Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
1/67
3.1 Measurement Method of Electrical System
1. Code E-01 : Substation and Equipment
1.1 Definition
This work item is defined as the installation works of substation and equipment in
accordance with the drawings, technical specifications and manufacturers instruction
manual at the Site, including unloading of the Contractor supplied materials at the
Contractor designated locations, site transportation, hauling, rigging, setting, assembling,
bolting, terminating, welding if necessary, alignment, inspection, calibration, test, pre-
commissioning and assistance for commissioning/start-up and operational test.
This work item shall also include, but not limited, the following ;
Installation of all parts /components/supports shipped separately for transportation
Furnishing and installation of anchor bolt/bolt/nut/washer, if required
Installation and connection of vendor cable/wire, including supply of terminal lug, ifrequired
Furnishing and installation of warning tape and sign board
Test and inspection as per the project specification and inspection procedure
Furnishing and installation of field fabricated steel support material shall not be includedin this work item, but shall be included in Code E-25.
Further details of this work item are listed below. But all other associated activities
required until issuance of Provisional Turnover Certificate shall also be included in the
scope of this work item.
Receiving, storing and maintaining the Contractor supplied materials
Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations
Mechanical and electrical connections between shipping sections, including bus and
ground joints
Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,
methodology, inspection/test plan and procedure, etc.)
Removal of existing obstacles to installation work and restoration work uponcompletion thereof. Reinforcement or protection work for existing facilities, as required
by the Contractor
Preassembling work prior to the commencement of the installation work, as necessary
Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary
-
8/12/2019 2.3.1 Measurement Method for Electical
2/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
2/67
The following works related to the installation of the work item on concretefoundation :
Checking anchor bolts and foundation with respect to location, size, level, etc.
Chipping concrete foundation Setting mortar pads and liner plates
Adjusting anchor bolts
Setting and grouting box-out anchor bolts
Mortar grouting and curing
Welding washers and/or liner plates, as required by technical specifications and/ordrawings
Opening and re-closing manholes and/or handholes for cleaning and inspection
Rust prevention during the construction work and timely removal of such rust andprevention materials, if any
Cleaning equipment inside / outside as required Application of necessary anti-seizing solvent/compound/paste for bolts and nuts
Application of specified compound/paste to gaskets
Application of touch-up paint
Preparation and submission of inspection/test record as per inspection/test plan
All other work, as required by the drawings, technical specifications and manufacturers
instruction manual
Site cleaning the work place
1.2 Measurement method and unit of quantities
1.2.1 General
The Subcontractor Prices shall not be adjusted for the differences in installation method,
size, electrical rating, weight, type of equipment and elevation/location of working places,
etc.
1.2.2 Measurement method and unit of quantities
The quantities shall be measured by number of complete set of equipment, where specified
by SET, and by length of net installed cable excluding any waste or allowance, where
specified by M.
Any accessories, components and parts will not be separately measured.
Furnishing and installation of Scaffolding should not be measured separately, but deemed
measured and included in the unit price of this work.
No measurement shall be made for any rework.
1.2.3 Progress Measurement method (to be decided later or refer to the Contractors PMS)
-
8/12/2019 2.3.1 Measurement Method for Electical
3/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
3/67
The quantities measured as per 1.2.2 above shall be broken down into the following
activities with the relevant factor for progress measurement and to calculate monthly
progress payment thereof.
Completion of installation and alignment : 80 %
Submission of inspection and test record : 15 %
Completion of Energization : 5 %
-
8/12/2019 2.3.1 Measurement Method for Electical
4/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
4/67
2. Code E-02 : Transformer
2.1 Definition
This work item is defined as the installation works of transformers in accordance with the
drawings, technical specifications and manufacturers instruction manual at the Site,
including unloading of the Contractor supplied materials at the Contractor designated
locations, site transportation, hauling, rigging, setting, assembling, bolting, terminating,
welding if necessary, alignment, inspection, calibration, test, pre-commissioning and
assistance for commissioning/start-up and operational test.
This work item shall also include, but not limited, the following ;
Installation of all parts /components/supports shipped separately for transportation Furnishing and installation of anchor bolt/bolt/nut/washer, if required
Installation and connection of vendor cable/wire, including supply of terminal lug ifrequired
Installation of transformer oil including purification and testing of the oil
Furnishing and installation of warning tape and sign board
Test and inspection as per the project specification and inspection procedure
Furnishing and installation of field fabricated steel support material shall not be included
in this work item, but shall be included in Code E-25.
Further details of this work item are listed below. But all other associated activities
required until issuance of Provisional Turnover Certificate shall also be included in the
scope of this work item.
Receiving, storing and maintaining the Contractor supplied materials
Material transportation from/to the Contractors warehouse and laydown areas, and
installation locations
Mechanical and electrical connections between shipping sections, including bus and
ground joints
Preparation of work plans and procedures and submission for the Contractors approval
prior to starting the work (work procedure, construction method statement,methodology, inspection/test plan and procedure, etc.)
Removal of existing obstacles to installation work and restoration work uponcompletion thereof. Reinforcement or protection work for existing facilities, as required
by the Contractor
Preassembling work prior to the commencement of the installation work, as necessary
Removal of reinforcing or protection materials used for the transportation or installation
of equipment, as necessary
The following works related to the installation of the work item on concrete
foundation :
Checking anchor bolts and foundation with respect to location, size, level, etc.
-
8/12/2019 2.3.1 Measurement Method for Electical
5/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
5/67
Chipping concrete foundation
Setting mortar pads and liner plates
Adjusting anchor bolts
Setting and grouting box-out anchor bolts Mortar grouting and curing
Welding washers and/or liner plates, as required by technical specifications and/ordrawings
Opening and re-closing manholes and/or handholes for cleaning and inspection
Rust prevention during the construction work and timely removal of such rust andprevention materials, if any
Cleaning equipment outside/inside as required
Application of necessary anti-seizing solvent/compound/paste for bolts and nuts
Application of specified compound/paste to gaskets
Application of touch-up paint Preparation and submission of inspection/test record as per inspection/test plan
All other work, as required by the drawings, technical specifications and manufacturersinstruction manual
Site cleaning the work place
2.2 Measurement method and unit of quantities
2.2.1 General
The Subcontractor Prices shall not be adjusted for the differences in installation method,size, electrical rating, weight, type of equipment and elevation/location of working places,
etc.
2.2.2 Measurement method and unit of quantities
The quantities shall be measured by number of complete set of transformer.
Any accessories, components and parts will not be separately measured.
Furnishing and installation of Scaffolding should not be measured separately, but deemed
measured and included in the unit price of this work.
No measurement shall be made for any rework.
2.2.3 Progress Measurement method (to be decided later or refer to the Contractor s PMS)
The quantities measured as per 2.2.2 above shall be broken down into the following
activities with the relevant factor for progress measurement and to calculate monthly
progress payment thereof.
Completion of installation and alignment : 80 %
-
8/12/2019 2.3.1 Measurement Method for Electical
6/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
6/67
Submission of inspection and test record : 15 %
Completion of Energization : 5 %
-
8/12/2019 2.3.1 Measurement Method for Electical
7/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
7/67
3. Code E-03 : Switchgear/MCC/Panel
3.1 Definition
This work item is defined as the installation works of switchgear, MCC and miscellaneous
panels in accordance with the drawings, technical specifications and manufacturers
instruction manual at the Site, including unloading of the Contractor supplied materials at
the Contractor designated locations, site transportation, hauling, rigging, setting,
assembling, bolting, welding if necessary, alignment, inspection, calibration, test, pre-
commissioning and assistance for commissioning/start-up and operational test.
