  • Pearl GTL Project

    LINDE ENGINEERING

    Shell Project No: HP-3000-QAT Contractor Project No: 5887

    Project Document Number: T- 4.250.917 Project Rev.: B Page 2 of 15

    Purchase Order Number:

    2MH127

    Tag/Item Number(s): N/A

    Unit(s): ASU

    PCWBS: Z

  • QATAR SHELL GTL PROJECT (PEARL) C2 AIR SEPARATION UNITS CONSTRUCTION

    I B 27.11.08 Ready For Construction SB EO AG RFC

    H B 24.11.08 Ready For Construction SB EO AG RFC

    G A 23.10.08 Company Comments Incorporated SB EO AG CCI

    F A 17.09.08 Issue for Review SB EO AG IFR

    E A 14.09.08 Issue for Review SB EO AG IFR

    D A 08.04.08 Ready For Construction BR UA ZG RFC

    C O 03.12.07 Issued for Company comments BR AU/MC ZG ICC

    B 22.11.07 Issued for Review BR AU/MC ZG IFR

    A 20.11.07 Issued for Internal Review BR AU/MC ZG IIR

    GAMA Rev.

    Project Rev

    Date Description Prepared

    By Checked

    By

    Approved By

    Status

    No. No. ORIGINATOR

    LINDEGINEERING AG

    Document Title:

    ITP FOR STRUCTURAL STEEL PRE-ASSEMBLING AND ERECTION (FSI)

    Contractor

    Gama Qatar Co. W. L. L.

    Document No. LOC470

    GAM ITP QAC GTL 026 I

    Org.

    Code

    Doc.

    Type

    Disc. Code

    Geogr. Area

    Seq.

    No

    Rev. No

    Vendor Code

    Project Document Number: T-4.250.917

    Rev No: B

  • QSGTL PEARL PROJECT Document No.: GAM-ITP-QAC-GTL-026

    C2 ASU Construction Works

    ITP FOR STRUCTURAL STEEL PRE-ASSEMBLING AND ERECTION ( FSI )

    DATE: 27.11.08 - Rev. I

    S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. THIRD PARTY (TPI)

    I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)

    Item Activity Test Frequency Reference Document Acceptance Criteria Responsible

    Party Verifying Documents S X C A

    T-4.250.917 Rev. B Page 4 of 15

    1.0 METHOD STATEMENTS/PROCEDURES

    1.1

    Quality Control Procedure for Pre-assembly and erection of structural steel.

    Applicable QC Procedure

    QCP - T.4.250.907

    T-13.376.359 QA/QC - H R R

    2.0 CONTROL OF INSPECTION, MEASURING AND TESTING EQUIPMENT

    2.1 Torque wrenches

    100%

    T.4.250.915 Validity Calibration certificate H R R

    2.2 Inspection measuring and test equipment calibration

    100% T.4.250.915 QC Procedure for

    calibration QCI Calibration certificate H R R

    3.0 MATERIAL CERTIFICATES

    3.1 Receiving of structural steel materials

    100%

    Material Test Certificates

    Material Test Certificates

    QC INSPECTO

    R Applicable Standards I R R

    4.0 A. INSPECTIONS

    STRUCTURAL STEEL ASSEMBLING

    4.1 Verification of applicable WPS, Welder Qualifications

    100% 34.28.00-31;

    T.13.376.359E

    AWSD1.1 / ASME IX

    Welding Engineer

    WPS H H H H

  • QSGTL PEARL PROJECT Document No.: GAM-ITP-QAC-GTL-026

    C2 ASU Construction Works

    ITP FOR STRUCTURAL STEEL PRE-ASSEMBLING AND ERECTION ( FSI )

    DATE: 27.11.08 - Rev. I

    S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. THIRD PARTY (TPI)

    I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)

    Item Activity Test Frequency Reference Document Acceptance Criteria Responsible

    Party Verifying Documents S X C A

    T-4.250.917 Rev. B Page 5 of 15

    4.2

    Inspections of structural steel weld preparation. Fit up, tack welding, Pre Dimensional Checks ( If required )

    100% 34.28.00-31;

