7.installation,operation & maintenance(iom)

65
7/24/2019 7.Installation,Operation & Maintenance(IOM) http://slidepdf.com/reader/full/7installationoperation-maintenanceiom 1/65 I nstallation, O peration & M aintenance anual PACV-S Packaged Air Conditioners

Upload: naveenkrishnas

Post on 20-Feb-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    1/65

    Installation,Operation&Maintenanceanual

    PACV-S

    Packaged Air Conditioners

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    2/65 2 |2 |

    Table of Contents1 Introduction 4

    Nomenclature . . . . . . . . . . . . . . . . . . . . 5

    Safety Instructions . . . . . . . . . . . . . . . . . . 5Specic Hazards. . . . . . . . . . . . . . . . . . . . 5

    Points To Remember. . . . . . . . . . . . . . . . . . 6

    Component Features . . . . . . . . . . . . . . . . . 7

    Liquid Line Controls . . . . . . . . . . . . . . . . . . 9

    Electrical Control panel . . . . . . . . . . . . . . . 10

    Room Unit . . . . . . . . . . . . . . . . . . . . . 11

    2 Installation

    Receiving of Equipment . . . . . . . . . . . . . . . 13

    Rigging . . . . . . . . . . . . . . . . . . . . . . 13

    Handling . . . . . . . . . . . . . . . . . . . . . . 13

    Storage . . . . . . . . . . . . . . . . . . . . . . 14

    Location & Space Requirements . . . . . . . . . . . 14

    Pre-Installation Checkup. . . . . . . . . . . . . . . 15

    Preparation For Installation . . . . . . . . . . . . . 16

    Carrying Out Installation . . . . . . . . . . . . . . . 16

    Condensate Draining . . . . . . . . . . . . . . . . 16

    3 Operation

    Pre-Startup Checklist . . . . . . . . . . . . . . . . 17

    Pre-Startup Procedure . . . . . . . . . . . . . . . . 17

    Service Record . . . . . . . . . . . . . . . . . . . 18

    Unit Startup . . . . . . . . . . . . . . . . . . . . 19

    Display & Keypad Operation . . . . . . . . . . . . . 20

    Alarms . . . . . . . . . . . . . . . . . . . . . . . 21

    List of alarms in the unit controller . . . . . . . . . . 21

    Operation of the Room Unit . . . . . . . . . . . . . 22

    Setting the address of the room unit . . . . . . . . . 22

    switching in and switching off the unit . . . . . . . . 22

    Commissioning Test Report . . . . . . . . . . . . . 25

    4 Maintenance

    Periodic Maintenance . . . . . . . . . . . . . . . . 26

    Leak Testing, Evacuation &

    Charging Procedures . . . . . . . . . . . . . . . . 28

    Fan . . . . . . . . . . . . . . . . . . . . . . . . 32

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    3/65 | 3

    Bearing . . . . . . . . . . . . . . . . . . . . . . 32

    Fan Belt Adjustment. . . . . . . . . . . . . . . . . 33

    Fan Pulley Adjustment

    (For variable pitch pulleys only) . . . . . . . . . . . 35

    Alignment of Shafts & Sheaves . . . . . . . . . . . . 35

    Mold In And Around Drain Pans . . . . . . . . . . . . 36

    Coil . . . . . . . . . . . . . . . . . . . . . . . . 37

    Coil Cleaning . . . . . . . . . . . . . . . . . . . . 37

    Compressor Oil . . . . . . . . . . . . . . . . . . . 37

    Adding Oil . . . . . . . . . . . . . . . . . . . . . 37

    Dismantling & Disposal . . . . . . . . . . . . . . . 38

    Expansion valve service & maintenance . . . . . . . . 38

    Hot gas by pass . . . . . . . . . . . . . . . . . . . 40

    Refrigerant Recovery, Recycling &

    Reclamation . . . . . . . . . . . . . . . . . . . . 43

    Trouble Shooting . . . . . . . . . . . . . . . . . . 46

    5 Appendix

    Appendix I . . . . . . . . . . . . . . . . . . . . . 49

    Loading Points . . . . . . . . . . . . . . . . . 49

    Appendix II . . . . . . . . . . . . . . . . . . . . . 51

    Dimensional Data . . . . . . . . . . . . . . . . 51

    Appendix III . . . . . . . . . . . . . . . . . . . . 55

    Refrigerant Piping Layout . . . . . . . . . . . . 55

    Appendix V . . . . . . . . . . . . . . . . . . . . . 57

    Filter Dimension . . . . . . . . . . . . . . . . 57

    Appendix IV . . . . . . . . . . . . . . . . . . . . 58

    Spare parts . . . . . . . . . . . . . . . . . . . 58

    Appendix VII . . . . . . . . . . . . . . . . . . . . 57

    Typical wiring diagram . . . . . . . . . . . . . . 57

    Appendix VIII . . . . . . . . . . . . . . . . . . . . 62

    Typical Wiring Diagram . . . . . . . . . . . . . 62

    Appendix IX . . . . . . . . . . . . . . . . . . . . 63

    Instructions For Downloading/Upgrading The

    Software For Microprocessor . . . . . . . . . . . 63

    Appendix X . . . . . . . . . . . . . . . . . . . . . 64

    P-T Chart . . . . . . . . . . . . . . . . . . . . 64

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    4/65 4 |

    INSTALLATION, OPERATION & MAINTENANCE

    This manual must be carefully read and followed in

    order to avoid unnecessary/dangerous conditions in the

    machine and to guarantee the safety of the equipment.

    The contents in this manual are mainly the installation and

    operating instructions of your Package Air Conditioning

    unit. The precautions mentioned through out this manualshould be taken seriously to derive maximum safety forall. Installation, service and start up of any air-conditioning

    equipment should be done only by a qualified personnel or

    service technician. Always observe precautions in the manual

    and be familiar of all the symbols / labels attached in the unit

    when dealing or working with the equipment.

    Unit DescriptionThe PACV-Sseries is a modern, diversified and environment

    friendly series of packaged air conditioners which use R - 134a

    as the refrigerant.

    The complete PACV-Spackage provides an extremely rugged,

    heavy duty, long-life, energy efficient and self-contained package

    air conditioner that will provide cooling at higher efficiency overa long and extended life. What makes PACV-Sseries the prideof SKM products is the use of :

    The SKM PACV-S series packaged air

    conditioning units are durable, dependable,

    strong, reliable, versatile, quiet and energy

    efficient. Wherever a heavy duty packaged

    air-conditioner is required, the PACV-Sseriesshould be an automatic choice.

    Unit Name PlateTypical SKM Air Cooled Packaged Unit

    nameplate is as shown.Check the nameplate data with the P.O/

    Submittal when receiving the unit.

    For the representation and understanding of the points

    of caution, attention, danger, and information. Following

    symbols are used throughout the manual.

    Note:- It is not the intention of this manual

    to cover all possible variations in systems

    that may occur or to provide comprehensive

    information concerning every possible

    contingence that may be encountered during an installation,

    operation and maintenance. If additional infor mation isrequired or if specific problems arise that are not fully

    discussed in this manual, contact your local office.

    Always heed all WARNING and SAFETY

    INSTRUCTION boxes. Always read and heed all

    instructions in this manual carefully. Failure to

    follow WARNING, SAFETY INSTRUCTIONS and all

    other instructions could result in severe personal

    injuries and death.

    Introduction

    General Warning

    CAUTION

    General Information .

    INFORMATION

    Take special attention

    and po in ts to be

    noted.ATTENTION

    Indicates dangers

    through electricalshock, system

    pressure, and

    location.DANGER

    Indicates dangers by

    high voltage

    HIGH VOLTAGE

    Indicates dangers

    by moving/rotating

    parts

    MOVING/ROTATING PARTS

    HOT PIPES

    Indicates dangers by

    hot pipes

    MODEL

    Qty KW FLA

    Qty KW FLA

    MANUFACTURING SERIAL NO

    MANUFACTURED IN SHARJAH,UNITED ARAB EMIRATES

    HEATER KW/NO. OF STAGES

    R-134A CHARGE(KGS)

    CONDENSER MOTOR

    EVAPORATOR MOTOR

    MIN.CIR AMPS/MAX. FUSE AMPS

    COMPRESSOR MODEL Qty LRA RLA

    POWER SUPPLY (V/Ph/Hz)

    CONTROL VOLTAGE(V/Ph/Hz)

    Factory/Field

    ITEM CODE

    High efficiency totally sealed hermetic scrollcompressor.

    Totally enclosed, Class F insulated, IP55

    protected condenser and evaporator fan

    motors.

    Heavy duty condenser and evaporator coils

    optimised in design for long-life maintenance

    free operation.

    Cabinet construction specifically designedfor Gulf climates.

    IP 54 Electrical panel.

    Factory installed, advanced and user friendlymicroprocessor based control system.

    Interface capability with major BMS protocols

    (option).

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    5/65 | 5

    INSTALLATION, OPERATION & MAINTENANCE

    SKM reserves the right tochange, in part

    or in whole the specifi cations of its Air

    Conditioning Equipment at any time in

    order to add the latest technology. Therefore,the enclosed information may change without

    any prior notice.