This work item shall also include, but not limited, the following ;
Installation of all parts /components shipped separately for transportation Furnishing and installation of anchor bolt/bolt/nut/washer, if required
Installation and connection of vendor cable/wire, including supply of terminal lug ifrequired
Furnishing and installation of warning tape and sign board
Test and inspection as per the project specification and inspection procedure
Furnishing and installation of field fabricated steel support material shall not be included
in this work item, but shall be included in Code E-25.
Further details of this work item are listed below. But all other associated activities
required until issuance of Provisional Turnover Certificate shall also be included in the
scope of this work item.
Receiving, storing and maintaining the Contractor supplied materials
Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations
Mechanical and electrical connections between shipping sections, including bus andground joints
Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,
methodology, inspection/test plan and procedure, etc.) Removal of existing obstacles to installation work and restoration work upon
completion thereof. Reinforcement or protection work for existing facilities, as required
by the Contractor
Preassembling work prior to the commencement of the installation work, as necessary
Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary
The following works related to the installation of the work item on concretefoundation :
Checking anchor bolts and foundation with respect to location, size, level, etc.
Chipping concrete foundation
-
8/12/2019 2.3.1 Measurement Method for Electical
8/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
8/67
Setting mortar pads and liner plates
Adjusting anchor bolts
Setting and grouting box-out anchor bolts
Mortar grouting and curing Welding washers and/or liner plates, as required by technical specifications and/or
drawings
Opening and re-closing manholes and/or handholes for cleaning and inspection
Rust prevention during the construction work and timely removal of such rust and
prevention materials, if any
Cleaning equipment inside/outside as required
Application of necessary anti-seizing solvent/compound/paste for bolts and nuts
Application of specified compound/paste to gaskets
Application of touch-up paint
Preparation and submission of inspection/test record as per inspection/test plan All other work, as required by the drawings, technical specifications and manufacturers
instruction manual
Site cleaning the work place
3.2 Measurement method and unit of quantities
3.2.1 General
The Subcontractor Prices shall not be adjusted for the differences in installation method,
size, electrical rating, weight, type of equipment and elevation/location of working places,etc.
3.2.2 Measurement method and unit of quantities
The quantities shall be measured by number of panel where specified by panel, and by
number of complete set of equipment where specified by lot.
Any accessories, components and parts will not be separately measured.
Furnishing and installation of Scaffolding should not be measured separately, but deemed
measured and included in the unit price of this work.
No measurement shall be made for any rework.
3.2.3 Progress Measurement method (to be decided later or refer to the Contractor s PMS)
The quantities measured as per 3.2.2 above shall be broken down into the following
activities with the relevant factor for progress measurement and to calculate monthly
progress payment thereof.
Completion of installation and alignment : 80 %
-
8/12/2019 2.3.1 Measurement Method for Electical
9/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
9/67
Submission of inspection and test record : 15 %
Completion of Energization : 5 %
-
8/12/2019 2.3.1 Measurement Method for Electical
10/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
10/67
4. Code E-04 : Bus Duct
4.1 Definition
This work item is defined as the installation works of bus duct in accordance with the
drawings, technical specifications and manufacturers instruction manual at the Site,
including unloading of the Contractor supplied materials at the Contractor designated
locations, site transportation, hauling, rigging, setting, assembling, laying, bolting, welding
if necessary, alignment, terminating, inspection, test, pre-commissioning and assistance for
commissioning/start-up and operational test.
This work item shall also include, but not limited, the following ;
Installation of all parts /components/supports shipped separately for transportation Furnishing and installation of anchor bolt/bolt/nut/washer, if required
Furnishing of welding rod and welding consumables, if required
Test and inspection as per the project specification and inspection procedure
Furnishing and installation of field fabricated steel support material shall not be included
in this work item, but shall be included in Code E-25.
Further details of this work item are listed below. But all other associated activities
required until issuance of Provisional Turnover Certificate shall also be included in the
scope of this work item.
Receiving, storing and maintaining the Contractor supplied materials
Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations
Mechanical and electrical connections between shipping sections, including bus andground joints
Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,
methodology, inspection/test plan and procedure, etc.)
Removal of existing obstacles to installation work and restoration work upon
completion thereof. Reinforcement or protection work for existing facilities, as requiredby the Contractor
Preassembling work prior to the commencement of the installation work, as necessary
Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary
The following works related to the installation of the work item on concretefoundation :
Checking anchor bolts and foundation with respect to location, size, level, etc.
Chipping concrete foundation
Setting mortar pads and liner plates
Adjusting anchor bolts
-
8/12/2019 2.3.1 Measurement Method for Electical
11/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
11/67
Setting and grouting box-out anchor bolts
Mortar grouting and curing
Welding washers and/or liner plates, as required by technical specifications and/or
drawings Opening and re-closing manholes and/or handholes for cleaning and inspection
Rust prevention during the construction work and timely removal of such rust andprevention materials, if any
Cleaning equipment inside/outside as required
Application of necessary anti-seizing solvent/compound/paste for bolts and nuts
Application of specified compound/paste to gaskets
Application of touch-up paint
Preparation and submission of inspection/test record as per inspection/test plan
All other work, as required by the drawings, technical specifications and manufacturers
instruction manual Site cleaning the work place
4.2 Measurement method and unit of quantities
4.2.1 General
The Subcontractor Prices shall not be adjusted for the differences in installation method,
size, electrical rating, weight, type of equipment and elevation/location of working places,
etc.
4.2.2 Measurement method and unit of quantities
The quantities shall be measured by length (linear meter) along the center line of bus duct
from the construction drawing, or by number of complete set of equipment where specified
by lot.
Any accessories, components, fittings and support structure will not be separately
measured.
Furnishing and installation of Scaffolding should not be measured separately, but deemed
measured and included in the unit price of this work.
No measurement shall be made for any rework.
4.2.3 Progress Measurement method (to be decided later or refer to the Contractor s PMS)
The quantities measured as per 4.2.2 above shall be broken down into the following
activities with the relevant factor for progress measurement and to calculate monthly
progress payment thereof.
Completion of installation and alignment : 85 %
-
8/12/2019 2.3.1 Measurement Method for Electical
12/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
12/67
Submission of inspection and test record : 15 %
-
8/12/2019 2.3.1 Measurement Method for Electical
13/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
13/67
5. Code E-05 : Emergency Diesel Generator
5.1 Definition
This work item is defined as the installation works of emergency diesel generator in
accordance with the drawings, technical specifications and manufacturers instruction
manual at the Site, including unloading of the Contractor supplied materials at the
Contractor designated locations, site transportation, hauling, rigging, setting, assembling,
bolting, welding if necessary, alignment, terminating, calibration, inspection, test, pre-
commissioning and assistance for commissioning/start-up and operational test.
This work item shall also include, but not limited, the following ;
Installation of all parts /components/supports shipped separately for transportation Furnishing and installation of anchor bolt/bolt/nut/washer, if required
Installation and connection of vendor cable/wire, including supply of terminal lug ifrequired
Test and inspection as per the project specification and inspection procedure
Furnishing and installation of field fabricated steel support material shall not be included
in this work item, but shall be included in Code E-25.
Further details of this work item are listed below. But all other associated activities
required until issuance of Provisional Turnover Certificate shall also be included in the
scope of this work item.
