75th st. corridor improvement project cost …createprogram.org/fastlane_2016/grant linked...
TRANSCRIPT
75th St. Corridor Improvement Project
COST ESTIMATE REVIEW
Final Report
September 2014
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
2 | P a g e
TABLE OF CONTENTS
EXECUTIVE SUMMARY ........................................................................................................... 4
CHAPTER 1 – REVIEW PROCESS .............................................................................................. 9
REVIEW OBJECTIVE...................................................................................................................... 9
BASIS OF REVIEW......................................................................................................................... 9
REVIEW TEAM ........................................................................................................................... 10
DOCUMENTS REVIEWED ........................................................................................................... 10
REVIEW METHODOLOGY........................................................................................................... 11
CHAPTER 2 – REVIEW SUMMARY ......................................................................................... 17
PROJECT BACKGROUND, PURPOSE AND NEED ......................................................................... 17
REVIEW FINDINGS ..................................................................................................................... 22
REVIEW RECOMMENDATIONS .................................................................................................. 23
CHAPTER 3 – RISK ANALYSIS ................................................................................................ 24
COST FORECAST ........................................................................................................................ 24
SCHEDULE FORECAST ................................................................................................................ 27
REVIEW CONCLUSION ............................................................................................................... 30
ALTERNATIVE ANALYSIS SIMULATION ........................................................................................... 30
APPENDICES ........................................................................................................................ 31
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
3 | P a g e
FIGURES
Figure 1 Year of Expenditure Cost Probability Curve ...................................................................... 4
Figure 2 Probability Based Project Completion Date ..................................................................... 6
Figure 3 75th Street CIP Project Study Area ................................................................................. 20
Figure 4 Distribution of Total Project Costs in YOE Dollars ......................................................... 25
Figure 5 Project Potential Schedule ............................................................................................. 28
TABLES
Table 1 CER Results vs. Pre-CER Cost Estimate ............................................................................... 5
Table 2 Base Variability ................................................................................................................. 12
Table 3 Market Condition - Probability of experiencing cost increase/decrease ........................ 14
Table 4 Market Conditions Variance from "As-Planned" ............................................................. 14
Table 5 Project Inflation Rates ...................................................................................................... 16
Table 6 Base Estimate Adjustments .............................................................................................. 21
Table 7 Base for CER Analysis ....................................................................................................... 21
Table 8 Project Summary Schedule Dates .................................................................................... 22
Table 9 Percentile Rankings of Total Project Costs in YOE Dollars ............................................... 26
Table 10 Simulation of Delayed Project Start ............................................................................... 30
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
4 | P a g e
EXECUTIVE SUMMARY
A review team (Team) of the Federal Highway Administration (FHWA), the Illinois Department
of Transportation (IDOT) and their project consultants, the City of Chicago Department of
Transportation (CDOT), the Association of American Railroad (AAR) and railroad representatives
conducted a Cost Estimate Review (CER) to evaluate the cost and schedule estimates for the
proposed 75th Street Corridor Improvement Project (75th Street CIP), a project proposed as part
of the Chicago Region Environmental and Transportation Efficiency (CREATE) Program. The CER
was held at the Chicago, Illinois office of Jacobs Engineering Group, Inc. (IDOT Phase I Project
Consultant) from June 23 through June 26, 2014.
The objectives of the review were to:
Verify the accuracy and reasonableness of the current project estimate (including all
engineering, ROW, construction and other costs) and schedule.
Develop a probabilistic range for the cost estimate that represents the project’s current
stage of development (i.e., Phase I engineering).
Determine potential schedule impacts on the cost.
Range of Project Cost
Figure 1 Year of Expenditure Cost Probability Curve
70% = $952 M
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
5 | P a g e
The CER cost probability curve in Figure 1 shows the potential range of project cost in Year of
Expenditure (YOE) dollars. FHWA requires the 70% level of confidence value or greater to be
used for major project Financial Plans and for published project documents. At a 70%
confidence level the CER YOE project cost is $951.9 million, which is 3.4% below the pre-CER
Project YOE cost estimate of $984.4 million provided by the project team (see also Table 1).
Two different approaches were used to arrive at the pre-CER (project team method) and the
CER (FHWA method) estimates. However, the CER estimate used the pre-CER base estimate
(2014 dollars) as its starting point. The difference in the estimate values can be attributed to a
combination of several actions taken in applying the FHWA approach to the pre-CER base
estimate, including removing the estimate contingency and adding in risk-based costs, adjusting
the base cost estimate using revised information provided during the review, and reducing the
inflation factor from 4.5% per year in the pre-CER estimate to 3.5% in the current CER.
Table 1 CER Results vs. Pre-CER Cost Estimate
The CER results are based on the Team’s input related to base estimate variability, market
conditions, inflation and risk factors for the project. The resulting range of probable project
costs from the 10% to 90% confidence levels is from $877 million to $984 million.
Based on this review, the 70% level of confidence amount of $951.9 million (YOE) is the
minimum that should be utilized in the current financial plan being prepared for the project,
with the use of a range recommended.
Risk Threats and Opportunities
The CER process began with removing contingencies from the pre-CER estimate, and then
adding the impact of base variability, market conditions, inflation and identified risks to arrive
at the CER results noted. The major cost threats identified that could potentially increase
project costs were:
Base Project YOE Pre-
CER Estimate
(with Contingency)
70% Level of Confidence
from CER YOE
Probability Curve Results
(with risks)
Delta /
Pct. Delta
Total Project Cost with
Inflation and previous /
fixed costs
$984.4 Million $951.9 Million $32.5 Million /
3.4%
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
6 | P a g e
Structure Superstructure Cost Increases
Structure Substructure Cost Increases
Potential Construction Change Orders
The major Schedule threats that could potentially delay the project’s originally estimated
schedule and increase inflation costs are the following:
Right-of-way (ROW) Acquisition delay to project
Existing Railroad Operations during construction
Delays in the construction of new Bridge structures
Utility Relocation delays
Full project funding
Social and political sensitivities
A Schedule Opportunity was also modeled:
Opportunity to Avoid delays due to mild winter weather
The results of modeling the above schedule risks (threats and opportunities) are:
Figure 2 Probability Based Project Completion Date
70% = 10/29/2022
Pre-CER scheduled completion:
10/31/2021
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
7 | P a g e
Figure 2 demonstrates that the current schedule has substantial risk of delay. The model shows
the range of predicted project completion dates with a 70% confidence level at the end of
October 2022, which is an approximate 12 month delay beyond the pre-CER scheduled
completion of the end of October 2021. This potential delay is the result of the impact of the
previously mentioned schedule threats.
Findings and Recommendations
The major findings during the CER included the following:
The Pre-CER estimate detail is advanced for level of design (preliminary engineering)
Relevant unit prices were utilized from IDOT/CDOT/ Railroads’ experience and project
complexity (i.e-CREATE –P1 project) and were found to be reasonable
The team had performed an analysis of risks specific to unique CREATE partnership (i.e.-
maintaining freight rail operations through construction)
Most construction is proposed within existing ROW, except portions of the east end of
P2
The structural elements of the project have been designed to the preliminary
engineering level (i.e. 30% plans) and are therefore relatively early in the design stage,
with greater uncertainty
Alignment geometrics and project limits have been tightly established via the input
received from CREATE partners and preliminary engineering/NEPA/public involvement
processes
Railroad force account work (vs. bid work) is expected to experience less risk due to
limited ROW needs and previously developed force account/firm labor contract
conditions and pre-established cost control procedures
The recommendations resulting from the review were the following:
Manage risk of structures cost uncertainty and scope creep
Mitigate potential or avoid change orders via strong design and construction
management practices, such as risk management and cost and schedule controls.
Manage schedule risks leading up to project construction, such as ROW acquisition,
utility relocation, track outages.
Contractors (non-railroad) should be ready to utilize good winter weather
Update and QA overall estimate as decisions are made, market conditions change, or other threats or opportunities are avoided, minimized, mitigated or realized
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
8 | P a g e
Coordinate early on with Utility service providers and other contractors to inform them
of Buy America Requirements, advise potential contractors of this requirement and how
it could impact their material procurement
Understand utility costs and impact on schedule
Continue coordination and communication through the CREATE partnership
Continue proactive public outreach and involvement into the final design and
construction phases
Continue implementing risk management procedures, using the risk register
Update the cost estimate based on risk management process
Ensure that the project management plan addresses risk response strategies for
identified risks
In conclusion, the 70% level of confidence amount of $951.9 million (YOE) is the minimum that
should be utilized in the current financial plan being prepared for the project, with the use of a
range recommended.
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
9 | P a g e
CHAPTER 1 – REVIEW PROCESS
A review team (Team) consisting of the Federal Highway Administration (FHWA), the Illinois
Department of Transportation (IDOT) and their project consultants, the City of Chicago
Department of Transportation (CDOT), the Association of American Railroad (AAR) and other
railroad representatives conducted a Cost Estimate Review (CER) to evaluate the cost and
schedule estimates for the proposed 75th Street Corridor Improvement Project (75th Street CIP),
a project proposed as part of the Chicago Region Environmental and Transportation Efficiency
(CREATE) Program. The CER was held at the Chicago, Illinois office of Jacobs Engineering Group,
Inc. (IDOT Phase I Project Consultant) from June 23 through June 26, 2014.
This document summarizes and reports the results of this review. Appendix D of this report
includes the Team’s close-out presentation provided on June 26.
The purpose of this chapter is to provide a general overview of the cost estimate review
process, including a discussion of the review objectives, team members, documentation
provided and methodology.
REVIEW OBJECTIVE
The objective of the CER was to conduct an unbiased risk‐based review to:
Verify the accuracy and reasonableness of the current total cost estimate to complete
the project
Develop a probabilistic range for the cost estimate that represents the current stage of
project design (i.e., Phase I engineering).
Determine potential schedule impacts to the project cost.
This review is a snapshot in time and it is recognized that the estimate will change as additional
information becomes available.
BASIS OF REVIEW
The Moving Ahead for Progress in the 21st Century (MAP-21) Act (P.L. 112-141) requires the
financial plan for all Federal‐aid projects with an estimated total cost of $500M or more to be
approved by the Secretary of Transportation (i.e. FHWA) based on reasonable assumptions. The
$500M threshold includes all project costs (i.e. Engineering, Construction, Right‐of‐Way (ROW),
Utilities, Construction Engineering, Inflation, etc.). The FHWA policy has established reasonable
cost variability assumptions to be utilize as a risk based analysis. A CER is required to provide
the risk based analysis of the estimate for a project over $500M and is used in the development
of the financial plan.
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
10 | P a g e
The base estimates for the 75th Street Corridor Improvement Program were well above the
$500M, qualifying the project for the CER. The Team was able to present the scope of the
project, the basis for the current cost estimate, and input on the risks, market conditions and
other variables used in the CER analysis.
REVIEW TEAM
The Team brought together individuals with a strong knowledge of the project, including
expertise in specific disciplines represented in the project design. Throughout the CER
individuals with specific project expertise briefed the Team on technical issues and the estimate
development process, including the development of quantities, unit prices, assumptions,
opportunities and threats.
The Review Team was comprised of members of the following organizations:
FHWA
CREATE Program Manager
Resource Center Construction and Project Management (CPM) Team
Atkins Consultant
CREATE partner Railroads/Association of American Railroads Illinois DOT/Dept. of Public & Intermodal Transportation Chicago DOT Illinois DOT/CREATE Program Management Consultant
HNTB Project Consultant
Jacobs
The list of all CER attendees / participants is included in Appendix E on sign-in sheets.
DOCUMENTS REVIEWED
Documents provided to the Review Team prior to and during the workshop included:
Project Cost Estimate, including narrative of cost estimating methodology
Project Schedule
Project Risk Register
Current NEPA Documents
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
11 | P a g e
Project Web Site Link
5-year construction sequencing plan for the project
REVIEW METHODOLOGY
The methodology for this cost estimate review is outlined as follows:
Verify Accuracy of Estimate
– Review major cost elements, descriptions, cost components and assumptions
– Review allowances and contingencies
– Adjust estimate as necessary
Discuss / Model
– Base Variability
– Market Conditions & Inflation
– Key Schedule & Cost Risks
Perform Monte Carlo simulation to generate a forecast range of estimated project costs
Communicate Results to the Project Team
VERIFY ACCURACY OF COST ESTIMATE
The Team was provided a project overview, including the scope of the project, stage of design
and the IDOT consultant cost estimating process utilized. A review of project documents
including the physical layout (e.g. maps, drawings) was also provided. The Team attended a site
visit on the initial day of the study, receiving a comprehensive overview of the construction
sites and the existing conditions of the project corridors. The Team also interviewed the
subject matter experts (SMEs) and developed an understanding of the estimate for both
quantity and unit cost development for the major cost categories.
MODEL PROJECT UNCERTAINTIES AND PERFORM MONTE CARLO SIMULATION
In general, uncertainties in the project estimate can be described as those relating to base
variability, market risks, inflation, cost and schedule risk events. Each of these were discussed
and modeled to reflect the total uncertainty associated with the estimate.
Base variability is a measure of uncertainty applied to the base estimate that represents the
inherent randomness associated with the estimating process. For example, if a different
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
12 | P a g e
estimator were to develop the estimate using the same data source and following the same
general guidance his/her estimate would be different from that of the first estimator. Base
variability is also a function of the project’s current level of design and the process used to
develop the estimate. Additionally, the lack of details about the project and assumptions that
should be used to develop the estimate would cause more variability in the estimate. This base
variation is a function of the system (i.e., assumptions and data sources used to define the
estimate). Base variability has been applied to the base estimate exclusive of risks.
Contingencies that include risks are removed from the estimate to avoid double counting risks
identified in the risk register. Allowances, such as items included as percentages of other items
in early estimates, and change orders typically remain in the base estimate.
Base variability is defined using a symmetrical distribution and often stated as a percentage
variation from the underlying base estimate. The team considered the variability to be +/- 9%
as shown in Table 2. This assumes the project is relatively well defined and has advanced
engineering and identification of issues, such that reasonable estimators would fall within +/-
9% of the current estimate at this point in the project. This base variability was developed with
the input that the non-railroad (civil infrastructure) elements of the project were defined to a
point where a base variability of 10% was deemed appropriate. The railroad portion of the
project is very well defined (when compared with the civil infrastructure improvements) and
the unit prices are likely to be more stable into the near future because of long term labor and
other contracts, thus minimizing the potential for variance within a range of near 8%. This is
combined with the potentially greater variability of the non-railroad elements, thus resulting in
a composite of near 9%.
Portion Final Design Right of Way
Acquisition Utility Relocation Construction
Base Variability +/- 9% +/- 9% +/- 9% +/- 9%
Table 2 Base Variability
Market Conditions - The Team discussed the uncertainties associated with Market Conditions at
the time of the construction procurement, when contractors or suppliers are pricing the
project. There is typically a strong relationship between the number of bidders and the
construction cost of a project at the time of pricing. Market conditions are a measure of
uncertainty that reflects the overall competitive environment at the time of pricing. The market
conditions are applied to the base estimate using a probability for “better than planned”, “as-
planned”, or “worse than planned” bidding environments (totaling 100%). The Review team
had discussion regarding the major projects competing for local resources during the years
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
13 | P a g e
2017 – 2021, which is the planned schedule for 75th Street CIP construction. Major competing
projects and markets for resources include the following:
Utilities market: $300 million to $400 million per year is anticipated for the next 10 years, with
a resource constrained market that could likely drive up utility costs.