    Nomenclature

    Safety Instructions

    Carefully read the content of this

    manual before installing the air

    conditioning equipment. For maximumsafety installers should always follow

    the list of warnings. During the

    installation process care should be

    taken to avoid any accidents related to:

    1. High voltage

    2. High pressure in the system

    3. Hot pipes due to discharge

    temperature

    4. Moving/Rotating parts

    This manual explains how to install,

    operate and maintain SKM PACV-S

    series,Air coo led packaged unit . The

    manufacturer shall not be responsible

    for damages arising from wrong

    practices used. So SKM recommendsto do the installation including the

    connection of electricity, operation and maintenance

    by a person qualified for the air- conditioning and

    refrigeration work only.

    The manufacturer shall not be responsible for

    damages originating from unauthorized changes

    or the improper connection of electricity and not

    adhering to the operation limits included in the

    manual. Also this shall invalidate the warranty.

    The air conditioning equipment should be used

    only for the applications for which it has been

    designed.

    Refer product name plate, wiring diagrams and catalogues

    for the electrical characteristic, of the equipment to selectcorrect wire sizes and isolators prior to the insulation.

    It is the responsibility of the user or the person installing

    the equipment to provide proper grounding and branch

    circuit protection according to NEC, Local & National

    safety regulations.

    This Air Conditioning equipment must be disconnected

    from the mains if any repair work is to be carried out.

    Do not use the units if damaged. If problems occur, switch

    the unit off and disconnect it from the power supply.

    The control ON/OFF switch in the control panel does not

    disconnect the equipment from the mains and thus it is

    not to be used as a safety switch.

    Do not attempt to repair, move, alter or reinstall the unit. If

    performed by an unauthorized personal, these operations

    may cause electrical shock or fires.

    Always remember to inspect the units, refrigerant tubes

    and protection regularly. These operations should beperformed by a qualified personnel only.

    Contact SKM After sales in case any technical support

    is required.

    PAC V - 5 1 008 S Y

    Packaged Air

    Conditioner

    V-shaped condenser

    construction

    Power supply frequency

    5 = 50 Hz

    6 = 60 Hz

    Power Supply CodeY: 380-415V/3Ph/50Hz

    P: 440V/3Ph/50HzR: 380V/3Ph/60Hz

    E: 460V/3Ph/60HzT: 220V/3Ph/60Hz

    Scroll Compressor

    (R-134a)Nominal

    Capacity (TR)

    No. of Refrigerant

    Circuits

    Specific Hazards

    Do not stand or work under suspended loads.

    Wear a hard hat, safety shoes and gloves.

    Noise Emission

    The sound emission expected in normal use of the fan

    should be duly taken into account.

    Wear ear defenders when

    working near to or on the running

    fan!

    Rotating Shafts and Impellers

    Objects fixed to rotating shafts and impellers can fly

    off at an angle and cause serious injury.

    Articles of clothing and hair can get caught in rotating

    shafts and impellers.

    Heavy Loads

    The heavy weight of fans

    and their components entail

    the following risks during

    maintenance:

    Risk of being trapped,

    crushed or cut by moving or toppling

    machinery.

    Danger of falling components.

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    6/65 6 |

    INSTALLATION, OPERATION & MAINTENANCE

    Being an electromechanical machine, the unit may fail or

    cause difficulties. Remembering the following few points will

    ensure correct and prompt rectification and continued optimal

    performance.

    Points To Remember

    A correct installation ensuring proper clearances forcorrect condenser air flow and maintenance as per the

    drawings shown for recommended clearances

    Proper level base on foundation with appropriatevibration mount. All connections and hook up to be

    followed as per instructions, which ensures long term trouble

    free operation and performance.

    If power fuse is blown off, be sure to replace the same

    with a new fuse having pre designed Amperage. Donot use a steel wire or copper wire instead of proper

    fuse. Genuine fuse ensures safety and proper protection.

    Incorrect fusing may cause fire or trouble with your equipment.

    Before replacing any fuse or opening any electrical

    panel door, make sure the main switch is OFF.

    Do not spray or sprinkle water directly over or into

    the air conditioning equipment for cleaning becauseelectric insulations and terminal of the components

    are opened.

    Following a power supply interruption during operation,

    the microprocessor is programmed to restart the unit

    automatically when power supply has returned to normal.

    Periodical maintenance of the unit will give better

    performance in the long run than only break down

    maintenance.

    The microprocessor controller is programmed to stop

    functioning the Air conditioning equipment includingthe compressor in the event of a safety device trips. The

    problem should be investigated and repaired or rectified as per

    trouble shooting instruction in this manual before attempting to

    reset and restarting the machine.

    This Air conditioning equipment is meant to be installedout doors and suitable to normal environment elements.

    Do not try to cover or block any inlets or discharge openings

    to condenser.

    Insist on maintenance from a reputable maintenance

    contractor to ensure a trouble free operation.

    Do not remove guards

    during operation.

    Do not wear loose-fitting

    clothing when working

    near rotating shafts and

    impellers.

    Wear gogg les.

    Hot Surfaces

    There is a risk of sustaining burns or scalds

    on hot surfaces during operation.

    Do not touch the Motor,

    Compressor bo dy, Discharge

    line during operation.

    When the condenser fan has

    stopped wait until the motor

    has cooled down.

    Wear protecti ve gloves.

    Electrical Shock Hazards

    All p ower must

    be disconnected

    prior to installation

    and servicing this

    equipment. More

    than one source of

    power may be present. Disconnect

    all power sources to avoid

    electrocution or shock injuries.

    Avoid breathingfiber glass dust.

    Use a NIOSH approved dust/mist respirator.

    Avoid contact with the skin or eyes. Wear

    long-sleeved, loose-fitting clothing, gloves,and eye protection.

    Wash clothes separately from otherclothing: rinse washer thoroughly.

    Operations such as sawing, blowing,tear-out, and spraying may generate

    fibre concentrations requiring additional

    respiratory protection. Use the appropriate

    NIOSH approved respiration in these

    situations.

    Fiber glass Insulation!This Product contains fiber glass wool. Disturbing

    the insulation in this product during installation,

    maintenance or repair will expose you to airborne

    particles of glass wool fibers and ceramic fibers.

    All necessary Personal Protective Equipment

    (PPE) including gloves, eye protection, mask,long sleeves and pants must be worn when

    working with products containing fibreglass

    wool. Exposition to glass wool fibers without

    all necessary PPE equipment could result in

    cancer, respiratory, skin or eye irritation, which

    could result in death or serious injury.

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    7/65 | 7

    INSTALLATION, OPERATION & MAINTENANCE

    Compressor

    Compressors used in PACV-S packaged unit series are

    hermetically sealed, compact scroll with the following features:

    Vacuum operation!Compressor damage!

    Scroll compressors should never be

    used to evacuate a refrigeration or

    air-conditioning system.

    Do not pump down the scroll

    compressor into a vacuum!

    Three phase compressors

    only: On initial startup, if

    the compressor sound isabnormally high and the readings

    of suction and discharge pressures

    are outside normal range, there is

    a possibility that the compressor

    rotation is in the reverse direction.

    In this case, interchange any

    two legs of the power supply

    and attempt to restart. Running

    a scroll compressor in reverse

    direction for an extended period

    of time will cause damage to the

    compressor. such damage is not

    covered under manufacturers

    limited warranty.

    Reverse rotation for 5 to

    15 minutes will result in

    the overheating of motor

    windings. In thi s case, the thermostat

    in the motor windings open and

    result in stopping of the compressor.

    Continued reverse operation of scroll

    compressor will result in failure of scroll

    compressors. Such failures are

    Component Features

    High Efficiency.

    Quite operation, Low Sound levels.

    Compact and light .

    Limited wear.

    70% fewer moving parts than comparably sized

    reciprocating compressors

    Unique ability to handle liquid refrigerant.

    Suction gas motor cooling.

    Centrifugal oil pumps with filter and magnet.

    Brazed fittings or Rotalock as options.

    Multiple refrigerant circuits on larger units provides

    efficient part load.

    Parallel Operation

    A parallel compressors installation, with common suction line

    and common discharge line, gives a reduced operating cost

    through greater control of capacity and power consumption. This

    is achieved by staggering compressor switch-on sequences that

    allow the parallel system to match its power with the capacity

    needed. By switching-off individual compressor from parallelinstallation, while other compressor is operating 100%, the

    improved part load efficiency can be achieved. The specially

    developed and adopted oil equalization system ensures correct

    compressors operation, oil balancing between compressors and

    reliability.

    Condensers

    Condenser coils are manufactured of seamless copper tubesmechanically bonded to aluminum

    fins to ensure optimum heat transfer.

    All coils are tested against leakage by

    air pressure of 450 psig (3100 kPa)

    under water. All standard coils are

    2,3 or 4 rows/14 FPI, 3/8 (9.5 mm)

    O.D. tubes. An integral subcooling

    circuit is provided to increase the

    cooling capacity, without additionaloperating cost.

    For different application requirements,

    other optional condenserfin materials

    are available:

    Copper fins. Electrotinned Copper Fins.

    Copper finned coils with electro-tinned after manufacturing.

    Precoated Aluminum fins

    The pre-coated is hydrophobic polyurethane resin. This optionprovides substantial corrosion protection beyond standard

    coil construction.

    Aeris Guard Coil Coating

    The Aeris Guard Coil is a self etching high performance

    modified epoxy finish that is specifically designed to coat

    and protect Aluminum and Copper surfaces. In addition, the

    coating is ideal for the protection of ferrous and non ferrous

    materials.

