Scope of Contract & Details
The purpose of this contract is to provide round the clock
support services to Mechanical Maintenance at ISRPL. This shall
include Static Maintenance, Fabrication Jobs, Scaffolding,
Process Assistance Services etc. at ISRPL as per Scope of Work.
SCOPE OF SUPPLY
PART-A: SCOPE OF OWNER'S SUPPLY
1) Owner will issue the following materials as free of charge
(unless otherwise stated) like plates, flanges, pipes & pipe
fittings, all types of valves, gaskets, nuts & bolts/studs,
gland packing, nozzles, structural steel (Except for Structural
Steel SOR with Contractor Material), lube oils, grease, cotton
waste/cloth etc. shall be supplied as free issue materials from
owner's store or from any other specified location within the
ISRPL Premises. However, contractor has to keep the record of
all the materials issued to them for reconciliation purpose.
2) Crane, Hydra, Forklift will be provided subject to
availability as Free of Charge. Transportation referred in
Contract refers to Transportation within ISRPL Premises.
3) Utility: Utility requirement like Plant Water, Plant Air (
5-6 kg/cm2),Instrument Air(5-6 kg/cm2), nitrogen( 6-7 kg/cm2)
and electricity will be supplied by ISRPL free of charge. For
electricity ISRPL will provide nearest welding receptacle or
single phase power connection. Necessary extension to be done
by contractor with proper cabling as per ISRPL standard and
safety rules and regulations.
4) ISRPL shall provide special PPE's to the workers Free of
Charge like Online Breathing Apparatus, PVC Suits, Canister
Mask.
5) Office Space in Porta Cabin and open space for placing ISO
Container for storing tools/tackles. The space for storage shall
be limited to 20 Feet by 8 Feet. The same needs to be vacated/
removed at the end of Contract Period.
PART-B: SCOPE OF CONTRACTOR'S SUPPLY
1) Contractor has to carry out the job on round the clock basis
with minimum time to complete all jobs within schedule.
2) Contractor has to follow all safety & contractual rules &
regulation of the company every time.
3) All PPE's except special PPE(Point 4 in Scope of Owner's
Supply) is within Contractor's Scope of Supply. It must be
ensured that all items are ISI/CE certified and in good
condition. Contractor should ensure that PPE's are in sufficient
quantity at site.
4)All tools/tackles including non-spark tools,
skilled/unskilled manpower, welding/gas cutting machine,
grinding sets, DP test materials, Hydro testing pump, emery
paper, wire brush, PPE (except special PPE, under Owner Scope),
manual & hydraulic trolley (min 2 nos each),scaffolding
materials all types of consumables & tools (as indicated in
SOR's) etc. This is applicable for all manpower & job-rate SOR's.
5) Above scope of supply is indicative only and not exhaustive
and therefore all other materials/ facilities which has not been
specifically mentioned in ISRPL scope of supply shall be
supplied by the contractor to complete the job in all respect
as per direction of Engineer-in-charge.
6) All electrical appliances like grinding machine, welding
machine shall be properly guarded and supply board must be fitted
with required rating of ELCB. All the machines certified by
Electrical Maintenance Department and only the machines declared
'Fit for Use' shall be allowed at site. (Refer Annexure-1).
7) All lifting tools and tackles including lifting slings of all
capacities should have a valid Load Test Certificate issued by
Govt Approved Agencies. All test certificates to be maintained
by the Contractor and a copy of the same should be submitted to
EIC. All certificates must be identifiable with the equipment.
8) All gas cutting equipment shall be properly fitted with flash
back spark arrestor fitted at both ends (cylinder and cutting
torch end).
9) Compressed Gas Cylinder like Argon, Oxygen, Oxy-Acetylene
should be checked as per the Compressed Gas Cylinder Checklist
and records should be maintained by the Contractor. A copy of
the same must be submitted to EIC. The Contractor should be able
to produce the records of the Compressed Gas Cylinder inside the
complex as and when asked by EIC.
10) Work Permit System of ISRPL shall be followed in without
fail. Accordingly, the contactor shall be responsible for
coordinating the necessary approvals and clearances of different
departments. These activities shall be completely in
contractor's scope and shall not be payable extra.
11) The Contactor shall be responsible for site preparation for
Fabrication Jobs, Confined Space Jobs, Work at Height etc. These
activities shall be completely in contractor's scope and shall
not be payable extra.
12) After completion of job, scrap removal & area cleaning has
to be carried out by the contractor at no extra cost.
13) The Contractor has to follow the SOP for all type of Jobs.
14) Contractor has to deploy desirable manpower as mentioned.
Any additional manpower mobilization as per requirement of work
/ job plan and as advised by EIC/site engineer, shall be arranged
by the contractor without any additional cost
15) Contractor is required to mobilize their resources required
to carry out the job within the time frame to complete the job
as per technical specification, instruction, and satisfaction
of the EIC /Site Engineer.
16) Measurements of all job done and Manpower Mobilized must be
submitted to EIC within 1 day of the execution of Jobs. Work
Measurement Sheets and Attendance Sheets should be complete in
all aspects including Permit Nos, Resource Consumed etc.
17) Reports & Information System: Contractor shall be required
to submit daily reports in approved format for proper
documentation & monitoring. Additionally, monthly reports shall
be submitted covering the physical and financial progress of the
contract.
18) If desired by EIC, the Contractor has to prepare the estimate
for the jobs before starting of the job.
19) If any manpower needs to overstay to compensate for the
absenteeism of the manpower, OT Payment shall not be paid by
ISRPL. The same needs to be borne by the Contractor. However,
if any manpower on supply is overstaying beyond normal working
hours owing to plant requirement as required by EIC, OT Payment
shall be paid by ISRPL.
Special Note for Fabrication Jobs:
1) Welder Certification: Welder certification will be done as
per ASME/Inspection Department Procedure. Welder has to undergo
the qualification procedure at ISRPL. Qualification of the
Welder will be at the sole discretion of ISRPL Inspection
Department. All the test pieces to be brought by the contractor
and any cutting, grinding, welding or any other activities
required for testing shall not be paid. As per ASME Section IX-
2nos bend test is required for the welder qualification, and
alternative is radiography or UT, initial qualification is based
on mechanical test and later test can be covered by alternative
method based on welder performance. These activities shall be
completely in contractor's scope and shall not be payable extra.
