Virginia Transportation Construction Alliance (VTCA)
Joint Conference
with
Salem and Lynchburg Districts
April 26, 2016
Ken King, P.E., Salem District Engineer
Chris Winstead, P.E., Lynchburg District Engineer
2
VDOT Dashboard
3
VDOT Performance Measures
4
Lynchburg District
5
Lynchburg District Organization
Chris Winstead
District Engineer
Don Austin
Appomattox
Residency
John Hays
ADA Business
Dale Totten
ADA Maintenance
Paula K. Jones
Communications
Scot Shippee
Dillwyn Residency
Terry Meadows
ADA Construction
Robert Guercia
ADA Preliminary
Engineering/PIM
Chris McDonald
Regional Operations
Kenneth Martin
Halifax Residency
Lynchburg District Residencies
Appomattox – Amherst, Appomattox, Campbell and Nelson
Counties
Dillwyn – Buckingham, Charlotte, Cumberland and Prince
Edward Counties
Halifax – Halifax and Pittsylvania Counties
Mike Allen
Safety
• Comprised of 10 counties including Amherst, Appomattox,
Buckingham, Campbell, Charlotte, Cumberland, Halifax, Nelson,
Pittsylvania and Prince Edward
• Includes two cities, numerous towns and two of the largest
counties by land area in the Commonwealth
• Responsible for maintenance of more than 15,000 miles of
primary and secondary roads. This is the only district that does
not maintain interstate highways.
• Responsible for 1,986 structures on all roads
6
Lynchburg District
7
Lynchburg District Safety Report
0
10
20
30
40
50
60
70
80
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Cu
mu
lati
ve
Dea
ths
2015 Lynchburg District Traffic Deaths
Target 3-Year Average (2012-2014) 2015 Deaths
• 2015 deaths were about 6.5 percent above the 3-year average • Overall crashes were up from 3-year average by 5.6% • Approximately 40 percent of fatal crashes in 2015 were fixed object off road
(road departure) • FY17-22 HSIP Program has over $31 M planned for road departure mitigation
projects within the district
• Other FY17 projects include pedestrian (sidewalk) projects, district-wide curve countermeasure signage, and road departure countermeasures within the paving schedule
• Locality safety projects included a Flashing Yellow Arrow Retrofit project (Danville) and an Adaptive Signal Control System installation (Lynchburg)
• Ongoing safety projects include an offset right turn lane, left-turn lanes and a roundabout.
8
Lynchburg District Safety
Action Items
• Goals: Zero fatalities, zero injuries, zero preventable accidents
• This FY, 26 total injuries (6 recordable, 3 lost-time).
Most frequent injury types – struck by and sprain/strain
Most common lost-time injury types – slip/trip/fall, sprain/strain & struck by.
• This FY, 20 total accidents and 8 incident (11 preventable). Most common type –
backing.
• Continue to emphasize Slow Down to Speed Up- Safety First and communicating
expectation that employees work together in assessing risks, mitigating risks and
watching each other’s backs when it comes to safety.
• District Safety Committee continues to provide venue for lessons learned. Monthly DAC
Safety Initiative and District Safety Manager’s Meeting.
• District Management continues visits with teams across the district.
9
Lynchburg District Safety
Worker and Contractor Safety
97% 100%
0%
20%
40%
60%
80%
100%
Actual VDOT Actual LAP
% Advertisement On Time- Lynchburg (01/06/15 Dashboard data)
Lynchburg Project Performance 2016 Project Development
District Continuous Improvement Strategies: Frequent/open communication among VDOT and Contractor staff at all levels
Close collaboration between Project Development and Project Delivery staff – Team work
Contract accountability and rapid collaborative response to any slippage
70% Target
2015 Project Delivery (04/12/16 Dashboard data)
Dashboard FY2016 On-Time Delivery Forecast
Fund Contract
Count
Completed
Green
Active
Green
% Green (Forecast)
Target
CN 9 8 0 89% 77%
MN 30 23 1 80% 77%
Dashboard FY2016 On-Budget Delivery Forecast
Fund
Contract
Count
Completed
Green & Yellow
Active
G & Y
% G & Y (Forecast)
Target
CN 9 9 0 100% 82%
MN 30 27 2 97% 90%
11
Lynchburg District Pavement Conditions
12
Lynchburg District Pavement Conditions
Primary Secondary
Target 82% 65%
Predicted 83% 73%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
Percent Sufficient by System (by the end of CY 2016)
Target Predicted
13
Lynchburg District Bridge Conditions
14
Lynchburg District
Operations Performance
Measure
Target
FY15 (July-Dec)
FY16 (July-Dec)
Travel Time
Reliability Index
Vehicle Hours
of Delay TBD 14,527 32,332
Median Incident
Duration 59 58 59.98
Vehicle Hours of Delay data source = RITIS Vehicle Probe Project
Incident data source = VaTraffic: Disabled Vehicles, Vehicle Crashes and Tractor-Trailer Crashes on Interstates and at Special Facilities on Interstates
Strategies and Plans Going Forward:
• Staff are participating in NHI-sponsored event traffic
management class in May.
