university of southampton research repository …eprints.soton.ac.uk/191383/1/00354011.pdf ·...
TRANSCRIPT
University of Southampton Research Repository
ePrints Soton
Copyright © and Moral Rights for this thesis are retained by the author and/or other copyright owners. A copy can be downloaded for personal non-commercial research or study, without prior permission or charge. This thesis cannot be reproduced or quoted extensively from without first obtaining permission in writing from the copyright holder/s. The content must not be changed in any way or sold commercially in any format or medium without the formal permission of the copyright holders.
When referring to this work, full bibliographic details including the author, title, awarding institution and date of the thesis must be given e.g.
AUTHOR (year of submission) "Full thesis title", University of Southampton, name of the University School or Department, PhD Thesis, pagination
http://eprints.soton.ac.uk
UNIVERSITY OF SOUTHAMPTON
Faculty of Engineering, Science and Mathematics
School of Civil Engineering and the Environment
Performance of a propped retaining wall at the
Channel Tunnel Rail Link, Ashford
Jo Clark
•
Thesis for the degree of Doctor of Philosophy
June 2006
UNIVERSITY OF SOUTHAMPTON
ABSTRACT
FACULTY OF ENGINEERING, SCIENCE AND MATHEMATICS
SCHOOL OF CIVIL ENGINEERING AND THE ENVIRONMENT
Doctor of Philosophy
PERFORMANCE OF A PROPPED RETAINING WALL AT THE CTRL, ASHFORD
Jo Clark
This thesis is based on the field monitoring of a propped bored pile retaining wall installed
in an overconsolidated clay. Pile bending moments, prop loads, pore water pressures and
lateral earth pressures were logged automatically at intervals of up to 5 minutes
throughout construction (and for 4 years afterwards) and wall deflections were measured
during construction, making this the most comprehensive instrumentation project of its
kind.
The magnitude of the over-read associated with the use of spade cells (used to measure
lateral earth and pore water pressures) in overconsolidated deposits was determined by
comparing readings from a spade cell aligned to measure vertical stress with the estimated
overburden acting on it as the overburden was excavated. This study adds significantly to
the previous data as spade cells have not previously been \lsed in the Atherfield Clay, and
the performance of spade cells under a known changing load has not previously been
measured in the field.
Analysis of the changes in lateral stress and pore water pressure during the wall
installation process showed significant reductions in horizontal stress during wall
installation, reducing the ratio of effective horizontal to effective vertical stress, K, from
about 1 to nearly the active condition. Following wall installation there was no further
change in horizontal stress over a period of about 10 months, during which time no further
construction work took place.
Analysis of the data yielded good agreement between pile bending moments estimated
from inclinometer and strain gauge measurements in the piles, and the onset of concrete
cracking was identified. The components of strain measured in the reinforced concrete
props due to shrinkage, creep and applied load were also identified, allowing prop loads to
be estimated. A simple equilibrium calculation showed that these agree with the measured
wall bending moments and total horizontal soil stresses, demonstrating the overall
consistency of the data collected.
Simple equilibrium analysis of the behaviour of the wall during construction shows that
the soil stresses measured are compatible with the measured structural loads. The long
term horizontal soil stresses, bending moments and RC prop loads show no increase over
the 6 years since construction began.
