a critical examination of the community … nkem project 1-5 final... · local governments in the...
TRANSCRIPT
![Page 1: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/1.jpg)
A CRITICAL EXAMINATION OF THE COMMUNITY BASED POVERTY
REDUCTION (CPRP) PROGRAMME IMPLEMENTATED BY THE FEDERAL
GOVERNMENT THROUGH THE NATIONAL PLANNING COMMISSION (NPC)
A RESEARCH PROJECT
PRESENTED TO THE DEPARTMENT OF PUBLIC ADMINISTRATION AND LOCAL
GOVERNMENT IN FULFILMENT OF THE REQUIREMENTS FOR THE AWARD OF
MASTER OF SCIENCE (M.SC) IN P PUBLIC ADMINISTRATION
UNIVERSITY OF NIGERIA, NSUKKA
BY
EZEORA, J. NKEMDILIM
PG/M.Sc./10/58013
SUPERVISOR: DR. B. A. AMUJIRI
JUNE , 2013
![Page 2: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/2.jpg)
i
TITLE PAGE
A CRITICAL EXAMINATION OF THE COMMUNITY BASED POVERTY
REDUCTION (CPRP) PROGRAMME IMPLEMENTATED BY THE FEDERAL
GOVERNMENT THROUGH THE NATIONAL PLANNING COMMISSION (NPC)
![Page 3: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/3.jpg)
ii
APPROVAL PAGE
This project has been approved for the Department of Public Administration and Local
Government, Faculty of the Social Sciences, University of Nigeria Nsukka.
BY
……………………….. ……………………… Dr. B. A. Amujiri Prof. Fab. O. Onah Project Supervisor Head of Department
………………………… Prof. Tagbo Ugwu
Dean Faculty of the Social Sciences
…………………………… External Examiner
![Page 4: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/4.jpg)
iii
DEDICATION
This research work is dedicated
To
God Almighty, for His unconditional grace and mercy.
![Page 5: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/5.jpg)
iv
ACKNOWLEDGMENTS
The successful completion of this research work is as a result of a combination of efforts,
handwork, willing and sincere moral, financial and material support of many people. My special
thanks go to my project supervisor Dr. B.A. Amujiri whose co-operation, constructive criticisms
and intellectual guidance helped to sharpen my technical skills and for putting this project into an
academic shape.
My very sincere appreciation goes to my uncle and his beloved wife, Professor and Dr.
(Mrs.) Osita Ogbu for their supports, inspiration, advice and encouragement. The family has
stood with me to get this far in my life and I remain very grateful.
I will not forget to express my gratitude to my grandmother Nneokwukwe Comfort
Okoli, my aunts and uncles and the entire family of Okoli and Ogbu. Indeed, they have been very
supportive.
I sincerely appreciate my friends particularly Onyemaechi, Chimataram, Onyekachi,
Obinna and Mrs. Uche Atugwu for their love and encouragement. Finally, I thank my parents,
Mr. and Mrs. Fabian Ogbonna Ezeora and my siblings, Ngozi, Chizoba, Stella, Ogechi,
Akachukwu and my cousins who are numerous to mention for always being there for me. I
remain very grateful and love you all.
![Page 6: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/6.jpg)
v
ABSTRACT
Poverty is an unfreedom and limitations to mankind and appears in different dimensions. This is why subsequent governments in Nigeria adopted different strategies to address the challenges posed by this monster called Poverty. The research work studied the implementation of the Community based Poverty Reduction Project (CPRP) by the Federal Government as a strategy to reduce the poverty of the citizens. The CPRP was piloted in 12 States of the Federation in two phases. The phase 1 which was assisted mainly by the World Bank was made up of Abia, Cross River, Ekiti, Kogi, Kebbi, and Yobe Sataes while the phase 2 states were Ebonyi, Kwara, Edo, Gombe, Osun and Zamfara States. While the World Bank funded two states in the phase 2 (Ebonyi and Kwara), the African Development Bank (ADB) funded the remaining four states (Edo, Gombe, Osun and Zamfara). The Study focused on the four states funded by the ADB which was coordinated by the National Planning Commission (NPC). The study opined that the CPRP is a feasible strategy in that it enabled the poor which ordinarily were difficult to reach because of their remoteness to access poverty reduction through the implementation of micro projects/sub programmes by the communities. The data collected for the study was obtained mainly from the secondary sources. The primary source data was by conducting oral/personal interviews to confirm, verify and reinforce or otherwise the result of the analysis carried out on the secondary data. The secondary data were obtained from the records of the Social Fund Agencies saddled with the implementation of the project at the states and from the National Planning Commission (NPC) which coordinated the implementation of the project. The study formulated three hypotheses to guide the analysis of the data. The data was analyzed using simple percentages and proportions, tables and chi-square. The result of the analysis revealed that the CPRP aimed at improving the living conditions of the poor through targeted, cost effective, demand driven and promptly delivered programmes. The findings revealed that within a short period of five years and with a total sum of N2,652,521,721.45,a total of 872 communities accessed different poverty reduction projects spread across social service, Economic and Infrastructural sectors. The findings also revealed that the non involvement of the Local Governments in the process affected the utilization of some completed projects which required specialized manpower example community health centres for operationalization. Based on the findings, the study recommended among others that the CPRP strategy should be adapted to fast track the achievement of the Millennium Development Goals (MDGs) for Nigeria while the Local Government Councils which is closer to the communities should be involved by dedicating a department for CPRP activities. This would help in manpower planning and addressing such challenges if it crops up.
![Page 7: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/7.jpg)
vi
TABLE OF CONTENTS
Title Page i
Approval Page ii
Dedication iii
Acknowledgements iv
Abstract v
Table of Contents vi
CHAPTER ONE: INTRODUCTION
1.1 Background of the Study 1
1.2 Statement of the Problem 3
1.3 Objective of the Study 6
1.4 Significance of the Study 7
1.5 Scope and Limitations of the Study 8
CHAPTER TWO: LITERATURE REVIEW AND METHODOLOGY
2.1 Literature Review 9
2.1.1 Understanding Poverty in Nigeria 9
2.1.2 Causes of Poverty in Nigeria 16
2.1.3 Nigeria’s Development Planning and Economic Policymaking
In Relation to Poverty Reduction 21
2.1.4 Poverty Reduction Programmes in Nigeria 26
2.1.4.1 Justification of CPRP 31
2.1.5 Key Issues in Poverty Reduction in Nigeria 33
2.1.6 Effects of Unabated Poverty Growth in the Socio-Economic
Well being in Nigerians 38
2.2 Hypotheses 40
2.3 Operationalization of Key Concepts 41
2.4 Methodology 42
2.5 Theoretical Framework 47
![Page 8: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/8.jpg)
vii
CHAPTER THREE: BACKGROUND INFORMATION ON COMMUNITY
BASED POVERTY REDUCTION PROJECT (CPRP)
3.1 Origin of CPRP 50
3.2 The Design of CPRP Programmes 51
3.3 States Participation and Selection in CPRP 52
3.4 CPRP Programmes/Projects 55
3.5 Resources Base and Budget Releases 56
3.6 Institutional Arrangements 58
3.7 CPRP Monitoring and Evaluation 62
CHAPTER FOUR: DATA PRESENTATION, ANALYSIS
AND FINDINGS
4.1 Data Presentation and Analysis for Edo State 64
4.2 Data Presentation and Analysis for Gombe State 75
4.3 Data Presentation and Analysis for Osun State 88
4.4 Data Presentation and Analysis for Zamfara State 100
CHAPTER FIVE: SUMMARY, CONCLUSION AND
RECOMMENDATIONS
5.1 Summary 128
5.2 Conclusion 134
5.3 Recommendations 136
Bibliography 138
![Page 9: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/9.jpg)
1
CHAPTER ONE
INTRODUCTION
1.1 Background to the Study
Poverty far from being a condition in which a person or people cannot afford the basic
material necessities without which life becomes virtually unlivable, is a multidimensional and
multifaceted phenomenon. Politically, it goes back beyond income inequality as it includes
rights, power relations and access to and distribution of resources. Socially, it involves the
question of human dignity, social relationships and opportunities. Thus poverty has become a
social reality and a global affliction which virtually seems to have defied a permanent solution.
This is why Onah (2006:314) emphasized that:
The issue of poverty has provoked concerns and debates among scholars and organizations in the world. It has become an issue of global interest. It is a socio-economic epidemic affecting majority of the people in the world, including Nigeria.
Poverty as the Central Bank of Nigeria (2004) and Word Bank (1991:1) stressed is one of the
symptoms and manifestations of underdevelopment. Nigeria’s poverty rate over the years has
continued to grow unabated. According to the United Nations Reports (1999-2001) Nigeria’s
Human Poverty Index (HPI) was 41.6% which places the country among the 25 poorest nations
in the world. The HPI for some other African countries as indicated in the reports indicated that
Zimbabwe, Botswana, Kenya Burkina Faso and Niger has 17.3%, 22.9%, 26.1%, 58.3% and
66.0% respectively.
Additional data from the Federal Office of Statistics (FOS, 1999) cited in Nwatu,
(2006:295) further indicated that the life expectancy for Nigeria was 51 years, literacy rate was
51% and 70% of the rural population do not have access to potable water, healthcare facilities
![Page 10: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/10.jpg)
2
and electricity. The adult illiteracy rate for Nigeria is also increasing at a galloping rate while
the infant mortality rates for Nigeria were 82 and 191 by 1995 Soludo (2004:12).
Assessment of the Federal Office of Statistics (FOS) indicated that the state by state
poverty incidence in Nigeria between 1980 to 1996 show clearly high varying poverty levels
among the states of the federation which simply tells us that the issue of poverty affects every
nook and cranny of Nigeria (Soludo, 2004).
In the post colonial epoch of Nigeria, poverty has intensified by the many years of
military rule and political instability and failure of civilian government since over 50 years, of
independence from the British colonial era, coupled with poor policy and programme
implementation, fiscal neglect, mismanagement, lack of investment to create employment
opportunities that trickle down economic opportunities, corruption, and misappropriation, are
the root causes of poverty in the country. Although, poverty in Nigeria has colonial inducement
but there are still no holistic policy approach to tackle the problem in the post-colonial era.
Despite of the above, the Nigerian state through her government has expressed
determination and effort at uplifting the living conditions of Nigerians, especially the poor. All
of Nigeria’s National development plans since 1970, have emphasized poverty eradication as a
key area of every government in power. Since 1970, Nigerian governments-military and
civilian rules have created virtually tantalizing array of policies, plans, programmes and
projects to eliminate poverty. These include, Operation Feed the Nation (OFN); Green
Revolution (GR), Directorate for Food Roads and Rural Infrastructure (DFRRI); National
Directorate for Employment (NDE); Family Economic Advancement Programme (FEAP); Go
Bank to Land Porgamme (GBLP); Better Life for Rural Women Programme (BLRWP);
Federal Urban Mass Transit Authority (FUMTA), Nigerian Agricultural Corporative and Rural
![Page 11: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/11.jpg)
3
Development Bank (NAPCRDB); National Poverty Eradication Programme (NAPEP),
Community Based Poverty Reduction (CBPR), and others which billions of naira and dollars
have been invested in by both governmental and non-governmental agencies especially the
donor agencies such as World Bank, International Monetary Fund, United Nations Children’s
Fund, International Development Association, among others.
Apparently, these policies, plans, programmes and projects initiated by the government
as its efforts to reduce poverty have explicitly failed to in their objectives to reduce poverty as
it is more evident that poverty is still a chronic national problem. There is still a strong believe
that poverty is at increase in some states where CBPR was implemented such as Ebonyi,
Kwara, Sokoto, Therefore, this study is an attempt to critically examine the Community Based
Poverty Reduction (CBPR) programme implemented by the Federal Government through the
National Planning Commission (NPC).
1.2 Statement of the Problem
Poverty has indeed become a pandemic national disease with symptomatic effects of
high unemployment rates, poor health care, poor accessibility to water, food, housing, low
human development, low per capita income, and poor infrastructural development. This has no
doubt made poverty alleviation programme a recurring decimal in Nigeria’s public policy
either in the military or the civilian rule as no administration has come to power without
initiating a poverty alleviation package. In contrast, there are no empirical evidence or
justifications to show for the enormous resources put into these programmes, as the rate of
poverty has been progressively on the increase with each new poverty alleviation programme
being implemented. Many people particularly in the rural areas are not aware of various
government programmes on poverty alleviation. Those that are aware also hardly benefit from
![Page 12: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/12.jpg)
4
such poverty alleviation programmes due to some problems which one could describe as poor
implementation and evaluation of programmes. The truth is that the beneficiaries of these
poverty alleviation programmes are mainly people far above the poverty line or the rich. This
situation has always present these programmes as illusive and deceit on the view of poor
population (Nwatu, 2006).
Also in a situation, where the programme pays off, the situation is such that while in
some areas governments addresses some of their community needs, in some other areas, there
are no adequate provisions of government social amenities to better their lives. Hence, such
communities resort to self-help community development projects in addressing some of their
community needs. This has been a recurring decimal in Nigeria especially in the rural
communities. Most communities in Nigeria exist with virtually no good roads, portable
drinking water, security, health care clinic, electricity and good education due to absence of
primary and secondary schools in the areas. For instance, the report of the National Economic
Empowerment and Development Strategy (NEEDS) 2004, gave that about 40 per cent of rural
communities lack electricity, good motorable roads, standard health centres and good water
supply. Evidence from the NEEDS (2004:1) put that:
Poverty has become endemic in Nigeria with almost 70% of the population below the poverty line. Poverty implies all the associated problems of low incomes, poor education and health, malnutrition, as well as social and political exclusion.
The failure of previous anti-poverty programmes is partly because of lack of involvement
or participation of the people and politicization of the programmes. As carefully demonstrated by
some scholars like (Nwatu, 2006:295; Onah, 2005:67 and Ukwedeh, 2003:245), this is true of
such national initiatives on poverty alleviation like National Accelerated Food Production
Programme (NAFPP), Operation Feed the Nation (OFN), Nigerian Green Revolution (NGR),
![Page 13: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/13.jpg)
5
Directorate for Food Roads and Rural Infrastructure (DFRRI), National Directorate Employment
(NDE), Better Life for Rural Women Programme (BLRWP), Family Support Programme (FSP),
Family Economic Advancement Programme (FEAP), Former Poverty Alleviation Programme
and now National Poverty Eradication Programme (NAPEP). As a matter of fact, the initiation of
these programmes as Abdullahi (2006:2) has strongly argued do not take into consideration, the
environmental impact analysis (EIA) and social impact analysis (SIA) to give the problem a
holistic approach.
Apparently, poverty alleviation programmes fail to achieve their objectives in the face of
high incidence of corruption and lack of accountability of the implementing agencies. In most
cases, at the implementing stage, the resources and funds allocated for the poverty alleviation
programmes in Nigeria are diverted to private purse leaving the objectives of the programmes
totally unachievable. In other words, programmes monitoring and evaluation are given less
attention. In this condition, it becomes difficult to clearly ascertain who actually benefits from
the programme, and the targeted population groups are not in most the true beneficiaries. Poor
programme monitoring and evaluation hinders the progress and success of poverty alleviation
programmes.
Therefore, it is against this lacuna that the researcher tends to investigate on the poverty
reduction strategies in Nigeria using the Community-Based Poverty Reduction Project (CPRP)
implemented by the Federal Government through the National Planning Commission (NPC).
Bearing in mind that poverty rate in most of the states where CPRP is being implemented such as
Abia, Cross-River, Ebonyi, Edo, Gombe, Kogi, Kwara, Osun, Zamfara and Yobe is still on the
high side. In view of the foregoing, the study raises the following questions:
![Page 14: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/14.jpg)
6
i. To what extent has the Community-Based Poverty Reduction Project (CPRP) reduced
poverty rate in the states where it is piloted?
ii. Why has Nigeria’s poverty rate continued to grow despite the government efforts to
reduce poverty through poverty alleviation programmes such as CPRP?
iii. How effective are the implementation strategies adopted by CPRP in achieving its
mandates in reducing poverty in the states where it is piloted?
iv. What are the implementation problems affecting the CPRP programmes in these
states where it is piloted?
v. What are the measures to be adopted in ensuring effective implementation and
sustainability of CPRP programmes in the participating states?
1.3 Objectives of the Study
The objectives of this study are grouped into broad and specific objectives. The broad
objective of this study is to assess the poverty reduction strategies adopted by government in
Nigeria especially as it concerns CPRP.
Other specific objectives of the study are to:
i. Ascertain the extent Community-Based Poverty Reduction Project (CPRP) has
reduced poverty rate in the states where it is piloted.
ii. Ascertain why Nigeria’s poverty rate has continued to grow despite the government
efforts to reduce poverty through poverty alleviation programmes such as CPRP.
iii. Examine how effective the implementation strategies adopted by CPRP are in
achieving its mandates in reducing poverty in the states where it is piloted.
iv. Identify the implementation problems affecting the programmes of CPRP in these
states where it is piloted.
![Page 15: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/15.jpg)
7
v. Outline measures towards ensuring effective implementation and sustainability of
CPRP programmes in the participating states.
1.4 Significance of the Study
The significance is two-fold, theoretical and empirical significance. Theoretically, the
study has the potential of contributing greatly to the growth of existing theories in social sciences
particularly in public administration by helping to enrich the bank of knowledge through its
reliable findings on the activities of the Community-Based Poverty Reduction Poverty (CPRP) in
the implementing states. This is to say that our study would assist in improving the frontiers of
knowledge especially in managing public programmes in Nigeria especially as it concerns the
evaluation of the poverty reduction programmes in Nigeria. The study will be of immense
significance in ascertaining the progress so far made by CPRP in reducing poverty in these
states. On the other hand, the study will assist in unveiling the challenges or factors militating
against effective implementation of poverty reduction programmes in Nigeria and will make
useful suggestions towards ensuring the achievement of goals of government poverty reduction
programmes.
Empirically, this study is considered significant because it will contribute in providing
the decision makers and other key actors in the government the road- maps that will necessitate
prompt, responsive and efficient policy making in Nigerian poverty reduction programmes. It
will also suggest the panacea through which frequent failures in Nigerian poverty reduction
programmes will be overcome in order to achieve the targeted objectives towards poverty
reduction in Nigeria.
![Page 16: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/16.jpg)
8
1.5 Scope and Limitations of the Study
Every research study must have a scope and therefore must be pinpointed. This study, as
matter of fact, focuses on poverty reduction programmes in Nigeria but narrowed down to the
evaluation of the Community-Based Poverty Reduction Project (CPRP) in the states where it is
piloted.
Nevertheless, a study of this magnitude cannot be completed successfully without the
research encountering some constraints or limitations. Therefore, this work will not pretend to be
containing all information on the poverty alleviation programmes in Nigeria rather it will
endeavour to highlight the dominant issues on poverty reduction programmes in Nigeria
especially as it concerns the evaluation of CPRP.
It is pertinent to mention that inadequacy of data or near absence of a reliable and up-to-
date central data bank on the theme of this study, which has been compounded by the inability of
public bureaucrats to grant full access to the researcher nearly marred the effort of the researcher.
In other words, paucity of literature on the activities of CPRP in the states where it is
implemented almost marred the effort of the researcher. Also most of the relevant information
collected so far, for this study is not narrowed down to the states where CPRP is being
implemented.
On the other hand, some information was classified information and out of bound to non-
staff of the (CPRP). Considering this, the researcher sought other means to supplement and
consolidate the information through the use of internet materials, text books, journals,
newspapers, magazines and past research project by students and research institutes. Further
information was collected from the selected people both staff of CPRP in some states nearer to
the researcher and some communities that have benefited from CPRP programmes using
questionnaire and interview.
![Page 17: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/17.jpg)
9
CHAPTER TWO
LITERATURE REVIEW AND METHODOLOGY
2.1 Literature Review
The study reviewed some relevant literature that related to the subject matter of this
research work and for simplicity and understanding; the literature review was organized under
sub-headings as follow:
• Understanding Poverty in Nigeria
• Poverty: A Multi-Dimensional Concept
• Types of Poverty in Nigeria
• Causes of Poverty in Nigeria
• Nigeria’s Development Planning and Economic Policy-making in Relation to Poverty
Reduction
• Poverty Reduction Programmes in Nigeria
• Key Issues in Poverty Reduction in Nigeria
• Effects of Unabated Poverty Reduction Growth in the Socio-Economic Well-Being of
Nigerians
2.1.1 Understanding Poverty in Nigeria
In recent times, ideas about poverty conception increasingly broadened beyond the
original conception in terms of incomes. There are essentially two reasons for this broader
conception of poverty. In the first place, it has been increasingly recognized that the experience
of poverty is a multi dimensional one. To be poor is often to suffer ill-health, to be socially
excluded and to be vulnerable. Also, as understanding of the causes of poverty have developed,
![Page 18: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/18.jpg)
10
there is now a greater perception of how economic, social, cultural, political and geographical
factors tend to reinforce, one another to keep the poor entangled in a vicious cycle of poverty.
Definitions of poverty based on a minimum income levels however continue to be
essential to poverty measurement, partly because they are quantitative, and so can be compared
over time and between groups, and be subject to the vigour of statistical testing. Measuring
poverty in this way requires the definition of poverty line that is a standard of living that
separates the poor from the non-poor. There are a number of ways of setting this line for example
as a minimum income or as a certain level of consumption or expenditure. In most surveys
carried out on Nigeria, the approach taken has typically been to fix two lines relatives to the
standard of living, a moderate poverty line equivalent to two thirds of mean per capital
expenditure, and a core, or extreme poor, moderately poor, and non-poor Enugu State Economic
Empowerment and Development Strategy (SEEDS, 2004:52).
Health and Education (human capital in economic terms) are as essential to wellbeing as
incomes. In a significant step towards broader definitions of poverty, UNDP in 1990 introduced
the Human Development Index (HDI). The HDI combines as single index gross domestic
product (a measure of average income) measures reflecting three basic components of human
development: longevity (life expectancy, knowledge) adult literacy mean years of schooling and
standard of living, purchasing power, based on purchasing power parity (UNDP, 1994:20).
Well-being has thus increasingly become recognized as a broad phenomenon,
encompassing the whole range of factors which influence human capabilities the capacities, the
person to be, and to do. These include the social and institutional environment within which
people live: levels of social autonomy, empowerment, political representation, access to justice
and physical security. Thus, poverty, or the lack of well-being, may take the form of physical
![Page 19: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/19.jpg)
11
isolation, vulnerability and powerlessness as well as lack of income and assets. Some of these
attributes may be measured and are the emendable to quantitative analysis. Other aspects of
poverty, such as its institutional or cultural dimensions, or its lived experience, are more
subjective analysis thus best captured by the participatory method of research in which the
opinions of the poor are sought about their own conditions and experiences. This method is now
generally accepted as the best way of lessening about the subjective experience of poverty, and
of acquiring local insights into its causes and remedies.
Poverty: A Multi-Dimensional Concept
Poverty is a concept with multi-dimensional meaning (Ekot, 2000), cited in Onah
(2006:69). Many scholars view poverty from different perspectives based on their state of
existence, such as political, economical, social, cultural, technological, religious, gender and
educational perspectives. On that note, Aboyade (1975) states that it is relatively difficult to
demarcate poverty by given it a specific definition. This is due to the imprecision of the concept
and the difficulty of its measurement as a socio-economic phenomenon. However, Tamuno and
Alapila (1995:1) hold that despite the complex nature of poverty, social scientists have been able
to identify, describe and analyze poverty, as well proffer solutions to alleviate poverty.
According to Fields (1994:69) poverty “is the inability of an individual or family to
command sufficient resources to satisfy their basic needs”. Ekong (1991) says that poverty is
one’s general inability to attain or enjoy given social, cultural or economic benefits. The
significant issues in the views of Fields and Ekong are inability, basic needs and individuals or
groups, which states clearly, the incapability state of the poor. No wonder, Ekpe (2000:121)
states that the central theme of poverty is the state of inadequacy of essential needs of life. In a
similar view, Sen (1987:12) stated that poverty is “the lack of certain capabilities such as being
![Page 20: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/20.jpg)
12
able to participate with dignity in society”. Demonstrating the dynamism of the concept further,
Engelama and Bamidele (1997) see poverty as a state of individual not being able to cater
adequately for his/her basic needs of food, clothing and shelter,… meeting social and economic
objectives, lack of gainful employment, skills, assets and self esteem, education, health, portable
water and sanitation, which reduces the opportunity of advancing his/her well being to the limit
of his/her capability. The above definition of poverty explicitly poverty is not only the inability
of individual to afford the basic needs of life, but reduces the strength and prestige of such
individual to participate in any given activity in the society. In a strict economic sense, Ekpo
(2000:49) states that poverty is a situation whereby income and consumption are low. Obandan
(1997:61) explains that the poor are those whose standard of living are measured in terms of
income or consumption and is below the poverty line, which separates the poor form the rich. In
a broader term, Chambers (1995:71) sees poverty as the lack of physical necessities, assets and
income. It is a general condition of deprivation, which comprises poverty itself, social inferiority,
isolation, physical weakness, vulnerability powerlessness and humiliation. The poor earn below
the international measurement of one US Dollar per day (World Bank, 1996), which affects their
purchasing power to acquire their basic needs. It is on that note that Achor (2001:35) states that
the poor lack cash income that is sufficient to cover their minimum standard of living. On the
other hand, the literature explains that poverty is not only a situation of poor standard of living,
but also a state of severe deprivation in the society.
Types of Poverty in Nigeria
Poverty as we know exist in different types and poverty is geographically relative. This is
why Onah (2006:72) carefully stated that “different types of poverty exist at different times and
stages in different parts of Nigeria, based on the socio-cultural, economic and political
![Page 21: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/21.jpg)
13
environment”. However, the dividing line between types of poverty is thin because of
overlapping factors and sometimes it is the pre-fixing adjective that makes the difference, but the
need to classify poverty for whatever value is still founded. The common types of poverty in
Nigeria are:
Absolute Poverty: This is a kind of poverty in which the poor a severely deprived of basic needs
of life. Haralambos and Heald (2001:140) view it as the situation where the poor live below the
poverty line. It is a state of not having enough resources for basic needs of life, such as good
health, cloths, shelter, good water and food etc. This is one of the most prominent types of
poverty in Nigeria. The poor are unable to afford the required resources to acquire the elements
necessary to sustain life and health. The World Bank Report (1996) states that greater percent of
Nigerians are living below the universal poverty line of US one Dollar per day, which makes life
meaningless to the poor. Majority of Nigerians are unable to afford the required resources to
acquire elements necessary to sustain life. They find it difficult to afford at least one balanced
meal out of the required three per day. Today, many Nigerians struggle for shelters that are not
even worthy of accommodating domestic animals. They have turned under the bridges and
watersides better alternative shelters in absence of any. Good health care is now a strange issue
to majority of Nigerians, due to their inability to afford the resources for it. The high
unemployment rate has worsened the matter even those who are working, due to the higher
inflationary trend, suffer a lot of inadequacies. Indeed this type of poverty has eroded the dignity
of Nigerians and increased dependency unabated.
