ANALISIS PERBANDINGAN METODE ERECTION GIRDERMENGGUNAKAN CRAWLER CRANE DAN LAUNCHERGIRDER PADA PEMBANGUNAN UNDER BRIDGE STA
03+550 JALAN TOL PANDAAN-MALANG
Skripsi
Diajukan Kepada Universitas Muhammadiyah Malang
Untuk Memenuhi Salah Satu Persyaratan Akademik
Dalam Menyelesaikan Program Sarjana Teknik
Disusun Oleh:
MUHAMMAD FADLY WICAKSONO
2013 1034 0311 213
JURUSAN TEKNIK SIPIL
FAKULTAS TEKNIK
UNIVERSITAS MUHAMMADIYAH MALANG
2018
i
LEMBAR PENGESAHAN
JUDUL : ANALISIS PERBANDINGAN METODE ERECTION GIRDER
MENGGUNAKAN CRAWLER CRANE DAN LAUNCHER
GIRDER PADA PEMBANGUNAN UNDER BRIDGE STA
03+550 JALAN TOL PANDAAN – MALANG
NAMA : MUHAMMAD FADLY WICAKSONO
NIM : 2013103140311213
Pada hari Kamis 25 Januari 2018, telah diuji oleh tim penguji:
1. Ir. Ernawan Setyono, MT Dosen Penguji I ……………………
2. Ir. Erwin Rommel, MT Dosen Penguji II ……………………
Disetujui,
Dosen Pembimbing I Dosen Pembimbing II
(Moh. Abduh, ST., MT) (Rini Pebri Utari, S.Pd ., MT)
Mengetahui,
Ketua Jurusan Teknik Sipil
(Ir. Rofikatul Karimah, MT)
ii
SURAT PERNYATAAN
Yang bertanda tangan di bawah ini:
Nama : MUHAMMAD FADLY WICAKSONO
NIM : 201310340311213
Jurusan : TEKNIK SIPIL
Fakultas : TEKNIK
UNIVERSITAS MUHAMADIYAH MALANG
Dengan ini saya menyatakan sebenar-benarnya bahwa: Tugas Akhir dengan
judul: “Analisis Perbandingan Metode Erection Girder Menggunakan Crawler
Crane dan Launcher Girder pada Pembangunan Under Bridge Sta 03+550 Jalan
Tol Pandaan-Malang”. Adalah hasil karya saya dan bukan karya tulis orang lain.
Dalam naskah tugas akhir ini tidak terdapat karya ilmiah yang pernah diajukan oleh
orang lain untuk memperoleh gelar akademik di suatu Perguruan Tinggi dan tidak
terdapat karya atau pendapat yang pernah ditulis atau diterbitkan oleh orang lain,
baik sebagian maupun seluruhnya, kecuali yang secara tertulis dikutip dalam
naskah ini dan disebutkan dalam sumber kutipan atau daftar pustaka. Demikian
pernyataan ini saya buat dengan sebenarnya dan apabila pernyataan ini tidak benar
saya bersedia mendapat sanksi akademis.
Malang, 25 Januari 2018
Yang menyatakan
Muhammad Fadly Wicaksono
iii
KATA PENGANTAR
Puji syukur penulis panjatkan kepada Allah SWT atas berkat rahmat dan
hidayah yang diberikan sehingga Tugas Akhir dengan judul “Analisis
Perbandingan Metode Erection Girder Menggunakan Crawler Crane dan
Launcher Girder pada Pembangunan Under Bridge Sta 03+550 Jalan Tol
Pandaan-Malang” dapat diselesaikan.
Meskipun dalam penyelesaian Tugas Akhir ini melalui perjalanan waktu
yang panjang serta melibatkan banyak bantuan dari berbagai pihak, penulis
berharap Tugas Akhir ini dapat bermanfaat bagi pembaca.
