Virginia Aviation Board Meeting Agenda
Thursday, December 2, 2021 The Virginia Aviation Board will hold a meeting at 10:00 a.m., Thursday, December 2, 2021 at the Metropolitan Washington Airports Authority Headquarters, 5th Floor Board Room, 2733 Crystal Drive, Arlington, VA 22202. Following CDC guidelines and the Governor’s guidance, individuals considered fully vaccinated are not required to wear face coverings. Face coverings are required for those not considered fully vaccinated.
1. Call to Order
Rod Hall, Chairman
(5 minutes)
2. Introduction of New Board Members Rod Hall, Chairman (5 minutes)
3. Review and approve August 19, 2021 minutes Rod Hall, Chairman (5 minutes)
4. Kappa Alpha Psi Fraternity Youth Aviation Program Ken Bynum, Esq. Alexandria-Fairfax Alumni Chapter
(5 minutes)
5. Virginia Aviation Board Resolutions A. David Darrah, Warrenton-Fauquier Airport B. Ed Wallis, Stafford Regional Airport C. Local Government Support of Airports
Rod Hall, Chairman (10 minutes)
6. Leesburg Executive Airport Activities and Remote Tower Scott Coffman Manager
(15 minutes)
7. DOAV Director’s Update Mark Flynn DOAV
(15 minutes)
8. VAOC Update Mickey Hines, VP VAOC
(10 minutes)
9. VABA Update Bud Oakey, President VABA
(10 minutes)
10. Old Business A. Virginia Air Transportation System Plan Update Airport Program
Manual – Local Service Airports B. Airport Program Manual – Local Service Airports
Stephanie Ward Meade Hunt Cliff Burnette DOAV
(30 minutes)
(10 minutes)
11. New Business
A. Airport Licensing Issue – Lunenburg County Airport Cliff Burnette DOAV
(5 minutes)
B. Consideration of Amended FY22 Entitlement Utilization Plans
Mike Swain DOAV
(10 minutes)
VAB Package December 2021 2
C. Virginia Aviation Board Review Tentative Allocations from the Commonwealth Aviation Fund
Mike Swain DOAV
(10 minutes)
12. Public Comment Period (3 minutes per person to address the board)
Rod Hall, Chairman
13. Board Member Comments and Reports
Rod Hall, Chairman
(5 minutes)
14. Adjournment
VAB Package December 2021 3
Virginia Aviation Board Meeting Minutes
The Virginia Aviation Board held a meeting on Thursday, August 19, 2021, at the Hilton Norfolk The Main 100 E. Main Street Norfolk, VA 23510. The meeting was audio recorded. The audio recording, meeting documents, and presentation materials are available on the Virginia Department of Aviation’s website, www.doav.virginia.gov. MEMBERS
Roderick D. Hall, Chairman Absent TBD, Region 1 n/a Victoria Cox, Region 2 Present Derek M. Hardwick, Region 3 Present Alan C. Abbott, Region 4 Present Maggie Ragon, Region 5 Present TBD, Region 6 n/a Vanessa Christie, Region 7 Present
OTHER ATTENDEES
Mark K. Flynn, Director Virginia Department of Aviation DOAV staff, state government representatives, federal government representatives, airport sponsors and managers, consultants, engineers, business owners, and city and county representatives were also present.
1. Call to Order Derek Hardwick, Vice Chairman
The vice-chairman called the meeting to order at 10:09 a.m.
2. Military Aviation Museum Presentation Nicole Lutz, Military Aviation Museum
Nicole Lutz, Military Aviation Museum education coordinator provided a presentation on museum activities. Ms. Lutz noted that a financial contribution from the department has helped in promoting aviation programs throughout the year. Slides from the presentation are available on the DOAV website.
3. Advanced Air Mobility Presentation
A. Presentation Dr. Michael Patterson NASA Langley
VAB Package December 2021 4
Dr. Patterson provided a presentation on Advanced Air Mobility and highlighted opportunities for aviation as a new technology. Slides from the presentation are available on the DOAV website.
B. Resolution
Derek Hardwick, Vice Chairman
A resolution declaring the board’s acknowledgement of the importance and support of Advanced Airport Mobility was presented. Resolution attached. Motion to approve: Abbott Second: Christie Vote: Aye: Cox, Abbott, Ragon, Christie; Nay: none
4. Virginia Air Transportation System Plan Update Stephanie Ward Mead & Hunt
Mr. Burnette introduced Stephanie Ward, of Mead & Hunt, to provide an update on the status of the Virginia Air Transportation System Plan, am FAA requirement for the agency to continue eligibility for federal funding. Ms. Ward presented an update on the status of the plan. Slides from the presentation are available on the DOAV website. Ms. Ward fielded questions about inclusion of advanced air mobility in the plan.
5. Economic Development Strategic Planning Committee Report
Vicki Cox, VAB
A. Report
Ms. Cox provided a report from the Economic Development Strategic Planning Committee meeting, noting that they will continue a deeper dive into Advanced Air Mobility and noted the committee’s work in prioritizing lengthening appropriate airport runways to over 5,000 feet.
B. Vacancy
Ms. Cox reported that there is currently a VAB representative vacancy on the Economic Development Strategic Planning Committee due to Jack Kennedy’s retirement. She made a motion recommending Vanessa Christie be appointed to the committee to fill the vacancy. Motion to approve: Cox Second: Ragon Vote: Aye: Cox, Abbott, Ragon, Christie; Nay: none
The vice-chairman recessed the meeting for lunch at 11:56 a.m. The vice-chairman reconvened the meeting at 2:32 p.m.
6. Resolution of Appreciation for Robert Bowen Service to Virginia Vanessa Christie, Region 7 VAB Member
Ms. Christie called upon Robert Bowen, president and CEO of Norfolk International Airport, and presented the VAB’s Resolution of Appreciation for his service to Virginia. Mr. Bowen extended his gratitude for the acknowledgement.
7. Resolution for Williamsburg-Jamestown Airport Celebrating 50 Years of Operation
Vanessa Christie, Region 7 VAB Member
VAB Package December 2021 5
Ms. Christie called upon Larry Waltrip, owner and operator of Williamsburg-Jamestown Airport, and presented the VAB’s resolution to acknowledge the airport’s 50 years of operation. Mr. Waltrip extended his gratitude for the acknowledgement.
8. DOAV Director’s Update Mark Flynn, DOAV
Mr. Flynn reported on department activities to include an update on VA-FIX, the approval of two emergency regulations mandating take-off and landings for UAS and the new airline incentive fund and Breeze Airways. He complimented the commercial air service airports in working through a very difficult time with the pandemic.
9. Review and approve June 17, 2021 minutes Derek Hardwick, Vice Chairman
The minutes were presented for review and consideration of approval. Motion to approve: Ragon Second: Abbott Vote: Aye: Cox, Abbott, Ragon, Christie; Nay: none
10. Old Business
A. Airport Program Manual
1. Local Service Airport
Cliff Burnette, DOAV
Mr. Abbott commented that he would like the board to have time to review information recently presented before a final decision was made. He made a motion to table action until the next meeting. Motion: Abbott Second: Cox Vote: Aye: Cox, Abbott, Ragon, Christie; Nay: none
2. Promotional Grant Term Date
John Campbell, DOAV
Ms. Christie made a motion to approve the staff recommendations. Motion to approve: Christie Second: Abbott Vote: Aye: Cox, Abbott, Ragon, Christie; Nay: none
B. Airport Licensing Issues - Falwell Airport Vernon Carter, DOAV
Staff provided an update on the work accomplished at the airport and recommended issuing to Falwell Airport a standard license with waivers for the normal 7-year cycle, so the license and waiver would expire September 30, 2026. Motion to approve: Ragon Second: Christie Vote: Aye: Cox, Abbott, Ragon, Christie; Nay: none
VAB Package December 2021 6
11. New Business
A. Consideration of FY21 Entitlement Utilization Reports and FY22 Entitlement Utilization Plans
Mike Swain, DOAV
Mr. Swain presented the following FY21 Entitlement Utilization Reports and FY22 Entitlement Utilization Plans. Staff recommended approval of the reports and plans.
Airport Recommendations for FY21 Entitlement Utilization Reports
Recommendations for FY22 Entitlement Utilization Plans
Charlottesville-Albemarle Airport Approved Approved Lynchburg Regional Airport Approved Approved Newport News-Williamsburg International
Airport Approved Approved
Norfolk International Airport Approved Approved Richmond International Airport Approved Approved Roanoke-Blacksburg Regional Airport Approved Approved Shenandoah Valley Regional Airport Approved Approved Washington Dulles Airport Approved Approved
Motion to approve: Abbott Second: Ragon Vote: Aye: Cox, Abbott, Ragon, Christie; Nay: none
B. Virginia Aviation Allocations Review
Tentative Allocations from the Commonwealth Aviation Fund
Mike Swain, DOAV
Mr. Hardwick noted that federal legislation is continuing to move forward with 100 percent funding for AIP projects and made the following recommendations. • If a sponsor receives a tentative allocation from the Virginia Aviation Board, and then receives an FAA AIP
grant offer for 100 percent of the project costs, the tentative allocation shall be automatically revoked, and the Department is directed to withdraw the tentative allocation.
• If a sponsor executes a state grant offer and then receives an FAA AIP grant offer for 100 percent of the project costs, the sponsor must repay the Department of Aviation for any reimbursements previously received, and the Department of Aviation will close the state grant.
Motion to approve: Abbott Second: Christie Vote: Aye: Cox, Abbott, Ragon, Christie; Nay: none Mr. Swain reported that a six-month estimate for the Commonwealth Aviation Fund (CAF) was used as the basis for funds available for the board to award at the meeting. He also reported that entitlement payments in Fiscal Year 2022 will be made at the end of the quarters, based on available CAF funds in the bank. Mr. Swain presented the project requests and staff recommendations. The board actions are summarized below. These results are available at www.doav.virginia.gov.
For Region 1, staff recommended the following:
Airport Project Description VAB Action Amount
VAB Package December 2021 7
New River Valley Airport
Taxiway Crack Seal (Construction) Approved $29,600.00
Tazewell County Airport
Easement Acquisition Services - Obstruction Removal - BRIDGE LOAN - INCREASE
Approved $11,520.00
Motion to approve: Cox Second: Abbott Vote: Aye: Cox, Abbott, Ragon, Christie; Nay: none For Region 2, staff recommended the following:
Airport Project Description VAB Action Amount Front Royal-Warren
County Airport Terminal Roof Replacement (Construction) Approved $67,626.00
Luray Caverns Airport
T-Hangars & Taxilane Site Preparation (Design) Approved $75,000.00
Shenandoah Valley Regional Airport
Land Acquisition (Parcel 37B) Approved $798,800.00 (E)
Motion to approve: Cox Second: Ragon Vote: Aye: Cox, Abbott, Ragon, Christie; Nay: none For Region 3, staff recommended the following:
Airport Project Description VAB Action Amount Culpeper Regional Apron Lighting - Phase 2 (Construction) Approved $187,068.00 Airport Greenhouse Road Extension - Phase 1
(Construction) Tabled N/A
Manassas Regional Airport
Runway 16L-34R Remarking (Construction) Approved $37,780.00
Motion: Abbott Second: Cox Vote: Aye: Cox, Abbott, Ragon, Christie; Nay: none For Region 4, staff recommended the following:
Airport Project Description VAB Action Amount Louisa County
Airport Environmental Assessment (Re-Evaluation) for Southside Hangars
Disapproved N/A
Richmond Executive - Chesterfield County Airport
Terminal Apron Rehabilitation (Design) Approved $13,480.00
Motion to approve: Abbott Second: Cox Vote: Aye: Cox, Abbott, Ragon, Christie; Nay: none For Region 5, staff recommended the following:
Airport Project Description VAB Action Amount
VAB Package December 2021 8
Farmville Regional Airport
Runway Safety Area Grading (Construction) Approved $119,444.00
Motion to approve: Ragon Second: Cox Vote: Aye: Cox, Abbott, Ragon, Christie; Nay: none For Region 6, staff recommended the following:
Airport Project Description VAB Action Amount Mecklenburg-
Brunswick Regional Airport
Helicopter Parking Apron and Hangar Taxiways (Design)
Approved $15,200.00
Motion to approve: Abbott Second: Cox Vote: Aye: Cox, Abbott, Ragon, Christie; Nay: none For Region 7, staff recommended the following:
Airport Project Description VAB Action Amount Chesapeake
Regional Airport T-Hangar Taxilanes Rehabilitation - Phase 2 (Construction)
Approved $842,400.00
Hampton Roads Apron & Wash Rack (Construction) Approved $888,000.00 Executive Airport Wash Rack (Design) - INCREASE Approved $3,842.00 James City County Access Road Rehabilitation / Reconstruction
(Construction) - INCREASE Approved $79,408.91
Middle Peninsula Regional Airport
Access Road & Box Hangar Site (Environmental) Approved $22,400.00
Suffolk Executive Airport
Easement Acquisition Services - Obstruction Removal - BRIDGE LOAN - INCREASE
Approved $36,860.00
Motion to approve: Christie Second: Ragon Vote: Aye: Cox, Abbott, Ragon, Christie; Nay: none
12. Public Comment Period
Derek Hardwick, Vice Chairman
No public comments were offered.
13. Board Member Comments and Reports
Derek Hardwick, Vice Chairman
Region 2: Ms. Cox thanked the department and everyone involved in setting up the conference. She noted it was nice to be back. Region 4: Mr. Abbott noted that he enjoyed lunch and the opportunity to meet with the airports. Region 5: Ms. Ragon thanked all the airport representatives for keeping everything going through it all. She expressed her thanks to Courtney Beamon and her team as well as Norfolk International Airport for the efforts in organizing the conference. Region 7: Ms. Christie echoed everyone’s comments. Director: Mr. Flynn stated that he would be polling board members on the next meeting date, since one board member is unavailable for two weeks in November. December 9 may be an option.
VAB Package December 2021 9
Vice Chairman: Mr. Hardwick stated that everything was outstanding all the way around.
14. Adjournment
Derek Hardwick, Vice Chairman
The meeting adjourned at 3:25 pm. Motion to approve: Abbott Second: Cox Vote: Aye: Cox, Abbott, Ragon, Christie; Nay: none
VAB Package December 2021 10
ENTITLEMENT UTILIZATION REPORTS & PLANSAMENDED FY2022 PLANS
FY2021 REPORT FY2022 PLANAIRPORT DOAV RECOMMENDATION DOAV RECOMMENDATION COMMENTS
Lynchburg Regional Disapprove Received after the VAB policy deadline
Newport News-Williamsburg Int'l Approve
ACTION ITEM ACTION ITEM
Entitlement Utilization Report Plan Approvals December 2021 VAB
VAB Package December 2021 11
Commonwealth Airport Fund
Entitlement Utilization Report and Plan
Airport NewportN€s/WilliamsburglnternationalAirport
Part 1 - Entitlement Utilization Report il2022
A, Entitlcm.nt Funds Ahilebl. fo. ktsnditur. end Commitm.nt
Subtotal Entltlehent Re50ur.er AEilable FY2021
8. Rcimbumm.nt otSEtc Entitl.mcd Fun&- PFC''; Btidtc Ldns; dhcr fl2021
Total Funds Available for commitmentfrom FY2o20
Entitlement Funds Reeived in FY2021
lni€.est Earned in FnO21
sa342,47 4.54
s2,000,000.00
s40,s3.88
Sponsor: PenlnsulaAirportCommlssion
s10,382.5X8.42
Pro.ied &scriptionProjed
Number
DOAV
Projed
Number
PFC
PrcjedNumber
Costs
State state PFC Local
I
Tobl
Prcjed
Cost
sEte
Funding Reimbursement
subtobl ReimbuEementof sbte EntitlementFunds
Iot.l Funds Availrble
c. FundintAtsnditurcsforPreicGcl6.d: fl2o21
s0.m
5x0,382,51s.42 (Entitlement Resou r@s Available FY2O21 + Reimbursement of State Entitlement Funds)
Design TaxiwayA Lightin& ShouldeB & RealignmentTxys B & C
Annual Maintenan@ and lnspedion of bilers/ChilleE/CoolingTowe6 I
Annual and Quaderlv File Sodnkler and Suppression lnspedions
Aiffi.ld baint removal. oaintinc and crack sealin€
10K baderFirPh6u<. G.nerato.
