assignment-emcm (contract management) q3

Upload: izam-muhammad

Post on 03-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    1/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 1 of 24

    Question 3

    Your company has a 2-year, RM 80 million construction contract that has got into troubles.

    The problems include:

    Soil problems that necessitate additional RM 5 million of concrete piles and 2-month

    delay.

    Material price was up 20%.

    Transportation cost was up by 30%.

    Shoddy work by two sub-contractors has necessitated re-work causing RM 3 million

    and a delay of 1 month.

    Long monsoon season with heavy rain and flood caused a aggregate delay of two

    months.

    The consultant modified the design which caused RM 5 million worth of re-work

    (including tear-down, clearing and re-build) and 2-month delay (including re-design

    time).

    Work efficiency is only 70% of original estimate

    The client (owner) has threatened to sue your company for the delays and claim

    penalties of RM 100,000 per day.

    Your company may be facing huge direct financial losses and possible litigation. Your boss

    put the blame on the project manager, who is your colleague, and he was removed from the

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    2/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 2 of 24

    project and subsequently asked to resign. You have been assigned by the management to take

    over the project.

    This is the golden opportunity for you to show off your skills, and to avoid the prospect of been

    sacked!

    Describe how you would manage the contract.

    Be specific, i.e., solve the problems one by one. Dont just give general approaches. You are

    solving a problem in this particular case study. Use all the knowledge and skills you have

    learnt from the Contract Management module. You are encouraged to use your initiatives.

    Present your solution with the following headings: Status Definition, Solution Approach,

    Resolution of the legal and contractual problems, Strategy for Modern Contract Management,

    Solutions of problems.

    (Approx. 2 to 4 marks for each of the first four sections, rest for solution section)

    [TOTAL: 20 MARKS]

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    3/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 3 of 24

    Answer 3;

    The original contract worth is RM 80 million and the construction contracts duration is to be

    completed in 2 years. Assumption was made that this is a government project, the Director of

    JKR is the Superintending Officer (S.O) and the power was delegated to JKR District

    Engineer. The project name is The Proposed Construction of Academic Building, Dental

    Hospital, Hostel and Infrastructure Works for the Faculty of Dentist UITM Sungai Buloh,

    Selangor Darul Ehsan. Also assumed that the contract is bounded by JKR (PWD) 203a

    conditions of contract where bill of material is form part of the contract and shall also referred

    to The Commercial Law of Malaysia.

    Figure 1: Traditional Building Contract (BEM Bulletin, Sep-Nov 2007).

    It is important to overcome the current difficulties, disadvantage and under pressure situation

    and turn it to a better position. The proposal to overcome this situation shall be structured as

    follows;

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    4/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 4 of 24

    1. Status Definition.

    2. Solution Approach.

    3. Resolution of the legal and contractual problems.

    4. Strategy for Modern Contract Management.

    5. Solutions of problems.

    1. Status Definition.

    This is a traditional contract where client (JKR) initiates and sanctions of a project, concept

    design was done by the architect and the design engineering consultant who are the one who

    design and prepare all the necessary document for tender. The company is now facing huge

    direct financial losses, progress claims was freeze due to some unresolved issues and possible

    litigation. The former project manager was removed from the project and I have just been

    assigned by the management to take over the project.

    In any contract three main criteria which are the time,cost andacceptableperformance with

    safety and sustainability are upmost important to determine the project success. In order to

    achieve that the commercial issue which is the cash flow and the adequate time are very-very

    important or else the project cannot be running smoothly. We had analysed the project current

    situation and it can be summarised as follows;

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    5/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 5 of 24

    Table 1: Summary of Estimated Delay and Forecast Additional Cost Incurred.

    No Description Delay Cost (RM)

    i) Soil Problems, additional concrete piles (fallunder provisional quantities)

    2 months 5.0 Million

    ii) Material price was up 20%. 3.0 Million(Assumption)

    iii) Transportation cost was up by 30% 0.3 Million(Assumption)

    iv) Shoddy work by two sub-contractors hasnecessitated re-work

    1 months 3.0 Million

    v) Long monsoon season with heavy rain andflood 2 months

    vi) The consultant modified the design whichcaused to re-work and additional design time.

