2017-07-24 futurist gdr issue 2 - borough of scarborough · willmott dixon construction ltd...
TRANSCRIPT
Willmott Dixon Construction Ltd
Futurist Site
Geotechnical Design Report
REP/GDR/002
Issue | 25 July 2017
This report takes into account the particular
instructions and requirements of our client.
It is not intended for and should not be relied
upon by any third party and no responsibility
is undertaken to any third party.
Job number 251657-00
Ove Arup & Partners Ltd
9th Floor 3 St Paul's Place
Norfolk Street
Sheffield S1 2JE
United Kingdom
www.arup.com
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Document Verification
Job title Futurist Site Job number
251657-00
Document title Geotechnical Design Report File reference
0-03-08
Document ref REP/GDR/002
Revision Date Filename 2017-06-29 Futurist GDR_ISSUE.docx
Issue 29 Jun
2017
Description Issued for planning
Prepared by Checked by Approved by
Name Paddy Samengo-
Turner Justin Howell Matt Lovell
Signature Paddy Samengo-
Turner Justin Howell Matt Lovell
Issue 2 25 July
2017
Filename 2017-07-25 Futurist GDR_ISSUE 2.docx Description Updated with comments
Prepared by Checked by Approved by
Name James Wardman Justin Howell Matt Lovell
Signature James Wardman Justin Howell Matt Lovell
Filename Description
Prepared by Checked by Approved by
Name
Signature
Filename
Description
Prepared by Checked by Approved by
Name
Signature
Press Control+Shift+D to insert or Issue Document Verification with Document �
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Contents Page
1 Introduction 1
1.1 General 1
1.1 Geotechnical category 2
1.2 Scope of report 2
1.2 Assumptions 2
1.3 Previous reports 2
1.4 Use of this report and limitations 2
2 The site 4
2.1 Site location 4
2.2 Site description 4
2.3 Site history 5
2.4 Unexploded Ordnance 6
2.5 Ground level information 6
2.6 Proposed development 6
3 Ground model 8
3.1 Ground investigations 8
3.2 Ground contamination risk assessment 8
3.3 Stratigraphy 8
3.4 Derivation of geotechnical parameters 11
3.5 Key parameter data 11
3.6 Parameters for slope stability assessment 12
3.7 Parameters for new retaining wall 12
3.8 Piezometric conditions 13
4 Global stability 14
4.1 Back-analysis 14
4.2 Existing slope stability 14
4.3 Stability of proposed slopes 15
4.4 Summary of stability analyses 19
5 Earthworks 21
5.1 Site-won fill material 21
5.2 Re-use of site-won fill material 21
6 Demolition of the buildings 23
7 Existing retaining structures 24
7.1 Main section to the Futurist 24
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
7.2 Section adjacent to King’s Steps 24
7.3 Main section to the Mermaid 24
7.4 Mermaid wall supporting Bland’s Cliff 24
7.5 Terrace walls 25
7.6 Sub-station 25
8 New retaining structures 26
8.1 Design standards & sources of reference 26
8.2 Walls for development platform 27
8.3 King’s Steps 28
8.4 Other Walls to Facilitate the Slope Re-grading 28
9 Drainage 29
9.1 Existing Drainage Infrastructure 29
9.2 Proposed Drainage Strategy 33
9.3 Conclusions 36
9.4 Next Steps 36
References
Figures
Figure 1 Site location
Figure 2 Evidence of Possible Retaining Wall Drainage
Figure 3 Government Guidance on Climate Change Allowances (gov.uk)
Drawings
Drawing FUT-ARUP-ZZ-XX-DR-STR-4010 Sections & Elevations Sheet 4Drawing FUT-ARUP-ZZ-XX-DR-CD-0001 Existing Drainage Network
Drawing FUT-ARUP-ZZ-XX-DR-CD-0002 Existing Catchment Areas
Drawing FUT-ARUP-ZZ-XX-DR-CD-0003 Proposed Drainage
Drawing FUT-ARUP-ZZ-XX-DR-CD-0004 Proposed Catchment Areas
Appendices
Appendix A
Slope stability back-analyses
Appendix B
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Global stability calculation output
Appendix C
Yorkshire Water plan
Appendix D
Utility survey
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 1
1 Introduction
1.1 General
Ove Arup and Partners Ltd (Arup) has been commissioned by Willmott Dixon
Construction Ltd (WDCL) to provide design services relating to enabling works
for the proposed redevelopment at the site of the former Futurist theatre.
The enabling works will involve:
• Demolition of the former Futurist theatre and Mermaid buildings, but leaving
existing retaining structures in place.
• Removal of the surface car park at the top of the slope.
• Re-grading of the slope to ensure that global stability is not adversely affected.
• Backfilling in front of the existing retaining structures at the toe of the slope.
• Construction of a new retaining structure around a new development plot
adjacent to Foreshore Road.
• Preparation of a temporary surface on the new development plot.
• Surface water and land drainage to suit the temporary condition and likely
future development.
• Placing erosion control layer and seeding on the slope.
Future development of the site is likely to comprise a leisure-related building on
the new development plot, with ancillary structures constructed on the slope
above.
This Geotechnical Design Report relates to the following:
• Existing global slope stability.
• Earthworks, including re-use of site-won soils as engineered fill.
• Future global slope stability.
• Future local slope stability.
• Future stability of existing retaining walls.
• Design of new retaining structure around new development plot.
• Design of new drainage to the site.
The future development is not considered in this report, in particular no
assessment is made of building foundations and the impact of new structures on
global and local slope stability.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 2
1.1 Geotechnical category
The enabling works scheme has been identified to be Geotechnical Category 3
according to BS EN 1997-1:2004+A1:2013, in that it relates to a steep slope
where instability could directly affect existing residential and commercial
properties and public highways.
1.2 Scope of report
This Geotechnical Design Report (GDR) is prepared in accordance with BS EN
1997-1:2004+A1:2013. It contains the following
• A summary of the findings of the Ground Investigation Report
• A presentation of the ground and groundwater model used in design
• A description of the proposed works
• Detailed assessment of slope stability
• Assessment of the existing and proposed retaining structures
• Assessment of the potential for re-use of soil arisings
• Details of the proposed surface water and land drainage
This Geotechnical Design Report should be read in conjunction with the Ground
Investigation Report (GIR) 251657/REP/GIR/001.
1.2 Assumptions
To prevent uncertainty, the geotechnical investigations and design contained in
this report are based upon the assumptions listed in BS EN 1997-1:2004,
paragraph 1.3 i.e. that all investigation, design and construction works are carried
out by appropriately qualified and experienced personnel.
1.3 Previous reports
In addition to the factual ground investigation reports, this report uses information
from the following references:
Geo-Environmental Interpretative Report, Mermaid/Futurist Theatres, White
Young Green, August 2008 (for Yorkshire Forward).
Phase II Geotechnical and Environmental Assessment, Proposed Town Hall
Development Site, URS, October 2014 (for Scarborough Borough Council).
Site Investigation & Slope Stability Analysis Report, Futurist Theatre, Solmek
Ltd, March 2015 (for Billinghurst George & Partners).
1.4 Use of this report and limitations
This report has been prepared by Arup on behalf of WDCL in connection with the
Futurist site project. It takes into account our Client’s particular instructions and
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 3
requirements and is not intended for, and should not be relied upon by any third
party and no responsibility is undertaken to any third party in relation to it.