2) Contractor has to maintain sufficient stock of DCP Fire
Extinguishers (2 Nos), Fire Water Hose (4 Nos), Non-Asbestos
Fire Blankets (10 Nos) etc for execution of the Fabrication
Jobs. This is completely in contractor's scope
3) Electrode & Filler Wire: Contractor has to use approved
manufacturer & brand of electrode and filler wire and submit
manufacturer batch test certificate and physical verification
has to be done before any use. In case of any discrepancy,
Contractor has to test that lot as per ASME section IIC latest
edition.
If any Electrode/Filler Batch Number Test Certificate is not
submitted for review and found to be used at site, that joint
should be cut and re weld on Contractor cost.
For new manufacturer which is not in approved vendor list have
to conduct electrode qualification test as per ASME section IIC
latest edition. Recommended Brands are Adhor, D&H Secheron, Esab
or brands as per ISRPL approved Vendors.
Vendor is also responsible for baking of Low hydrogen electrode
as per approved ISRPL procedure. As per ISRPL Procedure 1 nos
of Electrode Oven has to be maintained at site.
a) Holding oven for each welder using lower hydrogen electrode
upto 100 degC.
Initial calibration done through manufacturer or other lab and
next calibration done at site by ISRPL Inspection Department.
4)DPT and DPT Test Kit: Contractor shall use approved
Manufacturer & Brand of PT Material. Recommended brands are
Megnaflux, Flowcheck, Orion.
Contractor has to submit Manufacture Test Certificate and
physical verification of batch number with MTC is required.
DPT Test shall be performed by ASNT Level I Person or Person who
has been authorized by ISRPL Inspection Department. ISRPL may
authorize a person after 20 hrs of internal training and
assessment.
5) Contractor shall be responsible for offering jobs for Stage-
Wise and Final Inspection of jobs as per QAP i.e. Fit-Up, Final
Weld inspection, PT Test, Radiographs for interpretation, Hydro
Test, Pneumatic Test, Painting etc.
Any activity not cleared by Inspection Department shall not be
considered for billing and preparation of Inspection Report is
in Contractor's Scope.
6) Contractor shall use calibrated measuring instruments and has
to submit Instrument List with Calibration Status. All
instruments shall be in sound condition with proper
identification and date of revalidation on instruments, it
includes pressure gauges, etc.
7) Contractor shall be responsible for maintaining the material
traceability as per approved ISRPL procedure, in case of any
discrepancy the cost of Check Test (Tensile and Chemical) shall
be recovered from the Contractor.
8) The Pipe Fabrication SOR's are applicable for new pipelines
and modification of pipelines. In case of modification of
pipelines cutting of the joints (includes Socket and Butt
joints) shall be paid separately only if there is any extra
cutting compared to number of welding joints. There are no
separate SOR for Field Joints.
9) Manpower as per Annexure-2 must be tentatively deployed for
Fabrication Jobs
Special Note for Cold Works:
1) Contractor must have sufficient manpower and Tools and
Tackles for the execution of Jobs.
2) Contractor shall maintain minimum 2 nos of Non-Spark Tool
Box.
3) Manpower as per Annexure-2 must be tentatively deployed for
Cold Work.
4) Use of Iron Hammer is not allowed at site without written
permission in the Work Permits. By default, Brass/Non-Spark
Hammers are to be used.
5) Any box-up of Flange, Equipment etc shall be inclusive of
leak testing. Any rework during leak testing eg gasket
replacement, realignment etc will not be paid separately.
6)The Details of Exchanger are as per List provided separately
-Exchanger Details at ISRPL
7) Details of few Cold Work SOR is as per List provided
separately-Details of Few Cold Work SOR
Special Note for Scaffolding Jobs:
1) The job is meant for providing scaffolding for various
maintenance activities like Mechanical, Civil and Instrument and
Electrical maintenance works in ISRPL Complex.
2) Contractor shall strictly follow ISRPL's SOP/Work Instruction
of scaffolding erection and dismantling.
3) The job shall be irrespective of nature & period like routine
maintenance and shutdown. In shutdown the quantity requirement
may shoot up very high (Approx- 4 times) in short time.
4) The contractor must have sufficient resources to mobilize
sufficient quantity of scaffolding materials, manpower and
transportation of the same for erection and dismantling of
scaffolding on short notice i.e within 24hrs for emergency jobs
and within 14 days for shutdown jobs.
5) Contractor shall necessarily have the following minimum
scaffolding materials for successful completion of job within
time. Contractor should have at least one trolley for carrying
scaffolding pipes inside the plant premises.
i).Scaffolding pipe of different size(as per IS:1239 Medium
Duty)
a. 6 meter MS Plain pipe-400 nos
b. 4 meter MS Plain pipe -400 nos
c. 3 meter MS Plain pipe -200 nos
d. 2 meter MS Plain pipe -200 nos
ii). Base plate (Anti-skid feature) 200 each
iii). Scaffolding Jaali (MS) different size 200 each
iv). Aluminium ladder of different height (6 Feet, 10 feet, 12
feet, 20 feet,long etc.)-12 nos
v). Scaffolding fix clamp -3000 nos
vi). Cuplok Horizontal
a.HZ-3 meter -200 nos
b.HZ-2.5 meter-200 nos
c.HZ-2 meter -200 nos
d.HZ-1.5 meter-200 nos
e.HZ-1 meter -200 nos
vii). Cuplock Vertical
a.VL-3 meter-200 nos
b.VL-2.5 meter-200 nos
c.VL-2 meter-200 nos
d.VL -1.5 meter-200 nos
e.VL-1 meter-200 nos
viii). Spigot- 200 nos
ix). Adjustable base plate- 200 nos
6) The scaffolding material shall be kept in position i.e. inside
ISRPL complex till the completion of intended job and no extra
claim shall be entertained on this ground.
7) The scaffolding can be renewed only after 21 days and half
rate of the same can be charged depending upon the type mentioned
in SOR.
