Distribution of Ocean Desalinated Water Board of Directors February 3, 2016 1 Updated

Upload: others

Post on 14-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Distribution of Ocean Desalinated Water

Board of Directors February 3, 2016

1

Updated

Page 2: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Background • May 2015 – OCWD approved Term Sheet with

Poseidon Resources – Poseidon construct treatment plant – OCWD construct necessary distribution infrastructure

• OCWD staff asked to review option of recharging Poseidon water into the groundwater basin

• Report attached (Options 1A, 1B, 1C) • Other options also reviewed

2

Page 3: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Presentation Topics I. Distribution Options II. Financial Impacts III. Schedule IV. Total Water Demands V. Future Water Supply Portfolio VI. Using GAP System to distribute Poseidon water VII. Water Chemistry/Integration

3

First Workshop(s)

Page 4: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Poseidon Distribution Options Option Description Capital

Cost

1A 26 New Injection Wells, Talbert Barrier, and necessary pipelines $305 M

1B 16 New Injection Wells, Talbert Barrier, and new pipeline off GWRS pipeline to Kraemer Basin $316 M

1C Zero New Injection Wells, Talbert Barrier, and new pipeline from FV to new 20 acre recharge basin $325 M

1D* Four New Injection Wells, Talbert Barrier, Burris Booster PS, Burris Outlet, and necessary pipelines $160 M

2A* Zero New Injection Wells, Talbert Barrier, Burris Booster PS, Burris Outlet, and pipelines/turnouts to sell directly to NB & HB $131 M

2B Zero New Injection Wells, Talbert Barrier, and pipelines/turnouts to sell directly to NB, HB, SB, FV, GG, GSW $97 M

3 Zero New Injection Wells, Talbert Barrier, and pipelines/turnouts to sell directly to NB, HB, SB, FV, GG, GSW, and South County Agencies $161 M

4 All water distributed to Producers (no recharge) $107 M 4

Page 5: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

OCWD Existing Facilities

• GWRS • Talbert Seawater Barrier • GAP • GWRS Pipeline • MBI • Recharge Basins

5

Page 6: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Desal Option 1A

6

54-inch Desal Distribution Pipe

Southeast Talbert Inj. Wells

SAR Injection Wells

Dyer Wellfield Inj. Wells

Campesino Park Inj. Wells

ARTIC Inj. Well

Desal Distribution Pump Station

Ball Road Basin Inj. Wells Facility Flow

(MGD) Capital

Cost ($M)

Burris Outlet - $1

Ball Road Basin Inj. Wells 4.5 $19

ARTIC Inj. Well 2 $6

Campesino Park Inj. Wells 4.5 $19

Dyer Wellfield Inj. Wells 12 $79

SAR Injection Wells 6 $24

Talbert Seawater Barrier 15 -

Southeast Talbert Inj. Wells 6 $35

Desal Dist. Pipeline - $41

Desal Dist. Booster PS - $6

Property Acquisition - $5

Contingency (30%) - $70

TOTAL 50 $305

Page 7: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

7

30-inch Desal Kraemer Distribution Pipeline

Dyer Wellfield Inj. Wells

Facility Flow (MGD)

Capital Cost ($M)

Kraemer Basin Recharge 15 -

Desal Kraemer Dist. Pipeline - $68

Burris Outlet - $1

ARTIC Inj. Well 2 $6

Desal Kraemer Booster PS - $6

Dyer Wellfield Inj. Wells 12 $79

Talbert Seawater Barrier 15 -

Southeast Talbert Inj. Wells 6 $35

Desal Dist. Pipeline - $41

Desal Dist. Booster PS - $6

Property Acquisition - $1

Contingency (30%) - $73

TOTAL 50 $316

Desal Option 1B

54-inch Desal Distribution Pipe

ARTIC Inj. Well

Southeast Talbert Inj. Wells

Desal Kraemer Booster Pump Station

Page 8: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

8

42-inch Desal Recharge Basin Distribution Pipeline

42-inch Desal Barrier Distribution Pipeline

New Recharge Basin Facility Flow

(MGD) Capital

Cost ($M)

New Recharge Basin 35 $9

Burris Basin Outlet - $1

Talbert Seawater Barrier 15 -

Desal Distr. Pipeline (Barrier) - $33

New Desal Distr. Pipeline (Recharge Basin)

