cms tracker infrastructure work in ls1

32
CMS Tracker infrastructure work in LS1 Scope • Planning 2012-2014 • Infrastructure tasks • Implications for funding agencies TK_It 26/03/2012 Ettore Focardi 1

Upload: arsenio-dunn

Post on 31-Dec-2015

52 views

Category:

Documents


0 download

DESCRIPTION

CMS Tracker infrastructure work in LS1. Scope Planning 2012-2014 Infrastructure tasks Implications for funding agencies. Scope of LS1 infrastructure work. Photo: M. Hoch. Main objective: After LS1 the Tracker must run cold. Need -10 0 C on sensors - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: CMS Tracker infrastructure work in LS1

CMS Tracker infrastructure work in LS1

• Scope• Planning 2012-2014• Infrastructure tasks • Implications for funding agencies

TK_It 26/03/2012 Ettore Focardi 1

Page 2: CMS Tracker infrastructure work in LS1

Scope of LS1 infrastructure work

• Main objective: After LS1 the Tracker must run cold.• Need -100 C on sensors• Need -200 C (or -25C, if possible) coolant in Tracker• At present, lowest SST coolant temperature is +4C

• Current obstacles on lowering the temperature:• Humidity levels too high: Dew point ~ 0C in the TK service channels inside YB0• Cooling capacity of the SS and ‘brine’ cooling plants not sufficient (min. -40 C)

• In addition, improvements needed on performance and reliability of many related sub-systems: dry gas, dew point measurements, Pipes insulation, heaters, thermal screens, etc.

• LS1 is the UNIQUE OCCASION to solve these, we need to prepare for it now!

TK_It 26/03/2012 Ettore Focardi 2

Photo: M. Hoch

Page 3: CMS Tracker infrastructure work in LS1

Planning 2012-2014

• LS1 is already this year !

TK_It 26/03/2012 Ettore Focardi 3

Now

LS1 start

LS1 end

2012

2014

2013

• For many of the tasks we need full access to inside YB0, both ends.• We want to work inside YB0 early,

to leave time for testing and possibly needed improvements.

‘Full’ Limited

• Are the currently allocated access times enough? We don’t know yet, need to work out a more detailed planning,

looking to the interconnections between other subdetectors work and services availability

CMS closedMagnet test

• Full proof check when CMS closed and magnet on. • If failing, need a big planning change to re-gain access inside YB0.

Currently planned YB0 accesses: Limited

Page 4: CMS Tracker infrastructure work in LS1

CMS LS1 planning, March 2012 draft

TK_It 26/03/2012 Ettore Focardi 4

Full access to YB0, currently 40 working daysin March-April 2013

Page 5: CMS Tracker infrastructure work in LS1

Plan details

TK_It 26/03/2012 Ettore Focardi 5

Page 6: CMS Tracker infrastructure work in LS1

Infrastructure tasks to be accomplished

• Tasks grouped in following categories:• Vapour barriers and seals• Dry gas• Dew point sensors• Other YB0 activities• C6F14 cooling system

• CO2 cooling system

• Power system• Rack cooling• General services• Other tasks

• Tasks listed in an Excel file, available on “CMS Tracker Engineering and Infrastructure” Sharepoint site: https://espace.cern.ch/cms-tracker-engineering/Shared%20Documents/Forms/AllItems.aspx

TK_It 26/03/2012 Ettore Focardi 6

Page 7: CMS Tracker infrastructure work in LS1

Vapour barriers and seals

TK_It 26/03/2012 Ettore Focardi 7

Continuous vapour barrier up to PP1s or edge of vac-tank

Potting of services

Inner seal between CMS end-cap and TK bulkhead

CMS inflatable seal

Bulkhead cover plates and seals up to beam-pipe

Local sealing

Page 8: CMS Tracker infrastructure work in LS1

Humidity barriers

Ettore Focardi

Photo: M. Hoch

TK_It 26/03/2012

TK service channels

BulkheadPixel volume seals

8

Page 9: CMS Tracker infrastructure work in LS1

TK bulkhead open

TK_It 26/03/2012 Ettore Focardi 9

Page 10: CMS Tracker infrastructure work in LS1

TK bulkhead edge

TK_It 26/03/2012 Ettore Focardi 10

This is ECAL. No vapour barrier on the backside between ECAL and TK services !

