user training manual_ps_tp_end user v1.2 final1
DESCRIPTION
user trainingTRANSCRIPT
![Page 1: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/1.jpg)
BSNL
User ManualProject System
Transmission ProjectsReference Business Process No.-
BSNL_BBP_PS_TP
Version:1.2
25.03.2011
![Page 2: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/2.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
Version Control
Date Version Author Change Description0.1 Gaurav Verma Draft 0.2 Rajeev Sharma Review1.0 Rajesh Jain/Rajeev
Sharma/Gaurav Verma/Pawan Yadav
Final Submission and agreement
1.1 Abhinav Bhalla Updated CE fields1.2 Nimish Goswamy/Abhinav
BhallaReview and update after FIT
The document has been prepared to be used by the following stake-holders:
End Users Performing day to day transactions as per their Roles and Authorizations in SAP System.
Core Team – Directly involved in the Projects and supporting the various activities in Project Phases
Business Process Owners – Respective Business Leaders, involved in validating the process design.
Important Note:
The information in this document is only meant to be a reference for ERP Process configured as per the Business Process approved by BSNL Management for Project System Module and is not a complete description of the SAP product and its functionalities. Its main purpose is to serve as a
reference Document for User Training and Support.
Page 1 of 107
![Page 3: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/3.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
Course OverviewSAP Project System supports comprehensive functions for planning, controlling and organizing all the
activities carried out during the course of a project. It helps you manage your project structures, dates,
costs, and resources throughout the entire project lifecycle. Course provides you with an overview of the
functions in SAP Project System.
Target Audience
This course is intended for the following audiences:
Project managers Project team members Consultants
Course Prerequisites
Knowledge of navigating SAP systems Basic knowledge of project management
Course Goals
This course will prepare you to:
Discuss the basic functions of SAP Project System for RTPC MOM Discuss the basic functions of SAP Project System for structuring, planning, executing,
and monitoring projects
Course Objectives
After completing this course, you will be able to:
Upload and Review RTPC MOM in SAP System Use work breakdown structures, activities, and networks to structure projects Discuss aspects of planning dates, resources, materials, costs, and revenues Name the functions used for budgeting Explain aspects and processes used for executing projects
Page 2 of 107
![Page 4: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/4.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
Explain various period-end closing activities in Project Management Use reporting options for monitoring project data
Table of Contents
1. UPLOAD AND READ RTPC MOM..................................................................................................9
2. SEARCH THE PROJECT LIST ON THE BASIS OF SELECTION CRITERIA.......................13
3. CREATE OPERATIVE PROJECT DEFINITION & WBS............................................................16
4. SEND WBS ELEMENT FOR DETAILING / SURVEY USING NOTE SHEET......................27
5. READ NOTE SHEET RECEIVED IN THE SAP INBOX.............................................................28
6. CREATE & ASSIGN SURVEY REPORT TO THE PROJECT....................................................29
7. CREATE & ASSIGN PROJECT RELATED DRAWINGS TO THE PROJECT........................31
8. APPROVE / RELEASE PROJECT RELATED DRAWINGS.......................................................35
9. UPDATE THE WBS STATUS TO SURVEY DONE....................................................................37
10. SEND WBS FOR SURVEY APPROVAL TO COMPETENT AUTHORITY............................38
11. RELEASE SURVEY REPORT FOR THE PROJECT....................................................................44
12. UPDATE THE WBS STATUS TO SURVEY APPROVED (SRVA).........................................46
13. CREATE PROJECT CUM DETAILED ESTIMATE.......................................................................48
14. ASSIGN INTERNAL ACTIVITY.......................................................................................................50
15. ASSIGN MATERIAL TO AN INTERNAL ACTIVITY..................................................................51
16. ASSIGN & EXPLODE BILL OF MATERIALS..............................................................................54
17. ASSIGN SERVICE ACTIVITY..........................................................................................................58
18. ASSIGN GENERAL COST ACTIVITY............................................................................................60
19. DEFINE RELATIONSHIP BETWEEN ACTIVITIES....................................................................61
20. ATTACH MILESTONE TO AN ACTIVITY....................................................................................63
21. ATTACH MILESTONE TO A WBS ELEMENT............................................................................64
22. PROJECT SCHEDULING.................................................................................................................. 65
Page 3 of 107
![Page 5: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/5.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
23. UPDATE THE WBS STATUS TO PE CUM DE CREATED......................................................67
24. SEND WBS FOR PE CUM DE APPROVAL TO COMPETENT AUTHORITY USING NOTE SHEET............................................................................................................................................... 68
25. READ NOTE SHEET RECEIVED IN THE SAP INBOX.............................................................70
26. REVIEW PROJECT ESTIMATE.......................................................................................................71
27. UPDATE THE WBS STATUS TO PE CUM DE CONCURRED (PEFI)..................................72
28. UPDATE THE WBS STATUS TO PE CUM DE APPROVED...................................................73
29. VIEW APPROVED PE/DE/RE PDF DOCUMENTS....................................................................74
30. LINK WBS ELEMENT TO AN INVESTMENT PROGRAM POSITION.................................76
31. BUDGET DISTRIBUTION TO THE PROJECT.............................................................................76
32. PLAN FOR PROJECT WISE ACTIVITIES (SKF – STATISTICAL KEY FIGURE)...............76
33. UPDATE THE SYSTEM STATUS OF A WBS ELEMENT TO RELEASED...........................77
34. UPDATE THE SYSTEM STATUS OF A NETWORK TO RELEASED....................................79
35. POST ACTUAL SKF DURING THE PROJECT EXECUTION PHASE....................................80
36. UPDATE THE WBS STATUS TO REVISED ESTIMATE CREATED.....................................81