8) Contractor shall erect model scaffolding duly checked and
certified by Maintenance and Fire & Safety Department , in ISRPL
Complex (about 1~2 in numbers). These activities shall be
completely in contractor's scope and shall not be payable extra.
9) No wooden planks / bamboo/ coir or manila rope shall be used
in scaffolding.
10) The metallic plank used for working platform, toe board,
ladders shall be tied with the ledger / transom pipe strictly
with the scaffolding clamp/ metallic wire only.
11) Manpower as per Annexure-2 must be tentatively deployed for
Scaffolding Jobs
12) Before any planned shutdown the requirement of scaffolding
materials and extra manpower shall be jointly accessed by EIC &
contractor representative and contractor has to arrange the
additional materials and necessary manpower for taking up the
shutdown job in the stipulated time.
13) All the scaffolding material shall be as per following
specification only (13.1 to 13.4).
13.1 PIPES
1. All pipes shall be of Medium Class of 40 mm Nominal Bore size
as per IS 1239 and painted.(minimum specification)
2. All the Pipe ends be preferably blocked/plugged by welding a
cap.
3. All the pipes should be straight and without any
damage/corrosion.
13.2 CLAMPS/SLEEVE COUPLER
1. All the clamps must be of forged material only and sleeve
couplers should be of pressed steel
2. There should be no visual damage and corrosion.
2. Each coupler/clamp shall be capable to handle minimum 1.5 Ton
of load without slippage or distortion. The same may be tested
at ISRPL on sample basis.
4. All the clamps and sleeve couplers shall be Hot Dip galvanized
as per IS 4736.
5. Length of the coupler must not be less than 150 mm.
6. For extension purpose, each pipe should be connected with
other pipe only by means of Sleeve coupler.
13.3 BASE PLATE
1. Base plate size should be a mild steel square plate of 150
X 150 X 6mm thick with 38mm dia. X 150mm long spigot at center.
2. The Spigot (Pipe) should be properly welded and visually
there should be no damage and corrosion.
13.4 SCAFFOLDING JAALI
1. All Jaali shall have a square pipes welded properly without
any bending. Each square pipe of Jaali should have minimum 2.0
mm thickness.
2. There should be no corrosion on pipes and visual damage.
Special Note for Painting Jobs
1) All painting consumables needs to be duly approved by
Inspection Department. Paints shall be of reputed make like
Berger, Asian Paints, ICI, Shalimar or brands as per ISRPL
approved Vendors.
2) The painting has to be done as per the SOP and QAP laid down
by the Inspection Department
Special Conditions of Contract
1. Penalty for damaging property of ISRPL due to negligence of
manpower during maintenance work is 10000 Rs.
2. Failure to mobilize manpower as per Job Schedule/shift
schedule/Requirement will attract penalty for 10000 Rs per
instance if the same is affecting the plant uptime or resulting
in extended maintenance time.
ANNEXURE-1
The Electrical Equipment shall be certified based on the
following criteria. The 'Fit for Use' Certificate will be issued
for 6 months beyond which it will have to be renewed.
Welding Machine:
*Equipment Name plate should be available otherwise manufacturer
test certificate should be available
*63A, 415 V 30mA ELCB with Box for internal protection.
*Input And output Cable Properly Connect with Cable Gland.
*Indication Lamp For Main Supply Indicate should be healthy
condition.
*Earthing Cable for Body Earthing with one side proper lugs and
one side crocodile clamp.
*4 core 4 sq-mm Input cable length required should me minimum
20 meter without any joint.
*Outgoing welding cable without any joint and both length
(Positive and Negative) are same.
*Welding Machine Physical condition good and all screw and bolt
available in machine without missing.
*Machine current variable knob should be available.
Grinding, Cutting and Drilling Machine:
*Equipment Name plate should be available otherwise manufacturer
test certificate should be available.
*Input Cable properly connect with machine without any joint
with plug top, (As per machine Rating)
*Grinding and cutting machine wheel guard and key should be
proper assembled.
Extension Board:
*20A 30 mA 2 pole ELCB as per required Load installed in
Extension board.
*Extension board installed in frame and proper covered.
*Extension board cable required 3 core 2.5 Sq-mm minimum 25
meter.
*Extension board physical good condition with all screw and
bolts.
*Extension board internal terminal should be connect properly.
ANNEXURE-2
A) The tentative total manpower mobilization at site shall be
as below:
1) Site-In-Charge- 1 Nos
The Person shall have minimum experience of 5 years and should
have managed similar sites in the past.
2) Supervisor-5 Nos
1 nos for A,B & G Shifts for Cold Work and 1 No for
Scaffolding and 1 No for Fabrication Jobs. The person shall
have minimum 3 years of experience in similar type of jobs.
3)Fabrication Gang comprising of
Fabrication Fitter 1 Nos
Welder 1 Nos (CS and SS all positions, MMAW and GTAW)
Gas Cutter 1 Nos
Grinder 1 Nos
Rigger 2 Nos
Helper 2 Nos
4)Cold Work
Static Work Fitter 6 Nos
Rigger 13 Nos
Helper 14 Nos
5)Scaffolding Work
Scaffolders 5 Nos
B) The Contractor shall mobilize additional Supervisor, if
required, as per the instruction of EIC, without any additional
cost.
C) Fabrication Gang and Scaffolding Gang will be working in G-
Shift Monday to Saturday. In case of emergency requirement,
Contractor should be able to mobilize additional manpower and
work on round the clock basis.
D) Cold /Static & Work Manpower Deployment (Point No:4)
A Shift: 1 No- Static Work Fitter, 2 Nos-Rigger, 2 Nos-Helper
(On Job Rate Basis) AND 1 No Rigger, 1 No Helper (On Manpower
Basis)
B Shift: 1 No- Static Work Fitter, 3 Nos-Rigger, 3 Nos-Helper
(On Job Rate Basis) AND 1 No Rigger, 1 No Helper (On Manpower
Basis)
C Shift: 1 No- Static Work Fitter, 3 Nos-Rigger, 3 Nos-Helper
(On Manpower Basis)
G Shift: 3 No Static Work Fitter, 3 Nos Rigger, 4 Nos Helper (On
Job Rate Basis)
E) All Manpower will be working in A, B, C and G Shift.