All reasonable skill, care and diligence have been exercised within the timescale
available and in accordance with the technical requirements of the brief.
Notwithstanding the efforts made by the professional team in preparing the report
it is possible that other ground conditions or ground contamination may exist, as
yet undetected, and consequently reliance on this report must be limited
accordingly.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 4
2 The site
2.1 Site location
The site is located on the seafront close to Scarborough town centre, at approximate
National Grid Reference 504470, 488597. The site location is shown in © Crown copyright and
database rights 2017 Ordnance Survey
Figure 1.
© Crown copyright and database rights 2017 Ordnance Survey
Figure 1 Site location
2.2 Site description
The site is bounded by Foreshore Road to the east, Bland’s Cliff and commercial
and residential properties to the north, King Street to the west and King’s Steps
and St Nicholas Gardens to the south.
The site can be divided into two distinct areas:
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 5
• The disused Futurist and Mermaid buildings on the seafront, including a series
of terraces on the slope above
• King Street public car park at the top of the slope
The King Street car park is at around 27mOD and Foreshore Road lies at around
5mOD. The Futurist and Mermaid buildings are built into the toe of the slope and
incorporate buttressed retaining walls with retained heights of around 8m.
Retaining structures also retain Bland’s Cliff along the side of the Mermaid
building.
The overall gradient of the terraced slope is around 25°.
2.3 Site history
The GIR includes details of site history. Refer to Table 1 for a condensed
summary.
Table 1: Summary of historical OS maps
Date Site land use
1700s Site is undeveloped. Bland’s Cliff is shown as an elevated track that extends
down to the beach by retained embankment.
The Kings Steps appear to have been built in the early 1700s on a part of the
slope that forms a promontory.
Various buildings are shown at the top of the slope and on the opposite side
of Bland’s Cliff.
1854 The earliest OS map shows buildings in the west and south of the site along
King Street and Kings Steps.
The site is surrounded by buildings (assumed to be a mixture of residential
and commercial properties) to the north and west
1892
One of the buildings adjacent to King Street is labelled as King’s Cliff
Hospital. Buildings adjacent to Kings Steps include a public house and two
buildings marked as Marine Terrace. A public house is present in the north
east corner of the site on Foreshore Road. The remainder of the site is
landscaped and a footpath is shown from the Foreshore to the top of the
cliff.
1903 The Arcadia Theatre building was built on the site of the existing Futurist
Theatre (although did not extend as far into the toe of the slope). At the
same time, Kingscliffe Holiday Camp was established on the hillside above,
with huts arranged along terraces on the slope.
1912 The Palladium Picture House was constructed adjacent to the Acadia
Theatre.
1920 The Arcadia building was demolished and replaced with the Futurist
Cinema, including cutting further into the toe of the slope and incorporating
a substantial retaining wall.
The Palladium was renamed the Arcadia Theatre.
1957 In 1957 the Futurist Cinema was converted for live theatre and from the
1960s became a popular theatre venue.
1966
The Arcadia Theatre was closed and much of its auditorium was used to
extend the Futurist Theatre stage.
The remainder of the Arcadia Theatre was utilised as the Minstels Lounge.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 6
Date Site land use
1990 The OS map shows the buildings along the lower terrace level labelled as
Futurist Flats with an electrical substation to the north. The building on the
upper tier of the site is marked as a Council Office.
1994 The Council Office building has been demolished and presumably the car
park was extended onto this area shortly afterwards.
2006 The Futurist Flats were demolished in this year.
2010 The building in the northern tip of the site is no longer shown on the map.
2.4 Unexploded Ordnance
Historical records indicate that Scarborough was affected by naval bombardments
in 1914 (killing 18 people) and in 1941 (killing 137 people).
In 1914, the slope on the site was occupied by Kingscliffe Holiday Camp and it is
understood that the camp offices were hit directly by the bombardment.
The site was similarly occupied in 1941, although it is not known whether the
holiday camp was still in operation. It is understood that the nearby Grand Hotel
was hit directly, but it is not known whether the site itself was hit.
It is recommended that a UXO specialist is asked to prepare a UXO risk
mitigation report for any future site works.
2.5 Ground level information
2.5.1 Topographic Survey
The site and surrounding public highways are covered by a topographic survey
carried out by Landtech Surveys in 2012 (for URS), with supplementary data
collected by APS in 2017.
2.5.2 Lidar data
In order to carry out global stability analyses that considered slopes outside of the
site boundary (in particular the properties and gardens on Prospect Place), it has
been necessary to use ground level information from Lidar data. The Lidar data
used in this assessment was a Digital Terrain Model (DTM) obtained from the
Environment Agency under an Open Government Licence.
2.6 Proposed development
This report is based on the following proposed development:
1. Demolition of the Futurist and Mermaid buildings, but leaving the existing
retaining structures in-situ.
2. Re-grading of the slope above to mitigate potential global slope instability.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 7
3. Placing of fill at the toe of the slope to enhance the stability of the existing
retaining structures.
4. Items 1 to 3 above would be coordinated to ensure that global slope stability is
not reduced at any stage.
5. Preparation of a new building development plot adjacent to Foreshore Road.
6. Possible future building development adjacent to Foreshore Road may include
structures built onto the slope above. The potential impact of such structures is
not considered in this report.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 8
3 Ground model
3.1 Ground investigations
Ground investigations have been carried out in four phases, starting with WYG in
2008 (covering the whole site), then ESG in 2014 (covering the site and the
existing Council offices to the west), Solmek in 2015 (supplementary boreholes
above and below the Mermaid building) and SEG in 2016 (supplementary
investigation).
The ground investigations have been carried out to obtain information for both
geotechnical and geo-environmental purposes
3.2 Ground contamination risk assessment
Refer to the GIR for a geo-environmental risk assessment, a summary of which is
presented below.
The ground contamination testing recorded only two local occurrences of elevated
PAH concentrations. Ground gas monitoring found very low levels of methane
and low levels of carbon dioxide as well as low gas flow rates. The site presents a
low risk from ground contamination in relation to future end uses.
It is noted that the above risk assessment assumes that the asbestos-containing
materials known to be present within the Futurist and Mermaid buildings will be
removed completely from site as part of the demolition process.
3.3 Stratigraphy
As presented in the GIR, for the purpose of assessing ground conditions, the site is
divided into five areas with similar stratigraphy:
1. Car park
2. Terraced slope
3. Back of Futurist wall
4. Beneath Futurist/Mermaid buildings
5. Foreshore Road
3.3.1 Car park
The stratigraphy beneath the car park is summarised in Table 2 below.
Table 2: Stratigraphy beneath car park
Stratum Description Thickness
(m)
Made ground Tarmacadam, typically over some
sub-base/capping and underlain by
demolition rubble. Occasional soft
clay layers, in particular WYG WS11
between 0.9 and 2.8m bgl.
Min 1.4m (WYG WS4) outside of
historical building footprints
Typically 3.0 to 3.5m within
historical building footprints
(Maximum 3.8m in WYG WS5)
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 9
Glacial Till Stiff to very stiff clay with varying
sand and gravel content. Occasionally
firm in uppermost part.
(Presumed) discontinuous lenses of
medium dense to dense silty
sand/gravel
Base of Till not proved
Sand/gravel encountered at 8.8 to
11.7m bgl and 23.8 to 27.5m bgl
(ESG CP105).
