flex mods: effect on industry and u2 startup
Post on 18-Dec-2016
214 Views
Preview:
TRANSCRIPT
FLEX MODS: EFFECT ON INDUSTRY AND U2 STARTUP
Joe Calle Manager – WBN Dual Unit Interface and Transition
Bob Williams WBN Flex Project Manager
OBJECTIVES 1) Explain the consequences of the tsunami
inundating the Fukushima plant site.
2) Identify actions taken by the Nuclear Regulatory Commission (NRC) and the Institute of Nuclear Power Operations (INPO).
3) Explain the Station Blackout rule (SBO).
OBJECTIVES (continued)
4) Explain Diverse and Flexible Coping Strategies(FLEX).
5) Identify WBNs response and actions taken to NRC and INPO requirements concerning the Fukushima disaster.
Introduction
The earthquake and tsunami at the Fukushima Nuclear Plant (March 2011) resulted in significant damage to the facility.
Before
After
Introduction
Earthquake epicenter was off the coast. • The earthquake resulted in a large tsunami that is estimated to have
exceeded 45 feet. • Units 1, 2, and 3 were in
operation • 5, and 6, were shut down for
routine refueling • Unit 4 reactor fuel had been
offloaded into the Unit 4 spent fuel pool
The Accident
The plant staff were challenged with: • Loss of all A/C power. • Control and instrument power was limited and soon failed. • No means for cooling the Spent Fuel Pool (SFP). • Lost long term core cooling capability.
The Accident
Following the earthquake: • The three operating units automatically shut down
• Offsite power was lost to the entire facility • Emergency diesel generators started at all six units
The facility response to the earthquake was normal.
The Accident
Approximately 40 minutes following the earthquake and shutdown of the operating units, the first large tsunami wave inundated the site. The tsunami caused extensive damage to site facilities and resulted in a complete loss of all ac electrical power on Units 1 through 5.
The Accident
Control Room Emergency Diesel
Electrical Switchgear
Battery Room
Flooded Buildings
The Accident
Unit 6 retained the function of one air-cooled emergency diesel generator and shared this power with unit 5. Operators lost the ability to cool the fuel in the Units1, 2 and 3. Damage to the nuclear fuel occurred shortly after the loss of cooling capabilities on these units.
The Accident
Workers wearing protective suits work to restore electricity at the Fukushima nuclear power plant.
Near-Term Task Force March 23, 2011 the NRC Chairman directed the staff to establish the Near-Term Task Force (NTTF) The NTTF recommended revising the NRC’s Station Blackout (SBO) rule (Title 10 of the Code of Federal Regulations (10 CFR) section 50.63). Advanced Notice of Proposed Rulemaking has been issued in Federal Register. August 2011 INPO issued IER 11-4 in response to NRC NTTF SBO recommendations. March 2012 NRC issued Order EA-12-049 to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis Events. March 2012 NRC issued Order EA-12-051, to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation.
Industry Response August 2012 Nuclear Energy Institute (NEI) issued Rev 0 of NEI 12-06 “Diverse and Flexible Coping Strategies (FLEX) Implementation Guide”. NEI 12-06 was endorsed by NRC in August 2012 by JLD-ISG-2012-01 “Compliance with Order EA-12-049, Order modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events”. August 2012 NEI issued Rev 1 of NEI 12-02 “Industry Guidance for Compliance with NRC Order EA-12-051”. NEI 12-02 was endorsed by NRC in August 2012 by JLD-ISG-2012-03 “Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation”.
SBO Rule 1. Establish a minimum coping time of 8 hours for a loss of all
AC Power.
2. Establish the equipment, procedures, and training necessary to implement an ‘‘extended loss of all AC Power (ESBO)’’ coping time of 72 hours for certain Critical Safety Functions:
A. Core cooling B. Spent Fuel Pool (SFP) cooling C. Reactor Coolant System (RCS) and primary containment integrity.
3. Preplan and pre-stage offsite resources to Support the Critical Safety Functions
Include the ability to deliver the equipment to the site in the time period allowed for extended coping, under conditions involving significant degradation of offsite transportation infrastructure associated with significant natural disasters.
TVA plants can not meet the ESBO requirements without :
• Supplemental Diesel Generators for 6.9 KV Shutdown Boards.
• Supplemental Diesel Generators for DC and AC control systems.
• Diesel powered pumps to provide make up water to the Steam Generators.