Contractor must have sufficient Manpower to give rotational
weekly-off to the manpower. All G-Shift shall have Sunday as
Weekly -Off. Shift Manpower should be available on all days.
F) Contractor must have sufficient number of Supervisors to meet
the above requirements.
G) For Heat Exchanger, Painting Jobs: Contractor may be required
to mobilize extra skilled manpower as and when the job comes.
H) Contractor has to mobilize additional resources to attend any
eventuality including unplanned shutdown, short shutdown,
breakdown & other top priority job, which shall be executed on
round o' clock basis.
I) Based on Job requirement, the Contractor in consultation with
EIC, may increase or decrease manpower from the mobilized
manpower. This must have prior authorization from EIC.
J) During Bi-Weekly Cleaning usually 1 Day per week contractor
shall have to mobilize total 19-20 manpower to complete the job
in 10hrs.
K) During Grade Change-Over Cleaning usually 2 Day per month
contractor shall have to mobilize additional 19-20 manpower to
complete the job in 32hrs.
Annexure-3
Indicative List of PPE for the Contractor's Scope of Supply:
1) Safety Googles
2) Ear Plugs
3) Hand Gloves (Cotton, PVC, Heat Resistant etc)
4) Overall(Boiler Suit for all personals)
5) Safety Helmet (Yellow Colour)
6) Safety Shoes
7) Welding Helmet
8) Googles for Grinder
9) Apron for Welder/Grinder
10) Safety Belt (Double Hook) duly Certified with fall
arrestor.
11) Safety Net
12) Life Line
Above list of PPE is indicative and not exhaustive and therefore
all other PPE which has not been specifically mentioned in ISRPL
scope of supply shall be supplied by the contractor to complete
the job safely in all respect as per direction of Engineer-in-
charge.
ANNEXURE-4
Indicative List of Equipment/Tools and Tackles for the
Contractor's Scope of Supply:
1) Welding Rectifier Machine (3-Phase) with MMAW and GTAW
Welding arrangement -2 Nos
2) Welding Machine (1-Phase) with MMAW Welding Arrangement-1 Nos
3) Grinding Machine with Consumables (AG-7, AG-5, FF2)- In-
Sufficient Nos
4) Gas Cutting Set with Accessories- 1 Set
5) Drilling Machine with Magnetic Base (upto 32mm)-As and when
reqd
6) Plasma Cutting Machine -As and when reqd
7) Electrode Drying Oven -2 Nos
8) Chain Pulley Block (5-10 MT) with variable chain length-5 Nos
9) Chain Pulley Block (1-3 MT) with variable chain length -5 Nos
10) D-Shackles, Wire Rope Slings, Belts etc- In-Sufficient Nos
11) Mechanical Tools for general Maintenance and Heavy Rigging
(Spanners upto 90mm, Hammers, Brass Hammers, Chisel etc) -
In-Sufficient Nos
12) Electrical Extension Boards-In-Sufficient Nos
13) Non-Sparking ToolBox-3 Nos
14) Hydro Test Hand Pumps-2 nos
15) Material Shifting Trolley (Manual & Hydraulic Hand Trolley)
2 Nos each
Above list is indicative and not exhaustive and therefore
Contractor has to bring all tools and tackles/ equipment
required to complete the job safely in all respect as per
direction of Engineer-in-charge.
DETAILS OF FEW COLD WORK SOR
Item No/ SOR No
Short Description/ Long Description UOM No of Manpower
Approximate time for execution
15 COLUMN TRAY WORK
10004043
STRIPPER COLUMN INSPECTION The scope shall involve inspection of Column Tray, tightening, replacement of missing fasteners, gaskets etc. All labour charges, tools and tackles, transportation of materials etc is in Contractor's Scope. The job has to be completed to the full satisfaction of EIC. Note: Any Blinding/ De-blinding, Scaffolding will be paid separately.
Lumpsum 2 4
17 ROTARY EQPT OPEN/BOX-UP CLEANING
10003284
ROTARY EQPT OPEN/BOX-UP-CLEANING The scope shall involve opening/box-up of Rotary Equipment casing, seal for cleaning/dechoking. The job shall be done under the guidance of the ISRPL Engineer. All equipment piping shall be paid separately as per relevant SOR. Supply of labour, tools and tackles, consumables, transportation of spares/damaged components etc. will be in Contractor's Scope. All spares is in ISRPL Scope of Supply. Any special tools required shall be provided by ISRPL. Rotary Equipment Open and Box-Up for cleaning/dechoking purpose. Only opening or Box-up will be considered as half a unit measurement.
NO 3 3
18 DEWATERING PRESS CAGE OPENING/BOX-UP
10002446
The Scope invloves opening and Box-Up of Dewatering Press Cover, Cage, Coupling Guards, Exhaust Duct Cover. Supply of labour, tools and tackles, consumables, transportation of spares/damaged components etc. will be in Contractor's Scope. All spares is in ISRPL Scope of Supply. Both side opening and Box-up will be considered as a unit measurement. one side opening or box-up shall be considered as 0.25 unit measurement.
NO 4
1)4 Hrs to open and Box-Up using
Pneumatic Tools
2) 6 Hrs to open and Box-Up
manually
19 DISINTEGRATOR MAINTENANCE
10002447
DISINTEGRATOR SCREEN GRATES OPEN AND BOX-UP The Scope involves opening and box-up of Disintegrator Screen Grates.Supply of labour, tools and tackles, consumables, transportation of spares/damaged components etc. will be in Contractor's Scope. All spares is in ISRPL Scope of Supply. All opening and reinstallation of 3 nos
NO 3 1 Hrs to
Open and Box-Up
Screen Grates installed in one machine will be considered as a unit measurement. Note: Inspection Window Opening/Box-Up is included.
