addendum no. 3...robles forebay restoration specification no. 19-415 acknowledgement: by signature...

25
ADDENDUM NO. 3 Date of Issue: July 3, 2019 To all prospective Bidders on the Work titled: ROBLES FOREBAY RESTORATION, SPECIFICATION NO. 19-415 The Drawings and Project Manual including Specifications are modified as follows. This Addendum forms a part of the Contract Documents and modifies the original documents dated May 17, 2019. Acknowledge receipt of this Addendum in the space provided and in the Bidder’s Proposal. Failure to do so may subject the Bidder to disqualification. This Addendum consists of 4 pages and five attachments. Item AD3-1 Cover Sheet: Replace the last paragraph with the following: Bids will be received at the office of Casitas Municipal Water District, 1055 Ventura Avenue, Pak View, California 93022 until 11:00 a.m. on Thursday, July 11, 2019. Item AD3-2 Notice Inviting Bids: On page 1 of the Notice Inviting Bids, replace the first paragraph with the following: Sealed bids for the above referenced project and specification will be received by the Casitas Municipal Water District up to 11:00 a.m. on Thursday, July 11, 2019 at the office of the District, 1055 Ventura Avenue, Oak View, California 93022, at which time they will be opened and publicly read aloud. Item AD3-3 Bidder’s Bond: Replace with the attached Bidder’s Bond. Item AD3-4 RFI Question #1: Can the radial gates be opened or closed, if need be for construction? RFI Answer#1: Assume gates must remain closed during construction. Item AD3-5 RFI Question #2: Please provide elevations for the inlets to the fish ladder.

Upload: others

Post on 13-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

ADDENDUM NO. 3

Date of Issue: July 3, 2019

To all prospective Bidders on the Work titled:

ROBLES FOREBAY RESTORATION, SPECIFICATION NO. 19-415

The Drawings and Project Manual including Specifications are modified as follows. This Addendum

forms a part of the Contract Documents and modifies the original documents dated May 17, 2019.

Acknowledge receipt of this Addendum in the space provided and in the Bidder’s Proposal. Failure to do

so may subject the Bidder to disqualification.

This Addendum consists of 4 pages and five attachments.

Item AD3-1 Cover Sheet:

Replace the last paragraph with the following:

Bids will be received at the office of Casitas Municipal Water District,

1055 Ventura Avenue, Pak View, California 93022 until 11:00 a.m. on

Thursday, July 11, 2019.

Item AD3-2 Notice Inviting Bids:

On page 1 of the Notice Inviting Bids, replace the first paragraph with the

following:

Sealed bids for the above referenced project and specification will be received

by the Casitas Municipal Water District up to 11:00 a.m. on Thursday, July 11,

2019 at the office of the District, 1055 Ventura Avenue, Oak View, California

93022, at which time they will be opened and publicly read aloud.

Item AD3-3 Bidder’s Bond:

Replace with the attached Bidder’s Bond.

Item AD3-4 RFI Question #1:

Can the radial gates be opened or closed, if need be for construction?

RFI Answer#1:

Assume gates must remain closed during construction.

Item AD3-5 RFI Question #2:

Please provide elevations for the inlets to the fish ladder.

CASITAS MUNICIPAL WATER DISTRICT 2 Addendum No.3

Robles Forebay Restoration Specification No. 19-415

RFI Answer #2:

Drawings for the fish ladder are posted to the District’s website.

Item AD3-6 RFI Question #3:

Per the Surface Water Diversion Plan –What specific agencies have jurisdiction?

RFI Answer #3:

The Regional Water Quality Control Board (RWQCB) has jurisdiction. CMWD

prepared the attached Stream Diversion Plan for the Robles Forebay Restoration

and has submitted to RWQCB for approval. The RWQCB has 30 days to

respond and it is anticipated approval will be received in time for the Contractor

to implement the Stream Diversion Plan within the project timeframe.

Item AD3-7 RFI Question #4:

Per the Groundwater Water Discharge Permit – Due to time constraints, has

CMWD applied for the permit?