37. UPDATE THE WBS STATUS TO REVISED ESTIMATE FI CONCURRED.........................82
38. UPDATE THE WBS STATUS TO REVISED ESTIMATE APPROVED..................................83
39. ACTIVITY CONFIRMATION............................................................................................................85
40. MILESTONE CONFIRMATION ASSIGNED TO A WBS ELEMENT......................................87
41. MILESTONE CONFIRMATION ASSIGNED TO AN ACTIVITY..............................................87
42. UPDATE THE WBS STATUS TO OFFERED FOR AT..............................................................89
43. UPDATE THE WBS STATUS TO LIST OF PENDING POINTS / SHORTCOMING FROM AT (IF ANY)................................................................................................................................................. 90
44. UPDATE THE WBS STATUS TO CLEARANCE OF PENDING POINTS (IF ANY)...........91
45. UPDATE THE WBS STATUS TO RELAXATION FOR PENDING POINTS NOT CLEARED (IF ANY)................................................................................................................................... 93
46. UPDATE THE WBS STATUS TO PROVISIONALLY FIT FOR COMMISSIONING..........94
Page 4 of 107
![Page 6: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/6.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
47. UPDATE THE WBS STATUS TO DECLARED FIT FOR COMMISSIONING......................95
48. UPDATE THE STATUS OF A WBS ELEMENT TO TECO (TECHNICALLY COMPLETE)96
49. UPDATE THE STATUS OF A NETWORK TO TECO (TECHNICALLY COMPLETE)........97
50. UPDATE THE WBS STATUS TO COMMISSIONING DONE.................................................98
51. ENTER DETAILS AFTER UPDATE OF STATUS COMMISSIONING DONE......................99
52. SETTLEMENT OF NETWORK TO WBS ELEMENT................................................................101
53. UPDATE THE WBS STATUS TO OFFERED FOR TAKING OVER.....................................103
54. UPDATE THE WBS STATUS TO TAKEN OVER.....................................................................104
55. UPDATE THE SYSTEM STATUS OF A WBS ELEMENT TO CLOSED..............................105
56. TRANSACTIONS FOR PROJECT MONITORING:-..................................................................106
Page 5 of 107
![Page 7: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/7.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
OVERVIEW
SAP Project System supports comprehensive business Process for Planning, Controlling & Organizing all the activities carried out during the course of a Project. It helps you to manage your Project structure, dates, cost & task throughout the entire Project lifecycle.
Western Telecom Projects is responsible for planning, survey and execution of various long distance Telecom Transmission Projects and Switching Projects for building up National Telecom Infrastructure in different Zone for Optical Fiber Cable system, Digital Microwave, Trunk Automatic Exchange (TAX) and Satellite based communication systems in entire Western part of the country which includes states of
Maharashtra
Gujarat
Madhya Pradesh
Chattisgarh
Goa
Important information to be noted:-
All documents are to be created in reference to the preceding document. All SAP Transactions can be executed either by navigating to the required
Transaction through the Menu Path or by simply entering the Transaction Code for the respective Transaction in the Command Field.
Page 6 of 107
![Page 8: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/8.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
1. Upload and Read RTPC MOM
Create Document CV01N
Menu path Logistics Project System Document Management SystemDocument Create
Transaction CV01N
1. Enter the Required details:Document Type: ZPDDocument Part: 000Document Version: 00
Page 7 of 107
![Page 9: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/9.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
2. Enter the Document Description and click the tab
Page 8 of 107
![Page 10: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/10.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
3. Select the Class “Project Details” and select the Characteristics “Approval Channel” and
4. Press to go back to initial screen.
Page 9 of 107
![Page 11: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/11.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
5. On the initial Screen Press to attach the document(Word/Excel File), which contains the list of projects.
6. Press to save the document in DMS.
7. If this screen appears, select the “Vault” radio button.
8. And press to finally save the document.
Page 10 of 107
![Page 12: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/12.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
2. Search the Project List on the basis of Selection Criteria
Change Document CV02N
Menu path Logistics Project System Document Management SystemDocumentChange
Transaction CV02N
1. Select the search criteria “Find document Via Class”
Page 11 of 107
![Page 13: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/13.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
2. Enter the class name “Project_Details”
3. Select the “Approval Channel” and click on
Page 12 of 107
![Page 14: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/14.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
NOTE: The system will give the list of documents on the search criteria.
4. Open the document by double clicking it and see the List of projects by opening the attached file in it.
5. Click on Send to send the list of Approved projects to the person concerned
6. Enter details in the space provided.
7. Enter the name/User ID of the person to whom message is to be sent.
Page 13 of 107
![Page 15: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/15.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
8. Enter the name/User ID of a person to whom message is to be sent.
9. Click on .
3. Create Operative Project Definition & WBS
Project Definition: Project Definition is a binding framework in SAP for all Organizational Elements created within a Project (e.g. WBS and SAP Networks). Data like Company Code, Plant and Person Responsible can be defaulted in a WBS Element if it is initially entered in the Project Definition.
WBS: Work breakdown structure (WBS) is a model of the Project that organizes Project tasks into a hierarchy. It forms the operative basis for planning Costs, Revenues, and Payments, as well as for Scheduling, and Budgeting.
Page 14 of 107
![Page 16: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/16.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
Following steps shall be followed to create a Project:
Create Project CJ01
Menu path Logistics Project system Project Special Maintenance function Work Break Down Structure(WBS)Create
Transaction CJ01
1. Click on open number (Refer Fig. below)
2. Enter the appropriate coding mask (For example TP/11/00001) for Project
Definition in the Start value. Definition-Open Number-This is the free
number available in the System.