    T.13.376.359E AWSD1.1

    QC Inspector

    GAM-QCR-QAC-GTL-035 I

    H

    S

    4.3

    Inspection of Pre-assembled Structural steel

    a) Dimensional acceptance

    b) Welded joints acceptance

    100% 34.28.00-31;

    T.13.376.359E AWSD1.1& T-13-

    376.377 QC

    Inspector GAM-QCR-QAC-GTL-035 I W S

    STRUCTURAL STEEL INSTALLATION

    4.4

    Foundation acceptance

    a) Check elevation of foundation

    b) Location of anchor bolts (if applicable)

    c) Embedded plates installation (if applicable)

    100% IFC Drawings IFC Drawings QC

    Inspector

    GAM-QCR-QAC-GTL-037 (Revised)

    I

    S

    R

  • QSGTL PEARL PROJECT Document No.: GAM-ITP-QAC-GTL-026

    C2 ASU Construction Works

    ITP FOR STRUCTURAL STEEL PRE-ASSEMBLING AND ERECTION ( FSI )

    DATE: 27.11.08 - Rev. I

    S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. THIRD PARTY (TPI)

    I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)

    Item Activity Test Frequency Reference Document Acceptance Criteria Responsible

    Party Verifying Documents S X C A

    T-4.250.917 Rev. B Page 6 of 15

    4.5

    Verify a) Visual inspection of field welds. b) Repair welds (if applicable).

    100% Applicable WPS

    IFC Drawings QC

    Inspector

    GAM-QCR-QAC-GTL-037

    (Revised)

    I

    S

    S

    4.6

    Verification of lifting points & support points(During transportation, Before& after lifting the structure)

    100% T.4.250.897 34.28.00-31;

    T.13.376.359E Site

    Engineer --------------- I S S

    4.7

    Check bolt tightening

    a) Verification of torque

    b) Check anchor bolt tightening (if applicable)

    100% T.4.250.907 34.28.00-31;

    T.13.376.359E Site

    Engineer

    GAM-QCR-QAC-GTL-041 & Red Indication Mark over

    bolt head

    I

    W

    S

    4.8

    Verify a) alignment b) verticality (after bolt tightening and or welding)

    100% T.4.250.907 34.28.00-31;

    T.13.376.359E Site

    Engineer

    GAM-QCR-QAC-GTL-038,

    039

    I

    W

    S

    4.9

    Painting / Coating Repair works ( if applicable)

    Refer To Painting ITP I

    W

    S

  • QSGTL PEARL PROJECT Document No.: GAM-ITP-QAC-GTL-026

    C2 ASU Construction Works

    ITP FOR STRUCTURAL STEEL PRE-ASSEMBLING AND ERECTION ( FSI )

    DATE: 27.11.08 - Rev. I

    S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. THIRD PARTY (TPI)

    I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)

    Item Activity Test Frequency Reference Document Acceptance Criteria Responsible

    Party Verifying Documents S X C A

    T-4.250.917 Rev. B Page 7 of 15

    4.10

    Grouting Verification of surface preparation

    Refer To Grouting ITP I

    W

    S

    4.11

    Final Inspection of accessories

    Ladders, stairs treads, safety cages, Gratings, Toe plates

    Davits, Mono rails Equipment platforms

    Metal Cladding, roofing etc.

    100% T.4.250.907 T-13.376.377; 34.28.00-31;

    T.13.376.359E

    Site Engineer

    GAM-QCR-QAC-GTL-040 I

    I

    S

    4.12 Load test (if applicable)

    Mono Rails, Davits etc 100%

    Manufacturers recommendation

    Manufacturers recommendation

    Site Engineer

    TPI Report I I W W

    4.13 Released to next activity

    a) To Grouting (Civil Work)

    100% T.4.250.907 34.28.00-31;

    T.13.376.359E QCI

    GAM-QCR-QAC-GTL-146

    I W S

    4.14 Inspection on completion and release for Mechanical installation

    100% IFC Drawings As per Project Specification

    QCE / QCI --- I H H

  • QSGTL PEARL PROJECT Document No.: GAM-ITP-QAC-GTL-026

    C2 ASU Construction Works

    ITP FOR STRUCTURAL STEEL PRE-ASSEMBLING AND ERECTION ( FSI )

