vdot’s p3 approach to the midtown...

71
VDOT’s P3 Approach to the Midtown Tunnel Presented to: ODU/CEECV Spring 2012 Seminar, May 3, 2012 ODU/CEECV Spring 2012 Seminar, May 3, 2012 Presented by: Frank Fabian, P.E., Senior Project Manager, Virginia Department of Transportation Fred Parkinson, P.E., S.E., DBIA, Vice President, Parsons Brinckerhoff, Inc.

Upload: lamhuong

Post on 03-Apr-2018

217 views

Category:

Documents


2 download

TRANSCRIPT

VDOT’s P3 Approach to the Midtown TunnelPresented to:

ODU/CEECV Spring 2012 Seminar, May 3, 2012ODU/CEECV Spring 2012 Seminar, May 3, 2012

Presented by:

Frank Fabian, P.E., Senior Project Manager, Virginia Department of Transportation

Fred Parkinson, P.E., S.E., DBIA, Vice President,Parsons Brinckerhoff, Inc.

1VDOT P-3 PROCESS

1VDOT P 3 PROCESS

2

PPTA ACT of 1995

• Public-Private Transportation ACT (PPTA) passed in 1995 to allow

Virginia to leverage private dollars for public projects

• Allows innovative project delivery techniques to be used to bring

projects to Virginia faster and potentially cheaper than through

ti lconventional sources.

• Collapses project development process to allow multi-tasking

• Risk sharing between the Developer and VDOT

3

PPTA ACT of 1995

Typical Funding Sources:

• Bonds (PAB, GARVEE or other)

• TIFIA grants or loans

• Tolls

• Conventional FHWA/VDOT funding

• Development rightsp g

4

Virginia’s P3 Project Portfolio

Virginia’s Candidate P3 Projects

P t ti l C did t P3 j t■ Potential Candidate P3 projects

– Six-Year Improvement Program (VDOT / VDRPT)

– Virginia Surface Transportation Plan (statewide)g p ( )

– MPO Vision Plans (statewide)

– Governor’s PPTA Priorities

– Legislative Mandate

– Virginia Port Authority Master Plan

Si Y Ai t C it l I t Pl– Six-Year Airport Capital Improvement Plan

Virginia’s P3 Program

P j t P j t S i P j t P j tProject Identification

Project Screeningand Prioritization

Project Development

Project Procurement

• Two primary sources – • Organized in two • Two-stage competitive • Prepare project for p ySolicited Projects and Unsolicited Projects

• Coordination with multiple sources for candidate P3 projects

gphases - high-level screening and detail-level screening followed by the prioritization

g pprocurement process

• Develop procurement documents

• Conduct procurement process

p p jprocurement with assistance from relevant disciplines within the Agencies

• Coordinate project

• P3 Office, in coordination with sponsoring agency, manage project identification process

• Systematic and consistent application of evaluation criteria to candidate projects

• Assists P3 Office with determination of

process

• Update Value for Money Analysis

• Select Preferred Proposer

development activities, (scope, design concept and schedule; obtain regulatory approvals; update cost estimates; conduct initial VfM; determination of

suitability delivering projects under the PPTA

• Finalize Contract

• Award Contract

determine procurement method)

Virginia's P3 Project Delivery Framework

Solicited/Planned Projects

Unsolicited Projects

Proj

ect

Iden

tific

atio

n

High-Level Screening Policy Review

Detail-Level S i

Detail-Level S i

Decision Point 1

and

Prio

ritiz

atio

n

Screening Screening

Project Prioritization

Decision Point 2

Proj

ect S

cree

ning

Project Development

Decision Point 3

Proj

ect

Dev

elop

men

t

Project Procurement

Decision Points 4 & 5

ojec

t Pro

cure

men

t

Contract Award Pro

Responsibilityp yOTP3VDOT

C t l OffiPre- Comprehensive

Central Office Agreement

VDOT DistrictPost Comprehensive

Agreement

Project Delivery

Concessionaire

9

Hampton Roads District Special Projects (SP) SectionSpecial Projects (SP) Section