gackhoePAswtem Reolacement
s€curiw Gme.a UDsrades Phase 2
p.nm.br Rord Abbroach End Runwav 2 and 7 Construdion
Replace ARFF truck thermal emera kit (ln House repair)
Rebair leak in terminal air chillerf2ldrd bank aideld €ult zenerator
fire
site visit repair Flm
Rerlace bumperturret control box on ARFF truck (ln House repair)
Reoalce &o in-line boiler oumo moto6
Reolace TaxiwavccR rcB and cutdut lln House reoairlRepalce U joint shaft and shield (ln House repair)
Escaleto.and Elevaior lnsDedion and Maintenance
JLG or similar liftARFF #3 Rescue tires
AHU #2 DamDers 4 Each
Projed Des.ription
3-51-m35-052-2019
3-51-0035-051-2019
AIP
Prcjed
Number
mavPrcjed
PFC
Projed
Number
302,400.m
s2,834,1m.m
F€deral sEte
Entitlement
s33,600.m
s4,356.m
s1.616.m
e36.A2.mS13,183.55
s135,8m.00
q?2 521.a6572,s50.m
s4,4t4.OA
s42.62L.a6
s314.9m.00522.O72.43
s4.330.52
s1.920.96
s2,029.30
s2,64.00
S14,639.69
s2,760.00
s7,226.52
$1,080.00s1.47La0
S155,ooo.oo
Ss,953.sg
Ss,1e.oo$8,491.04
s8,455.17
5a,47.27
s10,314.i10
s6,079.60
Final CosB
Sbte PFC tocal
q6 534-ms2,424.@
s7.862.00
s3.295.89
s34.2m-ms8.130.4
s18.1&.ms66,620.m
s10,655.47
50.m
so.ms6,495.78
S4o.24
s3.043.95
5652.m
So.m
So.oo
$o.00
S1,490.8s
s11,M6.00
92.a22.76
s2,773.79
s2,111.80
$15,471 60
s9-119.40
336.m.m10.490.m
s 4040.00
43,954.m
76,479.4
s 171.m.@s{.6s2.3290,7m.00
4 111.O34.m
s1 277 13
3,149,m.ms 22.O72.43
( 10.426.30I 2,&t.2oS s,073.2s
3,310.00
14,639.69
6,9m.00
t 1.226.52I 1,47LaO
s 7.454.47
5 ss,23o.oo
10,513.80
s m.s64.9610,559.01
s 15.199.m
Total
Projed
Cdqt
t@6
4ea
4M82%
80Ph
AM80f/6
ao%
40%
AMLM
100%
4MAM40%
80%
LOOA
4e/o
1ffi
ago1ffi
IM80%
ec/.av6AMac,a
4{,.6
State
Funding
Percentase
Estim.kd PFC5
to bimbuase
Entitlements
subtotal Expenditures for Prcje* Completed: ry2o21
Unexpended Funds Available for commitment
Eniitlement Lnilization FY2O21 and Plan FY2o22 Fofr
$1,026,887.06 (stateEntitlementFunds)
59,355,531.35 (Total Funds AEilabl€ - Expenditu.es for Completed Projeds)
1d3
VAB Package December 2021 15
Commonwealth Airport Fund
Entitlement Utilization Report and Plan
D. Fundin! Commiinlntr tor onioint Prei.G
Airifield liEhilDs cotrtrols sstem uosrade
lndall.ubbl€mental ai..onditionin.in main communiotions room
Annual maintenance and inspedion AFFF system weter and foam ratio on firetrocks
Annual Maintenanceand lnsDdion of bilere/chille6/CoolinaTowe6
Annual and ouad.dv Fies6rinklerand suDordsion lnsDedions
Airfield paint.emoval, paintingand crack Faling;RE Facilitu &sift Sitins& Envi.onmental
MDP Over/Undervoltage protedion main powerto terminal
Securitv Cameras Phase 3
bnd &bt South brDorate
Bond Oebt South Corporate
Bond &bt South Coroorate
Reloete/Combine Upper & Lower level Fire Panels circuits to main fire panel
Wafndinsstudv Phase 1
SRE Facilitu
Fli"ht lnformation Disolav Svstem
Old Terminal tusiEn & Enilronmental Phase 1
Main Tdrminal Rmf Rebair Phase 2 Brick lrfiltration MitigationMain Terminal BuildinE Rehabilibtion Design
DumD Truckwith olow
Lrmihal window Reblacement Phasp 2
Reolac€ment ln@mins gas geltSstems Phase 2
Reolacement ln@mins gae BeltSstems Phase 1
FOD bss
Drainare Reoair G AvenuE
D6iF &ga8e Claim Rehabilitation
Firehouse Roof Repak Phase 2
lscalator and Elevator lnsoedion and Maintenance
South Coroorat€ Pawmont AnalsisSouth Corporate Development - Permiting and Mitigation
south corporat &velopment - lnvkonmental Analysis
South Coro Aoron khabiliEtion Desisn and Biddins
Access Control System
Purchase 22ft Winsed Cuter
GA Ramo Rehab Enuronmental and Dsicn
a6n<tn,di6n TtvA liphtin" ShouldeB & RealienmEnt ofTM B & C
Projed Description
2022
2022
2022
2022
2022
7027
2022
2022
)n222023
2022
2027
2022
zo24
2023
2022
2022
2022
2024
2022
2022
2022
2022
2022
2022
2022
2024
202t
2022
2022
2022
)o)?2022
2022
2022
2022
2022
2022
2022
2022
2022
2022
2022
2022
Estimated
Fiscal Year
AIP
Prcjed
DOAV
Prcjed
5.5
6,5
6.3
6-3
6.3
6,1
6.X
6-1
6.1
6.2
PFC
Projed
Ss,32o,i77 .u
FundingSou.ces with Estimated tusB
S 33,3oo.oo
smo,m.frs24.m0.frsa.mo.tr4q soo tr
s24.OOO-tr54,e77.oc
52,024.0C
s160-OOO-fr
S4m,ooo.tr
s160,0m.tr
s12_om_tr
E1m-mo-ot5155,000.0c
q155.Om.OC5lss,0m.0[
512,m.0(
s20,000.0c
s2,400,m.0c
s40,m.trs30,m.tr
s150.m.0cS2m,m.trs240,m.0(3120.m.tr94o,m.o(
5720,[email protected](
s720.m.trsa.m-tr
S8o,ooo.fr
$11,000.tr
s240,m0.fr
(4.m.trs120,m.trs200.m.tr31ao.m.trs40,m.0(s56,m.tr
s160.m.ocS24m.o(s15.OO0.0(
31.a39.2C
sbteEntitlement
state
Dissetionary
so.ms60,m.m
{5o m.mSlsoooo.oo
s180.000.00
s60,000.m
s12.000.m
q30 000 msso,000.m
s45.000.m
s40.000.m
PFC
s66,70O.00
s25,000.00
s6,000.00
512,m.0C
s2.ffi.tr
s6.m.m
q7 315 0a
s3,O36.0C
s40.m.0c
qlmmds40,m.tr
s8,000.0c
s2s.m.tr
518,ooo.q
s30.ooo.tr
s6m.ooo-ff
s10.000.tr
q45 000 trs4o m0.0c
s3m.ooo-tr
s30.0m.frso.tr
s2,0m.0(
s20-mo.0t
58,ooo.o(
52,lm.oc
s60.ooo-ocs14000.oc
s6.OOO-tr
54,ooo.tr
s2,758.8C
Lo.al
s 1m,m0.ms 125,000.00
5 3o,ooo.m
20,0m.00
s 12.m.OO
30,m.m
s 5,060.00
2m,0m.00
g 5m.m.oos 2m,m.00
20,m.mu5,m.00
s 155.000.m
$5,m.00s 155.m.me 30.m.m
s 50.mo.m
3.000.000.m
50,000.m
s 75.OOO_m
S 2m,[email protected]
?oomm150,m.m
s mo.m.m4 9m ooo.m$ 9@,000.00
10,000.00
lm,000.00
11,000.m
s 3m.oo0-005 6,000.00S 1o,5oo.oo
60,000.00
s 150.OOO_@
I 2so,om.m225,000.m
mo.m0.m
( 70 om_m200,000.@
30.m.ms 20.ooo_m
4,598.m
5,320,777.6
Estimated
Total
33%
807.
8016
4@6
8M
80%
4M4ea80%
AM80%
6ea
aeaL@A
x0096
10M4M
M
aqo
8096
M8ea&%AMaea4MAMa0,6
ac/.a0,6
L0rf/6
AMAMag.ae/.
AGA
AMae/.w.a&a@6
8016
AM4ea
e/o
EstimaEd
stat€ Funding
€stimated PFCS
to ReimbuEe
Entitlem€nb
farm upgrad€
Subtohl Funding Commitments for Ongoing Prcjeds 57,430,040.20 (StateEntitlementFunds)
s2,000,0oo.00Anticipated ry2o22 Entitlement Funds (use lastFar's amount)
Entitlement Ljtilizalion FY2O21 and Plan FY2OD Fon 2d3
VAB Package December 2021 16
A-
B.
S2,74,m0.@ {stateEntitlementFunds)
91,181,591.16
Commonwealth Airport Fund
Entitlement Utilization Report and Plan
Funds Available
Part 2 - Entitlement Utilization Plan: FY2022
S3,925,591.15 (Unexpended Funds AvailableforCommitment - Funding OmmitmenBfor Ongoing Proje6+Anti.ipated FYz022 Entitlement Funds))
9
8
7
6
5
4
3
2
1
EUP
t
Old te.minal Demo Phase 3 and Phase4
old terminal Abatement Lead paint/tubestos phase 2
Eenovate entrre baggage clarm area to accomadate new
bagage sstem
Main Terminal Roof Repair Phase 2 Brick lnfiltration Mitigation
Dlls uo
UtilityVehicle
Secutiycamera phas€ 3 plus up
Access conlrol svstem Plus uo
Master Plan update
old lerminal ksign & Environmental Phase 1 Plus up
Prcjed kscription GYeat
Plan
Estimated
Stad D.te(Fisel Year)
AIP
Projed
Number
DOAV
Projed
Number
PFC
Prcjed
s 900.000.m
Federal
Funding Sources with Estimated Costs
$8@,ooo,o€
s950,0m.00
s200.m.oc
s2o0,m.0c
s24000.0c
s100.m.0c
q&.om.oc
s1m,om.0c
s320.Om.OC
State
Entitlehent
State
Discrctionary
PFC
s200.mo.ms240,000.00
s50,000.m
s300.000.o0
s5,000.00
$25,ooo.m
s60.om.m
s80.000.m
Lodl
1.mo.m.@S l,2oo,m.mS 2so,m.oo
s 500,m0.00
s 30,000.00
S ns,m.msxm,000,0c
s1,m,000.0c
s 400,m0.00
Estimated
Total
Projed cost
AMAMaea
4@6
ae/.
AM
4M
LM
8M
Estimated
state Funding
Perentase
Estihaled PFCa
to Reimburse
EnritlemPnts
Total Planned CommltmenE for Future ProjeG
Funds Available
9
R
7
5
5
43
2
rEUP *
Demolish apDrox 80.000sq ft of old abandoned terminal space Phase 3 and 4 combined to lower mobilization cost
AhetemFht of ell ha7ar.l6u( material( nee.lt.l befdre demdlishinE 6f old terminal in ohase 3 and 4 can bpein
plu(rtbinirirlie+inoandin(bedionbrdvedmaiorfailsinduterbrickwalls cab<androofinmostareasarrover30vearsoldsinqleDlvrubberfailins
Plu( !6 re.rrritu Gmera dudtes came in hlsher than anti.ibatedPlus uo access control ouotes. bids came in hieherthan exoeded.
Recent meeting with Airport, FM, and DOAV agreed that Master Plan needs to be updated.
Plus up on Old terminal design and Enviromental initial quotes enviromental testing for lead paint and asbestos higher than anticipated
Narratiw
hd 3-c.titietion
Dir.dot * th. chi.f Fin.nri.lOftieron b.h.lt of thc sponsr, lc.difythrtth. informtion puidcdto th. to thc oi
Signature
t/ /"L'i\uz r
Entitlement LJtilization FY2O21 and Plan FY2O22 Fon
Date
3d3
VAB Package December 2021 17
i4*
*.-l- --'
I
)
4|,, "{fr1S
b
+.f*
tl:i
a; r- rIr'
\
it:i':.
?Ko YgtT+3
RTU-XI IOOG
FULL.SIZE DIESELUTILITY VEHICLES
MSRP A$ LOW A$$VAB Package December 2021 18
'u{ - od
'$:1'
'Y,.
{$
e&e8q$
'?,t.*8
s1t' .:'
ffi,rc\
rSl-f. 'a
d
I
-,"\i
* r.i
tIt
b # h,scldVAB Package December 2021 21
Net Estimated Revenues (per VDOT 7/25/2021): 2.4% Special Session Revenues $ 13,269,311.50 Interest Revenues 62,500.00 Estimated Revenues 13,331,811.50
Adjusted Resources for FY 2022 $ 13,331,811.50
In accordance with VAB policy, the 25% cap for the maximum allocation available to one airport for FY 2022 is: $ 3,332,952.88
Funds Available for Allocation by the Virginia Aviation Board
Adjusted Resources for FY 2022 $ 13,331,811.50Base Amount from Code of Virginia (Section 58.1-638.A.3.) (6,050,000.00) New Funds in Excess of Base $ 7,281,811.50
MWAA Entitlement (60% of New Funds in Excess of Base [$6,050,000], limited to $1,000,000.00) $ 1,000,000.00Additional Air Carrier Entitlement (40% of New Funds in Excess of Base) $ 2,912,724.60Additional Resources Over MWAA's Maximum to be Split 40%, 40% and 20% $ 3,369,086.90Uncommitted Combined Fund Carryover from FY2021 $ 3,716,541.66
AC/Rel GAEntitlements Discretionary Discretionary Total
Base Amount Resources for FY 2021 $ 2,420,000.00 $ 2,420,000.00 $ 1,210,000.00 $ 6,050,000.00
MWAA Entitlement 1,000,000.00 0.00 0.00 1,000,000.00
Additional Air Carrier Entitlement 2,912,724.60 0.00 0.00 2,912,724.60
Additional Resources over MWAA's Maximum 1,347,634.76 1,347,634.76 673,817.38 3,369,086.90
Uncommitted Combined Fund Carryover from FY2020 0.00 2,477,694.44 1,238,847.22 3,716,541.66
Funds Available for Allocation as of July 1, 2021 $ 7,680,359.36 $ 6,245,329.20 $ 3,122,664.60 $ 17,048,353.16
Allocation Activity Since July 1, 2021 (4,000,000.00) (1,167,678.28) 591,519.59 (4,576,158.69)
Funds Available for Allocation $ 3,680,359.36 $ 5,077,650.92 $ 3,714,184.19 $ 12,472,194.47 as of December 2, 2021
Test Check-1 0.00Test Check-2 0.00
Commonwealth Airport FundFunds Available for Financial Assistance to Airports
Fiscal Year 2022 - Quarters 1 and 2
CAF Funds Available FY2022 Quarters 1 and 2
VAB Package December 2021 23
203 Hanover County Municipal Airport East Side Perimeter Fencing - Phase 1 (Construction) $0.00 $18,603.00 $2,067.00 $20,670.00
140 Richmond Executive - Chesterfield CountyAirport
Southeast Apron Expansion (Design) - Change in Scope /Increase
$0.00 $161,520.00 $40,380.00 $201,900.00
105 Hampton Roads Executive Airport Fueling System (Design) - INCREASE $0.00 $1,584.00 $3,218.50 $4,802.50
$0.00 $181,707.00 $45,665.50 $227,372.50FUNDING TOTALS:
AVAILABLE DOLLARS FOR THE VAB TO COMMIT: $5,077,650.92$4,895,943.92BALANCE:
AIR CARRIER / RELIEVER AIRPORTS - DISCRETIONARY FUNDSRECOMMENDED PROJECTS
STATEWIDE
FUNDEDPRIORITYNO. AIRPORT NAME DESCRIPTION
FEDERALAMOUNT
STATE DISCR.AMOUNT LOCAL AMOUNT
TOTAL PROJECTAMOUNT
Print Date: 11/18/2021 Page 1 of 2
VAB Package December 2021 24
194 Hanover County Municipal Airport Terminal Building Roof Replacement (Construction) $0.00 $0.00 $49,820.00 $49,820.00
$0.00 $0.00 $49,820.00 $49,820.00FUNDING TOTALS:
AIR CARRIER / RELIEVER AIRPORTS - DISCRETIONARY FUNDSNOT RECOMMENDED PROJECTS
STATEWIDE
Not RecommendedPRIORITYNO. AIRPORT NAME DESCRIPTION
FEDERALAMOUNT
STATE DISCR.AMOUNT LOCAL AMOUNT
TOTAL PROJECTAMOUNT
Print Date: 11/18/2021 Page 2 of 2
VAB Package December 2021 25
187 Virginia Highlands Airport Sinkhole & Drainage Repair (Construction) $0.00 $414,000.00 $103,500.00 $517,500.00
164 Dinwiddie County Airport Terminal Building Roof Replacement (Construction) $0.00 $21,600.00 $8,400.00 $30,000.00
128 New Kent County Airport Fueling System Repair - Pump $0.00 $5,988.00 $2,950.00 $8,938.00
123 Mountain Empire Airport Fueling System Tank Repainting (Construction) $0.00 $3,531.00 $7,171.00 $10,702.00
110 Hummel Field Environmental Impact Review - Runway Improvements $0.00 $31,920.00 $7,980.00 $39,900.00
90 Lonesome Pine Airport Spill Prevention, Control, and Countermeasure Plan Update $0.00 $3,781.00 $945.00 $4,726.00
90 Lunenburg County Airport Runway & Apron Rehabilitation (Preliminary Engineering) $0.00 $17,600.00 $4,400.00 $22,000.00
$0.00 $498,420.00 $135,346.00 $633,766.00FUNDING TOTALS:
AVAILABLE DOLLARS FOR THE VAB TO COMMIT: $3,714,184.19$498,420.00COMMITTED:
$3,215,764.19BALANCE:
GENERAL AVIATION AIRPORTS - DISCRETIONARY FUNDSRECOMMENDED PROJECTS
STATEWIDE
FUNDEDPRIORITYNO. AIRPORT NAME DESCRIPTION
FEDERALAMOUNT
STATE DISCR.AMOUNT LOCAL AMOUNT
TOTAL PROJECTAMOUNT
Print Date: 11/18/2021 Page 1 of 2
VAB Package December 2021 26
199 Culpeper Regional Airport Greenhouse Road Extension (Construction) (AIP) $2,900,000.00 $0.00 $322,222.00 $3,222,222.00
150 Culpeper Regional Airport Northeast Stub Taxiway (Design) $201,954.00 $0.00 $22,440.00 $224,394.00
115 Culpeper Regional Airport Greenhouse Road Extension (Construction) (non-AIP) $0.00 $0.00 $698,861.24 $698,861.24
93 Danville Regional Airport Fuel Farm Modification (Design) $0.00 $0.00 $111,090.00 $111,090.00
$3,101,954.00 $0.00 $1,154,613.24 $4,256,567.24FUNDING TOTALS:
GENERAL AVIATION AIRPORTS - DISCRETIONARY FUNDSNOT RECOMMENDED PROJECTS
STATEWIDE
Not RecommendedPRIORITYNO. AIRPORT NAME DESCRIPTION
FEDERALAMOUNT
STATE DISCR.AMOUNT LOCAL AMOUNT
TOTAL PROJECTAMOUNT
Print Date: 11/18/2021 Page 2 of 2
VAB Package December 2021 27
COMMONWEALTH AVIATION FUND ALLOCATION STATUS
For the FYE June 30, 2022
as of July 7, 2021
updated 11/9/21 MS AIRPORT TENTATIVE ALLOCATION STATUS
