wide area measurement

Upload: ajayvarma

Post on 03-Jun-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 Wide Area Measurement

    1/16

    Smart Grid, Smart City Project

    Monitoring and Measurement Report

    Report III

    Grid Applications Stream: Wide Area Measurement

    01 January 2012 30 June 2012

  • 8/11/2019 Wide Area Measurement

    2/16

    Smart Grid, Smart City Monitoring and Measurement Report III Wide Area Measurement 2

    IMPORTANT NOTE:

    In a number of attachments, Ausgrid has removed certain material that we do not consider

    appropriate to release, such as personal information and commercially sensitive financial information.

    Ausgrid believes the removal of this information does not detract from the general value of the

    information or findings in the attachments.

    This document has been approved for publication by Ausgrid and the consortium partners who

    contributed to it. The document has been prepared with all reasonable care and responsibility.

    Ausgrid believes these findings to be technically and factually accurate when applied to Ausgrids

    network as at the date of those findings.

    However it should not be considered a recommendation and naturally, it would be prudent for anyone

    who wishes to rely on, or use the information in this report to independently verify its accuracy,

    completeness and suitability for use for their own purpose.

    Consequently, Ausgrid makes no representation or warranty as to the accuracy, currency, reliability,

    completeness or suitability, of the information in this report. You acknowledge that Ausgrid (and itsofficers, employees, agents and consultants) to the full extent permitted by law, excludes all liability:

    (a) (including liability to any person by reason of negligence or negligent misstatement) for any

    statement, opinion, information or matter (expressed or implied) contained in, and for any omissions

    from, this document; and (b) arising out of your use of or reliance on this document and any

    information contained in it.

    Ausgrid owns copyright in (or otherwise has the rights necessary to publish) this document. You may

    only reproduce this document with the permission of Ausgrid.

  • 8/11/2019 Wide Area Measurement

    3/16

    Smart Grid, Smart City Monitoring and Measurement Report III Wide Area Measurement 3

    Contents

    1 Wide Area Measurement ................................................................................... 5

    1.1

    Introduction ............................................................................................................................... 5

    1.2

    Trial Design and Architecture .................................................................................................. 6

    1.2.1 Trial Location ....................................................................................................................... 6

    1.2.2

    WAM Trial Components ...................................................................................................... 7

    1.3 Activities .................................................................................................................................... 9

    1.4

    Analysis and results ............................................................................................................... 10

    1.4.1 Data Priorities .................................................................................................................... 10

    1.4.2

    Data gathered.................................................................................................................... 10

    1.4.3 Analysis ............................................................................................................................. 14

    1.5

    Lessons Learnt ........................................................................................................................ 14

    1.6

    Case studies ............................................................................................................................ 15

  • 8/11/2019 Wide Area Measurement

    4/16

    Smart Grid, Smart City Monitoring and Measurement Report III Wide Area Measurement 4

    Attachment List

    AREA TITLE CATEGORY TYPE

    GA MMR3_GA_WAM_Beresfield and Singleton phase B.xlsx Raw Data Spreadsheet

  • 8/11/2019 Wide Area Measurement

    5/16

    Smart Grid, Smart City Monitoring and Measurement Report III Wide Area Measurement 5

    1 Wide Area Measurement

    1.1 Introduction

    Wide Area Measurement seeks to monitor network stability of the HV network. Stability includes a

    number of grid management aspects including: state determination and grid imbalance (voltage

    stability, phase imbalance); disturbance recording; network safety; and generation control. Improved

    planning will also result from the data gathered from WAM. The trial will evaluate the use of phasor

    measurement unit (PMU) technology in improving system stability, avoiding cascading load shedding

    during system overload (supported by wide area protection schemes), providing data to enable event

    analysis (subsequent to a wide scale unplanned outage), and supporting "black start" recovery when

    returning from a wide scale outage. The measurement takes place at transmission and sub-

    transmission substations, therefore involving TransGrid as well as Ausgrid.

