contract change order no. 9 redacted

Upload: l-a-paterson

Post on 07-Aug-2018

226 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/20/2019 Contract Change Order No. 9 Redacted

    1/10

    Citv

    of

    Carmel-bv-the-Sea

    PUBLIC WORKS DEPARTMENT

    POST OFFICE BOX CC, CARMEL-BY-THE-SEA, CA 93921

    (831) 620-2070

    CONTRACT CHANGE ORDER NO. 9

    CONTRACT AWARDED

    BY

    City Council DATE OF AWARD

    Apr

    7, 2015

    ~ P ~ R ~ O ~ J ~ E ~ C ~ T ~ ~ F ~ o ~ r e ~ s ~ t ~ T ~ h ~ e ~ a ~ t e ~ r ~ R ~ e ~ n ~ o ~ v ~ a = t i ~ o ~ n _________________________________________

    SHEET

    _____ f _ 1 ~

    PROJECT ID#: 13-70903 Purchase Order#: 76-004428

    TO:

    Otto

    Construction

    Company; 2150 Garden Road, Suite A-1, Monterey, CA 94940 ,CONTRACTOR

    You are hereby requested to make the herein described changes from the plans and specifications or do the

    following described work not included in the plans and specifications on this contract.

    NOTE: THIS CHANGE IS NOT EFFECTIVE UNTIL FULLY EXECUTED.

    Cha

    Description:

    1 CHANGES TO CONTRACT PLANS AND SPECIFICATIONS.

    ' . -

    #14, RFI #34 and PCO #19 (Otto's tracking number). Summary of Work includes remove

    existing corners

    of

    the main stage, partially demo existing stone wall and install new concrete

    sill , new

    framing and new

    T111

    siding to match existing

    Agreed Lump

    Sum

    ..........

    .. ..  

    .  

    ..

    ... .

    ..

    .. ..... .

    ..

    ..... .

    2 CONTRACT PRICE

    Total Increase

    in

    contract price

    3 CONTRACT TIME

    Two additional days

    $

    6,212.  Increase

    Estimated

    Exact

    Sum net change in Contract Price is

    $ 1,462,236.00

    $

    41,487.00

    of the original Contract Price

    3.3%

    $

    1 935.00

    Decrease

    uncrers.iqmld contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is

    1 a o o r o 1 ~ e d that we will provide all equipment, furnish all materials, except

    as

    may otherwise be noted above, and perform all

    services

    l n e t ~ e s < ; a r v

    for the work above specified,

    and

    will accept

    as

    full payment therefore the price shown above.

    Accepted Date

    Signed By:

    f

    he

    con tra}CI

     S

    Submitted By:

    Andy Vanderford

    Project Manager

    Contractor: Otto Construction

    Company

    Title: f t c ~ ~ e e l

    . / '7A - '6( ; ; .&

    l - .

    ,

    v

    $

    $

    6,212.

    0

    6,212.0

    2

    Approved:

    u b l i c

    Works Director

    Rob Mullane

    Date

    k J / ~ / s

    Authorized:

    0

    City Administrator

    Doug Schmitz

    Authorized:

    lEI

    City Council

    Attachments: Contractor Proposal (3 pages total)

    RFP #14

    RFI #34

    Lt

    f ' o 'r

    nr

    Note to Contracts and Budgets Office: Council awarded a 10% construction contingency in the amount of $146,224.

    00

    and the

    cost

    of

    ceo 4

    i.e.

    the

    Terraced Step design at a

    Not

    to Exceed

    amount

    of $45,000.00 (actua l cost@

    21

    ,346.00). Thus $167,570.

    00

    is the

    adjusted

    total

    amount of all change

    orders

    which

    the

    City

    Administrator

    has authority,

    or

    11.46% of the

    Original Contract

    Price.

  • 8/20/2019 Contract Change Order No. 9 Redacted

    2/10

      TT

    I

    Potential Change Order PCO) Cost Breakdown Summary

    Project

    Forest Theater Renovation

    Description o

    Change

    Project

    1 5 3 1 4 1 ~ 0

    Below

    and

    attached

    is pricing for material

    and

    labor to remove existing corners

    of

    the main stage, partial ly demo existing stone wall and install new

    concrete

    sill,

    new

    framing and new T111 siding

    to

    match existing per RFI 34.