Many TK cooling pipes without insulation

Page 11: CMS Tracker infrastructure work in LS1

THIP venue

TK_It 26/03/2012 Ettore Focardi 11

Multiple paths for humidity to reach the TK bulkhead, via HCAL and ECAL volumes

Page 12: CMS Tracker infrastructure work in LS1

Local vapour barrier @ bulkhead

TK_It 26/03/2012 Ettore Focardi 12

Last Section of a PP1-Channel

Region to be “boxed”

A C

B

Pipe insulation ends ~here

Tracker bulk-head

Extra dry gas flow

Page 13: CMS Tracker infrastructure work in LS1

CMS global seals

TK_It 26/03/2012 Ettore Focardi 13

Add here a seal between CMS barrel and endcap?

Page 14: CMS Tracker infrastructure work in LS1

Tasks: Vapour barriers and seals (1/2)

TK_It 26/03/2012 Ettore Focardi 14

2012 2013Tasks / Sub-tasks / Milestones Contact Comments Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb

LS1   Dates still to be confirmed                   16 Nov start of LS1                               All sample materials available Antti Vapor barrier, tapes, foams                          Material safety qualifications ready Antti Fire safety tests not done at CERN!!                          Mock-up tests completed Antti Also to train people                          Define final sealing configuration                              Review of the THIP Karl Decisions on procurements&plans. TC, 

ECAL and HCAL involved.                         

Order all needed materials Antti                            All needed materials available Antti                            Push-tool ready for pixel volume leak test Paolo, Mimmo                            Pixel volume leak-test with push toolIncludes visual inspection of all seals from beam-pipe to TK bulkhead

Paolo, Gino, Mimmo

Immediately after CMS opened and access to TK Bulkhead

                         

Check and seal Pixel and Strip volumes from each other

  After Pixels and Beam-pipe removal                          

Seal the empty Pixel volume with a cap                              

Page 15: CMS Tracker infrastructure work in LS1

Tasks: Vapour barriers and seals (2/2)

TK_It 26/03/2012 Ettore Focardi 15

2013 2014Tasks / Sub-tasks / Milestones Contact Comments Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb

LS1   16 Nov start of LS1Pixel platform in use, until end of 27 Feb 2012   36 days in the current global planning                                

Surkov frame in use   When can we install this?                                Restricted access, to one end at a time   As of 24 April 2012                                Install local sealing at the Bulkhead perimetry   See Karl's proposal for starts.

What can be done from the Pixel platform?Add extra gas injection + sensors, and measure.Install final humidity sensors, before 'boxing'.

                               

Install sealing below and inbetween all TK, EB and HB service channels, at the TK PP1 level.

  Can this be started while we have the Pixel platform?

                               

Open PP1 boxes and 'inject sealing' to the exit side service channel.

  Can this be started while we have the Pixel platform?

                               

Open EB/HB channels and 'inject sealing' at the PP1 level / vactank end?

  What can be done? Armaflex, potting?                                

Install global sealing from Bulkhead to PP1 level.   Where to start? Try to measure the dew point evolution?

                               

Measure humidity levels   Permanently during all work                                

Humidity performance measurement, with cooling on.

  Can we have the cooling on at this time!?

                               

Improve sealing, during limited access period                                    

Provide access for HB electronics, through global sealing

  Later in LS1                                

Redo global sealing at HB electronics   Later in LS1                                Sealing after Beam-pipe and Pixel installation                                    

Re-measure humidity levels   After CMS closed                                Design and implement dry gas injection and exhaust to Pixel volume

Pixel team

During Pixel stay in the upstairs Cold Room.