RFI Answer #4:

CMWD performed water quality sampling for groundwater and surface water

and has received only limited laboratory results to date. Upon receipt of all

water quality sampling results, CMWD will submit a Notice of Intent (NOI) to

the RWQCB for Discharge of Groundwater to Surface Water. For the purposes

of bidding, use the following information:

Estimated pumping volume:

Conservative volumetric estimates for dewatering pumping were calculated using surface

water discharge based on the 2018-19 water year, historic hydrology records, and

understanding of the local hydrogeology. The estimated discharge volume of

groundwater is approximately 485,000 to 1,292,000 gallons per day (337 – 898 gallons

per minute), with an estimated average of 889,000 gallons per day (617 gallons per

minute).

Treatment requirements:

Based on available analytical data, treatment is required for DEHP [Di(2-ethylhexyl)

phthalate], in accordance with the General Permit (Order R4-2018-0125). Assume

treatment is required for the pending analytes (metals and miscellaneous pollutants). The

attached list of analytes (part of the NOI) compares the analytical results to the General

Permit screening levels. Note the blanks in the quantitation column, which identifies the

pending analysis. Also attached is a draft figure to present the approximate intake and

discharge locations as well as the planned treatment system location (these locations

were chosen based on site knowledge, but are subject to change based on site conditions

and project needs).

Item AD3-8 Notice Inviting Bids:

On Page 9, Replace Bid Schedule with the attached Bid Schedule.

Item AD3-9 Part C Special Conditions:

On Page 74, replace sections 12. (f) and (g) with the following:

(f) In the event surface water is present, the Contractor is required to implement the

approved water diversion plan the District has obtained from the Regional Water Quality Control

CASITAS MUNICIPAL WATER DISTRICT 3 Addendum No.3

Robles Forebay Restoration Specification No. 19-415

Board (RWQCB). The District will conduct the water sampling and testing. Once water is

successfully being diverted with no impact on water quality, the Contractor can begin work.

(g) In the event groundwater is present, the Contractor is required to dewater the

site. The groundwater must be treated and discharged downstream. The District expects to have a

groundwater discharge permit by the time construction begins. The Contractor shall be expected

to treat up to 620 gallons per minute and treat for full range of pollutants (list of Analytes

attached). The District will conduct the water sampling and testing. The District will notify the

Contractor in writing when the water is acceptable to discharge. Once water is successfully

discharged with no impact on water quality, the Contractor can begin work.

Item AD3-10 Part D Measurement & Payment:

On Page 76, replace Section 6. (d) Bid Item No. 2 Groundwater Dewatering,

Treatment and Discharge with the following:

(1) Measurement shall be based on a Unit Cost basis for the treatment and discharge

of groundwater at the rate of 620 Gallons Per Minute (GPM) in a 24 hour

period (1 day). Payment based upon such measurement shall constitute full

compensation for: installing the system; controlling, treating and discharging

groundwater; permit/agreement requirements; maintenance of system during the

project; the complete removal and disposal of the system at the conclusion of the

project; and all other related or appurtenant work and actions to meet the

requirements of the permit conditions.

(2) In the event the District terminates the Contract, measurement shall be based on

a field survey that shall be converted to a number of whole days for the work

performed by the Contractor associated with dewatering, treating and

discharging of groundwater. Payment shall be based on the number of whole

days, as determined by the measurement applied to the unit cost for Bid Item No.

2 provided by the Contract proposal. Payment based on said measurement shall

constitute full compensation for completed work specified for Bid Item No. 2.

Item AD3-11 Part D Measurement & Payment:

On Page 76 and 77, replace section 6. (e) Bid Item No. 3 Surface Water

Diversion with the following:

(1) Measurement shall be based on a lump sum basis. Payment based upon such

measurement shall constitute full compensation for controlling surface water,

permit/agreement requirements, all other related or appurtenant work and actions

to meet the requirements of the permit conditions, maintenance of system during

the project and the complete removal and disposal of the system at the

conclusion of the project.