TABLE OF CONTENTS
Index of Figures
Index of Tables
1
2
Introduction
1-1 In situ embedded retaining walls
1-2 Measurement of horizontal stress
1-3 Channel Tunnel Rail Link
1-4 Objectives
1-5 Outline of report
Literature Review
2-1
2-2
Introduction
Review of investigations into retaining wall behaviour
2-2-1
2-2-2
2-2-3
2-2-4
2-2-5
2-2-6
Background
Limiting conditions
Development of active and passive pressures
Distribution of earth pressures
Change in horizontal earth pressure due to wall installation effects
Behaviour of embedded walls in the longer term
2-3 General overview of retaining wall design standards
2-3-1 Choice of soil parameters
2-3-2 Application of safety factors
2-3-3 Calculation of design bending moments
2-3-4 Advice on wall installation effects
2-4 Use of spade cells to measure horizontal stress in overconsolidated clay
2-4-1 Background
2-5 Conclusion
3 Case study
3-1 Introduction
3-2 Geology
3-2-1 Geotechnical data and sample collection
3-2-2 Site location and history
Vll
Xll
3
4
5
5
8
8
9
9
9
11
12
15
17
18
20
21
23
23
24
24
26
31
31
31
32
33
3-2-3 Reported geology
3-2-4 Observed geology
3-3 Geotechnical properties
3-3-1 Plasticity
3-3-2 Bulk density
3-3-3 Soil strength
3-3-4 In situ horizontal stress
3-3-5 Permeability and Groundwater
3-4 Description of site and geometry of structure at the instrumented section
3-5 Construction sequence and installation of instrumentation
3-5-1 Pile installation
3-5-2
3-5-3
3-5-4
3-5-5
3-5-6
3-5-7
3-5-8
3-5-9
Sand drains
Removal of pile tops
Capping beam
Reinforced concrete props
Backfilling and material placement behind North wall capping beam
Excavation
Temporary props
Base slab
3-5-10 Installation of storm drain
3-6 Data collection and vibrating-wire instrument technology
4 Structural monitoring
4-1
4-2
Introduction
Inclinometer
4-2-1 Description and Use
34
36
38
38
38
39
40
41
42
43
45
47
48
49
49
49
50
50
51
51
51
97
97
98
98
4-2-2 Calculation of bending moments from inclinometer data 1 01
4-3 Vibrating-wire gauges 104
4-3-1 Use 104
4-3-2 Method for calculation of prop loads from strain gauge measurements 104
4-3-3 Method for calculation of bending moments from strain gauges 105
4-3-4 Correction for temperature effects
4-4 Analysis of instrumentation data
4-4-1 Temporary prop data
4-4-2 Base slab data
4-4-3
4-4-4
Reinforced concrete prop data
Pile data
107
107
107
108
109
115
11
4-4-5 Comparison between pile bending moments calculated from strain gauges and inclinometer 118
4-5 Measured changes due to construction events
4-5-1
4-5-2
4-5-3
Temporary props
Base slab data
Reinforced concrete props
4-5-4 Pile bending moments measured with strain gauges
4-5-5 Inclinometer data
4-6 Conclusions
5 Horizontal soil stress measurement
5-1
5-2
5-3
5-4
Introduction
Spade cell description
Calibration
Evaluation of spade cell over-reading
5-4-1
5-4-2
5-4-3
Introduction
Test procedure
Results and Discussion
5-5 Installation effects of a bored pile retaining wall in overconsolidated clay
5-5-1
5-5-2
5-5-3
5-5-4
5-5-5
5-5-6
5-5-7
Introduction
Calibration and installation of spade cells
Stabilization of spade cells following insertion
In situ total horizontal stresses and pore water pressures
Effective stress profile
Pore water pressure changes during and after wall installation
Total horizontal stress changes due to wall installation
5-5-8 Effective stress changes due to wall installation
5-5-9 Total and effective horizontal stress changes after wall installation
5-6 Effect of excavation in front of the wall on horizontal earth stresses
5-7 Conclusions
6 Long term monitoring
6-1 Introduction
6-2 Total horizontal stress and pore water pressure measurements
6-2-1 Installation of storm drain
6-3 Reinforced concrete prop loads
6-4
6-5
Pile bending moments
Conclusions
119
119
120
120
121
124
125
162
162
162
163
163
163
164
165
169
169
169
169
169
170
170
172
175
176
176
179
216
216
216
217
218
218
219
11l
7 Conclusions and recommendations
7-1
7-2
Conclusions
Recommendations for further work
Appendix A Wireline borehole BH1 and BH2 logs
Appendix B Piling diary
Appendix C Calculation of flexural rigidity of pile (El)
References
237
238
239
241
250
253
254
IV
LIST OF FIGURES
Figure 1-1 Map showing the route of the Channel Tunnel Rail Link 7
Figure 2-1 Coulomb's idealized earth pressure distribution 27
Figure 2-2 Fixed earth support 27
Figure 2-3 Free earth support 27
