vie: power transmission investment program, … monitoring report semi annual report january –...
TRANSCRIPT
Social Monitoring Report Semi Annual Report January – June 2016
VIE: Power Transmission Investment Program,
Tranche 2 – 220kV Cau Bong-Hoc Mon-Binh Tan
Transmission Line
Prepared by the Southern Vietnam Power Projects Management Board for the National Power
Transmission Corporation and the Asian Development Bank.
This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
NATIONAL POWER TRANSMISSION CORPORATION
SOUTHERN POWER PROJECT MANAGEMENT BOARD
Project Number: 42039-035
Period: Jan - Jun, 2016
SEMI-ANNUAL INTERNAL MONITORING REPORT
ON IMPLEMENTATION OF RESETTLEMENT PLAN
PROJECT
220KV CAU BONG - HOC MON - BINH TAN TRANSMISSION LINE
HO CHI MINH CITY, July 2016
Semi-annual Internal Monitoring Report - July 2016
220KV Cau Bong – Hoc Mon – Binh Tan transmission line i
ABBREVIATIONS
ADB Asian Development Bank
AP (project) Affected Person
AH (project) Affected Household
DCSCC Compensation, Site Clearance Council
CPC Commune People’s Committee
DMS Detailed Measurement Survey
DP Displaced Persons
DPC District People’s Committee
EVN Vietnam Electricity
GoV Government
HH Household
IOL Inventory of Losses
LURC Land Use Rights Certificate
NPT National Power Transmission Corporation
PPC Provincial Peoples Committee
REMDF Resettlement and Ethnic Minority Development Framework
ROW Right of Way
RP Resettlement Plan
SES Socio-Economic Survey
SPMB Southern Power Projects Management Board
SPS Safeguard Policy Statement
USD United States Dollars
VND Viet Nam Dong
Semi-annual Internal Monitoring Report - July 2016
220KV Cau Bong – Hoc Mon – Binh Tan transmission line ii
TABLE OF CONTENTS
PART I - INTRODUCTION ..................................................................................................... 1
I. Project Description ...................................................................................................... 1
II. Project Impacts ........................................................................................................... 1
III. Progress of the Project Implementation ....................................................................... 2
3.1 Project Construction Progress .............................................................................. 2
3.2 Progress of URP Implementation ......................................................................... 3
3.2.1 Detailed Measurement Survey .......................................................................... 3
3.2.2 Price Valuation and Appraisal ........................................................................... 4
3.2.3 Compensation Plan Preparation ....................................................................... 4
3.2.4 Compensation Payment ................................................................................... 4
IV. Safeguard Policy and Human Resources .................................................................... 5
4.1 Project Policy and Compliance with Government’s Regulations and ADB’s Requirements ................................................................................................................. 5
4.2 Safeguards team .................................................................................................. 6
PART II - IMPLEMENTATION OF SAFEGUARD POLICY ..................................................... 8
I. Public Consultation, Participation, and Information Disclosure .................................... 8
II. Detailed Measurement Survey and Entitlement ........................................................... 9
III. Compensation Payment and Assistance ................................................................... 10
3.1 Compensation Payment and Assistance for AHs ............................................... 10
3.2 Compensation Payment and Assistance for Relocated HHs .............................. 10
3.3 Other Support for Severely AHs and Vulnerable Groups .................................... 11
IV. Land Acquisition ........................................................................................................ 11
V. Grievance Redress Mechanism ................................................................................ 11
PART III - MONITORING ..................................................................................................... 13
I. Internal Monitoring .................................................................................................... 13
II. Monitoring the Compliance of RP Implementation ..................................................... 14
PART IV - CONCLUSIONS AND RECOMMENDATIONS.................................................... 15
I. Conclusions and Recommendations ......................................................................... 15
1.1 Conclusion ......................................................................................................... 15
1.2 Recommendations ............................................................................................. 15
II. Plan for the next period ............................................................................................. 15
PART V - APPENDIX ........................................................................................................... 17
5.1 Appendix 1. Project Impacts ............................................................................... 17
5.2 Appendix 2. Progress on RP implementation ..................................................... 18
5.3 Appendix 3. Project Entitlement Matrix ............................................................... 19
Semi-annual Internal Monitoring Report - July 2016
220KV Cau Bong – Hoc Mon – Binh Tan transmission line iii
5.4 Appendix 4. Public Information Booklet .............................................................. 24
5.5 Appendix 5. Minutes of announcement mettings of compensation plan .............. 30
5.6 Appendix 6. List of AHs who have received payment in advance ....................... 43
5.7 Appendix 7. Decision on approving of adjustment coefficient plan of land price for
calculating compensation, support for AHs ................................................................... 46
5.8 Appendix 8. Decision on approving of compensation plan, section through Cu Chi
District .......................................................................................................................... 55
5.9 Appendix 9. Some pictures from Public Consultation Meetings .......................... 62
LIST OF TABLES
Table 1: Location of points ..................................................................................................... 1
Table 2: Summary of Subproject impacts on land and assets on land ................................... 2
Table 3: Construction works up to July 2016 .......................................................................... 3
Table 4: Summary of the detailed measurement survey in Districts ....................................... 3
Table 5: RP implementation progress up to July 2016 ........................................................... 4
Table 6: Members of monitoring team .................................................................................... 7
Table 7: Dates of meeting on announcing compensation plan ............................................... 9
Table 8. DMS progress by area as of January 2016 .............................................................. 9
Table 9: DMS implementation progress in affected communes .............................................. 9
Table 10: Situation of payment in advance .......................................................................... 10
Table 11: Summary of resolving until the end of this quarter ................................................ 11
Table 12: Summary of submitted internal monitoring report ................................................. 13
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 1
PART I - INTRODUCTION
I. Project Description
1. The Cau Bong - Hoc Mon - Binh Tan 220 kV Transmission Line (TL) Project has a
total length of 15.94 km. The TL starts in Cau Bong Substation (SS) at Tan Phu Trung
Commune in Cu Chi District, Ho Chi Minh City and terminate at the proposed Hoc Mon SS in
Tan Thoi Hiep ward in District 12, Ho Chi Minh. A double circuit connection is created
between the Cau Bong 220kV SS which the World Bank would partly finance and the new
substations at District 12 that is financed by Ho Chi Minh Electricity Company. The
corresponding TL uses partly the ROW of the existing 110kV Hoc Mon - Ben Cat and partly
the towers of the 220kV Phu Lam - Hoc Mon TL.
Table 1: Location of points
No. Starting ÷ ending point City/
Province District Commune Length (m)
1 DD2-G2.1A
Ho Chi Minh
Cu Chi
Tan Phu Trung 464
2 G2.1A-G2.1
Tan Thanh Dong
1,456
3 G2.1-G2.2 2,549
4 G2.2-G2.3 1,330
5 G2.3-G2.4 Binh My
1,077
6 G2.4-G2.5 271
Subtotal 1 1 1 3 7,147
1 G2.5-G2.6
Ho Chi Minh
Hoc Mon
Dong Thanh
515
2 G2.6-G2.7 826
3 G2.7-G2.8 559
4 G2.8-G2.9 Thoi Tam Thon
781
5 G2.9-G2.10 870
6 G2.10-G2.11
District 12
Tan Chanh Hiep
791
1 G2.11-G2.12 707
2 G2.12-G2.13 567
3 G2.13-G2.14 748
4 G2.14-G2.15 819
5 G2.15-G2.16 Tan Thoi Hiep
150
6 G2.16-ĐC2 308
Subtotal 2 1 1 3 7,641
TOTAL(1+2) 2 2 6 14,788 1 Connect Cau Bong 220kV
Ho Chi Minh
Cu Chi Tan Phu Trung 314
2 Connect Cau Bong 110kV 619
3 Hoc Mon 110/220 kV District 12 Tan Thoi Hiep 219
Connect to Substations 1,152 GRAND TOTAL 1 3 6 15,940
2. Land is required for the following based on the above technical requirements: (i) right-
of-way; (ii) suspension towers; and, (iii) tension towers. No land is required for the earth
grounding zone because this is a 220kV TL and subject to a range of conditions. Houses and
other physical structures are allowed to exist within the right-of-way (ROW) of the 220 kV TL
as per the Decree No. 14/2014/ND-CP dated 26 February 2014 stipulating in detail the
implementation of Electricity Law regarding electricity safety. However, they are subject to
certain conditions including installation of grounding conductor and fireproof material for
safety reason.
II. Project Impacts
3. Results of Detailed Measurement Survey (DMS) show that the implementation of the
Project causes land restrictions and acquisition in seven (07) communes. Of which three (03)
communes belong to Cu Chi District namely Tan Phu Trung, Tan Thanh Dong and Binh My,
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 2
two (02) communes belong Hoc Mon District namely Dong Thanh and Thoi Tam Thon, and
two (02) wards of Tan Chanh Hiep and Tan Thoi Hiep belong to District 12, Ho Chi Minh City.