Highway Market: Anticipated competing projects include, but may not be limited to:
the I-90/I-94/I-290 Circle Interchange in downtown Chicago (schedule through 2018),
the current “Illinois State Toll Highway Authority (ISTHA)” program, although that program
is expected to taper after 2016 and wrap-up by 2020; and
the Illiana Expressway, although there is no ROD yet.
Comments identified that the highway construction market in Illinois is currently stressed;
however, there is minimal design underway at this time pointing to a decreasing IDOT program.
A potential increase could be in bridge rehabilitation projects.
Transit Market: The Chicago Transit Authority (CTA) has a $500 million per year capital
program for the next four years, with the potential for slight increases, particularly if funding is
identified for major rail projects such as the Red Line Extension or Red Purple Modernization
projects. . The CTA program beyond the next four years is relatively uncertain. Metra commuter
rail has substantial identified needs, but funding and time line for addressing these needs is
unknown at this time.
Aviation Market: Chicago O’Hare airport is unlikely to have large projects that will impact the
75th Street CIP project. The largest project planned at O’Hare is the consolidated rental car
facility (CONRAC) that is unlikely to have an impact on Highway / Rail projects.
Facilities Market: The vertical facilities market is relatively slow in the area at this time, with
most construction being apartments.
Rail Market: there is a “Positive Train Control” mandate for trains by 2015. It is not anticipated
that this mandate will impact the 75th Street CIP.
After discussing these local market factors, the team did not foresee any reason to forecast a
large market condition increase (worse than planned) or a large market condition decrease
(better than planned) for construction pricing. However, the Team forecasted market risk
increases with Utilities and Right-of-Way (ROW) costs, and utilized the following probability
distribution in the model:
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
14 | P a g e
Project Element
Market Conditions
Probability of experiencing cost increase/decrease
Better Than
Planned As-Planned
Worse Than
Planned
Final Design / ROW / Utility costs 10% 60% 30%
Construction (projects P2 and P3) 8.5% 83% 8.5%
Construction (project EW2) 8% 84% 8%
Construction (project GS19) 10% 80% 10%
Table 3 Market Condition - Probability of experiencing cost increase/decrease
Table 3 notes the CER team’s expectations for future cost proposals on this project. Note that
each of the different design portions of the project have slightly differing ranges, with EW2
predicted to have the least market conditions impact since it is primarily railroad elements; P2
and P3 are slightly higher with a mix of railroad and civil work, and GS19 is even higher since it
is primarily civil and structural work. When the market condition variations shown in Table 3
occur, the Team expected the variance from the current estimate (As-Planned) as shown in
Table 4.
Project Element
Market Condition Cost Impact
(Variance from As-Planned)
Better Than Planned Worse Than Planned
Final Design, ROW, Utility costs 5% 10%
Construction (projects P2 and P3) 10% 15%
Construction (project EW2) 10% 15%
Construction (project GS19) 10% 15%
Table 4 Market Conditions Variance from "As-Planned"
Table 4 also illustrates that the CER Team generally considered cost increases (worse than
planned) would be of greater potential magnitude than if the variances are below the estimate
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
15 | P a g e
(better than planned). This demonstrates the Team’s expectation that, should price escalation
from market conditions occur, it could have an increasing cost impact on the project.
Following the market conditions review, the CER Team discussed the project cost estimate (See
Appendix A), and established the risk register for both the cost and the schedule
threat/opportunity risks (See Appendix B). The project team provided a Pre-CER risk register
that was utilized to initially populate the CER risk register. (Where appropriate, cost elements
with multiple risks or groups of like risk elements were consolidated to reduce the number of
total risks entries . Each of these risks was then analyzed by the Team based on current project
conditions, and additional risks were also developed during the CER.
The risk register includes the event risk name, a description of the event, a probability measure
of the likelihood the event will occur, and a probability distribution of costs if the event were to
occur. The register also identifies if the risk event is a threat or opportunity for cost/schedule.
Risk threats increase costs/schedule length and opportunities decrease cost/schedule length . A
very important feature of the risk register is to establish the relationship of risk events. For
example, some risks are mutually inclusive/exclusive. Mutually inclusive means the risk event
can only occur if the prior risk event occurs. Conversely, for a risk event to be mutually exclusive
means that it can only occur if the prior risk event does not occur. Risk events can also be
independent in which case the probability of occurrence is not dependent on any other risk
event. Correlation determines how one risk event will sample relative to another risk event.
Correlation was established when there was reason to suspect that a relationship exists and
should be accounted for in the simulation.
After model inputs were developed for market conditions, base variability, and risk events, the
Team utilized the Monte Carlo simulation to generate a probability based estimate in Year of
Expenditure Total Project Costs. The simulation provides “what‐if” sensitivity analysis using
randomly selected values from the Team’s models. The simulation performs random sampling
to model thousands of project cost/schedule scenarios built from the Team’s input. The
simulation is run until the number of iterations creates a relatively smooth distribution curve. It
is important that the simulation outcomes be reviewed to ensure accuracy. The simulation
results from distribution curves covering all possible outcomes as shown in Figures 1 and 2 in
the Executive Summary. The key benefit of this process is that estimated cost and schedule
outcomes are associated with their probability of occurrence (See Appendix C).
Inflation usually has a significant impact on Year of Expenditure (YOE) Total Project Costs, and
its affects were modeled in this review. Costs were inflated using the current project schedule
and inflating to the midpoint of the planned expenditure for each project element (P2, P3, EW2,
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
16 | P a g e
GS19), including any delays where appropriate. The inflation applied to the base estimate
utilized annual inflation rates per year (See Table 5). These inflation rates are based on a
discussion held by the project team where rates from 3% to 3.5% per year were expected.
After input from the 75th Street CIP cost estimating team, 3.5% for construction activity costs
and 3% for pre-construction professional services and relocations was agreed to. An inflation
rate of 4.5% was utilized for the pre-CER cost estimate. All other CREATE projects are inflated at
the 4.5% level.
Year’s Applied Final Design, ROW,
Utilities Construction
2014 to midpoint of phase/project
3.0% / year 3.5% / year
Table 5 Project Inflation Rates
The base dates for each project element are based on the preliminary 5-year construction
sequencing plan developed and agreed upon by the CREATE Program partners immediately
prior to the CER review.
COMMUNICATE RESULTS
The last part of the review is to communicate the results. This is accomplished by providing the
closeout presentation and final report to the Project Team and agency leaders. At the end of
the review, the CER Team provided a closeout presentation that summarized the review
findings. The presentation identified the review objectives and agenda, discussed the
methodology, available resources, estimate adjustments and highlighted the results of the
review. The closeout presentation also identified any significant cost and schedule risks, and
provided a brief overview of recommendations by the Review Team. This presentation is
included as Appendix D to this report.
It is important to understand that the estimate review is a snapshot in time of the estimate. As
additional information becomes available it is expected that the estimate will change and be
updated.
This final report communicates all findings of the review to the State DOT and the FHWA
Division office and serves as the official document for the CER. As noted earlier, the review
results are used in published reports and eventually in the approval of the financial plan. CER
reports are maintained by the FHWA Office of Innovative Program Delivery’s Project Delivery
Team in Washington D.C.
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
17 | P a g e
CHAPTER 2 – REVIEW SUMMARY
PROJECT BACKGROUND, PURPOSE AND NEED
The Chicago Region Environmental and Transportation Efficiency (CREATE) Program was initiated in 2003 as a public‐private partnership to improve the rail and roadway transportation network within the Chicago area. The CREATE 75th Street Corridor Improvement Project (CIP) consists of four (4) supporting projects of independent utility, linked by the NEPA environmental clearance process. A substantial portion of freight and passenger rail traffic in the Chicago region suffers from congestion, low operating speeds, and service delays due to traffic demands that exceed the capacity of the regional rail system. The CREATE Program Final Feasibility Plan established overall Program Level Goals and Strategies and the CREATE Program Final Preliminary Screening (both published in August 2005) presented the purpose or objective of each component project within the program. These documents have since been amended and modified, most recently in January 2012. Based on the needs to improve the regional rail system, the goals of the CREATE Program are as follows:
Reduce rail and motorist congestion;
Improve the efficiency and reliability of freight and passenger rail service;
Enhance public safety through the reduction of rail-highway conflict points;
Promote economic development and job creation;
Improve air quality; and
Reduce noise from idling or slow moving trains throughout the Chicago metropolitan area. As part of meeting the CREATE goals, the purpose of the 75th Street Corridor Improvement Project (CIP) is to improve mobility for rail passengers, freight, and motorists. The specific needs of this project include:
Reducing conflicts that affect rail;
Reducing highway-rail crossing problems;
Reducing local mobility problems; and
Improving rail transit passenger service. Five (5) private railroad operators (RR) have been instrumental in assessing their own operational and infrastructure needs within the 75th Street CIP project area. In coordination with CREATE partners and consultant staff, independent capital costs estimates were developed for each railroad operators’ rail infrastructure improvements as well as signal
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
18 | P a g e
systems required for efficient operations. CREATE RR partners participating in the 75th Street CIP include:
BRC – Belt Railway Company of Chicago
BNSF
B&OCT- Baltimore & Ohio Chicago Terminal Railroad (CSX) also known as CSX Transportation
CP
IHB
Metra – Metra Commuter Rail
NS – Norfolk Southern Railway
UP – Union Pacific Railroad The 75th Street CIP capital cost estimate was prepared to allow for the independent quantification and calculation of construction and professional service costs of the four (4) CREATE Program component projects (P2, P3, EW2, and GS19) that make up the 75th Street CIP. A description of the major construction components associated with each of these projects is shown below: P2 – Metra South West Service (SWS) Connection to Rock Island District (RID) Line
New rail flyover structure for a passenger rail connector through residential area
Metra flyover bridge on 40 MPH reverse curve, connecting to the RID Line at 74th St
ROW acquisition from the neighborhood south of Hamilton Park = 1.39 acres (No ROW required from Hamilton Park)
P3 ‐ B&OCT Yard Flyover of 75th Street Junction also known as Forest Hill Junction
Raise the two compass north/south CSX tracks over the east/west tracks at 75th Street Junction and over 71st Street (GS19)
Two (2) temporary tracks constructed east of existing B&OCT tracks (property owned primarily by City of Chicago) during construction
EW2 – 80th Street Junction
Two (2) additional tracks through 80th Street Junction
Relocates Amtrak, B&OCT and UP operations from the west side of corridor to east side of corridor
New bridge constructed for the UP over 88th Street t
New NS track constructed from I‐94 (Dan Ryan) north and west to Landers Yard
ROW acquisition of vacant land between two sets of RR tracks north of Vincennes Ave
and south of 80th Street Junction
Add second mainline track southeast of existing Metra track along Columbus Avenue, through existing NS Landers Yard
Reconfigure tracks in Landers Yard
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
19 | P a g e
GS19 – 71st Street Grade Separation
Depress 71st Street profile by approximately 3 feet to provide vertical clearance of 16’‐6” beneath the new rail structure. Total length of reconstruction ≈ 660 feet.
The CREATE Railroad partners generally staff their own, independent teams for construction of trackwork, signals and associated facilities (known as force account work). Under certain circumstance, Railroads may use the services of outside contractors specifically for grading activities, environmental mitigation, structures, roadway improvements, and track construction. In general, all CREATE Program project grade separations are contracted by the State or by local Agencies. The GS19 project segment, however, may be an exception where the structure work may be included with the scope of work of the P3 project, which may be led by CSX. Project phasing and funding – For the CER, the assumption was the 75th Street CIP would be built as one complete project, with all funding available prior to bidding, and a five-year construction schedule. The project team also wanted to document that MAP-21 (the federal transportation funding bill) allows projects to include a phasing plan that identifies fundable incremental improvements or phases that will address the purpose and the need of the project in the short term in the event there are insufficient financial resources to complete the entire project. Given the substantial total capital cost of the Preferred, there is some potential the entire project cost will not be provided in a single allocation, but will rather be provided over a number of years. Based on these considerations, an initial conceptual construction phasing plan for the project consisting of at least two major phases has been developed and will be considered with future CERs as appropriate. The specific sequence and duration of each of these phases will be adjusted to match the funding that is made available for the project as it is identified in future years. Each of these major phases could be built and would function as a viable transportation facility with substantial transportation benefits even if the other phases were never constructed. Each of these major phases is therefore considered to have operational independence and meets some element(s) of the project purpose and need. In order to meet all elements of the project purpose and need though, completion of all of the separate phases is necessary. The two major potential phases of the overall project are: P3/GS19 and P2/EW2.
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
20 | P a g e
Figure 3 75th Street CIP Project Study Area
BASE ESTIMATE
The project team provided a cost estimate prior to the workshop. This pre-review estimate of
project cost was $818.5 million in 2014 dollars, and $984.4 million escalated to year of
expenditure (YOE) costs. The summary for this base estimate is shown in Appendix A of this
report.
BASE ESTIMATE ADJUSTMENTS
During the review of the project and estimate details, certain items came to the attention of
the review team that were considered to be adjustments to the base estimate, as opposed to
being risks for potential cost changes. These estimate adjustments are summarized as follows:
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
21 | P a g e
Estimate Item Adjustments during CER Change to Base Estimate
($ in millions)
Final Design from 6% to 9% on different set of categories (now 1-9) $30.75
Public Outreach from .5% to 1% $4.03
Legal/permits from .5% to .25% ($0.38)
RR flagging, CEI and OH for RR company ($0.6)
Merged CEI and CM (total reduced from 8% to 7% for non-RR work) ($6.12)
MOT on contract P3 was removed (1% previous) ($1.35)
Temporary Facility Utility Relocation, Temporary ROW easements allowances for GS19 grade separation removed when line item cost was moved from Category 5.0 (Structures) to Category 2.0 (Civil)
($1.15) ($0.6)
($0.06)
Reduced Program Mgmt from 4% to 1% on different set of categories (now 1-9)
($8.9)
Total Estimate Adjustments $15.6
Table 6 Base Estimate Adjustments
This $15.6 million adjustment to the base estimate increased the present day estimate from
$818.5 million to $834.1 million that was used as the base for the CER. The $834.1 million
included $119.4 million of contingencies that were removed from the estimate to establish the
base CER value prior to adjusting for base variation, market conditions, risks and inflation. The
CER base was calculated using the following:
Item Description Cost Estimate Value
Pre-CER Base Present Day Cost Estimate $818.5
Cost Estimate adjustments during CER $15.6
Subtotal Cost Estimate Base $834.1
Removal of Contingency from Cost Estimate ($119.4)
Exclusion of expended/fixed costs (1) ($10.4)
Base Estimate for CER Analysis $704.3
Table 7 Base for CER Analysis
Note (1): The $10.4 million of expended / fixed costs is related to the preliminary engineering
and environmental document work (i.e., Phase I engineering) that has been completed or is
under contract.