3. Press Find to use the proposed Project Definition by the system.
4. Click on copy or Press Enter.
(Note: Please use Project Coding Mask TP/11/00001 for
Financial Year 2011-12)
Page 15 of 107
![Page 17: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/17.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
5. Select Project profile: BSNL_TP Transmission Projects (Fig. below)
(Project profile: This contains default values and control parameters for
processing objects and functions in the Project System)
Page 16 of 107
Click on Open Number
Select the Project Profile
![Page 18: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/18.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
6. If you want to copy an existing Project, enter the Project Definition /
Standard Project Definition (Project to be copied) in the Template section
(Refer Fig. below)
7. Press Enter or Click on
8. Enter description/Short text for Project
9. Click on the Basic data tab (Organization section) and,
Enter Company Code; Business Area & Plant (Refer Fig.) For Example:
Field Description
Remarks
Person Responsible
Enter the Person Responsible
Start Date Enter the Start date of ProjectFinish Date Enter the Planned finish date of ProjectCompany Code Select the relevant Project circleBusiness area Select the Project AreaPlant Select the relevant Plant
Page 17 of 107
Description field is mandatory
![Page 19: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/19.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
10. Click on Details –> Project Definition customer fields & enter the data
Open the below file to view the Project Definition Customer Fields;
11.Click on WBS Element Overview
Page 18 of 107
![Page 20: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/20.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
Note: Above Screen will appear when the new project is created by copying the existing project.
12. Deselect the line which is not required as per the project structure of
current project
13. Click on replace button,
Page 19 of 107
![Page 21: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/21.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
14. A pop up screen will appear, mention the last two digit of the project
which is to be copied in Search and last two digit of the new project
number.
15. Click on Include button.
16. Ensure that the PE (Planning Element) indicator is ticked for all the
WBS Elements (Except for the Level 1, Level 2 WBS Elements)
(Definition-Planning Element: An Element of a work breakdown structure for which costs can be planned)
If this indicator is un-ticked for a particular WBS Element, system will not allow cost planning for that WBS Element.
17. Ensure that the Acct (Account Assignment Element) indicator is ticked
for all the WBS Elements (Except for the Level 1, Level 2 WBS Elements)
Page 20 of 107
![Page 22: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/22.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
(Definition-Account Assignment Element: An Element of a work breakdown structure on which Actual Costs can be posted)
If this is un-ticked for a particular WBS Element, system will not allow Posting of actual cost on that WBS Element.
18. Select the respective WBS & click on at the bottom left corner.
Select the relevant Project Type & Person Responsible.
Page 21 of 107
Account Assignment Indicator
Planning Indicator
Project Type
![Page 23: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/23.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
19. Now, Click on the Dates Tab. Enter the Basic start & Basic Finish Dates
for the WBS Element.
Page 22 of 107
![Page 24: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/24.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
20. Click on or press Enter.
21. Click on DetailsWBS Element Customer Fields
Page 23 of 107
![Page 25: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/25.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
22. Click on to the below file to view the WBS Element Customer Fields.
23. Save the Project .
Note: WBS Element Customer Fields are to be filled for each WBS mentioned in the Project.
Change Project CJ02
Menu path Logistics Project system Project Special Maintenance function Work Break Down Structure(WBS)Change
Transaction CJ02
For making any changes in the parameters once the Project is created the above menu path OR the Transaction is to be used.
Display Project CJ03
Menu path Logistics Project system Project Special Maintenance function Work Break Down Structure(WBS)Display
Transaction CJ03
Page 24 of 107
![Page 26: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/26.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
4. Send WBS Element for Detailing / Survey using Note Sheet
CJ02 / ZPS_NOTESHEET
1. Select the WBS element & Click on details –WBS Element Customer fields
2 Click on Create Note sheet button
3 Enter the WBS element and employee id of the person to whom the note sheet is to be sent.
Page 25 of 107
![Page 27: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/27.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
In the Comment box add/see the comments and press
If you want to see the details of the WBS element in edit mode press .
If you want to see the details of the WBS element in display mode press
If you want to see the document attached to the WBS Element press
If you want to print the Note sheet press
To see the Planned / Actual cost of the WBS element press
To approve the Project Estimate (PE) press .
This button should be used by the Competent authority, at the Root WBS Element, to approve the PE of all WBS Elements in a single shot.
Note: Project Estimate shall be approved by the competent authority.
Alternatively you can use the T-Code “ZPS_NOTESHEET” to open the note sheet.
5. Read Note Sheet received in the SAP Inbox
Read Note Sheet SBWP
Menu path Office Workplace
Transaction SBWP
1. Click on Inbox icon
2. Click on the
Note: The note sheet screen will appear. Add the details and forward it to next level, as explained in the Step 4.
Page 26 of 107
![Page 28: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/28.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
6. Create & Assign Survey Report to the Project
Create Document CV01N
Menu path Logistics Project system Documents Document Management System Document Create
Transaction CV01N
1. On the entry screen, enter the Document Type ZPD2. Enter the Document version3. Press Enter
4. Enter the Description of the document.
Page 27 of 107
![Page 29: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/29.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
5. Click on Open Original button & browse the File to be attached.
6. File will be attached as shown below
Page 28 of 107
![Page 30: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/30.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
7. To assign the document to a WBS Element, click on the Object Links tab and then go to the WBS Element Tab. Enter the WBS Element No. and press enter.
8. Save the document .The Document number will be generated. Note down the number.
7. Create & assign Project related drawings to the Project
Create Document SBWP
Menu path Logistics Project system Documents Document Management System Document Create
Transaction CV01N
1. On the entry screen, enter the Document Type e.g. ZCD /ZED (Civil / Electrical Drawings).
2. Enter the Document version.3. Press Enter.
Page 29 of 107
![Page 31: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/31.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
4. Enter the Description of the document.
Page 30 of 107
![Page 32: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/32.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
5. Click on Open Original button & browse the File to be attached.
Page 31 of 107
![Page 33: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/33.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
6. File will be attached as shown below.
7. To assign the document to a WBS Element, click on the Object Links tab and then go to the WBS Element Tab. Enter the WBS Element No. and press enter.
