey was conducted for all affected households during February 2022, and data entry and
analysis were completed in March 2022.
15. It may be mentioned that, during February 2022, ten (10) FGDs were conducted with the
affected populations and primary stakeholders of the project area. The discussions were held on
relevant matters, like potential project impacts and mitigation measures, income/business restoration,
income generating alternatives, farmers, gender issues etc. The Socio-Economic Survey was done in
conjunction with stakeholder consultations and FGDs. The survey questionnaire is attached as Annex
01.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 6 PGCB.
16. The objectives of the socio-economic survey were to identify the AHs, establish a detailed
inventory of losses that would occur by type and quantity due to the construction of Transmission Tower,
develop socio-economic profiles of the affected households (AHs).
1.8 Eligibility Cut-of Date
17. The cut-off date refers to the date, after which eligibility for compensation or resettlement
assistance will not be considered. As per SPS-2009 of the ADB, Starting date of carrying out the
census/inventory of losses (IoL) is considered as the Cut-of Date for eligibility for receiving
compensation. The location of the tower of this transmission line has been video filmed to document
the actual inventory to be affected by the Project. This has been done to prevail over fraudulent claims
for compensation from the project. The cut-off date for this project is 14th February 2022.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 7 PGCB.
2 SCOPE OF LAND REQUIREMENT FOR THE SUB-PROJECT AND RESETTLEMENT
2.1 Introduction
18. The component-2 of the Dhaka and Western Zone Transmission Grid Expansion Project
(DWZTGEP), includes expansion of transmission system in the western zone of Bangladesh. The 230
kV capacity transmission line between Gopalganj-Shibchar is one of the major sub-projects. Total length
of the Gopalganj-Shibchar transmission line is 25 km, and a total of 58 tower will be constructed,
however, PGCB approved 53 towers for construction. Constrcutuion approval of the remaining (5)
towers is under process. For constructing transmission tower and installing transmission line, the sub-
project requires land. There are no provisions in the Electricity Act-18 for procuring required land to
establish RoW for transmission lines. However, founding tower footings can cause permanent loss of
land, and clearing RoW for transmission stringing can cause temporary damage to the land during
construction period, loss of standing crops and trees. Clearing width of the RoW to pave the way for
constructing transmission lines lead to permanent economic displacement due to removal of trees, and
temporary restriction on agricultural activities on land.
19. The PGCB appointed and engaged EQMS Consulting Limited as consultant for conducting
social value assessment surveys, preparation, upgradation, and implementation of Resettlement Action
Plans (RAPs) and environmental and social safeguard supervision and monitoring for the proposed grid
substations and transmission lines under DWZTGEP.
20. EQMS Consulting Limited conducted social survey, identified landowners of tower foundation,
assessed project impact, assessed loss of land, structures, trees, loss of income, and assessed value
of lost assets in February 2022. Scope of land requirement and resettlement impact based on social
assessment is presented hereunder categorically.
2.2 Transmission Towers
21. The location of Goplaganj to Shibchar 230 kV transmission line spans from Muksodpur upazila
of Gopalganj district to Shibchar Upazila where Bhanga upazila of Faridpur district and Rajoir Upazila
of Madaripur will also touched by the transmission line. The number of transmission towers required for
Goplaganj to Shibchar transmission lines through 58, which include 17 angle/terminal towers and 43
suspension towers. Though, PGCB approved 53 towers for construction as of today. The line span
(tower to tower distance) is 370 m approximate for 230 kV lines. The ratio between angle/tension towers
and suspension towers is 35:65. This RP is prepared based on the entire number of towers. The number
of towers required and approved for Guplaganj to Shibchar transmission lines are shown in Error!
Reference source not found. below.
Table 2-1 Number and Type of Transmission Towers
Name of the
Lines
Estimated No. of Towers Approved No. of Towers
Angel + Terminal Suspension Angel + Terminal Suspension
Guplaganj to
Shibchar 230 (kV)
17 43 12 41
Source: Estimates based on PGCB’s information
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 8 PGCB.
2.3 Impact on Land
22. The Gopalganj-Shibchar sub project requires land for constructing and installing transmission
tower and stringing conductor. The length of 230 kV capacity Gopalganj-Shibchar sub-project is 25.1
km and will be connected through 58 towers of both angle and suspension category. As of today, PGCB
has approved 53 towers for construction. Erection of towers, service area during towers erection and
temporary clearing ROW width for stringing required land. Land requirement for the sub-project is
presented specifically in following sub-section.
2.3.1 Land Requirement for Tower Foundation
23. Under the Gopalganj-Shibchar sub-project, a total of 58 towers will be erected at different
locations. Among 58 towers, 17 is angle towers, and the rest are suspension towers. It has been stated
that, PGCB approved 53 towers for construction as of today. A RP has been prepared for DWZTGEP
project. Based on available data provided in the RP, each tower required approximate 0.012506003
acres (50.61 m2), and the four tower footings of the tower combinedly required only 0.000138379 acres
(0.56 m2) of land within the Tower foundation base area. Erection of Towers have permanent impact on
land selected for the tower, and it is the common evidence in Bangladesh that the peoples will be
allowed to cultivate underneath the Towers base area. Land requirement for the Tower foundations and
four tower footigs combinedly is presented in the below Table 2-2. The ownership of affected land
belongs to private and applicable compensation will be provided as per entitlement matrix of the RP.
The Gopalganj-Shibchar subproject crosses 2 upazila of Madaripur district and 1 upazila of Gopalganj
district and 1 upazila of Faridpur district. Upazila-wise number of towers and impact on land for
proposed towers is presented in the below Table 2-2:
Table 2-2: Land Requirement for Tower Foundation and four tower footings
Name of District Name of Upa-Zila No. of Towers
Impact on Land for Foundation Base (acres)
Land lost Permanently for Tower Footings (acres)
Gopalganj Moksodpur 3 0.04 0.0004
Faridpur Bhanga 12 0.15 0.0017
Madaripur
Shibchar 26 0.21 0.0024
Rajoir 17 0.33 0.0036
Total 58 0.73 0.0081
2.3.2 Land Requirement of Service Area for Tower Construction
24. For the interim period during construction of Transmission Towers, the project requires
additional land to be used as service area. The Towers installation contractor will use the land for
keeping construction materials and equipment and temporary worker’s shade. The electricity Act-2018
has no provision for land acquisition, and the tower-specific additional land for service area will be
procured for comparatively short period of time. As there is no permanent impact on land, the project
anticipated loss of crops and trees standing on the land and livelihood impact. After completion the
construction of the Tower, the landowner will retain the land for agricultural uses. However, the project
authority ensured compensation for lost crops and trees standing on the land. As discussed with the
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 9 PGCB.
ESU, each Angle Tower requires 0.25 acre (1011.62 m2) of land for service area, while each
Suspension Tower requires 0.15 acre (606.98 m2). Summary of temporary requirement of additional
land for the Gopalganj-Shibchar 230 kv sub-project is presented in the below Table 2-3
Table 2-3 Upazila wise Land Requirement of Service Area for Gopalganj-Shibchar sub-project
Name of
district
Name of
Upazila No. of Towers
Amount of Land
required (Acre)
Total No. of
Towers and
Land (Acre)
Angle Suspension Angle Suspension Towers Land
Gopalganj Moksodpur 1 2 0.25 0.30 3 0.55
Faridpur Bhanga 3 9 0.75 1.35 12 2.10
Madaripur Rajoir 5 12 1.25 1.80 17 3.05
Shibchar 8 18 2.00 2.70 26 4.70
Total 17 41 4.25 6.15 58 10.4
2.4 Impact on Crops
2.4.1 Impact on Crops within Tower Foundation and Service area
25. Construction of Transmission Towers, the project requires additional land to be used as service
area. The Towers installation contractor will use the land for keeping construction materials and
equipment and temporary worker’s shade. The electricity Act-2018 has no provision for land acquisition
and the tower-specific additional land for service area will be procured for comparatively short period.
As there is no permanent impact on land, the project anticipated loss of crops on the land and livelihood
impact. After completing the construction of the Tower, the landowner will retain the land for agricultural
uses. However, the project authority ensured compensation for lost crops standing on the land. As
discussed with the ESU, each Angle Tower requires 0.25 acre (1011.62 m2) of land for service area,
while each Suspension Tower requires 0.15 acre (606.98 m2). Impact of tower foundation will directly
affect the populations living within the service area.
However, economic loses are anticipated due to the removal of crops during construction period. While
updating RP for the Gopalganj-Shibchar sub-project, EQMS assessed loss of crops grown within the
said service area and estimated crops value. All lands within service area are agricultural land and
cultivated 2-3 times in a year. There are two distinct cropping seasons: Rabi (mid-November to mid-
March) and Kharif (mid-March to mid-November). The Kharif season is further sub-divided into two
parts namely Kharif-I (mid-March to mid-July) and Kharif-II (mid-July to mid-November). In Rabi season
which is extended from November to March are mainly produce crops like potato, lentil, cumin, wheat,
nut, onion, garlic etc. With some winter vegetable. In kharif-I, which is extended from march to July is
mainly grows Paddy and kharif-II which is extended from July to November is known for growing jute
and Paddy within these areas. However, compensation for lost crops will be provided for single year
produce to facilitate the civil construction works. Average distance from one tower to next tower is 380m,
and total land has been calculated that comes under service area and tower foundation is 11.03 acres.
Summary of approved tower-specific temporary requirement of additional land for the Gopalganj-
Shibchar 230 kv sub-project is presented in the below
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 10 PGCB.
Name of
district
Name of
Upazila
Amount of Land
required (Acre)
Total
land
required
for
service
area
(acre)
Average Crops Produce (In kg)
season wise1
Kharip-
I
(March-
July)
Kharip-II
(July-
November)
Rabi
(November-
March) Angle Suspension
Gopalganj Moksodpur 0.26 0.32 0.58 870 1450 1972
Faridpur Bhanga 0.78 1.45 2.24 3360 5600 7616
Madaripur
Rajoir 1.31 1.95 3.25 4875 8125 11050
Shibchar 2.08 2.93 4.96 7440 12400 16864
Total 4.43 6.65 11.03 16545 27575 37502
2.5 Impact on Crops within Clearing Width for Transmission Lines
26. Impacts of transmission lines causing from installation of transmission towers and stringing
conductors will directly affect the populations living within the clearing width of the 20 m corridor of the
230 kV Gopalganj-Shibchar sub-project. Installation of overhead stringing conductor will have direct
and temporary impacts on the crops grown within the clearing width of the 40 m corridor due to its
clearing ROW to facilitate the transportation of construction material and the movement of machinery.
Except for permanent loss of land for tower foundations, transmission towers will not have adverse
impacts on the agricultural activities and the livelihoods of people. However, economic loses are
anticipated due to the removal of crops during construction period. While updating RP for the Gopalganj-
Shibchar sub-project, EQMS assessed loss of crops grown within 40 m corridor of the ROW and
estimated crops value. All lands within the ROW width are agricultural land and cultivated 2-3 times in
a year. There are two distinct cropping seasons: Rabi (mid-November to mid-March) and Kharif (mid-
March to mid-November). The Kharif season is further sub-divided into two parts namely Kharif-I (mid-
March to mid-July) and Kharif-II (mid-July to mid-November). In Rabi season which is extended from
November to March are mainly produce crops like potato, lentil, cumin, wheat, nut, onion, garlic etc.
with some winter vegetable. In kharif-I, which is extended from march to July is mainly grows Peddy
and kharif-II which is extended from July to November is known for growing jute and Peddy within these
areas. However, compensation for lost crops will be provided for single cropping season which is
Rabi/dry season to facilitate the civil construction works. Average distance from one tower to next tower
is 380m, and total land has been calculated within the 40m width ROW. Total 248.1746 acre
(1004234.697m2) came within ROW of which 15.5354 acre (62863.6936m2) in Gopalganj district, while
45.5634 acre (184371.4803m2) belongs to Faridpur district and 187.0758 acre (756999.5527m2)
belongs to Madaripur district., crops loss in the Rabi season has been consider for compensate to
facilitate the work of ROW clearence. Value for crops is assessed according to the methods of
Department of Agricultural Extension (DAE). District-wise number of towers, amount of land, average
agricultural production and value of standing crops is presented in the below Table 2-4.
1 Volume of crops production derived from the DAE’s projection of crops production/hectare
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 11 PGCB.
Table 2-4 District wise land required for ROW and Estimated Damaged Crops
Name of District Total Length of
TL No.of Towers
Amount of Land
(acre) with ROW
Average Crops Produce in a
Single season (In kg)
Gopalganj 1.6 3 15.5354 21,420
Faridpur 4.6 12 45.5634 62,560
Madaripur 18.9 43 187.0758 257,380
Total 25.1 58 248.1746 341,360
2.6 Impact on Built Structures
27. During census and preparation of individual Inventory of Loses (IoL), no built structures of both
primary or secondary category were identified on the land selected for tower foundation, service area
and clearing width of ROW for installing transmission line of 230 kV Gopalganj-Shibchar sub-project.
As there are no structures, which means that the Gopalganj-Shibchar sub-project does not have
physical displacement due to the project intervention.
2.7 Impact on Trees
28. Given technical specification of the construction of towers and transmission lines, a significant
number of standing trees of different varieties and size have been affected and must be removed to
pave the way of the tower foundation and transmission lines. Clearing width of RoW defined 20 m on
either side from the center line of the route. All trees and scrubs within the 40 m RoW of transmission
line route should be cut down and remove for clearing the ROW. Appropriate mitigation measures have
been adopted and identified owner of tress will be compensated. Trees standing on the land of tower
location, and withing the ROW of transmission lines of the 230 kv Gopalganj-Shibchar sub-project has
been enumerated during sub-project specific RP updating. The total number of trees to be removed is
estimated at 2979 which include 890 fruit-bearing trees (29.88%), 1904 timber trees (63.91%), and 185
medicinal plants (6.21%), 1010 sapling from different vareities. During the survey, it was found that
most of the timber trees are mehgini, raintree, korai and akasi (local name), fruit bearing trees have
many species mostly mango, jackfruit, palm, dates, peach. Medicinal trees found mostly as neem, sishu
though the quantity is few. Trees on tower location and within the ROW of transmission line of 230kv
Gopalganj-Shibchar sub-project is presented in the below Table 2-5:
Table 2-5: Trees Affected by the Gopalganj-Shibchar230 kv Sub-project
Location Fruit Trees Timber Trees Medicinal Plant
Total Trees (> 10 m
height)
(5-10 m
height)
(> 10 m
height)
(5-10 m
height)
(> 10 m
height)
(5-10 m
height)
Tower Foundation 10 14 5 20 5 15 69
ROW Transmission Line 155 710 429 1450 126 40 2910
Total 165 725 434 1470 131 55 2979
29. Additionally, during the field visit and the survey, it was observed that, some bamboo yard will
be affected at different points of Gopalganj-Shibchar transmission line. Different size of baboo must be
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 12 PGCB.
cleared in the the tower foundation and ROW as it is considered the fastest growing species. Number
of bamboo of different size on within the RoW of transmission line of 230kv Gopalganj-Shibchar sub-
project is presented in the following Table 2-6
Table 2-6: Number of Affected Bamboos
Location Bamboo
Total (> 10 m height) (5-10 m height)
ROW Transmission Line 859 2535 3394
Total 859 2535 3394
2.8 Measure Adopted to Mitigate Impacts
30. The project will use private land for a short period of time to construct towers in the chosen
location. The project has ensured avoiding and minimizing any adverse socio-economic impact on the
community by adopting a mitigation policy. Since no residential structures will be affected by the project,
there will be no displacements. The project will ensure that compensation for assets lost in the process
is paid according to current market price and other measures will be taken to ensure that the
socioeconomic conditions of the affected population do not deteriorate from the present status.
