Page 1: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

Existing Building Commissioning

Tom Poeling, P.E., CEM, CCP2019 BCxA President

U.S. Engineering Company

Director of Quality Assurance

[email protected]

Seminar 33: The Value of Building Commissioning Study

Page 2: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

• Present the results of a joint BCxA/LBNL study that provides updated metrics on the value of (EBCx) commissioning.

• Provide data that can be used by commissioning stakeholders to promote the industry.

• Understand market opportunities to improve the commissioning industry.

• Understand Cx scope of work improvements to improve delivery process.

Learning Objectives

Page 3: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

Funding by U.S. Department of Energy grant.Lawrence Berkeley National Laboratory:Dr. Jessica Granderson, Eliot Crowe, Claire Curtin, Dr. Evan Mills

Building Commissioning Association (Staff):Liz Fischer, Diana Bjornskov, Sheri Adams, Nicole Gardner, Aimee Brown

BCxA Task Force:David Lewis, Matt Malinosky, Rock Ridolfi, Louis Starr, Ben Hixson, Frank Carleo, Colin Moar, Philip Sauod, Jack Schirpke, Richard Young

BCxA Marketing Committee:Candice Rogers, Tony DiLeonardo, Alyssen Nassif, Dan Forino

Acknowledgements

Page 4: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

4

Prior LBNL Studies – Cost Effectiveness of Commercial Building Commissioning

(2004)

(2009)

Page 5: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

• Refresh the LBNL 2009 survey • Maintain consistency in the dataset• Reflect changes to the industry due to maturity• Define effects of changes to Cx approach (such as Ongoing Cx)• Include economics for Cx of new and additional systems• Expand database for different building types, markets

• Establish new baseline for Cx metrics

• Identify appropriate level of data to gather

• Create an iterative process for data gathering

• Engage industry to provide more feedback over time on project level and market level trends

5

Value of Commissioning Study - Goals

Page 6: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

6

Value of Commissioning Study

Data Survey (NCCx, EBCx, OCx)

• Project Specific Description• Reason for Cx• Deficiencies & Measures

• Cx Cost Data• Scope of Cx• Baseline Energy Use &

Savings

• Non-Energy Impacts

Market Survey • Company information• Certification• NCCx Market Factors• NCCx SOW Tasks• EBCx Market Factors• EBCx Economics• EBCx SOW Tasks• OCx Economics• OCx SOW Tasks

Page 7: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

7

Value of Cx Study - Phases

LBNL

BCxAReview Market Survey

Research Market Databases

Created Market SurveyPL

ANN

ING

Provide Data Survey

Coordinated scope/grant with DOE

Reviewed Data Survey

DAT

AAC

QU

ISIT

ION

ANAL

YSIS

"Gimme Five" CampaignBCxA MembersUtility Providers

Data Survey Form sent toUtility Providers

Market Survey sent toBCxA Members

Organize/QC Data Survey

Create Data Graphs

Create Preliminary Presentation

Create Deliverables, Presentations

Page 8: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

8

Data Survey StatisticsNew Construction Cx 2009 Study 2018 Study

# of Buildings 82 101# of Projects (w/cost data) 74 71Floor Area (SF) 8,813,925 22,217,059Construction Cost $2.2B $10.1B# of States Represented 10 18

Existing Building Cx 2009 Study 2018 Study

# of Buildings (total) 562 738# of Projects (w/energysavings data)

300 705

Floor Area (SF) 90,410,884 252,159,847# of States Represented 21 18

Page 9: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

Discussion Topics

9

• Building data: Preliminary narratives regarding CxValue metrics

1. EBCx – Cost Summary2. EBCx – Market Demand Factors 3. EBCx – Scope of Work Observations

• Review Data Survey Results• What’s Changed? • Check Calibration• Market Drivers & Issues

Page 10: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

EBCx Cost per Square Foot

N = MedianUtility_1 414 $0.17

Non-Utility 36 $0.24Utility_2 156 $0.42

Utility_MBCx 54 $1.61

$0.26 Median overall

Page 11: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

EBCx Cost per Square Foot (Bldg. Size)

$0.26 Median overall

Page 12: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

Median nUtility_1 5% 326Utility_2 7% 156

Utility_MBCx 9% 41Other_EBCx 14% 107

EBCx Percent Savings by Project Type

• Median energy savings = 6%• Utility typical range = 3 to 11%• 2018 median less than 2009

savings of 10%

n=533

n=107

n=41Median 6% (all data)

Page 13: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

EBCx Percent Savings by Project Type

8.5%

22.0%

46.3%

22.0%

1.2%

Less than 5% 5 to 10% 10 to 20% 20% to 30% More than 30%0%

5%

10%

15%

20%

25%

30%

35%

40%

45%

50%

Median energy savings = 12%

Page 14: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

-

5

10

15

20

25

30

35

Sim

ple

Payb

ack

(Yre

ars)

(n=300 bldgs.)