Receiving, storing and maintaining the Contractor supplied materials
Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations
Mechanical and electrical connections between shipping sections, including bus andground joints
Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,
methodology, inspection/test plan and procedure, etc.)
Removal of existing obstacles to installation work and restoration work uponcompletion thereof. Reinforcement or protection work for existing facilities, as required
by the Contractor
Preassembling work prior to the commencement of the installation work, as necessary
Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary
The following works related to the installation of the work item on concretefoundation :
Checking anchor bolts and foundation with respect to location, size, level, etc.
Chipping concrete foundation
Setting mortar pads and liner plates
-
8/12/2019 2.3.1 Measurement Method for Electical
14/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
14/67
Adjusting anchor bolts
Setting and grouting box-out anchor bolts
Mortar grouting and curing
Welding washers and/or liner plates, as required by technical specifications and/ordrawings
Opening and re-closing manholes and/or handholes for cleaning and inspection
Rust prevention during the construction work and timely removal of such rust andprevention materials, if any
Cleaning equipment outside/inside as required
Application of necessary anti-seizing solvent/compound/paste for bolts and nuts
Application of specified compound/paste to gaskets
Application of touch-up paint
Preparation and submission of inspection/test record as per inspection/test plan
All other work, as required by the drawings, technical specifications and manufacturersinstruction manual
Site cleaning the work place
5.2 Measurement method and unit of quantities
5.2.1 General
The Subcontractor Prices shall not be adjusted for the differences in installation method,
size, electrical rating, weight, type of equipment and elevation/location of working places,
etc.
5.2.2 Measurement method and unit of quantities
The quantities shall be measured by number of complete set of diesel engine generator.
Any accessories, components, fittings and support structure will not be separately
measured.
Furnishing and installation of Scaffolding should not be measured separately, but deemed
measured and included in the unit price of this work.
No measurement shall be made for any rework.
5.2.3 Progress Measurement method(to be decided later or refer to the Contractor s PMS)
The quantities measured as per 5.2.2 above shall be broken down into the following
activities with the relevant factor for progress measurement and to calculate monthly
progress payment thereof.
Completion of installation and alignment : 85 %
Submission of inspection and test record : 15 %
-
8/12/2019 2.3.1 Measurement Method for Electical
15/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
15/67
6. Code E-06 : DC/AC and UPS System Equipment
6.1 Definition
This work item is defined as the installation works of DC/AC and UPS system equipment
in accordance with the drawings, technical specifications and manufacturers instruction
manual at the Site, including unloading of the Contractor supplied materials at the
Contractor designated locations, site transportation, hauling, rigging, setting, assembling,
bolting, welding if necessary, alignment, terminating, calibration, inspection, test,
precommissioning and assistance for commissioning/start-up and operational test.
This work item shall also include, but not limited, the following ;
Installation of all parts /components/supports shipped separately for transportation Furnishing and installation of anchor bolt/bolt/nut/washer, if required
Installation and connection of vendor cable/wire/bus bar
Installation of battery rack
Installation of battery electrolyte
Test and inspection as per the project specification and inspection procedure
Furnishing and installation of field fabricated steel support material shall not be included
in this work item, but shall be included in Code E-25.
Further details of this work item are listed below. But all other associated activities
required until issuance of Provisional Turnover Certificate shall also be included in the
scope of this work item.
Receiving, storing and maintaining the Contractor supplied materials
Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations
Mechanical and electrical connections between shipping sections, including bus andground joints
Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,
methodology, inspection/test plan and procedure, etc.) Removal of existing obstacles to installation work and restoration work upon
completion thereof. Reinforcement or protection work for existing facilities, as required
by the Contractor
Preassembling work prior to the commencement of the installation work, as necessary
Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary
The following works related to the installation of the work item on concretefoundation :
Checking anchor bolts and foundation with respect to location, size, level, etc.
Chipping concrete foundation
-
8/12/2019 2.3.1 Measurement Method for Electical
16/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
16/67
Setting mortar pads and liner plates
Adjusting anchor bolts
Setting and grouting box-out anchor bolts
Mortar grouting and curing Welding washers and/or liner plates, as required by technical specifications and/or
drawings
Opening and re-closing manholes and/or handholes for cleaning and inspection
Rust prevention during the construction work and timely removal of such rust and
prevention materials, if any
Cleaning equipment inside/outside as required
Application of necessary anti-seizing solvent/compound/paste for bolts and nuts
Application of specified compound/paste to gaskets
Application of touch-up paint
Preparation and submission of inspection/test record as per inspection/test plan All other work, as required by the drawings, technical specifications and manufacturers
instruction manual
Site cleaning the work place
6.2 Measurement method and unit of quantities
6.2.1 General
The Subcontractor Prices shall not be adjusted for the differences in installation method,
size, electrical rating, numbers of battery, weight, type of equipment and elevation/locationof working places, etc.
6.2.2 Measurement method and unit of quantities
The quantities shall be measured by number of complete set of DC/AC and UPS system.
Any accessories, components, fittings and battery rack will not be separately measured.
Furnishing and installation of Scaffolding should not be measured separately, but deemed
measured and included in the unit price of this work.
No measurement shall be made for any rework.
6.2.3 Progress Measurement method(to be decided later or refer to the Contractor s PMS)
The quantities measured as per 6.2.2 above shall be broken down into the following
activities with the relevant factor for progress measurement and to calculate monthly
progress payment thereof.
Completion of installation and alignment : 80 %
Submission of inspection and test record : 15 %
-
8/12/2019 2.3.1 Measurement Method for Electical
17/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
17/67
Completion of pre-commissioning : 5 %
-
8/12/2019 2.3.1 Measurement Method for Electical
18/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
18/67
7. Code E-07 : Cable Tray/Rack/Duct with Accessories, Fittings and Covers
7.1 Definition
This work item is defined as the installation works of cable tray/rack/duct in accordance
with the drawings, technical specifications and manufacturers instruction manual at the
Site, including unloading of the Contractor supplied materials at the Contractor designated
locations, site transportation, hauling, rigging, setting, assembling, laying, bolting, welding
if necessary, alignment and inspection.
This work item shall also include, but not limited, the following ;
Installation of cable tray/rack/duct cover
Installation of accessories and fittings including horizontal/vertical bend, tee, etc. Installation of grounding bonding jumper
Furnishing and installation of sealing compound
Furnishing and installation of cable tray rack/duct marker
Furnishing and installation of anchor bolt/bolt/nut/washer, if required
Test and inspection as per the project specification and inspection procedure
Furnishing and installation of field fabricated steel support material shall not be included
in this work item, but shall be included in Code E-25.
Further details of this work item are listed below. But all other associated activities
required until issuance of Provisional Turnover Certificate shall also be included in the
scope of this work item.
Receiving, storing and maintaining the Contractor supplied materials
Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations
Mechanical and electrical connections between shipping sections, including bus andground joints
Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,
methodology, inspection/test plan and procedure, etc.) Removal of existing obstacles to installation work and restoration work upon
completion thereof. Reinforcement or protection work for existing facilities, as required
by the Contractor
Preassembling work prior to the commencement of the installation work, as necessary
Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary
The following works related to the installation of the work item on concretefoundation :
Checking anchor bolts and foundation with respect to location, size, level, etc.
