acf pakistan drm (rne) final evaluation

Upload: asad-mahmood

Post on 23-Feb-2018

230 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    1/34

    Photo NIaz Murtaza

    Funded by Royal Norwegian Embassy in Islamabad

    Niaz Murtaza, January 2012

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    2/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    1

    TABLE OF CONTENTS

    Executive Summary

    2

    Chapter 1: Brief Background

    Emergency Context in Pakistan

    Overview of the ProjectProject Details

    4445

    Chapter 2: Methodology

    Evaluation QuestionsEvaluation Approach

    Evaluation Constraints

    777

    8

    Chapter 3: Findings

    TargetingProject DesignProject ImplementationProject MonitoringProject SustainabilityCross-Cutting Issues

    99

    1316192022

    Chapter 4: Conclusions and Recommendations

    ConclusionsRecommendations

    252526

    Appendix

    Damage in KP from 2010 FloodsScoring Matrix

    AcronymsList of interviews

    List of documents reviewedGood practice case study

    2929293131

    3232

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    3/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    2

    XECUTIVE SUMMARYOver the last decade, Pakistan has experienced large-scale internal displacement

    caused by a range of natural and human-made disasters. Structural poverty,

    inappropriate development, rapid urbanization, inadequate infrastructures,

    increased deterioration of the environment - deforestation, increased human

    settlements in hazard prone areas, etc. have increased the vulnerability to disasters. Thus, even

    a moderate flooding could have devastating effects in the future. An ACF DRM assessment

    identified a lack of awareness amongst stakeholders concerning DRM, and thus a need for

    capacity building. Thus, ACF carried out a DRM project funded by the Royal Norwegian

    Embassy during 2011-12 to reduce morbidity and mortality risks by improving community

    resilience to natural disasters in Nowsherra, Charsadda, Mardan and Lower Dir regions of KPK

    province in northern Pakistan which are vulnerable to both serious floods and earthquakes.

    At the end of 2012, ACF commissioned an evaluation to evaluate the impact and approach of

    ACFs RNE funded DRM project. ACF subscribes to the Development Assistance Committee(DAC) criteria for evaluation: Impact, Sustainability, Coherence, Coverage, Relevance /

    Appropriateness, Effectiveness and Efficiency. ACF also promotes systematic analysis of the

    monitoring system and cross cutting issues (gender, HIV/AIDS etc). These dimensions served

    as the main evaluation criteria. The tools included documents review, interviews with ACF

    international and national staff, government officials and partner staff and household interviews

    (with 204 community members), Focus Group discussions and transect walks in 18 villages.

    Conclusions and Recommendations

    Overall, the project is highly relevant to Pakistan given its high disaster vulnerability and is a

    well-conceived one with an excellent and comprehensive mix of hardware and softwareactivities. Many of the project activities have also been implemented well though others do have

    some room for improvement. The main findings can be summarized as follows: i) Targeting of

    the most vulnerable is excellent in Charsadda and Nowshera but is less accurate in Mardan and

    Dir; ii) ACF has set-up village committees to enhance the sustainability of project activities but

    the committees must be linked adequately with other NGOs and the government to enhance

    sustainability, iii) The hardware activities should focus more on those which provide more

    structural and pro-active protection against floods, iv) Spreading the message to the whole

    communities in villages has proven to be a challenge due to their large sizes, v) A sizeable

    proportion of the project activities got delayed to the last month due to government permission

    delays, procurement delays and staff training, vi) there is a need to enhance the technical

    capacity of the team in software DRM activities, vii) monitoring and accountability mechanism

    need to be strengthened. Thus, the main recommendations are as follows:

    I. Targeting: It is recommended to continue work in Dir, Charsadda and Nowshera but to

    reconsider working in Mardan due to its relatively low vulnerability and to undertake a more

    thorough needs assessment in Dir to be able to target the most vulnerable village there. ACF

    E

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    4/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    3

    is also advised to focus on districts highly vulnerable to major floods based on the following

    three criteria: River and drainage channels mapping; Damage incurred during 2010 floods and

    UNDP One DRM project list of most vulnerable districts. Consider Sindh for DRM work too

    since it has recently become the most repeatedly struck province in Pakistan.

    II. Number of villages: Review the possibility of increasing the number of villages in the nextphase by increasing the number of field staff, covering each village with only one hardware

    construction activity and linking with other NGOs and government agencies to cover some of

    the construction work that ACF cannot afford in its budget.

    III.

    Selection of hardware activities: Use the prevention-mitigation-capacity-evacuation-

    rescue-relief continuum of DRM activities presented in Chapter 3 to select hardware activities.

    The contingency stocks are an important hardware input given their relatively low cost and the

    fact that they cover three categories in the continuum even though they are the three bottom-

    most categories. Select other hardware construction activities from the highest possible

    category of this continuum which is relevant and affordable.

    IV.

    Village committee sustainability: Enhance the sustainability village committees by

    providing them training on CBO management issues, having them adopted by other agencies

    working long-term in the area (e.g., Concern), and linking nearby committees with each other

    for mutual support and learning during crisis and normal times

    V.

    Community DRM awareness-raising: Follow up more closely with committees about their

    community DRM awareness-raising session schedules and also look at the possibility of

    training young educated and unemployed persons in each UC to conduct sessions in all

    targeted villages in that UC for a small honorarium

    VI. Monitoring and accountability: Develop formal monitoring plans which clearly specify the

    role for all relevant staff in the projects monitoring, including the frequency, modality, project

    dimension and indicators for each relevant ACF staff and how the information coming from the

    monitoring done by each staff will be analyzed and summarized Also institute strong and

    responsive accountability measures in future projects. Build sufficient time in projects for

    government approvals and procurements.

    VII. External linkages: ACF should aim to increase government involvement in the project. ACF

    could get its village committees registered, and advocate with the DDMAs to treat NGO village

    committees as valid structures any government future grass-roots DRM initiatives. It should

    sign an MOU with government at time of starting the project which mentions the roles,

    responsibilities and inputs that both sides will provide. ACF should also enhance its profile in

    coordination sectors like the DRR Forum and the UNDP DRM project and obtaining greater

    technical inputs from them. Enhance technical inputs on DRM work by having CPDM provide

    some degree of field-based support to ACF staff on software issues, e.g., by developing the

    software package in one model village.

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    5/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    4

    HAPTER

    1

    : BACKGROUND

    This chapter provides an overview of the emergency context in Pakistan, and

    the specific project implemented by ACF with Royal Norwegian Embassy

    funding which is the subject of evaluation in this report. The chapter serves the

    purpose of placing the whole evaluation in its proper context and in familiarizingthe reader with the project constraints and scope.

    1.

    Emergency Context in Pakistan

    Over the last decade, Pakistan has experienced large-scale internal displacement caused by a

    range of natural and human-made disasters. Large-scale displacement occurred in Pakistan in

    2010 after the worst flooding to hit Pakistan in memory affected 20 million people, forcing over 7

    million people from their homes. Although most of the flood IDPs returned to their home areas

    soon after floodwaters receded, most were living in the open for prolonged periods as over 1.9

    million houses were damaged or destroyed. The crisis in 2010 was only the latest in Pakistan. It

    had been preceded by dislocation of population following clashes between rival militant and

    sectarian groups in the tribal areas; military operations against extremist militants and

    insurgents; generalized violence and violations of human rights; a devastating earthquake in

    2005; and annual floods across the country. Structural poverty, inappropriate development,

    rapid urbanization, inadequate infrastructures, increased deterioration of the environment -

    deforestation, increased human settlements in hazard prone areas, etc. have increased the

    vulnerability to disasters. Flooding recurred in 2011 and 2012, which combined with incomplete

    recovery in the 2010 flood-affected districts. Thus, even a moderate flooding could have

    devastating effects in the future.