• Signal Optimization
• Increasing the number of signals able to
communicate to the TOC
Salem District
15
16
Comprised of 12 counties including Bedford, Botetourt, Carroll,
Craig, Floyd, Franklin, Giles, Henry, Montgomery, Patrick,
Pulaski and Roanoke
Includes five cities and numerous towns including the
Commonwealth’s most populous town (Blacksburg)
Responsible for maintenance of more secondary roads than any
other district—some 7,000 miles, in addition to 122 miles of
interstate and 983 miles of primary roads
Responsible for 2,878 bridges with 1,971 on secondary roads,
740 on the primary system and 217 on the interstates
Salem District
17
Salem District Organization
Ken King
District Engineer
Todd Daniel
Bedford Residency
Thelma Ingle
ADA Business
Allen Williams
ADA Maintenance
Jason Bond
Communications
David Clarke
Christiansburg
Residency
Robbie Williams
ADA Construction
Tommy DiGiulian
ADA Preliminary
Engineering/PIM
Chris McDonald
Regional Operations
Lisa Hughes
Martinsville
Residency
Salem District Residencies
Bedford – Bedford and Franklin Counties
Christiansburg – Floyd, Giles, Montgomery and
Pulaski Counties
Martinsville – Carroll, Henry and Patrick Counties
Salem – Botetourt, Craig and Roanoke Counties Dan Collins
Salem Residency
Mike LaFon
Safety
18
Salem District Safety Report
0
10
20
30
40
50
60
70
80
90
100
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Cu
mu
lati
ve
Dea
ths
2015 Salem District Traffic Deaths
Target 3-Year Average (2012-2014) 2015 Deaths
19
Salem District Safety
Action Items
• There were 84 fatalities in Salem District in 2015.
• 2015 fatalities were 11 percent below the 2012-2014 average; three year
average is 94.3 fatalities per year.
• 2015 fatalities were 21 percent above the target value of 69 fatalities.
• Approximately 57% of fatal crashes in 2015 were fixed object off road (road
departure).
• FY17-22 HSIP Program has over $19 M planned for road departure
mitigation projects within the district.
• I-77 ATSMS project award awarded in February 2014 for $9.6 M. Anticipated
completion by mid-summer 2016.
• Locality safety projects included Flashing Yellow Arrow (Roanoke)
• Shoulder widening, guardrail, rumble strips on three corridors
• Route 100 – Under Construction – $1.9 M
• Route 311 – Advertised December 2014 – $3.5 M
• Route 220 – Advertisement late 2015 – $3.7 M
20
Salem District
Worker and Contractor Safety
• District Recordable Injury Rate and Lost Time Injury Rate continues to be
reduced.
• Leading causes include Strains, Struck by Object, and Walking Working
Surfaces (stepping in holes).
• Engage managers and employees in accountability for safe operations, using
a new Facilities Self Review checklist that informs and encourages safe
operations.
• Participate in annual Work Zone Awareness Week, April 11-15, 2016.
• Very focused on work zone training for installation and removal of traffic
control devices. Daily work zone review checklists are required of all work
areas.
• Coordination and notification for work zone is very important.
• Notify Traffic Operations Center at 1-888-782-7982 for all work zones
(sign/cone up to sign/cone down)!
Salem Project Performance Project Development & Delivery
District Improvement Strategies:
• Continue working with our localities to help develop/monitor schedules and holding quarterly teleconferences to discuss project progress.
• DE, DME and DCE working closely with contractor’s senior managers and industry leaders to improve quality and program delivery.
• Added a third ACE to serve the Bedford and Martinsville Residencies and re-structured staff under the District Project Controls Engineer to improve
consistency with schedules / CTD’s and to help identify scope, constructability concerns, and industry resource constraints.
70% Target
32.8% 32.4%
District Obligations/Commitments
reporting discontinued; Measure
for this area being reworked
2016 Project Delivery (01/05/16 Dashboard data)
Year’s Active Green % Green
Contract Count On-time (Forecast)
CN 5 4 0 80% 77%
MN 86 77 1 91% 77%
CN 5 4 1 100% 82%
MN 86 80 4 98% 90%
Dashboard FY2016 On-Time Delivery Forecast
FundCompleted Green On-
timeTarget
Dashboard FY2016 On-Budget Delivery Forecast
FundCompleted Green &
Yellow On-budget
Active Green &
Yellow On-budget
% Green & Yellow (Forecast)
TargetYear’s
Contract Count
22
Salem District Pavement Conditions
23
Salem District Pavement Conditions
24
Salem District Bridge Conditions
25
Salem District Operations
Measure
Target
FY15
(July-Mar)
FY16
(July-Mar)
Travel Time
Reliability Index
Vehicle Hours of
Delay TBD 289,094 532,483
Median Incident
Duration 48 49.5 50.88
Vehicle Hours of Delay data source = RITIS Vehicle Probe Project
Incident data source = VaTraffic: Disabled Vehicles, Vehicle Crashes and Tractor-Trailer
Crashes on Interstates and at Special Facilities on Interstates
Strategies and Plans Going Forward:
• I-77 Active Traffic & Safety Management System/Variable Speed Limit
Project
• G4S – Beginning device testing with system integration to start
soon.