Relative Poverty: Poverty in this case is measured based on conventional standard of living in
the society. According to Townsend (1974) in Haralambose and Heald (2001:124) “individuals,
families and groups in the populations can be said to be in poverty when they lack the resources
![Page 22: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/22.jpg)
14
to obtain the type of diets, participate in the activities and have the living conditions and
amenities which are customary, or at least widely encouraged and approved in the society to
which they belong. Their resources are below those commanded by the average individual or
family that they are, in effect, excluded from ordinary living patterns, customs and activities”. It
is a kind of poverty experienced by different people at different stages.
The standard of living of individuals differs and they experience the poverty whenever
there is a fall below the standard. In Nigeria, the socio-economic inequality has induced relative
poverty, resulting to creation of different classes of people (the rich, middle and poor) in the
country. The standard of living of various classes varies, as what may be seen as convenient and
accommodating by one class, might not be by the other class. Therefore, the deficiency or
inconvenience in the standard of living of any class makes that class poor in such a giving
period. For example, the acceptable standard of living of successful Nigerian politicians may be
different from that of civil servants. What could be seen as luxury by one class could be seen as
necessity by others.
Subjective Poverty: This type of poverty is experienced due to some circumstances. People
graduate into it based on the available circumstance and perception of the individual. It arises
due to shift or reduction in income and status from a particular level to the other. For example, a
retired civil servant that lives on pensions sees himself or herself as a poor individual due to
retirement. He/ she earns income, but in a reduced capacity compared to what he/she was earning
before. At that point, the perception and status of the individual change Amuguo (2003). The
individual is subjected to poverty due to the circumstance.
Direct Poverty: This poverty is common among Nigerians and seriously increasing. It involves
inability to afford good portable water for drinking, inadequate food and shelter due to the
![Page 23: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/23.jpg)
15
activities of the rich who have taken over the control of the state resources. In the Niger Delta
Region of the country, access to portable water had become difficult as virtually all the natural
sources of portable water have been polluted by the activities of multinational and oil exploration
companies, who are also reluctant to provide alternative water sources Onah (2006:75). He
further explained that in the North, the source of water supply is very low, due to their desert
environment. Some part of the South-West and virtually all the South-East suffer same. The
government has not taken adequate measure to correct the problem. Accommodation is a basic
problem in many cities and rural villages of the federation. Basic amenities generally are scarce
in our communities and towns, thereby causing high rate of urban migration to the few cities
where they are found. At the end, it results to overpopulation of the few urban towns and severe
hardship on the citizenry.
Subsistence Poverty: This poverty is common among the villagers. Sometimes they could have
access to safe water, adequate food, good shelter, based on their level, but poor because they lack
resources to maintain other sectors such as good health, access to good education, social
amenities etc. The consequences are constant rural-urban migration in search of resources to
maintain other sectors.
Socio- Cultural Poverty: According to Obadan (1997), poverty at this level is influenced by the
activities of the culture of the people. In the traditional, Hausa/Fulani communities, women are
not given equal opportunities like their male counterparts when it comes to formal education.
They are deprived due to the ethics of their culture. This results to a good number of the women
being poor at the end of the day. He also explained that before now, first sons in Ibibio and
Ikwere tribes of Akwa Ibom and Rivers states respectively were not given equal opportunities
like other children in terms of formal education. They are rather preferred to be farmers to enable
![Page 24: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/24.jpg)
16
them be good custodian of their father’s farm lands. These men are deprived of formal education
on account of cultural practices (Obadan, 1997). Culturally, driven discrimination of various
dimensions against women observable all over Nigeria also leads to this variant of poverty
(Ozigboh, 1998).
Urban Poverty: From the view point of Umoh (2001) and Onah (2006), the poverty at this level
is common and associated with the urban areas. Poverty exists due to absence or inadequate
presence of the required basic needs of life in the urban area. In this case, there could be shelter,
portable water, good food etc. but these are inadequate due to the level of demands, the high
demand after the few supply results to high cost of living in the area, thereby making the low
income earners to suffer miserably in the urban areas. This results in forcing people to seek for
accommodation in urban slum, ghettos and under flyovers, eating unbalanced diet etc. Urban
poverty is usually caused by high rural-urban migration.
Endemic Poverty: This is a type of poverty caused be low productivity and income, and poor
nutrition and health Onah (2006). Many Nigerians today suffer from endemic poverty. The
productivity and income of many individuals are low. Since their income is low, they lack
sufficient resources to afford adequate food, good health and shelter.
2.1.2 Causes of Poverty in Nigeria
Literatures on the causes of poverty in Nigeria are indeed enormous as there are authors.
Many different factors have been attributed to be responsible for the national poverty rate. These
factors or causes will be holistically examined before proceeding to poverty reduction
programmes in Nigeria.
1. Macro- Economic Distortions: Poor macro-economic and monetary policies resulting in
low economic growth rate and continuous slide in the value of the Naira which depreciated
![Page 25: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/25.jpg)
17
from N 1.0 to N138.0 to $1.0 between June 1986 and January 2002 in the parallel markets
Nwatu (2006:304). In this respect, for any poverty eradication/reduction to succeed,
government must ensure low inflation rate, low interest rate, stable national currency, and
high GDP Growth rate coupled with balanced income distribution. These are usually difficult
to achieve.
2. Effect of Globalization: The process of globalization which started about a decade and half
ago, caught Nigeria in the throes of political instability (Nwatu, 2006:305). The main features
of globalization process include liberation of trade, free movement of capital and accelerated
development in information technology. Globalization provides windows of opportunity if
the indices of development (interest and exchange rates, terms of trade, tariffs, etc) are on the
positive and favourable scale. In Nigeria, however, by the middle of the eighties, public
infrastructure and utility had gone into serious dilapidation. The road networks were in bad
shape, schools and hospitals deteriorated seriously to increase poverty among Nigerians.
Telecommunication and power supply became very erratic. According to Anyanwu (1997)
and Nwatu (2006) “as a result of petroleum related activities, agriculture was relegated to the
background and those that remained in it, were operating at subsistence level” and
characterized by the following:
(i) Collapsing and uncompetitive industrial sector activities (30% surviving in the last 10
years).
(ii) Rapid growth in unemployment, under-employment and poverty (about 60% among the
youths aged 14-25 years) translating into 3 million jobless persons entering the labour market
annually;
(iii) Social instability and intolerance (ethnic nationalists and religious friction);
![Page 26: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/26.jpg)
18
(iv) Hyperinflation (averaging 50% between 1985-1995).
(v) Unstable interest and exchange rate (from $ 1=N1.0 in 1985 to $ 1 to N 100 in 1990
interest rate of 35% per annum as the September 2000);
(vi) Low productivity of Nigerian economic sectors; and
(vii) Endemic corruption, greed and avarice among Nigerian leaders.
Given the Nigeria’s political and socio-economic disposition, globalization presented
more challenges to the country as it lacks what it takes to be relevant or event adapt and/or cope
with it. Until the country can achieve certain level of good governance and revamped industrial
base to enhance modest economic growth and, fairly efficient public infrastructure and utilities,
Nigeria shall remain at the receiving end of globalization (Nwata, 2006:306).
3. Governance: Bad governance over the years had deprived Nigerians of the ideals and
dividends of democracy. It is objective of the government of Nigeria to tap through democratic
process, the energy and creative talents of the people and harness the nation’s resources to
enhance the welfare of the citizenry. This is with a mission to create a dynamic economy and
establish a free, democratic and just society through the pursuit of people centred programmes.
The process will facilitate and consistently cultivate a style of governance that places premium
on openness, transparency and accountability, probity and effective leadership.
Without any fear of contradiction, we can rightly say that governance with aggressive
instinct towards poverty had not been achieved in Nigeria. The assessment of different regimes
in Nigeria, right from the epoch of colonialism and post colonial period of military and civilian
administrations, there are no pragmatic policy commitment to tackle poverty from its root causes
(absence of basic needs to the people). Ake (1987) and Nnoli (1986) noted that in the colonial
administration, efforts were only made to build and construct facilities that would aid the
![Page 27: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/27.jpg)
19
exploitation and exportation of natural resources for the British development. No infrastructural
development was initiated for the economic survival of Nigeria. This undoubtedly left Nigeria’s
on economic dependency and widened the gap of poverty unabated.
4. Corruption: Corruption comes in different forms and differs from country to country.
Corruption has been variously approached by scholars, Lipset and Lenz (2000:112) defined it as
“effort to secure wealth or power through illegal means, and it is usually for private gains at
public expenses; or a misuse of public power for private benefit”. In Nigeria, illegal takeover of
government, through military coup, embezzlement, nepotism, looting, bribery, vote buying abuse
of office powers, etc. are very common. The manifestation of corruption in Nigeria progressed
among individuals, and there after assumed an institutional and later national dimension. In
Nigeria, corruption has contributed immensely to poverty and misery of a large segment of the
population (Onah, 2006:78). He further observed that corruption exacerbates poverty and
disproportionately affects those of lower income because it pulls resources from the national
treasures, placing the money into the accounts of few individuals, who are politically powerful.
This has devastating effect on developing economy that needs the money for poverty alleviation
and development.
5. Debt Burden: Debt burden has been one of the drawbacks to Nigeria’s developmental efforts.
The debt portfolio which was slightly above 14.28 billion US dollars in 1980 rose to about 30
billion US dollars in the year 2000 (Nwatu, 2006). In a similar note, Business Times (1993:14)
noted that the serving of the debt has encroached on the volume or resources needed for socio-
economic development; as it is estimated that around 40 per cent of Nigeria’s national incomes
goes to debt payments. The high debt service ratio translate into resources constant needed for
![Page 28: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/28.jpg)
20
such public infrastructure and utilities as: hospitals schools, roads (urban and rural); and supply
and portable water.
6. Low Productivity: Productivity sectors of the economy like agriculture, industry,
manufacturing etc. are equally constrained leading to low productivity, low capacity utilization,
underemployment and low purchasing power thereby throwing majority of Nigerians into object
poverty.
7. Unemployment: Unemployment in Nigeria assumed crisis level in the late 80s and early 90s
especially among school leavers and graduates in tertiary institutions. A survey carried out by the
centre for Investment Sustainable Development, Management and Environment in 1998 gave the
features as follows:
(i) Over 70% of the unemployed are relatively unskilled primary and secondary school between
age 13-25 years;
(ii) Graduates unemployment which hitherto was un-noticed, started to emerge in the 1980s, the
following influences the rising graduate unemployment;
a. Nigeria had a total enrolment of about 600,000 students in 149 tertiary institutions
1996/97 academic year,
b. There were 123,000 graduates in the 1995/96 session and about 130,000 graduates in
1996/97;
c. Commutatively, Nigeria produced a total of 1,110,000 graduates form tertiary; and
d. About 10 per cent i.e. 100,000 got formal jobs over one million might be openly
unemployed or under-employed.
The unemployment situation was further worsened by the primary schools, secondary
schools and college dropouts and retrenched workers due to the closure of many industries.
![Page 29: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/29.jpg)
21
Although there are no reliable data for all these unemployed, it has roughly been estimated to be
over 5.0 million Soludo (2004) cited in Nwatu (2006). All these unemployment worsened the
high level of poverty recorded by Federal Office of Statistics (FOS) in 1999.
8. High Population Growth Rate: Statistics show that in 1980, Nigeria’s population was about
65 million, it rose to 88 million in 1991 and further increased to 102.3 million in 1996. It is
estimated that the Nigeria’s population is currently about 140 million (National Population
Commission Census 2006). This increase in population has over stretched the basic social and
infrastructural facilities as well as public goods in the face of dwindling national resources. A
situation in which population growth average of 2.83 against GDP growth rate of 2.7% meant
that resources meant for investment are consumed with little left for development thereby
reinforcing the vicious cycle of poverty.
2.1.3 Nigeria’s Development Planning and Economic Policymaking in Relation to Poverty
Reduction
At independence in 1960, Nigeria adopted five-year National Development Plans
(NDPs), based on import substitution industrialization and agricultural development strategies, to
promote social and economic development (Anyanwu, 1997). As put by Iwayemi (1994:75) “the
first Nigeria development plan 1962-1966 focused on infrastructural development, rapid
industrialization, job creation and poverty reduction which were to be achieved through import
substitution industrialization and agricultural development strategies”. Thus, the overriding
objective of any government is to improve the quality of life of its citizens which in effect is
reducing the poverty of its citizens. This is justifiable in their policy making and development
planning objectives as is in the view expressed by Eboh (2003:12) “growth, poverty reduction
and improved welfare are usually acknowledged as central goals of Nigeria’s economic
policymaking and development planning”. Okeke (2001:67) noted that the government of
![Page 30: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/30.jpg)
22
Nigeria, between the periods 1962-1985 executed four National Development Plans (NDPs)
categorized as follows:
1962 – 1966 - 1st National Development Plan
1971 – 1975 - 2nd National Development Plan
1976 – 1980 - 3rd National Development Plan
1981 – 1985 - 4th National Development Plan
Adu (2009:34) stressed that what is supposed to serve as the 5th National Development
Plan was prepared by the National Planning Commission recently to cover the period 2010-2013.
It is a four-year development plan meant to serve as the 1st development plan for the
implementation of the Nigeria Vision 20:2020. How far Nigeria will go in this respect, time will
surely tell. Although, the 1st National Development Plan ended with the declaration of the
Nigeria civil war in 1966, the 2nd National Development Plan was developed to address the new
challenges (destruction of infrastructure, poverty, fear, etc) aftermath of the war. Consequently,
there was some political undertone to the drawing up of the 2nd National Development Plan
(NDP) as emphasis was placed on reconstruction, rehabilitation and reconciliation of all parts of
the country. The implementation of the 2nd NDP benefited immensely from increased oil revenue
which was occasioned by the oil boom at that period. However, by the time the 3rd NDP was
hatched, there was burst in the international oil market which triggered the economic crises of
the 80s and consequently led to inability of government to execute the plan effectively. The
fourth plan was not implemented at all because the economic crises had deepened. Government
could not generate the resources needed to finance the plan. The resulting consequences of the
unfulfilled plans and subsequent rise in the population was the over stretching of the existing
![Page 31: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/31.jpg)
23
infrastructure and its collapse, soaring unemployment and increase in poverty level from mere 15
percent at independence in 1960 to 27.2 percent in 1980 Ozughalu in NESG (2008:49).
In 1986, following the depth of the economic crises the nation was undergoing, the then
military government under General Ibrahim Babangida introduced a new economic framework,
the short-term economic stabilization policies referred to as the Structural Adjustment Plan
(SAP). At the point of the introduction of the economic stabilization programme, the economic
productive frontier had contracted and there were so much distortions, leakages and wastages in
the system. As explained by Eboh (2003:12) “the Structural Adjustment Programme (SAP) was
adopted to broaden the economy’s productive base, eliminate distortion and reduce the role of
government in order to encourage competition”. In other words, the non implementation of the
National Development Plans must have contributed to the bastardization of the economy by
subsequent governments and soaring incidence of poverty. The assessment of the pro-poor
impact of the Structural Adjustment Programme showed mixed results.
In the view of the World Bank (2002:156) “the SAP measures triggered significant
supply responses from the rural economy in terms of a substantial increase in food and export
crop production. It led to an expansion of rural income and a dramatic reduction in rural poverty
with the incidence decreasing from 51 percent in 1985 to 46 percent in 1992”. Whereas the
assessment of SAP by the World Bank seems palatable, the unintended effect on the vulnerable
groups was unsatisfactory. This is supported by Nigeria Government view on SAP (NPC 2004:9)
“The onset of the Structural Adjustment Programme (SAP) in 1986, stressed greater realization
of the need for policies and programmes to alleviate poverty and provide safety-nets for the poor.
This emphasis arose from an awareness of the unintended negative effects of structural
adjustment policies on vulnerable groups in the society.
![Page 32: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/32.jpg)
24
There was no doubt that while structural adjustment had its salutary effects on economic
growth, it lacked emphasis on development which also accentuated socioeconomic problems of
income inequality, unequal access to food, shelter, education, health and other necessities of life.
It indeed aggravated the incidence of poverty among many vulnerable groups in the society”.
Reinforcing its position on the SAP, the Report of the Federal Government of Nigeria on Vision
20:2020 on page 17 affirmed thus; “SAP was introduced in 1986 against the background of the
negative economic growth rate of the first half of the 1980s, but then, the performance of the
economy in the light of the SAP policy reform was generally sluggish”. Perhaps, the observation
of government may have suggested the accompanying of the SAP economic measure with some
targeted poverty reduction initiatives among which were Directorate for Food, Road and Rural
Infrastructure (DFRRI) aimed at developing rural infrastructure (road, agro-facilities, electricity
etc), National Directorate of Employment (NDE) for skill acquisition, job creation and
entrepreneurship development, Peoples Bank to ease access to credit in the informal sector of the
economy and gender development-Better Life Programme for Rural Women aimed at improving
women’s productive abilities and income. In 1990, the Government of Nigeria adopted another
development planning strategy – the Rolling Plan. The rolling plan is more flexible and was
expected to have ameliorated the short comings of the fixed five-year development plans earlier
adopted and link policy to budget. According to Eboh (2003:12) “the Government, between 1990
and 2001 put in place several two-year horizon Rolling Plans” which were intended to
consolidate the achievement of the economic reform programme. The programmes seem not to
have tracked poverty. This is evidenced from the National Bureau of Statistics (NBS) 2005
poverty profile which revealed that poverty level had reached 65.6 percent by 1996. Over the
period surveyed, the depth and severity of poverty in Nigeria more than doubled, increasing with
![Page 33: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/33.jpg)
25
household size and decreasing with the level of education. There is also an indication of rapidly
increasing urban poverty which certainly will constrict consumption and therefore
production/output.
Faced by consistent poverty and other socio-economic related challenges, the
Government thereafter constituted a committee in 1997 with members from the public and
private sectors and the civil society to articulate a new development framework, the Vision 2010.
Although, the final document produced envisioned people-centered, broad based, market
oriented, highly competitive, and self-reliant and private sector driven economy with government
proactively providing the enabling environment, the vision document was abandoned following
the collapse of the military regime (General Sani Abacha) that initiated it. As noted by Eboh
(2003:13) “the abandonment of the Vision 2010 is a vivid example of policy inconsistency in
Nigeria, a situation inimical for economic growth and poverty reduction”. Furthermore, most
government programmes failed to make the desired impact on the people because right from the
design to the implementation, the programmes lacked ownership and participation by the
beneficiaries. This view is collaborated by Eboh (2003:14) when he stated that “post
independence development planning and policymaking in Nigeria was largely predicated on
trickle-down hypothesis, being essentially top-bottom they failed to alleviate poverty”. Besides,
another key challenge is the issue of Monitoring and Evaluation (M&E) of programmes and
projects. According to Obadan (2003:34) “The implementation and impact of planning strategies
were undermined by weak M&E systems and apparent disconnect between fiscal/budgeting and
planning/policies (misalignment of public expenditures, that is, budget process and execution
with economic policies and development plans)”. The National Planning Commission (NPC)
was established in 1992 to fill this gap. The responsibility of the Commission was to formulate,
![Page 34: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/34.jpg)
26
coordinate and monitoring of development plans and economic policies. On inception, the NPC
combined its functions of planning and capital budgeting but the capital budget component was
removed from the NPC in 1993 i.e a year after commencing operation; thus deteriorating further
the weak link between budgets and planning thereby reducing their impact on poverty reduction
as observed by Eboh (2003:14). Given the shortcomings of the previous development planning
approaches and policies in reducing poverty, it has become imperative to consider a dynamic
approach which is demand-driven and participatory capable of guaranteeing sustainable poverty
reduction. Hence, according to NPC in Madu et al (2009:2) “the Federal Government in
consultation with the State Governments and donor agencies drew up the concept of Community
Based Poverty Reduction Project (CPRP) in December 1999. The CPRP is a Community Driven
Development (CDD) with emphasis on bottom-top approach to development.
2.1.4 Poverty Reduction Programmes in Nigeria
Poverty reduction is the most difficult challenge facing Nigeria and its people and the
greatest obstacle to pursuit of sustainable socio-economic growth (NEEDS, 2005:28). Poverty
reduction or eradication has appeared as most priority of every regime in power in Nigeria and
its emphasis as the top most priority or objective of the Millennium Development Goals (MDGS)
“to eradicate extreme poverty” makes news approach in the government programmes on poverty.
Poverty reduction is a global and national task. Globally organizations like United
Nations International Children’s Emergency/Fund (UNICEF) United Nations Development
Programme (UNDP), United Nations Industrial Development Organization (UNIDO), and
United Kingdom Department for International Development (DFID), United States Agency for
International Development (USAID), International Development Association (IDA), Joint
United Nations Programme on HIV/AIDS (UNAIDS), to mention but a few have taken the lead
![Page 35: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/35.jpg)
27
on poverty reduction especially on developing countries like Nigeria. Nationally, agencies and
establishment, such as Nigerian Agricultural Cooperation and Rural Development Bank
(NACRDB), National Empowerment and Economic Development Strategy (NEEDS), National
Poverty Eradication Porgramme (NAPEP), Partnership for Transformation of Health System
(PATHS), National Action Committee on Aids (NAC), State Empowerment and Economic
Development Strategy (SEEDS), Stated and Local Government Programme (SLGP), Local
Empowerment and Economic Development Strategy (LEEDS), Local Empowerment and
Environmental Management Project (LEEMP), Community Development Co-coordinating
Council (CDC), Community Based Poverty Reduction Project (CPRP) etc. have also taken the
challenges of poverty reduction in Nigeria.
The establishment of these agencies has been necessitated due to high poverty level in
Nigeria for instance, the establishment of poverty alleviation/reduction strategy by each state
under the State Empowerment and Economic Development Strategy (SEEDS). Poverty reduction
constitutes measures taken by the government to address the problems of poverty. These
measures include improving delivery of basic social services, improving basic infrastructures,
supporting entrepreneurship and self help human development and empowerment, etc. This is
why Nnamani (2003) cited in Nigeria, the State Empowerment Economic and Development
Strategy (SEEDS) is “state and community approach to achieve sustainable poverty reduction by
the enhancement of livelihood and human capabilities through board based wealth creation and
employment generation”.
The awareness on poverty reduction and actions on poverty alleviation programmes are
both global and national efforts. We shall proceed to examine the various efforts of the federal
environment to cub poverty in Nigeria and other component programmes in Nigeria.
![Page 36: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/36.jpg)
28
Before the creation of Nation’s Poverty Eradication Programme (NAPEP) in 2002, there
had been various efforts by the Federal Government or Nigeria to attack national poverty Ukoha
(2003:15). Ukoha further noted that by 1999, eighteen (18) Federal Ministries and 30 Agencies
and Extra-ministerial Department were involved in poverty alleviation activities at the federal
levels.
Although national efforts to tame poverty in Nigeria can be traced to the nation’s fourth
national development plans which were indirectly aimed at tackling people’s poverty Ukaoha
(2003). Observations from and Anyanwu (1997), Onah (2006) and Ukaoha (2003) showed that
the most serious poverty reduction programmes of the Federal Government of Nigeria took place
in the post 1980s era following the consequences that followed the introduction of the structural
adjustment programme (SAP) by the Babangida military regime in 1986.
Ukoha (2003) for instance noted that “the austerity measures contained in SAP were
believed to have worsened the poverty situation in Nigeria. Indeed, even today, many economists
do argue that the present socio-economic situation which is receiving the present administrative
economic reforms is still as a result of SAP (UNNP 2000).
By 1997, Nigeria was ranked as the 5th poorest nation among 78 developing nations in
recent times; poverty has become pervasive in the country. According to the World Bank report
of 2000 “the poverty situation has aptly been described as a paradox, the paradox is that the high
level of poverty in Nigeria contradicts the country’s enormous wealth. Among other things,
Nigeria is endowed with immense human agricultural, petroleum, gas and solid mineral
resources, much of which have not been harnessed, yet Nigeria’s remained poor (Ogwunike,
2005:94). He further stated that “it is important to note that the country’s has earned over 300
billion U.S dollars from its natural resources during the last decade of the 20th century. But
![Page 37: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/37.jpg)
29
instead of making progress in the national socio-economic development, the country retrogressed
to become the 25th poorest country in the world at the beginning of the 21st century where as she
was among the richest 50 countries in the early 1970 (Ekhator, 2003:73).
In the light of the above, Federal Government has apparently concern its policy directives
mainly for poverty reduction in Nigeria, numerous policies and programmes have been designed
at one time or the other to solve the problem of poverty in the country. It is important to
emphasize that the advent of Structural Adjustment Programme (SAP) in 1986 brought out more
forcibly, the need for policies and programmes to alleviate poverty and provide safety nets for
the poor. Indeed, since after the introduction of SAP there have been conscious efforts by various
governments towards the alleviation of poverty situation in the country has been worsening over
the years.
Consequently, when the former President Chief Olusegun Obasajo came to power as an
elected President of Federal Republic of Nigeria on May 29th,1999, the first step taken in solving
the county’s poverty problems was creation of Poverty Alleviation Programme (PAP) under
which the regime intended to create 200,000 jobs within the first year of his tenure, that is by the
year 2000 Aliyu (2003:24). Also, the then first Lady, Chief (Mrs.) Stella Obasanjo (now late)
followed suit and introduced of the Child Care Programme for the disabled children of the
indigent people. The wife of the former Vice President, Chief (Mrs) Titilayo Atiku Abubakar
complemented this with the WOTCLEF, a programme designed to fight against abuse of poor
women and prostitution. Ezeonu (2011) also attributed that the objectives of Child Care
Programme and WOTCLEF have been carried over in the new programme by the wife of
incumbent President Mrs. Dim Patience Jonathan in her “Women for Change Initiative”
programme.
![Page 38: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/38.jpg)
30
Ekhator (2003:74) asserts that “if the only success determinant for measuring the
performance of the various programmes so far implemented is the degree of poverty in the
country, it would not be difficult to conclude that they have all failed woefully since the number
of the poor people has been on the increase” (Ekhator, 2003:57).
Asiodu (2000) cited in Ekhotor (2003:74) further stated that “the United Nations and its
Development Report of 1998 indicates that about 48% of Nigerian population live below the
poverty line”. According to Ekhator (2003), Asiodu who made the statement in his address at the
Annual Directors Conference held in Ibadan on 28th June, 2000, asserted that the United National
Report provided the basis upon which the present administration formulated its poverty
alleviation programme to attest for poverty and improve the standard of living of Nigerians.
