vsl product watch crigler jan 08.532
TRANSCRIPT
-
7/22/2019 VSL Product Watch Crigler Jan 08.532
1/4STRUCTURE magazine
PRODUCTWATCHupdates on emerging technologies, products and services
January 200848
Expanding the Use ofPost-Tensioning in BuildingsBy John Crigler, P.E.
Part 1 of this series of articles on Post-Tensioning ran in theJuly 2007 issue of STRUCTUREmagazine.
Visitwww.STRUCTUREmag.orgfor archived articles.
Transfer Plates
The suspended floors in multistorybuildings are generally supported bycolumns and load bearing walls. Thelayout and size of these elements helpdefine the space available within thebuilding. Floor framing systems areselected with consideration for bothspace needs and economics. In multi-story buildings, the requirements maychange from floor to floor. Therefore,the selection of a single framing system
for an entire structure is not alwaysideal. As the population grows, the costand availability of building sites willbecome more challenging and the needfor multifunction multistory buildings
will increase. This trend is seen in manyareas of the U.S., where multifamilyresidential buildings are built withunderground parking. These structuresare built with hybrid framing systemsconsisting of post-tensioned slabs for
the underground parking area, with a loabearing wood frame for the living area aboveIn Hong Kong, where the populatio
density is high and good building sites arscarce, multifunction high rise buildingare more common. For these buildingspost-tensioned transfer plates have beeextensively used to adjust the floor framinsystem as the requirements change withinthe height of the building.An early example of a large transfer plate i
the Pacific Place building in Hong Kong. Th222-meter (728-foot) tall building consists oa large retail/commercial/parking area thaextends up to the 57-meter (187-foot) leve
with residential and hotel space above. Thupper part of the building utilizes closelspaced supports which were suitable for thuse, whereas the base of the building requirelong spans. A 4.5-meter (14.7-foot) thicpost-tensioned transfer plate is used at the 57meter (187-foot) level to transfer the vertica
Buildings are created to achieve
well defined goals. While there aremany different systems used torealize these goals, the structural
system plays a key role. For more than 40years, post-tensioned concrete has been usedin buildings. It is widely accepted by structur-al engineers for offices, parking garages, con-dominiums and apartments. Post-tensioningis particularly well suited to reinforce slabs.When compared to conventionally reinforced
slabs of equal strength, post-tensioned slabscrack at a higher demand level which reducesdeflection under service loads, permittingthinner slabs and/or longer spans. The resultis a reduction in floor system weight which inturn reduces demand on the other structuralmembers (columns and shear walls) and thefoundations, while longer spans enhance thevalue of the building. For these reasons, theuse of post-tensioning for building slabs willcertainly continue to be the dominant appli-cation for post-tensioning in buildings. A rendering of the Pacific Place Building showing the transfer plate in relation to the
various building sections.
The Pacific Place Building in Hong Kong.
-
7/22/2019 VSL Product Watch Crigler Jan 08.532
2/4STRUCTURE magazine January 200849
loads between the building zones. While this isan early example, there have been more than80 post-tensioned transfer plates constructedin Hong Kong over the last 20 years.While the residential transfer plates thatare more common here in the U.S. and thestructures built in Hong Kong represent therange of possibilities, they both demonstratethe advantages:
Accommodate irregular loading/support
paths, which can be challenging withbeam/girder framing systems Significant reduction in reinforcement Reduced construction time In many cases, reduction of depthwhich reduces the buildingheight and weight
Greater stiffness, which results in bettercracking and deflection control.
Foundations
The use of post-tensioning in single family
residential slabs on ground is currently thelargest market segment for the industry. Forthis application, the post-tensioning tendonsare usually installed concentrically in the slab
without the benefit of the deviation forceswhich result from draped tendons that arenormally used in elevated structures. Whilethis approach is adequate for lighter loads,a different approach is needed for moreheavily loaded foundations.Two-way mat foundations are used to
support multistory buildings. The prin-ciple of mat foundations is very similar to
that of a floor slab turned upside-down.The distributed soil pressure applies upliftpressure to the bottom surface, which isheld in equilibrium by the vertical con-centrated loads from columns and walls.Similarly, strip foundations behave likeupside-down beams.Post-tensioning of mat and beam foun-
dations has similar advantages to those infloors and beams: More uniform soil pressure distribution Increased shear resistance Reduction in thickness and
reinforcement quantity Compressed construction schedule Improved cracking and
deflection behavior Reduced excavation quantity and depth Improved water tightnessBasically, the designer has the choice be-
tween unbonded monostrand and bondedmultistrand tendons. For thin slabs, includ-ing residential slab on ground, industrialfloor slabs and low rise buildings, unbondedmonostrands are a logical choice. Bonded
multistrand tendons are best for larger foun-dations with heavier loads. They have highercapacity and are bonded, which improvescrack control and local flexural behavior.
Precast
Today many bridges take advantage ofthe combined benefits of precast and post-tensioning, but the use of post-tensioning inprecast buildings has been largely unexploited.