    2 months 5.0 Million

    vii) Work efficiency dropped to 70% of originalestimate productivity

    2 months 1.0Million(Assumption)

    viii) The client (owner) has threatened to sue yourcompany for the delays and claim penalties ofRM 100,000 per day.

    Not

    effective

    yet

    Max 10% of

    Contract Value 8

    Million (estimated)

    Total 9 months 25.3 Million

    Note:Marked inblue - Consultant/Client issues

    Marked inred - Contractor issues

    Project progress claims have been very little since a couple of monthsduring the monsoon

    and floodas the work progress is affected very badly. In the same time due to the shoddy

    works by our two sub-contractors, our progress claims under their portion were not being

    approved and not paid. These had tarnished the project cash flow very badly and had caused

    thepayment to suppliers, sub-contractors, machineries and even the wages to our in house

    workers were also two months delayed. Due to this the project had loose its momentum and

    productivities were reduce to 70%.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    6/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 6 of 24

    Need to carry out additional pilling works due to soil issue, estimated cost incurred RM 5

    million with two months additional time. In addition JKR had requested their consultant to

    redesign some building section where all of this had resulted to some reworks and

    additional to existing job scope. This shall involve quite extensive amount of money where

    RM 5million worth of re-work (including tear-down, clearing and re-build) and 2-month

    delay (including re-design time) shall be required.

    Due to petrol/diesel hikes, natural disaster and redevelopment for those affected countries e.g.

    Japan, Australia, New Zealand, United States and others, currently the company need to

    absorb the materials and transportation escalation costsof 20% and 30% in which these had

    worsened the project cash flow. The project will be at lost shall we are forced to absorb all

    these additional cost not to mentioned the heavy penalty/LAD of approximately RM

    100,000.00 per day for 9 month which is surely additional of RM 8 million (Normally,

    maximum LAD is limited to 10% of the contract value).

    The company shall requires additional funding to finance theadditional incurred cost of RM

    25.3 million and may requires additional time of nine (9) months to complete all these

    works shall no step or action taken to resolve them via contractually approach. Additional

    32% of cost from the total contract value (25.3 million / 8 million X 100 = 32%) is very huge

    and surely cannot be covered with the 15% (12 million) estimated net profit. In addition RM 4

    million (5% of the contract value) are deducted gradually from the claims and shall be retained

    for 12 months after the completion date as retention money.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    7/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 7 of 24

    Basically all the matter arises here can be portrayed in these followings figures;

    Figure 3: Provisional Quantities in Conjunction to PWD Form 203a Condition of

    Contract Clause 26.5 to 26.7.

    Chart 4: S.Os Instruction and Variation are in Conjunction to PWD Form 203a Condition

    of Contract Clause 5.0 to 24.0.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    8/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 8 of 24

    Chart 3: Failure to Complete on Time (BEM Bulletin, Sep-Nov 2007).

    Chart 4: Price Escalation Who Will Pay??? (BEM Bulletin, Sep-Nov 2007).

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    9/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 9 of 24

    2. Solution Approach.

    I believe collaboration approaches between contractor, consultants and client is the best

    strategy to overcome this issues. After all Conditions of Contract in PWD Form 203a is a

    very established form of contract and the most important is it offers a very fair deal to all the

    parties involves. We can fight for our right via collaboration approach and win-win strategy.

    However shall the matter have been left for a length of time and therefore some personnel that

    represent the parties involves might leaved the project either resigned or being assigned to

    another project, the solution even via collaboration also not as simple as it take especially

    when the person who give the instruction is no more in the picture.

    The good working relations between all the parties involves i.e. the client, consultant and

    contractor that have the spirit of partnering and sharing the common goal objectives to

    complete the project within budgeted cost, scheduled time and at acceptable performance with

    safety and sustainability shall ease the collaboration and the negotiation of all parties in

    finding the best solution methods to resolves these issues.

    In partnering and collaboration contract approach, it can lower the risk of time and cost

    overrun as the parties including the contractor, client and consultant are working together

    towards the completion of the project and to complete them on time. This understanding of all

    parties involve are also reducing the exposure to litigation. Less confrontation and a good

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    10/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 10 of 24

    working environment and trust contribute the fast solving problems before they escalate to

    disputes. The project performance and quality are improved because energies are focused to

    achieve the project goal and not misdirected to adversarial concerns.