    2.Overview of the ProjectAn ACF DRM assessment in 2010-11 showed that community and provincial DRM plans do not

    exist (except for symbolic or outdated documents). It identified a lack of awareness amongst

    stakeholders concerning DRM, and thus a need for capacity building. It also recognized a need

    for structural mitigation to reinforce infrastructure against the damage caused by a disaster, a

    need for improved management of agricultural land as well as a need for community level DRM

    activities. Thus, ACF carried out a DRM project funded by the Royal Norwegian Embassy during

    2011-12 to reduce morbidity and mortality risks by improving community resilience to natural

    disasters. With a focus towards infrastructure that is highly affected by disasters, yet vital after a

    disaster occurs, as well as early warning systems which are imperative for reducing loss of lifeand environmental degradation stemming from natural hazards, ACF aimed to develop local

    capacity and introduce risk mitigation in the intervention areas. The project was a multi-

    disciplinary initiative that aimed to involve a variety of stakeholders including ministries, local

    authorities, disaster management agencies, NGOs, the academic sector and communities. The

    direct beneficiaries of the project were the vulnerable populations affected by natural and man-

    made disasters in Nowsherra, Charsadda, Mardan and Lower Dir regions of KPK province in

    C

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    6/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    5

    northern Pakistan which are vulnerable to both serious floods and earthquakes. The basic

    premise of the project was that communities generally understand local realities and contexts

    better than outsiders. If at-risk groups are involved in all stages of the disaster risk

    management, a stronger foundation will be created for the development of sustainable

    programs for risk reduction. Through the use of participatory techniques for data collection and

    analysis, hazard analysis, trainings, ACF aimed to ensure full participation.

    3.Project Details

    Project General Objective

    To reduce vulnerability and improve resilience to disasters in four districts of KPK, Pakistan

    Specific Objectives

    To enable communities to prepare for and mitigate the impacts of disasters using participatory

    methods aimed at strengthening the self-reliance capacities of the population and reinforcing

    or adapting infrastructure

    Results

    R.1- The ability to recognize hazard events and to cope with their effects is improved

    R.2- The capacity to reduce the effect of hazards on communities and services is improved

    R.3- The understanding/application of DRM at community and institutional level is improved

    Programme Activities

    R.1- The ability to recognize hazard events and to cope with their effects is improved

    80% of intervention communities have functional local early warning systems

    80% of target community can claim access to contingency stocks

    90% of target communities are covered by disaster management plans.

    R.2- The capacity to reduce the effect of hazard event on communities is improved

    Facilities serving 60 communities are structurally strengthened to resist hazard events

    90% of intervention communities have identified and equipped evacuation sites

    R.3-The understanding/application of DRM at community/institutional level is improved

    80% of intervention communities have disaster management units

    240 individuals from local or district authorities receive DRM training

    25500 individuals in the communities receive DRM Training

    Specific Activities

    Installation of Early Warning Systems in 48 Villages

    Formation of 48 early warning groups in the community

    Training of 48 early warning groups in the community

    Development of emergency response plans and contingency stocks in 48 villages

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    7/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    6

    Development of disaster preparedness coping mechanisms in 54 villages

    Conducting of PCVA assessments/community risk and vulnerability mapping

    Preparation of village disaster management plan in 54 villages

    Signing Memorandum of understanding with 48 communities

    Rehabilitation of 14 Flood affected small scale irrigation channels for agriculture

    Construction of 5 Retaining and Flood protection walls

    Rehabilitation of 13 hazard proof water supply schemes

    water quality testing (Bacteriological and chemical testing)

    Rehabilitation/reconstruction of water and sanitation facilities at evacuation centers

    Rehabilitation of culverts at 15 evacuation routes

    Rehabilitation of 13 evacuation roads

    Formation of 48 Village Disaster Management Units within the community

    Training of 48 DMU's on CBDRM

    Training and sensitization of 240 local authorities and local institutions in CBDRM

    Development of Contingency Stock at District Level

    Community training on CBDRM

    Awareness sessions on DRM at Boys & Girl Schools

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    8/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    7

    HAPTER

    2

    : METHODOLOGY

    At the end of 2012, ACF commissioned an evaluation of the RNE funded

    DRM project activities in Khyber Pakhtunkhwa (KP). ACF subscribes to the

    Development Assistance Committee (DAC) criteria for evaluation: Impact,Sustainability, Coherence, Coverage, Relevance / Appropriateness,

    Effectiveness and Efficiency. ACF also promotes systematic analysis of the monitoring system

    and cross cutting issues (gender, HIV/AIDS etc). These dimensions served as the main

    evaluation criteria.

    1.Evaluation QuestionsThe detailed evaluation questions are provided in chapter 3 and were grouped as follows:

    Targeting

    Project DesignProject Implementation

    Project Monitoring

    Project Sustainability

    Cross cutting Issues

    2.Evaluation ApproachReview of Relevant Documents

    Prior to the field work, the evaluator reviewed the relevant documents, including those related to

    this project, ACFs general work in Pakistan and DRM globally and documents related to DRM

    and emergencies in Pakistan in order to gain a better understanding of the project and itscontext and to help develop the evaluation methodology and instruments. Sufficient

    documentation was available.

    Initial Briefing

    Prior to the field work, the evaluator participated in a teleconference with ACF New York HQ.

    Indirect Information

    Interviews were conducted with local authorities in Lower Dir, Mardan and Charsadda; project

    expatriate and national staff in Islamabad and the districts; donor representatives and the

    Director CDPM University of Peshawar.

    Field activities

    Household interviews with community members and Focus Group Discussions (FGDs) with

    village committee members based on participatory evaluation methods were utilized. The

    villages visited were selected randomly from lists provided by ACF while the community

    members for household interviews were selected based on convenience sampling. Random

    sampling for household interviews was not attempted since the project provided community-

    C

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    9/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    8

    level services rather than individual household level services and as such there were no project

    beneficiary lists from which people could be randomly selected. In each village, transect walks

    were also conducted to the source of disaster vulnerability of each village (e.g., rivers near the

    village) to get a better understanding of the disaster profile of the village and the manner in

    which ACF work addressed the source of vulnerability. During the transect walks, the hardware

    work constructed by ACF in each village were also visited to get a better understanding of themanner in which ACF work addressed the source of vulnerability of the village.

    Village Sampling Details

    Villages FGDs HH interviews

    Charsadda 5 5 60

    Mardan 3 3 36

    Nowshera 5 5 60

    Lower Dir 5 5 48

    Total 18 18 204

    3.Evaluation ConstraintsA major evaluation constraint was the budget available for the evaluation which meant that while

    the evaluation was conducted by an external evaluator, he was assisted in interviewing females

    by two ACF female staff members from other ACF projects. In order to analyze the impact of the

    participation of ACF staff in the data collection on the neutrality and objectivity of the findings,

    the field data is presented separately by males (interviewed by external evaluator) and females

    (interviewed by ACF staff). As seen later in chapter 3, except for one section of the household

    questionnaire, the differences in the responses given to the external evaluator and internal ACF

    staff were not found to be unusually different. However, for the future, it would be advisable for

    ACF to recruit independent females for evaluations wherever possible even though the external

    evaluator did accept the ACF proposition in this case. The budget implications of this strategy

    could be managed by reducing the number of field visit days, which the external evaluator found

    to be on the high side compared with other evaluations that he has conducted. Thus, the

    additional villages visited did not necessarily add to the richness of the data collected and the

    number of days in each district could easily have been reduced by one without affecting the

    quality of data collection. Another constraint was the security situation in Pakistan as a result of

    which the evaluator could not visit Peshawar due to the sudden deterioration of the security

    situation during the evaluation. Field work on two particular days was also scaled back due to

    security incidents. However, given the fact that the external evaluator is originally from Pakistanand speaks the national language, the impact of security incidents on the evaluation activities

    was minimized. Finally, timing was also a constraint as the evaluation was conducted near the

    end of the year when some of the staff members were on leave, ACF was also focused on

    finishing project activities and the Project Manager had finished his contract. However, despite

    all these constraints, the evaluator succeeded in collecting adequate amounts of quality

    information, mainly because of his strong background in conducing evaluations in Pakistan.

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    10/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    9

    HAPTER3: FINDINGSThis chapter provides the findings according to each question included in the

    TORs under the headings mentioned in the last chapter. However, the

    sequence of the questions and their placement under the headings has been

    changed in some places to enhance readability. The findings under eachquestion are based on triangulation of information from the various sources of information

    mentioned in the last chapter.

    1.