Figure 2-4 Relationship between earth pressure and wall rotation measured by Terzaghi for normally consolidated sand (modified by Simpson, 1992) 28
Figure 2-5 Relationship between earth pressure and wall rotation computed by Potts and Fourie (1986) for overconsolidated clay 28
Figure 2-6 Influence of movement type on pressure distribution 29
Figure 2-7 Stress distributions behind and in front of (a) stiff and (b) flexible embedded walls (after Rowe, 1952) 29
Figure 2-8 Over-reading v. cu. After Ryley and Carder, 1995 30
Figure 3-1 The relative locations of the areas described in this work 54
Figure 3-2 Geology of the Weald of Kent 55
Figure 3-3 Layering in the Weald Clay 56
Figure 3-4 Light brown band defining the boundary between the upper and lower Atherfield Clay (observed in the nadir sump) 57
Figure 3-5 Showing the peds and softer matrix of the upper Atherfield Clay 57
Figure 3-6 In situ block sample of the Hythe Beds 58
Figure 3-7 Photo looking into the cutting between RC props during excavation 59
Figure 3-8 Photo showing an elevation of the excavation face 59
Figure 3-9 Shear plane in the upper Atherfield Clay, 50 m from the instrumented section 60
Figure 3-10 Sketch taken of discontinuity observed in the bottom of the excavation at the instrumented section 61
Figure 3-11 Geotechnical profile including liquid and plastic limits from wireline boreholes 1 and 2 62
Figure 3-12 Comparison of geology at locations referred to in this study 63
v
Figure 3-13 Bulk density v depth 64
Figure 3-14 Effective stress paths of lower Atherfield Clay 65
Figure 3-15 Undrained shear strength v depth from laboratory samples and 66 standard penetration test results
Figure 3-16 Undrained shear strength v depth from self-boring pressuremeter test 67
Figure 3-17 Total horizontal stress measured by self-boring pressuremeter 68
Figure 3-18 Permeability data 69
Figure 3-19 Pore water pressure: measurements and assumed profile 70
Figure 3-20 Location of the instrumented section 71
Figure 3-21 Cross-section of the cutting at the instrumented section 72
Figure 3-22 Elevation illustrating the ground profile around the structure 73
Figure 3-23 Plan of instrumented section 74
Figure 3-24 Elevation of instrumented section 74
Figure 3-25 Pile installation sequence 75
Figure 3-26 Photo showing pile boring 76
Figure 3-27 Photo showing installation of casing 77
Figure 3-28 Photo showing installation of reinforcement cage 78
Figure 3-29 Elevation of instrumented section showing strain gauge arrangement 79
Figure 3-30 Strain gauges for measurement of pile bending moment 80
Figure 3-31 Photo showing sand drain and cable for spade cell 11 81
Figure 3-32 Changes in total horizontal stress and pore water pressure in front of the wall around the period of sand drain installation 82
Figure 3-33 Excavation either side of the north wall before pile top removal 83
Figure 3-34 Pile top removal 84
Figure 3-35 Wall before construction of capping beam 85
Figure 3-36 Dimensions of capping beam 86
Figure 3-37 Photo showing capping beam 86
Figure 3-38 Preparation for RC prop construction 87
Figure 3-39 Relative location of the instruemented props and piles 88
Figure 3-40 Photo showing instrumented area before excavation 89
Figure 3-41 Compacting backfill in the instrumented section 90
Figure 3-42 Elevation showing props and order of excavation 91
VI
Figure 3-43 Excavation using long-reach excavator 92
Figure 3-44 Temporary prop arrangement and strain gauge housings 92
Figure 3-45 Temporary prop gauges welded onto prop 93
Figure 3-46 Elevation showing base slab arrangement 94
Figure 3-47 Strain gauges wired onto base slab reinforcement 94
Figure 3-48 Storm drain installed behind north wall in November 2001 (Day 864) 95
Figure 3-49 Datalogger setup 96
Figure 3-50 Vibrating-wire gauge 96
Figure 4-1 Inclinometer probe 127
Figure 4-2 Analysis of inclinometer data for face errors 127
Figure 4-3 Movement of wall toe with time measured by the inclinometer 128
Figure 4-4 Correction of inclinometer data 129
Figure 4-5 Movement of wall toe and bottom 10m of inclinometer tube 130
Figure 4-6 Inclinometer measurements taken during construction 131
Figure 4-7 Movement of the top of the wall 132
Figure 4-8 Typical relationship between load and temperature (temporary prop) 133
Figure 4-9 As measured temporary prop loads 134
Figure 4-10 Temporary prop loads corrected for temperature effects 135
Figure 4-11 Base slab readings 136
Figure 4-12 Temperature v load for a typical base slab gauge 137
