windspeed project: making space for offshore wind powerpolicy/growth modelling vii.key messages....
TRANSCRIPT
EWEA 2011, 15th March
WINDSPEED project:
Making space for offshore
wind power
Lachlan Cameron, ECN
EWEA 2011, Brussels, 15th March
www.windspeed.eu
EWEA 2011, 15th March
I. Methodology
II. Default case
III. Sensitivity examples
IV. Scenarios
V. Spatial results
VI. Policy/growth modelling
VII. Key messages
EWEA 2011, 15th March
Spatial potential(DSS tool)
Policy/growth constrained potential(RESolve-E model)
Economic potential(NetOp/COMPETES)
I. Methodology
EWEA 2011, 15th March
I. DSS cost inputs
Bathymetry
Geological Conditions
Storm Surge
Spring Tidal Amplitude
Mean Wave Height
Extreme Wave Height
Staging Ports
Grid Connection Points
Ave. Wind Speed at 90m shading indicates levelised production cost
EWEA 2011, 15th March
I. DSS spatial inputsCables & Pipelines
Military
Sand Extraction
Shipping Density
Shipping Routes
Oil & Gas Platforms
Fisheries
Nature Conservations Zones
Fish species richness
Benthic value
Bird Sensitivity
Existing and Planned OWP
EWEA 2011, 15th March
WINDSPEED Decision Support System
Default map
EWEA 2011, 15th March
Size of area(1,000 km2)
Percentage of WINDSPEED area*
Theoretical generation
(TWh)
Suitable for new OWE 120 33% 1,100
Exclusion: existing/planned OWE 28 8% n/a
Exclusion: shipping 75 20% 634
Exclusion: oil and gas 47 13% 405
Exclusion: fisheries 105 29% 916
Exclusion: military zones 47 13% 389
Exclusion: cables/pipelines 31 8% 265
Exclusion: sand extraction 6 2% 48
Exclusion: nature areas 42 11% 351
Exclusion: marine wildlife 34 9% 273
15 1284%
* Excluding areas in territorial waters
II. Default case
EWEA 2011, 15th March
Size of area(1,000 km2)
Percentage of ‘remaining area’
Theoretical generation
(TWh)
Suitable for new OWE 120 33% 1,100
Exclusion: existing/planned OWE 28 8% n/a
Exclusion: shipping 75 20% 634
Exclusion: oil and gas 47 13% 405
Exclusion: fisheries 105 29% 916
Exclusion: military zones 47 13% 389
Exclusion: cables/pipelines 31 8% 265
Exclusion: sand extraction 6 2% 48
Exclusion: nature areas 42 11% 351
Exclusion: marine wildlife 34 9% 273
Hard Firm Soft
EWEA 2011, 15th March
48
916 405
389
634
351265
273
150
160
170
180
190
200
210
40% 50% 60% 70% 80% 90% 100%
Ave
rage
leve
lised
pro
du
ctio
n c
ost
(€
/MW
h)
Percentage overlap with other sea use functions
sand extraction
fisheries
oil and gas extraction
military areas
shipping exclusions
nature conservation areas
cable or pipelines
marine wildlife preservation
II. Key spatial drivers
Labelled bubble size represents the total excluded area in TWh
EWEA 2011, 15th March
III. Sensitivity: Shipping
0
200
400
600
800
1000
1200
1400
140 150 160 170 180 190 200 210 220 230
Cu
mu
lati
ve e
xclu
ded
po
ten
tial
(TW
h)
Levelised Production Cost (€/MWh)
IMO plus high density (default)
default - buffer increased 500m
default - buffer increased 1000m
default - buffer increased 2000m
default - buffer decreased 500m
default - buffer decreased 1000m
default - buffer decreased 2000m
IMO only
IMO plus medium and high density
EWEA 2011, 15th March
III. Sensitivity: Oil & Gas
-200
-100
0
100
200
300
400
500
radius1nm
radius2nm
radius3nm
radius4nm
radius5nm
radius6nm
Ge
ne
rati
on
Po
ten
tial
(TW
h)
Differing helicopter clearance radii
Change in total excluded potential versus baseline of 5nm clearance
Change in potential suitable for OWE versus baseline of 5nm clearance
EWEA 2011, 15th March
III. Sensitivity observations Shipping: relatively hard constraint, dominant in areas with low cost OWE. Buffer
modification has limited effect. IMO widths match anticipated OWP spacing
Oil & gas: hard regulatory constraint – but a changing one so important to scale for decommissioning
Fisheries: largest constraint but relatively ‘soft’. Opportunity for co-use with OWE
Military: firm constraint via negotiation – need to set realistic level of exclusion
Cables/pipes: hard regulatory constraint that is growing – need to scale up
Sand extract: small constraint – Dutch law will restrict this to territorial waters
Natura 2000: firm constraint with some potential for OWE – countries have different conservation philosophies.
