work breakdown structure
DESCRIPTION
Work Breakdown StructureTRANSCRIPT
URP4161_PROJECT PLANNING:03
2.3 Work Breakdown Structure
Md. Sabbir Sharif Lecturer
Dept. of Urban & Regional Planning KUET, Khulna-9203, Bangladesh
What is the problem?
• Your boss: “How long will this take?” • You: “Between 1 and 6 months.” • People are not happy when you respond that way.
• You figure out that finishing anytime before six months will meet your promise.
• Your boss figures that with some hard work you can be done in a month!
• In reality, you don’t have the slightest clue how long it will take, because you don’t know the work to be done.
• Solution: Use divide and conquer • To give a good answer you have to break the work
down into activities for which you can get good timing estimates
• From these estimates you compute the estimated project duration
Activities to obtain good time estimates
• Identify the work that needs to be done • Work breakdown structure (WBS)
• Identify the dependency between work units • Dependency Graph
• Estimate the duration of the work to be done • Schedule
What are the activities that are needed to build a house?
• Surveying • Excavation • Request Permits • Buy Material • Lay foundation • Build Outside Wall • Install Exterior Plumbing • Install Exterior Electrical • Install Interior Plumbing • Install Interior Electrical
• Install Wallboard • Paint Interior • Install Interior Doors • Install Floor • Install Roof • Install Exterior Doors • Paint Exterior • Install Exterior Siding • Buy Pizza
1) Identify the work to be done: Work Breakdown Structure
2) Hierarchically organize the activities
• Preparing the building site consists of • Requesting permits • Surveying • Excavation • Buying of material • Laying of the foundation
• Building the house consists of • Prepare the building site • Building the Exterior • Building the Interior
3) Identify dependencies between tasks
• The work breakdown structure does not show any dependence among the activities/tasks
• Can we excavate before getting the permit? • How much time does the whole project need if I
know the individual times? • What can be done in parallel? • Are there any critical activities, that can slow
down the project significantly?
• Dependencies like these are shown in the dependency graph
• Nodes are activities • Lines represent temporal dependencies
START
Request
Survey ing
Excava tion
Buy Material
Founda tion
Build Outside
Wall
Install Exterior Plumbing
Install Interior Plumbing
Install Exterior Electrical
Install Interior
Electrical
Install Exterior
Siding
Install Wallboard
Paint Exterior
Install Roofing
Install Flooring
Paint Interior
Install Interior
Doors
Install Exterior
Doors
FINISH
The activity „Buy Material“ must Precede the activity
„Lay foundation“
Lay
Building a House (Dependency Graph)
4) Map tasks onto time • Estimate starting times and durations for each
of the activities in the dependency graph • Compute the longest path through the graph:
This is the estimated duration of your project
Building a House (Schedule, PERT Chart)
Duration
Start Time
Slack Time
Each Activity has a start time and an estimated duration
START
8/27/94
0 0
Request Permits
8/27/94
15 0
Survey ing
8/27/94
3 12
Excava tion
9/17/94
10 0
Legend
8/29/94
0
Buy Material
10/1/94
10 0
Lay Founda
tion
10/15/94
15 0
Build Outside
Wall
11/5/94
20 0
Install Exterior Plumbing
12/3/94
10 12
Install Interior Plumbing
12/3/94
12 0
Install Exterior Electrical
12/17/94
10 12
Install Interior
Electrical
12/21/94
15 0
Install Exterior
Siding
12/31/94
8 12
Install Wallboard
1/11/95
9 0
Paint Exterior
1/12/95
5 12
Install Roofing
1/19/95
9 12
Install Flooring
1/22/95
18 0
Paint Interior
1/22/95
11 0
Install Interior
Doors
2/8/95
7 0
Install Exterior
Doors
1/19/95
6 15
FINISH
2/16/95
0 0
0
Intranet WBS & Gantt Chart
Responsibility Matrix
The WBS represents a logical decomposition of the work to be performed and focuses on how the product, service, or result is naturally subdivided. It is an outline of what work is to be performed.
WBS – Rules of thumb A “Rule of thumb” is not a rule or a law. It is a strategy that we do because we know it works. o There is no rule as to the number of levels that a WBS has o Always start with Project Management as the first o Deliverable here should be no more than 10 top-level
Deliverables o Use a Noun: Object naming convention o Each sub-component must have a deliverable… the lowest
level of sub-division with a deliverable is called a “work package”
o Each and every sub-component must be assignable to one and only one person…
o Do not break the work into any inner detail than you intend to track or is of value – do not micro-manage