While the benefits of precast elements arewell known, the advantages of combiningprecast with post-tensioning are somewhat
unrealized. Post-tensioning can be usedsplice precast members together to bustructures with fewer joints and bearin
which reduces maintenance and provides structural benefits of continuous memband frames.Construction of fully hybrid precast/c
in-place buildings is perhaps the best wayoptimize both. An example of this approis the new Venetian Macao Resort. For
structure, continuous main beams with meter (66-foot) and 30-meter (98-foot) spwere constructed using 4 inverted pre
continued on page
Visit us at CONEXPO 2008, Booth# S8529
-
7/22/2019 VSL Product Watch Crigler Jan 08.532
3/4STRUCTURE magazine January 200850
The precast secondary beams are installed on top of the corbels of precast main beams afterstressing the continuity tendons. The beams are T- or I-shaped to minimize the weight to 28 tonnes(30 tons) for erection. Half joints at either end of the beams are detailed by using strut-and-tiemodels to ensure the load transfer at the critical zones. In between the typically 4m (13ft) spacedsecondary beams, 75mm (3 in) thick precast planks with cast in lattice girders are installed. Topslab reinforcement is fixed directly on top of the lattice girder to receive the in-situ cast topping.
Level 3 and Level 6 have typical bay layouts of 20m x 20m (66ft x 66ft) and 20m x 30m (66ft x98ft). The structure consists of continuous post-tensioned framing beams, made up of semi-precast
pre-tensioned beams supported on column heads. Simply supported precast and pre-tensioned Tor I shaped secondary beams are supported on the continuous corbels on either side of the mainbeams. Precast planks are placed in between the secondary beams to receive a cast-in-situ topping.The precast beams and planks are installed by custom made high capacity traveling cranes, whichallow placing 25 tonne (27.5 ton) beams at a 50m (164ft) radius.
AFFORDABLECAD
SERVICESGlobal EngineeringTechnologies, LLP
STRUCTURAL CAD SERVICES
Specializing in qualitydrafting services forStructural Engineers
Cost effective,innovative solutions
Fast turnaround
Decades of experience
Complete satisfactionguaranteed
Mon.Fri. 8 am 5 pm EDST
502-589-0149
www.globalengtech.com
NO COMPETE 7CONFIDENTIALITY HONORED
Global EngineeringTechnologies, LLP
i
,
g
g
-
7/22/2019 VSL Product Watch Crigler Jan 08.532
4/4STRUCTURE magazine January 200851
Figure 1: 4-in-1 semi-precast main beams in the sequence of works.
The details of the 4-in-1 semi-precast main beams play a vital role to the success ofVSLs alternative design. The sequence of work is as follows:
Installation of 4 nos. of semi-precast main beams by heavy duty tower craneon column heads.
Stitching of flanges of precast beams to ensure the structural integrity. Fixing of steel reinforcement cages and P-T ducts in between precast beams.
In-situ concrete in-fill of main beam. Span by span stressing of continuity tendons across columns. Installation of precast secondary beams supported by corbels on main beams. Erection of precast planking supported by secondary beams. Fix top reinforcement and cast topping.
Typical weights of precast beams are 20 to 28 tonnes (22 to 28 tons).
An aerial view of the transfer plate under construction.
beams (see Figure 1 below) combined withpost-tensioning and cast-in-place concrete.These beams support the highly loadedfloors, and serve as elements in the seismic/
wind resisting frames. For this project, thesystem was selected to improve constructionspeed and reduce the impact of formworkand shoring on other trades.
Conclusion
The use of post-tensioning in buildings willcontinue to expand, with traditional applica-tions dominating. Post-tensioned structuresinherently use less material when compared
with conventionally reinforced concrete. As wegain a better understanding of the impact ofcement production on the environment, thisfactor will become increasingly important.The next article in this series will address
what to consider when incorporating post-tensioning into a structures design. Theseinclude reviewing the applicable Post-
Tensioning Institute (PTI) and AmericanSociety for Testing and Materials (ASTM)standards and their adequacy for theintended application, and selecting theappropriate materials.
John Crigler, P.E., is Senior Vice President andTechnical Manager of VStructural LLC (VSL).Crigler serves as the Secretary/Treasurer of the
American Segmental Bridge Institute (ASBI).He also serves on the Post-Tensioning Institute(PTI) Technical Activities Board (TAB). Inaddition, he is a member of the AmericanConcrete Institute and the American Society ofCivil Engineers. John can be reached via [email protected].
STAGE 7:
ERECT PLANKING
STAGE 8: CAST
INSITU TOPPING COUPLING BARS AT CORBEL
BENT OUT BARS FOR
SHEAR CONNECTION
CONCRETE PLINTH
WITH RUBBER STRIP
HALF
JOINT
HALF
JOINT
CORBEL CORBEL
500
75
100
5004700 1200
200
1225
STAGE 6: ERECTPRECASTSECONDARYI / T - BEAMS
STAGE 2:STITCHINGBETWEENSEMI-PRECASTMAIN BEAMS
STAGE 4:IN-FILLCONCRETE
STAGE 1:ERECTION OFSEMI-PRECASTMAIN BEAMS
STAGE 3:FIX IN-SITUSTEEL CAGE
STAGE 5:MULTISTRAND TENDON(6 - 19s / 6-22s)
PRETENSIONINGSTRANDS(0.6)