31. There will be no major impact on livelihood as no land acquisition is required or no primary and
secondary structures will be affected. There will be no major impact on income as project will pay
compensation for the crops for the entire season according to the market price.
2.9 Summary of Impacts
The table beneath shows the summary impact by the project on the people and local community due
to construction of transmission towers and establishments of lines. The details of summery impact have
been illustrated previously by sector.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 13 PGCB.
3 SOCIOECONOMIC INFORMATION AND PROFILE
3.1 Introduction
32. The socio-economic profile of the affected HHs is presented following demographic profile of
the HHs. A total of 71 HHs comprising 333 people will be affected by the project with average HH size
4.7 which is higher than the national average (4.3) according to BBS (2011). Below Table 3-1 shows
the general profile of the affected people.
Table 3-1 General Profile of Affected Population
Number of total affected households 71
Number of total populations 333
Average HH size 4.7
Source: EQMS census and IOL survey, February 2022
3.2 Demographic Profile of Affected HHs
33. Demographic profile of the affected community has been analyzed as part of socioeconomic
profile of the project area. This comprises of gender profile and age-sex distribution of the PAPs. All
surveyed HH’s are found male headed HHs against 88% male headed HHs in national level (BBS,
2011)2. However, the general scenario in Bangladesh is similar as most of the HHs are headed by
male.
3.3 Sex Profile of Affected Populations
34. Sex profile of the affected HHs is shown in Figure 3-1. From the sex profile, we can find out
that the percentage of male populations is higher than the females in the project area. The overall male
female ratio of the project area is 100:112.98 (the national ratio is 100:99.68) which implies that the
project area is different from the corresponding national condition with a higher female population.
2 POPULATION AND HOUSING CENSUS 2011, Socio-Economic and Demographic Report, National Series, Volume - 4
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 14 PGCB.
Figure 3-1 Sex Profile of the affected population
Source: EQMS census and IOL survey, February 2022
3.4 Marital Status
35. Marital status of the people from surveyed households are distributed by married, unmarried
and widow as the survey did not find any separated person during the survey. Among 333 people a
total 195 people were found married, 122 people unmarried and 16 widow. Figure 3-2 shows the
distribution of marital status among surveyed people from the affected households.
Figure 3-2 Marital Status of the PAPs
Source: EQMS census and IOL survey, February 2022
58.6
3.2
Male Female
Married 58%
Unmarried37%
Widow5%
Marital Status
Married Unmarried Widow
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 15 PGCB.
3.5 Age and Sex Distribution of Affected Population
36. Figure 3-3 to the below presents age distribution of the affected HHs. The survey findings
indicate that population percentage increases respectively from the age group of 18-30 years.
According to the age group distribution, the most prominent one is 18-45 years, which comprises of 172
of the total population. The numbers of affected persons steadily decrease at age limit 60+ years. The
steady decline in the number of populations after this age limit can be considered significant for low life
expectancy in the region. It is almost like the national scenario.
Figure 3-3 Age- Distribution of PAPs in the project area
Source: EQMS census and IOL survey, February 2022
3.6 Level of Education of PAPs
37. Education level of the affected population is presented in the below Table 3-2. The table
demonstrates that primary and secondary level enrolment is high in the area. It also indicates that higher
education rate is high among male population. Furthermore, illiteracy is high among male population.
HH members whose age is 5 years and above are counted in this analysis.
Table 3-2 Level of Education of PAPs
Education Male No % Female No % Total
Primary 49 47.6 54 52.4 103
SSC 66 70.2 28 29.8 94
HSC 23 79.3 6 20.7 29
Graduate 16 66.7 11 33.3 27
Postgraduate 3 59.3 4 40.7 7
Religious 2 42.9 1 57.1 3
18
55
94
78
52
36
0
10
20
30
40
50
60
70
80
90
100
1 to 5 6 to 17 18 to 30 31 to 45 46 to 60 60+
Population by age group
Population
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 16 PGCB.
Children 9 42.9 2 57.1 1
Uneducated 21 42.9 28 57.1 49
Total 189 56.8 144 43.2 333
Source: EQMS census and IOL survey, February 2022
3.7 Primary Occupation of PAHs
38. According to the census of the affected households 19.8% HHs primary occupation is
agriculture. There will not be any impact on their income as compensation will be paid for the entire
season and after one season; affected HHs will be able to use land as usual. Based on the income
level, their socio-economic condition is better than rest of the population in that region. In addition to
Agriculture, the other significant occupations are business, remittance, service, etc. Below Table 3-3
Occupation of PAH shows the details about the occupation of the PAH.
Table 3-3 Occupation of PAH
Employment Number Percentage
Agriculture 66 19.8
Business 14 4.2
Service 1 0.3
Driver 5 1.5
Mason 18 5.4
Remittance 15 4.5
Student 78 23.4
Elderly 18 26.1
Unemployed 31 5.4
Housewife 87 9.3
Total 333 100.00
Source: EQMS census and IOL survey, February 2022
3.8 Religion of PAHs
39. The religious background of the affected HHs is entire population from survey were found as
Muslim. No Hindu or other religious groups were found during the survey of affected household.
Therefore, there is no opportunity for religious discrimination among the people through this project.
3.9 Income of Affected HH
40. Income range as per the employment status from survey data conducted by EQMS is presented
in the Figure 3-4, where it is seen that majority of the people found with zero income and most of the
people belongs to 0-10 thousand income range and 11-20 thousand income range.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 17 PGCB.
Figure 3-4 Monthly Income of the AHHs
Source: EQMS census and IOL survey, February 2022
3.10 Energy Use of PAHs
41. Electricity is the main source of lighting for 100% grid connected households. Survey found that
100% households are under electricity coverage, no other source of lighting rather than the rural
electricity were found during the survey.
42. Households in the project affected areas experience frequent load shedding which deprives
them regular supply of electricity throughout the day. Daily power shedding is extensive and continues
for several hours both daytime and night. Load shedding adversely affect the farmers in irrigating their
cultivation fields and providing a regular supply of water, children’s studies at nighttime, and women in watching television programs during their leisure time. Sleep at night after a day’s hard work is difficult as they cannot operate fans particularly during warm seasons. Despite irregular and limited power
supply, households lament over having to pay high electricity bills.
3.11 Fuel Source of PAHs
43. Firewood is the main source of energy used by most of the households (41%) for cooking and
boiling purposes followed by 8.6% using liquefied petroleum gas, particularly by people living closer to
urban areas. Kerosene is used by 11.0% which is very harmful for the health and environment caused
by indoor pollutants. Below Figure 3-5 shows the fuel source of PAHs.
37 36
4 8 1
247
0
50
100
150
200
250
300
0-10 k 11-20 k 21- 30 k 31- 50 k 50 k- 5 lakhs No income
Income range and frquency
Frequnecy
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 18 PGCB.
Figure 3-5 Fuel Source of PAHs
Source: EQMS census and IOL survey, February 2022
3.12 Water Source of AHs
44. Survey data shows that, most of the household consumes drinking water from tube well, supply
and deep tube well is negligible in number. Number of the households that consumes drinking water
from the sources are presented in the Figure 3-6. However, river water used in domestic animals
bathing and for the irrigation.
Figure 3-6 Source of drinking water by household number
Source: EQMS census and IOL survey, February 2022
25
41
5
Fuel source
LPG Firewood Supply Gas
68
2 1
Source of drnking water
Tube-well Supply water Deep tube-well
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 19 PGCB.
3.13 Sanitation Facilities of Ahs
45. About 15% and 38% of households use water sealed and non-water-sealed sanitary latrine
facility, respectively, whereas about 18% households use non-sanitary facilities. The following Figure
3-7 shows sanitation facility of the project area.
Figure 3-7 Sanitation Facilities of AHs
Source: EQMS census and IOL survey, February 2022
3.14 Health and Services
46. No major chronic illnesses are reported from the subproject affected areas. However, incidence
of water borne diseases and skin ailments were frequently reported during consultations. People
approach multiple institutions for medical care and treatment. Despite the presence of several health
and medical service institutions, access to them from rural areas is rather remote. Distance from the
households to such institutions varies from 2 km to 10 km across the project affected areas. Medical
services at private clinics are expensive and unaffordable to many families. Government hospitals in
local areas lack enough medicine, diagnostic facilities, and staff. Patients must wait in long queues. For
serious illnesses, people must go to Dhaka for treatment. People sometimes travel more than 100 km
to get their medical tests done.
3.15 Role of Women and Gender Issues
47. Women in the project affected areas are engaged in multiple activities. Apart from their
household roles such as household cooking, cleaning, fetching water, feeding children, helping in
children’s studies, and looking after the in-laws (particularly those living in extended families), women
across the project areas also make a significant contribution to the household economy.
48. Despite strong pressures from the families to dissuade women finding employment, they take
a lead role in livestock farming and take care of the feeding of their cattle, goats, and poultry. Home
gardening is another important economic activity of women, produce of which is used for both
15
38
18
Saniotation Status
Sanitary water seal Sanitary non water seal Non sanitarry
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 20 PGCB.
household consumption and marketing. Other forms of economic activities conducted by women
include agricultural labor work, dressmaking, handicraft-making, employment in apparel industries etc.
Educated women are employed in both government and private sector jobs. Women’s earnings are mainly used for children’s education and clothing, to supplement the households’ consumption needs, and to repay the past debts. Some women would also save some money to be used in emergencies or
for their children’s future. In some communities, however, it has been reported that women must hand
over their earnings to husbands or else get prior consent of the husband to spend their earnings.
Women also participate in the activities of NGOs like BRAC and Grameen Bank to access micro-credit
which they would use to buy cattle, goats, and poultry.
49. Household level decision-making is largely vested with the husband. A few instances of joint
decision making by both men and women were reported. Women also perform a significant role in
managing household assets despite the key immovable assets like land and house are owned by men.
Physical assets such as land and jewelry received by women as part of their dowry remain in her
possession but on some occasions, they are transferred to the ownership of men as part of matrimonial
agreements. Women are discouraged from participating in social and political activities mostly by their
male counterparts. However, many women struggle to change this situation.
3.16 Indigenous Peoples
50. There are no indigenous people’s settlements in the affected area of the project. Therefore, no
permanent or temporary and direct or indirect impacts on indigenous people’s communities are anticipated. The project has taken necessary steps to avoid the indigenous people’s communities and their properties and other social and cultural activities from the areas identified for project
implementation.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 21 PGCB.
4 INFORMATION DISCLOUSER, CONSULTATION, AND PARTICIPATION
4.1 Consultation
51. Consultations were carried out with groups of men and women and their community-based
organizations and members of the local government authorities (union parishad) in the project affected
areas for the purpose of disclosing information about the proposed project and its various
subcomponents and eliciting their views and concerns. The persons to be affected by land acquisitions
were also consulted during project preparation. In addition to community level consultations, interviews
were also conducted with local level politicians and administrators including the district level officers
responsible for land acquisitions. The feedback received from consultations will be used by the project
executing agency to carryout necessary revisions to the technical designs to minimize the resettlement
impacts. Furthermore, consultation outcomes were also helpful in identifying the key issues and
concerns of the local communities on the potential impacts of the project on their economic and social
assets, specifically on land and livelihoods, assessing the level of compensation anticipated by the
affected persons, and establishing appropriate safeguards measures such as grievance redress
procedures and the preparation of the entitlement matrix in the resettlement plan. Consultations with
women also led to identifying the special safeguard measures that need to be adopted to secure the
rights of women and children during project construction and operation.
4.1.1 Participation through Focus Group Discussion
52. People were participated in discussion through several focus group during the site visits and
socioeconomic survey at Gopalganj-Shibchar sub-project area in the month of February 2022 as part
of the preparation of resettlement plan. Participants in the FGDs includes the affected land owners,
womens, dependents such as tenants and sharecroppers, local youth and elits, vulnerable groups, and
members of local government authorities (union paishad) and civil society organization. People from
different occupation and age group were participated in that group discussion to express their opinion
about the project. Information of the project dessiminated among the participants to obtain their views
and opinions. Women were consulted separately during the consultation and group discussion. The
FGDs were conducted in local languages.
53. Table 4-1 shown the the FGD’s locations and the number of participants..
Table 4-1 Locations and the Number of Participants at Public and Women’s Consultation
Date Area Participant details No of FGD
No of particpants Male Female
15/02/2022 Muksodpur
Land owners, Sahrecropers,
Local Elders, Community
infuletial,
1 0 6
18/02/2022 Bhanga Ward Member, Land owners,
Elders, Businessman 1 0 7
19/02/2022 Rajoir
Ward member, Land owners,
Businessman, School
teacher, Imam
1 1 15
23/02/2022 Shibchar Local leader, Elders, Land
owners, Businessman 1 1 14
Total 4 3 42
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 22 PGCB.
54. Discussion and response against each issue were noted during the FGD and reviewed carefully
whether any points missing. The purpose of the FGD’s is to let the participants express their opinion through participation. The key issues raised and discussed during consultations are mainly evolved
around perceived and potential impacts of the project, and issues related to land procurementand
compensation, grievance redress, project benefits, and safety related issues. Key issues were
discussed in the FGDs is summarized in below Error! Reference source not found.
Table 4-2 Summary of Issue discussed and response from FGD
Issue Discussed Response
Knowledge about projet
• Most of the participants have primary
knowledge about the project.
• Some says they don’t have clear concept
about it and they just come the light
through the groups discussion.
Any foreseen risk due to project
• Some says, if compensation for damage
property is not assessed properly it might
create displeased among owners.
• Work may delayed due to community
anger and unresolved payment for
damage.
How community people shows their views about
the project
• People mostly welcome and accept the
project for greter wellbeing.
• Some says, community engagement
should priorize before any kind of
construction started.
• More engagement with community will
help the project run smoothly.
Key challenges for implementing authority
• Proposde tower might decrease the
value of that particular land, and people
are showing their concern regarding this
issue.
• Some people might create obstacle for
construction due to land price issue if
they are not addreesd the issue properly.
• Determining crops compensation should
be fair and equal for every land owners.
Key concern from the land owners
• Most of the land owners claim for the
price of their land which will be
permanently blocked by the tower area
and the declined value of that land needs
to consider by the authority.
• People from vulnerable or single plot
holder raised concern about being
affected by the project and seeking
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 23 PGCB.
proper compensation for the land or any
better alnernative solutions for their loss.
• Affected trees are need to compensatate
based on marker price.
• Compensation must paid in a timely
manner with prior to the proper pricing to
that damaged crops.
• Land that are used for service area must
clear and kept as it was before. No rock,
sands or any material shouldn’t left on
the land.
Outcome of the project
• Every single participants agreed that, the
project will benefit the country’s power sector with more power supply.
• People of their community and nearby
areas will be benfitted due this project
once they started receiving electric
supply.
• Economically people will get benefited
from that project once they have
received power supply their business
and irrigation system will flowrish.
• Women will contribute more effectively
on their household activity and other
economic cycle they are already
engaged with.
• Power supply also will help the students
to be more attentive with their study.
Suggestions and Recommendations
• Participants suggested to active
participation form the community in the
project and implementing authoirity.
• During construction and tower erraction
people specilly the land owner needs to
informed and present there.
• Proper compensation for damaged crops
and trees are requested to paid timely.
• Consider the price of land that are going
to be fenced thorough the tower
permanently.
• Those who have only one piece of land
that are going to be affected needs to
pay special attention to that landowner.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 24 PGCB.
• Construction team must clear all kind of
material from the land once they finish
their work.
• Notify the land owner before start
working on his land.