Chipping concrete foundation
-
8/12/2019 2.3.1 Measurement Method for Electical
19/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
19/67
Setting mortar pads and liner plates
Adjusting anchor bolts
Setting and grouting box-out anchor bolts
Mortar grouting and curing Welding washers and/or liner plates, as required by technical specifications and/or
drawings
Opening and re-closing manholes and/or handholes for cleaning and inspection
Rust prevention during the construction work and timely removal of such rust and
prevention materials, if any
Cleaning equipment inside/outside as required
Application of necessary anti-seizing solvent/compound/paste for bolts and nuts
Application of specified compound/paste to gaskets
Application of touch-up paint
Preparation and submission of inspection/test record as per inspection/test plan All other work, as required by the drawings, technical specifications and manufacturers
instruction manual
Site cleaning the work place
7.2 Measurement method and unit of quantities
7.2.1 General
The Subcontractor Prices shall not be adjusted for the differences in installation method,
size, electrical rating, weight, type of equipment and elevation/location of working places,etc.
7.2.2 Measurement method and unit of quantities
The quantities shall be measured by length (linear meter) or piece along the center line of
net installed cable tray/rack/duct excluding any waste or allowance from the construction
drawings.
Any accessories, fittings, elbow, cross, tee, reducer, etc. and covers will not be separately
measured.
Furnishing and installation of Scaffolding should not be measured separately, but deemed
measured and included in the unit price of this work.
No measurement shall be made for any rework.
7.2.3 Progress Measurement method(to be decided later or refer to the Contractor s PMS)
The quantities measured as per 7.2.2 above shall be broken down into the following
activities with the relevant factor for progress measurement and to calculate monthly
progress payment thereof.
-
8/12/2019 2.3.1 Measurement Method for Electical
20/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
20/67
Completion of installation and alignment : 85 %
Completion of installation of cable tray cover: 15 %
-
8/12/2019 2.3.1 Measurement Method for Electical
21/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
21/67
8. Code E-08 : Rigid Steel Conduit with Accessories, Fittings and Boxes
8.1 Definition
This work item is defined as the installation works of rigid steel conduit in accordance with
the drawings, technical specifications and manufacturers instruction manual at the Site,
including unloading of the Contractor supplied materials at the Contractor designated
locations, site transportation, hauling, rigging, cutting, threading, reaming, bending, fitting,
assembling, setting, laying, bolting, welding if necessary, alignment and inspection.
This work item shall also include, but not limited, the following ;
Installation of accessories and fittings
Installation of condulets and boxes with cover plate Installation of steel conduit with fittings
Furnishing and installation of sealing compound
Furnishing and installation of conduit marker
Furnishing and installation of anchor bolt/bolt/nut/washer, if required
Test and inspection as per the project specification and inspection procedure
Furnishing and installation of field fabricated steel support material shall not be included
in this work item, but shall be included in Code E-25.
Excavation, concrete work and backfilling shall not be included in this work item, but shall
be included in Code E-24.
Further details of this work item are listed below. But all other associated activities
required until issuance of Provisional Turnover Certificate shall also be included in the
scope of this work item.
Receiving, storing and maintaining the Contractor supplied materials
Material transportation from/to the Contractors warehouse and laydown areas, and
installation locations
Preparation of work plans and procedures and submission for the Contractors approval
prior to starting the work (work procedure, construction method statement,methodology, inspection/test plan and procedure, etc.)
Removal of existing obstacles to installation work and restoration work uponcompletion thereof. Reinforcement or protection work for existing facilities, as required
by the Contractor
Preassembling work prior to the commencement of the installation work, as necessary
Removal of reinforcing or protection materials used for the transportation or installation
of equipment, as necessary
The following works related to the installation of the work item on concrete
foundation :
Checking anchor bolts and foundation with respect to location, size, level, etc.
-
8/12/2019 2.3.1 Measurement Method for Electical
22/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
22/67
Chipping concrete foundation
Setting mortar pads and liner plates
Adjusting anchor bolts
Setting and grouting box-out anchor bolts Mortar grouting and curing
Welding washers and/or liner plates, as required by technical specifications and/ordrawings
Opening and re-closing manholes and/or handholes for cleaning and inspection
Rust prevention during the construction work and timely removal of such rust andprevention materials, if any
Cleaning equipment inside/outside as required
Application of necessary anti-seizing solvent/compound/paste for bolts and nuts
Application of touch-up paint
Preparation and submission of inspection/test record as per inspection/test plan All other work, as required by the drawings, technical specifications and manufacturers
instruction manual
Site cleaning the work place
8.2 Measurement method and unit of quantities
8.2.1 General
The Subcontractor Prices shall not be adjusted for the differences in installation method,
size, electrical rating, weight, type of equipment and elevation/location of working places,etc.
8.2.2 Measurement method and unit of quantities
The quantities shall be measured by length (linear meter) of net installed rigid steel conduit
excluding any waste or allowance from the construction drawings.
Any accessories, fittings, condulets and boxes will not be separately measured.
Furnishing and installation of Scaffolding should not be measured separately, but deemed
measured and included in the unit price of this work.
No measurement shall be made for any rework.
8.2.3 Progress Measurement method(to be decided later or refer to the Contractor s PMS)
The quantities measured as per 8.2.2 above shall be broken down into the following
activities with the relevant factor for progress measurement and to calculate monthly
progress payment thereof.
Completion of installation and alignment : 85 %
-
8/12/2019 2.3.1 Measurement Method for Electical
23/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
23/67
Submission of inspection record : 15 %
-
8/12/2019 2.3.1 Measurement Method for Electical
24/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
24/67
9. Code E-09 : Flexible Conduit with Accessories, Fittings and Boxes
9.1 Definition
This work item is defined as the installation works of flexible conduit in accordance with
the drawings, technical specifications and manufacturers instruction manual at the Site,
including unloading of the Contractor supplied materials at the Contractor designated
locations, site transportation, hauling, rigging, cutting, threading, reaming, bending, fitting,
assembling, setting, laying, bolting, welding if necessary, alignment and inspection.
This work item shall also include, but not limited, the following ;
Installation of flexible conduit
Installation of accessories and fittings Installation of condulets and boxes with cover plate
Furnishing and installation of sealing compound
Furnishing and installation of conduit marker, if required
Furnishing and installation of anchor bolt/bolt/nut/washer, if required
Installation and termination of grounding jumper
Test and inspection as per the project specification and inspection procedure
Furnishing and installation of field fabricated steel support material shall not be included
in this work item, but shall be included in Code E-25.
Further details of this work item are listed below. But all other associated activities
required until issuance of Provisional Turnover Certificate shall also be included in the
scope of this work item.
Receiving, storing and maintaining the Contractor supplied materials
Material transportation from/to the Contractors warehouse and laydown areas, and
installation locations
Removal of existing obstacles to installation work and restoration work upon
completion thereof. Reinforcement or protection work for existing facilities, as required
by the Contractor
Preassembling work prior to the commencement of the installation work, as necessary Removal of reinforcing or protection materials used for the transportation or installation
of equipment, as necessary
Welding washers and/or liner plates, as required by technical specifications and/ordrawings
Opening and re-closing manholes and/or handholes for cleaning and inspection
Rust prevention during the construction work and timely removal of such rust andprevention materials, if any
Cleaning equipment inside/outside as required
Application of necessary anti-seizing solvent/compound/paste for bolts and nuts
Application of touch-up paint
-
8/12/2019 2.3.1 Measurement Method for Electical
25/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
25/67
Preparation and submission of inspection/test record as per inspection/test plan
All other work, as required by the drawings, technical specifications and manufacturersinstruction manual
Site cleaning the work place
9.2 Measurement method and unit of quantities
9.2.1 General
The Subcontractor Prices shall not be adjusted for the differences in installation method,
size, electrical rating, weight, insulation, type of equipment and elevation/location of
working places, etc.