    Engineering, permits, unforeseen conditions and GC's are not included.

    CHANGE ESTIMATE ITEM COST M/U% M/U

    TOTAL

    GC DIRECT COSTS

    GC DIRECT LABOR

    $3,919

    GC DIRECT MATERIALS

    $1,010

    GC

    DIRECT EQUIPMENT $588

    GC OTHERI INDIRECTS $47

    GC MARKUP ON DIRECT COST

    GC MARKUP ON DIRECT LABOR

    $3

    ,919 10.

    0% $392

    GC MAR KUP DIRECT MATERIAL

    $1,010 10.

    0%

    101

    GC

    MARKU

    P ON DIRECT EQUIPMENT

    $588

    10.

    0%

    $59

    GC MARKUP ON DIRECT OTHERIINDIRECTS $47 10.0% $5

    GC SUBCONTRACT(S)

    OR

    'OTHERS'

    GC

    FEE ON SUBCONTRACT(S)

    $0 5.0% $0

    ADDITIONAL TI

    ME

    REQUIRED

    2

    DAY(S)

    FOR CONTRACT COMPLETION

    .._ ..A

    COMPLETED BY :

    John Garayalde

    PCO

    :

    Related RFP

    :

    Related BUL :

    Related

    RFI

    19

    14

    N

    /A

    34

    DATE:

    10/06/15

    TOTAL

    L. M 

    &

    E DIRECT COST $5 .564

    TOTAL

    M

    ARKUP

    ON

    DIRECT COST $556

    T

    OTAL

    SUBCONTRACT COST $0

    TOTAL

    GC FEE ON SUBC

    ONTRACT(S)

    $0

    TOTAL

    UNAVOIDABLE DELAY

    COSTS

    $0

    TOTAL

    CONSTR

    UC

    T

    ION COSTS $6,120

    BOND AND NSU

    RANCE

    1 1/2%) $92

    TOTAL

    COST OF CHANGE ORDER $6,212

  • 8/20/2019 Contract Change Order No. 9 Redacted

    3/10

    OTTO

    l I

    ~

    Otto Const ruction

    21

    50

    Garden Road, Su i

    te

    A-1

    Mon te

    rey, CA 93940

    T

    EL 831

    .657.9805 FAX 831.657.9820

    License #178809

    OTTO ESTIM  TE SUMM RY SHEET

    ID

    Be

    lo

    w and

    at t

    ached is pricing for material and labor to remove

    ex

    isting corners

    of

    t he main stage,

    partiall

    y

    demo

    existing stone

    wall and

    inst

    all

    new

    co

    ncrete s

    il l

    ,

    new framing and new T111 siding

    to

    match exi sting per RFI 4.

    Engineering,

    penn

    i

    ts

    and unforeseen conditions are

    not

    inc

    lud

    ed.

    Description

    Hrs

    Rate

    Labor

    1 See Attached Estimate Breakdown

    3.919

    2 0

    4

    0

    5 0

    6

    0

    7 0

    8 0

    9 0

    10 0

    11 0

    12 0

    13 0

    14 0

    15

    0

    16 0

    17

    0

    18 0

    19 0

    20

    0

    21

    0

    22

    0

    23 0

    24

    0

    25 0

    26

    0

    27

    0

    28

    0

    29 0

    30 0

    31 0

    32 0

    33 0

    34 0

    Totals

    0.0 3,919

    CHEC

    K L,M,E,S :

    5,564

    Notes:

    Job

    No.: 15-3

    141

    -

    00

    Project: Forest Theater Renova tion

    PCO# 19

    Date· 10/6/2015

    Mat

    Equip

    Sub/Mise

    TOTAL

    1

    010

    588 47 5,564

    -

     

    -

     

    -

    -

    -

    -

    -

    -

    -

     

    -

     

    -

    -

    -

     

    -

    -

    -

    -

    -

    -

     

    -

     