• Assess labor from locality if possible
while doing civil work and other non-
techinical work.
• Facilitate any grivence to its redressal
and easy access to raise grievance.
• Any public utility should not blocked by
the project during construction or any
other phase of work.
4.2 Outcome of the FGDs discussion
55. Communities anticipated that the project would contribute to overcome one of their critical
power related issues, namely load shedding and that communities will also have stable power supply
particularly during dry seasons. Communities who are frequently affected by load shedding almost daily
are adversely affected by their inability to provide a stable supply of water for their crops as they cannot
operate their water pumps. Farmer communities expected to use electricity for irrigation purposes so
that they would be able to avoid crop losses, increase productivity and generate higher incomes.
Children are unable to engage in their studies at night due to lack of electricity. Women aspired better
lighting for their households and particularly to spend their leisure time in watching television programs.
56. Communities did express concerns over the potential loss of their land, trees and crops and
the adverse consequences that such losses can have on their livelihoods and incomes. They
emphasized that the project follows adequate measures to avoid/minimize any adverse impacts on their
private properties, residential dwellings, public infrastructure, livelihoods, and personal security. If
subprojects caused any adverse impacts on individual properties, valuable tree species and
cultivations, people requested that such losses irrespective of whether they are permanent or temporary
should be compensated adequately and timely. Consultations also highlighted that compensation for
any of their losses should be paid over and above the current market rates (3-5 times) to enable them
to buy alternate land, find alternate livelihoods or to invest in other productive activities to avoid their
impoverishment. Compensation for land devaluation causing from the installation of transmission
towers and lines traversing their private properties was another concern of the participants at the
consultations.
4.3 Information Disclosure
57. During the due diligence conducted for the project, information related to preliminary
engineering designs and line routes of the project, land requirements and acquisition procedures,
potential impacts of the project, both positive and negative and direct and indirect, entitlement policies
and frameworks for compensation for the affected parties and grievance redress procedures were
shared with affected persons during consultations. The PMU and its Environmental and Social Unit
(ESU) of the executing agency will continue their communications with the affected persons and other
stakeholders and disclose information such as the dates of final surveys and census of affected
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 25 PGCB.
households, valuation procedures, project related impacts, specific entitlements of the affected persons,
compensation procedures, grievance redress procedures and dates of the commencement of civil
works.Brochures and posters containing relevant information will be printed in Bengali and they will be
made available/displayed at places easily accessible to affected persons and other interested parties..
4.4 Continued Consultation and Participation
58. The PMU of the executing agency directs their project directors, engineers, and ESU to engage
in continuous consultations with the affected persons to minimize/avoid adverse impacts of the project
emanating from final engineering designs. For continued consultations, the following steps are
envisaged from the ESU:
• Organize and conduct periodic meetings with affected persons and other stakeholders e.g.,
members of union parishad, upazila nirbhai officers etc. to inform them the status of final
engineering designs, land acquisition process and entitlements and payment of compensation
to affected persons.
• In coordination with, engineers engage the affected persons and other stakeholders to review
the final engineering designs, and entitlements and other benefits to affected persons.
• Liaise with the office of the Deputy Commissioner to verify the status of land acquisitions and
communicate the same information to the affected persons.
• Conduct consultations with affected persons and other stakeholders to elicit their views and
suggestions to revise and to update the resettlement plan.
• Share the final resettlement plan with the affected persons and other stakeholders.
• Hold periodic meetings with the affected persons and other stakeholders to review any
unanticipated or indirect consequences of the implementation of safeguard plans.
• Assist the affected persons to access necessary information, prepare documentation related
to land acquisitions and receive compensation and other resettlement assistance and other
project related benefits.
• Organize public meetings and appraise the communities about the progress of project
implementation and the implementation of social safeguards such as payment of
compensation and other assistance to be provided.
• A regular update of the progress of the resettlement component of the project is placed for
public display at the offices of the executing agency and its PMU.
• All monitoring reports of the resettlement components of the project are disclosed in the same
manner as that of the resettlement plan.
• Conduct information dissemination sessions at major locations and solicits the help of the
local community leaders to encourage the participation of the affected persons in resettlement
plan implementation.
• Place special attention to assist the vulnerable groups to understand the process and to help
them in getting the compensation and other assistance.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 26 PGCB.
5 GRIEVANCE REDRESS MECHANISM
59. The impacts of the project may raise grievances and complaints on the part of affected persons.
Resolution of such grievances within the legal framework of Bangladesh largely rests with the Deputy
Commissioner who is responsible for land acquisitions. Affected parties can submit their grievances
and complaints to the Deputy Commissioner for redress. The land acquisition law also provides for the
affected parties recourse to the country's judicial system in case the Deputy Commissioner has not
resolved the issue or else the parties are dissatisfied with the decision of the Deputy Commissioner.
Meanwhile, there will be several other non-land acquisition-based grievances and complaints. The
clearance of standing trees and way-leaves within the RoW of the transmission lines can adversely
affect the livelihoods and incomes of households; civil construction works can cause destructions to
standing crops; stringing of transmission lines over private properties can lead to property devaluation
and raise people's concerns over their personal safety; and construction work of the project could also
result in various inconveniences to the general public such as access difficulties, restrictions to public
places, damages to privately owned built structures and common property resources, disturbances
causing from noise and dust, and issues related to labour influx etc.
60. However, the legal framework of the country may not address all grievances effectively
Therefore, the project will establish a project-based grievance redress mechanism (GRM) which is
easily accessible to the aggrieved parties, transparent and accountable in grievance handling and
responding while winning the confidence of the complainants. A well-established and well- functioning
GRM would be able to resolve the grievances locally and avoid lengthy court procedures.
61. The project will establish a three-tier GRM, details of which are described in the sections to
follow. The GRM will function throughout the life cycle of the project implementation and PGCB will
ensure its accessibility to affected parties, and transparency and efficiency in grievance resolution.
However, it will not deal or interfere with any matters which are already placed before the country's
courts of law. The project will provide wider publicity for the GRM established using a variety of media
such as brochures and leaflets printed in Bengali, and through community level awareness raising
programs. The roles and functions of the GRM and its different tiers, specific locations where the
different tires are established, grievance reporting procedures, time frames for grievance resolution at
each level etc. will be disseminated to the affected persons as well as the public using the above-
mentioned modes of communication. Furthermore, the project will provide orientation and training to
the members of the GRM on effective grievance handling procedures. Site level grivence box will be
set to receive grievance and the box will be hung on a place where grieving person can access easily
and drop the complain without any fear or hesitation. All expenses related to the functioning and use of
the GRM will be borne by the project. PGCB will carefully record on grievances and report on the status
of open and closed grievances in semi-annual monitoring reports submitted to ADB. Records on
grievances will be made available to the external monitor and ADB supervision missions.
62. GRM - Level 1: Level 1 of the GRM will be the project officer/s appointed by PGCB to a
subproject. The person can be a sub assistant engineer, or any other engineer appointed by PGCB to
a specific site. Also, contractors on project sites can be a window for field level grievances. In case of
grievances that are urgent and minor, aggrieved parties can easily approach PGCB's field officer and/or
contractors. Contact phone numbers, mails and names of the focal persons will be posted at all
construction sites at visible locations. Considering female complainant, a contact point of a focal female
person will be posted too. Grievance box will be set in a place where grieving person can drop his/her
appeal in a peaceful mind without any hesitation or discomfort. The field officer of PGCB and focal
person of the contractors will record the name of the complainant, the date of complaint and the nature
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 27 PGCB.
of the complaint. The field officer of PGCB and/or focal person of contractors will communicate with the
complainant/s to reach an amicable settlement within a period of two weeks.
63. GRM - Level 2: Level 2 of the GRM will be the Local Grievance Redress Committee (LGRC)
chaired by one of the Executive Engineers. PGCB will establish five LGRCs, one for each Division
under the project namely, Dhaka, Barishal, Khulna, Rajshai and Rangpur. 3The rest of the members
of the GRC will include (i) the project officer/assistant engineer from concerned project area; (ii) the
focal persons from the contractors; (iii) representatives of the concerned Union; (iv) representatives of
the relevant government offices such as DC; and (v) representative of the affected households.
Grievances that cannot be resolved at GRM-Level 1 or else if the affected persons were dissatisfied
with the Level 1 resolution can submit their grievances to LGRC. The meetings of the LGRC will be held
at the local office of PGCB or the union office in the area where the complaint originated. The LGRC
can convene the affected person to explain his/her grievance at its meeting. The complainant can also
send his/her nominee to the LGRC, if he/she is unable to physically participate in the LGRC. During the
committee deliberations, LGRC will clarify the issues involved, and would try its best to reach a
settlement acceptable to both the affected person and the project within a period of two weeks. The
executive engineer can also consult his/her respective deputy project director (DPD) for advice and
guidance if necessary. If an agreement or resolution is reached, the key points of the
agreement/resolution will be summarized, documented and signed by both the affected person and the
members of the LGRC. The project officer of PGCB at site level from where the complaint was submitted
to LGRC will assist in the documentation and record keeping, summaries of which will also be reported
to ADB through monitoring reports.
64. GRM - Level 3: Level 3 of the GRM will be the Project Management Unit of PGCB. The GRC
at the PMU will be charged by Project Director (PD) and comprise (i) external monitor for resettlement;
(ii) safeguards specialist(s) under PMU/ESU; (iii) relevant technicians and engineers from PGCB and
contractors; and (iv) representatives of the relevant government offices. The complainant and/or
representative will be called to appear before the Level 3 GRC and explain his/her grievance. An officer
from ESU/PMU will coordinate with the complainant. The complainant can send his/her nominee to the
GRC, and in the event of both being unable to physically participate in the GRC, the ESU officer will
explain the grievances on behalf of the complainant. If necessary, GRC members will undertake field
inspections to verify the issues reported. Level 3 GRC will reach a settlement through consensus among
its membership, failing which the decision may be taken on a majority vote. The GRC located at PMU
will conclude its proceedings within a period of one month since the submission of the grievance. Any
significant grievances which an implication on life of a person may have should be resolved
immediately. Also, in the case of critical issues to be resolved, PD can also consult the managing
director of PGCB for advice and guidance. The ESU officer will assist in the documentation and record
keeping, and summary outcomes will be reported to ADB through monitoring reports. Also, the external
monitor will take a role as a liaison between the GRC and ADB.
65. Apart from the above described three levels of GRM, contractors will also establish a GRM at
site level which will exclusively address the issues and grievances of the labor teams. It has been
observed that, during the site visit every construction site has grivence box in a accessible place for all
to drop or file their complain in a comfortable way. However, whenever necessary, the aggrieved
laborers also have the choice of approaching the project based GRM.
66. The GRM does not impede access to the legal system. Affected persons can resort to legal
action through the country's judiciary system at any time. They can also submit their grievances to
3 Since there will be only 4 executive engineers, one of them will be assigned to oversee 2 Divisions.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 28 PGCB.
ADB's Accountability Mechanism, which has both a problem-solving function to respond to concerns of
project affected people and a compliance review function where there is discrepancy with
implementation of ADBs operational policies.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 29 PGCB.
6 POLICY AND LEGAL FREMAWORK
6.1 Introduction
67. The government does not have a national policy on involuntary resettlement. The law of
eminent domain is applied for the acquisition of land for infrastructure projects of public interest. The
legal and policy framework for land acquisition and involuntary resettlement for the project will be based
on: (i) the recently enacted Acquisition and Requisition of Immovable Property Act (ARIPA) 2017 (ii) the
Electricity Act of 2018; (iii) the Bangladesh Telegraph Act of 1885 and (vi) ADB's Safeguards Policy
Statement (SPS), 2009, which applies to all ADB financed and/or administered projects, regardless of
the country of where the project is located or the financing modality (i.e. loan, a grant, or other means).
6.2 Legal Framework for Land Acquisition in Bangladesh
68. The principal legal instrument governing land acquisition in Bangladesh was the Acquisition
and Requisition of Immovable Property Ordinance (ARIPO) 1982. This ordinance was repealed by the
newly passed act under the name of Acquisition and Requisition of Immovable Property Act of 2017.
Land acquisitions for the 15 new substations and any land required for bay extensions for existing
substations will be carried out in accordance with the provisions in the ARIPA 2017. The ARIPA 2017
requires that compensation be paid for (i) land and assets permanently acquired (including standing
crops, trees, houses); and (ii) any other damages caused by such acquisition. The Act also provides
for the acquisition of properties belonging to religious organizations like mosques, temples, pagodas,
and graveyards if they are acquired for public interest, provisions for which were excluded from the
former ARIPO. However, the project for which the land is acquired is bound to provide similar types of
assets in some other appropriate place. The Act stipulates certain safeguards for the landowners and
provides for payment of "fair value" for the properties acquired.
69. The Ministry of Land (MOL) has overall responsibility to enforce land acquisition. The MOL
delegates some of its authority to the Commissioner at the Divisional level and to the Deputy
Commissioner at the District level. The Deputy Commissioners are empowered by the MOL to process
land acquisition and pay compensation to the legal owners of the acquired property. The burden to
establish his/her legal rights to the acquired property to be eligible for compensation under the law is
on the landowner. The Deputy Commissioner is empowered to acquire a maximum of 50 standard bigha
(16.50 acres) of land without any litigation for which he would obtain the approval of the Divisional
Commissioner. Acquisition of land exceeding 16.50 acres must be approved from the central land
allocation committee (CLAC) headed by the prime minister of the Government of Bangladesh. In the
case of acquiring Khas land (government owned land), the land will be transferred through an inter-
ministerial meeting following an acquisition proposal submitted to DC or MOL.
70. Under the ARIPA 2017, The Deputy Commissioner determines the value of the acquired assets
as at the date of issuing the notice of acquisition under section 4(1) of the Act. The premium for land is
200%, thus 3 times of the mouza value for the affected land is provided as compensation. In addition,
if there are other asset and income/livelihood losses caused by the land acquisition, 2 times of the
market rate for these items is provided as compensation, as premium for these items is 100%. The
compensation such determined is called the Cash Compensation under Law (CCL). If the land acquired
has standing crops cultivated by a tenant (Bargadar) under a legally constituted written agreement, the
law requires that compensation money be paid in cash to the tenants as per the agreement. Households
and assets moved from land already acquired in the past for project purposes, and/or government has
land are not included in the acquisition proposal, and therefore, excluded for considerations for
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 30 PGCB.
compensation under the law. Lands acquired for a public purpose cannot be used for any other purpose.
The new Act under section 4 (2) also facilitates the private organizations to request from the government
to acquire the land for their development activities. Furthermore, the new Act under its section 15
provides for the acquisition of entire houses/buildings if their owners request to acquire the entire house
or building against partial acquisition.
71. The government is obliged to pay compensation for the assets acquired. The previous
Ordinance of 1982 did not address social and economic impacts resulting from land acquisition such
as compensation and other assistance for non-titleholder project-displaced persons such as informal
settlers (squatters), occupiers, and informal tenants and leaseholders without registration document.
Furthermore, the Ordinance did not provide for compensation for loss of livelihoods and incomes. The
new Act of 2017 has incorporated certain provisions to address the above gaps, and therefore, it
reduces the gaps between the national legislative framework of the government and ADB's policies.
Below Error! Reference source not found. shows the details about land acquisition process under
ARIPA, 2017.
