author: bell, matthew, d paint line efficiency · figure 4: data collection board .....27 figure 5:...
TRANSCRIPT
1
Author: Bell, Matthew, D
Title: Paint Line Efficiency
The accompanying research report is submitted to the University of Wisconsin-Stout, Graduate School in partial
completion of the requirements for the
Graduate Degree/ Major: MS Technology Management
Research Adviser: James Keyes, Ph.D.
Submission Term/Year: Spring, 2012
Number of Pages: 48
Style Manual Used: American Psychological Association, 6th
edition
I understand that this research report must be officially approved by the Graduate School and
that an electronic copy of the approved version will be made available through the University
Library website
I attest that the research report is my original work (that any copyrightable materials have been
used with the permission of the original authors), and as such, it is automatically protected by the
laws, rules, and regulations of the U.S. Copyright Office.
My research adviser has approved the content and quality of this paper.
STUDENT:
NAME Matthew Bell DATE: May 10, 2012
ADVISER: (Committee Chair if MS Plan A or EdS Thesis or Field Project/Problem):
NAME Dr. James P. Keyes DATE: May 10, 2012
----------------------------------------------------------------------------------------------------------------------------- ----
This section for MS Plan A Thesis or EdS Thesis/Field Project papers only
Committee members (other than your adviser who is listed in the section above)
1. CMTE MEMBER’S NAME: DATE:
2. CMTE MEMBER’S NAME: DATE:
3. CMTE MEMBER’S NAME: DATE:
----------------------------------------------------------------------------------------------------------------------------- ----
This section to be completed by the Graduate School This final research report has been approved by the Graduate School.
Director, Office of Graduate Studies: DATE:
2
Bell, Matthew D. Paint line Efficiency
Abstract
The paint system of Company X was slowing the product flow within the production
system. Due to current line design and the lack of visual measures, current throughput was
limited and current flow was not meeting the needs of the production system. Therefore a
solution needed to be identified in order to effectively lay out the production line and design
visual measures that would allow for increased flow as well as increased efficiency. Through
the use of time studies the line design was changed in a way that would maximize the flow of
products through this cell allowing for greater volumes of products to be shipped. The primary
purpose of this project was to increase the number of products being shipped on a daily basis.
The second was the labor resources that were opened up due to the fact that items will hung on
the line in a more efficient and effective manner. Through freeing up these resources it allowed
for focus on other areas of the production system that were bottle necking.
3
Acknowledgments
I would like to thank everyone who guided me through my continued education, because
of them this is possible. I can’t thank my wife, Jennifer enough for her continued support and
patience with me over the course of the paper. I would also like to thank my research advisor,
Dr. James Keyes, for the persistence and guidance through this process.
Thank You.
4
Table of Contents
.................................................................................................................................................... Page
Abstract ............................................................................................................................................2
List of Tables ...................................................................................................................................6
List of Figures ..................................................................................................................................7
Chapter I: Introduction ....................................................................................................................8
Statement of the Problem .....................................................................................................8
Purpose of the Study ............................................................................................................9
Assumptions of the Study ....................................................................................................9
Definition of Terms..............................................................................................................9
Limitations of the Study.....................................................................................................10
Summary ............................................................................................................................11
Chapter II: Literature Review ........................................................................................................12
Management Styles ...........................................................................................................13
Effects of Lean Manufacturing .........................................................................................14
Value ......................................................................................................................15
Standardization ......................................................................................................15
Employee Empowerment .......................................................................................15
Toyota Production System .................................................................................................16
Equipment…………………………… ..............................................................................17
Total Quality Management ................................................................................................18
Employee Empowerment ...................................................................................................19
Culture change ...................................................................................................................19
5
Summary ............................................................................................................................20
Chapter III: Methodology ..............................................................................................................22
ERP Software .....................................................................................................................22
Data Collection Procedures ................................................................................................25
Methods..................................................................................................................26
Measure ..................................................................................................................27
Quality....................................................................................................................28
Summary ............................................................................................................................29
Chapter IV: Results ........................................................................................................................30
Results of the Define Phase ..............................................................................................30
Results of the Measure Phase ...........................................................................................31
Results of the Analyze Phase ............................................................................................33
Summary ..........................................................................................................................35
Chapter V: Discussion ...................................................................................................................36
Limitations ........................................................................................................................37
Results ..............................................................................................................................38
Recommendations for Further Research ...........................................................................39
Conclusions ......................................................................................................................40
References ......................................................................................................................................42
Appendix A: ...................................................................................................................................44
6
List of Tables
Table 1: Inventory List...................................................................................................................35
7
List of Figures
Figure 1: ERP System ....................................................................................................................24
Figure 2: Scatter Diagram ..............................................................................................................26
Figure 3: Data Table ......................................................................................................................26
Figure 4: Data Collection Board ....................................................................................................27
Figure 5: Current State Process Map .............................................................................................28
Figure 6: Value Stream Map ..........................................................................................................30
Figure 7: Hour by Hour Board .......................................................................................................32
Figure 8: Finished Product Board ..................................................................................................32
Figure 9: Floor Layout ...................................................................................................................33
Figure 10: Standard Work Documentation ....................................................................................34
Figure 11: Quality Tag ...................................................................................................................36
8
Chapter I: Introduction
Company X is a small custom metal fabrication shop that specializes in steel furniture.
Over the past 40 years Company X has remained a sole proprietorship. They have kept their
market share due to the company’s high quality and unique designs. Just as any other company,
Company X has gone through many changes in product mix. Currently, Company X has one
main customer (Customer X) and focuses almost solely on catering to the needs of this
organization. During this time period, Company X has had continued success due to the
substantial growth of Customer X, which is currently Company X’s largest customer. During the
past five years Company X has grown at a rate of 485%. Due to this continued growth, the
production system could not handle the added production. The largest constraint existed within
the paint system.
The prior production system was a batch system, which creates small quantities of
products traveling through the facility. This system allows for items to make it out the door in
less time. Although items can be processed faster it does add cost in the handling process due to
the small quantities of products. The cost of handling the small batch sizes is proportional to the
batch sizes. The constant product change puts extreme pressure on the paint system, which has
the task of painting the products but also washing and hanging these products in an efficient
manner. The batch system that was currently in place was not allowing for maximum efficiency
throughout this cell. With the use of time studies as well as visual tools, the efficiency of this
cell was increased substantially.
Statement of the Problem
9
Due to increased business level there was a need to improve the volume of products
processed through the paint system. The material flow was not meeting the needs of the
production system set by the sales volume.
Purpose of the Study
The purpose of this study was to examine the paint system inefficiencies within the
production system of Company X, and effectively laying out the production line and designing
visual measurements that will allow for increased flow as well as increased efficiency. As a
result of no current line design and the lack of visible measurements, current throughput was
limited. Through the use of time studies the line design was analyzed so that changes were made
to maximize the flow of products through this cell, allowing for increased volumes of products
processed through the plant by 25%. The expected outcome was to increase the number of
products being shipped on a daily basis by 40%. The secondary goal of the project was to
increase labor resource utilization which opened up due to the fact that items were hung on the
line in a more efficient and effective manner. Freeing up these resources allowed for focus on
other areas that were bottle necking the production system.