    Targeting

    This section focuses on the following questions

    a) Did the communities selected for the project classify as being most vulnerable andhighly exposed to disaster risk, and did they meet the criteria established in theproject design? Could the PCVA process have been in any way improved to better

    achieve this?The evaluator visited 18 of the 60 villages targeted by the ACF for this project. All the villages in

    all four districts were found to be vulnerable and those in Charsadda and Nowshera were also

    among the most vulnerable villages in KP province highly exposed to disaster risk in the opinion

    of the evaluator based on the numerous evaluations that he has conducted in Pakistan after the

    2010 floods. The worst-affected villages were those where the floods destroyed most houses in

    the village and most of the families in the villages were displaced for weeks or months, finally

    returning to live in their villages in tents or makeshift houses for prolonged periods until they

    could construct or received houses. Thus, the difference across the districts can be clearly seen

    in the response of individual households to the following questions across the four districts:

    Difference in disaster vulnerability across ACF districts

    Charsadda Nowshera Mardan L. Dir

    When was your village last affected by a major

    disaster? (% identifying 2010 floods)

    100% 100% 100% 100%

    Was your family displaced in the disaster?

    (% responding yes)

    96% 92% 62% 10%

    If yes, for how long? (no. of months) 2.1 1.2 0.7 0.4

    Was your house damaged during this disaster?(% responding yes)

    96% 92% 60% 40%

    In all districts, the 2010 floods were identified by people as the most devastating disaster inliving history. FGDs revealed that the 2010 floods were viewed as more damaging than the

    2005 earthquakes in the villages which experienced both mega-disasters. However, there is

    significant difference in the damages experienced across the four districts. While 90%+ of the

    families were displaced in Charsadda and Nowshera were displaced during the floods, only

    10% of the families in Dir were displaced while 62% were displaced in Mardan. The period of

    displacement ranged from a high of 2.1 months in Charsadda to 0.4 months in Dir. Finally, only

    C

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    11/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    10

    40% of the families reported house damage in Dir compared with 90%+ in Charsadda and

    Nowshera. Furthermore, FGDs revealed that even where houses were damaged in Dir, the

    damage was relatively minor, consisting of cracks or a wall partially collapsed compared with

    whole houses being swept away in Charsadda and Nowshera. However, villages in Dir did

    suffer crop and infrastructure damage. Even so, it would be useful to conduct more thorough

    assessments in Dir to see if there are more vulnerable areas for future work. Thus, the evaluatorwould recommend the adoption of formal and clear targeting criteria so that the most vulnerable

    villages can be targeted more consistently across all project areas. ACF currently has targeting

    criteria which include need, direct access, absence of other agencies and security. However,

    there is a need to operationalize the need criteria further for the KP context. The following

    sections provide the basis for developing such operationalized needs criteria.

    International NGOs can generally intervene with emergency response only in cases of major

    disasters because of the shortage of funds and based on the premise that communities and

    local authorities can deal with minor emergencies on their own. Thus, it is recommended that

    even for DRM work, international NGOs should focus on natural hazards which are capable of

    producing major disasters and on geographical areas where these natural hazards can be

    expected to produce major emergencies with a view to reducing the needs for major emergency

    response by INGOs subsequently as a result of this DRM work. Villagers and ACF staff in each

    area mentioned a wide range of natural hazards to which communities are exposed, including

    earthquakes, floods, snowfall, landslides, seasonal diseases and drought. However, it is also

    clear that within this long list, it is only earthquakes, droughts and floods that are capable of

    producing major disaster globally. Snowfalls, landslides and seasonal diseases almost never

    produce large-scale disasters which would justify emergency response by international NGOs.

    Moreover, even droughts are unlikely to produce major emergencies in the context of KP

    province. Thus, the starting point of formal targeting criteria for ACF should be to concentrate on

    areas which are highly prone to earthquakes and floods in KP. Even among these two, it isclearly floods which are more amenable to DRM work due to their more predictable nature,

    especially DRM work by ACF given the fact that earthquake-proofing generally requires

    structural improvements in shelter construction, which is not a core ACF sector. Thus, ACF

    should primarily focus on areas which are vulnerable to major floods and then incorporate

    earthquake DRM concerns if those flood-prone areas are also vulnerable to earthquakes.

    With floods identified as the most important natural hazard to focus on for KP, the next task

    would be to identify the most flood-prone areas in KP. Unfortunately, ACF is constrained in

    doing so by the fact that the Pakistani government has yet not developed rigorous, technology-

    based hazard mapping. Thus, it would have to rely on less rigorous sources of information. The

    starting point for the future would be to look at where the major rivers flow in KP. This wouldimmediately reveal the fact that Nowshera and Charsadda host all three major rivers in KP

    (Indus, Kabul and Swat), while Mardan hosts at most major drainage channels (e.g., the Kalpani

    drainage channel) while Dir hosts a couple of smaller rivers. It is the location of rivers which

    explains the vast differences in the responses above. All the villages in Charsadda and

    Nowshera were on major rivers banks, those in Mardan were generally next to the Kalpani while

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    12/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    11

    those in Dir were not near any major river or even drainage channels. Another source of

    information for identifying the most vulnerable districts, UCs and village would be to look at

    which areas incurred the most damage during the 2010 floods. Appendix A, which shows the

    damaged caused by the 2010 floods in KP, reveals that Charsadda, Nowshera, Dir and Mardan

    were number 1, 2, 8 and 20 among KPs 24 districts in terms of number of affected people.

    More disaggregated information at the UC and village levels may be available with thegovernment. This district ranking reveals that while Charsadda and Nowshera are prime targets

    for future DRM work, Mardan seems to be a low priority district since very few people were

    affected in the first place. Clearly, Dir is a very isolated area and one which is probably more

    poverty-stricken than the other three districts. Figures also reveal that it incurred a high degree

    of loss. While Dir has a relatively large number of people officially recognized as being affected

    (i.e., eligible for government assistance programs, such as the Watan cards), it seems that the

    Dir team has not been able to focus on some of them due to security issues as some of the

    areas identified by the Dir government authorities as highly affected (Lal Qila and Samarbagh)

    were perceived by the Dir team as unsecure. Thus, it would be useful to conduct more in-depth

    needs and security assessments there for future work. Finally, the UNDPs one DRM project

    has identified 30 most vulnerable districts in Pakistan. This list could also serve to guide ACFs

    geographical targeting. Thus, the PCVA process could be strengthened by first weeding out the

    less vulnerable villages by macro-level criteria and focusing the PCVA process on the most

    needy villages to begin with.

    Recommended needs criteria for future DRM geographical targeting

    Basis for initial targeting should be natural hazard, with floods being the main priority

    Subsequent targeting should be based on the districts, UCs and villages most flood-prone

    with the following being the main sources of information:

    -River and drainage channels mapping

    -Damage incurred during 2010 floods

    -UNDP One DRM project list of most vulnerable districts

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    13/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    12

    Vulnerability Zones and ACF Project Sites in 4 KP Districts

    The NGO Code of Conduct asserts that agencies will distribute assistance based on objective

    needs. The evaluator strongly feels that NGOs should have strong information within their files

    to demonstrate that they are doing so for each project. It would also be advisable for ACF to

    ensure that it does so for each project. Currently, while the targeting is excellent in Charsadda

    and Nowshera, even for those districts, the corresponding information to reveal that these really

    are the most vulnerable villages is not immediately available in project files. Having a map

    immediately available in its files which shows that all the villages in Nowshera and Charsadda

    are next to major villages along with information about the damage caused by the 2010 floods in

    various districts, UCs and villages will help ACF in clearly demonstrating its adherence to this

    NGO code of conduct principle. Currently, ACF has the maps with its project areas shown nextto rivers in Nowshera and Charsadda (see maps below) but not the information about 2010

    damages. As can be seen in the maps below, the project areas in Dir and Mardan are not next

    to major rivers. Similarly, if some areas are being left out due to security reasons, as in Dir, it

    would be good to have a formal security report by its professional security team and a

    subsequent SMT decision to back up this decision. If some areas are being left out because

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    14/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    13

    other agencies are already present there, it would be good to have on file minutes of meetings

    of coordination bodies where such coordination among NGOs normally takes place.

    b) Did the project strike the right balance between number of villages covered and theamount of work done in each village? If not would it have been better to cover morevillages with less work, or fewer villages with a greater amount of work?