(2) In the event the District terminates the Contract, measurement shall be based on

a field survey measurements that shall be converted to a number of whole days

of work performed by the Contractor for work to divert surface water. Payment

shall be based on the whole number of days, as determined by the measurement

applied to the total lump sum bid cost for Bid Item No. 3 provided by the

Contract proposal. Payment based on said measurement shall constitute full

compensation for completed work specified for Bid Item No. 3.

CASITAS MUNICIPAL WATER DISTRICT 4 Addendum No.3

Robles Forebay Restoration Specification No. 19-415

Acknowledgement:

By signature below, Bidder acknowledges Addendum No. 3.

Signed: ______________________________________

Attachments: 1 - Bidder’s Bond

2 - Stream Diversion Plan for Robles Forebay Restoration

3 - List of Analytes

4 - Draft Exhibit for Intake and Discharge Locations

5 - Bid Schedule

END OF ADDENDUM NO. 3

Casitas Municipal Water District Specification No. 19-415

13

BIDDER'S BOND

KNOW ALL MEN BY THESE PRESENTS,

That we

, as PRINCIPAL,

and

as SURETY,

are held and firmly bound unto the Casitas Municipal Water District, hereinafter called the

District, in the penal sum of TEN PERCENT (10%) OF THE TOTAL AMOUNT OF THE BID

of the Principal above named, submitted by said Principal to the Casitas Municipal Water

District, for the work described below, for the payment of which sum in lawful money of the

United States, well and truly to be made, we bind ourselves, our heirs, executors, administrators

and successors, jointly and severally, firmly by these presents.

In no case shall the liability of the surety hereunder exceed the sum of $

THE CONDITIONS OF THIS OBLIGATION ARE SUCH,

That whereas the Principal has submitted the above-mentioned bid to the Casitas Municipal

Water District, for certain construction specifically described as ROBLES FOREBAY

RESTORATION SPECIFICATION NO. 19-415 which bids are to be opened at the office of

Casitas Municipal Water District on Thursday, July 11, 2019 at 11:00 a.m.

NOW, THEREFORE, if the aforesaid Principal is awarded the contract and, within the time and

manner required under the heading Instructions to Bidders, after the prescribed forms are

presented to him for signature, enters into a written contract, in the form set forth in said

specifications, in accordance with the bid, and files the two bonds with the District, one to

guarantee faithful performance and the other to guarantee payment for labor and materials, as

required by Instructions to Bidders and Certificate of Insurance for Workmen's Compensation

and Contractor's liability insurance, then this obligation shall be null and void; otherwise, it shall

be and remain in full force and virtue.

In the event suit is brought upon this bond by the Obligee and judgement is recovered, the surety

shall pay all costs incurred by the Obligee in such suit, including a reasonable attorney's fee to be

fixed by the court.

Bidder's Bond (Continued)

Casitas Municipal Water District Specification No. 19-415

14

IN WITNESS WHEREOF, we have hereunto set our hands and seals this _______ day of

______________________________, 2019.

_________________________________________________

Principal

By ______________________________________________

(SEAL)

NOTE: Signatures of those executing for the surety must be properly acknowledged

1055 Ventura Ave • Oak View, CA 93022 • (805) 649-2251 • Fax (805) 649-3001 • www.casitaswater.org

ROBLES FOREBAY RESTORATION

STREAM DIVERSION PLAN

SUBMITTAL TO:

LOS ANGELES REGIONAL WATER QUALITY CONTROL BOARD

REFERENCE SECTION 401 WATER QUALITY CERTIFICATION

FOR ROBLES FOREBAY RESTORATION PROJECT

July 3, 2019

Prepared by: Julia Aranda, PE

[email protected] 805.649.2251

This page left intentionally blank

Casitas Municipal Water District Robles Forebay Restoration Stream Diversion Plan

Page i

Contents 1.0 Introduction ...................................................................................................................................... 1

2.0 Diversion Plan ................................................................................................................................... 2

2.1 Best Management Practices ............................................................................................................. 2

3.0 Preconstruction Baseline Monitoring ............................................................................................... 4

4.0 Construction Monitoring and Reporting ........................................................................................... 5

4.1 Sampling Locations ........................................................................................................................... 5

4.2 Sampling ............................................................................................................................................ 5

4.3 Corrective Measures for Non-compliance ........................................................................................ 5

4.4 Reporting........................................................................................................................................... 5

Figures Figure 2-1 Stream Diversion Plan

Figure 2-2 Stream Diversion Plan Detail

Casitas Municipal Water District Robles Forebay Restoration Stream Diversion Plan

Page ii

This page left intentionally blank.