    DATE: 27.11.08 - Rev. I

    S. GAMA QATAR X. CONTRACTOR QC C. COMPANY A. THIRD PARTY (TPI)

    I: INSPECTION / TEST R: DOCUMENT ISSUED/REPORT REVIEW S: SURVEILANCE H: HOLD POINT (Notification Required and Presence Mandatory). W: WITNESS (Notification Required but Presence not Mandatory)

    Item Activity Test Frequency Reference Document Acceptance Criteria Responsible

    Party Verifying Documents S X C A

    T-4.250.917 Rev. B Page 8 of 15

    4.15

    Flaw less (FSI)

    a) Tightness 1) Loose Bolts 2) Wrong Type of

    Bolts

    100% T.13.377.360 As per this ITP

    Site Engineer &

    QA-QC Inspector

    GAM-QCR-QAC-GTL-041 I W S

    4.16 Acceptance of QC Inspection Records

    100% IFC Drawings & as per Project Specification

    As per this ITP

    QA-QC Engineer

    Civil& Structural

    --- I R R

  • C2 ASU PEARL GTL PROJECT

    RAS LAFFAN INDUSTRIAL CITY STRUCTURES ASSEMBLING

    REPORT

    Subcontract Ref.: Report No.:

    Item Description: Inspection Date:

    Item No: Test Code No.:

    Subsystem: ITP No.: GAM-ITP-QAC-GTL-XXX

    Ref. DWG / Docs:

    Used Measuring and test equipment ref. (if applicable):

    General Welding Repair Welding ( Tick - If Applicable)

    Check the following:

    Item

    No.

    Description ACC REJ N/A Signature Date

    1. Dimensional to be checked as per Drawing

    2. Fit up checked

    3. Orientations checked

    4.

    Various bends checked

    5.

    Welding Acceptable in visual

    6.

    PT/MT verified

    7. Painting checked

    ORGANIZATIONS NAME SIGNATURE DATE

    Accepte

    d B

    y

    GAMA REP.

    LINDE REP.

    QSGTL OR its PMC REP.

    GAM-QCR-QAC-GTL-035

  • GAM-QCR-QAC-GTL-037

    C2 ASU PEARL GTL PROJECT

    RAS LAFFAN INDUSTRIAL CITY

    STRUCTURAL STEEL PRE ERECTION & INSTALLATION

    PROCESS SHEET

    Subcontract Ref.: Report No.:

    Item Description: Date:

    Item Location/ Area: ITP No.: GAM-ITP-QAC-GTL-

    Subsystem: Test Code No.:

    Ref. DWG / Docs:

    Used Measuring and test equipment ref. (if applicable):

    Check the following:

    Item

    No.

    Description QC Inspector

    Initial Date

    Pre Erection :

    1. Foundation Handing over (Civil to Mechanical).

    2. Preparation of grouting (Chipping & Cleaning).

    3. Checking for anchor bolt.

    4. Shim plate fixed as per RFC drawing & work instructions.

    Installation Process :

    1. Foundation Complete & inspected.

    2. All Structural members correctly installed.

    3. Base supports are set at correct elevation.

    4. Structures Plump & alignment in all directions.

    5. Length of bolts is correct.

    6. All washers are correctly mounted.

    7. Correct tightening for all bolts.

    8. All temporary construction materials are removed.

    9. Welding acceptable.

    The Installation of the above Steel has been Satisfactorily completed in accordance with the Drawings& Specifications. Note: This QCR form revised on 23.11.2008 as per the site requirement and QCR form # 125 shall not been used further as per (PMC commends) Transmittal # PI-092-LIN-PMC-TX-21510.

    ORGANIZATIONS NAME SIGNATURE DATE

    Accepte

    d B

    y

    THIRD PARTY REP.

    GAMA REP.

    LINDE REP.

    QSGTL OR its PMC REP.