Table 2: Summary of Subproject impacts on land and assets on land
Districts/
Communes
No. of
AHs
No. of
Organizati
ons
Affected
Lands
(m²)
No. of
Houses
No. of
Other
Structures
Trees/
Timbers
Cu Chi District 190 3 181,697.7
12 9 8,054
Tan Phu Trung 54 1 57,452.0 0 0
Tan Thanh Dong 49 1 60,479.5 0 7,424
Binh My 87 1 63,766.1 12 9 630
Hoc Mon District 400 2 96,591.2
202 9 716
Dong Thanh 241 1 67,772.9 115 6 381
Thoi Tam Thon 159 1 28,813.3 87 3 335 District 12 322 2
74,639.2
136 233 2,115
Tan Chanh Hiep 218 1 48,893.7 100 174 1,527
Tan Thoi Hiep 104 1 25,745.5 36 63 588
Total 912 7 352,928 350 251 10,885
Source: URP of the Cau Bong – Hoc Mon – Binh Tan 220KV TL, July 2014.
4. There are 912 households affected by the restrictions and land acquisition. The
Project affects 352,928 m² of land, of which 327,381.6 m² (equivalent to 92.8% of affected
land) is affected by land use restriction within the ROW and 25,546.4 m² (accounting 7.2% of
affected land) of land is permanently acquired. The Project affects 10,777.4 m2 of rice and
other annual crops (including maize, cucumber, cassava, etc.), 10,885 trees (including fruit
trees, timbers, ornamental trees and shade trees). There are 350 houses of 350 AHs that are
located under the ROW, of which none of these houses has to relocate.
5. None of the affected households is considered severely affected as well as vulnerable
groups, which includes (i) female headed households without support; (ii) disabled household
heads; (iii) poor households; (iv) children and the elderly headed households who are
landless and with no other means of support; (v) landless households; and (vi) ethnic
minorities. Therefore, that income restoration program implementation is not applied for the
project.
6. No public structure and historical or cultural place is affected by the project
implementation.
III. Progress of the Project Implementation
3.1 Project Construction Progress
7. There are two contractors carrying out the construction for the Cau Bong - Hoc Mon -
Binh Tan 220kV TL project that are the PCC1 and PCC3.
8. In order to ensure the construction progress of the towers, for this quarter period, the
contractors have fastened almost construction items of the construction activities of both
projects include excavation of towers’ foundation and tower erection.
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 3
9. The construction works of the Cau Bong - Hoc Mon - Binh Tan 220kV TL was kick-
started in late February 2014. As the construction and installation progress, up to the end of
June 2016, the works carried out by the two contractors of PCC1 and PCC3 have been
under the planned progress as table below.
Table 3: Construction works up to July 2016
Item Activities Unit Design
volume
Construction
volume
Completion
rate
1 Foundation excavation Tower foundation 59 59 100%
2 Foundation concretion Tower foundation 59 56 94.5%
3 Backfilling Tower foundation 59 56 94.5%
4 Grounding for tower Tower 59 56 94.5%
5 Tower erection Tower 59 56 94.5%
6 Cable stringing m 15,940 12,640 79.3%
Source: Project construction progress report by SPMB
10. The contractor was stringed cable at positions: In Cu Chi District from 500KV Cau
Bong Substation to position 27; In Hoc Mon District from position 28 to 34.
11. Currently, to meet with the progress of the construction works, at almost all positions,
the contractors and AHs have signed an agreement in which the contractor pays AHs in
advance to support for their affected land and assets and get site handover for construction
of tower foundation. It was expected to complete project construction in September 2016.
3.2 Progress of URP Implementation
12. The updated RP of the subproject was approved by ADB in July 2014. The updated
RP was prepared based on the DMS results and the approved resettlement policy framework
(REMDF) of the project. The policy framework is consistent with the governing policies of the
REMDF concurred by ADB and NPT that were applied in all TL projects of the Power
Transmission Investment Program.
13. For the Cau Bong - Hoc Mon - Binh Tan 220kV TL, the Resettlement Plan is carried
out following its steps conformed to the project’s policy, and the progress of RP implementation is as below.
3.2.1 Detailed Measurement Survey
14. Until the end of 2015, DMS has been completed. Summarized below is the progress
of DMS activities in each district.
Table 4: Summary of the detailed measurement survey in Districts
No. Disitrict
Surveyed Records verification
Foundation RoW
HHs % HHs % Records %
1 Cu Chi 56 100% 189 100% 221 100%
2 Hoc Mon 29 100% 416 100% 432 100%
3 District 12 31 100% 362 100% 362 100%
Total 116 100% 967 100% 1,015 100%
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 4
15. Records verification: DCSCCs and communes people’s committee have reviewed
legal ownership completely since June 2015 for 221/221 belongs to Cu Chi District, 432/432
AHs belong to Hoc Mon District and 362/362 AHs at District 12.
3.2.2 Price Valuation and Appraisal
16. Until the fourth quarter of 2015, the replacement price survey has been conducted
completely by price appraisal consultants. This price has been determined again by Districts
compensation site clearance committee and submitted to DONRE and City People’s Committee for appraising and approving. On December 10th 2015, Ho Chi Minh City
People’s Committee has issued Decision No. 6762/QD-UBND on approving adjustment
coefficient plan of land price for compensation for the 220KV Cau Bong – Hoc Mon – Binh
Tan in Cu Chi, Hoc Mon District and District 12.
3.2.3 Compensation Plan Preparation
17. Until the end of this quarter, the establishing for compensation plan has been
implemented in all Districts. The draft compensation plans have been announced for AHs at
all affected communes. On March 9th 2016, Cu Chi DPC has issued Decision No. 1494/QD-
UBND on approving compensation, allowance and resettlement plan for AHs of the 220KV
Cau Bong – Hoc Mon – Binh Tân (section through Cu Chi District). After that, on May 27th
2016, Hoc Mon DPC has issued Decision No. 2878/QD-UBND on approving compensation,
allowance and resettlement plan for AHs by the project, section through Hoc Mon District.
Currently, Hoc Mon and Cu Chi DCSCC were adjusting specific compensation value of each
AH to submit for approval before compensation payment. District 12 have been revised
compensation plan after announcing. It is expected to submit to DPC for approval in July
2016.
18. SPMB has contracted No. 08/2015/HDTV dated July 27, 2015 with the Asian Pacific
Consultancy Joint Stock Company for the service of independent monitoring. The
independent monitoring agency conducted the first monitoring in February 2016.
3.2.4 Compensation Payment
19. Until now, to meet with the progress of the construction works, DCSCCs, SPMB and
contractor cooperated with consulted agreements of affected households for the project
construction. The SPMB and contractors had paid in advance for affected households before
approved compensation plan (see Table 4). It is expected to conduct compensation payment
in July 2016.
Table 5: RP implementation progress up to July 2016
RP Implementation Activities
Ho Chi Minh City
Cu Chi Dist. Hoc Mon Dist. District 12
Tan
Phu
Trung
Tan
Thanh
Dong
Binh
My
Dong
Thanh
Thoi
Tam
Thon
Tan
Chanh
Hiep
Tan
Thoi
Hiep
Information Disclosure and Public
Consultation 100% 100% 100% 100% 100% 100% 100%
Detailed Measurement Survey 100% 100% 100% 100% 100% 100% 100%
Preparing Compensation Plan 100% 100% 100% 100% 100% 100% 100%
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 5
RP Implementation Activities
Ho Chi Minh City
Cu Chi Dist. Hoc Mon Dist. District 12
Tan
Phu
Trung
Tan
Thanh
Dong
Binh
My
Dong
Thanh
Thoi
Tam
Thon
Tan
Chanh
Hiep
Tan
Thoi
Hiep
Consulting and Counseling with
the APs on compensation plan 100% 100% 100% 100% 100% 100% 100%
Finalizing the Compensation Plan
and submit for approval 100% 100% 100% 100% 100% 80% 80%
Compensation Plan verifying and
approval 100% 100% 100% 100% 100% 0% 0%
Compensation Payment 0% 0% 0% 0% 0% 0% 0%
Site Clearance 100% 100% 94.5%
Independent Monitoring* Second monitoring
IV. Safeguard Policy and Human Resources
4.1 Project Policy and Compliance with Government’s Regulations and ADB’s Requirements
20. The NPT has reconciled the provisions from Safeguard Requirement 2: Involuntary
Resettlement of the SPS 2009 and other cross-cutting policy themes of ADB, and the
relevant laws of the GoV, from where the legal and policy framework for the compensation,
resettlement and rehabilitation of DPs were formulated. The framework is consistent with the
governing policies of the REMDF concurred by ADB and NPT that will be applied in all TL
projects of the Power Transmission Investment Program.
21. The ADB Safeguard Policy Statement (2009) consolidates three existing safeguard
policies: Involuntary Resettlement (IR), Indigenous Peoples (IP), and Environment. The
objectives of the IR policy are to: (i) avoid involuntary resettlement wherever possible; (ii)
minimize involuntary resettlement by exploring project and design alternatives; (iii) enhance,
or at least restore, the livelihoods of all displaced persons in real terms relative to pre-project
levels; and (iv) improve the standards of living of the displaced poor and other vulnerable
groups.