3.3.2 Terraces
The stratigraphy beneath the terraced slope is summarised in Table 3 below.
Table 3: Stratigraphy beneath terraces
Stratum Description Thickness
(m)
Made ground The holes on the upper terrace
(WS201 and WS202) encountered
clayey demolition rubble.
The holes on the lower terrace (WYG
WS7 to WS9) encountered more
variable conditions, but generally
typical of demolition rubble. WS8
encountered a void beneath a
concrete slab (former basement to the
Futurist Flats).
2.2m on the upper terrace.
On the lower terrace, a minimum
of 1.1m (WYG WS9) and a
maximum of at least 3.2m (WYG
WS7).
Glacial Till On the upper terrace, both WS201
and WS202 proved stiff clay beneath
the made ground.
On the lower terrace, only WYG
WS9 encountered natural soils,
comprising stiff to very stiff clay to
3.0m, underlain by gravel with sand.
Base of Till not proved
3.3.3 Back of Futurist wall
The stratigraphy behind the Futurist retaining wall is summarised in Table 4
below.
Table 4: Stratigraphy behind Futurist wall
Stratum Description Thickness
(m)
Made ground South end – WYG WS10
encountered predominantly soft and
very soft clay fill with some very
loose clayey sand.
Central – WYG BH1, BH3 and ESG
CP104 were closely-spaced but
encountered variable conditions. BH1
encountered very dense demolition
rubble over cemented rubble
(requiring rotary drilling to
penetrate). BH3 encountered
predominantly firm clay. CP104
encountered predominantly soft clay.
Around 8.5m
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 10
North – Solmek BHA encountered
predominantly firm clay fill with a
cemented rubble layer.
Glacial Till Stiff to very stiff clay with varying
sand and gravel content plus
occasional cobbles/boulders.
(Presumed) discontinuous lenses of
medium dense to very dense silty
sand/gravel
Base of Till not proved
In ESG CP104 sand/gravel
encountered between 10.0 to
12.2m bgl and 17.8 to 31.2mbgl
In Solmek BHA sand/gravel
encountered between 18.4 to
25.2m bgl and 17.8 to 31.2mbgl
3.3.4 Beneath Futurist/Mermaid buildings
The stratigraphy behind the buildings is summarised in Table 5 below.
Table 5: Stratigraphy beneath buildings
Stratum Description Thickness
(m)
Futurist
Floor slab Concrete 130mm
Made ground Limestone sub-base 210mm
Slab Concrete/asphalt 20mm
Made ground Brick/concrete rubble, clayey at base.
TP202 encountered obstruction
within this stratum.
340mm
Glacial Till Firm to stiff slightly sandy slightly
gravelly clay
Till proved to 3.45m bgl
Mermaid
Floor slab Concrete 200mm
Made ground Clayey concrete and brick rubble. 130mm
Glacial Till Firm to stiff slightly sandy slightly
gravelly clay
Firm from 1.2m to 3.0m bgl.
Till proved to 3m bgl
3.3.5 Foreshore Rd
The stratigraphy beneath the pavement on Foreshore Rd is summarised in Table 6
below.
Table 6: Stratigraphy beneath Foreshore Rd
Stratum Description Thickness
(m)
Made ground Tarmacadam and pavement build-up.
WYG WS15 encountered soft clay
fill between 1.0 and 1.9m bgl.
Apparently increases from south
to north from 0.7 to 1.9m thick.
Beach deposits Soils above around 1m OD appear to
be of different nature to the
underlying Glacial Till. The deposits
include soft clay and medium
dense/dense sand. The clay in
Solmek BHB included shell
fragments.
The base of the beach deposits
appears to be relatively consistent
at around 1m OD (approx. 3.5m
bgl).
Glacial Till Firm becoming stiff clay with
varying sand and gravel content.
Base of Till not proved
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 11
(Presumed) discontinuous lenses of
medium dense to dense silty
sand/gravel
3.4 Derivation of geotechnical parameters
Geotechnical parameters for design have been assessed with reference to the data
in the GIR as summarised in Table 7.
Table 7: Derivation of geotechnical parameters
Parameter Symbol Units Fine soils Coarse soils
Bulk unit
weight
γb kN/m3 Direct measurement of
undisturbed samples
Figs 1 and 2 in BS
8002:2015
Effective
angle of
shearing
resistance
φ’ ° CU triaxial tests. Plasticity
correlation (Eqn 7 in BS
8002:2015).
Shear box tests. Section
4.3.1.3 in BS 8002:2015
Effective
cohesion
c’ kPa CU triaxial tests, or zero. Assumed to be zero
Undrained
shear
strength
cu kPa SPT correlation (Stroud,
1975)
Not applicable
Stiffness E’ and
Eu
MPa SPT correlations (Stroud,
1975 and CIRIA 143)
CIRIA 143
3.5 Key parameter data
A summary of the findings of the in-situ and laboratory testing relevant to
derivation of geotechnical parameters is given in Table 8 below.
Table 8: Summary of testing data
Stratum Description In-situ and laboratory data
Made Ground Highly variable. Typically coarse
grained demolition rubble-type
material, but clayey made ground
also identified.
Coarse material generally loose (low
SPT N values).
Beach deposits Generally medium dense sand,
but soft clay also noted.
Minimum SPT N of 7 in the clay. High
SPT N values in the sand.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 12
Glacial clay Stiff to very stiff clay with
varying sand and gravel content.
Occasionally firm in uppermost
part.
SPT N values in the glacial clay show
an increase with depth, ranging from 5
to 15 at the top of the site to around 15
to 35 below around 5mbgl.
Predominantly low to intermediate
plasticity.
CU triaxial tests indicate a narrow
range of effective strength properties.
Can be summarised as φpeak’ = 31°,
cpeak’ = 3kPa.
Glacial
sand/gravel
Shallower deposits are presumed
to be discontinuous lenses of
medium dense silty sand/gravel
SPT N values similar to the glacial clay
above.
3.6 Parameters for slope stability assessment
The parameters in Table 9 are used in slope stability assessments.
Table 9: Slope stability parameters
Stratum γb
(kN/m3)
φk’
(°°°°)
ck’
(kPa)
Comments
Existing made
ground
20 30 0 Likely to be lower bound for mixed made
ground deposits.
Beach deposits 20 33 0 Ignored in slope stability models, as beyond
critical slips.
Glacial clay 22 31 2 Most critical stratum for overall stability.
Characteristic parameters chosen.
Glacial
sand/gravel
20 35 0 Some sand/gravel included to represent
lenses in upper part of slope and thick layer
at depth.
Engineered Fill
(granular site-
won)
19 33 0 Assumed as backfill behind new retaining
wall. Unit weight chosen to represent
reasonable degree of compaction.
3.7 Parameters for new retaining wall
The parameters in Table 10 are used in design of the new retaining wall.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 13
Table 10: Slope stability parameters
Stratum γb
(kN/m3)
φk’
(°°°°)
ck’
(kPa)
cu
(kPa)
E’
(MPa)
Comments
Beach deposits 20 33 0 N/A 15 Assumes sand, i.e. any soft
clay is removed.
Glacial clay
(formation
level)
22 28 0 60 15 Phi value chosen to
represent φcv’ for base
friction and sliding
calculations.