    SKM PACV-Sseries, all models, are restricted to a 14FPI (1.8

    mm) fin spacing condenser coil. Gulf dust storms and the general

    level of available maintenance in Gulf countries ensures this

    condenser coil design shall provide long life and maintenance

    free operation with the least possibility operational blockage on

    the condenser. Ample condenser surface and sensible air flow

    across the condenser ensures a low temperature differentialbetween condensing temperature and the high Gulf ambients

    making thePACV-Spackaged unit perform efficiently and durably.

    NOT covered under the manufacturers limited

    warranty.

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    8/65 8 |

    INSTALLATION, OPERATION & MAINTENANCE

    Condenser Fans

    Condenser fans are

    propeller type, aluminium

    alloy blades, directly driven

    by electric motors. Motors

    are Totally Enclosed Air Over(TEAO) six pole with class F

    insulation and minimum IP55

    protection. The TEAO and class F insulation features ensurelong life and are unique for SKM.

    The motors are factory wired, using wires specially selected forhigh ambients operation, to unit control panel where the motor

    contactors are located to control the operation of these motors.

    The condenser fans are individually statically and dynamically

    balanced at the factory.

    Complete fan assembly is provided with suitable acrylic coated

    fan guard.

    EvaporatorEvaporator coils are manufactured of seamless copper tubes

    mechanically bonded to aluminium fins to ensure optimum

    heat transfer. All evaporator coils are tested against leakage

    by air pressure of 300 psig (2068 kPa) under water. The DXevaporator coils are complete with headers of seamless

    copper tubing. Supply headers incorporate a correctly sized

    distributor. For different application requirements, other

    evaporator coil material and/or treatment are available

    on request.

    Evaporator coil supplied with suitable size

    thermostatic expansion valve(s) and multi-

    circuited distributors providing capacitymodulation to match the compressors. The cross

    wave fins and staggered tubes design uses the

    evaporator surface effectively by creating uniform

    air turbulence and optimum heat transfer over the

    entire finned surface. Requirements for higher

    face velocities can be handled by use of moisture

    eliminators to avoid carryover.

    Copper fins.

    Electrotinned Copper fins.

    Copperfinned coils with electro-tinned after

    manufacturing.

    Precoated Aluminum fins.

    The pre-coated is hydrophobic polyurethane

    resin. This option provides substantial

    corrosion protection beyond standard coil

    construction.

    Aeris Guard Coil Coating.

    The Aeris Guard Coil is a self etching high

    performance modified epoxy finish that is

    specifically designed to coat and protect

    Aluminum and Copper surfaces. In addition,

    the coating is ideal for the protection of

    ferrous and non ferrous materials.

    Fan Section

    Fans in the PACV-S units are selected for the best sound

    characteristics based on maximum fan efficiency. More than one

    arrangement of evaporator fans are used in the PACV-Sseries

    packaged units due to the wide range of air flow rates.

    Commonly, all fans are double inlet, double width, centrifugaltype with forward curved impellers provide the combination of

    efficiency and quietness of operation. All fans are statically and

    dynamically balanced, belt driven by motor sizes up to 15 kW are

    provided with adjustable pitch pulleys as standard.

    Above 15 kW motor sizes are equipped with fixed pitch pulleys

    s standard and adjustable pitch pulleys are option. Specify PP.

    Single fan is used for PACV-51008S, PACV-51010S, PACV-

    61009S & PACV-61012S models. Models PACV-51014S~PACV-

    52055S & PACV- 61018S~PACV- 62066S are equipped with twofans. These fans are mounted on a single heavy duty shaft driven

    by a single electric motor. Shaft end insert into over sized, tapered

    lock self aligning long life bearings. The motor is mounted on

    an adjustable base, so that belt tension can be easily adjusted.

    Models PACV-52065S and PACV-62076S onwards, use singlefan assembly, which has maximum strength, high performance,

    quietness and reliability. These fans use self aligned ball or pillow

    block bearings that are greased for life. Pillow block bearings

    are provided with re-greasing fittings. The motor is mounted on

    an adjustable base, so that belt tension can be easily adjusted.

    The complete fan-motor drive assembly is mounted on a floating

    sub-base. In order to limit transmission of noise and vibration,

    the complete fan motor sub-base assembly is mounted on anti-

    vibration mounts. Flexible connection is provided between fandischarge and casing panel to avoid transmission of vibration to

    the connecting duct.

    The optional modular construction units for models PACV-

    51008S~PACV-52055S & PACV-61009S~62066S are also using

    the same fan specifications as mentioned above.

    The electric motors are foot mounted, 4 pole, totally enclosed fan

    cooled (TEFC), IP-55 protected, Class F insulation with Class

    B temperature rise.

    Drive package is factory selected for the medium air flow rate as

    shown in the capacity ratings. Alternative drive packages to meet

    specific job or client requirements can be provided.

    Refrigerant Circui t

    PACV-S series comes complete, as standard, with correctly

    sized and piped refrigerant lines including sight glass, filter drier,

    thermostatic expansion valve, solenoid valve, shut-off valve, and

    a full operating charge of R-134a in each circuit.

    Piping is fabricated from ACR grade copper piping. Suction line isinsulated with (12 mm) wall thickness closed cell pipe insulation.

    Filter Section

    PACV-Sseries can be with a range of filter sections and filters

    to meet requirements for the most demanding applications.

    Flat or vee filter sections to accommodate 1 or 2

    cleanable aluminium media filters can be provided.

    A bag filter section to house 22, 30 or 36 deep

    bag filters having efficiencies as desired can also

    be provided, as required. Filter sections come with

    latches to provide easy access for removal and formaintenance.

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    9/65 | 9

    INSTALLATION, OPERATION & MAINTENANCE

    Shut Off Valve/Ball Valve

    Usually used so that portions of refrigeration system can be

    isolated for service or repairs.

    Sight glass

    Used to observe the flow of liquid refrigerant. Bubbles or

    foaming in the sight glass indicate a shortage of refrigerant or

    restriction in the liquid line that can adversely affect system

    operation. Sight glasses are widely used as a means of

    determining if the system is adequately charged.

    Filter Driers

    Driers are mounted in the refrigerant liquid line to ensure that

    all the refrigerant in circulation passes through the drier each

    time it circulates through the system so as to remove any

    moisture or foreign matter from the refrigerant stream.

    To order a sand trap louvre from SKM specify fresh air opening

    size with option ASL.

    Casing/Structure

    Designed for ease of handling and low cost to install. ThePACV-S

    Air Cooled Packaged Units are factory assembled and mounted

    on a rigid base. The unit casing used in PACV-SPackaged units

    is made of zinc coated galvanized steel sheets conforming to

    JIS-G 3302 and ASTM A653 which is phosphatized then bakedafter an electrostatic powder coat of approximately 60 microns.

    This finish and coating pass a 1000 hours in 5 % salt spraytesting at 95F (35C) and 95% relative humidity as per ASTM

    B117. The entire casing panels are designed to be leak proof

    against rain and ensure rain cannot enter the PACV-Sseries

    packaged air conditioner interior. Evaporator section sealed

    by the use of vinyl gasketing material.

    The evaporator section is insulated from all sides with black-

    neoprene faced heavy density 1 thick fiber glass insulation

    for models up to PACV-52055S & 62066S and 2 thick

    fiber glass insulation for models PACV-52065S & 62076S

    onwards. The insulation cum sound liner meets the fire

    requirements of NFPA90A and is secured with mechanicalfasteners in addition to water resistant adhesive.

    For applications requiring an inner skin in the evaporatorsection, option DSE provides 0.7 mm galvanized inner

    skin. Suitable isolation to ensure no cold-bridges

    and no condensation on the exterior of the unitsis provided. The condensate drain pan is heavily

    insulated to ensure that condensation may not

    occur. Stainless steel condensate drain pans are

    available on request.

    Liquid Line Controls

    Thermostatic Expansion Valve

    For controlling the flow of liquid refrigerant into

    the evaporator, an orifice in the valve meters

    the flow into the evaporator, the rate of being

    modulated as required by needle type plunger

    and seat, which varies the orifice opening.

    On 100% fresh air applications an initial sand

    trap louvre can effectively minimize entrance

    of sand into the air stream. High efficiency mini pleat panel filters are

    available as an alternative for bag filter where

    space is limited. Filter sections come with

    latches to provide easy access for removaland for maintenance.

    Low Pressure Switch

    This switch is fitted in the suction side of each refrigerant circuit

    and is wired to the unit controller digital input. Its function is to

    protect the compressors against low suction pressure. If therefrigerant circuit is On to meet the cooling demand and this

    switch remains open for a specific time (low pressure alarm delayset point), then the unit controller will switch off that circuit and

    generate Low suction pressure alarm.

    Solenoid ValveIt is used to stop the flow of refrigerant within

    the refrigeration system.

    The valve is typically a normally-closed type of

    valve so that it is closed when it is energized

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    10/65 10 |

    INSTALLATION, OPERATION & MAINTENANCE

    10 |

    Electrical Control PanelThe unit mounted control panel enclosure is fabricated out of heavy

    gauge sheet steel in phosphatized powder coated baked finish.

    The enclosure conforms to IP54 as per guidelines in IEC 529. A

    hinged access door and key-fastener is provided for easy access

    and security. The panel is factory wired in accordance with NEC430 & 440, labelled, tagged and features 220V/240v controls.

    All compressors are with DOL starting.

    Individual compressor, condenser fan motors and evaporator

    fan motor contactors.

    Motor protector circuit breaker for condenser and evaporator

    fan motors.