    The partners shall proactively anticipate and try to solve or avoided the problems. Variations if

    happen mean they are really genuine and unavoided. With a good communications and

    empowerment by senior management this shall be able to reduce the need of lawyers in the

    administration. Good communication allows all parties to resolve issues expeditiously as they

    can meet up frequently and this shall avoid mistake or rework. The opportunity for financial

    successful also increased because of non adversarial or win-win attitude on all parties.

    3.Resolution of the legal and contractual problems.

    It is part of a project manager responsibility find an equitable, speedy and cheap method of

    resolving disputes and maintains focus on the project. In my opinion collaboration and

    cooperative attitude among all parties involves including the client (JKR), consultant and

    contractor is still the best method to resolve all the issues and disputes face in this project

    however shall it is fails we still have other options as proposed by alternative dispute

    resolution approach as tabulated in Table 1, below;

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    11/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 11 of 24

    Table 2: Dispute Resolution Steps

    Steps Cost/

    Hostility

    Name Process

    1 Low Prevention Risk allocation, Incentive for cooperation, Partnering

    2 Negotiation Direct negotiation, Step negotiations

    3 Independent

    Expert

    Dispute review board, Standing arbitrator or Independent

    expert.

    4 Mediation Non-binding resolution, Mini-trial, Advisory opinion,

    Advisory arbitration.

    5 Arbitration Binding resolution6 High Litigation Civil Court, Judge

    In my opinion and based from my previous experiences, all the issues arise here are straight

    forward and can be resolved in conjunction to PWD Form 203a Conditions of Contractand

    the Contract Document. If all parties have the spirit of partnering and sharing common goal all

    these issues can be amicably resolved. Despite collaboration approach, negotiation is another

    good approach to resolve all the crops up issues. In normal practice contractor shall approach

    and convince the consultant and JKR especially on the variation orders that results to schedule

    and commercial impacts.

    The project team shall require to search for any documents that might help to support our

    claim on the variation, escalation cost, provisional quantities and E.O.T., The document might

    come in various forms e.g. Sites Instruction (if any), Notification of Change (if any), proof of

    any instruction written on site diary, instruction recorded in the Minute of Meetings, soil

    investigation report, piling records, rain records recorded in site diary and materials invoices,

    PWD Cost of Index for escalation cost and etc.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    12/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 12 of 24

    Convincing the consultant earlier then the client (JKR) might also help to resolve these issues.

    Maybe we should approach their COW and their RE and put all the issues, stories and issues

    to them for their understanding and for them to chew first. This can be done over a coffee talk,

    golf game or even a karaoke session. That is where good communication and interpersonal

    skill is very important. Later the consultant may give their good recommendation to the client

    shall we managed to explain them properly and convincingly about the problems faced. This

    can be followed appending all the issues, who responsible for it and how to solve in the

    weekly or monthly meetings with that is attended by the consultant and the client/JKR.

    It might creates a havoc as the quantities is quite big and not been highlighted in advance but

    this is unavoided as that should be done by the earlier project manager. We will also include

    all the issue arises in the coming biweekly or monthly report. After that notification about

    these issues can be forwarded concurrently to both the consultant and the client (JKR). In

    order to avoid an upset the client (JKR) we can also approach them separately. That is where

    in modern contract management, good relations between all parties are important as after all

    everybody are sharing the common goal to complete the work in time.

    Theorically most of the issues arises are unavoidable and allows by the contract and therefore

    with a good communication skill and approach might be able to achieve a mutual

    understanding and solution. Shall everybody are transparent to each other, have a high respect

    and understanding these issues can be easily be resolved cordially.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    13/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 13 of 24

    We shall then submit the detail justification and variation claim where normally it will be

    followed by a few meetings as the consultant and the client want to know these issues in more

    detail. Shall the consultant and the client agreed to the change order/variation and the EOT

    that have been submitted, another meeting shall normally be called in order to quantify and

    negotiate for the additional cost and EOT required.