Wall backfill
(coarse site-won
and imported
fill)
20 35 0 N/A N/A This assumes that only
coarse fill is used in the
critical zone within the
active wedge behind the
wall.
3.8 Piezometric conditions
3.8.1 Existing piezometric profile
The profile used for stability analyses of the current slope is based on all available
information from the site investigation(s) and is considered a representative
condition.
3.8.2 Future piezometric profile
The profile used for stability analyses of the final slope assumes that drainage is
installed as indicated in Section 9 and is considered a reasonable worst-credible
condition that should not be factored further for design.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 14
4 Global stability
4.1 Back-analysis
An initial global stability assessment was carried out using assumed original slope
profile to check that the parameters derived from ground investigation are
reasonable.
4.1.1 Assumptions
The following assumptions have been made in the analysis:
• Drained analysis using unfactored parameters. Original slope will have
had a marginal factor of safety (global FOS = 1.0 approx.)
• Original slope profile taken from historical review of the site and
surroundings, in particular estimated from the original profile of King’s
Steps (current profile with adjustments for former arrangement shown on
1892 OS map).
• Crest of slope kept at existing position and elevation, but without made
ground, on the assumption that the original buildings were built on
platforms cut into the slope.
• Cross section is taken across approximate centreline of site. Hence
imposed loading is only accounted from King’s Cliff Hospital (1892)
approximately 12m behind verge. Assumed 2-3 storey Victorian masonry
building with UDL of 25kPa.
• Piezometric conditions within the Glacial Clay are conservatively
assumed.
• The deeper Glacial Sand/Gravel with artesian groundwater is not
considered, as the critical slip surface does not penetrate to this depth.
• Superficial shallow failures are ignored.
4.1.2 Model and findings
Refer to Appendix A for summary output from Oasys SLOPE software.
The results indicate that the chosen parameters for the Glacial Till and assumed
groundwater conditions are reasonable, and compatible with the assumed history
of the site.
4.2 Existing slope stability
Refer to Appendix B for slope stability calculation outputs from Oasys SLOPE
software.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 15
4.2.1 Prospect Place section
Slope stability on this section is likely to be dominated by the presence of the
garden retaining wall above Bland’s Cliff and by the retaining structure forming
the rear of the Mermaid Building.
Due to the lack of information on their structure, no attempt has been made to
carry out detailed stability assessment of either of these structures, however refer
to Section 7.
Global stability analysis indicates that the whole slope is likely to have a factor of
safety of around 1.3.
4.2.2 North section
The North section includes the existing sub-station, with the retaining structure to
the rear of the Futurist Building below and terrace walls above. For consideration
of the retaining structures, refer to Section 7.
Global stability analysis indicates that the whole slope is likely to have a factor of
safety of around unity.
4.2.3 Central section
The central section comprises the terraced slope and retaining structure to the rear
of the Futurist Building. For consideration of the retaining structures, refer to
Section 7.
Global stability analysis indicates that the whole slope is likely to have a factor of
safety of around unity.
4.2.4 King’s Steps section
This section comprises the terraced slope and retaining structure to the rear of the
Futurist Building. For consideration of the retaining structures, refer to Section 7.
This part of the slope has the steepest overall gradient.
Global stability analysis indicates that the whole slope is likely to have a factor of
safety of around unity.
4.3 Stability of proposed slopes
4.3.1 Assumed drainage and erosion control
When assessing the stability of proposed slopes, it has been assumed that drainage
measures are installed and maintained as indicated in Section 9. Erosion control
measures are also assumed, as indicated in Section 9.
The measures are summarised as follows:
• Erosion control geotextile within topsoil layer
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 16
• Land drain across crest of slope at interface of made ground and natural clay
• French drain at back of existing Futurist/Mermaid retaining wall, keeping
groundwater a minimum of 2m below proposed ground level.
• Granular drainage layer on top of Futurist/Mermaid ground slab between
existing and new retaining walls (to keep groundwater levels down at the base
of the new backfill).
• French drain at back of proposed new retaining wall, to prevent run-off from
ponding at the back of the wall.
• French drain in front of proposed new retaining wall.
4.3.2 Prospect Place section
The proposed earthworks do not directly affect the properties on Prospect Place,
or the slope immediately below. Groundwater conditions beneath the Prospect
Place properties and gardens are similarly not expected to be affected by the
proposed works. There should therefore be no net change to slope stability above
the existing Mermaid building.
The retaining structure that forms the rear of the Mermaid building is to be
retained, but the building structure in front is to be removed and replaced with fill
placed behind a new retaining structure. The building structure may be
contributing to the stability of the existing retaining structure and therefore the
demolition and filling process will be coordinated to ensure that the existing
retaining structure remains stable at all times.
The surcharge pressure of the new fill will be more than the UDL imposed by the
Mermaid building, but the fill only extends around half way across the existing
footprint, in order to leave space for the proposed development plot. The proposed
works will therefore have an effect on global slope stability. Analyses have
therefore been carried out to confirm that there will be a net improvement in
global stability.
The results of the stability analyses indicate that the current global factor of safety
is around 1.3, which is normally considered acceptable for cutting slopes. When
the Mermaid building is removed, the reduction in toe weight results in a slight
reduction in factor of safety. Placing fill in front of the existing retaining wall
restores the global factor of safety to slightly above the current condition.
The analyses confirm that fill must be placed in front of the existing retaining wall
prior to removal of the building surcharge.
It should be noted that, although the proposed works slightly improve the global
stability, there are no works proposed to the Prospect Place gardens and their
associated retaining structures, and hence their stability will not be improved.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 17
4.3.3 North section
The proposed earthworks are not intended to have a significant effect on the slope
directly above the existing sub-station, although there may be minor tie-in of
earthworks to existing terrace walls.
Groundwater conditions beneath the upper slope may be affected slightly by the
proposed drainage works on the remainder of the site to the south. There is
expected to be a slight reduction in piezometric pressures due to this improved
drainage, and there is therefore likely to be a net improvement in slope stability
above the existing sub-station.
The retaining structure that forms the rear of the Futurist/Mermaid building is to
be retained, but the building structure in front is to be removed and replaced with
fill placed behind a new retaining structure. The building structure may be
contributing to the stability of the existing retaining structure and therefore the
demolition and filling process will be coordinated to ensure that the existing
retaining structure remains stable at all times.
The surcharge pressure of the new fill will be more than the UDL imposed by the
existing building, but the fill only extends around half way across the existing
footprint, in order to leave space for the proposed development plot. The proposed
works will therefore have an effect on global slope stability. Analyses have
therefore been carried out to confirm that there will be a net improvement in
global stability.
The results of the stability analyses indicate a current global factor of safety of
close to unity. When the Futurist/Mermaid building is removed, the reduction in
toe weight results in a slight reduction in factor of safety. Placing fill in front of
the existing retaining wall significantly improves the global factor of safety.
The analyses confirm that fill must be placed in front of the existing retaining wall
prior to removal of the building surcharge.
It is also noted that, although the proposed works will significantly improve the
global stability, there are no works proposed to the terraces above the sub-station
and hence their stability will not be improved, other than by the effect of new
surface water drainage measures.
4.3.4 Central section
The proposed earthworks will result in a large volume of soil being removed from
the top of the slope, with some fill placed over the terraced slope and a significant
volume of fill placed in front of the existing Futurist retaining wall. There will
therefore be a reduction in surcharge effect at the top of the slope and addition of
toe weight, which should result in a significant improvement in global stability.