AIRPORT DESCRIPTION DATE FAA FY PROJECT # DISCRETIONARY GRANT T.A. BALANCE
ACCOMACK COUNTY (GA-R) RUNWAY 21 TURNAROUND (DES) MAR 18, 21 XXXXXXXX 6,000.00
SPONSOR RETURN-RUNWAY 21 TURNAROUND (DES) OCT 14, 21 XXXXXXXX (6,000.00) 0.00
ALLEN C. PERKINSON / BLACKSTONE AAF (GA-C) (NON-NAPRON REHABILITATION (DES) JUN 17, 21 CS0008-11 40,000.00
GRANT-APRON REHABILITATION (DES) JUL 7, 21 CS0008-11 40,000.00 0.00
BLUE RIDGE (GA-R)
BRIDGEWATER AIR PARK (GA-L) (NON-NPIAS)
BROOKNEAL/CAMPBELL COUNTY (GA-C)
CHARLOTTESVILLE-ALBEMARLE (AC-N)
CHASE CITY (GA-L) (NON-NPIAS)
CHESAPEAKE REGIONAL (REL) TERMINAL BUILDING RESTROOMS RENOVATION JUN 17, 21 CS0006-57 5,543.00
GRANT-TERMINAL BUILDING RESTROOMS RENOVATION JUL 19, 21 CS0006-57 5,543.00
T-HANGARS TAXILANES REHABILITATION-PH 2 (CON) AUG 19, 21 CS0006-58 842,400.00
GRANT-T-HANGARS TAXILANES REHABILITATION-PH 2 (CON) OCT 6, 21 CS0006-58 842,400.00 0.00
CREWE MUNICIPAL (GA-L) (NON-NPIAS)
CULPEPER REGIONAL (GA-R) APRON LIGHTING=PHASE 2 (CON) AUG 19, 21 CS0010-30 187,068.00
GRANT-APRON LIGHTING=PHASE 2 (CON) AUG 31, 21 CS0010-30 187,068.00 0.00
DANVILLE REGIONAL (GA-R) BOX HANGAR SITE PREPARATION (DES) JUN 17, 21 CS0011-49 71,116.00
GRANT-BOX HANGAR SITE PREPARATION (DES) JUL 12, 21 CS0011-49 71,116.00 0.00
DINWIDDIE COUNTY (GA-R)
EAGLE'S NEST (GA-L) (NON-NPIAS)
EMPORIA-GREENSVILLE (GA-R)
FALWELL (GA-L) (NON-NPIAS)
FARMVILLE MUNICIPAL (GA-R) RUNWAY SAFETY AREA GRADING (CON) AUG 19, 21 XXXXXXXXX 119,444.00
CAF Allocation Status FY22.xlsx
VAB Package December 2021 28
COMMONWEALTH AVIATION FUND ALLOCATION STATUS
For the FYE June 30, 2022
as of July 7, 2021
updated 11/9/21 MS AIRPORT TENTATIVE ALLOCATION STATUS
AIRPORT DESCRIPTION DATE FAA FY PROJECT # DISCRETIONARY GRANT T.A. BALANCE
SPONSOR RETURN-RUNWAY SAFETY AREA GRADING (CON) OCT 19, 21 XXXXXXXXX (119,444.00) 0.00
FRANKLIN MUNICIPAL (GA-C) APRON SINKHOLE REPAIR (CON) JUN 17, 21 CS0017-15 11,600.00
GRANT-APRON SINKHOLE REPAIR (CON) NOV 9, 21 CS0017-15 11,600.00 0.00
FRONT ROYAL/WARREN COUNTY (GA-C) TERMINAL BUILDING ROOF REPLACEMENT (CON) AUG 19, 21 CS0019-23 67,626.00
GRANT-TERMINAL BUILDING ROOF REPLACEMENT (CON) SEP 7, 21 CS0019-23 67,626.00 0.00
GORDONSVILLE MUNICPAL (GA-L) (NON-NPIAS)
GRUNDY (GA-L) (PROPOSED) NPIAS JUSTIFICATION STUDY JUN 17, 21 CS0022-01 129,213.00
GRANT-NPIAS JUSTIFICATION STUDY JUL 7, 21 CS0022-01 129,213.00 0.00
HAMPTON ROADS AIRPORT (REL) WEST APRON TAXIWAYS REHABILITATION (CON) MAR 18, 21 XXXXXXXXX 40,000.00
SPONSOR RETURN-WEST APRON TAXIWAYS REHABILITATION (CON) NOV 9, 21 XXXXXXXXX (40,000.00)
APRON & WASH RACK (CON) AUG 19, 21 CS0040-57 888,000.00
GRANT-APRON & WASH RACK (CON) SEP 7, 21 CS0040-57 888,000.00
VAB INCREASE-WASH RACK (DES) AUG 19, 21 CS0040-49 3,842.00
AMENDMENT 2-WASH RACK (DES) SEP 7, 21 CS0040-49 3,842.00 0.00
HANOVER COUNTY (REL) RUNWAY 16-34 REHABILITATION (DES) MAR 18, 21 XXXXXXXXX 32,000.00
SPONSOR RETURN-RUNWAY 16-34 REHABILITATION (DES) OCT 12, 21 XXXXXXXXX (32,000.00)
TERMINAL BUILDING FURNITURE JUN 17, 21 CS0023-45 41,126.00
GRANT-TERMINAL BUILDING FURNITURE JUL 12, 21 CS0023-45 41,126.00 0.00
HUMMEL FIELD (GA-L) (NON-NPIAS)
INGALLS FIELD (GA-R)
JAMES CITY COUNTY / JGG VAB INCREASE-ACCESS ROAD REHABILITATION/REALIGNMENT (CON) AUG 19, 21 79,408.91
REALLOCATED TO WILLIAMSBURG-JAMESTOWN OCT 4, 21 (9,132.80) 70,276.11
LAKE ANNA (GA-L) (NON-NPIAS)
LAKE COUNTRY (GA-C) (NON-NPIAS)
LAWRENCEVILLE-BRUNSWICK (GA-L) (NON-NPIAS)
LEE COUNTY (GA-C) CRACK SEAL, SEALCOAT, & PAVEMENT REMARKING JUN 17, 21 XXXXXXXX 30,133.00
SPONSOR RETURN-CRACK SEAL, SEALCOAT, & PAVEMENT REMARKING OCT 14, 21 XXXXXXXX (30,133.00) 0.00
CAF Allocation Status FY22.xlsx
VAB Package December 2021 29
COMMONWEALTH AVIATION FUND ALLOCATION STATUS
For the FYE June 30, 2022
as of July 7, 2021
updated 11/9/21 MS AIRPORT TENTATIVE ALLOCATION STATUS
AIRPORT DESCRIPTION DATE FAA FY PROJECT # DISCRETIONARY GRANT T.A. BALANCE
LEESBURG EXECUTIVE (REL) HANGAR SITE PREPARATION (CON) (NON-AIP) JUN 17, 21 204,800.00
ADMIN INCR-TERMINAL ENTRANCE ROAD REHAB (CON) JUL 28, 21 CS0027-42 2,930.78
AMEND 1-TERMINAL ENTRANCE ROAD REHAB (CON) AUG 16, 21 CS0027-42 2,930.78 204,800.00
LONESOME PINE (GA-R) RUNWAY 6-24 REHABILITATION (CON) MAR 18, 21 XXXXXXXX 480,000.00
SPONSOR RETURN-RUNWAY 6-24 REHABILITATION (CON) NOV 8, 21 XXXXXXXX (480,000.00) 0.00
LOUISA COUNTY (GA-R)
LUNENBURG COUNTY (GA-L) (NON-NIPIAS)
LURAY CAVERNS (GA-C) TERMINAL BUILDING (DES) MAR 18, 21 CS0067-18 144,000.00
GRANT-TERMINAL BUILDING (DES) JUL 26, 21 CS0067-18 144,000.00
ROTATING BEACON REPLACEMENT JUN 17, 21 CS0067-20 7,316.00
GRANT-ROTATING BEACON REPLACEMENT JUL 12, 21 CS0067-20 7,316.00
T-HANGARS & TAXILANE SITE PREPARATION (DES) AUG 19, 21 CS0067-21 75,000.00
GRANT-T-HANGARS & TAXILANE SITE PREPARATION (DES) SEP 7, 21 CS0067-21 75,000.00 0.00
LYNCHBURG REGIONAL (AC-N)
MANASSAS REGIONAL (REL) MASTER PLAN UPDATE MAR 18, 21 XXXXXXXXX 48,000.00
SPONSOR RETURN-MASTER PLAN UPDATE OCT 18, 21 XXXXXXXXX (48,000.00)
T-HANGAR TAXIWAY REHABILITATION (CON) JUN 17, 21 CS0030-41 76,763.00
GRANT-T-HANGAR TAXIWAY REHABILITATION (CON) JUL 26, 21 CS0030-41 76,763.00
TERMINAL BUILDING BOILER REPLACEMENT JUN 17, 21 CS0030-42 38,642.00
GRANT-TERMINAL BUILDING BOILER REPLACEMENT JUL 26, 21 CS0030-42 38,642.00
RUNWAY 16L-34R REMARKING (CON) AUG 19, 21 CS0030-43 37,780.00
GRANT-RUNWAY 16L-34R REMARKING (CON) SEP 27, 21 CS0030-43 37,780.00 0.00
MECKLENBURG/BRUNSWICK REGIONAL (GA-R) HELICOPTER PARKING APRON & HANGAR TAXIWAYS (DES) AUG 19, 21 XXXXXXXXX 15,200.00
SPONSOR RETURN-HELICOPTER PARKING APRON & HANGAR TAXIWAYSNOV 9, 21 XXXXXXXXX (15,200.00) 0.00
MIDDLE PENINSULA REGIONAL (GA-R) ENVIRONMENTAL COORD-ACCESS ROAD & BOX HANGAR SITE PREP AUG 19, 21 CS0057-42 22,400.00
GRANT-ENVIRONMENTAL COORD-ACCESS ROAD & BOX HANGAR SITE P SEP 20 , 21 CS0057-42 22,400.00 0.00
MOUNTAIN EMPIRE (GA-C) OBSTRUCTION LIGHTING REPLACEMENT (CON) JUN 17, 21 CS0031-35 3,568.00
GRANT-OBSTRUCTION LIGHTING REPLACEMENT (CON) AUG 16, 21 CS0031-35 3,568.00
OBSTRUCTION REMOVAL-ROFA GRADING (DES) JUN 17, 21 XXXXXXXXX 22,000.00
SPONSOR RETURN-OBSTRUCTION REMOVAL-ROFA GRADING (DES) OCT 13, 21 XXXXXXXXX (22,000.00) 0.00
CAF Allocation Status FY22.xlsx
VAB Package December 2021 30
COMMONWEALTH AVIATION FUND ALLOCATION STATUS
For the FYE June 30, 2022
as of July 7, 2021
updated 11/9/21 MS AIRPORT TENTATIVE ALLOCATION STATUS
AIRPORT DESCRIPTION DATE FAA FY PROJECT # DISCRETIONARY GRANT T.A. BALANCE
NEW KENT COUNTY (GA-C)
NEW LONDON (GA-L) (NON-NPIAS)
NEW MARKET (GA-L) (NON-NPIAS)
NEWPORT NEWS/WILLIAMSBURG INT'L (AC-S)
NEW RIVER VALLEY (GA-R) MASTER PLAN UPDATE MAR 18, 21 XXXXXXXXX 40,000.00
SPONSOR RETURN-MASTER PLAN UPDATE OCT 18, 21 XXXXXXXXX (40,000.00)
TAXIWAY CRACK SEAL (CON) AUG 19, 21 CS0012-10 29,600.00
GRANT-TAXIWAY CRACK SEAL (CON) SEP 7, 21 CS0012-10 29,600.00
ADMIN INCR-TAXIWAY CRACK SEAL (CON) SEP 14, 21 CS0012-10 560.00
AMENDMENT 1-TAXIWAY CRACK SEAL (CON) OCT 4, 21 CS0012-10 560.00
ADMIN INCR-PARKING LOT REHABILITATION (DES/CON) SEP 14, 21 CS0012-09 838.19
AMENDMENT 1-PARKING LOT REHABILITATION (DES/CON) OCT 4, 21 CS0012-09 838.19 0.00
NORFOLK INT'L (AC-S)
ORANGE COUNTY (GA-C)
RICHMOND EXEC-CHESTERFIELD CO (REL) SOUTHEAST APRON EXPANSION (DES) JUN 17, 21 168,480.00
SOUTHEAST BOX HANGARS SITE PREPARATION (DES) JUN 17, 21 132,165.00
TERMINAL APRON REHABILITATION (DES) AUG 19, 21 XXXXXXXX 13,480.00
SPONSOR RETURN-TERMINAL APRON REHABILITATION (DES) OCT 13, 21 XXXXXXXX (13,480.00) 300,645.00
RICHMOND INTERNATIONAL (AC-S)
SHANNON (GA-C)
SHENANDOAH VALLEY (AC-S) LAND ACQUISITION (PARCEL 37B) ($798,800 E) AUG 19, 21
SMITH MOUNTAIN LAKE (NON-NPIAS)
STAFFORD COUNTY (REL) RUNWAY EXTENSION-PHASE 2 (CON) MAR 18, 21 XXXXXXXXX 464,000.00
SPONSOR RETURN-RUNWAY EXTENSION-PHASE 2 (CON) OCT 18, 21 XXXXXXXXX (464,000.00) 0.00
SUFFOLK (GA-R) VAB INCREASE-EASEMENT ACQUISITION SERVICES-OBST REMOVAL-BL AUG 19, 21 CS0050-42 36,860.00
AMEND 1-EASEMENT ACQUISITION SERVICES-OBST REMOVAL-BL SEP 27, 21 CS0050-42 36,860.00 0.00
CAF Allocation Status FY22.xlsx
VAB Package December 2021 31
COMMONWEALTH AVIATION FUND ALLOCATION STATUS
For the FYE June 30, 2022
as of July 7, 2021
updated 11/9/21 MS AIRPORT TENTATIVE ALLOCATION STATUS
AIRPORT DESCRIPTION DATE FAA FY PROJECT # DISCRETIONARY GRANT T.A. BALANCE
TANGIER ISLAND (GA-C)
TAPPAHANNOCK - ESSEX COUNTY (GA-R)
TAZEWELL COUNTY (GA-R) VAB INCREASE-EASEMENT ACQUISITION SERVICES-OBST REMOVAL-BL AUG 19, 21 CS0053-34 11,520.00
AMEND 1-EASEMENT ACQUISITION SERVICES-OBST REMOVAL-BL AUG 31, 21 CS0053-34 11,520.00 0.00
TWIN COUNTY (GA-C) TERMINAL BUILDING SECURITY CAMERAS REPLACEMENT JUN 17, 21 CS0020-29 3,577.00
GRANT-TERMINAL BUILDING SECURITY CAMERAS REPLACEMENT JUL 27, 21 CS0020-29 3,577.00 0.00
VIRGINIA HIGHLANDS (GA-R) RUNWAY 6-24 EXTENSION-PHASE 5 (EMBANKMENT SEASON 3) MAR 18, 21 XXXXXXXXX 334,000.00
SPON RET-RWY 6-24 EXTEN-PHASE 5 (EMBANKMENT SEASON 3) OCT 13, 21 XXXXXXXXX (334,000.00) 0.00
VIRGINIA TECH (GA-R) RUNWAY 12-30 EXTENSION-LAND ACQUISITION-PHASE 3 MAR 18, 21 XXXXXXXXX 57,777.00
SPONSOR RETURN-RUNWAY 12-30 EXTENSION-LAND ACQUISITION-PHASOCT 13, 21 XXXXXXXXX (577,777.00)
LOCALIZER ACCESS ROAD (CON) JUN 17, 21 CS0002-22 31,146.00
GRANT-LOCALIZER ACCESS ROAD (CON) JUL 19, 21 CS0002-22 31,146.00
BOX HANGAR SITE PREPARATION (DES) JUN 17, 21 CS0002-23 42,445.00
GRANT-BOX HANGAR SITE PREPARATION (DES) JUL 19, 21 CS0002-23 42,445.00
STORMWATER POLLUTION PREVENTION PLAN UPDATE JUN 17, 21 CS0002-24 6,530.00
GRANT-STORMWATER POLLUTION PREVENTION PLAN UPDATE JUL 19, 21 CS0002-24 6,530.00 (520,000.00)
WAKEFIELD MUNICIPAL (GA-C) (NON-NPIAS) RUNWAY LIGHTING REHABILITATION (DES) JUN 17, 21 CS9071-18 40,000.00
GRANT-RUNWAY LIGHTING REHABILITATION (DES) AUG 30, 21 CS9071-18 40,000.00 0.00
WARRENTON-FAUQUIER (REL)
WILLIAM M TUCK (GA-R)
WILLIAMSBURG-JAMESTOWN (GA-C) (NON-NPIAS) REALLOCATED FROM JAMES CITY COUNTY-ACCESS ROAD OCT 4, 21 CS9010-39 9,132.80
GRANT-REALLOCATED FROM JAMES CITY COUNTY-ACCESS ROAD NOV 8, 21 CS9010-39 9,132.80 0.00
WINCHESTER REGIONAL (GA-R)
OPEN T.A. BALANCE AS OF 7/7/21 55,721.11
TOTAL PLACED UNDER GRANT FY 2022 2,908,142.77
CAF Allocation Status FY22.xlsx
VAB Package December 2021 32
COMMONWEALTH AVIATION FUND ALLOCATION STATUS
For the FYE June 30, 2022
as of July 7, 2021
updated 11/9/21 MS AIRPORT TENTATIVE ALLOCATION STATUS
AIRPORT DESCRIPTION DATE FAA FY PROJECT # DISCRETIONARY GRANT T.A. BALANCE
TOTAL ALLOCATIONS 2,963,863.88
TEST CHECK 0.00
STATE/LOCAL PROJECT
FEDERAL/STATE/LOCAL PROJECT
COMBINED FUND - STATE/LOCAL PROJECT
COMBINED FUND - FEDERAL/STATE/LOCAL PROJECT
CAF Allocation Status FY22.xlsx
VAB Package December 2021 33
CONTRACT/GRANT DOLLARS
08/24/21 ANJ DEPARTMENT OF AVIATION
FACILITIES AND EQUIPMENT PROGRAM
No Funds No Funds Allocations and Expenditures
For the FYE June 30, 2022
Other issues
AIRPORT ALLOCATION STATUS
AIRPORT DESCRIPTION / VO. PAYEE Vo. # DATE W.O. # ALLOCATION EXPENDITURE UNEXP. BALANCE REVIEW
ORIGINAL APPROPRIATION 2020-2021 635,236.00
PLUS: PRIOR YEAR O/S COMMITMENTS XXXXXX
TOTAL APPROPRIATION FY '21 635,236.00
1 ACCOMACK COUNTY NEXT PROJECT FE0033-56 0.00
0.00
2 BLACKSTONE AAF NEXT PROJECT FE0008-07 0.00
0.00
3 BLUE RIDGE NEXT PROJECT FM0032-49 0.00
0.00
4 BRIDGEWATER AIRPARK NEXT PROJECT FE9072-10 0.00
OBS OFF-SITE 9/15/16 0.00
5 BROOKNEAL/CAMPBELL NEXT PROJECT FM0062-11 0.00
0.00
6 BRUNSWICK CO. NEXT PROJECT FM9012-10 0.00
0.00
7 CHARLOTT-ALBEMARLE NEXT PROJECT FE0004-12 0.00
0.00
8 CHASE CITY MUNI NEXT PROJECT FM0005-03 0.00
0.00
9 CHESAPEAKE REGIONAL NEXT PROJECT FM0006-66 0.00
0.00
10 CHESTERFIELD COUNTY NEXT PROJECT FM0007-39 C 0.00
0.00
11 CREWE MUNICIPAL NEXT PROJECT FE9065-06 0.00
0.00
12 CULPEPER REGIONAL NEXT PROJECT FE0010-18 C 0.00
0.00
300 DOAVAS 20210701 F&E Allocation Status FY22.xlsx
VAB Package December 2021 34
CONTRACT/GRANT DOLLARS
08/24/21 ANJ DEPARTMENT OF AVIATION
FACILITIES AND EQUIPMENT PROGRAM
No Funds No Funds Allocations and Expenditures
For the FYE June 30, 2022
Other issues
AIRPORT ALLOCATION STATUS
AIRPORT DESCRIPTION / VO. PAYEE Vo. # DATE W.O. # ALLOCATION EXPENDITURE UNEXP. BALANCE REVIEW
13 DANVILLE RGNL NEXT PROJECT FM0011-26 0.00
0.00
14 DINWIDDIE COUNTY NEXT PROJECT C FM0039-29 0.00
0.00
15 DULLES INTL NEXT PROJECT XXXXXX.XX 0.00
0.00
16 EAGLE'S NEST NEXT PROJECT FM9089-08 0.00
0.00
17 EMPORIA-GREENVILLE RGNL NDB REMOVAL - DGS BILLINGS FE0013-22 153.00
Department of General Services 6807 8/3/21 FE0013-22 153.00 0.00
18 FALWELL NEXT PROJECT FE9073-03 0.00
No Master Agreement 0.00
19 FARMVILLE RGNL NEXT PROJECT FM0015-40 0.00
0.00
20 FRANKLIN MUNICIPAL NEXT PROJECT FE0017-16 0.00
Obst. Mitigated 7/17/19 0.00
21 FRONT ROYAL-WARREN CO NEXT PROJECT FM0019-05 0.00
0.00
22 GORDONSVILLE MUNI. NEXT PROJECT FE9070-06 0.00
0.00
23 GRUNDY MUNICIPAL NEXT PROJECT FE0022-07 0.00
0.00
24 HAMPTON ROADS EXEC NEXT PROJECT FE0040-16 C 0.00
0.00
25 HANOVER CO MUNI NEXT PROJECT FE0023-40 0.00
0.00
26 HUMMEL FIELD (SALUDA) CO 1 PAPI INSTALL (DESIGN) 9/20/17 FM0076-13 2,640.00
2,640.00
NEXT PROJECT FM0076-17 0.00
0.00
300 DOAVAS 20210701 F&E Allocation Status FY22.xlsx
VAB Package December 2021 35
CONTRACT/GRANT DOLLARS
08/24/21 ANJ DEPARTMENT OF AVIATION
FACILITIES AND EQUIPMENT PROGRAM
No Funds No Funds Allocations and Expenditures
For the FYE June 30, 2022
Other issues
AIRPORT ALLOCATION STATUS
AIRPORT DESCRIPTION / VO. PAYEE Vo. # DATE W.O. # ALLOCATION EXPENDITURE UNEXP. BALANCE REVIEW
27 INGALL'S FIELD NEXT PROJECT FM0024-26 0.00
0.00
28 LAKE ANNA NEXT PROJECT FM9027-12
0.00
29 LAKE COUNTRY NEXT PROJECT FM9060-12 0.00
0.00
30 LEE COUNTY NEXT PROJECT FM0084-06 C 0.00
0.00
31 LEESBURG EXECUTIVE NEXT PROJECT FE0027-45 0.00
0.00
32 LONESOME PINE NEXT PROJECT FE0060-20 0.00