    Basically the following issues shall fall under the stipulated clause of the PWD 203a

    Conditions of Contract;

    Soil problems that necessitate additional RM 5 million of concrete piles and 2-month

    delay. - fall under clause 26.0 Bill of Quantities, Sub-clause Provisional Quantities 26.5,

    26.6 and 26.7 and additional time should fall under clause 43.0 Delay and EOT.

    Material price was up 20% - fall under clause 30.0 Fluctuation of Price.

    Transportation cost was up by 30% - fall under clause 30.0 Fluctuation of Price.

    Shoddy work by two sub-contractors has necessitated re-work causing RM 3 million and

    a delay of 1 month fall under clause 10.1 Obligation of the Contractor sub-clause i).

    Long monsoon season with heavy rain and flood caused a aggregate delay of two months

    - Clause 43.1 b) exceptionally inclement weather and clause 57.0 Effect of Force Majeure

    sub-clause 57.2 c) can be used to apply for extension of time clause 43.0 Delay and EOT.

    The consultant modified the design which caused RM 5 million worth of re-work

    l(including tear-down, clearing and re-build) and 2-month delay (including re-design

    time). - This fall under Clause 5.0 S.O.S Instruction and Clause 24.0 Variations. To apply

    for extension of time clause 43.0 Delay and EOT.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    14/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 14 of 24

    Work efficiency is only 70% of original estimate fall under 10.1 Obligation of the

    Contractor sub-clause i) to complete the works on time. It is the responsibility of the

    contractor to accelerate the works progress in order to get the work progress back to

    right track.

    The client (owner) has threatened to sue your company for the delays and claim penalties

    of RM 100,000 per day. fall under clause 40.0 Damages for Non-Completion but this

    can be avoided as most of the issues are actually subject to EOT in conjunction to clause

    43.0 Delay and EOT.

    In my opinion and through my past experiences dealing with various clients including JKR, all

    the above issues are not so serious as for most of them we have the basis to make claim for

    extra quantities, variation claims and EOT. I believed with the right approach, proper

    documentations, convincing justifications and sufficient proof and supporting documents, all

    these issues can be settled amicably. Most of the issues are actually allowed by the

    Conditions of Contract of JKR/PWD Form 203a. The most important thing we need to

    notify and justify to the consultant and JKR what make we feel we are entitle for the variation,

    additional claims on provisional sum and the EOT.

    In worst scenario shall some of our request being rejected although they are allowed by the

    contract conditions, we can bring this matter to arbitration court. Litigation although it is

    legally allowed in the contract law in the other hand is not advisable as it will be carried out

    openly and might not favourable by the client. One thing for sure although our intention is to

    protect the companys right and to recover from loses we also do not want this exercise to

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    15/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 15 of 24

    tarnish any parties and our potential for future job with them and other project provider might

    also notice this as well and may not favourable to our action. Arbitration in the other hand

    shall be carried out in a close court and can be settled quietly.

    4. Strategy for Modern Contract Management.

    In modern contract management win-win solution approach to all the parties involves is

    something that everybody is looking forward to achieve best. In modern contract management

    traditional approach which full with adversarial confliction should be avoided. Win-lose

    strategy in traditional adversarial attitude might put the project in jeopardy. Conflicting does

    not help the project to succeed. In modern contract management all the parties involved should

    sharing the common goals which is to complete the project within budgeted cost, scheduled

    time and at acceptable performance with safety and sustainability.

    Treating all the parties as smart partner can plays a key role in attaining continuous

    improvement especially in delivering of the construction project. The spirit of partnering

    approach treats contractors as own resources, motivate them, recognition of commons goal

    create atmosphere of trust, teamwork and goodwill which will facilitate this goals. Working in

    a good working atmosphere shall ease all parties in discussing sharing ideas and making a

    good decision shall any problem arise. By conflicting we not only will failed to solve the

    problems but might go deeper into trouble.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    16/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 16 of 24

    In the other hand prolong or avoidance of problems and the issues faced are not giving the

    project any good. All parties should understand that we are actually in this mess together and

    therefore in making the project into a success all parties involves should give their best

    commitment and to trust each other in solving the problems and achieving the mutual goals.