9.2.2 Measurement method and unit of quantities
The quantities shall be measured by length (linear meter) of net installed flexible conduit
excluding any waste or allowance from the construction drawings.
Any accessories, fittings, condulets and boxes will not be separately measured.
Furnishing and installation of Scaffolding should not be measured separately, but deemed
measured and included in the unit price of this work.
No measurement shall be made for any rework.
9.2.3 Progress Measurement method(to be decided later or refer to the Contractor s PMS)
The quantities measured as per 9.2.2 above shall be broken down into the following
activities with the relevant factor for progress measurement and to calculate monthly
progress payment thereof.
Completion of installation and alignment : 100 %
-
8/12/2019 2.3.1 Measurement Method for Electical
26/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
26/67
10. Code E-10 : PVC Conduit with Accessories, Fittings and Boxes
10.1 Definition
This work item is defined as the installation works of PVC conduit in accordance with the
drawings, technical specifications and manufacturers instruction manual at the Site,
including unloading of the Contractor supplied materials at the Contractor designated
locations, site transportation, hauling, rigging, cutting, reaming, bending, fitting,
assembling, setting, laying, bolting, alignment and inspection.
This work item shall also include, but not limited, the following ;
Installation of PVC conduit
Installation of accessories and fittings Furnishing and installation of sealing compound
Furnishing and installation of conduit marker, if required
Furnishing and installation of anchor bolt/bolt/nut/washer, if required
Test and inspection as per the project specification and inspection procedure
Furnishing and installation of field fabricated steel support material shall not be included
in this work item, but shall be included in Code E-25.
Excavation, concrete work and backfilling shall not be included in this work item, but shall
be included in Code E-24.
Further details of this work item are listed below. But all other associated activities
required until issuance of Provisional Turnover Certificate shall also be included in the
scope of this work item.
Receiving, storing and maintaining the Contractor supplied materials
Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations
Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,
methodology, inspection/test plan and procedure, etc.) Removal of existing obstacles to installation work and restoration work upon
completion thereof. Reinforcement or protection work for existing facilities, as required
by the Contractor
Preassembling work prior to the commencement of the installation work, as necessary
Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary
The following works related to the installation of the work item on concretefoundation :
Checking anchor bolts and foundation with respect to location, size, level, etc.
Chipping concrete foundation
-
8/12/2019 2.3.1 Measurement Method for Electical
27/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
27/67
Setting mortar pads and liner plates
Adjusting anchor bolts
Setting and grouting box-out anchor bolts
Mortar grouting and curing Welding washers and/or liner plates, as required by technical specifications and/or
drawings
Opening and re-closing manholes and/or handholes for cleaning and inspection
Cleaning equipment inside/outside as required
Application of necessary anti-seizing solvent/compound/paste for bolts and nuts
Preparation and submission of inspection/test record as per inspection/test plan
All other work, as required by the drawings, technical specifications and manufacturersinstruction manual
Site cleaning the work place
10.2 Measurement method and unit of quantities
10.2.1 General
The Subcontractor Prices shall not be adjusted for the differences in installation method,
size, electrical rating, weight, depth of burial, type of equipment and elevation/location of
working places, etc.
10.2.2 Measurement method and unit of quantities
The quantities shall be measured by length (linear meter) of net installed PVC conduit
excluding any waste or allowance from the construction drawings.
Any accessories, fittings and boxes will not be separately measured.
Furnishing and installation of Scaffolding should not be measured separately, but deemed
measured and included in the unit price of this work.
No measurement shall be made for any rework.
10.2.3 Progress Measurement method(to be decided later or refer to the Contractor s PMS)
The quantities measured as per 10.2.2 above shall be broken down into the following
activities with the relevant factor for progress measurement and to calculate monthly
progress payment thereof.
Completion of installation and alignment : 90 %
Submission of inspection record : 10 %
-
8/12/2019 2.3.1 Measurement Method for Electical
28/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
28/67
11. Code E-11 : 3.6/6/11KV Cable
11.1 Definition
This work item is defined as the installation works of 3.6/6/11KV power cable in
accordance with the drawings, technical specifications and manufacturers instruction
manual at the Site, including unloading of the Contractor supplied materials at the
Contractor designated locations, site transportation, hauling, rigging, pulling, laying,
arrangement, cutting, inspection, test, pre-commissioning and assistance for
commissioning/start-up and operational test.
This work item shall also include, but not limited, the following ;
Arrangement of cables Protection of installed cables from damage
Furnishing and installation of cable marker
Furnishing and application of cable pulling compound
Furnishing and installation of electrical tapes
Furnishing and installation of bolt/nut/washer, if required
Test and inspection as per the project specification and inspection procedure
Termination and splicing of 3.6/6/11KV cable shall not be included in this work item, but
shall be included in Code E-12.
Excavation, concrete work and backfilling shall not be included in this work item, but shall
be included in Code E-24.
Further details of this work item are listed below. But all other associated activities
required until issuance of Provisional Turnover Certificate shall also be included in the
scope of this work item.
Receiving, storing and maintaining the Contractor supplied materials
Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations
Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,
methodology, inspection/test plan and procedure, etc.)
Removal of existing obstacles to installation work and restoration work uponcompletion thereof. Reinforcement or protection work for existing facilities, as required
by the Contractor
Preassembling work prior to the commencement of the installation work, as necessary
Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary
The following works related to the installation of the work item on concrete
foundation :
-
8/12/2019 2.3.1 Measurement Method for Electical
29/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
29/67
Checking anchor bolts and foundation with respect to location, size, level, etc.
Chipping concrete foundation
Setting mortar pads and liner plates
Adjusting anchor bolts Setting and grouting box-out anchor bolts
Mortar grouting and curing
Welding washers and/or liner plates, as required by technical specifications and/ordrawings
Opening and re-closing manholes and/or handholes for cleaning and inspection
Rust prevention during the construction work and timely removal of such rust andprevention materials, if any
Cleaning equipment inside/outside as required
Application of necessary anti-seizing solvent/compound/paste for bolts and nuts
Preparation and submission of inspection/test record as per inspection/test plan All other work, as required by the drawings, technical specifications and manufacturers
instruction manual
Site cleaning the work place
11.2 Measurement method and unit of quantities
11.2.1 General
The Subcontractor Prices shall not be adjusted for the differences in installation method,
size, electrical rating, weight, depth of burial, type of insulation, type of equipment andelevation/location of working places, etc.
11.2.2 Measurement method and unit of quantities
The quantities shall be measured by length (linear meter) of net installed cable excluding
any waste or allowance from the construction drawings.
Any accessories and fittings will not be separately measured.
Furnishing and installation of Scaffolding should not be measured separately, but deemed
measured and included in the unit price of this work.
No measurement shall be made for any rework.
11.2.3 Progress Measurement method(to be decided later or refer to the Contractors PMS)
The quantities measured as per 11.2.2 above shall be broken down into the following
activities with the relevant factor for progress measurement and to calculate monthly
progress payment thereof.
Completion of installation and alignment : 80 %
-
8/12/2019 2.3.1 Measurement Method for Electical
30/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
30/67
Submission of inspection/test record : 10 %
Completion of energization : 10 %
-
8/12/2019 2.3.1 Measurement Method for Electical
31/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
31/67
12. Code E-12 : 3.6/6/8.7/15KV Cable Termination and Splicing Kit
12.1 Definition
This work item is defined as the installation works of termination and splicing kits for
1.8/3/6/10KV power cable in accordance with the drawings, technical specifications and
manufacturers instruction manual at the Site, including unloading of the Contractor
supplied materials at the Contractor designated locations, site transportation, hauling,
cutting, stripping, compressing, fitting, bolting, laying, arrangement, inspection, test, pre-
commissioning and assistance for commissioning/start-up and operational test.