A sum of N 10 billion was voted for this programme (Ekhator, 2003). No sooner did the
programme started that public outcry began to trail it. Beneficiaries of the earmarked N3,500
monthly stipends were believed to be more the relations and friends of politicians in the ruling
Peoples’ Democratic Party (PDP) (Ogwumike,2005:54). Following the recommendations of the
Technical Committee on the Review of Alleviation Programme (TCRPAP), the Obasanjo’s
administration re-designed the programme and again came up with another term” name- National
Poverty Eradication Programme (NAPEP) to carry on the objectives of the government from
where the Poverty Alleviation Programme (PAP) stopped.
The issue of poverty has provoked concerns and debates among scholars and
organizations in the world. It has become an issue of global interest. It is an epidemic affecting
majority of the people in the world, including Nigeria. It is one of the symptoms and a
manifestation of underdevelopment says the Central Bank of Nigeria/World Bank (1991:1). The
World Bank report (1996) show that in the sub-Sahara Africa; Nigerians are among the world
![Page 39: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/39.jpg)
31
poorest class of people in terms of Gross National Products (GNP) and access to social and
political life. The social statistics show that Nigerian is the worst in terms of poverty in the Sub-
Sahara Africa despite her numerous natural resources. World Bank report (1996) also holds that
greater percentages of Nigerians are living below the universal poverty line of US$1.00 dollar
per day. This very high incidence of poverty is equally expressed by Government agencies thus;
Nigeria population is projected at between 115 to 120 million people out of which over 66% or
70 million people in 2000 were classified poor as against the 55 million in 1998 (National
Population Commission 2000 and UNDP reports 2001). Amogu (2003:1) adds that the 2003
Federal Office of Statistics (FOS) now National Bureau of Statistics (NBS) shows that the
national poverty rate is projected at 70% amounting to 80 million poor people in Nigeria.
Similarly, Onah (2006) observed that poverty incidence has become alarming as two thirds of the
population is poor and is detrimental to Nigeria socio-economic and political development. The
UNDP 2001 report also agreed that poverty in Nigeria has been heightened. According to
Ighatayo (2001:1) poverty undermines development activities in Nigeria. The bottom line of all
these views is that poverty has found a place in the Nigeria society and much of the citizens have
become victims of poverty in several ways.
2.1.4.1 Justification of CPRP
Prior to the implementation of the Community-Based Poverty Reduction Project (CPRP)
model in Nigeria, the Federal Government had addressed the issue of poverty reduction through
sector-specific strategies or through multi-sectoral or cross cutting strategies. The Strategies
Programme (ADP), Mass Transit Programmes, Primary Health Care, Peoples Bank of Nigeria,
National Directorate of Employment among others were aimed at providing economic
infrastructure programmes to generate employment, enhance income earnings, increase
![Page 40: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/40.jpg)
32
productivity and those targeted at equitable distribution of income (Adu, 2008). Others were
aimed at increased production and supply of food, increased economic activities and curtailing
the spread of epidemics among others (NPC, 2000).
Although, these strategies were put in place, to target key poverty issues, they were
fraught with implementation and coordination challenges and consequently unable to produce
the desired result. The poverty alleviation institutional landscape is fraught with duplicity and
proliferation of programmes and implementing agencies (sometimes with overlapping
responsibilities and even conflicting mandates) leading to waste, poor coordination and
unhealthy rivalries and projects implement through the strategies did not eventually differentiate
the life of the poor, especially the rural poor who lacked basic social and economic amenities
needed for improved well being. Despite good intensions and technical feasibility of poverty
reduction projects, failure of most poverty alleviation projects is attributed to over centralized
administration and bureaucracy in government system. Hence, Federal Government in
consultation with state governments and donor agencies drew up the concept of a Community-
Based Poverty Reduction Project (CPRP) in December 1999 (NPC, 2001). Thus, by implication,
the CPRP strategy of poverty reduction was adopted to break the barrier of over centralization
and coordination at the Federal level and quicken the trickle-down of poverty reduction efforts to
the Local Government and community levels.
The rational for the community Based Poverty Reduction Project (CPRP) is premised on
the fact that most of the rural areas, the major target of CPRP, are characterized by limited or
complete non-existence of basic socio-economic infrastructure necessary for meaningful and
improved standard of living (Madu et. al. 2009). The Poverty Profile or rural dwellers (NBS,
2006) reveals that more than 70 percent of their income is spent on other necessities of life like
![Page 41: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/41.jpg)
33
clothing, shelter, health, education, sanitation, clean water, etc. If Government efforts to improve
the standard of living of her citizens is to be met, a more pragmatic approach to reach this group
have to be found hence the new concept of Community Based Poverty Reduction Project (Madu
et al 2009). The CPRP, unlike other previous strategies was considered as thought of as model
that can guaranty the participation of intending beneficiaries in the identification, implementation
and management of their developmental needs as opposed to Government imposition of projects
and programmes.
2.1.5 Key Issues in Poverty Reduction in Nigeria
The nature of the poverty problems and lessons learnt from efforts in combating the problems
has given indication to four major issues and concerns. These are the issues of Growth with
Equity; Human Capital; Targeted assistance to the poor; and Governance and Institutions.
Growth with Equity: According to the World Bank (1999:254), there is evidence that rapid
economic growth is important for poverty reduction. A decomposition of poverty between 1980
– 1996 into growth and redistribution shows that about 90% of poverty increase is due to fail in
real income. Similarly, the result of the simulation of the relationship between economic growth
(real income) and poverty level in Nigeria by the World Bank indicate that an aggregate
economic growth rate of not less than 8% is required for a considerable decline in poverty. To
achieve a decline of about 50% in the 1996 poverty level, a growth rate of not less than 5% is
mandatory (see annex 4). The table depicts a distribution neutral growth and also based on a
largely oil sector lead growth with poor income distribution pattern. The inequality of the growth
rates of 3.2%, 6.0% and 7.0% as depicted in the annex 4 with the respective poverty levels is
very undesirable. Thus as the World Bank puts it “if the inequality were to change, then the
poverty level in future years will also change”. This position is based on the computed elasticity
![Page 42: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/42.jpg)
34
of poverty incidence to change in Gini index (see annex 5.). The implication of the information is
that economic growth alone is not sufficient for poverty reduction. It is widely acknowledged
that growth must be deliberately accompanied with equity, promoted by participation for
sustainable poverty reduction. Participation of the poor themselves in the activities that would
“push” or “pull” them out of poverty is therefore a key to poverty reduction. A further
confirmation of the fact that growth alone is not sufficient for poverty reduction is confirmed by
the CBN (1999) and NBS (1999) see annex 6. From the table, it is clear that Nigeria did not
experience considerable or commensurate poverty reduction even in period of economic growth.
In 1985 – 1992 for instance, there was slight increase in GDP and per capita income and there
was a slight drop in aggregate poverty headcount level, but inequality worsened and the core-
poor did not share in the growth as the depth and severity of poverty did not improve
significantly. As opined by the NPC (2004:18), Government need to maximize its position by
focusing its efforts on the policy aspects of improving the welfare of its human resources and
rely more on the informal and private sector to increase capital investment. Land laws, property
rights tax structure are vital policy instruments in this regard, particularly for farming, mining
and manufacturing, improve access to credit, technology and materials and markets as well as
ancillary incentives to increase output and income are vital consideration for broad based
economic growth to aid poverty reduction.
Human Capital Issue: In the case of human capital, the poor people need to participate in
the growth process for assurance that the returns of the growth will be directly available to them
to increase their ability to improve their welfare. The human capital has to therefore be such that
can effectively and productively participate in the growth process. Sustained long-term growth
depends critically upon increasing the access of poor people to quality social services and
![Page 43: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/43.jpg)
35
essential infrastructure in order to enable them to increase their human capital and make full use
of their main asset, namely their labour. The dearth of the key social services – in terms of
availability, accessibility and usage exemplified by the poor social indicators trends described in
annex 2 explains the strong relationship between human capital and poverty. The key priorities
are health, education, water supplies and sanitation, rural roads, and urban transport. The present
situation requires an increase in funding in order to expand the number of facilities and to
improve service at each facility. Provision and maintenance of rural roads and affordable and
timely mass transportation in urban areas are important to provide people with access to jobs and
to markets. Access could be made effective, efficient and sustainable through increased
community and private sector participation in the development and maintenance of infrastructure
and provision of services. This of course is the key to ensuring growth with equity.
Targeting of Interventions: In the words of NPC (2004:19) shows the magnitude and profile of
the poverty situation in Nigeria and indicates that a sizable number of poor and disenfranchised
people cannot participate directly in broad growth process. They may not also be able to access
and use the social and economic infrastructure provided to improve human capital given the level
of impoverishment”. This means that targeted resources transfers as with the case of the CPRP
and support to such group of people in the rural and urban areas of Nigeria is very essential. A
large proportion of the core poor is in this category. The number of the core poor is increasing
rapidly and this is evidenced from professional beggars and street merchants at traffic junctions
across the country. Women and street kids, people living in remote and marginalized areas,
destitute and disabled, culturally disenfranchised groups, small scale farmers, micro enterprise
operators, civil servants and other categories of people that are open to risks and changing
fortune also belong to this group. The Government can target the delivery of some services and
![Page 44: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/44.jpg)
36
resources to reach poor areas and to communities living in poverty, building on existing
community-based organizations, civil society groups and their activities where possible. Some
elements of targeting should also be introduced into public expenditure particularly for social
sector spending.. According to NPC (2004:19), “Over the years, the share of the defence and
security in the budgets have consistently been higher than health and education which touch the
lives of the poor people than most of other public expenditure”. The Primary education and
healthcare and basic infrastructures should command larger share of their sectoral allocations.
Similarly, rural finance and microcredit programme to entrepreneurial poor and safety nets
programmes which include social funds, social action programmes, pension schemes,
employment schemes, public works programmes, school feeding programmes for the vulnerable
poor are all imperative to improve the well being of the citizens.
Governance and Institutional Issues: The inability of past government poverty programmes
and projects to yield the required results has been attributed not only to the unclear
understanding of the nature of the problem but also to the divergence in views and practices in
poverty alleviation strategies, particularly under a rather unconducive political and governance
arrangement. The persistence and pervasiveness of poverty in Nigeria has been linked to the lack
of popular participation in governance and decision making.. This has led to poor accountability
and transparency in resource allocation, program implementation and monitoring. The poor in
Nigeria and probably elsewhere had no voice and no right. Poverty usually flourishes in societies
deprived of human freedom and fundamental human rights as they are always engulfed in a
series of vicious circle of poverty. A state of pervasive social deprivation consequently creates a
condition of social and political unrest. In addition, because past governments were not based on
popular participation, corruption thrived. Although, the current development in Nigeria did not
![Page 45: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/45.jpg)
37
immune democratic governance from corruption, but for the fact that there is popular
participation, democratic governance is critical to poverty reduction. This is because, as the NPC
(2004:20) puts it “democracy is the gateway for human freedom and good political system”. A
lot of poverty reduction programmes had been instituted in the past some of which were DFRRI,
NALDA, MAMSER, FEAP, People’s Bank etc but performed below expectations. The most
probable reason for the non performance of these programmes is their top down approach. All
the initiatives were taken by the Federal authorities and States and Local Governments were
reduced to mere implementing authorities without consultation with the supposed beneficiaries
in the conceptualization and implementation of the programme. The programmes in all cases, did
not involve linkages with Non Governmental Organisations (NGOs) as well as Private Sectors.
The programmes are far removed from the beneficiaries. The poor and their social networks do
not participate NPC (2004:20). The implication of this state of being is that the comparative
advantage of the lower levels of governments (closeness to beneficiaries), private sector
effectiveness and the civil society trust were not utilized in implementing poverty reduction
programmes. Therefore, in the new dispensation of CPRP, decentralization and partnership
between the state governments, local government, private sector and the civil society is very
crucial. The private sector development is particularly important for poverty reduction in several
ways. First, it enhances competition which produces growth and jobs. Second, by allowing
governments to divest themselves of activities that the private sector can do as well or better it
reduces waste and free up public resources that can be invested in the social sectors and
infrastructure. The resources can also help to finance social safety nets and targeted programmes
to deal with the transitional costs of privatization and civil service reforms that could produce
retrenchments. Third, the financial system, hitherto preoccupied with financing state enterprises
![Page 46: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/46.jpg)
38
will be more able to provide financing to small and medium size entrepreneurs at affordable
interest rates. Finally, the decline in the budget deficit and the lowering of real interest rates that
will flow from the development will cause inflation to fall. Therefore, in essence, good
governance is a fundamental requirement for poverty reduction.
2.1.6 Effects of Unabated Poverty Growth in the Socio-Economic Well-Being of Nigerians
Perhaps, due to its (poverty) complexity and its corrosive effect on humanity, many
formal articles and books have tackled the issue of poverty. Schiller (2000) stated that poverty
destroys aspirations, hope, and happiness. Poverty affects tolerance of others, support of civil
liberties and openness towards foreigners’, affects positive relationships with subordinates, self-
esteem and sense of personal competence. It also affects ones disposition to participate in
community affairs, interpersonal trust and self satisfaction (Obadan, 2007:271). It has been noted
that deprivation of elementary capabilities can be reflected on premature morality and significant
undernourishment (especially on children), persistent mobility and illiteracy among other
problems. Life expectancy, literacy are correlated with the productivity and prosperity of a
nation (Adu, 2000:271). High level of poverty could also lead to brain drain - emigration of
many of the most highly educated workers to rich countries, where they can enjoy higher
standard of living (Mankiw, 2001). The poverty of a nation can also lead to human trafficking,
prostitution, spread of HIV/AIDS, child labour and abuse of human and civil right (Guardians
online June 28, 2002). Poverty also leads to corruption, disruption of family relations, social life,
rising crime rate, among other vices. Amartya Sen, (1997:87), argues persuasively that an
individual’s advantage (or otherwise) in society should not be judged solely on his or her income
poverty but must also be measured in “terms of substantive freedoms he or she enjoys to lead the
kind of life he or she had reason to value”. Thus, poverty is a deprivation of basic capabilities
![Page 47: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/47.jpg)
39
(such as undernourishment and illiteracy) rather than merely as lowness of income, which is the
standard criterion of identification of poverty. He adds that the “capability-poverty” perspective
does not involve any denial of the fact that low income is clearly one of the major causes of
poverty since lack of income can be a principal reason for person’s capability deprivation. He
notes that poverty as capability inadequacy and lowness of income are related because income is
such an important means of capacities that would tend to expand a person’s ability to be more
productive and earn a higher income. Poverty is degrading to human beings and the life of the
person afflicted by it is comparatively miserable and brief.
Political instability and national insecurity are other negative effect of poverty. According
to Onah (2006:97), poverty as a state of deprivation makes the deprived to be venerable and
violent in nature. Poverty increases illiteracy and poor performance of political leaders. Poverty
deprives the poor, who are majority of the electorate from having basic education. Since they are
not educated, it becomes difficult to impact on them such democratic values as freedom of
choice of candidate, freedom of speech, value and respect for the right of people, peaceful co-
existence. Illiteracy deprives the electorate the opportunity to participate effectively in
democratic activities. Even the elected representatives default in their responsibility as a result of
their ignorance-poverty of the mind arising from illiteracy. Most of the elected representatives
who are by circumstances victims of poverty find it difficult to effectively formulate and
implement good public policies for the masses they represent Onah 2006 (98:99).
Another negative effect of poverty is its social impacts on the poor masses which makes
them vulnerable to criminal behaviour or act. The unemployed and underemployed sometimes
always indulge in criminal activities to enable them afford their basic needs. In many occasion, a
good number of Nigeria young girls have been repatriated from Europe on account of
![Page 48: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/48.jpg)
40
prostitution. Outside the shores of Nigeria, several studies have shown that the involvement of
young girls in prostitution was as a result of poverty. The implication of Nigeria girls being in
such dimension of prostitution not only impacts negatively on Nigeria health record, but also
gives bad signal to foreign communities on the state of poverty and health in Nigeria.
Gap in Literature
Explicitly, this study has reviewed some salient literatures that have some degree of
relevance to the subject matter under the study. These literatures concentrated generally on
dominant issues on poverty and government efforts to reduce through policies decisions and
programmes with little emphasis on Community Based Poverty Reduction (CPRP) which is a
major focus of this research. The review of literature in this study did not detail us on the
programmes, achievements and failures of programmes of Community Based Poverty Reduction
(CPRP) in the states where it is being implemented. A thorough knowledge of the success and
the challenges encountered by CPRP is needed to refine the programme in meeting up with the
primary objectives. This study therefore, intends to cover this lacuna by examining in detail the
CPRP with the aim of noting the achievements and failure in poverty reduction in Nigeria.
2.2 Hypotheses
The following hypotheses were stated to guide this study:
Hypothesis One: Community-Based Poverty Reduction Project (CPRP) has not reduced poverty
rate in the states where it is piloted.
Hypothesis Two: Effective implementation strategies have not been adopted by Community-
Based Poverty Reduction Project (CPRP) in achieving its mandates in reducing poverty in the
states where it is piloted.
![Page 49: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/49.jpg)
41
Hypothesis Three: Poor funding and unintended beneficiaries due to corruption are key problems
affecting the CPRP programmes in the states where it is piloted.
2.3 Operationalization of Key Concepts
The operationalization of key concepts present the contextual use of terms in this
research study. These concepts includes:-
Effective Implementation Strategies:- Effective implementation strategies are measures
towards ensuring that objectives of poverty reduction are achieved.
High Incidence of Corruption by Implementing Agencies:- High incidence of corruption is
seen as any form of official miss-conduct to breach the official protocols or bend some rules and
regulations governing the implementation of government poverty alleviation policies or
programmes to achieve personal interest or that of others.
Policy:- Policy is governmental actions or course of actions or proposal actions or course of
proposed actions directed at achieving certain goal.
Programme-: A programme is a set or package of decisions, rule and regulations, activities and
structures designed to implement a particular policy.
Poor Funding:- Poor funding of programmes is a situation of making inadequate allocations to
poverty reduction programmes. It is the unwillingness to spend adequately to attain success in
programmes objectives. This is often gap between resources on the one hand and responsibilities
and directed accomplishment levels and expectations on the other hand.
Standard of Living:- Standard of living here refers to the state of economic well-being of the
people.
Unintended Beneficiaries:- Unintended beneficiaries here refer to people who are not within the
policy or programme targets but, who get benefited by manipulating the implementation
protocols of programmes on poverty reduction.
![Page 50: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/50.jpg)
42
Weak Implementation Strategies:- Implementation strategies are measures map-out framework
to be followed in administering policy actions. In other words, weak implementation strategies
are defaults in implementation of poverty alleviation policies or programmes.
2.4 Methodology
This section deals with the methods or the procedures of obtaining relevant data and
utilizing or analyzing them. According to Odo (1999:40), methodology is the authority base for a
research. The process followed in carrying out the research is presented below:
Research Design
According to Nwana (1985:34), research design relates to the general approach adopted
in executing a study. The study used the descriptive survey method to investigate into the topic:
Poverty Reduction Project in Nigeria: A Case Study of the Community-Based Poverty Reduction
Project (CPRP) implemented by the Federal Government of Nigeria through the National
Planning Commission. The study is limited to Four States (Edo, Osun, Gombe and Zamfara)
funded from the facilities provided by the African Development Bank (ADB).
Sources of Data Collection
The data used for this research work was obtained from primary and secondary sources.
The Primary Source of Data
Primary data are the original data put together in the course of this study such as account
of eye witness or participant and they include data from personal/oral interviews and
observations. The research made use of personal/oral interview and observation. The respondents
were chosen at random and the questions administered were uniform, thereby reducing biased
errors. The personal/oral interview and observation were undertaking because of the nature of the
![Page 51: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/51.jpg)
43
study which has four states (Edo, Osun, Gombe and Zamfara) as the population of the study. The
responses of the respondents were used to make inference and generalization.
The Secondary Source of Data
Secondary sources of data consist of all information recorded by someone else or event
observers published or unpublished. The secondary data used in this study were collected from
research and conceptual literatures such as journals, newspapers, magazines text books, past
research works by students and research institutes/organizations and some documents and
publication derived from government offices (specifically the National Planning Commission,
State Social Fund Agencies (i.e the offices of the State CPRP for Edo, Osun, Gombe, Zamfara
states), and the African Development Bank office in Nigeria.
Population of the Study
The term population has been defined by Odo (1992:40) as “the entire number of people,
objects, events, and things that all have one or more characteristic of interest to a study”. The
population of this study is the 12 pilot CPRP states made up of the 6 states in the phase 1 assisted
by the World Bank and the 6 states in the phase 2. Two of the States in the phase 2 were assisted
by the World Bank while the remaining 4 states by the African Development Bank. The CPRP
states are as follows; Abia, Cross River, Ekiti, Kogi, Kebbi, Yobe, Kwara, Ebonyi, Edo, Osun,
Gombe and Zamfara.
Sample of Study
The population sample is used to approximate the population size of the study. According
to Odo (1992:47), research sample is the “process of selecting a proportion of the population
considered adequate to represent all existing characteristics within the target population and to
any other population having similar characteristics with the target population”. To draw the
![Page 52: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/52.jpg)
44
sample for the research work, the researcher selected 4 states in the phase 2 of the CPRP project
which were assisted by the African Development Bank (ADB) and coordinated by the National
Planning Commission (NPC). The states are Edo, Osun, Gombe and Zamfara.
Sampling Procedure or Technique
The sampling procedure or technique adopted for this study is the random sampling
technique. The technique is used for the selection of respondents who were interviewed. Odo
(1992:51) said simple random sampling assume all the elements in the population to be studied
or identified, having all the characteristics, symmetrical, same and similar”. The Researcher, in
adopting the random sampling selected the respondents from the communities who are the
beneficiaries of the implemented micro projects/sub projects.
Data Gathering Instruments
The data used for the analysis were the secondary data obtained from the project document.
Reliability and Validity of Instrument
According to Obasi (2000:103), Black and Champman and Nachinias and Nachimas
(1981), the success of any research lies to a large extent on the dependability of the data
employed in analysis. This then raises the question of validity and reliability. Validity as the
name implies is the appropriateness of an instrument in measuring what is intended to measure.
According to Odo (1992:50) validity is the extent to which a test measures what it is supposed to
measure. Validity therefore, occurs when a careful attempt has been made to ensure that an
instrument adopted measures achieve the desired results by applying the theoretical knowledge
in the field about what is being studied and by convincing oneself common sense that the items
in the instrument has been logically validated Obsasi (2004:104). In validating the instruments
for data collection, we shall be concerned with establishing their content validity. We are doing
![Page 53: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/53.jpg)
45
this first, to ensure that they measure what they are expected to measure and more importantly,
because content validity comprises of face validity, predictive and concurrent validity, construed
validity or criterion related or empirical validity Black and Chempion (1976:91). We shall
therefore ensure that the interview questions we shall use will be appropriately structured; well
worded and covers a reasonable representation of the beneficiary communities of the CPRP
micro projects/sub projects in the ADB States. We shall ensure validity by insisting that our
empirical measure adequately reflects the real meaning of the concept under consideration. We
shall employ content or face validity method which will enable us to ensure that the instrument
we shall use will be valid. To ensure this, we must ensure that the questions our instruments are
good ones. We must equally ensure that they are logically and relevantly measuring what the
instruments are set out to measure.
Reliability, on the other hand, refers to the ability of an instrument to produce the same
results consistently over some time when applied to the same sample, Good and Hart (1952:86).
The reliability of our instruments will be assured by our consistency in our interview models.
According to Odoh (1992:54), reliability means consistency and it is the consistency of the test
in measuring whatever it purports to measure. We shall ensure reliability of our instruments by
ensuring that the questions we shall pose on the personal interviews shall be simple, good,
precise and understandable form to the respondents. To ensure reliability, we shall use internal
consistency method whereby cross-checking questions are built into the oral/personal interviews.
We shall further ensure reliability by cross-checking our information against many sources and
by ensuring that facts and figures collected from various sources earlier stated shall not only be
accurate and authentic but would remain same if the collection is repeated again and again. In
addition to the above measures aimed at ensuring validity and reliability of the study, we shall
![Page 54: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/54.jpg)
46
employ external criterion to check how correct the findings of a particular instruments are. We
shall do this by comparing the result with existing knowledge as well as our findings from field
work, oral interview, participants observation and content analysis. With the above processes, the
validity and reliability of the instruments as well as the study will be assured.
Method of Data Analysis
The method of data analysis shows the techniques used in analyzing the data collected.
The study made use of qualitative analysis which also includes the use of oral/personal
interviews and literature review in analyzing the data. Thus, the researcher would be guided by
the objectives of the study, the research hypotheses that were formulated for the study and
personal/oral interviews while analyzing the data. Also, as part of the analysis, the study adopts
the use frequency tables, pie charts, chi-square as well as content analysis. We will also make
use of simple percentage analysis to ascertain the proportionality contents of the implementation
of the micro projects/sub projects and chi-square statistical method to test the variables in our
hypothetical statements. Consequently, the formulas the computations are presented as follows:
Percentage:
y⁄Y×100
where, y = the number of micro projects or sub projects in each sector
Y = the total number of the micro projects or sub projects
100 = percentage term or constant factor
Chi-Square:
Y2 = ∑ Xij − Mij Mji Where Xij = number observed in the ith row and jth column
Mij = number expected in the cell under the null hypothesis. This is obtained with the formula: Mij = Ai x Bj
N
![Page 55: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/55.jpg)
47
Where Ai = Marginal row total
Bj = Marginal column total
N = Total number of observations
For the chi-square, we make use of the degree of freedom (df) and the df is obtained with the
formula: df = (r – 1)(c-1) where r = the number of rows and c = number of columns.
2.5 Theoretical Framework
For the purpose of this study, efforts have been made to incline on a theory that has
holistic view on the subject matter of public policy making and analysis and such that can
explain the present scenario of Nigeria poverty in the context of her potential wealth. Therefore,
the study adopted elite theory because of its significance to the problem under study. Elite theory
is supported by Karl Marx (1873), Frank Gunder (1967) Feldman,H (1967), David Easton
(1971), among other scholars, who see society from the class/ social class perspectives. The elite
class theory, being one of the most popularly advocated theories for public policy making and
analysis conceives public policies and programmes as the initiatives of the elites and not the
masses (the people). This is why Ikelegbe (1996:53) states that “the elite theory postulates that
public policy reflects the values and preference of the elites rather than the demands of the
masses. It is the elites that make policies, while administrators and public officials carry out the
elites’ policy decisions. The elites have common interest in the preservation of societal status
quo, policies are bound to be conservative, non innovative and marginal rather than those with
bold and high change potentials. Policies might sometimes be in the masses interest, even though
the long term interests may be that of the elites, but this happens as concessions to or reactions
by the elites to threats to the status quo by the masses. The elites are few in the society but they
wield power and influence, allocate values and rules. The majority (i.e. the masses only obey and
![Page 56: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/56.jpg)
48
are guided, controlled and governed by the few). The elites consist of those who hold leading
positions in the strategic aspects of society and who wield power in the strategic groups. There
are thus military elites, business elites, bureaucratic elites, political or governing elites, religious
and traditional elites. Many of the elites do not hold formal or legal authoritative powers but are
rather behind the scene, tele-guiding and manipulating overt political and policy actions. The
elites owe their positions to the control of the productive resources of the society and of the
social or religious values held by the society such as wealth, economic influence, social status
and education.