Assumptions of the Study
This study assumed that the current paint line design of Company X was out of the scope
of the project. This project focused on the constraints that were inherent to the current line
design. It also assumed that the management team of Company X would not remove necessary
resources from the operation.
10
Definition of Terms
Lean. “A manufacturing or management philosophy that shortens the lead time between
customer orders and shipment of the parts or service ordered through the elimination of
all forms of waste” (Alukal & Manos, 2006).
Kaizen. “A Japanese term for continuous improvement and the process of making
incremental improvements, no matter how small, and achieving results” (Liker 2004).
Takt Time. “A German word for musical meter. n lean production, it is the rate of sales
in a marketplace, or the drum beat of consumption” (Henderson & Larco, 2003).
Kanban. “A method of inventory control, originally developed in Japanese automobile
factories, that keeps inventories low by scheduling needed goods and equipment to arrive
a short time before a production run begins” (Flinchbaugh 2005).
Procedure. “A written description of work to be done at a specified operation. Written
in a manner that all operators perform a given operation in the same manner (Flinchbaugh
2005).
Maximum Line Design. “The number of finished goods that a manufacturing assembly
line is capable of in an eight hour period with a standard schedule” (Lee 2004).
End of Line Yield. “A quality number used to determine the number of rejects
compared to the number of units produced”(Barthomew 1999).
Limitations of the Study
This project was limited to the production system of Company X. This project was done
on the basis that the current equipment was used and no other significant changes were made to
the structure of the building. There was no study done into specific product sizes, and worked on
the assumption that the product mix is stable. The employee buy-in to the project did ultimately
11
affect the results of the project. The project is covering only one cell of the production facility,
so problems that exist in other parts of the facility will not be covered within this project.
Summary
Chapter one discussed the objective of this project. It went into the basic format on the
needs of Company X. It discussed many of the assumptions that went into the project. It also
took into consideration many of the built in biases that existed in the production system. Chapter
two will discuss the tools that were used to conduct the study. Many of these tools were
management styles, the effects of lean manufacturing, and many other tools that will be used to
increase the number of painted parts that were painted by Company X.
12
Chapter II: Literature Review
Company X’s sales have continued to grow faster than the production system can sustain.
To counter this imbalance, this project looked into lean principles that improved the product flow
within the facility. This project took a single piece flow approach to creating a more efficient
flow of parts through the paint line at Company X. This literature review will explore lean
management styles, Lean tools, Toyota Production System Tools, and concepts to improve line
efficiency through a facility.
Management styles
The greatest area for gain is in the organization as a system. Often times in business
today, we are looking for quick fixes to problems, when actually we are just compounding the
problem. Juran (2000) states that only 20% of the problems in a business are worker related,
where as 80% are due to the process. This is why Juran emphasizes pushing for deep fixes, and
not blaming the employee but the process. Juran was an author and known for his deep quality
roots and not just looking at the surface of issues. Brian Joiner emphasizes in Fourth Generation
Management the thoughts of Edward Deming that 4% of a company’s issues are related to
employees and 96% of the issues are due to the process. This is why Brian Joiner encourages his
readers to recognize that rapid learning leads to rapid improvement. The cornerstone of this
concept is the Plan-Do-Check-Act model (Joiner, 1994). Although this concept is simple, it has
taken him over a decade to truly come to grasp all of the concepts.
Staying customer focused is a key in being successful in today’s market. Joiner (1994)
shares many stories of companies who felt that they had taken positive steps for bringing a better
product to the customer, but without customer input, it leads to customer dissatisfaction and the
loss of many customers. Identifying and eliminating processes in our organization has little
13
meaning or value an organizations customer. Rather, talking with the customer to get feedback
and input is a necessity to meeting their needs. Efforts to get customer input should be made
through several facets of the company as customers have input on several aspects of the product.
This is especially important with universal products as customers will go willingly to the vendor
who will meet their needs. This is why Joiner believes that not only management should be
present and available for customer needs, but many times it is more effective to allow first line
employees to meet and assist the customer. This allows for employees feel a sense of ownership
and importance to the company as well as create a learning experience for both the customer and
employee. Meeting the needs of the customers by rapidly responding to the customer’s changing
needs and concerns in the end will be what will create customer loyalty and success of a
company .
One of the concepts used was Fourth Generation Management (Joiner, 1994). Fourth
Generation Management is a management style that gives the power back to the employees. It
looks at management in a new light and does not allow supervisors to micro manage their
employees. It also uses a concept of getting individuals into their appropriate positions and
identifying those who do not fit in one role, by moving them into another role or ultimately out
the door. This method of management is predominately used in today’s market place. It is
important to acknowledge that every situation is different and what works in this facility may not
work in another. The concept of management is always evolving, and if a person stops learning,
one will quickly fall behind the times. Despite effort and hard work, most situations are too
complex and varied to address by one single concept of procedure. As Joiner says “Close the
loop hole, thinking is inherently flawed.” (Joiner, 1994) We all need to look at the goal of
14
management and revisit how we think and work. Continuous improvement is essential to stay
competitive in today’s marketplace and to continue as a growing and thriving company.
Effects of Lean Manufacturing
Many manufacturers are now critically evaluating their processes to determine their
effectiveness in bringing maximum value to customers (Flinchbaugh, 2005). Factory
management techniques of yesterday are being replaced by more efficient methods that greatly
minimize delays, reduce costs, and improve quality. This is done through Lean manufacturing
which is a whole-systems approach that creates a culture in which everyone in the organization
continuously improves processes and production. It is a system focused on and driven by
customers, both internal and external (Shingo, 1996).
Lean manufacturing is not just the latest industry buzzword or quick-fix alternative
(Henderson & Larco 2003). Increasing competition demands a continuous focus on minimal
costs, maximum customer options, fast delivery, and high-quality products and services. Today's
manufacturers must be innovative while focusing on waste reduction, improved lead-time,
maximized flexibility, and upgraded quality. Lean manufacturing concepts are proven strategies
to help manufacturers obtain these attributes. Converting to a lean production system is a process
that requires every level of an organization to develop a complete understanding of the basic
concept and its execution. Companies that have fully implemented lean systems are rare, but the
list of manufacturers trying to become lean is growing fast.
The transition to a lean environment does not occur overnight. A continuous
improvement mentality is necessary to reach your company's goals. The term "continuous
improvement" means incremental improvement of products, processes, or services over time,
with the goal of reducing waste to improve workplace functionality, customer service, or product
15
performance (Covey, 1989). Continuous improvement principles, as practiced by the most
devoted manufacturers, result in astonishing improvements in performance that competitors find
nearly impossible to achieve.
Standardization of process is a mandatory component of lean manufacturing because it is
supposed to eliminate as much non-value added time as possible (Joiner 1994). As Joiner states,
the arguments for and against standardization are both valid. Procedures only work as well as
they are implemented. If the management team comes up with procedures and begins to strictly
enforce them, but does not get input from the employees, the procedures will ultimately fail.