Figure 4-13 Strains measured in the base slab gauges 138
Figure 4-14 Strain measured in reinforced prop PI 140
Figure 4-15 Strain measured in reinforced prop P4 140
Figure 4-16 Strain measured in reinforced prop P2 141
Figure 4-17 Time/strain versus time for an RC prop gauge at chainage 89+205 143
Figure 4-18 Measured and calculated strain against time for RC prop gauges at chainage 89+205 143
Figure 4-19 Prop loads uncorrected for effects of shrinkage 144
Figure 4-20 Prop loads corrected for effects of shrinkage using Ross' equation 145
Figure 4-21 Close up showing up to after Excavation Phase 2 from Figure 4-20 146
Figure 4-22 Change in stiffness with time for RC prop 147
VB
Figure 4-23 Temperature v load for a typical RC prop gauge 147
Figure 4-24 Difference in strain measured in pile gauges over construction period 148
Figure 4-25 Strain measurements over period of construction for some gauges 149
. Figure 4-26 Deflections measured in pile Z around time of Excavation Phase 2 and Temporary Prop Removal 150
Figure 4-27 Photos showing bulge in pile concrete 151
Figure 4-28 Strains measured in Pile Y over the 30 days after excavation and 152 before Base Slab Construction
Figure 4-29 Bending moments calculated before and after Excavation Phase 2 from inclinometer and strain gauge measurements 154
Figure 4-30 Bending moments calculated before and after Temporary Prop Removal from inclinometer and strain gauge measurements 155
Figure 4-31 Individual temporary prop loads 156
Figure 4-32 Pile Y bending moments plotted against time (below base slab) 158
Figure 4-33 Pile Y bending moments plotted against time (above base slab) 159
Figure 4-34 Pile X bending moments plotted against time (below base slab) 160
Figure 4-35 Pile X bending moments plotted against time (above base slab) 161
Figure 5-1 Spade cell 181
Figure 5-2 Spade cell calibration equipment 182
Figure 5-3 Equipment for drilling horizontal borehole 183
Figure 5-4 Nadir sump plan and elevation 184
Figure 5-5 Spade cell: uncovered in excavation 185
Figure 5-6 Total vertical stress measured by spade cell in nadir sump 186
Figure 5-7 Elevations and plans detailing the excavation of material above the 187 spade cell in the nadir sump
Figure 5-8 Measured total stress versus overburden 188
Figure 5-9 Nadir sump spade cell stiffness calibration ]89
Figure 5-10 Finite element analysis mesh ]90
Figure 5-11 Measured and calculated vertical stresses against overburden 191
Figure 5-12 Over-read error: measured and calculated from limit equilibrium analysis 192
Figure 5-13 Comparison between spade cell readings corrected by 0·35 Cu and self-boring pressuremeter test results 193
Vlll
Figure 5-14 Spade cell installation 194
Figure 5-15 Spade cell measurements taken between their installation and wall installation 195
Figure 5-16 Stabilized readings of total horizontal stress and pore water pressure from all spade cells (before wall installation) 196
Figure 5-17 The profile of 0\0 with depth 197
Figure 5-18 Piezometer readings over the period of wall installation 198
Figure 5-19 Pore water pressures measured before, during and 10 months after 199 wall installation
Figure 5-20 Total horizontal stress measurements taken during the period of wall installation 200
Figure 5-21 Pile installation sequence for the elastic analysis and Mohr circle showing calculation of correction for stress change measured on spade cell 201
Figure 5-22 Measured reduction in total horizontal stress normalised with respect to the in situ total horizontal stress 202
Figure 5-23 Reduction in total horizontal stress due to installation of pile nearest to spade cell only with distance from the wall compared with the elastic prediction 203
Figure 5-24 Total horizontal stresses measured by all spade cells before wall 204 installation and by those 1·275 m from the edge of the wall after wall installation
Figure 5-25 Change in total horizontal stress 205
Figure 5-26 Effective horizontal stresses measured by all spade cells before wall 206 installation and by those 1·275 m from the edge of the wall after wall installation
Figure 5-27 Change in effective horizontal stress 207
Figure 5-28 Total horizontal stress measured before, during and 10 months after wall installation 208
Figure 5-29 Total pressure and pore water pressure measured 1·275 m behind the wall during the construction period 210
Figure 5-30 Total pressure and pore water pressure measured 2·375 m behind the wall during the construction period 211