22. To address the discrepancies between ADB Safeguard Policy and relevant GoV
regulations, the project principles on resettlement policy are as follows:
a. Meaningful consultations have been carried out with the APs and concerned groups and ensure participation from planning up to implementation. The comments and suggestions of the APs and communities have been taken into account;
b. The RP is disclosed to APs in a form and language that understandable to them;
c. Involuntary resettlement and impacts on land, structures and other fixed assets are avoided or minimized where possible;
d. Compensation and assistance is based on the principle of replacement cost;
e. Severely affected household is entitled when they are losing 10% or more of the household’s productive land;
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 6
f. Special assistance has been incorporated in the resettlement plan to protect socially and economically vulnerable groups such as households headed by women, children, disabled, the elderly, landless and people living below the provincial poverty line;
g. Gender concerns are incorporated through RP implementation;
h. Reporting and independent monitoring is defined as a part of the subproject management system. Periodically independent monitoring on implementation of RP has been implemented.
23. Since the 1st July, 2014, the updated and amended compensation and resettlement policy of the Government of Vietnam had been entered into force which are applied in the implementation of the updated RP include:
(i) The newly revised Land Law 2013 No.45/2013/QH13 dated November 29th, 2013;
(ii) Decree No.43/2014/ND-CP dated May 15th, 2014 guiding the implementation of the Land Law 2013;
(iii) Decree No.44/2014/ND-CP dated May 15th, 2014 regulating land price;
(iv) Decree No.45/2014/ND-CP dated May 15th, 2014 regulating collection of land use levy;
(v) Decree No.47/2014/ND-CP dated May 15th, 2014 on compensation, assistance, rehabilitation and resettlement in the event of land recovery by the State.
(vi) Circular No. 36/2014/TT-BTNMT dated June 30th, 2014 of MONRE on regulating
determination methods of specific land price and consultancy on land pricing;
(vii) Decision No. 23/2015/QD-UBND dated May 15th, 2015 of Ho Chi Minh City PC on regulating for compensation, allowance and resettlement when the state recover land on the Ho Chi Minh City area.
24. Details of project policy for compensation and allowances are indicated in the
Entitlement Matrix (see Appendix 3).
4.2 Safeguards team
25. Monitoring and evaluation the implementation of compensation and assistance
activities is continuously conducted to ensure that activities have been carried out effectively
and sufficiently as per the RP and mitigation measures of the project.
26. The NPT and the SPMB have joint responsibilities in the internal monitoring of the RP
implementation with results will be reported to ADB on quarterly basis. All activities in
resettlement are time bounded and the progress of implementation will be obtained by SPMB
from the field on monthly basis and transmit them to the PICs for its assessment, and adjust
the work program if necessary. The monthly internal monitoring reports will cover those
related to performance indicating the measurement of input indicators against proposed
timetable and budget including the provision and physical delivery of compensation, repair of
houses and structures and assistance to APs, including grievance and redress, among
others.
27. SPMB had assigned a full-time team allocated from its Compensation Department for
supervising and implementation of the RP. Compensation Department has assigned tasks to
support the Director Board on the implementation of compensation, land clearance,
resettlement and environmental impact assessment. It has a total number of 22 staff
specializing in both resettlement and environment aspects. For this project, five persons are
frequently involved in the assigned works.
28. In additionally, in June 2014 two consultants (resettlement and environment) were
recruited and mobilized on intermittent basis to support the implementation of project’s resettlement and environment safeguard policy (resettlement consultant had terminated the
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 7
contract from early of 2015. Until early of June 2016, SPMB has signed contract with other
consultant for replacing the former consultant). PICs closely work with safeguards team
under SPMB in the implementation of RP. The resettlement consultant has assisted SPMB
team to:
(i) Continue undertaking the consultation and disclosure programs. Ensure that options or agreements reached with affected people (APs) in terms of replacement of assets, i.e. cash or in-kind are provided in a timely manner.
(ii) Establish and implement liaison mechanisms to ensure proper technical and logistical support to SPMB and DCSCCs, as well as procedures for a centralized resettlement and social management information system and internal monitoring.
(iii) Assist in the implementation of all resettlement activities, and ensure that the terms of references are properly and effectively achieved.
(iv) Review and assess grievance redress mechanism and ensure that the responsibilities, reporting requirements, and budget allocation to support the committee's functions are in place.
(v) Carry out on-the-job training on consultation and grievance mechanism strategies to SPMB, DCSCCs and mass organizations, so they will be able to provide correct and clear information and culturally appropriate support to affected persons.
(vi) Assist in the preparation of quarterly progress and internal monitoring reports to be submitted to NPT and then forwarded to ADB.
Table 6: Members of monitoring team
No. Name Position Responsibility
1 Mr. Nguyen Hai Dang Head, Compensation Dept.
Overall management of RP implementation of the project
2 Mr. Le Tuan Anh Deputy head, Compensation Dept.
Supervising and reporting the progress of RP implementation of the project
3 Mr. Phan Van Tranh Expert, Compensation Dept.
Supervising and reporting the progress of RP implementation of two subprojects
4 Mr. Le Trong Man Expert, Compensation Dept.
Supervising implementation of RP
5 Mr. Nguyen Huynh Duc Tuan
Expert, Compensation Dept.
Supervising implementation of RP
6 Mr. Le Trung Thong has been replaced by Mr. Nguyen Truong Thong
Resettlement Consultant
Support SPPMB in the implementation of resettlement safeguard policy
7 Mr. Duong Dinh Dung Environmental Consultant
Support SPPMB in the implementation of environmental safeguard policy
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 8
PART II - IMPLEMENTATION OF SAFEGUARD POLICY
I. Public Consultation, Participation, and Information Disclosure
29. In compliance with GoV’s Land Law 2013 (Article 48, Article 67, and Article 69), SPS (2009) and ADB’s Public Communication Policy: Disclosure and Exchange of Information (2011), the SPMB, as representative of NPT in Southern Vietnam, promotes the active
participation of the Project-based stakeholders. They have been identified during the series
of disclosures and public consultations at District, commune and village levels, involving
stakeholders such as the District level DSCCs, CPCs, mass organizations, non-AP residents,
and the APs.
30. In the first quarter of 2016, in Cu Chi and Hoc Mon District has organized meetings
with AHs for announcement of draft compensation plan from early of March to end of March
2016. In the second quarter of 2016, District 12 has also organized meetings with AHs to
announce draft compensation plan in May 2016. Summary of dissemination contents as
below:
i. Scope of project, right-of-way, and location of towers;
ii. Scope of land acquisition; alternatives of land acquisition mitigation; land acquisition
for construction of tower foundations and land use restriction under ROW.
iii. Entitlements of affected households/community; gender and ethnic minority policies
and strategies;
iv. Calculating sheet of compensation value of each AHs based on result of DMS and
project’s entitlement policies for AHs.
31. During the dissemination of draft compensation plan, AHs have been introduced to
review their compensation calculating sheet. AHs can comment or complain if their benefits
were not ensured. Besides, AHs have been also distributed a form for writing their comments
and send it to competence agencies for resolving. Summary of feedback contents of AHs
and local authorities as below:
i. Almost AHs have agreed with draft compensation plan and had no comments; AHs
have agreed with compensation and allowance policies that applied to calculate
compensation for them.
ii. Suggest informing width of ROW and methods to determine affected assets under
ROW.
iii. AHs requested to submit compensation plan to competence agencies for approving
as soon as possible because AHs have waited so long for approved compensation
plan to pay compensation for them.
32. The above-mentioned issues of concerns and proposals from the APs were listened
and consulted by DCSCCs, resettlement consultant and representatives of SPMB then
clearly explained and discussed at the meetings in terms of project policies, entitlements as
well as obligations of the APs.
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 9
Table 7: Dates of meeting on announcing compensation plan
Communes Dates of
Consultations
Number of Participants
Total Male Female
Tan Phu Trung March 11th 2016 49 28 21
Tan Thanh Dong March 11th 2016 49 31 18
Binh My March 14th 2016 92 51 41
Dong Thanh March 10th 2016 46 27 19
Thoi Tam Thon March 9th 2016 69 45 24
Tan Chanh Hiep May 6th 2016 57 38 19
Tan Thoi Hiep May 6th 2016 43 25 18
Total 405 245 160
II. Detailed Measurement Survey and Entitlement
33. Detailed Measurement Survey (DMS) has been carried out since mid-June 2014 and completed at the end of June 2014. DCSCCs and the CPCs have reviewed legal ownership of APs’ property for all AHs including 221 AHs in Cu Chi District, 432 AHs in Hoc Mon District and 362 AHs in District 12. The DMS progress by area is described as below:
Table 8. DMS progress by area as of January 2016
District
DMS for households affected by permanent
LA for tower foundations
DMS for households affected by land use
restrictions within the ROW
No. of AHs Status No. of AHs Status
Cu Chi 32 Done 189 Done
Hoc Mon 16 Done 416 Done
District 12 11 Done 362 Done
34. The DMS implementation with participation of many stakeholders including the representatives of DCSCC, SPMB, head of villages, cadastral officers, and APs.
