work shop - certification preparation training institute shop (based on fidic standard) pmi, pmp,...
TRANSCRIPT
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Sub-Contracts Management
and Administration –
WORK SHOP
(Based on FIDIC Standard)
PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
FOUNDATIONAL KNOWLEDGE
FIDIC – SUBCONTRACTORS
“UNDERSTANDING THE RELATIONSHIP BETWEEN
MAIN CONSTRUCTION CONTRACTORS
AND VARIOUS TYPES OF SUBCONTRACTORS
WORKING ON CONSTRUCTON SITES”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
FIDIC’S APPROACH TO
SUBCONTRACTORS
FIDIC’s Red Book, Sub-Clause (SC) 4.4, provides
for the basis of Subcontracting under their
provisions.1. Unless otherwise agreed the Contractor CANNOT subcontract the
whole of the works;2. The Contractor remains wholly responsible to the employer for the acts
of that subcontractor as if those acts had been carried out by him;3. The prior consent of the Engineer is required for all subcontractors apart
from suppliers and subcontractors named in the Contract;4. The Contractor must give the Engineer 28-days notice of both the
intended and actual commencement date of any subcontract’s work;and
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
FIDIC’S APPROACH TO
SUBCONTRACTORS (CON’T)
5. The subcontract must contain suitable provisionsentitling the employer to require the subcontract toassigned to him in the event of termination. Sub-Clause (SC) 4.4(d) states:
– “…each subcontract shall include provisions which wouldentitle the Employer to require the subcontract to be assignedto the Employer under Sub-Clause 4.5 [Assignment of Benefitof Subcontract] (if or when applicable) or in the event oftermination under Sub-Clause 15.2 [Termination byEmployer]...”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
FIDIC’S APPROACH TO
SUBCONTRACTORS (CON’T)
FIDIC’s Sub-Clause 4.4, provides for the basis of
Subcontracting under the Red Book.
6. Whereas Sub-Clause (SC) 4.5 (Assignment of Benefitof Subcontract) reads:
– “..If a Subcontractor’s obligations extend beyond the expiry dateof the relevant Defects Notification Period and the Engineer, priorto this date, instructs the Contractor to assign the benefit of suchobligations to the Employer, then the Contractor shall do so.Unless otherwise stated in the assignment, the Contractor shallhave no liability to the Employer for the work carried out by theSubcontractor after the assignment takes effect…”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
DIFFERENCES ACROSS FIDIC’S
RAINBOW: SUBCONTRACTORS
Under the Silver Book – for example – the Contractor only
has to notify the Employer of the appointment of a
subcontractor, but also providing pertinent details about thesubcontractor in question:
– Subcontractors past performance and experience– When they intend to begin work on the project;– Other information as required
Red and Pink Book, reference the language under 4.4(d) previously stated;
Gold Book provisions referencing subcontractors – state:
– “…If the Subcontractor is entitled to any relief from risk on broader terms thanthose specified between Contractor and Employer, then those additionalcircumstances shall not serve as an excuse for non-performance by theContractor…”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
FIDIC’S RULE: CONTRACTOR
RESPONSIBLE FOR SUBCON ACTIONS
• REMEMBER: No matter what version of FIDIC, THECONTRACTOR WILL ALWAYS BE WHOLLY RESPONSIBLE for theperformance (or NON-performance) of the subcontractor.
• This includes time, quality and paying the subcontractor inaccordance with (IAW) the contract between the main contractorand subcontractor regardless of any issue between the maincontractor and the employer.
• THIS OBLIGATION – extends not only to subcontractorsappointed by the contractor (Domestic), but also to thesubcontractors NOMINATED by the employer in accordance withclause 5 of the Red Book. (SC 5.1)
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
SUBCONTRACTORS, CONTRACTORS
& EMPLOYERS
BASIC TERMINLOGY GROUNDING
SUBCONTRACTOR’S INTO
THE INDUSTRY OF THE UAE
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY: SHANKLIN PIER LTD
V DETEL PRODUCTS LTD
• Shanklin Pier Ltd (hereinafter called “Shanklin” or
“Claimant”) owned a pier and intended to repair it.
(have it repainted);
• Detel Products (hereinafter called “Detel”), warranted
to Shanklin that their paint would provide rust
protection for up to 10 years;
• Claimant relied upon this warranty and when
engaging the Main Contractor (MC), instructed the
MC to place an order for this paint.
• The paint was judged a total failure after a short
period of time!!!
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY: SHANKLIN PIER LTD
v DETEL PRODUCTS LTD
• Shanklin sought to recover damages direct
from the defendant (Detel) – NOT THE MAINCONTRACTOR – as the MC had not warranted the paintmaterials used, primarily because it had been thesubcontractor (Detel) that warranted the goods to theemployer originally;
• This despite the fact that the sale of the paint
product had taken place between the MC and
the defendant (Detel)
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY: SHANKLIN PIER LTD
v DETEL PRODUCTS LTD
Shanklin Pier Ltd v Detel Products Ltd [1951]
2 KB 854 remains a leading judgment on the subjectof collateral contracts in English contract law.
In it the High Court of Justice, King's Bench
Division, used the principle of collateral
contracts, to create an exception to the ruleof privity of contract where a contract may begiven consideration by entering into another contract.
Judge McNairs’ Judgement read as follows.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY: SHANKLIN PIER LTD
v DETEL PRODUCTS LTD
“This case raises an interesting and comparatively novel question whether or
not an enforceable warranty can arise as between parties other than parties to
the main contract or the sale of the article in respect of which the warranty is
alleged to have been given.... I am satisfied that, if a direct contract of purchase
and sale of [the paint] had then been made between the plaintiffs and the
defendants, the correct conclusion on the facts would have been that the
defendants gave to the plaintiffs the warranties substantially in the form alleged
in the statement of claim. In reaching this conclusion, I adopt the principles
stated by Holt CJ in Crosse v Gardner and Medina v Staughton that an affirmation
at the time of sale is a warranty provided it appear on evidence to have been so
intended.”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY: SHANKLIN PIER LTD
v DETEL PRODUCTS LTD
JUDGE McNair concluded his remarks on this
precedent setting case as follows:
“…If, as is elementary, the consideration for the warranty in the
usual case is the entering into of the main contract in relation to
which the warranty is given, I see no reason why there may not be
an enforceable warranty between A and B supported by the
consideration that B should cause C to enter into a contract with
A or that B should do some other act for the benefit of A...” [1]
[1] Beale (2002) p.55
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
IDENTIFICATION AND DESCRIPTION OF
SUBCONTRACTOR
“TYPES”
OPERATING AT A WORKS SITE
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
RELATIONSHIP BETWEEN
MC AND SUBCON - DEFINATIONS
• THREE TYPES OF ‘SUB-CONTRACTORS’;
– Domestic
– Nominated
– Named
• “…Domestic sub-contractor (SC) is one selected and employed by the Main Contractor (MC) for whom the MC is solely and entirely responsible…”
[Nick Gould, Partner – Fenwick Elliott]
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
RELATIONSHIP BETWEEN
MC AND SUBCON - DEFINITIONS
• “Nominated Subcontractor is selected by the Employer butemployed by the MC…”
• “Named Subcontractor is where the Employer names one ormore ‘preferred’ sub-contractors. To that list the MC may addfurther potential sub-contractors. The cumulative list is then usedfor tendering purposes and a sub-contractor is selected by the MC.The sub-contractor is then treated as a domestic sub-contractor ofthe MC, thus avoiding the employer liability disadvantages ofnomination, but still giving the employer some element ofinvolvement in the selection process.
• THIS type of SC derives from JCT forms of contract
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
SUBCONTRACTING
TYPES
Nominated Sub-
Contractor
Domestic
Sub-Contractor
Named
Sub-
Contractor
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
WHY USE ‘NOMINATED SUBCON?
• ALLOWS EMPLOYER and/or Employers selectedARCHITECT to identify a sub-contractor who is supplying along lead item or element of the work (example – a ‘lift’ orelevator, or other specialized equipment), and moreimportantly, secures a manufacturing and delivery slot beforethe MC has been selected.
• Another advantage is the selection of ‘specialist’ sub-contractors that is required to carry out some of the initialworks on site (Early Works). Examples of this type workusually involves foundation works (piling operations).
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE LAW’S
THAT GOVERN
“SUBCONTRACTING”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CONTRACTORS ‘LEGAL RIGHT’ TO
SUBCONTRACT UNDER UAE LAW
• EMPLOYERS in the UAE – typically – prefer to enter
into a contract with one (1) Main Contractor for
the whole works – rather than to have several
separate contracts for the performance of
separate segments of works.
• Main Contractors rarely carry out the whole of
works themselves in the UAE, and generally use
more than one sub-contractor to carry out
portions of the works.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CONTRACTORS ‘LEGAL RIGHT’ TO
SUBCONTRACT UNDER UAE LAW
Main Contractors are granted the right to sub-contract their assigned works as derived under article
890(1) of the Federal Law No. 5 of 1985, under the
Civil Transactions Code of the UAE.
Under UAE Law – the Main Contractor is lawfully entitled toentrust the performance of the whole or part of the work to anothercontractor (sub-contractor) unless he is prevented from so
doing by a condition of the contract (such as per
FIDIC SC 4.4) or unless the nature of the work
requires the MC to do it in person.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
SUB-CONTRACTORS ‘RIGHTS’ UNDER
UAE SUBCONTRACTING LAWS
Claims for Payment – by the sub-
contractor for performance rendered under asubcontract lies solely with the Main Contractor(Privity of Contract rule);
Sub-contractor has no legal basis toinstitute a claim against an employer for paymentdue from the MC for performance rendered undera subcontract.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
SUB-CONTRACTORS ‘RIGHTS’ UNDER
UAE SUBCONTRACTING LAWS
“…Article 891, UAE Civil Transaction Code
prohibits a subcontractor from instituting a
claim against an employer for any amounts that
are claimable from the MC unless the MC has
given the subcontractor an assignment of
its rights against the employer…”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
SUB-CONTRACTORS ‘RIGHTS’ UNDER
UAE SUBCONTRACTING LAWS
• NOTE:
“…Article 891, UAE Civil Transaction Code
prohibits a subcontractor from instituting a
claim against an employer for any amounts that
are claimable from the MC unless the MC has
given the subcontractor an assignment of
its rights against the employer…”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE CIVIL
TRANSACTION
CODE(a.k.a., “Civil
Code” REGARDING
SUBCONTRACTING
– SPECIFICALLY
“Article 891”
NOTE:
Online Access to
Official UAE website for
legal information:
http://www.elaws.gov.ae
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Full
Text
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE GOVERNING
SUBCONTRACTING LAWS
• Article 1109(1) of the UAE Civil Transaction Code
provide terms for validity of an assignment of rights is theconsent of the assignor, assignee, and the party in whosefavor the assignment is made.
• Unless expressly provided for under the main
contract – an Employer would only be entitled to make alawful direct payment to a sub-contractor for paymentdue under a subcontract in the event that all three parties(Employer, Contractor and Sub-Contractor) haveconsented thereto.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Article 1109 “legalese
wording” describing
direct payments to a
Subcontractor by the
Employer
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Article 1109
1 – “The validity of a transfer is
conditioned upon the acceptance
of he transferor, the transferee
and the third party beneficiary.”
2 – “The transfer is formed
between the transferor and the
transferee provided it is accepted
by the concerned creditor”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE GOVERNING
SUBCONTRACTING LAWS
• Employers typically expressly provide in
the main contract with its MC, the right
to pay a sub-contractor directly and to
deduct the sums so paid from money due
the MC, particularly where the
subcontractor is a “nominated” sub-
contractor by the Employer.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UAE GOVERNING
SUBCONTRACTING LAWS
• BUYER BEWARE!!!