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
22 | P a g e
SCHEDULE
Table 8 outlines some of the project milestone schedule dates.
Project Phase / Scope Schedule Start
Date Scheduled
Completion Date
P2 – Final Design / Right-of-Way / Utilities 4/1/2015 7/30/2017
P3 – Final Design / Right-of-Way / Utilities 4/1/2015 7/30/2017
EW2 – Final Design / Right-of-Way / Utilities 2/1/2015 10/1/2017
GS19 – Final Design / Right-of-Way / Utilities 4/1/2015 7/30/2017
P2 - Construction 8/1/2017
11/30/2020
P3 - Construction 8/1/2017
8/30/2019
EW2 - Construction 8/1/2017
10/31/2021
GS19 - Construction 10/1/2017
10/31/2019
Table 8 Project Summary Schedule Dates
The schedule date table is the current concept for the project that will be refined over time.
These dates were utilized primarily to develop the proper inflation calculations for the year of
expenditure estimates for the project.
REVIEW FINDINGS
Several findings were noted during the CER, including the following:
The Pre-CER estimate detail is advanced for level of design (preliminary engineering)
Relevant unit prices were utilized from IDOT/CDOT/ Railroads’ experience and project
complexity (i.e-CREATE –P1 project) and were found to be reasonable
The team had performed an analysis of risks specific to unique CREATE partnership (i.e.-
maintaining freight rail operations through construction)
Most construction is proposed within existing ROW, except portions of the east end of
P2
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
23 | P a g e
The structural elements of the project have been designed to the preliminary
engineering level (i.e. 30% plans) and are therefore relatively early in the design stage,
with greater uncertainty
Alignment geometrics and project limits have been tightly established via the input
received from CREATE partners and preliminary engineering/NEPA/public involvement
processes
Railroad force account work (vs. bid work) is expected to experience less risk due to
limited ROW needs and previously developed force account/firm labor contract
conditions and pre-established cost control procedures
REVIEW RECOMMENDATIONS
The following recommendations resulted from this review:
Manage risk of structures cost uncertainty and scope creep
Mitigate potential or avoid change orders via strong design and construction
management practices, such as risk management and cost and schedule controls.
Manage schedule risks leading up to project construction, such as ROW acquisition,
utility relocation, track outages.
Contractors (non-railroad) should be ready to utilize good winter weather
Update and QA overall estimate as decisions are made, market conditions change, or other threats or opportunities are avoided, minimized, mitigated or realized
Coordinate early on with Utility service providers and other contractors to inform them
of Buy America Requirements, Advise potential contractors of this requirement and how
it could impact their material procurement
Understand utility costs and impact on schedule
Continue coordination and communication through the CREATE partnership
Continue proactive public outreach and involvement into the final design and
construction phases
Continue implementing risk management procedures, using the risk register
Update the cost estimate based on risk management process
Ensure that the project management plan addresses risk response strategies for
identified risks
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
24 | P a g e
CHAPTER 3 – RISK ANALYSIS
Cost estimates, especially those for Major Projects, usually contain a degree of uncertainty due
to unknowns and risks associated with the level of detailed design completion. For this reason,
it is logical to use a probabilistic approach and express the estimate as a range rather than a
single discrete value. During the cost estimate review, uncertainties in the Project estimate
were modeled by the Team to reflect the opinions of the Subject Matter Experts (SMEs)
interviewed. The Team used the Monte‐Carlo simulation to incorporate the uncertainties into
forecast curves representing the expected range of cost and schedule for the Project.
These probability based estimates provide essential components to the decision making
process. Probability accounts for the uncertainty and reflects the collective “best guess” of
SMEs. A probability distribution can be used to represent the estimate’s Total YOE Project
Costs. Since the dollars represent YOE, the curve is often referred to as a forecast curve. The
forecast curve of YOE Total Project Cost for this Project is discussed below.
COST FORECAST
The forecast distribution curve for the project (shown in Figure 4 below and also as Figure 1 in
the Executive Summary) reflects all the underlying variation and risks associated with the
project. The variation and risks include base variability, market conditions at time of letting (i.e.
competition, supply and demand), inflation and project risks.
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
25 | P a g e
Figure 4 Distribution of Total Project Costs in YOE Dollars
Figure 4 demonstrates the results of the simulation and the proximity of the project pre-CER
YOE estimate ($984 Million) to the 70% probability guidance of $952 million, including to-date
and fixed costs. These costs include construction, design/engineering,
administration/overhead, right-of-way, inflation and contingencies (expressed in YOE dollars),
and depict the following:
The blue shaded (darker shade on left) area, represents a 70% probability that the total
cost for the cost will be less than $952 million dollars.
The red shaded area (lighter shade on right) of the graph represents a 30% probability
that total project costs will exceed $952 million based on the underlying variation within
the estimate.
The 70% result of $952 million is lower than the pre-CER estimate of $984 million by $32
million dollars, or approximately a 3% difference. This variance is a combination of
adjustments to the base estimate during the CER, the assessment of risk, and the
reduction of inflation from 4.5% in the pre-CER estimate to 3.5% in the CER.
Table 9 displays the probability range of forecast YOE costs from results in Figure 4:
70% = $952 M
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
26 | P a g e
Percentile Forecast values
0% $783,264,643
10% $876,945,471
20% $894,251,316
30% $908,217,603
40% $920,158,763
50% $930,286,668
60% $940,368,522
70% $951,904,257
80% $965,439,258
90% $984,108,792
100% $1,079,809,439
Table 9 Percentile Rankings of Total Project Costs in YOE Dollars
Table 9 demonstrates that the 20% to 80% range for the cost estimate is approximately $894 to
$965 million; a variance of approximately 8% between these values. The ranges below 20% and
above 80% are extremely wide and demonstrate the uncertainty of costs for this project should
extreme opportunities and/or risks be realized.
PROJECT RISKS (THREATS AND OPPORTUNITIES)
The purpose of the Risk Register is to identify significant cost and schedule risks for the project
so they can be modeled instead of assuming general contingency values. In the traditional cost
estimate, risks are often accounted for using estimates of contingency. During this review, the
pre-CER estimate contingency was removed, and the team developed the potential threats
and/or opportunities in lieu of contingency items. The Review Team worked together with the
SMEs to develop the threats and opportunities shown in the Risk Register in Appendix B to this
report. The most significant of these cost risks that could impact the project included the
following:
THREATS TO INCREASE PROJECT COSTS
Structures Superstructure Cost Increases: Likelihood of occurrence 80%; Most likely
impact if occurring $29 million
The Team identified the potential for large increases in the superstructure costs for structures
as the design progresses. Currently the structures are at a conceptual design level consistent
with Phase I preliminary engineering projects. As final design proceeds there is the risk or
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
27 | P a g e
greater structural reinforcement; beam or deck replacement, and widening than currently
estimated.
Structures Substructure Cost Increases: Likelihood of occurrence 80%; Most likely
impact if occurring is $14 million
The Team identified the potential for large increases in the substructure costs for structures as
the design progresses. Currently the structures are at a conceptual design level, and as final
geotechnical information is available and final design proceeds there is the risk of substructure
requirements that are more costly than presently estimated.
Potential Change Orders during construction: Likelihood 100%: Most likely impact
per portion of the project: P2-$8.9; P3-$12.8; EW2-$11.9; GS19-$1.2
The team agreed that there would likely be change orders during construction due to elements
such as unforeseen conditions or unanticipated changes to the design. A potential range of
impact was agreed to and modeled as from a low of 2% to a high of 10%, with a most likely of
6% of project costs for P2, P3 and EW2. The railroad work on these portions of the project are
expected to have a lower change order percentage than the civil work, and these composite
percentages were agreed to. For the portion GS19, a range of low of 5% to a high of 15%, with
a most likely of 10% of project costs was used, as this portion is all civil work and has a greater
potential for variance based on the team’s experience.
Other threats modeled that were low in probability and potential impacts include the potential
for additional railroad track replacement should there be design changes to the geometry of
the track layout, additional temporary track and signal work for extended duration or if portion
P3 is not first in the project sequence, potential additional work on the viaducts, and
miscellaneous potential quantity variances.
OPPORTUNITIES TO REDUCE PROJECT COSTS
There were no opportunities modeled related to the potential reduction of project costs. It was
part of the discussion that being able to mitigate the largest cost threats (structures increases
and construction change orders) will in effect reduce the costs of the project. The management
of these threats in effect is the opportunity to reduce project costs.
SCHEDULE FORECAST
Figure 5 (same as Figure 2 from the Executive Summary) displays results showing a low
probability for the project to end at the current scheduled completion date of October 31,
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
28 | P a g e
2021. The 70% probability level results in a date of October 29, 2022, approximately 12 months
after the current planned date of October 31, 2021. This variance can be attributed to the
significant schedule risks that have been identified and need to be managed. These threats are
described in the following section.
Figure 5 Project Potential Schedule
THREATS TO DELAY PROJECT SCHEDULE
Delay to Right of Way Acquisition; Likelihood – 80%; Most Likely Impact – 9 months
The CER Review Team discussed the potential for the delay of ROW acquisition on portions P2
and EW2 of the project. The potential acquisition delays are from 6 months to 12 months, with
a most likely impact of 9 months. Part of this delay threat is the current schedule that includes
2 years per portion of the project for completion of final design and right-of-way acquisition,
and the Team considered that this could be somewhat aggressive. There was discussion during
the CER that IDOT could ask for legislative approval for "quick take" authority to advance ROW
Acquisition to help mitigate this potential schedule threat.
Current Schedule Completion:
10/31/2021
70% = 10/29/2022
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
29 | P a g e
Existing Railroad Operations delaying construction: Likelihood – 50%; Most Likely
Impact – 3 months
The review team identified the threat, ensuring rail operations continue unimpeded by
construction during peak times, could extend the duration of project portion EW2 from 2 to 4
months, with the most likely impact being 3 months. Mitigation of this threat will require close
coordination between the railroads and the contractor related to peak time needs and
potential conflicts.
Bridge Structure material delivery delays: Likelihood – 50%; Most Likely Impact – 3
months
Potential delay in the delivery of fabricated material for bridge structures could have an impact
on the schedules for bridge construction, with a potential impact modeled from 1 month to 4
months, with the most likely impact being 3 months. The advanced scheduling and
coordination of any long lead-time materials will help mitigate this potential delay.
Bridge Structure construction delays: Likelihood – 50%; Most Likely Impact – 2 months
There is the potential that work on certain bridge structures may have to be delayed due to
work on other structures in the area and the importance of maintaining vehicular traffic. This
impact was modeled with a range of 1 to 4 months of potential delay. Mitigation of this threat
would be close coordination and scheduling of bridge construction well in advance to minimize
local maintenance of traffic.
Utility Relocation delays: Likelihood – 30%; Most Likely Impact – 3 months
The relocation of utilities was determined by the Team to have a 30% likelihood of impacting
the construction schedule. Should this threat occur, the impact was in a range from 1 to 5
months, with 3 months being the most likely delay. Communication and coordination with the
utility companies will mitigate much of this delay, although the threat of encountering
unknown utilities could still have an impact.
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
30 | P a g e
OPPORTUNITIES TO ADVANCE PROJECT SCHEDULE
Avoiding Weather Impacts: Likelihood – 60%; Most Likely Impact – 3 months
The current construction schedule assumes 4 months per year of slowed or inactive
construction due to the impact of inclement weather.The team considers that there is an
opportunity that this schedule could be improved should the winter weather be better than
typical and/or the contractor is able to schedule specific construction during the winter months.
REVIEW CONCLUSION
The results of the review demonstrate that the contingency amount in the pre-CER estimate
was sufficient to cover the risks identified during the CER, with the 70% result of $952 million
being approximately 3% less than the per-CER estimate of $984 million. There are major
threats for the team to manage, including the initial schedule threats to right-of-way acquisition
and utility relocation. There are also opportunities during the design stage to avoid some of the
major cost threats, and during the construction stage by aggressively managing scope changes,
to potentially reduce the overall project costs.
ALTERNATIVE ANALYSIS SIMULATION
The Team discussed a simulation option to model the threat of the project being delayed by 3
years due to funding constraints. The objective was to determine the potential total cost impact
of such a delay and an approximate monthly cost impact. This simulation was based on
delaying the start of final design for the portions of the project from 12/1/2014 to 12/1/2017.
This 3 year delay simulation resulted in the following:
Version 70% Cost Result
Current CER $952 million
Simulation with 3 yr delay to start $1,055 million
Delta $103 million
Delta Cost per month (delta / 36 months) $2.9 million / month
Table 10 Simulation of Delayed Project Start
The conclusion of this simulation is that for every month of delay to the start of the project the
project cost increases approximately $2.9 million, assuming that the cost escalation is in the
range of 3.5% per year. Note that this is a “straight line” calculation and does not examine the
compounding of inflation costs over time.