    All parties should sit down and discuss about the project problems and what is the best

    approach to resolve are the issues. For instance all parties involve should accept their fault

    shall any, fairly treatment to other parties, to fulfil each party obligations as what have been

    stipulated in the Conditions of Contract, to work as a team, and etc. in order to lead the

    project towards a success. Owner and contractor work together to manage the risk and achieve

    a better result for both parties.

    Client also need to safeguards and to protect the contractors against unforeseen risks and

    circumstances beyond their control for their mutual benefits. The key to all of this is

    communication, consideration and anticipation for risk how to solve them before they occurs.

    Farsighted project contract management Ex-ante Incentivization that plan incentives in

    advance normally adopted to goverment projects where project risk are between low to

    medium. In the other hand Ex-post Governance were used where the risk need to be monitored

    closely to allow adaptation to deal with uncertainty or unforeseen events that can caused

    incompleteness.

    The following conclusion was made by the contractor on who should be responsible for each

    problem arises;

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    17/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 17 of 24

    Table 3: Proposed Amicably Solution as Per Modern Contract Management Strategy.

    No Description of Problems Responsibility of Proposed Solution

    1 Soil problems that necessitate additional

    RM 5 million of concrete piles and 2-

    month delay. Under ProvisionalQuantities)

    Client To allow contractor

    claim for extra

    quantities underProvisional Quantities /

    re-measured items and

    to grant EOT.

    2 Material price was up 20%. Client Client to issue VariationOrder under Fluctuation

    of Price (Building CostIndex).

    3 Transportation cost was up by 30%. Client Client to issue Variation

    Order under Fluctuation

    of Price.

    4 Shoddy work by two sub-contractors has

    necessitated re-work causing RM 3

    million and a delay of 1 month.

    Main Contractor

    and sub-

    contractor

    Main Contractor to

    ensure the re-works is

    carried out either by the

    sub-contractors or

    themselves.

    5 Long monsoon season with heavy rain

    and flood caused an aggregate delay oftwo months.

    Client Client to issue EOT.

    6 The consultant modified the design which

    caused RM 5 million worth of re-work

    (including tear-down, clearing and re-

    build) and 2-month delay (including re-

    design time).

    Client/Consultant Client to issue Variation

    Order and grant EOT

    7 Work efficiency is only 70% of original

    estimate.Main Contractor Main Cont to accelerate

    the work at their owncost to fulfil their

    contractual obligation.

    8 The client (owner) has threatened to sueyour company for the delays and claimpenalties of RM 100,000 per day.

    Main ContractorSubject towhether the

    requested EOT is

    sufficient or not.

    Negotiation and requestfor the EOT.

    Note:Marked inblue - Consultant/Client issues

    Marked inred - Contractor issues

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    18/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 18 of 24

    5. Solutions of problems.The following is our strategy on how to settle these problems;

    a) Commercial Issues;Additional RM 25.3 million estimated shall be required in order to complete the works and to

    pay the LAD and the statuses are tabulated below;

    Table 4: Estimated Commercial Impact and their Solution.

    No Description Cost (RM) What to do

    i) Soil Problems additional concretepiles (Under Provisional Quantities)

    5.0 Million To notify the Consultant and

    JKR on Extra amount under

    Provisional Quantities and

    request EOT.

    ii) Material price was up 20%. 3.0 Million(Assumption)

    To notify the Consultant and

    JKR request Variation Order

    and EOT.

    iii) Transportation cost was up by 30%. 0.3 Million

    (Assumption)

    To notify the Consultant and

    JKR request Variation Orderand EOT.

    iv) Shoddy work by two sub-contractorshas necessitated re-work.

    3.0 Million To notify the sub-contractors

    v) Long monsoon season with heavyrain and flood

    To notify the Consultant and

    JKR request EOT.

    vi) The consultant modified the designwhich caused to re-work and

    additional design time.

    5.0 Million To notify the Consultant and

    JKR and request Variation

    Order and EOT.

    vii) Work efficiency dropped to 70% oforiginal estimate productivity.

    1.0Million(Assumption)

    Catch up plan to increase

    productivity by adding

    resources.viii) The client (owner) has threatened to

    sue your company for the delays and

    claim penalties of RM 100,000 per

    day.

    Not effective yet

    8 Million

    (estimated)

    Max 10% of Contract Value

    Shall request for EOT.

