  • Directional Drilling

    And Surveying

  • What is Directional Drilling?

    Directional Drilling is the process of directing a well bore along some trajectory to a predetermined target.

    Basically it refers to drilling in a non-vertical direction. Even vertical hole sometimes require directional drilling techniques.

    Examples: Slanted holes, high angle holes (far from vertical), Extended Reach Holes, and Horizontal holes.

  • North

    Direction Angle

    Direction Plane X

    Inclination AngleZ Axis (True Vertical

    Depth)Inclina

    tion

    Plane Y

    , or I

    , or A

    Non-Vertical Wellbore

  • Figure 8.2 - Plan view of a typical oil and gas structure under a lake showing how directional wells could be used to develop it. Best locations? Drill from lake?

    Lease Boundary

    Surface Location for Well No. 1

    Bottom Hole Location for Well 2

    Surface Location for Well No. 2

    Houses

    Oil-Water Contact

  • Figure 8.3 - Typical offshore development platform with directional wells.

    NOTE: All the wells are directional

    Top View

    5 - 50 wells per platform

  • Figure 8.4 - Developing a field under a city using directionally drilled wells.

    Drilling Rig Inside Building

  • Fig. 8.5 - Drilling of directional wells where the reservoir is beneath a major surface obstruction.

    Why not drill from

    top of mountain

    ?

    Maximum lateraldisplacement

  • Figure 8.6 -Sidetracking

    around a fish.

    Sidetracked Hole Around Fish

    Fish Lost in Hole and Unable to Recover

    Cement Plug

  • Figure 8.7 -Using an old

    well to explore for new oil by sidetracking

    out of the casing and

    drilling directionally.

    Possible New Oil

    Sidetracked Out of Casing

    Oil Producing Well Ready to Abandon

    Old Oil Reservoir

  • Figure 8.8 - Major types of wellbore trajectories.

    Build and Hold Type

    Continuous Build

    Build-hold Drop and/or Hold (Modified S Type)

    Build-hold and Drop (S Type)

    Horizontal Departure to Target

    Type I

    Type III

    Type II

  • Build Section

    Build Radius:

    BUR*,

    =00018r1

    Figure 8.10 -Geometry of the

    build section.

  • Build Section:

    ==

    deg rad

    180*

    100Lr 1

    1

    11

    BUR*,

    =00018r1 BUR = build rate in deg/100 ft

    Length of arc, L = r11Vertical depth = CD = r1 sin 1Horiz. Depart. = DD = r1 (1-cos 1 )

  • Build-hold-and drop for the case where:42131 xrr and xr
  • Build-hold-and drop for the case where:

    Kickoff

    End of Build

    Maximum Inclination Angle

    Drop Off

    Target

    42131 xrr and xr >+