This work item shall also include, but not limited, the following ;
Termination and Splicing of cable installed Furnishing and installation of electrical tapes
Furnishing and installation of bolt/nut/washer, if required
Furnishing and installation of warning tape and sign board
Test and inspection as per the project specification and inspection procedure
Further details of this work item are listed below. But all other associated activities
required until issuance of Provisional Turnover Certificate shall also be included in the
scope of this work item.
Receiving, storing and maintaining the Contractor supplied materials
Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations
Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,
methodology, inspection/test plan and procedure, etc.)
Removal of existing obstacles to installation work and restoration work uponcompletion thereof. Reinforcement or protection work for existing facilities, as required
by the Contractor
Preassembling work prior to the commencement of the installation work, as necessary
Removal of reinforcing or protection materials used for the transportation or installation
of equipment, as necessary The following works related to the installation of the work item on concrete
foundation :
Checking anchor bolts and foundation with respect to location, size, level, etc.
Chipping concrete foundation
Setting mortar pads and liner plates
Adjusting anchor bolts
Setting and grouting box-out anchor bolts
Mortar grouting and curing
Welding washers and/or liner plates, as required by technical specifications and/or
drawings
-
8/12/2019 2.3.1 Measurement Method for Electical
32/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
32/67
Opening and re-closing manholes and/or handholes for cleaning and inspection
Cleaning equipment inside/outside as required
Preparation and submission of inspection/test record as per inspection/test plan
All other work, as required by the drawings, technical specifications and manufacturersinstruction manual
Site cleaning the work place
12.2 Measurement method and unit of quantities
12.2.1 General
The Subcontractor Prices shall not be adjusted for the differences in installation method,
size, electrical rating, weight, depth of burial, type of insulation, type of equipment and
elevation/location of working places, etc.
12.2.2 Measurement method and unit of quantities
The quantities shall be measured by number of complete set of termination kit from the
construction drawings and by number of complete set of splicing kit physically done at Site
due to cable drum limitation.
Any accessories and fittings will not be separately measured.
Furnishing and installation of Scaffolding should not be measured separately, but deemed
measured and included in the unit price of this work.
No measurement shall be made for any rework.
12.2.3 Progress Measurement method(to be decided later or refer to the Contractor s PMS)
The quantities measured as per 12.2.2 above shall be broken down into the following
activities with the relevant factor for progress measurement and to calculate monthly
progress payment thereof.
Completion of installation and alignment : 80 % Submission of inspection/test record : 20%
-
8/12/2019 2.3.1 Measurement Method for Electical
33/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
33/67
13. Code E-13 : 600V/1KV Power/Control/Instrument/FO/miscellaneous Cable
13.1 Definition
This work item is defined as the installation works of 600V/1KV power cable, control
cable, telephone cable, F/A cable, CCTV cable, Access Control cable, Public
Address/paging cable and miscellaneous cable in accordance with the drawings, technical
specifications and manufacturers instruction manual at the Site, including unloading of the
Contractor supplied materials at the Contractor designated locations, site transportation,
hauling, rigging, pulling, laying, arrangement, cutting, stripping, compressing, fitting,
Splicing and terminating, bolting, inspection, test, pre-commissioning and assistance for
commissioning/start-up and operational test.
This work item shall also include, but not limited, the following ;
Arrangement of cables
Termination and Splicing of cable installed
Furnishing and installation of termination material such as terminal lug, wire connector,etc.
Protection of installed cables from damage
Furnishing and installation of cable tie
Furnishing and installation of cable marker
Furnishing and application of cable pulling compound
Furnishing and application of duct sealing compound
Furnishing and installation of electrical tapes
Furnishing and installation of bolt/nut/washer, if required
Test and inspection as per the project specification and inspection procedure
Excavation, concrete work and backfilling shall not be included in this work item, but shall
be included in Code E-24.
Further details of this work item are listed below. But all other associated activities
required until issuance of Provisional Turnover Certificate shall also be included in the
scope of this work item.
Receiving, storing and maintaining the Contractor supplied materials Material transportation from/to the Contractors warehouse and laydown areas, and
installation locations
Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,
methodology, inspection/test plan and procedure, etc.)
Removal of existing obstacles to installation work and restoration work upon
completion thereof. Reinforcement or protection work for existing facilities, as required
by the Contractor
Preassembling work prior to the commencement of the installation work, as necessary
-
8/12/2019 2.3.1 Measurement Method for Electical
34/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
34/67
Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary
The following works related to the installation of the work item on concrete
foundation : Checking anchor bolts and foundation with respect to location, size, level, etc.
Chipping concrete foundation
Setting mortar pads and liner plates
Adjusting anchor bolts
Setting and grouting box-out anchor bolts
Mortar grouting and curing
Welding washers and/or liner plates, as required by technical specifications and/ordrawings
Opening and re-closing manholes and/or handholes for cleaning and inspection
Rust prevention during the construction work and timely removal of such rust andprevention materials, if any
Cleaning equipment inside/outside as required
Application of necessary anti-seizing solvent/compound/paste for bolts and nuts
Preparation and submission of inspection/test record as per inspection/test plan
All other work, as required by the drawings, technical specifications and manufacturersinstruction manual
Site cleaning the work place
13.2 Measurement method and unit of quantities
13.2.1 General
The Subcontractor Prices shall not be adjusted for the differences in installation method,
size, electrical rating, weight, depth of burial, type of insulation, type of equipment and
elevation/location of working places, etc.
13.2.2 Measurement method and unit of quantities
The quantities shall be measured by length (linear meter) of net installed cable excluding
any waste or allowance from the construction drawings.
Any accessories, terminal lugs and fittings will not be separately measured.
Furnishing and installation of Scaffolding should not be measured separately, but deemed
measured and included in the unit price of this work.
No measurement shall be made for any rework.
13.2.3 Progress Measurement method(to be decided later or refer to the Contractors PMS)
-
8/12/2019 2.3.1 Measurement Method for Electical
35/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
35/67
The quantities measured as per 13.2.2 above shall be broken down into the following
activities with the relevant factor for progress measurement and to calculate monthly
progress payment thereof.
Completion of installation and alignment : 80 %
Submission of inspection/test record : 10 %
Completion of pre-commissioning : 10 %
-
8/12/2019 2.3.1 Measurement Method for Electical
36/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
36/67
14. Code E-14 : Lighting Fixture
14.1 Definition
This work item is defined as the installation works of lighting fixture in accordance with
the drawings, technical specifications and manufacturers instruction manual at the Site,
including unloading of the Contractor supplied materials at the Contractor designated
locations, site transportation, hauling, rigging, fitting, setting, assembling, bolting, welding
if necessary, alignment, inspection, test, pre-commissioning and assistance for
commissioning/start-up and operational test.
This work item shall also include, but not limited, the following ;
Installation of ballast, lamp, diffuser, louver and mounting accessories Replacement of lamps
Installation of pole
Furnishing and installation of anchor bolt/nut/washer, if required
Test and inspection as per the project specification and inspection procedure
Furnishing and installation of field fabricated steel support material shall not be included in
this work item, but shall be included in Code E-25.