“…In the event that such direct payment is in
any way determined unlawful, the Employer
would then remain liable to pay the Main
Contractor for the same work and would have to
pursue the sub-contractor in a separate cause
of action for the recovery of the direct payment
made…”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
FIDIC SUBCONTRACT 2011:
“CONDITIONS OF SUBCONTRACT
FOR CONSTRUCTION
OF BUILDING AND ENGINEERING”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UNDERSTANDING SUB-CONTRACTORS
RIGHTS UNDER CLAUSE 20 (2011 Subcontract)
Introduction:
Two FIDIC Documents Examined:
1. “Subcontract for Construction of Building and
Engineering Works designed by the Employer, 1st
Edition, 2011 (known as the ‘2011 Subcontract’)”[1]
2. “The Guidance for the Preparation of the Particular
Conditions of Subcontract (the ‘Guidance’)”[2]
[1] Lexology, November 2012
[2] Ibid
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
jjj
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
“Guidance for the Preparation of
Particular Conditions of Subcontract”.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UNDERSTANDING SUB-CONTRACTORS
RIGHTS UNDER CLAUSE 20 (2011 Subcontract)
Direct application of “Clause 20” of the ‘2011
Subcontract’ provides:
• An Alternative Dispute Resolution (ADR)
procedures similar to the Main Contract FIDIC Red
Book relief remedies, mainly:
– Disputes arising under a subcontract are first referred tothe Subcontracts DAB (Dispute Adjudication Board)and thereafter (if desired), dispute escalates to anarbitration panel for final determination.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UNDERSTANDING SUB-CONTRACTORS
RIGHTS UNDER CLAUSE 20 (2011 Subcontract)
Under item number two (2) above (Guidance for
the Preparation of the Particular Conditions of
Subcontracts) - there are two (2) optional ADR
provisions;
1. Simple Dispute Resolution Procedures involving onlyArbitration;
2. Complex mechanism intended to make the
Subcontractor bound by Main Contractor DAB
decisions and Arbitration awards on disputes
related to those under the Main Contract.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
UNDERSTANDING SUB-CONTRACTORS
RIGHTS UNDER CLAUSE 20 (2011 Subcontract)
COURSE GOAL - FORWARD:
• Provide a “High Level” overview to course participantsregarding the second alternative clause 20 provisionsand highlight particular areas which
contractors and subcontractors should
be concerned with.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
THE “SECOND ALTERNATIVE
CLAUSE 20”
as described in
“THE GUIDANCE FOR THE
PREPARATION OF THE PARTICULAR
CONDITIONS OF SUBCONTRACTS”
(known as the “Guidance”)
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
SECOND ALTERNATIVE CLAUSE 20
An Overview:
IMPORTANT POINTS:
• The Clause is separated into sub-clauses dealing with
the Subcontractor’s claims for extension of time (EOT)
and/or additional payment under the Subcontract (sub-
clauses 20.1 – 20.5) and disputes (sub-clauses 20.6 to
20.8);
• For claims for extensions of time and/or additional
payment, the Subcontractor is required to give notice
within 21 days of it becomes (or should have become)
aware of the event or circumstance giving rise to the
claim (sub-clause 20.1)
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
SECOND ALTERNATIVE CLAUSE 20
An Overview:
IMPORTANT POINTS continued:
• Such claims are then separated into “RELATED
CLAIMS” (claims that arise from circumstances which
may also give rise to a claim under the Main Contract or
otherwise concern existing claims or disputes under
the Main Contract) and;
• “UNRELATED CLAIMS” – which is any disagreement
between the parties on whether a claim is “Related” or
“Unrelated” will ultimately be referred to the ICC pre-
arbitral referee procedure (sub-clause 20.2)
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
SECOND ALTERNATIVE CLAUSE 20
An Overview:
• For Unrelated Claims – the Subcontractorputs forward its detailed claim to the Contractor. If
agreement cannot be reached in respect of
the claim, the Contractor is required to
make a “fair determination” (sub-clause
20.3)
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CLAUSE 20, Related Claims
Under sub-clause 20.4, Contractor obligated to submit Related Claims to
the Engineer and Main Contractor must use “all reasonable
endeavors” to secure claim from the Employer. The Sub-contractor
is entitled to be involved in any meetings with the Engineer which
concerns the Related Claim, although there is no requirement in Red Bookthat obligates the Engineer to allow the Subcontractors to be present.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
SECOND ALTERNATIVE CLAUSE 20
An Overview:
“Unless the Subcontractor is
present in those meetings, or
refuses to attend where
permitted to do so, the
Contractor is not allowed to
reach an agreement with the
Engineer on the Related Claim(s)
without ‘prior consultation’ with
the Subcontractor.”
Given that the sub-clause goes on to state that Subcontractors could be bound by thatagreement if they do not serve a notice of dissatisfaction within a prescribedperiod, Subcontractors would no doubt want this wording to do further and prohibit theContractor form reaching any agreement with the Engineer without its prior, written,approval.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
SECOND ALTERNATIVE CLAUSE 20
An Overview:
• Sub-clause 20.4 continues to state that, wherethe Engineer and Contractor reach agreement on the RelatedClaim(s), or the Engineer issues a determination, such thatthe Contractor is entitled to an extension of time (EOT)and/or additional costs under the Main Contract – theContractor is required to pass the share of benefit(s)applicable to the Related Claim to the Subcontractor.
• HOWEVER; the Contractor is only liable to pass on monetarybenefits if it first receives payment from the Employer, which, islikely to be controversial.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
SECOND ALTERNATIVE CLAUSE 20
An Overview:
• If the Contractor and Subcontractor disagree
what the Subcontractor’s share of the
benefit(s) will be, the Contractor will make a
“fair determination”, which the Subcontractor
will be bound by if it does not issue a notice of
dissatisfaction on time.
• IF HOWEVER - the Engineer and Contractor agree, or the Engineerdetermines, that no additional payment and/or extension of time (EOT)is due the Contractor under the Main Contract, then the Subcontractorwill be bound by this unless it serves a notice of dissatisfaction with theprescribed period.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
SUBCONTRACT DISPUTES
Sub-Clause 20.6 – 20.8
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CLAUSE 20 “Disputes”
An Overview:
Similar to Claims discussed in the last
section –
• Subcontract Disputes are categorized
into two categorizes:
1. Unrelated Disputes
2. Related Disputes
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CLAUSE 20 “Disputes”
An Overview: Sub-clause 20.7
NOTE: “Disputes” arising from “unrelated claims”
and “related claims” AUTOMATICALY constitute
“Unrelated Disputes” and “Related Disputes”.
Accordingly;
• Sub-clause 20.7 – “Unrelated Disputes” – can bereferred by either the Contractor or the Subcontractor foradjudication by the Subcontract DAB.
• If either party issues a notice of dissatisfaction in relation to theSubcontract DAB’s decision the parties shall attempt to amicablysettle the dispute or proceed directly to the ICC Arbitration.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CLAUSE 20 “Disputes”
An Overview: Sub-clause 20.8
• Sub-clause 20.8 – “Related Disputes” – are initiallyreferred by the Contractor to the Main Contract DAB and theContractor is required to “use all reasonable endeavors” to pursuethe claim on the Contractor’s and Subcontractor’s behalf and forboth their benefit(s).
• The Subcontractor is required to provide information to theContractor to pursue the Related Dispute and is to be provided areasonable opportunity to be involved in (amongst other things)preparing written submissions an making oral submissions to theMain Contract DAB
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Related Claims (SC 20.8) Chart
SC MC
Subcontractor shares common, related dispute with Main Contractor. Subcontractor supports the Main Contractor by suppling relevant and timely information related to the mutual dispute, and is
included in the all written submissions to the Main DAB. SC is allowed also to participate in “oral arguments” before the Main DAB.
DAB convenes Board and listens to Oral Arguments from both the MC and the Sub-Contractor
Main Contract attends DAB and presents joint Related Claim evidence for DAB consideration.
MC & SC share a similar Claim
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CLAUSE 20 “Disputes”
An Overview: Sub-clause 20.8 (Con’t)
Sub-clause 20.8 – “Related Disputes” (continued)
• If the Subcontractor is not able to be involved in
the Main Contract procedure in this way then (which, again,is certainly likely given that, again, there is nothing in the Red Book that obligates
the Employer to agree to this) the Contractor is not entitled to
reach any settlement with the Employer on the
Related Dispute without prior consultation with
the Subcontractor.
• Concern for the Subcontractor: Contractor reaching anagreement with the Employer that might ultimately be binding onthe Subcontractor.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CLAUSE 20 “Disputes”
An Overview: Sub-clause 20.8 (Con’t)
Sub-clause 20.8 – “Related Disputes” (continued)
• The Contractor is required to notify the Subcontractor
of the Main Contract DAB decision, which will in turn bebinding on the Subcontractor unless it provides a notice of dissatisfactionwithin 7 days.
• If the Main Contract DAB finds in the Contractor’s favor,
then the Contractor has to use all reasonable
endeavors to secure the relevant benefit(s) form the
Employer, and keep the Subcontractor updated as to its progress. Aswith the Related Claims provisions, receipt of payment from the Employeris a condition precedent to the Contractors liability to the Subcontractorin respect of the same, and there is a similar provision in relation todetermining the parties’ respective shares of the benefit received.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CLAUSE 20 “Disputes”
An Overview: Sub-clause 20.8 (Con’t)
Sub-clause 20.8 – “Related Disputes” (continued)
• If the Subcontractor serves a notice of dissatisfaction
(NOD) wit the Main Contract DAB’s decision, the
Contractor will need to serve a corresponding notice to
prevent the Main Contract DAB’s decision from
becoming final and binding under the Main Contract.
• Under Red Book Conditions of Contract, the
Contractor’s NOD is a condition precedent to its
entitlement to refer the dispute for final determination
by the ICC arbitration.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CLAUSE 20 “Disputes”
An Overview: Sub-clause 20.8 (Con’t)
Sub-clause 20.8 – “Related Disputes” (continued)
• If the Contractor does not respond to the
Subcontractor’s NOD, or does not serve a
corresponding notice against the Main Contract DAB
decision to prevent it from becoming final and binding
under the Main Contract – then the dispute will be
considered an “Unrelated Dispute”.
• Sub-clause 20.7 will then apply. The Subcontractor will
essentially need to start again and refer the now
Unrelated Dispute to the Subcontract DAB for a
decision.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Employer Main Contractor
Disputes Adjudication Board
(1) Employer and MC come to resolution on Dispute presented at the Main Contract DAB.
Subcontractor
(2) However, upon informing the SC of the decision, the SC is not content, issues a Notice of Dissatisfaction (NOD) to MC7 Days Max before resolution is final, SC must notify MC
with NOD during this time
No guidance within FIDIC on timing of notification back to DAB or Employer of Subcontractor NOD from Main
Contract DAB Decision. Reasonable timing is thought to be same notification timing as Subcontractor – 7 days.
Employer Main Contractor
(3) Main Contractor, upon receiving NOD from SC, must then notify the Employer and DAB that their mutual decision reached earlier btw Employer and Contractor, cannot be implemented.