6.3 Valuation of Assets and Property Compensation
72. The ARIPA provides for the payment of compensation for land and other assets permanently
acquired, including standing crops, trees, and houses and any other damages caused by such
acquisition. The Deputy Commissioner determines the market value of acquired assets as per its value
on the date of issue of the notice of acquisition (Section 4 (1) Notice under ARIPA), based on the
registered value of similar property bought and/or sold in the area over the preceding 12 months. The
market value of the property determined by the Deputy Commissioner is reinforced by 200% due to
compulsory nature of acquisition. The law specifies methods for calculation of market value of property
based on recorded prices obtained from relevant Government departments such as Registrar (for land),
Public Works Department (for structures), Department of Forests (for trees), Department of Agriculture
(for crops) and Department of Fisheries (for fish stock). The following factors will be considered by the
Deputy Commissioner in determining the market value of the property to be acquired.
i. The market value of the land permanently lost for four tower footings combined calculated using
mouza rate of each mouza of tower location.
ii. Damages caused to any standing crops or trees on the property because of acquisition.
iii. Any severance of the property from other property held by the interested parties.
iv. Any injurious affection on other properties, movable or immovable, in any other manner, or the
earnings of the interested parties
v. Any possibilities that compel the person interested in the property (to be acquired) to change
his residence or place of business, the reasonable expenses, if any, incidental to such change;
and
vi. Any damages that may result from diminution of the profits of the property between the date of
serving the notice under section 7 (ARIPA) and the date of taking possession of the property
by the Deputy Commissioner.
6.4 The Electricity Act, 2018
73. The Electricity Act enacted on 12th February 2018 repealed the former Electricity Act of 1910
with amendments to develop and reform the sectors of power generation, transmission, supply, and
distribution and for better service delivery to consumers and to meet the increasing demand for
electricity. The Act specifies the role of licensees in the supply of energy and construction of lines for
energy transmission. The key features of the Act are given below in Table 6-1.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 31 PGCB.
Table 6-1 Key Features of the Electricity Act, 2018
Chapter Issues Provisions in the Electricity Act,
2018
Chapter 3, section 6 Civil works If any licensee is permitted to
lay power supply lines within the
area of supply or, subject to the
terms of his license, beyond the
area of supply, the licensee
may, as soon as may be, do
necessary civil works, with
intimation to the concerned
person or the local authority for
supplying electricity to that
area. Licensee must take
consent from all affected
parties. However, if any power
supply line or civil works creates
any obstacle to proper
execution of legitimate authority
of any person, the licensee may
shift the site for power supply
line or civil works.
Chapter 3, section 9 Damages lf any road, railway,
underground drain, sewer, or
tunnel is damaged in
consequence of civil works, the
part excavated shall have to be
filled up by soil, the part
damaged shall have to be
repaired and the garbage shall
have to be removed
immediately after such works.
Chapter 3, section 12 Compensation If any damage, harm, or
inconvenience is caused while
doing civil works under this Act,
the licensee shall, in such
manner as may be prescribed
by rules, pay compensation to
the person affected or the
owner of the land affected for
acquiring land for construction
of electricity towers.
Chapter 3, section 13 Right of Way For the purpose of laying power
supply lines or doing civil works
under this Act, the licensee
shall reserve the right of way
over the land and the space
above or underground there of:
Provided that the licensee shall
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 32 PGCB.
inform the landowner in writing
before laying of power supply
lines and doing civil works
within a reasonable time.
Chapter 3, section 14 Acquisition of land If acquisition of land is required
for establishment of power
generation plant or sub-station,
it shall be deemed to have been
necessary for public interest
and the existing laws and
regulations on acquisition of
land shall have to be followed. If
any private company holding
license requires any land for
constructing any connection
line with power station, sub-
station, or grid substation the
licensee may purchase or
acquire such land from the
concerned landowner in
accordance with the existing
laws and regulations regarding
land acquisition.
Chapter 5, section 29 Accidents and investigation lf any accident occurs, or any
risk arises due to power
generation, transmission,
supply or distribution or due to
power supply line or any other
work, the person affected or the
person having knowledge of it,
as the case may be, may give
notice in writing to the Authority
of such incidence or damage.
6.5 ADB’s Safeguard Policy Statement (SPS) 2009
74. The Safeguard Policy Statement (SPS) of ADB (2009) includes safeguard requirements for
environment, involuntary resettlement, and indigenous people. The objectives of the Involuntary
Resettlement Safeguard policy are to avoid involuntary resettlement wherever possible; to minimize
involuntary resettlement by exploring project and design alternatives; to enhance, or at least restore,
the livelihoods of all displaced persons in real terms relative to pre- project levels; and to improve the
standards of living of the displaced poor and other vulnerable groups. The involuntary resettlement
safeguards cover physical displacement (relocation, loss of residential land, or loss of shelter) and
economic displacement (loss of land, assets, access to assets, income sources, or means of
livelihoods) because of (i) involuntary acquisition of land; or (ii) involuntary restrictions on land use or
on access to legally designated parks and protected areas. It covers them whether such losses and
involuntary restrictions are full or partial, permanent, or temporary. The three important elements of
ADB's SPS (2009) are: (i) compensation at replacement cost for lost assets, livelihoods, and incomes
prior to displacement; (ii) assistance for relocation, including provision of relocation sites with
appropriate facilities and services; and (iii) assistance for rehabilitation to achieve at least the same
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 33 PGCB.
level of well-being that affected persons had prior to the project. The SPS gives special attention to poor
and vulnerable households to ensure their improved well-being because of project interventions.
75. The ARIPA of 2017 provides for the payment of compensation, 3 times of the mouza value for
land and 2 times of the market value for other assets and income/livelihood loses, but there can be a
gap between this compensation amount and replacement cost required by ADB. If there is a gap
between the compensation amount by ARIPA and the replacement value by ADB's SPS then it will be
filled by the project as provided for in the entitlement matrix of the resettlement plan.
76. ADB's involuntary resettlement requirements emphasize that displaced persons without titles
to land or any recognizable legal rights to land are eligible for resettlement assistance and
compensation for loss of non-land assets. However, ARIPA recognizes only the entitlements of legal
titleholders who can establish their ownership rights. The Act does not address losses of the project-
affected persons who do not have titles or ownership records to their properties such as informal
settlers, squatters, and occupiers, nor the informal tenants and leaseholders who are unable to produce
any documentary evidence in support of their properties. Neither the Act provides for any resettlement
assistance or transitional allowances for restoration of livelihoods of non-titled affected persons. The
only exception is for bargadar (registered sharecroppers/tenants) who have cultivated standing crops
under a legally constituted written agreement. These sharecroppers/tenants are entitled to a part of the
compensation money as provided for in the written agreement. Therefore, any payment of
compensation for project affected non-titleholders will be in accordance with the provisions in the
entitlement matrix of the resettlement plan, the cost of which will be entirely borne by the project
executing agency.
77. ADB's involuntary resettlement policy recognizes the need for resettlement of physically and
economically displaced persons providing them with needed assistance including secured tenure to
relocation land, better housing at resettlement sites with comparable access to employment and
production opportunities, transitional support and development assistance, such as land development,
credit facilities, training, or employment opportunities and civic infrastructure and community services,
as required. The regulatory framework in Bangladesh does not provide for such resettlement and
rehabilitation assistance for displaced persons. It only provides for cash compensation for properties
acquired. This gap between the safeguards requirements of ADB and the national regulatory framework
will be bridged through a series of project specific measures built into the resettlement plan such as
provisions to pay compensation for non-titleholders who as per the SPS are entitled to compensation
at replacement cost for assets other than land affected by the project; and extend special assistance to
restore and improve the livelihoods of the affected persons including the vulnerable groups such as
elderly and women headed households.
78. ADB's policy recommends adequate and appropriate replacement land or cash compensation
at full replacement cost for lost land. Neither the Telegraph Act of 1885 nor the Electricity Act of 2018
have any provisions to pay compensation for the land used for the erection of tower foundations of the
transmission lines. The Telegraph Act provides for compensation for the trees fell, if those trees were
in existence before the telegraph line was erected. The Electricity Act recognizes full compensation for
damage, detriment or inconvenience caused by the project. In the circumstances, the project ensures
cash compensation for the land lost for the foundation areas of the transmission towers as well as
permission for the landowners to cultivate the land under the transmission towers after they are erected.
However, erecting any structures or planting any tall trees under the towers will be disallowed.
79. Carrying out meaningful consultations with affected persons, host communities, and concerned
nongovernment organizations and establishing a grievance redress mechanism that would receive and
facilitate resolution of the concerns of the affected persons are key policy requirements of ADB. The
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 34 PGCB.
ARIPA does not make any provisions for consultations or a project- based grievance redress
mechanism. The law provides only limited space for the affected persons to raise objections to land
acquisition (after section 5 Notice under ARIPA is issued) while disputes over land acquisition must be
settled through an arbitrator or the courts of law. Therefore, the vacuum for consultations and grievance
redress procedures observed in the regulatory framework will be addressed through the resettlement
plan. Following Table 6-2 discusses about the Compliance Review of the Legal Framework of
Bangladesh and the Safeguard Principles of the ADB Safeguard Policy Statement of 2009.
Table 6-2 A Compliance Review of the Legal Framework of Bangladesh and the Safeguard
Principles of the ADB Safeguard Policy Statement of 2009
Sl. No. ADB Safeguard Policy
Principles (2009)
Legal Framework of
Bangladesh (ARIPA 2017)
Degree of Compliance or
Gaps and Proposed Action
to Address Gaps
1
Screen the project early on
to identify past, present, and
future involuntary
resettlement impacts and
risks.
Deputy Commissioner
conducts a joint verification
with PGCB and categorizes
land by types and any
assets thereon and
identifies owners of physical
assets prior to issue of
section 4(1) notice.
Partially complied. PGCB &
consultants will conduct an
independent assessment &
prepare an Inventory of
Losses and identify
resettlement issues.
2
Carry out meaningful
consultations with affected
persons, host communities,
and concerned
nongovernment
Organizations.
Affected persons are
allowed to raise objections
under section 4(7) of ARIPA,
if they disagree with joint
verification assessment,
and under section 5(1)
against land acquisition.
Deputy Commissioner
hears the complaints and
grievances under section
4(9) of ARIPA.
Partially complied. PGCB
will initiate a comprehensive
process of consultation with
affected persons and others
during resettlement plan
preparation and
implementation, to inform
them of their entitlements
and resettlement options, to
ensure their participation in
resettlement planning and to
address the needs of
vulnerable groups.
3
Establish a grievance
redress mechanism to
receive and facilitate
resolution of the affected
persons' concerns.
Affected persons are
allowed to raise objections
under section 4(7) if they
disagree with joint
verification assessment and
under section 5(1) against
land acquisition. Deputy
Commissioner hears the
complaints and grievances
under section 4(9).
Partially complied. PGCB
will establish a project
based GRM through
resettlement plan to
address grievances.
4
Provide cash compensation
at replacement cost.
For land, 200% premium is
given in addition to the
original mouza value.
Partially complied. PGCB
will appoint a Property
Assessment and Valuation
Committee (PAVC) to
recommend replacement
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 35 PGCB.
cost and pay additional
compensation directly to the
affected persons, if they are
entitled through the
entitlement matrix and if the
CCL paid by Deputy
Commissioner is lower than
the replacement cost or if
not covered by CCL. PAVC
will also recommend
additional resettlement and
rehabilitation assistance to
relevant affected persons.
5
Improve or at least restore
the livelihoods of all
displaced persons.
For the other asset and
income/livelihood loses,
100% premium is given in
addition to the market value
of the items.
Partially complied. PGCB
through the Entitlement
Matrix of the resettlement
plan will provide additional
compensation for loss of
trees and crops, transitional
allowances, shifting costs,
reconstruction assistance,
livelihood training, access to
credit & grants, employment
during project
6.6 Involuntary Resettlement Safeguard Principles Applicable to
Project
80. Based on the national regulatory framework and the safeguards policy of ADB, the project
implementation will be guided by the following safeguards principles.
• Adverse impacts arising from project design, planning and implementation including involuntary
resettlement would be avoided, minimized and mitigated by exploring design alternatives.
• Project related information including entitlements to affected persons will be disclosed in a
timely manner and will be made available in places easily accessible to them and in local
languages.
• Consultations will be carried out with the affected persons and their communities to elicit their
views and suggestions on project design and implementation procedures, and to ensure their
participation in project planning, implementation, and monitoring.
• Permanent and temporary loss of crops, standing trees and commercial trees due to project
constructions will be compensated at replacement cost as determined by the Property
Assessment and Valuation Committee (PAVC) to be established by the executing agency.
• Civil construction works will be scheduled for off-farming seasons to minimize adverse impacts
on crops and cultivations. If unavoidable, affected persons will be compensated at replacement
cost for their loss of production and incomes.
• Vulnerable persons/households and persons significantly affected by land acquisitions will be
provided with special assistance as per the entitlement matrix of the resettlement plan.
• All entitlements and compensation will be paid to the affected persons prior to the
commencement of the civil construction work.
• Livelihoods and incomes of all displaced persons will be restored and improved.
• Affected households will be eligible for compensation, irrespective of tenure status, social or
economic standing, and any such factors that discriminate against achievement of the
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 36 PGCB.
resettlement objectives. Lack of legal rights to lost assets, tenure, social or economic status will
not bar the affected households from entitlement to compensation and assistance.
• A grievance redress mechanism will be established at different levels from construction sites to
the executing agency level to receive and resolve any.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 37 PGCB.
7 ENTITLEMENTS, ASSISTANCE AND BENEFITS
81. The Dhaka and Western Zone Transmission Grid Expansion Project will provide cash
compensation against the lost land and other aniticipated impacts.
82.
83. The affected persons will include both legal titleholders, and non-titleholders. Among them are
landowners/claimants affected by landprocurement , and the leaseholders/tenants, and share-croppers
dependent on such land. The corridors earmarked for transmission lines will also affect several persons
such as those who would lose their land for tower foundation area at ground level of the transmission
towers, , standing trees and crops are located within those boundaries due to temporary impacts
imposed on land use. Furthermore, both land procurmentand transmission corridors can also affect
people’s livelihoods and incomes. 84. Though the legal and regulatory framework of Bangladesh does not recognize nontitle holders
and their rights to compensation, this resettlement plan advocates compensation and/or R&R
assistance to all persons affected by the project irrespective of their title to offset such losses and
enabling restoration of living conditions to a state better or equal to the pre-project situation.
85. All affected persons who are identified in the project-affected areas on the cut-off date will be
entitled to compensation for their affected assets, and rehabilitation measures. The social cutoff date
for non-title holders and affected people by transmission lines is the final date of the census of APs
conducted based on the detailed measurement survey and the final engineering design. All entitlements
will be paid to eligible households prior to physical and economic displacement commencement of civil
works.
7.1 Entitlement Matrix
86. This section presents an entitlement matrix that provides for compensation and other R&R
assistance for different losses of the affected persons depending on the type and scope of the losses,
its impact, and status of ownership to the affected assets and the social and economic vulnerability of
the affected persons. The land procured for the project as well as the land, trees, and crops that would
be affected by impacts imposed on land use during the construction of the transmission towers and
lines will be compensated. Furthermore, the landowners will be allowed to continue to use the land
falling within the RoW of the transmission lines and under the transmission towers (except for planting
of tall trees) after the completion of construction work. In addition, since there are no land acquisitions
for transmission lines, people can still retain their ownership to the land, and use it for residential and
cultivation purposes provided the vertical clearance requirement is maintained. The standard vertical
clearance between lines and structures is 6 m for 230 kV.
87. Apart from the statutory compensation/cash compensation under the law (CCL) paid for the
land acquired for the project, the executing agency (PGCB) will ensure that parties affected by land
procurement are paid compensation... All affected persons will be entitled to receive compensation for
their losses at replacement cost. The executing agency will establish independent Property Assessment
and Valuation Committees (PAVCs) in project areas to assess all losses to the affected persons and
advise on the replacement cost for all such losses. All entitlements of compensation will be paid to the
affected persons prior to their displacement and handing over the construction sites to the contractors.