In summary, the theoretical tenets of the elites’ theory attempt a realistic explanation of
the source of public policy by predicating it on the elites rather than the masses. In the reality,
however, the masses of the population hardly have any considerable influence on public policies.
Again, elite theorists however have tended to see elite power as cumulative and pervasive in all
aspects of society. To them, the same few wield power in all areas. This enables the elites to
maintain and preserve the societal status quo where the rich get richer and the poor get poorer.
Application of the Theory
The elites’ theory has much significance to the continuous rise or increase of Nigerian
poverty rate. Ordinarily, in Nigeria, it may be assumed that public preferences articulated by
representatives are the main source of policy flow. In reality, however, the masses of population
hardly have any considerable influence on public policies made or initiated by government
judging from the elites theory. In other words, poverty reduction programmes such as the
National Poverty Alleviation Programme (NAPEP), National Directorate of Employment (NDE),
National Economic Empowerment and Development Strategy (NEEDS), Local Empowerment
and Environmental Management Project (LEEMP), Community Based Poverty Reduction
![Page 57: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/57.jpg)
49
(CPRP), among others, are considered as the policy actions and programmes to the society’s
status quo. In common sense, these create more avenue for the exploitation of the masses and as
well create more poverty among the masses. This is why the true beneficiaries of poverty
alleviation programmes deviate from the poor to the rich.
Demonstratively, the practical tenets or postulations of the elite theory show that
Nigerian society is controlled by the elite who have the control of economic, social, cultural,
political, and religious powers. In other words, the elites view poverty as a normal economic
phenomenon that must exist and should be maintained, if the society must grow Onah
(2006:80).The elites also look at poor as a normal economic class that must exist and need not to
be allowed to leave their status quo. In Nigeria, however, poverty alleviation programmes are
structurally designed to enrich the elites and create more poverty. For instance, certain jobs are
structurally designed for the poor. By so doing, the elites continue to deprive the poor from
having access to enhance their poverty. This is achieved by the elites through authoritative
allocation of values to the poor. Therefore, it is believed that Community Based Poverty
Reduction (CPRP) is one of poverty alleviation policies made by the Nigerian elites as an
attempt to solve the multi-dimensional problems of high poverty rate in Nigeria, but the question
that often comes to mind is who are the actual beneficiaries and how far has such policy been
able to reduce poverty in the country? This question becomes more imperative considering the
structural designs fashioned out in the implementation of some key programmes of CPRP such
as human empowerment-(micro-credits/loans and skill acquisition), community development
projects (water boreholes, roads, schools, healthcare centres, rural electrification, etc),
agricultural assisted projects (irrigations, distribution of fertilizers, agricultural extensions
services).
![Page 58: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/58.jpg)
50
CHAPTER THREE
BACKGROUND INFORMATION ON THE COMMUNITY-BASED POVERTY
REDUCTION PROJECT (CPRP)
3.1 Origin of CPRP
The failure of the respective initiatives to empower the poor, improve their poverty status
and enhance their wellbeing prompted the Nigerian Government to start thinking of a new
pragmatic approach that will allow the beneficiaries of poverty alleviation programmes to have
say. Thus, in 1994, the Nigerian Government, through the National Planning Commission (NPC)
set up a broad based committee which comprised government institutions, the World Bank,
(WB), United Nations Development Programme (UNDP), United Nations Children Education
Fund (UNICEF), United Kingdom Department for International Development (DFID), experts
from Nigerian universities, Organized Private Sector (OPS) including labour to design an
appropriate framework for poverty reduction in Nigeria (NPC, 1996:23). After two years of
activity, the committee, in February 1996, proposed to the Government of Nigeria a community
based approach to poverty alleviation which adopts a combination of social funds and social
action strategies known as Community Action Programme for Poverty Alleviation (CAPPA)
which was subsequently accepted by the Government (NPC, 2001).
The CAPPA document draws largely from the past experiences in poverty reduction
efforts in the country. Unlike the previous strategies, the CAPPA approach was to ensure that the
poor are not only carried along in the design and implementation of poverty projects that affects
them but the poor themselves actually formulate and manage the poverty projects (NPC, 1996).
The pilot programme that will arise from CAPPA will emphasize (a) coordination of all on-going
and new sector specific programmes and projects that may impact on the poor, and (b)
![Page 59: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/59.jpg)
51
implementation by selected communities (themselves), of relatively small, well targeted,
demand-driven projects and sub-projects that would impact on their poverty situation. According
to the (NPC, 2001:34), the objectives of the pilot programme were:
i. To improve the living condition of the poor through targeted, cost effective, demand-
driven and promptly delivered programme;
ii. To enhance the productivity of the poor by increasing their access to and resources
through skill improvement;
iii. To empower the poor by increasing their participation in decision making and
mobilizing their talents for community development projects;
iv. To enhance the capacity of the poor to help themselves on a sustained basis through
the strengthening of appropriate local institutions.
v. To build on existing safety nets for alleviating transient or transitory poverty at the
local level; and
vi. To improve the nutritional status of the poor through improved household food
security and health practices.
The emphasis on the CAPPA anticipated pilot programmer as well as its objectives gave birth to
the “Community-Based Poverty Reduction Project (CPRP) which funding was declared effective
by the World Bank in September 2001 (NPC, 2001).
3.2 The Design of CPRP Programmes
The CPRP is a pilot poverty reduction programme designed to operationalize the concept
of CAPPA. This concept is born out of Government desire to tackle poverty challenges whose
incidence is high among rural areas and increasing at the urban centres. The CPRP is anchored
on an all inclusive, participatory process that focuses on a paradigm shift from the top-down,
![Page 60: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/60.jpg)
52
supply driven approach to poverty reduction to a bottom-up, demand-driven and multi-sectoral
project development approach that puts communities in charge of the decision making process,
as well as heir basic needs (NPC, 2009). The operationalization at community levels was
targeted as the best approach to enhance effective implementation of CPRP programmes. The
communities are to identify their priority needs, implement and maintain the projects (NPC,
2009). The involvement of the communities in the entire project process is to engender
ownership and sustainability.
The concept of CPRP is new and unique when compared with all the poverty reduction
strategies implemented by the Government of Nigeria before the piloting of CPRP. The past
poverty reduction strategies such as (NALDA, MAMSER, ADP, NDE, Peoples Bank, Primary,
Health Care, etc) had been implemented in a top-down manner without the involvement of the
beneficiaries in the choice of projects as well as he implementation process. The expected output
according to (NPC, 2009:231) at the community level includes:
• Improved living conditions of the poor through improved access to basic infrastructure in
the management of developmental resources, project implementation and management.
• Improved access to socio-economic infrastructure.
• Reduced level of poverty in the rural areas arising from gainful employment through the
improved access to socio-economic infrastructure.
3.3 States Participation and Selection in CPRP
The design of the CPRP implementation created a platform for the sub-national levels of
government (State and Local Government) to operate in the implementation process. The state
selection process is quite unique, simple and scientific, thus; did not give rise to protest or
agitation from any quarter. The states were selected based on the poverty profile from the report
![Page 61: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/61.jpg)
53
of the National Bureau of Statistics (NPC, 2004) which ranked the states and Federal Capital
Territory (FCT) according to their poverty levels. Based on the poverty profile, the Nigerian
Government selected the most poorest state from each of the six geopolitical zones to form the
very first six states in the phase 1 namely Abia (South East), Cross River (South South), Ekiti
(South West), Kebbi (North West), Kogi (North Central) and Yobe (North East).
The additional six states referred to as the phase 2 were similarity selected the next
poorest state in the geopolitical zone. Based on the same NBS poverty index, the next ranked
poorest state from the geopolitical zones were identified as Benue (North Central), Delta (South
South), Enugu (South East), Gombe (North East, Osun (South West) and Zamfara (North West).
The three states (Benue, Delta and Enugu), however, opted out of the arrangement and were
subsequently replaced with the next poorest states from their zones as follows: Kwara State
(North Central), Edo Sate (South South), and Ebonyi State (South East), thus, completing the
phase II states as Kwara (North Central), Edo (South South), Ebonyi (South East), Gombe
(North Eas), Osun (South West) and Zamfara (North East), Osun (South West) and Zamfara
(North East), Osun (South West) and Zamfara (North West).
The phase II states were assisted by the World Bank (WB). The preparation of the states
for the take-off of the project stared in year 2000 and by September 28, 2001 was formerly
declared effective by the WB. The phase I eventually closed on August 31, 2006. In the phase 2,
states, the WB assisted only two of the states (Kwara and Ebonyi) while the African
Development Bank (ADB) four states (Edo, Gombe, Osun and Zamfara) popularly referred to as
ADB states. The phase 2 states became effective in year 2003 and closed in June 2009. In order
to facilitate the implementation of the CPRP in each of the pilot states, the states were by law
mandated to establish a community based Poverty Reduction Agency (CPRA). The CPRA is the
![Page 62: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/62.jpg)
54
State Social Fund Agency which is saddled with the responsibility to set the processes of
identifying and appraising appropriate micro projects applications for approval, disburse funds
and liaise with the National Planning Commission (NPC) at the Federal level which is the
“Clearing House” for CPRP via the Poverty Alleviation United (Madu et. al, 2009). The
establishment of the CPRA is part of the preparatory activities which must be completed before
the finding becomes effective. The State House of Assemblies promulgates a law which set up
the Agency and the law grants autonomy to the Agency such that the State Government signs off
every control including financial control of the Agency. This might equally opted out of the
programme because it is not easy to relinquish financial authority. The agencies according to the
report of the NPC, (2005:67) were changed with the following responsibilities:
• Collation of project proposal from communities.
• Review of projects from communities.
• Desk and field appraisal of proposed projects.
• Approval of the micro-projects to be implemented; and
• Routine supervision of community projects.
In this regard, in order to facilitate the project execution at the community level, the various
communities were required to establish Community Project Implementation Committee (CPIC).
The CPIC facilitates the execution of projects in their communities. The CPIC is only acceptable
to the CPRA if women are included or occupy some key positions in the committee. As part of
the bottom-top approach, the beneficiary communities are responsible for the following:
• Identifying, prioritizing and proposing projects; and
• Management of resources, implementation of identified projects and maintenance of
projects on completion.
![Page 63: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/63.jpg)
55
3.4 CPRP Programmes/Projects
The programmes and projects implemented under the CPRP are mainly micro projects.
They are broadly classified under three main groups namely: economic projects, infrastructure
projects and social service projects.
Economic Projects
According to the (NPC, 2006) report the micro projects under this category seek to
empower the beneficiaries economically. The focus is to improve the income status of the
beneficiaries. The micro projects involve:
• Market development
• Community agricultural mini processing plan.
• Small-scale community age industry.
• Skill acquisition centres
Infrastructure Projects
The infrastructure projects provide the beneficiaries the platform to create economic
empowerment. The micro projects in this category include:
• Construction, rehabilitation and maintenance of roads, drainage, erosion and flood
control.
• Rural electrification.
• Construction of bridges and culverts.
• Construction and maintenance of water and sanitation facilities.
Social Service Projects
The social service projects cover micro projects or sub-projects that improve human
capital development. The projects involve:
![Page 64: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/64.jpg)
56
• Provision of new and improvement of existing health care services and provision of
essential medicines and equipment.
• Expansion and improvement of school buildings and educational facilities including
laboratories, libraries.
• Television viewing centres for public enlightenment.
The project selection process starts with the identification of the project by the
community. The community then applied to the state CPRA for funding. The CPRA then carries
out desk and field appraisal of the project. If the project satisfies the spelt out criteria, it is
approved by the state CPRA and funded. The detailed schematic framework is at annex, while
the detailed list of CPRP micro projects and sub-projects is at annex.
3.5 Resources Base and Budget Releases
Public finance is central to poverty reduction and the practice of public expenditure
management can hinder or promote the achievement of poverty reduction objectives (World
Bank; 2002). The hall mark of CPRP success is dependent upon sound financial control and
expenditure management. The resource base of the CPRP is funded from four major sources.
These four sources are the African Development Bank (ADB), Federal Government of Nigeria
(FGN), (i.e. four ABD states) and the communities.
The ADB provided a loan facility of UA 20 million (an equivalent $26.74 million) for the
project through credit agreement with the FGN for on-lending to the four states. This
arrangement implies that the FGN takes he loan from ADB and then lend the fund to the four
states for use for implementation of the CPRP. Since the ADB credit/loan is on-lending, the
participating states ensure responsibility for repayment (NPC 2009). Consequently, a subsidiary
![Page 65: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/65.jpg)
57
between the FGN and each of the four benefiting states exist to facilitate the programme
implementation.
The FGN is represented by the Federal Ministry of Finance (FMF) in contracting the loan
while the NPC is the executing agency on behalf of the FGN. By the loan agreement, the FGN
will provide 109% counterpart fund for its component of the loan which is utilized by the NPC
for preparation of states for the take-off of the project and overall coordination activities. The
participating four states also provide 10% counterpart fund for their respective credit/loan
component that was on-lend to them for the State Social Fund Agency to implement its
programmes. This counterpart contribution by each state is estimated at about N6million yearly
(NPC, 2009). The proof of thee fact that 10% counterpart fund has entered the Naira account of
the executing agency qualifies the Agency to begin to drawdown the loan which had been
credited to a separate dollar account.
At the community level, when a project has been approved by the state CPRA, the
beneficiary community was required to open an account with a bank where an equivalent of 10%
of the project cost is credited into as their counterpart fund component. The remaining 90% cost
of the project is provided from the loan by the state CPRA aid paid into he community project
account. This means that communities benefiting from the projects automatically operate two
accounts. In a situation where a beneficiary community does not have cash to credit into a
counterpart fund account, it will then be computed in kind. The inputs provided by such
community in terms of labour and materials for execution of the project is costed to cover he
required counterpart contribution.
The fund release process is very interesting and unique. When a community project is
approved, funds are released to them for execution of the project in three branches in the ratio of
![Page 66: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/66.jpg)
58
30:30:40. The unique aspect is that when a tranche is released, it will be divided into two pars
90% it from the loan account (project account) and the remaining 10% from the counterpart fund
account. The next tranche is released only when the state CPRA is satisfied with the expenditure
of the previous release and proper records are kept. The CPIC which executes the project on
behalf of the community manages the accounts. As part of the preparatory activities, the
members of the CPIC have been trained on simple book keeping (even in a local language where
needs be). Usually, the cheque is handed over to the community by the state CPRA at a project
launching. Depending on the type of project, selected by the community, they are usually
completed within 3 to month 6 months range.
3.6 Institutional Arrangements
The institutional arrangement is the administrative structure put in place to facilitate the
implementation and realization of the objectives of CPRP. The administrative is at three levels as
follows:
• Federal level
• State level
• Community level
Institutional Structure at the Federal Level
The operations at the federal level are domiciled at the National Planning Commission
(NPC). The NPC is the policy-level focal point for poverty reduction efforts in Nigeria (ADB-
PAD, 2006). Its broad responsibilities include coordinating and monitoring all activities of the
government funded poverty alleviation programmes (Madu et al 2009).
![Page 67: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/67.jpg)
59
Poverty Alleviation Steering Committee (PASC)
In the light of its mandate and to be able to effectively manage the CPRP, the NPC set up
a Poverty Alleviation Steering Committee (PASC). The PASC is a multi-sectoral inter-
ministerial committee whose role is an advisory board and plays an over sight function to
Poverty Alleviation Unit (PAU) The operation manual of CPRP state that the PASC do not take
part in the day-to-day running of CPRP belt carries out is function by:
a. Set overall policy for the PAU;
b. Review work programme, progress reports audit and evaluation.
The committee is made up 15 members and meets quarterly.
The membership are drawn from the NPC, Federal Ministry of Finance (FMF), Federal
Ministry of Agriculture, Federal Ministry of Health, Federal Ministry of Works, Federal Ministry
of Women Affairs and social Development, Federal Ministry of Education, Central Bank of
Nigeria (CBN), representatives of State Social Fund Agency and Civil Societies.
Poverty Alleviation Unit (PAU)
The Poverty Alleviation Unit (PAU) is established within the National Planning
Commission (NPC). The NPC serves as a “Clearing House” for all CPRP activities. This is done
through the PAU which has the responsibility to manage, coordinate and facilitate the overall
activities of CPRP. The PAU provides the national framework and common set of standards for
financial reporting accounts/procurement, monitoring evaluation of the project (Madu et al
2009). The key role of NPC which is exercised by the PAU includes:
a. Formulation of poverty policies and strategies and disseminations;
b. Coordination of the CPRP programmes in the ADB-states;
c. Advocacy and sensitization;
d. Capacity building at the Federal, state and communities;
![Page 68: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/68.jpg)
60
e. Monitoring and Evaluation; and
f. Impact assessment.
The PAU is headed by a Project Manager appointed by the Government and is assisted by four
Operational Project Officers, Project Accountant and Project International Auditor. The Project
Officers are responsible for the four components of the project that helps the NPC in carrying out
its mandates – Poverty Policy Analysis and Disseminations; Advocacy and sensitization;
capacity building; and monitoring and evaluation (M & E). The PAU also relates with Federal
line Ministries in carrying out its functions in the following:
• Involve the expertise of relevant line sectoral ministries through formation of
technical committee whenever call for evaluation of proposal/study is to be made.
• From time to time liaise with relevant sectoral ministries in designing and
propagation of public awareness programmes;
• Harnessing the expertise of relevant ministries when carrying out monitoring and
evaluation of programmes and projects;
• Designing of Terms of Reference (TOR) as it relates to activities of policy
coordination, Awareness and mobilization, capacity building, Poverty Monitoring
and Impact Assessment.
• Sensitization, mobilization and Advocacy for the poor against Malaria and AIDS.
State Level
Each participating state by law of their State House of Assembly established a state social
Fund Agency referred to as the Community-Based Poverty Reduction Agency (CPRA). The law
establishing the agency granted it autonomy in all its daily operations from the State Government
and independent from the National Planning Commission. Consequently, funds accruing to the
![Page 69: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/69.jpg)
61
Agency either from the State Government or account. Also, all replenishment by the ADB are
carried out directly on meeting the requirement.
The CPRA is headed by a Project Manager and assisted by a Project Officer and
Assistant, Project Accountant and Assistant; Procurement officer and other support staff
(secretary, messenger, cleaner, Driver). The key staff were recruited by the NPC in a competitive
manner at the preparatory stage of the states. He CPRA is responsible for the following:
• Collation of project proposals from the communities.
• Review of projects from communities desk and field appraisal of projects proposed by the
communities.
• Approval of the micro projects to be implemented.
The State Agency has its own Board which plays advisory role and oversight function. Strategic
implementation of the CPRP at the state involves: sensitization and awareness creation for the
local government chairmen, community development officers in the local government council,
traditional rulers, community leaders, community development organization (e.g. Town Unions,
Community Based Organisations and Associations (CBOSWCBAS)). The CPRA also assist in
capacity building of the community members in the areas of project and financial management,
disbursement of funds to CPICS, ensuring that the 10% counterpart contribution is made by the
beneficiary communities. In a situation where a communities implementing a project and a skill
required in an aspect of the project is lacked in the community, the CPRA assists the community
to procure such skill so that the final product meets the required standard.
The Community Level
The Community level is the last level in the institutional arrangement for the
implementation of the CPRA. All physical activities for implementation of projects are carried
![Page 70: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/70.jpg)
62
out at that level. The community themselves identify baskets of projects, prioritize them and
apply to the State Social Fund Agency-CPRA for approval. After the usual desk and field
appraisal, the Agency approves the community project. On approval of the project, the
community establishes community project implementation committee (CPIC). The CPIC is
saddled with the responsibility of implementing the project and management of resources.
Usually, women are encouraged to hold some key positions like Treasure, secretary, chairman
etc in the CPIC. The members of the CPIC are usually available to conduct any Supervisory
Mission round the project whenever there is mission from Tunisia (ADB), NPC and even the
State Agency.
3.7 CPRP Monitoring and Evaluation
The project Monitoring and Evaluation (M & E) of CPRP is one of the major components
of the project. It is done to track down the implementation of projects with a view to attaining
project goals and objectives. It is also for the assessment of performance, efficiency and impacts
of project in relation to stated objectives. The purpose of the M & E was to track project
implementation, compare actual project performance with the planned activities for a period, to
ensure that the CPRP remain on course, meeting expected outputs and outcomes in a timely
manner and that impediments to smooth implementation of projects are nipped in the bud (NPC;
2009).
The M & E activities are carried out at two levels. The first level is the State Social Fund
Agency. The Agency visits the projects at the communities very regularly to ensure that project
implementation are carried out in accordance with work plan and the financial disbursements.
The Agency assists the communities to address various challenges that may crop up in the course
of project implementation. The other level is the NPC. The NPC carries out M & E exercise at
![Page 71: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/71.jpg)
63
the beneficiary communities in the states on quarterly basis. It is usually carried out in
conjunction with relevant Federal Ministries, most especially the Federal Ministry of Finance
(FMF). The M & E is usually preceded by a Quarterly Review Meeting (QRM) organized by the
NPC to address issues relating to project implementation as well as expectations in the quarter.
The report of the quarterly monitoring exercise conducted by the NPC is forwarded to the
African Development Bank (ADB) for their information. The ADB also usually undertakes
supervisory mission of the community projects twice annually to assess the performance of the
project. This activity is carried out in conjunction with the NPC.
![Page 72: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/72.jpg)
64
CHAPTER FOUR
DATA PRESENTATION, ANALYSIS AND FINDINGS
The chapter four of this research work will deal with the presentation and analysis of the data
used for the study. The data is mainly compiled or derived from the secondary source (project
documents) and interfaced with the results of the oral/personal interviews conducted with the
beneficiaries of the micro-projects or sub-projects. The chapter also focused on the testing of the
research hypotheses with a view to ascertaining the consistence of the hypotheses in relation with
the findings. Consequently, in presenting and analyzing the data, we followed alphabetically
thus; Edo State, Gombe State, Osun State and Zamfara State respectively.
4.1 Data Presentation and Analysis for Edo State
Table 4.1 Funding of Edo State CPRP
Source Amount (N) Percentage (%)
African Development Bank (ADB) 730,109,103.75 95.31
Edo State Government 30,006,580.20 3.92
Miscellaneous Income 5,890,750.60 0.77
Total 766,006,434.55 100
Source: Compiled from Edo State and NPC CPRP documents
The table 4.1 above shows the sources of funds for Edo State Community based Poverty
Reduction Project (CPRP). The total funds obtained for the financing of the activities of CPRP in
Edo State amounted to N766,006,434.55. This is N233,993,565.45 or 30.55 percent less than one
billion naira marked for state reduction programmes under the joint partnership of Edo state and
the donor agencies especially the African Development Bank. Of the total funds mobilized, the
![Page 73: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/73.jpg)
65
African Development Bank (ADB) alone provided the sum of N730,109,103.75 or 95.31
percent, while, the Edo State Government provided the sum of N30,006,580.20 or 3.92 percent.
The miscellaneous sources which comprised interest payments and other charges amounted to
N5,890,750.60 or 0.77 percent. The researcher however attempted to find out why there was no
contribution from the beneficiary communities of the micro-projects/sub-projects which
originally as clearly stated in the project document were supposed to contribute equivalent 10
percent of the project cost as counterpart contribution in cash or kind. The oral interview
conducted among the staff of the State Agency revealed that the contributions by the beneficiary
communities are not part of disbursements made by the Agency and therefore not an ADB
component of funds. The response also disclosed that community contributions are paid directly
by the Project Implementing Committee (PIC) into the community project account which is
managed directly by the community, thus alluding to the social fund and demand driven qualities
of the project. Similarly, the share of the contribution by the ADB – 95.31 percent justifies the
ascribing of the project as ADB-Assisted Project. The oral interview also revealed that the
management of the project funds directly by the beneficiary communities necessitated or helped
in the building of the capacity of the rural communities to be able to handle the implementation
of the micro projects/sub projects at the communities.
Table 4.2 Utilization of Funds
Activity Amount (N) Percentage (%)
Fixed Asset 18,230,490.00 2.38
Training/Workshops 25,725,865.00 3.36
Micro Projects/Sub Projects 650,918,630.00 84.98
Operating Costs 71,130,449.55 9.28
Total Expenditure 766,006,434.55 100
Source: Compiled from Edo State and NPC CPRP documents
![Page 74: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/74.jpg)
66
The table 4.2 shows the utilization of the mobilized funds by the Edo State Social Fund
Agency-the CPRP. As depicted on the table, the funds was expended on procurement of fixed
assets, training and workshops for Agency staff and Project Implementing Committee members,
implementation of micro-projects/sub- projects at the community levels and operating costs. The
share of the expenditures on fixed assets is 2.38 percent or N18,230,490.00 while, that on
training/workshops amounted to N25,725,865.00 or 3.36 percent. The expenditures on micro-
projects and operating costs amounts respectively to the sum of N650,918,630.00 or 84.98
percent and N71,130,449.55 or 9.28 percent. The revelation of the table is very interesting to any
project management and worthy of note. For instance, it is often advocated that operating costs
of projects should not exceed 20 percent of the total funds. In the case of the Edo CPRP, this
component only took 9.28 percent which is very reasonable. The oral interview also revealed that
salaries and wages as well as other sundry expenditures benefited from the operating costs
components. The highest proportion of the expenditure was on the implementation of micro-
projects/sub-projects and this also reveals some prudence on the side of the Agency in the
management of the project funds.