SC 20.8 RELATED DISPUTE GRAPHICAL
REPRESENTATION
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CLAUSE 20 “Disputes”
An Overview: Sub-clause 20.8 (Con’t)
Sub-clause 20.8 – “Related Disputes” (continued)
• If the Contractor does issue a NOD under the Main
Contract, it will first try to reach a settlement with the
Employer and if, unsuccessful, will proceed to
commence ICC arbitration proceedings against the
Employer in respect of the Related Disputes under the
Main Contract.
• The Subcontractor will be given the opportunity to be
involved in the proceedings. [NOTE: Subcontractor will
NOT be entitled to become party to those proceedings]
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CLAUSE 20 “Disputes”
An Overview: Sub-clause 20.8 (Con’t)
Sub-clause 20.8 – “Related Disputes” (continued)
• The award under the Main Contract arbitration is
deemed to be binding on the Subcontractor to the same
extent as it is binding on the Contractor.
• The contractual benefit of any award shall be shared
with the Subcontractor to an appropriate extent to be
determined by the Contractor.
• Any disagreement as to the level of the share shall be
deemed an Unrelated Dispute to be settled by
arbitration between the Contractor and Subcontractor.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
RELATED DISPUTES –
Depicted Graphically
ICC Arbitration Decision
Main Contractor
Sub-Contractor
Arbitration Decision is binding on both MC
and SC, unless monetary award to SC is not agreed. In this case, a new disputes
is recorded as a “unrelated Dispute”
Favorable Decision awarded to MC only
Financial benefits of ICC Decision shared between MC and SC
as determined by MC or previously
agreement btw MC and SC.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CLAUSE 20 “Disputes”
An Overview: Sub-clause 20.8 (Con’t)
Sub-clause 20.8 – “Related Disputes” (continued)
• NOTE: Wording within the 2011 Subcontract Form - is notclear and contractors are best advised to tighten up theircontract language in respect to ensure that if theSubcontractor does not give a timely NOD, then it will be
bound by the Main Contract DAB decision,otherwise the Contractor could find itself bound by the MainContract DAB decision but still defending a Subcontractarbitration in relation to the same dispute (Double-jeopardy).
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
FIDIC’S SIMILARITIES WITH OTHER
“FORMS” REGARDING SUBCON’S.
• COLLATERAL WARRANTIES:
– Usually found in Joint Contracts Tribunal (JCT) contract
forms; Collateral warranties may be formed informally, eitherwith correspondence or even verbally;
– Represents a “separate, legally enforceable” contract from theobligations under the main contract.
– Collateral warranty exists…
“…where an employer insists upon the main contractor enteringinto a subcontract with a particular sub-contractor after thewarranty has been given by the sub-contractor to the
employer…”
– In this type of situation, the employer can sue the sub-
contractor or supplier for any loss caused by breach of
warranty.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
COLLATERAL WARRANTIES
• In practice - EMPLOYERS may require theSUBCONTRACTORS to provide a collateral warranty thatthe employer can rely upon to seek the subcontractor’sdirect liability for defective works.
• A COLLATERAL WARRANTY is enforceable under
the UAE law.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
COLLATERAL WARRANTIES
• It is deemed a unilateral act according to Article 276 ofthe Civil Transactions Code; thus, the subcontractor isbound by its terms according to Article 278 of the sameCode.
• A COLLATERAL WARRANTY typically contains provisionsfor the assignment and step-in rights to ensure that theemployer may assign the obligations set out in thewarranty to other beneficiaries such as subsequentowners or tenants.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
CASE STUDY – “ASSIGNMENT”
LINDEN GARDENS TRUST Ltd vs
LENESTA SLUDGE DISPOSALS LTD and others;
ST MARTIN'S PROPERTY CORPORATION LTD and another vs
SIR ROBERT MCALPINE LTD
HOUSE OF LORDS
(Lord Keith of Kinkel, Lord Bridge of Harwich,
Lord Griffiths, Lord Ackner and Lord Browne-Wilkinson)
22 July 1993.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
ASSIGNMENT –
UAE CASE STUDY
• IN THIS CASE - an assignment of contractual rights inbreach of a prohibition against such assignment wasineffective to vest the contractual rights in the assignee.
• A building owner who had parted with the property couldrecover substantial damages for breach of a buildingcontract.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
ASSIGNMENT –
UAE CASE STUDY
• In 1979, Stock Conversion and Investment Trust plcentered into a building contract with M & H under whichM & H was to remove asbestos from Stock's property.
• The contract was in the Joint Contract Tribunal StandardForm of Building Contract (1963 ed revised July 1975).
• Clause 17 prohibited assignment of the contract.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
ASSIGNMENT –
UAE CASE STUDY
• In 1985, when asbestos which should have been removedwas found on the premises and removed by anothercompany, Stock Conversion issued a writ.
• It disposed of its interest in the property in 1987 to LindenGardens. More asbestos was found and further removalwork undertaken. Linden Gardens claimed damagesagainst M & H.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
ASSIGNMENT –
UAE CASE STUDY
• A party to a building contract could have a genuinecommercial interest in seeking to ensure that he was incontractual relations only with a person whom he hadselected as the other party to the contract. There was nopolicy reason why a contractual prohibition onassignment of contractual rights should be contrary topublic policy.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
ASSIGNMENT –
UAE CASE STUDY
• The existing authorities established that an attemptedassignment of contractual rights in breach of a contractualprohibition was ineffective to transfer such contractualrights. The law was satisfactorily settled in that sense.
• It followed that the Linden Gardens claim failed and itsactions must be dismissed.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
ASSIGNMENT –
UAE CASE STUDY
• The existing authorities established that an attemptedassignment of contractual rights in breach of a contractualprohibition was ineffective to transfer such contractualrights. The law was satisfactorily settled in that sense.
• It followed that the Linden Gardens claim failed and itsactions must be dismissed.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
ASSIGNMENT –
UAE CASE STUDY
• It was submitted that although Corporation retained itsrights under the contract, it was only entitled to nominaldamages as it had suffered no loss and had parted withthe property at the date of the breach. However, thepresent case fell within the rationale of the exceptions tothe general rule that a plaintiff could only recoverdamages for his own loss.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
ASSIGNMENT –
UAE CASE STUDY
• The property, to the knowledge of both Corporation andMcAlpine, was going to be occupied by third parties. It couldbe foreseen that damage caused by a breach would cause lossto a later owner and not merely to the original contractingparty.
• It was proper to treat the parties as having entered thecontract on the footing that Corporation would be entitled toenforce contractual rights for the benefit of those whosuffered from defective performance but who could no acquireany right to hold McAlpine liable for breach.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
ASSIGNMENT –
UAE CASE STUDY
• In the prolonged period of recession in the property marketmany developments have had to be sold off beforecompletion, thereby producing the risk that the ownership ofthe property might have become divided from the right to sueon the building contract at a date before any breach occurred.The original building owner would not be entitled to recoverdamages for loss suffered by others who could themselves suefor such loss.
• Therefore, Corporation was entitled to substantial damages forany breach by McAlpine of the building contract.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
COLLATERAL WARRANTIES
• Regardless of if a collateral warranty is provided or not, according to Article 890(2) of the Civil Transactions Code, the main contractor remains liable to the
employer for the subcontractor’s
performance.
• In many cases, the UAE courts emphasized that “the
main contractor remains contractually liable
for the acts or defaults of the subcontractor
even if the subcontractor in reality
performed the employer’s instructions
during the course of the project”.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
COLLATERAL WARRANTIES –
UAE CASE STUDY
• In the well-known decision of the Dubai Court ofCassation in case No. 266 of 2008, the court held that:
“…when the subcontractor is selected by theemployer or its consultants, the employer shall beliable for any delay in the performance of thesubcontracted part and the main contractor shallnot be liable for any delay fines if they can provethat the delay is caused by such subcontractorand the main contractor played no part in thedelay…”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
COLLATERAL WARRANTIES –
UAE CASE STUDY
• The grounds of this decision have been debatable asthe court provided no specific criteria to disregard thegeneral rule set out in Article 890(2).
• Thus, this controversial decision is deemed anexception to the general rule that the maincontractor’s liability remains in place even so withnominated subcontractors.
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 1 of 30
CLAUSE 20 NOTICES, SUBCONTRACTOR CLAIMS AND DISPUTES
This Clause has been drafted to allow for resolution of Subcontract Disputes by a Subcontract DAB,
followed by arbitration of the Subcontract dispute if either Party is dissatisfied with the Subcontract
DAB’s decision and they have been unable to settle the Subcontract dispute amicably. This Clause is also
drafted so that, in circumstances where the Contractor is of the opinion that a Subcontract dispute
involves issues(s) that is/are the subject of a dispute under the Main Contract, either Party’s entitlement
to refer the Subcontract dispute to the Subcontractor DAB is deferred by a period of 112 days or as
otherwise agreed. This suspension period gives the Contractor time to pursue resolution of his dispute
by the Main Contract DAB under the Main Contract, and to attempt to settle the Subcontract dispute
with the Subcontractor, before the resolution procedure under the Subcontract is initiated for the
Subcontract dispute.
It takes account of 84 days for the Main Contract DAB’s decision plus 28 days for the serving of a notice
of dissatisfaction (if any) (making a total of 112 days), which periods are specified under Main Contract
Clause 20.4 [Obtaining Dispute Adjudication Board’s Decision]. It should be noted that, unless this
Clause is amended by Particular Conditions to expressly provide for such, the Subcontractor is not bound
by any decision of the Main Contractor DAB and/or any arbitral award under the Main Contract.
If it is preferred that the Subcontractor is to be bound by any decision of the Main Contract DAB and/or
any arbitral award under the Main Contract, consideration may be given to adopting the amendments as
set out in the Second Alternative below.
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 2 of 30
If the Parties choose to have arbitration of their dispute conducted in a language other than the ruling
language under the Subcontract, then this different language should be specified in the Particular
Conditions of the Subcontract.
SUB-CLAUSE 20.5 APPOINTMENT OF THE SUBCONTRACT DAB
At tender stage, consideration should be given as to the whether a one-person or a three-person
Subcontract DAB is preferable for the Subcontract, taking account of its size, complexity,
duration, and the fields of expertise which will be involved.
The adjudication procedure depends for its success on, amongst other things, the Parties’
confidence in the individuals who will serve on the Subcontract DAB. Therefore, it is essential
that candidates for this position are not imposed by either Party on the other Party.
Under this Sub-Clause, a Subcontract DAB is to be appointed if and when a Subcontract dispute
has arisen. The Subcontract DAB’s appointment terminates when its decision is given as to the
matter in dispute, unless other disputes have been referred to the Subcontract DAB by that time
in which event its appointment terminates when the Subcontract DAB has given its decisions on
those disputes.
Alternatively, due to the size, complexity and duration of the Subcontract, the Parties may prefer
to have the Subcontract DAB appointed at the commencement of the Subcontract, as a full-term
board to decide all disputes that arise under the Subcontract, in which case the wording of this
Sub-Clause should be amended to conform to the wording of Main Contract Clause 20.2
[Appointment of the Dispute Adjudication Board] and 20.3 [Failure to Agree Dispute
Adjudication Board].
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 3 of 30
Subcontracting On Construction Projects in the UAE
Sub-Clause 20.6 Obtaining Subcontract DAB’s Decision
The third paragraph of this Sub-Clause is intended to encourage the Parties to settle a
Subcontract dispute amicably, without the need for arbitration: for example, by direct
negotiation, conciliation, mediation, or other forms of dispute resolution. Amicable settlement
procedures often depend, for their success, on confidentiality and on the Parties’ acceptance of
the procedure. Therefore, neither Party should seek to impose the procedure on the other Party.