It is assumed that new fill placed over the terraced slope will be granular general
fill and not clayey fill, other than a surface layer of topsoil that will include a
geotextile for erosion control.
Groundwater conditions will change due to the earthworks causing changes in
ground level and also due to the proposed drainage works.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 18
The retaining structure that forms the rear of the Futurist building is to be
retained, but the building structure in front is to be removed and replaced with fill
placed behind a new retaining structure. The building structure may be
contributing to the stability of the existing retaining structure and therefore the
demolition and filling process will be coordinated to ensure that the existing
retaining structure remains stable at all times.
The surcharge pressure of the new fill will be more than the UDL imposed by the
existing building, but the fill only extends around half way across the existing
footprint, in order to leave space for the proposed development plot. The proposed
works will therefore have an effect on global slope stability. Analyses have
therefore been carried out to confirm that there will be a net improvement in
global stability.
The results of the stability analyses indicate a current global factor of safety of
close to unity.
The removal of the slope crest results in a slight improvement in stability, but then
this would be cancelled out by the removal of the surcharge effect at the toe of the
slope when the Futurist building is removed. Placing fill in front of the existing
retaining wall significantly improves the global factor of safety.
The analyses confirm that fill must be placed in front of the existing retaining wall
prior to removal of the building surcharge.
4.3.5 King’s Steps section
Global stability
Similarly to the Central section, the proposed earthworks will result in soil being
removed from the top of the slope, redistributed on the terraced slope and used as
fill in front of the existing Futurist retaining wall. However, the extent of
earthworks are restricted by the need to avoid impacting King’s Steps and
therefore the net improvement in global stability is less than for the Central
section.
It is assumed that new fill placed over the terraced slope will be granular general
fill and not clayey fill, other than a surface layer of topsoil that will include a
geotextile for erosion control.
Groundwater conditions will change due to the earthworks causing changes in
ground level and also due to the proposed drainage works.
The retaining structure that forms the rear of the Futurist building is to be
retained, but the building structure in front is to be removed and replaced with fill
placed behind a new retaining structure. The building structure may be
contributing to the stability of the existing retaining structure and therefore the
demolition and filling process will be coordinated to ensure that the existing
retaining structure remains stable at all times.
The surcharge pressure of the new fill will be more than the UDL imposed by the
existing building. The proposed works will therefore have an effect on global
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 19
slope stability. Analyses have therefore been carried out to confirm that there will
be a net improvement in global stability.
The results of the stability analyses indicate a current global factor of safety of
less than unity. There are no obvious signs of global instability and therefore the
assumed ground model must be over-conservative. However, the intention of the
analyses are to demonstrate the relative changes in factor of safety throughout the
proposed sequence of work, and therefore the exact numbers are less significant.
The removal of the slope crest results in a slight improvement in stability, but then
this would be cancelled out by the removal of the surcharge effect at the toe of the
slope when the Futurist building is removed. Placing fill in front of the existing
retaining wall significantly improves the global factor of safety.
The analyses confirm that fill must be placed in front of the existing retaining wall
prior to removal of the building surcharge.
Local stability
The Kings Steps section includes the steepest re-graded slope (1v:2h) likely to be
within existing made ground materials. Slope stability analysis indicates that the
re-graded slope will have a factor of safety of around 1.2 (or an over-design factor
of 0.99 using EC7 DA1-2 partial factors), which is slightly lower than would
normally be sought for slopes.
The analyses assume the made ground has a drained phi (φ’) of 30°. The made
ground on the slope is likely to include infilled former cellars and platforms
created for historical buildings. The assumed strength parameter is therefore likely
to be over-conservative and the re-graded slope is considered to be acceptable.
However, it is noted that stability is dependent on groundwater remaining below
around 2mbgl.
4.3.6 Council offices section
The above analyses indicate that there will be an overall improvement in global
stability of the slope within the site. However, it has been suggested that the
removal of soil from beneath the existing car park could have a negative impact
on stability of the existing Council offices that lie uphill of the site.
Additional analyses were therefore carried out to study this potential impact above
the main slope. In terms of global slope instability that could affect the office
foundations, the analyses indicate a small improvement in factor of safety.
4.4 Summary of stability analyses
The above assessments are summarised in Table 11.
Table 11: Summary of stability analyses
Stage Section Council
Offices
Kings
Steps
Central North Prospect
Place
1 Current (SLS) 1.16 0.94 1.05 1.03 1.34
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 20
2 Removal of slope crest
(SLS)
1.25* 1.01 1.17 N/A N/A
3 Removal of
Futurist/Mermaid building
surcharge
N/A 0.95 1.04 1.00 1.28
4 Placing fill and new
retaining wall (SLS)
N/A 1.44 1.51 N/A 1.36
(1.09 ULS)**
5 Final after regrade of
terrace slope (SLS)
N/A 1.39 1.49 1.29 N/A
Final after regrade of
terrace slope (ULS)**
N/A 1.12 1.20 1.04 N/A
*For slip surface potentially affecting the office foundations.
**ULS analysis uses EC7 DA1-2 partial factors.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 21
5 Earthworks
Earthworks drawings can be found in the drawings section at the back of this
report.
5.1 Site-won fill material
The proposed removal of soil from the crest of the slope is targeted on the central
part of the crest, i.e. around exploratory holes WYG-BH2, WYG-16, BH201 and
WS201.
• WYG-BH2 – the arisings will probably comprise around 25% gravelly clay
and 75% sand/gravel (clayey in places).
• WYG-16 – the arisings will probably comprise 25% gravel, 25% sandy gravel
with clay and 50% natural glacial clay
• BH201 – the arisings will probably comprise around 50% sandy gravel with
clay and 50% natural glacial clay
• WS201 – the arisings will probably comprise sandy gravel with clay.
There is expected to be around 3,500m3 of soil arisings in total. On the basis of
the above assessment, the anticipated volumes and classification of materials is
presented in Table 12.
Table 12: Anticipated fill classification and volumes
Material type SHW Series 600 Class Approximate volume (m3)
Sandy gravel 1A (well graded granular general fill) 1,000
Sandy gravel with
clay
2C (stony cohesive general fill) 1,500
Natural glacial clay 2A (wet cohesive general fill) 1,000
The different classes of material should be kept separate as much as possible
when excavating, in particular the natural glacial clay. The different classes of
material shall also be stockpiled separately and kept protected from rain.
The demolition of the Futurist and Mermaid buildings will generate concrete and
brick rubble. This could be processed (crushed and graded) to produce Class 6F2
(or similar) material. However, the contractor may consider that importing fill
materials is preferable to such processing on a restricted and sensitive site.
5.2 Re-use of site-won fill material
Compaction of the site-won fill materials shall be as recommended in SHW Series
600.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 22
For the purposes of slope stability design, the compacted fill should be assumed to
have the properties in Table 13.
Table 13: Anticipated properties of engineered fill
Fill class Unit weight
(kN/m3)
φ’
(°)
c’
(kPa)
Undrained shear
strength
(kPa)
Site-won Class
1A
19 32 0 N/A
Site-won Class 2C 20 28 0 N/A
Site-won Class
2A
20 26 0 40
Site-won Class
6F2 (crushed
concrete and brick
from former sub-
structures and
building
demolition)
19 35 0 N/A
Class 2 materials are unsuitable for re-use on the re-graded slope; this includes
reworked glacial clay and mixed clayey made ground. Such materials could be
used as bulk fill in front of the existing Futurist retaining wall.