• Algorithm developed
• Day 1 operations program 90% developed.
• Valley View Boulevard, Southgate Drive and Exit 150 Projects continue.
• Signal Optimization
• Increasing the number of signals able to communicate to the TOC.
• Left turn phasing evaluations: Going from protected only to protect-
permissive phasing.
• Traffic Incident Management Training (2 classes)
26
Robert Guercia, P.E.
and
Tommy DiGiulian, P.E.
Consulting Engineering Opportunities
Upcoming Construction Projects
Lynchburg and Salem Districts
27
Intersection Improvements at Route
501 & 642
Halifax County
Est. Construction Cost -
$1.4 million
Advertisement –
November 8, 2016
28
UPC Route Locality Project Description Projected AD Estimated Cost
90676 40 Charlotte County Route 40 over Louse Creek 2/9/2016 $4,963,149
106281 40 Charlotte Courthouse Pedestrian Safety in Charlotte Courthouse 3/8/2016 $494,901
104678 460 Campbell County Construct Offset Right Turn Lane at Route 656 5/10/2016 $429,154
108558 Various Districtwide DP3A17 Lynchburg Districtwide Secondary Pipe Rehabilitation 7/26/2016 $474,387
108559 Various Districtwide DP3A17 Lynchburg Districtwide Secondary Pipe Rehabilitation 7/26/2016 $242,964
107018 Various Districtwide Lynchburg Districtwide Curve Counter Measures 8/9/2016 $500,000
108200 Various Districtwide Districtwide Guardrail Upgrades 8/9/2016 $1,000,000
101037 761 Pittsylvania County Bridge and Approaches at Straightstone Creek 10/11/2016 $1,632,521
104951 501 Halifax County Construct Left and Right Turn Lanes at Route 642 11/8/2016 $1,369,211
104676 151/6 Nelson County Construct Left Turn Lane at Route 635 11/8/2016 $900,000
104677 151/6 Nelson County Construct Left Turn Lanes at Route 638 11/8/2016 $1,256,163
5240 610 Charlotte County Trench Widening and Overlay 12/13/2016 $1,238,262
12 Projects - Total Estimated Cost of $15 Million
29
UPC Route Locality Project Description Projected AD Estimated Cost
105755 Revenue Sharing Campbell County Liberty Mountain Road – Construction of new alignment 3/27/2016 $6,035,929
106561
Transportation Alternatives Buckingham Buckingham Streetscapes Phase 3 5/31/2016 $224,000
107205 Revenue Sharing Danville Route 58 – Widen from 2 to 3 lanes. 6/30/2016 $1,050,000
107452 Revenue Sharing Lynchburg Liberty University Phase 2 Construction of New Road 6/30/2016 $3,200,000
107212 Revenue Sharing Lynchburg Pavement Overlay Project – Milling and Overlay of Various Streets throughout City 5/30/2016 $300,000
108420 Revenue Sharing Farmville Pavement Overlay Project – Milling and Overlay of Various Streets throughout Town 6/30/2016 $760,956
6 Projects - Total Estimated Cost of $11.6 Million
Salem District
30
31
Project Development
Consultant Engineering Opportunities
Route 220 Safety Improvement Project
Proposed Phases 1 and 2
Total Funding = $79 Million
RFQ Release Date – April 25, 2016
RFP Release Date – Fall 2016
Design-Build Contract
* Final project limits to be based on actual costs.
