cms si tracker project - us cms meeting at riverside – may 19, 2001 1 us cms tracker outer barrel...

25
CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina) Kansas State University US CMS Silicon Tracker Project

Upload: philip-clark

Post on 14-Jan-2016

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1

US CMS Tracker Outer Barrel (TOB) Silicon Project

US CMS Tracker Outer Barrel (TOB) Silicon Project

Tim Bolton

(for Regina Demina)

Kansas State University

US CMS Silicon Tracker Project

Page 2: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 2

The PlanThe Plan

Scope has increased:• Build ~6000 modules (all of the TOB modules)

• Place them in ~700 Rods

• Fly them to CERN and install & test them

• Build the TIB cylinders and ship them to Pisa

• Help install and commission the tracker

• Beyond construction project:• Help maintain and operate the tracker

• Analyze data

• R&D for future tracker upgrades/replacements

Page 3: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 3

CMS tracker layoutCMS tracker layout

Outer barrel

Page 4: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 4

Outer Barrel Space FrameOuter Barrel Space Frame

Page 5: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 5

Outer Barrel RodsOuter Barrel Rods

Page 6: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 6

Rod installationRod installation

Page 7: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 7

Outer barrel geometryOuter barrel geometry

ModuleWidth, cm 11.8Length,cm 21# sensors 2Strip pitch, mm 140/210Thickness, mm >400# of APV25chips 6|4

layer # r, cm pitch, mm # sides # of mod/side1 75 140/210 2 6442 85 140 1 7283 95 140/210 2 8124 105 140 1 8965 115 140 1 952

total number of modules 5488

Rods# of modules 6

Outer Barrelrmin, cm 75rmax, cm 115length, cm 273

Page 8: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 8

September ReviewSeptember Review

Project files• Resource loaded schedule

• WBS dictionary

• Cost estimates

• Basis for estimate of each task

• Contingency analysis

• Institutional responsibilities

• Task managers

PMG review Sep.14-15 (M. Crisler/chair)• Recommendations received

• Responses returned Nov. 1, 2000

PAC review Nov. 4, 2000

Approved by Director Nov. 13, 2000

Page 9: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 9

Institution Interface to Institutional Responsibilities L3 ManagerFermilab L. Spiegel Assem bly infras tructure L. Spiegel

Module assem bly L. Spiegel

Docum entation & database L. Spiegel

Tes t equipm ent setup & m aintenance S. Tkaczyk

Inner barrel cylinders D. Glenzinski

Rod assem bly B. Flaugher

Test boxes & wirebond fixtures des ign B. Flaugher

Shipping & receiving Technician TBD

UCSB J.Incandela Module repairs at UCSB C. Cam pagnari

Ins tallation & com m iss ioning at CERN J. Incandela

Dum m y rods des ign J. Incandela

Dum m y rods fabrication C. Cam pagnari

Kansas State R. Demina Probing at KSU R. Dem ina

Wirebonding & s im ple repairs at FNAL W. Kahl

Storage boxes R. Dem ina

UIC C. Gerber Burn-in of m odules at FNAL C. Gerber

Module quality tes ting C. Gerber

Testing boxes fabrication C. Gerber

Rochester P. Tipton Burn-in cooling and interlocks P. Tipton

Module inspection at FNAL Post-Doc TBD

Transport boxes des ign & fabrication P. Tipton

Kansas A. Bean Hybrid and m odule tes ting at FNAL M. Bailey

Test equipm ent & ins trum entation A. Bean

Northwestern D. Buchholz QA/QC at NU D. Buchholz

Organization in US CMSOrganization in US CMS

Page 10: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 10

Physicist ManpowerPhysicist Manpower

US CMS Sillicon Tracker Total Physicists

0

200

400

600

800

1000

1200

1400

Q1'01

Q2'01

Q3'01

Q4'01

Q1'02

Q2'02

Q3'02

Q4'02

Q1'03

Q2'03

Q3'03

Q4'03

Q1'04

Q2'04

Q3'04

Q4'04

Q1'05

Q2'05

Q3'05

Q4'05

% F

TE

Available

Scheduled

Page 11: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 11

Schedule IssuesSchedule Issues

Schedule slips• Hybrids & Frames are delayed

• FEDs for testing of large quantities of FE hybrids and modules are expected to be ready in Summer of 2002

• Optical hybrids for assembly of modules into Rods will be available starting Summer 2002

Other critical items are performing better• Gantries

• PC based test stands

• Probe stations

• Sensors

Page 12: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 12

US Gantry PreparationsUS Gantry Preparations

1st Gantry at FNAL• Delivery was

delayed 2 months.

• Expect to have it operational this month or next.

Page 13: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 13

Other US ActivitiesOther US Activities

Probe station at KSU is ready to go• Waiting for first silicon which will arrive here soon

Mock-up frames for training gantries• Last minute request to our group to make these

• We completed 80 frames in early March

Page 14: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 14

Tracker I&CTracker I&C

Tracker Outer Barrel (TOB)~3.5 Million channels

Run 2 CDF and D0 combined

CERN and USA only• USA has to contribute heavily

• Final testing and repair of Rods at CERN

• Installation of Rods in the TOB support frame

• Testing of Rods in place

• System Ops: • Software development,

determination operational settings, calibration methods, database management, data quality assurance…

CDF and D0 Experience• A direct scaling implies

many tens of physicists required for I&C and M&O.

