1 Aerospace Vehicle Systems Institute System and Software Integration Verification System and Software Integration Verification Texas Engineering Experiment Station Aerospace Vehicle Systems Institute Aerospace Vehicle Systems Institute The idea for this cooperative began in 1997 when Walt Gillette (now the 747X program manager Boeing Commercial Airplanes) met for a Texas A&M College of Engineering, Advisory Council meeting. B. Don. Russell, the A&M Associate Dean in charge of TEES, briefed Walt Gillette on a new research cooperative A&M had recently established for the petroleum industry. Walt was intrigued by the possibility of linking several industry members to do cooperative R&D under the protection of the National Cooperative Research and Production Act of 1993. Walt Gillette wanted to improve the research for aircraft systems -- an area he believed was a problem in Boeing’s efforts to effectively design and build new commercial aircraft. These complex and expensive systems typically pace airplane programs. Walt’s vision is to use AVSI as a vehicle to work with experts throughout the industry (Commercial and Defense), academia and elsewhere. Everyone will benefit by leveraging resources and developing an improved ability to work together.

Upload: habao

Post on 23-Mar-2018

224 views

Category:

Documents


1 download

TRANSCRIPT

1

Aerospace Vehicle Systems Institute

System and Software Integration VerificationSystem and Software Integration Verification

Texas Engineering Experiment Station

Aerospace Vehicle Systems InstituteAerospace Vehicle Systems Institute

The idea for this cooperative began in 1997 when Walt Gillette (now the 747X program manager Boeing Commercial Airplanes) met for a Texas A&M College of Engineering, Advisory Council meeting. B. Don. Russell, the A&M Associate Dean in charge of TEES, briefed Walt Gillette on a new research cooperative A&M had recently established for the petroleum industry. Walt was intrigued by the possibility of linking several industry members to do cooperative R&D under the protection of the National Cooperative Research and Production Act of 1993.

Walt Gillette wanted to improve the research for aircraft systems -- an area he believed was a problem in Boeing’s efforts to effectively design and build new commercial aircraft. These complex and expensive systems typically pace airplane programs.

Walt’s vision is to use AVSI as a vehicle to work with experts throughout the industry (Commercial and Defense), academia and elsewhere. Everyone will benefit by leveraging resources and developing an improved ability to work together.

2

Version Aerospace Vehicle Systems Institute

Slide 2

Project OverviewProject Overview

Overall Concept of OperationsDesign and production based on early and continuous integration (virtual => physical)Integrate, then build

ObjectiveShift architecting, design, and production activities to explicitly address integration issues early, reducing program execution risks, cycle time and cost

ApproachAdopt/develop “integration-based” software and system development processes with emphasis on integrating component-based, model-based and proof-based development

SSIV is a very ambitious, multi-year project to develop and demonstrate a “virtual integration” approach to product development that is likely to significantly affect how the aerospace industry handles embedded software-intensive systems in the future. The key concept is to address integration issues earlier and more comprehensively with improved consistent processes and tools.

3

Version Aerospace Vehicle Systems Institute

Slide 3

ParticipantsParticipants

CurrentActive – BAE, Boeing, DoD (Army, Navy), FAA, GE Aerospace (Smiths), Honeywell, Lockheed Martin, Rockwell Collins, SEI/Carnegie Mellon

Joining – Airbus, Dassault-Aviation, JPL/NASA

PotentialCurrent AVSI members – DoD (Air Force), Goodrich, Hamilton Sundstrand (UTC) {Sikorsky, P&W}

Potential new members – General Dynamics, Meggitt, NorthrupGrumman, Raytheon, Thales, Woodworth

Current membership suggests the strong leanings toward avionics and electronic systems. Government agencies (FAA and NASA) typically join as Liaison Members, under a change to the original agreement that essentially allows such members to behave as full members with recognition that their interests are public in nature and are not profit-motivated.

Universities, consultants, research institutions, tool vendors and standards bodies are not mentioned on this slide, but are acknowledged to be absolutely necessary to the success of the project.

4

Expanded objectives from the current draft AFE 60

5

This chart is starts on the left with the repository of models and background data in the integrators repository. The “model bus” is both an internal conduit for developing an initial concept system and passing the “specs”(in the form of models) to a supplier. Each of the suppliers has their own repository of models and background (some of it proprietary) to merge with the integrator’s “specs” model and perhaps improve upon the system or subsystem. The project is designed to address thecolored (blue and green) parts of this process; it is hoped that the file sharing and configuration management can be handled with commercially available tools - not a part of this AVSI effort.

Aerospace Vehicle Systems Institute

Slide 5

Single Information and Relationships Single Information and Relationships RepositoryRepository

Integrate information and relationships in a single repository with a “model bus”

Better requirementsBetter integrationBetter communicationBetter consistency

Multi-Aspect Model Repository

“Model Bus”

File Sharing

Configuration Management

Supplier 1 IDE/Tools

Models

ModelsImport/Export

Supplier N IDE/Tools

Multi-Aspect Model Repository

Multi-Aspect Model Repository

Assembly Models Assembly Models

Components Assemblies Components Assemblies

“Model Bus”

System Integrator

Models

“Model Bus”

Configuration Management

Configuration Management

File Sharing File Sharing

...Models Models

IDEModeling

SimulationAnalysis

Virtual Integration

Multi-Aspect Model Repository

“Model Bus”

Components Assemblies

Configuration Management

File Sharing

6

Version Aerospace Vehicle Systems Institute

Slide 6

Overview of MultiOverview of Multi--Aspect Model Aspect Model Repository & Model Bus Repository & Model Bus

ModelRepository

MatLab

Esterel

TOPCASED

SCADE

SimuLink

Eclipse

Rhapsody

DOORS

OSATE

?