                               

Page 16: CMS Tracker infrastructure work in LS1

N2 & Compressed air network @ P5Update on March 19th, 2012 (Paola)

Summary of existing systems for air and N2

3 Compressed air production sites/circuits- SU5: “Soufflettes” – in good conditions, being used also for Tk brine cabinet flushing in CV room (a better solution should be investigated)- SL5: “Haute Pression” – used for moving wheels, CMS responsibility- SH5: “Instrument air” + Tk cooling units, etc.– most critical circuit, 180

Nm3/h available

2 liquid N2 dewar systems- 1 “Big” for magnet cryo + detector flushing, max gas flow 60 Nm3/h- 1 “Small” for DT and piloting of gas circuit valves

TK_It 26/03/201216Ettore Focardi

Page 17: CMS Tracker infrastructure work in LS1

USERS OF N2 and DRY AIR @ P51) UGX55 quick connectors2) EN/CV valves in CV zone3) Tk I/P cabinets

(top of by-pass)4) Ecal I/P cabinets (top of by-

pass)5) Drier A (gas room)6) Drier B (gas room)7) Switch-over panel N2/dry air

for detector flushing (gas room)8) Tk & ES cooling cabinets9) Detector flushing10) Beam pipe vacuum system

shut-off valves (+many “piquages” in UXC)

11) Cryo valves (magnet area)

Present layout of Nitrogen (gas) and dry air at P5

TK_It 26/03/2012 Ettore Focardi17

Cryo cold box

N2 dewar62 Nm3/h gas when no LN2 is used

SH5 compressors dry air supply105 Nm3/h average180 Nm3/h peak

GN2 back-up line

9Detectorflushing

62 Nm3/h GN2 for detector flushing

LN2 line

1

2

3 4

567

88

11

10

Page 18: CMS Tracker infrastructure work in LS1

Present issues and outlook

• The instrument dry air is used both for detector flushing (when no N2 is available/can be used), cooling box flushing, valve piloting

• The total dry air flow available is NOT enough for all applications (see tables)

• In addition, no precise instrumentation and recording of consumptions!

• N2 cannot be used both for detector flushing and magnet cool down neither for nominal consumptions nor future guess consumption

• In the tables: the total amount of dry air and N2 consumptions as of today and the nominal/foreseen consumption for the future:N.B. Yellow values are guess numbers! HUGE MARGIN SHALL BE FORESEEN AT LEAST TILL THE END OF LS1

TK_It 26/03/2012 Ettore Focardi 18

Page 19: CMS Tracker infrastructure work in LS1

Detector flushing during LS1: needs and proposal

- During LS1, sealing works will be executed at the level of the Tk bulkhead and will need to be validated

- Validation of such works implies operation of the TK cooling systems at low T while CMS is still in open configuration

- In this scenario, only dry air can be used for flushing, and not N2- Only a tentative guess can be made on the needed air flow for this exercise

(at least 50 Nm3/h for Tk bulkhead, at least 60 Nm3/h for cooling plants….but it could be much more)

Present dry air system gives max 180 Nm3/h. Estimated needs for LS1- About 70 Nm3/h for valve operation- At least 60 Nm3/h for cooling plant flushing- At least 130 Nm3/h for detector flushing

Market Survey from A. Gaddi: plant exists that can provide both dry air or N2 do exist on the market, typical size could be 400 Nm3/h N2 or 700 Nm3/h dry airMore details in the following

TK_It 26/03/2012Ettore Focardi 19

Page 20: CMS Tracker infrastructure work in LS1

USERS OF N2 and DRY AIR @ P51) UGX55 quick connectors2) EN/CV valves in CV zone3) Tk I/P cabinets

(top of by-pass)4) Ecal I/P cabinets (top of by-

pass)5) Drier A (gas room)6) Drier B (gas room)7) Switch-over panel N2/dry air

for detector flushing (gas room)8) Tk & ES cooling cabinets9) Detector flushing10) Beam pipe vacuum system

shut-off valves (+many “piquages” in UXC)

11) Cryo valves (magnet area)