10003283
DISINTEGRATOR OPEN/BOX-UP CLEANING The Scope invloves opening and Box-Up of Disintegrator for dechoking/cleaning purpose. This scope shall involve 1)Opening and Box-Up of 5 Nos 10 inch 150# Plate Flange 2)Opening and Box-Up of Hopper with one side 1.143m x 0.876m and 1 Nos 10 inch 150# Plate Flange. The Hopper is approximately 600 mm long 3)Installtion/Removal of Venturi approximately 120 kg weight. 4)Disintegrator Inspection Windows Open and Box-Up 2 nos 0.25m x 0.2m, 2 nos 0.3m x 0.35m
NO 5 1.5 Hrs
20 RUBBER DRYER MAINTENANCE
10003281
DRYER TOP COVER OPEN/BOX-UP The Scope invloves opening and Box-Up of Dryer Top Cover.Only opening or Box-up will be considered as half a unit measurement.
NO 4 20 minutes
10003282
DRYER FAN SIDE PLATE OPEN/BOX-UP The Scope invloves opening and Box-Up of Dryer Fan Side Plate.The size of side plate is 1m x 0.35m and 1mm thick. This is fixed by 4 nos screw. Only opening or Box-up will be considered as half a unit measurement.
NO 1 10 minutes
21 SHAKER SCREEN OPEN AND BOX-UP
10002448
The Scope involves opening and box-up of Shaker Screen Screens etc. Supply of labour, tools and tackles, consumables, transportation of spares/damaged components etc. will be in Contractor's Scope. All spares is in ISRPL Scope of Supply. Complete Shaker Screen Opening and Box-up will be considered as a unit measurement. Part Disassembly/Assembly shall be considered on fraction basis.
NO 3
2.5 Hrs to open and Box-Up
manually
22 INCLINED CONVEYOR CLEANING AND ALIGNMENT
The Scope involves cleaning of Inclined Conveyor Rollers, Belt Alignment, Rubber Scrapper Replacement. Supply of labour, tools and tackles, consumables, transportation of spares/damaged components etc. will be in Contractor's Scope. All spares is in ISRPL Scope of Supply.
10002449 Cleaning of Tail or Head Pulley and One Time Alignment
NO 2 3 Hrs
10002451 Complete Cleaning of Inclined Conveyor and One Time Alignment
NO 4 5 Hrs
10002452 Belt Alignment NO 1 1 Hrs
10002453 Rubber Scrapper Replacement M 2 1 Hrs
23 MINOR MAINTENANCE WORK ON CONVEYORS AND FILM WRAPPING MACHINE
10002454
The scope involves minor maintenance activities like roller replacement, greasing, chain/belt adjustment or replacement, chain sprocket adjustment, motor replacement, adjustment/replacement of levelling screws, structural adjustment, sealing strip replacement, installation of Acrylic Sheets etc. Supply of labour, tools and tackles, consumables, transportation of spares/ damaged components etc. will be in Contractor's Scope. All spares is in ISRPL Scope of Supply. Conveyors as per Tag No will be considered as a unit measurement.
NO 2 1 Hrs
32 HYDRO & PNEUMATIC TEST
10004044
LEAK TEST_STATIC EQUIPMENT Leak test of static equipment (Like Pipe, Vessel, Exchangers etc) with water/air. Contractor shall connect Vessel with Utility connection by hose and perform leak test of flange joint and exchanger tube at available utility pressure. Rubber hose,water and Hose coupler will be in ISRPL's scope. Any blinding/deblinding and flange connection will be paid separately.
NO 2 1 Hrs
Details of SOR No-10004661_ Biweekly Cleaning-Finishing:
The SOR-10004661, will be paid as a single unit for the list of
Jobs as given below. Individual SOR summation is also given for
clarity. Incase any other additional job is done, then the vendor
will be paid through individual SOR.
List of Jobs- Biweekly Cleaning in Finishing Area Total Planned Time:10hrs
Manpower:Tentatively 19-20 nos SOR No-10004661_ Biweekly Cleaning-Finishing
Sr no.
Individual SOR No
Job Description Size KG Qty UNIT Total Qty.
1 10002448 Coagulation shaker screen open 1 No 0.5
2 10002448 Coagulation shaker screen boxup 1 No 0.5
3 10002448 Leach shaker-1 screen open 1 No 0.5
4 10002448 Leach shaker-1 screen boxup 1 No 0.5
5 10002448 Leach shaker-2 screen open 1 No 0.5
6 10002448 Leach shaker-2 screen boxup 1 No 0.5
7 10002333 Leach shaker screen bottom duct- 1/2 open 14'' 1 No 0.5
8 10002333 Leach shaker screen bottom duct-1/2 boxup 14'' 1 No 0.5
9 10002446 Dewatering Press-1/2 open 1 No 0.5
10 10002446 Dewatering Press-1/2 open 1 No 0.5
11 10002328 Blinding of 40T07/08 Tank line 4'' 1 No 1
12 10002347 Blinding of 40T07/08 Tank line 3'' 1 No 1
13 10002345 Blinding of 40T07/08 Tank line 2'' 1 No 1
14 10002324 Blinding of 40T07/08 Tank line (Tail Blind) 2'' 1 No 1
15 10002323 Blinding of 40T07/08 Tank line (Tail Blind) 1.5'' 1 No 1
16 10002321 Blinding of 40T07/08 Tank line 0.75'' 2 No 2
17 10002328 Deblinding of 40T07/08 Tank line 4'' 1 No 1
18 10002347 Deblinding of 40T07/08 Tank line 3'' 1 No 1
19 10002345 Deblinding of 40T07/08 Tank line 2'' 1 No 1
20 10002324 Deblinding of 40T07/08 Tank line (Tail Blind)
2'' 1 No 1
21 10002323 Deblinding of 40T07/08 Tank line (Tail Blind)
1.5'' 1 No 1
22 10002321 Deblinding of 40T07/08 Tank line 0.75'' 2 No 2
23 10003283 Disintegrator-1 line chute venchuri open 1 No 0.5
24 10003283 Disintegrator-2 line chute venchuri boxup 1 No 0.5
25 10003283 Disintegrator-1 line chute venchuri open 1 No 0.5
26 10003283 Disintegrator -2 line chute venchuri boxup 1 No 0.5
27 10002426 Coagulation Floor latex line open 4'' 2 No 1
28 10002328 Coagulation Floor latex line open 4'' 4 No 2
29 10002326 Coagulation Floor latex line open 3'' 2 No 1
30 10002426 Coagulation Floor latex line boxup 4'' 2 No 1
31 10002328 Coagulation Floor latex line boxup 4'' 4 No 2
32 10002326 Coagulation Floor latex line boxup 3'' 2 No 1
