231-executive board meeting of nha

Upload: hamid-naveed

Post on 01-Jun-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 231-Executive Board Meeting of NHA

    1/48

    NHA Executive Board’s Confirmed Minutes

    NATIONAL HIGHWAY AUTHORITYSecretariat Section

    CONFIRMED MINUTES

    Subject: 231st Meeting of the NHA Executive Board held on Dec

    17, 2013 at Islamabad

    1.

    Introduction

    1.1. The 231st meeting of the Executive Board of the National

    Highway Authority was held at 1030 hours on Dec 17, 2013 at the

    NHA Head Office Auditorium, Islamabad. Mr Maroof Afzal, Chairman

    NHA presided.

    1.2. All Members attended except Mr Raja Nowsherwan,

    Member (Planning) NHA being on sick leave. List of participants is at

    Annex-A.

    1.3. The meeting commenced with recitation of verses from theHoly Quran and Urdu translation.

  • 8/9/2019 231-Executive Board Meeting of NHA

    2/48

    NHA Executive Board’s Confirmed Minutes

    Item Noa. Secretariat /Confirmation of minutes 2

    b. Planning 8

    c. Construction/Aided Projects 5

    d. BOT/PPP 1

    e. Finance 2

    f. Operation 1Total 19

    4. Agenda Item 1

    Confirmation of Minutes - 230th Meeting of the

    Executive Board Held on Sep 17, 2013

    4.1. The Secretary NHA solicited confirmation of minutes of 

    the 230th Executive Board meeting held on Sep 17, 2013. Comments

    / observations from Mr Munir Ahmed Anjum, Chief (T&C) Planning

    Commission received vide letter No 4(67-24)/PC/T&C/2013 dated Dec

    16, 2013 were presented before the Board for information, discussion

    & decisions. After deliberations the Board agreed to the saidobservations for insertion in the confirmed minutes of meeting.

    4 2 I l d b h Chi f (T&C) h i l

  • 8/9/2019 231-Executive Board Meeting of NHA

    3/48

    NHA Executive Board’s Confirmed Minutes

    4.5. After detailed deliberations it was decided by the Boardthat all NHA Members should remain within NHA’s premises during

    Board meeting so that they should be readily available whenever

    required by the Board.

    4.6. Minutes were accepted for confirmation.

    Decision

    4.7. The Executive Board confirmed minutes of 230th meeting

    held on Sep 17, 2013 with following amendments:-

    a. In Agenda Item 16 “Withdrawal of Induction/

    Absorption of Syed Imran Qadir Gilani as Director(Amin, BS-19) in NHA” Para-18.3 may be rephrasedas follows:-

    For: The Chief (T&C) stated that, case forinduction of officer was brought before theBoard thrice. The reasons mentioned for

    review of earlier decision were required tobe scrutinized before submission of caseto the Board.

  • 8/9/2019 231-Executive Board Meeting of NHA

    4/48

    NHA Executive Board’s Confirmed Minutes

    b. In Agenda Item 17 “Creation of 3x Supernumerary(Temporary) Posts of GMs (Engr, BS-20)” Para-19.4

    may be reworded as follows:-

    For: The Board deliberated and recommended

    the proposal to NHC.

    Read: The Board deliberated and recommended

    the proposal to NHC (if it was in the

    competency of NHC).

    c. In Agenda Item 19 “Request for Job in NHA against

    “Deceased Quota”: Mr Muhammad Nawaz S/o Ali

    Nawaz, Ex-Driver of NHA”

    i. Para-21.2 may be redrafted follows:-

    For: ------ Chief (T&C) was of the view that the

    item may not be withdrawn, but should be

    discussed later on along with other similartypes of cases for decision.

    Read: Chief (T&C) was of the view that the

  • 8/9/2019 231-Executive Board Meeting of NHA

    5/48

    NHA Executive Board’s Confirmed Minutes

    5. Agenda Item 2

    Amendment in NHA (Meetings of Executive Board)

    Regulations, 2003

    Proposal

    5.1. NHA (Meetings of Executive Board) Regulations, 2003,approved by the Executive Board (10th meeting of Apr 24, 2003) prescribeprocedure for conducting the Board’s business. Clause-20 of theseregulations deals with circulation of minutes, as follows:-

    a. A copy of the minutes (proceedings) of every meeting, dulysigned by the Chairman of the meeting, shall be

    circulated by Secretary/Deputy Secretary as soon aspossible after the meeting.

    b. The minutes shall be circulated among all the Members.

    c. The minutes so circulated shall be again signed by theChairman at the next (succeeding) meeting after final

    adoption by the Board, with amendments or otherwise, asthe case may be.

    d The finally adopted minutes shall be circulated afresh

  • 8/9/2019 231-Executive Board Meeting of NHA

    6/48

    NHA Executive Board’s Confirmed Minutes

    5.4. The Chairman explained that under existing procedure

    decisions of the Executive Board do not become actionable until &

    unless they are confirmed by the Board in its succeeding meeting. The

    Board meetings are often delayed due to one or other unavoidable

    reasons. This situation holds important proposals under suspension

    and causes delays in their implementation that may range upto three

    months in extreme cases. Thus, essence of the Board decision is not

    timely realized.

    5.5. The Additional Secretary (Finance) opined that there is no

    hurdle in accepting the proposal. The Board Members also agreed to

    the suggestion. However, the Chief (T&C) remarked that proposals of 

    important nature that require immediate processing may be

    earmarked at the time of discussion so that the Board Members are

    fully cleared and satisfied about what is going to be implemented.

    5.6. The Board deliberated and cleared the proposal.

    Decision

  • 8/9/2019 231-Executive Board Meeting of NHA

    7/48

    NHA Executive Board’s Confirmed Minutes

    6. Agenda Item 3

    Revised PC-I for Construction of Sultan Bahoo Bridge

    Across River Chenab Linking Shorkot and Garh

    Maharaja

    Proposal

    6.1. The NHA Executive Board is requested to recommend the

    Revised PC-I for Construction of Sultan Bahoo Bridge across River

    Chenab Linking Shorkot and Garh Maharaja costing Rs 4,354.28

    million to CDWP / ECNEC for approval.