Figure 5-31 Total pressure and pore water pressure measured 3·475 m behind the wall during the construction period 212
Figure 5-32 Total horizontal stress and pore water pressure measured in front of the wall during the construction period 213
Figure 5-33 Measured bending moments and bending moments calculated from horizontal soil stresses within 10% of those measured 214
IX
Figure 5-34 Measured and estimated total horizontal stresses 215
Figure 6-1 Long-term total horizontal stress measured 1·275 m behind the wall 220
Figure 6-2 Long-term pore water pressure measured 1·275 m behind the wall 221
Figure 6-3 Long-term total horizontal stress measured 2·375 m behind the wall 222
Figure 6-4 Long-term pore water pressure measured 2·375 m behind the wall TY' ---'
Figure 6-5 Long-term total horizontal stress measured 3·475 m behind the wall 224
Figure 6-6 Long-term pore water pressure measured 3·475 m behind the wall 225
Figure 6-7 Long-term total horizontal stress measured in front of the wall 226
Figure 6-8 Long-term pore water pressure measured in front of the wall 227
Figure 6-9 Total horizontal stress and pore water pressure measured 1·275 m 228 behind the wall over period of storm drain installation
Figure 6-10 Total horizontal stress and pore water pressure measured 3-475 m 229 behind the wall over period of storm drain installation
Figure 6-11 Immediate response of spade cells nearest to excavation of storm 230 drain trench
Figure 6-12 Long-term reinforced concrete prop loads 231
Figure 6-13 Long-term RC prop loads corrected for the effects of creep 232
Figure 6-14 Long-term bending moments in Pile Y - gauges 1-14 233
Figure 6-15 Long-term bending moments in Pile Y - gauges 15-26 234
Figure 6-16 Long-term bending moments in Pile X - gauges 1-14 235
Figure 6-17 Long-term bending moments in Pile X - gauges 15-26 236
x
LIST OF TABLES
Table 3-1: Geological succession 34
Table 3-2: Soil parameters of the Atherfield Clay and Weald Clay 40
Table 3-3: Dates of main construction events 44
Table 4-1: Example of inclinometer data analysis and correction using face errors: 41·593 mAOD 99
Table 4-2: Flexural rigidity of concrete piles 105
Table 4-3: The cracking moment of the wall, Mer, calculated by different methods 106
Table 4-4: Values of a and b calculated for all gauges at chainage 89+205 m 111
Table 4-5: amount of strain occurring due to shrinkage and equivalent load indicated by this strain for the props at the instrumented section 112
Table 4-6: Values of constants for best-fit line to stiffness/time relationship (to 5 significant figures) 114
Table 4-7: Changes in deflection, 8, (mm) (relative to the toe) and changes in curvature, K,
(x 103m-I) (from the 5th order polynomial curve fit) over periods of pile cracking.
Positions where cracks have occurred are highlighted. 1 17
Table 4-8: Changes in RC prop load due to excavation directly under individual props 121
Table 4-9: Load at specific stages of construction 121
Table 5-1: Details of nadir sump excavation 165
Table 5-2: Measured and estimated total horizontal soil stress behind the wall 177
Table 5-3: Measured and estimated total horizontal soil stress in front of the wall 178
Table 5-4: Measured and calculated bending moments 178
Table 5-5: Increase in prop load over period where no construction activities were carried out during Excavation Phase 1 179
Xl
PAPERS ARISING FROM THIS THESIS
Clark, J., Richards, D.J. and Powrie, W. (2004). Wall installation effects - preliminary
findings from a field study at the CTRL, Ashford. Proc. of the Skempton Memorial
Conference, London.
Richards, D.J., Clark, J., Powrie, W. and Heyman, G. (2005). An evaluation oftotal
horizontal stress measurements using push-in pressure cells in an overconsolidated clay
deposit. Proc. Inst. Civ. Engrs. Geotech. Engng - acceptedfor publication.
Clark, J. and Richards, D.J. (2005). Measurement of bending moments in concrete. Proc.
16th Int. Con! Soil Mech. Grnd Engng., Japan.
Richards, D.J., Clark, J. and Powrie, W. Installation effects of a bored pile wall in
overconsolidated clay. Submitted to Geotechnique.
XlI
ACKNOWLEDGEMENTS
First I must thank my supervisor David Richards for his valuable support and
encouragement throughout the fieldwork, analysis and write-up periods of this work. I
would also like to thank William Powrie and Chris Clayton for advising me and all three
for being a fantastic combination of mentors.