To ensure an efficient design, only selected granular fill (e.g. Class 6F2) should be
used within the ‘active wedge’ behind the proposed new retaining wall.
As noted in Section 4.3, proposed slopes should be left no steeper than 1v:2h
(26°) in the permanent condition, including the side slopes where the re-grading
ties into existing terraces.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 23
6 Demolition of the buildings
In the temporary case some existing Futurist and Mermaid walls are being used to
retain the King’s Steps, Bland’s Cliff and the slope behind. The demolition
sequence and techniques used will be important for ensuring slope stability during
the works until the new retaining structure can be completed and the slope re-
graded.
The stability of the existing wall could be affected by removal of parts of the
building superstructure or ground slabs and/or excavations at its toe. However, the
removal of mass at the top of the slope and replacement of mass at the base of the
slope prior to demolition allows them to be used in the temporary case as
described in Section 8. Through review of existing building drawings, site survey
and discussion with the demolition contractor, the following basic demolition
sequence has been established:
• Undertake asbestos removal and soft strip.
• Add ballast locally to rear of existing retaining wall in the form of mass
concrete to improve global stability.
• Demolish Mermaid structure and install temporary support to Bland’s
Cliff wall. It is anticipated this will take the form of temporary propping.
These two operations will be completed in tandem working from the front
of the building to the rear.
• Demolish the flat roof section of the Futurist down to first floor level.
• Remove roof sheets to main Futurist building.
• Remove steel roof trusses to main Futurist building.
• Demolish walls to Futurist down to first floor level, starting at Northern
end of the building working towards the central stage beam. The
buttressed wall forming the rear of the building will need to remain in-situ
including the buttresses.
• Demolish the level one tiered seating.
• Remove central stage beam to ground.
• Continue with demolition of building from central stage beam towards
Kings Steps. The buttressed wall forming the rear of the building will need
to remain in-situ including the buttresses.
• Install temporary sheet piling to support the wall to Kings Steps until the
new retaining structure can be completed and backfilled.
During the detailed design stage the demolition sequence will be developed along
with the necessary temporary works required to maintain the stability of the slope.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 24
7 Existing retaining structures
The existing Futurist and Mermaid buildings currently retain the Kings Steps, the
slope to the rear and Bland’s Cliff. Refer to the drawings in the back of this report
for the line of the existing retaining structures.
7.1 Main section to the Futurist
The retaining structure at the rear of the Futurist Building is likely to be of a
combination of mass and reinforced concrete construction and appears to be
buttressed in several places by concrete structures, including shear walls. There is
no reason to suspect that it is currently unstable or even marginally stable, but
there is evidence of water ingress and the wall’s integrity could have been affected
by movement of water.
The stability of the wall could be affected by removal of parts of the building
superstructure or ground slabs and/or excavations at its toe. Considering the past
use of the site, the retaining structure should be capable of tolerating construction
plant loading behind.
7.2 Section adjacent to King’s Steps
The Futurist building wall retaining the Kings Steps is constructed entirely from
brick and varies in thickness from 0.7m to 1.2m. The stability of the wall could be
affected by removal of parts of the building superstructure or ground slabs and/or
excavations at its toe and as such suitable temporary works will be required until
the new wall can be constructed and backfilled.
7.3 Main section to the Mermaid
The retaining structure at the rear of the Mermaid Building is likely to be of mass
and/or reinforced concrete construction. There is no reason to suspect that it is
currently unstable or even marginally stable. However, its stability could be
affected by removal of parts of the building superstructure or ground slabs and/or
excavations at its toe. Considering the past use of the site, the retaining structure
should be capable of tolerating construction plant loading behind.
7.4 Mermaid wall supporting Bland’s Cliff
The Mermaid wall retaining Bland’s Cliff is constructed from a brick internal skin
with a brick aggregate concrete outer skin. It varies in thickness from 0.7m to a
minimum depth of 1.3mm. The stability of the wall could be affected by removal
of parts of the building superstructure or ground slabs and/or excavations at its toe
and as such suitable temporary works will be required until the new wall can be
constructed and backfilled.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 25
7.5 Terrace walls
The terrace walls are typically of brick construction, with occasional concrete
sections. Many of the sections of wall are in poor condition and exhibiting
evidence of damage, e.g. bulges, cracks, leaning.
For the purpose of this report, it is assumed that the terrace walls are potentially
marginally stable and could become unstable if undermined by excavations at
their toe, surcharge loading or by removal of mature trees.
7.6 Sub-station
From a review of historical mapping, it is considered most likely that the
substation was constructed by cutting into a former terrace and then backfilling
around. It is assumed that the substation building walls are retaining soil on three
sides. The arrangement of retaining structures at the rear of the building is
unclear, but the next terrace wall is located immediately behind and may therefore
impose load on the building. The stability of the substation building walls have
not been considered in detail for this report. However, it is assumed that any
increase in surcharge above or to the sides of the building could adversely affect
their stability.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 26
8 New retaining structures
In order to create a development platform at the base of the re-graded slope, a new
retaining structure is required to support the slope and limit its extents. It is
proposed that this will take the form of a reinforced concrete cantilever wall on a
reinforced concrete base. Because of the site constraints and varying retained
heights the wall construction varies along its length.
8.1 Design standards & sources of reference
8.1.1 CDM Regulations
The design and construction of the building will be in accordance with the
Construction Design and Management (CDM) Regulations 2015. The structural
design takes into account the responsibilities of designers stated in the CDM
Regulations. Refer to the Arup Hazard Risk Register for details of residual risks.
8.1.2 Codes of Practice & References
Document
number
Year of
publication Description
BS EN 1990 2002
+A1:2005
Eurocode: Basis of Structural Design
NA to BS EN
1990:
2002
+A1:2005
UK National Annex for Eurocode – Basis of structural
design.
BS EN 1992-1-1 2004 Eurocode 2: Design of concrete structures. General rules
and rules for buildings
NA to BS EN
1992-1-1
2004 UK National Annex to Eurocode 2 - Design of concrete
structures. General rules and rules for buildings
BS EN 1997-1 2004 Eurocode 7: Geotechnical design. General rules
NA to BS EN
1997-1
2004:2007 UK National Annex to Eurocode 7 - Geotechnical design.
General rules
BS EN 206-1 2002 Concrete Part 1. Specification, performance, production and
conformity.
BS8500
Complementary
BS to BS EN
206-1
Part 1: 2006 Concrete. Methods of Specifying and Guidance for the
Specifier.
Part 2: 2006 Concrete. Specification for constituent materials and
concrete.
2008 +
A1:2010
National Structural Concrete Specification for Building
Construction, 4th Edition, as expanded and amended by the
Project Specification
2010 National Structural Steelwork Specification for Building
Construction, 5th Edition, as expanded and amended by the
Project Specification
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 27
8.2 Walls for development platform
The design of the new walls has been completed based on the geotechnical
parameters described in section 3 of this report, and on the basis that the drainage
described in section 9 is installed and maintained.
Drawings for the new walls can be found in the back of this report.