0.00
33 LOUISA COUNTY NEXT PROJECT FE0078-27 0.00
0.00
34 LUNENBURG COUNTY NEXT PROJECT FE0025-03 0.00
0.00
35 LURAY CAVERNS NEXT PROJECT FE0067-08 C 0.00
0.00
36 LYNCHBURG REGIONAL NEXT PROJECT FE0029-XX 0.00
0.00
37 MANASSAS REGIONAL NEXT PROJECT FM0030-31 0.00
0.00
38 MECK-BRUNSWICK RGNL NEXT PROJECT FE0070-36 0.00
0.00
39 MIDDLE PENINSULA RGNL NEXT PROJECT FE0057-21 0.00
0.00
300 DOAVAS 20210701 F&E Allocation Status FY22.xlsx
VAB Package December 2021 36
CONTRACT/GRANT DOLLARS
08/24/21 ANJ DEPARTMENT OF AVIATION
FACILITIES AND EQUIPMENT PROGRAM
No Funds No Funds Allocations and Expenditures
For the FYE June 30, 2022
Other issues
AIRPORT ALLOCATION STATUS
AIRPORT DESCRIPTION / VO. PAYEE Vo. # DATE W.O. # ALLOCATION EXPENDITURE UNEXP. BALANCE REVIEW
40 MOUNTAIN EMPIRE NEXT PROJECT FE0031-30 0.00
OBS OFF-SITE 6/16/16 0.00
41 NEW KENT COUNTY NEXT PROJECT FM0041-15 0.00
0.00
42 NEW LONDON NEXT PROJECT FE9083-01 0.00
0.00
43 NEW MARKET NEXT PROJECT FE9084-03 0.00
0.00
44 NEW. NEWS/WMSBG INTL NEXT PROJECT FE0035-22 0.00
0.00
45 NEW RIVER VALLEY NEXT PROJECT FM0012-27 0.00
0.00
46 NORFOLK INT'L NEXT PROJECT FE0036-17 0.00
0.00
47 ORANGE COUNTY NEXT PROJECT FE0037-18 0.00
ONGOING OBS RWY 26 0.00
48 RICHMOND INT'L NEXT PROJECT FE0043-22 0.00
0.00
49 ROANOKE REGIONAL NEXT PROJECT FE0045-05 0.00
0.00
50 SHANNON NEXT PROJECT FE9016-12 0.00
0.00
51 SHENANDOAH VALLEY REG. NEXT PROJECT FE0049-35 0.00
0.00
52 SMITH MOUNTAIN LAKE NEXT PROJECT FM9040-02 C 0.00
0.00
53 STAFFORD RGNL NEXT PROJECT FE0069-16 200,000.00
300 DOAVAS 20210701 F&E Allocation Status FY22.xlsx
VAB Package December 2021 37
CONTRACT/GRANT DOLLARS
08/24/21 ANJ DEPARTMENT OF AVIATION
FACILITIES AND EQUIPMENT PROGRAM
No Funds No Funds Allocations and Expenditures
For the FYE June 30, 2022
Other issues
AIRPORT ALLOCATION STATUS
AIRPORT DESCRIPTION / VO. PAYEE Vo. # DATE W.O. # ALLOCATION EXPENDITURE UNEXP. BALANCE REVIEW
200,000.00
54 SUFFOLK MUNICIPAL NEXT PROJECT FE0050-39 0.00
0.00
55 TANGIER ISLAND NEXT PROJECT FE0051-05 0.00
0.00
56A TAPPAHANNOCK-ESSEX NEXT PROJECT FE0081-30 0.00
0.00
57 TAZEWELL COUNTY NEXT PROJECT FE0053-25 0.00
0.00
58 TWIN COUNTY NEXT PROJECT FE0020-32 0.00
0.00
59 VIRGINIA HIGHLANDS NEXT PROJECT FM0001-08 0.00
0.00
60 VIRGINIA TECH REPLACE LOCALIZER - EQUIP., INSTALL & FLT CHK 1/29/20 FE0002-52 183,000.00
Virginia Tech 6942 9/30/21 FE0002-52 4,475.00 178,525.00
61 WAKEFIELD MUNICIPAL NEXT PROJECT FE9071-02 0.00
Obstructions 0.00
62 WARRENTON-FAUQUIER AWOS RADIO REPAIR / REPLACEMENT FM0068-24 0.00
0.00
63 WILLIAMSBURG/JAMESTOWN REPAIR BAR VASI SYSTEM 10/1/19 FM9010-11 3,740.79
Monitor APT Condition 3,740.79 Begin 07-10
64 WILLIAM TUCK/SOUTH BOSTON NEXT PROJECT FE0047-03 0.00
0.00
65 WINCHESTER REGIONAL NEXT PROJECT FM0059-51 0.00
0.00
DEPARTMENT OF AVIATION***** WAREHOUSE STOCK / REPAIR ITEMS 7/1/20 FE9999-01 5,000.00
5,000.00
AUSTIN ELECTRICAL CONSTR. - NAV. MAINT. 7/1/19 FE9999-02 105,140.46 (Remaining bal from FY'21)
Austin Electrical Constrtuction 6742 7/9/21 FE9999-02 7,680.00 9,247.62
300 DOAVAS 20210701 F&E Allocation Status FY22.xlsx
VAB Package December 2021 38
CONTRACT/GRANT DOLLARS
08/24/21 ANJ DEPARTMENT OF AVIATION
FACILITIES AND EQUIPMENT PROGRAM
No Funds No Funds Allocations and Expenditures
For the FYE June 30, 2022
Other issues
AIRPORT ALLOCATION STATUS
AIRPORT DESCRIPTION / VO. PAYEE Vo. # DATE W.O. # ALLOCATION EXPENDITURE UNEXP. BALANCE REVIEW
Austin Electrical Constrtuction 6776 07/20/21 FE9999-02 7,220.00
Austin Electrical Constrtuction 6802 7/30/2021 FE9999-02 6,375.00
Austin Electrical Constrtuction 6803 7/30/2021 FE9999-02 737.84
Austin Electrical Constrtuction 6815 8/10/21 FE9999-02 5,545.00
Austin Electrical Constrtuction 6854 8/25/21 FE9999-02 9,180.00
Austin Electrical Constrtuction 6886 9/7/21 FE9999-02 7,010.00
Austin Electrical Constrtuction 6887 9/7/21 FE9999-02 735.00
Austin Electrical Constrtuction 6915 9/16/21 FE9999-02 10,250.00
Austin Electrical Constrtuction 6927 9/22/21 FE9999-02 12,315.00
Austin Electrical Constrtuction 6941 9/30/21 FE9999-02 9,510.00
Austin Electrical Constrtuction 6986 10/20/21 FE9999-02 5,960.00
Austin Electrical Constrtuction 6987 10/20/21 FE9999-02 7,220.00
Austin Electrical Constrtuction 7009 10/28/21 FE9999-02 6,155.00
DEAN KENNEDY - ILS TECH. SERV. - NAV. MAINT. 7/1/19 FE9999-03 59,055.00 (Remaining bal from FY'21)
ILS Technical Service 6743 7/9/21 FE9999-03 6,060.00 30,735.00
ILS Technical Service 6812 08/04/21 FE9999-03 3,760.00
ILS Technical Service 6885 9/7/21 FE9999-03 8,900.00
ILS Technical Service 6955 10/7/21 FE9999-03 3,675.00
ILS Technical Service 7023 11/10/21 FE9999-03 5,925.00
SURVEY EQUIPMENT (cc. 541, ac 1311) 11/6/20 FE9999-55 540.00
540.00
SOUTHERN AVIONICS - NDB PARTS FE9999-57 0.00
0.00
THALES - (AIRSYS ATM) - PARTS 7/1/21 FE9999-58 4,194.00 (Remaining bal from FY'21)
MARK 1F LOC PARTS 8/24/21 FE9999-58 7,004.00 11,198.00
SELEX ( OLD ARLENIA MARCONI SYSTEMS (ASII)) - PARTS 7/1/21 FE9999-59 5,000.00
5,000.00
UPS/FEDEX SHIPPING FE9999-60 500.00
cc541 ac1212 500.00
AAR COOPER (MIC'S/Antenna's) FE9999-62 0.00
0.00
PARK AIR INC. - AWOS TRANSCEIVER FE9999-63 0.00
0.00
INTERNATIONAL CRYSTAL MANUF FE9999-65 0.00
0.00
FAA DEPOT FE9999-66 0.00
0.00
300 DOAVAS 20210701 F&E Allocation Status FY22.xlsx
VAB Package December 2021 39
CONTRACT/GRANT DOLLARS
08/24/21 ANJ DEPARTMENT OF AVIATION
FACILITIES AND EQUIPMENT PROGRAM
No Funds No Funds Allocations and Expenditures
For the FYE June 30, 2022
Other issues
AIRPORT ALLOCATION STATUS
AIRPORT DESCRIPTION / VO. PAYEE Vo. # DATE W.O. # ALLOCATION EXPENDITURE UNEXP. BALANCE REVIEW
MCG SURGE PROTECTION FE9999-67 0.00
0.00
AWOS DATA NETWORKING 7/1/21 FE9999-69 8,288.05 (Remaining bal from FY'22)
RSI NETLLC 6804 8/2/21 FE9999-69 3,538.04 1,211.76
RSI NETLLC 6988 10/21/21 FE9999-69 3,538.25
UNICOM RADIOS 7/1/20 FE9999-70 0.00
0.00
NAVAID BUILDING REPAIRS - LKU A/C 7/1/21 FE9999-71 0.00
0.00
BIRD ELECTRONICS FE9999-74 0.00
0.00
NAVAID COMPUTER SERVICE - VITA FE9999-75 0.00
0.00
B R COMMUNICATIONS (UNICOMS) FE9999-77 0.00
0.00
NAVAID BUILDINGS - TRANSPORT FE9999-83 0.00
0.00
PUBLICATION SUBSCRIPTIONS 7/1/21 FE9999-84 57.86
INCREASE (New P.O. & price increase) 8/23/21 FE9999-84 300.00 357.86 (Remaining bal from FY'22)
OPEN T.A. / GRANT BALANCE AS OF REPORT DATE 448,696.03
TOTAL EXPENDITURES AS OF SEPT 2020 * 135,917.13
TOTAL ALLOCATIONS AS OF REPORT DATE equest additional appropriation at 80%) $520K = 80% 584,613.16
$0.00 test check
APPROPRIATIONS UNALLOCATED 50,622.84
28,072.84 July total (rev. 20210917)
22,176.04 Aug
53,195.00 Sept chk'd 20210917
26,548.25 Oct
0.00 Nov
0.00 Dec
0.00 Jan
0.00 Feb
300 DOAVAS 20210701 F&E Allocation Status FY22.xlsx
VAB Package December 2021 40
CONTRACT/GRANT DOLLARS
08/24/21 ANJ DEPARTMENT OF AVIATION
FACILITIES AND EQUIPMENT PROGRAM
No Funds No Funds Allocations and Expenditures
For the FYE June 30, 2022
Other issues
AIRPORT ALLOCATION STATUS
AIRPORT DESCRIPTION / VO. PAYEE Vo. # DATE W.O. # ALLOCATION EXPENDITURE UNEXP. BALANCE REVIEW
0.00 Mar
0.00 April
0.00 May
0.00 June
* 129,992.13 Total Expended
300 DOAVAS 20210701 F&E Allocation Status FY22.xlsx
VAB Package December 2021 41
Balance Test DEPARTMENT OF AVIATION260,892.49 0.00 MAINTENANCE PROGRAM
Allocations and Expenditures No Funds For the FYE June 30, 2022
Other issues APPROPRIATION JULY, 2021 750,000.00 OBSTRUCTIONS
LESS PRIOR YEAR OVERCOMMITTMENT 0.0011/16/21 - ANJ PLUS: PRIOR YEAR COMMITMENTS XXXXXX
-----------------------------------------------------------------------------------------------------------TOTAL APPROPRIATION FY 2022 750,000.00 **
** $75,000 MAX TO SPONSOR PER YEAR =
AIRPORT Expiration DESCRIPTION / VO. PAYEE VO. NO. DATE PROJ. # JULY-SEPT OCT-DEC JAN-MAR APR-JUN EXPENDITURE UNEXP. BALANCE
ACCOMACK (T 80%, F 67%) 9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0033-17 C 1,220.0061,877.61 Accomack County 6878 8/31/21 MT0033-17 1,140.00 80.00
11/30/21 REPLACE TERMINAL BUILDING ENTRANCE DOORS 5/27/21 MT0033-24 C 6,960.00Accomack County 7028 11/10/21 MT0033-24 6,960.00 0.00
9/1/21 AWOS EVAL - TEMP SENSOR 5/27/21 MT0033-25 C 1,002.25FINAL DECREASE - SP 8/30/21 MT0033-25 (760.00) 0.00Accomack County 6868 8/31/21 MT0033-25 242.25
11/1/21 REPLACE PCA VOICE SPARE AWOS 5/27/21 MT0033-26 C 4,062.69FINAL DECREASE - SP 10/26/21 MT0033-26 (2,862.55) (0.00)Accomack County 700 10/28/21 MT0033-26 1,200.14
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0033-27 3,500.00Accomack County 7012 10/28/21 MT0033-27 1,140.00 2,360.00
9/1/21 REPLACE AWOS TEMP PROBE 7/14/21 MT0033-28 C 1,960.14Accomack County 6,873.00 8/31/21 MT0033-28 1,960.14 0.00
BLACKSTONE (T: ?, F: 33%) 12/15/21 AWOS EVALUATION & REPAIR 9/9/21 MT0008-13 1,273.0071,795.98 INCREASE FOR ADDT'L REPAIR 11/4/21 MT0008-13 1,931.02 3,204.02
BLUE RIDGE (T 80%, F 80%) 9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0032-60 C 3,500.0068,000.00 Blue Ridge Airport Authority 6727 7/1/21 MT0032-60 3,420.00 80.00
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0032-64 3,500.003,500.00
11/1/21 TAXIWAY LIGHTING OUTAGE 7/20/21 MT0032-65 844.00844.00
10/1/21 AWOS OUTAGE 8/12/21 MT0032-66 C 1,192.25Blue Ridge Airport Authority 6935 9/30/21 MT0032-66 1,192.25 0.00
BRIDGEWATER 9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT9072-17 C 1,220.00Identified 9/15/16 Dynamic Aviation Group Inc 6770 7/20/21 MT9072-17 1,140.00 80.0073,780.00
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT9072-19 3,500.00Dynamic Aviation Group Inc 7027 11/10/21 MT9072-19 1,140.00 2,360.00
BROOKNEAL (T: ?, F: 67%) 11/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0062-34 C 3,500.0071,500.00 FINAL - DECREASE 9/8/21 MT0062-34 (1,315.00) 0.00
Brookneal Campbell Airport Authority 6906 9/13/21 MT0062-34 2,185.00
11/1/21 WEEDKILL APPLICATION 5/27/21 MT0062-35 C 3,024.00FINAL 9/10/21 MT0062-35 0.00Brookneal Campbell Airport Authority 6905 9/13/21 MT0062-35 3,024.00
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0062-36 3,500.003,500.00
AWOS OUTAGE EVALUATION 10/22/21 MT0062-37 1,192.251,192.25
BRUNSWICK COUNTY 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT9012-54 3,500.0071,500.00 3,500.00
CHARLOTTESVILLE NEXT MT0004-56 0.0058,098.75 0.00
CHASE CITY 9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0005-19 C 1,220.0070,360.00 FINAL - DECREASE 7/21/21 MT0005-19 (80.00) 0.00
AIRPORT ALLOCATION STATUS
300 DOAVAS 20210701 Maintenance Allocation Status FY22.xlsx
VAB Package December 2021 42
AIRPORT Expiration DESCRIPTION / VO. PAYEE VO. NO. DATE PROJ. # JULY-SEPT OCT-DEC JAN-MAR APR-JUN EXPENDITURE UNEXP. BALANCE AIRPORT ALLOCATION STATUS
Town of Chase City 6789 7/27/21 MT0005-19 1,140.00
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0005-20 3,500.003,500.00
NEXT PROJECT MT0005-21 0.000.00
CHESAPEAKE(T: 80, F: 50%) 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0006-82 3,500.0070,125.76 3,500.00
3/1/22 REPLACEMENT AIRFIELD LAMPS 10/28/21 MT0006-83 1,374.241,374.24
CREWE (T: 80, F: 67%) 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT9065-30 3,500.0071,500.00 3,500.00
CULPEPER (T: ?, F: 67%) 9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0010-44 C 1,220.0073,780.00 County of Culpeper 6756 7/13/21 MT0010-44 1,140.00 80.00
9/1/21 2021 WEEDKILL APPLICATION 5/27/21 MT0010-46 C 3,289.00FINAL DECREASE - SP 8/17/21 MT0010-46 (481.80) 0.00County Of Culpeper 6837 8/17/21 MT0010-46 2,807.20
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0010-47 3,500.003,500.00
DANVILLE (T 28.1%, PARK 25%) NEXT PROJECT MT0011-48 C 0.0075,000.00 0.00
DEPARTMENT OF MILITARY AFFAIRS 9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0DMA-07 ? 3,500.00CLOSE - ANJ 9/14/21 MT0DMA-07 (3,500.00) 0.00
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0DMA-08 3,500.003,500.00
NEXT PROJECT MT0DMA-09 0.000.00
DINWIDDIE (T: 72%, F: ?%) 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0039-33 3,500.0071,500.00 3,500.00
11/1/21 REIL COMPLETION 7/29/21 MT0039-34 1,598.921,598.92
EAGLE'S NEST 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT9089-28 3,500.0071,500.00 Aero Drive Farm, Inc 6761 7/14/21 MT9089-28 1,140.00 2,360.00
NEXT PROJECT MT9089-29 0.000.00
EMPORIA-GREENSVILLE (T: 77, F: ?%) 11/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0013-79 1,220.0063,983.00 1,220.00
11/1/21 OBSTRUCTION IDENTIFICATION 5/27/21 MT0013-80 C 3,360.00FINAL - INCREASE (ALLOWABLE 10%) 10/19/21 MT0013-80 336.00 0.00Emporia Greensville Airportr 6992 10/25/21 MT0013-80 3,696.00
3/1/22 EVALUATION AWOS OUTAGE (95%) 5/27/21 MT0013-81 1,273.001,273.00
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0013-82 3,500.003,500.00
12/1/21 ROTATING BEACON TROUBLESHOOT 7/14/21 MT0013-83 C 928.00INCREASE ALLOCATION PER RCVD QUOTE ON 6/30/21 - ANJ 11/4/21 MT0013-83 400.00 0.00FINAL 11/4/21 MT0013-83Emporia Greenville Airport Commission 7030 11/10/21 MT0013-83 1,328.00
FALWELL NEXT PROJECT MT9073-17 0.0075,000.00 0.00Missing State Funding Annual ReportFunding Report - N/A - no funds rec'd -VCNo Master Agreement
FARMVILLE (T: 80, F: 33%) 9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0015-10 C 1,220.0066,892.50 FINAL - DECREASE 7/21/21 MT0015-10 (80.00) 0.00
Town of Farmville 6790 7/27/21 MT0015-10 1,140.00
300 DOAVAS 20210701 Maintenance Allocation Status FY22.xlsx
VAB Package December 2021 43
AIRPORT Expiration DESCRIPTION / VO. PAYEE VO. NO. DATE PROJ. # JULY-SEPT OCT-DEC JAN-MAR APR-JUN EXPENDITURE UNEXP. BALANCE AIRPORT ALLOCATION STATUS
9/1/21 AWOS TROUBLESHOOT 4/1/21 MT0015-13 C 1,140.00FINAL - DECREASE 7/21/21 MT0015-13 (57.00) 0.00Town of Farmville 6791 7/27/21 MT0015-13 1,083.00