    While detailed appropriateness of the software and hardware work done by ACF will be

    discussed in the next section (project design), in order to answer this question, it can be

    asserted briefly here that the evaluator finds the particular mix of such activities to be highly

    appropriate and well-selected, which means that it would not be advisable to drop any of them

    in order to increase the number of villages. At the same time, given Pakistans large size and

    high vulnerability, the number of most vulnerable villages is very high compared with the 60

    villages covered in this project and probably runs into hundreds if not thousands. At the same

    time, the number of agencies undertaking DRM work is small. Thus, there is a clear need to

    increase the number of villages from the present 60 in a future similar project without completely

    dropping any category or even sub-category of work. This obviously poses a dilemma. As faras the evaluator can see, the main bottleneck to increasing the number of villages is the number

    of front-line field staff who work at the village level. Fortunately, such staff does no cost much

    and an additional staff member could perhaps be hired for as little as 12,000-15,000 dollars per

    year, which could easily be absorbed by some minor reconfiguration of the overall budget. The

    other bottleneck is the cost of hardware work which is much higher. However, the evaluator also

    noticed that in some villages more than one hardware activity was being implemented. By

    keeping hardware activity down to one activity per village, it may be possible to cover more

    villages. Also, ACF could overcome the hardware-related constraint and increase the number of

    villages by trying to leverage its work by getting the government and other NGOs to cover some

    of the hardware activities which may be beyondACFs budget.

    2.Project Designa) Were the objectives, results and activities selected in the implementation of this

    program relevant for the identified population needs? Was the participatory approachused appropriate an effective in identifying and selecting specific interventions? Wasthere sufficient consultation and participation of beneficiaries in the design, targeting,implementation and post-implementation stages? Did the activities match with whatpeople wanted?

    The starting point of ACFs work for this project is the Participatory Community Vulnerability

    Analysis (PCVA) exercise which aims to view each villages vulnerability and possible steps to

    reduce it through the eyes of the community by using participatory methods to understand themain hazards, community strengths and weaknesses, and possible remedial measures for

    strengthening the communitys resilience. The use of such an approach has helped ACF to

    adopt a highly participatory process and identify the main components of the project in light of

    community perspectives. While many of the project components, such as early warning

    systems, contingency stocks and village plans, are obviously based on industry standards for

    DRM work, their specific form in different villages has depended on community perspectives. To

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    15/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    14

    begin with, the identification and development of the village hazard profile and community

    resilience and weaknesses is largely based on community perspectives. Furthermore, the

    village committees, which were the main lynchpin for project implementation, were selected by

    gathering villagers and having them select responsible, trustworthy people who represented all

    segments of the community. Furthermore, the village disaster plans were based largely on

    community perspectives. The specific contents of the early warning systems, evacuation sitesand contingency stocks were based on community participation. Finally, the hardware work

    done in villages was largely selected by villagers within the constraints of the project budget.

    b) What are the main problems (negative or unexpected impacts from the interventions)that the population identified concerning the implementation of the activities andwhat solutions were identified by the project team?

    The responses to the following questions reveal the high degree to which communities felt

    involved in the project. Satisfaction was very high across all districts, though slightly lower in Dir,

    and both sexes. The main problems identified by the committees related to the difficulty in

    covering the whole communities with DRM awarenessraising given the large sizes of some of

    the villages. A couple of villages also mentioned that ACF staff sometimes came late tomeetings, a problem created often due to the security situation in the area because of which

    ACF security staff asked ACF program staff not to proceed until the security situation cleared.

    However, there were no complains with the basic contents and approach of the program.

    Community satisfaction with ACF project approach

    Percentage saying Yes Char-

    sada

    Now-

    shera

    Mar-

    dan

    Lwr

    Dir

    Male Fem

    ale

    Were you consulted about the types of services and

    their content?

    98 96 92 84 90 95

    Did agency staff always treat you according to yourcultural norms? 95 95 97 96 95 99

    Were services provided keeping in mind your work

    schedule?

    96 97 97 88 95 94

    Were the services timely for you in light of your

    needs?

    97 96 97 81 99 92

    c) Did the project strike a good balance between hardware and software? If not, definewhat the balance should have been? Was the scope of hardware activities sufficient?If not, what other activities could have been added? Was the scope of softwareactivities sufficient? If not, what other activities could have been added?

    The main hardware activities within the project consisted of the provision of contingency stock

    for evacuation, rescue and relief activities and the construction of latrines, evacuation paths,

    drainage and irrigation channels and flood protection walls to reduce the risk of disasters. The

    main software activities were the setting up and training of village committees, development of

    village disaster plans and early warning systems, awareness-raising about DRM among

    communities and schools, training on DRM for construction workers and training of government

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    16/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    15

    officials. These activities can be better compared with the help of a conceptual framework to

    evaluate and compare the value and impact of different DRM activities. As shown in the table

    below, DRM activities can be classified along a continuum consisting of six categories with each

    higher category representing a more structural and stronger form of disaster risk reduction than

    those below it. Prevention activities include efforts to reduce the occurrence of destructive

    hazards, e.g., through reforestation and riverbed dredging, and are obviously the most effectiveform of DRM. However, such activities are generally done by governments rather than NGOs.

    Given that even with high prevention efforts, there will still be some hazards occurrence, the

    next best option is mitigation, i.e., redirecting hazards away from communities through flood

    protection walls, drainage channels etc. Given that even with high mitigation efforts, there will

    still be some hazards reaching communities, the next option is to move communities out of the

    way of the hazards through evacuation before the hazard reaches them. The next option is

    rescue efforts for those who could not be evacuated in time. Finally, the provision of timely relief

    activities to both evacuated and rescued people reduces the risk of epidemics. In addition,

    building the capacities of communities can also enhance their resilience to disasters.

    Continuum of DRM Activities

    DRM categories Purpose Examples Related ACF

    activities

    Prevention To reduce the

    occurrence of

    destructive hazards

    Global climate change

    advocacy; riverbed

    dredging; reforestation

    None

    Mitigation To build buffers

    between hazards and

    communities

    Drainage channels,

    flood protection walls

    Drainage channels,

    flood protection walls

    Communitycapacity-building To enhance theresilience of

    communities by

    strengthening their

    socio-economic status

    Livelihoods work,nutrition work, CBO

    strengthening

    Irrigation channels;VDMUs; community

    awareness-raising;

    Village disaster plans

    Evacuation

    preparedness

    To help communities

    escape approaching

    disasters

    Early warning systems;

    evacuation paths and

    sites;

    EWS, evacuation

    paths and sites

    selection, contingency

    stock items (e.g.,

    megaphones)

    Rescue

    preparedness

    To help rescue people

    caught by hazard

    Rescue tool and

    equipment stocks

    Contingency stock

    items (e.g., life

    jackets)

    Relief preparedness To provide life-saving

    services to evacuated

    and rescued people

    Watsan, health,

    shelter, NFIs stocks

    Evacuation center

    latrines; contingency

    stock items (e.g.,

    water jerry cans)

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    17/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    16

    With the understandable exception of prevention activities, which are generally out of the range

    of NGO technical and financial capacities, ACF work is covering all the remaining categories of

    DRM work. This reflects the comprehensive nature of the DRM package that ACF is providing.

    On the software side, activities like village committee and disaster plan development, early

    warning system and evacuation site identification do not cost much and can also be seen asmandatory components of DRM work. Thus, those activities should all be retained. The real

    issue is about hardware activities since they cost much more. The above framework can help in

    making decisions about specific hardware work. Thus, the objective in each village should be to

    select activities which fall in the highest possible category above while being relevant to the

    village and affordable within the ACF budget. So for example, flood protection walls, drainage

    channels and irrigation channels are much more durable forms of DRM work than activities such

    as evacuation paths and latrines in evacuation centers since the former reduce the chances of

    communities getting affected by disasters in the first place while the latter are about helping

    communities once they have been struck by hazards. Flood protection walls tend to be

    expensive and should preferably be built where benefiting large or several villages os that their

    per beneficiary cost is closer to other mitigation activities. More specifically, the evacuation

    paths built will not be helpful in major disasters as they will become fully submerged. Within

    community capacity-building, especially those related to livelihoods strengthening, activities

    which benefit the whole community, such as irrigation channels, are more beneficial than

    activities which target individual families, such as provision of agricultural inputs to individual

    households. Finally, ACFs contingency stocks packages are also a very useful input even

    though they target the lower categories for the simple reason that they have a low cost but still

    cover three DRM categories (evacuation, rescue and relief categories). In summary, the

    software activities and contingency stocks should be mandatory components given their low

    cost and wide-ranging coverage. Among the remaining hardware activities, those targeting

    mitigation and community capacity-building are more useful than evacuation paths and latrines.That said, it is recognized that the latter may be the best affordable option for some villages.