Marine wildlife: soft introduced constraint – currently doubles Natura 2000 areas
Planned/known OWP: hard constraint – little opportunity for obvious reasons
EWEA 2011, 15th March
• OWE is not prioritised. Current use patterns take preference
• No offshore meshed grid
• OWE limited to depths and distances in line with current ambitions
• OWE is prioritised
• No offshore meshed grid
• OWE limited to depths and distances in line with current ambitions
• OWE is not prioritised and development is largely limited to areas further from shore
• Moderate offshore meshed grid develops
• With/without 70m depth limit
• OWE is prioritised
• Comprehensive offshore meshed grid develops
• With/without 70m depth limit
EWEA 2011, 15th March
IV. Scenario Design
Feasibility
CostsPotential
EWEA 2011, 15th March
IV. Density
• 2 MW/km2 – provides an adequate distance between each farm to mitigate the impact of inter wind farm wakes
~12km
EWEA 2011, 15th March
DriverLittle will, Little wind
Going Solo In the Deep Grand Design
Existing OWP common across scenarios – based on NREAPs and known plans
Sand extract. P P
Military zones P P
Natura 2000 P P
Shipping P P
Oil & Gas P PP P PP
Cables / pipes OO O OO O
Fisheries P P
Marine wildlife
Technology P P
Grid P P
= baseline assumption for OWEP = assumptions give more OWEO = assumptions give less OWE
EWEA 2011, 15th March
V. Results
EWEA 2011, 15th March
EWEA 2011, 15th March
0
500
1000
1500
2000
140 150 160 170 180 190 200 210 220 230
Cu
mu
lati
ve S
uit
able
Cap
acit
y (T
Wh
)
Levelised Production Cost (€/MWh)
Little will Little wind
Going Solo
In the Deep
In the Deep - 70m depth constraint
Grand design
Grand design - 70m depth constraint
V. Supply curves
182GW
82GW
80GW
26GW
EWEA 2011, 15th March
0
10
20
30
40
50
60
70
80
90
100
BE DE DK NL NO UK
Incr
emen
tal s
pat
ial c
apac
ity
(GW
)
No will No wind (< 200 €/MWh) No will No wind (> 200 €/MWh)Going Solo (< 200 €/MWh) Going Solo (> 200 €/MWh)In the Deep (< 200 €/MWh) In the Deep (> 200 €/MWh)Grand Design (< 200 €/MWh) Grand Design (> 200 €/MWh)
V. Results by country – incremental spatial capacity
EWEA 2011, 15th March
0
10
20
30
40
50
60
70
80
90
100
BE DE DK NL NO UK
Incr
em
en
tal s
pat
ial c
apac
ity
(GW
)
No will No wind (< 200 €/MWh)Going Solo (< 200 €/MWh)In the Deep (< 200 €/MWh)Grand Design (< 200 €/MWh)
V. Results by country – incremental spatial capacity
EWEA 2011, 15th March
Spatial potential(DSS tool)
Policy/growth constrained potential(RESolve-E model)
Economic potential(NetOp/COMPETES)
VI. Non-spatial constraints
EWEA 2011, 15th March
VI. REsolve-E
Policy-based demand for
renewable electricity
Supply curves
based on
technology
costs & potentials
• Risk
• Transaction
costs
• Lead times
years
• Technology mix
• Trade flows
Scenarios
EWEA 2011, 15th March
VI. Overview potentials
0
100
200
300
400
500
600
Little willLittle wind
GoingSolo
In theDeep
GrandDesign
Cap
acit
y [G
W]
Policy/growth constrained potential
Spatial potential > 70 m
Spatial potential
EWEA 2011, 15th March
VI. Maps of potentials
In the DeepSpatial constraint
In the DeepSpatial & policy/growth constraint
EWEA 2011, 15th March
VIII. Key messages - spatial• The assumed density of the installed wind parks is relatively low. There
are many potential opportunities for co-use/integration
• Limited new nearshore OWE after 2020 without spatial prioritisation
• Scenarios with an offshore grid have 2 – 3 times the spatial potential of the scenarios that use radial connections
• Floating technologies double the total spatial OWE potential
• For most countries only a fraction of the indicated suitable areas are used due to policy/growth constraints
• Differences in the OWE costs and potentials between countries hints at the value of an offshore-grid
EWEA 2011, 15th March
III. Sensitivity: Oil & Gas
0
100
200
300
400
500
600
145 155 165 175 185 195 205 215 225 235
Cu
mu
lati
ve e
xclu
ded
po
ten
tial
(TW
h)
Levelised Production Cost (€/MWh)
exclusion radius 1nm
exclusion radius 2nm
exclusion radius 3nm
exclusion radius 4nm
exclusion radius 5nm (default)
exclusion radius 6nm
EWEA 2011, 15th March
II. Default case
Size of area(1,000 km2)
Percentage of WINDSPEED
area
Theoretical generation
(TWh)
Total WindSpeed area 432 100% 3,726
Exclusion: distance to shore 63 15% 490
Exclusion: too small 2 0.5% 16
Exclusion: depth 0 0% 0
Remaining area 368 85% 3,219