33 10004633 Coagulation Floor latex line ball i/v remove 4'' 35 2 Kg 70
34 10004633 Coagulation Floor latex line ball i/v installation
4'' 35 2 Kg 70
35 10002329 Coagulation tank inlet venchuri open 6'' 1 No 0.5
36 10002328 Coagulation tank inlet venchuri open 4'' 2 No 1
37 10002322 Coagulation tank inlet venchuri open 1'' 1 No 0.5
38 10002329 Coagulation tank inlet venchuri box-up 6'' 1 No 0.5
39 10002328 Coagulation tank inlet venchuri box-up 4'' 2 No 1
40 10002322 Coagulation tank inlet venchuri box-up 1'' 1 No 0.5
41 10002336 Coagulation to serum tank duct open 20'' 2 No 1
42 10002336 Coaglation to serum tank duct boxup 20'' 2 No 1
43 10002329 Leach pump suction and discharge line open 6'' 3 No 1.5
44 10002328 Leach pump suction and discharge line open 4'' 2 No 1
45 10002328 Leach pump suction and discharge line open 4'' 2 No 1
46 10002329 Leach pump suction and discharge line boxup
6'' 3 No 1.5
47 10002328 Leach pump suction and discharge line boxup
4'' 2 No 1
48 10002328 Leach pump suction and discharge line boxup
4'' 2 No 1
49 10002329 Wash pump suction and discharge line open 6'' 4 No 2
50 10002328 Wash pump suction and discharge line open 4'' 2 No 1
51 10002329 Wash pump suction and discharge line boxup
6'' 4 No 2
52 10002328 Wash pump suction and discharge line boxup
4'' 2 No 1
53 10002329 Serum pump suction and discharge line open
6'' 2 No 1
54 10002328 Serum pump suction and discharge line open
4'' 11 No 5.5
55 10002329 Serum pump suction and discharge line boxup
6'' 2 No 1
56 10002328 Serum pump suction and discharge line boxup
4'' 11 No 5.5
57 10002332 40T09/10 H pipe end blind open line 12'' 5 No 2.5
58 10002332 40T09/10 H pipe end blind boxup line 12'' 5 No 2.5
59 10002336 40K08 Suction and discharge open line 20'' 2 No 1
60 10002336 40K08 Suction and discharge open line 20'' 2 No 1
61 10002332 40K08 Suction and discharge open 12'' 2 No 1
62 10002332 40K08 Suction and discharge open 12'' 2 No 1
63 10002336 40K08 Suction and discharge boxup 20'' 2 No 1
64 10002336 40K08 Suction and discharge boxup 20'' 2 No 1
65 10002332 40K08 Suction and discharge boxup 12'' 2 No 1
66 10002332 40K08 Suction and discharge boxup 12'' 2 No 1
67 10003280 Cyclone separator inspection window open 0.04 4 No 2
68 10003280 Cyclone separator inspection window open 0.04 4 No 2
69 10003280 Cyclone separator inspection window boxup 0.04 4 No 2
70 10003280 Cyclone separator inspection window boxup 0.04 4 No 2
71 10002331 Cyclone separator line open 10'' 2 No 1
72 10002331 Cyclone separator line open 10'' 1 No 0.5
73 10002331 Cyclone separator line open 10'' 2 No 1
74 10002331 Cyclone separator line open 10'' 1 No 0.5
75 10002331 Cyclone separator line boxup 10'' 2 No 1
76 10002331 Cyclone separator line boxup 10'' 1 No 0.5
77 10002331 Cyclone separator line boxup 10'' 2 No 1
78 10002331 Cyclone separator line boxup 10'' 1 No 0.5
79 10002317 Cyclone separator bellow cloth open 0.35 1 No 0.5
80 10002317 Cyclone separator bellow cloth open 0.35 1 No 0.5
81 10002317 Cyclone separator bellow cloth boxup 0.35 1 No 0.5
82 10002317 Cyclone separator bellow cloth boxup 0.35 1 No 0.5
83 10003040 Vibrator spreader-1 top cover open 0.875 1 No 0.5
84 10003040 Vibrator spreader-2 top cover open 0.875 1 No 0.5
85 10003040 Vibrator spreader-1 top cover boxup 0.875 1 No 0.5
86 10003040 Vibrator spreader-2 top cover boxup 0.875 1 No 0.5
87 10002320 Dryer silicon rod cloth Open 1.65 1 No 0.5
88 10002320 Dryer silicon rod cloth Open 1.65 1 No 0.5
89 10002320 Dryer silicon rod cloth boxup 1.65 1 No 0.5
90 10002320 Dryer silicon rod cloth boxup 1.65 1 No 0.5
91 10002267 Dryer inlet H tray frame dismantle 0.031 1 MT 0.031
92 10002267 Dryer inlet H tray frame dismantle 0.031 1 MT 0.031
93 10002267 Dryer inlet H tray frame installation 0.031 1 MT 0.031
94 10002267 Dryer inlet H tray frame installation 0.031 1 MT 0.031
95 10002451 Inclined conveyor complete cleaning 1 NO 1
96 10002451 Inclined conveyor complete cleaning 1 NO 1
97 10003040 Baler-1inlet hopper open 1 1 M2 0.5
98 10003040 Baler-1 inlet hopper boxup 1 1 M2 0.5
Individual SOR Summation- Biweekly Cleaning in Finishing Area Total Planned Time:10hrs
Manpower:Tentatively 19-20 nos SOR No-10004661_ Biweekly Cleaning-Finishing
Individual SOR No
SOR Description UOM Qnty
10002267 INSTALL & DISMANTLE EQPT MT 0.124
10002317 Upto 0.5 SqM No 2
10002320 Above 1.5 SqM No 2
10002321 Upto 0.75 inch No 4
10002322 1 inch No 1
10002323 1.5 inch No 2
10002324 2 inch No 2
10002326 3 inch No 2
10002328 4 inch No 25
10002329 6 inch No 10
10002331 10 inch No 6
10002332 12 inch No 9
10002333 14 inch No 1
10002336 20 Inch No 6
10002339 30 inch No 2
10002345 2 inch No 2
10002347 3 inch No 2
10002426 4 inch No 2
10002446 DEWATERING PRESS CAGE OPENING/BOX-UP No 1
10002448 SHAKER SCREEN OPEN AND BOX-UP No 3
10002451 Complete Cleaning Conveyor and Alignment No 2
10003040 0.5 SqM to 1.0 SqM No 3
10003280 upto 0.125 SqM No 8
10003283 DISINTEGRATOR OPEN/BOX-UP CLEANING No 2
10004633 FLNG VLV <=200 KG No 140
Details of SOR No-10004662_ Grade Changeover Cleaning-Finishing:
The SOR-10004662, will be paid as a single unit for the list of
Jobs as given below. Individual SOR summation is also given for
clarity. Incase any other additional job is done, then the vendor
will be paid through individual SOR
List of Jobs- Grade Changeover Cleaning in Finishing Area Total Planned Time:32hrs
Manpower:Tentatively 19-20 nos SOR No-10004662_ Grade Changeover Cleaning-Finishing
Sr no.