88. The entitlement matrix was prepared taking into consideration the provisions in the national
regulatory framework of Bangladesh and in compliance with ADB’s SPS 2009. The good practices that Bangladesh followed in externally funded development projects that involved involuntary resettlement
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 38 PGCB.
impacts have also been incorporated into the entitlement matrix. The enititlement matrix is prepared on
the basis of impact identified during census in the course of RP updating.
89. Error! Reference source not found. summarizes the main types of losses and the
corresponding entitlements in accordance with the policies and legal framework of the government and
ADB safeguard policies.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 1 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
Land
Land used for four
tower foundation
areas at ground
level of the
transmission
towers
Agricultural, fallow
land, pond land,
and commercial
land used for
tower footing
Legal Titleholders
C
a
s
h
C
o
m
p
e
n
s
a
t
i
o
n
• Cash compensation for the
affected land (four footing area)
will be calculated at actual as per
mouza rate.
• Though, the land will not be
acquired under ARIPA-2017, but
owner will get
compensation/price for that
amount of land which was
permanently lost due to four
tower footing and the amount will
paid to him at actual as per
mouza rate.
• Compensation will be paid
before startng of construction
work.
• Prior advance notice to the
affected persons to cut down
• PGCB
• Contractors
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 2 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
standing trees and the right to
possess the timber and any
other produce.
• Landowner will gain his
ownership of the land
underneath the tower and can
cultivate.
• Compensation for the damaged
crops will be paid as per the
assessed rate of DAE.
Trees
Trees in the tower
footing area and
within the RoW of
transmission lines.
Trees within the
RoW of the
transmission lines
Legal titleholders, non-
titleholders, tenants, &
socially recognized tree
growers
C
a
s
h
c
o
m
• Cash compensation at the rate of
DOF and recommend by PAVC
based on the type, age,
productivity, and lost income
during the life cycle of the trees
including additional
• PAVC
• PGCB
• Contractors
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 3 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
p
e
n
s
a
t
i
o
n
a
t
r
e
p
l
a
c
e
m
e
compensation for fruit bearing
trees.
• Prior advance notice to the
affected persons to cut down
standing trees and the right to
possess the timber and any
other produce.
• Tree owner allow to take away
sulvagable tree free of cost and
will clear the ROW of
transmission line within one
week of receiving the
compensation.
• Linkages with relevant agencies
which can support tree planting
programs.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 4 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
n
t
c
o
s
t
a
n
d
R
&
R
a
s
s
i
s
t
a
n
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 5 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
c
e
Crops
Any crops
within the tower
foundation area
and service area
of the tower
footing
Legal titleholders, non-
titleholders,
sharecroppers, and
tenants
C
o
n
s
i
d
e
r
i
n
g
t
h
e
a
s
• Advance notice to the affected
person to harvest crops.
• PAVC
• PGCB
• Contractors
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 6 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
s
e
s
s
e
d
r
a
t
e
o
f
D
A
E
o
f
a
g
i
v
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 7 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
e
n
v
a
r
i
e
t
y
o
f
c
r
o
p
,
a
v
e
r
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 8 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
a
g
e
s
e
a
s
o
n
a
l
p
r
o
d
u
c
t
i
o
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 9 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
n
o
f
t
h
e
c
u
l
t
i
v
a
t
e
d
l
a
n
d
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 10 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
a
n
d
t
h
e
n
u
m
b
e
r
o
f
s
e
a
s
o
n
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 11 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
s
l
o
s
t
t
o
t
h
e
f
a
r
m
e
r
A
s
s
i
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 12 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
s
t
a
n
c
e
f
o
r
r
e
s
t
o
r
a
t
i
o
n
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 13 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
o
f
t
h
e
l
a
n
d
t
o
i
t
s
p
r
e
v
i
o
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 14 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
u
s
s
t
a
t
e
o
r
b
e
t
t
e
r
l
e
v
e
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 15 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
l
.
Crops within the
RoW of the
transmission lines
Legal titleholders,
non- titleholders,
sharecroppers
and tenants
C
a
s
h
c
o
m
p
e
n
s
a
t
i
o
n
• Advance notice to the affected
person to harvest crops.
• PAVC
• PGCB
• Contractors
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 16 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
r
e
c
o
m
m
e
n
d
e
d
b
y
P
A
V
C
b
a
s
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 17 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
e
d
o
n
a
s
s
e
s
s
e
d
r
a
t
e
o
f
D
A
E
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 18 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
f
o
r
g
i
v
e
n
v
a
r
i
e
t
y
o
f
c
r
o
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 19 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
p
,
a
v
e
r
a
g
e
s
e
a
s
o
n
a
l
p
r
o
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 20 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
d
u
c
t
i
o
n
o
f
t
h
e
c
u
l
t
i
v
a
t
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 21 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
e
d
l
a
n
d
a
n
d
t
h
e
n
u
m
b
e
r
o
f
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 22 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
s
e
a
s
o
n
s
l
o
s
t
t
o
t
h
e
f
a
r
m
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 23 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
e
r
.
A
s
s
i
s
t
a
n
c
e
f
o
r
r
e
s
t
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 24 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
o
r
a
t
i
o
n
o
f
t
h
e
l
a
n
d
t
o
i
t
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 25 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
s
p
r
e
v
i
o
u
s
s
t
a
t
e
o
r
b
e
t
t
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 26 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
e
r
l
e
v
e
l
.
Special assistance to vulnerable and significantly affected households
Vulnerable
allowances
Vulnerable Households R&R
a
s
s
i
s
t
• One-time grant of Tk 10,000 per
vulnerable household
• Contractors
• PGCB
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 27 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
a
n
c
e
Livelihood
restoration
allowances
Significantly affected
households
R&R
a
s
s
i
s
t
a
n
c
e
• Livelihoods restoration grant
of Tk 15,000 per household
• PGCB
• Contractors
Compensation for unforeseen impacts
Unforeseen Legal titleholders,
non- titleholders,
Ca• Properties and livelihoods as
determined by PAVC.
• PAVC
• PGCB
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 28 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
adverse impacts
on properties and
livelihoods during
project
construction
sharecroppers,
tenants, daily wage
laborers
and vulnerable
households
sh compensation at replace
• A written agreement between the
landowner and the contractor for
the temporary use of land for
construction related activities.
• Full restoration of the land
temporarily used for construction
related activities to its original
condition before returning to their
respective owners.
• Contractors
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 29 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
ment cost
Unforeseen other
impacts Affected persons
Will be assessed a
• Will resolve upon discussion and
proper obersavation.
• Maintain coordination with the
respected person to avoid further
any impact.
• PGCB
• Contractors
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 30 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
nd determined based on safe
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 31 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
guards principles and inco
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 32 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
rporated into the entitlem
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 33 PGCB.
Type of Loss
Affected
Persons/Institution
s
E
n
t
i
t
l
e
m
e
n
t
s
Details Responsibilities
ent matrix
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 34 PGCB.
8 INCOME RESTORATION
90. The project will not cause permanent physical displacements and relocation of affected
people. Landowners will receive compensation from the project for the acquired land at replacement
cost together with additional compensation for affected standing trees, crops, and fish stocks.
Meanwhile, leaseholders and sharecroppers will receive cash compensation for the loss of their
crops and incomes. Livelihood restoration grants will be provided to the significantly affected
households to help them restoring their livelihoods and incomes. Additional cash grants will also be
provided to vulnerable households to cope with their income losses during a transitional period and
until their livelihoods are reestablished. The project encourages the landowners to invest their
compensation money diligently, and for productive purposes such as buying alternate land for
cultivations or initiating alternate livelihoods so that they would not be impoverished by the loss of
their land or face food insecurities in their households. Project will also extend assistance to
leaseholders and sharecroppers to find alternate land for cultivations. The construction work of the
transmission lines will temporarily affect the crops cultivated within the clearing RoW as well as trees
grown therein. It is estimated that 71 households would be affected. Project will pay compensation
for the affected crops for the duration of the construction period and the trees that are to be removed
from the RoW. Project will encourage APs to use part of their compensation for re-planting the trees
and will facilitate linkages with support agencies that can assist the APs in replanting programs.
Project will also reach agreements with construction contractors to offer employment in construction
work, specifically for households affected by the project.
Table 8-1 Livelihood and Income Restoration Plan
Affected Persons Livelihood and Income Restoration
Measures
Responsibility
Households/persons
affected by the
construction of
transmission lines
Cash compensation at replacement
cost for affected crops to off-set their
production and income losses
PGCB/ESU
Cash compensation at replacement
cost for affected trees to off-set their
losses as well as to invest part of the
compensation money in tree planting
PGCB/ESU
Cash compensation for the land
under four tower footings PGCB
Temporary employment at project
construction sites for affected men
and women with equal wages as per
the contractual agreement reached
with respective contractors
PGCB/Contractors
Full restoration of the land
temporarily affected by construction
related activities to its original
condition before returning to their
respective owners
Contractors
Full restoration of the land
temporarily affected by construction
related activities to its original
PGCB/ESU
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 35 PGCB.
condition before returning to their
respective owners
Tenants and
Sharecroppers affected
by land acquisitions
Cash compensation at replacement
cost to off-set their loss of trees and
crops as well as to invest part of the
compensation money in tree planting
and crop cultivations in alternate
land
PGCB/ESU
Assistance for sharecroppers and
tenants to identify and move into
alternate land
PGCB/ESU
Temporary employment at project
construction sites for affected men
and women with equal wages as per
the contractual agreement reached
with respective contractors
PGCB/Contractors
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 36 PGCB.
9 BUDGET AND FINANCING PLAN
91. The budget will be revised and updated after completion of the final engineering designs,
final inventory of losses and a systematic valuation of the losses by the executing agency. The
preparation of the budget was guided by the entitlement matrix which provides for payment of
compensation at replacement cost and includes compensation for both temporary and permanent
loss of land and the other assets. The budget also makes provisions for additional resettlement
assistance for non-titleholders, vulnerable and significantly affected households and particularly
for their livelihood restoration. A contingency provision of 5% of the total budget is set aside to cover
unanticipated.
92. The RP of Gopalganj-Shibchar sub-project estimated budget for the impacted land and other
assets are presented in the following section separately.
9.1 Cost Estimation for Land of Tower Footing
93. Price of land in Bangladesh varies substantially depending on productivity, commercial
utility, and proximity to urban centers and access to communications. Therefore, land price also
varies within a given geographical boundary like the smallest land administration unit called “Mouza”. The Deputy Commissioner determined mouza-wise price by “Land Category” which differs from mouza to mouza. The land types in the project area recognized are as follows:
• Dhani/Bilan (Agricultural/Crop Land)
The replacement cost for the permanently affected land for the tower footing area will be determined
as per mouza rate of the respective Upazila. The estimated amount for land procurement has been
assessed based on mouza rate which land is 30745 Tk.Table 9-1 shows the land amount required
for tower in each mouza and price as per mouza rate. Detailed calculation for the lnad value of tower
footing area is presented in the Annex.
Table 9-1 Upazila wise land and cost estimation for tower footing
Name of
Upazial
No of tower Amount of land for
four tower footing
combined
Estimated cost for
the lost land Angle Suspenssion Total
Moksudpur 1 2 3 0.000415 955
Bhanga 3 9 12 0.001660 6514
Rajoir 5 12 17 0.002352 8049
Shibchar 8 18 26 0.003597 15227
Total 17 41 58 0.008024 30745
9.2 Cost Estimation for Crops
94. The cost for compensation of standing crops for land has been estimated based on a fixed
rate for total cropped land. Compensation for standing crops for tower footing and service area during
the construction of the tower has been estimated for one time crop for three seasons. Compensation
for crops to be damaged during stringing of the wire for the transmission lines will be paid one crop
season in single year. Rates for the cost estimation for the crops has collected from the Department
of Agricultural Extension Offices in respective Districts. Following Department of Agriculture
Extension’s rate for category wise crops and production rate of crops per hectre in that area the
estimated value for the service area’s damaged crop is 10,004,210 Tk. Table 9-2 shows the
estimated crops value for tower footing and service area.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 37 PGCB.
Table 9-2: Crops compensation value for Tower foundation service area and ROW
Sl. No. Particulars Estimated Cost (BDT)
1 Cash Compensation for standing crops to be paid during the
construction of the Towers 6,629,030
2 Cash Compensation for standing crops to be paid during the
stringing of the wire 3,375,180
Total Cost for the land 10,004,210
9.3 Cost Estimation for Trees of Tower Foundation Area
95. All trees and scrubs within the tower foundation area should be cut down and remove for
clearing the area to construct the tower. Appropriate mitigation measures have been adopted and
identified and owner of tress will be compensated. Trees standing on the land of tower footing and
foundation area of 230 kv Gopalganj-Shibchar sub-project has been enumerated during sub-project
specific RP updating. The total number of trees to be removed is estimated at 69 which include 24
fruit-bearing trees, 25 timber trees, and 20 medicinal plants. Cost calculation for trees that are going
to be affected due to tower foundation of the transmission line has been determined based on the
calculation from local market, assessment value of forest department and reviewing of other similar
kind of resettlement project in that area. Estimated value for the trees is 792,000 Tk.
No of
small
trees
No of
medium
trees
No of
large
trees
Estimaed cost
for small trees
Estimaed cost
for medium
trees
Estimaed
cost for large
trees
Total
Estimated
cost for
trees
24 25 20 132,000 300,000 360,000 792,000
9.4 Cost Estimation for Trees& Bamboos of ROW
96. The compensation for affected trees on private land in the tower foundations and
transmission lines are presented in below Table. In some cases, the trees will not be fell down but
will require tuning of the branches for easy stringing of the wires. In case of installation of the towers,
affected trees will need to fell-down. The trees owners will be allowed to fell and take away the trees
after payment of compensation. In case of tuning of the branches the PAVC will assess the losses
and compensation through detailed measurement. This RP considers all trees might be affected
within the transmission line and tower foundations for full compensation and budget has been
prepared accordingly based on the rates obtained from the Department of Forest. Value of the fruits
will be applicable 30% of the timber value for each grown trees (above 5 meter I height) as one-time
grants
97. The total number of fruit and timber trees including to be removed is estimated at 3644 and
a total 3698 bamboos to be removed as well. Total estimated cost for the trees of transmission line
is 36,755,400.
Table 9-3 Cost Estimation for Trees and Bamboos of ROW Clearance
Sl. No. Type of Trees Estimated Cost
(BDT)
1 Affected Fruits and Timber Trees in the Transmission Lines 31,267,000
2 Medicinal Trees in the Transmission Lines 1,413,000
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 38 PGCB.
3 Bamboos 1,190,000
4 Value of fruits @ 30% of timber value for each grown up trees (Above
5 meter) 2885400
Total Cost for the Trees 36,755,400
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 39 PGCB.
9.5 Resettlement budget (Summary)
SL No. Particulars Affected Amount/Unit
Estimated Cost at Mouza Rate
Total Cost
A
Private land
1 Tower Footing Area 0.008024 30,745
Sub Total 30,745
Total Cost for Private Land 30,745
B
Crops Affected Unit Estimated Cost
1 Cash Compensation of Standing Crops for Tower Footing and Service Area
81,622 6629030
2
Cash Compensation of Standing Crops for ROW Clearance-one-time cash grant
37,502 3375180
Sub Total 10,004,210
Total Cost for Crops 10,004,210
C
Trees
Affected Unit Estimated Cost
Fruit Trees
1 Large 161 2898000
2 Medium 560 6720000
3 Small 170 935000
Value of fruits @ 30% of timber value for each grown up trees (Above 5 meter)
2885400
Sub Total 13438400
Timber Trees
1 Large 440 7920000
2 Medium 912 10944000
3 Small 462 2541000
Sub Total 21405000
Medicinal
1 Large 43 774000
2 Small 131 1572000
Sub Total 2346000
Bamboos
1 Large 859 429500
2 Medium 2535 760500
Sub Total 1190000
Total Cost for Trees 46047000
Total Estimated Cost
Total Estimated Cost of SRAP (A+B+C)
47,081,955
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 40 PGCB.