35. During DMS, enumeration was conducted fully and exactly for all lost land and assets on land of the AHs and affected communities. The DMS results were publicly disclosed and posted at the CPCs’ offices for AHs to recheck and complain for correction (if any). APs were announced schedule for DMS before and their attendance were required, therefore most APs have attended in DMS progress. After DMS, APs rechecked their affected assets and signed the DMS minutes. They were supplied with a copy of their DMS record for keeping. So far, no households has lodged complaint regarding the DMS results. DMS duration by commune is described in the table below.
Table 9: DMS implementation progress in affected communes
District Commune Detailed Measurement Survey
Starting date Finishing date
Cu Chi
Tan Phu Trung 15/6/2014 24/6/2014
Tan Thanh Dong 15/6/2014 24/6/2014
Binh My 15/6/2014 24/6/2014
Hoc Mon Dong Thanh 15/6/2014 24/6/2014
Thoi Tam Thon 15/6/2014 24/6/2014
District 12 Tan Chanh Hiep 15/6/2014 24/6/2014
Tan Thoi Hiep 15/6/2014 24/6/2014
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 10
36. Price survey and appraisal: Until now, the replacement price survey has been conducted completely by price appraisal consultants. This price has been determined again by Districts compensation site clearance committee and submitted to DONRE and City People’s Committee for appraising and approving. On December 10th 2015, Ho Chi Minh City People’s Committee has issued Decision No. 6762/QD-UBND on approving adjustment coefficient plan of land price for compensation for the 220KV Cau Bong – Hoc Mon – Binh Tan in Cu Chi, Hoc Mon District and District 12.
37. Establishing for Compensation plan: Until present, the establishing for compensation plan has been implemented in all Districts. The draft compensation plans have been announced for AHs at all affected communes. On March 9th 2016, Cu Chi DPC has issued Decision No. 1494/QD-UBND on approving compensation, allowance and resettlement plan for AHs of the 220KV Cau Bong – Hoc Mon – Binh Tân (section through Cu Chi District). After that, on May 27th 2016, Hoc Mon District has issued Decision No. 2878/QD-UBND on approving compensation, allowance and resettlement plan for AHs by the project, section through Hoc Mon District. Currently, Hoc Mon and Cu Chi DCSCC were adjusting specific compensation value of each AH to submit for approval before compensation payment. District 12 have been revised compensation plan after announcing. It is expected to submit to DPC for approval in July 2016.
III. Compensation Payment and Assistance
3.1 Compensation Payment and Assistance for AHs
38. So far, in Hoc Mon and Cu Chi District, although the plan of compensation and support have been approved but DCSCCs need to re-adjust exactly compensation value of each AH before compensation payment. Therefore until the end June of 2016, compensation payment has not been done. Compensation payment is expected to conduct in July 2016. However, to meet with the progress of the construction works, at almost all positions, SPMB, contractors and AHs have signed an agreement in which the SPMB pays AHs in advance to support for their affected land and assets and get site handover for construction of tower foundation and stringing cable. So far, The SPMB and contractors have paid in advance to 51 AHs for construction of towers and cable stringing, with total amount of VND
18,154,740,471. Status of compensation payment for AHs described as Table below.
Table 10: Situation of payment in advance
No District/Commune Amount (VND)
(Until the previous quarter)
Amount (VND) (In this quarter)
No of AHs who have received
compensation in advance
I Cu Chi District 1,052,090,000 2,100,000,000 10
1.1 Tan Phu Trung 18,024,000 1
1.2 Tan Thanh Dong 620,000,000 2,100,000,000 4
1.3 Binh My 414,066,000 5
II Hoc Mon District 6,923,568,000 1,942,266,500 25
2.1 Dong Thanh 5,018,000,000 303,000,000 10
2.2 Thoi Tam Thon 1,905,568,000 1,639,266,500 15
III District 12 6,136,815,971 3,112,132,896 16
3.1 Tan Chanh Hiep 1,705,541,971 146,712,896 7
3.2 Tan Thoi Hiep 4,431,274,000 2,965,420,000 9
Total 14,112,473,971 4,042,266,500 51
3.2 Compensation Payment and Assistance for Relocated HHs
39. No one needs to be relocated due to the project implementation.
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 11
3.3 Other Support for Severely AHs and Vulnerable Groups
40. DMS found that there is no AH entitled as severely or vulnerable groups.
IV. Land Acquisition
41. The results of the DMS indicated that there is no AP has to be relocated. Since the
updated RP has been approved, the land acquisition activities are implemented based on
agreement among AHs, SPMB and contractors for handing over land in advance for tower
foundation construction and cable stringing. AHs were paid compensation in advance and
land handed over to contractors.
42. Up to the end of the this quarter, although compensation payment are not done yet,
all land areas acquired (100% of positions) for tower construction have been handed over to
the contractors for construction (including: 32/32 towers in Cu Chi District, 16/16 towers in
Hoc Mon and 11/11 towers in District 12) and 98.1% of ground for cable stringing has been
handed over for project construction. Present, SPMB, DSCCs and contractors keep
negotiating with AHs for handing over ground for stringing cable.
V. Grievance Redress Mechanism
43. During the information disclosure and public consultation campaign, the resettlement
consultant and SPPMB disclosed to the AHs for them to understand about the procedures
and steps of logging complaints and grievance redress mechanism by four steps based on
the principles of publicity, democracy, protection of rights and interests of the APs.
44. Status of complaint and redress until the end of this quarter described as below:
Table 11: Summary of resolving until the end of this quarter
Time Complaint contents Resolving status
Complaint
has raised
from the
previous
quarter
At position 43, Mr. Pham Van Luc
requested compensated price for
land is 20 million/m2. He also
requested being allowed to
transfer use purpose of whole of
the affected land plot from
agricultural land to residential
land.
Hoc Mon DCSCC, SPMB, contractor and
people's committee of project communes
have cooperated for negotiating with the
household to allow constructing project.
Until now, the AH has agreed to sign
agreement minutes to hand over site to
contractor for project construction.
However, He requested compensated
price for land is 20 million/m2. He also
requested being allowed to transfer use
purpose of whole of the affected land
plot from agricultural land to residential
land. The Hoc Mon DCSCC have been
considering looking for a reasonable
redress option.
This quarter
On the June 29th 2016, household
of Mr. Nguyen Ba Truu located at
Thoi Tam Thon Commune have
sent his complaint to Hoc Mon
DCSCC on requesting temporarily
don’t pay compensation for household Mr. Le Dai Hung
because they have been
Currently, Hoc Mon DCSCC is
considering resolving.
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 12
Time Complaint contents Resolving status
disputing land use right of
compensated land plot.
45. Besides, AHs’ the complaints, during the RP implementation have been raised some
AH’s difficulties. Summary of specific comments described as below:
- Suggest informing width of ROW and methods to determine affected assets under ROW.
- AHs requested to submit compensation plan to competence agencies for approving as
soon as possible because AHs have waited so long for approved compensation plan to
pay compensation for them.
46. The above-mentioned issues of concerns and proposals from the APs were listened
and consulted by DCSCCs, resettlement consultant and representatives of SPMB then
clearly explained and discussed at the meetings in terms of project policies, entitlements as
well as obligations of the APs.
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 13
PART III - MONITORING
I. Internal Monitoring
47. The SPMB conducts internal monitoring of RP implementation and results of the
internal monitoring are reported on quarterly basis to NPT and ADB. Internal monitoring
activities are periodically carried out by SPMB staffs to ensure the implementation of RP is
on the right direction and any problems/issues that may be occurred, including complaints of
the AHs shall be timely resolved.
48. The semi-annual monitoring report is prepared summarizing all activities relevant to
the implementation of RP done during the six-month period in compliance with the ADB
requirements. This report incorporated monitoring results for the period from January to June
2016 to report the situation has been implemented and tasks taken to improve the situation,
where needed. Related information has been collected monthly from the field to assess the
progress of RP implementation and then consolidated.
49. SPMB’s consultant has periodically conducted field visits to project affected
communes. Field surveys carried out during this period to (i) collect information on the
opinions and the needs of AHs regarding the policy of the project; (ii) support in
implementation of public consultation and information disclosure; (iii) collect and review
grievance redress; (iv) coordinate with contractors of construction to ensure that allowance
for temporary affected assets due to construction work is taken into account. Working with
stakeholders such as CPCs, DCSCCs, mass organizations, and in-depth interviewing APs
has been applied to achieve the monitoring target.
50. Summary of submitted report on internal monitoring such as below:
Table 12: Summary of submitted internal monitoring report
No. Type of report Status of submission
I Quarter report
1 The second quarter, 2014 Submitted
2 The third quarter, 2014 Submitted
3 The fourth quarter, 2014 Submitted
4 The first quarter, 2015 Submitted
5 The second quarter, 2015 Submitted
6 The third quarter, 2015 Submitted
7 The fourth quarter, 2015 Submitted
8 The first quarter, 2016 Submitted
9 The second quarter, 2016 Submitted
II Semi-annual report
1 The semi report of 6 months end of 2014 Submitted
2 The semi report of 6 months early of 2015 Submitted
3 The semi report of 6 months end of 2015 Submitted
4 The semi report of 6 months end of 2016 Being submitted
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 14
II. Monitoring the Compliance of RP Implementation
51. In addition to the internal monitoring taken by the SPMB, it is always required to have
a different objective information channel independently. The key objective of external
monitoring is to determine whether NPT/SPMBs’ efforts on RP implementation have been properly conceived and executed consistent with the agreed actions in the RP. The external
monitoring will verify in the filled-up DMS questionnaire and asset compensation forms (ACF)
that all affected losses of APs, have been satisfactorily compensated and rehabilitation and
transition assistance have been provided with. It will also ascertain whether the entitlements
were adequate in meeting the objectives, and whether the objectives were suited to APs.