Page 32 of 107
![Page 34: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/34.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
8. Save the document. An internal no. will be generated. Note down the Document No.
8. Approve / Release Project Related Drawings
Create Document SBWP
Menu path Logistics Project system Documents Document Management System Document Create
Transaction CV02N
1. On the initial screen, enter the Document Number.2. Enter the Document Type e.g. ZCD / ZED 3. Press Enter.
Page 33 of 107
![Page 35: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/35.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
4. Change the Document Status to ‘Preliminary Approval’.
5. Repeat the procedure described above and change the Document Status to ‘Final Approval’.
Page 34 of 107
![Page 36: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/36.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
6. Save the Document .Note: Step 7 & 8 will be applicable only when some drawing works (e.g. civil
drawings, electrical wiring diagrams etc) is to be carried out in the Project.
9. Update the WBS Status to Survey Done.
Change WBS CJ02
Menu path Logistics Project system Project Special Maintenance function WBS Change
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Click on details
4. Click on
Page 35 of 107
![Page 37: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/37.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
5. Check the Status Profile. Select the relevant status.
6. Click on Back & check the new status
7. Similarly change the status of other WBS Elements.
8. Click on Save
10. Send WBS for Survey Approval to competent Authority
Change WBS CJ02
Menu path Logistics Project system Project Special Maintenance function WBS Change
Transaction CJ02
1. Select the WBS element & click on details -WBS Customer fields
Page 36 of 107
![Page 38: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/38.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
2. Click on Note sheet button
3. Enter the WBS element and Employee id of the person to whom the note sheet is to be sent.
4. Take the input help for Send Mail to.
5. Go to the Organizational assignment tab.
Page 37 of 107
![Page 39: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/39.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
Page 38 of 107
![Page 40: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/40.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
6. Choose the relevant Personnel Area from the input help. Alternatively use the search option (with the help of Binoculars)— Enter WTP
Click on
Click on
System gives “7600” as the Personnel Area.
7. Choose the relevant Personnel Sub area from the input help, Select “7600” in the restrictions to get the Personnel Sub Area relevant to WTP Only and find Nagpur from the list.
Page 39 of 107
![Page 41: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/41.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
Press Enter
Page 40 of 107
![Page 42: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/42.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
8. Select the Name of Employee/Personal No. and Click on .
In the Comment box add/see the comments and press
Page 41 of 107
![Page 43: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/43.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
If you want to see the details of the WBS element in edit mode press.
If you want to see the details of the WBS element in display mode press
If you want to see the document attached to the WBS Element press
If you want to print the Note sheet press
To see the cost in WBS element press
To approve the Project Estimate (PE) press .
This button should be used by the competent authority, at the Root WBS Element, to approve the PE of all WBS Elements in a single shot.
Note: Project Estimate shall be approved by the competent Authority
Alternatively use the T-Code “ZPS_NOTESHEET” to open the note sheet.
11. Release Survey Report for the Project
Create Document SBWP
Menu path Logistics Project system Documents Document Management System Document Create
Transaction CV02N
1. On the entry screen, enter the Document Number.2. Enter the Document Type ZPD (Project Documents).3. Press Enter.
Page 42 of 107
![Page 44: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/44.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
4. Change the Document Status to ‘Released’ and save the document.
Page 43 of 107
![Page 45: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/45.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
12. Update the WBS Status to Survey Approved (SRVA)
Change WBS CJ02
Menu path Logistics Project system Project Special Maintenance function WBS Change
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Click on details
Page 44 of 107
![Page 46: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/46.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
4. Click on
5. Check the Status Profile. Select the relevant status.
6. Click on Back & Check the new status
7. Similarly change the status of other WBS Elements.
8. Click on Save
Page 45 of 107
![Page 47: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/47.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
13. Create Project cum Detailed Estimate
A Network represents the flow of Activities or Tasks in a Project. Network Header can be used to default certain values for all the Activities in that Network.
Create Network CN21
Menu path Logistics Project system Project Special Maintenance function NetworkCreate
Transaction CN21
1. Select the Network Profile: BSNL_TP Transmission Project Network Profile
2. Enter Following data
Field Description RemarksNetwork Type Select ZPS2Plant Select the relevant PlantMRP Controller Select the Relevant MRP Controller
3. Enter the Std. Network (If required) from which data is to be copied.
4. Enter description for the Network
Page 46 of 107
Network Profile
![Page 48: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/48.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
5. Go to the Assignments tab and Enter Project Definition and WBS Element (Operative Project).
6. Click on Save
7. Note down the Network number created.
Change Network CN22
Menu path Logistics Project system Project Special Maintenance function NetworkChange
Transaction CN22
For making any changes in the Network once it is created the above menu path or the Transaction Code CN22 is to be used.
Page 47 of 107
![Page 49: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/49.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
Display Network CN23
Menu path Logistics Project system Project Special Maintenance function Network Display
Transaction CN23
To view the Network created the above menu path or the Transaction Code CN23 is to be used.
14. Assign Internal Activity
Change Network CN22
Menu path Logistics Project system Project Special Maintenance function NetworkChange
Transaction CN22
1. Enter the Network number created and press Enter (Refer Fig. below)
2. Go to the Activity Overview .
3. On the Int. processing tab, enter the relevant description
4. Click on
5. Click on Save
Page 48 of 107
![Page 50: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/50.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
15. Assign Material to an Internal Activity
Change Network CN22
Menu path Logistics Project system Project Special Maintenance function NetworkChange
Transaction CN22
1. Enter the Network number created and press Enter (Refer Fig. below).
2. Click on Activity Overview .
3. Select the internal Activity
4. Go to Component Overview
5. Search the relevant Material code through the Search option (F4)
Page 49 of 107
![Page 51: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/51.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
6. Click on Start Search
7. Select the relevant material from the list.
Page 50 of 107
![Page 52: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/52.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
8. Enter following data.
Material Line wise enter the Material code required for the Activity
Requirement Qty
Enter quantity to be procured.