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0015-14 3,500.003,500.00
12/15/21 AWOS DIAL-UP EVALUATION 7/14/21 MT0015-15 2,384.502,384.50
3/1/22 AWOS OUTAGE EVALUATION 10/28/21 MT0015-16 1,273.001,273.00
FRANKLIN (T: 80, F: 67%) 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0017-74 3,500.00Obst. Mitigated 7/17/19 3,500.0071,500.00
FRONT ROYAL (T: 78%, F: ?%) 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0019-59 3,500.0071,500.00 3,500.00
3/1/22 AWOS WIND SENSOR REPLACEMENT 10/28/21 MT0019-60 1,678.86INCREASE FOR ADDT'L REPAIRS 11/12/21 MT0019-60 1,837.14
3,516.00
GORDONSVILLE 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT9070-33 3,500.0071,500.00 Town of Gordonsville 6859 8/25/21 MT9070-33 1,140.00 2,360.00
GRUNDY NEXT PROJECT MT0022-17 0.0075,000.00 0.00
HAMPTON ROADS 11/1/21 RWY 28 REILS REPAIR 3/18/21 MT0040-76 C 5,892.0063,927.05 Hampton Roads Airport 6869 8/31/21 MT0040-76 4,619.30 1,272.70
9/1/21 2021 WEEDKILL APPLICATION 5/27/21 MT0040-77 C 3,480.00HAMPTON ROADS AIRPORT 6760 7/13/21 MT0040-77 3,480.00 0.00
11/1/21 RWY 28 REILS ADDITIONAL MOBILIZATION 8/26/21 MT0040-78 C 1,700.95Hampton Roads Airport 6984 10/20/21 MT0040-78 1,700.95 0.00
HANOVER (T: ?, F: 50%) 5/31/22 ZERO TURN MOWER - KUBOTA 9/3/21 MT0023-60 C 6,976.6168,023.39 6,976.61
HUMMEL FIELD (T 65%, F 67%) 9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0076-69 C 1,220.0069,500.00 Middlesex County 6838 8/17/21 MT0076-69 1,140.00 80.00
9/1/21 2021 WEEDKILL APPLICATION 5/27/21 MT0076-71 C 780.00Middlesex County 6839 8/17/21 MT0076-71 780.00 0.00
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0076-72 3,500.003,500.00
INGALLS FIELD (T 80%, F 67%) 11/1/20 FY20 AWOS INSP & REPAIR 7/1/19 MT0024-96 C 2,090.0071,698.94 2,090.00
11/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0024-01 1,211.061,211.06
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0024-03 3,500.003,500.00
11/1/21 AWOS OUTAGE 9/9/21 MT0024-04 C 1,273.00Bath County Airport Commission 6959 10/12/21 MT0024-04 1,273.00 0.00
LAKE ANNA 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT9027-31 3,500.0071,500.00 Miles High Charters LLC 6783 7/26/21 MT9027-31 1,140.00 2,360.00
LAKE COUNTRY 9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT9060-57 C 3,500.0065,324.80 Lake County Airport Commission 6825 8/10/21 MT9060-57 3,420.00 0.00
CLOSED - ANJ 11/8/21 MT9060-57 (80.00)
11/1/21 WEED CONTROL 5/27/21 MT9060-59 C 2,755.20FINAL 9/8/21 MT9060-59 0.00Lake Counyty Airport Commission 6903 9/13/21 MT9060-59 2,755.20
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT9060-60 3,500.003,500.00
300 DOAVAS 20210701 Maintenance Allocation Status FY22.xlsx
VAB Package December 2021 44
AIRPORT Expiration DESCRIPTION / VO. PAYEE VO. NO. DATE PROJ. # JULY-SEPT OCT-DEC JAN-MAR APR-JUN EXPENDITURE UNEXP. BALANCE AIRPORT ALLOCATION STATUS
LEE COUNTY 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0084-33 3,500.0066,862.05 3,500.00
12/1/21 AWOS TEMPERATURE PROBE REPLACEMENT 8/12/21 MT0084-34 C 2,717.95FINAL 11/3/21 MT0084-34 0.00Lee County 7031 11/10/21 MT0084-34 2,717.95
12/1/21 RWY 25 PAPI TROUBLESHOOT 8/17/21 MT0084-35 C 800.00FINAL 11/3/21 MT0084-35 0.00Lee County 7032 11/10/21 MT0084-35 800.00
12/1/21 ROTATING BEACON TROUBLESHOOT 9/23/21 MT0084-36 C 1,120.00FINAL 11/3/21 MT0084-36 0.00Lee County 7033 11/10/21 MT0084-36 1,120.00
LEESBURG 9/1/21 HERBICIDE TREATMENT - APRONS & FENCE 5/27/21 MT0027-08 C 2,240.0068,610.44 Town of Leesburg 6850 8/24/21 MT0027-08 2,240.00 0.00
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0027-09 3,500.003,500.00
11/1/21 AWOS TEMP SENSOR 8/26/21 MT0027-10 C 649.56Town Of Leesburg 6956 10/12/21 MT0027-10 649.56 0.00
LONESOME PINE (T 81%, F %) 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0060-51 3,500.0068,589.60 3,500.00
11/1/21 PLUMBING REPAIRS (80%) 7/29/21 MT0060-52 C 1,591.20FINAL 9/8/21 MT0060-52 0.00Cumberland Airport Commission 6904 9/13/21 MT0060-52 1,591.20
3/1/22 PCL TROUBLESHOOT 11/4/21 MT0060-53 480.00FINAL 11/16/21 MT0060-53 0.00Cumberlands Airport Commission 7044 11/17/21 MT0060-53 480.00
3/1/22 ODAL EVALUTATION 11/12/21 MT0060-54 839.20839.20
LOUISA 9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0078-79 C 1,220.0070,280.00 1,220.00
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0078-82 3,500.00Louisa County 6960 10/12/21 MT0078-82 1,140.00 2,360.00
11/1/21 AWOS EVAL AND REPAIR WEATHER SENSOR 9/16/21 MT0078-83 C 1,083.00FINAL DECREASE - SP 10/26/21 MT0078-83 (760.00) 0.00Industrial Development Autority Of Louisa County 7014 10/28/21 MT0078-83 323.00
LUNENBURG 9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0025-52 C 3,500.0061,923.89 FINAL - DECREASE 7/21/21 MT0025-52 (1,742.50) 0.00Obstructions identified 8/11/21 County of Lunenburg Board Of Supervisors 6792 7/27/21 MT0025-52 1,757.50Sponsor notified 8/26/21
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0025-54 3,500.003,500.00
12/15/21 WINDSOCK REPLACEMENT 7/29/21 MT0025-55 143.28FINAL - DECREASE 11/16/21 MT0025-55 (11.14) 0.00County Of Lunenburg Board of Supervisors 7045 11/17/21 MT0025-55 132.14
12/15/21 AWOS TEMP/DEW POINT SENSOR REPAIR 8/12/21 MT0025-56 C 1,667.25FINAL 11/9/21 MT0025-56 0.00County Of Lunenburg Board of Supervisors 7043 11/17/21 MT0025-56 1,667.25
12/15/21 FUEL FARM FLOW METER REPAIR (67%) 8/12/21 MT0025-57 2,465.60INCREASE FOR REPAIRS 9/23/21 MT0025-57 3,553.62 0.00FINAL - DECREASE 11/9/21 MT0025-57 (1,872.49)County of Lunenburg Board Of Supervisors 7046 11/17/21 MT0025-57 4,146.73
LURAY 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0067-45 3,500.0071,500.00 3,500.00
12/1/21 VENTRAC 4500Y MOWER 7/27/21 MT0067-46 C 14,757.20FINAL - DECREASE 11/9/21 MT0067-46 (6.25) 14,750.95
LYNCHBURG REGIONAL NEXT PROJECT MT0029-46 0.0075,000.00 0.00
MANASSAS REGIONAL (F=?, T: 69.5%) 9/1/21 TERMINAL BUILDING ROOF REPLACEMENT (Construction) 69.5% 7/28/20 MT0030-69 C 49,067.0025,933.00 FINAL 7/21/21 MT0030-69 0.00
300 DOAVAS 20210701 Maintenance Allocation Status FY22.xlsx
VAB Package December 2021 45
AIRPORT Expiration DESCRIPTION / VO. PAYEE VO. NO. DATE PROJ. # JULY-SEPT OCT-DEC JAN-MAR APR-JUN EXPENDITURE UNEXP. BALANCE AIRPORT ALLOCATION STATUS
City of Manassas 6793 7/27/21 MT0030-69 49,067.00
MECKLENBURG (T = 80%) 9/1/21 FUEL FARM PULSER (67%) 5/27/21 MT0070-81 C 830.1363,439.68 INCREASE FOR ADDT'L REPAIRS 7/14/21 MT0070-81 2,476.99 0.00
FINAL - DECREASE 8/25/21 MT0070-81 (830.13)Mecklenburg Brunswick Regional Airport Commission 6874 8/31/21 MT0070-81 2,476.99
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0070-84 3,500.003,500.00
12/15/21 SECURITY GATE KEYPAD REPLACEMENT 9/16/21 MT0070-85 981.18INCREASE FOR ADDT'L REPAIRS 10/7/21 MT0070-85 526.62 1,507.80
12/15/21 AIRFIELD LIGHTING REPAIRS 9/16/21 MT0070-86 3,422.403,422.40
12/15/21 AWOS WIND SENSOR BEARING REPLACEMENT (95%) 9/23/21 MT0070-87 653.13653.13
MIDDLE PENINSULA (T 70.2%, F 67%, W 12/31/21 TRACTOR REPLACEMENT 5/27/21 MT0057-40A C 29,550.00(5,898.76) MIDDLE PENINSULA REGIONAL AIRPORT 6750 7/12/21 MT0057-40A 29,550.00 0.00
9/1/21 AWOS CPU CARD REPLACEMENT 5/27/21 MT0057-41 C 3,013.84MIDDLE PENINSULA REGIONAL AIRPORT 6759 7/13/21 MT0057-41 3,013.74 0.10
11/1/21 LIGHTING REPAIRS 5/27/21 MT0057-42 C 1,864.00FINAL DECREASE - SP 9/21/21 MT0057-42 (640.00) 0.00Middle Peninsula Regional Airport 6930 9/22/21 MT0057-42 1,224.00
3/1/22 AV GAS PUMP REPAIR 5/27/21 MT0057-43 6,738.346,738.34
9/1/21 KUBOTA TIRES 5/27/21 MT0057-44 C 355.96DECREASE FINAL - SP 8/9/21 MT0057-44 (131.70) 0.00Middle Peninsula Regional Airport Authority 6822 8/10/21 MT0057-44 224.26
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0057-45 3,500.003,500.00
11/1/21 AWOS OUTAGE EVAL 8/9/21 MT0057-46 C 1,273.00FINAL DECREASE 10/18/21 MT0057-46 (950.00) 0.00Middle Peninsula Regional Airport Authority 6980 10/18/21 MT0057-46 323.00
5/31/22 REPLACE CEILOMETER (NB: Grant) 8/26/21 MT0057-47 34,180.7234,180.72
3/1/22 EVAL & REPAIR RWY LIGHT 9/30/21 MT0057-48 2,144.602,144.60
MOUNTAIN EMPIRE (T 75.2%, F 67%) 9/30/21 RWY 26 OBS REMOVAL (AIP) 9/20/17 MT0031-37 C 817.05Identified 6/16/16 INCREASE - RWY 26 OBS REMOVAL (AIP) JTH & VC 7/27/21 MT0031-37 2,730.0063,794.03 Smyth Wythe Airport Commission 6818 8/10/21 MT0031-37 3,547.05 0.00
9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0031-56 C 1,790.00CLOSED - ANJ 8/26/21 MT0031-56 (1,790.00) 0.00
9/1/21 OBSTRUCTION LIGHT WIRING REPAIR 10/1/20 MT0031-57 396.00CLOSED AT AIRPORT REQUEST 8/23/21 MT0031-57 (396.00) 0.00
9/1/21 AIRFIELD SIGNAGE TROUBLESHOOT 5/27/21 MT0031-59 400.00CLOSED AT AIRPORT REQUEST 8/26/21 MT0031-59 (400.00) 0.00
11/1/21 AIRFIELD LIGHTING REPLACEMENT LAMPS 5/27/21 MT0031-60 C 1,200.00FINAL - DECREASE 9/14/21 MT0031-60 (923.47) 0.00Smyth Wythe Airport Commission 6911 9/15/21 MT0031-60 276.53
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0031-62 3,500.003,500.00
12/15/21 AWOS CPU AND MODEM UPDATE (95%) 9/16/21 MT0031-63 C 3,778.63FINAL 10/19/21 MT0031-63 0.00Smyth Wythe Airport Commission 6993 10/25/21 MT0031-63 3,778.63
RUNWAY LIGHTS REPAIR KIT 11/12/21 MT0031-64 103.76103.76
NEW KENT (T: ?, F: 67%) 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0041-83 3,500.0070,704.85 3,500.00
9/1/21 FUEL FARM PUMP DISPENSER MOTOR REPLACE (67%) 7/14/21 MT0041-84 787.25
300 DOAVAS 20210701 Maintenance Allocation Status FY22.xlsx
VAB Package December 2021 46
AIRPORT Expiration DESCRIPTION / VO. PAYEE VO. NO. DATE PROJ. # JULY-SEPT OCT-DEC JAN-MAR APR-JUN EXPENDITURE UNEXP. BALANCE AIRPORT ALLOCATION STATUS
CLOSED AT AIRPORT REQUEST 9/16/21 MT0041-84 (787.25) 0.00
RWY/TWY LIGHTING REPAIRS 10/7/21 MT0041-85 795.15795.15
12/15/21 RWY 29 REIL REPAIR 10/15/21 MT0041-86 231.65231.65
NEW LONDON NEXT PROJECT MT9083-0375,000.00 0.00Missing State Funding Annual ReportFunding Report - N/A - no funds rec'd -VC
NEW MARKET 9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT9084-29 C 1,220.0070,360.00 FINAL DECREASE - SP 7/26/21 MT9084-29 (80.00) 0.00
Roberto O Thomas 6794 7/27/21 MT9084-29 1,140.00
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT9084-32 3,500.00Robert O. Thomas 7011 10/28/21 MT9084-32 1,140.00 2,360.00
NEW RIVER VALLEY 9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0012-27 C 1,116.1570,360.00 FINAL INCREASE - SP 23.85 0.00
New River Valley A/P Commission 6785 7/27/21 MT0012-27 1,140.00
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0012-28 3,500.00New River Valley Airport Comission 7047 11/17/21 MT0012-28 2,280.00 1,220.00
11/1/21 AWOS ASPIRATOR FAN 7/14/21 MT0012-29 C 1,105.04New River Valley A/P Commission 6910 9/15/21 MT0012-29 1,105.04 0.00
NEWPORT NEWS NEXT PROJECT MT0035-23 0.0075,000.00 0.00
NORFOLK NEXT PROJECT MT0036-33 0.0075,000.00 0.00
ORANGE COUNTY 9/1/21 AWOS SURGE SUPPRESSOR 5/27/21 MT0037-03 C 1,022.5869,898.65 County of Orange 6771 7/20/21 MT0037-03 1,022.58 0.00
9/1/21 REPAIR AWOS VHF RADIO 5/27/21 MT0037-04 C 1,338.77DECREASE FINAL - SP 7/20/21 MT0037-04 (760.00) 0.00County of Orange 6772 7/20/21 MT0037-04 578.77
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0037-05 3,500.003,500.00
RICHMOND EXECUTIVE (T: ?, F: 33%) 12/15/21 VEGETATION MANAGEMENT 9/16/21 MT0007-69 C 3,772.0071,228.00 FINAL 10/27/21 MT0007-69 0.00
Chesterfield County 7029 11/10/21 MT0007-69 3,772.00
RICHMOND INTERNATIONAL NEXT PROJECT MT0043-91 0.0075,000.00 0.00
ROANOKE NEXT PROJECT MT0045-56 0.0075,000.00 0.00
SHANNON 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT9016-67 3,500.00 C70,144.78 Shannon Airport, LLC 6757 7/12/21 MT9016-67 1,140.00
Shannon Airport, LLC 6953 10/6/21 MT9016-67 1,140.00 1,220.00
10/1/21 RUNWAY EDGE LIGHT BULB PURCHASE 7/29/21 MT9016-68 C 307.22Shannon Airport LLC 6824 8/10/21 MT9016-68 307.22 0.00
11/1/21 EVALUATE ROTATION BEACON OUTAGE 7/29/21 MT9016-69 C 1,048.00Shannon Airpprt LLC 6962 10/12/21 MT9016-69 1,048.00 0.00
10/1/21 PLASI BULB PURCHASE 8/12/21 MT9016-70 C 240.41Shannon Airport, LLC 6907 9/13/21 MT9016-70 240.41 0.00
1/1/22 ROTATING BEACON BULB PURCHASE 10/22/21 MT9016-71 C 150.48150.48
SHENANDOAH VALLEY NEXT PROJECT MT0049-46 0.000.00
SMITH MT. LAKE (T: 91.2%, F: %) 10/1/21 WIND SOCK REPLACEMENT 8/9/21 MT9040-33 C 62.30
300 DOAVAS 20210701 Maintenance Allocation Status FY22.xlsx
VAB Package December 2021 47
AIRPORT Expiration DESCRIPTION / VO. PAYEE VO. NO. DATE PROJ. # JULY-SEPT OCT-DEC JAN-MAR APR-JUN EXPENDITURE UNEXP. BALANCE AIRPORT ALLOCATION STATUS
74,558.65 Smith Mountain Lake Airport LLC 6851 8/24/21 MT9040-33 62.30 0.00
10/1/21 WEED CONTROL CHEMICALS 8/9/21 MT9040-34 C 366.30FINAL INCREASE - SP 8/23/21 MT9040-34 12.75 0.00Smith Mountain Lake Aiport 6852 8/24/21 MT9040-34 379.05
STAFFORD 9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0069-65 C 3,500.0069,492.28 Stafford Regional Airport 6870 8/31/21 MT0069-65 3,420.00 80.00
6/1/21 RUNWAY TAXIWAY LIGHT REPAIR 12/8/20 MT0069-67 C 2,007.72CLOSED - SP 6/29/21 0.00STAFFORD REGIONAL AIRPORT AUTHORITY 6748 7/12/21 MT0069-67 2,007.72
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0069-68 3,500.003,500.00
11/1/21 AWOS III WIND SENSOR 9/9/21 MT0069-69 1,052.36REQUEST TO CLOSE - SP 11/16/21 (1,052.36) 0.00
1/1/22 RUNWAY AND TAXIWAY LIGHTING MAITENANCE 10/28/21 MT0069-70 3,620.003,620.00
SUFFOLK FF: 33% 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0050-54 3,500.0071,500.00 3,500.00
.NEXT PROJECT MT0050-55
TANGIER ISLAND 9/1/21 FY20 AWOS INSP & REPAIR 7/1/19 MT0051-13 1,395.0069,425.00 CLOSE - ANJ 9/14/21 MT0051-13 (1,395.00) 0.00
11/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0051-14 2,075.002,075.00
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0051-16 3,500.003,500.00