Alternatively, if the employees have feedback and the guidelines are in place to constantly
improve the documentation, it sets the foundation for improvement that will ultimately lead to
success. A company must standardize if they want to achieve consistently high performance.
Standardization can do exactly what lean intends or if implemented incorrectly it can lead to
chaos. This chaos then cannot be overcome until employees feel empowered.
Employee empowerment can be attained in many different ways. First and foremost it is
obtained by adequate training (Henderson, 2003). Too many companies look at training as cost
detraction from production, whereas training needs to become a priority and should not be
treated as unnecessary cost. Training can bring benefits in so many different ways. It can help
with the strategic re-design of procedures, bring employees closer as a team and feel as if their
insight is helpful. It raises spirits because they feel as if they are needed and are responsible for
continuously searching for ways to improve the process. However, employee empowerment can
backfire if the employees bring their thoughts to management and management never attempts to
implement the employees’ ideas.
Toyota Production System
16
For many years, Toyota Production System (TPS) and its derivatives such as lean
manufacturing have been viewed as a best-way approach for managing operations. There are
inherent problems presented by a universal adoption of ‘best practice’, and the obvious practical
problems are certainly illuminated when we extend the idea of ‘one best way’ from the design of
complex work systems to the design of complex technical systems, as in the preceding
paragraph. Nevertheless, the methods associated with Toyota had an impressive currency largely
because of the long-standing recognition that Toyota is an outstanding manufacturer (Jones &
Roos, 1990).
Great attention has been paid to Toyota’s ‘Just-in-Time’ production control tools as well
as to its ability to improve continuously on their procedures. Toyota designs work systems so
they generate information immediately when a problem has occurred. These signals become the
baseline for the problem solving activities that allow TPS-managed organizations to engage in an
adaptive, hierarchical search for superior designs for an organization’s system. In terms of the
final organizational form it discovers, it is certainly a superior way for facilitating situated,
problem solving-based learning that leads to organizational forms that fit strategically with the
organizational mission (Flinchbaugh 2005).
U.S. manufacturers have always searched for efficiency strategies that help reduce costs,
improve output, establish competitive position, and increase market share. Early process oriented
mass production manufacturing methods common before World War II shifted afterwards to the
results-oriented, output-focused, production systems that control most of today's manufacturing
businesses (Joiner, 1994).
Japanese manufacturers re-building after the Second World War were facing declining
human, material, and financial resources. The problems they faced in manufacturing were vastly
17
different from their Western counterparts. These circumstances led to the development of new,
lower cost, manufacturing practices. Early Japanese leaders such as the Toyota Motor
Company's Eiji Toyoda, Taiichi Ohno, and Shingeo Shingo developed a disciplined, process-
focused production system now known as the "Toyota Production System", or "lean production."
The objective of this system was to minimize the consumption of resources that added no value
to a product (Covey, 1989).
The "lean manufacturing" concept was popularized in American factories in large part by
the Massachusetts Institute of Technology study of the movement from mass production toward
production as described in The Machine That Changed the World, (Womack, Jones & Roos,
1990), which discussed the significant performance gap between Western and Japanese
automotive industries. This book described the important elements accounting for superior
performance as lean production. The term "lean" was used because Japanese business methods
used less human effort, capital investment, floor space, materials, and time in all aspects of
operations. The resulting competition among U.S. and Japanese automakers over the last 25
years has led to the adoption of these principles within all U.S. manufacturing businesses.
Equipment
Spraying lacquer-based paint is a difficult process, but the process can be simplified with
the right equipment. Conventional paint-guns usually operate at approximately 60 pounds per
square inch. High-pressure air from these units tends to blast the paint into small particles
causing low transfer efficiency from bouncing off, blowback and overspray. These losses result
in excessive paint, thinner, and filter consumption, and increase the disposal costs. In contrast,
high-volume low-pressure paint guns operate at less than 10 pounds per square inch and atomize
18
the paint into a pattern of low speed particles. This results in dramatically improved transfer
efficiency.
The Environmental Protection Agency (EPA) estimates that the transfer efficiency of
conventional paint guns is as low as 20% to 30%, while that of high volume low pressure
(HVLP) is about 65 % to 90 % (Liberto, 2004). Thus, the change to HVLP guns would reduce
both paint purchase and disposal costs. This will create a better outcome of the finish applied to
the product as well as creating a greener culture within the business model. It is crucial to
companies in today’s society to maintain their competitive edge, which can come from any
portion of the company.
Total Quality Management
Strategy is a number of decisions and actions that an organization uses to achieve its
long-term goals. A strategy has both content and process (Demarco, 2001). Specific decisions
which are made to achieve specific objectives are known as content strategy, and the procedure
which is used within a business to formulate its business is known as process strategy.
Companies around the world use different contents and processes. A company’s objectives and
successes are dependent on choosing the right operation strategy. A Just-in-time production
system tries to meet demand instantaneously with perfect quality and no waste. It differs from
traditional operations practices as it stresses waste elimination and fast throughput, both of which
contribute to low inventories. Planning and control of many Just-in-time techniques are directly
concerned with pull scheduling, kanban control, leveled scheduling, mixed-model scheduling
and synchronization of flow (Demarco, 2001).
19
Employee Involvement
One of the many challenges in today’s work place is the competitive nature of the current
market place. To compete in these markets, companies are faced with the reality that process
needs to be continually improving. The key to a continually evolving process is employee
involvement. Keeping employees engaged is a challenging effort. It’s essential with these types
of efforts that good communication is established across all levels of an organization. If
employees feel as if their ideas are being dismissed they are not going to be willing to offer up
suggestions the next time around. It is said that no one knows how to do the job better than the
people who are involved in the process each day. People have the need to feel as if they are
doing a good job. One of the challenges with this is that people create these contextual biases,
which can hinder people’s ability to see outside the box (Joiner, 1994).
Culture change
Lean manufacturing is a whole-systems approach that creates a culture in which everyone
in the organization continuously improves processes and production. It is a system focused on
and driven by customers, both internal and external. Effective lean producers normally require
25-40% fewer people to produce the same level of output (Henderson & Larco, 2003). This
connotation alone has given many people who work in a facility the feeling that lean is a tool for
eliminating jobs. However, in reality lean is a tool that is needed to get the employees involved
in improving the processes. Without using lean concepts, organizations do not have the tools to
compete in today’s market place. The competitive nature of the manufacturing industry will not
let you sit back and watch otherwise your competition will take the business away from your
organization. Lean Manufacturing can only be achieved if you have the people who are involved
in the process directly involved in the improvement efforts.
20
Improvement ideas need to come from within the organizations. Henderson and Larco
(2003) state that there are four important steps to the success of continuous improvement. First,
improvement ideas should be reviewed, approved, and implemented at the lowest possible level
in the organizations as possible. Second, it is critical to ensure that teams set aside time each day
to discuss improvement ideas. The third concept relates to suggestions that originate from
outside one’s immediate work area. Fourth is implementing a recognition system. Recognition
programs are a key concept to keeping employees involved in improvement programs.