32
UPC Route Locality Project Description Projected AD
Date
Estimated
CN Cost
($Millions) 56899 I-81 Montgomery/Pulaski
Counties
Interstate 81 NB Bridge and Rte. 232 Bridge Replacement 2016 $53.9
103210 220 Botetourt County Rte. 220 Replace 2 Narrow Structures 2016 $7.8
106802 99 Town of Pulaski/Pulaski
County
Rte. 99 - Paved Shoulder, Guardrail Replacement &
Lighting
2016 $1.2
97043 221 Bedford County Rte 221 & Rte 668 Intersection Improvements 2016 $0.4
107049 122 Franklin County Rte. 122 Safety Improvements 2016 $2.0
51916 668 Bedford County Rte. 668 Bridge Replacement Over Norfolk Southern
Railroad
2016 $3.5
104675 220 Henry County Rte. 220 Safety Improvements 2016 $3.5
96069 8 Montgomery County Rte. 8 & Rte. 669 Intersection Improvements 2016 $1.2
93277 122 Franklin County Rte. 616 & Rte. 122 Intersection Improvements 2016 $0.4
4544 606 Montgomery County Rte. 606 Rural Rustic Improvements 2016 $1.2
99542 81 Roanoke County Rte. 81 Exit 140 Park ‘n Ride Facility Expansion 2016 $3.1
67309 693 Pulaski County Rte. 693 Reconstruction 2016 $1.0
107053 24 Bedford County Rte. 24 Safety Improvements 2017 $1.5
107051 100 Giles County Rte. 100 Safety Improvements 2017 $3.6
11908 10th
Street City of Roanoke 10th
Street Reconstruction (Second Phase) 2016* $12.4
15 Projects - Total Estimated Construction Cost of $96.7 M
*Subject to HB2 Funding
33 33 Projects - Total Estimated Cost of $39.3 M
UPC Locality Project Description Projected AD Estimated CN
Cost ($Millions)
87002 Henry Co Collinsville Streetscaping 2016 $1.30
106544 Henry Co Collinsville Street Signs, Ped Signals 2016 $0.07
98220 Roanoke Co Route 115, Plantation Road Corridor Improvements 2016 $0.90
103607 Roanoke Co Plantation Road Streetscape Improvements 2016 $3.10
101264 Pulaski Co Roundhouse St/Rte 11 Intersection Improvements 2016 $0.67
104128 Floyd Town of Floyd Heritage Pathways Phases 3-4 2016 $0.60
104241 Blacksburg Construct Sidewalk West side of Giles Road 2016 $0.40
104242 Christiansburg Storm Drainage Improvements 2016 $0.90
104248 Roanoke Franklin Rd Bridge Replacement 2016 $15.00
104252 Rocky Mount Scuffling Hill Drainage Improvements 2016 $0.72
104253 Vinton Glade Creek Greenway 2016 $0.23
105303 Montgomery Co SRTS Belview Elementary School 2016 $0.16
105304 Montgomery Co SRTS Auburn Elementary/Middle School 2016 $0.20
105738 Roanoke Glimer Ave Box Culvert Replacement Over Trout Run 2016 $0.55
105765 Blacksburg Construction of New Off Road Trail along Cohee Road 2016 $0.10
105766 Blacksburg Huckleberry Trail Segment – Downtown Blacksburg 2016 $0.10
105768 Christiansburg Drainage Improvements to Town Streets 2016 $1.00
105770 Christiansburg Storm Drains and Sidewalk Improvements 2016 $0.30
105772 Christiansburg Drainage Improvements – Hans Meadow Drive 2016 $1.00
105775 Blacksburg Research Center Drive Improvements 2016 $0.50
107275 Bedford Co Corporate Dr Extension 2016 $0.60
107281 Blacksburg Sidewalk Tripping Hazard Removal 2016 $0.03
107282 Blacksburg Traffic Signal – Glade Rd at University City Blvd 2016 $0.40
107283 Blacksburg Sidewalk Missing Links – Various Locations 2016 $0.11
107286 Christiansburg Pavement Overlays at Various Locations 2016 $1.00
107294 Giles Co Springdale Rd Reconstruction 2016 $0.12
107310 Roanoke Co Kenwick Tr Drainage Improvements 2016 $0.04
107312 Roanoke Co Belle Meade Dr Drainage Improvements 2016 $0.04
107313 Roanoke Co Merriman Rd Drainage Improvements 2016 $0.08
102763 Montgomery Co Rte 658 Meadow Creek Rd Realignment 2017 $1.09
105439 Roanoke Roanoke River Greenway – Bridge the Gap 2017 $7.00
106486 Salem Eddy Ave Bike/Ped Bridge 2017 $0.84
107298 Pearisburg Pavement Reconstruction and Overlay at Various Locations 2017 $0.12
34
Dale Totten, P.E.
Maintenance Contracts
Lynchburg District
• Predicted to exceed performance targets for Primary and Secondary Systems
by end of Calendar Year 2016.
• Residencies and district partners are engaged in planning pavement
solutions.
• Evaluating pavement locations and preparing for new paving projects
throughout the year.