EBCx Simple Payback (Years)

2.2

1.1

201825th Percentile 1.3

Median 2.275th Percentile 4.2

Page 15: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

EBCx Implementation by Payback

• 2 year payback or less: Implemented 55%• 3 to 4 year payback: 34%• 5 year payback or greater: 18%

0%5%

10%15%20%25%30%35%40%45%

less than 10% 10 - 20% 20 - 40 % 40 - 60% 60 - 80% Greater than80%

2 years or less payback 3 to 4 years payback 5 year payback

Page 16: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

Reasons for Implementing EBCx

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Other

Reduce liability

Research/demonstration/pilot

Comply with existing buildings ordinance

Increase occupant productivity

Extended equipment life

Comply with organizational mandate/policy

Comply with LEED or other rating system

Participation in utility program

Train/increase awareness of operators or occupants

Qualify for rebate, financing, or other services

Ensure adequate indoor air quality

Ensure or improve thermal comfort

Ensure system performance

Obtain energy savings

Fraction of reporting projects with reason (EBCx), 2009 vs. 2018

2009 2018

Page 17: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Other

Reduce liability

Research/demonstration/pilot

Comply with existing buildings ordinance

Increase occupant productivity

Extended equipment life

Comply with organizational mandate/policy

Comply with LEED or other rating system

Participation in utility program

Train/increase awareness of operators or occupants

Qualify for rebate, financing, or other services

Ensure adequate indoor air quality

Ensure or improve thermal comfort

Ensure system performance

Obtain energy savings

Fraction of reporting projects with reason (EBCx), 2009 vs. 2018

2009 2018

Reasons for Implementing EBCx

Page 18: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

Were Cost and Energy Savings calculations included with EBCx?

Never Rarely Sometimes Often Always0%

5%

10%

15%

20%

25%

30%

35%61%

Page 19: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

Significant repairs before EBCx?

Never Rarely Sometimes Often Always0%

5%

10%

15%

20%

25%

30%

35%

40%

45%

45%87%

Page 20: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

How often is TAB included?

Never Rarely Sometimes Often Always0%

5%

10%

15%

20%

25%

30%

35%

40%

75%

36%

Page 21: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

Level of TAB investigation

Central plant only AHUs only Central plant and AHUs Including someterminal unitequipment

Including all terminalunit equipment

0%

5%

10%

15%

20%

25%

30%

35%

40%

45%

53%

Page 22: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

35.1%

16.4%

19.6%

11.9%

13.1%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

Cont

ribut

ion

to O

vera

ll Pr

ogra

m S

avin

gs (%

)

Utility Program EBCx Measure Types (n = 3,695 measures, 503 projects)

Loop Tuning

Calibration

Maintenance - Other

Mechanical Fix

Modify Sequence of Operations

Modify Setpoint

Implement Advanced Reset

Operations & Control - Other

Scheduling

EBCx Measure Mix

Page 23: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

How were EBCx issues addressed?

In-housePersonnel

MechanicalContractor

ElectricalContractor

ControlsContractor

CommissioningProvider

0

0.5

1

1.5

2

2.5

3

3.5

4

4.5

Page 24: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

Visit the following website:

https://www.bcxa.org/knowledge-center/value-of-cx-project/

For More Information

Page 25: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

1. Energy Savingsa. Median 6%, typical range 3% to 11% (combined utility and non-utility

EBCx programs)b. EBCx outside utility programs could hit 10% to 25% range c. 2018 median down from 2009, though looking at project type suggests no

major market shift

2. Simple Paybacka. Median 2.2 years. Range generally 1 and 4 years paybackb. Median $0.26 project cost per sq.ft., with a typical range $0.15 to $0.56c. Projects at lower percent savings can still be highly cost-effective

3. Owner’s reasons for implementing EBCx: Top 4 are unchanged from 2009 study

4. EBCx Measures: Top 5 measures account for 95% of all measures

Conclusion

Page 26: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

Bibliography

• Poeling T., Bjornskov D., et.al “Value of commissioning – 2018 market survey”, (2019)

• Crowe E., Mills E., Granderson J., Curtin C., “Building Commissioning Costs and Savings Across Two Decades and 1,500 Projects” (2019)

Page 27: Existing Building Commissioning - BCxA · Existing Building Commissioning. Tom Poeling, P.E., CEM, CCP. 2019 BCxA President. U.S. Engineering Company. Director of Quality Assurance

Tom Poeling, P.E., CEM, [email protected]

Questions?