  • GAM-QCR-QAC-GTL-038

    C2 ASU PEARL GTL PROJECT

    RASLAFFAN INDUSTRIAL CITY

    STEEL STRUCTURES ELEVATION REPORT

    ( BASED ON SURVEY REPORT)

    Subcontract Ref.: Report No.:

    Item Description: Inspection Date:

    Item Location / Area: Test Code No.:

    Subsystem: ITP No.:

    Ref. DWG / Documents:

    Used Measuring and test equipment ref. (if applicable):

    INSPECTIONS

    Column No Planned Level Actual Level Level/Difference Plumb

    0 Degree 90 Degree

    ORGANIZATIONS DATE NAME SIGNATURE

    Accepte

    d B

    y THIRD PARTY REP.

    GAMA REP.

    LINDE REP.

    QSGTL OR its PMC REP.

  • GAM-QCR-QAC-GTL-039

    C2 ASU PEARL GTL PROJECT RAS LAFFAN INDUSTRIAL CITY

    ALIGNMENT REPORT FOR STEEL STRUCTURE

    Subcontract Ref.: Report No.:

    Item Description: Inspection Date:

    Item Location / Area: Test Code No.:

    Subsystem: ITP No.:

    Ref. DWG / Docs:

    Used Measuring and test equipment ref. (if applicable): Unit No.:

    OUT OF PLUMBNESS

    ORGANIZATIONS DATE NAME SIGNATURE

    THIRD PARTY REP.

    GAMA REP.

    LINDE REP.

    Acc

    epte

    d B

    y

    QSGTL OR its PMC REP.

  • GAM-QCR-QAC-GTL-040

    C2 ASU PEARL GTL PROJECT-RAS LAFFAN

    INDUSTRIAL CITY CHECK LIST OF LADDER,

    HANDRAIL, STAIRCASE & GRATING

    Subcontract Ref.: Report No.:

    Item Description: Inspection Date:

    Item Location / Area: Test Code No.:

    Subsystem: ITP No.: Ref. DWG / Documents:

    Used Measuring and test equipment ref. (if applicable):

    INSPECTIONS

    Item Mark No. Check of Ladders

    Check of Handrail

    Check of Staircases

    Check of Grating

    ORGANIZATIONS DATE NAME SIGNATURE

    THIRD PARTY REP.

    GAMA REP.

    LINDE REP.

    Acce

    pted

    By

    QSGTL OR its PMC REP.

  • GAM-QCR-QAC-GTL-041

    C2 ASU PEARL GTL PROJECT RASLAFFAN INDUSTRIAL CITY

    BOLT TIGHTENING INSPECTION REPORT

    Subcontract Ref.: Report No.:

    Item Description: Inspection Date: Item Location / Area: Test Code No.:

    Subsystem: ITP No.:

    Ref. DWG / Docs:

    Used Measuring and test equipment ref. (if applicable):

    INSPECTIONS Bolting Item No/Spool

    No Mark No./Joint No

    Grade Size Bolt Tightening (Torque Value)

    Inspectors Signature

    ORGANIZATIONS DATE NAME SIGNATURE

    THIRD PARTY REP.

    GAMA REP.

    LINDE REP.

    Acce

    pted

    By

    QSGTL OR its PMC REP.

  • Hand Over - Structural Group to Civil Group (For Grouting)

    Area : Date :

    Check

    Accepted

    Not

    Accepted

    N/A

    Remarks

    Bolt Torque Tightening Completion

    Alignment Check

    Anchor Bolts Tightening Check

    Shim Plates as per Work Instruction Check

    Module Washing Completion

    Structural steel works within the area are completed and released for Grouting Works.

    Check the Punch List Enclosed or Not

    Ready For Grouting

    Enclosures : 1. RFI for Torque Tightening for Field Bolts

    2. Alignment Records

    3. RFI and All Records for Module Inspection

    GAM-QCR-QAC-GTL-146

    Accepted By Handover By (Steel Structures) Accepted By (Civil / Equipment /

    Piping)

    GAMA Name : Sign / Date :

    Name : Sign / Date :

    LINDE Name : Sign / Date :

    Name : Sign / Date :

    FINAL ACCEPTANCE BY PMC Name : Sign / Date :