FIRST ALTERNATIVE If the size, complexity and duration of the Subcontract is such that
the Parties prefer a simpler dispute resolution process, involving
just arbitration, then:
EXAMPLE PROVISIONS FOR SUBCONTRACT ARBITRATION ONLY
Delete Sub-Clause 20.4 [Subcontract Disputes], Sub-Clause 20.5 [Appointment of the
Subcontract DAB], Sub-Clause 20.6 [Obtaining Subcontract DAB’s Decision] and Sub-Clause 20.7
[Subcontract Arbitration] of the General Conditions of Subcontract and substitute with Sub-
Clause 20.4 [Subcontract Disputes] as follows:
If a dispute (of any kind whatsoever) arises between the Contractor and the Subcontractor in
connection with, or arising out of, the Subcontract or the execution of the Subcontract Works,
then either Party may give a notice of the dispute to the other Party (the ‘Notice of Dispute’), in
which case the Parties shall attempt for the next 56 days to settle the dispute amicably before
the commencement of arbitration.
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 4 of 30
Any dispute which has not been amicably settled within 56 days after the date of the Notice of
Dispute shall be finally settled under the Rules of Arbitration of the International Chamber of
Commerce, even if no attempt at amicable settlement has been made, and the provisions of
Main Contract Clause 20.6 [Arbitration] shall apply to the Subcontract dispute except that the
dispute may be settled by one arbitrator appointed in accordance with the Rules.
If the Contractor is of the opinion that a dispute (of any kind whatsoever) between the
Contractor and the Employer in connection with or arising out of the Main Contract or the
execution of the Main Works touches or concerns the Subcontract Works, then the Contractor
may be notice require that the Subcontractor provide the information and attend the meetings
in connection with that dispute that the Contractor may reasonably request.
SECOND ALTERNATIVE If the Subcontract and the Main Contract are such that it is very
likely that the anticipated subject matters of Subcontract claims
and disputes are related to the anticipated subject matters of the
Contractor’s claims, Employer’s claims and/or disputes under the
Main Contract, the Parties may prefer that any Engineer’s
determination under the Main Contract may have a bearing on and
limit the Parties’ entitlements under the Subcontract and that any
decision and/or arbitral award under the Main Contract shall be
binding on the Parties under the Subcontract.
In the example, Clause 20 set out below as a second alternative, it
is essential to understand that a Subcontractor’s claim may arise
out of the Subcontract itself (Unrelated Claim) or out of an event
or events that may also give rise to additional payment and/or an
extension of time which is/are claimable under the Main Contract
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 5 of 30
or may concern the same issue(s) as a Contractor’s claim or a
dispute under the Main Contract (a Related Claim).
Both Parties should be acutely aware that, when the
Subcontractor serves a notice of claim, it will be
necessary at that time to establish whether the
Subcontractor’s claim is a Related Claim or an
Unrelated Claim.
Should a disagreement arise between the Contractor and the
Subcontractor as to whether a Subcontractor’s claim is an
Unrelated Claim or a Related Claim, the example Clause
20 below provides for a single fork-in-the-road
process to decide the issue by a pre-arbitral
referee in accordance with ICC Rules for Pre-
Arbitral Referee Procedure. Both the Contractor and the
Subcontractor should give serious consideration to agreeing the
name of the Referee at the time of entering into the Subcontract.
Also, the example Clause 20 set out below
includes provisions (under Sub-Clause 20.9)
where an Employer’s claim under the Main
Contract may arise from a matter for which the
Subcontractor is responsible under the
Subcontract, and where any determination,
decision and/or arbitral award concerning such
Employer’s claim under the Main Contract shall be
binding on the subcontractor under the
Subcontract.
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 6 of 30
Contractors and Subcontractors considering this
Second Alternative will note the length and complexity
of the clauses. This is necessary because of the
number of issues that need to be catered for,
beginning with the question of whether the
Subcontract disputes are or are not related to Main
Contract disputes. The following example
provisions are suggested by FIDIC on a trial basis
only, after which they will be re-evaluated. Feed-
back form users and all suggestions for
improvements would be welcomed. Users are
advised to consult an arbitration specialist before
using these alternative provisions in a
Subcontract to ensure that they will operate
successfully.
EXAMPLE PROVISIONS WHERE A DECISION AND/OR ARBITRAL AWARD
UNDER THE MAIN CONTRACT CONCERNING A SUBCONTRACT’S CLAIM
OR AN EMPLOYER’S CLAIM SHALL BE BINDING UNDER THE
SUBCONTRACT:
Delete Clause 20 [Notices, Subcontractor’s Claims and Disputes] of the General Conditions of
Subcontract and substitute:
20 NOTICES, CLAIMS AND DISPUTES
20.1 NOTICES
Without prejudice to the generality of Clause 4 [The Subcontractor], whenever the Contractor is
required by the Main Contract to give any notice or other information to the Engineer or to the
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 7 of 30
Employer, or to keep contemporary records (whether in relation to a claim or otherwise), to the
extent that these terms apply to the Subcontract Works, the Subcontractor shall give a similar
notice or other information in writing to the Contractor and keep contemporary records that will
enable the Contractor to comply with these terms of the Main Contract. The Subcontractor shall
do so in good time to enable the Contractor to comply with these terms. Provided always that
the Subcontractor shall be excused from any non-compliance with this requirement for so long as
he could not have reasonably known of the Contractor’s need of the notice or information form
him or the contemporary records.
Notwithstanding this Sub-Clause and Sub-Clause 3.3 [Contractor’s Claims in connection with the
Subcontract], each Party shall immediately give notice to the other Party of any delay event
which has occurred, or specific probable future events or circumstances, which may adversely
affect the other Party’s activities or delay the execution of the Subcontract Works and/or the
Main Works. The Subcontractor shall immediately give notice to the Contractor of any event
which has occurred, or specific probable future events or circumstances, which may increase the
Subcontract Price and/or the Contract Price.
If the Subcontractor considers himself to be entitled to any extension of the Subcontract Time for
Completion and/or any additional payment, under or in connection with the Subcontract, the
Subcontractor shall give notice to the Contractor describing the event or circumstance giving rise
to the claim, and settling out the contractual basis for the claim. Notice shall be given as soon as
practicable but in any case, not later than 21 days after Subcontractor became aware (or should
have become aware) of the event or circumstance. If the Subcontractor fails to give notice of a
claim within the period of 21 days referred to above, the Subcontract Time for Completion shall
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 8 of 30
not be extended, the Subcontractor shall not be entitled to additional payment, and the
Contractor shall be discharged from all liability in connection with the claim.
20.2 SUBCONTRACTOR’S CLAIMS
Within 7 days of receipt of the Subcontractor’s notice of claim in accordance with Sub-Clause
20.1 [Notices], the Contractor may notify the Subcontractor, with reasons, that the
Subcontractor’s claim:
(a) Arises from an event or events that may also give rise to additional payment and/or an
extension of time as may be claimable in accordance with the Main Contract;
(b) Concerns issue(s) which is/are the subject of a Contractor’s claim in accordance with Main
Contract Clause 20.1 [Contractor’s Claims]; or
(c) Involves issue(s) which is/are also involved in a dispute between the Contractor and the
Employer under the Main Contract;
Unless the Contractor so notifies the Subcontractor, the claim shall therefore be considered an
Unrelated Claim for the purposes of Sub-Clause 20.3 [Unrelated Claims]. If the Contractor does
so notify the Subcontractor the claim shall thereafter be considered a Related Claim for
the purposes of Sub-Clause 20.4 [Related Claims] and the Subcontractor shall have no right to
pursue this claim under Sub-Clause 20.3 [Unrelated Claims], save;
(a) Where it is decided by the pre-Arbitral Referee in accordance with this Sub-Clause that this
claim is an Unrelated Claim, or
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 9 of 30
(b) To the extent expressly provided for under Sub-Clause 20.4 [Related Claims].
Upon receipt of the Contractor’s notice, unless the Subcontractor raises a written objection to
the Contractor’s opinion that the claim is a Related Claim within 7 seven days, this opinion shall
be deemed to be accepted by the Subcontractor. If the Subcontractor raises an objection the
Contractor shall give all due consideration to this objection and shall give his written response,
with reasons, within 7 days of its receipt.
If the Subcontractor is dissatisfied with this response then, by notice in writing, he may refer the
question of whether the Subcontractor’s claim is a Related Claim or an Unrelated Claim to a pre-
arbitral referee for an order. Save where the provisions of this Sub-Clause require, the ICC Rules
for Pre-Arbitral Referee Procedures shall apply.
With reference to Article 2.1.1 of the ICC Rules for the Pre-Arbitral Referee Procedures, the
Referee’s sole power shall be to decide the question of whether the Subcontractor’s claim is a
Related Claim or an Unrelated Claim. The Referee shall issue his Order within 21 days from the
date on which he receives the file form the Secretariat (as defined in the ICC Rules for a Pre-
Arbitral Referee Procedures) and
(i) The costs arising out of the Pre-Arbitral Referee Procedure shall be borne in equal shares
by the Parties;
(ii) The Order of the Referee (who shall not be considered to be an arbitrator and whose
decision shall not be considered as an arbitral award) shall be binding on both Parties,
and Articles 6.3 and 6.4 of the ICC Rules for the Pre-Arbitral Referee Procedure shall not
apply;
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 10 of 30
Whether the Subcontractor’s claim is a Related Claim or an Unrelated Claim, the Subcontractor
shall keep contemporary records that may be necessary to substantiate the claim, shall comply
with any Contractor’s Instruction to keep further contemporary records, shall permit the
Contractor to inspect all these records, and shall (if instructed) submit copies to the Contractor.
Unless the Subcontract has already been abandoned, repudiated or terminated, the
Subcontractor shall continue to proceed with the Subcontract Works in accordance with the
Subcontract.
20.3 UNRELATED CLAIMS
If a Subcontractor’s claims is an Unrelated Claim in accordance with Sub-Clause 20.2
[Subcontractor’s Claims]:
(1) Within 42 days after the Subcontractor become aware (or should have become aware) of the
event or circumstance giving rise to the Unrelated Claim, or within such other period as may
be proposed by the Subcontractor and/or approved by the Contractor, the Subcontractor
shall send to the Contractor a fully detailed claim which includes full supporting particulars of
the basis of the claim of the claim and of the additional payment and/or extension of time
claimed;
(2) If the event or circumstance giving rise to the Unrelated Claim has a continuing effect:
(a) This fully detailed claim shall be considered as interim;
(b) The Subcontractor shall send further interim claims at monthly intervals, giving the
accumulated delay and/or amount claimed, and the further particulars that the
Contractor may reasonably require, and
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 11 of 30
(c) The Subcontractor shall send a final claim within 28 days after the end of the effects
resulting from the event or circumstances, or within the other period that may be
proposed by the Subcontractor and approved by the Contractor;
(3) Within 42 days after receiving a claim or any further particulars supporting a previous claim,
or within the other period that may be proposed by the Contractor and approved by the
Subcontractor, the Contractor shall respond with approval or disapproval and detailed
comments. He may also request any necessary further particulars, but shall nevertheless give
his response on the issue of the Subcontractor’s entitlement to the Unrelated Claim within
this time;
(4) The Contractor shall consult with the Subcontractor in an endeavor to reach agreement on
the additional payment and/or extension of the Subcontract Time of Completion to which the
Subcontractor may be entitled for this Unrelated Claim. If agreement is not reached, the
Contractor shall make a fair decision as to the appropriate and applicable additional payment
(if any) and/or extension of the Subcontract Time for Completion (if any), taking due account
of the Subcontractor’s submissions, the extent to which his claim for additional payment
and/or extension of time has been substantiated, and all other relevant circumstances; and
(5) The Contractor shall make the additional payment (if any) and /or grant the extension of the
Subcontract Time for Completion (if any) to the Subcontractor that he has decided is
appropriate and applicable. Unless and until the particulars supplied for the Unrelated Claim
are sufficient to substantiate the whole of this claim, the Subcontractor shall be entitled to
additional payment and/or extension of time only for the part that has been substantiated.