Table 4.3 Sectoral Implementation of Micro-Projects/Sub-Projects
Sub-Sectors No. of Micro Projects
Implemented
Percentage (%)
Education 27 16.87
Health 15 9.37
Skill Acquisition/ Civic/Computer Centre 49 30.63
Water 52 32.50
Power (Electricity) 10 6.25
Environment (Sanitation) 1 0.63
Markets 6 3.75
Total 160 100
Source: Computed from Edo State and NPC CPRP documents
The table 4.3 is the focus of the project. The table showed the sectoral implementation of
the micro-projects/sub-projects through the duration of the CPRP activities. As disclosed by the
![Page 75: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/75.jpg)
67
table, a total of 160 micro projects/sub projects were executed or implemented with the total
amount of N650,918,630.00 as indicated in table 4.2. The water sub-sector had the highest
number of micro- projects with about 52 of them representing 32.50 percent. The next in that
order is skill acquisition/civic/computer education centres with 49 micro-projects representing
30.63 percent, education with 27 micro-projects or 16.87 percent, health with 15 micro-projects
or 9.37 percent, power (electricity) with 10 micro- projects or 6.25 percent while markets and
sanitation/environment projects were 6 and 1 projects or 3.75 and 0.63 percent respectively. The
researcher attempted to find out the preference for water micro-projects. The oral interview with
some respondents in the beneficiary communities revealed that most of the communities actually
lacked portable water. Furthermore, beside the fact that water table is high within the region
thereby making it relatively cheap to implement mini water projects, the respondents also poised
that their sources of water had been either stream, ponds, local well, collected rain water and
paid water tankers. The researcher observed that with the mini water projects, the beneficiary
communities saved money as well as time spent in search of water. Also, some of the
respondents informed that agriculture is the predominant occupation of the rural dwellers and
that they had been relying on seasonal rain water for their farming activities but that the mini
water scheme has facilitated local irrigation of their backyard vegetable and fruit farms and
enabled them to embark on dry season farming and consequently boosting their income and
reducing poverty. The least of micro-projects came from the environment/sanitation sub-sector.
![Page 76: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/76.jpg)
68
Table 4.4 Total Expenditure on Sub-Sectors
Sub Sectors Amount (N) Percentage (%)
Education 107,280,314.00 16.48
Health 64,063,836.00 9.84
Skill Acquisition/ Civic/Computer Centre 230,007,194.00 35.34
Water 181,310,063.00 27.85
Power (Electricity) 44,949,561.00 6.91
Environment (Sanitation) 3,514,818.00 0.54
Markets 19,792,844.00 3.04
Total 650,918,630.00 100
Source: Computed from Edo State and NPC CPRP documents
The table 4.4 shows total expenditure on micro projects for each sub sectors. As shown
on the table, total amount of money expended on implementing micro- projects/sub-projects in
Edo State amounted to N650,918,630.00. This is made up of the highest expenditure of
N230,007,194.00 or 35.34 percent on skill acquisition/civic/computer centres micro projects and
N107,280,314.00 or 16.48%, N64,063,836,00 or 9.84% and N181,310,063.00 or 27.85% for
executing Education, Health and Water micro-projects respectively. The least expenditure is on
Environment/Sanitation with the total amount of N3,514,818.00 while the Power/Electricity and
Market sub-sectors shared N44,949,561.00 and N19,792,844.00 respectively. The researcher
attempted to find out the share of the community contributions on the micro each sub sector with
a view to ascertaining the real cost to the communities. The oral interview conducted on the
respondents however revealed that the contributions by the communities were either in cash or
kind and expended by the community directly without remitting to the CPRP Agency while the
amounts shown on the table is the share of the contributions by the ADB and State Government
![Page 77: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/77.jpg)
69
counterpart contributions. Similarly, more than one third of the total expenditure was on
empowerment and job creation through skill acquisition.
Table 4.5 Mean Cost of Micro Projects in each Sub Sectors
Sub-Sectors Amount (N) Percentage (%)
Education 3,973,344.96 14.33
Health 4,270,922.40 15.40
Skill Acquisition/ Civic/Computer Centre 4,694,027.37 16.93
Water 3,486,731.98 12.57
Power (Electricity) 4,494,956.10 16.21
Environment (Sanitation) 3,514,818.00 12.67
Markets 3,298,807.33 11.89
Total 27,733,608.14 100
Source: Computed from Edo State and NPC CPRP documents
The table 4.5 shows the mean cost of implementing the micro-projects/sub- projects in
each sub sector in Edo State. The average cost of the micro projects in Edo State is
N4,068,241.44. From the table, the least cost sub-sector micro- projects are those of the markets
with an average cost of N3,298,807.33 while water and environment/sanitation micro-projects
are the next lowest at N3,486,731.98 and N3,514,818.00 respectively. The most expensive
projects are the ones implemented under the Skill Acquisition/Civic/Computer Centres at an
average cost of N4,694,027.37. The high cost of the micro-projects of this sub- sector may have
suggested the highest expenditure of N230,007,194.00 or 35.34 % of the total expenditures as
recorded in table 4.4. The researcher attempted to find out the justification for the high cost of
Skill Acquisition projects in relation to other sectors. The oral interview conducted on the
respondents confirmed that the cost of furnishing and equipping the centres contributed to the
![Page 78: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/78.jpg)
70
high cost of implementing projects in the sub sector in Edo state. The respondents similarly
attributed the capital intensive nature of the Power/Electricity projects and equipping and
furnishing of Health and Education projects as reasons for the average costs of N4,494,956.10,
N4,270,922.40 and N3,973,344.96 respectively.
Table 4.6 Categorization of the Implementation of Micro Projects into Main Sectors
Main Sector No. of Micro Projects
Implemented
Percentage (%)
Social Services Projects 42 26.25
Economic Sectors Projects 55 34.38
Infrastructure Sector Projects 63 39.37
Total 160 100
Source: Computed/Analyzed from Edo State and NPC CPRP documents
The table 4.6 shows the categorization of the implementation of micro- projects in Edo
State into main sectors. The National Planning Commission (NPC) defined the CPRP micro-
projects across three main sub-sectors namely Social Service sector projects, Economic Sector
Projects and Infrastructure Sector projects. From the table, of the 160 micro projects
implemented, 42 of them representing 26.25 percent was implemented from the social services
while 55 or 34.38 percent and 63 or 39.37 percent were from the Economic and Infrastructure
sectors respectively. The Edo State seems to have preferred infrastructure projects which include
Power/Electricity, mini Water projects, Environment/Sanitation projects than the Economic and
Social Service sector projects. The social service projects comprised Education and Health micro
projects while the Economic sector projects included Skill Acquisition Centres/Civic/Computer
Centre and Markets.
![Page 79: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/79.jpg)
71
Table 4.7 Categorization of the Expenditures on Micro Projects into Main Sectors
Main Sector Amount (N) Percentage (%)
Social Services Projects 171,344,150.00 26.32
Economic Sectors Projects 249,800,038.00 38.38
Infrastructure Sector Projects 229,774,442.00 35.30
Total 650,918,630.00 100
Source: Computed from Edo State and NPC CPRP documents
The table 4.7 shows the categorization of the expenditures on the Edo CPRP micro
projects into the three main sectors. Of the total resources expended on the micro projects, the
sum of N171,344,150.00 or 26.32 percent was spent on provision of social services related
micro projects while the economic sector projects gulped N249,800.038.00 or 38.38 percent. The
share of expenditure on infrastructure sector micro projects amounted to N229,774,442.00
representing 35.30 percent. As shown by the table, more funds were expended on the economic
sector than the infrastructure and social service sectors. The total expenditure pattern correlated
with the mean costs. For instance, eventhough the number of micro projects in the infrastructure
sector is more than the economic projects, the amount spent on economic projects is higher
because of the average costs of the micro projects that constitute that sector as reflected on table
4.5
Table 4.8 Mean Expenditure on Micro Projects Categorized into Main Sectors
Main Sector Amount (N) Percentage (%)
Social Services Projects 4,079,622.62 33.25
Economic Sectors Projects 4,541,818.87 37.02
Infrastructure Sector Projects 3,647,213.36 29.73
Total 12,268,654.85 100
Source: Computed from Edo State and NPC CPRP documents
![Page 80: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/80.jpg)
72
The table 4.8 shows the mean expenditure on micro projects categorized into main
sectors namely the Social Service sector projects, Economic sector projects and Infrastructure
sector projects. The table shows that the most expensive micro projects are the ones implemented
under the economic sector which averaged N4,541,818.87 while the cheapest were the projects
of Infrastructure sector at N3,647,213.36. The mean cost of Social service sector projects as
shown on the table amounts to N4,079,622.42. The mean cost of the economic sector projects
may have attributed to the more money expended on the sector as confirmed on table 4.7
Table 4.9 Approved and Completed Micro Projects
Sub Sectors Total Micro
Projects
Approved
No. of Micro
Projects
Completed
Completion
Percentage
(%)
Education 27 27 100
Health 15 15 100
Skill Acquisition/ Civic/Computer Centre 49 49 100
Water 52 52 100
Power (Electricity) 10 10 100
Environment (Sanitation) 1 1 100
Markets 6 6 100
Total 160 160 100
Source: Computed from Edo State and NPC CPRP documents
The table 4.9 shows the sub-sectoral distribution of the approved and completed projects
in the Edo CPRP. The table showed that all the 160 micro projects approved for the communities
for implementation by the Edo CPRP Agency were fully implemented. There is no sector where
a project is still on- going. The researcher attempted to find out why the CPRP was able to
complete all the approved projects. The result of the oral interview conducted revealed that the
![Page 81: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/81.jpg)
73
decision to implement any project was demand driven and bank rolled with little demonstration
of counterpart contribution. The counterpart contributions have been made easier through the
equating of kind to cash for the communities.
Table 4.10 Distribution of Completed Micro Projects put into use
Sub-Sectors No. of Micro
Projects
Completed
No. of Micro
Projects in
Use
Proportion
in Use in
Percent
(%)
Education 27 27 100
Health 15 15 100
Skill Acquisition/ Civic/Computer Centre 49 49 100
Water 52 52 100
Power (Electricity) 10 10 100
Environment (Sanitation) 1 1 100
Markets 6 6 100
Total 160 160 100
Source: Computed from Edo State and NPC CPRP documents
The table 4.10 shows the number of micro-projects put into use vis-a-vis the completed
projects. As the table portrayed, all the 160 micro-projects completed by the Edo State CPRP
Agency have been put into use by the beneficiary communities. The implication of this is that all
160 communities have accessed the various micro projects implemented by the CPRP Agency to
reduce the poverty of the rural people.
![Page 82: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/82.jpg)
74
Table 4.11 Abandoned or Uncompleted CPRP Projects
Sub-Sectors Total Micro
Projects
Approved
No. of Micro
Projects
Abandoned or
Uncompleted
Percentage
(%)
Education 27 0 0
Health 15 0 0
Skill Acquisition/ Civic/Computer Centre 49 0 0
Water 52 0 0
Power (Electricity) 10 0 0
Environment (Sanitation) 1 0 0
Markets 6 0 0
Total 160 0 0
Source: Computed from Edo State and NPC CPRP documents
Table 4.11 shows that there is no micro project that was approved for implementation
that has been stalled or abandoned. All the 160 approved micro projects have been completed
and being used by the beneficiary communities to alleviate whatever type of poverty that was
identified by the community. That there is no abandoned project also shows the efficacy of the
CPRP strategy in tackling poverty in Nigeria. The researcher however sought opinion of some
beneficiary why the projects were not abandoned. The result of the oral interview attributed it to
regular release of funds by the CPRP Agency and transparent management of resources by the
PIC members. They also confirmed that training received by the PIC members helped the
community in the implementation process.
![Page 83: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/83.jpg)
75
4.2 Data Presentation and Analysis for Gombe State
Table 4.12 Funding of Gombe State CPRP
Source Amount (N) Percentage (%)
African Development Bank (ADB) 753,046,512.32 95.34
Gombe State Government 30,028,769.12 3.80
Miscellaneous Income 6,797,460.05 0.86
Total 789,872,741.49 100
Source: Compiled from Gombe State and NPC CPRP documents
The table 4.12 above shows the sources of funds for Gombe State Community based
Poverty Reduction Project (CPRP). The total funds accessed for financing of the activities of
CPRP in Gombe State amounted to N789,872,741.49. This is N210,127,258.51 or 21.01 percent
less than one billion naira mark. Of the total funds mobilized, the African Development Bank
(ADB) alone provided the sum of N753,046,512.32 or 95.34 percent, while the Gombe State
Government provided the sum of N30,028,769.12 or 3.80 percent. The miscellaneous sources
which comprised interest payments and other charges amounted to N6,797,460.60 or 0.85
percent. The researcher similarly attempted to find out why the counterpart contribution from
beneficiary communities of the micro-projects/sub-projects which originally as clearly stated in
the project document were to contribute equivalent 10 percent of the project cost as counterpart
contribution in cash or in kind. The oral interview conducted among the staff of the Gombe State
CPRP Agency revealed that the contributions by the beneficiary communities are not part of
disbursements made by the Agency and therefore not an ADB component of funds. The
responses also disclosed that community contributions are paid directly by the Project
![Page 84: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/84.jpg)
76
Implementing Committee (PIC) into the community project account which is managed directly
by the community, thus alluding to the demand driven qualities of the project. Similarly, the
share of the contribution by the ADB–95.34 percent justifies the ascribing of the project as
ADB–Assisted Project. The oral interview also revealed that the management of the project
funds directly by the beneficiary communities necessitated or helped in the building of the
capacity of the rural communities to be able to handle the implementation of the micro-
projects/sub-projects at the communities.
Table 4.13 Utilization of Funds
Activity Amount (N) Percentage (%)
Fixed Asset 23,258,293.20 2.95
Training/Workshops 27,582,928.05 3.49
Micro Projects/Sub Projects 653,207,986.66 82.70
Operating Costs 85,823,533.95 10.86
Total Expenditure 789,872,741.49 100
Source: Compiled from Gombe State and NPC CPRP documents
The table 4.13 shows the utilization of the mobilized funds by the Gombe State Social
Fund Agency–the CPRP. As depicted from the table, the funds was expended on procurement of
fixed assets, training and workshops for Agency staff and Project Implementing Committee
members, implementation of micro projects/sub projects at the community levels and operating
costs. The share of the expenditures on fixed assets is 2.95 percent or N23,258,293.20 while that
on training/workshops amounted to N27,582,928.05 or 3.49 percent. The expenditures on micro
projects and operating costs amounts respectively to N653,207,986.66 or 82.70 percent and
N85,823,533.95 or 10.86 percent. Again, the performance of this table is very interesting and
![Page 85: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/85.jpg)
77
worthy of note for project management. For instance, it is often advocated that operating or
administrative costs of projects should not exceed 20 percent of the total funds. In the case of the
Gombe State CPRP, this component took only 10.86 percent which is very reasonable. In fact,
all other costs components consisting of fixed assets, training/workshop and the operating costs
shared a total of 17.30 percent of the total expenditure/fund. The oral interview also revealed
that salaries and wages as well as other sundry expenditures benefited from the operating costs
components. The highest proportion of the expenditure was on the implementation of micro
projects/sub projects and this also reveals some prudence on the side of the Agency in the
management of the project funds.
Table 4.14 Implementation of Micro-Projects/Sub-Projects
Sub Sectors No. of Micro Projects
Implemented
Percentage (%)
Education 133 57.08
Health 36 15.45
Skill Acquisition/ Civic/Computer Centre 5 2.15
Water 30 12.87
Power (Electricity) 4 1.72
Environment (Sanitation) 1 0.43
Roads & Culverts 19 8.15
Markets 4 1.72
Others (Orphanage) 1 0.43
Total 233 100
Source: Computed from Gombe State and NPC CPRP documents
![Page 86: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/86.jpg)
78
The table 4.14 table showed the sectoral implementation of the micro projects/sub-
projects through the duration of the CPRP activities. As depicted on the table, a total of 233
micro-projects/sub-projects were executed or implemented in Gombe State with the total amount
of N653,207,986.66 as indicated in table 4.13. The Education sub-sector had the highest number
of micro projects with a total of 136 representing 57.08 percent. This is more than half the
number of projects executed in the State. The next project in demand in the State is the Health
sector projects with a total of 36 projects representing 15.45 while Water sector projects which
was the highest in Edo State took a third position in preference with a total of 30 micro-projects
representing 12.87 percent. The roads projects executed were 19 representing 8.15 percent, Skills
acquisition projects were 5 representing 2.15 while, the Power/Electricity projects and Markets
projects were 4 projects each representing 1.72 percents respectively. As usual, the researcher
attempted to find out the preference for Education micro projects in Gombe State. The oral
interview with some respondents in the beneficiary communities revealed that most of the
remote communities actually lacked education facilities. Some respondents informed the
researcher that many children trekked a long distance to get to school and in the schools the
classes are overcrowded with some pupils or students seating on the floor to take their lessons.
Furthermore, the researcher also observed that the choice of Education projects more than the
other sector projects was for the State to take advantage of the CPRP to support their move to
bridge the gap in education. This therefore tallies with the growing concern for the Northern
States being disadvantaged in education. Thus, the CPRP is being used by the Gombe State to
address the challenge. Similarly, the next preferred projects – Health and Water projects
according to the researcher’s oral interview respondents are to help the State improve their
human development index as well as addressing the Millennium Development Goals (MDGs)
![Page 87: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/87.jpg)
79
needs of the State. To an extent, the objective is being achieved since 36 remote communities
had health facilities and 30 communities had good sources of drinking water under the CPRP
project. Similarly some of the respondents informed the researcher that they are farmers and that
they preferred road projects/culverts to enable carry their farm produce to markets where they
can obtain relatively fair prices. This of course would in the short and long-run improve the
income poverty of the people.
Table 4.15 Total Expenditure on Sub Sectors
Sub-Sectors Amount (N) Percentage (%)
Education 339,091,218.00 51.91
Health 156,337,179.66 23.93
Skill Acquisition/ Civic/Computer Centre 16,247,832.14 2.49
Water 46,242,053.06 7.08
Power (Electricity) 16,310,400.00 2.50
Environment (Sanitation) 1,530,000.00 0.24
Roads & Culverts 66,655,387.20 10.20
Markets 7,013,916.60 1.07
Others (Orphanage) 3,780,000.00 0.58
Total 653,207,986.66 100
Source: Computed from Gombe State and NPC CPRP documents
The table 4.15 shows total expenditure on micro projects for each sub- sectors for Gombe
State. As depicted on the table, total amount of money expended on implementation of micro-
projects/sub-projects in Gombe State amounted to N653,207,986.66. This is made up of the total
expenditure on Education amounting N339,091,218.00 representing 51.91 percent, Health
projects amounting N156,337,179.66 representing 23.93 percent, Rural roads projects
![Page 88: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/88.jpg)
80
amounting N66,655,387.20 representing 10.20 percent, Water micro projects amounting to
N46,242,053,06 representing 7.08 percent, Power/Electricity projects amounting
N16,310,400.00 representing 2.50 percent, Skills Acquisition/Civic/Computer centre micro-
projects amounting N16,247,832.14 representing 2.49 percent. The least expenditure is on
Environment/Sanitation with the total amount of N1,530,000.00 representing 0.24 percent of the
total expenditures on micro projects. The researcher similarly attempted to find out the share of
the community contributions on the micro-projects of each sub-sector with a view to ascertaining
the real cost to the communities. The oral interview conducted on the respondents however
revealed that the contributions by the communities were either in cash or kind and expended by
the community directly without remitting to the CPRP Agency while the amounts shown on the
table is the share of the contributions by the ADB and State Government counterpart
contributions. The very huge amount spent on the Education sub sector which gulped more than
half of the total expenditures is a proof and indication of Gombe State people wanting to rise to
the club of educationally advantage states rather than continue to remain as an educationally
disadvantaged state. Also, the expenditure on roads according to the respondents of the oral
interview conducted by the researcher is to make the rural roads accessible to help the rural
people to transport their farm products to the urban markets.
![Page 89: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/89.jpg)
81
Table 4.16 Mean Cost of Micro Projects in each Sub-Sectors
Sub Sectors Amount (N) Percentage (%)
Education 2,549,558.03 9.68
Health 4,342,699.43 16.50
Skill Acquisition/ Civic/Computer Centre 3,249,566.43 12.34
Water 1,541,401.77 5.84
Power (Electricity) 4,077,600.00 15.49
Environment (Sanitation) 1,530,000.00 5.81
Roads & Culverts 3,508,178.27 13.33
Markets 1,753,479.15 6.65
Others (Orphanage) 3,780,000.00 14.36
Total 26,324,483.08 100
Source: Computed from Gombe State and NPC CPRP documents
The table 4.16 shows the mean cost of implementing the micro-projects/sub- projects in
each sub sector in Gombe State. The average cost of the micro-projects in Gombe State is
N2,803,467.75. From the table, the least cost sub-sector micro projects are those of the
Environments/Sanitation with an average cost of N1,530,000.00, Water projects with an average
cost amounting N1,541,401.77 and Markets projects amounting to N1,753,479.15. The most
expensive projects are the micro projects implemented under the Health sector whose average
cost amounted to N4,342,699.43 and the Power/Electricity micro projects amounting to
N4,077,600.00. The researcher attempted to find out the justification for the high cost of Health
and Power/Electricity sectors micro projects in relation to other sectors. The oral interview
conducted on the respondents confirmed that the cost of furnishing and equipping as well as
providing seed drugs to the rural health centres contributed to the high cost of implementing the
![Page 90: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/90.jpg)
82
sub sector projects in Gombe state. The respondents similarly attributed the capital intensive
nature of the Power/Electricity projects as reasons for the high mean costs.
Table 4.17 Categorization of the Implementation of Micro Projects into Main Sectors
Main Sector No. of Micro Projects
Implemented
Percentage (%)
Social Services Projects 170 72.96
Economic Sectors Projects 9 3.86
Infrastructure Sector Projects 54 23.18
Total 233 100
Source: Computed from Gombe State and NPC CPRP documents
The table 4.17 shows the categorization of the implementation of micro projects in
Gombe State into main sectors. In line with the National Planning Commission (NPC) the
researcher grouped the CPRP micro projects into three main sectors namely Social Service sector
projects, Economic Sector Projects and Infrastructure Sector projects. From the table, of the 233
micro projects implemented at the State, 170 of them representing 72.96 percent was
implemented from the Social Services while 9 or 3.86 percent and 54 or 23.18 percent were
from the Economic and Infrastructure sectors respectively. The Gombe State from the table have
preference for the Social Service sector projects which include Education and Health projects
than the Economic and Infrastructure sector projects. The Economic sector projects included
Skill Acquisition Centres/Civic/Computer Centre and Markets while the Infrastructure projects
include Power/Electricity, Environment/Sanitation, Water and Road/Culverts. The high number
of projects implemented from the Social Services is a further indication for the quest by the
Gombe State to improve on the Human Development Index (HDI) of the state. The Human
Capita Development contributes immensely to economic and overall development of the people.
![Page 91: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/91.jpg)
83
Table 4.18 Categorization of the Expenditures on Micro Projects into Main Sectors
Main Sector Amount (N) Percentage (%)
Social Services Projects 499,208,397.66 76.42
Economic Sectors Projects 23,261,748.74 3.56
Infrastructure Sector Projects 130,737,840.26 20.02
Total 653,207,986.66 100
Source: Computed from Gombe State and NPC CPRP documents
The table 4.18 shows the categorization of the expenditures on the Gombe CPRP micro
projects into the three main sectors. Of the total resources expended on the micro projects, the
sum of N499,208,397.66 or 76.42 percent was spent on provision of social services related
micro projects while the economic sector projects took only N23,261.748.74 or 3.56 percent. The
share of expenditure on infrastructure sector micro projects amounted to N130,737,840.26
representing 20.02 percent. As depicted by the table, more funds were expended on the social
services sector projects than the economic and infrastructure sectors. The total expenditure
pattern correlated with the total number of projects in each group as in table 4.17 and even partly
related to mean costs of the social services projects represented by health sector projects mean
costs in table 4.16.
Table 4.19 Mean Expenditure on Micro Projects Categorized into Main Sectors
Main Sector Amount (N) Percentage (%)
Social Services Projects 2,936,519.99 36.98
Economic Sectors Projects 2,584,638.75 32.54
Infrastructure Sector Projects 2,421,071.12 30.48
Total 7,942,229.86 100
Source: Computed from Gombe State and NPC CPRP documents
![Page 92: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/92.jpg)
84
The table 4.19 shows the mean expenditure on micro projects categorized into main
sectors namely the Social Service sector projects, Economic sector projects and Infrastructure
sector projects. The table shows that the most expensive micro projects are the ones implemented
under the Social Services sector which averaged N2,936,519.99 while the cheapest were the
projects of Infrastructure sector at a mean cost of N2,421,071.12. The mean cost of the
Economic sector projects as shown on the table amounts to N2,584,638.75. The mean cost of the
social services sector projects as well as the number of the projects executed in the sector may
have attributed to the more money expended on the sector as found in table 4.18. Also, the cost
of equipping and furnishing the social services micro projects could increase the unit costs of the
sector micro projects.
Table 4.20 Approve and Completed Micro Projects
Sub Sectors Total Micro
Projects
Approved
No. of Micro
Projects
Completed
Completion
Percentage
(%)
Education 133 133 100
Health 36 36 100
Skill Acquisition/ Civic/Computer Centre 5 5 100
Water 30 30 100
Power (Electricity) 4 4 100
Environment (Sanitation) 1 1 100
Roads & Culverts 19 19 100
Markets 4 4 100
Others (Orphanage) 1 1 100
Total 233 233 100
Source: Computed from Gombe State and NPC CPRP documents
![Page 93: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/93.jpg)
85
The table 4.20 shows the sub-sectoral distribution of the approved and completed projects
in the Gombe State CPRP. The table showed that all the 233 micro projects approved for the
communities for implementation by the Gombe CPRP Agency were fully implemented. There is
no sector where a project is still ongoing. The researcher attempted to find out why the CPRP
was able to complete all the approved projects in the State. The result of the oral interview
conducted revealed that the decision to implement any project was taken by the communities in a
demand driven manner and the projects were bank rolled in three tranches in the ratio 40 : 30 :
30 with little demonstration of counterpart contribution by the beneficiary communities. The
counterpart contributions have been made easier for the communities by the monetization of the
in-kind contributions to cash.
Table 4.21 Distribution of Completed Micro Projects put into use
Sub Sectors No. of Micro
Projects
Completed
No. of Micro
Projects in
Use
Proportion
in Use in
Percent
(%)
Education 133 133 100
Health 36 35 97.22
Skill Acquisition/ Civic/Computer Centre 5 5 100
Water 30 29 96.67
Power (Electricity) 4 4 100
Environment (Sanitation) 1 1 100
Roads & Culverts 19 18 94.74
Markets 4 4 100
Others (Orphanage) 1 1 100
Total 233 230 98.71
Source: Computed from Gombe State and NPC CPRP documents
The table 4.21 shows the number of micro projects put into use vis a vis the completed
projects. As the table portrayed, of the 233 micro projects completed by the Gombe State CPRP
![Page 94: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/94.jpg)
86
Agency, 230 of them representing 98.71 percent have been put into use by the beneficiary
communities. The implication of this is 230 communities have accessed the various micro
projects implemented by the CPRP Agency to reduce the poverty of the rural people. From the
table, 1No. project each from the Health, Water and Roads/Culverts were not put into use
immediately. The researcher attempted to ascertain why a project which had been completed was
not put into use. The response from the respondents revealed that the delay in the use of the
Health project was occasioned by the delay of the Local Government Council to post or deploy
skilled staff to man the project. Although, the project has eventually become operational, it
however took more time than similar projects. Further revelation from the respondents in the oral
interview pointed to the fact that the Local Government was not carried along in the
implementation of the project and as a result, the required manpower plan for the Local
Government did not accommodate the community health project. This of course is a serious
challenge for communities which are very remote and require some kind of inducements to
attract staff to go on posting to such areas. On the issue of the Water project, the researcher was
informed that initially when the borehole was drilled as the installation of the overhead tanks and
reticulation to some points, the water was running and that after a while, the water seized. This
problem is associated with the water level which is also common in other parts of Nigeria and
not necessarily the failure of the CPRP. The road project was a bridge and it was washed away
not long after it was completed when a serious down poor led to the overflowing of a nearby
river which broke down the bridge.