Casitas Municipal Water District Robles Forebay Restoration Stream Diversion Plan

Page 1

1.0 Introduction

This document provides the Stream Diversion Plan for the Robles Forebay Restoration Project, located at Casitas Municipal Water District’s (CMWD) Robles Diversion Facility along the Ventura River in Ojai, California. This Plan was prepared in accordance with the Los Angeles Regional Water Quality Control Board’s 401 Water Quality Certification, an application for which was submitted May 8, 2019.

The Robles Diversion Facility was affected due to the Thomas Fire. The Forebay upstream of the facility filled with sediment which impacts the ability of CMWD to regulate the amount of water available to divert to storage and discharge down the fish ladder. This project seeks to remove approximately 50,000 cubic yards of sediment from the Forebay and place it downstream of the timber cutoff wall in August/September 2019 for transportation by future storm events. In future years the amount of sediment removal will vary and is expected to range between 20,000 and 50,000 cubic yards annually. The proposed stream diversion and water quality monitoring are described in the following sections.

Casitas Municipal Water District Robles Forebay Restoration Stream Diversion Plan

Page 2

2.0 Diversion Plan

The area in the Robles Forebay is usually dry by June each year. Due to the heavy rains in winter 2019, the late storms in May 2019, and the lack of mature vegetation in the watershed due to the Thomas Fire, this area is still saturated and has active flow. The diversion is needed to allow the Forebay to dry out sufficiently so sediment removal can be performed. Should stream flow persist in August 2019, when the project is scheduled to begin, the stream diversion will remain in place throughout sediment removal activities in the Forebay, to divert stream flow around the work area. Figure 2-1 shows the elements of the water diversion. If the river is still flowing, a sandbag cofferdam will be erected to divert surface water into a 24-inch diameter high-density polyethylene (HDPE) pipe. The inlet of the diversion will be located approximately 1,000 feet upstream of the Robles Diversion Facility.

The pipe will convey water downstream approximately 800 feet and will be directed in to the high flow exit of the fish ladder. The water will travel down the existing five-foot wide concrete channel and exit into the screen forebay of the fish passage. At this point, the water has rejoined the normal pathway through the fish passage.

The pipe is sized to handle the current flow rate of approximately 15 cubic feet per second (cfs) while maintaining a velocity of no more than approximately six feet per second (fps). Fish may still pass should they choose to move upstream. The diversion pipe will have a cone shaped metal grate installed on the inlet as shown in Figure 2-2. The grate will keep debris from clogging the pipe and humans from attempting to or accidentally entering the pipe, but will still allow fish to move freely through the device.

The contractor will access the site from the end of Rice Road and use the existing access road to cross

the River. In the event there is active flow across the low-flow weir crossing, steel plating will be placed

across the weir as it is a steep slope. The HDPE pipe will be fused together in the upland disturbed area

west of the facility headworks and the contractor will attach a strap to the pipe and use an excavator to

put the pipe in place. The contractor may need to use the excavator to move some larger rocks out of

the way in the stream channel.

2.1 Best Management Practices

The following Best Management Practices will be implemented:

The District intends to implement the project between August 15 and September 30 each year outside the bird nesting season (typically February 1 – August 1) and winter rainy season (typically November – April) to avoid the conditions in which special status species may be present.

Project activities occurring between February 1 and August 31 will involve a qualified biologist to survey the project site within five (5) days of project commencement for nesting birds. Should any protected breeding/nesting birds be observed, the biologist will flag the area and implement appropriate avoidance measures to preclude impacts.