11/1/21 AWOS DISPLAY REPLACEMENT 7/14/21 MT0051-17 2,385.092,385.09
TAPPAHANNOCK-ESSEX 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0081-73 3,500.0070,701.60 3,500.00
9/1/21 WEED CONTROL 7/14/21 MT0081-74 C 798.40Essex County Airport Authority 6871 8/31/21 MT0081-74 798.40 0.00
1/1/22 REIL BULB 11/4/21 MT0081-75 702.51702.51
TAZEWELL COUNTY (T 83%, F ?) 9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0053-10 C 3,500.00Notified 9/20/17 of OBS off-airport Tazewell Cpunty Airport Authority 6917 9/20/21 MT0053-10 3,420.00 80.0068,000.00
9/1/21 REPLACE HMP 155 PAPI 5/27/21 MT0053-11 D 1,225.01DISAPPROVED (WORK INITIATED PRIOR APPROVAL) 8/17/21 MT0053-11 (1,225.01) 0.00
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0053-12 3,500.003,500.00
TWIN COUNTY (F - 67%, T - ) 9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0020-46 C 935.0067,631.84 935.00
9/1/21 PAPI REPAIR 5/27/21 MT0020-48 C 2,590.40Twin County Airport Commission 6823 8/10/21 MT0020-48 2,590.40 0.00
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0020-49 3,500.00Twin County Airport Commission 6957 10/12/21 MT0020-49 855.00 2,645.00
11/1/21 2021 Bulb Replacement 7/14/21 MT0020-50 C 139.20Twin County Airport Commission 6872 8/31/21 MT0020-50 139.20 0.00
9/1/21 2021 Windsock Replacement 7/14/21 MT0020-51 C 203.56Twin County Airport Commission 6816 8/10/21 MT0020-51 200.36 0.00FINAL DECREASE - SP (3.20)
VA. HIGHLANDS 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0001-70 3,500.0070,417.00 3,500.00
300 DOAVAS 20210701 Maintenance Allocation Status FY22.xlsx
VAB Package December 2021 48
AIRPORT Expiration DESCRIPTION / VO. PAYEE VO. NO. DATE PROJ. # JULY-SEPT OCT-DEC JAN-MAR APR-JUN EXPENDITURE UNEXP. BALANCE AIRPORT ALLOCATION STATUS
9/1/21 HERBICIDE APPLICATION 2021 7/14/21 MT0001-71 3,658.62CLOSED AT AIRPORT REQUEST - WORK COMPLETED 7/19/21 MT0001-71 (3,658.62) 0.00
9/1/21 AWOS DIAL-IN REPAIR 7/14/21 MT0001-72 C 1,083.00FINAL 7/28/21 MT0001-72 0.00Virginia Highlands Airport Authority 6808 8/3/21 MT0001-72 1,083.00
VA. TECH (T: ?, F: 50%) 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0002-59 3,500.0071,072.30 Virginia Tech Montgomery Regional Airport Authority 6928 9/22/21 MT0002-59 1,140.00 2,360.00
9/1/21 Taxiway Light Replacement 7/14/21 MT0002-60 C 427.70Virginia Tech Montgomery Regional Airport Authority 6821 8/10/21 MT0002-60 427.70 0.00
1/1/22 REPAIR RAMP FLOOD LIGHTS 10/22/21 MT0002-61 2,200.342,200.34
WAKEFIELD NEXT PROJECT MT9071-14 0.00Obstruction mitigated 4/27/18 0.0075,000.00
WARRENTON 9/30/23 RUNWAY SEAL COAT & MARKING (8% STATE/FED. PROJECT) 10/3/19 MT0068-03 C 1,509.5865,600.88 1,509.58
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0068-10 3,500.0010/13/21 Fauquier County 6965 10/13/21 MT0068-10 2,280.00 1,220.00
9/1/21 VEGETATION MANAGEMENT 2021 7/14/21 MT0068-11 C 3,948.80FINAL - DECREASE 8/25/21 MT0068-11 (640.00) 0.00Fauquier County 6875 8/31/21 MT0068-11 3,308.80
9/1/21 RWY 15 PAPI REGULATOR REPAIR 7/14/21 MT0068-12 C 1,080.74FINAL 8/25/21 MT0068-12 0.00Fauquier County 6876 8/31/21 MT0068-12 1,080.74
11/1/21 RWY 33 PAPI TIMING TRIGGER REPAIR 7/29/21 MT0068-13 C 1,695.20FINAL 8/25/21 MT0068-13 0.00Fauquier Couny 6877 8/31/21 MT0068-13 1,695.20
WILLIAM M. TUCK 6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0047-48 3,500.0089,720.56 3,500.00
2/1/22 AWOS MECHANICAL WIND SENSOR 8/9/21 MT0047-49 6,779.446,779.44
WILLIAMSBURG 9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT9010-70 C 2,550.00Monitor Airport Condition Williamburg- Jamestown Airport Inc 6773 7/20/21 MT9010-70 950.00 1,600.0062,777.00
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT9010-75 3,500.003,500.00
11/1/21 ANNUAL WEED CONTROL 7/14/21 MT9010-76 C 3,604.00 Williamsburg - Jamestown Airport 6954 10/6/21 MT9010-76 3,604.00 0.00
10/1/21 TERMINAL ROOF CONDUIT REPAIR 8/12/21 MT9010-77 C 1,296.00Williamburg Jamestown Airport Inc 6929 9/22/21 MT9010-77 1,296.00 0.00
11/1/21 AWOS CEILOMETER EVAL 8/26/21 MT9010-78 C 1,273.00Williamsburg jamestown 7013 10/28/21 MT9010-78 1,273.00 0.00
WINCHESTER 9/1/21 FY21 AWOS INSP & REPAIR 7/1/20 MT0059-28 C 1,220.0070,280.00 Winchester Regional Airport Authority 6749 7/12/21 MT0059-28 1,140.00 80.00
6/1/22 FY22 AWOS INSP & REPAIR 7/1/21 MT0059-30 3,500.003,500.00
12/1/21 FY22 AIRFIELD LAMP RESTOCK 10/7/21 MT0059-31 C 1,689.12Winchester Regional Airport 7026 11/10/21 MT0059-31 1,683.79 5.33
FY '21 carried over 351,767.53 469,803.94 19,303.57 0.00 0.00
TOTAL TA BALANCE AS OF REPORT DATE 266,305.87
TOTAL EXPENDITURES AS OF JULY 2021 * 222,801.64
TOTAL ALLOCATIONS AS OF REPORT DATE 489,107.51
APPROPRIATIONS UNALLOCATED 260,892.49
300 DOAVAS 20210701 Maintenance Allocation Status FY22.xlsx
VAB Package December 2021 49
AIRPORT Expiration DESCRIPTION / VO. PAYEE VO. NO. DATE PROJ. # JULY-SEPT OCT-DEC JAN-MAR APR-JUN EXPENDITURE UNEXP. BALANCE AIRPORT ALLOCATION STATUS
TEST CHECK 0.00(6,378.12)
Quarterly Budget Check July 351,767.53 489,107.51 120,712.24 (Jul - Sep alloc)Susan is purple: Oct 3,167.35 (Oct - Dec Alloc)purple expiration date is extension Jan (Jan - Mar alloc)C confirms closing cross-check Apr (Apr - Jun alloc)D confirms denied in closing cross-check 123,879.59 Total New FY22 alloc.
W confirms withdrawal in closing cross-check check 469,803.94 475,647.12 266,300.54letter at end of project number to allow Cardinal to accept a repeated number
Cardinal Check107,330.31 July41,229.56 Aug
300 DOAVAS 20210701 Maintenance Allocation Status FY22.xlsx
VAB Package December 2021 50
AIRPORT DESCRIPTION DATE PROJECT # ALLOCATION GRANT TA BALANCE
CHASE CITY Runway Rehabiliation (Prelim Design & Geotech) 4/1/20 RA0005-01 25,000.000.00 25,000.00
EAGLES NEST Runway Rehabilitation (Design/Construction) 7/17/19 RA9089-01 C 172,687.00Runway Rehabilitation (Design/Construction) 7/26/19 * RA9089-01 172,687.00 0.00Runway Rehabilitation (Design/Construction) 2/13/20 RA9089-01 19,183.00Runway Rehabilitation (Design/Construction) 2/20/24 RA9089-01 19,183.00 0.00
GORDONSVILLE Runway Rehabilitation (Constr) 3/23/2021 RA9070-01 445,000.00Runway Rehabilitation (Constr) 4/7/2021 RA9070-01 445,000.00 0.00
NEW MARKET RWY REHAB DESIGN/BID 3/4/2019 RA9084-01 5,000.00RWY REHAB DESIGN/BID 3/8/2019 RA9084-01 5,000.00 0.00
NEW MARKET Runway Rehabilitation (Design/Bid) 2/13/20 RA9084-01 C 890.00Runway Rehabilitation (Design/Bid) 2/24/20 RA9084-01 890.00 0.00
Runway Rehabilitation (Construction) 1/30/20 RA9084-02 323,000.00Runway Rehabilitation (Construction) - Increase for construction admin 2/14/20 RA9084-02 7,000.00Runway Rehabilitation (Construction) 6/29/20 RA9084-02 330,000.00 0.00
__________TOTAL PLACED UNDER ALLOCATION 997,760.00
TOTAL PLACED UNDER GRANT 972,760.00
OPEN T.A. BALANCE AT 02/22/19 25,000.00
as of Feb 22, 2019
RURAL AIRPORT RUNWAY REHAB STATUSFY 19 - FY 21
DEPARTMENT OF AVIATION
Rural Airport Runway Project - Funding Summary.xlsx
VAB Package December 2021 51
1234567891011121314151617181920212223242526272829303132333435363738394041424344454647484950515253545556575859606162
A B C D E F G H I J K L M N O P Q R S T U VDEPARTMENT OF AVIATIONAVIATION AND AIRPORTS PROMOTION PROGRAMFYE June 30, 2021
ORIGINAL APPROPRIATION 2021‐2022 (FY21) $350,000.00PLUS PRIOR YEAR COMMITMENTS (FY21) $0.00TOTAL APPROPRIATION $350,000.00
UNALLOCATED BALANCE FY22 $74,000.00
Airport Date Grant No. Description/Notes Pre T/A Date Pre T/A $ T/A Date T/A $ Grant Date Grant $ Expenditure 1 Expenditure 2 Expenditure 3 Expenditure 4 Unexpended Balance Carryover Date Voucher # Returned to Fund Grant Expiration Final RSVP Grant ClosedAccomack $0.00Charlottesville $0.00Culpeper 8/9/2021 PR0010‐03 8/9/2021 8/9/2021 8/17/2021 $10,000.00 $10,000.00 4/29/22Danville 8/9/2021 PR0011‐05 8/9/2021 8/9/2021 8/18/2021 $7,500.00 $7,500.00 4/29/22Front Royal Warren $0.00Hampton Roads $0.00Hummel Field 8/9/2021 PR0076‐04 8/9/2021 8/9/2021 8/20/2021 $10,000.00 $10,000.00Hot Springs 8/9/2021 PR0024‐03 8/9/2021 10/13/2021 10/25/2021 $10,000.00 $10,000.00Leesburg 8/9/2021 PR0027‐03 8/9/2021 8/9/2021 9/17/2021 $10,000.00 $10,000.00 4/29/22Lonesome Pine $0.00Louisa $0.00Lynchburg 8/9/2021 PR0029‐04 8/9/2021 8/9/2021 8/25/2021 $35,000.00 5/13/22Manassas $0.00Mecklenburg Brunswick $0.00Middle Peninsula $0.00New Kent $0.00Newport News Williamsburg 8/9/2021 PR0035‐05 8/9/2021 8/9/2021 8/9/2021 $35,000.00 $35,000.00Norfolk 9/28/2021 PR0036‐04 9/28/2021 9/28/2021 10/5/2021 $35,000.00 $35,000.00 5/13/22Richmond Executive Chesterfield 8/9/2021 PR0007‐04 8/9/2021 8/9/2021 8/24/2021 $10,000.00 $10,000.00 5/6/22Richmond International 8/9/2021 PR0043‐04 8/9/2021 8/9/2021 8/25/2021 $35,000.00 $35,000.00 5/13/22Roanoke Blacksburg 8/9/2021 PR0045‐07 8/9/2021 8/9/2021 8/17/2021 $35,000.00 $35,000.00 5/13/22Shenandoah Valley 8/9/2021 PR0049‐05 8/9/2021 8/9/2021 8/16/2021 $35,000.00 $35,000.00 5/13/22Stafford $0.00Tappahannock‐Essex $0.00Tazewell $0.00VA Highlands $0.00VA Tech/Montgomery $0.00Warrenton‐Fauquier 9/28/2021 PR0068‐03 8/9/2021 9/28/2021 10/20/2021 $1,000.00 $1,000.00Winchester 8/9/2021 PR0059‐03 8/9/2021 8/9/2021 8/17/2021 $7,500.00 $7,500.00 4/29/22
$0.00$0.00$0.00
$0.00 $0.00
$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00$0.00
$0.00 $0.00 $276,000.00 $241,000.00 $0.00 $0.00
VAB Package December 2021 52
GENERAL AVIATION AIRPORTS - DISCRETIONARY FUNDSRECOMMENDED PROJECTS
Region: 1
FUNDEDPRIORITYNO. AIRPORT NAME DESCRIPTION
FEDERALAMOUNT
STATE DISCR.AMOUNT LOCAL AMOUNT
TOTAL PROJECTAMOUNT
187 Virginia Highlands Airport Sinkhole & Drainage Repair (Construction) $0.00 $414,000.00 $103,500.00 $517,500.00
123 Mountain Empire Airport Fueling System Tank Repainting (Construction) $0.00 $3,531.00 $7,171.00 $10,702.00
90 Lonesome Pine Airport Spill Prevention, Control, and Countermeasure Plan Update $0.00 $3,781.00 $945.00 $4,726.00
$0.00 $421,312.00 $111,616.00 $532,928.00REGION TOTALS:
Print Date: 11/18/2021 Page 1 of 7
VAB Package December 2021 53
Airport:Region:Name:
Lonesome Pine Airport1Ms. Sophie Vance
State Funding Summary
EntitlementAir Carrier/Reliever DiscretionaryGeneral Aviation DiscretionaryTOTALS
Requested Recommended$0.00$0.00
$3,781.00$3,781.00
$0.00$0.00
$3,781.00$3,781.00
Sponsor:Contact:
Phone:
Cumberlands Airport CommissionMr. Donnie Rose , Chairman276-395-2029
Unmitigated Obstructions Based Aircraft:Annual Operations:Service Role:
209,390
GR
Development Program Projects
Description Priority Project Cost Federal State Local Federal State LocalProjects Requested Funding Recommended Funding
Spill Prevention, Control, and CountermeasurePlan Update
90 $4,726.00 $3,781.00 $945.00 $3,781.00 $945.00
TOTALS $0.00 $3,781.00 $945.00 $0.00 $3,781.00 $945.00
Remarks:
$4,726.00
Spill Prevention, Control, and Countermeasure Plan Update
Staff recommends approval.
COMMONWEALTH AVIATION FUNDFUNDING REQUEST SUMMARY
VAB DATE: 12/02/2021
Print Date: 11/17/2021 Page 1 of 12
VAB Package December 2021 54
LNP SPCC PLAN UPDATE NARRATIVE 2021
This project will update the Spill Prevention and Countermeasure Control Plan
(SPCC) for the Lonesome Pine Airport. Updates to this plan will keep the airport in
compliance with current regulations. The current SPCC plan is dated January
2016.
See attached Scope of work for project details.
The total cost of the Lonesome Pine SPCC plan update will be $4726.59
VAB Package December 2021 55
Airport:Region:Name:
Mountain Empire Airport1Ms. Sophie Vance
State Funding Summary
EntitlementAir Carrier/Reliever DiscretionaryGeneral Aviation DiscretionaryTOTALS
Requested Recommended$0.00$0.00
$3,531.00$3,531.00
$0.00$0.00
$3,531.00$3,531.00
Sponsor:Contact:
Phone:
Smyth-Wythe Airport CommissionMr. Curtis Pennington , Chariman276-686-0102
Unmitigated Obstructions Based Aircraft:Annual Operations:Service Role:
1610,057
GR
Development Program Projects
Description Priority Project Cost Federal State Local Federal State LocalProjects Requested Funding Recommended Funding
Fueling System Tank Repainting (Construction) 123 $10,702.00 $3,531.00 $7,171.00 $3,531.00 $7,171.00
TOTALS $0.00 $3,531.00 $7,171.00 $0.00 $3,531.00 $7,171.00
Remarks:
$10,702.00
Fueling System Tank Repainting (Construction)
Staff recommends approval.
COMMONWEALTH AVIATION FUNDFUNDING REQUEST SUMMARY
VAB DATE: 12/02/2021
Print Date: 11/17/2021 Page 2 of 12
VAB Package December 2021 57
AIRPORT CAPITAL IMPROVEMENT PROGRAM PROJECT NARRATIVE
MOUNTAIN EMPIRE AIRPORT (MKJ)
1 Fuel Tank – Painting (Construction)
The two fuel tanks at Mountain Empire Airport are showing signs of surface rust. The tanks were
last painted in 2013. In order to protect the investment in the fuel farm by the Commonwealth and
the Sponsor, this project includes surface preparation and painting of both tanks to extend the life
of the fuel farm.
VAB Package December 2021 58
Airport:Region:Name:
Virginia Highlands Airport1Ms. Sophie Vance
State Funding Summary
EntitlementAir Carrier/Reliever DiscretionaryGeneral Aviation DiscretionaryTOTALS
Requested Recommended$0.00$0.00
$414,000.00$414,000.00
$0.00$0.00
$414,000.00$414,000.00
Sponsor:Contact:
Phone:
Virginia Highlands Airport AuthorityMr. Mickey Hines , Airport Manager276-628-2909
Unmitigated Obstructions Based Aircraft:Annual Operations:Service Role:
6111,626
GR
Development Program Projects
Description Priority Project Cost Federal State Local Federal State LocalProjects Requested Funding Recommended Funding
Sinkhole & Drainage Repair (Construction) 187 $517,500.00 $414,000.00 $103,500.00 $414,000.00 $103,500.00
TOTALS $0.00 $414,000.00 $103,500.00 $0.00 $414,000.00 $103,500.00
Remarks:
$517,500.00
Sinkhole & Drainage Repair (Construction)
Staff recommends approval.