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
31 | P a g e
APPENDICES
APPENDIX A – Pre-CER Project Cost Estimate
APPENDIX A1: Updated Cost Estimate for CER Model
APPENDIX B – CER Risk Register
APPENDIX C – Crystal Ball Probability Analysis Results
APPENDIX D – Closeout Presentation
APPENDIX E – Workshop Agendas and Sign-in Sheets
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
32 | P a g e
APPENDIX A – Pre-CER Project Cost Estimate
CREATE - 75th ST CIPCost Estimate Review (CER)
DRAFT Project Summary
Revised: 5/12/2014
(DRAFT) CREATE 75th ST CIP: Summary of CER Inputs
Segment
LOOKUPPE/ENV Final Design ROW / Utility Construction
Construction
Related Prof SvcsPE Final Design ROW / Utility Construction
Construction
Related Prof Svcs
CREATE Phase I
Contingency &
Mgmt ResP2 $2,695,090 $6,800,338 $8,075,709 $148,873,168 $17,958,342 $0 $0 $1,615,142 $29,774,634 $0 $31,389,775
P3 $3,879,335 $9,451,679 $7,661,970 $214,289,326 $25,574,258 $0 $0 $1,532,394 $42,857,865 $0 $44,390,259
EW2 $3,602,048 $5,160,968 $7,886,081 $198,972,363 $20,501,911 $0 $0 $1,577,216 $39,794,473 $0 $41,371,689
GS19 $246,832 $799,055 $640,015 $13,634,660 $1,802,988 $0 $0 $128,003 $2,726,932 $0 $2,854,935
Segment Total $10,423,305 $22,212,040 $24,263,776 $575,769,517 $65,837,499 $0 $0 $4,852,755 $115,153,903 $0 $120,006,659
Check vs Detail $10,423,305 $22,212,040 $24,263,776 $575,769,517 $65,837,499 $0 $0 $4,852,755 $115,153,903 $0 $120,006,659
CREATE Total
Base Year
Estimate
Summary
No Contingency
With Phase I
Contingency &
Mgmt Res
Year of
Expenditure
Estimate
Summary
No Contingency
With Phase I
Contingency &
Mgmt Res
Base Yr (2013)
Project Totals
Base Yr (2013)
Project Totals
Future (Inflated)
Project Totals
Future (Inflated)
Project TotalsP2 $184,402,647 $215,792,422 P2 $220,727,857 $258,512,826
P3 $260,856,569 $305,246,828 P3 $305,950,453 $366,251,123
EW2 $236,123,371 $277,495,060 EW2 $288,719,102 $333,229,820
GS19 $17,123,550 $19,978,486 GS19 $20,113,313 $23,929,122
Future (Inflated) Total $698,506,137 $818,512,796 Future (Inflated) Total $835,510,725 $981,922,891
Cost of Inflation (Future - Base Year) $137,004,588 $163,410,095
Summary by
Account
Account Description Direct CostPhase 1 Allocated
ContgcyDirect Cost
Phase 1 Allocated
ContgcyDirect Cost
Phase 1 Allocated
ContgcyDirect Cost
Phase 1 Allocated
ContgcyDirect Cost
Phase 1 Allocated
ContgcyGrand Total
1.0 Removals / Demolition $3,236,987 $647,397 $4,257,380 $851,476 $21,296,492 $4,259,298 $0 $0 $28,790,859 $5,758,172 $34,549,031
2.0 $1,174,570 $234,914 $1,912,096 $382,419 $14,121,662 $2,824,332 $896,272 $179,254 $18,104,600 $3,620,920 $21,725,520
3.0 $21,116,900 $4,223,380 $22,525,775 $4,505,155 $41,379,526 $8,275,905 $0 $0 $85,022,201 $17,004,440 $102,026,641
4.0 $14,775,000 $2,955,000 $35,000,000 $7,000,000 $39,700,000 $7,940,000 $0 $0 $89,475,000 $17,895,000 $107,370,000
5.0 $92,837,000 $18,567,400 $133,978,000 $26,795,600 $49,309,625 $9,861,925 $11,544,000 $2,308,800 $287,668,625 $57,533,725 $345,202,350
6.0 $897,750 $179,550 $865,700 $173,140 $3,010,350 $602,070 $0 $0 $4,773,800 $954,760 $5,728,560
7.0 $1,650,317 $330,063 $3,834,495 $766,899 $18,508,916 $3,701,783 $39,988 $7,998 $24,033,716 $4,806,743 $28,840,459
8.0 $13,184,644 $2,636,929 $11,915,880 $2,383,176 $11,645,793 $2,329,159 $1,154,400 $230,880 $37,900,717 $7,580,143 $45,480,860
9.0 $4,769,253 $953,851 $6,933,910 $1,386,782 $3,541,445 $708,289 $579,199 $115,840 $15,823,807 $3,164,761 $18,988,568
10.0 $3,306,456 $661,291 $728,061 $145,612 $4,344,637 $868,927 $60,816 $12,163 $8,439,969 $1,687,994 $10,127,962
11.0 $27,453,769 $0 $38,905,272 $0 $29,264,927 $0 $2,848,875 $0 $98,472,844 $0 $98,472,844
SUBTOTAL $184,402,647 $31,389,775 $260,856,569 $44,390,259 $236,123,371 $41,371,689 $17,123,550 $2,854,935 $698,506,137 $120,006,659 $818,512,796
Utility
ROW
Professional Services
Signals & Systems
Structures
Viaducts
Environmental Mitigation
Miscellaneous & Temporary Facilities
$698,506,137 $120,006,659
CREATE Phase 1 Contingency (Mgmnt Res + Allocated)
Civil - Earthwork
Trackwork
Functional Class Costs (Less Contingency)
P2 P3 EW2 GS19 CREATE TOTAL
print date: 7/17/2014
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
33 | P a g e
APPENDIX A1: Updated Cost Estimate for CER Model
CREATE - 75th ST CIPCost Estimate Review (CER)
DRAFT Project Summary
Revised: 5/12/2014
(DRAFT) CREATE 75th ST CIP: Summary of CER Inputs
Segment
LOOKUPPE/ENV Final Design ROW / Utility Construction
Construction
Related Prof SvcsPE Final Design ROW / Utility Construction
Construction
Related Prof Svcs
CREATE Phase I
Contingency &
Mgmt ResP2 $2,706,856 $13,827,818 $8,875,709 $148,873,168 $14,211,924 $0 $0 $1,775,142 $29,774,634 $0 $31,549,775 $23,662,332
P3 $3,871,754 $19,788,732 $7,661,970 $212,940,889 $20,338,419 $0 $0 $1,532,394 $42,588,178 $0 $44,120,572 $33,090,429
EW2 $3,617,775 $18,226,243 $7,086,081 $198,972,363 $18,732,527 $0 $0 $1,417,216 $39,794,473 $0 $41,211,689 $30,908,767
GS19 $226,920 $1,123,403 $2,209 $12,480,260 $1,154,609 $0 $0 $442 $2,496,052 $0 $2,496,494 $1,872,370
Segment Total $10,423,305 $52,966,196 $23,625,970 $573,266,680 $54,437,479 $0 $0 $4,725,194 $114,653,336 $0 $119,378,530 $89,533,898
Check vs Detail $10,423,305 $52,966,196 $23,625,970 $573,266,680 $54,437,479 $0 $0 $4,725,194 $114,653,336 $0 $119,378,530 $89,533,898
CREATE Total
Notes:
Phase I - PE/ENV; Phase II - FD/ROW/UT; Phase III - Construction
Construction Related Professional Services include: Project Management; Construction Management (RR Force Acct & Consultant); Legal, Permitting, Reviewing Agency Fees; Survey, Permitting and Inspections; Public Information/Advocacy
CREATE Partners agreed to range of 7% - 10% for Construction Management OR as determined by Owner
YOE Calculations utilize Phase I, Phase II, Phase III escalation rates corrollated to segments P2, P3, EW2, GS19 expenditures
CREATE Phase I (PE, Environmental) Contingency includes: 5% Management Reserve + 15% Applied (Design, Construction) Contingency
CREATE Phase II (conclusion of Final Design) Contingency includes: 5% Management Reserve + 10% Construction Contingency
Segment
LOOKUPStart Date Duration (Mo) Start Date Duration (Mo) Start Date Duration (Mo) Start Date Duration (Mo) % Completion
P2 Jan-11 47 Apr-15 26 Apr-15 28 Aug-17 40
P3 Jan-11 47 Apr-15 26 Apr-15 28 Aug-17 24
EW2 Jan-11 47 Feb-15 30 Feb-15 32 Oct-17 49
GS19 Jan-11 47 Apr-15 26 Apr-15 28 Aug-17 26
Notes:
Final Design Duration is calculated as 2 months less than ROW / Utility Coordination duration
Base Year
Estimate
Summary
No Contingency
With Phase I
Contingency &
Mgmt Res
With Phase II
Contingency &
Mgmt Res
Year of
Expenditure
Estimate
Summary
No Contingency
With Phase I
Contingency &
Mgmt Res
With Phase II
Contingency &
Mgmt Res
Base Yr (2013)
Project Totals
Base Yr (2013)
Project Totals
Base Yr (2013)
Project Totals
Future (Inflated)
Project Totals
Future (Inflated)
Project Totals
Future (Inflated)
Project TotalsP2 $188,495,475 $220,045,251 $212,157,807 P2 $217,041,988 $253,642,869 $244,492,967
P3 $264,601,765 $308,722,337 $297,692,194 P3 $299,971,907 $356,371,643 $343,483,102
EW2 $246,634,989 $287,846,678 $277,543,755 EW2 $288,539,390 $332,301,394 $320,261,214
GS19 $14,987,401 $17,483,895 $16,859,772 GS19 $17,062,808 $20,231,560 $19,493,845
Future (Inflated) Total $714,719,630 $834,098,160 $804,253,528 Future (Inflated) Total $822,616,092 $962,547,467 $927,731,128
Cost of Inflation (Future - Base Year) $107,896,462 $128,449,307 $123,477,600
Account Direct CostPhase 1 Allocated
ContgcyDirect Cost
Phase 1 Allocated
ContgcyDirect Cost
Phase 1 Allocated
ContgcyDirect Cost
Phase 1 Allocated
ContgcyDirect Cost
Phase 1 Allocated
ContgcyGrand Total
1.0 $3,236,987 $647,397 $4,257,380 $851,476 $21,296,492 $4,259,298 $0 $0 $28,790,859 $5,758,172 $34,549,031
2.0 $1,174,570 $234,914 $1,912,096 $382,419 $14,121,662 $2,824,332 $12,440,272 $2,488,054 $29,648,600 $5,929,720 $35,578,320
3.0 $21,116,900 $4,223,380 $22,525,775 $4,505,155 $41,379,526 $8,275,905 $0 $0 $85,022,201 $17,004,440 $102,026,641
4.0 $14,775,000 $2,955,000 $35,000,000 $7,000,000 $39,700,000 $7,940,000 $0 $0 $89,475,000 $17,895,000 $107,370,000
5.0 $92,837,000 $18,567,400 $133,978,000 $26,795,600 $49,309,625 $9,861,925 $0 $0 $276,124,625 $55,224,925 $331,349,550
6.0 $897,750 $179,550 $865,700 $173,140 $3,010,350 $602,070 $0 $0 $4,773,800 $954,760 $5,728,560
7.0 $1,650,317 $330,063 $3,834,495 $766,899 $18,508,916 $3,701,783 $39,988 $7,998 $24,033,716 $4,806,743 $28,840,459
8.0 $13,184,644 $2,636,929 $10,567,443 $2,113,489 $11,645,793 $2,329,159 $0 $0 $35,397,880 $7,079,576 $42,477,455
9.0 $4,769,253 $953,851 $6,933,910 $1,386,782 $3,541,445 $708,289 $1,999 $400 $15,246,607 $3,049,321 $18,295,928
10.0 $4,106,456 $821,291 $728,061 $145,612 $3,544,637 $708,927 $210 $42 $8,379,363 $1,675,873 $10,055,235
11.0 $30,746,598 $0 $43,998,905 $0 $40,576,544 $0 $2,504,932 $0 $117,826,980 $0 $117,826,980
$188,495,475 $31,549,775 $264,601,765 $44,120,572 $246,634,989 $41,211,689 $14,987,401 $2,496,494 $714,719,630 $119,378,530 $834,098,160
Phase 2 Allocated
Contgcy$23,662,332 $33,090,429 $30,908,767 $1,872,370 $714,719,630 $89,533,898 $804,253,528
Description
Summary by Account
SUBTOTAL
GS19 CREATE TOTAL
Functional Class Costs (Less Contingency) CREATE Phase 1 Contingency (Mgmnt Res + Allocated)CREATE Phase II
Contingency &
Mgmt Res
$714,719,630 $119,378,530
PE/ENV Final Design ROW / Utility Construction
P2 P3 EW2
Removals / Demolition
Civil - Earthwork
Trackwork
Signals & Systems
Structures
Viaducts
Environmental Mitigation
Miscellaneous & Temporary Facilities
Utility
ROW
Professional Services
print date: 9/30/2014
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
34 | P a g e
APPENDIX B – CER Risk Register
Risks included in the Probability Model: the following risks were considered by the Team to have a reasonable chance of occurrence and were included in the model with a probability percentage and range of impact should they occur.
Risk # Event Risk Name Risk Type Detailed Description of Risk Event Probability 10% Cost Most Likely Cost 90% Cost
Cost Risk
(Threat/
Opportunity)
10% Schedule
(Mo)
Most Likely
Schedule (Mo)
90% Schedule
(Mo)
Schedule Risk
(Threat/
Opportunity)
1 Removal of Track & Signal items Cost/Schedule
Design changes to track geometric
layout requiring additional track
replacement
25% 1,138,234$ 1,422,793$ 1,707,352$ Threat 0.00 0.00 0.00 Threat
2Quantity Variance with Civil/Earthwork
itemsCost/Schedule
Potential additional quantities for
Civil/Earthwork items as required10% 1,263,827$ 1,579,784$ 1,895,741$ Threat 0.00 0.00 0.00 Threat
3 71st St at-grade crossing Cost Potential additional utilities work 50% 40,713$ 50,891$ 61,069$ Threat 0.00 0.00 0.00 Threat
4Interim Track and Signal work for
extended durationCost
Additional temporary track and
signal work for extended duration
or if project P3 is not first in the
project sequence
40% 2,000,000$ 2,500,000.00 3,000,000$ Threat 0.00 0.00 0.00 Threat
5Structures - waste site near
abmutment exc.Cost
Special waste site near abutment
excavation; addtl geotech will
occur in the future, cost is based
on additional excavation and
hauling of material
5% 2,876,686$ 5,753,372.50 8,630,059$ Threat 0.00 0.00 0.00 Threat
6Substructure Rehabilitation
(Structures)Cost
Basic Rehabilitation will change as
geotech information is realized80% 7,191,716$ 14,383,431.25 21,575,147$ Threat 0.00 0.00 0.00 Threat
7Superstructure Rehabilitation /
Widending (Structures)Cost
Substantial Structural
Reinforcement; Beam or Deck
Replacement; Widening
80% 14,383,431$ 28,766,862.50 43,150,294$ Threat 0.00 0.00 0.00 Threat
8 Structures - delivery delays Schedule Delay in delivery of materials 50% 0 0.01 0.02 Threat 1 3 4 Threat
9 Structures - delayed improvements Schedule
Consecutive (or close by) bridge
improvements may be delayed to
minize traffic impacts due to road
closures
50% 0 0.01 0.02 Opportunity 1 2 4 Threat
10 Opportunity to avoid weather impacts Schedule
4 months per year are included for
the impact of Weather events
requiring construction to slow or
stop; the team considers that
there is an opportunity that this
schedule could be improved
60% 0 0.01 0.02 Opportunity 2 3 4 Opportunity
11 EW2 Operations impact delays SchedulePotential for operations delays
during peak RR seasons50% 0 0.01 0.02 Threat 2 3 4 Threat
12Viaduct elements; additional costs and
scopeCost
There will likely be additional work
on the viaducts as the scoping and
pricing for improvements are
finalized
90% 500,000$ 1,000,000$ 1,500,000$ Threat 0.00 0.00 0.00
13 P2 ROW Acquisition Delay SchedulePotential delay to the acquisition
of ROW on project P2. 80% 0 0.01 0.02 Threat 6 9 12 Threat
Risk # Event Risk Name Risk Type Detailed Description of Risk Event Probability 10% Cost Most Likely Cost 90% Cost
Cost Risk
(Threat/
Opportunity)
10% Schedule
(Mo)
Most Likely
Schedule (Mo)
90% Schedule
(Mo)
Schedule Risk
(Threat/
Opportunity)
14 EW2 ROW Acquisition Delay SchedulePotential delay to the acquisition
of ROW on project EW2. 80% 0 0.01 0.02 Threat 6 9 12 Threat
15 Utility relocaton delays Schedule
Potential for delay to the
relocation of utilities delaying the
start of consructon on the project.
Probability is at 30% since there is
an opportunity to complete the
utility relocations at the beginning
of construction, if necessary.