Proposal for new layout of Nitrogen (gas) and dry air at P5

TK_It 26/03/2012 Ettore Focardi20

Cryo cold box

N2 dewar62 Nm3/h gas when no LN2 is used

SH5 compressors dry air supply105 Nm3/h average180 Nm3/h peak

GN2 back-up line

9Detectorflushing

62 Nm3/h GN2 back-up for detector flushing

LN2 line

1

2

3 4

567

88

11

10

SH5 NEW dry air/N2 supply700/400 Nm3/h

RED DASHED: NEW CONNECTION x CABINET FLUSHING

Page 21: CMS Tracker infrastructure work in LS1

Tentative planning

Summer 2012: Order launched for new plant in SH5Nov-Dec 2012: installation and commissioning of new N2/dry air plantAp 2013: Tk sealing and cooling work completedMay-Jun 2013: Humidity tests of new sealing, using dry air, assessment of total quantity neededJan 2014: New beam pipe & Pix inside CMSFeb 2014: CMS closed, Tk cold and ON as soon as possible for tests of humidity and operation in cold - at this stage N2 source is needed!!! Rental of dewar seems a good optionLater in 2014: commissioning of N2 plant, switch from rental dewar to plantTK_It 26/03/2012 Ettore Focardi

21

Now

LS1 start

LS1 end

2012

2014

2013

Install new dryer/N2 plant

Rented N2 dewar operational

N2 plant operational

Buy newplant

Page 22: CMS Tracker infrastructure work in LS1

Dew point sensors, not an easy installation job!

TK_It 26/03/2012 Ettore Focardi22

Page 23: CMS Tracker infrastructure work in LS1

Dew point sensors2012 2013

Tasks / Sub-tasks / Milestones Contact Comments Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar AprLS1                                    Sensors stand for FOS, XENTAUR, 

HS2000, Arduino,Sniffer                             

Install test sensors in Cooling station

      in DCS

                         

Qualify sensors           get experience, exchange sensor arrays?

               

Define final config for LS1   Need to know number of sensors                              Define cable routing                                  Procure more sensors if needed   if add sensors needed                              Procure connectors, cabling and piping

                                 

Calibrate sensors    if add sensors needed                              Connections ready at balconies   cables incl. length to VACTANK 

ready and connected to readout systems. Use a Technical stop to go through cavern seal?

                             

Array of local 'test' sensors ready    for first "test sector sealing"                              Temporary routing to VACTANK/BH

  as soon as we have access                     plus minus     

Sensor installation    according to final config                         plus minus Final routing of services   if YB1 & YB2 will be opened at all                              Decide if/which 'test' sensors will remain in VACTANK

                                 

FOS Salvatore/PaoloXENTAUR Andromachi/PGVSniffer system Andromachi/Roberto/LalithHS2000 Andromachi/PGVArduino 'test' sensors Francesco

TK_It 26/03/2012 Ettore Focardi23

Page 24: CMS Tracker infrastructure work in LS1

Other tasks in YB0Tasks / Sub-tasks / Milestones Contact Comments

Design and construct missing tooling / platforms

  2nd bulkhead bridge platform (Paolo)

Leak checks    Checking of broken parts    Thermal testing / improvements of YB0 cooling bundles?

  1 bundle tested to -20C. Can anything more be done now?

     PS sensing lines Anne-Marie Requires access to pp1 (BH)Problematic control rings Anne-Marie Requires access to pp1 (BH), detail; list 

will come     Commission cable channel heaters Andromachi/PGV Test heating, with sensors in-situThermal Screen faulty heating panel Andromachi/PGV This is a must. Need access to BH.Commission Thermal screen for cold operation

  The heating side is weak.

     Leak search and repair Fabrizio Raffaelli R&D on possible solutions on leaks 

inside TK volume. Ideal solution is access from balcony.

Check leak situation in BH area   SniffCooling Pipes insulation check Nicola

TK_It 26/03/2012 Ettore Focardi24

Page 25: CMS Tracker infrastructure work in LS1

Tracker Cooling Pipes Check-out

TK_It 26/03/2012 25Ettore Focardi

As mentioned before, LS1 goal is o Operate the whole tracker system (SS, Pixel and TS) at

« nominal » coolant temperature. From radiation damage point of view, it seems that it would be

beneficial to reach beyond -200 C (perhaps -250 C) and every further degree we can go to it would improve detector lifetime, but is possible?