AADL

SysML

Requirements

Design

Verification

Integration/Deployment

In an earlier phase of the project AADL was chosen as the best starting point•Language features•Tool support (existing)•Extensibility support (AADL is good, not perfect)

7

Aerospace Vehicle Systems Institute

Slide 7

Modified Business ModelModified Business Model

System Integrator defines a new product using internal repository of virtual “parts”Specifications for virtual subcomponents sent to suppliers

A modification to the approach of developing complex systems is anticipated, placing the emphasis on model-based development. This chart illustrates the flow of specs (in model form) to suppliers and the return of component modules (CM) and system modules (SM)

back to be integrated in a virtual sense before any the product is produced.

8

Aerospace Vehicle Systems Institute

Slide 8

Modified Business Model Modified Business Model (continued)(continued)

Virtual parts returned for virtual integration into a virtual productCost savings realized by finding problems early on virtual parts

Once the virtual product is satisfactory, the actual product is developed

Cycle-time reduction realized since re-work on physical parts virtually eliminated

New SMNew SM

Repository

Parse &Process Modify Create

VirtuallyIntegrate

Existing CM/SM

Modified CM/SM

New CM/SM

CM/SM

IssuesNew SM

Repository

Parse &Process Modify Create

VirtuallyIntegrate

Existing CM/SM

Modified CM/SM

New CM/SM

CM/SM

IssuesNew SM

Repository

Parse &Process Modify Create

VirtuallyIntegrate

Existing CM/SM

Modified CM/SM

New CM/SM

CM/SM

IssuesNew SM

Repository

Parse &Process Modify Create

VirtuallyIntegrate

Existing CM/SM

Modified CM/SM

New CM/SM

CM/SM

Issues

New SM

VirtuallyIntegrate

New Product DefinitionNew SM

Issues

Specs

The benefits of such an model-based development are summarized on this chart - cost savings and cycle-time reduction are the overarching drivers in most complex system’s development. This chart underscores the feedback of the virtual integrations (both internal to the supplier and the OEM as well as between supplier and OEM).

9

Aerospace Vehicle Systems Institute

Slide 9

DeliverablesDeliverables

Component-Based Model FrameworkMulti-Aspect Model Repository Definition

Framework for Description of ComponentsRules for constructing and interconnecting componentsRules for property definitions supporting required (integration) analyses

Model Bus Definition for Consistent Model to Model Information Interchange

Virtual Integration Analyses Definitions CatalogParametric Process Definition for achieving Virtual Integration

Integrating Component-Based, Model-Based and Proof-Based Development

Pilot Project(s) Results and Lessons Learned

10

Version Aerospace Vehicle Systems Institute

Slide 10

Backup SlidesBackup Slides

11

Aerospace Vehicle Systems Institute

Slide 11

Transition to System and SW Engineering Transition to System and SW Engineering Integration Based on ComponentIntegration Based on Component--Based Based ArchitecturesArchitectures

SoS and Systems are Composed Primarily of Components

Modules that Encapsulate Both Data and Functionality, and Are Configurable at Run-TimeRequires accurate Modeling and Analysis of Properties, Relationships, Attributes, Associations, Interactions and Dependencies between Components

Control, Data, Timing, Sequencing, Synchronization, Interrupts, Performance, Latency, Jitter, Safety, Security, Reliability, Resources, Fault Tolerance, and other Quality FactorsComposable, Reusable Software Modules

Requires Two PerspectivesIndependent of the context in which they are usedDependent on the context in which they are used

Requires Component-Based Model Framework

B C DA

BLK DETCMP

S1 S2

Sensor

SSn

The sketch emphasizes that subsystems and systems are built up from components that are composable and reusable (based on both mathematical and empirical “proofs”. The models that allow this must be

consistent internally and must interface seamlessly in an integrated system.

12

Aerospace Vehicle Systems Institute

Slide 12

MultiMulti--Aspect Models for ModelAspect Models for Model--Centric DevelopmentCentric Development

Different models, modeling, simulation and analysis tools may be necessary for

Different propertiesDifferent users

Compatible modelling tools (open source or commercially available)

TOPCASEDAADLMATLAB/Simulink

This chart illustrates four types of multiple-aspect models used to carry out this scheme of consistent, not necessarily identical models. It is imperative to recognize both the essential differences (purpose, intent, and implementation) of models and the need for consistency in interfaces to allow the strengths of these different properties to be harnessed in an integrated system. Whatever the origin of the tool, this need for consistency and proof-testing is a strong driver for this concept to work.

13

The overall effort is broken down into eight work packages in the expectation that each work package is likely to have its own set of interested participants and one or more AFEs to complete their tasks. Some work packages will underpin or overarch the whole project - like WP0, which sets the management structure for this multifaceted project. Similarly, WP6 and WP7 are concerned with how to adapt infrastructure to this style of model-based development.

There are a lot of interactions between the subtasks of the different WPs. The work is planned to take 3+ years to perform, and is split into five phases: red label preparation, red label execution (initial pilot project), red label assessment and revision for black label (i.e., preparation), black label execution (final pilot project), black label validation (assessment) and production preparation. Red label execution will be performed mainly by researchers, and will use proof-of-concept prototype tools, some of which may just be paper procedures. Black-label execution will be performed mainly by program people and will use pre-production tools.