Immediately prior to ground disturbance, the impact areas and channel will be surveyed to ensure no sensitive terrestrial and aquatic species have entered the work area.

During ground disturbance activities, a biological monitor will be on site to ensure agency mitigation requirements are met.

Casitas Municipal Water District Robles Forebay Restoration Stream Diversion Plan

Page 3

The clean-up of any accidental spill will begin immediately pursuant to all relevant hazardous materials regulations. If the spill could affect downstream water quality or impact special status resources, the appropriate regulatory agencies will be notified to determine the appropriate course of action.

All trash will be properly contained and removed from the work site daily. Any construction materials that could potentially wash downstream will be removed from the project site prior to inundation by high flows. When operations are completed, any excess materials or debris will be removed from the work area.

Any material/spoils generated from project activities will be located away from jurisdictional areas and protected from stormwater run-off using temporary perimeter sediment barriers such as berms, silt fences, fiber rolls, covers, sand/gravel bags, and straw bale barriers, as appropriate.

Any spillage of material will be cleaned up immediately and any contaminated materials will be properly disposed.

Staging and laydown areas shall be unvegetated areas and previously disturbed sites.

All vehicles and equipment shall be in good working condition and free of leaks. The contractor shall prevent oil, petroleum products, or any other pollutant from contaminating the soil or entering a watercourse (dry or otherwise). When vehicles or equipment are stationary, mats or drip pans shall be placed below vehicles to contain fluid leaks.

All re-fueling, cleaning, or maintenance of equipment will occur at least 100-feet from potentially jurisdictional waters.

Casitas Municipal Water District Robles Forebay Restoration Stream Diversion Plan

Page 4

3.0 Preconstruction Baseline Monitoring

Baseline water sampling for dissolved oxygen, pH, turbidity, and temperature will be conducted no more than 24 hours prior to the commencement of in-river water activities to determine the baseline parameters at the site. The data will be recorded on a Water Quality Monitoring Log.

The baseline sampling location will be within the low flow channel above and below the project impact area. All equipment utilized for sampling will be utilized and calibrated per the manufactures’ specifications. Sampling equipment will include a dissolved oxygen meter, a waterproof pH/temperature meter, and a portable turbidity meter.

Casitas Municipal Water District Robles Forebay Restoration Stream Diversion Plan

Page 5

4.0 Construction Monitoring and Reporting

All monitoring and reporting will be done in compliance with the 401 Water Quality Certification to be issued by the RWQCB for the project.

4.1 Sampling Locations

The upstream and downstream sampling locations will be determined prior to and immediately following the construction of the diversion and photographs will be taken. The upstream location will be immediately upstream of the diversion where water enters into the diversion pipe and the downstream point will be immediately downstream of the high flow fish exit.

4.2 Sampling

Per typical 401 Water Quality Certification requirements, daily testing will be conducted for dissolved oxygen, pH, turbidity, and temperature for the first week and weekly thereafter. Oil and grease will be monitored visually on a continuous basis.

Samples will be compared to receiving the following water quality standards:

Dissolved oxygen (DO): concentration of a single sample shall not be less than 5.0 milligrams per liter (mg/l) except when natural conditions cause lower concentrations. The DO content of all surface waters designated as COLD shall not be depressed below 6 mg/l as a result of the diversion.

pH: shall not be depressed below 6.5 or raised above 8.5 as a result of the diversion. Ambient pH levels shall not be changed more than 0.5 units from natural conditions as a result of waste discharge.

Turbidity: Downstream total suspended solids (TSS) shall be maintained at ambient levels. Where natural turbidity is between 0 and 50 Nephelometric Turbidity Units (NTUs), increases shall not exceed 20 percent; where natural turbidity is greater than 50 NTUs, increases shall not exceed 10 percent.

4.3 Corrective Measures for Non-compliance

If sampling indicates non-compliance with the thresholds described above the situation will addressed immediately. Corrective actions will include ensuring compliance with all the Project Implementation Conditions in the project’s 401 certification and/or adjusting Best Management Practices for erosion control if applicable. If water quality objectives are not met by these means, a Baker tank will be considered and discussed with the Water Board to allow for settling of sediment and/or removal of dewatered water from the site for disposal. Any non-compliant readings will be recorded in the daily log with a description of the corrective actions taken.