    3.

    PROJECT IMPLEMENTATION

    a) Evaluate the impact of the DRM training and disaster plans e.g. impact on capacity oftrained population to be better prepared through the training and preparedness plans.Evaluate the effectiveness of the Early Warning system that was put in place.

    DRM village committee and training: In all the villages visited in the four districts, the

    evaluators found that both men and women village DRM committees had been formed and hadreceived training from ACF on DRM activities. The village committees seemed representatives

    of all sections of the community in each village and seemed highly engaged in the DRM work

    initiated by ACF. As a result of their DRM training, the committee members generally seemed

    familiar with DRM concepts and fully geared up to play an active role in keeping their villages

    safer during future disasters. They were highly appreciative of the DRM training and seemed

    well aware about things like the values of early warning system, contingency stock and

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    18/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    17

    evacuation sites. The committee members demonstrated ownership about the work done by

    ACF and expressed a willingness to continue it after ACFs withdrawal.

    ...We can vouch that ACF has

    done excellent work with us,better than any other NGO or

    government agency and we

    are very happy with its work

    and find no problems in it.

    Committee members in a

    Charsadda village

    Village disaster and contingency plans: Village disaster plans were seen hanging on the

    walls in all the villages visited in Mardan, Charsadda and Nowshera although there was some

    variation in the level of details contained by the plans across the villages. Thus, it would be

    useful for ACF to develop a clear outline for the topics to be covered by such plans and ensure

    that all villages complete all the topics. In Dir, the team had not yet engaged the villagers in any

    village to complete such plans by the time of the evaluation which was undertaken during the

    last two weeks of the project. The Dir team felt that they would still be able to complete the

    plans in all the villages by December 31. However, clearly, even if they did so, it would seem to

    be a rush, last moment job with little follow-up possible, which would affect the quality of the

    whole exercise.

    Early warning system: The early warning systems planned by ACF include linking the village

    committees with governmental sources of information (by giving both parties the telephone

    numbers of each other) about approaching hazards and also providing them with equipment,

    such as megaphones and battery-operated loudspeakers for communicating the information

    received from external sources within the villages. Most of the village committees had been

    provided with the telephone numbers of relevant local authorities, such as police stations and

    Civil Defence offices. However, the village committees had not been registered with government

    departments so that those departments could proactively provide information to villagers. This

    issue will be discussed in more detail under the sustainability section. Finally, due to some

    delays in procurement, the equipment for intra-village dissemination of early warning systems

    was being delivered in villages around the time of the evaluation. However, even so, such

    systems would still be up and running before the 2013 flood season in July-August. However,

    the success of ACFs EWS will of course depend on villages getting timely and accurate early

    warning from government departments. Unfortunately, the technical and management capacity

    of governments departments to provide such information is very low in Pakistan at the moment,

    which is a major challenge for ACF. The final chapter will look at this issue in more detail.

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    19/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    18

    Evacuation sites selection: In almost all villages, the committees had selected evacuation

    sites in the village. Those sites generally consisted of schools, mosques or high, open places

    within the village which were already being used as evacuation sites by villagers. In many of

    these sites, ACF has built latrines. However, it would also be useful for ACF to help each village

    select evacuation sites outside the village as well in case the floods are so severe that they

    threaten to submerge the whole village, including the internal evacuation sites.

    DRM construction training: These trainings had not been delivered yet in any district by the

    time of the evaluation because of the delays in the project caused by late government

    permission and procurement delays. According to subsequent information sent by ACF, these

    trainings were completed before the end of the project.

    Community DRM awareness-raising: These 3-hour sessions were supposed to be carried

    out by the village committee members once they were trained by ACF. Such sessions were held

    by committee in many villages. However, their efficacy was affected by two major reasons.

    Firstly, in most of the villages, the committee members and in fact people in general did not

    have the immediate capacity to become good trainers based on the 3-day training that they

    received. Secondly, the population in some of the villages ran up to 3-4,000 persons. Thus,

    assuming that in one session, the committee trained up to 100 villagers, it would still take it

    around 20-25 sessions to train all adults and children above the age of 5. This obviously is not

    an easy task for people who have full-time vocations and only work as volunteers on the

    committee. These community trainings were supposed to be the main conduit for imparting

    knowledge to the community members on DRM concepts and about the village disaster plans,

    early warning systems, contingency stocks etc. As a result of these constraints, understanding

    within the larger community about DRM concepts and the village DRM activities was found to be

    variable across villages, districts and gender as shown in the table below which is based on

    household interviews. The table reveals that while familiarity with the village committees and thehardware work is very high (90+) across all districts and both sexes. However, familiarity within

    the general community is much lower and highly uneven across the districts and sexes.

    Familiarity in Dir is lower than in the other three districts. The most notable difference is across

    the two sexes, with women reporting much greater familiarity with project activities than men,

    which in some ways is counter-intuitive since usually Pakistani men have more opportunity to

    participate in project activities due to the cultural conservatism. This difference may partially be

    due to the fact that women are more village-bound and hence easier to attract to awareness-

    raising sessions and meetings. However, the fact that women were interviewed by internal ACF

    staff while men were interviewed by the external evaluator could also have been a reason for

    the higher positive responses reported by women. In any case, even if women are as well

    informed as reported below, increasing the awareness among men would be crucial since

    women enjoy much less freedom of movement and initiative in Pakistan during disasters and in

    normal times. As mentioned earlier, spreading awareness across such large, illiterate and busy

    communities is an enormous structural challenge faced not only by ACF but all agencies. Some

    related recommendations are provided in the last chapter.

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    20/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    19

    Community familiarity with ACF DRM project components

    Are you familiar with:

    (Percentage responding yes)

    Char-

    sadda

    Now-

    shera

    Mar-

    dan

    Lwr

    Dir

    Male Female

    1. DRM village committee 98 98 97 95 94 100

    2. Early warning system 75 61 73 50 38 94

    3. Village disaster plan 94 74 73 30 48 85

    4. DRM contingency stock 64 58 56 2 21 68

    5. Evacuation sites 89 85 61 52 55 100

    6. DRM training 95 91 71 73 69 94

    7. DRM construction work 95 98 85 93 95 92

    Overall, the communities generally felt that the project activities have benefited them in a variety

    of ways, including increasing their self-reliance, ability to deal with crisis and physical dangers,security of property knowledge about DRM and access to water and sanitation facilities. The

    differences in responses across the four districts and the two sexes were minor with respect to

    these issues. Communities mainly perceived these improvements due to their familiarity with the

    establishment of the village committee, which they felt was a huge boon for the whole village,

    and the visible DRM construction work that had occurred in all the villages and to a lesser extent

    the other software activities with which their familiarity was lower as seen earlier.

    Community perceptions about project impact

    Has ACF DRM work

    increased your:

    (Percentage responding yes)

    Char-

    sadda

    Now-

    shera

    Mar-

    dan

    Lwr

    Dir

    Male Female

    Ability to stand on own feet 96 98 97 92 94 98

    Ability to deal with crisis 98 98 100 90 94 98

    Safety from physical dangers 98 98 97 78 94 91

    Security of property 98 95 97 80 93 90

    Knowledge about DRM 92 88 78 75 69 100

    Access to water and

    sanitation services

    96 98 97 95 95 98

    4.

    Project Monitoring

    a) How suitable and effective were the M&E systems in place through the duration of theproject and how could these have been improved? What systems were put in place toensure that outputs provided were of the highest quality possible and wereacceptable to beneficiaries?