    Measurement is achieved through the installation of 11 PMUs along high voltage corridors in the

    Transmission network (TransGrid 5 units) and Distribution network (Ausgrid 6 units). Other

    monitoring (existing data collected through SCADA) is combined to give an overall picture of grid

    stability. Monitoring and control capabilities are achieved with local and central data collection

    capability. Backend IT systems allow central collection, analysis and visualisation of data. Depending

    on existing monitoring systems at a substation,augmentation of the substation switches that interface

    with the communications network is sometimes necessary for deployment of PMUs.

    Ausgrids PMU and backend IT implementation has progressed to the point where data is being

    collected, stored and analysed from two sites. The remaining four sites are planned for before year

    end. Ausgrid has included collected data in this progress report, provided some visualisation to

    Ausgrid planners, and has completed an implementation case study..

    TransGrids implementation of PMUs has progressed to ordering of five PMUs. Locations have beenselected for priority deployment. Installation, commissioning through to centralised data collection

    and data sharing between organisations is planned for the second quarter of 2013.

    As data collection proceeds during 2013 the project will move to evaluating the effectiveness in

    sensing and responding to stability issues, simulating automated response to failure conditions and

    improved decision support to Transmission and Distribution system operations. Specifically the

    project will

    Continue installation of AMETEK relays in Sydney Ausgrid sits and GE relays at TransGrid

    sites

    Streamline collection of data to support the investigations and benefits analysis of fault

    recording and phasor monitoring

    Continue analysis of WAM data with the assistance of Ausgrid and TransGrid business units.

    The scope of this analysis will be refined in parallel with the commissioning of new PMUs as

    more tests will drive new test requirements

    Develop a front-end for the WAM system (synchrophasor data) and the Wide Area Control

    simulation

    Estimate the bounds of measurement uncertainty in the overall system. This will include an

    estimation of the phasor accuracy of the existing CTs and VTs that are being used, the GPS

    clock signal accuracy, and the accuracy of the PMU devices themselves

    Commence development of a WAM benefits framework for network businesses and the

    broader energy industry

  • 8/11/2019 Wide Area Measurement

    6/16

    Smart Grid, Smart City Monitoring and Measurement Report III Wide Area Measurement 6

    1.2 Trial Design and Architecture

    1.2.1 Trial Location

    The site selection criteria for substations part of the WAM trial was as follows:

    Close to the TransGrid network: This allows phasor measurements to indicate the impact ofupstream network conditions on voltage and current phasors in Ausgrids network. This

    resulted in selecting Ausgrid sub-transmission substations closest to bulk supply points

    Directly connected to Ausgrid sub-transmission substations: This may also allow for the

    review of sub-transmission feeder ratings due to a higher accuracy in measurement of power

    being delivered

    Geographically dispersed: This will enable measurement of phasors across a wide area.

    Figure 1. PMU Deployment

    The map displays

    TransGrid and Ausgrid

    substations that were

    included in the scope of

    the WAM project.

  • 8/11/2019 Wide Area Measurement

    7/16

    Smart Grid, Smart City Monitoring and Measurement Report III Wide Area Measurement 7

    Phasor measurement units will be installed in a total of 11 locations, 5 at TransGrid sites and 6 at

    Ausgrid sites. Based on the above criteria, the following table lists the substations and feeders that

    will be monitored by PMU devices:

    Substation Network PMU Device BusVoltage

    Comment

    Beresfield STS Ausgrid N60 132kV Installed and commissioned

    Singleton STS Ausgrid N60 132kV Installed and commissioned

    Ourimbah STS Ausgrid TR-2100 132kV

    Peakhurst STS Ausgrid TR-2100 132kV

    Lane Cove STSS Ausgrid TR-2100 132kV

    Mason Park STSS Ausgrid TR-2100 132kV

    Newcastle BSP TransGrid N60 330kV Priority install

    Tomago BSP TransGrid N60 330kV

    Muswellbrook BSP TransGrid N60 330kV Priority install

    Waratah West BSP TransGrid N60 330kV

    Beaconsfield West BSP TransGrid N60 330kV Priority install

    Sydney South BSP TransGrid N60 330kV Priority install

    Sydney North BSP TransGrid N60 330kV Priority install

    Sydney East BSP TransGrid N60 330kV

    Vales Point BSP TransGrid N60 330kV

    Tuggerah BSP TransGrid N60 330kV

    1.2.2 WAM Trial Components

    Wide Area Measurement project components and functions are described below.