![Page 95: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/95.jpg)
87
Table 4.22 Abandoned or Uncompleted CPRP Projects
Sub-Sectors Total Micro
Projects
Approved
No. of Micro
Projects
Abandoned or
Uncompleted
Percentage
(%)
Education 133 0 0
Health 36 0 0
Skill Acquisition/ Civic/Computer Centre 5 0 0
Water 30 0 0
Power (Electricity) 4 0 0
Environment (Sanitation) 1 0 0
Roads & Culverts 19 0 0
Markets 4 0 0
Others (Orphanage) 1 0 0
Total 233 0 0
Source: Computed from Gombe State and NPC CPRP documents
Table 4.22 shows the uncompleted or abandoned projects in the Gombe State CPRP. The
above table depicted that there is no micro project that was approved for implementation that has
been stalled or abandoned in Gombe State. All the 233 approved micro projects have been
completed. The projects are being used by the beneficiary communities to alleviate whatever
type of poverty that was identified by the community. That there is no abandoned project also
shows the efficacy of the CPRP strategy in tackling poverty in Nigeria. The researcher however
sought opinion of some beneficiary why the projects were not abandoned. The result of the oral
interview also attributed it to regular release of funds by the CPRP Agency, commitment by the
PIC members and the transparent management of resources by both the PIC members and
Gombe CPRP staff. They also confirmed that training received by the PIC members helped the
community in the implementation process.
![Page 96: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/96.jpg)
88
4.3 Data Presentation and Analysis for Osun State
Table 4.23 Funding of Osun State CPRP
Source Amount (N) Percentage (%)
African Development Bank (ADB) 738,928,801.01 92.85
Osun State Government 52,059,942.75 6.54
Miscellaneous Income 4,845,246.52 0.61
Total 795,833,990.28 100
Source: Compiled from Osun State and NPC CPRP documents
The table 4.23 above shows the sources of funds for Osun State Community based
Poverty Reduction Project (CPRP). The total funds accessed for financing of the activities of
CPRP in Osun State amounted to N795,833,990.28. This is N204,166,009.72 or 20.42 percent
less than one billion naira mark. Of the total funds mobilized, the African Development Bank
(ADB) alone provided the sum of N738,928,801.01 or 92.85 percent, while the Osun State
Government provided the sum of N52,059,942.75 or 6.54 percent. The miscellaneous sources
which comprised interest payments and other charges amounted to N4,845,246.52 or 0.61
percent. The researcher also attempted to find out why the counterpart contribution from
beneficiary communities of the micro projects/sub projects which originally as clearly stated in
the project document were to contribute equivalent 10 percent of the project cost as counterpart
contribution in cash or in kind. The oral interview conducted among the staff of the Osun State
CPRP Agency disclosed that the contributions by the beneficiary communities are not part of
disbursements made by the State CPRP Agency and therefore not an ADB component of funds.
The responses also confirmed that community contributions are paid directly by the Project
Implementing Committee (PIC) into the community project account which is managed directly
![Page 97: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/97.jpg)
89
by the community, thus alluding to the demand driven qualities of the project. Similarly, the
share of the contribution by the ADB – 92.85 percent justifies the ascribing of the project as
ADB – Assisted Project. The oral interview also revealed that the management of the project
funds directly by the beneficiary communities is an inbuilt plan to help in the building of the
capacity of the rural communities to be able to handle the implementation of the micro
projects/sub projects at the community level.
Table 4.24 Utilization of Funds
Activity Amount (N) Percentage (%)
Expenditure on Goods 9,237,715.00 1.16
Expenditure on Services 26,976,243.00 3.40
Micro Projects/Sub Projects 627,692,525.48 79.03
Operating Costs 130,290,560.04 16.41
Total Expenditure 794,197,043.52 100
Note: Unspent Balance = N1,636,946.76
Source: Compiled from Osun State and NPC CPRP documents
The table 4.24 shows the utilization of the mobilized funds by the Osun State Social Fund
Agency – the CPRP. The Osun State CPRP sent a total of N794,197,043.52 out of the total
mobilized funds of N795,833,990.28 with an unspent balance of N1,636,946.76 or 0.21 percent.
As depicted from the table, the funds were expended on procurement of goods, services,
implementation of micro projects/sub projects at the community levels and operating costs. The
share of the expenditures on goods is 1.16 percent or N9,237,715.00 while that on services
(including training/workshops) amounted to N26,976,243.00 or 3.40 percent. The expenditures
on micro projects and operating costs amounts respectively to N627,692,525.48 or 79.03 percent
![Page 98: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/98.jpg)
90
and N130,290,560.04 or 16.41 percent. As with the case of international best practices, the tabled
exhibited some credible performance. The operating costs component of expenditure is 16.41
percent which is 3.59 percent less than the internationally recommended figure of 20% of total
project cost. The oral interview conducted by the researcher regarding the payment of salaries of
staff revealed that salaries and wages as well as other sundry expenditures benefited from the
operating costs components. The highest proportion of the expenditure was on the
implementation of micro projects/sub projects and this also reveals some prudence on the side of
the Agency in the management of the project funds. On the curiosity of the researcher regarding
the unspent balance while other communities could have used it for any project, it was disclosed
that the money could not be used to fund any activity at that time because it was against the rule
to continue spending if the project implementation has been closed. This thus implied that the
communities or the Agency cannot access the fund after project has closed.
Table 4.25 Implementation of Micro Projects/Sub-Projects
Sub-Sectors No. of Micro Projects
Implemented
Percentage
(%)
Education 48 21.43
Health 17 7.59
Skill Acquisition/ Civic/Computer Centre 8 3.57
Water 72 32.14
Power (Electricity) 44 19.64
Environment (Sanitation) 1 0.45
Roads & Culverts 15 6.70
Markets 13 5.80
Others (Cassava Storage/Processing skill Unit) 6 2.68
Total 224 100
Source: Computed from Osun State and NPC CPRP documents
![Page 99: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/99.jpg)
91
The table 4.25 table showed the sectoral implementation of the micro projects/sub
projects in Osun State. As depicted on the table, the State implemented a total of 224 micro
projects/sub projects with the total amount of N627,692,525.48 as indicated in table 4.24. The
Water sub sector had the highest number of micro projects with a total of 72 projects
representing 32.14 percent. The next projects demanded in the State are the Education and
Power/Electricity sector projects with total of 48 projects representing 21.43 and 44 projects
representing 19.64 percent respectively. The Health sector projects executed were 17
representing 7.59 percent while Road projects were 15 representing 6.70 percent, Market
projects were 13 representing 5.80 percent, Skills acquisition projects were 8 representing 3.57
percent while the Cassava storage/processing skill units had 6 projects representing 2.68 percent.
The least sector project demanded in Osun State was the Environment/Sanitation sub sector with
only 1No. project representing 0.45 percent. As usual, the researcher attempted to find out the
preference for water micro projects in Osun State. The oral interview with some respondents in
the beneficiary communities revealed that most of the remote communities actually lacked
portable water and that probably may have led to the high demand for water in the state.
Similarly, some respondents from the visited communities which implemented education
projects informed the researcher in an oral interview that they want to decongest the classroom
and improve the quality of education of their children hence their preference for education
projects.
![Page 100: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/100.jpg)
92
Table 4.26 Total Expenditure on Sub Sectors
Sub-Sectors Amount (N) Percentage
(%)
Education 137,305,059.43 21.87
Health 50,404,475.24 8.03
Skill Acquisition/ Civic/Computer Centre 28,707,838.06 4.57
Water 154,999,998.10 24.69
Power (Electricity) 143,788,610.50 22.91
Environment (Sanitation) 7,763,855.00 1.24
Roads & Culverts 43,949,445.05 7.01
Markets 42,323,244.10 6.74
Others (Cassava Storage/Processing skill Unit) 18,450,000.00 2.94
Total 627,692,525.48 100
Source: Computed from Osun State and NPC CPRP documents
The table 4.26 shows total expenditure on micro projects for each sub sectors for Osun
State. As depicted on the table, total amount of money expended on implementation of micro
projects/sub projects in Osun State amounted to N627,692,525.48. This is made up of the total
expenditure on Education amounting N137,305,059.43 representing 26.87 percent, Health
projects amounting N50,404,475.24 representing 8.03 percent, Rural roads projects amounting
N43,949,445.05 representing 7.01 percent, Water micro projects amounting to N154,999,998.10
representing 24.69 percent, Power/Electricity projects amounting N143,788,610.50 representing
22.91 percent, Skills Acquisition/Civic/Computer centre micro projects amounting
N28,707,838.06 representing 4.57 percent. The expenditure on Market and Cassava
Storage/Processing Skill unit amounted to N42,323,244.10 or 6.74 percent and N18,450,000.00
![Page 101: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/101.jpg)
93
or 2.74 percent respectively. The least expenditure is on Environment/Sanitation with the total
amount of N7,763,855.00 representing 1.24 percent of the total expenditures on micro projects.
The researcher equally attempted to find out the amount contributed by the communities for each
sub sector of the project with a view to ascertaining the real cost to them. The oral interview
conducted on the respondents however revealed that the contributions by the communities were
either in cash or kind and expended by the community directly without it being remitted to the
CPRP Agency. The amounts shown on the table is the share of the contributions by the ADB and
State Government counterpart contributions. The Education, Water and Power/Electricity sub
sectors alone consumed a total of 69.47 percent of the total expenditure. The researcher was
curious regarding the issue of gender in implementing projects. The respondents at one of the
cassava storage/processing skill unit revealed that the project was designed to empower women
and that since the project was put into use, it has been spinning money for women. Again, this
affirmed the CPRP as a good strategy for poverty reduction by enhancing the income earning
capacity of the rural women of the affected communities.
Table 4.27 Mean Cost of Micro Projects in each Sub-Sectors
Sub-Sectors Amount (N) Percentage
(%)
Education 2,860,522.07 8.98
Health 2,964,969.13 9.31
Skill Acquisition/ Civic/Computer Centre 3,588,479.76 11.26
Water 2,152,777.75 6.76
Power (Electricity) 3,267,922.97 10.25
Environment (Sanitation) 7,763,855.00 24.37
Roads & Culverts 2,929,963.00 9.20
Markets 3,255,634.16 10.22
Others (Cassava Storage/Processing skill Unit) 3,075,000.00 9.65
Total 31,859,123.84 100
Source: Computed from Osun State and NPC CPRP documents
![Page 102: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/102.jpg)
94
The table 4.27 shows the mean cost of implementing the micro projects/sub projects in
each of the sub sectors in osun State. The average cost of the micro projects in Osun State is
N2,802,198.77. From the table, the least cost sub sector micro projects are those of the Water
micro projects with a mean cost of N2,152,777.75, Education projects with a mean cost of
N2,860,522.07, Roads projects with a mean cost of N2,929,963.00 and Health with a mean cost
of N2,964,969.13. The most expensive projects are the micro projects implemented under the
Environment/Sanitation with a mean cost of N7,763,855.00, Skills Acquisition/Civic/Computer
Centre with a mean cost of N3,588,479.76, Power/Electricity with a mean cost of
N3,267,922.97, Markets projects with a mean cost of N3,255,634.16 and the Cassava Storage
and Processing with a mean cost of N3,075,000.00 The researcher attempted to find out the
justification for implementation of just 1No. Environment/Sanitation project which gulped as
much as more than thrice the cost of the least mean cost project – Water. The oral interview
conducted on the respondents revealed that erosion menace grounded the economic life of the
people and the implementation of the project was a choice for economic rescue.
Table 4.28 Categorization of the Implementation of Micro Projects into Main Sectors
Main Sector No. of Micro Projects
Implemented
Percentage (%)
Social Services Projects 65 29.02
Economic Sectors Projects 27 12.05
Infrastructure Sector Projects 132 58.93
Total 224 100
Source: Computed from Osun State and NPC CPRP documents
The table 4.28 shows the categorization of the implementation of micro projects in Osun
State into main sectors. In line with the National Planning Commission (NPC) the researcher
![Page 103: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/103.jpg)
95
grouped the CPRP micro projects into three main sectors namely Social Service sector projects,
Economic Sector Projects and Infrastructure Sector projects. From the table, of the 224 micro
projects implemented at Osun State, 65 of them representing 29.02 percent was implemented
from the Social Services while 27 or 12.05 percent and 132 or 58.93 percent were from the
Economic and Infrastructure sectors respectively. The Osun State from the table have preference
for the Infrastructure sector projects which include Power/Electricity, Water,
Environment/Sanitation and Roads projects than the Economic and Social Service sector
projects. The Economic sector projects included Skill Acquisition Centres/Civic/Computer
Centre, Cassava Storage/Processing Skill Unit and Markets while the Social Service projects
include Education and Health. The high number of projects implemented from the Infrastructure
sectors is an indication of the area of challenge facing the Osun State. Beside the general
deterioration of infrastructure in Nigeria, Osun State is among the new generation rural states
grappling with renewed vigour for rapid infrastructural development.
Table 4.29 Categorization of the Expenditures on Micro Projects into Main Sectors
Main Sector Amount (N) Percentage (%)
Social Services Projects 187,709,534.67 29.91
Economic Sectors Projects 86,459,244.10 13.77
Infrastructure Sector Projects 353,523,746.71 56.32
Total 627,692,525.48 100
Source: Computed from Osun State and NPC CPRP documents
The table 4.29 shows the categorization of the expenditures on the Osun CPRP micro
projects into the three main sectors. Of the total resources expended on the micro projects, the
sum of N187,709,534.67 or 29.91 percent was spent on provision of social services related
micro projects while the economic sector projects shared N86,459.244.10 or 13.77 percent. The
![Page 104: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/104.jpg)
96
share of expenditure on infrastructure sector micro projects amounted to N353,523,746.71
representing 56.32 percent. As depicted by the table, more funds were expended on the
Infrastructure sector projects than the economic and Social Services sectors put together. The
total expenditure pattern also correlated with the preference sector of the State as obtainable in
the total number of projects in each group as in table 4.28.
Table 4.30 Mean Expenditure on Micro Projects Categorized into Main Sectors
Main Sector Amount (N) Percentage (%)
Social Services Projects 2,887,838.99 32.94
Economic Sectors Projects 3,202,194.23 36.52
Infrastructure Sector Projects 2,678,210.20 30.54
Total 8,768,243.42 100
Source: Computed from Osun State and NPC CPRP documents
The table 4.30 shows the mean expenditure on micro projects categorized into main
sectors namely the Social Service sector projects, Economic sector projects and Infrastructure
sector projects. The table shows that the most expensive micro projects are the ones implemented
under the Economic sector which averaged N3,202,194.23 while the cheapest were the projects
of Infrastructure sector at a mean cost of N2,678,210.20. The mean cost of the Social service
sector projects as shown on the table amounts to N2,887,838.99. The cost of equipping the
economic projects may have suggested to the high mean cost of the sector.
![Page 105: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/105.jpg)
97
Table 4.31 Approved and Completed Micro Projects by Osun CPRP
Sub Sectors Total Micro
Projects
Approved
No. of Micro
Projects
Completed
Completion
Percentage
(%)
Education 48 48 100
Health 17 17 100
Skill Acquisition/ Civic/Computer Centre 8 8 100
Water 72 72 100
Power (Electricity) 44 44 100
Environment (Sanitation) 1 1 100
Roads & Culverts 15 15 100
Markets 13 13 100
Others (Cassava Storage/Processing skill
Unit)
6 6 100
Total 224 224 100
Source: Computed from Osun State and NPC CPRP documents
The table 4.31 shows the sub sectoral distribution of the approved and completed projects
in the Osun State CPRP. The table showed that all the 244 micro projects approved for the
communities for implementation by the Osun CPRP Agency were fully implemented. There is
no sector where a project is still ongoing. The researcher attempted to find out why the CPRP
was able to complete all the approved projects in the State. The result of the oral interview
conducted revealed that the Communities unanimously decided to implement their projects in a
demand driven manner. The approved projects were funded adequately after appropriate desk
and field appraisals in three tranches in the ratio 40 : 30 : 30 with counterpart contribution by the
![Page 106: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/106.jpg)
98
beneficiary communities. The counterpart contributions have been made easier for the
communities by the monetization of the in-kind contributions to cash.
Table 4.32 Distribution of Completed Micro Projects put into use
Sub Sectors No. of Micro
Projects
Completed
No. of Micro
Projects in
Use
Proportion
in Use in
Percent
(%)
Education 48 48 100
Health 17 17 100
Skill Acquisition/ Civic/Computer Centre 8 8 100
Water 72 72 100
Power (Electricity) 44 44 100
Environment (Sanitation) 1 1 100
Roads & Culverts 15 15 100
Markets 13 13 100
Others (Cassava Storage/Processing skill
Unit)
6 6 100
Total 224 224 100
Source: Computed from Osun State and NPC CPRP documents
The table 4.32 shows the number of micro projects put into use vis-a-vis the completed
projects. As the table portrayed, all the 224 micro projects completed by the Osun State CPRP
Agency have been put into use by the beneficiary communities. The implication of this is that
224 communities have accessed the various micro projects implemented by the CPRP Agency to
reduce the poverty of the rural people.
![Page 107: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/107.jpg)
99
Table 4.33 Abandoned or Uncompleted CPRP Micro Projects/Sub-Projects
Sub-Sectors Total Micro
Projects
Approved
No. of Micro
Projects
Abandoned or
Uncompleted
Percentage
(%)
Education 48 0 0
Health 17 0 0
Skill Acquisition/ Civic/Computer Centre 8 0 0
Water 72 0 0
Power (Electricity) 44 0 0
Environment (Sanitation) 1 0 0
Roads & Culverts 15 0 0
Markets 13 0 0
Others (Cassava Storage/Processing skill Unit)
6 0 0
Total 224 0 0
Source: Computed from Osun State and NPC CPRP documents
Table 4.22 shows the uncompleted or abandoned projects in the Osun State CPRP. The
above table depicted that there is no micro project that was approved for implementation that has
been stalled or abandoned in Osun State. All the 224 approved micro projects have been
completed. The projects are being used by the beneficiary communities to alleviate whatever
type of poverty that was identified by them. That there is no abandoned project in Osun state
equally indicates the efficacy of the CPRP strategy in tackling poverty in Nigeria. The researcher
however sought opinion of some beneficiary why the projects were not abandoned. The result of
the oral interview also attributed it to regular release of funds by the CPRP Agency, commitment
by the PIC members and the transparent management of resources by both the PIC members and
![Page 108: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/108.jpg)
100
the Osun CPRP staff. The respondents also commended the Osun state government which
allowed the Agency free hand to operate. It was also confirmed that training received by the PIC
members equally helped the community in the implementation process.
4.4 Data Presentation and Analysis for Zamfara State
Table 4.34 Funding of Zamfara State CPRP
Source Amount (N) Percentage (%)
African Development Bank (ADB) 812,081,499.58 91.36
zamfara State Government 70,028,769.41 7.88
Miscellaneous Income 6,797,460.96 0.76
Total 888,907,728.95 100
Source: Compiled from Zamfara State and NPC CPRP documents
The table 4.34 shows the sources of funds for Zamfara State Community based Poverty
Reduction Project (CPRP). The total funds accessed for financing the activities of CPRP in
Zamfara State amounted to N888,907,728.95. This is N111,092,271.05 or 11.11 percent less than
one billion naira mark. Of the total funds mobilized, the African Development Bank (ADB)
alone provided the sum of N812,081,499.58 or 91.36 percent, while the Zamfara State
Government provided the sum of N70,028,769.41 or 7.88 percent. The miscellaneous sources
which comprised interest payments and other charges amounted to N6,797,460.96 or 0.76
percent. The researcher also attempted to find out why the counterpart contribution from
beneficiary communities of the micro projects/sub projects which originally as clearly stated in
the project document were to contribute equivalent 10 percent of the project cost as counterpart
contribution in cash or kind. The oral interview conducted among the staff of the Zamfara State
CPRP Agency disclosed that the contributions by the beneficiary communities are not part of
disbursements made by the State CPRP Agency and therefore not an ADB component of funds.
The responses also confirmed that community contributions are paid directly by the Project
![Page 109: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/109.jpg)
101
Implementing Committee (PIC) into the community project account which is managed directly
by the community, thus alluding to the demand driven nature of the project. Similarly, the share
of the contribution by the ADB – 91.36 percent justifies the ascribing of the project as ADB –
Assisted Project. The oral interview also revealed that the management of the project funds
directly by the beneficiary communities is an inbuilt plan to help in the building of the capacity
of the rural communities to be able to handle the implementation of the micro projects/sub
projects at the community level.
Table 4.35 Utilization of Funds
Activity Amount (N) Percentage (%)
Fixed Asset 15,253,753.00 1.72
Training/Workshops 39,532,288.09 4.45
Micro Projects/Sub Projects 720,702,579.31 81.08
Operating Costs 113,419,108.55 12.75
Total Expenditure 888,907,728.95 100
Source: Compiled from Zamfara State and NPC CPRP documents
The table 4.35 shows the utilization of the mobilized funds by the Zamfara State Social
Fund Agency-the CPRP. As depicted from the table, the funds was expended on procurement of
fixed assets, training and workshops for Agency staff and Project Implementing Committee
members, implementation of micro projects/sub projects at the community levels and operating
costs. The share of the expenditures on fixed assets is 1.72 percent or N15,253,753.00 while that
on training/workshops amounted to N39,532,288.09 or 4.45 percent. The expenditures on micro
projects and operating costs amounts respectively to N720,702,579.31 or 81.08 percent and
N113,419,108.55 or 12.75 percent. Again, the performance of this table is very interesting and
![Page 110: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/110.jpg)
102
worthy of note for project management. The operating or administrative costs of projects did not
exceed 20 percent of the total funds. This ceiling is the international best practice for project
management. In the case of the Zamfara State CPRP, this component took only 12.75 percent
which is very reasonable. In fact, all other costs components consisting of fixed assets,
training/workshop and the operating costs shared a total of 18.92 percent of the total
expenditure/fund. The oral interview also revealed that salaries and wages as well as other
sundry expenditures benefited from the operating costs components. The highest proportion of
the expenditure was on the implementation of micro projects/sub projects and this also reveals
some prudence on the side of the Agency in the management of the project funds.
Table 4.36 Implementation of Micro Projects/sub projects
Sub-Sectors No. of Micro Projects
Implemented
Percentage (%)
Education 166 65.10
Health 12 4.70
Skill Acquisition/ Civic/Computer Centre 23 9.02
Water 28 10.98
Power (Electricity) 5 1.96
Environment (Sanitation) 12 4.70
Roads & Culverts 8 3.15
Markets 0 0.00
Others (Transport) 1 0.39
Total 255 100
Source: Computed from Zamfara State and NPC CPRP documents
![Page 111: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/111.jpg)
103
The table 4.36 table showed the sectoral implementation of the micro projects/sub
projects by the Zamfara State CPRP. The table showed that a total of 255 micro projects/sub
projects were executed or implemented in Zamfara State with the total amount of
N720,702,579.31 as indicated in table 4.35. The Education sub sector had the highest number of
micro projects with a total of 166 projects representing 65.10 percent. This is more than half the
number of projects executed in the State. The next project in demand in the State is the Water
sector projects with a total of 28 projects representing 10.98 percent. The Skill Acquisition
projects executed were 23 representing 9.02 percent, while Health and Environment/Sanitation
projects were 12 projects each representing 4.70 percent respectively. The Road and
Power/Electricity projects were 8 and 5 projects representing 3.15 percent and 1.96 percent
respectively. As usual, the researcher attempted to find out the preference for Education micro
projects in Zamfara State. The oral interview conducted with some respondents in the beneficiary
communities revealed that most of the remote communities lacked education facilities. The
respondents informed the researcher too their schools classrooms are overcrowded with some
pupils or students seating on the floor to take their lessons. The researcher also observed that the
choice of Education projects more than the other sector projects was for the State to use the
opportunity created by the CPRP to increase opportunities for the state indigenes to earn more
education. It also revealed the growing concern for the Northern States being disadvantaged in
education. Thus, the CPRP is being used too by Zamfara State to address the challenge of
belonging to the so called educationally disadvantaged states. The table also showed the State
preference for Water and Skill Acquisition centres. The oral interview conducted by the
researcher also revealed that Water is of high necessity in the remote communities of Zamfara
State while the demand for Skill Acquisition centres was to help provide skills for the street
![Page 112: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/112.jpg)
104
children popularly referred to as Almajeri in order to take them out of the streets. The objective,
to some extent is being achieved with 28 communities provided good sources of drinking water
and people acquiring skills at the Skill Acquisition centres.
Table 4.37 Total Expenditure on Sub Sectors
Sub-Sectors Amount (N) Percentage (%)
Education 458,630,120.42 63.64
Health 43,029,667.53 5.97
Skill Acquisition/ Civic/Computer Centre 90,331,798.00 12.53
Water 59,525,073.00 8.26
Power (Electricity) 17,687,690.00 2.45
Environment (Sanitation) 17,835,727.30 2.47
Roads & Culverts 32,562,503.06 4.53
Markets 0.00 0.00
Others (Transport) 1,100,000.00 0.15
Total 720,702,579.31 100
Source: Computed from Zamfara State and NPC CPRP documents
The table 4.37 shows total expenditure on micro projects for each sub sectors for Zamfara
State. As the table showed, total amount of money expended on implementation of micro
projects/sub projects in Zamfara State amounted to N720,702,579.31. This is made up of the
total expenditure on Education amounting N458,630,120.42 representing 63.64 percent, Health
projects amounting N43,029,667.53 representing 5.97 percent, Rural roads projects amounting
N32,562,503.06 representing 4.53 percent, Water micro projects amounting to N59,525,073.00
representing 8.26 percent, Power/Electricity projects amounting N17,687,690.00 representing
2.45 percent, Skills Acquisition/Civic/Computer centre micro projects amounting
![Page 113: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/113.jpg)
105
N90,331,798.00 representing 12.53 percent and Environment/Sanitation with N17,835,727.30
representing 2.47 percent of the total expenditures on micro projects. The researcher similarly
attempted to find out the share of the community contributions on the micro projects of each sub
sector with a view to ascertaining the real cost to the communities. The oral interview conducted
on the respondents however revealed that the contributions by the communities were either in
cash or in kind and the communities were directly responsible and not the State CPRP Agency.