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    21/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    20

    ACF staff is regularly monitoring field activities, starting from field-level staff all the way up to the

    Country Director. However, it would be useful for ACF to have formal monitoring plans for each

    project which clearly specify the role for all relevant staff, starting from field-level staff all the way

    up to the Country Director in the projects monitoring. This would include the frequency,

    modality, project dimension and indicators for each relevant ACF staff. More importantly, the

    plan would also specify how the information coming from the monitoring done by each staff willbe analyzed and summarized (preferably through a software-based monitoring application) and

    then fed to progressively higher levels of the ACF Pakistan team, terminating with the Country

    Coordination Team and what decisions and follow-up each level would undertake to ensure that

    the project achieves its objectives on time. In this way, the team could constantly monitor the

    progress on the common program dimensions (e.g., effectiveness, efficiency etc) that eventually

    will be part of the project evaluation TORs (instead of being informed about shortcomings by

    external evaluators) and take remedial timely action to ensure high project quality. While project

    monitoring is clearly occurring, it is also true that there have been schedule slippages along

    some project components, especially in Dir. The presence of such a formal plan would have

    made it much easier to ensure timely achievement of objectives.

    Another missing piece in ensuring quality and timely achievement of objectives is the institution

    of strong accountability measures, which can enhance the ability of the ACF team to gain

    information about project achievement beyond that coming from its own physical monitoring.

    ACF Pakistan has now set up a Performance, Quality and Accountability unit in Islamabad and

    plans to incorporate accountability mechanisms in future projects.

    5.Project Sustainability

    a) Were the construction material and masonry techniques applied appropriate (werethey disaster-resilient?) What alternatives would have been better?

    Since there was no technical person on the evaluation team, the analysis of technical

    construction quality undertaken as part of the evaluation was limited and was based on three

    dimensions. Firstly, the external evaluator observed the construction quality visually for the

    following common construction problems in all villages and only minor, occasional problems

    were found:

    Are there any cracks or plaster falls in the construction?

    Have the fixtures and fittings (e.g., doors and windows) been fixed properly?

    Dampness on walls/floor?Is the toilet design ok?

    Does the foundation look straight?

    Are any hinges and bolts loose?

    Secondly, the evaluator reviewed the construction-related documents. ACF has qualified

    engineers within its DRM teams who had developed detailed Bills of Quantities for each

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    22/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    21

    construction work. The evaluator requested the ACF team to share sample documentation for

    some sites to show whether the BOQ material was actually delivered and used in the

    construction and the required documentation from Nowshera, Charsadda and Mardan was

    reviewed and found to be in order. Finally, the evaluator also checked with village committee

    members about the technical quality of work who in some cases did have some background in

    the small-scale construction work that ACF undertook as part of this project and they expresseda high degree of satisfaction. Thus, overall, the construction quality seems sturdy, disaster-

    resilient and best possible option under given conditions, though it would have been better for a

    qualified technical person to physically observe the work and review construction documents. It

    would also be good for ACF to undertake standard construction tests, e.g., brick quality, wood

    quality, sand quality and retained weight of crush tests.

    b) Evaluate whether the maintenance requirements of the structures were within the

    capacity of the beneficiary users, if ACF did enough to reinforce these local

    capacities. Evaluate the willingness of communities to maintain the infrastructure and

    propose how community ownership could have been improved or reinforced.

    The main mechanism used by ACF to ensure maintenance of both the software and hardware

    work is the setting up of village committees. While in a few villages, the committees already

    existed, in most villages the committees set up by ACF were the first experience of communities

    with such committees. Committee members seemed motivated and keen to maintain the

    committees even after ACFs withdrawal while communities saw the committees as an

    extremely helpful form of social capital developed for them by ACF. So, the chances seem high

    that most committees will survive even after the withdrawal of ACF and will maintain the

    software and hardware work. However, given the high migration in some areas in KP, turnover

    within committees could be high and it would be a test of their endurance whether villagers keep

    refilling the vacancies. In this regard, some additional steps by ACF could increase the chancesof committee continuation. Firstly, while ACF has trained committees on DRM issues, it would

    also be useful to give them some basic training on management, CBO operations and

    development issues. Second, it would also be advisable for ACF to see whether there are other

    international or local NGOs working long-term in these areas which could adopt the committees

    after ACFs withdrawal. Third, it would also be helpful for ACF to link committees of nearby

    villages with each other for mutual support, information sharing and learning during floods and

    even normal times. Finally, it would be important to link these committees more strongly with

    government structures, as discussed in the next section.

    c) Evaluate whether links between VDMUs and authorities are sufficiently reinforced.

    Evaluate the impact of the DRM training for local and district authorities. What werethe main issues/weaknesses and how could this have been improved? Were the local

    disaster authorities (PDMA and DDMU) sufficiently involved at all levels of the

    project? If not, in what aspects of the project could their involvement have been

    improved?

    ACF organized DRM trainings from relevant district-level departments in all four districts though

    some of the training in Mardan was still outstanding at the time of the evaluation. The evaluator

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    23/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    22

    interviewed district staff in three of the districts (except Nowshera) and all of them expressed a

    high degree of appreciation and satisfaction with the training. With respect to involvement of

    disaster authorities, all NGOs have to take official permissions from government authorities and

    to that extent the government authorities were involved in the project. However, government

    departments in Pakistan tend to be highly bureaucratic and it is not easy to get them involved to

    any greater extent, beyond granting permissions, in NGO projects. Nevertheless, suchinvolvement would be crucial for the success of ACFs DRM project more so than for other

    watsan or food security projects. Viewed so, it is felt that ACF should have built upon the good

    will created by the government trainings and expended greater effort in increasing the

    involvement of government departments in the project and enhancing the linkages between

    them and its village committees in various ways despite the bureaucratic nature of Pakistani

    government departments. To begin with, ACF could have got its village committees registered

    with the Social Services Departments in district governments to enhance the chances of the

    survival of these committees after ACFs withdrawal. Secondly, ACF could have advocated with

    the DDMUs, preferably in coordination with other DRM NGOs) to treat the village committees

    set up by ACF as valid structures for disseminating early warning information, and involving in

    any government future grass-roots DRM initiatives. Thirdly, ACF could have followed up on the

    trainings by trying to have some practical linkages between government departments and the

    village committees, e.g., by arranging mock drills between the Civil Defence Departments

    (which has grass-roots presence through a cadre of community-based volunteers), and

    encouraging the government to initiate small-scale mitigation measures in ACF villages which it

    could not afford itself.

    6.Cross-Cutting Issues

    a) How realistic and appropriate was the budget of the project? Was it respected?The table above provides information on the original budget, actual % expenditure by October

    2012 and expected % expenditure by project end. This information reveals that almost all major

    cost budget lines are being respected and will be fully utilized by the end of the project with an

    overall burn rate of 97%. However, there were some budget issues due to the exchange rate

    fluctuations given that three currencies (Nok, USD and PKR) were involved. Overall, ACF lost

    budget of around $100,000 due to the depreciation of the USD against the Nok despite the fact

    that the PKR has also depreciated significantly against the USD. According to the ACF Pakistan

    Finance team, this loss was covered by a budget modification where district-level contingency

    stock items were dropped. Overall, the Finance team felt that the DRM team had done good

    budget management which helped in the budget being respected.

    ACF DRM Project Budget utilization

    DESCRIPTION

    Budget

    (Nok)

    SPENT

    oct 12)

    Estimated

    Spent , 31-12-

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    24/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    23

    2012

    Personnel 475,953 84% 98%

    Expatriates 238,076 87% 98%

    Local staff 237,877 82% 97%

    Communication, Visibility, Information 4,900 4% 104%

    Equipment Procurement 17,164 100% 100%

    Equipment Hire 64,445 89% 108%

    External Evaluation 20,000 0% 50%

    Project Costs 597,098 76% 97%

    Construction mitigation 458,165 83% 97%

    Disaster preparedness in community 67,380 47% 125%

    Capacity building 71,553 62% 69%

    Other Costs 107,772 88% 97%

    TOTAL DIRECT COSTS 1,287,333 80% 97%

    Indirect Costs (9%) 115,860 80% 97%

    TOTAL COSTS 1,403,193 80% 97%

    b) Were ACFs rules on procurement adhered to? Have concerns relating to a zerotolerance on corruption policy been adequately observed in the projectimplementation?