Item Category Enter “L” for stock item.Procurement type
A submenu opens, where we have to select the required button.
9. Press Enter (A Pop Up will appear to select the Procurement Type)
10. Choose the relevant Procurement type
11. Press Enter
12. Click on Save
Page 51 of 107
![Page 53: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/53.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
Note:- Procurement Types
Although a no. of options are proposed by the system, but the user has to select the following as per the current WTP scenario.
Reservation for WBS Element: To be used if a reservation is to be created for the WBS Element items kept in stock.
To know about the other options, user can select the option, press F1 and read the SAP help content.
Continue attaching the remaining required Items.
See the details by pressing the detail button and enter the Purchase Group / Purchase Org / Price and currency. The G/L account flows from the settings and should not be changed.
16. Assign & Explode Bill of Materials
Change Network CN22
Menu path Logistics Project system Project Special Maintenance function NetworkChange
Transaction CN22
1. Enter the Network number created and press Enter (Refer Fig. below)
2. Click on Activity Overview
3. Select the Activity & Click on Component Overview at the bottom of
the screen
Page 52 of 107
![Page 54: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/54.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
4. Enter following data.
Material Line wise enter the Material code required for the Activity
Requirement Qty
Enter quantity to be procured.
Item Category
Enter “L” for stock item.
Procurement type
A submenu opens, where we have to select the required button.
5. Search the relevant Material code by Search option (F4)
6. Click on Continue
7. Double click on the Material.
8. Select the relevant Item Category.
Page 53 of 107
![Page 55: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/55.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
9. Select the relevant Procurement type
10. Click on Component - Explode BOM
Page 54 of 107
![Page 56: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/56.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
11. Click on Continue. Select the Materials & click on Copy.
Page 55 of 107
![Page 57: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/57.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
12.Click on Save
17. Assign Service Activity
Change Network CN22
Menu path Logistics Project system Project Special Maintenance function NetworkChange
Transaction CN22
1. Enter the Network number created and press Enter (Refer Fig. below)
2. Go to Activity Overview and click.
Page 56 of 107
![Page 58: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/58.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
3. Press Enter.
Enter the Services and go to back
4. Select the Activity & Click on Details
5. Enter the Purchasing data i.e. Purchasing Organization, Purchasing
Group, Material Group, Requisitioner.
6. Click on Back
7. Click on Continue , Save
Page 57 of 107
![Page 59: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/59.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
18. Assign General Cost Activity
Change Network CN22
Menu path Logistics Project system Project Special Maintenance function NetworkChange
Transaction CN22
1. Enter the Network number created and press Enter (Refer Fig. below)
2. Go to Activity Overview .
3. On the Prim. Costs tab, enter the relevant description and assign it to the
relevant WBS Element. (Refer Fig. below)
4. Select the Activity & Click on
Page 58 of 107
![Page 60: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/60.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
5. Enter the cost and cost element.
Note: Cost Element field is mandatory.
6. Click on Save
19. Define Relationship between Activities
Change Network CN22
Menu path Logistics Project system Project Special Maintenance function NetworkChange
Transaction CN22
1. Enter Network No.
2. Click on Activity Overview.
3. Select the Activity.
4. Click on to create relationship between activities:-
Page 59 of 107
![Page 61: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/61.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
5. Activities can be linked together by assigning FS/SF/FF/SS relation by
clicking on the connect tab
6. Click on & Back & Click on Save (Ctrl+S)
Page 60 of 107
![Page 62: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/62.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
20. Attach Milestone to an Activity
Change Network CN22
Menu path Logistics Project system Project Special Maintenance function NetworkChange
Transaction CN22
1. Enter the Network number created and press Enter (Refer Fig. below)
2. Go to Activity Overview
3. Select the Activity.
4. Click on Milestone Overview.
5. Milestone can be attcahed by following methods :
a) Use Standard Milestone – Click on Standard Milestone
at the Bottom of screen & Search for suitable Milestone.
b) Use Milestone Group – Click on Milestone Group
at the bottom of screen .Search & select the suitable Miestone Group.
Double click on the relevant Milestone Group. All the Milestones
assigned to the group will be displayed on the screen .
c) Define milestone – Enter the Milestone Usage & Description.
6. Select the Row of a Milestone & Click on Details
7. Enter the Planned finish date & Percentage of completion.
Page 61 of 107
![Page 63: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/63.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
8. Click on continue and Save
21. Attach Milestone to a WBS Element
Change WBS CJ02
Menu path Logistics Project system Project Special Maintenance function WBSChange
Transaction CJ02
1. Enter the WBS Element and press Enter (Refer Fig. below)
2. Go to WBS Overview
3. Select the WBS.
4. Click on Milestone Overview.
Page 62 of 107
![Page 64: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/64.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
5. Milestone can be attcahed through the following methods :
a) Use Standard Milestone – Click on Standard Milestone
at the Bottom of the screen & Search for the relevant Milestone.
b) Use Milestone Group – Click on Milestone Group
at the bottom of the screen . Search & select the relevant Miestone Group.
Press Enter & double click on the Milestone.
c) Define milestone – Enter the Milestone Usage & Description.