The total amount shown on the table is the share of the contributions by the ADB and Zamfara
State Government counterpart contributions. The very huge amount spent on the Education sub
sector which gulped more than half of the total expenditures is a proof and an indication of the
zamfara State people effort to climb the ladder to the educationally advantage states instead of
settling with the educationally disadvantaged state. Also, the expenditure on skill acquisition and
water projects revealed the need of the projects to improve the well being of the people.
Table 4.38 Mean Cost of Micro Projects in each Sub Sectors
Sub-Sectors Amount (N) Percentage (%)
Education 2,762,832.05 12.23
Health 3,585,805.63 15.87
Skill Acquisition/ Civic/Computer Centre 3,927,469.48 17.38
Water 2,125,895.46 9.41
Power (Electricity) 3,537,538.00 15.65
Environment (Sanitation) 1,486,310.61 6.58
Roads & Culverts 4,070,312.88 18.01
Markets 0.00 0.00
Others (Transport) 1,100,000.00 4.87
Total 22,596,164.11 100
Source: Computed from Zamfara State and NPC CPRP documents
![Page 114: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/114.jpg)
106
The table 4.38 shows the mean cost of implementing the micro projects/sub projects in
each of the sub sectors in Zamfara State. The average cost of the micro projects in Zamfara State
is N2,826,284.62. From the table, the least cost sub sector micro projects are the others
(Transport) with a mean cost of N1,100,000.00, Environment/Sanitation projects with a mean
costs of N1,486,310.61, Water projects with mean cost of N2,125,895.46 and Education projects
with a mean cost of N2,762,832.05. The most expensive projects are the micro projects
implemented under the Roads subsector with a mean cost of N4,070,312.88, Skills
Acquisition/Civic/Computer Centre with a mean cost of N3,927,469.48, Health projects with
mean cost of N3,585,805.63 and Power/Electricity with a mean cost of N3,537,538.00. The
researcher attempted to find out the justification for the high mean cost for road projects. The
oral interview conducted on the respondents revealed that the topography of the communities
involved is very poor and involved construction of culverts which escalated unit costs.
Table 4.39 Categorization of the Implementation of Micro Projects into Main Sectors
Main Sector No. of Micro Projects
Implemented
Percentage (%)
Social Services Projects 178 69.80
Economic Sectors Projects 24 9.42
Infrastructure Sector Projects 53 20.78
Total 255 100
Source: Computed from Zamfara State and NPC CPRP documents
The table 4.39 shows the categorization of the implementation of micro projects in
Zamfara State into main sectors. As with the National Planning Commission (NPC), the
researcher grouped the CPRP micro projects into three main sectors namely Social Service sector
projects, Economic Sector Projects and Infrastructure Sector projects. From the table, of the 255
![Page 115: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/115.jpg)
107
micro projects implemented at the State, 178 of them representing 69.80 percent was
implemented from the Social Services while 24 or 9.42 percent and 53 or 20.73 percent were
from the Economic and Infrastructure sectors respectively. The Zamfara State as can be deduced
from the table had preference for the Social Service sector projects which include Education and
Health projects than the Economic and Infrastructure sector projects. The Economic sector
projects included Skill Acquisition Centres/Civic/Computer Centre and Markets while the
Infrastructure projects include Power/Electricity, Environment/Sanitation, Water and
Road/Culverts. The high number of projects implemented from the Social Services is an
indication of the efforts of Zamfara State to improve on the Human Development Index (HDI) of
the state. The performance on the infrastructure is to help advance the economic well being of
the people.
Table 4.40 Categorization of the Expenditures on Micro Projects into Main Sectors
Main Sector Amount (N) Percentage (%)
Social Services Projects 501,659,787.95 69.61
Economic Sectors Projects 91,431,798.00 12.69
Infrastructure Sector Projects 127,610,993.36 17.70
Total 720,702,579.31 100
Source: Computed from Zamfara State and NPC CPRP documents
The table 4.40 shows the categorization of the expenditures of the Zamfara State CPRP
micro projects into the three main sectors. Of the total resources expended on the micro projects,
the sum of N510,659,787.95 or 69.61 percent was spent on provision of social services related
micro projects while the economic sector projects had a total of N91,431.789.00 or 12.69
percent. The share of expenditure on infrastructure sector micro projects amounted to
N127,610,993.36 representing 17.70 percent. As depicted by the table, more funds were
![Page 116: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/116.jpg)
108
expended on the social services sector projects than the economic and infrastructure sectors add
together. The total expenditure pattern correlated with the total number of projects in each group
as in table 4.39.
Table 4.41 Mean Expenditure on Micro Projects Categorized into Main Sectors
Main Sector Amount (N) Percentage (%)
Social Services Projects 2,818,313.41 31.19
Economic Sectors Projects 3,809,658.25 42.16
Infrastructure Sector Projects 2,407,754.59 26.65
Total 9,035,726.25 100
Source: Computed from Zamfara State and NPC CPRP documents
The table 4.41 shows the mean expenditure on micro projects categorized into main
sectors namely the Social Service sector projects, Economic sector projects and Infrastructure
sector projects. The table shows that the most expensive micro projects are the ones implemented
under the Economic sector which averaged N3,809,658.25 while the cheapest were the projects
of Infrastructure sector at a mean cost of N2,407,754.59. The mean cost of the Social service
sector projects as shown on the table amounts to N2,818,313.41. The cost of equipping the
economic projects may have suggested to the high mean cost of the sector.
![Page 117: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/117.jpg)
109
Table 4.42 Approved and Completed Micro Projects by Zamfara CPRP
Sub-Sectors Total Micro
Projects
Approved
No. of Micro
Projects
Completed
Completion
Percentage
(%)
Education 166 166 100
Health 12 12 100
Skill Acquisition/ Civic/Computer Centre 23 23 100
Water 28 28 100
Power (Electricity) 5 5 100
Environment (Sanitation) 12 12 100
Roads & Culverts 8 8 100
Markets 0 0 NA
Others (Transport) 1 1 100
Total 255 255 100
Source: Computed from Zamfara State and NPC CPRP documents
The table 4.42 shows the sub sectoral distribution of the approved and completed projects
in the Zamfara State CPRP. The table showed that all the 255 micro projects approved for the
communities for implementation by the Osun CPRP Agency were fully implemented. There is
no sector where a project is still ongoing. The researcher attempted to find out why the CPRP
was able to complete all the approved projects in the State. The result of the oral interview
conducted also revealed similar positions that the Communities selected their projects for
implementation in a demand driven manner. The approved projects were funded adequately after
appropriate desk and field appraisals in three tranches in the ratio 40 : 30 : 30 with counterpart
contribution by the beneficiary communities. The counterpart contributions have also been made
easier for the communities by the monetization of the contributions in kind to cash.
![Page 118: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/118.jpg)
110
Table 4.43 Distribution of Completed Micro Projects in use
Sub-Sectors No. of Micro
Projects
Completed
No. of Micro
Projects in
Use
Proportion
in Use in
Percent
(%)
Education 166 165 99.40
Health 12 10 83.33
Skill Acquisition/ Civic/Computer Centre 23 23 100
Water 28 27 96.43
Power (Electricity) 5 5 100
Environment (Sanitation) 12 12 100
Roads & Culverts 8 8 100
Markets 0 0 NA
Others (Transport) 1 1 100
Total 255 251 98.43
Source: Computed from Zamfara State and NPC CPRP documents
The table 4.43 shows the number of micro projects put into use vis-a-vis the completed
projects. As the table portrayed, of the 255 micro projects completed by the Zamfara State CPRP
Agency, 251 of them representing 98.43 percent have been put into use by the beneficiary
communities. The implication of this is that 251 communities in Zamfara State have accessed the
various micro projects implemented by the CPRP Agency to reduce the poverty of the rural
people. From the table No. 1 Education project, 2 Nos. from Health and 1 No. from Water
projects were not put into use immediately. The researcher attempted to ascertain why the
projects were not put into use after it had been completed. The response from the respondents
revealed that the delay in the use of the Health projects was occasioned by the delay of the Local
Government Council to deploy skilled manpower to the two projects. Although, the projects
have eventually become operational, it however took more time than similar projects. Further
revelation from the respondents in the oral interview pointed to the fact that the Local
![Page 119: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/119.jpg)
111
Government was aware of the project but did not have the necessary skilled manpower at the
time of the completion. On the issue of the Water project, the researcher was informed that that
the tap became dry after it had served for sometimes. This problem is associated with the water
level which is also common in other parts of Nigeria and not necessarily the failure of the CPRP.
The plan is to drill the borehole at another site with government resources since the CPRP has
closed. The Education project was a school laboratory which was not put into use initially
because of lack of science teachers. The researcher was however informed that the School has
secured the services of Youth Corp members who now make use of the laboratory.
Table 4.44 Abandoned or Uncompleted CPRP Projects
Sub-Sectors Total Micro
Projects
Approved
No. of Micro
Projects
Abandoned or
Uncompleted
Percentage
(%)
Education 166 0 0
Health 12 0 0
Skill Acquisition/ Civic/Computer Centre 23 0 0
Water 28 0 0
Power (Electricity) 5 0 0
Environment (Sanitation) 12 0 0
Roads & Culverts 8 0 0
Markets 0 0 0
Others (Transport) 1 0 0
Total 255 0 0
Source: Computed from Zamfara State and NPC CPRP documents
![Page 120: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/120.jpg)
112
Table 4.44 shows the uncompleted or abandoned projects in the Zamfara State CPRP.
The above table depicted that there is no micro project that was approved for implementation
that has been stalled or abandoned in Zamfara State. All the 255 approved micro projects have
been completed. The projects are being used by the beneficiary communities to alleviate
whatever type of poverty that was identified by them. That there is no abandoned project in
Zamafara state, again confirmed the efficacy of the CPRP strategy in tackling poverty in Nigeria.
The researcher also sought opinion of some beneficiary why the projects were not abandoned.
The result of the oral interview also attributed it to regular release of funds by the CPRP Agency,
commitment by the PIC members and the transparent management of resources by both the PIC
members and the Zamfara State CPRP staff.
Hypothesis One: Community-Based Poverty Reduction Project (CPRP) has not reduced poverty
rate in the states where it is piloted.
Hypothesis Two: Effective implementation strategies have not been adopted by Community-
Based Poverty Reduction Project (CPRP) in achieving its mandates in reducing poverty in the
states where it is piloted.
Hypothesis Three: Poor funding and unintended beneficiaries due to corruption are key problems
affecting the CPRP programmes in the states where it is piloted.
Test of Hypotheses
The researcher made some assumptions in the stating of the hypotheses for this study.
These assumptions will now be subjected to chi-square test. The result of the test is expected to
further certify the analysis carried out in the previous section and affirm the findings. Three
hypotheses were formulated by the researcher for the study. These hypotheses will be tested
![Page 121: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/121.jpg)
113
using 5% level of significance to ascertain their validity or otherwise. The chi-square formula is
stated thus:
Chi-Square:
X2 = ∑ Oij − Eij Eji Where Oij = number observed in the ith row and jth column
Eij = number expected in the cell under the null hypothesis. This is obtained with the formula: Eij = Ai x Bj
N Where Ai = Marginal row total
Bj = Marginal column total
N = Total number of observations
For the chi-square, we make use of the degree of freedom (df) and the df is obtained with the
formula: df = (r – 1)(c-1) where r = the number of rows and c = number of columns.
Restatement of Hypotheses
The four hypotheses earlier formulated for the study is stated as follows:
� Hypothesis One: Community-Based Poverty Reduction Project (CPRP) has not reduced
poverty rate in the states where it is piloted.
� Hypothesis Two: Effective implementation strategies have not been adopted by
Community-Based Poverty Reduction Project (CPRP) in achieving its mandates in
reducing poverty in the states where it is piloted.
� Hypothesis Three: Poor funding and unintended beneficiaries due to corruption are key
problems affecting the CPRP programmes in the states where it is piloted.
![Page 122: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/122.jpg)
114
Decision Rule
The decision rule is thus: When the calculated value is greater than the critical value i.e
the table value, we reject the hypothesis and accept the hypothesis if otherwise at 5% or 0.05
level of significance.
Research Hypothesis One
Community-Based Poverty Reduction Project (CPRP) has not reduced poverty rate in the states
where it is piloted. In order to test the hypothesis, we combined the analysis of tables 4.3, 4.14,
4.25 and 4.36.
Table 4.45
Implemented Micro Projects by all ADB States
States Edu Health Skills Water Power Env Roads Mkts Others Total
Edo 27 15 49 52 10 1 0 6 0 160
Gombe 133 36 5 30 4 1 19 4 1 233
Osun 48 17 8 72 44 1 15 13 6 224
Zamfara 166 12 23 28 5 12 8 0 1 255
Total 374 80 85 182 63 15 42 23 8 872
Source: Field Work, 2012.
Computation of the expected (e)
e1 = 374x160 = 68.62 872
e2 = 80x160 = 14.68 872
e3 = 85x160 = 15.60 872
e4 = 182x160 = 33.39 872
![Page 123: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/123.jpg)
115
e5 = 63x160 = 11.56 872
e6 = 15x160 = 2.75 872
e7 = 42x160 = 7.71 872
e8 = 23x160 = 4.22 872
e9 = 8x160 = 1.47 872
e10 = 374x233 = 99.93 872
e11 = 80x233 = 21.38 872
e12 = 85x233 = 22.71 872
e13 = 182x233 = 48.63 872
e14 = 63x233 = 16.83 872
e15 = 15x233 = 4.01 872
e16 = 42x233 = 11.22 872
e17 = 23x233 = 6.14 872
e18 = 8x233 = 2.14 872
e19 = 374x224 = 96.07 872
e20 = 80x224 = 20.55 872
e21 = 85x224 = 21.83 872
![Page 124: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/124.jpg)
116
e22 = 182x224 = 46.75 872
e23 = 63x224 = 16.18 872
e24 = 15x224 = 3.85 872
e25 = 42x224 = 10.79 872
e26 = 23x224 = 5.91 872
e27 = 8x224 = 2.05 872
e28 = 374x255 = 109.37 872
e29 = 80x255 = 23.39 872
e30 = 85x255 = 24.86 872
e31 = 182x255 = 53.22 872
e32 = 63x255 = 18.42 872
e33 = 15x255 = 4.39 872
e34 = 42x255 = 12.28 872
e35 = 23x255 = 6.72 872
e36 = 8x255 = 2.34 872
![Page 125: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/125.jpg)
117
Computation of the Chi-Square
o e o – e (o – e)2 (o – e)
2/e
27 68.62 -41.20 1696.44 62.87
15 14.68 0.32 0.102 0.01
49 15.60 33.40 1115.56 71.51
52 33.39 18.61 346.33 10.37
10 11.56 -1.56 2.43 0.21
1 2.75 -1.75 3.0625 1.11
0 7.71 -7.71 59.44 7.71
6 4.22 1.78 3.168 0.75
0 1.47 -1.47 2.1609 1.47
133 99.93 33.07 1093.62 10.94
36 21.38 14.62 213.74 10.00
5 22.71 -17.71 313.644 13.81
30 48.63 -18.63 347.077 7.14
4 16.83 -12.83 164.609 9.78
1 4.01 -3.01 9.06 2.26
19 11.22 7.78 60.53 5.39
4 6.14 -2.14 4.58 0.74
1 2.14 -1.14 1.2996 0.61
48 96.07 -48.07 2310.72 24.05
17 20.55 -3.55 12.6025 0.61
8 21.83 -13.83 191.2689 8.76
72 46.75 25.25 637.5625 13.64
44 16.18 27.82 773.9524 47.83
1 3.85 -2.85 8.1225 2.11
![Page 126: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/126.jpg)
118
15 10.79 4.21 17.7241 1.64
13 5.91 7.09 50.2681 8.50
6 2.05 3.95 15.6025 7.61
166 109.37 56.63 3206.9569 29.32
12 23.39 -11.39 129.7321 5.55
23 24.86 -1.86 3.4596 0.14
28 53.22 -25.22 636.0484 11.95
5 18.42 -13.42 180.0946 9.77
12 4.39 7.61 57.9121 13.19
8 12.28 -4.28 18.3184 1.49
0 6.72 -6.72 45.1584 6.72
1 2.34 -1.34 1.7956 0.7673
Total X2 i.e chi-square calculated is 410.27 410.27
Source: Research Data 2012
The hypothesis shall be tested at 0.05 significant level to find out its correlation with the research
findings. The critical value using the degree of freedom (r – 1)(c – 1) where r which is the
number of row is 4 and c which is the number of column is 9. Thus, the degree of freedom (df)
will be (4 – 1)(9 -1) which is 3x8 = 24. Thus, X2 critical value using the table of sampling
distribution, chi-square for 24 df at 0.05 significant level is 36.415.
Decision Rule: Reject hypothesis if the chi-square calculated is greater than the chi-square
critical value and do not reject if otherwise.
Conclusion:
From the result of the calculation, the value of calculated chi-square (X2) is greater than
the chi-square (X2) critical value. We therefore reject and accept the hypothetical statement that
the Community-Based Poverty Reduction Project (CPRP) has not reduced poverty rate in the
![Page 127: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/127.jpg)
119
states where it is piloted. Judging from the poverty profiles in Nigeria, Edo, Zamfara, Gombe,
and Osun states still have high poverty indices based on human development, unemployment
rate, healthcare, infrastructures, etc. It is the opinion of this study that CPRP has recorded partial
success in reduction of poverty considering the recent statistics released by the Federal Bureau of
Statistics that Nigeria’s poverty rate increased despite the effort by the government. This attracts
questions in the implementation of the programmes, who actually benefit from the programmes
(the societal elites or the those within the poverty line?), achievements and failures of these
programmes, etc.
Research Hypothesis Two
Effective implementation strategies have not been adopted by Community-Based Poverty
Reduction Project (CPRP) in achieving its mandates in reducing poverty in the states where it is
piloted.
We will test this hypothesis using the combination of the following tables 4.6, 4.17, 4.28 and
4.39
Table 4.46 Sectoral Implementation of Micro Projects by the four ADB States
States Social Services
Sector
Economic
Sector
Infrastructure
Sector
Total
Edo 42 55 63 160
Gombe 170 9 54 233
Osun 65 27 132 224
Zamfara 178 24 53 255
Total 455 115 302 872
Source: Research Data 2012
Computation of the expected (e)
e1 = 455x160 = 83.49 872
e2 = 115x160 = 21.10 872
![Page 128: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/128.jpg)
120
e3 = 302x160 = 55.41 872
e4 = 455x233 = 121.58 872
e5 = 115x233 = 30.73 872
e6 = 302x233 = 80.69 872
e7 = 455x224 = 116.88 872
e8 = 115x224 = 29.54 872
e9 = 302x224 = 77.58 872
e10 = 455x255 = 133.06 872
e11 = 115x255 = 33.63 872
e12 = 302x255 = 88.31 872
Computation of the Chi-Square
o e o – e (o – e)2 (o – e)
2/e
42 83.49 -41.49 1721.42 20.62
55 21.10 33.90 1149.21 20.89
63 55.41 7.59 57.6081 1.04
170 121.58 48.42 2344.496 19.28
9 30.73 -21.73 472.1929 15.36
54 80.69 -26.69 712.3561 8.83
![Page 129: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/129.jpg)
121
65 116.88 -51.88 2691.153 23.03
27 29.54 -2.54 6.4516 0.22
132 77.58 54.42 2961.5364 38.17
178 133.06 44.94 2019.6036 15.18
24 33.63 -9.63 92.7369 2.76
53 88.31 -35.31 1246.7691 14.12
Total X2 i.e chi-square calculated is 179.50 179.50
Source: Research Data 2012
We obtain the chi square (X2) critical value using the degree of freedom (r – 1)(c – 1)
where r which is the number of row is 4 and c which is the number of column is 3. Thus, the
degree of freedom (df) will be (4 – 1)(3 -1) which is 3x2 = 6. Thus, X2 critical value using the
table of sampling distribution, chi-square for 6 df at 0.05 significant level is 12.592.
Decision Rule: Reject the hypothesis if the chi-square calculated is greater than the chi-square
critical value and do not reject the hypothesis if otherwise.
Conclusion
From the result of the calculation, the value of calculated chi-square (X2) is greater than the chi-
square (X2) critical value. We therefore accept the hypothetical statement that effective
implementation strategies have not been adopted by Community-Based Poverty Reduction
Project (CPRP) in achieving its mandates in reducing poverty in the states where it is piloted.
Research findings showed that the implementation strategies are not grassroots based and the
coordination of projects as well as funding were not efficient. This finding is truth because
sectoral coverage of CPRP micro projects/sub projects has not enhances the outreach and
![Page 130: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/130.jpg)
122
efficacy of the CPRP model of poverty reduction. Analytically, the implementation of CPRP
micro projects covered the critical sectors of the Nigeria economy namely the social services,
economic and infrastructure. The UN Human Development Index ranked Nigeria as number 158.
If the CPRP model is adopted by legislating on it, the likelihood that the human capital
development for Nigeria would be fast tracked is but this has not materialized. Also, the
importance of the other two sectors to national development cannot be overemphasized. This
explains the why the present Nigeria government considered it necessary to appoint a
coordinating Minister for the Economy in the person of Dr. Ngozi Okonjo-Iweala and
continually emphasizing development of critical infrastructure. However, the spillover effects of
sectoral development needed to speed up the standards of livings are not well harnessed in the
socio-economic projects of the CPRP.
Research Hypothesis Three
Poor funding and unintended beneficiaries due to corruption are key problems affecting the
CPRP programmes in the states where it is piloted.
In order to test the hypothesis, we shall combine the analysis of tables 4.10, 4.21, 4.32 and 4.43.
Table 4.47
Completed Micro Projects put into use by all the four ADB States
States Edu Health Skills Water Power Env Roads Mkts Others Total
Edo 27 15 49 52 10 1 0 6 0 160
Gombe 133 35 5 29 4 1 18 4 1 230
Osun 48 17 8 72 44 1 15 13 6 224
Zamfara 165 10 23 27 5 12 8 0 1 251
Total 373 77 85 180 63 15 41 23 8 865
Source: Research Data 2012
![Page 131: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/131.jpg)
123
Computation of the expected (e)
e1 = 373x160 = 68.99 865
e2 = 77x160 = 14.24 865
e3 = 85x160 = 15.72 865
e4 = 180x160 = 33.29 865
e5 = 63x160 = 11.65 865
e6 = 15x160 = 2.77 865
e7 = 41x160 = 7.58 865
e8 = 23x160 = 4.25 865
e9 = 8x160 = 1.48 865
e10 = 373x230 = 99.18 865
e11 = 77x230 = 20.47 865
e12 = 85x230 = 22.60 865
e13 = 180x230 = 47.86 865
e14 = 63x230 = 16.75 865
e15 = 15x230 = 3.99 865
e16 = 41x230 = 10.90 865
e17 = 23x230 = 6.11 865
![Page 132: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/132.jpg)
124
e18 = 8x230 = 2.13 865
e19 = 373x224 = 96.59 865
e20 = 77x224 = 19.94 865
e21 = 85x224 = 22.01 865
e22 = 180x224 = 46.61 865
e23 = 63x224 = 16.31 865
e24 = 15x224 = 3.88 865
e25 = 41x224 = 10.61 865
e26 = 23x224 = 5.96 865
e27 = 8x224 = 2.07 865
e28 = 373x251 = 108.23 865
e29 = 77x251 = 22.34 865
e30 = 85x251 = 24.66 865
e31 = 180x251 = 52.23 865
e32 = 63x251 = 18.28 865
e33 = 15x251 = 4.35 865
e34 = 41x251 = 11.90 865
![Page 133: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/133.jpg)
125
e35 = 23x251 = 6.67 865
e36 = 8x251 = 2.32 865
Computation of the Chi-Square
o e o – e (o – e)2 (o – e)
2/e
27 68.99 -41.99 1763.16 25.56
15 14.24 0.76 0.5776 0.04
49 15.72 33.28 1107.5584 70.45
52 33.29 18.71 350.0641 10.51
10 11.65 -1.65 2.7225 0.23
1 2.77 -1.77 3.1329 1.13
0 7.58 -7.58 57.4564 7.58
6 4.25 1.75 3.0625 0.72
0 1.48 -1.48 2.1904 1.48
133 99.18 33.82 1143.7924 11.53
35 20.47 14.53 211.1209 10.31
5 22.60 -17.60 309.76 13.71
29 47.86 -18.86 355.6996 7.43
4 16.75 -12.75 162.5625 9.70
1 3.99 -2.99 8.9401 2.24
18 10.90 7.10 50.41 4.62
4 6.11 -2.11 4.4521 0.73
1 2.13 -1.13 1.2769 0.60
48 96.59 -48.59 2360.9881 24.44
17 19.94 -2.94 8.6436 0.43
8 22.01 -14.01 196.2801 8.92
![Page 134: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/134.jpg)
126
72 46.61 25.39 644.6521 13.83
44 16.31 27.69 766.7361 47.01
., 3.88 -2.88 8.2944 2.14
15 10.61 4.39 19.2721 1.82
13 5.96 7.04 49.5616 8/31
6 2.07 3.93 15.4449 7.46
165 108.23 56.77 3222.8329 29.78
10 22.34 -12.34 152.2756 6.82
23 24.66 -1.66 2.7556 0.11
27 52.23 -25.23 636.5529 25.81
5 18.28 -13.28 176.3584 9.65
12 4.35 7.65 58.5225 13.45
8 11.90 -3.90 15.21 1.28
0 6.67 -6.67 44.4889 6.67
1 2.32 -1.32 1.7424 0.75
Total X2 i.e chi-square calculated is 387.25 387.25
Source: Research Data 2012
We obtain the chi square (X2) critical value using the degree of freedom (r – 1)(c – 1)
where r which is the number of row is 4 and c which is the number of column is 9. Thus, the
degree of freedom (df) will be (4 – 1)(9 -1) which is 3x8 = 24. Thus, X2 critical value using the
table of sampling distribution, chi-square for 24 df at 0.05 significant level is 36.415
Decision Rule: Reject hypothesis if the chi-square calculated is greater than the chi-square
critical value and do not reject if otherwise.