    Control circuit breaker.

    Control circuit on/off switch.

    Microprocessor control boards.

    Control Relays.

    Power and control terminal blocks.

    Microprocessor Controller

    All PACV-Sseries package units are equipped with a full function

    microprocessor based controller as a standard feature. Thecontroller is factory programmed for the control of evaporator

    fan, compressors and condenser fans. The controller comes

    with a built in keypad and display for simple but meaningful man

    machine interface. This controller provides complete operational

    control for the unit and has built-in auto diagnostic capability

    that can signal normal operation or alarm conditions as well asshutting down the unit or system if necessary.

    .The Main Features of the controller are as follows:

    Built in LCD display with back light.

    Roll & push knob and 3 function buttons.

    Battery backed up built in real time clock.

    Multiple authorization level to provide tight security

    for the control system.

    Capacity control based on room temperature or

    return air temperature.

    Alarm history.

    A sleek & elegant design room unit.

    Discharge Pressure Transducer

    This transducer is fitted in the discharge side of

    each refrigerant circuit and is wired to the analogueinput of the unit controller. Through this transducer,

    the unit controller will monitor the discharge

    pressure of the refrigerant circuits and cycle thecondenser fans (when compressors are running)

    in order to maintain proper head pressure.

    Facto ry se t t ings fo r p ressu re

    switches and Fan cycling

    Factory Switch Settings

    DescriptionCut Out

    (PSIG)

    Cut In

    (PSIG)

    Low Pressure

    Switch14.5 29

    High PressureSwitch

    300 200

    Table 1

    Factory Fan Cycling Settings

    in Unit Controller

    (Units with 4 fans)

    Description On (PSIG) Off (PSIG)

    Fan Cycling

    Stage- 1180 130

    Fan Cycling

    Stage- 2200 150

    Fan Cycling

    Stage- 3220 170

    Fan Cycling

    Stage- 4240 190

    Table 2

    digital input. Its function is to protect the compressors

    against high discharge pressure. If this switch

    remains open for one second, then the unit controllerwill switch off the corresponding refrigerant circuit

    and generate High Discharge pressure alarm.

    High Pressure Switch

    This switch is fitted in the discharge side of each

    refrigerant circuit and is wired to the unit controller

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    11/65 | 11

    INSTALLATION, OPERATION & MAINTENANCE

    Display Information

    SKM Pacvs series package units offer LCD

    display which allows the operator to accessdifferent parameters of the unit. Operator can

    view and change the unit parameters. The display

    information includes: Status

    Outputs

    Inputs

    Alarms

    Set points

    Password

    System Protection

    The intelligent microprocessor based controller

    monitors all the safeties related to the unit and

    makes the necessary protections,by shutting

    down the entire unit or the effected circuit. Theprotection includes

    Low suction pressure. High discharge pressure.

    High compressor motor temperature. (For

    compressors with internal motor protector).

    Compressor short cycling.

    Evaporator fan motor overload

    BMS Connectivi ty (Optional)

    Volt free contacts for run status, common fault

    status, auto mode status and provision for remote

    on/off shall be provided as option if required.

    In addition, the PACVS microprocessor can

    support the major BMS protocols such as BACnet,

    Modbus & LON. Extra hardware may be required

    depending on the protocol.

    Room UnitThe controller comes with a loose supplied sleek

    and elegant design room unit for installing in the

    conditioned space. Communication between

    unit controller and room unit is through two

    wire interface. The communication cable

    should be 2 core, twisted pair, unscreened

    with stranded conductors, as per KNX

    specification. Maximum distance between room

    unit and controller can be 700 meters. The room

    unit has a built in sensor for measuring the room

    temperature. It transmits room temperature,

    set point, unit operating mode etc. to the unitcontroller. Control of the compressors is based

    on room temperature and the set point, as

    standard. If unit control needs to be based

    on duct temperature, please specify during

    time of order.

    Room unit display (Operator Controls)

    ON/OFFButton for unit power on or unit

    power off

    Program

    Button for Time scheduler, pressing

    this button allows date/time setting,while holding it allows schedule

    programming

    Minus

    Button for set-point adjustment,

    each operation of the Minus (-)

    button reduces the set point by

    differential which is defined in

    controllers setting

    Plus

    Button for set-point adjustment,

    each operation of the Plus (+)

    button increases the set point by

    differential which is defined in

    controllers setting

    OK

    Button for confirmation of date/time

    and scheduler settings. Long pressof this button can toggle between

    measurement units -oC and oF

    FanButton for fan mode either

    continuous mode or auto mode

    Mode

    Button for unit mode: Cool, heat,

    ventilation and or cool-heat

    auto changeover (*Cool-Heat

    is available only if heat mode is

    applicable)

    Control or data communication

    cables should not be routed alongwith power cables. Sufficient distance

    is to be maintained while routing the cables

    between Power and data communication cables

    (If any).

    Room Unit Installation

    Installation must be carried with unit

    power off.

    Table 3

    A brief description of each button in the room unit is shown in

    table below:

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    12/65 12 |12 |

    Figure 1

    Figure 2

    Step Two: Remove back cover

    Open the back cover of the room unit as shown

    using a screwdriver.

    Step Three: Back plate Wiring

    Install wiring into terminal blocks as indicated,

    and push slack wire back into wall or junction box.

    The communication cable between

    room unit and microprocessor

    controller should be 2 core, twisted pair,

    unscreened with stranded conductors (As per

    KNX Specification). Maximum distance between

    room uni t and con troller can be 700 meters.

    Step Four: Cover Installation

    Install cover plate as shown. Cover plate may be removed using

    a screwdriver as needed to access the terminals for wiring.

    The room unit is not protected against

    accidental connection to AC 230 V

    The microprocessor controller & room

    unit include electrical and electronic

    components and must not be disposed

    off as domestic waste. Current local laws on

    disposal of electronic waste are to be observed.

    INSTALLATION, OPERATION & MAINTENANCE

    Step One: Location and Mounting

    Select a mounting location with good air circulation away

    from ventilation inlets, doors, windows, or other fresh air entry

    points or near direct heat sources. For room installation, the

    room unit should be mounted at least 4-1/2 feet above thefloor. Avoid direct sunlight and draught. Admissible ambient

    conditions are to be observed.The room unit is designed for semi-flush surface mounting

    with recessed conduit box. Cable entry is through the rear of

    the unit. The unit comprises front housing and rear housing.

    These can be locked together and released by snap

    mechanism. Both the housings are plastic. Use the backplate as a template for locating holes for screws and wiring.

    Mount the back plate using screws provided. Wall anchors

    are recommended for drywall installations.

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    13/65 | 13

    INSTALLATION,

    Use all lift ing point s. Improper lifting can

    cause severe personal injury and property

    damage.

    a. Support the unit well along the length of the base rail

    b. Level the unit (no twists uneven ground surface)

    c. Provide proper draining around the unit to prevent

    flooding of the equipment

    d. Provide adequate protection from vandalism,

    mechanical contact, etc.

    e. Securely close the doors

    f. Cover the supply and return air openings an limits

    without isolation dampers.

    Rigging holes are provided on the sides of the unit.

    Avoid twisting or uneven lifting of the unit

    The cable length from bracket to the hook should always

    be longer than the distance between the outer lifting points.

    If the unit is stored at the construction site for an intermediateperiod, follow these additional precautions:

    HandlingReceiving of Equipment

    Responsibility should be assigned to a

    dependable individual at the job site to

    receive material. Eachshipment should be

    carefully checked against the bill oflading. The shipping receipt should

    not be signed until all items listed on

    the bill of lading have been accounted

    for.

    When uncrating, care should

    be taken to prevent damage.Heavy equipment should be

    left on its shipping base until it has been

    moved to the final location.

    Check carefully for concealed damage. Any

    shortage or damages should be reported to the

    delivering carrier. Damaged material becomes thedelivering carrier s responsibility, and should not be

    returned to the manufacturer unless prior approval is given

    to do so.

    The packing list included with each shipment

    should be carefully checked to determine if

    all parts and equipment have been received.Any accessories such as starters, contactors

    or controls should be fastened to the basic unit to avoid

    loss and prevent possible interchanging with other

    units.

    Make sure that wiring diagrams and

    IOM manuals are available within theequipment control panel.

    Rigging

    Regardless of the packaging

    used in transporting of the units, it

    should preferably be lifted with a fork

    lift truck or a crane and belts. The

    units should be unpacked as close

    as possible to its final installation position. The

    unit should always be left standing upright.

    Before positioning the unit, it is advisable tore-check the weights.

    Remove the wooden pallet from underneath

    the machine before installation

    Use protectors to prevent sling or cable as

    per Figure 3-4.

    All protection/spreader bars shown in the

    rigging illustration should be provided by the

    customer on site.

    WOODEN PIECE

    HOOK

    SLING

    SHACKLE

    WOODEN PIECE

    SPREADER

    SHACKLE

    4No.EQUAL SLING

    HOOK

    Figure 3

    Figure 4

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    14/65 14 |

    INSTALLATION,

    Storage Single Unit Installation

    Table 4

    Location and Space Requirements

    When thePACV-Sunits need to be stored in a prolonged

    period prior to installation, the following protective

    measures are required: Units must be stored in a protected area and

    safe from construction debris. Do not remove thewooden coil guard.

    Check the pressure in high pressure side of

    refrigerant circuit to confirm that the refrigerant

    charge is intact in every three months. Take note

    of the ambient while checking. Contact SKM After

    Sales Office or SKM sales representative.