- $156

New Desal Booster PS - $16

Property Acquisition - $35

Contingency (30%) - $75

TOTAL 50 $325

Desal Option 1C

New Desal Booster Pump Station

Page 9: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

GWRS Final Expansion

(30 mgd of new water)

72”

78”

66”

60”

Edinger

Willowick Golf Course

Burris

Kraemer Miller

Miraloma

La Palma

Five Mid Basin Injection Wells at Centennial Park - ~8 mgd

7 mgd

Booster Pump Station to send additional 15 mgd to recharge basins

GWRS Pipeline (not to scale)

9

Page 10: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Desal Option 1D

10

54-inch Desal Distribution Pipe

Centennial Park Inj. Wells

Desal Distribution Pump Station

Burris Booster Pump Station & Outlet

Facility Flow (MGD)

Capital Cost ($M)

Burris Booster Pump Station* 15 $25

Burris Basin Outlet* 12 $1

Centennial Park Inj. Wells* 6.5 $25

MBI Inj. Well* 1.5 -

Talbert Seawater Barrier 15 -

Desal Dist. Pipeline - $41

Desal Dist. Booster PS - $6

GWRS IE – SAR Inj Wells - $24

GWRS IE – ARTIC Inj Well - $6

Contingency (30%) - $32

TOTAL 50 $160

*Projects Planned for GWRS Final Expansion

Page 11: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Desal Option 2A

11

54-inch Desal Distribution Pipe

Desal Distribution Pump Station

Burris Booster Pump Station & Outlet

*Projects Planned for GWRS Final Expansion

Turnouts

Facility Flow (MGD)

Capital Cost ($M)

Burris Booster Pump Station* 15 $25

Burris Basin Outlet* 12 $1

Talbert Seawater Barrier 15 -

Desal Dist. Pipeline - $41

Desal Dist. Booster PS - $6

Turnouts & Pipeline for NB & HB 8 $3

GWRS IE – Centennial Park Inj Wells - $25

Contingency (30%) - $30

TOTAL 50 $131

Page 12: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Comparison of Desal vs GWRS Final Expansion Distribution Cost for Options 1D & 2A

12

• Total capital cost for GWRS Final Expansion Distribution Facilities is approximately $70 M

– MBI & Centennial Park Inj Wells – Burris Booster PS at Burris – Burris Outlet

• If the above facilities are designated for desalinated water – then additional injection wells will have to be constructed for GWRS Final Expansion

• The total capital cost for the new injection wells required to recharge GWRS Final Expansion water is estimated to be ~ $200 M

Page 13: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

13

42-inch Desal Distribution Pipe

42-inch Desal Producer Distribution Pipe via

WOCWBF

Desal Option 2B Facility Flow

(MGD) Capital Cost

($M)

Burris Outlet - $1

Desal Producer Dist. Pipeline and WOCWBF Turnouts

27 $40

Desal Distr. Pipeline and Adams Turnouts

8 $2

Talbert Seawater Barrier 15 -

Desal Distr. Pipe - $33

Contingency (30%) - $21

TOTAL 50 $97

24-inch Desal Producer Distribution Pipe via Adams

Page 14: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

14

Desal Option 3

42-inch Desal Distribution Pipe

42-inch Desal Producer Distribution Pipe via WOCWBF

36-inch OC-44 Pipe Improvements

36-inch South County Desal

Distribution Pipe HB Desal Facility

Facility Flow (MGD)

Capital Cost ($M)

Burris Outlet - $1

Desal Producer Dist. Pipeline and WOCWBF Turnouts

25 $40

Talbert Seawater Barrier 15 -

Desal Distr. Pipeline - $33

Improvements to OC-44 - $12

South County Desal Pipeline 10 $39

Contingency (30%) - $36

TOTAL 50 $161

Page 15: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

15

42-inch Desal Distribution Pipe

48-inch Desal Producer Distribution Pipe via

WOCWBF

Desal Option 4

36-inch OC-44 Pipe Improvements

Facility Flow (MGD)

Capital Cost ($M)

Burris Outlet - $1

Desal Producer Dist. Pipeline and WOCWBF Turnouts

29 $44

Desal Distr. Pipeline - $27

Improvements to OC-44 w/Turnouts 21 $12

Contingency (30%) - $23

TOTAL 50 $107

Page 16: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Preliminary Permitting Assessment

16

Permit Desal Option

1A 1B 1C 1D 2A 2B 3 4

CRWQCB – 401 Water Quality x x x x x

Dept. of Fish and Game – 1602 Streambed Alteration x x x x x

US Army Corps – 404 Permit x x x x x

County of Orange – Encroachment Permit x

Storm Water and City Encroachment Permits will apply to all Options.