SPProject

Mgr

Frank Fabian, PEREVISION December 2011

Frank Fabian, PE

AdminAssistant

Lynette Guy, MBA

A t PM

Route 4603 VDOT Staff

Shared Services7 VDOT Staff

MT / DT / MLK3 VDOT Staff

Public AffairsCo-ord

Vacant

CivilRightsOfficer

Vacant

Asst PMConst Mgr

Warren Bixler, PE

Asst PMConst Mgr

Vacant

PE Required

Account

Deanna Davenport, MA

ROWCo-ord

Vacant

TunnelInspectCo-ord

Vacant

PE Required

TrafficEng

BradleyWeidenhammer, PE

ConsultSupportServices

STP

ConsultSupportServices

HDR

EnvironOfficer

Vacant

BridgeInspectCo-ord

Vacant

PE Required

Utilities

Vacant

BridgeInspectCo-ord

Vacant

PE Required

RoadwayInspectCo-ord

Vacant

PE RequiredPE Required PE Required PE Required PE Required

22

DT/MT/MLK PROJECT OVERVIEWDT/MT/MLK PROJECT OVERVIEW

11

Project Overview

New, parallel two-lane tunnel Brambleton Avenue

Hampton Bo le a dHampton Boulevard interchange modificationsRefurbishment and

safety improvements

Extending MLK toExtending MLK to I-264, High St interchange

Refurbishment and safety improvements

12

The Midtown Team

Owner – Virginia Department of Transportation (VDOT)

Stakeholders – Federal Highway Administration (FHWA)U.S. Navy Cities of Portsmouth and NorfolkVirginia Port AuthorityBusinesses and Citizens of the Commonwealth

Consultant Southeastern Transportation Partners (STP)Consultant – Southeastern Transportation Partners (STP) JV: Parsons Transportation Group (PTG) and

Rummel, Klepper & Kahl (RK&K)

Subs: Athavale Lystad & Assoc. Business Transf Group Capita Symonds Continental Field Services,GET Solutions GZA Geo EnvHBA Arch Keville EntKimley-Horn MBPNXL Seventh Point

13

The Midtown Team

Developer – Elizabeth River Crossings (ERC)g ( )• JV of Skanska ID and Macquarie Capital

Design/Builder – a JV between:• Skanska SE (45%) • Kiewit (40%) • Weeks (15%)

Design Team – Parsons Brinckerhoff (Tunnel)Volkert (MLK Civil/Structural)Schnabel (MLK Geotech)PMI (Survey)

• Seven Subconsultants

14

Value to the RegiongReduces congestion and travel time

R d idl i i f l dReduces idle time, saving fuel and lowering emissions

Creates seamless connection to I-264Creates seamless connection to I-264

Extends useful life of existing tunnels

Ends bi-directional traffic in Midtown Tunnel

Improves reliability and connectivity

Enhanced public transportation i d il bl th h

15

services made available through partnership with Hampton Roads Transit

Value Beyond Traffic Imp o ementsImprovements

Direct Promotes Local Job

Over $1 billion in $170 to $254 million Over 500

Direct Economic Stimulus

Promotes Economic Development

Local JobCreation

Over $1 billion in construction worksBuilt by local companiesBuilt by local labor

$170 to $254 million increase in regional productivity1

Long-term economic development

Over 500 construction jobs directly createdOver 1000 jobs indirectly createdBuilt by local labor

Utilizes local suppliers and contractors

developmentAccess to 2,000 more jobs2

Local projects can be prioritized

indirectly created200 facilities maintenance and operations jobsSmall womenbe prioritized Small, women, minority owned business involvementApprenticeship

16

Apprenticeship Programs

(1), (2) Source: The Hartgen Group

Project Development Timeline j p

Timetable

M 2008C ll f C t l P l

September 2008Conceptual Proposal Submittal

March to June 2009Public Hearings – Independent Review Panel

May 2008Call for Conceptual Proposals

July 2009Positive CTB RecommendationOctober 2009Key Business Points Presented to CTB

January 2010Signature of Interim Agreement

July 2011

January 2011Comprehensive Agreement Negotiations Begin

December 2011Comprehensive Agreement

Key Business Terms Agreed

April 13, 2012Financial Close

Construction Starts Q3/Q4 2012

2013 2014

17

2013-2014Tolling Commences

Construction Final Acceptance Q2 2018

Key Business Termsy

Value of Comprehensive Tunnels 58 Y

InvestmentEZ PassTolls Terms

Value of ComprehensiveAgreement is $2.1 billion

ERC to finance design

TunnelsAuto off-peak: $1.59; Peak: $1.84Truck off-peak: $4 77 P k $7 36

58 Years

ERC to finance, design,build, operate andmaintain facilities

ERC to provide $1 7

$4.77; Peak: $7.36

MLK Extension$0.50 for tunnel ERC to provide $1.7

billion investment

Commonwealth providing contribution

users$1.00 for non-tunnel users

1818

providing contributionof $308 million tospecifically lower toll

3PROJECT DEVELOPMENT AND

3PROJECT DEVELOPMENT AND CONSTRUCTION

19

CONSTRUCTION WORK STREAMSCONSTRUCTION WORK STREAMS

4321

NEW TUNNEL TUNNEL APPROACHES MLK EXTENSION EXIST TUNNEL REHAB

Dredging SOE Site Prep Structural

F b i ti Pili E ti & Pili M h i lFabrication Piling Excavation & Piling Mechanical

