commissioning geothermal systems - bcxa · commissioning geothermal systems. learning objectives 1....

46
Kenneth Von Bank, PE, CCP Mechanical Engineer Sustainable Engineering Group LLC Commissioning Geothermal Systems

Upload: others

Post on 10-Mar-2020

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Kenneth Von Bank, PE, CCPMechanical EngineerSustainable Engineering Group LLC

Commissioning Geothermal Systems

Page 2: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Learning Objectives

1. Gain a better understanding of the challenges of geothermal

system design, installation, and operation.

2. Demonstrate the ability to incorporate the knowledge of

geothermal systems into all phases of the commissioning

process.

AIA Quality Assurance

Page 3: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Assumptions

•Geothermal system has been shown to

be the “best fit” for the project through a

Life Cycle Cost Analysis or similar

•Geothermal feasibility study has been

performed

Page 4: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Energy From the Earth/Sun

•Earth = solar battery

•Absorbs nearly half

of the sun’s energy.

•The ground stays a

relatively constant

temperature

•Warm heat source in

winter

•Cool heat sink in

summer

Page 5: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

The earth is like a solar battery absorbing nearly half of the sun’s energy.

The ground stays a relatively constant temperature through the seasons,

providing a warm source in winter & a cool heat sink in summer.

4% absorbed

by clouds.

17% reflected

by clouds.

6% reflected

by surface.

19% absorbed by

water vapor, dust

46% absorbed by

the ground

Outer SpaceOuter SpaceOuter SpaceOuter Space

AtmosphereAtmosphereAtmosphereAtmosphere

EarthEarthEarthEarth

100%100%100%100%

Nearly ½ of the

sun’s energy is

absorbed by earth

5

Page 6: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Ground-Source Heat Pumps

GSHP

• A term applied to a variety of system

components that use the ground,

groundwater, or surface water as a heat

source and sink.

Also Known As:

• Ground-Coupled Heat Pumps (GCHP)

• Ground-Water Heat Pumps (GWHP)

• Surface Water Heat Pumps (SWHP)

• Direct Expansion (DX) GCHP

Page 7: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Ground Coupled Heat Pumps (GCHP)

Closed-loop ground-source

heat pumps

• Reversible vapor

compression cycle

• Closed ground loop heat

exchanger

• Water or Water/antifreeze

solution

Most common type ����

Water-to-air heat pump

Page 8: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Focus on Geothermal Field:

•Once the system is buried, it should remain

buried for 50+ years.

•Repairing geothermal systems is difficult and

costly after the system has been backfilled.

•Proper design, installation, and Cx will

minimize the chances that the buried system

will need repairs.

Page 9: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

GCHP Further Subdivided

Type of ground heat exchanger design

•Vertical vs. Horizontal

•Hybrid System

Page 10: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Advantages of Vertical GCHP

• Requires relatively small plots

• Soil varies very little in temperature and thermal properties

• Requires smallest amount of pipe and pumping energy

• Can yield the most efficient GCHP system performance

Page 11: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Disadvantages of Vertical GCHP

Higher cost because

of equipment needed

to drill borehole

• Drill Rig

• Grout

• Grout Mixer

Limited experienced

contractors

Page 12: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Horizontal GCHP

Advantages

• Less Expensive than vertical GCHP

• Residential applications have

adequate ground area

• More trained

equipment operators

Disadvantages

• Larger Ground area requirement

• Greater adverse variations in

performance

○ Ground Temperatures

○ Rainfall

○ Burial Depth

• Higher Pumping-

Energy Requirements

• Lower System

Efficiencies

Page 13: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Commissioning Phases

•Planning

•Design

•Construction

•Occupancy/Operations

Page 14: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Commissioning Phases

Part 1: Planning Phase

Page 15: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Planning Phase

•Approval from DNR or other governing body

or Authority Having Jurisdiction (AHJ)

•Formation & Thermal Conductivity (TC) Test to

determine ground properties

Page 16: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Field Tests

•Drill to desired depth

•Use same pipe

diameter and grout

•Wait 5 days

•Insulate entire device

•Minimum test length

= 48 hours

Page 17: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Thermal Conductivity Test

Advantages

• Accurate borefield size

• Indicates level of effort required to insert loop

• Type of drilling

• Reduce Contractor’s uncertainty

• May reduce bid price

• Can use test bore in design

Disadvantage

• Initial cost

• Results can be inaccurate

Page 18: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

F&TC Test Report

• Copy of Drill Log

• Ground Thermal Conductivity (Btu/h·ft·°F)

• Ground Thermal Diffusivity (ft2/day)

•Undisturbed Ground Temperature (°F)

•Depth to Water Table

Page 19: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Water Problems

Page 20: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Commissioning Phases

Part 2: Design Phase

Page 21: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Design Review: What to Look For…

• Qualifications: Geothermal contractor

certified by IGSHPA

• As-built drawings of geo field required

(including GPS coordinates)

• F&TC Test results

• Contractor to integrate test bore into the

geothermal field

Page 22: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Design Review: What to Look For…

• Pipe and fittings shall be HDPE classified for geothermal installation (IGSHPA)

• 50 year warranty provided by pipe manufacturer

• Heat transfer fluid must be approved by DNR or State Regulatory Agency

• Locating Wire and Warning Tape

• Thermal Grout: TC of at least 1.0 Btu/hr-ft-F (obtain samples for testing)

Page 23: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Thermally Enhanced Grout

80

90

100

110

120

130

Bores

0.45 0.6 0.85 1 1.2

Grout Conductivity (Btu/h·ft·°F)

200-Ton, 300' deep Vertical System

Page 24: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Design Review: What to Look For…

Header Pit Vault• HDPE classified for geothermal installations

• Factory pressure tested – no leaks at 1 psi air test for at least 30 minutes

• Entry to vault – minimum 28” diameter, neoprene gasket on lid, traffic rated frame and cover if located in traffic area.