    Deliberation

    6.2. The Project Director presented the details.

    6.3. The VP-NESPAK observed that the original PC-I was notbased on hydraulic model study. He added that it has been noticed

    that PC-Is are often prepared without conducting proper hydraulic

    d l d th d t il d t di Thi ti t l lt i

  • 8/9/2019 231-Executive Board Meeting of NHA

    8/48

    NHA Executive Board’s Confirmed Minutes

    6.5. The Chief (T&C) observed that traffic volume on

    Hasanabdal - Havelian Expressway (E-35) is more than this project;

    why pavement thicknesses on this project is more than E-35? He

    added that design be reviewed and pavement thickness be checked as

    compare to E-35. He pointed that nomenclature of the project be

    checked and accordingly mentioned in the revised PC-I.

    6.6. The VP-NESPAK opined that the revised pavement

    thickness seem reasonable and acceptable.

    6.7. The Chairman ensured that the proposal would be

    referred to CDWP / ECNEC after requisite design review under

    intimation to the Board.

    6.8. The Board deliberated and cleared the proposal.

    Note: The GM (Planning) clarified that pavement thicknesses of Sultan Bahoo Bridge 

    have been checked, scrutinized and found appropriate.

    Decision

  • 8/9/2019 231-Executive Board Meeting of NHA

    9/48

    NHA Executive Board’s Confirmed Minutes

    Deliberation

    7.2. The Director (ADB) presented the case.

    7.3. The Additional Secretary (Finance) asked about reasons

    for increase in the cost of project. The Director (ADB) explained major

    reasons as under:-

    a. The Engineer’s Estimates amounting to Rs 874.70

    million for the projects were worked out on the basis

    of NHA- CSR (Sep-2006). The contracts were awarded

    in Oct-2009.

    b. Re-designing of the projects due the damages causedby floods of Jul-2010.

    c. The works executed under “day works” in the interest

    of projects for emergency restoration of traffic after

    flood damages.

    d. Revised costs inclusive of all contractual claims,

    price adjustments, updated cost of civil works of all

  • 8/9/2019 231-Executive Board Meeting of NHA

    10/48

    NHA Executive Board’s Confirmed Minutes

    b. NHA will also seek ADB’s concurrence for inclusion

    of minimum works required to safeguard the already

    executed and balance works costing Rs 636 million.

    c. NHA will vigorously pursue with ERRA and impress

    upon them to expedite submission of revised PC-I of 

    Rs 1,466 million pending with them for quite some

    time to the Planning Commission.

    7.6. The Senior Joint Secretary (MoC) suggested that

    implementation status on decisions of 216th meeting be seen and

    Board be informed accordingly.

    7.7. The Board was informed that ERRA was time & again

    pursued in this regard. Recently, NHA requested vide letter No 3(26)M

    (AP)/NHA/2013/444 dated Sep 6, 2013 to process the revised PC-I toPlanning Commission for soliciting approval since NHA was the

    executing agency only, whilst the project was implemented by ERRA

  • 8/9/2019 231-Executive Board Meeting of NHA

    11/48

    NHA Executive Board’s Confirmed Minutes

    c. Keeping in view and the earlier request made videour letter No ERRA/2-4/2012/SPC dated Aug 26,

    2013, it will be appropriate and prudent in the best

    interest of this National Highway Road that case for

    its PC-I (Revised) for complete scope of work, be

    taken up by NHA and processed through Planning

    Commission with intimation to ERRA.

    7.8. The Board deliberated and cleared the proposal.

    Decision

    7.9. The Executive Board recommended the revised PC-I for

    widening and improvement of Alpuri - Besham Road Project (N-90)costing Rs 3,090.087 million to CDWP / ECNEC.

    Action By : Member (Planning)

    8. Agenda Item 5

    Amended PC-I for Improvement & Widening of Jaglot-

    Skardu Road, S-I (163.821 Km)

    Proposal

  • 8/9/2019 231-Executive Board Meeting of NHA

    12/48

    NHA Executive Board’s Confirmed Minutes

    a. Whether it is necessary to assign the project toChinese firm or GoP can execute it; wherein it was

    apprised that EXIM Bank of China extends loan for

    only those projects which are to be undertaken by

    the Chinese firms. The loan would be negotiated by

    EAD. It was also discussed that the Planning

    Commission is the authority which can confirm the

    availability of funds with GoP.

    b. Is it feasible / possible to link this project with

    Economic Corridor Packages? It was apprised that

     Jaglot - Skardu Road Project does not fall on the

    alignment of Economic Corridor. This project and

    Economic Corridor are to be financed by the EXIMBank of China; it is therefore upto the Planning

    Commission and EAD to decide.

    8.5. The Board deliberated and desired that comparison of 

    costs as offered by Chinese firm and the Engineer’s Estimate worked

    out by NHA itself be presented in next meeting.

    Decision

  • 8/9/2019 231-Executive Board Meeting of NHA

    13/48

    NHA Executive Board’s Confirmed Minutes

     Total Cost: The total revised cost of the project including all

    components is Rs 19,951 million.

    i. ADB Share: Rs 4,470 million (incurred up to loan closing onAug 31, 2010)

    ii. GoP Share: Rs 5,997 million (including Rs 4,532 millionalready incurred & balance Rs 1,456 million to be

    incurred)

    iii. USAID Share: Rs 9,484,million (to be incurred)

    Deliberation

    9.2. The General Manager (Balochistan), Quetta made detailed

    presentation.

    9.3. The VP-NESPAK inquired about the additional works for

    revision of cost. The GM informed about details of additional works

  • 8/9/2019 231-Executive Board Meeting of NHA

    14/48

    NHA Executive Board’s Confirmed Minutes

    9.5. The Chief (NTRC) suggested that installation of pedestrian

    bridges need to be properly surveyed to identify appropriate places for

    the purpose. He offered services of NTRC for this survey and designing

    the bridges. The Chief (T&C) supported the above version and

    recommended assignment of said job to NTRC.