Communication and recognizing improvement successes are what create the continued success
of an implementation project. However, companies can quickly revert back to their old
processes due to lack of communication and recognition. Allowing this type of culture to exist
will never create an environment of continuous improvement (Henderson & Larco, 2003).
An employee’s knowledge of the process is critical to the successful implementation of
an idea. Lean thinking requires that the people closest to the work be involved in improving it.
The success of a lean initiative depends on everyone’s contributions of energy and thought. The
key concept to retain by everyone involved in a lean culture is that everyone has a vested interest
in helping make their job easier and more productive. Creating this type of cycle can be
extremely difficult to create, but once a culture of continuous improvement has been achieved
the sustain portion of implementation is no longer a something that is tracked, but it becomes
second nature to all people involved.
Summary
The literature review discussed that implementing lean tools in many situations greatly
improves the efficiencies in a production system. It also revealed that management styles greatly
affect an organization’s performance. The results of the study showed that the combination of
21
lean tools and the proper equipment can change the culture within an organization. The literature
review also showed that sustainability in equipment and processes are keys in a successful
organization.
22
Chapter III: Methodology
The paint system was slowing the product flow within the production system of
Company X. Effectively laying out the production line and designing visual measures that
allowed for increased flow as well as increased efficiency was the purpose of this project. Due
to poor line design and the lack of visible measures, current throughput was limited. Through
the use of time studies the line design were changed in a way that will maximize the flow of
products through this cell allowing for great volumes of products to be completed and shipped
within the customers’ expectations.
Data required
The first item analyzed was the number of jobs shipped over the last year that had to go
through the paint booth before completion. The information analyzed came from the company’s
Enterprise Resource Planning (ERP) software package as seen in Figure 1. The information is
available to all employees with access to the software package. The information used was based
on actual sales over the previous 12 months. It is Company X’s policy that the information
within the ERP software may be shared with an outside company as long as the information is
not in real time. This ERP system will not allow the export of information into any other
software packages. The information can not be altered due to the fact that they were based on
actual sales over a 12 month period.
23
Figure 1. ERP System
The second item analyzed was an actual count of jobs that passed through the paint booth
over a two month period. The samplings were based on two shifts of painters over a 40 hour
work week for two consecutive months. The samplings were based on an hourly rate, and
tabulated on a weekly basis. It was the employee’s responsibility to keep the chart up to date and
current with their work. The count was not based on the number of pieces that went through the
booth, but number of jobs. Company X uses the term job as a representation of 4 hours of weld
time. The job figure did not directly convert into the amount of effort it took to paint the
product. This number was set on a form and the painters based their tabulations off of the
24
conversion from jobs to a piece count. The information used was only as reliable as the painter
and the management staff watching over the tabulation of this information.
Methods
First, the sales information was taken from the ERP system over the past 12 months. The
data was then broken down by items that went through the paint booth and those items that did
not go through the paint booth. Then, items were broken down into monthly sales to point out
overall productivity based on given sales, which had a significant influence on the results. This
information was then put into a bar graph to graphically represent the results for each month.
The data was also placed in a scatter diagram shown in Figure 2 to point out the mean, the Upper
Control Limit, and the Lower Control Limit. After all of the information was compiled it was
presented to the management staff to show the results and base future projections off of these
figures. In conjunction with the information from Figure 2, the data was combined with the
shipping dollars to show their direct connection. Figure 3 shows the direct relationship between
the parts painted to the shipping dollars. This information was collected over a 6 month period.
25
Figure 2. Scatter diagram
Figure 3. example data table
Date Range On-
time
Total
ShipmentsHours in operation Number of parts painted
1/1-1/5/01
1/8-1/12
1/15-1/19
1/22-1/26
1/29-2/2
2/5-2/9
2/12-2/16
2/19-2/23
2/26-3/2
3/5-3/9
3/12-3/16
3/19-3/23
3/26-3/30
4/2-4/6
4/9-4/13
4/16-4/20
4/23-4/27
4/30-5/4
5/7-5/11
5/14-5/18
5/21-5/25
5/28-6/1
6/4-6/8
25
Figure 2. Scatter diagram
Figure 3. example data table
Date Range On-time
Total Shipments Hours in operation Number of parts painted
1/1-1/5/011/8-1/121/15-1/191/22-1/261/29-2/22/5-2/92/12-2/162/19-2/232/26-3/23/5-3/93/12-3/163/19-3/233/26-3/304/2-4/64/9-4/134/16-4/204/23-4/274/30-5/45/7-5/115/14-5/185/21-5/255/28-6/16/4-6/8
26
The first action item was to come up with an accurate expected job count for the paint
system. Then a job count was assigned that was specific for the paint booth based on the fact
that this system was different than all other operations within the process. A board was then
hung in the operator’s area tracking the number of parts that were coming off of the paint line.
An example of the board can be seen in Figure 4. The board collected the number of painted
parts that were inspected and taken off of the line. The board only accounted for the number of
pieces and did not account for the size. A takt time calculation to calculate the needed line speed
to meet the required output needed.
Figure 4. Example Data Collection Board
This not only allowed for the data to be collected but also acted as a visual for the operator to
gauge their progress in comparison to their expected progress and to the painter on the other
shift. The information off of these boards was recorded on a daily basis by the production
supervisor. The information was then added to a spread sheet and analyzed.
Through creation of the final spread sheet, it brought up many action items for
improvement that were acted upon immediately as well as other areas that were uncovered that
need to be further investigated. The data brought to light that many differences existed between
27
the two shifts. This information was used to train the employees and brought immediate results.
The chart acted as a visual motivator for the employees, but was monitored very closely to see
that it was not driving the employees further apart or creating quality issues. The results from
the data collection were placed into charts and used to give the paint system a baseline measure
of success.
Data Collection
The data collected in the project consisted of process analysis through observation during
a kaizen event (Liker, 2004). The data was captured and recorded on a current state value stream
map shown in Figure 5 and compared to future state value stream maps to identify waste steps
that could be eliminated to improve process efficiencies.
Figure 5. Current State Process Map
28
Quality
Check Process before the Project
The objective of this project was to increase the capacity of painted parts that were
painted at Company X. One of the concerns was that quality would suffer due to the increased
parts being processed. To ensure this would not occur through the changes made to the process a
quality tag was created, which will not only specify who inspected the part, but also on what date
the part, went through the facility. The quality tag as shown in figure 11 had different benefits.
One of the benefits was giving the employees ownership of the products they were checking. It
also gave the organization the ability to go back and track quality issues that were coming back
from the customers. Product returns were becoming an issue and there was no one measure in
place to track or control any of the quality issues that were being seen from the customer. There
was no quality check system put into place.
System Waste Identification
A current state value stream map was created to visually illustrate the takt time and show
which process was the constraint within the system. The takt will show which process needs to
be focused on to increase the output of the production system. Figure 6 is an example of a value
stream map which includes takt time information.