SBO Rule (continued)
NEI 12-06 FLEX
NEI 12-06 FLEX Plan to implement NRC Order EA-12-049
Three Phase approach: • Initially cope by relying on installed plant equipment. • Transition from installed plant equipment to on-site FLEX equipment. • Obtain additional capability and redundancy from off-site equipment
until power, water, and coolant injection systems are restored or commissioned.
NEI 12-06 FLEX NEI 12-06 FLEX Plan to implement NRC Order EA-12-049
Boundary Conditions • Beyond-design-basis external event occurs impacting all units on site. • All reactors on-site initially operating at power, unless site has procedural
direction to shut down due to the impending event. • Each reactor is successfully shut down when required (i.e., all rods inserted, no
ATWS). • On-site staff are at site administrative minimum shift staffing levels. • No independent, concurrent events, e.g., no active security threat. • All personnel on-site are available to support site response. • Spent fuel in dry storage is outside the scope of FLEX.
…the FLEX strategies are also “diverse and flexible” such that they can be implemented in many different conditions as it is not possible to predict the exact site conditions following a beyond-design-basis external event. As such, the strategies can be implemented in all modes by maintaining the portable FLEX equipment available to be deployed during all modes.
NEI 12-06 FLEX
FLEX Response Select FLEX equipment and Plant Connection points to meet FLEX requirements:
• Engineering:
• Procure and install two 3 MW diesel generators with rapid connection strategy.
• Procure and install two 225 kva diesel generators with rapid connection strategy
• Procure diesel driven and electric motor FLEX pumps (Dominator, Tritons, Intermediate Pressure, and High Pressure)
• Provide structure to protect FLEX Equipment from environmental events. FLEX Equipment Storage Building will protect FLEX equipment.
• Provide FLEX Connections into the following systems:
ERCW RWST BAT
SFP Cooling TWST PWST
Safety Injection Aux FW DWST
FLEX Response
Operations and Maintenance procedures: • Develop and issue new class of procedures called FLEX Support
Guidelines (FSG)
WBN Training: • Develop/conduct training for connecting and maintaining FLEX
equipment.
FLEX Response
Watts Bar Nuclear Modifications for U1R12 • Install two 3 MW Air Cooled D/Gs and connect to Shutdown boards
through Existing SR DG Building Cables. • Install two 225 kva Air Cooled D/Gs and connect to battery chargers
and RMOV boards. • Construct a hardened Aux FW Supply Tank (AFWST) and piping to
supporting AFW pump suction to ensure SG cooling water supply is available.
• Install FLEX connection points into required systems at multiple locations.
• Provide ARV and AFW LCV backup control stations above flood level PMF
WATTS BAR MITIGATION STRATEGIES SITE IMPLEMENTATION
Contract Partners
Design Organizations: • Westinghouse - Integrator • Bechtel - WBN • Bechtel - Frederick • Sergeant & Lundy • Worley Parsons • MESA • URS • CB&I • Scientech • Rizzo • Facilities Risk Consultants (FRC) • AMAC • Pacific Engineering – Dr. Walt Silva • University of Texas – Dr. Ken Stoke • University of Tennessee – Dr. Bob Hatcher
Implementing Organizations: In-Plant Modifications: • Bechtel (U2) – 15% • Day & Zimmerman (U1 and Common) – 85% • Mechanical Taps • Electrical Disconnects/Transfer Switches • N2 Station Relocation • Seismic Mod Exterior-Plant Modifications: • Aux. Feedwater Storage Tank (AFWST) - URS/CB&I • FLEX Equipment Storage Tank (FESB) - Kiewit
FLEX Equipment Storage Building (FESB) and Auxiliary Feedwater Storage Tank (AFWST)
Design and Purpose
Flex - Forms/Rebar Preparations
Fukushima Flex Strategies
• Portable and Pre-staged (FLEX) Equipment – Portable Pumps – Generators – Hoses/connections – Disaster kits – Portable MET Tower – Nitrogen Bottles – Tow vehicle – Portable Fans – Debris removal equipment
FLEX Equip. Storage Bldg.
Flex – AFWST - SSI Micro Piles, Slab, Tank Fabrication
FLEX Equipment Storage Building Key Mechanical Equipment
Flex - Mechanical The Triton 5000 Pumping System is a single, integrated pumping module capable of pumping 5,000 gpm at 350 ft total dynamic head(150 psig).
It uses a satellite pumping system consisting of two floating submersible source pumps that supply water to a Dominator pump at distances up to 150 ft.