    Phasor Measurement Units

    Wide area measurement systems (WAM) rely on a set of phasor measurement units (PMUs) installed

    at diverse locations across an electrical transmission network. A PMU is a device that is connected to

    a feeder at a substation and takes current and voltage measurements in order to determine phasors

    (as defined by the IEEE C37.118-2005 standard). A phasor is a measurement of the magnitude and

    angle of an electrical waveform, either current or voltage. The electric system information is sampled

    at very high speeds with individual measured values being transmitted at 50 times per second.

    All PMUs in a WAM system each take a phasor measurement at exactly the same time, as they are

    synchronised with a common time source (GPS). These time-synchronised phasors are called

    synchrophasors. When these sets of synchrophasors are returned to a central location from each

    PMU, the state of the network from a wide area perspective can be seen. The angle in a phasor is a

    relative unit; therefore for analysis a reference for zero angle is usually selected, generally this is a

    voltage phasor. The key piece of information this wide area status of the network gives is the absolute

    phase differences between different parts of the network.

  • 8/11/2019 Wide Area Measurement

    8/16

    Smart Grid, Smart City Monitoring and Measurement Report III Wide Area Measurement 8

    WAM Communications

    The commissioned phasor measurement units use Ausgrid's existing fibre MPLS network between

    sub-transmission substations and the corporate network to communicate with the central server that

    hosts the open PDC application.

    Grid Model Validation

    The measurements provided by the WAM system can be used to give a more accurate view of the

    state of the network, in addition to measurements already provided by protection devices.

    It can be used to verify the network model and SCADA data used to perform power flow analysis.

    Stability Analysis

    Power flow can be predicted under different scenarios with more accurate measurements from the

    WAM system.

    With more accurate measurements of bus states, the network can be operated closer to the stability

    threshold resulting in a higher power transfer, which is particularly important for interconnections.

    Early detection of insecure or unstable conditions by the WAM system can provide early detection of

    the system trending towards an insecure state (that is, not meeting contingency requirements), or

    unstable state, and will assist operators in making informed remedial decisions.

    Post Event Analysis

    Post event analysis after a disturbance on the network can make use of the WAM measurements to

    determine the sequence of events that led to the cause of the disturbance.

    If PMUs retain power during a black start (where all generators have had to shut down due to loss of

    grid stability) the frequency and phasor angle information can assist system operators to conduct therestoration process.

    Phasor Data Concentrator

    An open source phasor data concentrator (openPDC) is the system used to manage, process and

    respond to dynamic changes in fast moving streaming phasor data. More specifically, the system can

    process any kind of data that can be described as time-stamped measured values.

    WAM data access and presentation

    Besides engineers accessing the data, the requirements of system planners, system operators, and

    protection engineers are being gathered in order to develop an appropriate visualisation front-end for

    their use of phasor measurement data. System planners are interested in historical data to verify

    planning models. System operators are interested in recent history and near real-time data to

    complement their existing understanding of the operation of the network that is gained through

    SCADA measurements, and some post-fault view of events. Protection engineers are interested in

    post event (fault) waveform information.