29
Figure 6. Example of a value stream map with Tact time.
Summary
The current process in place at Company X was not meeting the customer’s demands.
Through the evaluation of this system and the application of lean tools, this process was able to
exceed the current demands of the customer. During the process there was a lot of unseen waste
that was limiting the number of pieces that were being painted. Increasing the number of parts
shipped did not have a negative impact on the number of items being returned from the
customer. The effects of these changes and how they affected the output of the system are
demonstrated in Chapter IV.
30
Chapter IV: Results
The paint system was slowing the product flow within the production system of
Company X. This chapter will show how effectively laying out the production line and
designing visual measures allowed for increased flow as well as increased efficiency. The
implementation of visual measures showed how current throughput was limited by the lack of
visual measures in place. The time studies showed how the line design was changed in a way
that maximized the flow of products through the cell allowing for increased production.
The use of Company X’s ERP system allowed the project to set a base line of where the
company’s output was currently and illustrate where the production level needed to be. This
information was collected and placed into a scatter diagram. Lean tools were then used to
improve the efficiency of the paint line.
This chapter will review the results of applying the lean tools and creating a system that
allows for single piece flow. It will show how the output volumes of the paint line improved
dramatically. The use of visual measures and better communication techniques were also used
as part of the study.
Results from implementing hour by hour boards
The implementation of the hour by hour boards revealed there were varying amounts of
painted parts, depending on the product mix. The study brought to light that the upstream
process also needed to be monitored to create a better product mix for the paint line. In Figure 7
the results show the variation in parts coming off of the line between hours was substantial. The
hour by hour board was filled out by the product wrapper due to the time constraints on the paint
operator.
31
Figure 7. Hour by hour board.
The hour by hour board showed what was coming off the paint line on an hourly basis. The
actual numbers of parts being painted were placed on a finished product and quality board which
was placed in the work cell. Figure 8 shows the number of parts that were completed on a
particular shift. These numbers were collected over a six month period and are shown in
Appendix A.
Figure 8. Finished product board
The painter’s output at the beginning at the project was 8.5 parts per hour. To meet the
customer’s needs the output level needed to be at 12.2 parts per hour. Looking at the current
state of the product flow through the facility allowed for the optimal flow of material through the
facility. The shop was organized in a manner that created a single piece flow through the
32
facility. This allowed the paint booth to receive the products in an efficient manner to flow
through the paint booth. The flow of product through the facility can be seen in Figure 9. The
primary production area that was reorganized was the grind department. This reorganization
allowed for better visualization of where products were at.
Figure 9. Floor Layout
Implementing Standard Work
In a manufacturing setting getting the parts to the upstream processes in the manner in
which they are needed is one of the keys to success. To ensure this was happening, standard
work was created to ensure that the upstream process was getting parts in the manner in which
they needed them.
33
The standard work document was written for the wash and parts hanging operations.
This documentation helped to create an environment in which the painter was receiving parts in a
standardized manner because it allowed the washer and hanger to understand the needs of the
painter. This was one of the major improvements that increased the output of this cell.
Figure 10. Standard work documentation.
The paint cell had a total availability of 16 hours and 40 minutes per day, Monday through
Thursday, and 7 hours and 20 minutes on Fridays. This timing allowed for the equipment to be
turned off for breaks and for the 10 minute clean up at the end of each shift. This information
can be seen in Table 1. This table lays out the number of parts that were averaged before the
improvements and what the average number of parts painted throughout the course of a day after
the improvements had been implemented. The output increased by 27% after the improvements
had been implemented.
34
Table 1. Inventory list comparison results
The results that were collected did not take into account the downstream processes, which
did starve the paint process at times. This meant that the paint process was no longer the
constraint in the process. The excess capacity that was created allowed the labor resources used
in the paint department to assist in other departments when needed.
Once the single piece flow concepts were put into place, the paint line could then be set
to one consistent speed and run at that speed for the entire shift without stoppages. The constant
speed not only helped with the increased output of the paint line, but it also gave the paint line
predictability. It created a stable product flow allowing the managers to make adjustments to the
rest of the process as needed. This provided the opportunity to mangers to be proactive instead
of reactive to issues that arose within the production system.
Quality Process
Shipping a quality part to your customer is the ultimate goal of any operation. One of the
ways quality was assured was with the implementation of a quality tag which was shipped with
Availability # of minutes per day Avg Painted parts before Avg Painted parts After
hours of operation 6:00am - 1:00am 1080 - -
1st shift (Monday - Friday) 6:00am - 2:30pm 510 60.2 85.4
2nd Shift (Monday - Thursday) 2:30pm - 1:00am 630 89.4 119.6
Breaks-
1st shift 9:30am to 9:45am -15 0 0
1st shift 11:45am-12:00pm -15 0 0
1st shift - lunch (unpaid) 12:00pm - 12:30pm -30 0 0
2nd shift 5:00pm - 5:15pm -15 0 0
2nd shift lunch (unpaid) 7:30pm - 8:00pm -30 0 0
2nd shift 10:45pm - 11:00pm -15 0 0
Cleanup -
1st shift 2:20pm - 2:30pm -10 0 0
2nd shift 12:50am - 1:00am -10 0 0
1000.0 149.6 205Total per day (Monday - Thursday)
35
each product. The tag illustrated the date, the job number, and the name of the person doing the
inspecting. This tag as shown in Figure 11 allowed Company X to cut the number of returns
down by 20%. The project took into account that Company X had been having issues with
quality. It was noted that the number of returns could not correlate directly to the increased
shipping volume or the customer would have to look into alternate sources.
Figure 11. Quality Tag
Summary
The combination of lean tools and visual management drastically Improved Company
X’s output of products through the paint line by 27%. Impressively, this occurred without the
addition of equipment or labor resources. Using the existing employees and paint line, the
improvements were able to optimize the current process and meet the needs of the customer.
The education of employees on the concepts of lean manufacturing significantly aided in the
success of the improvements that were put into place. The employees’ involvement and the
support of upper management of the improvements created an environment that was able to
sustain the gain, while allowing other cells within the organization to get involved with
additional improvements and bring some of those same concepts into other cells within the
36
organization. The dollar volume of parts shipped within this period increased by 17 %. The
implementation of standard work documents helped keep these improvements moving forward.
The increased capacity allowed the organization to meet the needs of its customers’ current
demands, while setting the stage for additional volume in the future.
37
Chapter V: Discussion
The purpose of this study was to increase the output of the paint line by using lean tools
to identify problem areas as well as improving them. The paint system was slowing the product
flow within the production system of Company X. Chapter I detailed the background of
Company X and looked at the issues that existed within the current paint system as well as the
purpose for doing this study. It walked through the steps of why improvements were needed.