6. Select the Row of a Milestone & Click on details
7. Enter the Plan Date of finish in ‘Fix`Date’ & Percentage of completion.
8. Click on continue. Save
22. Project Scheduling
Project Scheduling CJ29
Menu path Logistics Project system Dates SchedulingTransaction CJ29
1. Enter the Project number
2. Click on the Sched. Basic dates button
Page 63 of 107
![Page 65: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/65.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
3. On Next Screen Select:- Network & Maintenance/service Order
4. Click on Execute . “Scheduling Carried out”
5. Click on to Check Scheduled Dates for the WBS Element.
6. Select the TOP WBS Element.
7. Click on to view Gantt chart.
8. Click on Save (Ctrl+S)
23. Update the WBS Status to PE cum DE Created
Page 64 of 107
![Page 66: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/66.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
Change WBS CJ02
Menu path Logistics Project system Project Special Maintenance function WBS Change
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Click on
4. Check the Status Profile. Select the relevant status.
5. Click on Back & Check the new status
6. Similarly change the status of other WBS Elements.
Page 65 of 107
![Page 67: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/67.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
7. Click on Save
24. Send WBS for PE Cum DE Approval to competent Authority using Note Sheet
Note sheetZPS_NOTESHEET
1. Select the WBS element – Details - click on Customer fields:
2 Click on Create Note sheet button
3 Enter the WBS element and Employee ID of the person to whom the Note Sheet is to be sent.
Page 66 of 107
![Page 68: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/68.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
4 Enter the WBS element and Employee ID of the person to whom the Note
Sheet is to be sent.
In the Comment box add/see the comments and press
If you want to see the details of the WBS element in edit mode press .
If you want to see the details of the WBS element in display mode press
If you want to see the document attached to the WBS Element press
If you want to print the Note sheet press
To see the cost in WBS element press
To approve the Project Estimate (PE) press .
This button should be used by the competent authority, at the Root WBS Element, to approve the PE of all WBS Elements in a single shot.
Page 67 of 107
![Page 69: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/69.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
Note: Project Estimate shall be approved by the competent Authority
Alternatively use the T-Code “ZPS_NOTESHEET” to open the note sheet.
25. Read Note Sheet received in the SAP Inbox
Note sheet SBWP
Menu path Office Workplace
Transaction SBWP
1. Click on Inbox icon
2. Click on .
3. The note sheet screen will appear. Add the details and forward it to next level, as explained in the Step-6.
Page 68 of 107
![Page 70: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/70.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
26. Review Project Estimate
After receiving the mail, the Project estimate can be reviewed by using this report. This report will give the details of Plan/Actual/Commitment for a Project.
Structure Overview CN41
Menu path Logistics Project System Information System Structures Structure Overview
Transaction Code
CN41
1. Enter PS Info prof. 000000000001
2. Enter Project number
3. Click on Execute.
4. Check the Plan, Actual & Commitment column.
Page 69 of 107
![Page 71: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/71.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
5. Click on Back.
27. Update the WBS Status to PE cum DE Concurred (PEFI)
Change WBS CJ02
Menu path Logistics Project system Project Special Maintenance function WBS Change
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Click on details
4. Click on
5. Check the Status Profile. Select the relevant status.
Page 70 of 107
![Page 72: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/72.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
6. Click on Back & Check the new status
7. Similarly change the status of other WBS Elements.
8. Click on Save
28. Update the WBS Status to PE cum DE Approved
Change WBS CJ02
Menu path Logistics Project system Project Special Maintenance function WBS Change
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Click on details
4. Click on
Page 71 of 107
![Page 73: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/73.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
5. Check the Status Profile. Select the relevant status.
6. Similarly change the status of other WBS Elements.
7. Click on Save .
29. View Approved PE/DE/RE PDF Documents
View approved PE/DE/RE DocumentsZPEDE / CJ02
Menu path N/ATransaction ZPEDE / CJ02
1. Enter the WBS element number
2. Click on Execute
3. Click on the Document number
Page 72 of 107
![Page 74: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/74.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
Note: Document is appeared and the same can be downloaded in the local systemAlternatively, Approved PE/DE/RE can be viewed through CJ02 also,
1. Select the Relevant WBS Element
2. Go to WBS Element Tab - Document Overview Tab
3. Select the Relevant Document
Page 73 of 107
![Page 75: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/75.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
4. Click on
30. Link WBS Element to an Investment Program Position
Please Refer Budget Allocation User Manual
31. Budget Distribution to the Project
Please Refer Budget Allocation User Manual
32. Plan for Project Wise Activities (SKF – Statistical Key Figure)
Plan SKF CJS2
Menu path Logistics Project System Financials PlanningStatistical Key FiguresChange
Transaction CJS2
1. Enter Version, From & To Period, Fiscal Year, Relevant WBS Element, &, Stat. Key Figure
2. Click on the ‘Overview screen’ (F5)
On the overview screen,
Page 74 of 107
![Page 76: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/76.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
enter:
Current Plan Value
3. Select the Row
4. Click on Period Screen
5. Enter the Month wise Plan Values
6. Click on Save (Ctrl+S)
33. Update the System status of a WBS Element to Released
Project Release CJ02
Menu path Logistics Project System Project Special Maintenance FunctionsWork Break Down Structure (WBS)Change
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element
3. Go to Menu to Menu Bar Edit Option Status Release (Refer Fig.
below)
4. This will change the System Status from Created to Released.
Page 75 of 107
![Page 77: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/77.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
Following error message might appear while changing the status to Release.
In that case, co-ordinate with Finance to run the transaction IM52 (Budget Distribution) /CJBV (Activate Availability Control).
5. Check the status
6. Similarly change the status of all other WBS Elements & the the Project
Definition.