COMMONWEALTH AVIATION FUNDFUNDING REQUEST SUMMARY
VAB DATE: 12/02/2021
Print Date: 11/17/2021 Page 3 of 12
VAB Package December 2021 60
VIRGINIA HIGHLANDS AIRPORT
PROJECT NARRATIVE
FISCAL YEAR 2021 December 2021 VAB Meeting
The following narrative addresses the detailed project description and justification for the Airport Capital Improvement Plan
SINKHOLE REPAIR PROJECT
The scope of this project includes the construction cost and construction administration phase services for the repair of three major sink holes on the airfield. The scope of the project includes repair of the three sink holes and the repair of the channels above the sink holes. Two of the sink holes are located under an existing concrete channel that is failing due to the sink holes. The failing portion of the concrete channel will be replaced and regraded as needed. No environmental was required for this project. Proposed Funding Allocation –State 80%, Local 20%
VAB Package December 2021 61
Sink Hole LocationsVirginia Highlands AirportSeptember 2021
Terminal
Approximate SinkHole #1 Location
Approximate SinkHole #2 and #3Location
VAB Package December 2021 62
Virginia Aviation Board December 2, 2021 Meeting
No requests were received for Region 2.
VAB Package December 2021 63
GENERAL AVIATION AIRPORTS - DISCRETIONARY FUNDSNOT RECOMMENDED PROJECTS
Region: 3
Not RecommendedPRIORITYNO. AIRPORT NAME DESCRIPTION
FEDERALAMOUNT
STATE DISCR.AMOUNT LOCAL AMOUNT
TOTAL PROJECTAMOUNT
199 Culpeper Regional Airport Greenhouse Road Extension (Construction) (AIP) $2,900,000.00 $0.00 $322,222.00 $3,222,222.00
150 Culpeper Regional Airport Northeast Stub Taxiway (Design) $201,954.00 $0.00 $22,440.00 $224,394.00
115 Culpeper Regional Airport Greenhouse Road Extension (Construction) (non-AIP) $0.00 $0.00 $698,861.24 $698,861.24
$3,101,954.00 $0.00 $1,043,523.24 $4,145,477.24REGION TOTALS:
Print Date: 11/18/2021 Page 2 of 7
VAB Package December 2021 65
Airport:Region:Name:
Culpeper Regional Airport3Mr. Derek "Dak" Hardwick
State Funding Summary
EntitlementAir Carrier/Reliever DiscretionaryGeneral Aviation DiscretionaryTOTALS
Requested Recommended$0.00$0.00
$834,817.00$834,817.00
$0.00$0.00
$834,817.00$834,817.00
Sponsor:Contact:
Phone:
County of CulpeperMr. John Egertson , County Administrator540-727-3404
Unmitigated Obstructions Based Aircraft:Annual Operations:Service Role:
15460,943
GR
Development Program Projects
Description Priority Project Cost Federal State Local Federal State LocalProjects Requested Funding Recommended Funding
Greenhouse Road Extension (Construction)(AIP)
199 $3,222,222.00 $2,900,000.00 $257,777.00 $64,445.00 $2,900,000.00 $257,777.00 $64,445.00
Greenhouse Road Extension (Construction)(non-AIP)
115 $698,861.24 $0.00 $559,089.00 $139,772.24 $0.00 $559,089.00 $139,772.24
Northeast Stub Taxiway (Design) 150 $224,394.00 $201,954.00 $17,951.00 $4,489.00 $201,954.00 $17,951.00 $4,489.00
TOTALS $3,101,954.00 $834,817.00 $208,706.24 $3,101,954.00 $834,817.00 $208,706.24
Remarks:
$4,145,477.24
Greenhouse Road Extension (Construction) (AIP)
A meeting between the DOAV, FAA, and the Airport Sponsor is scheduled for November 22. A staff recommendation for all three projects will be provided based on the results of the meeting.
Greenhouse Road Extension (Construction) (non-AIP)
Northeast Stub Taxiway (Design)
COMMONWEALTH AVIATION FUNDFUNDING REQUEST SUMMARY
VAB DATE: 12/02/2021
Print Date: 11/17/2021 Page 1 of 12
VAB Package December 2021 66
Culpeper Regional AirportGreenhouse Road Extension – Phase 1 (Construction)
Narrative
The Greenhouse Road Extension – (Construction) is necessary for the development ofCulpeper Regional Airport in accordance with the approved master plan. The west side of theairport is almost completely developed. This road extension will provide vehicle access to theeast side of the airport for development, hangar space, apron areas, and potential aviation relatedbusinesses. Additionally, the road extension represents the “relocation” of Beverly Ford Roadbecause it will assume the Beverly Ford Road role of maintaining south-north automobileconnectivity past airport property. Further, the Greenhouse Road Extension project willultimately eliminate the Part 77 airspace conflict created by the current alignment of BeverlyFord Road.
This scope of work is for phase 1 of the Greenhouse Road Extension (Construction)project. Phase 1 is for the first ± 2,900 feet of the road from Greenhouse Road proceeding north.Phase 1 will provide access to the east side of the Culpeper Regional Airport for developmentand will enable future completion of phase 2. Phase 2 will eliminate the Part 77 airspace conflictcreated by the current alignment of Beverly Ford Road.
The scope of work provides for the construction of the Greenhouse Road Extension –Phase 1 project, including construction phase services, nutrient credits, and stream mitigationcredits.
VAB Package December 2021 67
Culpeper Regional AirportNortheast Taxiway Connector (Design)
Project Narrative
The Northeast Taxiway Connector (Design) project at Culpeper Regional Airport willprovide plans, specifications, and other contract documents enabling the County of Culpeper toadvertise for bids to construct the northeast taxiway connector. The northeast taxiway connectorwill provide access to the future parallel taxiway and future apron / hangar development plannedfor the east side of the airport. No other airside access to the east side development is currentlyavailable.
The project is part of the approved airport layout plan (ALP) and is part of the county andFAA capital improvement plans. This project will work in tandem with the Greenhouse RoadExtension project to open the east side of the airport for development. This is an AIP-fundedproject, and funding is being requested at 90% federal, 8% state, and 2% local shares.
VAB Package December 2021 69
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XXXXXXXXXXXXXXXXXXXX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
XX
TOFA
TOFA TOFA
TSA TSA TSA TSA
TSA
TSA
TSA
TSA
TSA TSA
TSA
TOFA
TOFA TOFA
UE
RO
FZ
ROFZROFZROFZROFZROFZ
ROFZ ROFZ ROFZ ROFZ ROFZ
RO
FAR
OFA
ROFAROFAROFAROFAROFA
ROFA ROFA ROFA ROFA ROFA ROFA
RSARSARSARSARSA
RSA RSA RSA RSA RSA
RPZ
RPZ
RPZ
RPZ
RPZ
RPZ
RPZ
RPZ
RPZ
RPZ
RPZ
EX 04 THRESHOLDELEV - 314.50'LAT - N038° 31' 53.47"LONG - W077° 51' 19.75"
PROPLN
PROPLN
PROPLN
PROPLN
PROPLN
PROPLN
PROPLN
EX. METAL HANGAR EX. METAL HANGAR
TREELN TREELN TREELN
TREELN
TREELN
TREELN
EX-CONTROLORANGE CAP W/PK NAILELEV - 307.68'N - 6876954.55E - 11666785.50
EX. CONCRETEELECTRICAL
HANDHOLE
EX. ESINV = 304.60 (18" RCP)EX. ES
INV = 304.06 (18" RCP)P)
CMP)
EX. GRATERIM = 309.59INV. OUT = 307.09 (18" CMP)
EX. ESINV = 304.97 (15" RCP)
EX. ESINV = 304.70 (15" RCP)
EX. ESINV = 307.97 (18" RCP)
EX. ESINV = 303.47 (18" RCP) EX. ES
INV = 304.16 (18" RCP)
EX. ESINV = 303.46 (24" RCP)
EX. ESINV = 303.98 (24" RCP)
EX. DITCHINV = 308.03
TAXIWAY NORTHEASTCONNECTOR
SEPTEMBER 2021
STATE No.-
DES
IGN
ED B
Y:
FM SCA
LE:
AS
SHO
WN
CA
MPB
ELL
& P
AR
IS E
NG
INEE
RS
4215
LA
FAY
ETTE
CEN
TER
DR
., SU
ITE
2C
HA
NTI
LLY
, VA
. 201
51 (7
03) 8
02-0
093
CO
UN
TY O
F C
ULP
EPER
, VIR
GIN
IAC
ULP
EPER
CO
UN
TY R
EGIO
NA
L A
IRPO
RT
TAX
IWA
Y N
OR
THEA
ST C
ON
NEC
TOR
NO
.D
ATE
REV
ISIO
NB
Y
AIP No.-
SHEET INDEX1
APP
RO
VED
BY
:H
DC
, PK
CC
&PE
PR
OJE
CT
#:C
JR-3
8PR
OJE
CT
PHA
SE:
EXH
IBIT
VAB Package December 2021 70
AIR CARRIER / RELIEVER AIRPORTS - DISCRETIONARY FUNDSRECOMMENDED PROJECTS
Region: 4
FUNDEDPRIORITYNO. AIRPORT NAME DESCRIPTION
FEDERALAMOUNT
STATE DISCR.AMOUNT LOCAL AMOUNT
TOTAL PROJECTAMOUNT
203 Hanover County Municipal Airport East Side Perimeter Fencing - Phase 1 (Construction) $0.00 $18,603.00 $2,067.00 $20,670.00
140 Richmond Executive - Chesterfield CountyAirport
Southeast Apron Expansion (Design) - Change in Scope /Increase
$0.00 $161,520.00 $40,380.00 $201,900.00
Print Date: 11/18/2021 Page 1 of 3
VAB Package December 2021 71
AIR CARRIER / RELIEVER AIRPORTS - DISCRETIONARY FUNDSNOT RECOMMENDED PROJECTS
Region: 4
Not RecommendedPRIORITYNO. AIRPORT NAME DESCRIPTION
FEDERALAMOUNT
STATE DISCR.AMOUNT LOCAL AMOUNT
TOTAL PROJECTAMOUNT
194 Hanover County Municipal Airport Terminal Building Roof Replacement (Construction) $0.00 $0.00 $49,820.00 $49,820.00
$0.00 $180,123.00 $92,267.00 $272,390.00REGION TOTALS:
Print Date: 11/18/2021 Page 2 of 3
VAB Package December 2021 72
GENERAL AVIATION AIRPORTS - DISCRETIONARY FUNDSRECOMMENDED PROJECTS
Region: 4
FUNDEDPRIORITYNO. AIRPORT NAME DESCRIPTION
FEDERALAMOUNT
STATE DISCR.AMOUNT LOCAL AMOUNT
TOTAL PROJECTAMOUNT
128 New Kent County Airport Fueling System Repair - Pump $0.00 $5,988.00 $2,950.00 $8,938.00
$0.00 $5,988.00 $2,950.00 $8,938.00REGION TOTALS:
Print Date: 11/18/2021 Page 3 of 7
VAB Package December 2021 73
Airport:Region:Name:
Hanover County Municipal Airport4Mr. Alan Abbott
State Funding Summary
EntitlementAir Carrier/Reliever DiscretionaryGeneral Aviation DiscretionaryTOTALS
Requested Recommended$0.00
$58,459.00$0.00
$58,459.00
$0.00$18,603.00
$0.00$18,603.00
Sponsor:Contact:
Phone:
County of HanoverMr. Mike Flagg , Director of Public Works840-365-6182
Unmitigated Obstructions Based Aircraft:Annual Operations:Service Role:
11037,729
RL
Development Program Projects
Description Priority Project Cost Federal State Local Federal State LocalProjects Requested Funding Recommended Funding
East Side Perimeter Fencing - Phase 1(Construction)
203 $20,670.00 $18,603.00 $2,067.00 $18,603.00 $2,067.00
Terminal Building Roof Replacement(Construction)
194 $49,820.00 $39,856.00 $9,964.00 $0.00 $49,820.00
TOTALS $0.00 $58,459.00 $12,031.00 $0.00 $18,603.00 $51,887.00
Remarks:
$70,490.00
East Side Perimeter Fencing - Phase 1 (Construction)
Staff recommends approval.
Terminal Building Roof Replacement (Construction)
Staff recommends disapproval.
A new East Side Terminal Building is scheduled to open by January 2022. The building will contain the maximum areas of public space eligible for funding under VAB policy resulting in theWest Side Terminal Building containing excess eligible public space. In addition, the current lease between the Sponsor and the FBO directs the FBO to convert the West Side TerminalBuilding into a flight training facility and pay additional rent. This conversion will also make the West Side Terminal Building ineligible for funding.
COMMONWEALTH AVIATION FUNDFUNDING REQUEST SUMMARY
VAB DATE: 12/02/2021
Print Date: 11/18/2021 Page 5 of 12
VAB Package December 2021 74
Project Narrative
East Side Security Fencing Phase I
Hanover County Municipal Airport
Background:
Hanover County has permanent security fencing around approximately 70% of the airport aircraft
runway. The East side (with exception of the new Development) has a temporary electric fence to deter
deer from accessing the aircraft movement areas. The East Side Development currently has no fencing
and deer are accessing the runway from this area creating safety hazards.
The Luck Stone Hangar Corporate Hangar is completed along with the Medtran’s Medevac Crew Facility.
The new East Side Terminal building is currently under construction in addition to the HOVA Fixed Base
Operator 15,000 S.F. corporate storage hangar and midfield Public Utilities water tank/pump station.
Jet aircraft and Medivac helicopters are operating daily from the East Side Ramp Apron. Security for
these operations is currently handled by an electric vehicle access gate at the 9500 Sliding Hill Road
entrance which limits public access. Once the new East Side Terminal is completed, the Sliding Hill Road
entrance gate will be open to the public. Security fencing will be needed to keep unauthorized public
from accessing hazardous aircraft operating areas.
A permanent security fence meeting the attached specs is planned to connect the temporary electric
fence with the Medtran’s Building, HOVA Hangar, Terminal Building, and Luck Stone Hangar as shown in
the attached narrative sketch (Phase II). Permanent fencing will first be installed from the existing
fencing at the East Side Vehicle Gate across the new Fuel Farm Loop Road adding two manual sliding 30’
vehicle gates made surplus from the West Side Perimeter Security Fence (Phase I).
Temporary Fencing is planned at the County expense to connect the permanent fencing at the fuel farm
loop road to the Luck Stone Hangar. This will be temporary to allow for future additional hangar
construction (see diagrams for temporary fencing location).
Fencing Type and Controls:
Planned fence specs are attached. In the area of the terminal building, black vinyl pvc coated chain link
fence is planned. A 16’ Electric vehicle gate is planned for the access to the ramp apron located
between the terminal building and Luck Stone Hangar. Access will be controlled by Key pad card reader
and an intercom link to the terminal front desk along with a video feed allowing the staff to visually
verify vehicles requesting access. It is planned for an internet based card access controller system which
would control the electric vehicle gate as well as pedestrian gate access to the ramp areas (including the
door from inside the terminal building to the ramp apron). This internet system would also replace the
current failing gate access controllers on West Side (two vehicle gates and two pedestrian gates) and
would allow one system to control and record all access cards.
VAB Package December 2021 75
Phase I The current request is for funding the permanent perimeter security fence to be extended from
the electric vehicle gate on the Sliding Hill Road entrance directly to cross the Fuel Farm Loop Road
where a 30 foot sliding gate will be installed (to handle the larger radius turns needed for tractor trailer
tanker deliveries). The stretch of fencing on this portion is adjacent to a wooded area and a ten foot
clear area per FAA recommended specs is needed inside the fence. A cost of $2,900 for this tree/brush
clearing was the low quote from Wells Tree Service. Wells has performed work for Hanover County for
several years and meets insurance requirements. Two other higher tree quotes were received from
Companies which also have experience working for the County: Medek Tree Service $3,500 and Shady
Tree Service $3,500.
Once the first lane of the Fuel farm Loop Road is crossed, the perimeter fence makes a right then left
turn to maximize space inside the future tank farm before another 30 foot sliding gate is installed
crossing the second lane. A Quick Quote was advertised on eVA and Hercules Fencing was the low bid
with a quote of $16,150. This included additional fencing and installation of the two 30 foot wide
(sliding) cantilever gates across the Fuel Farm Loop Road. Survey of fence line to mark installation
location was quoted by County Contract and is $1,620, making the total Phase I project cost of $20,670:
Gates and Fencing Installed: $16,150 Hercules Fence
Survey Lines: $1,620 JenningStephenson P.C.
Brush/Trees: $2,900 Wells Tree Service
Project Total: $20,670 State Security Funding Requested @ 90% = $18,603.00
Hanover County Local Share @ 10% = $ 2.067.00
VAB Package December 2021 76
OFP Terminal Building Roof Repair
Project Narrative
The roof on the Airport Terminal Building has had several leaks repaired over the last couple years. Most
recently we had numerous areas repaired in June and July of 2021. The existing roof has begun to shrink
and has pulled away and torn the metal drip edge.
A search of the airport files indicates that the current roof was installed 27 years ago in July 1994 under
VDOA Grant CS0023-06 at a cost of total cost of $37,054.91 (State Grant amount of $32,719.49).
The roof has exceeded its maximum life expectancy of between 15 to 25 years and needs to be repaired
by removing damaged insulation and wet or rotten wood in select areas followed by an overlay on top
of the existing roof.
We have had the County Annual Roofing Contractor J. King DeShazo perform repairs to stop current
leaks and provide an estimated cost to repair or replace (attached).
Repair would start with $1,150 infrared inspection and if acceptable a $39,590 overlay on existing roof
for a total cost of $40,740. A new roof replacement quote as of August 8, 2021 was $49,820.
Based on rapidly rising construction labor and materials pricing since August, the amount of repair
requested likely equals the original quoted cost to replace the roof of $49,820.
Requested grant amount is 80% or $39,856.
VAB Package December 2021 78
Airport:Region:Name:
New Kent County Airport4Mr. Alan Abbott
State Funding Summary
EntitlementAir Carrier/Reliever DiscretionaryGeneral Aviation DiscretionaryTOTALS
Requested Recommended$0.00$0.00
$5,988.00$5,988.00
$0.00$0.00
$5,988.00$5,988.00
Sponsor:Contact:
Phone:
County of New KentMr. Duane Goss III, Manager804-932-3984
Unmitigated Obstructions Based Aircraft:Annual Operations:Service Role:
4320,113
GC
Development Program Projects
Description Priority Project Cost Federal State Local Federal State LocalProjects Requested Funding Recommended Funding
Fueling System Repair - Pump 128 $8,938.00 $5,988.00 $2,950.00 $5,988.00 $2,950.00
TOTALS $0.00 $5,988.00 $2,950.00 $0.00 $5,988.00 $2,950.00
Remarks:
$8,938.00
Fueling System Repair - Pump
Staff recommends approval.
COMMONWEALTH AVIATION FUNDFUNDING REQUEST SUMMARY
VAB DATE: 12/02/2021
Print Date: 11/17/2021 Page 6 of 12
VAB Package December 2021 80
SCOPE OF WORK
REHABILITATION OF THE FUEL FARM DISPENSER PUMP
NEW KENT COUNTY AIRPORT
QUINTON, VA 23141
September 13, 2021
The fuel farm mechanical dispenser pump has been in service for no less than
thirty-five years.
The unit has served the airport well but is showing its age and has required
hands-on attention and repairs more frequently.