4.4 Reporting

A report will be prepared and submitted to the Los Angeles Regional Water Quality Control Board by the 15th day of each subsequent sampling month, after the diversion is constructed and/or dewatering begins. The report will provide:

Casitas Municipal Water District Robles Forebay Restoration Stream Diversion Plan

Page 6 Date and time samples are taken

Location(s) of sampling

A narrative description of diversion function and stage

A table with sampling results for dissolved oxygen, pH, turbidity, oil/grease, and analysis discussion

Corrective actions taken, if any

Photos of the sampling points and any pertinent photos of the diversion

The In-Water Work/Diversions Water Quality Monitoring Report will be submitted to the Los Angeles Water Board staff within three working days following completion of the stream diversion.

Casitas Municipal Water District Robles Forebay Restoration Stream Diversion Plan

Page 7

FIGURES:

FIGURE 2-1 STREAM DIVERSION PLAN

FIGURE 2-2 STREAM DIVERSION PLAN DETAIL

This page left intentionally blank

Quantitation Level Minimum LevelsMUN(a) Others(b)

(μg/L) (μg/L) (μg/L) (μg/L)

1097 Antimony (Sb) 6 14 51000 Arsenic (As) 10 36 101012 Beryllium (Be) 4 NA 0.51027 Cadmium (Cd) 2.3 2.2 (9.3) 2 0.51033 Chromium III (Cr3+) 50 180 101032 Chromium VI (Cr6+) 11 11 51119 Copper (Cu) 9 9.0 (3.1) 2 0.5

720 Cyanide (CN) 5.2 5.2 (NA) 2 51051 Lead (Pb) 2.5 25 (8.1) 2 0.5

71900 Mercury (Hg) 0.05 0.051 0.21067 Nickel (Ni) 52 52 (8.2) 2 11147 Selenium (Se) 5 5 (71) 2 21077 Silver (Ag) 3.4 3.4 (1.9) 2 0.251059 Thallium (Ti) 1.7 6.3 11092 Zinc (Zn) 120 120 (81) 2 1

34496 1,1 Dichloroethane ND 5 5 0.534501 1,1 Dichloroethylene ND 0.057 3.2 0.534506 1,1,1 Trichloroethane ND 200 200 234511 1,1,2 Trichloroethane ND 0.6 42 0.534516 1,1,2,2 Tetrachloroethane ND 0.17 1 0.534536 1,2 Dichlorobenzene ND 600 600 0.532103 1,2 Dichloroethane ND 0.38 99 0.534541 1,2 Dichloropropane ND 0.52 39 0.534549 1,2-Trans Dichloroethylene trans-1,2-Dichloroethylene ND 10 10 134566 1,3 Dichlorobenzene ND 400 2600 234561 1,3 Dichloropropylene 1,3 Dichloropropene (Total) ND 0.5 0.5 0.534571 1,4 Dichlorobenzene ND 5 0.5 0.534576 2-Chloroethyl vinyl ether ND NA NA 134210 Acrolein ND 100 100 534215 Acrylonitrile ND 0.059 0.66 234030 Benzene ND 1 1 0.532104 Bromoform ND 4.3 360 0.532102 Carbon Tetrachloride ND 0.25 0.5 0.534301 Chlorobenzene ND 30 21000 234306 Chlorodibromo-methane 0.401 34 0.585811 Chloroethane ND 100 100 232106 Chloroform ND 100 100 232101 Dichlorobromo-methane Bromodichloromethane ND 0.56 46 0.578113 Ethylbenzene ND 700 700 234413 Methyl Bromide Bromomethane ND 10 4000 234418 Methylene Chloride ND 4.7 1600 0.534475 Tetrachloroethylene Tetrachloroethylene (PCE) ND 0.8 8.85 0.534010 Toluene 0.697 150 150 239180 Trichloroethylene ND 2.7 5 0.539175 Vinyl Chloride ND 0.5 0.5 0.5