    Keep the liquid line Shut Off valve closed.

    When selecting a location for the unit, the following

    points should be considered:

    There should be enough space for air movement

    beside the condenser coils which should beapproximately equal to the height of the coils.

    The discharged air from the condenser fan should

    not be obstructed by any roofing, ducting etc whichcould cause air short circuiting.

    There should be sufficient area provided to enable

    for the servicing of the unit.

    The schematic shown in Figures 5-9 gives the

    recommended clearance areas around the unit for

    both maintenance and air flow.

    A B C

    51008-S 61009-S

    51010-S 61012-S

    51014-S 61018-S52015-S 62018-S

    51017-S 61020-S

    52017-S 62020-S

    52020-S 62024-S

    52023-S 62028-S 54

    52026-S 62033-S

    52030-S 62036-S

    52032-S 62037-S

    52038-S 62046-S

    52045-S 62055-S

    52050-S 62060-S

    52055-S 62066-S 86

    52065-S 62076-S 78

    53070-S 63085-S53075-S 63090-S

    53080-S 63095-S

    53085-S 63100-S 108

    53090-S 63105-S 114

    53095-S 63110-S 121

    54100-S 64120-S 124

    54110-S 64130-S 128

    54115-S 64136-S 134

    54125-S 64145-S 142

    ALL DIMENSIONS ARE IN INCHES

    72

    78

    72

    82

    66

    96

    104

    78108

    PACV-S

    50

    52

    -84

    6066

    SPACING FOR SERVICE

    DUCT

    A

    B

    A

    PACV- 51008 S TO 52055 S

    PACV- 61009 S TO 62066 S

    Figure 5

    SPACING FOR AIR FLOW

    [1981]78

    A

    A

    PACV- 62076 SPACV- 52065 S

    DUCT

    B

    DUCT

    Figure 6

    [1165]46

    A*

    B

    A

    *

    PACV- 63085 S TO 64145 S

    PACV- 53070 S TO 54125 S

    DUCT

    DUCT

    SPACING FOR BOTH AIR FLOW AND SERVICE*

    Figure 7

    Figure 8

    DUCT

    C

    DUCT

    B

    SPACING FOR SERVICE SPACINGFOR AIR FLOW

    PACV- 61009 S TO 62066S

    PACV- 51008 S TO 52055S

    Multiple Unit Installation

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    15/65 | 15

    INSTALLATION,

    Multiple Units Installation (Modular

    Construction)

    t.

    Recommendations

    It is a necessity that the units are installed with adequate

    free space around them to ensure proper circulation ofair that is rejected by the condensers and to provide

    adequate space for unit access for servicing and

    maintenance. There is a possibility of recycling of air

    if the rejected air from condenser encounters any

    obstacles leading to an increase in the ambient air

    temperature surrounding the units.

    Air distribution across the entire heat exchange

    area will be impaired if the air outlet is obstructed.

    These conditions lead to a reduction in the

    heat exchange capacity of the coils causing

    an increase in discharge pressure of the

    compressors. This leads to a loss of capacity &increase in compressor power input

    Units should not be

    completely shrouded

    with higher uninterrupted

    wind shield in order to prevent

    reversing of airflow. In case, sucha confi guration cannot be avoided,

    a properly designed exhaust duct

    or hood that does not influence

    any additional pressure a properly

    designed exhaust duct or hood that

    does not influence any additional

    pressure on the fans and which of the

    same hight as surrounding shield to be

    installed.

    PACV- 51008 S TO 52055S

    PACV- 61009 S TO 62066S

    DUCT

    DUCT

    B

    If there are walls on one or two adjacent sides of the unit.

    The walls may be of any height. If there are walls on more

    than two adjacent sides of the unit. The walls should not behigher than the unit.

    Do not locate outside air intakes near exhaust vents or

    other sources of contaminated air.

    If the unit is installed where windy conditions are common,

    install wind screens around the unit.

    Units surrounded byscreensor solid walls must have no

    over head obstructions over any part of the unit.

    The area above the condenser must be installed

    unobstructed to allow vertical air discharge.

    A flat concrete foundation or floor which can support the

    weight of the equipment must provided as the unit must be

    level for proper operation and functioning of controls.

    Under certain critical conditions it is recommended thatvibration isolators of rubber-in-shear or spring type beinstalled under the base refer to loading points(Page 49).

    Electrical

    Pre-Installation Check-Up

    IMPORTANT: When installi ng t he unit , always

    disconnect the electric supply.

    Make sure that the power supply is compliant with current

    safety standards. Always install the air conditioner in

    compliance with current local safety standards.

    Verify that suitable grounding connection is available.

    Verify that the voltage and frequency of the power supply

    comply with the specifications and that the installed poweris sufficient to ensure the operation of any other domestic

    appliance connected to the same electric lines.

    Verify that the air conditioner is connected to the power

    supply in accordance with the instructions provided in the

    wiring diagram included in the manual.

    Verify that electric connections (cable entry, section

    of leads, protections....) are compliant with the electric

    specification and with the instructions provided in the

    wiring scheme. Verify that all connections comply with the

    standards applicable to the installation of air conditioners.

    Figure 9

    Foundation

    A flat level concrete foundation which can support the weight of

    the equipment must be provided.

    Where units are to be located, over steel trusses or on a steel

    platform, careful analysis to ensure proper distribution of weight

    onto the structural members should be ensured. The steel platform

    should be strong enough to hold the operating weight.

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    16/65 16 |

    OPERATION

    Avoid installing the equipment in the

    following:

    In areas where it is exposed to

    direct sunlight. Close to any heat

    source.

    In damp areas or locations where

    it could come into contact with

    water.

    In areas where curtains and

    furniture could affect the supply

    and discharge of air.

    In areas in which there is no

    enough space around the unit.

    (Must install as per the required/

    recommended spacing, shown in

    the lay out drawings).

    On surfaces that are unable to

    support the weight of the unit

    without deforming, breaking or

    causing vibrations when the unit

    is running.

    General

    Do NOT install the equipment in a location

    where it will come in contact with the

    following elements :

    Combustible gases

    Saline air

    Machine oil

    Sulphide gas

    Special environment conditions,

    if you must install the unit in such

    conditions, first consult SKM.

    Carrying Out Installation

    1. Unpack the unit carefully.

    2. Unfasten or dismantle transport locks.

    3. Packing material to be fully removed and disposed.

    4. The unit base frame must be fixed without stresses to the

    supporting structure.

    5. AVM to be regularly placed around centre of gravity and

    firmly fixed. Check whether AVM is balanced under load.

    6. No forces or vibrations may be transferred from other plant

    parts.

    7. The flexible connections at intake and/or discharge should

    be installed, well aligned and freely moving.

    8. The AVM should be freely moving and under even load.

    9. The impeller should be turning idly and should not touch

    the intake cone.

    10. The stability against collapse of the unit should be checked.

    Preparation For Installation

    When deciding on the location of the unit with the

    owner, the following restrictions must be taken into

    consideration:

    The discharge air from the condenser fan

    should not be obstructed by any roofing,

    shelter, ducting etc. Any obstruction will

    cause short circuiting of condenser fans leading

    to reduction in capacity or nuisance tripping of

    the PACV-Spackage unit from the high pressure

    control and sometimes in motor burnout .

    Condensate Draining

    It is mandatory to install a properly sized drain trap in order toensure proper draining of condensate collected in the drain pan.

    Below mentioned are recommendations for sizing a drain trap.

    Measure the maximum negative static pressure upstream from

    the fan. The height H1 shown in belowfigures must be greater

    than or equal to the negative static pressure at design conditions.

    Ensure that there is sufficient water in the trap before starting in

    order to maintain the seal.

    H1= 1 f or each 1 of negative static pressure + 1

    H2= H1/2

    H= H1 + H2+ Pipe Diameter + Insulation

    Condensate traps serving the cooling coils should be of sufficient

    height to be effective.

    The unit should be located on a suitable base to provide adequate

    height from the ground in order to accommodate the drain trap.

    Figure 10

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    17/65 | 17

    OPERATION

    Pre-Startup Procedure

    After the installation has been completed, the following points

    should be covered before the system is placed in operation.

    Precaution: Carry out a fan test run

    Risk of injury from rotating impeller!

    Never reach into t he impeller when the fan

    is in operation.

    a. Check electrical connections. Be sure they

    are all tight.

    b. Observe compressor oil level before start-up.

    The oil level should be at or slightly above the

    center of the sight glass. Use only oil approved

    by compressor manufacturer.

    c. Remove or loosen shipping retainers undermotor- compressors. Make sure hold down

    nuts on spring mounted compressors are nottouching the compressor feet.

    d. Check high and low pressure controls,pressure regulating valves and all other safety

    controls, and adjust if necessary.

    e. Check refrigerant used in the system.

    f. Wiring diagrams, instruction bulletins, etc

    attached to PACV-S units should be read

    and filed for future reference.

    g. Make the proper refrigerant connections

    and charge the unit with the refrigerant to

    be used. Weigh the refrigerant drum before

    charging so an accurate record can be kept

    of the weight of refrigerant put in the system.h. Observe system pressures during charging

    and initial operation. Do not add oil while the

    system is short of refrigerant, unless oil level

    is dangerously low.

    i. Continue charging until system has sufficient

    refrigerant for proper operation. Do not over-

    charge. Remember that bubbles in a sight

    glass may be caused by a restriction as well

    as a shortage of refrigerant.

    j. Do not leave unit unattended until the system

    has reached normal operating conditions and

    Pre Startup Checklist

    Make sure the power supply voltage and frequency

    are as given in the unit name plate.

