ral 27 april 2006the beta-beam task, eurisol1 status of the beta-beam study mats lindroos on behalf...
TRANSCRIPT
RAL 27 April 2006 The beta-beam task, EURISOL 1
Status of the beta-beam study
Mats Lindroos on behalf of the EURISOL beta-beam task
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 2
Outline
The beta-beam Progress on a conceptual design
EURISOL beta-beam facility Challenges for the beta-beam Conclusions
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 3
The EURISOL beta-beam facility!
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 4
Beta-beam R&D The EURISOL Project
Design of an ISOL type (nuclear physics) facility. Performance three orders of magnitude above existing facilities. A first feasibility / conceptual design study was done within FP5. Strong synergies with the low-energy part of the beta-beam:
Ion production (proton driver, high power targets). Beam preparation (cleaning, ionization, bunching). First stage acceleration (post accelerator ~100 MeV/u). Radiation protection and safety issues.
Subtasks within beta-beam task ST 1: Design of the low-energy ring(s). ST 2: Ion acceleration in PS/SPS and required upgrades of the existing machines
including new designs to eventually replace PS/SPS. ST 3: Design of the high-energy decay ring. Around 38 (13 from EU) man-years for beta-beam R&D over next 4 years (only within
beta-beam task, not including linked tasks).
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 5
Design study objectives
Establish the limits of the first study based on existing CERN accelerators (PS and SPS)
Freeze target values for annual rate at the EURISOL beta-beam facility Close cooperation with neutrino physics community
Freeze a baseline for the EURISOL beta-beam facility
Produce a Conceptual Design Report (CDR) for the EURISOL beta-beam facility
Produce a first cost estimate for the facility
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 6
Challenges for the study
Production Charge state distribution after ECR source The self-imposed requirement to re-use a maximum
of existing infrastructure Cycling time, aperture limitations etc.
The small duty factor The activation from decay losses The high intensity ion bunches in the accelerator
chain and decay ring
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 7
Intensity distribution during acceleration
30% of first 6He bunch injected are reaching decay ring Overall only 50% (6He) and 80% (18Ne) reach decay ring
Normalization Single bunch intensity to maximum/bunch Total intensity to total number accumulated in RCS
Bunch20th
15th
10th
5th1st
total
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 8
Power losses - comparison
Nucleon losses compared PS and SPS comparable for CNGS and bb operation PS exposed to highest power losses
Ploss/l [ions] Beta-beam
CNGS 6He 18Ne
RCS - 0.17 0.14
PS 3.3 2.2 2.8
SPS 0.25 0.4 0.25
Power loss per unit circumference of a machine
machinecycle
lossloss ncecircumferet
cycleElP
*
//
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 9
Dynamic vacuum
Decay losses cause degradation of the vacuum due to desorption from the vacuum chamber
The current baseline includes the PS, which does not have an optimized lattice for unstable ion transport and has no collimation system The dynamic vacuum degrades to
10-5 Pa in steady state (6He)
An optimized lattice with collimation system improves the situation by two orders of magnitude
1.00E+08
1.00E+09
1.00E+10
0 5 10 15 20 25 30 35
s [m]
6L
i lo
ss
es
[/0
.1m
/6s
-cy
cle
]
P. Spiller et al., GSI
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 10
Merging
Achieving >90% merging efficiency of injected particles
Some ions are already collimated before having been stacked for 15 (20) merging cycles
2 4 6 8 10 12 14
0.5
0.6
0.7
0.8
0.9
Ions
stor
ed/io
nsin
ject
ed
t [s]
5 10 15 20
0.4
0.5
0.6
0.7
0.8
0.9
Ions
stor
ed/io
nsin
ject
ed
t [s]
6He
18Ne
S. Hancock, CERN
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 11
Inje
cted
/mer
ged
collimated
decayed
Decay ring - Momentum collimation
After 15 (20) merges 50% (70%) of the injected 6He (18Ne) ions are pushed outside the acceptance limits.