Chapter II discussed how Company X’s sales have continued to grow faster than the production
system can sustain. To counter this imbalance this project looked into lean principles that
improved the product flow within the facility. Chapter II also described management styles,
Lean tools, Toyota Production System Tools, and concepts to improve line efficiency through a
facility, and provided research methods to look at the issues and implement lean tools that had
the greatest effect on the paint system. Chapter III showed how the paint system was currently
slowing the product flow within the production system of Company X. The study then
effectively laid out the production line and design visual measures that allowed for increased
flow as well as increased efficiency. Chapter IV showed the results of the study. It showed how
current line design and the lack of visible measurements was limiting throughput. Time studies
were used at Company X to show the maximized flow of products through this cell allowing for
increased volumes.
Limitations
This study was limited by the product flow of Company X. This study was limited to the
paint cell and did not address issues that exist in other areas within the process. The figures used
within this paper were limited by the accuracy of data obtained over the previous twelve month
38
period. The study was conducted using current personnel, and did not address issues that existed
within this cell.
Results
Effectively laying out the production line and designing visual measures increased flow
as well as increased efficiency. Due to current line design and the lack of visible measures, the
current throughput was limited. Through the use of time studies the line design was changed in a
way that maximized the flow of products through this cell allowing for increased volumes of
products processed through the plant by 27%. The implemented improvements increased the
number of products being shipped on a daily basis by 17%. The goal of the project was also look
at labor resource utilization based on the number of painted products that were produced.
Freeing up these resources allowed labor resources to be shifted into other areas
To demonstrate the results, the sales information was taken from the ERP system over the
past 12 months. The data was then broken down by items that went through the paint booth and
those items that did not go through the paint booth. From there, items were broken down into
monthly sales in order to determine overall productivity based on given sales, which did have a
significant influence on the results. This information was then put into a bar graph to graphically
represent the results for each month. The data was also placed in a scatter diagram to point out
the mean, the UCL, and the LCL. Once this information was presented to the management staff
it saw that the production system was not dependable. The extreme variation in the number of
parts was a concern for the management team.
The first action item was to come up with an accurate base line of where the system was
at. This allowed the management team to assign a job count to each product, but was specific to
the paint booth. This was done due to the fact that the paint operations were too different from
39
other processes to have a comparable measure. The board was then hung in the operator’s area
where information was posted on an hourly basis and was proven to be effective. This not only
allowed for the data to be collected, but also acted as a visual for the operator to base not only
where they were expected to be but also as a comparison to the painter on the other shift. The
information off of these boards was recorded each Friday by the production supervisor. This
information was used to create a baseline for how well the paint cell was doing.
This information was placed onto a spread sheet to give the shop floor some visibility as
to how they were doing on an hourly basis, but also how they did over the course of a week.
This information was used to create standards of what needed to be produced. The fact that there
were two different operators did not matter due to the fact that each operator knew what they
were expected to produce. The chart should have acted as a visual motivator for the employees,
going forward this will have to be monitored very closely to see that it is not driving the
employees further apart. One of the keys of this project was to create an environment that
allowed the employees to work together and not create a divide between the two shifts.
Employee morale played a large role in ultimate success of the project.
Recommendations for Further Research
This study made significant improvements at Company X, but many more changes could
still be implemented. Continually involving the employees would bring many new improvement
ideas as well as continue to improve on the ideas that were already implemented. Employee
involvement is the key to any lean initiative. Company X will have to continue involving their
employees, but they will also have to get the management staff on board to drive the lean
initiatives.
40
During the course of the project single piece flow concepts were implemented, but based
on the upstream processes a true single piece flow system could not be implemented.
Establishing single piece flow through the rest of the shop would help with the output volumes.
Implementing a single piece flow throughout the entire shop would cause the shop to have to
change, and the sales force would have to go back to start in the front office. Orders were
released in small batches which consist of order quantities of either five or ten. Creating a
system that would produce one piece would allow for greater growth within the organization.
The organization would have greater visibility how the production system was doing if
they were fully utilizing their ERP software. Company X uses their ERP system for evaluating
costs, but does not translate the information onto the shop floor. If the system was set up
properly more of the information being collected could be usable at the shop floor level. Reports
generated through the current system are not formatted in a way that the information can be used.
In the future, if an information technology person was hired the system itself could be better
utilized. With greater visibility of the production system, Company X could approve their ability
to meet the needs of its customers and thereby ensuring the company’s continued growth.
Conclusion
During the course of this study, Company X made many improvements with the use of
different lean tools. The need to sustain the implemented improvements will be essential for the
continued growth and success of Company X. The improvements made have allowed Company
X to exceed the needs of its current customers allowing them to further diversify their customer
base. Upon completion of the study, Company X had increased the number of painted parts by
27%. The encouragement of further employee engagement and the focus on communication has
41
greatly helped with product output and has also allowed for the implementation of effective
processes throughout the entire facility.
One can conclude that the predictions of the project have exceeded expectations. The
only unforeseen part of the project was the impact the increased volumes would have on the
quality of parts being shipped. Once this issue was detected a quality tag was put into place and
the returns were reduced by 20%. If you take into account the increased volume of what is being
shipped then returns were actually reduced by 25%. This demonstrates that the predictions of the
project met the outcomes. The only unforeseen part of the project was the quality issues that
crept into the scope of the project.
42
References
Alukal, G., & Manos, A. (2006). Lean Kaizen: A Simplified Approach to Process Improvements.
Milwaukee, WI: American Society for Quality.
Bartholomew, D., (1999). Lean vs. ERP. Industry weekly, 24 (6), 24-30.
Bradford, M., Mayfield, T., Toney, C,. (2001). Does ERP fit in a Lean World?. Strategic
Finance Journal, 82 (11).
Burns, J. & Scapens, R. W. (2000), 'Conceptualising Management Accounting Change:
AnInstitutional Framework', Management Accounting Research, 11: 3-25.
Covey, S.. (1989) The 7 Habits of Highly Effective people. Fireside book, New York.
Demarco, Tom. (2001). Slack, Getting Past Burnout, busywork, and myth of total efficiency.
Henderson, B.A., & Larco, J. L. (2003). Lean Transformation: How to Change Your Business
into a Lean Enterprise. Richmond, VA: Oaklea.
Flinchbaugh, J., Carlino, A., (2005). The Hitchhiker's Guide to Lean: Lessons from the Road.
Dearborn, MI. Society of Manufacturing Engineers.
Joiner, B.. (1994). Fourth Generation Management. McGraw-Hill, Inc, New York.
Juran, J,. Godfrey, B.. (2000). Juran’s Quality Control Handbook 5TH Edition. McGraw-Hill,
Inc, New York.
Lee, Q,. (2004). What’s Lean Manufacturing and its history. Lean Manufacturing
Academy.
Liberto, Nocholas.. (2004). Powder Coating The Finisher’s Complete Handbook 3rd
Edition.
Goyer Management International.
Liker, J. (2004).The Toyota way: 14 management principles from the world’s greatest
manufacturer. New York, MY: McGraw-Hill.
43
Shigeo, Shingo. (1996). Quick Changeover for Operators. Kraus Organization, ltd. New York.
N.Y.:Broadway Press.