    Total 25.3 Million

    Note:Marked inblue - Consultant/Client issuesMarked inred - Contractor issues

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    19/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 19 of 24

    The details of action and justification to be made shall be as follows;

    i. Due to soil problems that necessitate additional RM 5 million of concrete piles and the

    project was delayed 2 months because of it. Under Bill of Quantities Contract, the

    concrete piles quantities should fall under clause 26.0 Bill of Quantities, Sub-clause

    Provisional Quantities 26.5, 26.6 and 26,7 Therefore despite we can actually claim the

    additional quantities under re-measured items we can also apply for extension of time due

    this issue under clause 43.0 Delay and EOT.

    In addition shall we refer to the case of, The Privy Council held in the case of Mitsui

    Construction Co v. Attorney of Hong Kong (1986) 33 BLR 1 that quantities for certain

    works in the BQ under re-measurement contract are wildly wrong (in this case

    substantially increased) and contractor was entitled to higher rates for those works.

    ii. Material price was up 20% due to patrol hikes and a lot of development going on in

    almost in every part of the world which had push the materials cost to an upward trend. In

    JKR 203a there is a clause that allows claims for escalation on materials. It is under clause

    30.0 Fluctuation of Price.

    iii. Transportation cost was up by 30% due to patrol hikes and increase on maintenance and

    spare parts cost. The clause 30.0 Fluctuation of Price of the Contract Conditions shall be

    used.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    20/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 20 of 24

    iv. Shoddy work by two sub-contractors has necessitated re-work causing RM 3 million and

    a delay of 1 month. The two sub-contractors are actually the nominated sub-contractors

    for this project, under clause 61.0 stated no liability to the government because of the

    nominated sub-contractor/supplier failure to do their job. But being our sub-contractor we

    can either instruct them to repair or re-do their shoddy job or we can deduct their claims

    and retention money and seeking the S.O. approval either to do it ourselves or to engage

    other sub-contractors. After all the payments to nominated sub-contractor/supplier are

    made direct to them deducted from the main contractor claims. Therefore shall our claim

    are not approved due to their shoddy job, they also shall not got their claims. Clause 60.0

    Payment to Nominated Sub-Contractor or supplier.

    v. Long monsoon season with heavy rain and flood caused an aggregate delay of two

    months. Clause 43.1 b) exceptionally inclement weather and clause 57.0 Effect of Force

    Majeure sub-clause 57.2 c) can be used to apply for extension of time clause 43.0 Delay

    and EOT.

    vi. The consultant modified the design which caused RM 5 million worth of re-work

    (including tear-down, clearing and re-build) and 2-month delay (including re-design time).

    This additional works should be fall under Clause 5.0 S.O.S Instruction and Clause 24.0

    Variations, where the price shall later being discussed and agreed by all parties. The

    agreed addition/omission shall be later be adjusted to the contract sum. To apply for

    extension of time clause 43.0 Delay and EOT.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    21/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 21 of 24

    Referring to section 71 (Act 136) Contract Act 1950 stated, Where a person lawfully

    does anything for another person, or delivers anything to him, not intending to do so

    gratuitously, and such other person enjoys the benefit thereof, the latter is bound to make

    compensation to the former in respect of, or to restore, the thing so done delivered.

    (Emphasis supplied). Case of Aw Yong Wai Choo & Ors v. Arief Trading Sdn Bhd. &

    Anor [1992] 1 MLJ 166 are referred.

    vii.Work efficiency is only 70% of original estimate fall under 10.1 Obligation of the

    Contractor sub-clause i) to complete the works on time. It is the responsibility of the

    contractor to accelerate the works progress in order to get the work progress back to right

    track.

    viii. The client (owner) has threatened to sue your company for the delays and claim penalties

    of RM 100,000 per day. Maximum of RM 8 million as max LAD are limited to 10% of

    Contract Value. I believed it should fall under clause 40.0 Damages for Non-Completion

    but this can be avoided as most of the issues are actually subject to EOT in conjunction to

    clause 43.0 Delay and EOT.