    -

    -

    1,010 588

    47

    5,

    564

  • 8/20/2019 Contract Change Order No. 9 Redacted

    4/10

      TT

    ••m

    0 U : ( t · P ~ oa

    14

    82)

    c;z Dlmo

    Maunry

    w,u,.,

    - . ~

    l\1(1 F

    I ' '

    11 ' "> tr o

    I, .. , Y

    'J   . . • . J e C O .

    b : . X I I .

    v•'

    D M ' I t l ~ r l f y Y t ; a : l r v

    1 : .. -

    :•

    J

    ·,

    r \ • . r ; r . . l •w•

    :>erroF)ccu :r c l l

    N

    C.:-'1 ' V ' · : : I U EJ;to. 1(

    t

    •:nr.o.o.-•-

    rr ..

    ' -J

    .,..., G"

    . : .

    ~ s c

    : , ,

    t i   l.S

    .

      f-J

    LF I

    ,

    '

    - .t.

    '

    H.l

    .t.C

    •:(,:)

    .,4 ' ( ~

    H( ) l D . ~ - "

    ;' 11 CF

    · ~ o

    • •••

    :

    , _ ' ~ 8 1

    ,:,

    ·.v

  • 8/20/2019 Contract Change Order No. 9 Redacted

    5/10

    D TE :

    REQUEST FOR PROPOSAL

    City ofCarmel by the Sea

    PUBLIC WORKS DEPARTMENT

    POST OFFICE BOX CC

    CARMEL-BY-THE-SEA, CA 93921

    (831) 620-2070 OFFICE

    August6,2015 14

    ROPOSAL

    PROJECT

    10

    .

    13-70904

    CONTRACT: Forest Theater Renovation

    TO :

    John Garayalde

    Otto Construction

    2150 Garden Road, Suite A 1

    Monterey, CA 94940

    SUBJECT

    escription

    of

    Proposed hanges

    FROM: Andy Vanderford

    City of Carmel-by-the-Sea

    Reference RFI 34 Response attached, sketch CA-27

    This request for proposal is neither a change in the subject Contract, nor an order to the Contractor to

    perform any work. However, it pertains to certain proposed modifications to the work covered by said

    contract. The provisions, drawings and specifications

    of

    said Contract and previous modifications thereto

    will apply, as applicable, unless specifica lly indicated otherwise herein.

    The City of Carmel-by-the-Sea hereby requests that the Contractor submit within

    ten

    (10) working days

    after receipt

    of

    this request a proposal to make the changes described herein. All changes to the Contract

    Price and Contract Time should be detailed for each separate item listed. Detail

    ed

    breakdown must include

    deductive or added cost for all labor, equipment, materials and all applicable mark-up

    s.

    Nothing written in this Request for Proposal will obligate the City of Carmel-by-the-Sea to incur any costs nor

    change the Contract Time unless such changes are included in

    an

    approved Contract Change Order.

    Signed

    Enclosure:

    Distribution:

    ndy

    Vanderford

    RFI 34 Response

    CAW

    Joe Headley, Building Official

    Matt Wetmore, Otto

    Oscar Cisneros, Otto

    Yuri Rodriguez, Otto

  • 8/20/2019 Contract Change Order No. 9 Redacted

    6/10

    OTTO

    ONSTRU TION

    2150 GARDEN ROAD, SUI

    TE

    A-1

    MONTEREY,

    CA

    93940

    Ph: 831 657-9805

    To:

    Andrew Vanderford

    CITY OF CARMEL BY THE SEA

    P.O. Box CC

    Carmel

    By

    the Sea, CA 93921

    Ph: 831-620-2078

    R I

    I

    RFI : 4

    Date: 7/15/2015

    Job:

    15-3141-00 FOREST THEATER RENOVATIONS

    Phone:

    831

    )620-2078

    cc:

    Jilian Cadouri Cody Anderson Wasney), Monique Vllood Cody Anderson Wasney), Oscar Cisneros Otto Construction),

    John Garayalde Otto Construction)

    Subject: Added existing Stage Corners

    Drawing:

    Spec Section:

    Cost

    Impact:

    Yes

    Schedule Impact: TBD

    Request: Date Required:

    Located at the corners

    of

    the stage, it looks like these sections

    of

    the stage were added after. Currently the wood DF) is dry rotting

    at certain locations. Contractor would like to remove the existing framing, and reframe with pressure

    tr

    eated material. In addition, we

    would like to close up thi s area with T-111 siding.