    Make sure that unit has been installed in accordance

    with the installation instruction and applicable codes.

    Check all electrical connections in unit control panel;

    tighten them as required.

    Make sure the compressor oil level is within the

    sight glass range.

    Check the power supply phase sequence for proper

    direction of rotation of motors.

    Make sure all system hand valves are in fully open

    position and system contains an operating charge

    of refrigerant.

    Switch on the power supply to the unit

    Crank case heaters of all compressors to be

    energized at least 24 hours prior to start up.

    PACV-S unit is factory charged

    Please make sure to open supply air

    dampers fully (if any) before starting the

    fan motor. Otherwise, blower fan can be

    damaged due to back pressure and warranty

    will be void.

    Take measures to prevent centrifugal fan

    from being switched on accidentally.

    Clear the ducting system and fan of all foreign

    bodies (tools, small parts, construction

    waste, etc.).

    Close all the inspection openings.

    Switch on fan and check direction of rotation

    of impeller by comparing it with the arrow on

    the fan indicating the direction of rotation. If the direction of rotation is wrong, reverse

    the polarity of the motor having due regard to

    the safety instructions.

    Once operating speed has been reached

    measure the current consumption and

    compare it with the nominal motor current on

    the fan type plate or motor rating plate.

    If there is continuous overload switch the

    centrifugal fan off immediately.

    Check that the fan runs smoothly and quietly.

    Ensure that there are no unusual oscillations

    or vibrations.

    Check the motor for any abnormal noises.

    Prior to starting up the unit, we

    recommend checking if the following

    steps have been carried out:

    the oil charge has been properly adjusted to maintain the oil level

    at the center of the sight glass.

    If the state of the fan does not allow adapted

    action for repair it has to be put out of

    order immediately and to be replaced if

    required.

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    18/65 18 |

    OPERATION

    Operational Check-Out

    After the system has been charged and has operated for

    at least two hours at normal operating conditions without

    any indication of malfunction, it should be allowed to operate

    over-night on automatic controls. Then a thorough recheckof the entire system operation should be made as follows:

    a. Compressor manufacturer model and serial number.

    b. Equipment manufacturer model and serial number.

    c. Design operating temperatures.

    d. Refrigerant and weight of charge.

    e. Electrical service, volts, cycles, phase, wire size.

    f. Control circuit, voltage, breaker size.

    g. Contactor or starter, manufacturer, model, size, part

    number.

    h. Compressor motor protection(if available), type, size,

    part number.

    i. Data on relays or other electrical components.

    j. Pressure control, type, size, model number, setting.

    k. Data on miscellaneous components such as pressure

    controls, crankcase heaters, solenoids, valves, etc.

    l. Liquid line drier, manufacturer, size, model number,

    connections.

    m. Schematic diagram of refrigerant piping.

    n. Final settings on all pressure, regulating and safety

    controls.

    o. Microprocessor details

    a. Check compressor head and suctionpressures. If not within system design limits,

    determine why and take corrective action.

    b. Check liquid line sight glass and expansion

    valve operation. If there are indications that

    more refrigerant is required, leak test allconnections and system components and

    repair any leaks before adding refrigerant.

    c. When applicable, observe oil level in

    compressor crankcase sight glass, and addoil as necessary to bring level to center of

    the sight glass.

    d. Thermostatic expansion valves must be

    checked for proper superheat settings.Sensing bulbs must be in positive contact with

    the suction line. Valves with high superheat

    settings produce little refrigeration and poor

    oil return. Too little superheat causes low

    refrigeration capacity and promotes liquid

    slugging and compressor bearing washout.

    Liquid refrigerant must be prevented from

    reaching the crankcase. If proper control

    cannot be achieved with the system in normaloperation, a suction accumulator must be

    installed in the suction line just a head of the

    compressor to prevent liquid refrigerant from

    reaching the compressor.

    e. Using suitable instruments, carefullycheck line voltage and amperage at the

    compressor terminals. If high or low voltage

    indicated, notify the power company. The

    current normally should not exceed 120%

    of the nameplate rating. If amperage draw

    is excessive, immediately determine the

    cause and take corrective action. On three

    phase motor-compressors, check to see that

    a balanced load is drown by each phase.

    f. All fan motors on air cooled condensers,

    evaporators, etc should be checked for

    proper rotation. Fan motor mounts should

    be carefully checked for tightness and properalignment. If belt drives are used, check the

    belt tension. All motors requiring lubrication

    should be oiled or greased as necessary.

    Service Record

    A permanent data sheet should be prepared on each

    installation, with a copy for the owner and the original for the

    installing contractors files. If any other firms are to handle

    service and maintenance, additional copies should be prepared

    as necessary.The form of the data sheet may vary, but a complete record

    of sizes and identification of all components used in theinstallation, together with any pertinent information should be

    included. Following is suggested check-off list:

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    19/65 | 19

    OPERATION

    Unit Start Up

    Sequence of OperationThe unit may be enabled or disabled through the Run/

    Stop toggle switch in the unit mounted control panel or

    from the room unit on/off button. Control is based on room

    temperature sensed by room unit(for units with duct sensor

    ,control is based on duct temp). Evaporator fan motor

    starts first. Compressors will be staged based on the set

    point and actual room temperature. On an increase inroom temperature, cooling stages will be added and

    on a decrease in room temperature, cooling stages

    will be removed from the system. Sequence for the

    compressors and motors are as given below:

    Switch on the three phase power supply to the unit.

    Switch on the control circuit breakers. Unit controller

    will start up.

    Check for any alarms in the controller. If there are

    any alarms, correct the cause and clear them.

    Turn on the Run/Stop toggle switch in the unit

    control panel.

    Press the power button in the room unit. Then

    supply fan will start.

    Make sure the refrigerant circuits are enabled in

    the relevant circuit screen in the controller display.

    Compressors will start based on the temperature setpoint set in the room unit and the indoor temperature.

    Make sure that the unit is in cooling mode, which

    can be selected from the room unit.

    Condenser fans will start with compressors and will

    cycle based on discharge pressure.

    Supply FanSupply fan will be switched on if the belowconditions are satisfied.

    Controller start up is finished.

    Run/Stop switch in the unit controlpanel is ON.

    Room unit power icon is ON.

    Room unit schedule is ON (If schedule is

    disabled, then unit will run continuously)

    Communication between unit controller

    and room unit is healthy.

    Motor overload is healthy.

    Voltage Monitor is healthy.

    Supply fan has two modes; ON (continuouslyON) or AUTO (ON when there is cooling or

    heating demand).

    Compressor

    Compressor will switch on if the below conditions

    are satisfied.

    Compressor minimum OFF time

    completed.

    Supply fan runs for 30 seconds.

    Circuit enable (from controller display)

    is enabled. Unit is in cool mode.

    Demand for compressor is present.

    Discharge pressure and motor protector

    module (if available in compressor) are healthy.

    If above are satisfied, solenoid valve will be opened

    and when the low pressure switch closes, compressor

    will be started.

    A typical two compressor control is as shown below:

    Condenser fans

    Condenser fans will switch on with associated compressor(s)

    and cycle based on discharge pressure.

    For single compressor units or units with circuits having

    independent condenser fans, condenser fans will be

    switched on based on the discharge pressure of that

    circuit. Each fan will switch on if pressure is above the

    stage on value and will switch of if the pressure is below

    stage off value.

    For units with more than one compressor sharing the

    condenser fans, the highest pressure among the circuits

    will be taken to cycle the fans.

    Unit Control ler Display and Keypad

    The keypad/display of the controller consists of a 64 x 144 screen

    resolution 5 line 22 character display screen,3 buttons and a push

    & turn knob for navigation.

    Buttons

    Info button: This is used to enter the unit information screen

    where the SKM Unit model & serial number can be viewed.Alarm but ton: This is used to enter directly the alarm screen for

    viewing the alarm details & to reset them manually if required.

    Esc button:This is a back button to move back to the previous

    screen or to the home screen.

    Push & Turn Knob

    This is a navigation wheel that can be rotated as well as pushed.

    Rotating the wheel navigates between the lines of the screenand also to change/edit the changeable values on the screen.

    Clockwise rotation increases the values and anti-clockwise rotation

    decreases the value. Pushing the wheel acts as an Enter button

    to acknowledge the changed value.

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    20/65 20 |

    OPERATION

    If supply fan is not starting, navigate to these screens to find out

    the reason. In order for the supply fan to start, the Run/Stop input

    should be Run, Room Unit should be On, Schedule Status

    should be On in case the schedule is enabled, Motor over load

    should be healthy and Voltage monitor should be healthy.

    Circuit ScreenEach circuit screen will show the status of all the inputs and

    outputs related to that circuit.

    These will show the status of supply fan motor (On or Off), Circuit

    enable/disable selection, Unit mode (Cool, Heat, Auto or Vent),

    Discharge pressure (Healthy or Trip), Suction pressure (Healthy

    or Trip), compressor motor protectors if available (Healthy or

    Trip), compressors (On or Off) and liquid line solenoid valve

    (Open or Closed).