    9.6. The Chief (T&C) pointed out that the cost of revised PC-I

    is different from that presented in the Technical Working Party (TWP)

    meeting. NHA may check and correct accordingly. He also suggested

    that in future minutes of TWP meeting be made part of such working

    papers.

    9.7. The Board deliberated and cleared the proposal.

    Decision

    9.8. The Executive Board recommended the revised PC-I of  

    Kalat - Quetta -Chaman Road Project (N-25) costing Rs 19,951 million

    (ADB Share: Rs 4,470 million, GoP Share: Rs 5,997 million, USAID

    Share: 9,484 million) for approval by CDWP/ECNEC and execution of 

    remaining and additional works by FWO on single tender basis at

  • 8/9/2019 231-Executive Board Meeting of NHA

    15/48

    NHA Executive Board’s Confirmed Minutes

    10.3. The Chairman briefed the Board about background &

    importance of the route and discussions along with the Secretary

    Communications with the Asian Development Bank (ADB).

    10.4. The VP-NESPAK made a query whether PC-I for this road

    is prepared on 4 or 6-lane basis?

    10.5. The Chairman explained that NHA’s loan negotiations

    with ADB are underway and ADB has expressed its willingness to

    provide the funds only if the road is constructed as 4-lane. A Periodic

    Financing Request for US$ 315 million was forwarded to ADB through

    EAD. ADB intimated only US$ 200 million are available for the project

    (Package I & II) during 2013 and the balance amount for Package-III

    will be processed in 2014. However, there is a policy decision of the

    Prime Minister to develop this road with 6-lane facility. A summary in

    this regard has been moved to the Prime Minister’s Office for decision.

    10.6. The Chief (T&C) suggested that the agenda may be held in

    abeyance till decision of the summary from Prime Minister is received.

  • 8/9/2019 231-Executive Board Meeting of NHA

    16/48

    NHA Executive Board’s Confirmed Minutes

    11. Agenda Item 8

    Award of Works: Construction of Peshawar Northern

    Bypass

    Proposal

    11.1. The Executive Board is requested to accord approval for

    award of the works for Construction of Peshawar Northern Bypass,

    Package-II: Charsadda Road to Warsak Road-11 Km (Km 7+600 – Km

    19+500) to the lowest evaluated bidder i.e. M/s Riaz Malik

    Construction Company and M/s China Liaoning International

    Economic & Technical Cooperation Group Corp. Ltd. (Joint Venture),M/s RMC – CLIC JV at bid price of Rs 4,405,621,229, which is 1.08%

    above the Engineer’s Estimate (Rs 4,358,618,689.48) based on CSR-

    2011 + 15% premium.

    Deliberation

    11.2. The General Manager (P&CA) made detailed presentation.

    11 3 The Board deliberated and cleared the proposal

  • 8/9/2019 231-Executive Board Meeting of NHA

    17/48

    NHA Executive Board’s Confirmed Minutes

    12. Agenda Item 9Construction of Highway Research & Training Centre

    (HRTC): Request for Provision of Funds of Rs 340

    Million for Acquisition of Land Measuring 2176

    Kanals and 17 Marla

    Proposal

    12.1. The Executive Board of NHA is requested to approve an

    additional estimated amount of Rs 340 million from NHA Road

    Maintenance Account (RMA) for completion of land acquisition process

    for Highway Research & Training Centre (HRTC).

    Deliberation

    12.2. The Pavement Specialist NHA presented the case.

    12.3. The Additional Secretary (Finance) and the VP-NESPAK

    opined that establishment of Highway Research & Training Centre

    (HRTC) is an important move by NHA, however, there is a need to

    devise a result oriented program in the field of highway research &training. HRTC should conduct country wide research in road sector.

    12 4 Th IG (NH&MP) hi hli ht d th t th h i d

  • 8/9/2019 231-Executive Board Meeting of NHA

    18/48

    NHA Executive Board’s Confirmed Minutes

    12.7. The VP-NESPAK inquired whether NHA is in position to

    release the funds through Road Maintenance Account (RMA)? The

    Member (Finance) explained that utilization of RMA funds needs to be

    revisited in the light of present scenario where PSDP funds are

    released project-wise and no provision is made for unfunded &

    completed projects. Re-appropriation of funds from one project to

    another has to be approved by the P&D Division. He was of the view

    that very essential & obligatory expenditures like payments on

    account of court cases and long outstanding land compensation

    should also be made eligible from RMA funds.

    12.8. The Chairman updated the Board that he has received

    non bail-able warrants from the court in case of a land compensation

    pertaining to M-2 projects. Due to non availability of PSDP funds,

    compensation to some of the land owners could not be made. Under

    this situation he has no option but to make the payment from RMA.

    12.9. The Member (Finance) suggested that RMA should provide

    for some amount for such cases. The Additional Secretary (Finance)endorsed the proposal of Member (Finance) and suggested that at

    least a remarkable amount should be provided in the current years

  • 8/9/2019 231-Executive Board Meeting of NHA

    19/48

    NHA Executive Board’s Confirmed Minutes

    13. Agenda Item 10

    NHA’s Composite Schedule of Rates (CSR)-2013

    Proposal

    13.1. The Executive Board (229th meeting of Jul 9, 2013) considered

    the working paper on NHA’s Composite Schedule of Rates (CSR)-2013and decided as follows:-

    a. NHA CSR-2013 shall be re-presented incorporating

    GST and other recent price hikes in fuel etc. after

    three months.

    b. Meanwhile, 15% premium over NHA CSR-2011 shall

    be applicable for preparation of project estimates,

    PC-I and Bid evaluations till the approval of CSR-

    2013.