Excavation, concrete work and backfilling shall not be included in this work item, but shall
be included in Code E-24.
Further details of this work item are listed below. But all other associated activities
required until issuance of Provisional Turnover Certificate shall also be included in the
scope of this work item.
Receiving, storing and maintaining the Contractor supplied materials
Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations
Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,
methodology, inspection/test plan and procedure, etc.) Removal of existing obstacles to installation work and restoration work upon
completion thereof. Reinforcement or protection work for existing facilities, as required
by the Contractor
Preassembling work prior to the commencement of the installation work, as necessary
Removal of reinforcing or protection materials used for the transportation or installation
of equipment, as necessary
The following works related to the installation of the work item on concrete
foundation :
Checking anchor bolts and foundation with respect to location, size, level, etc.
Chipping concrete foundation
-
8/12/2019 2.3.1 Measurement Method for Electical
37/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
37/67
Setting mortar pads and liner plates
Adjusting anchor bolts
Setting and grouting box-out anchor bolts
Mortar grouting and curing Welding washers and/or liner plates, as required by technical specifications and/or
drawings
Opening and re-closing manholes and/or handholes for cleaning and inspection
Rust prevention during the construction work and timely removal of such rust and
prevention materials, if any
Cleaning equipment inside/outside as required
Application of necessary anti-seizing solvent/compound/paste for bolts and nuts
Application of touch-up paint
Preparation and submission of inspection/test record as per inspection/test plan
All other work, as required by the drawings, technical specifications and manufacturersinstruction manual
Site cleaning the work place
14.2 Measurement method and unit of quantities
14.2.1 General
The Subcontractor Prices shall not be adjusted for the differences in installation method,
size, electrical rating, weight, depth of burial, type of insulation, type of equipment and
elevation/location of working places, etc.
14.2.2 Measurement method and unit of quantities
The quantities shall be measured by number of complete set of lighting fixture from the
construction drawings.
Any mounting accessories, poles, ballast, louver, diffuser and lamps will not be separately
measured.
Furnishing and installation of Scaffolding should not be measured separately, but deemed
measured and included in the unit price of this work.
No measurement shall be made for any rework.
14.2.3 Progress Measurement method(to be decided later or refer to the Contractors PMS)
The quantities measured as per 14.2.2 above shall be broken down into the following
activities with the relevant factor for progress measurement and to calculate monthly
progress payment thereof.
Completion of installation and alignment : 80 %
-
8/12/2019 2.3.1 Measurement Method for Electical
38/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
38/67
Submission of inspection/test record : 10 %
Completion of energization : 10 %
-
8/12/2019 2.3.1 Measurement Method for Electical
39/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
39/67
15. Code E-15 : Wiring Device
15.1 Definition
This work item is defined as the installation works of receptacle, switch, welding
receptacle, terminal box, cable gland and local control station in accordance with the
drawings, technical specifications and manufacturers instruction manual at the Site,
including unloading of the Contractor supplied materials at the Contractor designated
locations, site transportation, hauling, fitting, setting, assembling, bolting, welding if
necessary, alignment, inspection, test, pre-commissioning and assistance for
commissioning/start-up and operational test.
This work item shall also include, but not limited, the following ;
Installation of pull box, outlet box, cover plate and mounting accessories
Furnishing and installation of anchor bolt/nut/washer, if required
Test and inspection as per the project specification and inspection procedure
Furnishing and installation of field fabricated steel support material shall not be included in
this work item, but shall be included in Code E-25.
Further details of this work item are listed below. But all other associated activities
required until issuance of Provisional Turnover Certificate shall also be included in the
scope of this work item.
Receiving, storing and maintaining the Contractor supplied materials
Material transportation from/to the Contractors warehouse and laydown areas, and
installation locations
Preparation of work plans and procedures and submission for the Contractors approval
prior to starting the work (work procedure, construction method statement,
methodology, inspection/test plan and procedure, etc.)
Removal of existing obstacles to installation work and restoration work upon
completion thereof. Reinforcement or protection work for existing facilities, as required
by the Contractor
Preassembling work prior to the commencement of the installation work, as necessary Removal of reinforcing or protection materials used for the transportation or installation
of equipment, as necessary
The following works related to the installation of the work item on concrete
foundation :
Checking anchor bolts and foundation with respect to location, size, level, etc.
Chipping concrete foundation
Setting mortar pads and liner plates
Adjusting anchor bolts
Setting and grouting box-out anchor bolts
Mortar grouting and curing
-
8/12/2019 2.3.1 Measurement Method for Electical
40/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
40/67
Welding washers and/or liner plates, as required by technical specifications and/ordrawings
Opening and re-closing manholes and/or handholes for cleaning and inspection
Rust prevention during the construction work and timely removal of such rust andprevention materials, if any
Cleaning equipment inside/outside as required
Application of necessary anti-seizing solvent/compound/paste for bolts and nuts
Application of touch-up paint
Preparation and submission of inspection/test record as per inspection/test plan
All other work, as required by the drawings, technical specifications and manufacturers
instruction manual
Site cleaning the work place
15.2 Measurement method and unit of quantities
15.2.1 General
The Subcontractor Prices shall not be adjusted for the differences in installation method,
size, electrical rating, weight, depth of burial, type of insulation, type of equipment and
elevation/location of working places, etc.
15.2.2 Measurement method and unit of quantities
The quantities shall be measured by number of complete set of wiring device from the
construction drawings.
Any mounting accessories and cover plates will not be separately measured.
Furnishing and installation of Scaffolding should not be measured separately, but deemed
measured and included in the unit price of this work.
No measurement shall be made for any rework.
15.2.3 Progress Measurement method(to be decided later or refer to the Contractor s PMS)
The quantities measured as per 15.2.2 above shall be broken down into the following
activities with the relevant factor for progress measurement and to calculate monthly
progress payment thereof.
Completion of installation and alignment : 90 %
Submission of inspection/test record : 10 %
-
8/12/2019 2.3.1 Measurement Method for Electical
41/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
41/67
16. Code E-16 : CCTV/Access Control System Equipment
16.1 Definition
This work item is defined as the installation works of CCTV/Access Control system
equipment in accordance with the drawings, technical specifications and manufacturers
instruction manual at the Site, including unloading of the Contractor supplied materials at
the Contractor designated locations, site transportation, hauling, rigging, fitting, setting,
assembling, bolting, welding if necessary, alignment, inspection, calibration, test, pre-
commissioning and assistance for commissioning/start-up and operational test.
This work item shall also include, but not limited, the following ;
Installation of parts/components/supports shipped separately for transportation Installation of mounting accessories, boxes and bracket, etc.
Installation and connection of vendor cable/wire, including supply of terminal lug ifrequired
Furnishing and installation of anchor bolt/nut/washer, if required
Test and inspection as per the project specification and inspection procedure
Furnishing and installation of field fabricated steel support material shall not be included in
this work item, but shall be included in Code E-25.
Excavation, concrete work and backfilling shall not be included in this work item, but shall
be included in Code E-24.
Further details of this work item are listed below. But all other associated activities
required until issuance of Provisional Turnover Certificate shall also be included in the
scope of this work item.
Receiving, storing and maintaining the Contractor supplied materials
Material transportation from/to the Contractors warehouse and laydown areas, and
installation locations
Preparation of work plans and procedures and submission for the Contractors approval
prior to starting the work (work procedure, construction method statement,methodology, inspection/test plan and procedure, etc.)