• Ladder – Conform to current OSHA guidelines

• Anti-buoyancy calculations – amount of concrete needed to anchor vault

• Valves: Isolation valve on supply line of each circuit. Balancing valve on return line of each circuit.

• P/T port on each supply and return main and all circuit pipes

Page 25: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Vault Installation

Page 26: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Header Pit Vault

•Circuits routed to

underground vault

o Typically 3” Dia Circuits

o Balancing Valves

•Only two pipes go back

to building

•Concrete vs HDPE

o Concrete cheaper

o HDPE water tight

Page 27: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Design Review: What to Look For…

•Pressure Testing

•Flushing and Purging

•Grouting

•Backfilling

Page 28: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Design Review: What to Look For…

Borefield Design

• Minimum bore spacing

• Bore depth

• Reverse Return piping configuration

• Minimum burial depth of lateral pipes (based on frost layer depth)

Page 29: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Frost Layer

Page 30: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Example: 100 Bore System

Page 31: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Circuit

Below Grade in Sand Bedding

Reverse Return – Balanced Flow

Page 32: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Commissioning Phases

Part 3: Construction Phase

Page 33: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Construction Verification

Before Excavation Begins

• Contractor Qualifications

• Shop drawings must be approved prior to ordering materials or starting work

• Site Erosion Control Plan in place

• DNR and/or State Regulatory Agency approval

Timing is critical

Page 34: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Construction Verification

During Excavation / Drilling / Pipe Installation• Bore spacing / depth

• Materials on site: pipes, grout, backfill materials, vault, etc.

• Lateral pipe (trench) depth – below frost line

• Grouting Procedure

○ Must grout within 24 hours of drilling. No more than four un-grouted boreholes at any one time.

○ Test grout mixture samples early.

• Seal open ends of pipes to prevent entry of contaminants

Timing of verification is critical

Page 35: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Open Pipe Ends

Page 36: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Construction Verification

Prior to Backfilling• Pressure Testing successful and witnessed

○ Test with water, NOT air

• Flushing and Purging successful and witnessed

○ At least 2 ft/sec to remove air and debris

• Bedding material (sand) is free of rocks, clay, and sharp objects

• Locating wire installed on pipes

• Location of bores and pipes have been surveyed – as-built drawings are accurate

Did I mention that timing of verification is critical?

Page 37: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Unapproved Pipe Bedding

Page 38: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Construction Verification

During Backfilling

• No backfilling in freezing weather or with frozen materials

• Warning tape installed approximately 36” above pipes

Page 39: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Commissioning Phases

Part 4: Occupancy/Operations Phase

Page 40: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

System Maintenance

•Borefield is essentially maintenance-free

•Verify glycol concentration

•Verify system pressure

•Check fluid temperatures – range of 30F to 100F is normal

•Annual check of vault interior (if applicable)

Page 41: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Cooling & Heating EWT - Efficiency

0

1

2

3

4

5

6

20 30 40 50 60 70 80 90 100

Entering Water Temp (°F)

COP_

0

5

10

15

20

25

EER_

Page 42: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

EER & COP

EER = Energy Efficiency Ratio

• Cooling Mode

• Typical Range 18-27 EER

COP = Coefficient of Performance

• Heating Mode

• Typical range 2.8-4.0 COP

)(

)/(

WInputElectrical

hrBtuOutputCoolingEER =

)/(

)/(

hrBtuInputElectrical

hrBtuOutputHeatingCOP =

Page 43: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Resources

1. Kavanaugh, S.P., K. Rafferty. 1997. Ground-Source Heat Pumps: Design of Geothermal Systems for Commercial and Institutional Buildings, ASHRAE.

2. 2007 ASHRAE Handbook-HVAC Applications, Chap. 32.

3. 2008 ASHRAE Handbook-HVAC System & Equipment, Chap. 48.

4. 1988. Closed-Loop Ground-Source Heat Pump Systems: Installation Guide, Oklahoma State University & International Ground Source Heat Pump Association.

5. Wisconsin Department of Natural Resources. http://dnr.wi.gov

6. U.S. Department of Energy, EERE Program. http://www.eere.energy.gov

Page 44: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

Questions?

Page 45: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

AIA Quality Assurance

Portland Energy Conservation, Inc is a registered provider with The

American Institute of Architects Continuing Education Systems. Credit

earned on completion of this program will be reported to CES Records

for AIA members. Certificates of Completion for non-AIA members are

available on request.

This program is registered with the AIA/CES for continuing

professional education. As such, it does not include content that may

be deemed or construed to be an approval or endorsement by the AIA

of any material of construction or any method or manner of handling,

using, distributing, or dealing in any material or product. Questions

related to specific materials, methods, and services will be addressed

at the conclusion of this presentation.

Page 46: Commissioning Geothermal Systems - BCxA · Commissioning Geothermal Systems. Learning Objectives 1. Gain a better understanding of the challenges of geothermal ... • As-built drawings

THANK YOU

Kenneth Von Bank, PE, CCP