8.2.1 Bland’s Cliff
Bland’s Cliff falls from a level of approximately 12m at the rear of the Mermaid
building to a level of 5.2m at Foreshore Road. The wall has been split into four
sections and it is anticipated that these can largely be constructed with the
temporary works to Bland’s Cliff remaining in place. Careful consideration will
need to be given to the sequencing of this work and a clear construction strategy
developed during detailed design, particularly where the new wall clashes with the
assumed existing structure.
This wall is generally a 1m thick stem with a base 7.5m in length and 1m thick.
8.2.2 King’s Steps
The King’s Steps are currently retained by the Futurist building. To maximise the
size of the development platform the new wall has been located adjacent to the
existing Futurist retaining wall at Foreshore Road. The wall is perpendicular to
the main retaining wall to the rear of the site. This will mean that the temporary
works stabilising the existing will likely encroach on the construction of the new
wall, particularly at the rear of the site. It is therefore proposed that this section of
new wall will be constructed in short sections to limit the amount of temporary
works being removed during construction. Careful consideration will need to be
given to the sequencing of this work and a clear construction strategy developed
during detailed design.
Similar to Bland’s Cliff, the King’s Steps fall from a level of 16.5m at the rear of
the Futurist to a level of 5.2m at Foreshore Road. The wall has been split into two
sections, though these do not necessarily coordinate with any sequencing strategy
at this stage.
This wall is generally a 1.5m thick stem with a base 6m in length and 1.5m thick.
8.2.3 Main Slope
The wall to the rear of the site retains an approximately uniform height of 5.3m.
The wall is set back approximately 15m from the existing wall. This wall is
generally a 1m thick stem with a base 7.5m in length and 1m thick.
Weepholes will be provided close to the base of the wall at approximately 3m
centres. In addition, free-draining granular materials will be placed behind and
below the wall to ensure that water pressures do not build up in the event that
weepholes become blocked in the future.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 28
8.3 King’s Steps
From the rear of the Futurist building to King Street, the King’s Steps and slope
are retained by an existing brick wall. Where possible it is proposed to re-use this
wall, however new walls similar to the existing may be required. During the
detailed design stage a survey of the existing structure will be undertaken. This
will identify areas of the wall requiring repair or replacement, with appropriate
solutions being designed as required.
8.4 Other Walls to Facilitate the Slope Re-grading
To the northern side of the site, the new slope profile has been tapered in to the
existing site levels providing an offset of approximately 10m from the site
boundary where no significant works are being undertaken. This will require a
number of the existing terrace walls on the site to be reduced in height and re-used
to retain the edge of the new slope. Similar to the wall along the King’s Steps it is
proposed to re-use these walls where possible, however new walls similar to the
existing may be required. During the detailed design stage a survey of the existing
structures will be undertaken. This will identify areas of the wall requiring repair
or replacement, with appropriate solutions being designed as required.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 29
9 Drainage
9.1 Existing Drainage Infrastructure
9.1.1 Desk Study
9.1.1.1 Statutory Undertaker Assets
Yorkshire Water sewer records have been provided to Arup indicating the
position and details of public sewers within the vicinity of the site (refer to
Appendix C). The relevant assets are summarised below:
• A 2000mm concrete public combined sewer within Foreshore Road
• A 225mm vitrified clay public combined sewer within Blands Cliff,
discharging to the sewer within Foreshore Road.
• A 675/500mm brick culvert within King Street.
• A section of public combined sewer is present within the north-western
area of the site (within the car park). This sewer appears to receive flows
from two adjacent properties outside of the site boundary on King Street
and Newborough. The status of this sewer and any easements or
wayleaves affecting it is not known. The outfall is also not shown on the
records, but it is assumed to discharge into the site drainage network.
9.1.1.2 Scarborough Borough Council Assets
An enquiry was made to Scarborough Borough Council (as Local Authority for
the area) to confirm whether there were any records of drainage assets in this area.
No drainage records were available for the site area.
9.1.1.3 North Yorkshire County Council Assets
An enquiry was made to North Yorkshire County Council (as highway authority
for the area) to confirm whether there were any records of highway drainage
assets in this area. No drainage records were available for the site area.
9.1.2 Site Observations
Although there are visible gaps within retaining wall masonry, it is not known
whether there are any functioning weep holes or back of wall drainage systems to
existing retaining structures.
A grated drainage channel is present within the Futurist basement which suggests
that some groundwater may permeate through the wall to be collected on the
internal face (see Figure 2). There are however no records or surveys to confirm
the condition or the outfall from this system.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 30
Figure 2 Evidence of Possible Retaining Wall Drainage
9.1.3 Drainage Survey
A drainage survey has been undertaken by L&M Survey Services to determine the
presence and condition of existing drainage infrastructure within the site. Full
details can be found within the drainage survey report, and a copy of the site
drainage plan is contained within Appendix D.
The survey findings are illustrated on drawing FUT-ARUP-ZZ-XX-DR-CD-0001
and summarised below:
• The survey did not establish full connectivity of the site drainage network.
Some of the outfall routes have been assumed based on the available data,
but some outfall routes couldn’t be determined.
• Surface water and combined water drainage systems are present along the
frontage of the Futurist building. These appear to receive flows from the
building roof drainage system and sanitary appliances (although an
internal drainage survey was not undertaken as part of this survey). These
networks appear to connect to the Yorkshire Water sewer within
Foreshore Road.
• A sewer was surveyed to the north of the site coinciding with the position
of the public combined sewer indicated on Yorkshire Water sewer
records. This extends to adjacent properties to the north and north-west.
• The car park drains via four road gullies. Two of these gullies discharge
into the public combined sewer and two gullies discharge into a private
surface water network. The outfall destination could not be determined for
either of these networks.
• A small section of surface water drainage system accepts downpipes from
the substation and hardstanding to the rear of the Futurist. This network
outfalls into the public combined sewer within Bland’s Cliff.
Manhole cards were not provided to allow verification of the condition and
connectivity of the manholes.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 31
9.1.4 Existing Site Catchment Areas
An assessment of the existing site catchment areas has been undertaken and is
shown on drawing FUT-ARUP-ZZ-XX-DR-CD-00002.
The catchment areas and assumed outfall destinations are summarised below:
Table 14 - Existing Site Catchment Areas
Catchment Area Assumed Outfall
Futurist Building 2,245 m² Yorkshire Water sewer in Foreshore Road.
Hardstanding 1 270 m² Yorkshire Water sewer in Bland’s Cliff
Hardstanding 2 310 m² Yorkshire Water sewer in Foreshore Road via King’s Steps
private sewer.
Landscaped
Terracing 1,115 m² No known drainage systems. Assumed to infiltrate.
Car Park Area 1 750 m² Yorkshire Water sewer within the site.
Car Park Area 2 750 m²
Private surface water sewer (assumed to connect to private
sewer in King’s Steps and ultimately connect to Yorkshire
Water sewer within Foreshore Road).
Third Party Plot 1* 220 m² Yorkshire Water sewer within site.
Third Party Plot 2* 190 m² Yorkshire Water sewer within site.
TOTAL 5,850 m²
* Third Party Plot catchment areas are assumed.
The assumed outfalls require verification to validate the drainage strategy.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 32
9.1.5 Existing Flow Rates
The average rainfall intensities for a 15 minute duration storm for three return
periods within the Futurist locality are provided in Table 15.