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 12 of 30
20.4 RELATED CLAIMS
If a Subcontractor’s claim is a Related Claim in accordance with Sub-Clause 20.2 [Subcontractor’s
Claims]:
(1) The Contractor shall submit a notice of claim, including the subject of the claim which the
Contractor considers to be a Related Claim, to the Engineer in accordance with Main
Contract Clause 20.1 [Contractor’s Claim] and in good time to ensure compliance with such
provision, regardless of any objection or referral by the Subcontractor under Sub-Clause 20.2
[Subcontractor’s Claims].
(2) The Contractor shall use all reasonable endeavors to secure from the Employer and the
Engineer, for both the Contractor’s and the Subcontractor’s benefit, any additional payment
and/or extension of time as may be claimable in accordance with the Main Contractor in
respect of the Subcontract Works and shall regularly keep the Subcontractor informed of the
progress of these endeavor’s;
(3) The Subcontractor shall have no right to pursue this claim under Sub-Clause 20.3 [Unrelated
Claims] save as expressly provided under this Sub-Clause 20.4. The Subcontractor shall
comply with any Contractor’s Instruction regarding the keeping of contemporary records
relevant to the event or circumstance giving rise to the Related Claim. The Subcontractor
shall permit the Contractor and the Engineer to inspect all these reports.
(4) The Subcontractor shall submit the Related Claim to the Contractor, which shall include full
supporting particulars of:
(a) The contractual or other basis of claim, and
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 13 of 30
(b) Additional payment claimed, and/or
(c) The extension of time
And any interim claims in accordance with Main Contract Clause 20.1 [Contractor’s Claims]
and in good time to enable the Contractor to comply with such provision;
(5) The Contractor shall submit a claim to the Engineer, which includes the supporting particulars
and any interim claims of the Related Claim provided by the Subcontractor, in accordance
with Main Contract Clause 20.1 [Contractor’s Claim] and in good time to ensure compliance
with such provision, regardless of any objection or referral by the Subcontractor under Sub-
Clause 20.2 [Subcontractor’s Claims];
(6) The Contractor shall give the Subcontractor all reasonable opportunity to be involved in any
consultation with, and to attend any meeting convened by, the Engineer which concerns the
Related Claim. Unless the Subcontractor is permitted by the Engineer to be involved in
consultation and/or to attend a meeting but the Subcontractor refuses or fails to do so, the
Contractor shall not reach any agreement with the Engineer concerning the Related Claim
without prior consultation with the Subcontractor. Where an agreement is reached under
the Main Contract or the Engineer makes a determination concerning the Related Claim, the
Contractor shall as soon as practicable but not later than 7 days of its receipt, notify the
Subcontractor of this agreement or determination. If the agreement or determination
insofar as it concerns the Related Claim is such that the Contractor has no entitlement to
additional payment and/or extension of time, unless the Subcontractor notifies the
Contractor of dissatisfaction with the agreement or determination within 7 days of his receipt
of the Contractor’s notice, this agreement or determination shall be deemed to be accepted
by the Subcontractor and as between them, shall be binding on the Parties. If the
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 14 of 30
Subcontractor notifies his dissatisfaction with the agreement or determination within 7 days
of his receipt of Contractor’s notice, the Subcontractor’s notice shall be deemed to be a
Notice of Dispute and Sub-Clause 20.6 [Subcontract Disputes] shall apply.
(7) If it is agreed under the Main Contract or the Engineer determines under the Main Contract
that the Contractor is entitled to additional payment and/or extension of time, within 28 days
of receiving this contractual benefit from the Employer, the Contractor shall pass on to the
Subcontractor a share of the benefit as may be appropriate and applicable to the Related
Claim. In the case of a Related Claim concerning additional payment, the receipt of payment
by the Contractor from the Employer that includes a sum in respect of the claimed amount
shall be a condition precedent to the Contractor’s liability to the Subcontractor in respect of
this share. The Contractor shall consult with the Subcontractor in an endeavor to reach
agreement as to this share. If agreement is not reached, the Contractor shall promptly and
with due diligence make a fair decision as to the appropriate and applicable share, taking due
account of the Subcontractor’s views and all other relevant circumstances. The Contractor
shall, making reference to this sub-paragraph, give notice to the Subcontractor of his decision
with reasons and supporting particulars. Unless the Subcontractor notifies the Contractor of
his dissatisfaction with this decision within 28 days of receipt of the Contractor’s notice, the
share decided by the Contractor shall be taken as accepted by the Subcontractor in full and
final settlement of the Related Claim; and
(8) If the Subcontractor notifies the Contractor of his dissatisfaction with this decided share
within 28 days of receipt of the Contractor’s notice, the Contractor shall give all due
consideration to this dissatisfaction and shall give his written response within 7 days of its
receipt. If the Contractor fails to so respond to the Subcontractor’s notice of dissatisfaction,
the Subcontractor shall be entitled to treat this non-response as if the Contractor maintains
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 15 of 30
that the decided share is appropriate and applicable. Any dispute concerning this share shall
thereafter be considered an Unrelated Dispute which shall be finally settled as between the
Parties under the Rules of Arbitration of the International Chamber of Commerce, and Main
Contract Clause 20.6 [Arbitration] shall apply to Unrelated Dispute except that the dispute
may be settled by one arbitrator appointed in accordance with the Rules.
20.5 FAILURE TO COMPLY
If, by reason of any failure by the Subcontractor to comply with the first and third paragraphs of
Sub-Clause 20.1 [Notices] and/or the provisions of Sub-Clause 20.2 [Subcontractor’s Claims],
the Contractor is prevented from recovering any sum other than in respect of Subcontractor’
claims form the Employer under the Main Contract in respect of the Subcontract Works, then
without prejudice to any other remedy of the Contractor for this failure of the Contractor shall,
subject to Sub-Clause 3.3 [Contractor’s Claims in connection with the Subcontract], be entitled
to deduct this sum from the Subcontract Price.
20.6 SUBCONTRACT DISPUTES
If a dispute (of any kind whatsoever) arises between the Parties in connection with, or arising out
of, the Subcontract or the execution of the Subcontract Works, then either Party may give a
notice of the dispute to the other Party the “Notice of Dispute”.
If the Subcontract dispute arises from an Unrelated Claim (as referred to in Sub-Clause 20.2
[Subcontractor’s Claims]), then it shall be considered to be an ‘Unrelated Dispute’ and Sub-
Clause 20.7 [Unrelated Dispute] shall apply.
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 16 of 30
If the Subcontract dispute arises from a Related Claim (as referred to in Sub-Clause
20.2[Subcontractor’s Claims]), then it shall be considered to be an ‘Related Dispute’ and Sub-
Clause 20.8 [Unrelated Disputes] shall apply.
If the Subcontract dispute DOES NOT ARISE out of an Unrelated Claim or a Related
Claim:
(a) “within 14 days” of receiving or giving opinion that the Subcontract dispute involves issue(s)
which are also involved in a dispute between the Contractor and the Employer under the
Main Contract. If the Contractor so notifies the Subcontractor within such period of 14 days
then, subject to sub-paragraphs (b) and (c) of this Sub-Clause, the Subcontract dispute shall
be considered to be a ‘Related Dispute’ and Sub-Clause 20.8 [Related Disputes] shall apply.
If the Contractor does not so notify the Subcontractor within such period of 14 days, then the
Subcontract dispute shall be considered to be an ‘Unrelated Dispute’ and Sub-Clause 20.7
[Unrelated Disputes] shall apply;
(b) “upon receipt” of the Contractor’s notice, unless the Subcontractor raises a written objection,
to the Contractor’s opinion that the Subcontract dispute is a Related Dispute within 7 days,
this opinion shall be deemed to be accepted by the Subcontractor. If the Subcontractor
raises an objection the Contractor shall give all due consideration to this objection and shall
give his written response, with reasons, within 7 days of its receipt; and
(c) If the Subcontractor is dissatisfied with this response then, by notice in writing, he may refer
the question of whether the Subcontractor dispute is a Related Dispute or an Unrelated
Dispute to a pre-arbitral referee for an order. Save where the provisions of this sub-
paragraph require, the ICC Rules for a Pre-Arbitral Referee Procedure shall apply. With
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 17 of 30
reference to Article 2.1.1 of the ICC Rules for a Pre-Arbitral Referee Procedure, the Referee’s
Dispute or an Unrelated Dispute. The Referee shall issue his order within21 days from the
date on which he receives the file from the Secretariat (as defined in the ICC Rules for a Pre-
Arbitral Referee Procedure) and:
(i) the costs arising out of the Pre-Arbitral Referee Procedure shall be borne in equal
shares by the Parties; and
(ii) the Order of the Referee (who shall not be considered to be an arbitrator and whose
decision shall not be considered as an arbitral award) shall be final and binding on
both Parties, and Articles 6.3 and 6.4 of the Rules for a Pre-Arbitral Referee
Procedure shall not apply.
Whether the Subcontract dispute is an Unrelated Dispute or a Related Dispute, unless the
Subcontract has already been abandoned, repudiated or terminated, the Subcontractor shall
continue to proceed with the Subcontract Works in accordance with the Subcontract.
20.7 UNRELATED DISPUTES
If the Subcontract dispute is an Unrelated Dispute:
(1) It shall be decided by a Subcontract DAB, which shall be jointly appointed by the Parties
within 42 days after the date of the Notice of Dispute or any other time as may be agreed in
writing. Unless it is stated in the Appendix to the Subcontractor’s Offer that is shall
compromise three members, the SUBCONTRACT DAB SHALL COMPRISE ONE
SUITABLY QUALIFIED PERSON. In all respects, other than as stated in this Sub-Clause,
Main Contract Clause 20.2 [Appointment of Disputes Adjudication Board] shall apply to the
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 18 of 30
appointment of the Subcontract DAB, save that Rules 1 to 4 of the Procedural Rules annexed
to the General Conditions of Dispute Adjudication Agreement shall not apply;
(2) If the Parties fail to agree upon the appointment of the Subcontract DAB within 42 days after
the date of the Notice of Dispute, or upon the appointment of a replacement person within
42 days after the appointed person appointed by the President shall, upon the request of
either or both Parties and after due consultation with both Parties, appoint the Subcontract
DAB. The appointment shall be final and conclusive. Each Party shall be responsible for
paying one-half of the remuneration of the appointing official;
(3) Either Party may refer the Unrelated Dispute in writing to the Subcontract DAB for its
decision, with a copy to the other Party. The referral shall state that it is given under this
Sub-Clause. In all respects, other than as stated in this Sub-Clause, Main Contract Clause
20.4 [Obtaining Dispute Adjudication Board’s Decision] shall apply to the resolution of the
Unrelated Dispute, save that Main Contract Clause 20.8 [Expiry of Dispute Adjudication
Board’s Appointment] SHALL NOT APPLY;
(4) The Subcontract DAB’s decision shall be binding on both Parties unless and until it shall be
revised in an amicable settlement or an arbitral award, as described in this Sub-Clause below;
(5) If either Party serves a notice of dissatisfaction with the Subcontract DAB’s decision within 28
days after receiving the Subcontract DAB’s decision, both Parties shall attempt to settle the
Unrelated Dispute amicably before the commencement of arbitration. However, unless both
Parties agree otherwise, arbitration may be commenced on the twenty-eighth (28th) day
after notice of dissatisfaction was given, even if no attempt at amicable settlement has
been made;
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 19 of 30
(6) Unless settled amicably, any Unrelated Dispute in respect of which the Subcontract DAB’s
decision has not become final and binding in accordance with Main Contract Clause 20.4
[Obtaining Dispute Adjudication Board’s Decision] shall be finally settled under the Rules of
Arbitration of the International Chamber of Commerce and Main Contract Clause 20.6
[Arbitration] shall apply to the Unrelated Dispute except that the dispute may be settled by
One Arbitrator Appointed in accordance with the Rules;
(7) In the event that a Party fails to comply with any decision of the Subcontract DAB whether
binding, or final and binding in accordance with Main Contract Clause 20.4 [Obtaining
Dispute Adjudication Board’s Decision], then the other Party may, without prejudice to any
other rights it may have, refer the failure itself to arbitration under the Rules of Arbitration of
the International Chamber of Commerce for the purpose of obtaining an award (whether
interim or other) to enforce the Decision, and in all other respects Main Contract Clause 20.6
[Arbitration] shall apply to the obtaining of such an award except that the award may be
rendered by One Arbitrator Appointed in accordance with the Rules. There shall be no
requirement to obtain a Subcontract DAB’s decision or to attempt to reach amicable
settlement in respect of this reference.