The floating submersible pumps can provide up to 50 ft of vertical lift.
Three LP Flex Pump 5000 gpm Portable Diesel Pump
Flex - Mechanical Two IP FLEX Pump (Diesel Driven) 150 gpm @ 922 ft hd
Two Each (Flood - Mode 5&6) IP FLEX Pump (Motor Driven) 150 gpm @ 922 ft hd
Three HP FLEX Pump (Motor Driven) 40 gpm @ 1384 ft hd.
Two FLEX Transfer Pump 500 gpm @ 374 ft hd
IP (Motor Driven) Pump/Motor Assembly
Fukushima Flex Strategies • Water Sources include:
• New Auxiliary Feedwater Supply Tank • Refueling Water Storage Tank • Condensate Storage Tank • Primary Water Storage Tank • Demineralized Water Storage Tank • Boric Acid Tank • Tritiated Water Storage Tank • Ultimate Heat Sink • Flood Waters
Flex – Haul Route PA Fence
FLEX Physical Plant Connections and Tie-ins
Flex - Mechanical
Safety Injection Tap – HP FLEX Injection
Flex - Mechanical
Refueling Water Storage Tank
Flex - Mechanical
Boric Acid Tank (BAT)
Flex - Mechanical 1A&1B MDAFW-HPFP Before/After
TDAFW
Flex - Mechanical
ERCW Header in 5th Diesel Generator Building
ERCW Taps in Aux Bldg.
Flex - Mechanical
Demin/ERCW feeds to SFP
Flex - Mechanical
Demineralized Water Storage Tank
Flex - Mechanical
Primary Water Storage Tank
Flex - Mechanical
Tritium Water Storage Tank (TWST)
FLEX 480V and 6900V Diesels
480V Flex Diesel Generator
480V Flex Diesel Generator
6900V Flex Diesel Generator
Nitrogen (N2) Station Relocation
Flex – N2 for AFW LCVs/ARVs B-Train
Spent Fuel Pool Level Instrumentation
Flex - Spent Fuel Pool
Cable Probe will provide 26’ measurement span to just above top of the fuel racks
Spent Fuel Pool Level Instrumentation
The new instruments will use guided wave radar technology
SFP Level – Guided Wave Radar
WBN FLEX Regional Response Center (RRC) Update
WBN RRC Support Activities Watts Bar staging area B
The Watts Bar helicopter pad is the B staging area. It is located west of the Watts Bar training building.
Staging Areas Watts Bar staging area C
Rockwood Municipal Airport located at 258 Rockwood airport Dr. in Rockwood, TN 37854. the airport has a 5000 x 100 ft. runway and is located 34 driving miles from
WBN. 100LL JET-A fuel onsite, a backup power generator and food and shelter facilities with ample parking and staging space. Located directly off I-40 west of Kingston, TN.
• Watts Bar staging area D • The Cleveland Regional Jetport has a 5,500 ft. concrete runway, aviation and diesel fuel
onsite, a backup power generator and food and shelter facilities onsite. It can accommodate a MD-80 aircraft. Parking areas are ample and additional parking areas for tractor trailers is planned to be expanded by the fall of 2014.
Site/RRC FLEX Equipment WBN On-site FLEX Equipment RRC Generic Equipment 2- 6900v DGs 2- 480 VAC DGs 480VAC DGs 3- 20 GPM HP Pumps High Pressure Pump 3 - 5000GPM Dominator Pumps Diesel Fuel Transfer 3 – 5000 GPM Triton Pumps LP/Med flow Pump 2 -150 GPM IP Diesel Driven Pumps LP/High flow Pump 2- 150 GPM IP 480V Pumps SG/RPV Makeup Pump 2-150 GPM Mode 5&6 480V Pumps SAFER Team Equipment 2- 500 GPM H2O Trans. Diesel Driven Pumps Hoses and Connections 2 -250 GPM SFP Spray Nozzles Connection Cable 2 – Tow Vehicles w/ Mounted Fuel Tank Portable Lighting 2- Trailer Diesel Fuel Tanks Transfer Pumps 1- Compact Track Loader w/ Attachments Debris Clearing Equipment RRC Non- Generic Equipment Hoses and Connections Lift Pump for Dominator Diesel Electrical Connection Mobile Boration skid Portable Light Stands Mobile Demin Skid
Communications
• Additional Communications capability will be provided by: • New protected phone system • Satellite Phones • Radios • Mobile Met Tower
top related