    Note that circuit can be enabled or disabled from the controller

    display itself. In order to do that, highlight the Circuit Enable line

    and then press the navigation wheel. Then rotate the navigation

    wheel in order to enable or disable the circuit and then press

    the wheel.

    Unit operating mode selection is from the Room unit.

    Condenser fans

    These screens will show the discharge pressures of each circuit

    and status of the condenser fans.

    Schedule

    The schedule screen will allow setting the On time and Off time

    for each day of the week. If the schedule is enabled, then unit

    will work based on this schedule only.

    Set poin ts

    This screen will show the temperature set point and actual indoor

    temperature (or duct temperature if optional duct sensor is used).

    If factory password is entered, then set points screen will show

    access to factory parameters as well.

    The main displayscreen consists of a5 line display, with

    the first linedisplayingthe page title and a numeric display

    of the number ofalarms along with the symbol if any

    alarmsare present. Second& third lines display the date &

    time respectively. There arethreesubmenus inthe display

    namely, SYSTEMOVERVIEW, PASSWORD &ALARMS.

    Everypagecan consist of data fields, eitherchangeable or with

    information only. As the cursormoves over each line, thetext

    in thelineis highlighted with ablackbox around it and the text

    turning white. As thenavigation wheel is rotated thesubsequent

    lines get highlighted witha black box around them. When a line

    consists of anarrow in the far rightof the page, it isreferred to as

    amenu group. When the navigation wheel ispushed, the display

    goesto a new page consisting of thesubmenus. Thetitleof the

    menu group appears as the title of the new page.

    Figure:Rotation of the navigation wheel

    Figure: Pushing the navigation wheel

    The system overview menu consists of information on

    thesupply fan, circuits, condenserfans, andset points.

    These submenus give more information on the unit

    including safeties and status of compressors, motors

    and setpoints. Different screensof thecontrollerare

    as given below.

    Main ScreenThis screen will show date & time,system over view,

    password & alarms.

    SystemOverviewSelecting thesystem overviewwill lead tobelow

    screens

    Fromthe abovetwo screens, further navigation

    is possible to different screenswhich will giveinformation about supply fan,each refrigerant

    circuit, condenser fans, schedule and set points.

    Supply fan

    Thebelow screens will give information about all

    theinputs andoutputs relatedto supply fan.

    Display and Keypad operation

    .

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    21/65 | 21

    OPERATION

    Factory parameters will show Compressor Minimum offtime, Compressor Minimum On time, Low pressure alarm

    delay, Cooling step, Cooling Differential, Condenser Stage1

    On pressure, Condenser Stage1 Off pressure, Condenser

    On Differential pressure, Condenser Off Differential pressure,

    Schedule enable/disable, Clearing alarm history and software

    BSP version of the controller.

    Note that factory parameters should be changed only by SKM.

    Unit InformationThis screen will provide the information about the unit model

    name and SKM serial number.

    Alarms

    This screen will show alarm list and alarm history.

    Pressing the alarm list will show all the active

    alarms. All alarms will be with date & time and will

    be in easily readable English language.

    Note that some of the alarms (like high

    discharge pressure) are manual reset. In orderto acknowledge the manual reset alarms, follow

    below steps.

    Below Screen will appear.

    Rotate the Navigation wheel and then screen will show

    Exe...

    Press the navigation wheel and all the alarms which are

    not active will get reset.

    List of Alarms in the Unit Controller

    Below are the various alarms configured in the Unit controller.

    Supply Fan Motor: Trip

    This alarm occurs when the overload of supply fan motor detects

    an overload condition in the motor. When this alarm happens,

    entire unit will be switched off. This alarm is auto reset as standard.

    Voltage Monitor: Trip

    This alarm occurs when the voltage monitor connected in the

    main incomer detects an under voltage or over voltage or phase

    reversal or phase imbalance or single phasing condition. Whenthis alarm happens, entire unit will be switched off. This alarm is

    auto reset as standard.

    Room Unit Communication: Lost

    This alarm occurs when the unit controller looses communication

    with the room unit. When this alarm happens, entire unit will be

    switched off. This alarm is auto reset as standard.

    Circuit-# Suction Pressure: Trip

    This alarm occurs when the low pressure switch senses a low

    suction pressure in the refrigerant circuit. This alarm will be

    generated, if one refrigerant circuit is On for cooling demand

    and the low pressure switch doesnt close for a specific time (low

    pressure alarm delay set point). When this happens, corresponding

    circuit will be switched off and alarm will be generated. This alarm

    is automatic reset as standard.

    Circuit-# Discharge Pressure: Trip

    This alarm occurs when the high pressure switch senses a

    high discharge pressure in the refrigerant circuit. This alarm

    will be generated, if the high pressure switch remains open for

    one second. When this happens, corresponding circuit will be

    switched off and alarm will be generated. This alarm is manual

    reset as standard.

    Compressor-# Motor Protector: Trip

    This alarm will be generated only for those compressors with a

    built in electronic motor protector module. It occurs when the motor

    Enter the user password 1234 (Refer

    Passwords)

    Go to alarm list screen and press

    acknowledge

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    22/65 22 |

    OPERATION

    If the room unit address is not set correctly, it will display as

    below (P- - blinking).

    Passwords

    In order to enter the password, use Password screen.Follow the below steps.

    Go to the Password screen in the Main Menu.

    Use the navigation wheel to enter password

    (Rotate to change and Press to select.). If user

    password is required, enter 1234.

    Once the password is entered, a number

    corresponding to the password level will

    appear on left top of the screen. For user

    password, it will be 4.

    Operation of the Room Unit

    The room unit displays indoor temperature (duct temperature if

    optional duct sensor is used), temperature set point, unit on/off

    status, unit operating mode, fan mode, day of the week, time of

    the day and schedule. Room unit will let the user to make the

    unit on/off, change the operating mode, change the fan mode,adjust the set point, change the temperature measurement unit,

    change date & time and operating schedule.

    Adjust the set point, change the temperature measurement unit,

    change date & time and operating schedule.

    Press power button, mode button, minus button and

    plus button simultaneously as shown below.

    Setting the address in Room Unit

    Room unit will display the software version as below.

    Press mode button; room unit will display parameter 001

    as below, with 001 blinking

    22 |

    asswor s

    In order to enter the password, use Password screen.Follow the below steps.

    Go to the Password screen in the Main Menu.

    wordUse the navi ation wheel to enter ass

    (Rotate to change and Press to select.). If user

    password is required, enter 1234.

    Once the password is entered, a number

    corresponding to the password level will

    appear on left top of the screen. For user

    password, it will be 4.

    Power Button

    Minus Button

    Mode Button

    Plus Button

    protector module senses a high internal temperature

    in the compressor. When this happens, corresponding

    circuit will be switched off and alarm will be generated.

    This alarm is automatic reset as standard.

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    23/65 | 23

    OPERATION

    Press plus button multiple times to reach

    parameter 005. At this stage parameter 005

    will be blinking. On pressing mode button;

    parameter value will start blinking. Use plus

    button or minus button to make it 005 as

    shown below (if it is already 0005, no need

    to do this step). Press mode button again,

    then parameter 005 will start blinking.

    Press plus button to reach parameter 006.

    At this stage parameter 006 will be blinking.

    Press mode button and then use plus

    button or minus button to make the value

    0002 (if it is already 0002, no need to do

    this step). Press mode button again, then

    parameter 006 will start blinking.

    Press plus button to reach parameter 007. At

    this stage parameter 007 will be blinking. Press

    mode button and then use plus button or

    minus button to make the value 0003 (if it is

    already 0003, no need to do this step). Press

    mode button again, then parameter 007 will

    start blinking.

    Press plus button multiple times to get back

    to parameter 001. Then press power button,

    the version screen will be displayed.

    Press power button again, then room unit

    will show normal display as below.

    Switching on and switching off the unit

    Press the button to make the unit on and off. When the unit is

    on, will be shown on the display.

    Changing the Unit operating mode

    Operating mode of the unit can be changed by pressing button.There are two modes for cooling only units and four modes for

    units with electric heater. The modes are cool ( ), heat ( ),

    auto cool-heat ( ) and Vent ( ). Note that in vent mode,

    compressors or heaters ( if available ) will not operate.

    Changing the fan operating mode

    Operating mode of the fan can be changed by pressing the button.

    There are two modes for the fan which are Auto ( ) and On ( ).

    Auto means the supply fan will run only when there is cooling or

    heating demand. On means supply fan will run continuously. Inthe units where there is much changes in temperature, always

    use On mode.

    Changing the Set poin t in Room Unit

    Press + and - buttons to adjust the temperature set point.

    Changing the Temperature display un it

    Long press the button to toggle the temperature display unitbetween oCelsius and oFahrenheit.

    Alarm Indication

    In case if there is any alarm present in the unit, will blink onthe room unit display. Once the alarms are cleared from the unit

    controller, then the alarm symbol will disappear.

    Time and Day of the week

    Room unit will show the time in 12 hour format and the day of

    the week. Day of the week will be 1 for Monday, 2 for Tuesday,

    3 for Wednesday, 4 for Thursday, 5 for Friday, 6 for Saturday

    and 7 for Sunday.

    Time and Date Setting

    By pressing the button, user will enter time and date setting.

    Pressing + or -button can change the variables those are

    blinking on the screen, while pressing button will confirm the

    changes and the cursor will move to the next variable automatically.

    The first view is time setting, user can change 3 items: hour,minute and time for-mat. The view is showed as follows:

    Firstly the hour area will be blinking; pressing + or - canchange the number of hour, pressing will confirm the changes

    and the cursor will move to the minute area automatically.