7. Click on Save.
Page 76 of 107
![Page 78: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/78.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
34. Update the System status of a Network to Released
Change Network CN22
Menu path Logistics Project System Project Special Maintenance FunctionsNetworkChange
Transaction CN22
1. Enter the Network No.
2. Go to Menu Bar Edit Option Status Release (Refer Fig. below)
3. This will change the Network Status from Created to Released
4. Check the status
5. Click on Save
Page 77 of 107
![Page 79: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/79.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
35. Post Actual SKF during the Project Execution phase
SKF Posting KB31N
Menu path Logistics Materials Management Foreign Trade/Customs General Foreign Trade ProcessingEnvironment Sales ExportSalesProduct Cost by Sales OrderActual PostingsSKF
Transaction KB31N
1. Select Screen variant and Input type
2. Enter the Relevant WBS Element
3. Select the Relevant SKF
4. Enter Quantity
Page 78 of 107
![Page 80: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/80.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
5. Click on Save
36. Update the WBS Status to Revised Estimate Created
Change WBS CJ02
Menu path Logistics Project System Project Special Maintenance FunctionsWork Break Down Structure (WBS)Change
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Click on details
4. Click on
Page 79 of 107
![Page 81: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/81.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
5. Check the Status Profile. Select the relevant status.
6. Click on Back & Check the new status.
7. Similarly change the status of other WBS Elements.
8. Click on Save.
Note: All FI Postings or any other type of cost booking will not be possible
until revised estimate statuses are active for a WBS Element.
37. Update the WBS Status to Revised Estimate FI Concurred
Change WBS CJ02
Menu path Logistics Project System Project Special Maintenance FunctionsWork Break Down Structure (WBS)Change
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Click on details
Page 80 of 107
![Page 82: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/82.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
4. Click on
5. Check the Status Profile. Select the relevant status.
6. Click on Back & Check the new status.
7. Similarly change the status of other WBS Elements.
8. Click on Save
38. Update the WBS Status to Revised Estimate Approved
Change WBS CJ02
Menu path Logistics Project System Project Special Maintenance FunctionsWork Break Down Structure (WBS)Change
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Click on details
Page 81 of 107
![Page 83: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/83.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
4. Click on
5. Check the Status Profile. Select the relevant status.
6. Click on Back & Check the new status.
7. Similarly change the status of other WBS Elements.
8. Click on Save
39. Activity Confirmation
Page 82 of 107
![Page 84: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/84.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
Change Network CN22
Menu path Logistics Project System Project Special Maintenance FunctionsNetworkChange
Transaction CN22
1. Go to the Activity Overview on the Header Details screen of the Network :-
2. Go to the tab for Int. Processing as shown below and select the internal activity
3. Click on the Confirmation icon on the lower part of the screen
4. On the Next screen carry out the following steps for Partial Confirmation of the Activity:-
5. Enter the Start and Finish Date in the respective fields as shown below:-
Page 83 of 107
![Page 85: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/85.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
6. Select the Reason by selecting the Reason ID
7. Press Enter.8. Click on the “Back” button.9. Save the Network.10. Ignore the Warnings.11. Click on Final Confirmation and Completed Indicators for Full and Final
Confirmation by repeating the above steps for the same activity
12. Click on Back icon
13. Click on Save (Ctrl+S)
Page 84 of 107
![Page 86: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/86.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
40. Milestone Confirmation assigned to a WBS Element
Change WBS CJ02
Menu path Logistics Project system Project Special Maintenance function WBS Change
Transaction CJ02
1. Enter the WBS Element No. and press Enter (Refer Fig. below)
2. Go to WBS Element Overview.
3. Select the WBS Element.
4. Click on Milestone Overview.
5. Select the Row of a Milestone & Click on details
6. Enter the Actual Date.
7. Click on Back.
8. Click on Save (Ctrl+S) .
41. Milestone Confirmation assigned to an Activity
Change Network CN22
Menu path Logistics Project system Project Special Maintenance function NetworkChange
Transaction CN22
1. Enter the Network no. and press Enter (Refer Fig. below)
2. Go to Activity Overview.
3. Select the relevant Activity.
Page 85 of 107
![Page 87: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/87.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
4. Click on Milestone Overview at the bottom of the screen .
5. Select the Row of a Milestone & Click on details
6. Enter the Actual Date.
Page 86 of 107
![Page 88: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/88.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
7. Click on Back.
8. Click on Save (Ctrl+S) .
42. Update the WBS Status to Offered For AT
Change WBS CJ02
Menu path Logistics Project system Project Special Maintenance function WBSChange
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Click on details
4. Click on
Page 87 of 107
![Page 89: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/89.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
5. Check the Status Profile. Select the relevant status.
6. Click on Back & Check the new status.
7. Similarly change the status of other WBS Elements.
8. Click on Save .
Note: - At this status user can attach any relevant documents on the WBS element to carry out AT (for reference.)
43. Update the WBS Status to List of Pending Points / Shortcoming from AT (If Any)
Change WBS CJ02
Menu path Logistics Project system Project Special Maintenance function WBSChange
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Click on details
4. Click on
Page 88 of 107
![Page 90: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/90.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
5. Check the Status Profile. Select the relevant status.
6. Click on Back & Check the new status.
7. Similarly change the status of other WBS Elements.
8. Click on Save .
44. Update the WBS Status to clearance of Pending Points (If Any)
Change WBS CJ02
Menu path Logistics Project system Project Special Maintenance function WBSChange
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Click on details
Page 89 of 107
![Page 91: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/91.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
4. Click on
5. Check the Status Profile. Select the relevant status.
6. Click on Back & Check the new status.
7. Similarly change the status of other WBS Elements.
8. Click on Save .
45. Update the WBS Status to Relaxation for Pending Points Not Cleared (If Any)
Change WBS CJ02
Menu path Logistics Project system Project Special Maintenance function WBSChange
Page 90 of 107
![Page 92: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/92.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Click on details
4. Click on
5. Check the Status Profile. Select the relevant status.
6. Click on Back & Check the new status.
7. Similarly change the status of other WBS Elements.
8. Click on Save .
46. Update the WBS Status to Provisionally Fit for Commissioning
Page 91 of 107
![Page 93: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/93.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
Change WBS CJ02
Menu path Logistics Project system Project Special Maintenance function WBSChange
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Click on details
4. Click on
5. Check the Status Profile. Select the relevant status.
6. Click on Back & Check the new status.
7. Similarly change the status of other WBS Elements.
Page 92 of 107
![Page 94: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/94.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
8. Click on Save .
47. Update the WBS Status to Declared Fit for Commissioning
Change WBS CJ02
Menu path Logistics Project system Project Special Maintenance function WBSChange
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Click on details
4. Click on
5. Check the Status Profile. Select the relevant status.
6. Click on Back & Check the new status.
Page 93 of 107
![Page 95: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/95.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
7. Similarly change the status of other WBS Elements.
8. Click on Save .
48. Update the Status of a WBS Element to TECO (Technically Complete)
Change WBS CJ02
Menu path Logistics Project System Project Special Maintenance FunctionsWork Break Down Structure (WBS)Change
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Go to the Menu Edit Status Technically Complete (Refer Fig. below)
4. This will change the System Status of the WBS Element to Technically
Complete.