    13.2. Keeping in view the above decision, further increase in

    input rates of basic materials & current bidding trend, the Executive

    Board is requested to approve the following two recommendations:-

  • 8/9/2019 231-Executive Board Meeting of NHA

    20/48

    NHA Executive Board’s Confirmed Minutes

    13.4. The GM (Design) also presented the details of biddingtrends of the bidders during the year 2013 by providing comparison of 

    bid amount and engineer’s estimates based on CSR-2011+15% and

    CSR-2013. It was highlighted that bid amount of seven (7) projects

    tendered during 2013 was 12% above Engineer’s estimates of CSR-

    2011+ 15% and 9% below that of CSR-2013 as shown in Annex-E.

    13.5. The Chief (T&C) opined that prevailing CSR rates

    influence the bidding trends of the Contractors. Thus revision /

    increase of rates through implementation of CSR-2013 would create

    tendency among the bidders to quote bids with higher rates.

     Therefore, keeping in view the bidding trends of 2013, it seems

    reasonable that implementation of CSR-2013 may be withheld for

    more couple of months. The VP-NESPAK supported the version and

    sought recommendations of the GM (Design) in this regard. The GM

    (Design) viewed that since estimates of CSR-2011+15% are at par with

    the bid amounts quoted by the bidders during current year, therefore,

    CSR-2013 may be implemented after March-2014.

    13.6. The Board agreed and cleared the proposal forimplementation of CSR-2013 from April 1, 2014 and it may be called

    as CSR-2014.

  • 8/9/2019 231-Executive Board Meeting of NHA

    21/48

    NHA Executive Board’s Confirmed Minutes

    14. Agenda Item 11

    Addendum-14 for Consultancy Services by M/s SMEC

    & Associates for Kalat-Quetta- Chaman Project (N-25)

    Proposal

    14.1. The Executive Board is requested to approve Addendum

    No 14 of M/s SMEC & Associates for an extension in the period of 

    Consultancy Services on Kalat - Quetta - Chaman Road Project (N-25)

    by 5 months, upto Mar 31, 2014 and additional cost of Rs

    9,720,609/= (Rupees nine million, seven hundred twenty thousand, six hundred

    and nine) only, over and above the cost of Consultancy Servicesapproved upto Oct 31, 2013 (Addendum No 13).

    Deliberation

    14.2. The General Manager (Balochistan) presented the case.

    14.3. The Board deliberated and cleared the proposal.

    Decision

  • 8/9/2019 231-Executive Board Meeting of NHA

    22/48

    NHA Executive Board’s Confirmed Minutes

    15. Agenda Item 12

    Variation Order 16-12 of FWO for Repair of Flood

    Damaged Works at Balakot S-Bound: Basian-Balakot-

    Naran Section, N-15

    Proposal

    15.1. The Executive Board is requested to accord approval of 

    the Variation Order No 16-12 of FWO for Repair of Flood Damaged

    Works at Balakot S-Bound: Basian-Balakot-Naran Section (N-15)

    costing Rs 317,811,627/= bringing the revised contract cost to Rs

    3,519.89 million.

    Deliberation

    15.2. The General Manager (NHIP) presented the case.

    15.3. The Chief (T&C) desired that cost of VO should not be

    over & above the cost of PC-I.

    15 4 The Board agreed with the view point of Chief (T&C) and

  • 8/9/2019 231-Executive Board Meeting of NHA

    23/48

    NHA Executive Board’s Confirmed Minutes

    16. Agenda Item 13

    Addendum-2 of M/s Associated Consultancy Center

    (ACC) for Construction Supervision: Rehabilitation of 

    Kamber - Shahdadkot Road Project

    Proposal

    16.1. The NHA Executive Board is requested to accord approval

    of Addendum-2 costing Rs 18,870,314/=, entailing extension in

    services of M/s Associated Consultancy Center (ACC) from Jun 20,

    2011 to Oct 16, 2013 for construction supervision and accountfinalization for Rehab of Kamber - Shahdadkot Road Project.

    Deliberation

    16.2. The Director (Construction-South) presented the case.

    16.3. The Board deliberated and cleared the proposal.

    D i i

  • 8/9/2019 231-Executive Board Meeting of NHA

    24/48

    NHA Executive Board’s Confirmed Minutes

    17. Agenda Item 14

    Revision of “Factor-C” for Price Adjustment on

    Construction of Shah Jeewna Bridge over River

    Chenab, District Jhang

    Proposal

    17.1. The Executive Board is requested to approve the revision

    of “Factor-C”, in context of Appendix “C” to the Bid for the contract of 

    Construction of Shah Jeewna Bridge across River Chenab at Chund

    District Jhang having cost effect of Rs 17,663,851/- against original

    “Factor-C”, as a Contractor’s claim.

    Deliberation

    17.2. The Director (Construction-North) presented the case.

    17.3. The VP-NESPAK opined that NHA should be careful while

    processing proposals soliciting price adjustments through revision of Factor-C as variations in rates of input materials are also covered

    through payment of escalation. Thus, revision of Factor-C may involve

  • 8/9/2019 231-Executive Board Meeting of NHA

    25/48

    NHA Executive Board’s Confirmed Minutes

    18. Agenda Item 15Revised Addendum-15 of M/s EA Consulting (Pvt) Ltd

    for Construction Supervision of Lyari Expressway

    Project

    Proposal

    18.1. The Executive Board is requested to accord approval of Addendum No 15 (Revised) to M/s EA Consulting (Pvt) Ltd for

    construction supervision of Lyari Expressway Project costing Rs

    49,945,839/=, increasing the revised contract cost to Rs

    199,845,629/=, which is 214% above the original contract and 33%

    above the approved revised cost of Rs 149,899,790/= as per

    Addendum No 15 consisting extension of time from Jan 1, 2010 to

    Dec 31, 2013 and the related cost along with the cost of design for re-

    aligned elevated stretches of Northbound Carriageway.