20.8 RELATED DISPUTES
If a Subcontract dispute is a Related Dispute:
(1) The subject of the Related Dispute shall be referred by the Contractor to the Main Contract
DAB in accordance with Main Contract Clause 20.4 [Obtaining Dispute Adjudication Board’s
Decision], with a copy to the Subcontractor, within 28 days of the Notice of Dispute. If, on
the date of the Notice of Dispute there is no Main Contract DAB in place, the Contractor shall
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 20 of 30
refer the subject of the Related Dispute to the Main Contract DAB in accordance with the
Main Contract Clause 20.4 [Obtaining Dispute Adjudication Board’s Decision], with a copy
to the Subcontractor, within 56 days of the Notice of Dispute. If the Contractor fails to refer
the subject of the Related Dispute to the Main Contract DAB within the period of 28 days or
56 days, whichever is applicable, the Subcontractor dispute shall thereafter be considered an
Unrelated Dispute and Sub-Clause 20.7 [Unrelated Disputes] shall apply;
(2) Where the subject of the Related Dispute is referred to the Main Contract DAB, the
Contractor shall use reasonable endeavors to pursue the dispute on the Contractor’s and the
Subcontractor’s behalf and for both the Contractor’s and the Subcontractor’s benefit, and
shall regularly keep the Subcontractor informed of the progress of these endeavors;
(3) The Subcontractor shall, in good time, afford the Contractor all information and assistance
that may be required to enable the Contractor to diligently pursue his dispute which includes
the subject of the Related Dispute on the Contractor’s and the Subcontractor’s behalf;
(4) If the Main Contract DAB proposes a period other than 84 days for giving its decision in
respect of the subject of the Related Dispute, in accordance with Main Contract Clause 20.4
[Obtaining Dispute Adjudication Board’s Decision], then the Contractor shall not give its
approval to another period without prior consultation with the Subcontractor;
(5) In any adjudication under the Main Contract with concerns the subject of the Related
Dispute, unless the Employer or the Main Contract DAB objects, the Contractor shall give the
Subcontractor all reasonable opportunity to:
(a) be involved in the preparation of any written submission to the Main Contract DAB;
(b) attend any site visit or hearing convened by the Main Contract DAB;
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 21 of 30
(c) Make any oral submission to the Main Contract DAB;
(d) Receive copies of all submissions and other documents submitted in the adjudication
which concern or relate to the Related Dispute, and
(e) Be involved in any discussions about the general strategy to be adopted in the
adjudication which concern or relate to the Related Dispute including, but not limited to,
choice of legal representation (if any), experts (if any) and witnesses.
If the Subcontractor is given such opportunity by the Employer or the Main Contract DAB, the
Contractor shall not reach any settlement with the Employer concerning the Related Dispute
without prior consultation with the Subcontractor;
(6) Where the Main Contract DAB gives a decision, which concerns the Related Dispute, the
Contractor shall as soon as practicable but not later than 7 days of its receipt from the Main
Contract DAB, notify the Subcontractor of this decision;
(7) Unless the Subcontractor notifies the Contractor of his dissatisfaction with the Main Contract
DAB’s decision within 7 days of the receipt of the Contractor’s notice, this decision shall be
deemed to be accepted by the Subcontractor insofar as it concerns the Related Dispute.
Whether or not a notice of dissatisfaction has been given, this decision shall be binding on
both Parties unless and until it shall be revised in an amicable settlement or an arbitral award
as described below;
(8) If the Subcontractor so notifies the Contractor of his dissatisfaction and the Contractor
responds by concurring with this dissatisfaction, the Contractor shall serve a notice of
dissatisfaction with the Main Contract DAB’s decision to the Employer in good time to
prevent the Main Contract DAB’s decision from becoming final and binding under Main
Contract Clause 20.4 [Obtaining Dispute Adjudication Board’s Decision];
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 22 of 30
(9) If the Subcontractor so notifies the Contractor of his dissatisfaction but the Contractor
responds by concurring with this dissatisfaction, or fails to respond to this notice of
dissatisfaction within 7 days of its receipt or fails to serve a notice of dissatisfaction with the
Main Contract DAB’s decision to the Employer in good time to prevent the Main Contract
DAB’s decision from becoming final and binding under Main Contract Clause 20.4 [Obtaining
Dispute Adjudication Board’s Decision], the Subcontract dispute shall thereafter be
considered an Unrelated Dispute and Sub-Clause 20.7 [Unrelated Dispute] shall apply;
(10) If the Main Contract DAB’s decision entitles the Contractor to any contractual benefit, the
Contract shall use all reasonable endeavors on the Contractor’s and the Subcontractor’s
behalf to obtain this contractual benefit, and shall regularly keep the Subcontractor informed
of the progress of these endeavors. Within 14 days of receiving this contractual benefit from
the Employer the Contractor shall pass on to the Subcontractor a share of the benefit as may
be appropriate and applicable to the Related Dispute. In the case of a Related Dispute
concerning additional payment, the Contractor’s receipt of payment from the Employer
which includes a sum in respect of the disputed amount shall be a condition precedent to the
Contractor’s liability to the Subcontractor in respect of this share. The Contractor shall
consult with the Subcontractor in an endeavor to reach agreement as to this share. If
agreement is not reached, the Contractor shall promptly and with due diligence make a fair
decision as to the appropriate and applicable share, taking due account of the
Subcontractor’s submissions concerning the Related Dispute and all other relevant
circumstance. The Contractor shall, making reference to this sub-paragraph, give notice to
the Subcontractor of his decision with reasons and supporting particulars. Unless the
Subcontractor notifies the Contractor of his dissatisfaction with this decision within 28 days
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 23 of 30
of receipt of the Contractor’s notice, the share decided by the Contractor shall be taken as
accepted by the Subcontractor in full and final settlement of the Related Dispute;
(11) If the Subcontractor notifies the Contractor of his dissatisfaction with this decided share
within 28 days of receipt of the Contractor’s notice, the Contractor shall give all due
consideration to this dissatisfaction and shall give his written response within 7 days of its
receipt. If the Contractor fails to so respond to the Subcontractor’s notice of dissatisfaction
within 7 days of its receipt, the Subcontractor shall be entitled to treat this non-response as if
the Contractor maintains that the decided share is appropriate and applicable. Any dispute
concerning this share shall thereafter be considered an Unrelated Dispute which shall be
finally settled as between the Contractor and the Subcontractor under the Rules of
Arbitration of the International Chamber of Commerce, and Main Contract Clause 20.6
[Arbitration] shall apply to the Unrelated Dispute except that the dispute may be settled by
one arbitrator appointed in accordance with the Rules;
(12) If the Main Contract DAB’s decision has not become final and binding under the Main
Contract, unless the Employer objects, the Contractor shall give the Subcontractor all
reasonable opportunity to be involved in the attempts, if any, to settle the Related Dispute
amicably under the Main Contract before the commencement of arbitration. If the
Subcontractor is not given such opportunity by the Employer, the Contractor shall not reach
any amicable settlement with the Employer concerning the Related Dispute without prior
consultation with the Subcontractor;
(13) If the Contractor shall reach such an amicable settlement with the Employer, he shall
immediately notify the Subcontractor. Within 28 days of the date of this settlement, the
Contractor shall consult with the Subcontractor in an endeavor to reach agreement as to the
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 24 of 30
Subcontractor’s entitlement to contractual benefit in connection with the Related Dispute. If
no agreement is reached with 56 days of the date of the settlement, the Parties’
disagreement shall thereafter be considered an Unrelated Dispute which shall be finally
settled as between the Contractor and Subcontractor under the Rules of Arbitration of the
International Chamber of Commerce, and Main Contract Clause 20.6 [Arbitration] shall apply
to the Unrelated Dispute except that the dispute may be settled by one arbitrator appointed
in accordance with the Rules;
(14) If no amicable settlement is reached between the Contractor and the Employer under the
Main Contract concerning the subject of the Related Dispute, the Contractor shall refer the
Related Dispute to arbitration under Main Contract Clause 20.6 [Arbitration]. If the
Contractor or the Employer does not refer the subject of the Related Dispute to arbitration
within 63 days, or any other time as may be agreed, after the day on which either the
Contractor or the Employer has served a notice of dissatisfaction with Main Contract DAB’s
decision, the dispute shall thereafter be considered an Unrelated Dispute which shall be
finally settled as between the Contractor and the Subcontractor under the Rules of
Arbitration of the International Chamber of Commerce, and Main Contract Clause 20.6
[Arbitration] shall apply to this dispute except that the dispute may be settled by one
arbitrator appointed in accordance with the Rules;
(15) In any arbitration under the Main Contract with concerns the Related Dispute, the Contractor
shall use all reasonable endeavors to purse his dispute which includes the subject of the
Related Dispute on the Contractor’s and Subcontractor’s behalf and for both the Contractor’s
and Subcontractor’s benefit, and shall regularly keep the Subcontractor informed of the
progress of these endeavors. Unless the Employer or the Arbitral Tribunal objects, the
Contractor shall give the Subcontractor all reasonable opportunity to:
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 25 of 30
(a) Be involved in the preparation of any written submission to the Arbitral Tribunal;
(b) Attend any site visit or hearing convened by the Arbitral Tribunal;
(c) Make any oral submission to the Arbitral Tribunal;
(d) Receive copies of all submissions and other documents submitted in the arbitration
which concern or relate to the Related Dispute, and
(e) Be involved in any discussions about the general strategy to be adopted in the
arbitration which concern or relate to the Related Dispute, including but not limited to
choice of legal representation, experts and witnesses.