  • 8/11/2019 Wide Area Measurement

    9/16

    Smart Grid, Smart City Monitoring and Measurement Report III Wide Area Measurement 9

    1.3 Activities

    GE N60 phasor measurement units have been commissioned at Beresfield and Singleton

    sites in the Hunter region, monitoring voltages and currents at the 132kV sub-transmission

    level. Ausgrids Sydney sites are expected to have AMETEK TR-2100s commissioned over

    the next few months TransGrid is progressing designs, with a target commissioning date of early 2013. The first

    order of GE N60 relays is at TransGrid for testing. The formal engagement with TransGrid

    has begun with 5 sites identified as a priority. Installations are due to complete by February

    2013

    Ausgrid has completed all the required designs (physical panel layout, protection wiring,

    substation communications and interfaces) for the installations in its network

    OpenPDC software has been deployed on Ausgrid's central data centre for synchrophasor

    data storage, basic visualisation and data exporting

    Ausgrid is currently implementing a fibre connection between Transgrid's Sydney South BSP

    and Ausgrid's network to facilitate installation of the Transgrid Phasor Data Concentrator

    (PDC). This work is scheduled for completion by 31st Oct 2012. Once complete the Transgrid

    PDC will transmit the PMU data to the Ausgrid PDC (and vice versa) for comparative analysis

  • 8/11/2019 Wide Area Measurement

    10/16

  • 8/11/2019 Wide Area Measurement

    11/16

    Smart Grid, Smart City Monitoring and Measurement Report III Wide Area Measurement 11

    OpenPDC is the phasor data concentrator that is being used at Ausgrid, and will be used by

    TransGrid. The OpenPDC application runs on a central server in the data centre, collecting phasor

    data, and providing simple visualisation and reporting tools. (More on openPDC at

    http://openpdc.codeplex.com/)

    The openPDC Phasor Data Concentrator software system is designed to process streaming time-

    series data in real-time. Measured data gathered with GPS-time from many hundreds of input sources

    is time-sorted and provided to user defined actions as well as to custom outputs for archival.

  • 8/11/2019 Wide Area Measurement

    12/16

    Smart Grid, Smart City Monitoring and Measurement Report III Wide Area Measurement 12

    Beresfield STS Voltage and Current Phasor Angle Difference

    Phasor measurement data is being received from existing current transformers (CTs) and voltage transformers (VTs) n

    and Singleton. The following table depicts the data received in SCADA and in OpenPDC for a moment in time.

    From SCADA Calculated From Open PDC

    CB Tag Base Feeder MW MVAr PF V-I Angle Ab Angle Ib Angle

    Beresfield:132kV:Cb_33806 98R -0.73600006 40.60800171 0.454777142 117.0505961 -

    29.0478516

    -143.042

    Beresfield:132kV:Cb_33812 9NA -2.38399982 -

    58.17599869

    0.208206205 -

    102.0172519

    -

    29.0478516

    72.98218

    Beresfield:132kV:Cb_33825 99Y 19.00799942 -

    50.97600174

    0.349382429 -69.5504536 -

    29.0478516

    42.03918

    Beresfield:132kV:Cb_33794 98N -

    27.36000061

    53.85599899 0.452925627 116.9315447 -

    29.0478516

    -

    144.9316

    Beresfield:33kV:Cb_33837 T1 21.16799927 7.776000023 0.938669755 20.17065411

    Beresfield:33kV:Cb_33849 T3 20.59199905 7.343999863 0.941890835 19.62843874

  • 8/11/2019 Wide Area Measurement

    13/16

    Smart Grid, Smart City Monitoring and Measurement Report III Wide Area Measurement 13

    There are some differences in refresh rates and accuracies of both systems that are likely to be

    responsible for some minor differences in the calculated voltage current angles (V-I).

    The following phasor plot demonstrates the B phase current phasors at Beresfield relative to the B

    phase voltage. This is a reasonably consistent difference during normal operation, varying by 3-4

    degrees as loads change.

    Figure 2. Beresfield STS and Singleton STS Phasor Angle Difference

    Green:98N Phase B Voltage

    Red:98N Phase B Current

    Black:98R Phase B Current

    Blue:9NA Phase B Current

    Purple:99Y Phase B Current

  • 8/11/2019 Wide Area Measurement

    14/16

    Smart Grid, Smart City Monitoring and Measurement Report III Wide Area Measurement 14

    The following phasor plot demonstrates the phasor angle difference between Beresfield and Singleton

    that was investigated as part of the case study below.

