directional drilling
DESCRIPTION
Directional DrillingTRANSCRIPT
-
Directional Drilling
And Surveying
-
What is Directional Drilling?
Directional Drilling is the process of directing a well bore along some trajectory to a predetermined target.
Basically it refers to drilling in a non-vertical direction. Even vertical hole sometimes require directional drilling techniques.
Examples: Slanted holes, high angle holes (far from vertical), Extended Reach Holes, and Horizontal holes.
-
North
Direction Angle
Direction Plane X
Inclination AngleZ Axis (True Vertical
Depth)Inclina
tion
Plane Y
, or I
, or A
Non-Vertical Wellbore
-
Figure 8.2 - Plan view of a typical oil and gas structure under a lake showing how directional wells could be used to develop it. Best locations? Drill from lake?
Lease Boundary
Surface Location for Well No. 1
Bottom Hole Location for Well 2
Surface Location for Well No. 2
Houses
Oil-Water Contact
-
Figure 8.3 - Typical offshore development platform with directional wells.
NOTE: All the wells are directional
Top View
5 - 50 wells per platform
-
Figure 8.4 - Developing a field under a city using directionally drilled wells.
Drilling Rig Inside Building
-
Fig. 8.5 - Drilling of directional wells where the reservoir is beneath a major surface obstruction.
Why not drill from
top of mountain
?
Maximum lateraldisplacement
-
Figure 8.6 -Sidetracking
around a fish.
Sidetracked Hole Around Fish
Fish Lost in Hole and Unable to Recover
Cement Plug
-
Figure 8.7 -Using an old
well to explore for new oil by sidetracking
out of the casing and
drilling directionally.
Possible New Oil
Sidetracked Out of Casing
Oil Producing Well Ready to Abandon
Old Oil Reservoir
-
Figure 8.8 - Major types of wellbore trajectories.
Build and Hold Type
Continuous Build
Build-hold Drop and/or Hold (Modified S Type)
Build-hold and Drop (S Type)
Horizontal Departure to Target
Type I
Type III
Type II
-
Build Section
Build Radius:
BUR*,
=00018r1
Figure 8.10 -Geometry of the
build section.
-
Build Section:
==
deg rad
180*
100Lr 1
1
11
BUR*,
=00018r1 BUR = build rate in deg/100 ft
Length of arc, L = r11Vertical depth = CD = r1 sin 1Horiz. Depart. = DD = r1 (1-cos 1 )
- Build-hold-and drop for the case where:42131 xrr and xr
-
Build-hold-and drop for the case where:
Kickoff
End of Build
Maximum Inclination Angle
Drop Off
Target
42131 xrr and xr >+