The work described in this thesis was carried out with the support of the Engineering and
Physical Sciences Research Council, (EPSRC), Rail Link Engineering, Union Railways
and Skanska.
I would particularly like to thank, Howard Roscoe, Gary Holmes (who's invaluable
support as a surrogate supervisor will not be forgotten), Fleur Loveridge, Hilary Shields,
Adam Chodorowski, Alex Pendleton, Vernon Pilcher, David Twine and the site staff at
Ashford Contract 430. I would like to thank Richard Wilson for collecting the bulk of the
very high quality inclinometer readings.
I would like to thank the Geotechnical Group the many other members of the School of
Civil and Environmental Engineering who have made my experience working at the
University of Southampton so enjoyable. Of particular note are Harvey Skinner, Antonis
Zervos, Michelle Theron, Martin Rust, Geoff Watson, Joel Smethurst and my office
mates.
Thank you to my parents and brother for leaving me to it when I asked, for help with proof
reading, for their constant support, and particularly for putting me up and feeding me,
often at late notice, during the fieldwork period.
If it wasn't for Nellies heroes I would have completed this work much sooner, but would
be a much poorer soul for it.
Thanks and love go. to Jon for the support, for the encouragement during the despair, for
sharing my excitement throughout the triumphs and for understanding what it is all for.
Xlll
1 INTRODUCTION
1-1 In situ embedded retaining walls
In situ embedded retaining walls are formed by installing a structure in a pre-excavated
cavity in the ground and removing the soil from one side of the structure to form a vertical
retaining wall. The term in situ is used to indicate that the wall has been constructed on
site from raw materials (fresh concrete and steel reinforcement). To provide stability, the
bottom of the wall remains embedded in the soil and sometimes props are used, for
example at the top ofthe wall, to provide extra support. These walls are typically used to
form basements and cuttings in urban areas throughout the world, where space is
restricted.
Traditionally, in situ embedded retaining walls have been designed using limit equilibrium
techniques, which are known to provide sound design solutions for walls installed in sand
and normally consolidated clays. More recently finite element techniques have been used
during design and to back analyse existing walls. Back analyses of walls constructed in
overconsolidated clays (which, due to their stress history, have a high horizontal to
vertical stress ratio compared to other natural soil deposits) have generally calculated
much higher bending moments and prop loads than both those obtained using
conventional limit equilibrium methods based on fully active pressures behind the wall
and those observed directly in the field (e.g. Potts & Fourie, 1984 & 1985; Tedd et 01.,
1984).
There are many uncertainties associated with the design of in situ embedded retaining
walls in overconsolidated deposits, for example: the effect of their installation on the stress
state of the surrounding soil; the equilibrium pore water pressures and their effect on the
overall wall stability; and the long-term horizontal stress acting on the wall. These issues
have been the subject of considerable research over the last few decades, including several
projects which used instrumentation andlor in situ testing to investigate the behaviour of
walls installed in overconsolidated clays (e.g. Garrett & Barnes, 1984; Tedd et ai., 1984;
Symons & Tedd, 1989; Ng, 1992; Symons & Carder, 1993; Carswell etai., 1993). In
order to further investigate the long-term behaviour of retaining walls, attempts have been
made to analyse walls already in service (Symons & Tedd, 1989; Carder & Symons, 1989;
Symons & Carder, 1990).
Some of these field studies have investigated the effect of in situ embedded retaining wall
installation on the stress state of the surrounding soil (e.g. Tedd et ai., 1984; Symons &
Carder, 1993) as it is generally accepted that the effect of installing such a wall influences
its subsequent behaviour in terms ofloads and bending moments (Gunn et ai., 1993;
Powrie & Kantartzi, 1996). Significant reductions in horizontal stress were observed in the
field studies. In addition, wall installation may cause significant ground movements
(which may be highly unacceptable) and its contribution to the recent stress history of the
soil will affect the subsequent stress-strain response of the soil (Powrie et at., 1998). Using
finite element analysis, Powrie & Li (1991) used a simplified technique to model wall
installation and calculated smaller wall bending moments than those obtained by Potts &
Fourie (1984 & 1985), which were closer to those measured in the field. However, the
process of wall installation in panels or piles is complex and three dimensional, so that the
magnitude, extent and longevity of the stress reduction associated with in situ wall
installation are all highly uncertain issues.