    Please confirm if acceptable.

    Requested by: Yuri Rodriguez

    OTTO CONSTRUCTION

    Response:

    Remove existing corners of stage that were a later addition. Partially demo stone wall and install new

    concrete sill, new frammg, and new T1-11 siding to match existing. Footprint of new stage corners to

    match existing. See attached CA-27 for details.

    REVIEWE

    By

    Andy

    Vanderford

    at

    10:

    33

    am

    Aug 6

      2015

    J. Cadouri

    Answered by

    CAW Architects

    8/6/15

    Company

    Date

    Page 1 of 1

  • 8/20/2019 Contract Change Order No. 9 Redacted

    7/10

    I

    I

    I

    I

    I

    I

    I

    I

    I

    I

    I

    I

    I

    I

    I

    New pressure

    t r e t e d

    sill nd

    x4

    §

    lfl

    g

    l l

  • 8/20/2019 Contract Change Order No. 9 Redacted

    8/10

  • 8/20/2019 Contract Change Order No. 9 Redacted

    9/10

  • 8/20/2019 Contract Change Order No. 9 Redacted

    10/10

    D

    r- EJ--- 

    - - - - - -

    DEMO (E) PLYWOCD/

    F R A ~ I N G

    ADDED

    STAGE

    C O R ~ E R S

    REMOVE DEBR

    IS F R O ~

    GROUND @STAGE

    CORNERS

    TO G

    BELOW

    (E) T1-11 S IDING EACH SIDE

    - - - - - - - -DEMO

    STO: :EI Ct- ;.J

    W ALL TO STAGE EDGE

    EACH S .DE

    ) - - - - - - ~ : : : - CONC. S l:...... $ STAGE

    FRAMING

    TO 1'- ATCH (E)

    FOOTPRI

    NT.

    -CONCRETE

    S i;..L TO BE 12

    WIDE $

    18 M.N

    D

    EE

    P

    -S:LL

    BO:..TS

    TO

    BE 5

    /8

    D A

    48

    O.C. MAX SPAC

    i

    f'...G, OR

    2M

    'N

    PER s

    -

    2XG PTDF

    L

    EDGER

    ATTACHED TO THE (E) STAGE

    FRAM IN G wr-rH t- ' f ,.; (2 ) - ·;-..·

    D IA S IMPSON SDS

    SCREWS

    SPACED AT

    'G

     

    O.C.,

    :---

    ,

     -.;

    SCREW

    PENETRAT,ON INTO

    (E)

    STAGE FI.;G TO

    TH E STUDS

    AT 6 O.C.

    ECGES

    $ JOiNTS, 12 O.C.

    AWAY

    FROM

    JO: . TS Af'...? EDGES

    ADDED EXISTING STAGE CORNERS

    SCA;..E: 3 /32  =

    1-0

     

    ARCH ITE CTS

    C o d y A n d e r s o n W a s n e y A r c h

    i t

    e c

    t

    s, I n c.

    455 L

    a m

    b

    e r

    t A

    v e n u e •

    P

    a

    I

    o

    A I t

    o,

    CA 94306

    650.328.1818·

    Fax

    3 2 8 . 1888

    Copyright © 2010 by CODY AN

    DER

    S

    ON

    WASNEY ARCHITECTS, INC.

    FOREST THEATER

    Pro)ecrNam

    e· ·-- ------------ ----------------------------------------- -

    --------------

    ----- --

    14017

    A2 3

    Projeci'NLirii6er ·

    --

    ·

    --

    ·--

    --

    · --· Refei-iiric·e·sflee

    8 /4 /2015

    CA 27

    ate

    ---- ·-- ··· ··--··--···---------- ---·--···-----·--·----·--·----·--···-- ·-- ·

    Slieef

    NLimoe