35
Lynchburg District
Pavement Action Plan
36
Lynchburg District Paving Mileage
Advertised
37
Lynchburg District
Resurfacing Program
Treatment # of 2015
Contracts
2015
Quantities
Contract
Value 2015
# of 2016
Contracts
2016
Estimated
Quantities
Contract
Value
2016
Plant Mix 7 271,463 $30.5 M 6 215,000
Tons $24.3M
Latex 1
6,991
Tons
$2.4M 1 4,300
Tons $1.5M
Surface 3 5,593,335
SY $9.0M 3
5,400,000
SY $8.8M
Total 11 $42.3 M 10 $34.6M
2015 advertised Fall 2015 and Spring 2016 for CY2016
2016 advertise Fall 2016 for CY2017
38
System 2016 Projects
Lane Miles
Estimated
Cost
Preliminary
2017
Lane Miles
Estimated
Cost
Primary 386 $33.0 M 216
$22.5 M
Secondary 1095 $ 9.3M 1360
$12.1M
Total 1481 $42.3 M 1576 $34.6M
Lynchburg District currently has 113 structurally deficient (SD) structures:
• 81 - SD bridges
• 32 - SD culverts
Anticipate eliminating 34 SD structures in FY16:
• 17-SD bridges
• 17-SD culverts
Continued effort to target SD structures
• Focus on SD culverts (30 SD culverts on Secondary System)
Continue focus on Condition Yellow Structures
• In addition to the planned 34 SD structures;
• Replaced 2 posted (condition yellow) bridges
• Replaced 2 timber decks this year
Concentrate efforts on the Secondary System
• 98 of the 113 deficient structures
94.3% of Lynchburg’s VDOT maintained structures are non-deficient
39
Lynchburg District
Bridge Action Plan
FY16
• Preventive Maintenance - $2.4 M • Restorative Maintenance - $0.7 M • Replacements - $7.3 M • Bridge Inspection - $3.3 M
FY17 • Preventive Maintenance - $2.5 M • Restorative Maintenance - $3.0 M • Replacements - $7.9 M • Bridge Inspection - $3.5 M
FY18
• Preventive Maintenance - $1.8 M • Restorative Maintenance - $1.7 M • Replacements - $7.7 M • Bridge Inspection - $3.7 M
40
Lynchburg District
Bridge Maintenance
Preventive Maintenance includes cleaning, joints, epoxy overlays and bridge painting.
Restorative Maintenance
includes rigid deck overlays and super/sub repairs.
Replacements includes
superstructure and culvert/pipe replacements.
Bridge Inspection
includes the scheduled inspections required for all structures (bridges and large culverts).
Roadside
FY16 - $1.2 M
FY17 - $1.0 M
FY 18 - $1.0 M
Drainage/Pipes/Slopes
FY16 - $800K
FY17 - $800K
FY18 – 1.0 M 41
Lynchburg District
Other Maintenance Contracts
42
Allen Williams, P.E.
Maintenance Contracts
Salem District
43
Salem District
Pavement Action Plan
• Advertising target for paving was $53M.
• As of December 31, the district plans to pave 1327 lane miles.
• Based on planned paving, the district is predicted to meet performance
targets on the interstate and primary systems but not on the secondary
system in CY17.
• Currently the district has 0 lane miles with CCI < 30 on the interstate system.
44
Salem District Paving Mileage
Advertised
45
Salem District
Resurfacing Program
Treatment # of 2015
Contracts
2015
Quantities
Contract
Value 2015
# of 2016
Contracts
2016
Quantities
Contract
Value 2016
Plant Mix 27
230,255
tons
$36.6 M 30
263,448
tons
$39.2 M
Latex 3
8,807
tons
$3.5 M 3
8,958
tons
$4.1 M
Slurry Seal 2
1,421,361
SY
$3.7 M 3
1,454,706
SY
$3.5 M
Surface 6 2,66,227
SY $3.9 M 10
4,573,953
SY $6.8 M
Total 38 $47.7 M 46 $53.6 M
46
System 2016 Lane
Miles
Est. Cost Preliminary
2017 Lane
Miles
Est. Cost
Interstate 25 lane miles $6.5 M 28 lane miles $7.9 M
Primary 336 lane miles $27.5 M 290 lane miles $24 M
Secondary 966 lane miles $19.6 M 718 lane miles
$17.6 M
Total 1327 lane miles $53.6 M 1036 lane miles
$49.5 M
Salem District currently has 164 structurally deficient bridges.
• 86% of those bridges are in a plan.
• 22 are currently under construction.
• 96 are in the PE phase.
• 24 are in the Six-Year Program awaiting PE start.
Salem District is currently at 94.3% non-SD.
This is first time we have been above the 94% target.
We continue to target structurally deficient structures in our planning
• $11.9 million (30%) of our FY16 maintenance allocation targets SD structure
projects
• FY16 goal was to eliminate 14 SD structures (net); eliminated 41 so far but
anticipate pace of new SDs to increase in the coming quarters
We also continue to maintain our “Good” bridges
• Currently 663, 22% of our structure inventory, is rated 5
• $21.5 million (55%) of our FY16 maintenance allocation targets preventive and
restorative maintenance on “Good” structures 47
Salem District
Bridge Action Plan
FY-16
• Preventive Maintenance - $12.6 M • Restorative Maintenance - $8.9 M • Replacements - $11.9 M • Bridge Inspection - $4.5 M
FY-17 • Preventive Maintenance - $5.1 M • Restorative Maintenance - $15.4 M • Replacements - $12.8 M • Bridge Inspection - $4.5 M
FY-18
• Preventive Maintenance - $6.9 M • Restorative Maintenance - $9.2 M • Replacements - $8.2 M • Bridge Inspection - $4.5 M
Preventive Maintenance includes cleaning, joints, and bridge painting.
Restorative Maintenance
includes deck overlays and super/sub repairs.
Replacements includes
superstructure and culvert/pipe replacements.
Bridge Inspection
includes the scheduled inspections required for all structures (bridges and large culverts).