Page 17: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Selling Poseidon Water To Local Groundwater Producers

• Generally less expensive option - Requires less infrastructure • Poseidon water integration / chemistry concerns • Need to formally approach agencies to determine interest

– Sell water at MWD rate – SWRCB recent actions will limit purchase amounts – Draft agreement

• Requires City Council approval • Option 2B, 3, and 4 requires West O.C. Water Board approval

17

Page 18: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Recharging Poseidon Water Into the Groundwater Basin

• Institutionally easier approach • Less parties involved - OCWD is the only customer • Could require more extensive CEQA/EIR • Constructing new injection wells can be riskier and take

longer • Raises the Basin Production Percentage • All Producers theoretically benefit

18

Page 19: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Recharging Poseidon Water • Increases the BPP by approximately 12-13% • Future BPP percentage could be in the 90’s • Automatically adds approximately $80/af to the

project’s unit cost – well extraction cost • Not aware of anyone recharging ocean desalinated

water into a groundwater basin • Total future OCWD recharge into the groundwater

basin could exceed 400,000 afy 19

Page 20: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Future Possible Basin Recharge Sources (afy)

20

357,000 Total Water Demands

84% BPP

AFY

#1 No

Poseidon

Page 21: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Future Possible Basin Recharge Sources (afy)

21

410,000 Total Water Demands

97% BPP

AFY

#2 With

Poseidon

Page 22: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Future Possible Basin Recharge Sources (afy)

22

383,000 Total Water Demands

90% BPP

AFY

#3 No

GWRSFE

Page 23: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Future Possible Basin Recharge Sources (afy)

23

345,000 Total Water Demands

81% BPP

AFY

#4 No MWD Untreated

Page 24: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin

– 366,000 afy of groundwater pumping - BPP was set at 80.2% – 8 of 19 Producers achieved the BPP

• Producers will have to construct additional wells, pipelines & pump stations

• Each Producers water distribution system is unique with different capabilities

• Some Producers will likely not be able to achieve the higher BPP • Producers with BEA waived water quality projects pumping above

the BPP (IRWD & MCWD) may not recover their capital investment 24

Page 25: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Estimated Financial Impacts

25

Page 26: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Financial Impacts • Slightly more complicated when recharging Poseidon Water

vs original Poseidon proposal • Eight different options • RA and BPP are increasing • OCWD is taking on long-term debt

– Need to maintain minimum 2.0 debt coverage ratio • OCWD operating budget increases

– Need to increase operating reserves • Requires different financial metric to evaluate the distribution

options and their total impact to the Producers water supply cost

26

Page 27: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Producers Variable Water Supply Cost

Component Amount Replenishment Assessment $322/af Well Pumping Cost $80/af Treated Imported Water (Includes $80/af for RTS and CC)

$1022/af

Basin Production Percentage 75% Water Supply Cost Total $557/af

27

Page 28: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Summary of Options Option # 1A 1B 1C 1D 2A 2B 3 4

Capital Cost $305 M $316 M $325 M $160 M $131 M $97 M $161 M $107 M

Annual O&M $5 M $5 M $4 M $2.7M $3 M $2.5 M $2.5 M $2.5 M

Unit Cost $469/af $482/af $475/af $247/af $217/af $166/af $245/af $179/af

RA Increase $248/af $252/af $253/af $191/af $171/af $110/af $135/af $85/af

BPP Increase 12% 12% 12% 12% 10% 4% 4% N/A

Producers Increase

$141/af $144/af $145/af $91/af $82/af $64/af $83/af $64/af

Monthly Water Bill

$6.30 $6.50 $6.50 $4.00 $3.70 $3.00 $3.70 $3.00

28

New Recharge GWRSFE WOCWB

OCWD Recharges All Poseidon Water Combination Original

Page 29: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Receiving Outside Grant Funding

• For every $10 million in grant funding received – Lowers project unit cost by ~ $12/af – Lowers impact to OCWD RA by ~ $4/af – Lowers impact to Producers water supply cost by ~

$3/af

29

Page 30: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Final Water Purchase Agreement Negotiation