Womack, J. P., Jones, D. T., & Daniel Roos. (1990). The machine that changed the world. New
York, N.Y.: Free Press.
44
Appendix A
Date Wld Sch
Non bb Wld
bb Jobs
Wld Sch Total NS Week Avg SS Week Avg
1/5 10.0 2.0 8.0 18.3 2.3 15.8 15 1 0.75 1
1/6 10.0 0.5 9.5 20.8 2.2 17.0 13.8 1 3.25 1
1/7 10.0 0.3 8.5 16.9 2.0 18.0 12.8 1 5.25 1
1/8 10.0 0.4 9.6 17.8 1.8 13.0 10.3 1 2.75 1
1/9 5.0 0.5 4.5 10.0 2.2 16.0 13.3 1 2.75 1
45.0 3.6 40.1 83.6 2.1 79.8 65.0 13.0 14.8 3.0
1/12 10.0 3.1 5.9 12.1 2.1 15.0 13.3 1 1.75 1
1/13 10.0 1.5 8.5 19.5 2.3 14.8 11.8 1 3 1
1/14 10.0 2.4 7.4 17.0 2.3 15.1 12.5 1 2.63 1
1/15 10.0 1.3 8.8 17.5 2.0 15.0 12.5 1 2.5 1
1/16 4.0 1.8 3.3 5.9 1.8 17.5 14 1 3.5 1
44.0 10.0 33.8 72.0 2.1 77.4 64.0 12.8 13.4 2.7
1/19 7.8 1.0 6.8 14.4 2.1 14.3 13.3 1 1 1
1/20 7.8 1.1 6.6 13.5 2.0 10.9 7.75 1 3.13 1
1/21 7.8 0.4 7.6 14.8 1.9 15.3 12.3 1 3 1
1/22 7.8 1.8 6.0 13.0 2.2 11.0 7.5 1 3.5 1
1/23 4.0 1.3 2.8 5.3 1.9 13.1 9 1 4.13 1
35.0 5.5 29.8 60.9 2.0 64.5 49.8 10.0 14.8 3.0
1/26 7.8 2.8 4.3 7.6 1.8 8.9 7.75 1 1.13 1
1/27 7.8 1.6 5.1 9.6 1.9 12.0 8.25 1 3.75 1
1/28 7.8 2.1 5.0 9.3 1.9 8.8 7 1 1.75 1
1/29 7.8 0.6 7.3 11.9 1.6 11.6 8.25 1 3.35 1
1/30 4.0 0.0 0 0
35.0 7.1 21.6 38.4 1.8 41.2 31.3 7.8 10.0 2.5
2/2 4.0 0.0 6.0 10.8 1.8 12.3 10.3 1 2 1
2/3 4.0 0.6 3.5 6.6 1.9 0.0 0 0
2/4 4.0 2.4 1.6 2.6 1.6 0.0 0 0
2/5 4.0 1.0 3.0 4.5 1.5 13.8 12.8 1 1 1
2/6 4.0 0.8 3.3 5.6 1.7 0.0 0 0
20.0 4.8 17.4 30.1 1.7 26.0 23.0 11.5 3.0 1.5
2/9 5.0 1.4 3.6 7.0 1.9 0.0 0 0
2/10 5.0 1.8 3.3 5.6 1.7 15.0 13 1 2 1
45
2/11 5.0 0.0 5.0 9.1 1.8 0.0 0 0
2/12 5.0 2.1 2.9 5.5 1.9 16.8 15.3 1 1.5 1
2/13 5.0 1.5 3.5 7.1 2.0 0.0 0 0
25.0 6.8 18.3 34.4 1.9 31.8 28.3 14.1 3.5 1.8
2/16 5.0 2.4 2.6 5.1 2.0 0.0 0 0
2/17 5.0 1.5 3.5 7.9 2.3 14.4 14 1 0.4 1
2/18 5.0 1.9 3.1 6.6 2.1 0.0 0 0
2/19 5.0 1.3 3.8 9.1 2.4 14.6 13 1 1.6 1
2/20 5.0 3.0 2.0 4.6 2.3 0.0 0 0
25.0 10.0 15.0 33.4 2.2 29.0 27.0 13.5 2.0 1.0
2/23 5.0 1.5 3.5 8.9 2.5 0.0 0 0
2/24 5.0 1.5 3.5 6.4 1.8 18.0 16.5 1 1.5 1
2/25 5.0 1.6 2.4 4.5 1.9 0.0 0 0
2/26 5.0 0.6 3.4 7.4 2.2 14.0 11 1 3 1
2/27 5.0 1.5 3.5 6.9 2.0 0.0 0 0
25.0 6.8 16.3 34.0 2.1 32.0 27.5 13.8 4.5 2.3
3/2 5.0 1.8 3.3 6.4 2.0 0.0 0 0
3/3 5.0 2.3 2.8 6.1 2.2 18.3 15 1 3.25 1
3/4 5.0 1.5 2.5 4.4 1.8 0.0 0 0
3/5 5.0 1.0 3.0 7.1 2.4 13.0 11 1 2 1
3/6 5.0 2.3 2.8 6.5 2.4 0.0 0 0
25.0 8.8 14.3 30.5 2.1 31.3 26.0 13.0 5.3 2.6
3/9 6.0 2.1 3.9 7.3 1.9 11.8 10.3 1 1.5 1
3/10 6.0 1.3 4.8 11.0 2.3 0.0 0 0
3/11 6.0 1.9 4.1 8.1 2.0 15.0 14 1 1 1
3/12 6.0 0.3 4.8 10.3 2.2 0.0 0 0
3/13 6.0 1.8 2.8 7.0 2.5 15.0 12 1 3 1
30.0 7.3 20.3 43.6 2.2 41.8 36.3 12.1 5.5 1.8
3/16 6.0 1.6 3.4 6.5 1.9 0.0 0 0
3/17 6.0 0.9 3.1 6.8 2.2 16.1 15 1 1.13 1
3/18 6.0 1.3 4.3 9.1 2.1 0.0 0 0
3/19 6.0 1.4 4.6 10.0 2.2 12.0 12 1 0 1
3/20 6.0 1.8 4.3 9.3 2.2 0.0 0 0
30.0 6.9 19.6 41.6 2.1 28.1 27.0 13.5 1.1 0.6
3/23 6.0 2.0 4.4 8.8 2.0 21.5 20 1 1.5 1
46
3/24 6.0 2.0 4.0 8.6 2.2 0.0 0 0
3/25 6.0 1.9 4.3 8.9 2.1 18.0 17.3 1 0.75 1
3/26 6.0 1.6 4.3 8.9 2.1 0.0 0 0
3/27 6.0 2.3 3.8 7.5 2.0 19.3 17.8 1 1.5 1
30.0 9.8 20.6 42.6 2.1 58.8 55.0 18.3 3.8 1.3
3/30 7.0 0.6 5.4 10.4 1.9 0.0 0 0
