chapter 7 copyright © 2010 pearson education, inc. publishing as prentice hall 7-1 risk management

18
Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

Upload: everett-floyd

Post on 01-Jan-2016

221 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

Chapter 7

Copyright © 2010 Pearson Education, Inc. Publishing

as Prentice Hall 7-1

Risk Management

Page 2: Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

1- Introduction: Risk

Copyright © 2010 Pearson Education, Inc. Publishing

as Prentice Hall 7-2

Risk management - the art and science of identifying, analyzing, and responding to risk factors throughout the life of a project and in the best interest of its objectives.

Project risk – any possible event that can negatively affect the viability of a project

Page 3: Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

Risk Vs Amount at Stake

Copyright © 2010 Pearson Education, Inc. Publishing

as Prentice Hall 7-3

Phase 1 Conceive

(C)

Phase 2 Develop

(D)

Phase 3 Execute

(E)

Phase 4 Finish

(F)

Time

$ V

alue

Incr

easi

ng R

isk

Total Project Life Cycle

Amount at stake

Plan Produce

Opportunity and riskPeriod of highest

risk impact

Combined risk impact

Page 4: Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

Process of Risk Management

Copyright © 2010 Pearson Education, Inc. Publishing

as Prentice Hall 7-4

What is likely to happen?

What can be done?

What are the warning signs?

What are the likely outcomes?

Risk is based on a simple equation:

Project Risk = (Probability of Event)(Consequences of Event)

Page 5: Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

2- Four Stages of Risk Management

Copyright © 2010 Pearson Education, Inc. Publishing

as Prentice Hall 7-5

1. Risk identification

2. Analysis of probability and consequences

3. Risk mitigation strategies

4. Control and documentation

Page 6: Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

Risk Clusters

Copyright © 2010 Pearson Education, Inc. Publishing

as Prentice Hall 7-6

Risk fall into one or more classifications:

FinancialTechnical

Common Types•Absenteeism•Resignation•Staff pulled away•Time overruns

• Skills unavailable• Ineffective Training• Specs incomplete• Change orders

CommercialExecutionContractual/

Legal

Page 7: Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

Risk Factor Identification

Copyright © 2010 Pearson Education, Inc. Publishing

as Prentice Hall 7-7

Brainstorming meetings: Brainstorming meetings: Bringing the members of the project team, clients

and top management can generate a good list of potential risk factors.

Expert opinionExpert opinion: The more quantifiable method is referred to Delphi

approach. It collects and consolidates the judgments of isolated anonymous

respondents.

Past history: Past history: Experience can be used not only to identify risk factors but

their leading indicators as well.

Multiple (or team based) assessmentsMultiple (or team based) assessments: A team based approach to risk

factor identification encourages identification of a more comprehensive set of

potential project risks.

Page 8: Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

Risk Impact Matrix

Copyright © 2010 Pearson Education, Inc. Publishing

as Prentice Hall 7-8

ConsequencesLi

kelih

ood

Hig

hLo

w

Low High

Page 9: Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

Project Risk Scoring

1. Identify factors and assess the probability (Pf ) and consequences (Cf) of failure

2. Calculate overall probability & consequence

3. Calculate overall risk factor

4c s r p

f

C C C CC

7-9Copyright © 2010 Pearson Education, Inc. Publishing

as Prentice Hall

3m c d

f

P P PP

( )( )f f f fRF P C P C

Page 10: Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

Risk evaluation

7-10Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 11: Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

Risk evaluation

Copyright © 2010 Pearson Education, Inc. Publishing

as Prentice Hall 7-11

Page 12: Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

Copyright © 2010 Pearson Education, Inc. Publishing

as Prentice Hall 7-12

Page 13: Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

Risk Mitigation Strategies

Copyright © 2010 Pearson Education, Inc. Publishing

as Prentice Hall 7-13

Accept Rik: Accept Rik: The decision “ to do nothing” is a reasoned calculation, not the result of inattention or incompetence.

Minimize Risk : Minimize Risk : The risk for Boeing in the event of faulty parts leading to a catastrophic failure are huge.

Share Risk: Share Risk: risk may be allocated proportionally among multiple members of the project.

Transfer risk: Transfer risk: in some circumstances, when it is possible to change the nature of the risk, either through elimination or minimization, it may be possible to shift the risks bound up in a project to another party.

Page 14: Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

Risk Mitigation Strategies

Copyright © 2010 Pearson Education, Inc. Publishing

as Prentice Hall 7-14

Contingency Reserves Contingency Reserves : include managerial or financial methods to mitigate risk.Task contingencyTask contingency: is used to offset budget cutbacks,

schedule overruns, or other unforeseen circumstances occurring to individuals tasks. These budget can be a very valuable form of risk management.

Managerial contingencyManagerial contingency: is budget safety measures that address higher level risks.

Mentoring: Mentoring: junior or inexperienced project personnel are paired with senior managers in order to help them learn best practices.

Cross training: Cross training: it requires that the team members not only learn their own duties but also the roles of others.

Page 15: Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

Control & Documentation

Copyright © 2010 Pearson Education, Inc. Publishing

as Prentice Hall 7-15

Help managers classify and codify risks, responses, and outcomes

Change management report system answers

What? Identify clearly the source of risk.Identify clearly the source of risk.

Who? Assign a project team member direct Assign a project team member direct

responsibility for following the issue and maintaining the responsibility for following the issue and maintaining the

ownership regarding its resolution.ownership regarding its resolution.

When? Establish a clear time frame.Establish a clear time frame.

Why? Pinpoint the most likely reason for the risk.Pinpoint the most likely reason for the risk.

How? Create a detailed plan for how the risk is to be Create a detailed plan for how the risk is to be

abated.abated.

Page 16: Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

Project Risk Analysis & Management

Copyright © 2010 Pearson Education, Inc. Publishing

as Prentice Hall 7-16

Extends risk management over project’s life cycle

Key Features of PRAMRisk management follows a life cycleRisk management strategy changes over

the project life cycleSynthesized, coherent approach

Page 17: Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

Nine Phases of Risk Assessment

Copyright © 2010 Pearson Education, Inc. Publishing

as Prentice Hall 7-17

1.Define2.Focus3. Identify4.Structure5.Clarify ownership of risks6.Estimate7.Evaluate8.Plan9.Manage

Page 18: Chapter 7 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 7-1 Risk Management

Copyright © 2010 Pearson Education, Inc. Publishing

as Prentice Hall 7-18