    Deliberation

    18.2. The Director (Construction-South) presented the case.

    18.3. The Chief (T&C) raised the following observations:-

    a Does contract allow re rating and who is competent

  • 8/9/2019 231-Executive Board Meeting of NHA

    26/48

    NHA Executive Board’s Confirmed Minutes

    19.Agenda Item 16Construction of Habibabad Flyover on NationalHighway (N-5) on Built-Operate-Transfer Basis

    Proposal

    19.1. Following decisions are solicited from NHA Executive

    Board:-

    a. The enclosed “Draft Concession Agreement” may be

    approved for signing with M/s Habibabad Operation

    and Management Engineering Company (Pvt) Ltd (the

    Concessionaire) for “Construction of Habibabad

    Flyover, on National Highway (N-5) on Build-Operate-

     Transfer basis.”

    b. Approval may be accorded to hand over Pattoki Toll

    Plaza to Concessionaire, within four (04) weeks of 

    signing of Concession Agreement, under the same

    terms and conditions as it is being operated by the

    existing toll operator, to facilitate the Concessionaire

    to undertake installation of electronic tolling system

    and completion of other required facilities during

    t ti i d Thi i l i it t

  • 8/9/2019 231-Executive Board Meeting of NHA

    27/48

    NHA Executive Board’s Confirmed Minutes

    19.3. The VP-NESPAK opined that the concession should have

    been considered for twenty (20) years with 6-lane flyover facility

    instead of 4-lane. The Chairman explained about the utilization of 

    N-5, which is mostly connecting and passing through cities, hence 4-

    lane flyover will be enough. As far as period of concession is

    concerned, the cost has been worked out on 10 years basis, the Board

    may consider the case accordingly.

    19.4. The Additional Secretary (Finance) asked about the

    criteria of bids evaluation and benchmark for sharing financing

    Contractor and NHA. The Board was informed that the sharing has

    been worked out on the basis of commercial feasibility study

    conducted by IPDF.

    19.5. The VP-NESPAK inquired whether cost analysis has been

    done through comparison of estimates on public & private basis to see

    the benefit of project on BOT basis or if it is done through public

    sector by NHA itself. The Member (Finance) explained that collection

    by NHA is lesser than the amount proposed by FWO / JV. The VP-

    NESPAK desired that public sector comparative must be the part of 

    BOT proposals in future.

    19 6 The Member (Finance) pointed out that M/s Muhammad

  • 8/9/2019 231-Executive Board Meeting of NHA

    28/48

    NHA Executive Board’s Confirmed Minutes

    19.8. The Chairman inquired that whether the case be

    forwarded to CDWP? The Chief (T&C) clarified that NHA Executive

    Board is the competent forum for approval of PPP projects.

    19.9. The Board Members appreciated the efforts made by the

    NHA’s PPP team in materializing the PPP projects and desired that

    more projects on PPP be initiated in order to reduced the load on GoP

    financing.

    19.10. The Board deliberated and cleared the proposal.

    Decision

    19.11. The Executive Board approved the “Draft ConcessionAgreement” for signing with M/s Habibabad Operation and

    Management Engineering Company (Pvt) Ltd, joint venture of M/s

    FWO & MAB (Muhammad Ayub Khan & Brothers) (the Concessionaire) for

    “Construction of Habibabad Flyover, on National Highway (N-5) on

    Build-Operate-Transfer basis”.

    19.12. The Board also accorded approval to hand over Pattoki

     Toll Plaza to Concessionaire, within forty five (45) days after

    completion of proceedings in respect of “Financial Close ” under the

  • 8/9/2019 231-Executive Board Meeting of NHA

    29/48

    NHA Executive Board’s Confirmed Minutes

    20. Agenda Item 17

    Payment of Arrears of Pay & Allowances wef Sep 12,

    2005 Due to Upgradation of Posts of Audit and

    Accounts Cadre

    20.1. The subject agenda item could not be discussed due topaucity of time and was deferred.

    Action By : Member (Finance)

    21. Agenda Item 18

    Revised Budget Estimates 2012-13 & BudgetEstimates 2013-14

    Proposal

    21.1. The NHA Executive Board is requested to consider &

    recommend to NHC the NHA’s Revised Estimates 2012-13 of Rs70,124.991 million & Budget Estimates 2013-14 of Rs 89,248.776

    million for approval.

  • 8/9/2019 231-Executive Board Meeting of NHA

    30/48

    NHA Executive Board’s Confirmed Minutes

    Decision

    21.6. The Executive Board considered & cleared the Revised

    Estimates 2012-13 (Annex-H) & Budget Estimates 2013-14 (Annex-I)

    for approval of NHC.

    Action By : Member (Finance)

    22. Agenda Item 19

    Annual Maintenance Plan for FY 2013-14

    Proposal

    22.1. The Executive Board is requested to approve the Annual

    Maintenance Plan amounting to Rs 17,930.41 million for FY 2013-14.

    Deliberation

    22.2. The Director (RAMS) presented the case.

  • 8/9/2019 231-Executive Board Meeting of NHA

    31/48

    NHA Executive Board’s Confirmed Minutes

    22.4. The Additional Secretary (Finance) asked about the value

    & strength of the above mechanism followed by NHA. It was informed

    that the said mechanism is adopted in more than 35 countries in the

    world. The Chairman further explained that NHA’s trying its best to

    maintain the roads trafficable through periodic maintenance and

    rehabilitation as the case may be. Therefore, AMP is prepared through

    the said mechanism as experienced since last many years.

    22.5. The VP-NESPAK suggested that besides timely

    maintenance of highways be ensured by NHA, status of contracts

    awarded under the AMP with progress be submitted to the Board on

    quarterly basis for information and monitoring the expenditures of 

    AMP. He further desired that technical audit of all maintenance works

    be also carried out and such reports be placed before the Board. Healso desired that status of works & expenditures to be carried out

    under “Special Maintenance Head” must be placed before the Board

    for information.