63 Xylenes ND 1750 1750 NAAcetone ND 700 700 NAEthylene Dibromide 0.05 0.05 NAMethyl Chloride Chloromethane ND 3 3 0.5Methyl ethyl ketone 2 Butanone (MEK) ND 700 700 NAMethyl tertiary butyl ether (MTBE) ND 5 5 NA

34536 1,2 Dichlorobenzene ND 600 17000 0.534346 1,2 Diphenylhydrazine ND 0.04 0.54 134551 1,2,4 Trichlorobenzene ND 70 NA 534566 1,3 Dichlorobenzene ND 400 2600 234571 1,4 Dichlorobenzene ND 5 2600 234586 2 Chlorophenol ND 120 400 534601 2,4 Dichlorophenol ND 93 790 534606 2,4 Dimethylphenol ND 540 2300 234616 2,4 Dinitrophenol ND 70 14000 534611 2,4 Dinitrotoluene ND 0.11 9.1 534624 2,4,6 Trichlorophenol ND 2.1 6.5 1034626 2,6 Dinitrotoluene ND NA NA 5

SEMI-VOLATILE ORGANICS

ID Num. POLLUTANT SynonymScreening Levels

METALS1

VOLATILE ORGANICS

34591 2-Nitrophenol ND NA NA 1034581 2-Chloronaphthalene ND 1700 4300 1034631 3,3’ Dichlorobenzidine ND 0.04 0.077 5

3-Methyl-4-Chlorophenol NA NA 13615 2-Methyl-4,6-Dinitrophenol 13 765 5

34646 4-Nitrophenol ND NA NA 534636 4-Bromophenyl phenyl ether ND NA NA 534641 4-Chlorophenyl phenyl ether ND NA NA 534205 Acenaphthene ND 1200 2700 134200 Acenaphthylene ND NA NA 1034220 Anthracene ND 9600 110000 539120 Benzidine ND 0.00012 0.00054 534526 Benzo (a) Anthracene ND 0.0044 0.049 534247 Benzo (a) Pyrene ND 0.0044 0.049 234230 Benzo (b) Fluoranthene ND 0.0044 0.049 1034521 Benzo (g,h,i) Perylene ND NA NA 534242 Benzo (k) Fluoranthene ND 0.0044 0.049 234278 Bis (2-Chloroethoxyl) methane ND NA NA 534273 Bis(2-Chloroethyl) ether ND 0.031 1.4 134283 Bis(2-Chloroisopropyl) ether ND 1400 170000 1039100 Bis(2-Ethylhexyl) phthalate 167 1.8 5.9 534292 Butyl benzyl phthalate ND 3000 5200 1034320 Chrysene ND 0.0044 0.049 534556 Dibenzo(a,h)-anthracene ND 0.0044 0.049 0.134336 Diethyl phthalate ND 23000 120000 1034341 Dimethyl phthalate 5.49 313000 2900000 1039110 di-n-Butyl phthalate 1.4 2700 12000 1034596 di-n-Octyl phthalate ND NA NA 1034376 Fluoranthene ND 300 370 1034381 Fluorene ND 1300 14000 1039700 Hexachlorobenzene ND 0.00075 0.00077 139702 Hexachlorobutadiene ND 0.44 50 134386 Hexachloro-cyclopentadiene ND 50 17000 534396 Hexachloroethane ND 1.9 8.9 134403 Indeno(1,2,3,cd)-pyrene ND 0.0044 0.049 0.0534408 Isophorone ND 8.4 600 134438 N-Nitrosodimethyl amine (NDMA) ND 0.00069 8.1 534428 N-Nitroso-di-n-propyl amine ND 0.005 1.4 534433 N-Nitrosodiphenyl amine ND 5 16 134696 Naphthalene ND 21 NA 1034447 Nitrobenzene ND 17 1900 1039032 Pentachlorophenol ND 0.28 7.9 134461 Phenanthrene ND NA NA 534694 Phenol 1.23 21000 4600000 5034469 Pyrene ND 960 11000 10