Removal of existing obstacles to installation work and restoration work uponcompletion thereof. Reinforcement or protection work for existing facilities, as required
by the Contractor
Preassembling work prior to the commencement of the installation work, as necessary
Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary
The following works related to the installation of the work item on concretefoundation :
Checking anchor bolts and foundation with respect to location, size, level, etc.
-
8/12/2019 2.3.1 Measurement Method for Electical
42/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
42/67
Chipping concrete foundation
Setting mortar pads and liner plates
Adjusting anchor bolts
Setting and grouting box-out anchor bolts Mortar grouting and curing
Welding washers and/or liner plates, as required by technical specifications and/ordrawings
Opening and re-closing manholes and/or handholes for cleaning and inspection
Rust prevention during the construction work and timely removal of such rust andprevention materials, if any
Cleaning equipment inside/outside as required
Application of necessary anti-seizing solvent/compound/paste for bolts and nuts
Application of touch-up paint
Preparation and submission of inspection/test record as per inspection/test plan All other work, as required by the drawings, technical specifications and manufacturers
instruction manual
Site cleaning the work place
16.2 Measurement method and unit of quantities
16.2.1 General
The Subcontractor Prices shall not be adjusted for the differences in installation method,
size, electrical rating, weight, depth of burial, type of insulation, type of equipment andelevation/location of working places, etc.
16.2.2 Measurement method and unit of quantities
The quantities shall be measured by number of complete set of CCTV/Access Control
system equipment from the construction drawings.
Any boxes, mounting accessories and brackets will not be separately measured.
Furnishing and installation of Scaffolding should not be measured separately, but deemed
measured and included in the unit price of this work.
No measurement shall be made for any rework.
16.2.3 Progress Measurement method(to be decided later or refer to the Contractors PMS)
The quantities measured as per 16.2.2 above shall be broken down into the following
activities with the relevant factor for progress measurement and to calculate monthly
progress payment thereof.
Completion of installation and alignment : 80 %
-
8/12/2019 2.3.1 Measurement Method for Electical
43/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
43/67
Submission of inspection/test record : 10 %
Completion of pre-commissioning : 10 %
-
8/12/2019 2.3.1 Measurement Method for Electical
44/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
44/67
17. Code E-17 : Communication System Equipment
17.1 Definition
This work item is defined as the installation works of Public Address/ Paging/
Telephone/Multi-Function/Radio system equipment in accordance with the drawings,
technical specifications and manufacturers instruction manual at the Site, including
unloading of the Contractor supplied materials at the Contractor designated locations, site
transportation, hauling, rigging, fitting, setting, assembling, bolting, welding if necessary,
alignment, inspection, calibration, test, pre-commissioning and assistance for
commissioning/start-up and operational test.
This work item shall also include, but not limited, the following ;
Installation of parts/components/supports shipped separately for transportation
Installation of mounting accessories, boxes and bracket, etc.
Installation and connection of vendor cable/wire, including supply of terminal lug ifrequired
Furnishing and installation of anchor bolt/nut/washer, if required
Test and inspection as per the project specification and inspection procedure
Furnishing and installation of field fabricated steel support material shall not be included in
this work item, but shall be included in Code E-25.
Further details of this work item are listed below. But all other associated activities
required until issuance of Provisional Turnover Certificate shall also be included in the
scope of this work item.
Receiving, storing and maintaining the Contractor supplied materials
Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations
Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,
methodology, inspection/test plan and procedure, etc.)
Removal of existing obstacles to installation work and restoration work uponcompletion thereof. Reinforcement or protection work for existing facilities, as required
by the Contractor
Preassembling work prior to the commencement of the installation work, as necessary
Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary
The following works related to the installation of the work item on concretefoundation :
Checking anchor bolts and foundation with respect to location, size, level, etc.
Chipping concrete foundation
Setting mortar pads and liner plates
-
8/12/2019 2.3.1 Measurement Method for Electical
45/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
45/67
Adjusting anchor bolts
Setting and grouting box-out anchor bolts
Mortar grouting and curing
Welding washers and/or liner plates, as required by technical specifications and/ordrawings
Opening and re-closing manholes and/or handholes for cleaning and inspection
Rust prevention during the construction work and timely removal of such rust andprevention materials, if any
Cleaning equipment inside/outside as required
Application of necessary anti-seizing solvent/compound/paste for bolts and nuts
Application of touch-up paint
Preparation and submission of inspection/test record as per inspection/test plan
All other work, as required by the drawings, technical specifications and manufacturers
instruction manual Site cleaning the work place
17.2 Measurement method and unit of quantities
17.2.1 General
The Subcontractor Prices shall not be adjusted for the differences in installation method,
size, electrical rating, weight, depth of burial, type of insulation, type of equipment and
elevation/location of working places, etc.
17.2.2 Measurement method and unit of quantities
The quantities shall be measured by number of complete set of Public
Address/paging/Telephone/Multi Function/Radio system equipment from the construction
drawings.
Any boxes, mounting accessories and brackets will not be separately measured.
Furnishing and installation of Scaffolding should not be measured separately, but deemed
measured and included in the unit price of this work.
No measurement shall be made for any rework.
17.2.3 Progress Measurement method(to be decided later or refer to the Contractors PMS)
The quantities measured as per 17.2.2 above shall be broken down into the following
activities with the relevant factor for progress measurement and to calculate monthly
progress payment thereof.
Completion of installation and alignment : 80 %
Submission of inspection/test record : 10 %
-
8/12/2019 2.3.1 Measurement Method for Electical
46/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
46/67
Completion of pre-commissioning : 10 %
-
8/12/2019 2.3.1 Measurement Method for Electical
47/67
Long Son Petrochemical Complex BCD Measurement GeneralElectrical and Instrument
47/67
18. Code E-18 : TEL/LAN System Equipment
18.1 Definition
This work item is defined as the installation works of TEL/LAN system equipment in
accordance with the drawings, technical specifications and manufacturers instruction
manual at the Site, including unloading of the Contractor supplied materials at the
Contractor designated locations, site transportation, hauling, rigging, fitting, setting,
assembling, bolting, welding if necessary, alignment, inspection, calibration, test, pre-
commissioning and assistance for commissioning/start-up and operational test.
This work item shall also include, but not limited, the following ;
Installation of parts/components/supports shipped separately for transportation Installation of mounting accessories, boxes and bracket, etc.
Installation and connection of vendor cable/wire, including supply of terminal lug ifrequired
Furnishing and installation of anchor bolt/nut/washer, if required
Test and inspection as per the project specification and inspection procedure
Furnishing and installation of field fabricated steel support material shall not be included in
this work item, but shall be included in Code E-25.
Further details of this work item are listed below. But all other associated activities
required until issuance of Provisional Turnover Certificate shall also be included in the
scope of this work item.
Receiving, storing and maintaining the Contractor supplied materials
Material transportation from/to the Contractors warehouse and laydown areas, andinstallation locations
Preparation of work plans and procedures and submission for the Contractors approvalprior to starting the work (work procedure, construction method statement,
methodology, inspection/test plan and procedure, etc.)
Removal of existing obstacles to installation work and restoration work upon
completion thereof. Reinforcement or protection work for existing facilities, as requiredby the Contractor
Preassembling work prior to the commencement of the installation work, as necessary
Removal of reinforcing or protection materials used for the transportation or installationof equipment, as necessary
The following works related to the installation of the work item on concretefoundation :
Checking anchor bolts and foundation with respect to location, size, level, etc.
Chipping concrete foundation
Setting mortar pads and liner