The goal is to replace the pump with a modern new like-mechanical unit.
Recently, the Point-of-Service M3000 card reader was replaced by the upgraded
M4000 unit due to the manufacturer no longer supporting the M3000 unit.
By upgrading the pump dispenser, the airport will be in a better position for
continued aviation fuel sales.
Three quotes were solicited. The most economical quote was submitted by
Petro Supply, Inc. of Richmond. It has been entered into AirportIQ.
Campbell Oil Company provided a quote of $ 17,375.00.
Titan Aviation Fuels provided a quote of $ 17,847.13.
Duane B. Goss
Airport Manager
VAB Package December 2021 81
Airport:Region:Name:
Richmond Executive - Chesterfield County Airport4Mr. Alan Abbott
State Funding Summary
EntitlementAir Carrier/Reliever DiscretionaryGeneral Aviation DiscretionaryTOTALS
Requested Recommended$0.00
$161,520.00$0.00
$161,520.00
$0.00$161,520.00
$0.00$161,520.00
Sponsor:Contact:
Phone:
County of ChesterfieldMr. Jeremy Wilkinson , Acting Airport Manager804-768-7700
Unmitigated Obstructions Based Aircraft:Annual Operations:Service Role:
11668,724
RL
Development Program Projects
Description Priority Project Cost Federal State Local Federal State LocalProjects Requested Funding Recommended Funding
Southeast Apron Expansion (Design) - Changein Scope / Increase
140 $201,900.00 $161,520.00 $40,380.00 $161,520.00 $40,380.00
TOTALS $0.00 $161,520.00 $40,380.00 $0.00 $161,520.00 $40,380.00
Remarks:
$201,900.00
Southeast Apron Expansion (Design) - Change in Scope / Increase
Staff recommends approval.
COMMONWEALTH AVIATION FUNDFUNDING REQUEST SUMMARY
VAB DATE: 12/02/2021
Print Date: 11/17/2021 Page 7 of 12
VAB Package December 2021 83
PROJECT NARRATIVE
SUBMITTED FOR DECEMBER 2021 VIRGINIA AVIATION BOARD MEETING
RICHMOND EXECUTIVE – CHESTERFIELD COUNTY AIRPORT 1. Southeast Apron Expansion (Design) – Change in Scope / Increase
Chesterfield County requests that the VAB consider additional funding for a change in scope and increase in funds for the Southeast Apron (Design) project. The proposed project at the Richmond Executive – Chesterfield County Airport includes design of a new apron to accommodate current and future operational and tenant demand and enhance customer service. All corporate hangar locations at the airport are currently leased and are fully occupied. The proposed apron will also serve transient aircraft, including DoD operations at the airport. The VAB awarded a contingent tentative allocation to the Richmond Executive-Chesterfield County Airport at the June 2021 VAB meeting for the Southeast Apron Expansion (Design) project. The contingency was due to outstanding questions regarding the ultimate design and usage.
Chesterfield County has coordinated with DOAV staff to come to an agreement on a revised scope of work for the Southeast Apron. The proposed project has been modified to increase the overall apron and to add a second connector taxiway, increasing the impervious area by approximately 135,000 square feet. The County is requesting additional funding for the increased scope of work.
Environmental review for the proposed work was completed in close coordination with the DOAV and FAA, with a Finding of No Significant Impact (FONSI) on both the original Environmental Assessment (EA) issued in January 2021 and a FONSI for the Supplemental EA issued in September 2021.
Proposed Funding: DOAV 80%, Local 20%
END OF PROJECT NARRATIVE
VAB Package December 2021 84
N
SCALE: 1"=300'
300 0
FEET
300 600LEGENDPROPOSED APRON
EXHIBIT
DRAWING: 20024 FCI Construct Southeast Apron.dwg LAYOUT: Layout1
DRAWN BY: CHECKED BY: SCALE: DATE:w w w . d e l t a a i r p o r t . c o m
CONSTRUCT SOUTHEAST APRONRICHMOND EXECUTIVE - CHESTERFIELD COUNTY AIRPORT
NYB TSE 1" = 300' SEPTEMBER 2021
1
C:\U
sers
\nyb
\ACC
Docs
\DAC
\200
24\P
roje
ct F
iles\
Exhi
bits
\200
24 F
CI C
onst
ruct
Sou
thea
st A
pron
.dw
g, L
ayou
t1, 9
/2/2
021
11:0
2:12
AM
, nyb
PROPOSED APRON
VAB Package December 2021 85
GENERAL AVIATION AIRPORTS - DISCRETIONARY FUNDSRECOMMENDED PROJECTS
Region: 5
FUNDEDPRIORITYNO. AIRPORT NAME DESCRIPTION
FEDERALAMOUNT
STATE DISCR.AMOUNT LOCAL AMOUNT
TOTAL PROJECTAMOUNT
164 Dinwiddie County Airport Terminal Building Roof Replacement (Construction) $0.00 $21,600.00 $8,400.00 $30,000.00
Print Date: 11/18/2021 Page 4 of 7
VAB Package December 2021 87
GENERAL AVIATION AIRPORTS - DISCRETIONARY FUNDSNOT RECOMMENDED PROJECTS
Region: 5
Not RecommendedPRIORITYNO. AIRPORT NAME DESCRIPTION
FEDERALAMOUNT
STATE DISCR.AMOUNT LOCAL AMOUNT
TOTAL PROJECTAMOUNT
93 Danville Regional Airport Fuel Farm Modification (Design) $0.00 $0.00 $111,090.00 $111,090.00
$0.00 $21,600.00 $119,490.00 $141,090.00REGION TOTALS:
Print Date: 11/18/2021 Page 5 of 7
VAB Package December 2021 88
Airport:Region:Name:
Danville Regional Airport5Ms. Maggie Ragon
State Funding Summary
EntitlementAir Carrier/Reliever DiscretionaryGeneral Aviation DiscretionaryTOTALS
Requested Recommended$0.00$0.00
$36,659.00$36,659.00
$0.00$0.00$0.00$0.00
Sponsor:Contact:
Phone:
City of DanvilleMr. Marc Adelman , Director of Transportation Services434-799-5110
Unmitigated Obstructions Based Aircraft:Annual Operations:Service Role:
4619,040
GR
Development Program Projects
Description Priority Project Cost Federal State Local Federal State LocalProjects Requested Funding Recommended Funding
Fuel Farm Modification (Design) 93 $111,090.00 $36,659.00 $74,431.00 $0.00 $111,090.00
TOTALS $0.00 $36,659.00 $74,431.00 $0.00 $0.00 $111,090.00
Remarks:
$111,090.00
Fuel Farm Modification (Design)
Staff recommends disapproval.
The required environmental approval has not been received.
COMMONWEALTH AVIATION FUNDFUNDING REQUEST SUMMARY
VAB DATE: 12/02/2021
Print Date: 11/17/2021 Page 8 of 12
VAB Package December 2021 89
NARRATIVE
DANVILLE REGIONAL AIRPORT
Fuel Farm Modification (20,000-gallon Jet ‘A’ Tank)
The Danville Regional Airport’s existing fuel farm consists of one 12,000, gallon Jet A tank and one 12,000, gallon AVGAS tank. Total fuel sales for the Danville airport during FY21 increased 62% compared to FY20. During FY20, a total of 144,964 gallons of aviation fuel were sold and during FY21 a total of 234,956 gallons were sold. In addition, during FY21 a total of 159,099 gallons of jet fuel was sold compared to the previous year when only 87,745 gallons of jet fuel was sold. This situation was spurred by increased business aviation traffic as well as increased jet aircraft operations related to the Virginia International Raceway. In fact, during one weekend in March 2021 and again during one weekend in June 2021, a total of more than 22,000 gallons of jet fuel were sold each weekend due to raceway traffic. Since the airport’s existing jet fuel tank holds 12,000 gallons, the tank required refilling during each weekend. An additional Jet A tank is needed to support anticipated jet traffic operations related to the 2023 Caesars casino resort opening and during weekends when operations associated with the casino overlap with major raceway events. It is anticipated that over 30,000 gallons of jet fuel will likely be sold during one weekend when this situation occurs, making it very challenging for the FBO to maintain adequate fuel supply with one 12,000, gallon jet fuel tank. To provide for a reliable supply of fuel this project request would involve the installation of one (1) additional 20,000 gallon for jet fuel. Adding the extra Jet A tank will also allow for redundancy if the existing jet tank system needs maintenance or goes down.
VAB Package December 2021 90
RUNWAY 2-20
August 24, 2021
RU
NW
AY 1
3-31
FUEL FARM EXPANSION
VAB Package December 2021 91
Airport:Region:Name:
Dinwiddie County Airport5Ms. Maggie Ragon
State Funding Summary
EntitlementAir Carrier/Reliever DiscretionaryGeneral Aviation DiscretionaryTOTALS
Requested Recommended$0.00$0.00
$21,600.00$21,600.00
$0.00$0.00
$21,600.00$21,600.00
Sponsor:Contact:
Phone:
Dinwiddie Airport and Industrial AuthorityMr. Jeremy Pultz , Manager804-861-0218
Unmitigated Obstructions Based Aircraft:Annual Operations:Service Role:
5733,340
GR
Development Program Projects
Description Priority Project Cost Federal State Local Federal State LocalProjects Requested Funding Recommended Funding
Terminal Building Roof Replacement(Construction)
164 $30,000.00 $21,600.00 $8,400.00 $21,600.00 $8,400.00
TOTALS $0.00 $21,600.00 $8,400.00 $0.00 $21,600.00 $8,400.00
Remarks:
$30,000.00
Terminal Building Roof Replacement (Construction)
Staff recommends approval.
COMMONWEALTH AVIATION FUNDFUNDING REQUEST SUMMARY
VAB DATE: 12/02/2021
Print Date: 11/17/2021 Page 9 of 12
VAB Package December 2021 92
AIRPORT CAPITAL IMPROVEMENT PROGRAM PROJECT NARRATIVE
DINWIDDIE COUNTY AIRPORT (PTB)
1 Terminal Building Roof Replacement (Construction)
The flat portion of the Terminal Building Roof is leaking in several different locations, causing
damage to the interior of the building (drywall & ceiling tiles). This is the original roof installed
in 2003. The roofing material is a rubber liner and has dry rotted to the point that patching of the
roof is not an option.
VAB Package December 2021 93
GENERAL AVIATION AIRPORTS - DISCRETIONARY FUNDSRECOMMENDED PROJECTS
Region: 6
FUNDEDPRIORITYNO. AIRPORT NAME DESCRIPTION
FEDERALAMOUNT
STATE DISCR.AMOUNT LOCAL AMOUNT
TOTAL PROJECTAMOUNT
90 Lunenburg County Airport Runway & Apron Rehabilitation (Preliminary Engineering) $0.00 $17,600.00 $4,400.00 $22,000.00
$0.00 $17,600.00 $4,400.00 $22,000.00REGION TOTALS:
Print Date: 11/18/2021 Page 6 of 7
VAB Package December 2021 95
Airport:Region:Name:
Lunenburg County Airport6Mr. Donald Robertson
State Funding Summary
EntitlementAir Carrier/Reliever DiscretionaryGeneral Aviation DiscretionaryTOTALS
Requested Recommended$0.00$0.00
$17,600.00$17,600.00
$0.00$0.00
$17,600.00$17,600.00
Sponsor:Contact:
Phone:
County of LunenburgMs. Tracy Gee , County Administrator434-696-2142
Unmitigated Obstructions Based Aircraft:Annual Operations:Service Role:
1754LO
Development Program Projects
Description Priority Project Cost Federal State Local Federal State LocalProjects Requested Funding Recommended Funding
Runway & Apron Rehabilitation (PreliminaryEngineering)
90 $22,000.00 $17,600.00 $4,400.00 $17,600.00 $4,400.00
TOTALS $0.00 $17,600.00 $4,400.00 $0.00 $17,600.00 $4,400.00
Remarks:
$22,000.00
Runway & Apron Rehabilitation (Preliminary Engineering)
Staff recommends approval.
COMMONWEALTH AVIATION FUNDFUNDING REQUEST SUMMARY
VAB DATE: 12/02/2021
Print Date: 11/17/2021 Page 10 of 12
VAB Package December 2021 96
Lunenburg County Airport The initial GEO/Technical engineering study is required to determine the approach needed to perform the runway and apron rehabilitation. It is the county’s hope that a simple mill and fill will be satisfactory, but we will not know that technique will be appropriate until this engineering study is completed.
Background All-About Pavements, Inc. last published report ‘Pavement Management Update’, dated October 2015 stated, all paved surfaces, except for the new apron area directly in front of the hanger were constructed in 1966. The hanger aprons were constructed in 2011. The surfaces constructed in 2011 according to the report were in either satisfactory or good condition. Runway 02-20 ,however, was listed as poor, Runway 20 turnaround was listed as very poor, Runway 02 turnaround was listed as serious, the terminal apron was listed as serious and Taxiway Alpha was listed as very poor. In October of 2020 All-About Pavements conducted another pavement inspection, we are currently waiting for that report. It is however most unlikely that any of these conditions have improved.
Recommendations As per the AAP 2015 report it was recommended to reconstruct the terminal apron and mill and fill RWY 02-20. Neither of these actions were taken. At the time of the 2015 report it was predicted that RWY 02-20 would move from a rating of poor to very poor by the year 2021. We will have to wait and see once the 2020 report becomes available.
Summary The maintenance on this runway has been neglected for a long time. As per the AAP report the expense to repair the runway will continue to escalate, the longer we wait. Acting now would seem to be prudent especially when considering the cost of doing nothing. The GEO/Technical report will answer the question of what the rehabilitation will require and what the estimated cost will be to implement the recommended repair. W-31 is currently in a growth phase with a dynamic new tenant whose business has brought an increase in traffic. We have also seen an increase in ag business and are expecting more growth this year with all our T-Hanger space rented. As soon as the new AAP pavement report becomes available, we would like to submit that report with our grant application. Thank you for your consideration. Please let me know if there are any other supporting documents you require.
VAB Package December 2021 97
AIR CARRIER / RELIEVER AIRPORTS - DISCRETIONARY FUNDSRECOMMENDED PROJECTS
Region: 7
FUNDEDPRIORITYNO. AIRPORT NAME DESCRIPTION
FEDERALAMOUNT
STATE DISCR.AMOUNT LOCAL AMOUNT
TOTAL PROJECTAMOUNT
105 Hampton Roads Executive Airport Fueling System (Design) - INCREASE $0.00 $1,584.00 $3,218.50 $4,802.50
$0.00 $1,584.00 $3,218.50 $4,802.50REGION TOTALS:
Print Date: 11/18/2021 Page 3 of 3
VAB Package December 2021 99
GENERAL AVIATION AIRPORTS - DISCRETIONARY FUNDSRECOMMENDED PROJECTS
Region: 7
FUNDEDPRIORITYNO. AIRPORT NAME DESCRIPTION
FEDERALAMOUNT
STATE DISCR.AMOUNT LOCAL AMOUNT
TOTAL PROJECTAMOUNT
110 Hummel Field Environmental Impact Review - Runway Improvements $0.00 $31,920.00 $7,980.00 $39,900.00
$0.00 $31,920.00 $7,980.00 $39,900.00REGION TOTALS:
Print Date: 11/18/2021 Page 7 of 7
VAB Package December 2021 100
Airport:Region:Name:
Hampton Roads Executive Airport7Ms. Vanessa Christie
State Funding Summary
EntitlementAir Carrier/Reliever DiscretionaryGeneral Aviation DiscretionaryTOTALS
Requested Recommended$0.00
$1,584.00$0.00
$1,584.00
$0.00$1,584.00
$0.00$1,584.00
Sponsor:Contact:
Phone:
Virginia Aviation Associates, LLCMr. Steven Fox , Sponsor757-373-3151
Unmitigated Obstructions Based Aircraft:Annual Operations:Service Role:
16572,708
RL
Development Program Projects
Description Priority Project Cost Federal State Local Federal State LocalProjects Requested Funding Recommended Funding
Fueling System (Design) - INCREASE 105 $4,802.50 $1,584.00 $3,218.50 $1,584.00 $3,218.50
TOTALS $0.00 $1,584.00 $3,218.50 $0.00 $1,584.00 $3,218.50
Remarks:
$4,802.50
Fueling System (Design) - INCREASE
Staff recommends approval.
COMMONWEALTH AVIATION FUNDFUNDING REQUEST SUMMARY
VAB DATE: 12/02/2021
Print Date: 11/17/2021 Page 11 of 12
VAB Package December 2021 101
AIRPORT CAPITAL IMPROVEMENT PROGRAM PROJECT NARRATIVE
HAMPTON ROADS EXECUTIVE AIRPORT (PVG)
PVG December 2021 Narrative Revised
The following program narrative addresses the project description and justification for the current
year of the Airport Capital Improvement Program.
1 Fuel Farm - Design INCREASE
The design of the Wash Rack and Fuel Farm was combined under one scope of work that included
bidding. The design was later split into two projects as the funding percentages for a wash rack
and fuel farm are different. At that time, the bidding costs were split evenly between the two
projects as it was anticipated that the projects would be bid together. Due to sponsor funding and
scheduling, the two projects were not bid at the same time. An increase to the Wash Rack project
was sought and approved to cover additional bidding costs; the bidding for Wash Rack project has
been completed. The Fuel Farm project is scheduled to be bid in January 2022. An increase is
needed to address the advertisement and bidding line items as was done with the Wash Rack
project.
VAB Package December 2021 102
Airport:Region:Name:
Hummel Field7Ms. Vanessa Christie
State Funding Summary
EntitlementAir Carrier/Reliever DiscretionaryGeneral Aviation DiscretionaryTOTALS
Requested Recommended$0.00$0.00
$31,920.00$31,920.00
$0.00$0.00
$31,920.00$31,920.00
Sponsor:Contact:
Phone:
County of MiddlesexMr. Matt Walker , County Administrator804-758-4330
Unmitigated Obstructions Based Aircraft:Annual Operations:Service Role:
2912,811
LO
Development Program Projects
Description Priority Project Cost Federal State Local Federal State LocalProjects Requested Funding Recommended Funding
Environmental Impact Review - RunwayImprovements
110 $39,900.00 $31,920.00 $7,980.00 $31,920.00 $7,980.00
TOTALS $0.00 $31,920.00 $7,980.00 $0.00 $31,920.00 $7,980.00
Remarks:
$39,900.00
Environmental Impact Review - Runway Improvements
Staff recommends approval.
COMMONWEALTH AVIATION FUNDFUNDING REQUEST SUMMARY
VAB DATE: 12/02/2021
Print Date: 11/18/2021 Page 6 of 12
VAB Package December 2021 104
Matthew L. Walker Betty S. Muncy
County Administrator Assistant County Administrator
County of Middlesex
Office of the County Administrator
PROJECT NARRATIVE
Hummel Field – W75
Environmental Impact Review
The Environmental Impact Review will be used to evaluate the proposed
alternatives for runway improvements at Hummel Field, including runway
realignment and lengthening. Environmental documentation will be prepared
in accordance with the National Environmental Policy Act (NEPA) and the
Code of Virginia with a goal of receiving a positive determination from the
Department of Environmental Quality, as well as identification of a runway
alternative that will provide public benefit while avoiding/minimizing
environmental impacts.
P. O. Box 428, Saluda, Virginia 23149-0428 ∙ Phone: (804) 758-4330 Fax: (804) 758-0061
www.co.middlesex.va.us
VAB Package December 2021 105