52. SPMB has contracted No. 08/2015/HDTV dated July 27, 2015 with the Asian Pacific
Consultancy Joint Stock Company for the service of independent monitoring. The independent
monitoring agency conducted the second monitoring on February 2016.
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 15
PART IV - CONCLUSIONS AND RECOMMENDATIONS
I. Conclusions and Recommendations
1.1 Conclusion
53. The RP implementation in Ho Chi Minh City has been delayed for a long time
because Ho Chi Minh City People's Committee has promulgated late regulation of
compensation, support and land clearance. However, currently these issues have been
resolved. DCSCCs have prepared compensation plan and announced to APs. Specially, Hoc
Mon and Cu Chi DPC have issued Decisions on approving compensation plan.
Compensation payment was expected to conduct in July 2016 at all District.
54. The DMS has been completed. District’s division of natural resources and environment have determined completely the legal ownership, reviewed the origin of land
title and relevant legal documents for formulating the compensation plan.
55. SPPMB in order to keep the project progress has in cooperation with the contractors
worked with DPCs and CPCs for negotiating with APs for implementing the construction in
advance. Until the end of this quarter, SPMB has paid in advance for 51 AHs with amount of
VND 18,154,740,471.
56. Up to the end June of 2016, although compensation payment are not done yet, all
land areas acquired (100% of positions) for tower and 98.1% of ground for cable stringing
has been handed over to contractors for project construction. Present, SPMB, DSCCs and
contractors keep negotiating with AHs for handing over ground for stringing cable. Besides,
this issue has been mentioned in due diligence report and independent monitoring report of
project. These reports also mentioned corrective activities for it and received agreement of
ADB.
57. AHs’ complaints have been receipting and considering resolving effectively and
timely.
1.2 Recommendations
58. In order for the work of compensation, support and resettlement for the APs of the
project to complete timely and efficiently, it is recommended that:
(i) DCSCCs need to speed up compensation payment progress for AHs. At the same
time, ensure all AHs would fully receive compensation for all their affected assets.
(ii) District 12 should speed up submitting compensation plan to DPC for appraisal and
approval.
(iii) SPMB and DSCCS need to carry out surveys to assess effects of land acquisition
before compensation. Thence, there are accordant corrective plans for APs if
necessary.
(iv) SPMB need to continue cooperating closely with local stakeholders to consult and
negotiate with APs about entitlement policies of the project. At the same time, it is
necessary to compensation in advance for APs to construct project while waiting for
approved compensation plan and official compensation payment for APs.
II. Plan for the next period
59. Cu Chi and Hoc Mon DCSCC should pay compensation for AHs as soon as possible.
60. In case necessary, public meeting activities will be still continuously carried out to
ensure that affected households, concerns and grievances are addressed and resolved in a
timely and satisfactory manner.
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 16
61. SPPMB and contractor need to push up the payment of compensation and supports
in advance for cable stringing to ensure the project progress.
62. DCSCCs and relevant agencies will consider to resolve completely AHs’ complaints to ensure efficiently and timely of complaint resolving.
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 17
PART V - APPENDIX
5.1 Appendix 1. Project Impacts
Affected land by communes of Cau Bong - Hoc Mon - Binh Tan 220kV TL
Districts/
Communes Agricultural land Residential land Garden land Total
Cu Chi District 13,378.7 63.6 3,832.3 17,274.6
Tan Phu Trung 6,292.7 6,292.7
Tan Thanh Dong 3,965.2 1,200.6 5,165.8
Binh My 3,120.8 63.6 2,631.7 5,816.1
Hoc Mon District 4,140.5 406,4
4,546.9
Dong Thanh 3,064 406,4 3,470.4
Thoi Tam Thon 1,076.5 1,076.5
District 12 3,352.0 36,6 336.4 3,725
Tan Chanh Hiep 1,624.5 36.6 336.4 1,997.5
Tan Thoi Hiep 1,727.5 1,727.5
Total 20,871.2 506.6 4,168.7 25,546.5
Source: DMS data, May-July, 2014
Impacts on lands under the ROWs by commune
Districts/ Communes No. of AHs (HH) Area of affected land
by the ROW (m2)
Cu Chi District 188 164,423.1
Tan Phu Trung 54 51,159.3
Tan Thanh Dong 49 55,313.7
Binh My 87 57,950.1
Hoc Mon District 400 92,044.3
Dong Thanh 241 64,302.5
Thoi Tam Thon 159 27,741.8
District 12 322 70,914.1
Tan Chanh Hiep 218 46,896
Tan Thoi Hiep 104 24,018
Total 910 327,381.5
Source: DMS data, May-July, 2014
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 18
5.2 Appendix 2. Progress on RP implementation
Status of compensation plan till July 2015
Province District Commune
Project information
dissemination
Detailed
Measurement Survey
Making compensation
plan
Verify and approve the
compensation plan
Compensation
payment
Starting
date
Finishing
date
Starting
date
Finishing
date
Starting
date
Finishing
date
Submitting
date
Date of
approval
Starting
date
Finishing
date
Ho Chi
Minh city
Cu Chi
Tan Phu Trung 27/12/2014 27/12/2014 15/6/2014 24/6/2014 Done Done Done Done Not yet Not yet
Tan Thanh
Dong 23/12/2014 23/12/2014 15/6/2014 24/6/2014 Done Done Done Done Not yet Not yet
Binh My 26/12/2014 26/12/2014 15/6/2014 24/6/2014 Done Done Done Done Not yet Not yet
Hoc Mon
Dong Thanh 14/1/2015 14/1/2015 15/6/2014 24/6/2014 Done Done Done Done Not yet Not yet
Thoi Tam Thon 17/1/2015 17/1/2015 15/6/2014 24/6/2014 Done Done Done Done Not yet Not yet
District
12
Tan Chanh
Hiep 19/12/2014 19/12/2014 15/6/2014 24/6/2014 Not yet Not yet Not yet Not yet Not yet Not yet
Tan Thoi Hiep 19/12/2014 19/12/2014 15/6/2014 24/6/2014 Not yet Not yet Not yet Not yet Not yet Not yet
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 19
5.3 Appendix 3. Project Entitlement Matrix
No
.
Type of
Loss/Impacts
Level of
Impacts Eligible Persons Entitlements Implementation Issues
I. LAND
I.1. Agricultural Land
1
Productive Land
permanently
acquired
Partially
affected (less
than 10% of
the total
productive
land holding)
Owners with LURC,
or in the process of
acquiring LURC and
owners eligible to
acquire LURC
according to
Government policies
a. Cash compensation for acquired land at
replacement cost at current market rates for
affected portion;
b. Entitled to allowance for vocational trainings
career change and job seeking in cash not
exceed 5 times of the affected land value.
+ AHs to be notified at least 90 days (for
agricultural land) and 180 days (for non-
agricultural land) prior to land acquisition
(Land Law 2013 - Article 67).
+ Full payment for AHs at least one (01)
month before site clearance.
2 Restrictions on
land use in ROW
Partially
and/or totally
affected
All AHs have
productive land in
ROW
a. No compensation for land;
b. Compensation for trees and other crops at
market prices;
c. Support for restrictions on land use on the
productive land plots adjacent to residential
land; support level is not higher than 80% of
the same land type’s price. AHs can still use land for production but they are not allowed to
grow plant higher than 4 m.
+ SPPMB and DCSCC guide the AHs to
use land in ROW, ensuring safety for
people and construction, consistent with
the Decree No.14/2014/ND-CP.
+ Affected land in ROW will be
rehabilitated by contractors after the
Project construction and land in ROW
could be used with the restricted
purposes.
+ AHs can be required to cut affected
trees, timbers. The Project will pay for
the cutting.
3 Temporary
impacts
Temporary
loss of land
and assets on
Users of affected
land (to be
determined during
For land area to be temporarily used during
construction stage: (i) rental in cash which will
be no less than the net income that would
+ Land characters and quality must be
restored before returning to the AHs;
+ If the quality of land will be radically
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 20
No
.
Type of
Loss/Impacts
Level of
Impacts Eligible Persons Entitlements Implementation Issues
land Project
implementation)
have been derived from the affected property
during disruption; (ii) restoration of the land
within one (01) month after use; compensation
is paid at full replacement cost or ‘land for land” compensation if contractor fails to restore the affected land within one (01) month
after the use (agreement between parties will
be monitored by external monitoring agency).
changed when returning to the AHs,
requiring the AHs to change the land use
purpose, then the AHs should be
compensated for all envisaged cost of
losses.
+ Contracts with the contractors should
include an article regulating specifically
the responsibilities of the contractors.
