air quality permitting guidelines for industrial sources

26
Pinal County Air Quality Workshop Casa Grande – January 14, 2014 Kale Walch & Anu Jain – Permit Engineers

Upload: mireya

Post on 04-Feb-2016

32 views

Category:

Documents


0 download

DESCRIPTION

Air Quality Permitting Guidelines for Industrial Sources. Pinal County Air Quality Workshop Casa Grande – January 14, 2014 Kale Walch & Anu Jain – Permit Engineers. Who needs an industrial permit?. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Air Quality Permitting Guidelines for Industrial Sources

Pinal County Air Quality Workshop

Casa Grande – January 14, 2014

Kale Walch & Anu Jain – Permit Engineers

Page 2: Air Quality Permitting Guidelines for Industrial Sources

Facilities that emit more than 5.5 pounds per day or 1 ton per year of any regulated pollutant.

Page 3: Air Quality Permitting Guidelines for Industrial Sources

Nitrogen Oxides, Carbon Monoxide, Sulfur Dioxide (NOX, CO, SO2):

Usually products of combustion: boilers, heaters, generators…

Page 4: Air Quality Permitting Guidelines for Industrial Sources

Volatile Organic Compounds/Hazardous Air Pollutants (VOCs/HAPs)

Associated with spray paints, solvents, fuels and other organic chemicals.HAPs can also be inorganic: Chlorine, lead and other metals…

Page 5: Air Quality Permitting Guidelines for Industrial Sources

Particulate Matter (PM10 and PM2.5)

PM10, commonly referred to as “dust”: usually from grain/cotton handling, mining operations, general manufacturing…

PM2.5 or “fine particles”: can be emitted from industrial combustion, vehicle exhaust, open fires…

Page 6: Air Quality Permitting Guidelines for Industrial Sources

1)West Pinal PM10 Nonattainment Area2012 Moderate PM10 Nonattainment Designation (based on 2006-2008 data)2013 Stakeholder process to develop the Emission Inventory and propose State Implementation Plan (SIP) componentsJanuary 2014 the PM10 SIP is due to be submitted to EPA

2)West Central Pinal PM2.5 Nonattainment Area2011 PM2.5 24-Hour nonattainment designation based on the 2008 three year average2013 clean data finding based on the 2012 three year averageMarch 2014 a maintenance SIP must be submitted to the EPA

Page 7: Air Quality Permitting Guidelines for Industrial Sources
Page 8: Air Quality Permitting Guidelines for Industrial Sources

Small sources• Area source rules may be incorporated into permits

Medium sources• Area source rules may be incorporated into permits• Source might have to take Federally Enforceable limits to stay under

100 tons per year (tpy) Large sources

• Nonattainment New Source Review (NNSR) for sources with a PM10 potential to emit (PTE) over 100 tpy

• Must install Lowest Achievable Emission Rate Technology (LAER) which does not consider economic impacts

• Offsets at a ratio of at least 1:1.1 will be required • Area source rules may be incorporated into permits

Page 9: Air Quality Permitting Guidelines for Industrial Sources

The purpose of a permit is to identify all the air quality rules your facility is subject to: local (PCAQCD), State (Statutes) or Federal (EPA).

A permit also contains air pollution limits for each significant emission source, defines allowable hourly and annual throughputs (e.g., fuel consumption in boilers), and consolidates monitoring, recordkeeping, and reporting requirements.

Permits allow you to take certain limitations at your facility to avoid more stringent air quality requirements.

Page 10: Air Quality Permitting Guidelines for Industrial Sources

Class I Title V sources (above “major source” thresholds)

Class II- General sources – rock products. - Medium & small spray paint operations- Feed Mills- Others

Class IIISmall gas stations, auto body shops, dry cleaners…

Page 11: Air Quality Permitting Guidelines for Industrial Sources

Application Fee (Non-refundable) Permit Processing Fee (not for Class III

sources) Annual Fee (invoiced every year) Emissions Fee (only for Class I sources)

*Fees for 2014 are posted on our website. *Some fees are adjusted annually by the

Consumer Price Index (CPI).

Page 12: Air Quality Permitting Guidelines for Industrial Sources

Permits valid for 5 years. Letters to renew permits sent at

least couple of months before the permit expiration date.

Revisions do not start the clock.

Page 13: Air Quality Permitting Guidelines for Industrial Sources

You will need to submit:

1) Permit Application

2) Additional Forms for Fuel Burning equipment, Storage Tanks, Crushing and Screening equipment, Cotton Gins, Generators, Soil Vapor Extraction Units, Spray Paint Booths and Wastewater Treatment Plants.