Momentum collimation required. Dispersion region; multi stage collimation system
Space required: placed in “unused” straight section
Collimation power corresponds to 150 kW average to MW peak level during the bunch compression process
compression process lasts a few hundred milliseconds
A. Chance et al., Saclay
He6 Ne18 LHC p+ LHC Pb
100 100 7461 2964
T/ion (GeV) 555 1660 7000 574000
τrepetition (s) 6 3.6 10h 10h
Number of stored ions 9.71 1013 7.4 1013 3.2 1014 4 1010
Stored beam energy (MJ) 8.8 19.7 2 x 362 2 x 3.81
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 12
aperture [cm]
Pow
er lo
ss [W
/m]
Decay ring - Decay losses
Decay products originating1) from straight section2) in arcs
1) are extracted at the first dipole in the arc, sent to dump
2) Arc lattice optimized for absorption of decay products To accommodate either ion species, the half-aperture
has to be very large (~ 8cm for the SC dipoles).
Absorbers take major part of decay losses ion arcs. About 60 W each SC dipoles still have to stand <10 W/m.
A. Chance et al., Saclay
-0,1
0,0
0,1
0,2
0,3
2300 2350 2400
HorizontalVertical
s (m)
envelopes (m)
Fluorine extraction
Bρ(18F9+) ≈ 621 T.m
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 13
Production
Major challenge for 18Ne Workshop at LLN for production, ionization
and bunching this summer New production method proposed by C.
Rubbia!
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 14
Production ring with ionization cooling (C. Rubbia, A.Ferrari, Y.Kadi and V. Vlachoudis)
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 16
Using existing PS and SPS, version 2Space charge limitations at the “right flux”
Space charge tune shift Note that for LHC the corresponding values are -0.078 and -0.34
[μm] 6He 18Ne RCS inj 16.4, 8.8 16.4, 8.8 PS inj 6.6, 3.5 4.0, 2.1 SPS inj 0.8, 0.4 0.5, 0.3
6He 18Ne RCS inj -0.019 -0.078 PS inj -0.11 -0.20 SPS inj -0.090 -0.15
Transverse emittance normalized to PS acceptance at injection for an annual rate of 1018 (anti-) neutrinos
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 17
The slow cycling time.What can we do?
Production
PS
SPS
Decay ring
Ramp time PS
Time (s)0 8
Wasted time?
Ramp time SPS
Reset time SPS
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 18
Accumulation at 400 MeV/u
2 4 6 8 10
Accumulationtime
21018
41018
61018
81018
11019
1.2 1019
Annualrate 6HeT1/2=1.67 s
T1/2=17 s
T1/2=0.67 s
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 19
Stacking
0.2 0.4 0.6 0.8 1
25000
50000
75000
100000
125000
150000
Multiturn injection with electron cooling
Half life [s] 0.1 1 10Tvacuum [s] 30 30 30Intensity ions [every 100 ms in 30 microsceonds] 104 5 105 5 105
Tcool[ms] 100 100 100Number of turns 10 10 10Final emittance [micrometer] 0.1 0.1 0.1Final number of particles in stack 3 104 3 107 3 108
2 4 6 8 10 12
Time [s]
0
2
4
6
8
Beam
Inte
nsity [
E8 ions]
beam lifetime : 6.5s
Linac III rep rate : 2.5 HzIon beam energy : 4.2 MeV/uElectron energy : 2.35 keVElectron current : 105 mA
Average accumulated intensity : 6E8 ionsPeak intensity : 7.1E8 ions
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 20
150Dy
Partly stripped ions: The loss due to stripping smaller than 5% per minute in the decay ring
Possible to produce 1 1011 150Dy atoms/second (1+) with 50 microAmps proton beam with existing technology (TRIUMF)
An annual rate of 1018 decays along one straight section seems as a realistic target value for a design study
Beyond EURISOL DS: Who will do the design? Is 150Dy the best isotope?
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 21
Long half life – high intensities
At a rate of 1018 neutrinos using the EURISOL beta-beam facility:
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 22
Gamma and decay-ring size, 6He
Gamma Rigidity
[Tm]
Ring length
T=5 T
f=0.36
Dipole Field
rho=300 m
Length=6885m
100 938 4916 3.1
150 1404 6421 4.7
200 1867 7917 6.2
350 3277 12474 10.9
500 4678 17000 15.6
Civil engineering
Magnet R&D
New SPS
RAL 27 April 2006 The beta-beam task, EURISOLBeta-beam
requirements, 23
In 2008 we should know
The EURISOL design study will with the very limited resources available give us: A feasibility study of the CERN-Frejus baseline A first idea of the total cost An idea of how we can go beyond the baseline
Resources and time required for R&D Focus of the R&D effort
Production, Magnets etc.