30% 0 0.01 0.02 Threat 1 3 5 Threat
16 GS19 Change Orders Cost
Unforeseen changes during
construction (Change Orders). For
the IDOT work on GS19, the range
is 5% low, most likely 10% and
high end 15%.
100% 624,013$ 1,248,026$ 1,872,039$ Threat 0.00 0.00 0.00
17 P2 Change Orders Cost
Unforeseen changes during
construction (Change Orders). For
the RR work on projects P2, P3
and EW2, 2% is low; 6% likeliest
and 10% high
100% 2,977,463$ 8,932,390$ 14,887,317$ Threat 0.00 0.00 0.00
18 P3 Change Orders Cost
Unforeseen changes during
construction (Change Orders). For
the RR work on projects P2, P3
and EW2, 2% is low; 6% likeliest
and 10% high
100% 4,258,818$ 12,776,453$ 21,294,089$ Threat 0.00 0.00 0.00
19 EW2 Change Orders Cost
Unforeseen changes during
construction (Change Orders). For
the RR work on projects P2, P3
and EW2, 2% is low; 6% likeliest
and 10% high
100% 3,979,447$ 11,938,342$ 19,897,236$ Threat 0.00 0.00 0.00
Risks not included in the Probability Model: the following risks were identified by the Team (many pre-CER) but were not considered to have a high enough probability of occurrence to be included in the probability model. Therefore, these risks had zero probability and did not impact the model. It is recommended that the Team continue to monitor these risks to determine if they could have any future impact.
Risk # Event Risk Name Risk TypeDetailed Description of Risk
Event Probability 10% Cost Most Likely Cost 90% Cost
Cost Risk
(Threat/
Opportunity)
10% Schedule
(Mo)
Most Likely
Schedule (Mo)
90% Schedule
(Mo)
Schedule Risk
(Threat/
Opportunity)
1 Demolition of ROW Schedule
Identification of contaminated
items requiring development of
mitigation strategy and potential
procurement of services. In team
discussion it was considered very
unlikely that a delay would occur,
and this risk was retired.
0% 0 0.01 0.02 Threat 0.00 0.00 0.00 Threat
2 Union Avenue Cost
Potential additional work to keep
Union Avenue open. In
discussion, it was considered
unlikely this risk would occur and
the risk was retired.
0% 0 0.01 0.02 Opportunity 0.00 0.00 0.00 Threat
3Track - added track, turnouts,
crossovers, etc.Cost
As design progresses, could be
additional track and related items
added. In the workshop
discussion, the team considered
the track quanitites would very
likely remain consistent.
Therefore, this risk was retired.
0% 0 0.01 0.02 Threat 0.00 0.00 0.00 Threat
4Control Point Signals; additional
work related to these new signalsCost
As design progresses, could be
additional control point signals
and related items added. During
the workshop, the team
considered it unlikely that
additional control point signals
would be added. Therefore, this
risk was retired.
0% 0 0.01 0.02 Threat 0.00 0.00 0.00 Threat
5Stuctures - improved schedule due
to design standardization Schedule
Standardization of structural
elements to decrease lead time
on material delivery. The team
considered it unlikely this could
improve the schedule. Therefore,
this risk was retired.
0% 0 0.01 0.02 Opportunity 0.00 0.00 0.00 Opportunity
6Stuctures - lower costs due to
standardization Cost
standardization of structural
elements resulting in greater
quantities and lower unit cost of
procurement. This item was
considered by the team to be very
unlikely that it would occur, and
therefore it was retired.
0% 0 0.01 0.02 Opportunity 0.00 0.00 0.00 Threat
Risk # Event Risk Name Risk TypeDetailed Description of Risk
Event Probability 10% Cost Most Likely Cost 90% Cost
Cost Risk
(Threat/
Opportunity)
10% Schedule
(Mo)
Most Likely
Schedule (Mo)
90% Schedule
(Mo)
Schedule Risk
(Threat/
Opportunity)
7 Viaducts - additional quantities Cost
Addtl quantities for special waste
site near abutments, rehab or
other modifications. Item was
considered by the team to be very
unlikely and therefore was
retired.
0% 0 0.01 0.02 Threat 0.00 0.00 0.00 Threat
8 Viaducts - standardized designs Cost/Schedule
Potential for standardized design
which should decrease costs and
save on delivery schedule. Item
considered very unlikely by the
team and therefore was retired.
0% 0 0.01 0.02 Opportunity 0.00 0.00 0.00 Opportunity
9Environmental Mitigation -
Hazardous MaterialsCost
unkown HazMat locations along
RR or Private ROW. After team
review, it was considered the
estimate is conservative for the
sites identified, and it is very
unlikely that the costs will exceed
what is estimated or that there
will be any schedule impact.
Therefore, this item was retired.
0% 0 0.01 0.02 Threat 0.00 0.00 0.00 Threat
10Misc - additional Staging, MOT,
FlaggingCost
Estimate is conservative with
allowances for these items. This
risk was considered by the team
to be very unlikely and was
retired.
0% 0 0.01 0.02 Threat 0.00 0.00 0.00 Threat
11 Utility Conflicts - RR ROW Cost/Schedule
Minor unkown utility conflicts
may be present within RR ROW.
This is considered unlikely and
was retired.
0% 0 0.01 0.02 Threat 0.00 0.00 0.00 Threat
12Utility Conflicts -
Roadway/InfrastructureCost/Schedule
Additional mitigation measures at
known utilty conflicts.
Coordination of relocation
between utility holders. The team
agreed that the allowance for
utility relocations is sufficient to
cover this potential, and therefore
the risk was retired.
0% 0 0.01 0.02 Threat 0.00 0.00 0.00 Threat
Risk # Event Risk Name Risk TypeDetailed Description of Risk
Event Probability 10% Cost Most Likely Cost 90% Cost
Cost Risk
(Threat/
Opportunity)
10% Schedule
(Mo)
Most Likely
Schedule (Mo)
90% Schedule
(Mo)
Schedule Risk
(Threat/
Opportunity)
13ROW - Acquisition of alternative
ROW parcelsCost/Schedule
Potential for the identification and
acquisition of alternative ROW
parcels. Risk was considered by
the team to be very unlikely and
therefore was retired.
0% 0 0.01 0.02 Threat 0.00 0.00 0.00 Threat
14 ROW - Advanced Procurement Schedule
Advance procurement of ROW to
proceed during the final design.
This could not advance until
funding is avialable. This is
unlikely at this point and was
retired.
0% 0 0.01 0.02 Threat 0.00 0.00 0.00 Opportunity
15 PS - NEPA Clearance delay Schedule
Delay of NEPA clearance would
delay the entire project. Current
NEPA clearance date is October
2014. Team considers that delay
to this item is very unlikely and
this risk was retired.
0% 0 0.01 0.02 Threat 0.00 0.00 0.00 Threat
16 PS - Delays during Final Design
Modifications to track schematics
or special trackwork causing
realignment of tracks and/or
grade separations; new ROW or
ENV impacts; very unlikely that
the design duration will be
exceeded. Therefore, this risk
was retired.
0% 0 0.01 0.02 Threat 0.00 0.00 0.00 Threat
17 PS - advanced track improvements
advance placement of temporary
and permanent track
improvements (where possible) at
the beginning of construction.
This item is considered part of the
normal construction, and no
advanced contracts are
anticipated. Therefore, this risk
was retired.
0% 0 0.01 0.02 Threat 0.00 0.00 0.00 Opportunity
18 PS - construction through winter
Identify opportunities to continue
construction activities through
winter months (where possible)
i.e. - drill shafts. This is
considered part of the current
schedule and therefore the risk
was retired.
0% 0 0.01 0.02 Threat 0.00 0.00 0.00 Opportunity
Risk # Event Risk Name Risk TypeDetailed Description of Risk
Event Probability 10% Cost Most Likely Cost 90% Cost
Cost Risk
(Threat/
Opportunity)
10% Schedule
(Mo)
Most Likely
Schedule (Mo)
90% Schedule
(Mo)
Schedule Risk
(Threat/
Opportunity)
19PS - Proj Development delays add
construction CM
Delays in project development or
construciton requiring additional
funds for PM activities beyond
forecast at contract execution.
This item was considered to be
included in the Change Order risk,
and therefore, this risk was
retired.
0% 0 0.01 0.02 Threat 0.00 0.00 0.00 Threat
20 Potential Labor Strike Schedule
Potential for a labor strike that
could delay the projects. There is
very little risk on the RR portion of
the work. Also not considered a
large risk on the State portion.
Therefore, this risk was retired.
0% 0 0.01 0.02 Threat 0.00 0.00 0.00
21
Scope Changes (Management
Reserve) are covered in the line
item details of the other risks
Cost
This item was considered to be
covered in other risks and
therefore was retired.
0% 0 0.01 0.02 Threat 0.00 0.00 0.00
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
35 | P a g e
APPENDIX C – Crystal Ball Probability Analysis
CER Template_v59_75th CIP_CER_Report(2).xlsm
Crystal Ball Report - Full
Simulation started on 6/26/2014 at 8:29 AM
Simulation stopped on 6/26/2014 at 8:30 AM
Run preferences:
Number of trials run 10,000
Monte Carlo
Random seed
Precision control on
Confidence level 95.00%
Run statistics:
Total running time (sec) 70.52
Trials/second (average) 142
Random numbers per sec 24,248
Crystal Ball data:
Assumptions 171
Correlations 0
Correlated groups 0
Decision variables 0
Forecasts 7
Forecasts
Page 1
CER Template_v59_75th CIP_CER_Report(2).xlsm
Worksheet: [CER Template_v59_75th CIP_CER_Jun_24_2014.xlsm]Risk Register
Forecast: Risks Cell: W8
Summary:
Entire range is from $13,051,296 to $131,082,301
Base case is $71,628,560
After 10,000 trials, the std. error of the mean is $193,117
Statistics: Forecast values
Trials 10,000
Base Case $71,628,560
Mean $72,027,064
Median $72,863,770
Mode ---
Standard Deviation $19,311,675
Variance $372,940,773,812,172
Skewness -0.0900
Kurtosis 2.59
Coeff. of Variability 0.2681
Minimum $13,051,296
Maximum $131,082,301
Range Width $118,031,004
Mean Std. Error $193,117
Total Probable Cost Impact
Page 2
CER Template_v59_75th CIP_CER_Report(2).xlsm
Forecast: Risks (cont'd) Cell: W8
Percentiles: Forecast values
0% $13,051,296
10% $45,933,408
20% $54,651,574
30% $61,635,254
40% $67,405,134
50% $72,861,095
60% $77,756,510
70% $83,070,699
80% $88,832,095
90% $96,522,932
100% $131,082,301
Page 3
CER Template_v59_75th CIP_CER_Report(2).xlsm
Worksheet: [CER Template_v59_75th CIP_CER_Jun_24_2014.xlsm]YOE
Forecast: Inflation Cell: C29
Summary:
Certainty level is 39.40%
Certainty range is from -Infinity to $137,719,391
Entire range is from $114,154,204 to $168,952,915
Base case is $139,266,247
After 10,000 trials, the std. error of the mean is $75,317
Statistics: Forecast values
Trials 10,000
Base Case $139,266,247
Mean $139,836,147
Median $139,745,470
Mode ---
Standard Deviation $7,531,733
Variance $56,727,006,162,600
Skewness 0.0658
Kurtosis 2.98
Coeff. of Variability 0.0539
Minimum $114,154,204
Maximum $168,952,915
Range Width $54,798,711
Mean Std. Error $75,317
Page 4
CER Template_v59_75th CIP_CER_Report(2).xlsm
Forecast: Inflation (cont'd) Cell: C29
Percentiles: Forecast values
0% $114,154,204
10% $130,272,678
20% $133,527,625
30% $135,796,387
40% $137,824,954
50% $139,744,106
60% $141,624,769
70% $143,775,034
80% $146,234,575
90% $149,478,782
100% $168,952,915
Page 5
CER Template_v59_75th CIP_CER_Report(2).xlsm
Forecast: Project Completion Date Cell: C30
Summary:
Certainty level is 70.00%
Certainty range is from -Infinity to 10/29/2022
Entire range is from 6/14/2021 to 6/10/2024
Base case is 9/8/2022
After 10,000 trials, the std. error of the mean is 1.62
Statistics: Forecast values
Trials 10,000
Base Case 9/8/2022
Mean 9/26/2022
Median 9/6/2022
Mode ---
Standard Deviation 162.15
Variance 26,293.48
Skewness -0.1478
Kurtosis 2.69
Coeff. of Variability 0.0036
Minimum 4/1/2021
Maximum 11/28/2023
Range Width 1,092.22
Mean Std. Error 1.62
Page 6
CER Template_v59_75th CIP_CER_Report(2).xlsm
Forecast: Project Completion Date (cont'd) Cell: C30
Percentiles: Forecast values
0% 4/1/2021
10% 8/15/2021
20% 10/12/2021
30% 2/15/2022
40% 5/15/2022
50% 7/31/2022
60% 9/10/2022
70% 10/29/2022
80% 2/15/2023
90% 5/6/2023
100% 11/28/2023
Page 7
CER Template_v59_75th CIP_CER_Report(2).xlsm
Forecast: Risks (Threats/Opps) Cell: C26
Summary:
Entire range is from $13,051,296 to $132,606,373
Base case is $72,142,237
After 10,000 trials, the std. error of the mean is $193,261
Statistics: Forecast values
Trials 10,000
Base Case $72,142,237
Mean $72,540,167
Median $73,401,733
Mode ---
Standard Deviation $19,326,112
Variance $373,498,622,862,276
Skewness -0.0893
Kurtosis 2.59
Coeff. of Variability 0.2664
Minimum $13,051,296
Maximum $132,606,373
Range Width $119,555,076
Mean Std. Error $193,261
Page 8
CER Template_v59_75th CIP_CER_Report(2).xlsm
Forecast: Risks (Threats/Opps) (cont'd) Cell: C26
Percentiles: Forecast values
0% $13,051,296
10% $46,485,017
20% $55,089,921
30% $62,128,351
40% $68,001,806
50% $73,401,473
60% $78,290,715
70% $83,601,360
80% $89,412,973
90% $97,115,899
100% $132,606,373
Page 9
CER Template_v59_75th CIP_CER_Report(2).xlsm
Forecast: Total Project Costs (CY) Cell: C27
Summary:
Certainty level is 89.15%
Certainty range is from -Infinity to $835,357,852
Entire range is from $662,379,072 to $921,055,806
Base case is $786,861,867
After 10,000 trials, the std. error of the mean is $358,530
Statistics: Forecast values
Trials 10,000
Base Case $786,861,867
Mean $790,702,813
Median $790,695,722
Mode ---
Standard Deviation $35,853,039
Variance ##################
Skewness 0.0594
Kurtosis 2.95
Coeff. of Variability 0.0453
Minimum $662,379,072
Maximum $921,055,806
Range Width $258,676,734
Mean Std. Error $358,530
Includes base costs, prior costs, fixed costs, and risks
Page 10
CER Template_v59_75th CIP_CER_Report(2).xlsm
Forecast: Total Project Costs (CY) (cont'd) Cell: C27
Percentiles: Forecast values
0% $662,379,072
10% $744,643,879
20% $760,386,574
30% $771,370,165
40% $781,383,510
50% $790,691,646
60% $799,327,456
70% $809,262,391
80% $821,062,777
90% $836,773,876
100% $921,055,806
Page 11
CER Template_v59_75th CIP_CER_Report(2).xlsm
Forecast: Total Project Costs (YOE) Cell: C28
Summary:
Certainty level is 70.00%
Certainty range is from -Infinity to $951,904,257
Entire range is from $776,533,276 to $1,088,060,285
Base case is $926,128,114
After 10,000 trials, the std. error of the mean is $429,027
Statistics: Forecast values
Trials 10,000
Base Case $926,128,114
Mean $930,538,960
Median $930,266,137
Mode ---
Standard Deviation $42,902,659
Variance ##################
Skewness 0.0561
Kurtosis 2.95
Coeff. of Variability 0.0461
Minimum $776,533,276
Maximum $1,088,060,285
Range Width $311,527,010
Mean Std. Error $429,027
Includes base costs, prior costs, fixed costs, risks, and inflation
Page 12
CER Template_v59_75th CIP_CER_Report(2).xlsm
Forecast: Total Project Costs (YOE) (cont'd) Cell: C28
Percentiles: Forecast values
0% $783,264,643
10% $876,945,471