Individual SOR No. Job Descrotion Size KG Qty UNIT
Total Qty.
1 10002448 Coagulation shaker screen open 1 No 0.5
2 10002448 Coagulation shaker screen boxup 1 No 0.5
3 10002448 Leach shaker screen open 1 No 0.5
4 10002448 Leach shaker screen boxup 1 No 0.5
5 10002448 Leach shaker screen open 1 No 0.5
6 10002448 Leach shaker screen boxup 1 No 0.5
7 10002333 Leach shaker screen bottom duct open 14'' 1 No 0.5
8 10002333 Leach shaker screen bottom duct open 14'' 1 No 0.5
9 10002333 Leach shaker screen bottom duct boxup 14'' 1 No 0.5
10 10002333 Leach shaker screen bottom duct boxup 14'' 1 No 0.5
11 10002446 Dewatering press open 1 No 0.5
12 10002446 Dewatering press open 1 No 0.5
13 10002446 Dewatering press boxup 1 No 0.5
14 10002446 Dewatering press boxup 1 No 0.5
15 10002328 Blinding of 40T07/08 Tank line 4'' 1 No 1
16 10002347 Blinding of 40T07/08 Tank line (Tail Blind) 3'' 1 No 1
17 10002345 Blinding of 40T07/08 Tank line(Tail Blind) 2'' 1 No 1
18 10002324 Blinding of 40T07/08 Tank line (Tail Blind) 2'' 1 No 1
19 10002323 Blinding of 40T07/08 Tank line (Tail Blind) 1.5'' 1 No 1
20 10002321 Blinding of 40T07/08 Tank line .75'' 2 No 2
21 10002328 Deblinding of 40T07/08 Tank line 4'' 1 No 1
22 10002347 Deblinding of 40T07/08 Tank line (Tail Blind) 3'' 1 No 1
23 10002345 Deblinding of 40T07/08 Tank line(Tail Blind) 2'' 1 No 1
24 10002324 Deblinding of 40T07/08 Tank line (Tail Blind) 2'' 1 No 1
25 10002323 Deblinding of 40T07/08 Tank line (Tail Blind) 1.5'' 1 No 1
26 10002321 Deblinding of 40T07/08 Tank line .75'' 2 No 2
27 10003283 Disintegrator line chute venchuri open 1 No 0.5
28 10003283 Disintegrator line chute venchuri open 1 No 0.5
29 10003283 Disintegrator line chute venchuri box-up 1 No 0.5
30 10003283 Disintegrator line chute venchuri box-up 1 No 0.5
31 10002426 Coagulation Floor latex line open 4'' 2 No 1
32 10002328 Coagulation Floor latex line open 4'' 4 No 2
33 10002326 Coagulation Floor latex line open 3'' 2 No 1
34 10002426 Coagulation Floor latex line boxup 4'' 2 No 1
35 10002328 Coagulation Floor latex line boxup 4'' 4 No 2
36 10002326 Coagulation Floor latex line boxup 3'' 2 No 1
37 10004633 Cougulation Floor latex line ball i/v remove 4'' 35 2 Kg 70
38 10004633 Coagulation Floor latex line ball i/v installation 4'' 35 2 Kg 70
39 10002329 Coagulation tank inlet venchuri open 6'' 1 No 0.5
40 10002328 Coagulation tank inlet venchuri open 4'' 2 No 1
41 10002322 Coagulation tank inlet venchuri open 1'' 1 No 0.5
42 10002329 Coagulation tank inlet venchuri boxup 6'' 1 No 0.5
43 10002328 Coagulation tank inlet venchuri boxup 4'' 2 No 1
44 10002322 Coagulation tank inlet venchuri boxup 1'' 1 No 0.5
45 10002336 Coagulation to serum tank duct open 20'' 2 No 1
46 10002336 Coagulation to serum tank duct boxup 20'' 2 No 1
47 10002329 Leach pump suction and discharge line open 6'' 3 No 1.5
48 10002328 Leach pump suction and discharge line open 4'' 2 No 1
49 10002328 Leach pump suction and discharge line open 4'' 2 No 1
50 10002329 Leach pump suction and discharge line boxup 6'' 3 No 1.5
51 10002328 Leach pump suction and discharge line boxup 4'' 2 No 1
52 10002328 Leach pump suction and discharge line boxup 4'' 2 No 1
53 10002329 Wash pump suction and discharge line open 6'' 4 No 2
54 10002328 Wash pump suction and discharge line open 4'' 2 No 1
55 10002329 Wash pump suction and discharge line boxup 6'' 4 No 2
56 10002328 Wash pump suction and discharge line boxup 4'' 2 No 1
57 10002329 Serum pump suction and discharge line open 6'' 2 No 1
58 10002328 Serum pump suction and discharge line open 4'' 11 No 5.5
59 10002329 Serum pump suction and discharge line boxup 6'' 2 No 1
60 10002328 Serum pump suction and discharge line boxup 4'' 11 No 5.5
61 10002332 40T09/10 H pipe end blind open line 12'' 5 No 2.5
62 10002332 40T09/10 H pipe end blind boxup line 12'' 5 No 2.5
63 10002336 40K08 Suction and discharge open line 20'' 2 No 1
64 10002336 40K08 Suction and discharge open line 20'' 2 No 1
65 10002332 40K08 Suction and discharge open 12'' 2 No 1
66 10002332 40K08 Suction and discharge open 12'' 2 No 1