    Figure 3. Phasor angle difference between Beresfield and Singleton

    All data from the SGSC trial will be made available via the Information Clearing House. For this

    MMR, only a sample data set can be made available, a 5 minute snapshot that demonstrates the

    phasor angle difference discussed in the case study. The main limitation to sharing all of the data at

    this stage is the high volume of data. Data for phasor angle difference between Beresfield and

    Singleton is available in: MMR3_GA_WAM_Beresfield and Singleton phase B.xlsx.

    1.4.3 Analysis

    Commissioning and integration of phasor measurement devices at Beresfield and Singleton provided

    data that was of significant interest to Ausgrid's Subtransmission Planning and System Operations

    groups. However, at this stage it has only been presented to Subtransmission Planning using the

    views of the data that OpenPDC provides. It is intended that phasor visualisation will be developed tomeet System Operations requirements.

    1.5 Lessons Learnt

    Installing new relays that have phasor measurement unit functionality fits in well with

    Ausgrid's existing protection design capabilities. The design and installation fit into the normal

    work of Ausgrid's Control and Protection and Transmission Substations groups, with only the

    additional complication of setting up PMU functionality on the relays

    Designs in the Hunter were independent of the control and protection systems, and

    connected through the MPLS switch to the corporate LAN, which made the overall design

    significantly less complicated than a retrofit within a protection system would have been

    Green:Beresfield 98N Voltage

    Postitive Sequence Phasor

    Blue:Singleton 95U Voltage

    Positive Sequence Phasor

  • 8/11/2019 Wide Area Measurement

    15/16

    Smart Grid, Smart City Monitoring and Measurement Report III Wide Area Measurement 15

    It was possible to use existing CTs and VTs, significantly reducing the cost of installation for

    the phasor measurement units. However, the complication this introduced is it relies on the

    quality of existing measurements used in SCADA and provides the WAM system with less

    end-to-end control over the accuracy of the data that is gathered

    Despite the fact that this is a trial, a major challenge for the design team was ensuring that

    the end-to-end solution had been detailed and agreed by the various business groupsresponsible for the communications and IT systems. It proved to be both challenging and

    time consuming to design the interface to the corporate network, understand the bandwidth

    requirements, design storage, and fit into the data centre environment. For a large scale

    deployment, the required support capabilities and business units involved must be well

    understood early in the program

    1.6 Case studies

    Ausgrid has multiple models that engineers use to predict, evaluate and mitigate problems that the

    network is expected to experience. Subtransmission planners maintain and use a network model for

    the Hunter area. Off-line load flow analysis is conducted on this model to predict voltage issues andcapacity constraints. Commissioning phasor measurement devices at Beresfield and Singleton helped

    Ausgrid planners to validate the subtransmission network model for the Hunter area. Comparing

    results of load flow calculations in the subtransmission network model against the synchrophasor

    magnitude and angle measurements allowed the planners to ensure that their model reflects the

    physical network.

    In particular, high load flows (600A) that were measured when the normally open switch was closed at

    Rothbury were verified against the synchrophasor measurements that confirmed that a 27 degree

    voltage phase shift exists between the Beresfield and Singleton bus bars. Ausgrid's model initially had

    predicted that only 200A should flow, but once the model had been updated, 580A flow was

    predicted, which better reflected the operational experience.

    Future case studies are planned to include a review of the use of phasor measurement data with

    internal stakeholders, the Wide Area Control simulation, and collaborative work with TransGrid.

  • 8/11/2019 Wide Area Measurement

    16/16

    Smart Grid, Smart City Monitoring and Measurement Report III Wide Area Measurement 16

    Glossary of Abbreviations

    Abbreviation Term

    BSP Bulk supply point

    CT Current transformer

    LAN Local area network

    GE General Electric

    GPS Global Positioning System

    MPLS Multiprotocol label switching

    PDC Phasor data concentrator

    PMU Phasor measurement unit

    SCADA System control and data acquisition

    SGSC Smart Grid, Smart City

    STS Sub-transmission substation

    VT Voltage transformer

    WAM Wide Area Measurement