    22.5.(a) The Chief T&C stated that the executive summary of the

    AMP may also include status of complete picture of proposed budget

    of previous financial year including all sub-heads of income & actual

    expenditure incurred. The Board recommended that the same would

    b i d b f b i i NHC f l Th

  • 8/9/2019 231-Executive Board Meeting of NHA

    32/48

    NHA Executive Board’s Confirmed Minutes

    22.8. The Chief (T&C) inquired about the Pasni - Gwadar Road

    overlay as its revised PC-I is yet under process for approval in P&D

    Division. As such, it appears that the project is not yet completed to

    consider for maintenance plan. The Member (Ops) explained that this

    road has been divided in to various sections for construction works

    and this section (439-508 km) has been completed and traffic is

    running on this section of road since 2003-04, hence road needs

    maintenance. The Chief (T&C) viewed that NHA should check the

    design period of road so that no section is picked up and included in

    AMP before completion of design period.

    22.9. The Additional Secretary (Finance) asked about funding inAMP whether on self finance basis out of NHA sources or otherwise. It

    was explained that AMP budget comprises GoP grant share formaintenance and revenue available with NHA.

    22.10. The Chief (T&C) pointed out that difference of estimatesfor 2013-14 in AMP (17 billion) and budget proposal (22 billion) beseen by NHA and figures be reconciled and corrected. The Member(Finance) explained that AMP estimates of 17 billion is a net costexcluding 30% cut off by GoP and O&M costs.

    22.11. The Board deliberated and cleared the proposal.

  • 8/9/2019 231-Executive Board Meeting of NHA

    33/48

    NHA Executive Board’s Confirmed Minutes

    EXTRACTS

    MINUTES OF THE231ST EXECUTIVE BOARD MEETINGDECEMBER 17, 2013 AT ISLAMABAD

  • 8/9/2019 231-Executive Board Meeting of NHA

    34/48

    NHA Executive Board’s Confirmed Minutes

    NATIONAL HIGHWAY AUTHORITY

    CONFIRMED MINUTES

    231st Executive Board MeetingIslamabad, December 17, 2013

    INDEX

    PARA AGENDA ITEM PAGE ACTION BY

    1. Introduction 1 --- 

    2. Opening Remarks (Chairman NHA) 1 --- 

    3. Formal Proceedings (Agenda Items) 1 --- 

    4. Agenda Item 1Confirmation of Minutes - 230th Meeting of theExecutive Board Held on Sep 17, 2013

    2 Secy NHA 

    5. Agenda Item 2Amendment in NHA (Meetings of Executive Board)Regulations, 2003

    5 Secy NHA 

    6 A d It 3

  • 8/9/2019 231-Executive Board Meeting of NHA

    35/48

    NHA Executive Board’s Confirmed Minutes

    PARA AGENDA ITEM PAGE ACTION BY

    12. Agenda Item 9Construction of Highway Research & Training Centre(HRTC): Request for Provision of Funds of Rs 340Million for Acquisition of Land Measuring 2176 Kanalsand 17 Marla

    17 Mem (O) & Mem (F) 

    13. Agenda Item 10NHA’s Composite Schedule of Rates (CSR)-2013 19 Mem (P) 

    14. Agenda Item 11Addendum-14 for Consultancy Services by M/s SMEC& Associates for Kalat-Quetta- Chaman Project (N-25)

    21Mem (C) 

    15. Agenda Item 12Variation Order 16-12 of FWO for Repair of FloodDamaged Works at Balakot S-Bound: Basian-Balakot-Naran Section, N-15

    22 Mem (C) 

    16. Agenda Item 13Addendum-2 of M/s Associated Consultancy Center(ACC) for Construction Supervision: Rehabilitation of Kamber - Shahdadkot Road Project

    23 Mem (C) 

    17. Agenda Item 14Revision of “Factor-C” for Price Adjustment on

    Construction of Shah Jeewna Bridge over River Chenab,District Jhang

    24 Mem (C) 

    18. Agenda Item 15

  • 8/9/2019 231-Executive Board Meeting of NHA

    36/48

    NHA Executive Board’s Confirmed Minutes

    Annex-A

    NATIONAL HIGHWAY AUTHORITY

    LIST OF PARTICIPANTS

    231ST EXECUTIVE BOARD MEETINGDECEMBER 17, 2013 AT ISLAMABAD

    IN CHAIR

    1. Mr Maroof Afzal Chairman

    MEMBERS

    2. Dr Shujat Ali AS (Budget)Finance Division

    3. Mr Zulfiqar Ahmad Cheema Inspector General, NationalHighways & Motorway Police

    4. Mr Aamir Hasan Senior Joint Secretary  

    Ministry of Communications

    5. Mr Qazi Iftikhar Ahmed Vice President NESPAK

  • 8/9/2019 231-Executive Board Meeting of NHA

    37/48

    NHA Executive Board’s Confirmed Minutes

    -2-

    NHA OFFICERS ITEM

    11. Mr Yousaf Ali Member (Con/AP) 3, 8 & 11 to 15

    12. Mr Mian Muhammad Asghar GM (ADB) 4

    13. Mr Pervez Iqbal Sulehri GM (P&CA) 5, 8

    14. Mr Noor-ul-Hassan GM (Bal), Quetta 6 & 11

    15. Mr Arbab Ali GM (Planning) 7

    16. Mr Fazal Nawab Khattak GM (M-1)/ HRTC 9

    17. Mr Asim Amin GM (Design) 10

    18. Mr Mukhtar Ahmad Durrani GM (NHIP) 12

  • 8/9/2019 231-Executive Board Meeting of NHA

    38/48

    NHA Executive Board’s Confirmed Minutes

    Annex-G

    OBSERVATION OF ADDITIONAL SECRETARY FINANCEON BUDGET ESTIMATES

    Observation #01:- Receivable from FWO amounting to Rs. 7,985.5million has been shown in the budget estimates 2012-13. The balanceof said amount which is still to be received should have to be reflectedin the Budget Estimates 2013-14.

    Reply:- Rs. 663.6 million was received in the financial year 2012-13and remaining amount of Rs.5,091.9 million is still receivable fromFWO after the adjustment of operational charges of Rs. 2,229.9million. The outstanding amount is not likely to be received fromPSDP account against the adjustments of claims of FWO on

    development projects therefore to avoid over commitment onmaintenance activities it was not included in the non-developmentportion of Budget Estimates 2013-14. However, in light of discussionthe receivables of Rs. 5,091.9 million from FWO have been included inBudget Estimates 2013-14 as “Reserve against receivables fromFWO (toll)”.