Delivery Construct/Cast-in-Place Foundations Electrical

Immersion Fill Substructures NFPA 502

Fill Access/Roadway Superstructure Communications/SecurityFill Access/Roadway Superstructure Communications/Security

M & E/Safety Finishes Finishes

Communications/Security

Finishes

20

Mar 2012

Dec 2011 Dec 2016

1. New TunnelSep 2016

Dec 2011

54 Months

* Per Initial BL ScheduleJune 2015

2. Approaches

eam

s

NTP/Design

Const

Aug 2012

Mar 2015

43 Months

e t a Sc edu e

3. MLKWor

k St

re Const.

Final AcceptanceAug 2012

Dec 2011 Dec 2016

61 Months3. MLKW Sep 2016

Jul 2013 Jul 2016 Sep 2016 Apr 2018

DTT MTT

4. Tunnel RehabApr 2016 Jan 2018

33 Months 16 Months

DTT MTT

2012 2014 2018

21

20132012 201620152014 2017 2018 20192011

Project Challenges

Structural Other

Adjacency to exist. tunnel

Soft and variable soils

Dredge disposal sites

Maintenance of marine

120-year design life

Element b o anc

traffic

Environmental – i.e. oysterbeds

Element buoyancy

Strict leakage criteriaChannel crossing utilities

Rehab tunnels constructed in Underwater placement of elements

1952, 1962 and 1982

22

Midtown Tunnel AlignmentMidtown Tunnel Alignment

23Norfolk Portals Portsmouth Portals

Midtown Tunnel Pl d P filPlan and Profile

24

Barge Sequence NomenclatureBarge Sequence Nomenclature

Dredge Barge

Screed Barge

Lay Barge

Fill Barge

25

4DREDGING AND BED PREPARATION

4DREDGING AND BED PREPARATION(DREDGE AND SCREED BARGE)

26

DredgingDredging

ClamshellApproximately 1 582 MCYApproximately 1.582 MCYHauled to landfill/offshore di ldisposal

27

Dredging ‘Obstacles’g g

28

Dredging and Prep WorkDredging and Prep Work

29

Midtown TunnelMidtown Tunnel Norfolk Dredging

30

Screed Barge, Crane g ,and Sand Scow

31

Place Foundation CoursePlace Foundation Course

FoundationFoundation Course

Displacement Piles (3 Elements onl )(3 Elements only)

32

How a Screed Barge WorksHow a Screed Barge Works

33

5TUNNEL STRUCTURE

5TUNNEL STRUCTURE FABRICATION AND DELIVERY

34

Sparrows Point DockSparrows Point Dock

35

Typical Bar Mat in Roofyp

36

Construction Sequenceq

37

Elements Constructedin Graving Dockin Graving Dock

38

Ballast Tanks(note ProMat)

39

Ready for Float-Outy

40

Towingg

41

Tow Down the Bay200 il200 miles

SparrowsSparrowsSparrows Sparrows PointPoint

MTTMTT

42

6TUBE IMMERSION

6TUBE IMMERSION (LAY BARGE)

43

Sequence of ITT Elements

PORTSMOUTH NORFOLK

3760’

1

2

3 9

10

11

C&C STA 90+01.50 C&C STA 127+60.78

3

4

5 6 7

8

9

PVI STA 103+31.69PGL EL. -84.07’

PVI STA 113+99.57PGL EL. -85.11’

PVI STA 109+69.63PGL EL. -87.26’

4 EA @ 332.5’ 3 EA @ 356’ 4 EA @ 340.5’

44

Element Immersion

45

Tube Placement - EquipmentTube Placement Equipment

Catamaran Lay BargeH i t l li tHorizontal alignment controlled by anchor

winches attached to the Lay Barge

46

Element Placed on BeddingElement Placed on Bedding

47

7BACKFILL

7BACKFILL(FILL BARGE)