Many design standards are used for the design of in situ embedded retaining walls
(including CIRIA 104 (Padfield and Mair, 1984); CIRIA C580 (Gaba et ai., 2003);
Eurocode 7, (British Standards Institution, 1995) and BD42 (Department of Transport,
2
2000) and each contains differing advice on the method of analysis, use of factors of
safety and selection of input parameters. The overall stability of these walls and conditions
at collapse have been studied in depth (e.g. Burland et aZ., 1981; Symons, 1983; Bolton &
Powrie, 1987; 1988), however the number of standards in use illustrates clearly that there
are still many uncertainties as to the best method for design.
A better understanding of the changes in stress that occur on installation of an in sitll
retaining wall, during excavation in front of the wall and in the long-term, could result in
better estimates of prop loads, wall bending moments and ground settlements than were
possible in the past, and lead to more economical designs. In this thesis the results from a
field study carried out on a section of in situ embedded retaining wall which forms part of
the Channel Tunnel Rail Link at Ashford, Kent, are presented and discussed. Strain gauges
were used to measure permanent and temporary prop loads and wall bending moments,
and push-in spade-shaped pressure cells were used to measure total horizontal stress and
pore water pressure in the soil adjacent to the wall. Conclusions are drawn regarding the
magnitude, pattern and longevity of horizontal stress changes due to wall installation and
the overall stability of the wall. Data collection is ongoing, and data that describe the
performance of the wall and the soil stresses existing 6 years after the retaining wall was
installed and 4 years after construction was completed are included in this thesis.
Observations are made on the long-term behaviour expected from consideration of the
measurements taken in the 4 years since construction was completed.
1-2 Measurement of horizontal stress
A number of previous retaining wall fieldwork studies utilised push-in spade-shaped
pressure cells (commonly known as spade cells), to measure horizontal soil stresses as
they are relatively cheap, easy to install and give reasonably reproducible readings (Tedd
& Charles, 1981). They were originally designed for use in normally consolidated clays
but are now frequently used in stiff overconsolidated clays, although in such deposits it is
known that they overestimate the magnitude ofthe soil stress due to the complex localised
stresses created during installation (Tedd & Charles, 1983). Attempts have been made to
predict the amount by which spade cells over-read in a particular material by relating the
over-reading to soil strength (Tedd et ai., 1990; Ryley & Carder, 1995), but the data are
rather scattered.
3
Due to the considerable uncertainty regarding the magnitude of the over-reading and the
factors that may affect it, it is advisable to directly determine this over-reading wherever
possible until more data are available. As part of the work for this thesis a study was
carried out to evaluate the magnitude of the over-read given by a spade cell installed in
Atherfield Clay - a stiff, overconsolidated clay - which exists at the site of the CTRL at
Ashford. A spade cell was installed horizontally in the ground, aligned to measure vertical
stress. The soil above the spade cell was excavated in stages over a period of several
weeks, and at each stage the overburden was calculated and compared with the reading in
the spade cell. Additionally, measurements of in situ horizontal stress obtained using the
spade cells installed during the main instrumentation project have been compared with
self-boring pressuremeter readings. In line with other recent research, the over-read due to
the installation process has been expressed in terms of the undrained shear strength of the
soil.
1-3 Channel Tunnel Rail Link
The Channel Tunnel Rail Link (CTRL) is the largest construction project in the UK and
Britain's first new railway for over a century. It consists of 109 km of railway which starts
at the Channel Tunnel entrance at Folkestone and ends at St. Pancras station in Central
London (see Figure 1-1). It is being constructed in two sections: Section 1 consists of74
km of track running from the Channel Tunnel to North Kent. Construction began in
October 1998 and Section 1 opened in September 2003. There are two stations included in
Section 1, at Ashford in mid-Kent and Ebbsfleet in North Kent, just south of the River
Thames. Section 2 takes the CTRL under the River Thames and through London to St
Pancras, with a station in North London at Stratford. Construction of Section 2 began in
July 2001 and is due to be completed in early 2007.
A quarter of the total route is in tunnel, including 1·7 km of cut-and-cover tunnel and
propped cutting in Ashford, which forms the approach to Ashford International Station
from London.
4
1-4 Objectives
The objectives of this project are:
• To collect continuous field data, over the entire period of construction and into the
long-term, from an instrumented section of a propped in situ embedded retaining
wall in an overconsolidated clay.
• To investigate the changes in the horizontal stresses and pore water pressures in
the soil during installation of the bored piles that form the retaining wall.