3/31 7.0 1.1 5.9 11.9 2.0 13.8 11 1 2.75 1
4/1 7.0 0.9 5.1 10.0 2.0 0.0 0 0
4/2 7.0 1.0 7.0 11.6 1.7 17.8 15.5 1 2.25 1
4/3 7.0 1.0 5.8 12.4 2.2 0.0 0 0
35.0 4.6 29.1 56.3 1.9 31.5 26.5 13.3 5.0 2.5
4/6 7.0 1.4 5.4 12.0 2.2 22.3 20.8 1 1.5 1
4/7 7.0 1.0 6.0 12.9 2.1 0.0 0 0
4/8 7.0 1.8 4.9 9.9 2.0 19.3 16.8 1 2.5 1
4/9 7.0 1.3 4.6 10.5 2.3 0.0 0 0
4/10 7.0 1.9 5.1 10.6 2.1 19.8 17.3 1 2.5 1
35.0 7.3 26.0 55.9 2.1 61.3 54.8 18.3 6.5 2.2
4/13 7.0 2.0 5.0 9.4 1.9 0.0 0 0
4/14 7.0 2.3 4.8 9.6 2.0 22.0 17 1 5 1
4/15 7.0 2.0 4.9 9.1 1.9 0.0 0 0
4/16 7.0 2.1 3.9 7.6 2.0 18.8 15.3 1 3.5 1
4/17 7.0 0.5 5.5 11.0 2.0 1.0 1 1 1
35.0 8.9 24.0 46.8 1.9 41.8 33.3 11.1 8.5 2.8
4/20 7.0 0.4 4.5 9.4 2.1 19.9 16 1 3.85 1
4/21 7.0 1.3 4.8 9.6 2.0 0.0 0 0
4/22 7.0 2.0 4.0 8.0 2.0 15.4 11.5 1 3.85 1
4/23 7.0 3.3 2.9 5.0 1.7 0.0 0 0
4/24 7.0 2.4 2.3 5.1 2.3 12.3 10.8 1 1.5 1
35.0 9.3 18.4 37.1 2.0 47.5 38.3 12.8 9.2 3.1
4/27 7.0 2.8 4.1 8.5 2.1 12.0 10.3 1 1.75 1
4/28 7.0 2.6 4.4 9.5 2.2 0.0 0 0
4/29 7.0 2.8 4.3 8.8 2.1 13.1 11.3 1 1.8 1
4/30 7.0 2.0 5.0 10.8 2.2 0.0 0 0
5/1 7.0 1.4 4.5 10.3 2.3 15.5 12.8 1 2.75 1
35.0 11.5 22.3 47.8 2.1 40.6 34.3 11.4 6.3 2.1
47
5/4 7.0 1.9 4.0 7.8 1.9 13.5 11 1 2.5 1
5/5 7.0 2.1 3.9 8.5 2.2 0.0 0 0
5/6 7.0 2.9 4.0 10.5 2.6 11.0 8.75 1 2.25 1
5/7 7.0 3.1 3.9 7.6 2.0 0.0 0 0
5/8 7.0 2.9 4.1 7.8 1.9 14.5 11.5 1 3 1
35.0 12.9 19.9 42.1 2.1 39.0 31.3 10.4 7.8 2.6
5/11 7.0 1.9 4.8 10.9 2.3 11.8 10 1 1.8 1
5/12 7.0 2.3 4.8 10.1 2.1 0.0 0 0
5/13 7.0 3.1 2.9 5.9 2.0 12.4 9.75 1 2.63 1
5/14 7.0 1.5 5.1 10.3 2.0 0.0 0 0
5/15 7.0 1.1 2.9 5.6 2.0 13.1 11 1 2.13 1
35.0 9.9 20.4 42.8 2.1 37.3 30.8 10.3 6.6 2.2
5/18 7.0 2.3 3.4 7.0 2.1 13.6 11.3 1 2.38 1
5/19 7.0 2.3 4.6 8.6 1.9 0.0 0 0
5/20 7.0 2.6 4.3 9.6 2.3 14.3 12 1 2.3 1
5/21 7.0 2.1 4.3 8.6 2.0 0.0 0 0
5/22 7.0 3.0 4.4 9.4 2.1 12.9 10.3 1 2.63 1
35.0 12.3 20.9 43.3 2.1 40.8 33.5 11.2 7.3 2.4
5/26 7.0 3.6 3.4 7.1 2.1 0.0 0 0
5/27 7.0 5.5 2.3 4.6 2.1 16.0 15 1 1 1
5/28 7.0 4.0 3.3 6.0 1.8 0.0 0 0
5/29 7.0 2.3 3.8 7.0 1.9 13.3 10.5 1 2.75 1
28.0 15.4 12.6 24.8 2.0 29.3 25.5 12.8 3.8 1.9
6/1 8.0 1.6 6.4 13.1 2.1 12.5 10 1 2.5 1
6/2 8.0 3.5 3.9 6.8 1.7 0.0 0 0
6/3 8.0 3.9 3.3 6.5 2.0 16.8 14.5 1 2.25 1
6/4 8.0 3.1 4.3 8.6 2.0 0.0 0 0
6/5 8.0 2.0 3.0 4.9 1.6 15.0 12.5 1 2.5 1
40.0 14.1 20.8 39.9 1.9 44.3 37.0 12.3 7.3 2.4
6/8 8.0 1.0 5.9 11.8 2.0 10.4 9.25 1 1.1 1
6/9 8.0 3.0 3.8 7.9 2.1 10.3 8.25 1 2 1
6/10 8.0 1.8 5.8 12.3 2.1 9.5 8.25 1 1.25 1
6/11 8.0 2.1 5.9 13.3 2.3 10.3 8.25 1 2 1
6/12 8.0 1.5 5.5 11.3 2.0 11.3 10 1 1.25 1
40.0 9.4 26.8 56.4 2.1 51.6 44.0 8.8 7.6 1.5
48
6/15 8.0 1.1 4.9 9.9 2.0 9.3 8 1 1.25 1
6/16 8.0 1.8 6.5 13.4 2.1 12.5 10.3 1 2.25 1
6/17 8.0 1.0 6.0 12.4 2.1 10.5 8 1 2.5 1
6/18 8.0 1.0 5.9 10.8 1.8 9.4 7.1 1 2.25 1
6/19 8.0 1.8 6.0 11.6 1.9 10.0 8.5 1 1.5 1
40.0 6.6 29.3 58.0 2.0 51.6 41.9 8.4 9.8 2.0
6/22 8.0 1.1 5.8 12.3 2.1 10.6 8.5 1 2.1 1
6/23 8.0 1.0 7.0 14.0 2.0 9.0 7 1 2 1
6/24 8.0 2.3 6.9 11.5 1.7 9.8 7.75 1 2 1
6/25 8.0 2.8 5.3 9.9 1.9 12.4 10.3 1 2.1 1
6/26 8.0 3.8 3.8 7.3 1.9 10.0 8.25 1 1.75 1
40.0 10.9 28.6 54.9 1.9 51.7 41.8 8.4 10.0 2.0