    The company shall required additional funding to finance the additional RM 25.3 million

    which consists of RM 13.3 million that we feel a claimable amounts from client due to

    variation to original scope of works and provisional sum and RM 3 million for repair/redo the

    shoddy works and RM 1 million for accelerating the works progress for catch up plan

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    22/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 22 of 24

    including increase resources e.g. manpower, machineries, longer working hours and etc and 8

    million for the LAD (maximum of 10% of the contract value).

    However wemight be able to recover RM 3 million for the shoddy works from the two sub-

    contractors or to instruct them to carry out the repair and redo works at their cost. Although

    contractually we can recover them from the two sub-contractors but there is a possibility it is

    not going to happen after all their performance bond is only 10% of their work value of RM 5

    Million which is only worth RM 500, 000.00. Good news is the client (JKR) has not paid their

    work portion yet therefore the sub-contractors might not have the capacity and money to carry

    out the redo works.

    My suggestion is, to buy the raw materials and supply required machineries in order to assist

    our sub-contractor but they need to supply the manpower and supervision. Later all these

    additional cost shall be deducted from the sub-contractors claims. One thing for sure they must

    be agreed but both parties and necessary notices and meeting need to be carried out to make

    them legally minuted in order to avoid any future argument. Another alternative is to take over

    the sub-contractors works and to be deducted accordingly from their contract.

    Shall the cost are more we can either forfeit their performance bond and bring them to

    arbitration court or litigation or to absorb the excess cost..

    My proposal requires us to spend extra RM 1 million from our own pocket for the catch up

    plan but shall this can be carried out within the approved period of EOT,this might enable us

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    23/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 23 of 24

    to avoid from paying high penalty or LAD. The partnering spirit and our effort to drive the

    work progress back to the right track might be sufficient to convince the consultant and client.

    b) Delay Proposed EOT Required.

    Below is how we strategise to resolve the delay issue;

    Table 5: Showing How Many EOT Required in Completing all Problematic Issues.

    No Description Delay Month

    M1 M2 M3 M3

    i) Soil Problems, additional concrete piles(Provisional Quantities)

    2 months

    ii) Material price was up 20%.

    iii) Transportation cost was up by 30%

    iv) Shoddy work by two sub-contractors has

    necessitated re-work

    1 months

    v) Long monsoon season with heavy rain and flood 2 months

    vi) The consultant modified the design which causedto re-work and additional design time.

    2 months

    vii) Work efficiency dropped to 70% of originalestimate productivity

    2 months

    viii) The client (owner) has threatened to sue your

    company for the delays and claim penalties of RM

    100,000 per day.

    Total Required EOT 4 months

    Note:Marked inblue - Consultant/Client issues

    Marked inred - Contractor issues

    Total extension of time (EOT) required shall be as the above table, where due to long

    monsoon and flood (this incident had occurred) we need a replacement of two months the

  • 7/28/2019 Assignment-EMCM (Contract Management) Q3

    24/24

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Q 3 - Page 24 of 24

    effected works can be carried out concurrently with the additional pilling works due to soil

    problems. For the change of design, this activity shall be carried out immediately after the

    piling works completed. This because the sequence of works as the pilling works needs to be

    completed before we could build the building structure. For this activity we are also entitled

    for EOT therefore in total only four months additional numbers of days are required. Two

    months additional duration also requires to carry out the acceleration works and one month for

    the repair/redo works as the result of our sub-contractors fault, we will also carry out them

    concurrently and to complete them within the requested EOT duration.

    By doing this weshall complete all of the said activities within the four (4) months required

    additional periods and possibly no penalty/LAD will be imposed to us. As mentioned earlier

    I personally feel that with win-win approach all these issues can be amicably resolve and the

    common goal of completing the project within budgeted cost, scheduled time and at

    acceptable performance with safety and sustainability can be achieved. It is important for

    every party involve giving a high respect to each other right and acting accordingly in

    conjunction to the conditions of contract fairly for everybody benefit and towards achieving

    the project common goals.

    All in all as other issues are more or less under control, we only need to spend additional cost

    of RM 1 million for the acceleration of works and shall be given VO and the provisional

    quantities amounted of RM 13.3 million. In which RM 5 million for additional concrete piles

    (provisional quantities), RM 3 million for materials escalation, RM 300 thousand for

    transportation escalation cost and RM 5 million for the rework due to the change in design.