Pada kesempatan kali ini penulis menyampaikan terima kasih yang sebesar-
besarnya kepada seluruh pihak yang telah membantu dalam menyelesaikan Tugas
Akhir ini. Oleh karenan itu penulis mengucapkan terimakasih kepada:
1. Bapak Dr. Ahmad Mubin, M.T., sebagai Dekan Fakultas Teknik Universitas
Muhammadiyah Malang, yang telah memberikan ijin perencanaan kepada
penulis.
2. Ibu Ir. Rofikatul Karimah, MT., sebagai Ketua Program Studi Teknik Sipil
Universitas Muhammadiyah Malang, yang telah memberikan arahan, petunjuk
dalam penyelesaian skripsi ini.
3. Bapak Moh. Abduh, ST., MT., sebagai pembimbing I dalam penyelesaian
skripsi ini yang telah memberikan bantuan, petunjuk dan arahannya dalam
penuyusunan skripsi ini.
4. Bapak Rini Pebri Utari, SPd ., MT sebagai pembimbing II dalam penyelesaian
skripsi ini yang telah memberikan bantuan, petunjuk dan arahannya dalam
penuyusunan skripsi ini.
5. Seluruh Dosen dan Karyawan Program Studi Teknik Sipil Universitas
Muhammadiyah Malang, yang telah memotivasi penulis, dari awal sampai
selesainya penulisan ini.
6. Rekan-rekan mahasiswa Program Studi Teknik Sipil Universitas
Muhammadiyah Malang, yang telah menyumbangkan tenaga dan pikiran dalam
penyelesaian skripsi ini.
iv
7. Kepada segenap pihak yang tidak dapat penulis sebutkan satu persatu dalam
kesempatan terbatas ini. Mudah-mudahan segala amalan mereka diterima disisi
Allah sebagai manifestasi ibadah kepada-Nya. Amiin.
Akhirnya, penulis menyadari bahwa penulisan skripsi ini masih banyak
kekurangannya. Untuk itulah, kritik yang sifatnya mendidik, dan dukungan yang
membangun, senantiasa penulis terima dengan lapang dada.
Malang, 25 Januari 2018
Muhammad Fadly Wicaksono
v
ANALISIS PERBANDINGAN METODE ERECTION GIRDERMENGGUNAKAN CRAWLER CRANE DAN LAUNCHER GIRDERPADA PEMBANGUNAN UNDER BRIDGE STA 03+550 JALAN TOL
PANDAAN-MALANG
Muhammad Fadly Wicaksono1 , Moh Abduh2, Rini Pebri Utari3,Jurusan Teknik Sipil Fakultas Teknik Universitas Muhammadiyah Malang
Jl. Raya Tlogomas No. 246, Malang (0341) 464318E-mail : [email protected]
ABSTRAK
Penelitian ini bertujuan untuk mengetahui faktor pertimbangan pemilihan metodeerection girder, metode yang efektif untuk pelaksanaan erection girder, faktor yangmempengaruhi proses pelaksanaan erection girder, dan membandingkan metodepelaksanaan erection girder menggunakan crawler crane dan launcher girder. Pertamadilakukan pengumpulan data baik primer maupun sekunder, kemudian dilakukan analisisrencana metode crawler crane dan launcher girder. Pada masing masing metode dilakukananalisis kebutuhan material dan alat, waktu, biaya dan mutu pekerjaan. Selanjutnya hasildari analisis tersebut digunakan untuk menentukan metode yang paling tepat. Berdasarkananalisis yeng telah dilakukan maka dapat disimpulkan faktor yang menjadi pertimbangandigunakannya metode erection girder diantaranya kondisi lapangan, letak lokasi, keadaancuaca, sumber daya manusia, spesifikasi alat dan mobilisasi peralatan. Perbedaan mendasarmetode crawler crane dan launcher girder adalah cara peletakan balok girder pada titiktumpuan. Metode crawler crane memiliki waktu pengerjaan relatif lebih cepat jikadibandingkan dengan metode launcher girder, karena mobilisasi alat dilakukan dalamkondisi terpisah, sedangkan metode launcher girder memiliki keuntungan dari segi biaya,kepresisian alat, dan cara operasi. Dari perhitungan analisis didapat hasil metode yangefektif untuk pekerjaan erection girder pada under bridge sta 03+550 proyek jalan tolpamal seksi 1 menggunakan crawler crane dengan biaya Rp 828.800.000,- dan waktupelaksanaan 25 hari.