Table 15 - Average Rainfall Intensities
Return Period 1 Year 5 Year 30 Year
Average Rainfall Intensity 28 mm/hr 47 mm/hr 69 mm/hr
Based on the rainfall intensities in Table 2 and the assumed outfall routes, the
peak flow rates discharging to Yorkshire Water sewers have been determined
based on the Modified Rational Method. The flow rates are shown in Table 16.
Table 16 - Estimated Existing Peak Flow Rates
Outfall Area (m²)
Peak Flow Rate (l/s) & Return Period
1 year 30 year 100 year
YW Sewer in Foreshore Road 3,305 25.7 43.1 63.3
YW Sewer in Bland’s Cliff 270 2.1 3.5 5.2
YW Sewer within site 1,160 9.0 15.1 22.2
TOTAL 4,735 36.8 61.8 90.8
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 33
9.2 Proposed Drainage Strategy
Drawing FUT-ARUP-ZZ-XX-DR-CD-0003 illustrates the proposed drainage
strategy.
The demolition of the futurist building and re-modelling of the terracing and car
park results in an overall reduction in impermeable area on the site. The strategy
therefore seeks to capitalise on this reduction to reduce the flow rates discharging
to public sewers by allowing for some infiltration through landscaping.
Although the re-graded slope is to be landscaped, the gradient of the slope is
likely to result in a degree of surface water run-off. The percentage run-off from
areas of soft landscaping has therefore been taken as 30%. This represents the
upper limit of the recommended rates provided in BS 752 Table E.3. A filter drain
is proposed behind the new retaining wall to collect run-off from the landscaped
areas. The flows from this system are to discharge into the sewer in King’s Steps
as this most accurately reflects the existing flow regime.
The new retaining wall requires a drainage system to relieve the build-up of pore
water pressures against the wall. However, a back-of-wall drainage system would
present an ongoing maintenance burden and the deep inspection chambers would
present a hazard to those maintaining the system. It is therefore proposed that a
weep-hole system is installed, discharging onto the development platform.
A temporary drainage system shall be installed on the development platform until
the construction of the future development. The details of this system are pending
confirmation of the intended temporary uses. However, at this stage the area is
assumed to be 100% impermeable and is assumed to utilise the existing building
drainage connections discharging into the Foreshore Road public sewer (note that
the final development shall be subject to a separate planning application).
The remaining area of car park and adjacent third party plots shall continue to
drain to the sewer network within the site. Upon confirmation of the full extents
of this network, modifications or diversions may be required to maintain
connectivity following the re-grading of the site.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 34
9.2.1 Proposed Site Catchment Areas
The proposed site catchment areas, percentage impermeability (PIMP) and outfall
destinations are shown in drawing FUT-ARUP-ZZ-XX-DR-CD-0003 and are
summarised below:
Table 17 - Existing Site Catchment Areas
Location Area PIMP Proposed Outfall
Development Platform 1,230m² 100% To continue to discharge to Yorkshire Water
sewer in Foreshore Road.
Hardstanding area
adjacent to sub-station 140m² 100%
To continue to discharge to Yorkshire Water
sewer in Bland’s Cliff.
Landscaped Terracing 230m² 0% Not to be positively drained.
Landscaped Slope 3,135m² 30% New connection to private surface water sewer
in King’s Steps.
Remaining Car Park 600m² 100% To continue to discharge to Yorkshire Water
sewer within the site.
Third Party Plot A* 190m² 100% To continue to discharge to Yorkshire Water
sewer within the site.
Third Party Plot B* 220m² 100% To continue to discharge to Yorkshire Water
sewer within the site.
Landscaped Area 1 105m² 0% Small area adjacent to retaining wall assumed to
infiltrate.
Landscaped Area 2 70m² 0% Small area adjacent to retaining wall assumed to
infiltrate.
TOTAL 5,850m²
* Third Party Plot catchment areas are assumed.
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 35
9.2.2 Proposed Flow Rates
The design rainfall intensities for the site have been determined by applying a
climate change uplift factor to the existing rainfall intensities as described in
government guidance on flood risk (see Figure 3).
Figure 3 Government Guidance on Climate Change Allowances (gov.uk)
The upper end confidence level has been adopted for design up to 2115,
representing an uplift in rainfall rates of 40%.
Table 18 - Design Rainfall Intensities
Return Period 1 Year 5 Year 30 Year
Existing Average Rainfall Intensity 28 mm/hr 47 mm/hr 69 mm/hr
Design Average Rainfall Intensity 39 mm/hr 66 mm/hr 97 mm/hr
Based on the rainfall intensities in Table 18 and the assumed outfall routes, the
peak flow rates discharging to Yorkshire Water sewers have been determined
based on the Modified Rational Method. The flow rates are shown in Table 19.
Table 19 - Proposed Peak Flow Rates
Outfall Area
(m²)
Impermeable
Area (m²)
Peak Flow Rate (l/s) & Return Period
1 year
+CC
30 year
+CC
100 year
+CC
YW Sewer in Foreshore
Road 3,185 2150.5 24.1 40.7 59.8
YW Sewer in Bland’s
Cliff 140 140 1.5 2.6 3.8
YW Sewer within site 960 960 10.4 17.6 25.9
TOTAL 4,735 3250.5 35.2 59.6 87.6
Willmott Dixon Construction Ltd Futurist SiteGeotechnical Design Report
REP/GDR/002 | Issue | 25 July 2017
\\GLOBAL\EUROPE\LEEDS\JOBS\250000\251657-00\0 ARUP\0-03 GROUND ENGINEERING\0-03-08 REPORTS\GDR\2017-07-24 FUTURIST GDR_ISSUE 2.DOCX
Page 36
9.3 Conclusions
Based on the site information available, the majority of the Futurist site is
assumed to discharge to the Yorkshire Water sewer in Foreshore Road, either via
King’s Steps, Bland’s Cliff or directly from the Futurist building.
The proposed drainage strategy seeks to maintain the current regime by
continuing to discharge flows to the sewers in King’s Steps and Bland’s Cliff.
The demolition of the Futurist building and remodelling of the site results in a
reduction in impermeable area, which reduces the peak flow rates reaching the
Yorkshire Water sewer in Foreshore Road.
Run-off from landscaped areas shall be collected using a simple filter drain
discharging to the sewer in King’s Steps.
A back-of-wall drainage system shall be installed behind the new retaining wall
with a weephole system discharging onto the development platform. The
discharge through this system is negligible for design purposes.
A temporary drainage system shall be installed on the development platform
utilising the existing building connections to the public sewer in Foreshore Road.
The drainage system for the permanent development works shall be subject to a
separate planning application.
The small section of Yorkshire Water sewer within the site and the incoming
connections from the adjacent plots shall be maintained as part of the permanent
works, and the route to outfall retained as part of the permanent works.
Modifications to this network may be required to ensure the route is compatible
with the new site level strategy.
9.4 Next Steps
Further assessment of the existing site drainage system is required to confirm the
outfall routes and enable the design of any modifications to existing networks
remaining as part of the permanent works.
The ownership of the sewer in King’s Steps should be determined to obtain a
consent to make a new connection and agree details.
The drainage strategy is subject to approval from Yorkshire Water. Further
consultation with Yorkshire Water is required to determine the status of the public
sewer within the site and confirm any easements or wayleaves affecting the sewer.
Works affecting public sewers also require approval from Yorkshire Water.