If the Subcontractor is not given such opportunity by the Employer or the Arbitral Tribunal,
the Contractor shall not reach any settlement with the Employer concerning the Related
Dispute without prior consultation with the Subcontractor;
(16) Where the Arbitral Tribunal makes an award, which concerns the Related Dispute, the
Contractor shall as soon as practicable but not later than 7 days of its receipt, notify the
Subcontractor of this award. Insofar as it concerns the Related Dispute, this award shall be
deemed to be binding on the Subcontractor to the same extent as it is binding on the
Contractor;
(17) If the Arbitral Tribunal’s award entitles the Contractor to any contractual benefit, the
Contractor shall use all reasonable endeavors on the Contractor’s and the Subcontractor’s
behalf to obtain this contractual benefit, and shall regularly keep the Subcontractor informed
of the progress of these endeavors. Within 14 days of receiving this contractual benefit from
the Employer the Contractor shall pass on to the Subcontractor a share of the benefit as may
be appropriate and applicable to the Related Dispute. In the case of a Related Dispute
concerning additional payment, the Contractor’s receipt of payment form the Employer
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 26 of 30
which includes a sum in respect of the disputed amount shall be a condition precedent to the
Contractor’s liability to the Subcontractor in respect of this share. The Contractor shall
consult with the Subcontractor in an endeavor to reach agreement as to this share. If
agreement is not reached, the Contractor shall promptly and with due diligence make a fair
decision as to the appropriate and applicable share, taking due account of the
Subcontractor’s submissions concerning the Related Dispute and all other relevant
circumstances. The Contractor shall give notice to the Subcontractor of his decision with
reasons and supporting particulars. Unless the Subcontractor notifies the Contractor of is
dissatisfaction with this decision within 28 days of receipt of the Contractor’s notice, the
share decided by the Contractor shall be taken as accepted by the Subcontractor in full and
final settlement of the Related Dispute;
(18) If the Subcontractor notifies the Contractor of his dissatisfaction with this decided share
within 28 days of receipt of the Contractor’s notice, the Contractor shall give all due
consideration to this dissatisfaction and shall give his written response within 7 days of its
receipt. If the Contractor fails to so respond to the Subcontractor’s notice of dissatisfaction
within 7 days of its receipt, the Subcontractor shall be entitled to treat this non-response as if
the Contractor maintains that the decided share is appropriate and applicable. The dispute
concerning this share shall thereafter be considered an Unrelated Dispute which shall be
finally settled as between the Contractor and the Subcontractor under Rules of Arbitration of
the International Chamber of Commerce, and Main Contract Clause 20.6 [Arbitration] shall
apply to this dispute except that the dispute may be settled by one arbitrator appointed in
accordance with the Rules.
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 27 of 30
20.9 EMPLOYER’S CLAIMS UNDER THE SUBCONTRACT
If the Contractor notifies the Subcontractor that the Employer or the Engineer has given notice of
claim under Main Contract Clause 2.5 [Employer’s Claims] and that the subject of such a claim
concerns the Subcontractor’s performance of the Subcontract:
(1) The Contractor shall provide a copy of this notice, and of all particulars given by the Employer
or the Engineer in connection with the Employer’s claim, to the Subcontractor;
(2) The Subcontractor shall comply with any Contractor’s Instruction regarding the keeping of
contemporary records relevant to the event or circumstances giving rise to the Employer’s
claim. The Subcontractor shall permit the Contractor and the Engineer to inspect these
records;
(3) The Contractor shall use all reasonable endeavors to defend against the Employer’s claim on
the Contractor’s and Subcontractor’s behalf, and shall regularly keep the Subcontractor
informed of the progress of these endeavors:
(4) The Subcontractor shall, in good time, afford the Contractor all information and assistance
that may be required to enable the Contractor to diligently defend the Employer’s claim on
the Contractor’s and Subcontractor’s behalf;
(5) The Contractor shall give the Subcontractor all reasonable opportunity to be involved in any
consultation with, and to attend any meeting convened by, the Engineer which concerns the
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 28 of 30
Employer’s claim. Unless the Subcontractor is permitted by the Engineer to be involved in
consultation and/or to attend a meeting but the Subcontractor refuses or fails to do so, the
Contractor shall not reach any agreement with the Engineer and/or the Employer concerning
the Employer’s claim without prior consultation with the Subcontractor;
(6) If it is agreed under the Main Contract, or the Engineer determines under the Main Contract,
that the Employer is entitled to be paid an amount by the Contractor, the Contractor shall
consult with the Subcontractor in an endeavor to reach agreement as to the share of such
amount that shall be paid by the Subcontractor to the Contractor. Receipt by the
Subcontractor of evidence of the amount paid by the Contractor to the Employer in respect
of the Employer’s claim shall be a condition precedent to the Subcontractor’s liability to the
Contractor in respect of this share;
(7) If agreement is not reached as to the share referred to in sub-paragraph (6) above, the
Contractor shall promptly and with due diligence make a fair decision as to the appropriate
and applicable share, taking due account of the Subcontractor’s views and all relevant
circumstances. The Contractor shall, making reference to this sub-paragraph, give notice to
the Subcontractor of his decision with reasons and supporting particulars. Unless the
Subcontractor notifies the Contractor of his dissatisfaction with this decision within 28 days
of receipt of the Contractor’s notice, the share decided by the Contractor shall be taken as
accepted by the Subcontractor;
(8) If the Subcontractor notifies the Contractor of his dissatisfaction with this decided share
within 28 days of the Contractors notice, the Contractor shall give all due consideration to
this dissatisfaction and shall give his written response within 7 days of its receipt. If the
Contractor fails to so respond to the Subcontractor’s notice of dissatisfaction, the
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 29 of 30
Subcontractor shall be entitled to treat this non-response as if the Contractor maintains that
the decided share is appropriate and applicable.
(9) If a dispute between the Employer and the Contractor arises from the Employer’s claim and is
referred to the Main Contract DAB under Main Contract Clause 20.4 [Obtaining Dispute
Adjudication Board’s Decision], the Contractor shall provide to the Subcontractor a copy of
the reference to the Main Contract DA, and of all additional information provided to the
Main Contract DAB;
(10) Sub-paragraphs (2) to (17) of Sub-Clause 20.8 [Related Disputes] shall apply to the dispute
and;
(i) Any reference to “the Related Dispute” shall be read as a reference to this dispute;
(ii) Sub-paragraph (10) of Sub-Clause 20.8 [Related Disputes] shall be amended to read:
“…If the Main Contract DAB’s decision required the Contractor to make payment to the Employer,
and the Contractor makes such payment, the Contractor shall consult with the Subcontractor in an
endeavor to reach agreement as to the share of such payment to be paid by the Subcontractor to
the Contractor. Receipt by the Subcontractor of evidence of such payment by the Contractor to the
Employer shall be a condition precedent to the Subcontractors liability to the Contractor in respect
of this share. If agreement is not reached, the Contractor shall promptly and with due diligence
make a fair decision as to the appropriate and applicable share, takin due account of the
Subcontractor’s submissions concerning this dispute and all relevant circumstances. The
Contractor shall, making reference to this sub-paragraph, give notice to the Subcontractor of his
Conditions of Subcontract for Construction, First Edition 2011
“GUIDANCE FOR THE PREPARATION OF PARTICULAR CONDITIONS OF
SUBCONTRACT”
For Building and Engineering Works Designed by The Employer
Page 30 of 30
decision with reasons and supporting particulars. Unless the Subcontractor notifies the Contractor
of his dissatisfaction with this decision within 28 days of receipt of the Contractor’s notice the
share decided by the Contractor shall be taken as accepted by the Subcontractor and the
Subcontractor shall immediately make payment of such share to the Contractor…”;
(iii) Sub-paragraph (13) of Sub-Clause 20.8 [Related Disputes] shall be deleted; and
(iv) Sub-paragraph (17) of Sub-Clause 20.8 [Related Disputes] shall be amended to read:
“…If the Arbitral Tribunal’s award requires the Contractor to make a payment to the Employer, and
the Contractor makes such payment, the Contractor shall consult with the Subcontractor in an
endeavor to reach agreement as to the share of such payment to be paid by the Subcontractor to
the Contractor. Receipt by the Subcontractor of evidence of such payment by the Contractor to the
Employer shall be a condition precedent to the Subcontractor’s liability to the Contractor is respect
of this share. If agreement is not reached the Contractor shall promptly and with due account of
the Subcontractor’s submissions concerning this dispute and all relevant circumstances. The
Contractor shall, making reference to this sub-paragraph, give notice to the Subcontractor of his
decision with reasons and supporting particulars. Unless the Subcontractor notifies the Contractor
of his dissatisfaction with this decision within 28 days of receipt of the Contractor’s notice the
share decided by the Contractor shall be taken as accepted by the Subcontractor and the
Subcontractor shall immediately make payment of such share to the Contractor…”.
Page 1 of 16
Proposals for a Subcontractor’s
Escape from a Conditional Clause
Published: June 2015
Publication: CONSTRUCTION LAW INTERNATIONAL Volume 10 Issue 2 June 2015
Title: Proposals for a subcontractor’s escape from a conditional clause
Practice: Construction
Authors: Antonios Dimitracopoulos
The common practice is that the main contractor (MC) will
contractually delegate various elements of its works to specialist
subcontractors. Such subcontractors (SC) may be sourced and
chosen by the main contractor or may be specifically nominated by
the employer. The UAE Civil Code1 at Article 8902 expressly
provides for the right of the main contractor to
subcontract, provided there are no contractual terms
preventing this in the main contract. Therefore, main
contractors are potentially exposed to making payments to their
subcontractors when they have not themselves received the
corresponding payments from the employer. Main contractors,
therefore, often include conditional payment clauses in
subcontracts so as to confer payment related risks onto the
subcontractor.
Page 2 of 16
Types of Conditional Clauses
Conditional clauses can be broadly divided into two (2) categories,
namely ‘pay when paid’ and ’pay if paid’ clauses.
Pay-When-Paid (PWP) clauses generally contain a condition
such that payment by the main contractor to the subcontractor will
be dependent upon payment being first received by the main
contractor from the employer.
The main purpose of a pay when paid clause is to defer payment to a point
in time that is determined by a specific event, namely payment by the employer to
the contractor.
The occurrence of Pay-If-Paid (PIP) clauses in the UAE is
relatively uncommon. In general, whenever pay if paid clauses are
included in subcontracts internationally, they may amount to specific
wording that aims to clarify that a shift of the risk of non-payment has
been agreed to*.
Instances of pay if paid clauses, identified in primarily US cases, can
be particularly focused in clearly and aggressively reflecting the parties’ intentions.
As indicated above, the intention of pay if paid clauses depend on the
eventuality rather than on deferring the timing of payment and to shift the risk
of non-payment from the main contractor to the subcontractor.
*Term known in Western Countries as “Working at Risk”
Page 3 of 16
UAE Statutory Law Background to
Conditional Payment Structures in Construction
UAE law provides a protective barrier for the employer and confirms, in the
Muqawala section of the UAE Civil Code, Article 891 that no
claim may be addressed by the subcontractor to the employer,
save for instances of assignment.3
This being the position, one must ask, “what consideration does the
subcontractor enjoy in return for this unenviable shift in risk-taking that
conditional clauses impose?”
For conditional clauses to have a fair sense of purpose in a subcontract, the
answer to that question must revolve around the following:
The main contractor is obliged to adopt the subcontractor’s claims for
payment as if the claims were its own;
To the extent, it considers the claims valid, the main contractor must
then pursue them with the employer, again as if they were its own; and
Any failure to do so, should prohibit the main contractor from relying
on any conditional clause, thus rendering it directly accountable to the
subcontractor.
In terms of legal authority, the concept of conditional payments seems to fall
squarely within the ambit of Part 3, Section 1 of the UAE Civil
Code, relating to ‘Dispositions conditional by suspension
or deferment’,4
Article 428 of which supports the view that “if the
Page 4 of 16
performance of an obligation is subject to a condition, then efforts
must be made for that condition to be observed.”5
It is not relevant how much time has passed since
payment to the subcontractor became due but rather
what can be proven to have taken place during such time.