Kata Kunci: crawler crane, erection girder, launcher girder
vi
COMPARATIVE ANALYSIS OF GIRDER ERECTION METHOD USINGCRAWLER CRANE AND LAUNCHER GIRDER ON DEVELOPMENT
UNDER BRIDGE STA 03+550 HIGHWAYPANDAAN-MALANG
Muhammad Fadly Wicaksono1 , Moh Abduh2, Rini Pebri Utari3,Department of Civil Engineering Faculty of Engineering University of
Muhammadiyah MalangJl. Raya Tlogomas no. 246, Malang (0341) 464318
E-mail: [email protected]
ABSTRACT
The aim of this research is to know the reason to choose erection girder method, to knoweffective method for erection girder implementation, to know affecting factor of erectiongirder implementation process, and to compare erection girder method implementationusing crawler crane and launcher method. First, the primary and secondary data werecollected, then crawler crane and girder launcher method plan were analyzed. Material,equipment requirements, time, cost and quality of each method were analyzed.Furthermore, the results of the analysis are used to determine the most appropriate method.Based on the analysis that has been done, conclude that the affecting factors of usingerection girder method was field conditions, field location, weather conditions, humanresources, equipment specifications and equipment mobilization. The fundamentaldifference between the crawler crane method and the girder launcher is how to lay thegirder beam at the point of support. The process of crawler crane method has relativelyfaster than girder launcher method, because equipment mobilization was done in separatecondition, while girder launcher method has some advantages in terms of cost, equipmentprecision, and operation mode. From the analytical calculation, it can be found that theeffective method of erection girder method implementation at under bridge Sta 03 + 550tollroad Panddan-Malang project section 1 was using crawler crane with total cost Rp828.800.000,- in 25 days.
Keywords: crawler crane, erection girder, launcher girder
vii
DAFTAR ISI
HALAMAN JUDUL ................................................................................................
LEMBAR PENGESAHAN ................................................................................... i
SURAT PERNYATAAN ..................................................................................... ii
KATA PENGANTAR ......................................................................................... iii
ABSTRAK ..............................................................................................................v
DAFTAR ISI........................................................................................................ vii
DAFTAR TABEL ............................................................................................... xi
DAFTAR GAMBAR .......................................................................................... xii
DAFTAR LAMPIRAN .......................................................................................xv
BAB I PENDAHULUAN.................................................................................1
1.1. Latar Belakang ......................................................................................1
1.2. Rumusan Masalah .................................................................................2
1.3. Tujuan Penelitian...................................................................................3
1.4. Manfaat Penelitian.................................................................................3
1.5. Batasan Masalah....................................................................................3
BAB II LANDASAN TEORI ............................................................................4
2.1. Manajemen Proyek ...............................................................................4
2.1.1. Pengertian Manajemen Proyek..............................................................4
2.1.2. Fungsi Dasar Manajemen Proyek .........................................................5
2.2. Biaya Proyek Kontruksi ........................................................................6
2.2.1. Jenis Estimasi Biaya Proyek .................................................................7
viii
2.2.2. Rencana Anggaran Biaya (RAB) .........................................................8
2.3. Manajemen Waktu Proyek ...................................................................9
2.4. Penjadwalan Proyek ............................................................................10
2.4.1. Metode Penjadwalan Proyek ………………………………………. 12
2.4.2. Diagram Balok (Bar Chart) .………………………………………. 12
2.4.3. Kurva S …………………….………………………………………. 13
2.5. Durasi Kegiatan ..................................................................................14
2.6. Microsoft Project ................................................................................15
2.7. Erection Girder ..................................................................................17
2.8. Alat dan Bahan ...................................................................................18