    Observation #02:-  The provision for the administrative expendituresin 2012-13 was 775 million whereas in the financial year 201314 ithas been increased to Rs 1 300 million which needs clarification

  • 8/9/2019 231-Executive Board Meeting of NHA

    39/48

    NHA Executive Board’s Confirmed Minutes

    Observation #04:- Why reserve for the pension funds amounting toRs. 242 million has been included in the estimates 2013-14?

    Reply:- NHA service is pensionable as per NHA Act and is governedby its regulations given in the NHA manual. As per ActuarialValuation the pension fund is in deficit of Rs. 1,830.3 million.Considering the fund position Rs. 242.1 million has been kept in thebudget to cover the deficit gap in 7-8 years time.

    Observation #05:- Explain 1% establishment expenditures.

    Reply:-  The permanent strength of NHA was increased from 252 to1642 in 1994 whereas the GoP was providing funds for 252 employee.In order to resolve the disbursement issue of the pay and allowances

    of these employees a special provision equal to 1% of PSDP allocationhas been created with the approval of NHA Executive Board to payoutthese expenditures.

    However as advised it has been renamed and showed as NHA’sestablishment expenditures in the Budget Estimates 2013-14.

    Observation #06:- Budget should be compiled in book form.

    Reply:- Budget Book 2013-14 has been compiled as advised

  • 8/9/2019 231-Executive Board Meeting of NHA

    40/48

    231st Meeting, December 17, 2013, Islamabad

    NHA Executive Board’s Confirmed Minutes

    Annex-D

    PRICE VARIATION OF VARIOUS INPUT ITEMS BASE RATES

    COLLECTED IN DECEMBER 2010 ~ APRIL 2013 ~ NOVEMBER 2013

    Item Unit

    CSR-2011 CSR-2013 %age CSR-2013 %age

    (Dec-2010) (April-2013) Increase (Nov-2013) Increase

    (Actual) (Actual)From Dec-2010

    to Apr-2013(Actual)

    From Apr-2013

    to Nov-2013

    Diesel Rs./Litre 78.33 108.59 38.63% 116.75 7.51%

    Bitumen Rs./Ton 68,550.00 83,112.00 21.24% 80,904.00 -2.66%

    Labour (Rwp) Rs./Day 325 400 23.08% 500 25.00%

    Cement Rs./Bag 330 420 27.27% 435 3.57%

    Reinforcement (G-60) Rs./Ton 69,500.00 83,000.00 19.42% 84,000.00 1.20%

    Crush (Rwp) Rs./CM 900.66 1,119.62 24.31% 1,165.00 4.05%

    Average Increase in Basic Items Input Rates 25.66% 6.45%

    General Sales Tax (GST) % 16% 16% 0.00% 17% 1.00%

    Rs. Vs Dollar I USD = PKR 86.05 98.3 14.24% 108.2 10.07%

  • 8/9/2019 231-Executive Board Meeting of NHA

    41/48

    231st Meeting, December 17, 2013, Islamabad

    NHA Executive Board’s Confirmed Minutes

    Annex-E

    BIDDING TREND OF THE TENDERS DURING 2013

    Engineer's Estimate(Million Rs.)

    Bid Amount(Million Rs.)

    Variation in % Between

    DescriptionBids Opening

    Date

    CSR -2011 CSR - 2013CSR-2011

    & CSR-

    2013

    BidAmount &

    CSR-2011

    BidAmount &

    CSR-2013

    1. ADB/FERP/ICB: Flood EmergencyReconstruction Project : ICB-N-03Rehab of Kohala-Muzaffarabad Road(S-2) Package-I: Km 00 To Km 20

    24/Dec/12 1,414.17 1,749.60 1,716.00 23.72% 21.34% -1.92%

    2. Package 1-ICB–S04(a) : Rehab/Reconstruction of Hala-Moro Section,N–5 (South Bound)

    30/Apr/13 1,957.72 1,776.66 2,146.18 20.80% 10.19% -8.78%

    3. Package 2-ICB–S04(b) : Rehab /Reconstruction of Hala-Moro Section,

    N–5 (South Bound)

    30/Apr/13 1,875.20 1,747.68 2,105.95 20.50% 7.30% -10.96%

    4. Package3 ICB–S04(C) : Rehab/Reconstruction of Hala-Moro SectionN–5 (South Bound)

    30/Apr/13 1,979.42 1,756.53 2,114.76 20.39% 12.69% -6.40%

    5. Flood Emergency ReconstructionProject (FERP): ADB/FERP/ICB-S-01a:Ranipur - Rohri Road (N-5) (NorthBound) Package-I: Km 412 to Km 440(Length: 28.18 Km)

    25/Apr/13 1,386.33 1,349.38 1,643.95 21.83% 2.74% -15.67%

    6. ADB/FERP/ICB-S-01b: Ranipur-RohriRoad (N-5) (North Bound) Package-II:

    Km 440 to Km 475

    25/Apr/13 1,296.19 1,259.39 1,541.10 22.37% 2.92% -15.89%

    7. Construction of Peshawar NorthernBypass, Package-II : Charsadda Roadto Warsak Road (Km 7+600 to19+500)

    5/Nov/13 4,405.62 3,790.10 4,680.78 23.50% 16.24% -5.88%

    TOTAL 13,093.92 15,963.36 14,616.49 21.91% 11.63% -8.44%

  • 8/9/2019 231-Executive Board Meeting of NHA

    42/48

    Rs. in million)