![Page 135: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/135.jpg)
127
Conclusion:
From the result of the calculation, the value of calculated chi-square (X2) is greater than
the chi-square (X2) critical value. We therefore reject and accept the hypothetical statement that
poor funding and unintended beneficiaries due to corruption are key problems affecting the
CPRP programmes in the states where it is piloted. Based on the findings of the study especially
from the oral interviews, the researcher found out most projects were allocated and executed
based on political sentiments and not necessarily on the need for poverty reduction. Though
these projects have the tendencies to reduce poverty level of the implementing states but the
issue of actually serving the people was poor as most projects are still fully completed and as a
matter of fact, they still do not serve the purpose in savaging the effects of poverty in the states.
The major reason of most the respondents interviewed by the researcher was mainly on poor or
inadequate funding of projects by the stakeholders (i.e. the federal and state governments as well
as donor agency ADB). This really affected the human and material resources needed to make
the implementation of projects a success.
This study also found out that delay or lack of posting of skilled staff to completed CPRP
projects by the state governments or the Local Government Council did affect the smooth
implementation of the CPRP micro projects/sub projects. The result reinforced the concern
raised by some of the respondents that they were unable to commence immediate use of their
project because they were either waiting for the commissioning of the project by the State
Governor/ high government functionary or as a result of lack of operational manpower. It is
however observed that this kind of delay was common to all the four states except that it was
pronounced in Gombe and Zamfara where some of the Local Government did not cooperate very
well at first. All the projects have eventually been put into use thereby improving the living
conditions of the poor as stated in the objective of the CPRP.
![Page 136: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/136.jpg)
128
CHAPTER FIVE
SUMMARY, CONCLUSION AND RECOMMENDATIONS
5.1 Summary
The research work attempted to study the implementation of poverty reduction strategies in
Nigeria with a particular interest on the implementation of the Community based Poverty
Reduction Project (CPRP). The CPRP is a Community Driven Development (CDD) approach
implemented through social actions and by Social Fund Agencies. This approach to development
had been implemented successfully in Botswana, Malawi, Egypt, China, etc. In order to share
from their experiences, the Nigeria Government piloted the CPRP strategy in 12 states of the
federation. The first 6 states namely Abia, Cross River, Ekiti, Kogi, Yobe and Kebbi were on the
phase 1 of the project and received assistance from the World Bank. The second 6 states
popularly referred to as phase 2 states were made up of Ebonyi, Kwara, Edo, Gombe, Osun and
Zamfara. The World Bank supported two states (Ebonyi and Kwara) in the phase 2 while, the
African Development Bank (ADB) assisted the implementation in the remaining 4 states (Edo,
Gombe, Osun and Zamfara) popularly referred to as ADB-States. The focus of the study is on the
implementation of the CPRP project in the ADB assisted states. In the past, the Government of
Nigeria had adopted different strategies among which were Operation Feed the Nation, DFFRI,
Green Revolution, People’s Bank etc. to address the issue of poverty reduction. In all these
efforts, the desired results were not achieved. However, the CPRP in its case seeks to reduce
poverty using the strategy of making social and economic infrastructure available to the poor.
Thus, the objectives of the CPRP include:
� Promote and strengthen poverty reduction in Nigeria through investments in community
based projects;
![Page 137: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/137.jpg)
129
� Improve the living conditions of the poor through targeted, cost effective, demand driven
and promptly delivered programmes;
� Enhance the capacity of the poor by increasing their participation in decision making and
mobilizing their talents for community development projects; and
� Promote a new approach to development that empowers communities to drive the
process.
In order to achieve these objectives, the government of Nigeria piloted the Community based
Poverty Reduction Project (CPRP) model in the ADB States (Edo, Gombe, Osun and Zamfara)
by the act of the State Houses of Assemblies. The act was to enable the agencies operate
independently without undue interference from the state executives. Each agency is headed by a
General Manager with supports from Project Officers and Assistants, Project Accountants and
Accounts Assistants, among others. The recruitment of the staff was conducted for each state
competitively and independent of the states by the National Planning Commission (NPC) in
collaboration with the African Development Bank (ADB). The ADB provided the fund for the
implementation of the project with a counterpart contribution by the State Governments. Each
community executing a micro project was required to provide an equivalent 10% of the total
cost of the project in the form of counterpart contribution in cash or in kind. This requirement
was not only for participatory purposes but also for the communities themselves to own the
project. Therefore, the broad objective of the study is to critically assess the implementation of
the Community based Poverty Reduction Project (CPRP) as a strategy for reducing poverty in
Nigeria with a specific objective to determine the extent to which the Community based Poverty
Reduction Project (CPRP) has effected poverty reduction in the four states where the African
Development Bank (ADB) funded their CPRP activities and coordinated by the National
![Page 138: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/138.jpg)
130
Planning Commission (NPC); investigate the efficacy or otherwise of the Community based
Poverty Reduction Project (CPRP) model in reducing poverty in Nigeria; ascertain the
desirability or otherwise of replicating the CPRP model in all the states of the federation and the
Federal Capital Territory (FCT); identify peculiar challenges/problems associated and unique to
the implementation of the Community based Poverty Reduction Project (CPRP) in the states
funded by the African Development Bank (ADB); and make recommendations for strengthening
and sustainability of the CPRP programme thereby enhancing its effectiveness in reducing rural
poverty in Nigeria.
The research work then delved into the views, opinions, and ideas of scholars regarding
poverty reduction/alleviation with a view to presenting a general and holistic picture of the
subject matter. Because of the nature of the implementation of CPRP activities and other
poverty reduction programmes in Nigeria, the research work inclined to the elites’ theory-which
tends to postulates that the public policies and programmes are manipulated by the elites to
satisfy their interests. Therefore, the major thrust of the elites theory is that the socio-economic
gains of public policies and programmes are seized by the elites class to set the societal status
quo. On the methodology, the research work made use of mostly secondary data for analysis and
the result of oral interview for crosschecking for confirmation or otherwise. The use of simple
average, percentages and chi-square were also adopted in analyzing the data collected from the
secondary sources.
Having carried out the detailed study of the implementation of the Community based
Poverty Reduction Project (CPRP) in the four African Development Bank (ADB) assisted states
(Edo, Gombe, Osun and Zamfara), the study came up with the following findings:
![Page 139: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/139.jpg)
131
• The implementation of the CPRP in the states has fast tracked the provision of micro
projects especially the social service sector goods (education and health) to the rural and
remote communities. Within the short timeframe of the piloting of the project, over 800
communities had been provided with either a school or health facilities with millions of
individuals benefiting from it.
• The time frame for starting and completing a micro project by any community had been
within three months. Only very few projects had lasted beyond three months but not up to
six months.
• The implementation of the CPRP did not create room for any project to be abandoned.
First, appraisal of the micro projects is carried out by the state CPRP Agency to ensure
that the benefiting community had the capacity to undertake such project and thereafter
funds are provided in three tranches in the ratio of 40 : 30 : 30 to complete the project
within the estimated time frame.
• Most rural communities had no capacity to manage the implementation of CPRP.
Because of this development, the CPRP made provision for capacity building, especially
of the people entrusted the implementation of the project (the Project Implementation
Committee (PIC) members) which are usually 10 people in number including women.
Although, most beneficiary communities PIC members had no requisite education, they
were sometimes trained in their local languages to understand project design and
implementation, monitoring of micro projects and financial management. Over 8,000
community PIC members have received such trainings thus constituting a plus to the
CPRP.
![Page 140: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/140.jpg)
132
• Within the project implementation period, the four ADB states (Edo, Gombe, Osun and
Zamfara) have completed a total of 872 micro projects/sub projects in 872 communities
at a total cost of N2,652,521,721.45. This amount is more than what Nigeria politicians
stash away to foreign countries.
• The CPRP encouraged cost effectiveness. The overall mean cost of undertaking the
CPRP micro projects in the four states is N3,041,882.71. This mean cost have been
observed to be by far (30 – 40%) cheaper than the cost of implementing similar projects
by other conventional means like through the treasury or by contracting.
• On the average, it is pretty more expensive executing micro projects in Edo State than in
any of the remaining three states (Gombe, Osun and Zamfar). The average cost of the
micro projects executed in Edo State is N4,068,241.44 and it is 31.09% or N1,264,773.69
higher than that of Gombe State, 31.12% or N1,266,042.67 higher than Osun State and
30.53% or N1,241,856.82 higher than Zamfara State micro projects.
• The implementation of the CPRP micro projects by the four states exposed further the
peculiar differences of the Nigeria nation. The two Northern States (Gombe and Zamfara)
preference was in the Education sub sector projects while the two Southern States (Edo
and Osun) preference was in Water sub sector projects. This is a very unique divide.
• There is no imposition of projects on the communities in any form by either the State
CPRP Agency or the influential people from the communities. The communities decides
on projects to be implemented through a townhall meeting and women involvement in
arriving at a decision on what project is implemented is usually given a high priority by
the State CPRP Agency before it is approved for implementation.
![Page 141: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/141.jpg)
133
• In over 800 communities where the CPRP micro projects were implemented in the four
ADB states, there has been no evidence or cases of fraud at the community level. The
funds provided for the communities had been judiciously applied on the project by the
community members.
• The implementation of CPRP micro projects/sub projects in over 800 communities of the
four ADB states has increased the access of the communities to poverty reduction
projects.
• The CPRP micro projects implemented by the beneficiary communities cut across many
sectors. The opportunity provided by the CPRP by allowing the projects to be selected
from different or any sector by the communities reduced to the barest minimum the
problem of choice or selection and ability of communities to participate in the
programme. Thus, the sectoral coverage has enabled the communities accessed the
poverty reduction project.
• An international best practice has been achieved in the management of the CPRP in
Nigeria. In line with best practices, it is often recommended that not more than 20% of
project funds should be used for administration or operating costs. This costs component
which also included procurement of goods and services, training, payment of salaries etc
is only 18.11%. This is a high point of the CPRP and thus worthy of note or
commendable.
• Although the CPRP had made some significant contribution to in the poverty reduction
process in both in terms of number and spread of micro projects as well as the
accessibility by the poor, the role of the third-tier of government–the Local Government
![Page 142: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/142.jpg)
134
which is closer to the rural people which the CPRP activities are actually meant for was
very negligible in the management and implementation process.
• Following the non involvement of the Local Governments administration in the CPRP
process, there have been some cases of delay in the posting of skilled staff to some very
remote communities to man the completed projects causing a delay in the use of the
micro project. This is experienced mostly in health related projects and few education
projects (primary education). This kind of thing happen because most often the Local
Government administration may not be aware of the project being implemented by the
community until after completion and probably commissioning and as result may not
have made adequate manpower plan for such a project.
• The staffing of State CPRP Agency is very thin. Traversing of the state by this few staff
for the purpose of supervision/monitoring of the implementation of the micro project is
overwhelming and may yield the desired result.
5.2 Conclusion
The research work studied the implementation of CPRP as a poverty reduction strategy in
four states of Nigeria – Edo, Gombe, Osun and Zamfara. It is noted that prior to the piloting of
CPRP, the government of Nigeria had adopted several poverty reduction strategies to tackle the
problem of rising poverty. Most of these strategies did not address the problem from the point of
view of accessibility. The strategy of addressing poverty reduction from the angle of accessibility
is the high point of CPRP. From the study, the CPRP had recorded very great positive
achievements in poverty reduction. Our findings showed that many rural communities in the four
states implemented different micro projects or sub projects and therefore have access to such
facility in record time. It is often said that time is money and the CPRP has played it out. The
![Page 143: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/143.jpg)
135
communities which implemented water projects for instance would have reduced the time spent
in search of potable water and may have reduced water related diseases while the primary health
centres could have at the least a first aid treatment before they could be rushed to far away
hospitals for further treatment if the need arises.
Although the CPRP had made giant stride in addressing poverty reduction through
enhancing accessibility to the poor, the implementation nonetheless from the findings of the
study is also saddled with some challenges. These challenges include among others the level of
literacy amongst the rural/remote communities, terrible and difficult terrains, non involvement of
the Local Governments from the early stage of project identification through implementation
especially in high skilled related projects like those in the health sector, thin staffing of State
CPRP agencies, delay in posting of skilled staff to completed micro projects and delay in the use
of already completed projects because they were awaiting commissioning by Governor or a very
top State Government official.
These challenges not withstanding however, the researcher reasonably concludes that the
CPRP is a very unique approach to poverty reduction in relation to previous approaches by the
Government of Nigeria. Within a short period, micro projects have spread like wild fire. The
activities of CPRP has been able to touch the lives of over 800 communities and millions of
citizens across the four states because the choice of which micro project to implement is not
limited to any area/sector and communities had freedom to implement projects that they are in
need of and could alleviate their poverty. Also, the cost of implementing CPRP micro projects is
relatively cheap with no recorded fraud from any of the over 800 communities.
![Page 144: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/144.jpg)
136
5.3 Recommendations
Consequent upon the findings of the study and given the peculiar nature of the CPRP
activities, the researcher wishes to make the following recommendations:
1. The Local Government administration should be involved in the implementation of
the CPRP programme. This would help that tier of government to be aware of the
choices of communities of some projects which may require Local Government
contributions in the form of deployment of skilled manpower for its
operationalization and plan in advance for it. The poor involvement of the local
governments tend to make the rural communities lose focus of the implementation of
development projects and programmes of the CPRP.
2. The sources of funding of CPRP activities should be expanded to include Local
Governments. The CPRP projects are micro in nature and are often within the
purview of the Local Government administration. The Nigerian Local Governments
today is riddled with corruption and there have not been any meaningful
achievements across boards from this tier of government. If the Local Governments
are made to contribute into CPRP funds through a compulsory deduction from the
source, more money would be made available for communities to implement more
projects and consequently improve the lives of the rural poor rather than leaving the
money in the hands of Local Government Chairmen for mere political patronage.
With less than N4.0 billion and for 5 years, over 800 communities have seen some
good things of life whereas more than that amount has been fraudulently taken away
by Governors whose cases have never ended in the Nigeria law courts.
![Page 145: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/145.jpg)
137
3. The organization of community members as well as the number of micro projects
executed and their accessibility is a proof of itself (CPRP) as an undoubtedly a
vehicle for rapid rural development and social mobilization. The community
members came together without coercion and agreed on projects, rallied among them
to provide the necessary counterpart contribution in cash or kind. With this level of
cooperation exhibited by communities in the implementation of CPRP, the
Government could legislate on CPRP model to make it a means or strategy for rapid
rural development and community mobilization for national development.
4. Implementation of the Millennium Development Goals (MDGs). The CPRP model
has worked in prompted delivery of poverty reduction micro projects and should be
adopted in the implementation of the Millennium Development Goals. By taking this
step, the Nigerian Government would achieve the Millennium Development Goals
(MDGs) targets on or before the 2015 target year without much ado.
5. Usually, there are some communities that are very rural and remote which may have
implemented some micro projects such as cottage hospital that may require
specialized and skillful manpower to man it. Such communities may have suffered
delay in getting these staff to be deployed to them to operationalize the project. In
cases of this nature, the researcher is inclined to recommend that such communities
should be encouraged from the onset of the project to volunteer some of their people
who are literate enough to undergo some basic trainings in such fields (eg traditional
birth attendants, rural nursing and drug dispensing etc). By this process, the door of
the project will be opened to patience for minor or first aid activities pending the
deployment of more sophisticated staff.
![Page 146: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/146.jpg)
138
BIBLIOGRAPHY
Books
Abayole, O. (1975) Integrated Economics: A study of Developing Economics. London: Addition-
Wesley publishers. Addison .D. (2002) Nigeria: Policy Options for Growth and Stability in a Challenging
Environment. Washington D.C: The World Bank, June 2002. Achebe, C. (1987) The Trouble with Nigeria. Enugu. Fourth Dimension. Achor, U.J (ed.) (2001) Managing the Environment in Popular Neighborhoods: A Manual for
Action. Ake, C. (1981) A Political Economy of Africa. Ibadan: Longman Nigeria Plc. Alapiki, H. (1995) Politics and Governance in Nigeria. Owerri: Corporate Impressions. Amuguo, A. (2003) The Poverty Problem: Will Nigerians Ever Get it Right. London:
Libertarian Variance. Anyanwu, J. C. et al (1997) The Structure of the Nigerian Economy (1968-1997). Onitsha: Jonee
Education Publishers. Black, J. and Champion, D. (1976) Methods and Issues in Social Research. New York: John
Wiley and Sons. Eboh E. C. and Ogbu .O. (2010) The Global Economic Crisis and Nigeria: Taking the Right
Lessons Avoiding the Wrong Lessons. Enugu: EL ‘Demak Publishers Ltd. Ekekwe, Eme (1986) Class and State in Nigeria. Lagos: Longman. Ekong, E. (1991) Rural Development and the Persistence of Poverty in Nigeria. Ugo: University
of Cross Rivers State Press. Egpe, B.O. (2000) “Implementation of Poverty Alleviation Programmes at the Grassroots” in
Uyo, O.E. and Oloro, J. (eds.) Local Government and Grassroots, Administration in
Nigeria. Calabar: University Pres. Fields, G. (1974) “Poverty Changes in Developing Countries” in Vander, H.R. and Anken, R.
(eds), Poverty Monitoring: An Internal Concern. New York: St. Martins Press.
![Page 147: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/147.jpg)
139
Goode, W.J and Hart, P.K. (1952) Methods in Social Research. New York; McGraw Hill
Company. Haralambos, M. (1980) Sociology: Themes and Perspectives. London: University Tutorial Press. Ikelegbe, A.O. (1997) Public Policy Making and Analysis. Benin City: Uri Pushing Ltd. Kerlinger, F.N. (1973) Foundations of Behavioural Research. New York: Holt, Rinehart and
Winston. Lipset, S. M. and Lenz, G.S. (1997) “Corruption, Culture and Markets”, in Harrison, E.I. and
Huntington, S.P. (eds), Culture Matters. New York: Basic Books. Nnadozie, U.O. (2004) The State, Civil Service and Underdevelopment in Nigeria An Analysis of
Public Policy Making Process in a Neo-Society. Enugu. Johnkens and Willy Publishing. Nwatu, R. (2006) Principles of Development Administration. Enugu Zik- Chuks Press. Obadan, M.I. (1997) “Analytical Framework for Poverty Reduction: Issues of Economic Growth
and other Strategies’ in Poverty Alleviation in Nigeria. Ibadan: The Nigerian Economic Society.
Obadan .M. I. (2003) “Poverty Reduction in Nigeria: The Way Forward” In
Obadan M.I, Fajingbesi A. A. and Uga B. O. (eds) Integrating Poverty Alleviation Strategies into Plans and Programmes in Nigeria, Ibadan, NCEMA.
Obadan M. I. (2003) National Development Planning and Budgeting in Nigeria:
Some Petinent Issues, Lagos, Broadway Press Ltd. Obasi, I. (2002) Politics and Globe Dictionary, Enugu: Jamoe Publishers. Obasi, I.N. (1999) Research Methodology in Political Science: Enugu: Academic Publishing
Company. Obikeze, D.S. (1990) Methods of Data Analysis in the Social and Behavioural Sciences. Enugu:
Auto- Century Publishing Company. Obuoforibo, G.I.J. (2002) “Local and Regional Government”. In Alagoa, E.J. and Derefaka, A
(eds) The Land and People of Rivers State. Port- Harcourt: Onyoma- Research Publishers.
Odo, M.O. (1992) Guide to Proposal Writing in Social and Behavioural Sciences; EnuguL
SNAAP Press Ltd.
![Page 148: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/148.jpg)
140
Onah, F.O. (2006) Managing Public Programmes and Projects. Nsukka: Great AP Express Publishers Ltd.
Soludo, C.C. (2004) Nigeria: National Economic Empowerment and Development Strategy
(NEEDS). Abuja: National Planning Commission. Sen .A. K. (1999) Development as Freedom, New York: Anchor Books. Tendier, Judith (2000) “Why are Social Funds so Popular?” In Shahid Yusuf,
Weiping Wu and Simon, (ed.) The Changing Development Landscape, Oxford University Press: Oxford.
Todd David (1995) Nigeria Participatory Poverty Assessment, ETC Foundation for the Oversea
Development Administration of the United Kingdom. United Kingdom Official Report.
Journals and Periodicals
Abdullahi .S. (2008) “The Hope for Nigeria: Vision 2020 Faces Difficult Challenges Ahead” In The Nigerian Economic Summit Group Economic
Indicators Journal, July – September 2008, Vol. 14, No. 3, p. 40.
Booth .D. (ed) (2003) Are PRSPs Making a Difference? The African Experience. Development
Policy Review, Special Issue Vol. 21, No. 2. Ekhator, V.E. (2003) “Poverty Alleviation Programmes in Nigeria: An Over View of Effort by
the Past and Present Administration”. International Journal of Governance and
Development, March, 2003, Vol. I No. 1 p. 73. Jamal Vali and Weeks John (1988) The Vanishing Rural – Urban Gap in Sub-Saharan Africa,
International Labour Review, Vol. 127 No. 3, p. 278. Ogwumike F. O. (2000) “An Appraisal of Poverty Reduction Strategies in Nigeria”, Central
Bank of Nigeria Financial and Economic Review, Vol. 39, No. 4. Oluba .M. (2008) “Reducing Poverty in Nigeria” In the Nigerian Economic
Summit Group Economic Indicators Journal, July – September 2008, Vol. 14, No. 3, p. 54.
Ozughalu .M. (2008) “Poverty, Underdevelopment and Global Competitiveness: A Reflection on Nigeria’s Situations’ In the Nigerian Economic Summit Group Economic
Indicators Journal, July – September 2008, Vol. 14, No. 3, p. 48.
![Page 149: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/149.jpg)
141
Newspapers
African, Pius (2007) “Social and Economic Cost of Corruption”, This-Day Wednesday, August
08, 2007, p. 28.
Anosike, K. (2001) “The Fictiveness of Poverty Alleviation” in the Guardian, Tuesday, February 20.
Seminar and Conference Papers
Aigbokhan .B.E. (2000) Poverty, Growth and Inequality in Nigeria, A Case Study, AERC Research Paper 102, Nairobi, November 2000.
Bernier, Rene (1994) Issues in the Financing and Delivering of Social Services in Nigeria: Lessons from other Federal Systems, Background Paper.
Canagarajan .S., Ngwafon .J. and Thomas .S. (1997) The Evolution of Poverty
and Welfare in Nigeria, 1985 – 1992. Policy Research Working Paper No. 1715. Washington D.C. The World Bank.
CDD – Centre for Democracy and Development (2003) “Communique of the CDD Poverty
Eradication Programme Consultative Forum held at Makurdi, Benue State, Nigeria on August 28, 2003
Dorosh, Paul (1994) Implication of Macroeconomic Policy for the Poor in Nigeria CGE
Analysis, Background Paper. Eboh .E. C. (2003) “The Poverty Reduction Process in Nigeria” Being Discussion Paper
presented at the Third Meeting of the African Learning Group on the Poverty Reduction Strategy Paper held at the Economic Commission for Africa, Addis Ababa, Ethiopia, 3 – 5 December, 2003.
Eboh .E. C., Amakom .U. and Oduh .M. (2006) “Budget and Public Expenditureacross Nigerian
States” BECANS Working Paper 3, Enugu; African Institute for Applied Economics.
Marrissey .O. (2001) “Pro-Poor Conditionality and Debt Relief in East Africa”
Being Paper Prepared for the WIDER Development Conference on Debt Relief, Helsinki, 17 – 18 August, 2001.
Okonjo-Iweala .N. (2003) “Nigeria Economic Challenges Going Forward” Being Nigerian
Economic Summit Group Public Lecture Delivered at the Nigerian Institute of International Affairs, Lagos, July 15, 2003.
![Page 150: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/150.jpg)
142
Okunmadewa F. and Williams .K. (2000) Nigeria: Voice of the Poor –Consultations with the Poor, Country Synthesis Report.
Soludo .C. C. (2006) “Law, Institutions and Nigeria’s Quest to Join the First World Economy”
Being a Lecture Delivered in Honour of the Retired Justice of the Supreme Court of Nigeria, Justice Kayode Eso, at the Obafemi Awolowo University, Ile-Ife, July 25, 2006.
Government Documents
Enugu State Government (2004) State Economic Empowerment and Development Strategy
(SEEDS), Enugu State Government Press. Federal Government of Nigeria (2004) National Economic Empowerment and
Development Strategy (NEEDS), National Planning Commission, Abuja. Federal Government of Nigeria (2009) Nigeria Vision 20:2020, National Planning Commission,
Abuja. Federal Government of Nigeria (2001) Areas of International Assistance, National Poverty
Eradication Programme (NAPEP), Abuja. Federal Government of Nigeria (2003) Nigeria I-PRSP; Draft Interim Paper on
National Poverty Reduction Strategy, August 2003, Economic Policy Coordinating Committee (EPCC), Abuja.
Federal Government of Nigeria (2008) Community Economic Empowerment and Development
Strategy (CEEDS) Model for Nigeria, National Planning Commission, Abuja. Federal Government of Nigeria (2005) SEEDS Manual, From Strategy to Action, A Framework
Guide for Development Planning, National Planning Commission, Abuja. Federal Government of Nigeria (2005) Local Government Assessment Scorecard: Governance
Tool for Poverty Targeting – Lessons from the Local Empowerment and Environmental management Project (LEEMP), Federal Ministry of Environment, Housing and Urban Development, Abuja.
Federal Government of Nigeria (1994) Government Policies and Program to Reach the Poor,
Background paper, National Planning Commission, Abuja. Federal Government of Nigeria (2010) Nigeria 2010 Millennium Development Goals Report,
National Planning Commission, Abuja.
![Page 151: A CRITICAL EXAMINATION OF THE COMMUNITY … Nkem Project 1-5 Final... · Local Governments in the process affected the utilization of some ... 2.1.4 Poverty Reduction Programmes in](https://reader033.vdocuments.mx/reader033/viewer/2022051723/5abe8f7b7f8b9a3a428d116d/html5/thumbnails/151.jpg)
143
FOS – Federal Office of Statistics (1999) Poverty Profile for Nigeria: A Statistical Analysis of 1996/1997 National Consumer Survey (with Reference to 1980, 1985 and 1992 Surveys), Abuja.
Poverty Alleviation Programme Development Committee (PAPDC), June (1995), Report on
Consultative Surveys in Thirty-Six Communities. World Bank (1996) Report on Consultative Surveys in Thirty-Six Communities
Prepared for the Poverty Alleviation Programme Development Committee. World Bank (2002) A Source Book for Poverty Reduction Strategies Vol. 1: Core Techniques
and Cross Cutting Issues. Washington D.C. The World Bank. World Bank (1996) Nigeria: Poverty in the Midst of Plenty: The Challenge of
Growth with Inclusion, A World Bank Poverty Assessment, Washington D.C. The World Bank.
World Bank (1995) The Evolution of Poverty and Welfare in Nigeria, Washington .D.C. The
World Bank.