2.8.1. Crawler Crane.....................................................................................18
2.8.2. Launcher Girder .................................................................................19
2.8.3. Trauler Truck Boggie ..........................................................................22
2.8.4. Girder .................................................................................................23
2.8.5. Sika Grout ..........................................................................................26
2.9. Pemilihan Alat ....................................................................................27
2.9.1. Sumber Peralatan.................................................................................27
2.9.2. Kapasitas Operasi Peralatan ................................................................27
BAB III METODE ............................................................................................29
3.1. Lokasi .................................................................................................29
3.2. Data Perencanaan ................................................................................29
3.2.1 Data Umum Proyek............................................................................30
3.2.2 Data Teknik Proyek............................................................................30
ix
3.3. Konsep Penelitian ...............................................................................31
3.4. Variabel Perencanaan.........................................................................31
3.5. Tahapan Penelitian .............................................................................32
3.5.1. Metode Pelaksanaan Erection Girder ................................................32
3.5.2. Analisis Produktifitas dan Durasi........................................................32
3.5.3. Analisi Biaya .......................................................................................32
3.5.4. Analisis Mutu dan Resiko ...................................................................32
3.6. Analisis Data .......................................................................................32
3.6.1. Analisis Perhitungan Material dan Alat .............................................33
3.6.2. Analisis Produktifitas dan Durasi Pekerjaan Erection Girder ............33
3.6.3. Analisi Biaya Pekerjaan Erection Girder............................................33
3.6.4. Diagram Alir (Flow Chart) ................................................................34
BAB IV HASIL DAN PEMBAHASAN ..........................................................35
4.1. Analisis Data Jembatan ......................................................................35
4.1.1. Spesifikasi Balok Girder Tipe I 20 Meter ...........................................35
4.1.2. Spesifikasi Balok Girder Tipe I 40 Meter ...........................................40
4.2. Pelaksanaan Erection Girder Under Bridge Sta 03+550 ...................44
4.3. Metode Erection Girder Menggunakan Crawler Crane ....................46
4.3.1. Analisis Produktivitas dan Durasi Pekerjaan Erection Girder............51
4.3.2. Analisis Biaya Pekerjaan Erection Girder ..........................................57
4.3.3. Analisis Mutu dan Resiko Pekerjaan Erection Girder........................59
4.4. Metode Erection Girder Menggunakan Launcher Girder ..................61
4.4.1. Analisis Produktivitas dan Durasi Pekerjaan Erection Girder............66
x
4.4.2. Analisis Biaya Pekerjaan Erection Girder ..........................................69
4.4.3. Analisis Mutu dan Resiko Pekerjaan Erection Girder........................70
4.5. Perbandingan Metode yang digunakan ..............................................71
BAB V PENUTUP...........................................................................................73
5.1. Kesimpulan ..........................................................................................73
5.2. Saran.....................................................................................................73
DAFTAR PUSTAKA
LAMPIRAN
xi
DAFTAR TABEL
Tabel 2.1. Lokasi Pemasangan Girder ...............................................................25
Tabel 2.2. Spesifikasi Balok Girder ...................................................................25
Tabel 2.3. Efisiensi Kerja ………………………………………………….….28
Tabel 2.4. Efisien Waktu ...................................................................................28
Tabel 3.1. Variabel Penelitian ............................................................................31
Tabel 4.1. Kebutuhan Erection Girder Metode Crawler crane ..........................46
Tabel 4.2. Spesifikasi Crawler Crane.................................................................46
Tabel 4.3. Data LHR yang melewati Under Bridge Sta 3+550 .........................50
Tabel 4.4. Cycle Time Erection Girder (Zona A) ..............................................52