SL No. Particulars Affected Amount/Unit
Estimated Cost at Mouza Rate
Total Cost
10% of total budget as contingency
4708196
Provisions for Applicable VAT at 15%
7768523
Grand Total 59,558,673
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 1 PGCB.
10 INSTITUTIONAL ARRANGEMENTS
98. PGCB will be the executing agency of the overall project. The executing agency will establish
a Project Management Unit (PMU) for the overall implementation and coordination of the project related
activities. The PMU with its Project Director (PD) appointed to be in-charge of different components of
the Project will be responsible for overall project planning and implementation, including procurement,
accounting, quality assurance, social and environmental issues, coordination with concerned agencies,
supervising, monitoring, and auditing. It is also the responsibility of PMU to report to ADB on the
implementation of the resettlement plan on a semiannual basis during construction and on annual basis
during operation. The PD will be assisted by two Deputy Project Directors (DPDs).
99. Bangladesh does not have a legal framework that provides guidance for resettlement plan
implementation. Therefore, an implementation procedure has been defined, based on the key
safeguards policy requirement of ADB and lessons learnt from many other successfully completed
donor funded projects in Bangladesh with resettlement plan requirements.
100. PGCB has an environmental and social unit (ESU) at its headquarters composed of a manager
and two engineers with resettlement experience. ESU has gained sufficient resettlement experience in
implementing several resettlements plans for ADB funded power sector projects of PGCB as well as
several World Bank projects such as Power System Reliability and Efficiency Improvement Project,
Bangladesh Rural Electricity Transmission and Distribution Project and Scaling up Renewable Energy
Project. One of the engineers will be responsible for the overall coordination and direction of the
resettlement plan implementation. In addition, PGCB/PMU will assign safeguards tasks to two staff
members with resettlement experience under each of the four executive engineers who will be
responsible for the implementation of resettlement activities at field level including coordination of land
acquisition process and payment of compensation. Of the two officers placed under the supervision of
each executive engineer, one will be assigned for transmission line component while the second will
look after the substation component. Altogether, there will be 10 officers (2 for each of the five divisions
where the project is implemented and supervised by 4 executive engineers) for field level safeguards
management and coordination. The safeguards management responsibilities of PMU at field level
include:
i. Conduct overall coordination, preparation, planning, and implementation of all field level
activities related to resettlement plan implementation.
ii. Implement Environmental Management Plan and the environment and social policy guidelines
and environmental and social good practices at the project site.
iii. Undertake and supervise compensation to the affected persons based on the entitlement matrix
in the resettlement plan.
iv. Oversight of construction contractor(s) on monitoring and implementing mitigation measures
during design, construction, and operation phases of the project.
v. Advise and coordinate within the PMU to finalize survey and detailed design and update the
safeguards documents following detailed design.
vi. Engage in grievance redress and ensure the prompt resolution of complaints.
vii. Set up appropriate record keeping system.
viii. Disclose relevant information to the affected people and continue consultations.
ix. Provide training and awareness on environmental and social issues and safeguards to the
project staff and engineering-procurement contractor(s), if necessary, with assistance from
external resettlement experts.
x. Engage the services of an external monitor; and Dhaka and Western Zone Transmission Grid
Expansion Project (RRP BAN 51137-003)71
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 2 PGCB.
xi. Preparation of environmental monitoring reports on a regular basis and semiannual social
monitoring reports (see Section11 for monitoring items).
10.1 Role of the Project Director in Managing Land Acquisition and
Resettlement
101. The specific duties of the PD will be the coordination of the preparation and implementation of
the land acquisition and resettlement activities in a timely and socially acceptable manner. The PD will
be assisted by the two DPDs and PGCB’s ESU. These duties will include: • Reviewing and updating schedules for the implementation of civil works and coordinating them
with the process tasks required for land acquisition and resettlement compensation.
• Coordinating the monitoring of all RP-implementation related activities performed at the PMU
level and ensuring that all tasks related to land acquisition and compensation, including the
placement of acquisition funds with the DC’s office, are all completed on time.
• Consulting with Chief Engineer and DPDs to resolve any issues that are deemed instrumental
for land acquisition and preparation and implementation of the resettlement activities.
• Monitoring the payments to APs, confirming that their compensations/entitlements are
delivered in full before the land is taken over for civil construction.
• Ensuring payment of compensation for crops and trees for temporary used land in the
transmission lines.
• Ensuring payment of compensation for damaged structures, trees, crops, and other assets
following the policy framework and entitlement matrix of this RP.
• Ensuring payment of compensation for vulnerable, and significantly affected households
defined in the RP and following the policy framework and entitlement matrix of the RP and ADB
SPS 2009.
• Ensuring that all mandatory reporting is completed and transmitted to the agencies as defined
in the RP.
10.2 Environment and Social Unit (ESU)
102. The Environmental and Social Unit of PGCB is responsible for the overall planning,
management, and monitoring of the implementation of the Environmental Management Plan and this
resettlement plan. The ESU and its officer assigned for overall coordination of resettlement plan
implementation will be assisted by the ten officers assigned for the 4 executive engineers. The specific
functions and responsibilities of the ESU in resettlement plan implementation include
i. Maintaining relevant files of the affected persons;
ii. Monitoring the timely disbursement of compensation and other entitlements;
iii. Establishing the GRM and ensuring its effective and efficient functioning;
iv. Liaison with the PAVC to ensure that the affected persons are compensated for their property
losses at replacement cost;
v. Plan and implement necessary resettlement measures including negotiations with the
contractors to offer employment for the affected persons;
vi. Monitor the unforeseen project impacts and plan and implement necessary mitigation
measures;
vii. Conduct training and orientation programs for resettlement/safeguards staff on resettlement
plan implementation and safeguards management, if necessary, with
viii. Dhaka and Western Zone Transmission Grid Expansion Project (RRP BAN 51137-003)72 the
assistance of external resource persons;
ix. Ensure and provide necessary funds for the implementation of resettlement activities; and
x. Preparation of periodic progress reports to the project management
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 3 PGCB.
103. Furthermore, ESU will be responsible to guide and direct the field level resettlement officers
placed under the executive engineers to engage in the mobilization of communities to participate in the
process of resettlement plan implementation, conducting the relevant socioeconomic surveys, project
impact assessments and enumeration of the affected persons, preparation of inventory of losses,
dissemination of relevant information including entitlements to affected persons, assisting and guiding
the affected persons in the process of preparing their title documents, appearing before inquiries and
compensation procedures, facilitation of the proper functioning of the GRM, ensuring timely payment of
compensation from both Deputy Commissioner and PGCB, implementation of the livelihood restoration
and improvement program and implementing all other safeguard measures to secure the rights of all
affected persons including women and vulnerable groups. The specific task of the ESU is given in the
following Table 10-1.
Table 10-1 Tasks and Responsibilities of ESU
No Tasks and Responsibilities
Surveys, data management, planning and documentation
1
Reconciliation of census and joint verification data of each affected household within the
land acquired for substations and the proposed RoW as per the final alignment and the
corresponding resettlement plan prepared by the consultant
2 Prepare and maintain profiles of affected persons
3 Collect and computerize all resettlement related data, including land acquisition and
census to prepare a resettlement databank
Assist in the land acquisition process
4
Participate with Deputy Commissioner and PGCB for carrying out Joint Verification Survey
or Joint On-Site Inventory verification of the affected assets of APs following final
resettlement plan
5 Assist PVAC in valuation of properties/assets for finalization of replacement cost
6 Collect Award list from office of the Deputy Commissioner
Assistance to resettlement implementation agencies
7 Assist formation of GRC and PAVC
8 Liaise with various agencies and officials in resettlement plan implementation and R&R
programs
Liasson with affected persons
9 Guide the field level resettlement officers to develop rapport with APs
10 Guide and direct resettlement officers to conduct awareness raising programs among Aps
on their entitlements and mechanism of payments as mentioned in the entitlement matrix
11
Guide and direct resettlement officers to engage in information dissemination activities to
create awareness about the project, and distribute/display booklets and posters prepared
by ESU in the affected areas and communities
12
Assistance to Affected Persons
13 Direct the resettlement officers to assist APs in opening of their bank accounts.
14 Ensure timely delivery of full entitlements to AP
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 4 PGCB.
15 Wherever possible, guide the resettlement officers to ensure proper utilization of
compensation and resettlement assistance by APs for productive purposes
16 Guide the resettlement officers to assist APs interested in purchasing alternate land and
in the process of restoring their damaged structures (if any)
17 Assist APs in redressing their grievances through Grievance Redress Committee
18 Facilitate establishing links with micro-finance institutions and other support organizations
that can help APs for their livelihood and income restoration
Monitoring and Reporting
19 Regularly monitor the progress of compensation payments to APs
20 Collect relevant data and assist PGCB to monitor and assess the progress of safeguards
management
10.3 Role of Implementing NGO
104. A RP implementing NGO will be appointed by the PIU by taking support of the ESU. The NGO
will play a key role in the RP implementation. The appointed NGO will set up necessary field offices,
carry out information campaign and involve APs including affected households (AHs) headed by women
and vulnerable persons in the RP implementation process. The NGO will collect, collate, computerize
and process data for correct identification of eligible persons for compensation payment as well as
ensuring all resettlement benefits through assessing the entitlement policy framed in the RP. Some of
the key roles and responsibilities of the NGO will comprise of the following:
i. To take lead responsibility in planning and implementing the resettlement activities following
the entitlement matrix mentioned in Chapter 7;
ii. Closely working with affected community and disseminate information to ensure correct and
complete information is available to affected persons and affected households;
iii. To assist in disbursement of compensation (making of ID cards etc);
10.4 Property Assessment and Valuation Committee (PAVC)
105. The PMU will establish Property Assessment and Valuation Committees at the district level
(Upazila) through a gazette notification to be issued by the Ministry of Power, Energy and Mineral
Resources (MPEMR). The Deputy Commissioners (DCs) and PGCB will conduct joint onsite verification
of the affected physical properties on private land proposed for acquisition for the substations. The DCs
will also assess the market price of the affected land, structures, trees and crops with available data,
and assistance from the Sub-Registry offices for land, Public Works Department (PWD) for structures,
Department of Forest (DoF) for trees, and Agriculture Extension and Agriculture Marketing Departments
for crops. The DCs will not compensate the residential structures, shops or any other entities affected
on Government land or having no legal documents/title to the assets to be affected by project
interventions. However, as per the ADB SPS 2009 on involuntary resettlement, the authorized and
unauthorized occupants of public land, sharecroppers, and lessees with no legal documents will also
be entitled for compensation and assistance irrespective of their titles. In the circumstances, the
physical and economic losses of these non-titled affected persons will be assessed at replacement cost
of affected physical assets and incomes will be determined by the Property Assessment and Valuation
Committee (PAVC) established for each district under the project. At each district, there will be five
members in each PAVC. The members of PAVC will be nominated by the Superintending Executive
(Grid Circle) of PGCB and the Project Director. The Vice Chairman of the relevant Upazila will
represents the interests and concerns of the Aps. The following Table 10-2 shows the membership
status of PAVC.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 5 PGCB.
Table 10-2 Membership of PAVC
Superintending Executive (Grid Circle) PGCP Convener
Executive Engineer, Grid Maintenance Division
(GMD) of the concern jurisdiction, PGCB
Member
ESU officer responsible for resettlement plan
implementation
Member-Secretary
Representative of concerned DC office Member
Upzila Vice Chairman (concerned Upazila) Member
106. The PAVC will verify and cross check the field books of the joint verification survey (JVS)
conducted jointly by PGCB and the Deputy Commissioners in respective project areas. The PAVC will
also review and certify the census of affected households (titled and non-titled) and assets conducted
by PGCB through ESU. If there is major variation between Census and JVS data (more than 10%) in
assessing affected properties, PAVC will consult the JVS for titled losses and the Census for non-titled
losses. PAVC will assess the quantity and the category of affected physical properties (structures, trees,
businesses, common properties etc.) on substations and transmission lines. Replacement cost of the
affected physical properties will also be determined by PAVC based on current market price. The PAVC
will also design and conduct a property valuation survey (PVS), review the secondary data available
and consult the public to recommend the replacement cost of land and structures and the market price
of trees and crops as well as the amount of income losses at current market price.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 6 PGCB.
11 MONITORING AND REPORTING
107. PGCB will have the overall responsibility for monitoring the project processes, outputs,
outcomes and impacts in periodic intervals. The project will be monitored both internally and externally
as required by ADB’s SPS 2009 for projects classified for A category. The executing agency will establish the necessary institutional arrangements required for monitoring of the implementation of the
resettlement plan. The project director who will be responsible for the overall project management and
coordination will appoint competent staff to carry out the internal monitoring activities. Semiannual
reports will be submitted to ADB and disclosed on the ADB website.
11.1 Internal Monitoring
108. The Environmental and Social Unit of PGCB in consultation with the resettlement officers
assigned to executive engineers will design a monitoring framework which will include the key areas for
monitoring, methodologies and relevant indicators and plans for disclosure of monitoring results well in
advance of the project implementation. The monitoring system will also focus on engaging all the
relevant stakeholders in the monitoring processes and adopt participatory processes. The
methodologies would include review of documents produced by the project staff, contractors etc.,
individual/group meetings with affected persons and other stakeholders and surveys and studies. The
ESU will maintain a database of all the relevant information such as baseline survey/census data,
profiles of affected persons and information related to resettlement. ESU will also provide necessary
training and orientation to the resettlement officers prior to the commencement of the monitoring
process
109. The ESU officer and the resettlement officers will undertake periodic field visits to project sites
and engage in communication with the affected persons and ensure that consultations are conducted
regularly and effectively. The monitoring process will also focus on (i) the progress of the
implementation of the resettlement plan; (ii) the level of compliance of project implementation with
safeguards plans and measures provided in the legal agreements including payment of compensation
and other resettlement assistance and mitigation of construction related impacts; (iii) disclosure of
monitoring results to the affected persons and other stakeholders; (iv) the level of consultations
conducted with the affected persons and other stakeholders to address gaps in resettlement plan
implementation and to identify necessary measures to mitigate, avoid or minimize adverse impacts
arising from project implementation; and (v) redressal of affected persons’ grievances. 110. The resettlement officers will systematically document the monitoring results and quarterly
(internal) reports will be produced during implementation of the resettlement plan. The executing agency
will submit consolidated semiannual reports for review by ADB on the progress of the safeguard’s implementation of resettlement activities and any compliance issues and corrective actions adopted
until a project completion report is issued. These reports will closely follow the involuntary resettlement
monitoring indicators (see Table 11-1: Monitoring Indicator) agreed at the time of resettlement plan
approval and will be disclosed on the ADBs and PGCBs websites.
Table 11-1 Monitoring Indicators
Monitoring Themes Monitoring Indicators
Status of RP implementation • Have all land acquisition and resettlement
staff been appointed and mobilized for field
and office work on schedule?
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 7 PGCB.
• Have capacity building and training activities
been completed on schedule (As per RP)?
• Have the surveys and census after the
completion of the final engineering designs
and updating the plan, disclosure to the
affected persons and other stakeholders
and obtaining approval been conducted?