5. Check the status
Page 94 of 107
![Page 96: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/96.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
6. Click on Save
49. Update the Status of a Network to TECO (Technically Complete)
Change Network CN22
Menu path Logistics Project System Project Special Maintenance FunctionsNetworkChange
Transaction CN22
1. Enter the Network No.
2. Go to Edit Status Close Technically (Refer Fig. below)
3. This will change the Network Status to Technically Complete.
4. Check the status
Page 95 of 107
![Page 97: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/97.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
5. Click on Save .
Note: At TECO status the user will not be allowed to expand the project structure. Planning in Projects as such is not allowed at this status, Actual cost can however be posted to the WBS element.
50. Update the WBS Status to Commissioning Done
Change WBS CJ02
Menu path Logistics Project system Project Special Maintenance function WBSChange
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Click on details
4. Click on
5. Check the Status Profile. Select the relevant status.
Page 96 of 107
![Page 98: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/98.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
6. Click on Back & Check the new status.
7. Similarly change the status of other WBS Elements.
8. Click on Save
51. Enter details after Update of Status Commissioning Done
Change WBS CJ02
Menu path Logistics Project system Project Special Maintenance function WBSChange
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Click on details and then go to tab
Page 97 of 107
![Page 99: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/99.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
4. Select field key Transmission Project –Equipment from the drop down
5. Press Enter
6. Enter the Equipment PO Number
7. Enter the PO Date & Commissioning Date
8. Press Enter or
9. Click on Save
Page 98 of 107
![Page 100: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/100.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
52. Settlement of Network to WBS element
Change WBS CJ88
Menu path Logistics Project system Financials Period- End Closing Single FunctionsSettlement
Transaction CJ88
1. Enter the Controlling Area
Maintain “1000” as controlling area.
2. Enter the Network Number
3. Select the hierarchy and with orders check box
4. Enter the following details
Settlement Period Fiscal Year Processing Type
Note: If not specified Posting period remains same as Settlement period.
5. On the Processing Option section select the Test run & Detail List Check box
Page 99 of 107
![Page 101: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/101.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
6. Click on Execute .
Note: The Above step is carried out for test run the settlement process so that any error can be checked. For Actual Settlement please Uncheck/Deselect the Test
Run check box and then execute the settlement.
53. Update the WBS Status to Offered for Taking Over
Change WBS CJ02
Menu path Logistics Project system Project Special Maintenance function WBSChange
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Click on details
Page 100 of 107
![Page 102: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/102.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
4. Click on
5. Check the Status Profile. Select the relevant status.
6. Click on Back & Check the new status
7. Similarly change the status of other WBS Elements.
8. Click on Save .
54. Update the WBS Status to Taken Over
Change WBS CJ02
Menu path Logistics Project system Project Special Maintenance function WBSChange
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
Page 101 of 107
![Page 103: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/103.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
2. Select the WBS Element.
3. Click on details
4. Click on
5. Check the Status Profile. Select the relevant status.
6. Click on Back & Check the new status
7. Similarly change the status of other WBS Elements.
8. Click on Save
Page 102 of 107
![Page 104: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/104.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
55. Update the System Status of a WBS Element to Closed
Change WBS CJ02
Menu path Logistics Project System Project Special Maintenance FunctionsWork Break Down Structure (WBS)Change
Transaction CJ02
1. Enter the WBS Element No. Press Enter.
2. Select the WBS Element.
3. Go to Menu to Menu Bar Edit Option Status CLSD (Refer Fig.
below)
4. This will change the System Status from Technically Complete to Closed.
5. Check the status
6. Click on Save .
Note: Once Closed Status is set ,no actual cost can be posted to the WBS
element.
Page 103 of 107
![Page 105: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/105.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
56. Transactions for Project Monitoring:-
1.Monitor Project Structure (CN41)
Enter Database Profile Value after executing the Transaction Code
Enter the Following Information:-
Project Definition, WBS element or Network No. in Single or Multiple Selection
Press Execute
Note the Output
Page 104 of 107
![Page 106: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/106.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
To Change the layout click on the icon on the top and select the desired fields.
Remarks:- In the output of this report user can access information as per a no. of categories viz.
2.Monitor Project Cost (CJI3)
Enter Controlling Area :- 1000
Enter Database Profile:- 000000000001
Enter the Following Information:-
Project Definition, WBS element or Network No. in Single or Multiple Selection
Press Execute
Note the Output
3.Monitor Project Milestones (CN53)
Enter Controlling Area :- 1000
Enter Database Profile:- 000000000001
Enter the Following Information:-
Project Definition, WBS element or Network No. in Single or Multiple Selection
Page 105 of 107
![Page 107: User Training Manual_PS_TP_End User V1.2 Final1](https://reader038.vdocuments.mx/reader038/viewer/2022102622/55cf92b5550346f57b98eafb/html5/thumbnails/107.jpg)
User Manual:-Title:-Module Name:-Business Process:-
PS_UTM_TP_01
Project SystemTransmission Projects
Press Execute
Note the Output
Page 106 of 107