3) Fill-in-able Forms available at http://www.pinalcountyaz.gov/Departments/AirQuality/Pages/IndustrialPermits.aspx

Page 14: Air Quality Permitting Guidelines for Industrial Sources

4. Follow filing procedures under:“Generic Outline or Air Quality Permit Filing Instructions”

Information required includes but not limited to:process description, site plan, flow diagram, plant and equipment capacities, MSDS sheets…

http://pinalcountyaz.gov/Departments/AirQuality/Pages/Industrial Permits.aspx

Page 15: Air Quality Permitting Guidelines for Industrial Sources

4) TIME FRAMES Form

Dear applicant,

As part of your application package and to ensure timely service, Pinal County Air QualityControl District would appreciate if you could indicate below when you will require theissuance of your permit. Below are our average time frames for issuing of industrialpermits. These time frames include a mandatory 30-day public notice, an additional 45-dayEPA review for Class I permits, permit processing time, and administrative time(invoicing, issuance of permit, etc…)

Class III: Small gas stations, auto body shops, dry cleaners, small fuel burning and/or generators – 60 to 90 daysClass I Title V – 120 to 300 daysClass I NSR/PSD – 180 to 300 daysClass II: Other facilities that do not fall under any of the categories above – 60 to 200 days

CONTACT PERMITTING STAFF FOR MORE SPECIFIC TIME FRAMES FORYOUR FACILITY.

THESE TIME FRAMES WILL NOT HOLD IF THE APPLICATION IS NOTCOMPLETE. INCOMPLETE APPLICATIONS MAY REQUIRE ADDITIONALPROCESSING TIMES.

IF THE PUBLIC REQUESTS A PUBLIC HEARING, THE TIME FRAMES MAYINCREASE BY 30-90 DAYS.

COMPANY: ______________________________________________________APPLICANT NAME: ______________________________________________________TITLE: ______________________________________________________REQUESTED PERMIT ISSUANCE DATE (MONTH/YEAR): _________________________SIGNATURE: __________________________________________DATE: _________________

Page 16: Air Quality Permitting Guidelines for Industrial Sources

TYPES:

Permit Revision: Changes in equipment, process, products.

Permit Transfer: Ownership change.

Page 17: Air Quality Permitting Guidelines for Industrial Sources

Same application form as for “New” permits, but check “Revision” box.

Same information needed as for “New” permits, but only in relation to changes and or modifications.

Revision application fee applicable to Class I permits only.

Page 18: Air Quality Permitting Guidelines for Industrial Sources

Use same Application form but check “Transfer” box.

No processing fee associated with transfers.

Apply before the transfer occurs.

Page 19: Air Quality Permitting Guidelines for Industrial Sources

Mandatory Public Notice period of 30 days for new permits, revisions and renewals.

Class I and some large Class II permits have a Mandatory EPA review period of 30-45 days.

Permit processing time depends on the complexity and the completeness of the application.

Page 20: Air Quality Permitting Guidelines for Industrial Sources

Some recent standards (subparts): 6H’s – Paint Stripping and Miscellaneous Surface

Coating (INCLUDES Autobody shops) 6W’s – Plating/Polishing 6X’s – Metal Fabrication/Finishing 6Z’s – Aluminum, Copper and other non-ferrous

Foundries 7C’s – Paint Manufacturers 7D’s – Prepared Feed Manufacturers. 4Z’s (RICE) – Diesel and Natural Gas Engines.

Page 21: Air Quality Permitting Guidelines for Industrial Sources

Each one contains a specific Compliance Date.

Must submit INITIAL NOTIFICATION. Brochures available at www.epa.gov/ttn/atw/area/

arearules.html

Page 22: Air Quality Permitting Guidelines for Industrial Sources

For new sources subjected to Pinal County’s

permitting thresholds an air quality permit is

required before starting construction or operation.

For current permit holders a revised permit is

required before any modifications or changes*.

*When in doubt call

Page 23: Air Quality Permitting Guidelines for Industrial Sources

Kale Walch, Senior Permit Engineer(520) [email protected]

Anu Jain, Permit Engineer(520) [email protected]

Page 24: Air Quality Permitting Guidelines for Industrial Sources
Page 25: Air Quality Permitting Guidelines for Industrial Sources

Biomass Boilers• July 20, 2011 EPA deferred the application of PSD and Title V to

CO2 emissions from bioenergy until July 21, 2014• July 12, 2013 the U.S. Court of Appeals vacated the deferral

Vacatur becomes effective 7 days after the deadline for rehearing motions passes

• August 26, 2013 the court extended the appeals deadline• October 15, 2013 the Supreme Court agreed to review limited

greenhouse gas issues Granted review over an issue involving the statutory trigger

for GHG permitting• October 22, 2013 a motion was filed asking the court to extend

the deadline for rehearing petitions to 30 days after the Supreme Court issues its decision

• November 14, 2013 Court of Appeals granted the extension

Next steps??????????

Page 26: Air Quality Permitting Guidelines for Industrial Sources

Counting GHG Fugitive Emissions in permitting applicability (12/12/13 guidance, http://www.epa.gov/nsr/ghgqa.html )

• Generally, GHG fugitive emissions are counted the same as other pollutants

• For determining whether a source is a major source fugitives are not included unless the source is a listed source. Once it is determined that a non-listed source is major

for at least one regulated NSR pollutant based on non-fugitive emissions, fugitive emissions are then included in all subsequent analyses (i.e. significant emission rates, BACT, air quality impacts)

• For modifications under PSD fugitive emissions are included in determining a physical or operational change is a major modification, regardless of source category