bh girder presentation in jakarta

34
BH GIRDER TOWOONG E&C

Upload: anton-husen-purboyo

Post on 12-Apr-2015

314 views

Category:

Documents


33 download

DESCRIPTION

BH

TRANSCRIPT

Page 1: BH Girder Presentation in Jakarta

BH GIRDER

TOWOONG E&C

Page 2: BH Girder Presentation in Jakarta

Universities U.C. Davis (USA)

Prof. Jonh Bolander

Yonsei University (Korea)

Prof. Yunmook Lim

Research Institute GS E&C Corporation

Infrastructure Research Team

Towoong E&C

Research Center

Structural Designer

Eurim E&D

Sambo Engineering

Yooshin Corporation

BH GIRDER

Page 3: BH Girder Presentation in Jakarta

BH GIRDER

Page 4: BH Girder Presentation in Jakarta
Page 5: BH Girder Presentation in Jakarta

Bulb-Tee Shape

Pre-Stress Optimization

Intermediate Anchoring Device

Half-Slab

Girder Continuation

BH Girder Outlines

Page 6: BH Girder Presentation in Jakarta

Advanced Bulb-T Shape

Bulb-Tee Shape (PCI) Bulb-Tee Shape (BH Girder) Comparison

PCI BH Girder (47.2m)

Span 47.2 60.0 (47.2)

Spacing 2.40 2.50(2.50)

Upper Flange Width

Lower Flange Width

1.19 2.20(2.20)

0.81 1.40(1.30)

Height 2.362 2.300

(1.900)

Page 7: BH Girder Presentation in Jakarta

Half-Slab

Replacement of Slab Thickness 100mm

Immediately Concrete Placing after Girder Set

Contribute to Girder Stiffness Increasing

Improvement of Workability and Safety

Replace a Form with Half-Slab

Page 8: BH Girder Presentation in Jakarta

Pre-stress Optimization

Straight Tendon Arrangement

Minimize of Friction Loss

Intermediate Tendon Arrangement

Maximization of PS Efficiency

Minimize of Long Term Loss

Page 9: BH Girder Presentation in Jakarta

Simple Continuation

Other Type Continuation Method BH Girder Continuation Method

Existing Continuation Method

Rebar Only or Extra PSC Continuation Method

Rebar Only : Crack Occurrence

Extra PSC : 3Span Over Continuation Impossible

BH Girder’s Continuation Method

Choice of a Simple Method

Need not Considering Girder when Continuation

Beneficial Way for Designing and Construction

For Reduce of Expansion Joint

Page 10: BH Girder Presentation in Jakarta
Page 11: BH Girder Presentation in Jakarta

Finite Element Analysis

End-Section Anchorage Intermediate Anchorage Continuation Part

RM Space RBSN (Rigid Body Spring Network)

Page 12: BH Girder Presentation in Jakarta

Launching Girder

Uijeongbu Light Railway

GS E&C and Towoong E&C’s Achievement

Site : UiJeoungBu Light Railway

Construction Period : 2007.10 ~ 2012.08

Construction Cost : 14,000,000 USD

Construct Bridge by Launching Gantry

Launching Application Analysis for BH Girder

UiJeongBu Light Railway Construction Site

Page 13: BH Girder Presentation in Jakarta
Page 14: BH Girder Presentation in Jakarta

Construction Process

Page 15: BH Girder Presentation in Jakarta
Page 16: BH Girder Presentation in Jakarta

BH Girder and PSC-I Beam(PCI)

PSC-I Beam’s Cross Section (PCI)

BH Girder’s Cross Section

Comparison

PCI-I BH Girder

Span 41.1 41.1

Spacing 2.40 2.50

Upper Flange Width

Lower Flange Width

1.07 2.20

0.71 1.30

Height 1.829 1.500

Page 17: BH Girder Presentation in Jakarta

BH Girder and PSC-I Beam (Beton)

PSC-I Beam’s Cross Section (Beton)

BH Girder’s Cross Section

Comparison

Beton BH Girder

Span 47.0 47.0

Spacing 2.30 2.50

Upper Flange Width

Lower Flange Width

0.80 2.20

0.70 1.30

Height 2.300 1.900

Page 18: BH Girder Presentation in Jakarta

Comparison

U-Girder BH Girder

Span 31.9 31.9

Spacing 2.30 2.50

Upper Flange Width

Lower Flange Width

1.90 2.20

1.30 1.30

Height 1.850 1.400

BH Girder and U-Girder

U-Girder’s Cross Section (Indonesia)

BH Girder’s Cross Section

Page 19: BH Girder Presentation in Jakarta

Comparison

Super-T BH Girder

Span 40.0 40.0

Spacing 2.25 2.50

Upper Flange Width

Lower Flange Width

1.96 2.20

0.70 1.30

Height 1.750 1.500

BH Girder and Super-T Beam

Super-T Beam’s Cross Section

BH Girder’s Cross Section

Page 20: BH Girder Presentation in Jakarta

Rule Out of Form and Supporting post

Conventional Slab Working Method

Threaten the Safety

Safety Working with Half-Slab

Exclude Slab Form Installation Works

Exclude Slab Form Disassemble Works

Exclude Slab Form Supporting works

Prevent Negligent Accidents

Improvement of Workability

Improvement of Safety

Page 21: BH Girder Presentation in Jakarta

Maintain Slab Surface Smoothness

Decked Bulb-T Girder Safety Working with Half-Slab

Full Deck Bulb Tee Beams Half Deck Bulb Tee Beams

Difficult to Compensate for Surface Deviations

Difficult to Girder Setting in Narrow Interval

Remaining Hazards like Overturn

Remaining Risks with Beam Structure Damaging

Available to Compesate for Physical Deviations

Available to Girder Interval

Safe to Overturn

Safe to Beam Structure Damaging

Page 22: BH Girder Presentation in Jakarta

The Lowest Height

Decrease Earthworks Amount than Another PSC Beams

Possible the Securement Space below Girders

Save the Cost of Construction for Earthwork

Keep the Slender Shape

Give the Sense of Openness

Contribution for making a fine view

Earthworks Reduction Amount

BH Girder’s Height PSC Beam(PCI)’s Height

Page 23: BH Girder Presentation in Jakarta

The Longest Length among PSC Beams

Suppose Constructing 240m Bridges… (in South Korea)