20% $894,251,316
30% $908,217,603
40% $920,158,763
50% $930,286,668
60% $940,368,522
70% $951,904,257
80% $965,439,258
90% $984,108,792
100% $1,079,809,439
End of Forecasts
Page 13
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumptions
Worksheet: [CER Template_v59_75th CIP_CER_Jun_24_2014.xlsm]BaseCost
Assumption: As-Planned CONSTR-EW2 Cell: J79
Triangular distribution with parameters:
10% $198,111,450 (=I62)
Likeliest $217,704,890 (=J62)
90% $237,298,330 (=K62)
Assumption: As-Planned CONSTR-GS19 Cell: J82
Triangular distribution with parameters:
10% $12,407,731 (=I65)
Likeliest $13,634,869 (=J65)
90% $14,862,007 (=K65)
Assumption: As-Planned CONSTR-P2 Cell: J73
Triangular distribution with parameters:
10% $148,407,434 (=I56)
Likeliest $163,085,092 (=J56)
90% $177,762,751 (=K56)
Page 14
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: As-Planned CONSTR-P2 (cont'd) Cell: J73
Assumption: As-Planned CONSTR-P3 Cell: J76
Triangular distribution with parameters:
10% $212,284,170 (=I59)
Likeliest $233,279,308 (=J59)
90% $254,274,446 (=K59)
Assumption: As-Planned FD/ROW/UTIL-EW2 Cell: J78
Triangular distribution with parameters:
10% $23,034,215 (=I61)
Likeliest $25,312,324 (=J61)
90% $27,590,433 (=K61)
Page 15
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: As-Planned FD/ROW/UTIL-GS19 Cell: J81
Triangular distribution with parameters:
10% $1,024,308 (=I64)
Likeliest $1,125,613 (=J64)
90% $1,226,918 (=K64)
Assumption: As-Planned FD/ROW/UTIL-P2 Cell: J72
Triangular distribution with parameters:
10% $20,660,209 (=I55)
Likeliest $22,703,527 (=J55)
90% $24,746,844 (=K55)
Assumption: As-Planned FD/ROW/UTIL-P3 Cell: J75
Triangular distribution with parameters:
10% $24,980,139 (=I58)
Likeliest $27,450,702 (=J58)
90% $29,921,265 (=K58)
Page 16
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: BtP Cell: D37
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=D37)
Assumption: BtP (D38) Cell: D38
Yes-No distribution with parameters:
Probability of Yes(1) 0.1 (=D38)
Assumption: BtP (D39) Cell: D39
Yes-No distribution with parameters:
Probability of Yes(1) 0.085 (=D39)
Page 17
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: BtP (D40) Cell: D40
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=D40)
Assumption: BtP (D41) Cell: D41
Yes-No distribution with parameters:
Probability of Yes(1) 0.1 (=D41)
Assumption: BtP (D42) Cell: D42
Yes-No distribution with parameters:
Probability of Yes(1) 0.085 (=D42)
Page 18
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: BtP (D43) Cell: D43
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=D43)
Assumption: BtP (D44) Cell: D44
Yes-No distribution with parameters:
Probability of Yes(1) 0.1 (=D44)
Assumption: BtP (D45) Cell: D45
Yes-No distribution with parameters:
Probability of Yes(1) 0.08 (=D45)
Page 19
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: BtP (D46) Cell: D46
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=D46)
Assumption: BtP (D47) Cell: D47
Yes-No distribution with parameters:
Probability of Yes(1) 0.1 (=D47)
Assumption: BtP (D48) Cell: D48
Yes-No distribution with parameters:
Probability of Yes(1) 0.1 (=D48)
Page 20
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: BtP CONSTR-EW2 Cell: I79
Triangular distribution with parameters:
10% $176,340,961 (=F62)
Likeliest $195,934,401 (=G62)
90% $215,527,841 (=H62)
Assumption: BtP CONSTR-GS19 Cell: I82
Triangular distribution with parameters:
10% $11,044,244 (=F65)
Likeliest $12,271,382 (=G65)
90% $13,498,520 (=H65)
Assumption: BtP CONSTR-P2 Cell: I73
Triangular distribution with parameters:
10% $132,098,925 (=F56)
Likeliest $146,776,583 (=G56)
90% $161,454,241 (=H56)
Page 21
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: BtP CONSTR-P3 Cell: I76
Triangular distribution with parameters:
10% $188,956,240 (=F59)
Likeliest $209,951,377 (=G59)
90% $230,946,515 (=H59)
Assumption: BtP FD/ROW/UTIL-EW2 Cell: I78
Triangular distribution with parameters:
10% $21,768,599 (=F61)
Likeliest $24,046,708 (=G61)
90% $26,324,817 (=H61)
Assumption: BtP FD/ROW/UTIL-GS19 Cell: I81
Triangular distribution with parameters:
10% $968,027 (=F64)
Likeliest $1,069,332 (=G64)
90% $1,170,637 (=H64)
Page 22
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: BtP FD/ROW/UTIL-P2 Cell: I72
Triangular distribution with parameters:
10% $19,525,033 (=F55)
Likeliest $21,568,351 (=G55)
90% $23,611,668 (=H55)
Assumption: BtP FD/ROW/UTIL-P3 Cell: I75
Triangular distribution with parameters:
10% $23,607,604 (=F58)
Likeliest $26,078,167 (=G58)
90% $28,548,730 (=H58)
Assumption: Schedule CONSTR-EW2 Cell: L25
Triangular distribution with parameters:
Minimum 44.1 (=J25*(1-K25))
Likeliest 49.0 (=J25)
Maximum 53.9 (=J25*(1+K25))
Page 23
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: Schedule CONSTR-GS19 Cell: L28
Triangular distribution with parameters:
Minimum 23.4 (=J28*(1-K28))
Likeliest 26.0 (=J28)
Maximum 28.6 (=J28*(1+K28))
Assumption: Schedule CONSTR-P2 Cell: L19
Triangular distribution with parameters:
Minimum 36.0 (=J19*(1-K19))
Likeliest 40.0 (=J19)
Maximum 44.0 (=J19*(1+K19))
Assumption: Schedule CONSTR-P3 Cell: L22
Triangular distribution with parameters:
Minimum 21.6 (=J22*(1-K22))
Likeliest 24.0 (=J22)
Maximum 26.4 (=J22*(1+K22))
Page 24
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: Schedule FD/ROW/UTIL-EW2 Cell: L24
Triangular distribution with parameters:
Minimum 28.8 (=J24*(1-K24))
Likeliest 32.0 (=J24)
Maximum 35.2 (=J24*(1+K24))
Assumption: Schedule FD/ROW/UTIL-GS19 Cell: L27
Triangular distribution with parameters:
Minimum 25.2 (=J27*(1-K27))
Likeliest 28.0 (=J27)
Maximum 30.8 (=J27*(1+K27))
Assumption: Schedule FD/ROW/UTIL-P2 Cell: L18
Triangular distribution with parameters:
Minimum 25.2 (=J18*(1-K18))
Likeliest 28.0 (=J18)
Maximum 30.8 (=J18*(1+K18))
Page 25
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: Schedule FD/ROW/UTIL-P3 Cell: L21
Triangular distribution with parameters:
Minimum 25.2 (=J21*(1-K21))
Likeliest 28.0 (=J21)
Maximum 30.8 (=J21*(1+K21))
Assumption: WtP Cell: F37
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=F37)
Assumption: WtP (F38) Cell: F38
Yes-No distribution with parameters:
Probability of Yes(1) 0.3 (=F38)
Page 26
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: WtP (F39) Cell: F39
Yes-No distribution with parameters:
Probability of Yes(1) 0.085 (=F39)
Assumption: WtP (F40) Cell: F40
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=F40)
Assumption: WtP (F41) Cell: F41
Yes-No distribution with parameters:
Probability of Yes(1) 0.3 (=F41)
Page 27
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: WtP (F42) Cell: F42
Yes-No distribution with parameters:
Probability of Yes(1) 0.085 (=F42)
Assumption: WtP (F43) Cell: F43
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=F43)
Assumption: WtP (F44) Cell: F44
Yes-No distribution with parameters:
Probability of Yes(1) 0.3 (=F44)
Page 28
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: WtP (F45) Cell: F45
Yes-No distribution with parameters:
Probability of Yes(1) 0.08 (=F45)
Assumption: WtP (F46) Cell: F46
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=F46)
Assumption: WtP (F47) Cell: F47
Yes-No distribution with parameters:
Probability of Yes(1) 0.3 (=F47)
Page 29
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: WtP (F48) Cell: F48
Yes-No distribution with parameters:
Probability of Yes(1) 0.1 (=F48)
Assumption: WtP CONSTR-EW2 Cell: K79
Triangular distribution with parameters:
10% $230,767,184 (=L62)
Likeliest $250,360,624 (=M62)
90% $269,954,064 (=N62)
Assumption: WtP CONSTR-GS19 Cell: K82
Triangular distribution with parameters:
10% $14,452,961 (=L65)
Likeliest $15,680,099 (=M65)
90% $16,907,237 (=N65)
Page 30
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: WtP CONSTR-P2 Cell: K73
Triangular distribution with parameters:
10% $172,870,198 (=L56)
Likeliest $187,547,856 (=M56)
90% $202,225,514 (=N56)
Assumption: WtP CONSTR-P3 Cell: K76
Triangular distribution with parameters:
10% $247,276,067 (=L59)
Likeliest $268,271,204 (=M59)
90% $289,266,342 (=N59)
Assumption: WtP FD/ROW/UTIL-EW2 Cell: K78
Triangular distribution with parameters:
10% $25,565,447 (=L61)
Likeliest $27,843,556 (=M61)
90% $30,121,665 (=N61)
Page 31
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: WtP FD/ROW/UTIL-GS19 Cell: K81
Triangular distribution with parameters:
10% $1,136,869 (=L64)
Likeliest $1,238,174 (=M64)
90% $1,339,479 (=N64)
Assumption: WtP FD/ROW/UTIL-P2 Cell: K72
Triangular distribution with parameters:
10% $22,930,562 (=L55)
Likeliest $24,973,880 (=M55)
90% $27,017,197 (=N55)
Assumption: WtP FD/ROW/UTIL-P3 Cell: K75
Triangular distribution with parameters:
10% $27,725,209 (=L58)
Likeliest $30,195,772 (=M58)
90% $32,666,336 (=N58)
Worksheet: [CER Template_v59_75th CIP_CER_Jun_24_2014.xlsm]Risk Register
Page 32
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: ci 10Substructure Rehabilitation (Structures) Cell: T19
Triangular distribution with parameters:
10% 7,191,715.63 (=Q19)
Likeliest 14,383,431.25 (=R19)
90% 21,575,146.88 (=S19)
Assumption: ci 11Superstructure Rehabilitation / Widending (Structures) Cell: T20
Triangular distribution with parameters:
10% 14,383,431.25 (=Q20)
Likeliest 28,766,862.50 (=R20)
90% 43,150,293.75 (=S20)
Assumption: ci 12Structures - delivery delays Cell: T21
Triangular distribution with parameters:
10% 0.00 (=Q21)
Likeliest 0.01 (=R21)
90% 0.02 (=S21)
Page 33
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: ci 13Structures - delayed improvements Cell: T22
Triangular distribution with parameters:
10% 0.00 (=Q22)
Likeliest 0.01 (=R22)
90% 0.02 (=S22)
Assumption: ci 14Stuctures - improved schedule due to design standardization Cell: T23
Triangular distribution with parameters:
10% 0.00 (=Q23)
Likeliest 0.01 (=R23)
90% 0.02 (=S23)
Assumption: ci 15Stuctures - lower costs due to standardization Cell: T24
Triangular distribution with parameters:
10% 0.00 (=Q24)
Likeliest 0.01 (=R24)
90% 0.02 (=S24)
Page 34
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: ci 16Viaducts - additional quantities Cell: T25
Triangular distribution with parameters:
10% $1,145,712 (=Q25)
Likeliest $1,432,140 (=R25)
90% $1,718,568 (=S25)
Assumption: ci 17Viaducts - standardized designs Cell: T26
Triangular distribution with parameters:
10% $190,952 (=Q26)
Likeliest $238,690 (=R26)
90% $286,428 (=S26)
Assumption: ci 18Environmental Mitigation - Hazardous Materials Cell: T27
Triangular distribution with parameters:
10% $849,246 (=Q27)
Likeliest $1,061,558 (=R27)
90% $1,273,869 (=S27)
Page 35
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: ci 19Misc - additional Staging, MOT, Flagging Cell: T28
Triangular distribution with parameters:
10% $1,141,702 (=Q28)
Likeliest $1,427,128 (=R28)
90% $1,712,554 (=S28)
Assumption: ci 1Removal of Track & Signal items Cell: T10
Triangular distribution with parameters:
10% $1,138,234 (=Q10)
Likeliest $1,422,793 (=R10)
90% $1,707,352 (=S10)
Assumption: ci 20Utility Conflicts - RR ROW Cell: T29
Triangular distribution with parameters:
10% 0.00 (=Q29)
Likeliest 0.01 (=R29)
90% 0.02 (=S29)
Page 36
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: ci 21Utility Conflicts - Roadway/Infrastructure Cell: T30
Triangular distribution with parameters:
10% $2,531,809 (=Q30)
Likeliest $3,164,761 (=R30)
90% $3,797,714 (=S30)
Assumption: ci 22ROW - Acquisition of alternative ROW parcels Cell: T31
Triangular distribution with parameters:
10% $829,405 (=Q31)
Likeliest $1,036,756 (=R31)
90% $1,244,107 (=S31)
Assumption: ci 23ROW - Advanced Procurement Cell: T32
Triangular distribution with parameters:
10% 0.00 (=Q32)
Likeliest 0.01 (=R32)
90% 0.02 (=S32)
Page 37
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: ci 24PS - NEPA Clearance delay Cell: T33
Triangular distribution with parameters:
10% 0.00 (=Q33)
Likeliest 0.01 (=R33)
90% 0.02 (=S33)
Assumption: ci 25PS - Delays during Final Design Cell: T34
Triangular distribution with parameters:
10% 0.00 (=Q34)
Likeliest 0.01 (=R34)
90% 0.02 (=S34)
Assumption: ci 26PS - advanced track improvements Cell: T35
Triangular distribution with parameters:
10% $619,899 (=Q35)
Likeliest $774,874 (=R35)
90% $929,849 (=S35)
Page 38
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: ci 27PS - construction through winter Cell: T36
Triangular distribution with parameters:
10% 0.00 (=Q36)
Likeliest 0.01 (=R36)
90% 0.02 (=S36)
Assumption: ci 28PS - Proj Development delays add construction CM Cell: T37
Triangular distribution with parameters:
10% $592,321 (=Q37)
Likeliest $740,401 (=R37)
90% $888,482 (=S37)
Assumption: ci 29Opportunity to avoid weather impacts Cell: T38
Triangular distribution with parameters:
10% 0.00 (=Q38)
Likeliest 0.01 (=R38)
90% 0.02 (=S38)
Page 39
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: ci 2Demolition of ROW Cell: T11
Triangular distribution with parameters:
10% 0.00 (=Q11)
Likeliest 0.01 (=R11)
90% 0.02 (=S11)
Assumption: ci 30 EW2 Operations impact delays Cell: T39
Triangular distribution with parameters:
10% 0.00 (=Q39)
Likeliest 0.01 (=R39)
90% 0.02 (=S39)
Assumption: ci 31Potential Labor Strike Cell: T40
Triangular distribution with parameters:
10% 0.00 (=Q40)
Likeliest 0.01 (=R40)
90% 0.02 (=S40)
Page 40
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: ci 32Viaduct elements; additional costs and scope Cell: T41
Triangular distribution with parameters:
10% $500,000 (=Q41)
Likeliest $1,000,000 (=R41)
90% $1,500,000 (=S41)
Assumption: ci 33P2 ROW Acquisition Delay Cell: T42
Triangular distribution with parameters:
10% 0.00 (=Q42)
Likeliest 0.01 (=R42)
90% 0.02 (=S42)
Assumption: ci 34EW2 ROW Acquisition Delay Cell: T43
Triangular distribution with parameters:
10% 0.00 (=Q43)
Likeliest 0.01 (=R43)
90% 0.02 (=S43)
Page 41
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: ci 35Utility relocaton delays Cell: T44
Triangular distribution with parameters:
10% 0.00 (=Q44)
Likeliest 0.01 (=R44)
90% 0.02 (=S44)
Assumption: ci 36GS19 Change Orders Cell: T45
Triangular distribution with parameters:
10% $624,013 (=Q45)
Likeliest $1,248,026 (=R45)
90% $1,872,039 (=S45)
Assumption: ci 37P2 Change Orders Cell: T46
Triangular distribution with parameters:
10% $2,977,463 (=Q46)
Likeliest $8,932,390 (=R46)
90% $14,887,317 (=S46)
Page 42
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: ci 38P3 Change Orders Cell: T47
Triangular distribution with parameters:
10% $4,258,818 (=Q47)
Likeliest $12,776,453 (=R47)
90% $21,294,089 (=S47)