    ACF has a whistle-blower policy and an anti-corruption policy to reduce the chances of

    corruption in the projects. Moreover, the approval limits of the Country Office and field offices

    are much lower than that seen by the evaluator in other agencies with a view to reducing the

    chances of corruption. The ACF Pakistan Finance team also diligently works to minimize thechances of corruption by having a zero-tolerance policy against corruption so much so that a

    driver was fired for a few hundred rupees violation. The team also calls additional suppliers by

    telephone even where the logistics and field teams have sent in the three mandatory quotations

    in order to further minimize the chances of fraud. All these steps ensure strong financial due

    diligence and the evaluator did not come across any reports of corruption within villages or field

    offices. However, this due diligence did slow up procurement to some extent with some of the

    delays mentioned earlier being related to delays in procurement, which in turn were also

    exacerbated by the lack of clarity among staff on procurement rules. ACF held a team workshop

    recently to smoothen out these issues.

    c) What measures were taken to ensure a gender balance at all stages of the project

    (assessment, design and implementation)? How could this process have been

    improved?

    KP is an extremely conservative environment even by Pakistani standards where womens

    rights are low and it is very difficult for NGOs to work with women to enhance their rights due to

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    25/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    24

    the significant threat of violent backlash by militants who in recent weeks have killed scores of

    female teachers and aid workers in KP. Within this background, ACF has still succeeded in

    involving women in the project. Thus, all villages had separate womens committees who were

    also provided DRM training like the male committees. Overall, womens understanding of the

    project activities seemed higher than that of men, as mentioned earlier under the Community

    DRM awareness-raising section. In many villages in Dir (which is more conservative thanCharsadda etc), women had formed the committees without the knowledge of men who did not

    approve of such activities. In some Dir villages, ACF did not work with women because it was

    not given access to women by the community men. However, given the severely conservative

    culture and the serious threat of violent backlash, there are severe limitations on the extent to

    which the involvement of women could be increased by ACF or other NGOs. There are greater

    opportunities to do so in the districts other than Dir. Thus, men in these villages admitted that

    they initially had some misgivings about allowing women to participate in the project as they had

    this impression that foreign NGOs spread vulgarity among women and encourage them to rebel

    against the local cultures. However, they also said that these misgivings had been largely

    removed after the start of the project due to its positive impact and the fact that they saw ACF

    staff constantly respecting local cultural values..

    d) Evaluate the added value to the project from the partnership with the Centre forDisaster Preparedness and Management (CDPM), and whether the involvement ofCDPM was maximised.

    The CPDM is the only institution focused exclusively on DRM activities in Pakistan. ACF

    requisitioned the CPDM to undertake the trainings for its own staff, the government departments

    and the village committees. The trainings were highly appreciated by all the stakeholders and as

    such the engagement with the CPDM seems like an excellent move by ACF to enhance and

    work with local capacity. However, there could have been scope to increase the utilization of

    CPDM services further since DRM is such a new area for ACF staff in Pakistan. While thetraining was certainly good, given the limited initial background of ACF staff in DRM work, it may

    have been useful to involve the CPDM at the field level to a limited extent, e.g., by having them

    undertake the software component in one model village and monitoring ACFs work in an

    additional 1-2 villages initially and providing feedback. This suggestion is based on the

    observation that the ACF staff, especially in Dir, needed more capacity and support in

    implementing the software component which was very new to them.

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    26/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    25

    HAPTER 4: CONCLUSIONS ANDRECOMMENDATIONSThis chapter summarizes the main findings and conclusions from the last

    chapter and provides recommendations for enhancing the quality of the project

    further in the future along each dimension of improvement identified in the

    conclusions section. The emphasis is on providing recommendations which

    would be feasible within the difficult working environment faced by ACF in Pakistan.

    1.Conclusions

    a) Did the program reach the intended results and objectives? If not, what were the mainconstraints faced by the organization and were they a consequence of poor quality of

    the initial assessment, poor project design or poor implementation? Did the projectsufficiently identify and manage risk related to the project activities?

    Overall project achiovements

    Results and related indicators Status at time of

    evaluation

    The ability to recognize hazards and cope with them is improved

    80% of communities have functional local early warning systems Work in progress at time

    of evaluation; ACF later

    confirmed completion by

    end of project though

    quality would have beenbetter with more spaced

    out completion

    80% of target community can claim access to contingency stocks

    90% of communities are covered by disaster management plans.

    The capacity to reduce the effect of hazards on communities is improved

    Facilities serving 60 communities are structurally strengthened to

    resist hazard events

    Done

    90% of communities have identified and equipped evacuation sites Identified everywhere but

    not all equipped due to

    government permission

    issues

    The understanding of DRM at community/institutional level is improved

    80% of intervention communities have disaster management units 100% have units

    240 individuals from local or district authorities receive DRM training Higher number trained

    25500 individuals in the communities receive DRM Training Trained but variable

    absorption of concepts

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    27/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    26

    The table above provides the status on the three results and corresponding indicators at the

    time of the evaluation field visits. Thus, the project is likely to achieve its objectives by

    December 31, 2012 though the quality of the work could have been higher if so much work was

    not squeezed into the last weeks of the project. These delays happened due to procurement

    and government permission issues. Overall, the project is a very well-conceived one and aims

    to fill a critical need in enhancing resilience within KP. Many components of the project havebeen implemented very well, such as the setting up of the village committees and their training

    and the completion of the construction activities. However, other components did have room for

    improvement. These shortcomings were caused by a wide range of external and internal

    constraints faced by ACF, including high insecurity, governmental bureaucracy, shortage of

    skilled staff, stringent procurement rules, low literacy levels within communities and the

    conservative culture in the country. Among these, ACF has managed security risks well and has

    comprehensive and efficient security systems in place. However, more attention should have

    been devoted to dealing with the risks associated with governmental bureaucracy, shortage of

    skilled staff (both quantity and skill level), stringent procurement rules, low literacy levels within

    communities and the conservative culture in the country. While the communities did not identify

    major areas of improvements (beyond the standard requests for more hardware services in the

    future), the evaluator himself has identified some. The next section provides recommendations

    for improving the quality of the project further in these areas in the future.

    2.RecommendationsTargeting: Targeting of the most vulnerable is excellent in Charsadda and Nowshera but is

    less accurate in Mardan and Dir. Mardan has structural issues as very few people were affected

    during the 2010 floods. In Lower Dir, a large number of people were affected, so the problem is

    more about ensuring more thoroughly that ACF is focusing on the most vulnerable areas. It is

    recommended to undertake a more thorough needs and security assessment in Dir. In general,

    ACF is advised to focus on districts and villages which are vulnerable to major floods. Toidentify such areas, the following three criteria are suggested: River and drainage channels

    mapping; Damage incurred during 2010 floods and UNDP One DRM project list of most

    vulnerable districts. Consider Sindh for DRM work too since it has recently become the most

    repeatedly struck province in Pakistan.

    Number of villages: Review the possibility of increasing the number of villages in the next

    phase by increasing the number of field staff, covering each village with only one hardware

    construction activity and linking with other NGOs and government agencies to cover some of

    the construction work that ACF cannot afford in its budget.

    Selection of hardware activities: Use the prevention-mitigation-capacity-evacuation-

    rescue-relief continuum of DRM activities presented in Chapter 3 to select hardware activities.

    The contingency stocks are an important hardware input given their relatively low cost and the

    fact that they cover three categories in the continuum even though they are the three bottom-

    most categories. Select other hardware construction activities from the highest possible

    category of this continuum which is relevant and affordable. For example, wherever possible

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    28/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    27

    prioritize drainage channels, irrigation channels and protection walls over evacuation routes and

    latrines. Focus on community-level activities, .e.g., irrigation channels, rather than individual

    household-level activities like provision of agricultural outputs given that the basic purpose of

    the project is community joint work which may be undermined by helping certain families with

    individual-level inputs and ignoring other families.

    Village committee sustainability: Enhance the sustainability village committees by

    providing them training on CBO management issues, having them adopted by other agencies

    working long-term in the area (e.g., Concern/IRSP), linking nearby committees with each other

    for mutual support and learning during crisis and normal times, getting committees registered

    with the Departments of Social Welfare and getting them recognized by DDMAs as valid

    structures for providing early warning information and inclusion in the governments DRM work

    in coordination with other agencies.