48
Salem District
Bridge Maintenance
49
Roadside
FY14 - $8.5 million
FY15 - $8.0 million
FY16 - $8.1 million
Drainage/Pipes/Slopes
FY14 - $12.0 million
FY15 - $14.5 million
FY16 - $17.6 million
Salem District
Other Maintenance Contracts
50
Anne Booker, P.E., PTOE
Regional Traffic Engineer
Upcoming Project Opportunities
Lynchburg and Salem Districts
51
Regional Operations
Strategies and Plans Going Forward
Focus on Real-Time Traffic Operations
• Signals, especially in support of detours
• Interstate 77 ATSMS with variable speed limits
• Smart Road Technology Funds will help fund ITS investments
• CCTV cameras
• Dynamic Message Boards
• 360 degree intersection cameras
Focus on Traffic Safety
• Continuing use of Flashing Yellow Arrow and backplates
• Roadway departure counter measure projects
• Residency-focused safety support and collaboration with paving schedule
Statewide TOC and ATMS Programs
• As of March 1, Iteris is currently staffing the Traffic Operations
Centers (TOC) floor services in a 24-month contract.
• VDOT intends to re-procure SSP/TOC, ATMS, and ITS Maintenance
as three separate contracts.
• VDOT plans to coordinate between all three contracts using Program
Management and Support Services Contract.
52
I-77 Active Traffic & Safety Management System Fancy Gap Mountain, Carroll County
• Objective: Integrated traffic management system will dynamically
adjust speed limits based on visibility
• Design Build Project awarded in February 2014 for $9.6 M
• Status: Contractor beginning sign testing with system integration with
the Salem TOC to follow soon
• Anticipated Completion: Mid-summer 2016
• System
53
54
Regional Operations On-Call
Project Opportunities
• Contracts will have a one-year initial term with two, one-year
renewable terms for a maximum contract duration of three years.
• Signals - On-call regional signal contract advertisement serving
Salem, Lynchburg, and Bristol Districts (Bid Letting on 4/27/16).
• Guardrail - Upgrade existing guardrail or new installation. Scheduled
for completion by December 2017.
• Salem Guardrail – $2.1 M
• Lynchburg Guardrail – $1.6 M
• Pavement Markings – Refresh existing pavement markings, markers
and messages. Scheduled for completion by December 2017.
• Salem Pavement Markings – $3 M
• Lynchburg Pavement Markings – $1.7 M
55
Regional Operations
Project Specific Opportunities
• Lynchburg District - Guardrail
− One scheduled advertisement in the next 6-8 months for guardrail
upgrades with an estimate of $1M
• Lynchburg District – Signs and Pavement Markings
− One scheduled advertisement in the next 18-24 months to replace
curve signage with an estimate of $900,000
• Salem District - Guardrail
− Four scheduled advertisements in the next 6-8 months for
guardrail upgrades with a grand total of $6M
• Salem District - Signs
− Three scheduled advertisements in the next 18-24 months to
replace ground mount signs with a grand total estimate of $2M
56
Terry Meadows, P.E.
and
Robbie Williams, P.E.
District Construction Programs
57
Focus Areas for 2016 Construction Season
• Project safety and work zone safety
• Pavement markings and work zone maintenance
• Quality construction both pavements and bridges
• Uniform tack application
• Schedule required prior to starting work
• Starting work within 15 days after Notice to Proceed
• Material invoices to be submitted prior to payment for work
58
Specification Changes (Asphalt)
• Section 211 - 50 gyration mixes to improve quality
• Section 310 - Tack & Bond - Tack as a pay item
• Section 305 - RAP use as shoulder stone
• Section 315 - Scratch & Leveling Course – defines quantitative and
compensation
• Section 515 – Cold Planing (Milling) Operations – Requirements
(time and disincentives)
• Pilot Projects to emphasis quality (increased density and
consistency)
59
MITS/PLAID
MITS/PLAID - MITS (Materials Inventory and Tracking System)
PLAID (Producer Lab Analysis and Information Details)
• Further implementation of system adding
• TL-102
• Control Charts
• Quality Management Report (QMR)
• Automatic Notifications
• Comparison Analysis (D2S) with flag
• Refined Access Control
• Localities, consultants, inspectors and contractors should be
guided by the Locally Administered Projects Manual (Updated
February 2014)
http://www.virginiadot.org/business/locally_administered_projects
_manual.asp
• This Locally Administered Projects manual has been written to
assist the Local Public Agency (LPA) in the administration of
federal and state funded transportation projects.
• FHWA and VDOT are making concentrated efforts to ensure that
LAP projects are being executed in accordance with the
requirements of the LAP Manual.
60
Locally Administered Projects (LAP)
61
Materials Certification School Program
• Transitioning to the Virginia Community College System.
Self Study Exams and Proficiencies
• Please contact Toni Quesenberry in Salem at 540-387-5381 or Bill Wise in
Lynchburg at 434-856-8105 for out-of-sequence “self study” and proficiency
exams.
• In Salem District, these exams are typically scheduled for every other Friday,
with a maximum of eight exams per date. Cut-off date for these exams is
November 30.
