april 2017 full beam - overhead cranes | port … 2017 | project of the month project of the month |...
TRANSCRIPT
APRIL 2017 | P R O J E C T O F T H E M O N T H P R O J E C T O F T H E M O N T H | APRIL 2017
6 | April 2017 | www.hoistmagazine.com www.hoistmagazine.com | April 2017 | 7
FULL BEAMAn Indonesian manufacturer of pre-stressed concrete beams has installed 16 CXT overhead cranes from Konecranes to optimise production at its plant in Surabaya.
PT Waskita Beton Precast
(WSBP) has a target capacity
of around 3.25m tonnes of
concrete beams this year,
which will be used for construction and
infrastructure projects, including flood
mitigation structures, maritime piling
and structures, as well as road, rail
bridge, and civil engineering works.
The company worked with Konecranes
and Konecranes’ East Java agent PT
Jakarta Prima Cranes (JPC) to install
16 CXT cranes. The cranes feature full
inverter control, for speed, safety and
precision, and log travel speeds of 100m
a minute to increase efficiency.
The cranes are a combination of single
and double girder types, with capacities
of 8–10t, and feature tandem operation
where required for hoisting wide, long
and heavy concrete and steel loads.
The precision modelling, specification
and engineering involved in preparing for
the installation was overseen by a global
collaboration between WSBP’s parent
company PT Waskita Karya (Persero)
Tbk, led by the plant manager of WSBP’s
Sidoarjo plant Bidaruni Anggarawati, with
JPC’s on-site personnel and Konecranes
SEA operation extensively supported by
engineers at Konecranes’ head office in
Finland.
The new installation of Konecranes
replaced slower and less efficient mobile
cranes used as an interim measure since
the Surabaya plant opened a year ago.
JPC sales manager Siat Tjie Djiang said:
“Obviously when you are handling long
and heavy beams—6–20m, weighing
3–15t—safety is a top priority. Not only
must any risk of collision be curtailed,
but also the process must be robustly
engineered to continue to reliably
provide an uninterrupted supply to vital
infrastructure projects.
“Because reliability is essential, PPC
and Konecranes spent more than two
months partnering with the customer,
settling all the technical specifications
and design criteria. This meant we were
able to supply Konecranes’ latest proven
lifting technologies complete with
suitable statutory compliance, technical
and design requirements based on actual
usage.
“We believe this is the first-ever
successfully installed full inverter
control system with 100m/min long
travel speeds, coupled with anti-sway
technology and comprehensive safety
devices for precast applications.
“All 16 cranes incorporate inverter
control for smoother travelling motion,
meaning better load control compared to
one- or two-speed contactor control. All
lift, cross travel and long travel speeds
are tailored to the exact application.”
Safety devices also include overload
protection, upper/lower limit switch,
cross travel and long travel limit switch,
anti-collision devices and thermal
protection for the motors. ●
006_007hst0417potm.indd 6-7 08/05/2017 14:10