• E.g. Continuous monitoring and analysis of data to catch and correct operational problems will require a lot of manpower

Mitigating considerations• TOB has relatively few

module types and only 2 hybrid types.

• We expect there to be a remote control room and ready access to data in the USA.

Page 15: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 15

PlanningPlanning

•Components Schedules & Updated Milestones• Now know the sensor deliveries from tender• Other tenders will occur this year for hybrids and frames• Update milestones when all vendor schedules are known

• Plan is to have updated milestones in October 2001

Page 16: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 16

US PlansUS Plans

• Preparations• First gantry

• Complete installation this spring• Some Module assembly this summer• Study wirebonding with mechanical prototypes

• Resolve fixturing and module handling issues

• Prototype working modules by this Fall

• Install second gantry this Autumn• Test stands

• Obtain a pc-based test station this Summer for testing modules made here.

• Prepare a preliminary burn-in station

• Full production• Will not start until we see steady parts flow• Need to prepare final burn-in and test facility• Probable start of ramp-up is Spring/Summer 2002

Page 17: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 17

Capacity fall-back planCapacity fall-back plan

Capacity Issues• Run2b

• Large overlap at SiDet appears unavoidable

• Contingency production line at UCSB• Planning a 3rd gantry to do assembly, also wirebonding

and testing of ~2000 modules at UCSB • Additional needs: 1 gantry, 1 high-speed wirebonder

• Purchase via startup funds and exchanges with CMS

• Probably no use of contingency required

• Gain additional experienced manpower• 2-3 Faculty

• 2-3 silicon and 1 electronics engineers

• Senior researcher

Page 18: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 18

Summary & ConclusionsSummary & Conclusions

• Scope has increased

• Some components are delayed• New schedule and milestones this October

• Currently estimate 6-8 month delay for start-up of full production

• Expect significant overlap with Run 2b

• 3rd US gantry production line at UCSB • ~30% of modules, relieve strain at SiDet, help make up

lost time if necessary

• No production until component deliveries reach a steady, sustainable rate.

Page 19: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 19

Back up slidesBack up slides

Page 20: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 20

Costs (FY00$)Costs (FY00$)

8 US CMS Silicon Tracker Project $3,429,715 8.1 Components $60,000 $6,0008.2 Equipment, Design, & Machining $1,600,528 8.2.1 Machine parts $310,100 $99,232 32%8.2.2 Mechanical Assembly Equipment $268,281 $95,243 36%8.2.3 Wirebonding Machinery $341,260 $45,240 13%8.2.4 Burn-in Cooling system with interlocks $133,812 $57,539 43%8.2.5 Boxes $217,204 $83,661 39%8.2.6 Instrumentation $329,871 $216,077 66%8.3 Sensor Probing $68,880 $38,573 56%8.4 Modules $1,059,312 8.4.1 Preproduction of 80 modules $69,184 $38,743 56%8.4.2 Assembly of 600 modules: ramp-up $152,495 $85,397 56%8.4.3 Assembly of 6000 modules $837,632 $469,074 56%8.5 Transportation $160,000 $100,600 63%8.6 Installation and Commissioning at CERN $303,300 $133,452 44%8.7 TIB Support Structures $108,096 $57,654 53%

Totals $3,360,115 $1,526,485 45%

520k$ of manpower at FNAL is covered by the original barter agreement between FNAL and Int’l CMS

Page 21: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 21

Schedule at ReviewSchedule at Review

Main Production Period:

~ 8 months of explicit float

Page 22: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 22

Scheduled & Performed Work, Actual Work CostsScheduled & Performed

Work, Actual Work Costs

Track Record• Not really meaningful yet

• Short lever arm and recently revised schedule

• Increased manpower allocated to I&C CR: +225,038 FY01$

$0

$100

$200

$300

$400

$500

$600

AY

K$

BCWS (K$)

BCWP (K$)

ACWP (K$)

0.00

0.20

0.40

0.60

0.80

1.00

1.20BCWP/BCWS

ACWP/BCWP

-5.0%

0.0%

5.0%

10.0%

15.0%

20.0%

BCWP/EAC

(EAC-Base)/Base

Page 23: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 23

I&C Manpower EstimatesI&C Manpower Estimates

• TOB Assembly period: 1/03 – 7/04

• Two shifts per day and several parallel efforts

• Final test/repair of rods

• Installation/test of rods

• System software development/test

• US Contribution at CERN• 5 FTE Physicists

• 1 Technician (Rod repair - disassembly and reassembly)

** In all cases, resources scheduled for scientists correspond to the incremental cost of residence at CERN (dislocation and travel).

• TOB commissioning: 7/04 – 9/30/05

• 3 shifts per day and several parallel efforts

• Debugging/Optimization

• Online ops, calibration

• Software development for monitoring data quality and catching problems.

• Offline analysis of data

• US contribution at CERN• 7 FTE physicists

• 1 FTE technician

Page 24: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 24

SOW 01 - SiTrkrSOW 01 - SiTrkr

Silicon Tracker SOWs FY01 -- $.8M

University of California-Santa Barbara

Fermilab

University of Illinois-Chicago

University of Kansas

Kansas State University

University of Rochester

Page 25: CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 1 US CMS Tracker Outer Barrel (TOB) Silicon Project Tim Bolton (for Regina Demina)

CMS Si Tracker Project - US CMS Meeting at Riverside – May 19, 2001 25

Current Schedule* Current Schedule*

*This is not official. It is our current conservative best guess.