• In Lynchburg District, these exams are scheduled periodically. The cut-off
date is mid-December.
62
Civil Rights
On-the-Job Training Manual for Standard Pre-Approved Job
Classifications
• A committee consisting of VTCA, VDOT, contractor, FHWA and Department of
Labor representatives was formed to update the training manual (last revised Jan.
1995)
• A draft of the manual was submitted by VTCA to the construction industry for
comment.
• Comments are due by Monday, May 2, 2016
If you have any questions about this manual,
Please contact:
VTCA at 804-330-3312
or any
VDOT Civil Rights Manager
63
Environmental and VPDES Changes
Read permits and special provisions carefully.
• Permit conditions and time of year restrictions regarding
threatened and endangered species (i.e. bats, logperch, bog
turtles, others) continue to be major factors affecting projects.
Rain gauges and log are required.
• Inspections and completion of the Construction Runoff Control
Inspection Forms (C107) every seven calendar days and within
48 hours following a measurable storm event (0.25 inches).
64
Environmental and VPDES Changes
• Temporary seeding required when operations are anticipated to be
suspended for greater than 14 days. Permanent seeding within 24
hours of reaching final grade.
• Concrete trucks may not be washed out on the ground.
• The SWPPP and VPDES permits for off-site facilities must be obtained
by the Contractor.
• Obtaining SWM (inspector) certifications will become a priority for both
VDOT and consultant inspectors.
65
Contracts 2016 2017 2018 2019
Contract 1
(2014)
$1.5 m $1.65 m $1.65 m
Contract 2
(2014)
$1.5 m $1.65 m $1.65 m
New District
Wide
TBD TBD
New District
Wide
TBD TBD
TOTAL $3 m $3.3m $3.3 m TBD
66
Contracts 2016 2017 2018 2019
Contract IV $1.5 M
Contract II
(2014)
$3.75 M $3.25 M
Contract III $3.75 M $3.25 M
Southgate $1.2 M $1.0 M $1.0 M
Exit 105 $0.6 M $1.2 M $1.2 M $1.2 M
New District
Wide
$1.25 M $3.0 M $3.0 M
New District
Wide
$1.25 M
$3.0 M $3.0 M
New District
Wide
$3.0 M
$3.0 M
Total $ 10.8 M
$ 11.2 M $11.2 M
$10.2 M
67
Chris Winstead, P.E.
Lynchburg District Engineer
and
Ken King, P.E.
Salem District Engineer
68
State of Good Repair
69
State of Good Repair
Prioritization Process Schedule
70
State of Good Repair Requirements
§33.2-369(B) and (C)
71
State of Good Repair – Preliminary
Percentage by District
72
HB2
District Number of Projects COST
Lynchburg 23 $ 85,765,598
Salem 19 $ 113,441,188
73
HB2 Revised Funding Scenario
Salem District
Organization Name Project Title Project
Benefit Score PROJECT_HB2_COST
Score Divided
by HB2 Cost
GRTC Transit Accessibility Improvement on
Edgewood St.(Roanoke) 1.234 $ 350,811 35.162
Roanoke Valley TPO U.S. 220 Communications and Adaptive
System Project 1.154 $ 422,500 27.306
Henry County US 58 East Turn Lane Construction at US
58/220 By-Pass 3.403 $ 1,654,198 20.573
City of Galax Cranberry Road Improvements 6.220 $ 3,067,161 20.280
City of Salem Multimodal Improvements along
Boulevard-Roanoke for Veterans 1.537 $ 884,881 17.369
Carroll County Route 52 North Spot Improvements 5.172 $ 3,731,701 13.858
City of Roanoke Colonial Avenue Improvements 2.631 $ 2,545,000 10.336
City of Salem UPC 8753 East Main Street Route 460
Phase I 2.847 $ 2,912,984 9.772
County of Franklin Safety Improvements to Route 122 at
Route 636 Intersection 2.585 $ 2,718,576 9.510
Town of Blacksburg North Main Intersection Improvements at
460 Bypass 3.110 $ 3,316,565 9.377
New River Valley MPO Route 460 at Franklin Street EB Ramp
Construction 1.439 $ 2,124,395 6.772
74
HB2 Revised Funding Scenario
Salem District
Organization Name Project Title Project
Benefit Score PROJECT_HB2_COST
Score Divided
by HB2 Cost
County of Roanoke Route 311 / Route 419 Int. Safety &
Congestion Improvements 1.143 $ 1,957,006 5.842
County of Roanoke Route 419 Widening, Safety, and
Multimodal Improvements 2.714 $ 4,853,432 5.591
Town of Christiansburg N. Franklin Street - Peppers Ferry Road
Connector Phase II 2.482 $ 9,340,000 2.657
County of Roanoke Lila Drive / Route 115 Intersection Safety
Improvements 0.280 $ 1,269,396 2.203
Roanoke Valley TPO Roanoke River Greenway--Green Hill Park
to Riverside Park 0.949 $ 4,542,105 2.090