    Community DRM awareness-raising: Reaching to the larger community has proved

    challenging due to the large size of the communities, busy schedules and low literacy levels.

    This challenge could be reduced by having communities develop detailed community

    awareness-raising schedules and following up more closely with committees about the

    schedules and also looking at the possibility of training young educated, unemployed persons in

    each UC to conduct sessions in all targeted villages in that UC for a small honorarium

    Village disaster plans: Develop a clear formal outline of what each plan should contain and

    then ensure that all villages closely follow and complete the plan according to this list to ensure

    consistency across villages

    Evacuation sites: Beyond the within-village evacuation sites identified now, also help

    communities identify evacuation sites outside villages which could be accessed in case thewhole village gets submerged.

    Monitoring and accountability: Develop formal monitoring plans which clearly specify the

    role for all relevant staff in the projects monitoring, including the frequency, modality, project

    dimension and indicators for each relevant ACF staff. More importantly, the plan would also

    specify how the information coming from the monitoring done by each staff will be analyzed and

    summarized (preferably through a software-based monitoring application) and then fed to

    progressively higher levels of the ACF Pakistan team, terminating with the Country Coordination

    Team and what decisions and follow-up each level would undertake to ensure that the project

    achieves its objectives on time. The presence of such a formal plan would make it much easier

    to ensure timely achievement of objectives and avoid slippages. Also institute strong and

    responsive accountability measures in future projects.

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    29/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    28

    Technical capacity/CPDM: Enhance technical inputs on DRM work by having CPDM provide

    some degree of field-based support to ACF staff on software issues, e.g., by developing the

    software package in one model village.

    Government linkages: ACF should build upon the goodwill created by the government

    trainings and expend greater effort in increasing the involvement of government departments inthe project. To begin with, ACF could get its village committees registered with the Social

    Services Departments. Secondly, ACF should advocate with the DDMAs, preferably in

    coordination with other DRM NGOs) to treat NGO village committees as valid structures for

    disseminating early warning information, and involving in any government future grass-roots

    DRM initiatives. Thirdly, ACF could try to have some practical linkages between government

    departments and the village committees, e.g., by arranging mock drills between the Civil

    Defense Departments, and encouraging the government to initiate small-scale mitigation

    measures in ACF villages which it could not afford itself.

    Coordination with other stakeholders on DRM: Having successfully completed one DRM

    project, ACF should enhance its profile in this sector by increasing its visibility and inputs in

    coordination sectors like the DRR Forum and the UNDP DRM project and obtaining greater

    technical inputs from these forums.

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    30/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    29

    APPENDIX

    1.

    Damage in KP from 2010 Floods

    KPK - Flood Affected Population

    S #

    District

    Total_Population

    Total_UCs

    Affected_UCs

    Affected_Population

    HH_Damage

    Aftec_pop_pec

    1

    Abbottabad

    1169904 51

    0

    2 Bannu 971930 49 49 54,473 7,782 6

    3 Battagram 451340 20 9 10,416 1,488 2

    4 Bunair 738496 27 24 5,614 802 1

    5 Charsadda 1492939 49 34 502,732 71,819 34

    6 Chitral 465075 24 12 69,164 9,881 15

    7 D.I.Khan 1234706 47 26 394,608 56,373 32

    8 Dir Lower 1131676 37 7 180,686 25,812 16

    9 Dir Upper 753313 28 14 210,498 30,071 28

    10 Hangu 459275 19 19 45,841 6,549 10

    11

    Haripur

    1007960

    45

    42

    56,646

    8,092

    6

    12

    Karak

    622919 21

    21

    50,935

    7,276

    8

    13 Kohat 774318 32 32 38,716 5,531 5

    14 Kohistan 684004 38 38 464,333 66,333 68

    15

    Lakki

    715139 33

    26

    28,092

    4,013

    4

    16 Malakand 660046 28 6 45,086 6,441 7

    17 Mansehra 1431208 59 12 22,870 3,267 2

    18 Mardan 2123149 75 43 19,992 2,856 1

    19 Nowshera 1174961 47 27 499,818 71,403 43

    20 Peshawar 2860402 92 16 237,068 33,867 8

    21 Shangla 632670 28 7 83,649 11,950 13

    22

    Swabi

    1494583

    56

    11

    15,389

    2,198

    1

    23 Swat 1834756 65 42 634,654 90,665 35

    24 Tank 349373 16 16 148,890 21,270 43

    Grand Total 25234142 986 533 3820170 545739 16%

    2.

    Scoring Matrix

    Criteria Rating (1

    low, 5 high)

    Rationale

    Impact 4 The data in chapter 3 from household interviews clearlyshows that over 90% of the respondents felt that the project

    helped improve their resilience due to the committees set upand the construction work. These aspects include:

    Ability to stand on own feet

    Ability to deal with crisis

    Safety from physical dangers

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    31/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    30

    Security of property

    Knowledge about DRM

    Access to water and sanitation services

    However, impact could be increased further by enhancing

    understanding within the larger community about otheraspects of the project through more effective communityawareness-raising sessions. As shown in chapter 3,understanding among men about other project componentslike EWS, contingency stopcock etc is variable.

    Sustainability 3 The committees set up are the main mechanism forensuring project sustainability. However, there is scope toimprove sustainability further by:

    linking communities with other agencies, governmentdepartments and with each other andthrough further training of the committees on CBOmanagement issues

    Coherence 4.5 This is the strongest point of the project since thecombination of hardware and software activities coveralmost all categories of the DRM activities continuumpresented in chapter 3. Coherence could be improvedfurther by concentrating more on the higher categories ofthe continuum in terms of hardware construction work, e.g.,by doing more irrigation and drainage channels andprotection walls than evacuation routes and latrineswherever feasible. The project is also in line with thePakistan governments Disaster Management strategy andthe grass-roots DRM approach of the DEC-funded NGOs,

    whose DRM project the evaluator reviewed recently.Coverage 3.5 The villages in Charsadda and Nowshera are all clearlyamong the most vulnerable villages in KP. However, there isa need to enhance the coverage of the most vulnerablevillages further.by using the following criteria:

    Basis for initial targeting should be natural hazard, with

    floods being the most priority natural hazard to focus on

    Subsequent detailed targeting should be based on

    collecting information about which districts, UCs and

    villages are the most flood-prone with the following beingthe main sources of information:

    -River and drainage channels mapping

    -Damage incurred during 2010 floods

    -UNDP One DRM project list of vulnerable districts

    Relevance 4.0 Relevance is again a very strong point of the project giventhat Pakistan has become increasingly vulnerable to major

  • 7/24/2019 Acf Pakistan Drm (Rne) Final Evaluation

    32/34

    ACF Pakistan RNE DRM Project Evaluation, 2012

    31

    disasters in recent years and very few agencies,government or NGO, are doing much active work in DRMthough some of the project areas, e.g., Mardan, are not veryhighly vulnerable.

    Effectiveness 3.5 Some project components have been implemented highlyeffectively, including hardware construction work and manysoftware components in Nowshera, Charsadda and Mardan.However, there were also much delay in completing manyproject activities, especially in Dir which reduced theeffectiveness of the project.

    Efficiency 4 ACF has managed to stay within budget limits till the endthrough efficient project financial management achievedthrough very close and regular coordination between theFinance department and the Project Manager. The budgetitself reflects efficiency as it increases the resilience of morethan 50,000 persons at relatively low cost.

    3.AcronymsBOQ Bill of Quantities

    CBDRM Community-based Disaster Risk Management

    CBO Community-based Organization

    CDPM Center for Disaster Prevention and Management

    DAC Development Assistance Committee

    DDMA District Disaster Management Authority

    DRM Disaster Risk Management

    EWS Early Warning System

    FGD Focus Group DiscussionIDPs Internally Displaced Persons

    KPK Khyber-Pakhtunkhwa Province

    NDMA National Disaster Management Authority

    PCVA Participatory Community Vulnerability Analysis

    RNE Royal Norwegian Embassy

    UC Union Council

    UNDP United Nations Development Program

    VDMU Village Disaster Management Unit

    4.List of InterviewsNoor-Ul Amin District Disaster Management Officer, Lower DirAbigail Chatagnon ACF Field Coordinator KP- Paki