Coastal Commission

Study Distribution

Options

Poseidon Financial

Close

Prepare CEQA

OCWD Board Action for consideration – “Go No-Go” decision 1. Water Purchase

Agreement 2. Other Possible

Agreements 3. CEQA

Possible Producer Agreements

Possible Distribution Agreements

Preliminary Design

May/June 2016 OCWD Board Action for consideration 1. Select Distribution Option 2. Initiate Prelim. Design 3. Initiate CEQA 4. Initiate Final Poseidon

Negotiations

X

Poseidon Schedule Overview

MWD LRP

Prop $ & State Loans

X

9-12 Month Process

30

Page 31: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Going Forward • Receive Board comments and questions • Receive public comments • Receive Producer comments – February 10th

Producers meeting • Schedule second workshop • Work towards deciding optimum distribution plan by

May/June.

31

Page 32: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

End of Presentation

32

Page 33: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Additional Project Information

33

Page 34: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Term Sheet

34

Page 35: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Term Sheet Details

• Poseidon owns, permits, designs, finances, constructs and operates the desalination treatment plant

• OCWD would purchase the plant water • OCWD owns, permits, designs, finances, constructs and

operates the necessary distribution facilities to transmit the water to the end users

• OCWD would find end users for water and/or use water to recharge the groundwater basin

35

Page 36: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

OCWD Payments to Poseidon Resources

Years OCWD Payment to Poseidon

1 - 10 MWD rate plus a premium of up to 20% of the MWD rate

11-20 MWD rate plus a premium of up to 15% of the MWD rate

21-30 MWD rate plus a premium of up to 10% of the MWD rate

31-40 MWD rate plus a premium of up to 5% of the MWD rate

41-50 MWD rate plus a premium of up to 0% of the MWD rate

36

• Initial ten year premium amounts to be negotiated based upon Poseidon’s actual and expected cost and an agreed upon return on investment

• In later years of contract the premium amount may be less than zero • Poseidon will be guaranteed a minimum annual escalation rate to be negotiated which is shown at 3% in

the Term Sheet • Beginning in year 15 and every 5 years thereafter the premium will be reviewed and lowered if Poseidon is

receiving an economic return above an agreed upon amount

Page 37: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Term Sheet Details

• MWD LRP subsidy must be obtained • OCWD can take possession of the treatment plant at the end

of the contract for $1 • Poseidon would provide water at an agreed to quality • The Term Sheet is not definitive • Does not legally commit either party to any future actions. • Practically commits the District to fully consider the project and

work towards developing a Water Purchase Contract

37

Page 38: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

City of Huntington Beach at a 75% BPP (afy)

Previous Typical SWRCB Reduction Total Water Demands 33,000 24,800

BPP 70% 75% Groundwater 23,100 18,600 MWD Water 9,900 6,200

38

Page 39: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

GWRS Final Expansion

39

Facility Flow (MGD)

Capital Cost ($M)

Talbert Seawater Barrier

15 -

Mid-Basin & Centennial Park Injection Wells

8 $25

Burris Basin Outlet 7 $1

Burris Booster Pump Station to Recharge Basins

100 $25

Contingency (30%) - $19

TOTAL 130 $70

Page 40: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

40

West Orange County Water Board Pipelines

(HB, West., GG, SB)

Feeder #1 Feeder #2

Page 41: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Water Supply Reliability Policy

• May 2013 • District policy to consider and develop a

variety of local water resources to ensure sufficient water supplies are always available to the residents and business within OCWD

41

Page 42: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Basin Production Percentage Goal

• January 2013 • District goal to achieve and sustain a 75% Basin

Production Percentage • If additional economical projects and programs can

be implemented that support a Basin Production Percentage above 75%, the District will undertake such projects and programs.

42

Page 43: Distribution of Ocean Desalinated Water...Higher BPP Issues • FY 2007-08 maximum pumping year from the GW Basin – 366,000 afy of groundwater pumping - BPP was set at 80.2% –

Long-Term Facilities Plan

• November 2014 • Identified 17 “Focused Study Projects” projects • District staff to “prioritize” these 17 projects for

evaluation • LTFP Water Supply Projects

– GWRS Final Expansion – GWRS Urban runoff diversion to Plant 1 – Poseidon – SARI flow treatment at Ball Road Basin – Purchase upper watershed wastewater – Recovery of evapotranspiration at Prado Basin

43