39310 4,4’-DDD ND 0.00083 0.00084 0.0539320 4,4’-DDE ND 0.00059 0.00059 0.0539300 4,4’-DDT ND 0.00059 0.00059 0.0178428 Alpha-Endosulfan Endosulfan I ND 0.056 0.0087 0.0239336 Alpha-BHC ND 0.0039 0.013 0.0139330 Aldrin ND 0.00013 0.00014 0.00534356 Beta-Endosulfan Endosulfan II ND 0.056 0.0087 0.0139338 beta-BHC ND 0.014 0.046 0.00539350 Chlordane ND 0.00057 0.00059 0.134198 delta-BHC ND NA NA 0.00539380 Dieldrin ND 0.00014 0.00014 0.0134351 Endosulfan Sulfate ND 110 240 0.0539390 Endrin ND 0.036 0.0023 0.0134366 Endrin Aldehyde ND 0.76 0.81 0.0139410 Heptachlor ND 0.00021 0.00021 0.0139420 Heptachlor Epoxide ND 0.0001 0.00011 0.0139340 gamma-BHC ND 0.019 0.063 0.02

4166 PCB 1016 ND 0.00017 0.00017 0.54166 PCB 1221 ND 0.00017 0.00017 0.54166 PCB 1232 ND 0.00017 0.00017 0.54166 PCB 1242 ND 0.00017 0.00017 0.54166 PCB 1248 ND 0.00017 0.00017 0.54166 PCB 1254 ND 0.00017 0.00017 0.5

PESTICIDES AND PCBs

4166 PCB 1260 ND 0.00017 0.00017 0.539400 Toxaphene ND 0.00073 0.00075 0.5

82698 2,3,7,8-TCDD (Dioxin) ND 1.30E-08 1.30E-08 0.00001948 Asbestos (in fibers count/liter) ND 7000000 7000000 NA

Di-isopropyl ether (DIPE) 0.8 0.8 21,4-Dioxane 3 3 NAEthanol 1000 1000 1000Ethyl tertiary butyl ether (ETBE) 2 2 2Methanol 1500 1000 1000 1000Methyl tertiary butyl ether (MTBE) ND 5 5 NAPerchlorate 6 6 NATertiary amyl methyl ether (TAME) 2 2 2Tertiary butyl alcohol (TBA) 12 12 10Total petroleum hydrocarbons ND 100 100 NA

(a) = Applies to water with Municipal and Domestic Supply (MUN) (indicated with E or an I in the Basin Plan) beneficial uses designations.(b) = Applies to all other receiving waters.1 = Metals concentrations are expressed as total recoverable.2 = Applicable to saltwater bodies only.NA = not applicable.

MISCELLANEOUS

CASITAS MUNICIPAL WATER DISTRICT 5 Addendum No.3

Robles Forebay Restoration Specification No. 19-415

BID SCHEDULE

ROBLES FOREBAY RESTORATION

SPECIFICATION NO. 19-415

Schedule of prices for all work, materials and site cleanup for the above-mentioned project and

specification in accordance with these specifications. Any item not specifically mentioned shall

be considered incidental to the item to which it pertains. The Bidder shall list prices for all bid

items. Bids received which do not list prices in succession shall be rejected.

Bid

Item

#

Quantity

Unit

Description & Price in Words Unit

Price

Amount $

1

N/A

1

Excavate 50,000 cubic yards of material and place

material in designated areas, debris removal and

disposal, grading, complying with requirements of

permitting agencies, and all other related or appurtenant

work thereto for the lump sum price of

Dollars

LS

$

2

30

day

Provide groundwater dewatering, treatment and

discharge, of 620 gallons per minute (gpm) at project

location for the unit cost price of

Dollars per day

Unit Cost

$

/ Day

$

3

N/A

1

Provide surface water diversion for the project for the

lump sum price of

Dollars

LS

$

TOTAL BID AMOUNT (Items 1 -3) $____________________________________________

(Figures)

______________________________________________________________________________

__________

______________________________________________________________________________

_ (Words)