    US Army Corps of Engineers

    BUILDING STRONG

    DALLAS FLOODWAY

    Feasibility Cost Share Agreement

    TRINITY RIVER CORRIDOR PROJECT(TRCP) COMMITTEE BRIEFING

    MARCH 2, 2010

  • 8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2

    2/16

    BUILDING STRONG2

    To provide information and requestapproval from the Trinity River Corridor

    Project Committee for the upcomingFeasibility Cost Share Agreement with

    the U.S. Army Corps of Engineers(USACE)

    PURPOSE

  • 8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2

    3/16

    BUILDING STRONG3

    Legal document binding USACE and the City toundertake a Feasibility Study and Integrated

    Environmental Impact Statement (EIS) for the DallasFloodway

    Provides cost sharing and other responsibilities of

    both parties Identifies studies and plan of action for completion of

    EIS

    WHAT IS A FEASIBILITY COST SHARE

    AGREEMENT (FCSA)?

  • 8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2

    4/16

    BUILDING STRONG4

    Required by National Environmental Policy Act(NEPA) for projects that have federal fundingand may have environmental, economic orsocial impacts

    Typically includes studies for hydraulics,geology, economics, historic and culturalresources, wildlife and vegetation

    Also includes 35% design level of projectcomponents

    Completion of this document is required toreceive approval to construct the project

    WHAT IS AN ENVIRONMENTAL IMPACTSTATEMENT (EIS)?

  • 8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2

    5/16

    BUILDING STRONG5

    1945 / 1950 Dallas Floodway Project Authorized 1960 US Army Corps of Engineers (USACE) Construction Completed

    1996 Feasibility Study Initiatedo Level of Protection decreased from 800-year to 300-500 yearo Basin-wide modeling completedo Economic database developedo Regional Corridor Development Certificate (CDC) process developedo Preliminary work completed on flood damage reduction, ecosystem restoration and recreation

    componentso Efforts continued in conjunction with Dallas Floodway Extension study, development of Citys

    Balanced Vision Plan and Interior Drainage Plan, and preliminary work on Trinity Parkway

    2007 (Nov) Dallas Floodway Project authorized in Water Resources DevelopmentAct (WRDA)

    2007 (Dec) Periodic Inspection of existing Dallas Floodway Levee SystemConducted

    2009 (Mar) Periodic Inspection Report on Dallas Floodway Levee SystemProvided to City with Unacceptable Rating

    2009 (May) Decision made to analyze all proposed actions within DallasFloodway comprehensively

    BACKGROUND

  • 8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2

    6/16

    BUILDING STRONG6

    Modified 1945 and 1950 Project Authorizations

    Authorized Construction of City Plans

    o Balanced Vision Plan (BVP)

    o Interior Drainage Plan (IDP)

    Required Determination of Technical Soundness &Environmental Acceptability Study Required

    Authorized Total Project Cost $459 million

    o Federal $298 million / Non-Federal $161 million

    Allowed Advancement of City Funds to Maintain Schedule -Credit Given in Future Phases of Project Development

    Water Resources Development Act 2007(Section 5141)

  • 8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2

    7/16

    BUILDING STRONG7

    Dallas Floodway Feasibility StudyDallas Floodway Balanced Vision Plan

  • 8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2

    8/16

    BUILDING STRONG8

  • 8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2

    9/16

    BUILDING STRONG9

    Feasibility Cost Share Agreement (FCSA)

    o Legal Instrument / Study Agreement (w/costs)

    o Requires 50/50 Cost Share for Studyo Execution Needed to Access Federal & Non-Federal Funds

    Project Management Plan (PMP)o Provides Detailed Scope, Schedule, Budget

    o Supports FCSA

    o Guides Study/Project

    o Identifies USACE and City Responsibilities

    Feasibility Cost Share Agreement

  • 8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2

    10/16

    BUILDING STRONG10

    Levee Remediation Plan (LRP)o Identify Measures to Restore Levees to Authorized Design Standards

    Balanced Vision Plan (BVP ) - Flood Risk Management (FRM)o Potential Levee Raises at Current Design Standards

    o Removal of AT&SF Bridge

    Balanced Vision Plan (BVP) Ecosystem / Recreationo Lakes, Parks, River Meanders, Wetlands, Athletic Fields, etc.

    Interior Drainage Plan (IDP)o Pumps, Sumps, Gravity/Pressure Storm Sewers, etc.

    Local Featureso Trinity Parkway, Bridges, Santa Fe Trestle Trail, etc.

    Major Study Elements

  • 8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2

    11/16

    BUILDING STRONG11

    Total study costs estimated at $38.4 milliono 50/50 cost share Federal and City

    Citys 2009 contract award to HNTB includes an estimated

    $23 million directly applicable to this new Feasibility Study

    Citys cost share requirements already met

    However, in order to maintain schedule, WRDA language

    allows City to provide funds to keep study progressing WRDA language provides opportunity for credit of Citys

    additional funding toward future phases of projectdevelopment

    Remaining study costs estimated at $15.4 million

    Feasibility Study Costs

  • 8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2

    12/16

    BUILDING STRONG12

    Presidents Budget request comes out inFebruary for the next fiscal year

    Congress is scheduled to approve budgetsby October of the current fiscal year

    If appropriations bill is not approved at that

    time, temporary funding is providedthrough a continuing resolution until finalbill is approved

    Continuing resolution typically limits theamount of funding available

    USACE Funding Process

  • 8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2

    13/16

    BUILDING STRONG13

    Needed for FY 10 (ending 9/30/10) $4.70 M Needed for FY 11 thru 3/2011* $2.05 M USACE funding FY 10 ($1.30 M)

    USACE funding FY 11** ($0.70 M) TOTAL FUNDING NEEDS $4.75 MFOR USACE thru 3/2011

    To keep the study moving at full speed, the Cityneeds to advance $4.75 M to USACE

    * In the event that the appropriations bill is not passed by the start of October 2010,the City proposes to provide funds to maintain schedule

    ** Included in Presidents Budget; however, there is an opportunity for additionalfunding through Congressional appropriations bills that could increase this amount

    Funding Needs for USACE

  • 8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2

    14/16

    BUILDING STRONG14

    WRDA 2007 language allows the City to receive credittoward future design and construction phases of the

    project for any City contributions over 50% cost shareduring the Feasibility Study

    When the Dallas Floodway project begins design

    and/or construction phases, agreements between Cityand USACE will incorporate this credit, thereby

    reducing the Citys future funding requirements

    How does the City get credited for

    advance contributions?

  • 8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2

    15/16

    BUILDING STRONG15

    Council approval on March 10, 2010 of FCSA andto provide $4.75 million to USACE to ensurecontinued USACE progress through March 2011

    If federal funding does not meet project needs forFY 11, City may be required to provide additionalfunds at that time

    Staff Recommendation

  • 8/14/2019 4-74 Million - Feasiblity Study From Trinity River Committee Combined 03-02-10-2

    16/16

    BUILDING STRONG16

    Dallas Floodway Feasibility Study

    QUESTIONS?