• Are involuntary resettlement implementation
activities being achieved against agreed
implementation plan?
• Are funds for land acquisition and
involuntary resettlement being allocated to
the EA on time?
• Have funds been disbursed according to
RP?
• Has the land made encumbrance- free and
handed over to the contractor in time for
feasibility study implementation?
Delivery of APs’ entitlements
• Have all APs received entitlements
according to categories of loss set out in the
entitlement matrix?
• Are activities related to income and
livelihood restoration being implemented as
planned?
• Have all processes been documented?
• Have resettlement information
brochures/leaflets been prepared and
distributed?
Consultations, grievances, and special issues
• Have consultations taken place as
scheduled, including meetings, groups, and
community activities?
• Who participated in consultations?
• What were the information shared and
disclosed with APs and other stakeholders?
• Were the APs and other stakeholders
consulted on final engineering designs and
RP?
• What were the outcomes of consultations?
• What were the measures adopted to
address issues emerged from
consultations?
• Have any APs used the grievance redress
procedures?
• What grievances were raised?
• What were the outcomes?
• Have problems/conflicts been resolved?
• Have grievances and resolutions been
documented?
• Have any cases been taken to court?
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 8 PGCB.
Benefit monitoring
• What changes have occurred in the lives
of families who were relocated and
resettled?
• What changes have occurred in patterns
of livelihoods compared to the pre-
project situation?
• What changes have occurred in income
and expenditure patterns compared to
pre-project situation?
• Have APs income kept pace with these
changes?
• What changes have occurred for
vulnerable groups and significantly
affected households?
11.2 External Monitoring
111. In parallel to the internal monitoring exercises, the executing agency will appoint an
Independent External Social Monitoring Expert to review and evaluate the social safeguards
management in the Project and its compliance with the safeguards policies of ADB and the government.
The Terms of Reference for the External Social Monitoring Expert is given in following Table 11-2.
Table 11-2 Reference for the External Social Monitoring Expert
Project Dhaka and Western Zone Transmission Grid
Expansion Project
Expertise External Social Monitoring Report
Source National
Objective and Purpose of the Assignment
An independent local expert (external expert) will be engaged to carry out external monitoring and to
verify monitoring information for the project. The external expert will be retained on behalf of PGCB,
executing agency. The external expert will be responsible for reviewing resettlement monitoring
reports and providing guidance in accordance with the resettlement plan (RP), loan agreements,
project administration manuals (PAM) and ADB’s Safeguard Policy Statement (2009). The external monitoring report will be prepared and submitted to ADB for review semi-annually.
Scope of Work
The external expert will be responsible for periodic monitoring of the progress and status of RP
implementation about achieving objectives of the ADB’s Safeguard Policy on Involuntary
Resettlement. Independent evaluation will be done twice during the project implementation period.
Detailed Tasks and/or Expected Outputs
i. The activities of this position include, but are not limited to the following:
ii. Review the progress and status of RP implementation and internal monitoring reports.
Identify the key issues that need to be addressed.
iii. Review compensation and entitlement policy compliance; adequacy of organizational
mechanism for implementing the RP; and provisions for adequate budgetary support for
implementing the RP.
iv. Assess whether resettlement objectives, particularly assistance to vulnerable and
significantly affected groups and restoration of livelihoods and living standards of the affected
persons have been fulfilled.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 9 PGCB.
v. Assess resettlement efficiency, its effectiveness, impact, and sustainability in relation to
policy and practices and to suggest any corrective measures.
vi. Appraise the accounting documents used in recording the payments of compensation to
affected people by PGCB.
vii. Provide guidance to PGCB on the grievance redress mechanism, grievance handling and
grievance log and documentation.
viii. To provide inputs into the RP and assist RP update, if necessary.
ix. The external monitoring expert should make necessary field visits and activities such as
conducting formal and informal surveys/interviews/public consultations/focus group
discussions and in-depth case studies to assess impact of resettlement.
Minimum Qualification Requirements
The specialist should have an advance degree in environmental studies, social science, or other
related disciplines and with at least 7 years of related work experience in resettlement. The specialist
should be an expert on resettlement and social issues especially in preparation of resettlement and
social monitoring reports.
Minimum General Experience: 7 years
Minimum Specific Experience: 5 years (relevant to assignment)
Regional/Country Experience: Required
Deliverables Estimated Submission Date Type
External Resettlement Monitoring Report bi-annually Report Final Evaluation Report
Place of Assignment Days Estimated Dates (dd/mm/yyyy)
TOTAL DAYS 178 (intermittent)
2 months/year and for 4 years
from the loan effective date.
Early termination is possible if
the land acquisition and
compensation for both
substations and transmission
lines is completed.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 10 PGCB.
12 IMPLEMENTATION SCHEDULE
112. Activities related to social safeguards management will go through different phases which
include preparation of draft and final resettlement plan, public consultations and information disclosure,
and disclosure of resettlement plans, land acquisition and payment of compensation and other
assistance, relocation and resettlement, grievance redress etc. The compensation will be provided
before any physical and/or economic displacement. The implementation schedules for each substation
and transmission line vary, and therefore finalizing resettlement plan encompassing all project
components and their implementation schedules into one single framework prior to the award of the
first contract is not feasible. Meanwhile, implementation schedules for transmission lines are difficult to
finalize prior to the award of contract as the design will be finalized by the contractors. Therefore, the
team will finalize the resettlement plan by component by component.
113. However, all activities related to assessment of losses and payment of compensation will be
completed before subproject sites are handed over to the contractors and the commencement of the
civil work constructions. No physical or economic displacement of the affected persons will occur until
full compensation is paid to the affected persons at replacement cost and the executing agency will
ensure that compensation is paid prior to the start of civil works. All land will be freed from its
encumbrances before they are handed over to the contractors. Public consultations, information
disclosure, grievance redress processes and monitoring will continue an intermittent basis for the entire
duration of the project which is now considered to be five years. Table 12-1 presents an implementation
schedule for resettlement activities. The timeframe planned for the completion of resettlement activities
will vary from minimum of 13 to 16 months, preceding the implementation of each project component.
The implementation schedule for resettlement activities is tentative and subject to modification based
on the actual progress of work.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 11 PGCB.
Table 12-1 Implementation Schedule
Activity 2022 2023 2024
1 2 3 4 1 2 3 4 1 2 3 4
Prepare the draft resettlement plan Census and Socio-
economic survey
ESU conducts a census survey and prepares IoL
Disclosure of resettlement plan
Submit the updated RP
Complete land procurement process for tower
foundationand payment of compensation including
compensation payments
Functionalize PAVC
Establish the Grievance Redress Mechanism (GRM)
Disclose information on GRM
PAVC verifies IoL and determines replacement cost for
all affected properties acquired and the properties
affected by transmission lines
PGCB pays additional compensation as recommended
by PAVC
ESU implements the resettlement plan including
livelihood restoration activities
Clear the land for construction work (component by
component)
Hand over the sites to contractors (component by
component)
Conduct grievance redress
Continue stakeholder consultations
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 12 PGCB.
Activity 2022 2023 2024
1 2 3 4 1 2 3 4 1 2 3 4
Information disclosure
Monitor safeguards compliance (internal and external)
Reporting resettlement plan implementation progress
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 13 PGCB.
APPENDIX A: PHOTOGRAPH OF SOCIAL SURVEY
Socioeconomic Suvey, Gopalganj to Shibchar Line
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 14 PGCB.
APPENDIX B: PHOTOGRAPHS OF FGDS
Public Consultation during safeguard consultation-Gopalganj and Madaripur District
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 15 PGCB.
APPENDIX C: ATTENDANCE OF FGDS
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 16 PGCB.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 17 PGCB.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 18 PGCB.
APPENDIX D: LIST OF LAND OWNERS
SL.NO Land Owner Name Father's Name Mobile Number Area Name
1. ABDUL JALIL MUNSHI LATE YUSUF MUNSHI 01614200479 CHAGOL CHIRA
2. FIROZA BEGUM HAMID MUNSHI 01614200479 KASHEMPUR
3. AWLID KHAN MAZED KHAN O1707199185 TOPARKANDI
4. WAHID KHAN LATE ANAR UDDIN KHAN 01726161859 TOPARKANDI
5. MD.EAR KHAN HASEN KHAN 01726161859 TOPARKANDI
6. ABDUL HAQUE TALU HOSEN MATUBBER 01307840149 SRI RAMPUR
7. ATIR MATUBBER HARUN MATUBBE 01718686931 SRIRAMPUR
8. DADON MATUBBER ABDUL WAZED MATUBER 01749157008 SRI RAMPUR
9. BABUL MATTUBER ABDUL SAMAD MATUBER 01740858674 MATUBER BARI
10. SIRAJ BATUBBER HELAL UDDIN MATUBER 01318593653 MATUBER BARI
11. MD.RIPON MATUBBER AHMED MAZID 01710859335 MUNSHI PARA
12. MD ENAYET HOSSAIN SEKENDAR MATUBBER 01753804275 DIGHLIA
13. SHAHIDUL MATUBBER LATE SIRAZUL ISLAM 01715972072 RANIPUKUR
14. SAIFUL ISLAM FIROZ LATE KADER MUNSHI 01727829754 BASUDEBPUR
15. MD.GOFFAR MUNSHI MD.YOUNUS MATUBBER 01717441287 MUNSHI PARA
16. RUHUL AMIN MATUBUR ALIM UDDIN JOMDDER 01716418832 RANIPUKUR
17. SHAH ALOM JAMDDER LATE JOYNAL KHALASHI 01722738175 DIGHLIA
18. SHORAB KHALASHI CHODURUDDIN MUNSHI 01762441065 MACHKANDA
19. MALEK MUNSHI MAZID MATUBBER 01770295809 NAWRA
20. KERAMOT MATUBBER HAQUE MATUBBER 01944034907 DAMER CHAR
21. HARUN BEPARI RASHID KHALIFA 01720029326 NAWRA
22. MINTU MATBOR TARAMIA MATBOR 01746416350 PROTHAR CHAR
23. MD.IMARAT MATUBBER MAKSED MATUBBER 01733011083 PROTHAR CHAR
24. ADEL UDDIN MOLLAH LATEAFSAR MOLLA 01317015208 PROTHAR CHAR
25. JAHANGIR MATUBBER ANSER UDDIN MATUBER 01308992308 SARISSTABAD
26. BALAM BEPARI HALIM MATUBBAR 01722484272 DEWRA
27. HASAN SHEKH SEKENDER FAKIR 01768994303 ATTABADSHA
28. MST.AMENA SATTAR MOLLIK 01726841269 ATTABADSHA
29. KAHINUR AKON LATE ISHAK MATUBBAR 01319792407 VARSHA
30. MST.AMELA BEGUM DABIR MATUBBER 01724021379 VARSHA
31. KHAKON MATUBBER LATE.HAZI OSMAN GAZI 01310374285 VARSHA
32. BAZLUR RAHMAN LATE.OYAZED MOLLA 01715479191 SAWTHER
33. SHIRAJ HAWLADER MD.HAFIZUL MUNSHI 01824211967 SAWTHER
34. AMIR MUNSHI LOTIF MUNSHI 01784720345 HAWLADER BARI
35. HARUN BEPARI MOSLEM MATUBBER 01317571662 MUNSHI PARA
36. MOSTOFA HAWLADAR RAHMAN HAWLADAR 01747604280 KACHIKATA
37. MUJIBOR HAWLADAR SHOFI HAWLADER DOLKANDI
38. ALAMGIR MATOBBOR SATTAR MATOBBER 01783324089 PATAIL
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 19 PGCB.
39. SHOHID MATOBBAR MD.NASIR KHA 12919630089 JANGAL
40. RAJAB ALI MATUBBER ANSER UDDIN MATUBER 01735742489
41. MOSLEM MATUBBER HALIM MATUBBAR SHIRWAIL
42. AZIZUL FAKIR SEKENDER FAKIR O1779007789 SHOLAPUR
43. KABUL MALLIK SATTAR MOLLIK 01727108484 SHOLAPUR
44. IBRAHIM MATUBBER MD.ISHAK MATUBBAR 01790520712 SHOLAPUR
45. AFZAL HOSSAIN DABIR MATUBBET 017122971436 MATBBAR BARI
46. ABDUL HAIGH MASTER HAZI OSMAN GAZI 01720177778 MATUBAR BARI
47. MD.MOJIBOR MOLLA LATE.OYAZED MOLLA 01905527646 MATUBAR BARI
48. MD.HAFIZUL MUNSHI MD.HAFIZUL MUNSHI 01763182781 MOLLA BARI
49. MANIK MUNSHI LOTIF MUNSHI 01716560427 CHAR KAKOIR
50. DADON MATUBBER MOSLEM MATUBBER 01722223534 CHAR KAKOIR
51. ABDU MANNAN MATBOR MALEK MATBBOR 01775337693 CHAR KAKOIR
52. JUBAYER MATOBBOR MOFAZZAL 01731119901 SENERBAT
53. JALAL KHA LATE.HALEM KHA 01714220074 SENERBAT
54. MOHAMMED KHA MD.NASIR KHA 01750478359 SENERBAT
55. MOHAMMAD KHA LATE.NASER KHA 01595494364
56. MD.SALAUDDIN KHAN LATE.LATIF KHAN SENERHAT
57. THANDU KHAN LATE. CHANMIA KHAN 01766841934 SENERBAT
58. MD.ALOMGIR LATE RATON MATUBAR 01906121433 SENERBAT
59. MD.FATEH ALI MADBOER JAYED ALI MADBER 01733658632 MATUBBAR BARI
60. ABDUR RAHMAN RAJJAK SHIKDAR 01552353050 JADUARCHAR
61. MD.SIDDIQ SHIKDER MUBARAK SHIKDER 01721850116 SHIKDER BARI
62. MIZANURAKON MANNAN AKON 01756723606 SHIKDER BARI
63. MST.BILKIS BEGUM HARUNUR RASHID 01765773538 AKON BARI
64. HOBI FARAZI SEKAN FARAZI 01311369049 HAWLADER BARI
65. AKBAR MATUBBER JALIL MATUBBER 01710590703 SHOTARPAR
66. HAMIDUL HAQUE MOTALLEB 01710497793 SUTAR PAR
67. MD.RUHUL AMIN ABDUL KARIM 01742608748 SUTAR PAR
68. HABI BEPARI DALILUDDIN BEPARI 01716654724 SUTAR PAR
69. EDRIS AKON LATE.KHALEK AKON 01784271701 GOZARIA
70. MD.KAWSAR HOSSAIN NURUL HAQUE MADBOR 01314892035 JADUARCHAR
71. DADON BEPARI SAYFUL BEPARI 01726301822 KUMERPAR
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 20 PGCB.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 21 PGCB.
APPENDIX E: SURVEY QUESTIONNAIRE
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 22 PGCB.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 23 PGCB.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 24 PGCB.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 25 PGCB.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 26 PGCB.