    REVISED ESTIMATES 2012-13

    Receipts  Budget Estimates Revised Estimates

    2012-13 2012-13

    i Development 50,727.221 51,661.089

    ii Non-Development 27,935.387 18,463.902

    Total:-   78,662.608 70,124.991

    Expenditure  Budget Estimates Revised Estimates

    2012-13 2012-13

    i Development 50,727.221 51,661.089

    ii Non-Development 27,935.387 18,463.902

    Total:-   78,662.608 70,124.991

  • 8/9/2019 231-Executive Board Meeting of NHA

    43/48

    (Rs. in million)

    REVISED DEVELOPMENT BUDGET 2012-13

    Receipts Budget Estimates Revised Estimates2012-13 2012-13

    i. Local Currency   24,602.32122,137.858

    ii. Foreign Aid   26,124.90028,339.480

    iii. Other Receipts   - 1,183.751

    Total:-   50,727.221 51,661.089

    ExpenditureBudget Estimates Revised Estimates

    2012-13 2012-13

    i Local Currency   22,764.461   22,013.127ii Foreign Aid   26,124.900 28,339.480

    iii Refund of Inter-office Borrowings of Previous PSDP Exp   1,330.590 786.210

    iv. 1% PSDP Share against Establishment Charges507.270

      522.272

    Total:-   50,727.221 51,661.089

  • 8/9/2019 231-Executive Board Meeting of NHA

    44/48

    REVISED ESTIMATES NON-DEVELOPMENT 2012-13

    (Rs. in million)

    Receipts  Budget Estimates Revised Estimates

    2012-13 2012-13i.   Grants

    a. Maintenance Grant   1,827.000 1,498.140

    b. Thakot Khunjrab   232.000 129.920

    c. KKH   69.000 38.640

    d. Establishment Grant   101.687 85.833

    ii. NHA own receipts (RMA and Other receipt)   16,389.573 15304.552

    i ii. Receivable from FWO for 2011-12   7985.537 663.607

    Iv. Refund of Internal Borrowings   1330.590 743.210

    Total:-   27,935.387 18,463.902

    Expenditure  Budget Estimates

      Revised

    Estimates

    2012-13 2012-13i.   Maintenance

    a. National Highways and Motorways   16,538.580 10,178.741

    b. Thakot Khunjrab   232.000 129.920

    c. KKH Skardu   69.000 38.640d. Establishment Grant   101.687 85.833

    ii. RMA Establishment expenses   775.000 615.928

    iii. Deficit in 1% expenses met from own resources   424.721 773.309

    iv. Operational Charges   1,405.159 1,718.929

    v. Police Fine Share   723.202 629.449

    vi. Operational Charges against receivable from FWO   2,229.941 2,229.941

    vii. Supplementary/Special Grant   242.178 242.178

    viii. Reserve for Contingencies   5,092.232 1,750.201

    Total:-   27,935.387 18,463.902

  • 8/9/2019 231-Executive Board Meeting of NHA

    45/48

    (Rs. in million)

    BUDGET ESTIMATES 2013-14

    Receipts   Budget Estimates2013-14

    i Development 63,038.619

    Total Development:- 63,038.619

    ii Non- Development:- 22,118.168

    a) RMA 21,265.822

    b) Others 852.346Total Non-Develo ment:-   22 118.168

    Total:-   85,156.787

    Expenditure  Budget Estimates

    2013-14

    i Development 63,038.619Total Development:- 63,038.619

    ii Non- Development 22,118.168

    a) RMA 21,265.822

    b) Others 852.346

    Total Non-Development:-   22,118.168

    Total:-   85,156.787

  • 8/9/2019 231-Executive Board Meeting of NHA

    46/48

    (Rs in million)

    BUDGET ESTIMATES DEVELOPMENT 2013-14

    Receipts  Budget Estimates

    2013-14

    i Local Currency 32,122.258

    ii Foreign Aid 30,916.361

      , .

    Expenditure  Budget Estimates

    2013-14

    i Local Currency 30,161.282ii Foreign Aid 30,916.361

    iii

    Refund of Inter-office Borrowings of Previous PSDP

    Exp. 1,330.590

    iv. 1% PSDP Share against Establishment Charges 630.386

    Total (B)   63,038.619

  • 8/9/2019 231-Executive Board Meeting of NHA

    47/48

    BUDGET ESTIMATES NON-DEVELOPMENT 2013-14

    (Rs. in million)

    Receipts

      Budget Estimates

    2013-14

    i Government Grants

    a. Maintenance Grant 1,918.362

    b. Thakot Khunjrab 232.000

    c. KKH 69.000

    ii NHA own receipts (RMA and Other receipt) 18,046.460

    iii Internal Borrowings 1,000.000

    Road Maintenance Account Receipts:-   21,265.822

    Iv Establishment Grant 121.756V Misc. Receipt 400.000

     Vi Refund of Internal Borrowings 330.590

    Other Receipts   852.346Total:-   22,118.168

    Expenditure  Budget Estimates

    2013-14

    i Maintenance of National Highways and Motorways 17,567.008

    Ii RMA Establishment expenses 1,338.810Iii Operational Charges 1,688.799

    iv Police Fine Share 671.205

    Road Maintenance Account Expenditures:- 21,265.822v Establishment Expenditure (252 core employees) 121.756

    vi Employee Pension fund Contribution 242.178

    vii Deficit in 1% expenses met from own resources 438.278

    Viii Reserve for contingencies 50.134

    Other Expenditures:-   852.346

    Total:-   22,118.168

  • 8/9/2019 231-Executive Board Meeting of NHA

    48/48

    BUDGET AT GLANCE

    (Rs. in million)

    ReceiptsBudget Estimates Revised Estimates Budget Estimates

    2012-13 2012-13 2013-14

    i Development 50,727.221 51,661.089 63,038.619

    ii Non- Development 27,935.387 18,463.902 22,118.168

    Total (A)   78,662.608 70,124.991 85,156.787

    Expenditure  Budget Estimates Revised Estimates Budget Estimates

    2012-13 2012-13 2013-14

    iDevelopment 50,727.221 51,661.089 63,038.619

    ii Non- Development 27,935.387 18,463.902 22,118.168

    Total (B)   78,662.608 70,124.991 85,156.787