This would appear to be a more dominant driver in determining the operation of a
conditional clause under UAE law.
By contrast, if it can be shown that no demonstrable efforts (in the context of
Article 428) have been made to observe the condition, then it would be arguable
under UAE law that the main contractor can no longer rely on a conditional pay
when paid clause and that to effectively avoid making payment to the
subcontractor, it would have to resort to more substantive defences.
As will be seen below, recent UAE jurisprudence has
indicated that, in the presence of a conditional clause, a
claim against the main contractor based purely on a
breach of the subcontract for non-payment, is likely to
fail.
Page 5 of 16
UAE Jurisprudence
Whilst many disputes arising out of subcontracts will be referred to private
and confidential arbitration, there have been a few instances where an arbitration
clause was absent and litigation ensued.
From the cases readily reported, save one case in 1995, where a
distinction was made by the Dubai Courts on whether a project
had been completed or not6 before a conditional payment clause
could be relied upon, most subsequent cases7 upheld the validity
of a pay when paid clause and rejected the claims filed by the
subcontractors on the basis of them being premature.
In one such case,8 the application of conditional payment
clauses in a subcontract was analyzed as follows:
The contractor imposed a condition that payments to the
subcontractor would be paid when such moneys from the
employer were paid;
This is an obligation suspended until the conditional fact
materialized; and
The subcontractor therefore did not have the right to claim the
balance of its dues until the condition was met, that is, payment
was received by the main contractor from the employer.
IMPORTANT NOTE:
Page 6 of 16
I. In all these cases, the SUBCONTRACTOR’S CLAIMS were made
on the simple basis of a breach of contract for non-payment.
II. They were not based on an argument that the true breach was
that the main contractor had failed to fully pursue the
subcontractor’s claims against the employer.
III. Nor were they based on the employer having rejected such claims, thus
containing the dispute strictly between the main contractor and the
subcontractor.
IV. The subcontractor’s position was countered by a
straightforward application of Article 420 of the UAE Civil
Code,9 in that the condition precedent (of payment by the
employer) had not yet occurred.
Page 7 of 16
Alternative Bases for the Subcontractor to Pursue Its Claims
In light of the above, and given the factors set out below, we
explore the alternative bases upon which a subcontractor can
successfully pursue its claims against the main contractor,
including whether the timing of any actions it needs to take to
achieve this:
Pay-If-Paid clauses are relatively rare in the UAE;
Pay-When-Paid clauses defer the timing of payment;
The UAE Civil Code acknowledges that some effort must be
made for a condition to materialize; and
That the consideration that the subcontractor must enjoy is
the Main Contractor’s obligation of pursuing the
subcontractor’s claims.
Page 8 of 16
Direct Payment Agreements with The Employer
Although the ability for subcontractors to successfully negotiate
the terms of their subcontract are usually very limited, we have seen
instances where nominated subcontractors managed to extract a
direct payment obligation by the employer, at least for certified
amounts, thus bypassing the main contractor.
This option is also envisaged by UAE law, in the Muqawala section of the
Civil Code10 as a possible exception to be executed by way of assigning the
obligation to pay the subcontractor from the contractor to the employer.
Two (2) issues are of note in instances where direct payment mechanisms have
been attempted in the UAE:
The standard obligation of the main contractor to effect payment to the
subcontractor (on a pay when paid basis) is often not removed from
either of the two subcontracts; and
Court proceedings that are normally brought by the subcontractor
against both the employer and the main contractor, have resulted in the
court ordering the subcontractor to first proceed to arbitration under the
subcontract against the main contractor and, if that were to fail or result
in non-payment, then, and only then, could the subcontractor proceed in
court against the employer under the direct payment agreement.
Direct payment agreements are seldom well coordinated with the contents of
either the main contract or the subcontract and commonly serve as a tool for the
employer to deflect liability for the subcontractor’s payments onto the main
contractor and vice versa.
Page 9 of 16
Lack of Pursuit of Subcontractor’s Claims
A further option for the Subcontractor is to argue that the
true breach lies in the Main Contractor failing to pursue the
subcontractor’s claims against the employer to the fullest extent
permissible by law. The instances where the subcontractor could
legitimately argue this include:
When the employer has rejected the subcontractor’s claim,
the main contractor has not accepted such rejection but has
failed to pursue the matter by way of a dispute resolution
process or otherwise; or
When the employer has deferred payment to an indefinite
point in time that can no longer be considered as reasonable
and the main contractor again fails to pursue the matter
whether by way of a dispute resolution process or otherwise.
Article 428 of the UAE Civil Code sets out the degree to which fulfilment of
the condition must be pursued. This lends itself to an argument that a main
contractor’s failure to pursue the subcontractor’s claims, could
effectively amount to a failure to observe the condition (of
payment by the employer) to the maximum degree
possible.
Page 10 of 16
One must be mindful of the fact that Main Contractors would commonly be
reluctant to start a dispute resolution process against an employer, purely in order
to pursue their subcontractors’ claims. In demonstrating such reluctance, the main
contractor may argue:
That at the stage the subcontractor’s action commenced, it
would be unreasonable for it (the main contractor) to have
commenced legal proceedings; or
That this may be supported by reference to various
commercial or contractual considerations.
Whichever option the main contractor adopts, it is likely that if pursuit of the
subcontractor’s claim is to be argued as a condition precedent for any conditional
clause to be relied upon, then such condition could be easily satisfied in most
instances, save for the case of the main contractor formally commencing legal
proceedings against the employer.
Page 11 of 16
Employer’s Outright Rejection of a Subcontractor’s Claim
As indicated above, instances of an outright rejection by the employer of a
main contractor’s claim that includes or relates to the subcontractor’s
works, would convert the question of when payment would be
made to a definite non-payment.
In terms of how this can be accommodated within the confines of UAE
law, Articles 420 to 428 of the UAE Civil Code, deal with
‘Dispositions conditional by suspension or deferment’,
essentially relating to conditional clauses.
The Main Contractor’s options in instances of outright rejection by the
employer would be either to:
Challenge the merits of the subcontractor’s entitlement (rather
than simply its timing) and adopt arguments raised by the
employer/engineer;
Challenge the merits of the subcontractor’s entitlement (rather
than simply its timing) and produce its own arguments for doing so;
or
Challenge the employer’s rejection, pursuing claims that would
include those of the subcontractor.
Page 12 of 16
TIMING S/C’s REQUEST/DEMAND BASIS
A. When invoices become overdue.
Payment of its outstanding invoices/dues
Contractual.
B.
When negative reply is received from main contractor (MC) on first request.
Evidence of inclusion of its work in monthly invoices to Employer (E).
Contractual/correspondence based.
C.
Once evidence of inclusion in monthly invoices/final statement of accounts has been provided.
Evidence of rejection of payment by E.
Contractual/correspondence based.
D.
Pay When Paid (PWP): Once confirmation of E’s rejection and MC’s agreement to this is obtained.
Payment of dues by MC. Legal: impossibility of condition, Art. 423 of Civil Code.
E.
Pay If Paid (PIP)/PWP: Whether or not E has rejected payment & whether or not MC has contested any rejection by E.
Evidence of pursuit of payment.
Legal: lack of pursuit, Art. 420 and 428 of Civil Code.
F. Once the scope of Subcontractor’s (SC) work has been completed.
Evidence of pursuit of payment.
Legal: lack of pursuit, Art. 420 and 428 of Civil Code.
G. Again, when the project has been handed over.
Evidence of pursuit of payment.
Legal: lack of pursuit, Art. 420 and 428 of Civil Code.
H. Again, when the defects liability period has expired.
Evidence of pursuit of payment.
Legal: lack of pursuit, Art. 420 and 428 of Civil Code.
I. When negative reply is received from MC on the above request.
Evidence of a legal notice issued for amounts inclusive of the subcontractor’s dues.
Legal: Lack of pursuit, Art. 420, 428 of Civil Code.
J. When the deadline of a legal notice expires.
Evidence of legal proceedings having been commenced.
Legal: Lack of pursuit, Article 420, 428 of Civil Code.
Page 13 of 16
Which option the Main Contractor adopts can be of critical relevance to
the application of either a Pay-When-Paid clause or a Pay-If-Paid clause.
Pay-When-Paid clauses are based on a presumption that payment
would eventually be made. They would therefore become inapplicable if
the employer refused to pay, for the simple reason that for the main
contractor to rely on them, it would have to unilaterally convert the
condition of ‘when’ to a condition of ‘if/whether’.
Page 14 of 16
Timing as a Key Factor to a Subcontractor’s Strategy
When being faced with a conditional payment clause, the subcontractor’s
main strategy in pursuing its claims against the main contractor is one of timing.
Therefore, a subcontractor that is deprived of its dues should sequence its
approach to a conditional payment clause by documenting its requests as follows:
Once the Main Contractor is forced to file a legal action against the
Employer, the Subcontractor’s Claims against the Main Contractor are
effectively carried over onto an action against the Employer.
Whilst the subcontractor can have little control over such
proceedings** (unless the main contractor encourages him to assist), the
conditional clause will have been given the purpose and substance that
the parties intended.
**Potential for Subcontractor DAB proceedings, if earlier adopted.
Scenario 1:
On the assumption that an award or judgment is eventually issued and
despite the Main Contractor’s perceived best efforts, the Subcontractor’s
Claims (or any part thereof) are not awarded, the question arises
whether this would be the end of the road for the Subcontractor.
The answer to this question would depend a lot more on
what the reason is behind the employer’s exoneration, rather
Page 15 of 16
than on whether the Subcontract contained a Pay-If-Paid or a
Pay-When-Paid clause.
CONCLUSION
In the presence of a conditional clause, it is
generally accepted that it is unwise for the
subcontractor to commence legal proceedings against
the main contractor on the simple basis of a debt
collection exercise as it is unlikely to succeed.
Ironically, the more unopposed (by the main contractor) a subcontractor’s
claim is, the more difficult it is to control the payment process and the more
hindered it is by a conditional clause. Conversely, any direct
challenge to its claims by the main contractor may block
the triggering of a conditional clause, thus making the
dispute resolution process an affair that is confined solely
between the main contractor and the subcontractor.
Finally, the question of whether a subcontractor can pursue its claims
against the main contractor, even after the employer has been exonerated of any
liability, will depend more on the reasons behind this, rather than on the nature of
the conditional clause.
Page 16 of 16
REFERENCES:
1 Federal Law No. 1/1987
2 An English translation of which states: (1) A contractor may entrust the performance of the whole or part of the work to another contractor unless he is prevented from so doing by a condition of the contract, or unless the nature of the work requires that he do it in person. (2) The first contractor shall remain liable as towards the employer.
3An English translation states that: ‘Article 891: A sub-contractor shall have no claim against the employer for anything due to him from the first contractor unless he has made an assignment to him against the employer.’
4Articles 420 to 428 of the Civil Code.
5An English translation states: ‘Article 428: A Condition must be observed as far as is possible.’
6Dubai Court of Cassation Case No. 281 of 1995: the distinction related to an obligation by the main contractor to pay the subcontractor, despite a conditional clause, if the project has been completed.
7Dubai Court of Cassation Case No. 267 of 2007, Dubai Court of Cassation Case No. 83 of 2009
8Dubai Court of Cassation Case No. 240 of 2006
9An English translation of which provides that: Article 420: A Condition is a future matter upon the existence or absence of which the full effectiveness (of a disposition) depends.
10Article 891, as previously mentioned.