APPENDIX F DETAILS OF BUDGET
Table 0-1 Estimated Budget for Tower Footing
MOUZA NAME
Land price in decimal
as per Mouza Rate
Land price in acre
Land require for tower
Total tower
Total Land
Total price
ATTABADSHA 23000 2300000 0.000138 3 0.000415 955
BASUDEBPUR 36885 3688500 0.000138 4 0.000554 2042
CHARKAKOIR 25695 2569500 0.000138 3 0.000415 1067
DAMER CHAR 29595 2959500 0.000138 2 0.000277 819
DIGHILIA 61328 6132800 0.000138 3 0.000415 2546
GOPALPUR 22771 2277100 0.000138 5 0.000692 1576
GOZARIA 35745 3574500 0.000138 4 0.000554 1979
KACHIKATA 54673 5467300 0.000138 4 0.000554 3026
NAWRA 28865 2886500 0.000138 3 0.000415 1198
NOJIRKHA 22480 2248000 0.000138 1 0.000138 311
PROTHAR CHAR 30515 3051500 0.000138 4 0.000554 1689
SADEKABAD 42881 4288100 0.000138 4 0.000554 2374
SAWTHAR 25000 2500000 0.000138 2 0.000277 692
SHIROAIL 46505 4650500 0.000138 2 0.000277 1287
SHOLAPUR 30637 3063700 0.000138 2 0.000277 848
SONAIMUKHIR CHAR 27000 2700000 0.000138 2 0.000277 747
SOUTH SARISSTABAD 50515 5051500 0.000138 3 0.000415 2097
SRI RAMPUR 48900 4890000 0.000138 3 0.000415 2030
TALUKDERKANTI 95139 9513900 0.000138 2 0.000277 2633
VARSHA 30000 3000000 0.000138 2 0.000277 830
Total
0.008026 30745
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 27 PGCB.
Table 0-2 Estimated Budget for Crops
Type Category of Losses Unit Affected Unit Estimate Budget
as per DAE
Tower
Footing
and
Service
Area
Cash Compensation of Standing
Crops for Tower Footing and
Service Area (Karif-I)
Kg 14,545 827,250
Cash Compensation of Standing
Crops for Tower Footing and
Service Area (Karif-II)
Kg 27,575 2,426,600
Cash Compensation of Standing
Crops for Tower Footing and
Service Area (Rabi)
Kg 37,502 3,375,180
ROW
Clearance
Cash Compensation of Standing
Crops for ROW Clearness- one-
time cash grant (Considering
Rabi Season)
Kg 37,502 3,375,180
Sub Total 1,000,4210
Total Cost of Crops 1,000,4210
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 28 PGCB.
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 29 PGCB.
Table 0-3 : Estimated Budget for Trees
Cost Estimation for Trees of Tower
Footing and Service Area
Unit
Rate
Affected
Unit
Estimatecd
Cost
Fruits
1 Above 10 Meter 18000 6 108000
2 5 Meter to 10 meter 12000 10 120000
3 Less than 5 meter 5500 10 55000
4 Sapling 100 0 0
Sub Total 283000
Timber
1 Above 10 Meter 18000 11 198000
2 5 Meter to 10 meter 12000 12 144000
3 Less than 5 meter 5500 12 66000
4 Sapling 100 0 0
Sub Total 408000
Medicinal
1 Above 10 Meter 18000 3 54000
2 5 Meter to 10 meter 12000 5 60000
3 Less than 5 meter 5500 0 0
Sub TotaL 114000
30% of fruit bearing trees 2885400
Total Cost for Trees of Tower Foundation and Service Area 3690400
Cost Estimation for Trees of ROW Clearance
Fruits
1 Above 10 Meter 18000 155 2790000
2 5 Meter to 10 meter 12000 550 6600000
3 Less than 5 meter 5500 160 880000
4 Sapling 115 0 0
Sub Total 10270000
Timber
1 Above 10 Meter 18000 429 7722000
2 5 Meter to 10 meter 12000 900 10800000
3 Less than 5 meter 5500 450 2475000
4 Sapling 115 1010 116150
Sub Total 21113150
Medicinal
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 30 PGCB.
1 Above 10 Meter 18000 40 720000
2 5 Meter to 10 meter 12000 126 1512000
3 Less than 5 meter 5500 0 0
Sub Total 2232000
Bamboo
1 Above 10 Meter 500 859 429500
2 5 Meter to 10 meter 300 2535 760500
Sub Total 1190000
Total Cost for Trees of Tower Foundation and Service Area 34074350
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 31 PGCB.
Appendix G List of Trees of ROW
Table 0-4 List of trees within ROW clearence
Tower No Trees Name Type Big Medium Small
DL4/2
MEHOGONY Timber 5 15
COCONUT Fruits 1 5
JACKFRUIT Fruits 1 12 8
DL4/2 TO AP5/0 KARAI Timber 17 7
MANGO Fruits 11
DL4/2 TO AP5/0 MEHOGONY Timber 12 7
PALM Fruits 13 2
DL4/2 TO AP5/0 CHAMBUL Timber 2
DL4/2 TO AP5/0 EUCALYPTUS Timber 29 5
RAINTREE Timber 3
DL4/2 TO AP5/0
MEHOGONY Timber 13 4
MANGO Fruits 1
PALM Fruits 124
EUCALYPTUS Timber 1
AP5/0 TO DL5/1 MEHOGONY Timber 19 7
AP5/0 TO DL5/2 KARAI Timber 1
DL5/2 TO 5/3 MEHOGONY Timber 3 10 11
DL 5/2 TO 5/3
JACKFRUIT Fruits 2
KARAI Timber 11
MEHOGONY Timber 1
DL5/2 TO 5/3 PALM Fruits 1 3
MEHOGONY Timber 15 4
DL5/2 TO 5/3
KARAI Timber 3
MEHOGONY Timber 8 16 2
BOMBAX Timber 1
DL5/2 TO 5/3 Mango Fruits 1
MEHOGONY Timber 17 6
DL5/2 TO 5/3 PALM Fruits 2 9
DL5/2 TO 5/3 KARAI Timber 12
JACKFRUIT Fruits 13
DL5/2 TO 5/3 KARAI Timber 3 4
MANGO Fruits 14
DL5/3 TO 5/4
PALM Fruits 1
MEHOGONY Timber 2 3
Akashmoni Timber 4
KARAI Timber 2 13
AP6/0 TP DL 6/1 KARAI Timber 4
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 32 PGCB.
Tower No Trees Name Type Big Medium Small
DATE PALM Fruits 1 13
MANGO Fruits 5
JACKFRUIT Fruits 22 3
MEHOGONY Timber 12
DL6/1 TO 6/2
MEHOGONY Timber 7
Karai Timber 5 19
KARAI Timber 1
Mango Fruits 17
DL6/1 TO 6/2 MEHOGONY Timber 11 6
WODIER Timber 12
DL6/1 TO 6/2
DATE PALM Fruits 1
ARJUN Medicinal 4 0 9
Tal Fruits
Karai Timber 21 35
WODIER Timber 1
DL6/1 TO 6/2
MEHOGONY Timber 5 10 10
BANYAN Timber 1 13
COCONUT Fruits 15
KARAI Timber 4 15
DL6/1 TO 6/2 MEHOGONY Timber 6
DATE PALM Fruits 1
DL6/1 TO 6/2
MEHOGONY Timber 1 13 9
MANGO Fruits 4 2
COCONUT Fruits 12
DATE PALM Fruits
ARJUN Medicinal 2 0 11
Mango Timber 6 15
DL6/1 TO 6/2
JACKFRUIT Fruits 1
KARAI Timber 20
COCONUT Fruits 2
MANGO Fruits 3
DL6/2 TO 6/3
MEHOGONY Timber 2
KARAI Timber 2 19
JACKFRUIT Fruits 2
DL6/2 TO 6/3 SHISHU Timber 10 7
DL6/2 TO 6/3
JACKFRUIT Fruits 3
ARJUN Medicinal 5 0 8
MEHOGONY Timber 9
DL6/3 TO AP 7/0
MEHOGONY Timber 5 13 2
KARAI Timber 13 2
PALM Fruits 1
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 33 PGCB.
Tower No Trees Name Type Big Medium Small
IJOL Timber 1
DL6/3 TO AP 7/0
DATE PALM Fruits 4 13
MANGO Fruits 3
MEHOGONY Timber 10
ARJUN Medicinal 3 0 7
Nim Timber 10
DL9/3 TO 9/4 MEHOGONY Timber 2 2
BOMBAX Timber 1
DL9/3 TO 9/4
KARAI Timber 1
CHAMBUL Timber 1
MEHOGONY Timber 7
PLUM Fruits 4 1
DL9/3 TO 9/4 MANGO Fruits 2
MEHOGONY Timber 1
DL9/6 TO 9/7
KARAI Timber 5 8 4
MEHOGONY Timber 6 3 32
MEHOGONY Timber 6 10
Jack Fruit Fruits
DL9/6 TO 9/7
MEHOGONY Timber 25 9 21
KARAI Timber 2 3
Karai Timber 10 5 4
CHAMBUL Timber 2 5
RAINTREE Timber 5 10
EARLEAF Timber 40 3
DL9/6 TO 9/7
KARAI Timber 2 3
MEHOGONY Timber 18 21 7
RAINTREE Timber 4 20 5
DL9/6 TO 9/7 MEHOGONY Timber 12 12 6
KARAI Timber 2 4 2
DL9/6 TO 9/10
MEHOGONY Timber 5 13 6
KARAI Timber 3 2
RAINTREE Timber 22 3
DL9/7 TO AP10/0 CHAMBUL Timber 3
Akashmoni Timber 12 2
DL9/7 TO AP10/0 MEHOGONY Timber 6 40 5
DL9/7 TO AP10/0
MEHOGONY Timber 3 7 3
BOMBAX Timber 1
Akashmoni Timber 5 5 6
CHAMBUL Timber 3
DL9/7 TO AP10/0 KARAI Timber 5 4
MEHOGONY Timber 4
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 34 PGCB.
Tower No Trees Name Type Big Medium Small
DL9/7 TO AP10/0 KARAI Timber 3 4
AP11 TO AP10/0
JACKFRUIT Fruits 3 12
MANGO Fruits 12
COCONUT Fruits
MEHOGONY Timber 2 5
AP11 TO AP10/0 MEHOGONY Timber 6
AP11 TO AP10/0
KARAI Timber 1 3
MEHOGONY Timber 4
DATE PALM Fruits 9 13
AP11 TO AP10/0 COCONUT Fruits
AP11 TO AP10/0 Mehogoni Timber 9 3
AP12/0 TO 11/0 KARAI Timber 9
AP12/0 TO 11/0 KARAI Timber 25 7
Mango Fruits 8 10
AP12/0 TO 11/0 MEHOGONY Timber 2
AP12/0 TO 11/0 MEHOGONY Timber 4
EARLEAF Timber 1
DL12/1 TO 12/2 KARAI Timber 4
MEHOGONY Timber 2
DL12/1 TO 12/2
MEHOGONY Timber 5 8
KARAI Timber 1
VELVET APPLE Fruits 2
JAVA PLUM Fruits 3
Nim Timber 0
BOMBAX Timber 1
COCONUT Fruits 1 13
DATE PALM Fruits 2 1
MANGO Fruits 8 1
DL12/3 TO 12/4 BAMNA Timber 2
DL12/4 TO 12/5
KARAI Timber 1 11
CHAMBUL Timber 2 3
Akashmoni Timber 9 5
DL12/4 TO 12/5
MEHOGONY Timber 3
MANGO Fruits 2
KARAI Timber 2
DATE PALM Fruits 6 11
CHAMBUL Timber 1
DL12/4 TO 12/5 Mehogoni Timber 5
BUR FLOWER Timber 1
AP13/0 TO DL 13/1 KARAI Timber 9
AP13/0 TO DL 13/1 KARAI Timber
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 35 PGCB.
Tower No Trees Name Type Big Medium Small
DL14/0 TO 14/3 DATE PALM Fruits 5
END PROPOSED TTO2
KARAI Timber 2 5
BOMBAX Timber 1
COCONUT Fruits 1
DL 14/3 TO 14/4
CHAMBUL Timber 5
DATE PALM Fruits 6
PALM Fruits 4 6 5
MEHOGONY Timber 2 5 10
DL15/0 TO DL 15/1 MEHOGONY Timber 6 2 8
DL 15/0 TO 15/1
MEHOGONY Timber 50 5 4
COCONUT Fruits 6
JACKFRUIT Fruits 2
CHAMBUL Timber 3
MEHOGONY Timber 3
ARJUN Medicinal 4 0 9
DL15/1 TO DL 15/2 Mehogoni Timber 5 7
DL15/1 TO 15/2
COCONUT Fruits 2 5
Nim Medicinal 2 0 11
RAINTREE Timber 2
CHAMBUL Timber 1
Mehogoni Timber
DL15/1 TO 15/2
MEHOGONY Timber 5 35 5
ARJUN Medicinal 5 0 13
CHAMBUL Timber 12 4
Akashmoni Timber 3 8
COCONUT Fruits 5 7
DL15/1 TO DL 15/2
MEHOGONY Timber 5
CHAMBUL Timber 1 2
RAINTREE Timber 1
DL15/1 TO DL 15/2
Akashmoni Timber 5 3 10
MEHOGONY Timber 13 4 2
Nim Medicinal 3 0 15
JACKFRUIT Fruits 5 6
DL15/1 TO DL 15/2
Mehogoni Timber 10
MANGO Fruits 4 7 2
CHAMBUL Timber 11 3 4
MEHOGONY Timber 1
DATE PALM Fruits 2
BUR FLOWER Timber 1
DL15/1 TO DL 15/2 Tal Timber 4 2 6
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 36 PGCB.
Tower No Trees Name Type Big Medium Small
MANGO Fruits 3 11
MEHOGONY Timber 2 1
DL15/2 TO AP16
JACKFRUIT Fruits 1 4
MEHOGONY Timber 13 6
Nim Medicinal 3 0 9
DL15/2 TO AP16
MEHOGONY Timber 4 5
COCONUT Fruits 2 12 7
Nim Medicinal 2 0 12
JACKFRUIT Fruits 3
DL15/2 TO AP16
MEHOGONY Timber 15 2
JACKFRUIT Fruits 3 1
COCONUT Fruits 4 8 1
KARAI Timber 1
Nim Medicinal 1 0 8
AP16 TO AP17 MEHOGONY Timber 6 3
MEHOGONY Timber 9 2 8
JAVA PLUM Fruits 1
COCONUT Fruits 12
MANGO Fruits 2 1
AP16 TO AP17 EUCALYPTUS Timber 5
AP16 TO AP17 Akashmoni Timber 2 6 3
AP16 TO AP17 Mango Fruits 50 6 10
AP16 TO AP17
MEHOGONY Timber 4 2 1
MANGO Fruits 1 8
COCONUT Fruits 2 5 8
SAPODILLA Fruits 4 1
POMELU Fruits 2 1
AP16 TO AP17
COCONUT Fruits 8 9 2
MEHOGONY Timber 4 10 5
MANGO Fruits 6
ARJUN Medicinal 2 0 5
JACKFRUIT Fruits 3 5
ARJUN Medicinal 3 0 7
PALM Fruits 3 3
PLUM Fruits 14 1
POMELO Fruits 2
TAMARIND Fruits 4 3
DEBDORON Timber 12
JAVA PLUM Fruits 1 6 6
SAPODILLA Fruits 4 4
AP16 TO AP17 MEHOGONY Timber 2
Resettlement Plan for Dhaka and Western Zone Transmission Grid Expansion Project (DWZTGEP)
EQMS Consulting Limited 37 PGCB.
Tower No Trees Name Type Big Medium Small
JACKFRUIT Fruits 2 5
AP16 TO AP17 MEHOGONY Timber 5 5
ARJUN Medicinal 4 0 7
AP 17 TO PROPOSED TT2
MEHOGONY Timber 6 5
COCONUT Fruits 5 10
DATE PALM Fruits 2 8 2
PALM Fruits 1 1
MANGO Fruits 2
AP 17 TO PROPOSED TT2
MEHOGONY Timber 2 3
CHAMBUL Timber 3 2
MANGO Fruits 5 9 7
JACKFRUIT Fruits 2 12
PLUM Fruits 4
AP 17 TO PROPOSED TT2 MEHOGONY Timber 2 5 10
Mango Fruits
Total 763 1472 644