Assumption: ci 39EW2 Change Orders Cell: T48
Triangular distribution with parameters:
10% $3,979,447 (=Q48)
Likeliest $11,938,342 (=R48)
90% $19,897,236 (=S48)
Assumption: ci 3Segment 1 Cell: T12
Triangular distribution with parameters:
10% $1,263,827 (=Q12)
Likeliest $1,579,784 (=R12)
90% $1,895,741 (=S12)
Page 43
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: ci 41Scope Changes (Management Reserve) are covered in the line item details of the other risksCell: T50
Triangular distribution with parameters:
10% 0.00 (=Q50)
Likeliest 0.01 (=R50)
90% 0.02 (=S50)
Assumption: ci 471st St at-grade crossing Cell: T13
Triangular distribution with parameters:
10% $40,713 (=Q13)
Likeliest $50,891 (=R13)
90% $61,069 (=S13)
Assumption: ci 5Union Avenue Cell: T14
Triangular distribution with parameters:
10% $477,358 (=Q14)
Likeliest $596,698 (=R14)
90% $716,038 (=S14)
Page 44
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: ci 6Track - added track, turnouts, crossovers, etc. Cell: T15
Triangular distribution with parameters:
10% 4,622,368.04 (=Q15)
Likeliest 5,777,960.05 (=R15)
90% 6,933,552.06 (=S15)
Assumption: ci 7Control Point Signals; additional work related to these new signals Cell: T16
Triangular distribution with parameters:
10% 2,727,000.00 (=Q16)
Likeliest 3,408,750.00 (=R16)
90% 4,090,500.00 (=S16)
Assumption: ci 8Interim Track and Signal work for extended duration Cell: T17
Triangular distribution with parameters:
10% 2,000,000.00 (=Q17)
Likeliest 2,500,000.00 (=R17)
90% 3,000,000.00 (=S17)
Page 45
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: ci 9Structures - waste site near abmutment exc. Cell: T18
Triangular distribution with parameters:
10% 2,876,686.25 (=Q18)
Likeliest 5,753,372.50 (=R18)
90% 8,630,058.75 (=S18)
Assumption: Pb EW2 Operations impact delays Cell: O39
Yes-No distribution with parameters:
Probability of Yes(1) 0.5 (=O39)
Assumption: Pb 71st St at-grade crossing Cell: O13
Yes-No distribution with parameters:
Probability of Yes(1) 0.5 (=O13)
Page 46
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: Pb Control Point Signals; additional work related to these new signals Cell: O16
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O16)
Assumption: Pb Demolition of ROW Cell: O11
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O11)
Assumption: Pb Environmental Mitigation - Hazardous Materials Cell: O27
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O27)
Page 47
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: Pb EW2 ROW Acquisition Delay Cell: O43
Yes-No distribution with parameters:
Probability of Yes(1) 0.8 (=O43)
Assumption: Pb GS19 Change Orders Cell: O45
Yes-No distribution with parameters:
Probability of Yes(1) 1.0 (=O45)
Assumption: Pb Interim Track and Signal work for extended duration Cell: O17
Yes-No distribution with parameters:
Probability of Yes(1) 0.4 (=O17)
Page 48
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: Pb Misc - additional Staging, MOT, Flagging Cell: O28
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O28)
Assumption: Pb Opportunity to avoid weather impacts Cell: O38
Yes-No distribution with parameters:
Probability of Yes(1) 0.6 (=O38)
Assumption: Pb P2 ROW Acquisition Delay Cell: O42
Yes-No distribution with parameters:
Probability of Yes(1) 0.8 (=O42)
Page 49
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: Pb Potential Labor Strike Cell: O40
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O40)
Assumption: Pb PS - advanced track improvements Cell: O35
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O35)
Assumption: Pb PS - construction through winter Cell: O36
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O36)
Page 50
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: Pb PS - Delays during Final Design Cell: O34
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O34)
Assumption: Pb PS - NEPA Clearance delay Cell: O33
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O33)
Assumption: Pb PS - Proj Development delays add construction CM Cell: O37
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O37)
Page 51
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: Pb Quantity Variance with Civil/Earthwork items Cell: O12
Yes-No distribution with parameters:
Probability of Yes(1) 0.1 (=O12)
Assumption: Pb Removal of Track & Signal items Cell: O10
Yes-No distribution with parameters:
Probability of Yes(1) 0.25 (=O10)
Assumption: Pb ROW - Acquisition of alternative ROW parcels Cell: O31
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O31)
Page 52
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: Pb ROW - Advanced Procurement Cell: O32
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O32)
Assumption: Pb Scope Changes (Management Reserve) are covered in the line item details of the other risksCell: O50
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O50)
Assumption: Pb Structures - delayed improvements Cell: O22
Yes-No distribution with parameters:
Probability of Yes(1) 0.5 (=O22)
Page 53
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: Pb Structures - delivery delays Cell: O21
Yes-No distribution with parameters:
Probability of Yes(1) 0.5 (=O21)
Assumption: Pb Structures - waste site near abmutment exc. Cell: O18
Yes-No distribution with parameters:
Probability of Yes(1) 0.05 (=O18)
Assumption: Pb Stuctures - improved schedule due to design standardization Cell: O23
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O23)
Page 54
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: Pb Stuctures - lower costs due to standardization Cell: O24
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O24)
Assumption: Pb Substructure Rehabilitation (Structures) Cell: O19
Yes-No distribution with parameters:
Probability of Yes(1) 0.8 (=O19)
Assumption: Pb Superstructure Rehabilitation / Widending (Structures) Cell: O20
Yes-No distribution with parameters:
Probability of Yes(1) 0.8 (=O20)
Page 55
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: Pb Track - added track, turnouts, crossovers, etc. Cell: O15
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O15)
Assumption: Pb Union Avenue Cell: O14
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O14)
Assumption: Pb Utility Conflicts - Roadway/Infrastructure Cell: O30
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O30)
Page 56
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: Pb Utility Conflicts - RR ROW Cell: O29
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O29)
Assumption: Pb Utility relocaton delays Cell: O44
Yes-No distribution with parameters:
Probability of Yes(1) 0.3 (=O44)
Assumption: Pb Viaduct elements; additional costs and scope Cell: O41
Yes-No distribution with parameters:
Probability of Yes(1) 0.9 (=O41)
Page 57
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: Pb Viaducts - additional quantities Cell: O25
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O25)
Assumption: Pb Viaducts - standardized designs Cell: O26
Yes-No distribution with parameters:
Probability of Yes(1) 0.0 (=O26)
Assumption: si 10Substructure Rehabilitation (Structures) Cell: AB19
Triangular distribution with parameters:
10% 0.00 (=Y19)
Likeliest 0.00 (=Z19)
90% 0.00 (=AA19)
Page 58
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: si 11Superstructure Rehabilitation / Widending (Structures) Cell: AB20
Triangular distribution with parameters:
10% 0.00 (=Y20)
Likeliest 0.00 (=Z20)
90% 0.00 (=AA20)
Assumption: si 12Structures - delivery delays Cell: AB21
Triangular distribution with parameters:
10% 1.00 (=Y21)
Likeliest 3.00 (=Z21)
90% 4.00 (=AA21)
Assumption: si 13Structures - delayed improvements Cell: AB22
Triangular distribution with parameters:
10% 1.00 (=Y22)
Likeliest 2.00 (=Z22)
90% 4.00 (=AA22)
Page 59
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: si 14Stuctures - improved schedule due to design standardization Cell: AB23
Triangular distribution with parameters:
10% 0.00 (=Y23)
Likeliest 0.00 (=Z23)
90% 0.00 (=AA23)
Assumption: si 15Stuctures - lower costs due to standardization Cell: AB24
Triangular distribution with parameters:
10% 0.00 (=Y24)
Likeliest 0.00 (=Z24)
90% 0.00 (=AA24)
Assumption: si 16Viaducts - additional quantities Cell: AB25
Triangular distribution with parameters:
10% 0.00 (=Y25)
Likeliest 0.00 (=Z25)
90% 0.00 (=AA25)
Page 60
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: si 17Viaducts - standardized designs Cell: AB26
Triangular distribution with parameters:
10% 0.00 (=Y26)
Likeliest 0.00 (=Z26)
90% 0.00 (=AA26)
Assumption: si 18Environmental Mitigation - Hazardous Materials Cell: AB27
Triangular distribution with parameters:
10% 0.00 (=Y27)
Likeliest 0.00 (=Z27)
90% 0.00 (=AA27)
Assumption: si 19Misc - additional Staging, MOT, Flagging Cell: AB28
Triangular distribution with parameters:
10% 0.00 (=Y28)
Likeliest 0.00 (=Z28)
90% 0.00 (=AA28)
Page 61
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: si 1Removal of Track & Signal items Cell: AB10
Triangular distribution with parameters:
10% 0.00 (=Y10)
Likeliest 0.00 (=Z10)
90% 0.00 (=AA10)
Assumption: si 20Utility Conflicts - RR ROW Cell: AB29
Triangular distribution with parameters:
10% 0.00 (=Y29)
Likeliest 0.00 (=Z29)
90% 0.00 (=AA29)
Assumption: si 21Utility Conflicts - Roadway/Infrastructure Cell: AB30
Triangular distribution with parameters:
10% 0.00 (=Y30)
Likeliest 0.00 (=Z30)
90% 0.00 (=AA30)
Page 62
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: si 22ROW - Acquisition of alternative ROW parcels Cell: AB31
Triangular distribution with parameters:
10% 0.00 (=Y31)
Likeliest 0.00 (=Z31)
90% 0.00 (=AA31)
Assumption: si 23ROW - Advanced Procurement Cell: AB32
Triangular distribution with parameters:
10% 0.00 (=Y32)
Likeliest 0.00 (=Z32)
90% 0.00 (=AA32)
Assumption: si 24PS - NEPA Clearance delay Cell: AB33
Triangular distribution with parameters:
10% 0.00 (=Y33)
Likeliest 0.00 (=Z33)
90% 0.00 (=AA33)
Page 63
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: si 25PS - Delays during Final Design Cell: AB34
Triangular distribution with parameters:
10% 0.00 (=Y34)
Likeliest 0.00 (=Z34)
90% 0.00 (=AA34)
Assumption: si 26PS - advanced track improvements Cell: AB35
Triangular distribution with parameters:
10% 0.00 (=Y35)
Likeliest 0.00 (=Z35)
90% 0.00 (=AA35)
Assumption: si 27PS - construction through winter Cell: AB36
Triangular distribution with parameters:
10% 0.00 (=Y36)
Likeliest 0.00 (=Z36)
90% 0.00 (=AA36)
Page 64
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: si 28PS - Proj Development delays add construction CM Cell: AB37
Triangular distribution with parameters:
10% 0.00 (=Y37)
Likeliest 0.00 (=Z37)
90% 0.00 (=AA37)
Assumption: si 29Opportunity to avoid weather impacts Cell: AB38
Triangular distribution with parameters:
10% 2.00 (=Y38)
Likeliest 3.00 (=Z38)
90% 4.00 (=AA38)
Assumption: si 2Demolition of ROW Cell: AB11
Triangular distribution with parameters:
10% 0.00 (=Y11)
Likeliest 0.00 (=Z11)
90% 0.00 (=AA11)
Page 65
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: si 30 EW2 Operations impact delays Cell: AB39
Triangular distribution with parameters:
10% 2.00 (=Y39)
Likeliest 3.00 (=Z39)
90% 4.00 (=AA39)
Assumption: si 31Potential Labor Strike Cell: AB40
Triangular distribution with parameters:
10% 0.00 (=Y40)
Likeliest 0.00 (=Z40)
90% 0.00 (=AA40)
Assumption: si 32Viaduct elements; additional costs and scope Cell: AB41
Triangular distribution with parameters:
10% 0.00 (=Y41)
Likeliest 0.00 (=Z41)
90% 0.00 (=AA41)
Page 66
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: si 33P2 ROW Acquisition Delay Cell: AB42
Triangular distribution with parameters:
10% 6.00 (=Y42)
Likeliest 9.00 (=Z42)
90% 12.00 (=AA42)
Assumption: si 34EW2 ROW Acquisition Delay Cell: AB43
Triangular distribution with parameters:
10% 6.00 (=Y43)
Likeliest 9.00 (=Z43)
90% 12.00 (=AA43)
Assumption: si 35Utility relocaton delays Cell: AB44
Triangular distribution with parameters:
10% 1.00 (=Y44)
Likeliest 3.00 (=Z44)
90% 5.00 (=AA44)
Page 67
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: si 3Segment 1 Cell: AB12
Triangular distribution with parameters:
10% 0.00 (=Y12)
Likeliest 0.00 (=Z12)
90% 0.00 (=AA12)
Assumption: si 41Scope Changes (Management Reserve) are covered in the line item details of the other risksCell: AB50
Triangular distribution with parameters:
10% 0.00 (=Y50)
Likeliest 0.00 (=Z50)
90% 0.00 (=AA50)
Assumption: si 471st St at-grade crossing Cell: AB13
Triangular distribution with parameters:
10% 0.00 (=Y13)
Likeliest 0.00 (=Z13)
90% 0.00 (=AA13)
Page 68
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: si 5Union Avenue Cell: AB14
Triangular distribution with parameters:
10% 0.00 (=Y14)
Likeliest 0.00 (=Z14)
90% 0.00 (=AA14)
Assumption: si 6Track - added track, turnouts, crossovers, etc. Cell: AB15
Triangular distribution with parameters:
10% 0.00 (=Y15)
Likeliest 0.00 (=Z15)
90% 0.00 (=AA15)
Assumption: si 7Control Point Signals; additional work related to these new signals Cell: AB16
Triangular distribution with parameters:
10% 0.00 (=Y16)
Likeliest 0.00 (=Z16)
90% 0.00 (=AA16)
Page 69
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: si 8Interim Track and Signal work for extended duration Cell: AB17
Triangular distribution with parameters:
10% 0.00 (=Y17)
Likeliest 0.00 (=Z17)
90% 0.00 (=AA17)
Assumption: si 9Structures - waste site near abmutment exc. Cell: AB18
Triangular distribution with parameters:
10% 0.00 (=Y18)
Likeliest 0.00 (=Z18)
90% 0.00 (=AA18)
Worksheet: [CER Template_v59_75th CIP_CER_Jun_24_2014.xlsm]YOE
Assumption: V20 Cell: V20
Triangular distribution with parameters:
5% 2.79%
Likeliest 3.00%
95% 3.21%
Page 70
CER Template_v59_75th CIP_CER_Report(2).xlsm
Assumption: V7 Cell: V7
Triangular distribution with parameters:
5% 1.58%
Likeliest 3.31%
95% 4.36%
End of Assumptions
Page 71
CER Template_v59_75th CIP_CER_Report(2).xlsm
Sensitivity Charts
Page 72
CER Template_v59_75th CIP_CER_Report(2).xlsm
Page 73
CER Template_v59_75th CIP_CER_Report(2).xlsm
End of Sensitivity Charts
Page 74
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
36 | P a g e
APPENDIX D – Closeout Presentation
Cost Estimate Review June 23-26, 2013
FHWA Closing Presentation
June 26, 2013
Conduct an unbiased risk-based review to verify the accuracy and reasonableness of the current total cost estimate and project schedule to complete the
• 75th Street CIP
and to develop a probability range for the cost estimate that represents the project’s current stage of design.