Tabel 4.5. Cycle Time Erection Girder (Zona B) ..............................................53
Tabel 4.6. Cycle Time Erection Girder (Zona C) ..............................................55
Tabel 4.7. Rekapitulasi Waktu Pelaksanaan Erection Girder metode 1.............56
Tabel 4.8. Perhitungan Biaya erection A1 – P1 .................................................57
Tabel 4.9. Perhitungan Biaya erection P1 – P2..................................................58
Tabel 4.10. Perhitungan Biaya erection P2 – A2 .................................................59
Tabel 4.11. Kebutuhan Erection Girder Metode Launcher Girder ......................61
Tabel 4.12. Spesifikasi Crawler Crane.................................................................61
Tabel 4.13. Rekapitulasi Waktu Pelaksanaan Erection Girder metode 2.............68
Tabel 4.14. Rincian Biaya Erection Girder dengan Metode Launcher Girder.....69
Tabel 4.15. Rekapitulasi biaya dan waktu pelaksanaan masing masing metode .71
Tabel 4.16. Perbandingan pelaksanaan masing masing metode ..........................72
xii
DAFTAR GAMBAR
Gambar 2.1. Contoh bar chart pada MS Project (Sumber : Wikipedia.com) .....13
Gambar 2.2. Gambar 2.2 Contoh kurva S dalam RAB pekerjaan .....................14
Gambar 2.3. Tampilan Gant Chart pada MS Project ..........................................16
Gambar 2.4. Tampilan Resource Sheet pada MS Project ...................................17
Gambar 2.5. Bagian-bagian dari Crawler Crane (Sumber : Libby,James R,op.cit
, Modern Prestressed Concrete : design principlies and construction
methods 1990)................................................................................18
Gambar 2.6. Perbandingan radius dan kapasitas beban Crawler crane (Sumber :
Peurojoy,Robert Leroy.,Clifford J. Schexnayder, hal.544 2002). .19
Gambar 2.7. (a) dan (b) macam – macam contoh alat Launcher Girder (Sumber :
Libby,James R,op.cit , Modern Prestressed Concrete : design
principlies and construction methods 1990). .................................20
Gambar 2.8. Urutan Kerja pada pemakaian Launcher Girder (Sumber :
Libby,James R,op.cit , Modern Prestressed Concrete : design
principlies and construction methods 1990). .................................21
Gambar 2.9. Perbandingan bobot girder jembatan dengan bobot Launching truss
untuk bermacam - macam bentang (Sumber : Libby,James R,op.cit
, Modern Prestressed Concrete : design principlies and construction
methods 1990)................................................................................22
Gambar 2.10. Trailer Truck Nissan CW445 (Sumber :
https://www.udtrucks.com/en-au/home ) .......................................23
xiii
Gambar 2.11. Tipe Balok I (Sumber : http://www.deal.it/equipment-
portfolio.asp?id-765)......................................................................24
Gambar 2.12. Sika Grout ......................................................................................26
Gambar 3.1. Lokasi Under Bridge Sta. 03+550 (Sumber : Dokumentasi PT. PP
(Persero) Tbk. 9 Februari 2017).....................................................29
Gambar 3.2. Diagram Alir Penelitian ................................................................34
Gambar 4.1. Balok girder bentang 20 m (Sumber : Perhitungan PP Precast
pembangunan jalan tol pamal) .......................................................35
Gambar 4.2. Penampang Balok Girder 20 m......................................................37
Gambar 4.3. Kontrol pengangkatan balok girder................................................38
Gambar 4.4. Balok girder bentang 40 m (Sumber : Perhitungan PP Precast
pembangunan jalan tol pamal) .......................................................40
Gambar 4.5. Penampang Balok Girder 40 m......................................................42
Gambar 4.6. Kontrol pengangkatan balok girder................................................43
Gambar 4.7. Layout Under Bridge Sta. 03+550 ( Sumber : Drafter PT. PP
(Persero) pembangunan proyek jalan tol pamal) ...........................45
Gambar 4.8. Alur Erection Girder ......................................................................45
Gambar 4.9. Pelaksanaan Erection Girder metode 1(1)......................................48
Gambar 4.10. Pelaksanaan Erection Girder metode 1(2)......................................48
Gambar 4.11. Pelaksanaan Erection Girder metode 1 (3).....................................49
Gambar 4.12. Pelaksanaan Erection Girder metode 1 (4).....................................49
Gambar 4.13. Denah dan alur Detour (Sumber : Drafter PT. PP (Persero)
pembangunan proyek jalan tol pamal ) ..........................................50
xiv
Gambar 4.14. Layout Erection Girder zona A ......................................................51
Gambar 4.15. Layout Erection Girder zona B ......................................................53
Gambar 4.16. Layout Erection Girder zona C ......................................................55
Gambar 4.17. Struktur potongan rangka Launcher Girder (Sumber : Drafter PT.