Other PSC Beams with 40m

BH Girder with 60m

Decrease the Cost of Making 2 Piers = about 200,000 USD x 2 span = about 400,000 USD

Decrease the Cost of Crane = about 15,000 USD x 2Crane x 2 Span = about 60,000 USD

Decrease the Period of Salvage Work = about 5,000 USD x 10 unit = about 50,000 USD

Total Saving Costs = about 510,000 USD

Page 24: BH Girder Presentation in Jakarta

Reduce Construction Periods

B=24.0m, L=180.0m

PSC-I Beam 30.0m

Pier Construction

390 Days Girder Installation

60EA/4Days

Slab Construction

140 Days

PSC-I Beam 45.0m

Pier Construction

234 Days

Girder Installation

40EA/3Days

Slab Construction

140 Days

BH Girder 60.0m

Pier Construction

156 Days

Girder Installation

30EA/3Days

Slab Construction

52 Days

534 Days

377 Days

211 Days

60% ~44%

Page 25: BH Girder Presentation in Jakarta

Construction Costs Reduction

Decrease of

Earthworks

Decrease of

Piers

Decrease of

Periods

PCI Bulb T Beam’s Height (Length= 47.2m) = 2.362m

BH Girder’s Height (Length = 47.2m) = 1.800m (except Half-Slab)

Reduced Percentage of Earthworks = (0.562/2.362)x100

Earthworks Reduce (compared with PCI Bulb-T)

PSC Beam’s General Longest Length : 40m x 6unit (5 Piers)

BH Girder’s Longest Length = 60m x 4unit (3 Piers)

Reduced Percentage of Pier works = (2/5)x100

Pier Works Reduce (assumption L=240m)

PSC Beam’s Construction Periods = 534 days

BH Girder’s Construction Periods = 211 days

Reduced Percentage of Periods = (323/534)x100

Periods Reduce (assumption B=24m, L=180m)

60.5%

Reduce

23.8% Reduce

40.0%

Reduce

Page 26: BH Girder Presentation in Jakarta

Reduce of CO2 Footprint

PSC 30m

Remicon

BH 60m

Oil

4240

t-CO2

48t-CO2

3072

t-CO2

17t-CO2

B=24.0m, L=180.0m (In South Korea)

1,199 Ton

Page 27: BH Girder Presentation in Jakarta
Page 28: BH Girder Presentation in Jakarta

Design & Construction Applying Results

Design Applying Results

Hwayang – Jeokgeum Expressway

Seoul – Moonsan Expressway

Pyeongtaek East Detour Way

Sejong Special Self-Governing City

Rural Development Administration Relocation

The Second Seoul-Incheon Expressway

Asan Tangjeong District Development

Kimhae Technovalley Development

Oksan – Ochang Expressway

Hwasung Dongtan District Development

Construction Applying Results

Seoul – Moonsan Expressway

Sejong Special Self-Governing City

Rural Development Administration Relocation

Kimhae Technovalley Development

Page 29: BH Girder Presentation in Jakarta

1st Girder Installation

Se-Jong Special Self Governing City

Salvage Working Process

Preparation Girder Loading Transporting

1st Girder Lifting 2nd Girder Lifting

Page 30: BH Girder Presentation in Jakarta

Se-Jong Special Self Governing City

The First BH Girder Pier Height = 27.0m, Span = 57.0m

Page 31: BH Girder Presentation in Jakarta
Page 32: BH Girder Presentation in Jakarta

Coping Rebar Pre-Assembling

Introduction of Technology Concept

Pre-Assembling on the Ground

Weight Lightening of Pre-Assembling Form

Applying of Shape Change Available Form

Process

1. Set and Install Pre-Assembling Forms

2. Pre-Assemble Rebars on the Ground

3. Lift the Pre-Assembled Rebar-Net

4. Insert the Rebar-Net on Coping Form in Advance

Expectation

Reduction of Construction Period : 35% Reduce

Reduction of Construction Cost : 24% Reduce

Minimize of Influence about Traffic Flow

Improvement of Workability and Safety

Page 33: BH Girder Presentation in Jakarta

PSC Trough(Lower Route) Bridge

Introduction of Technology

Available for 45m High-Speed Railway

Producing by Pre-Stressed Beam Method

Possession of Trough(Lower Route) Bridge

Less than 4m of Girder Height (Max. Height)

Available for Double Track Railway

Expectation

Reduction of Construction Period : 20% Reduce

Reduction of Construction Cost : 30% Reduce

Prevent of Noise

Secure Spaces under the Bridge

Train Fall Prevent Effect

Double Track Railway

Single Track Railway

Concept

Page 34: BH Girder Presentation in Jakarta

GS E&C Corporation

Senior Research Engineer

Kim, Do-Hak

[email protected]

Towoong E&C

General Manager

Yoon, Seok-Min

[email protected]