I.2. Residential Land and/or Non-agricultural Land (e.g. commercial purpose)
1
Residential Land
and/or Non-
agricultural Land in
ROW
Partially
and/or totally
affected
All AHs have
residential and/or
non-agricultural land
in ROW
a. No compensation for land;
b. Allowance for purchasing fireproof materials
and lightning arrestors for the existing
house/structure or cash compensation at
replacement cost of affected house/structure;
c. Support for utilization of restricted land.
Affected land in ROW will be
rehabilitated by contractors after the
project construction and land in ROW
could be used with the restricted
purposes.
II. MAIN HOUSES AND OTHER STRUCTURES IN ROW
II.1. Main houses
1 Main houses
affected
Partially
affected
(affected area
less than 50%
of total land
area without
any impact to
the remaining
Owners of the
houses with or
without acceptable
proof of ownership
over the land; with
or without building
permit
Retain houses according to the conditions
regulated by Article 13 of Decree
No.14/2014/ND-CP, and Cash compensation
for directly affected parts of the houses at the
replacement cost and cost for dismantling the
affected parts.
The technical norms for partially or fully
affected house will be determined by the
DCSCC with the technical assistance
from District or Provincial Construction
Department and concurred by the PDP
during the DMS.
+ The calculation of rates will be based
on the actual affected area and not the
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 21
No
.
Type of
Loss/Impacts
Level of
Impacts Eligible Persons Entitlements Implementation Issues
structures of
the house
useable area.
II.2. Other structures
1
Secondary
Structures
(kitchen, latrines,
bathrooms, wells,
animal shelters,
fences, etc.)
Structures lost
and/or
damaged due
to location in
ROW
All AHs have
structures in ROW
a. Cash compensation for the entire affected
structures will be provided at 100% of the full
replacement cost for materials and labor,
without provision for deduction of depreciation
or salvage value of construction materials,
whether or not they have title to the affected
land or permit to build the affected structure.
The amount will be sufficient to rebuild a
structure the same as the former one at
current market prices;
b. Provision of allowance for the installation of
fireproofing materials and lightning arrestors.
The calculation of rates will be based on
the actual affected area and not the
useable area.
III. ON-LAND AFFECTED CROPS AND TREES
1
Annual crops
(paddy and other
annual crops)
Crops lost
and/or
damaged due
to location in
ROW
Owners regardless
of tenure status
If standing crops are ripening and cannot be
harvested, cash compensation at replacement
cost equivalent to the highest production of
crop over the last three years multiplied by
current market value of crops at the time of
compensation.
+ APs have the right to use salvable
trees.
+ APs will be given three (03) months
notice in advance regarding evacuation
so that the land on which their crops are
planted will be recovered and that they
must harvest their crops on time.
2 Trees and timbers
(fruit trees,
Trees lost
and/or
Owners regardless
of tenure status
Cash compensation at replacement cost is
equivalent to current market value given the
+ Compensation must equal in value to
trees that would be harvested had
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 22
No
.
Type of
Loss/Impacts
Level of
Impacts Eligible Persons Entitlements Implementation Issues
timbers, wood
trees, etc.)
damaged due
to location in
ROW
type, diameter at breast height, age and
productive value at the time of compensation.
acquisition not occurred.
+ APs will be given notice at least three
(03) months in advance regarding
evacuation. Trees grown after issuance
of the deadline will not be compensated.
+ AHs can be required to cut affected
trees, timbers. The Project will pay for
the cutting.
IV. REHABILITATION ASSISTANCE
IV.1. Allowance for Vocational Training, Career Change and Job Seeking
1
Households
having agricultural
land affected
Affected and
loss of land
All AHs with
agricultural land
permanently
acquired
Assistance for vocational training, career
change and job seeking:
+ Cash compensation equal to 1.5 to 5 times
of compensation value for affected land
according to PPC’s regulation.
+ If the AP has demand for training, he/she will
be entitled to participate in a training course
for free.
IV.2. Allowances for houses in ROW
1
Assistance to
improve house or
install fire-proof
materials and
lightning arrestors,
and assistance to
Houses
partially or
fully affected
AHs with houses in
ROW
+ With houses Grade 4, allowance for
installing fireproof materials and lightning
arrestors.
+ With houses Grade 5, allowance for
improvement.
+ Allowance due to restricted usage and
At time of compensation, allowance will
be adjusted for inflation to ensure that
APs can do the improvement in safe
manners.
Semi-annual Internal Monitoring Report – July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 23
No
.
Type of
Loss/Impacts
Level of
Impacts Eligible Persons Entitlements Implementation Issues
mitigate impacts
due to restricted
usage and impacts
on daily life
activities
impacts on daily-life activities.
V.5. Allowances for other structures in ROW
1
Assistance to
improve or install
fireproof materials
and lightning
arrestors
Other
structures
partially or
fully affected
AHs with other
structures in ROW
+ With houses Grade 4, allowance for
installing fireproof materials and lightning
arrestors.
+ With houses Grade 5, allowance for
improvement.
At time of compensation, allowance will
be adjusted for inflation to ensure that
APs can do the improvement in safe
manners.
V.6. Other Allowances
1
Loss of land and
non-land assets
Affected households
whose houses will
be relocated from
the ROW
Every relocating AP will be provided with a
lump-sum one time allowance package to
cover the cost of domestic water, power and
telephone connections at the new site as per
PPC’s decision at payment time but it is not less than 3.5 million VND per household.
Based on the actual situation of the
locality, the PPC Chairman issues other
allowances (according to the Article 23 in
the Decree No. 69/2009/ND-CP) to
ensure accommodations, life stabilization
and production for DPs. Special cases
have to be submitted to the Prime
Minister for approval.
VI. Incentive Bonus
Loss of land and
non-land assets All AHs
If APs hand over the affected land immediately
after receiving compensation and allowances
will be awarded an incentive bonus of VND
5,000,000 as per regulations of the PPC
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 24
5.4 Appendix 4. Public Information Booklet
National Power Transmission
Corporation (NPT)
Southern Vietnam Power Projects
Management Board (SPPMB)
Ho Chi Minh City Province People’s Committees
Cu Chi/Hoc Mon/District 12 District People’s Committees
Cu Chi/Hoc Mon/District 12 District Compensation and
Resettlement Boards (DCSCCs)
Public Information Booklet
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project
I. PROJECT INTRODUCTION
The two Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project and Cau
Bong – Duc Hoa 220 kV Transmission Line Project are for Tranche 2 of the Power
Transmission Investment Program of the Government of Vietnam (GOV). The Projects under
the Program are designed to: (i) improve system stability and security, and improve the
reliability of power supply in Southern Viet Nam; and (ii) enable evacuation of electricity to
load centres from the both the planned public sector and private sector financed thermal
power plants in southern Viet Nam. The Projects shall be financed through the Multi-
Financing Facility (MFF) of Asian Development Bank (ADB). The National Power
Transmission Corporation (NPT) is the Project executing agency (EA) while the Southern
Vietnam Power Projects Management Board (SPPMB) is the implementing agency (IA).
1. Project Description
The Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project is designed to
ensure reliable electricity supply to load centres in Hoc Mon District, Binh Tan District, Go
Vap District and District 12 of Ho Chi Minh City; and strengthen the connectivity capacity for
power network in the Northwest of Ho Chi Minh City to provinces Tay Ninh and Long An.
The Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project has a total
length of 15.97 km that comprises the following sub-components: (i) 7.645 km for
improvement of existing transmission line; (ii) 7.147 for construction of new transmission line;
(iii) 0.314 km for connection to 220 kV transmission line; and (iv) 0.864 km for connection to
110 kV transmission line. The Project will traverse to seven communes of three districts of
Ho Chi Minh City, namely, Cu Chi, Hoc Mon and District 12. Of which, three communes of
Tan Phu Trung, Tan Thanh Dong and Binh My belong to Cu Chi district, two communes of
Dong Thanh and Tam Thoi Thon belong to Hoc Mon district and two wards of Tan Chanh
Hiep and Tan Thoi Hiep belong to District 12. Land will be required for the: (i) right-of-way; (ii)
suspension towers; and (iii) tension towers.
2. Scope of Land Acquisition and Resettlement
The rights-of-way (ROWs) for Cau Bong - Hoc Mon - Binh Tan Transmission Line
Project shall require a total are 352,928 m² of land, of which 327,381.6m² is covered in
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 25
restriction on lands under the ROW and 25,546.4 m² of land is permanently acquired for
permanent use of 59 suspension and tension towers.
The Project will impact on total of 910 affected household (AHs) who own the following
affected properties: (i) 350 houses due to height limit under the ROW, (ii) 10,885 trees due to
the clearing of ROWs. The affected households all belong to the mainstream society of
Vietnam. No ethnic minority group shall be affected under the Subproject.
II. INFORMATION REGARDING PROJECT COMPENSATION AND RESETTLEMENT
POLICIES AND REGULATIONS
Question 1: What is the Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Lines
Project?
Answer: The Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project is
designed to ensure reliable electricity supply to load centres in Hoc Mon District, Binh Tan
District, Go Vap District and District 12 of Ho Chi Minh City; and strengthen the connectivity
capacity for power network in the Northwest of Ho Chi Minh City to provinces Tay Ninh and
Long An.
The Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project has a total
length of 15.97 km that comprises the following sub-components: (i) 7.645 km for
improvement of existing transmission line; (ii) 7.147 for construction of new transmission line;
(iii) 0.314 km for connection to 220 kV transmission line; and (iv) 0.864 km for connection to
110 kV transmission line.
Question 2: How will the Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line
Project affect the local population?
Answer: The Project will cause the following effects: (i) Buildings and other structures
and buildings on land lost permanently; (ii) Trees are cut off on the land affected
permanently; and (iii) Reduction of the use of land, buildings / infrastructure in the safety
corridor of high-voltage grid (ROW).
Question 3: What is the main objective of the Project Resettlement Plan?
Answer: The main objective of this Resettlement Plan is to ensure that all APs will be
restored their socio-economic conditions at least equal to or better than they would have
been in the absence of the Project. Poor households, difficult condition households and other
vulnerable households (women-headed, eldly-, children-, disable person-headed, under-
policy-assisted households) will be supported rehabilitating their socio-economic conditions
equal to or better than prior Project conditions.
Question 4: What if my land is affected by the Project?
Answer: The affected land will be compensated for replacement land (if land fund
available) OR in cash at replacement value at current market rates at the time of
compensation. All affected households and local authorities will participate in replacement
cost survey. If the leased land is recovered, compensation will not be made for the land but
the investment costs in land.
Question 5: Do we need to have a land title in the order to be compensated?
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 26
Answer: No, lack of formal legal rights to land does not prevent any APs from receiving
compensation or allowances and/or rehabilitation assistances. Those APs who possess a
land use rights certificate (LURC) or any other form of written or verbal agreement to utilize
the land are entitled to compensation for the lost land as well as assets on the land. Those
APs who do not have legal/legalizable or temporary/lease rights for land will still be
compensated for the assets on the land, such as any structures, crops and trees.
Question 6: Is the compensation applied for affected houses and structures?
Answer: Yes. Compensation will be applied for all affected assets including houses,
shops and other structures (kitchen, bathroom, toilet, well, livestock cages, fence, etc.) as
well as other fixed assets at replacement value at current market prices (including materials
and labour) without any deductions for building depreciation or salvageable building
materials. This will ensure that APs are able to reconstruct their houses and other structures
with better or at least the same quality as in the absence of the Project.
Question 7: What about affected crops and trees?
Answer: Affected crops, fruit and timber trees and tree fences will be compensated in
cash at current market prices. Compensation for non-harvested crops will be based on the
average production in the past 3 years multiplied by current market prices. Compensation for
trees will be based on the type, age and productivity of trees.
Question 8: In addition to compensation, how will the Project support us?
Answer: In addition to compensation for affected land and asset as per Project policy,
the Project will provide rehabilitation assistances to eligible APs to ensure that their living
standard is restored or improved at least equal to or better than their pre-Project level.
Rehabilitation assistances for eligible APs include:
Severely affected households: Households that lose 10% or more of their total
productive land will receive rehabilitation assistances include (i) life stabilization
assistance (ii) income restoration assistance such as agriculture extension assistance for
better use of the remaining land area, participating in credit access programs or
recruitment related to the Project. The assistances are presented in the Entitlement
Matrix.
Relocated households: Affected people who must be relocated have rights to get: (1)
transition assistance; (2) life stabilization assistance for transitional period; and (3)
assistance for house rental at replacement cost. The assistances are presented in the
Entitlement Matrix.
Business owners that lose income while they relocate or rebuild their shops/businesses:
Households with small, unregistered businesses will receive cash compensation equal to
the provincial minimum wage for 3 months. Owners of registered businesses will receive
cash assistance due to loss of income equivalent to 30% taxable income in a year.
Annual taxable turnover average is determined on the basis of financial statements of
three years ago.
Employees and hired laborers who lose their jobs: will receive cash compensation for
lost salary/wages for each month they cannot work, if the loss is temporary; or, if the loss
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 27
is permanent, cash compensation equivalent to the provincial minimum wage for 6
months or cash compensation for remaining contract period whichever is higher.
Allowance for changing job: the affected households either have or not have registered
certificate on their residential land that after relocation but they could not be continued,
the person in working age who belonged to the affected households will be participated
in the free cost training course in one of the local vocation training centers, suitable for
the facts of region and their ability.
Question 9: How our affected public assets will be compensated?
Answer: With respect to affected public assets, compensation will be provided to
recover or newly construct depending on scope of impact after consulting with local
authorities/affected community.
Question 10: Does anybody in our community can claim for compensation?
Answer: No. Entitled Affected Persons (APs) are those persons or households that are
surveyed during the detailed measurement survey (DMS) activities. The APs and local
authorities will be informed of the cut-off date (the date of completion of census) for the
Project. Anyone moving into the Project area after cut-off date will not be entitled to
compensation and assistance under the Project.
Question 11: What can I do if I am not listed as affected people during the DMS but I
am asked to be relocated?
Answer: You are not in affected people list might be due to some mistakes during the
DMS. However, you will get the same kind of compensation as other APs. DCSCC will
responsible for adding your name in the list of affected people.
Question 12: How will APs be consulted and informed?
Answer: A consultation and public information program will be organized in your
commune to ensure that APs receive complete and timely information about the Project. APs
will be provided information on project components, impacts, their rights and entitlements,
grievance mechanism, rights of participation and consultation, resettlement activities,
responsibilities of institutions and implementation schedule. APs will participate in
resettlement planning and implementation and they will also be consulted on the following
issues: a) resettlement options according to their entitlement, b) training and training
preferences in current or new occupations, c) other project aspects.
This program will enable the Project to design the resettlement and rehabilitation
program to meet the needs of APs, and help APs to make informed decisions about
compensation and relocation. Consultations with APs and local authorities will reduce the
potential for conflicts and minimize the risk of project delays, and maximize the economic
and social benefits of the Project.
Question 13: In case where disagreement on compensation or dispute appears during
Project implementation, do we have the right to complain?
Answer: Yes, All affected people have the right to complain based on the following
procedures and orders:
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 28
First Stage - At Commune/Ward People’s Committee (CPC): An aggrieved AP may
bring his/her complaint to village head or any member of the CPC in either written or verbal
form. It is incumbent upon said village head or member of CPC to notify the CPC about the
complaint. The CPC will meet personally with the aggrieved AP and shall have thirdty (30)
days following the lodging of the complaint to resolve it. The CPC’s secretariat is responsible for documenting and keeping files of all complaints that it handles.
Second Stage - At District/Town People’s Committee (DPC): If after thirdty (30)
days the aggrieved AP does not hear from the CPC, or if the CPC gives its solutions, but the
AP disagrees with the settlement decision, the AP may bring the case, either written or
verbal, to any member of DPC. DPC shall have thirdty (30) days to resolve the case. The
DPC is responsible for documenting and keeping files of all complaints that it handles.
Third Stage - At Provincial People’s Committee (PPC): If after thirdty (30) days the
aggrieved AP does not hear from the DPC, or if the AP is not satisfied with the settlement
decision, the AP may bring the case, either in writing or verbal, to any member of the PPC.
The PPC shall have thirdty (30) days within which to resolve the complaint to the satisfaction
of all concerned. The PPC secretariat is also responsible for documenting and keeping file of
all complaints that it handles.
Final Stage - People’s Court: If after 30 days following the lodging of the complaint
with the PPC, the aggrieved AP does not hear from the PPC, or if he/she is not satisfied with
the settlement decision, the case may be brought to people’s courts. Under no circumstance, the AP will be evicted from his/her property or for the Government to take over his/her
property without the explicit permission of the people’s court.
Alll grievances and complaints of affected people on land acquisition, compensation
and resettlement will be resolve consistent with the above stages and complainants will not
shoulder any costs during grievance redress process.
Question 14: As a resident in the project area, how can I help?
Answer: We would like you to participate in all consultation meetings and other project
related activities in order to ensure that you are fully informed and consulted. Your active
participation during the detailed measurement survey (DMS) and implementation will allow
us to determine measures to mitigate impacts, to identify problems or potentials problems
and to identify ways of responding immediately to solve these problems.
Question 15: How will we know if the objectives of this project are met?
Answer: SPPMB will ensure internal monitoring all Project activities. In addition,
SPPMB will engage an independent external monitoring agency to conduct external
monitoring of resettlement activities during Project implementation. Every 6 months, the
independent monitoring agency will submit a report to SPPMB and ADB on resettlement
implementation progress. A post-resettlement impact evaluation will assess whether negative
impacts have been mitigated adequately and pre-project standards of living of APs have
been restored as a result of resettlement and the Project.