    After the number of minute is confirmed, the whole time areawill blink. Pressing + or -button will switch time format

    between 12-hour with AM/PM and 24-hour. It will shows as

    )

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    24/65 24 |

    OPERATION

    After the year is confirmed, it will jump to the view of month

    and day. The view is showed as follows:

    After the month and day is confirmed, HMI-SG will return

    to the view of time. Press button PROG or there is no any

    operation for 1 minute, it will exit the setting.

    follows in 24-hour time format:

    After the time format is confirmed, HMI-SG will jumpto the view of year. It will show as follows:

    ENTER PASSWORD

    ENTRY ****

    CIRCUIT-1SUPPLYFAN MOTOR : OFF

    CIRCUIT1 ENABLE : ENABLE

    UNIT MODE : VENT

    DISCH.PRES.-1 : TRIP

    SUCT.PRES-1 : HEALTHY

    COMPRESSOR-1 : OFF

    SOL.VALVE-1 : CLOSED

    SUPPLY FAN

    RUN/STOP INPUT : STOP

    ROOM UNIT : ON

    ON/OFF SCHEDULE : ENABLE

    SCHEDULE STATUS : ON

    FAN MODE : ON

    MOTOR OVERLOAD : TRIP

    VOLTAGE MONITOR : TRIP

    SUPPLY FAN MOTOR : OFF

    CIRCUIT-2

    SUPPLYFAN MOTOR : OFF

    CIRCUIT2 ENABLE : ENABLE

    UNIT MODE : VENT

    DISCH.PRES.-2 : TRIP

    SUCT.PRES-2 : HEALTHY

    COMPRESSOR-2 : OFF

    SOL.VALVE-2 : CLOSED

    CONDENSER FANS

    DISCH.PRES.-1 : XX.X PSI

    DISCH.PRES.-2 : XX.X PSI

    _____________________________FAN-1 : OFF

    FAN-2 : OFF

    FAN-3 : OFF

    FAN-4 : OFF

    SCHEDULE

    MONDAY:

    SCHEDULE-1: HH: MM-HH:MM

    TUESDAY:

    SCHEDULE-1: HH: MM-HH:MM

    WEDNESDAY:

    SCHEDULE-1: HH: MM-HH:MM

    THURSDAY:

    SCHEDULE-1: HH: MM-HH:MM

    FRIDAY:

    SCHEDULE-1: HH: MM-HH:MM

    SATURDAY:

    SCHEDULE-1: HH: MM-HH:MM

    SUNDAY:

    SCHEDULE-1: HH: MM-HH:MM

    MAIN MENU

    DATE

    TIME

    SYSTEM OVERVIEW

    PASSWORD

    ALARMS

    SYSTEM OVERVIEW

    SUPPLY FAN

    CIRCUIT-1

    CIRCUIT-2

    CONDENSER FANS

    SCHEDULE

    SETPOINTS

    HMI PASSWORDENTER PASSWORD

    CLOSE ACCOUNT

    ALARMS

    ALARMLIST

    ALARMHISTORY

    FACTORY SETTINGS

    COMP.MIN.OFF TIME : XXX s

    COMP.MIN.ON TIME : XXX s

    LP ALARM DELAY : XXX s

    COOLING STEP : XX.X C

    COOLING DIFF. : XX.X C

    COND.STG1 ON : XXX PSI

    COND.STG1 OFF : XXX PSI

    COND.DIFF.ON : XXX PSI

    COND.DIFF.OFF : XXX PSI

    ON/OFF SCHEDULE : Enable

    SETPOINTS

    TEMP.SETPOINT : XX.X C

    : XX.X C

    FACTORY SETTINGS

    BSP VERSION

    CLEAR ALM HIST

    : X.XX: PASSIVE

    INDOOR TEMP

    An Overview Of Menu Structure

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    25/65 | 25

    OPERATION

    Table 5

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    26/65 26 |

    MAINTENANCE

    26 |

    Periodic MaintenanceFollowing Checklist describes the suggested maintenance schedule to maintain proper operation of the unit. Detailed

    procedures are mentioned in the corresponding pages.

    The above mentioned schedule is typical and will vary largely based on si te conditions.

    Table 6

    Component Checkl ist Weekly Month ly Hal f Yearly Annual ly

    EvaporatorFan/MotorSection

    General Yes

    Check for Corrosion andRepaint as Necessary

    Yes

    Check amperage draw onblower motor

    Yes

    Check condensate lineand clean if necessary

    Yes

    Check for correct voltageat unit

    Yes

    Motors General Check Yes

    Check for unusual noisefrom the motor

    Yes

    Check all wiring for loose

    connectionsYes

    Filter SectionAir filter to be washed &cleaned

    Yes

    Evaporator CoilSection

    Check for Debris /Blockage over fins & cleancoil if necessary

    Yes

    Check connecting lines,joints & coil for evidenceof oil leaks

    Yes

    Operation LevelMaintenance

    Oil Level at Sight Glass Yes

    Superheat at Compressor Yes

    Crank Case HeaterOperation

    Yes

    Refrigerant Sub cooling inLiquid Line

    Yes

    Operating Pressures Yes

    Control Panel

    Dust & Debris on PowerTerminals/ Contactors/Loose Cable Lugs

    Yes

    Check for correct voltageat unit (Unit operating)

    Yes

    Check Unit Operation Yes

    Check for alarms in UnitMicroprocessor

    Yes

    Condenser Fan& Motor

    Check for Vibrations &Noise

    Yes

    Check unbalance of theFan

    Yes

    Motor Bearings to bechecked

    Yes

    Corrosion Yes

    Fan Blades to be checked/Balancing

    Yes

    Condenser CoilSection

    Check connecting lines ,joints & coil for evidenceof oil leaks

    Yes

    Clean & inspect outdoorcoil , wash with water ifnecessary

    Yes

  • 7/24/2019 7.Installation,Operation & Maintenance(IOM)

    27/65 | 27

    MAINTENANCE

    Never use oxygen fo r pressurizing a

    system; an explosion may occur if oil

    is present in the system. Always use

    a gauge equipped pressure regulator

    on the high pressure back-up gas, and never

    interconnect the refrigerant cylinder and the

    inert gas cylinder through a gauge manifold.

    Nitrogen and carbon dioxide cylinder pressures

    can rupture a refrigerant cylinder.

    6.Apply heat evenly over the length and circumference of thejoint to draw the brazing material into the joint by capillaryaction. Remove the brazing rod and flame from the joint assoon as a complete fillet is formed to avoid possible restriction

    in the line.

    7. Visually inspect the connection after brazing to locate anypin holes or crevices in the joint .

    Never solder, braze or weld on

    refrigerant lines or any unit

    components with pressures that are

    above atmospheric pressure or where

    refrigerant may be present. Always remove

    refrigerant by following the local guidelines.

    Af ter ref rigerant removal, use dry ni trogen to

    bring system back to atmospheric pressure

    before opening system for repairs. Mixtures of

    refrigerants and air under pressure may become

    combustible in the presence of an ignition sourceleading to an explosion. Excessive heat from

    soldering, brazing or welding with refrigerant

    vapours present can form highly toxic gases

    Failure to follow all proper safe refrigerant

    handling practices could result in death or

    serious injury!

    Maintenance

    The maintenance of this equipment shall be in accordance

    with the regulation of authorities having jurisdiction and

    all applicable codes. It is the responsibility of the installer

    to determine and follow the applicable codes. Low head

    pressure may lead to poor, erratic refrigerant feed control at

    the thermostatic expansion valve. The units have automatic

    control of the condenser fans which should provide adequate

    head pressure control down to 50 F (10 C) provided the

    unit is not exposed to windy conditions. The system design isresponsible for assuring the condensing section is not exposed

    to excessive wind or air recirculation.

    ProceduresIt is quite probable that a majority of operating failures can be

    traced to careless or inadequate maintenance procedures. The

    following instructions have been prepared to help the service

    engineer systematically cover the many points which must

    be considered to provide each installation with trouble freeperformance.

    Take extreme care to keep refrigeration tubing clean and

    dry prior to installation. The following procedures should be

    followed:

    Brazing Procedures

    1. When copper is heated in the presence of air,Copper oxide forms. To prevent copper oxide fromforming inside the tubing during brazing, an inert gas

    should be passed through the line at low pressure

    to prevent scaling and oxidation inside the tubing.

    Dry nitrogen is preferred. Nitrogen displaces air

    in the tubing and prevents oxidation of the interior

    surfaces. A pressure regulating valve is to be usedto control the flow.

    2. Ensure that the tubing surfaces to be brazedare clean, reaming at the ends of tubes isto be done to remove any burrs and keep the

    surface even.

    3. Make sure the inner and outer tubesof the joint are symmetrical and have aclose clearance, providing an easy slip fit. If

    the joint is too loose, the tensile strength of

    the connection will be significantly reduced.

    The overlap distance should be equal to the

    diameter of the inner tube.

    4. Wrap the body of each refrigerant linecomponent like expansion valve, solenoidvalve, Hot gas bypass with a wet cloth to keep

    it cool during brazing. Move any tube entrance

    grommets away for the brazing area.

    5. Flux , when used is to be applied in smallquantities only. Excessive flux, when used,can enter the system and contaminate the

    refrigerant system.

  • 7/24/2019 7.Installation,Operation & M