PP (Persero) pembangunan proyek jalan tol pamal ) .....................63
Gambar 4.18. Tipikal profil dan hoist crane struktur rangka Launcher Girder
(Sumber : Drafter PT. PP (Persero) pembangunan proyek jalan tol
pamal )............................................................................................63
Gambar 4.19. Pelaksanaan Erection Girder metode 2 (1).....................................64
Gambar 4.20. Pelaksanaan Erection Girder metode 2 (2).....................................64
Gambar 4.21. Pelaksanaan Erection Girder metode 2 (3).....................................65
Gambar 4.22 Pelaksanaan Erection Girder metode 2 (4).......................................65
xv
DAFTAR LAMPIRAN
Lampiran A Data Teknis Pembangunan Under Bridge Sta 03+550 Jalan Tol
Pandaan Malang
Lampiran B Penampang Balok PC-I Girder Pembangunan Under Bridge Sta
03+550 Jalan Tol Pandaan Malang
Lampiran C Plan Pelaksanaan Erection Girder Metode 1 dengan bantuan
Crawler Crane Pembangunan Under Bridge Sta 03+550 Jalan Tol
Pandaan Malang
Lampiran D Plan Pelaksanaan Erection Girder Metode 2 dengan bantuan
Launcher Girder Pembangunan Under Bridge Sta 03+550 Jalan
Tol Pandaan Malang
Lampiran E Spesifikasi Alat Berat Erection Girder Pembangunan Under Bridge
Sta 03+550 Jalan Tol Pandaan Malang
xvi
DAFTAR PUSTAKA
Jannah, Raudhotul. 2015. Efektifitas Pelaksanaan Erection Girder Serta Pemodelan
3D Menggunakan Software Tekla Structure17 pada Spillway Waduk Jatigede.
Repositor IPB. Departemen Teknik Sipil dan Lingkungan Fakultas Teknologi
Pertanian., IPB. Bogor.
Kumalasari., Aulia Indira 2017. Alternatif Pemilihan Metode Penjadwalan dan
Estimasi Biaya Proyek dengan Menggunakan Simulasi Monte Carlo pada
Pembangunan Gedung Neo Condotel Batu. Jurnal Teknik Sipil Fakultas Teknik.,
UMM. Malang.
Libby, James R. 1984. Modern Prestressed Concrete : Design, Principles, and
Construction Methods. New York. Van Nostrand Reinhold Company Inc.
Pratama, Dwi Dian. 2013. Analisa Perbandingan Metode Erection Girder
Menggunakan Launcher Girder dan Temporary Bridge dari Segi Biaya dan Waktu
pada Jembatan Kali Surabaya Mojokerto. Jurnal Teknik Pomits Vol. 1, No. 1,
(2013) 1-10 1. Fakultas Teknik Sipil Perencanaan., ITS. Surabaya.
Peurofoy, R. L., Clifford J. Schexnayder. 2002. Construction Planning, Equipment,
and Methods. New York. McGraw-Hill Higher Education.
Rasyid, M., R. 2008. Analisa Produktifitas Alat-Alat Berat Proyek (Studi
Kasus, Proyek Pembangunan Bandar Udara Hasanudin, Maros, Makasar).
Tugas Akhir Mahasiswa. Universitas Islam Indonesia. Yogyakarta.
Rochmanhadi. 2000. Kapasitas dan Produksi Alat-Alat Berat. Jakarta. Departemen
Pekerjaan Umum.
Sastramadja., A. S., 1994. Analisa ( cara modern ) Anggaran Biaya Pelaksanaan.
Bandung : Nova.