For further information and suggestions, please contact us to the following address:
Southern Vietnam Power Projects Management Board (SPPMB)
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 29
Tel: +84 822100 720
Fax: +84 83836 1096
Add: 610 Vo Van Kiet street, District 1, Ho Chi Minh City
Cu Chi District Compensation and Resettlement Board (DCSCC)
Tel: +84 38920001
Fax: +84 38920001
Add: Zone 7, Cu Chi township, Cu Chi District, Ho Chi Minh City
Hoc Mon District Compensation and Resettlement Board (DCSCC)
Tel: 08.37103933
Fax: 08. 37103933
Add: 36/2ª Nguyen Van Bua, Group 2, Xuan Thoi Son commune, Hoc Mon district
District 12 Compensation and Resettlement Board (DCSCC)
Tel: 08.37156031
Fax: 08.37156031
Add: No.1 Le Thi Rieng Street, Thoi An Ward, District 12
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 30
5.5 Appendix 5. Minutes of announcement mettings of compensation plan
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 31
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 32
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 33
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 34
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 35
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 36
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 37
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 38
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 39
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 40
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 41
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 42
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 43
5.6 Appendix 6. List of AHs who have received payment in advance
No. Name Tower
location Amount (VND) Commune
I Until the end of 2015
1 Đặng Phước Long 14 20,000,000 Tân Thạnh Đông
2 Phạm Văn Minh 27 150,000,000 Binh Mỹ
3 Nguyễn Thị Đào 28 200,000,000 Đông Thạnh
4 Nguyễn Văn Nhạn 30 30,000,000 Đông Thạnh
5 Lê Văn Cắt 32 30,000,000 Đông Thạnh
6 Trần Văn Út 33 100,000,000 Đông Thạnh
7 Huỳnh Văn Hít 34 150,000,000 Đông Thạnh
8 Trần Mỹ Dung 39 200,000,000 Thới Tam Thôn
9 Huỳnh Ngọc Tấn 1; 3A 144,688,000 -
10 Lâm Văn Đỗ 5 30,000,000 -
11 Đỗ Hòa 9 112,860,000 -
25 350,000,000 -
12 Trần Thị Phùng 48 170,000,000 -
13 Trần Văn Nhanh
49
40,000,000 -
14 Bùi Thị Én 29,260,000 -
15 Lê Thành Chung 110,000,000 -
16 Nguyễn Thị Cang
51
100,000,000 -
17 Trần Văn Hải 100,000,000 -
18 Nguyễn Văn Xuân 18,760,000 -
19 Trần Thị Nuôi 54 400,000,000 -
SUBTOTAL 2,485,568,000
II Until the end of the previous quarter
Củ Chi 882,090,000
1 Lê Văn Tùng 17;21 107,000,000 Bình Mỹ
2 Nguyễn Thị Mọng Điệp VT18 600,000,000 Tân Thạnh Đông
3 Đỗ Hòa VT19
4 Trần Thị Sáu VT16
5 Trần Thị Liễu 3,066,000 Bình Mỹ
6 Nguyễn Thị Yến Như VT13 18,024,000 Tân Phú Trung
7 Đặng Thị Nghễ VT17-21 130,000,000 Bình Mỹ
8 Trần Văn Đạo VT17-21 24,000,000 Bình Mỹ
Hốc Môn 4,608,000,000 -
1 Đặng Văn Trước VT37-47 100,000,000 Thới Tam Thôn
2 Nguyễn Văn Dũng VT29-37 3,000,000,000 Đông Thạnh
3 Nguyễn Văn Bền VT29-37 400,000,000 Đông Thạnh
4 Nguyễn Hữu Thắng VT29-37 228,000,000 Đông Thạnh
5 Phạm Văn Lức VT43
6 Nguyễn Văn Điệp VT41-43
7 Trần Văn Lo VT33
8 Đặng Trường Sơn VT29 880,000,000 Đông Thạnh
Quận 12 6,136,815,971 0
1 Bùi Đức Thành VT37-47 106,665,936 Tân Chánh Hiệp
2 Lưu Văn Nhẹ VT37-47 1,006,057,549 Tân Chánh Hiệp
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 44
No. Name Tower
location Amount (VND) Commune
3 Nguyễn Hữu Đồng VT37-47 78,247,250 Tân Chánh Hiệp
4 Thái Thị Hồng VT37-47 46,697,931 Tân Chánh Hiệp
5 Nguyễn Viết Ánh VT37-47 467,873,305 Tân Chánh Hiệp
6 Lương Văn Long VT37-47
7 Nguyễn Văn Triển VT37-47
8 Đỗ Văn Bắt VT37-47
9 Nguyễn Văn Trác VT37-47
10 Nguyễn Văn Điệp VT37-47
11 Huỳnh Thị Hoa VT37-47 530,000,000 Tân Thới Hiệp
12 Trần Viết Thắng VT47 58,274,000 Tân Thới Hiệp
13 Nguyễn Văn Giác VT46 2,600,000,000 Tân Thới Hiệp
14 Trịnh Xuân Bôn VT47-52 210,000,000 Tân Thới Hiệp
15 Nguyễn Minh Cương VT47-52 50,000,000 Tân Thới Hiệp
16 Trần Thị Cúc VT47-52 983,000,000 Tân Thới Hiệp
SUBTOTAL 11,626,905,971
III Until the end of this quarter
Củ Chi 2,100,000,000
1 Lê Văn Tùng 17;21 Bình Mỹ
2 Nguyễn Thị Mọng Điệp VT18 Tân Thạnh Đông
3 Đỗ Hòa VT19 400,000,000 Tân Thạnh Đông
4 Trần Thị Sáu VT16 1,700,000,000 Tân Thạnh Đông
5 Trần Thị Liễu Bình Mỹ
6 Nguyễn Thị Yến Như VT13 Tân Phú Trung
7 Đặng Thị Nghễ VT17-21 Bình Mỹ
8 Trần Văn Đạo VT17-21 Bình Mỹ
Hốc Môn 1,942,266,500 -
1 Đặng Văn Trước VT37-47 Thới Tam Thôn
2 Nguyễn Văn Dũng VT29-37 Đông Thạnh
3 Nguyễn Văn Bền VT29-37 Đông Thạnh
4 Nguyễn Hữu Thắng VT29-37 Đông Thạnh
5 Phạm Văn Lức VT43 359,266,500 Thới Tam Thôn
6 Nguyễn Văn Điệp VT41-43 1,280,000,000 Thới Tam Thôn
7 Trần Văn Lo VT33 303,000,000 Đông Thạnh
8 Đặng Trường Sơn VT29 Đông Thạnh
Quận 12 3,112,132,896 0
1 Bùi Đức Thành VT37-47 Tân Chánh Hiệp
2 Lưu Văn Nhẹ VT37-47 Tân Chánh Hiệp
3 Nguyễn Hữu Đồng VT37-47 Tân Chánh Hiệp
4 Thái Thị Hồng VT37-47 Tân Chánh Hiệp
5 Nguyễn Viết Ánh VT37-47 Tân Chánh Hiệp
6 Lương Văn Long VT37-47 116,712,896 Tân Chánh Hiệp
7 Nguyễn Văn Triển VT37-47 30,000,000 Tân Chánh Hiệp
8 Đỗ Văn Bắt VT37-47 430,141,000 Tân Thới Hiệp
9 Nguyễn Văn Trác VT37-47 55,279,000 Tân Thới Hiệp
Semi-annual Internal Monitoring Report - July 2016
Cau Bong - Hoc Mon - Binh Tan 220kV Transmission Line Project 45
No. Name Tower
location Amount (VND) Commune
10 Nguyễn Văn Điệp VT37-47 2,480,000,000 Tân Thới Hiệp
11 Huỳnh Thị Hoa VT37-47 Tân Thới Hiệp
12 Trần Viết Thắng VT47 Tân Thới Hiệp
13 Nguyễn Văn Giác VT46 Tân Thới Hiệp
14 Trịnh Xuân Bôn VT47-52 Tân Thới Hiệp
15 Nguyễn Minh Cương VT47-52 Tân Thới Hiệp
16 Trần Thị Cúc VT47-52 Tân Thới Hiệp
SUBTOTAL 7,154,399,396
TOTAL 18,154,740,471
Semi-annual Internal Monitoring Report - July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 46
5.7 Appendix 7. Decision on approving of adjustment coefficient plan of land price for
calculating compensation, support for AHs
Semi-annual Internal Monitoring Report - July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 47
Semi-annual Internal Monitoring Report - July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 48
Semi-annual Internal Monitoring Report - July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 49
Semi-annual Internal Monitoring Report - July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 50
Semi-annual Internal Monitoring Report - July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 51
Semi-annual Internal Monitoring Report - July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 52
Semi-annual Internal Monitoring Report - July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 53
Semi-annual Internal Monitoring Report - July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 54
Semi-annual Internal Monitoring Report - July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 55
5.8 Appendix 8. Decision on approving of compensation plan, section through Cu Chi
District
Semi-annual Internal Monitoring Report - July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 56
Semi-annual Internal Monitoring Report - July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 57
Semi-annual Internal Monitoring Report - July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 58
Semi-annual Internal Monitoring Report - July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 59
Semi-annual Internal Monitoring Report - July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 60
Semi-annual Internal Monitoring Report - July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 61
Semi-annual Internal Monitoring Report - July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 62
5.9 Appendix 9. Some pictures from Public Consultation Meetings
Tan Phu Trung Commune
Tan Thanh Dong Commune
Semi-annual Internal Monitoring Report - July 2016
Cau Bong – Hoc Mon – Binh Tan 220kV Transmission Line Project 63
Binh My Commune
Thoi Tam Thon Commune