48

Locking Fill by Tremie Pipes

Locking Fillg

Place 61,000 yardsof Locking Fill

50

Place Ordinary Fill and yArmor Stone

39 000 tons

555,000 yards of Ordinary Fill

39,000 tons Armor Stone

23,000 tons of Ordinary Fill Anchor Bands

51

8WATERTIGHTNESS AND

8WATERTIGHTNESS AND FINISHES

52

Gina Joint Prior to De-wateringGina Joint Prior to De watering

53

Tubes Brought Together

Dewatering compresses the Gina Gasket

Water between Bulkheads

After Dewatering

Omega Seal is Secondary Seal

Remove BulkheadRemove Bulkhead

56

Making the Connection Between Elements

57

Install Fans and FinishesInstall Fans and Finishes

58

9MIDTOWN TUNNEL

9MIDTOWN TUNNEL SAFETY SYSTEMS

59

State of the Art Safety SystemsState of the Art Safety Systems

Separate escape corridorSeparate escape corridor

Jet fans

Deluge system

Fire sensors

Fire alarms/extinguishers/ hose connections

Motorist aid phones

Fireproofing

Full camera surveillanceFull camera surveillance

60

Tunnel Safety SystemsTunnel Safety Systems

61

Fire Heat Release RateFire Heat Release Rate

Ultrafast Fire Growth Curve per NFPA 92B

62

Simulation ResultslAir Velocities

1 5 0 ft D o w n s tream o f Je t F an

U V e lo c ity

4 03 53 02 52 0

A t Je t F an O u tle t

(fp s )

ght(

ft)1 5

ght(

ft)1 5

2 01 91 81 71 61 51 4

Tunn

elH

eig

5

1 0

Tunn

elH

eig

5

1 0 1 31 21 11 0987

T u n n e l W id th (ft)

01 02 03 00

T u n n e l W id th (ft)

01 02 03 00

76543210

63

0

L o n g itu d in a l V e lo c ity C o n to u rsJe t F an s L o ca ted 3 ,6 0 0 ft fro m P o rta l

63

Backlayering Results(Plan View @ 15 feet)

2 5 02 5 0 F IR E @ 2 5 0 ft 2 5 02 5 0 F IR E @ 2 5 0 ft

2 2 0

2 3 0

2 4 0

2 2 0

2 3 0

2 4 0@

2 2 0

2 3 0

2 4 0

2 2 0

2 3 0

2 4 0@

1 8 0

1 9 0

2 0 0

2 1 0

1 8 0

1 9 0

2 0 0

2 1 0

1 8 0

1 9 0

2 0 0

2 1 0

1 8 0

1 9 0

2 0 0

2 1 0

X

1 5 0

1 6 0

1 7 0

1 8 0

1 5 0

1 6 0

1 7 0

1 8 0

X

1 5 0

1 6 0

1 7 0

1 8 0

1 5 0

1 6 0

1 7 0

1 8 0

1 2 0

1 3 0

1 4 0

1 2 0

1 3 0

1 4 0

1 2 0

1 3 0

1 4 0

1 2 0

1 3 0

1 4 0

641 0 0

1 1 0

1 0 0

1 1 0

01 02 03 0 3 0 0 lb f je t fa n s1 0 0

1 1 0

1 0 0

1 1 0

01 02 03 0 3 5 0 lb f je t fa n s 64

10MLK EXPRESSWAY

10MLK EXPRESSWAY

65

MLK Expressway Alignment p y g

Ramp ENp

Ramp SW

Ramp SE

66

MLK Expressway Alignmentp y g

High Street

New MLK Extension

London Boulevard

Start Construction

67

Context Sensitive Designg

68

How will tolls be collected?

All Electronic TollingD t ti & Cl ifi ti

License Plate C

An All Electronic Toll Gantry Example

Tolls can be paid via E-ZPass®

or by invoiceE-ZPass® is an automatic, electronic

Detection & Classification Camera

toll collection system that efficiently moves traffic through toll facilities and is used in 14 states, including Virginia

If a driver does not have E-ZPass®, an invoice will be mailed to them

Invoiced customers will be charged for cost recovery which by Virginia law iscost recovery, which by Virginia law is capped at two times base toll rate.

Payment can be made by mail, online or telephone

AntennaE Zpass®

69

AntennaE-Zpass® Transponder

11Q & A

11Q & A

70

Where to get more Info mation

Find out more about the project:

Information

p jwww.MidtownTunnel.org

VDOT Contact information:Dennis Heuer, P.E., D.B.I.A.District Administrator, Hampton Roads District [email protected]

Frank Fabian, P.E., Senior Project [email protected]

Developer Information:www.ERC-Info.com

ERC Contact information:Greg Woodsmall, ERC, O&M

71

[email protected]