Assuming we have no limits coming from the « brine » and cooling plants, what is the lowest coolant temperature we can safely achieve without condensating between cooling plants and PP1s(*) ?

In 2007, during the pipe installation campaign, some pipes of a sector were tested with -200 C coolant and measured T to be roughly at +13 0 C on the outside of the insulation layers, which is the guaranteed max. dew point value in the cavern.

(*) Here it is assumed that the heating cables/foils system between PP1 and the detector will give us quite a bit of margin and will not be the limiting factor. Is this true ?

Page 26: CMS Tracker infrastructure work in LS1

Tracker Cooling Pipes Check-out

TK_It 26/03/2012 26Ettore Focardi

• After some discussion (last week) it seems agreed to monitor T in all routes from PP1 to ~PP2

• It will be probably useful to test during LS1 at least the sector -6 route ( biggest

bundle of pipes, ~80) by using the Pixel pipes, bypassed at PP0

• Test bench with pipes, insulations, vapour barriers can be prepared and results compared with calculations.

Page 27: CMS Tracker infrastructure work in LS1

-2,-3

-16,-17,-18

-13,-14,-15

Muon Sector (black)PP1 (red)

-11,-12SS2

SS1PixelTS1,TS2

-4,-5,-6,-7,-8,-9

TK_It 26/03/2012 Ettore Focardi 27

-Z end

Page 28: CMS Tracker infrastructure work in LS1

Cooling systems

• C6F14 cooling system performance increase• Absolutely needed• Full performance necessary in 2014 when TK commissioned for cold operation.• Partial availability needed also in 2013 to check humidity sealing quality.

• CO2 cooling system (Pixel Ph1 upgrade)• Must progress also, and profit from unique access during LS1.• Prepare as much as possible the field for a much shorter access during a later

YETS;plant location and pipes/services installation

TK_It 26/03/2012 Ettore Focardi 28

Page 29: CMS Tracker infrastructure work in LS1

Other tasks

• TK power systems maintenance and replacements Possible replacement of mainframes and Branch controllers (2014)

• Rack cooling improvements• DAQ PC replacements

During 2013• Test Module Thermal behavior (186)

• 2012• Others … ?

TK_It 26/03/2012 Ettore Focardi 29

Page 30: CMS Tracker infrastructure work in LS1

Summary

• A very long list of tasks to be accomplished• Lots of careful engineering work to be done within the next few months,

followed by procurements:• Increased dry air supplies (compressors, driers, pipework components)• Materials for humidity barriers and sealing• Dew point sensors, including their calibration• C6F14 cooling system improvements (SS and brine plant heat-exchangers,

pumps, valves, plant door replacements, etc.)• ...

TK_It 26/03/2012 Ettore Focardi 30

Now

LS1 start

LS1 end

2012

2014

2013

Engineering, design

Procurements

Page 31: CMS Tracker infrastructure work in LS1

Implications for funding agencies

• Substantial investments to equipment (dry gas supplies, cooling system, sensors), but seems under control as reserves and provisions have been made (TFB)

• The bottle-neck is our very limited availability of suitable manpower to cover the complete list of tasks.Leads right now to tasks being left not covered, or with slow progress.• Engineering / Design• Procurements• Developments, testing

• The current big risk is that we will be late with the needed preparations before LS1 starts --- in 8 months ! This includes the summer vacation period...

• We pursue the planning work to more detail level, and are looking for persons to take responsibilities of specific tasks.TK_It 26/03/2012 Ettore Focardi31

Page 32: CMS Tracker infrastructure work in LS1

Impact on INFN

Tracker plan to face the manpower needs for the foreseen actions in LS1:• create ~6 teams of 3-4 people to act possibly in parallel

Cern plans to use 7-10 people

USA plans to use 3-5 people

INFN target 3-5 people

Others: 3-5 people

Possibility of technical positions (6-12 months) for young engineers/physicists Starting from 2012.Let me know eventual availability of people….

TK_It 26/03/2012 Ettore Focardi32