67 10002336 40K08 Suction and discharge boxup 20'' 2 No 1
68 10002336 40K08 Suction and discharge boxup 20'' 2 No 1
69 10002332 40K08 Suction and discharge boxup 12'' 2 No 1
70 10002332 40K08 Suction and discharge boxup 12'' 2 No 1
71 10003280 Cyclone seperator inspection window open 0.04 4 No 2
72 10003280 Cyclone seperator inspection window open 0.04 4 No 2
73 10003280 Cyclone seperator inspection window boxup 0.04 4 No 2
74 10003280 Cyclone seperator inspection window boxup 0.04 4 No 2
75 10002331 Cyclone seperator line open 10'' 2 No 1
76 10002331 Cyclone seperator line open 10'' 1 No 0.5
77 10002331 Cyclone seperator line open 10'' 2 No 1
78 10002331 Cyclone seperator line open 10'' 1 No 0.5
79 10002331 Cyclone seperator line boxup 10'' 2 No 1
80 10002331 Cyclone seperator line boxup 10'' 1 No 0.5
81 10002331 Cyclone seperator line boxup 10'' 2 No 1
82 10002331 Cyclone seperator line boxup 10'' 1 No 0.5
83 10002317 Cyclone seperator bellow cloth open 0.35 1 No 0.5
84 10002317 Cyclone seperator bellow cloth open 0.35 1 No 0.5
85 10002317 Cyclone seperator bellow cloth boxup 0.35 1 No 0.5
86 10002317 Cyclone seperator bellow cloth boxup 0.35 1 No 0.5
87 10003040 Vibrator spreader top cover open 0.875 1 No 0.5
88 10003040 Vibrator spreader top cover open 0.875 1 No 0.5
89 10003040 Vibrator spreader top cover boxup 0.875 1 No 0.5
90 10003040 Vibrator spreader top cover boxup 0.875 1 No 0.5
91 10002320 Dryer silicon rod cloth Open 1.65 1 No 0.5
92 10002320 Dryer silicon rod cloth open 1.65 1 No 0.5
93 10002320 Dryer silicon rod cloth boxup 1.65 1 No 0.5
94 10002320 Dryer silicon rod cloth boxup 1.65 1 No 0.5
95 10002267 Dryer inlet H tray frame dismantle line 0.031 1 MT 0.031
96 10002267 Dryer inlet H tray frame dismantle line 0.031 1 MT 0.031
97 10002267 Dryer inlet H tray frame installation line 0.031 1 MT 0.031
98 10002267 Dryer inlet H tray frame installation line 0.031 1 MT 0.031
99 10002451 Inclined conveyor complete cleaning 1 NO 1
100 10002451 Inclined conveyor complete cleaning 1 NO 1
101 10003027 Dryer 5th zone filter and flange open 1 1 No 0.5
102 10003027 Dryer 5th zone filter and flange open 1 1 No 0.5
103 10003027 Dryer 5th zone filter and flange boxup 1 1 No 0.5
104 10003027 Dryer 5th zone filter and flange boxup 1 1 No 0.5
105 10003040 Baler inlet hopper open 1 1 M2 0.5
106 10003040 Baler inlet hopper open 1 1 M2 0.5
107 10003040 Baler inlet hopper boxup 1 1 M2 0.5
108 10003040 Baler inlet hopper boxup 1 1 M2 0.5
109 10003281 Dryer top cover open and box up No 31
110 10003040 Dryer curtain open and box up 0.66 12 No 12
111 10002328
Latex line open and box up for black to white at DWP floor
4" 3
No 3
112 10002306 Blend area latex line strainer cleaning 20" 1 No 1
113 10002323 Blend area latex line strainer Drain&Vent open/Boxup 1.5 2 No 2
114 10004633
Blend area latex line strainer Drain&Vent IV open/Boxup 1.5 7
Kg 14
115 10004633 Latex line valve open and box up 4" 35 2 Kg 70
116 10002328
Blend area latex line open and box up for black to white
4" 9
No 9
Individual SOR Summation- Grade Changeover Cleaning in Finishing Area Total Planned Time:32hrs
Manpower:Tentatively 19-20 nos SOR No-10004662_ Grade Changeover Cleaning-Finishing
Individual SOR No
SOR Description UOM Qnty
10002267 INSTALL & DISMANTLE EQPT MT 0.124
10002306 20 inch to 24 inch No 1
10002317 Upto 0.5 SqM No 2
10002320 Above 1.5 SqM No 2
10002321 Upto 0.75 inch No 4
10002322 1 inch No 1
10002323 1.5 inch No 4
10002324 2 inch No 2
10002326 3 inch No 2
10002328 4 inch No 37
10002329 6 inch No 10
10002331 10 inch No 6
10002332 12 inch No 9
10002333 14 inch No 2
10002336 20 Inch No 6
10002345 2 inch No 2
10002347 3 inch No 2
10002426 4 inch No 2
10002446 DEWATERING PRESS CAGE OPENING/BOX-UP No 2
10002448 SHAKER SCREEN OPEN AND BOX-UP No 3
10002451 Complete Cleaning Conveyor and Alignment No 2
10003027 0.5 SqM to 1.5 SqM No 2
10003040 0.5 SqM to 1.0 SqM No 16
10003280 upto 0.125 SqM No 8
10003283 DISINTEGRATOR OPEN/BOX-UP CLEANING No 2
10004633 FLNG VLV <=200 KG No 224
10003281 DRYER TOP COVER OPEN/BOX-UP No 31