Central Virginia MPO Route 221 Congestion and Safety
Improvements 1.456 $ 8,137,995 1.790
Botetourt County I-81 Safety Improvements from MM 166.5-
168.5 5.762 $ 35,151,285 1.639
Town of Christiansburg N Franklin St - Cambria St Intersection/N
Franklin Corridor 1.195 $ 7,841,152 1.524
City of Roanoke 10th Street Reconstruction 1.538 $ 12,451,245 1.235
75
HB2 Funding Scenario Revisions
Salem District
76
Adopted HB2 Recommendations Lynchburg District
Organization Name Project Title Project
Benefit Score PROJECT_HB2_COS
T Score Divided by
HB2 Cost
County of Prince
Edward US 460 at VA 307 16.859 $ 2,744,657 61.424
Nelson County Route 29/655 Intersection Improvement 2.915 $ 1,133,329 25.722
Central Virginia
Metropolitan Planning
Organization Waterlick Congestion and Safety
Improvements 6.954 $ 3,233,297 21.507
County of Charlotte Crafton Gates US 360/Rt.47 Intersection
Improvements Project 0.508 $ 255,691 19.849
Danville MPO Route 58-Route 311 Intersection
Improvement 6.241 $ 3,393,452 18.391
County of Halifax Route 601, Buckshoal Road Safety
Improvements 5.088 $ 3,016,656 16.866
County of Prince
Edward US 15/VA 692 Intersection (Kingsville) 4.460 $ 2,808,037 15.882
County of Buckingham Intersection 15 & 636 (Shepards Corner) 3.771 $ 2,652,279 14.218
Nelson County Route 151/664 Turn Lane 1.234 $ 925,177 13.340
County of Buckingham Intersection of W James Anderson Hwy & S
James River (60&56) 3.142 $ 2,967,687 10.588
City of Danville Mount Cross Road Widening Phase 1 1.248 $ 1,283,365 9.721
77
Adopted HB2 Recommendations Lynchburg District
Organization Name Project Title Project
Benefit Score PROJECT_HB2_COS
T Score Divided by
HB2 Cost
Greater Lynchburg
Transit Company Central Business District Circulator 0.400 $ 479,348 8.351
Campbell Route 501 Turn Lanes @ Route 633 1.947 $ 2,478,998 7.853
County of Prince
Edward US 15/ VA 665 Intersection (Worsham) 3.445 $ 4,989,509 6.905
County of Charlotte Heartland Regional Business Park Entrance 0.514 $ 789,197 6.508
Campbell Route 501 Shoulder Widening 1.405 $ 2,171,487 6.470
Appomattox County 460/609 Turn Lanes 0.690 $ 1,182,981 5.834
Pittsylvania County Climax Road Improvements 0.495 $ 1,317,000 3.759
Town of Altavista Main Street and Lynch Mill Road
Intersection 0.847 $ 2,370,161 3.574
Appomattox County 460/630 Turn Lanes 0.232 $ 721,625 3.213
County of Amherst Route 682 Woody's Lake Road 2.029 $ 7,855,088 2.583
County of Halifax US 501 Passing Lanes and Shoulder
Widening 3.473 $ 19,794,412 1.754
Lynchburg Oddfellows Road Segment B2 2.796 $ 17,202,165 1.625
Emphasis:
Virginia Unique Standards are more stringent than Federal standards.
Review applicable standards for compliance
Global Harmonization becomes effective June 1, 2016 to include labeling,
SDS and training of employees
Virginia Administrative Regulations Manual requires training and usage of
equipment and tools be in compliance with manufacturers
recommendations.
Reporting fatalities and catastrophes. Fatalities within 8 hours
Any work-related inpatient hospitalization, amputation or loss of eye within 24 hours
78
Safety Points
Worker and Contractor Safety
• Review and update required
training
• Prepare personnel for the
day’s tasks.
Ensure staff is knowledgeable of:
• SDS Data and how to obtain
access while on site. Time is paramount in an emergency
• Virginia and OSHA emphasis on misclassification of workers – claiming
employees as independent contractors
79
Safety Points
Worker and Contractor Safety
Lynchburg District Contacts
Chris Winstead, P.E., District Engineer
434-856-8173
Robert Guercia, P.E., Engineering, Planning & Investment
434-856-8174
Terry Meadows, P.E., Construction
434-856-8317
Dale Totten, P.E., Maintenance
434-856-8175
Anne Booker, P.E., PTOE, Traffic Engineering
540-375-0143
Chris McDonald, Operations
540-375-0114
80
Salem District Contacts
Ken King, P.E., District Engineer
540-387-5348
Robbie Williams, P.E., Construction
540-387-5482
Tommy DiGiulian P.E., LS, Engineering, Planning & Investment
540-387-5356
Allen Williams, P.E., Maintenance
540-387-5346
Anne Booker, P.E., PTOE, Traffic Engineering
540-375-0143
Chris McDonald, Operations
540-375-0114
81
82
Questions?