2
Cost Estimate Review Objective
Planning Level Cost Est.
NEPA Process
Federally Funded
PLANNING
Potential cost ≥ $500 M
or TIFIA
NEPA APPROVAL (ROD, FONSI)
CER
Updates to FP, PMP, & Cost
Verifications
NO
NO
YES
Not Applicable
Not a Major Project *
*Unless of Special Interest
Draft PMP
Initial FP Authorization of
Federal funds for Construction
PMP Update
Final PMP
CER
Basic Major Project Process
3
4
Review Agenda June 23-26, 2014
525 W. Monroe - Room 200, Chicago, IL 60661 MONDAY, June 23
10:30 a.m. to 2:00 p.m. – Project Site Visit /Lunch 2:30 p.m. – FHWA overview for CER 3:00 p.m. – Overview State Estimation Process 3:30 p.m. – Market Conditions 4:00 p.m. – Soft Costs (Administrative, inflation, allowances) 4:30 p. m.- Contingency/ Risk Register Items 5:30 p.m. – Adjourn TUESDAY, June 24 8:00 a.m. – Removal/Demolition, Track work, Signals & Systems 11:30 a.m. – Lunch 1:00 p.m. – Structures, Civil / Earthwork, Viaducts 4:30 p.m. – Adjourn
5
Review Agenda (cont.)
WEDNESDAY, June 25 8:00 a.m. – Utilities, Right-of way 11:30 a.m. – Lunch 1:00 p.m. – Environmental, miscellaneous & Temporary Facilities, Funding 4:00 p.m. – Revisit estimate items and review risk register details, including descriptions and aggregate minor risks 5:30 p.m. - Adjourn THURSDAY, June 26 8:00 a.m. – Findings and Report Preparation 11:00 a.m. – Closeout Presentation
FHWA • CREATE Program Manager • Resource Center CPM Team • Atkins Consultant
Railroads/Assn. of American Railroads Illinois DOT/Dept. Public & Intermodal
Transportation Chicago DOT Project Team Consultants Jacobs HNTB
6
Review Participants
Project Cost Estimate
Project Schedule
Project Risk Register
Current NEPA Documents
Project Web Site Link
7
Documentation Provided
Basis of Review
8
Review based on estimates provided by the Team in advance with revisions made during the review
Review to determine the reasonableness of assumptions used in the estimate
Not an independent FHWA estimate – Did not verify quantities and unit prices – Goal is to verify accuracy and reasonableness of estimate
Risk-based Probabilistic Approach
Verify
• Major cost elements • Allowances/contingencies • Adjust estimate as necessary
Model
• Base variability • Market conditions and inflation • Risk events (cost, schedule, probability, impact, relationships) • Monte Carlo simulation
Communicate
• Closeout Presentation • Final report • Issuance of NEPA Decision Document • Approval of finance plan
Review Methodology
9
Review Baseline
*Assumes Inflation Rate 4.5%
10
Total Cost (2014): $818.5 million Total Cost (YOE): $984.4 million*
Project Completion October 31, 2021
CER Estimate Adjustments
11
Added $15.6 million of estimate adjustments: Modified Final Design from 6% to 9% on different
set of categories (now 1-9) Public Outreach from .5% to 1% Legal/permits from .5% to .25% Merged CEI and CM (total reduced from 8% to 7%
for non-RR work) MOT on contract P3 was removed (1% previous) Reduced Program Mgmt from 4% to 1% on different
set of categories (now 1-9)
75th St. CIP Estimate (2014 dollars) $818.5M Adjust for prior and fixed costs $(10.4M) Estimate adjustments $15.6M Subtotal $823.7M Contingencies ($119.4M) Base Cost for Risk Analysis $704.3M
12
CER Analysis
.
13
Review Findings
Advanced estimate for level of design Relevant unit prices from IDOT/CDOT/RRs
experience and project complexity Analysis of risks specific to unique CREATE
partnership Most construction in existing ROW, except P2 Structures – early in design -> greater uncertainty
14
Review Findings
• Geometrics & project boundaries have been tightly established via the NEPA/public involvement
• RR work expected to experience less risk due to limited ROW needs and previously developed force account/firm contract conditions and pre-established cost control procedures
15
Base Variability
• Cost +/- 9%, except PE/ENV 0% – (accounts for less risk for RR portion)
• Schedule +/- 10%, except PE/ENV 0% • Basis
• Current level of design of 15-30% • Good coordination has occurred in many areas for early
design level. RR work has less uncertainty.
16
Market Conditions Construction
Base Estimate
(As-Planned) XX% Probability
Worse Than Planned
8,9,10% Probability
Better Than Planned
8,9,10% Probability
Magnitude of Impact
+15% -10%
17
Inflation
• Annual Inflation - Model assumes: – 3% FD/ROW/Utilities – 3.5% Construction
• Basis - IDOT/RR experience
18
Example Risk Analysis
Likelihood of Occurrence – 90% Cost Risk Impact
– Minimum: $0 million – Most Likely: $12 million – Maximum: $19 million
ROW Property Acquisition – Threat Risk for the acquisition of ROW land acquisition (unit price does not reflect premium for settlements)
Likelihood of Occurrence 90%
Impact of Occurrence Triangular Distribution Most Likely : $12 M Minimum (10%): $ 0 M Maximum (90%): $19 M
19
Example Risk Analysis (cont.)
10%
90%
20
Cost Risks
Threats Structure Superstructure Cost Increases Likelihood – 80% Most Likely – $28.8 million
Structure Substructure Cost Increases Likelihood – 80% Most Likely – $14.4 million
21
Cost Risks
Threats (continued) Potential Change Orders Likelihood – 100% Most likely by contract: GS19: $1.2 Million P2: $8.9 Million P3: $12.8 Million EW2: $11.9 Million
22
Schedule Risks
Threats ROW Acquisition delay to project (P2 & EW2) Likelihood – 80% Most Likely – 9 months
EW2 Operations delaying construction Likelihood – 50% Most Likely – 3 months
23
Schedule Risks
Threats (continued) Structures delays Likelihood – 50% Most Likely – 3 months (Delivery Delays) Most Likely – 2 months (Minimize Traffic Impacts)
Utility Relocation Delays Likelihood – 30% Most Likely – 3 months
24
Opportunities
Opportunities Avoid Winter Weather Impacts Likelihood – 60% Most Likely – 3 months savings
25
Total Project Cost (YOE dollars)
*Submitted Pre CER YOE estimate = $984.4 Million
70% = $952 M
26
Total Project Cost (YOE)
Percentile Ranking
Percentile Forecast values 0% $783,264,643
10% $876,945,471 20% $894,251,316 30% $908,217,603 40% $920,158,763 50% $930,286,668 60% $940,368,522 70% $951,904,257 80% $965,439,258 90% $984,108,792
100% $1,079,809,439
27
Project Completion Date
*Submitted Pre-CER Completion Date: October 31, 2021
70% = 10/29/2022
28
Recommendations Manage risk of structures cost uncertainly and growth Mitigate change orders via strong design and
construction management practices Manage schedule risks leading up to project award: ROW acquisition, utilities, track outages, structures
and utility schedule delays Contractors (non-RR) ready to utilize good winter
weather Update and QA overall estimate as decisions are
made, market conditions change, or other threats or opportunities are avoided, mitigated or realized.
29
Recommendations Coordinate early on with Utilities. Inform Utilities of Buy
America Requirements early on. Continue aggressive coordination and communication
through the CREATE partnership Continue proactive public outreach and involvement Continue implementing risk management procedures Managing risks via the risk register Updating estimate based on risk management
Ensure that the project management plan addresses risk response strategies for risks identified
30
Total Project Cost (YOE dollars) Simulation with 2020 Construction Start
*Submitted Pre CER YOE estimate = $984.4 Million
70% = $1,026 M
31 Project Completion Date Simulation with 2020 Construction Start
*Submitted Pre-CER Completion Date: October 31, 2021
70% = 3/29/2025
FHWA will prepare a final report documenting review findings. Draft report for review within 30 days Draft report will be e-mailed to Division Office Division Office will review the draft and forward it to the
Project Team Final report issued within 30 days after receipt of comments Final report forwarded to the Division Office for distribution to
the Project Team FHWA uses the results as the official cost estimate for
the project (NEPA, IFP, reporting) Estimate review is a snapshot of the current estimate
CER Next Steps
32
Questions?
34
Simulation Results 2020 Construction Start
2020 Simulation Results*: $1,026 Million Current Results*: $ 952 Million Delta Costs: $ 74 Million 2020 Simulation Results: 3/29/2025 Current Results*: 10/29/2022 Delta Schedule: 29 months Cost Delta per month of delay: $2.5 Million • Rough estimate of inflation impact
* Year of Expenditure results at 70% confidence level
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
37 | P a g e
APPENDIX E – Workshop Agendas and Sign-In Sheets
1
75th CIP Cost Estimate Review Draft Agenda
June 23-26 My Major Project Project Date: June 23-26, 2014 My State Department of Transportation Meeting Location: 525 W. Monroe, Chicago, IL 60661 Room 200 MONDAY, June 23 10:30 a.m. to 2:00 p.m. – Project Site Visit (see route map below) 10:30 a.m. – Meet at CTCO (1501 S Canal St) 11:00 a.m. – Depart CTCO 11:30 a.m. – Arrive at 80th Street 11:45 p.m. – Arrive at Emerald Wye 12:05 p.m. – Arrive at 71st Street grade separation 12:15 p.m. – Eat “best hot dog in America” at Fat Johnnie’s Famous Red Hots (7242 S Western Ave) 1:00 p.m. – End lunch 1:10 p.m. – Arrive at 83rd St grade crossing 1:20 p.m. – Arrive at Forest Hill Jct. / P3 flyover 1:30 p.m. – Leave Forest Hill Jct. / P3 flyover 2:00 p.m. – Return to Jacobs (525 W Monroe) 2:30 p.m. – FHWA overview for CER 3 p.m. – Overview State Estimation Process 3:30 p.m. – Market Conditions 4 p.m. – Soft Costs (Administrative, inflation, allowances) 4:30 p. m.- Contingency/ Risk Register Items 5:30 p.m. – Adjourn TUESDAY, June 24 8:00 a.m. – Removal/Demolition, Trackwork, Signals & Systems 11:30 a.m. – Lunch 1:00 p.m. – Structures, Civil / Earthwork, Viaducts 4:30 p.m. – Adjourn WEDNESDAY, June 25 8:00 a.m. – Utilities, Right-of way 11:30 a.m. – Lunch 1:00 p.m. – Environmental, miscellaneous & Temporary Facilities, Funding 4:00 p.m. – Revisit estimate items and review risk register details, including descriptions
and aggregate minor risks 5:30 p.m. - Adjourn THURSDAY, June 26 8:00 a.m. – Finalize estimate items and risk register details. 10:00 a.m. – Findings and Report Preparation 11:30 a.m. – Lunch 1:00 a.m. – Findings and Report Preparation 3:30 p.m. – Closeout Presentation
2
*** Some CERs include a project site visit. This is usually dependent on the project’s vicinity to the location of the CER. Google 3D may be used as an alternative to a site visit.
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
38 | P a g e
APPENDIX F – Pre-CER Risk Register
75th St CIP – IDOT, CDOT, AAR FHWA COST ESTIMATE REVIEW
39 | P a g e
APPENDIX G – Project Cost Estimating Guidelines