• To investigate the wall movements and the development of prop loads and bending
moments associated with a retaining wall embedded in an overconsolidated clay,
and to relate these data to the horizontal stresses and pore water pressures
measured behind and in front of the monitored wall section.
• To analyse the observed performance.
• To investigate the performance of the spade-shaped pressure cells used in this
study.
This thesis describes work carried out towards the realization of these objectives, as well
as suggestions for future work.
1-5 Outline of report
Chapter 2 contains a review of retaining wall design, with references to previous
instrumentation projects, model testing and studies that used finite element techniques to
analyse the performance of retaining walls. This chapter also includes details of the use of
spade cells to measure horizontal stresses in overconsolidated deposits.
In Chapter 3 the case study is described. This chapter includes details of the local geology,
the geometry of the structure, the construction sequence and details of the instrumentation
used to monitor the performance of the structure and the stress changes in the adjacent
soil.
In Chapter 4 the structural monitoring is described in greater detail. The methods by which
the data have been calibrated and evaluated are described. The wall bending moment, wall
5
deflection and prop load data at various significant stages during construction are
presented.
In Chapter 5 the horizontal soil stress measurements are described in greater detail. The
instrumentation used to measure horizontal soil stresses and pore water pressures is
evaluated by means of a study in which the readings from a spade cell aligned to measure
vertical stress were compared with the estimated overburden acting on it (calculated from
bulk density measurements). The horizontal stress and pore water pressure data collected
during wall installation and excavation of the cutting are presented and analysed.
In Chapter 6 the long-term data collected from the spade cells and the RC props up to
November 2005, more than 4 years after construction was completed, are presented.
Chapter 7 contains conclusions arising from this research and recommendations for future
work.
6
5'
....J
StratfonL.···· .. -.... -(.$t Pancta's
Figure 1-1: Map showing the route of the Channel Tunnel Rail Link
2 LITERATURE REVIEW
2-1 Introduction
This chapter contains a general review of retaining wall design, including the effects of
wall installation on in situ horizontal soil stress. Work undertaken to study retaining wall
behaviour in similar field studies and using finite element analysis techniques is
summarised, and the sometimes differing advice provided by the most regularly used
design guidelines is described. This chapter also includes a background to the use of push
in spade-shaped pressure cells (spade cells) to measure horizontal stresses in
overconsolidated deposits. Previous use of spade cells in similar monitoring projects and
the measures taken to determine the over-read that occurs when spade cells are used in
overconsolidated clays are described.
8
2-2 Review of investigations into retaining wall behaviour
2-2-1 Background
There are essentially two design stages required for embedded retaining wall design:
1. determination of the depth of embedment required to prevent overall collapse of
the soil/structure as a whole and
2. design of the wall member and ancillary elements such that they are strong enough
to support the consequential forces and bending moments induced in service.
A limit equilibrium analysis is usually used to calculate the depth of embedment of the
wall, and a factor of safety is applied to one or more of the variables involved to ensure
against global collapse. The structural elements are then designed to carry the bending
moments and loads which are expected as a result of the geometry determined by the limit
equilibrium analysis. Separate consideration is given to the requirements for the working
condition and the ultimate failure state, as deformations occurring under the ultimate state
may be well beyond those that are acceptable under working conditions.
The following sections contain a brief outline of retaining wall design in which the various
components of design and the choices that must be made are discussed.
2-2-2 Limiting conditions
Most modem codes of practice use limit state design principles, where limits are set, e.g. a
maximum soil loading or a maximum wall deflection, and the corresponding structural
forces are found by assuming the structure is on the verge of exceeding these criteria. As
previously mentioned stability and displacement are considered separately; stability is
considered to be the primary aim (the ultimate limit state, ULS) and displacements are
usually only considered as a secondary serviceability issue (serviceability limit state,
SLS). However, displacements can often become a ULS, for example, if the displacements
cause ground movements that affect nearby structures or services, or if they cause
unsightly conditions for the structure. In such cases the serviceability requirements often
dictate the construction method utilised, e.g. the construction sequence, the propping
methods and the type of wall. The serviceability requirements are different for each
9
project, and therefore the designer must have a full understanding of the overall project
and surrounding factors before the serviceability criteria can be defined.
The principle of analysing retaining wall behaviour by determining the forces present
when the structure is on the verge of collapse began with Coulomb (1776), who developed
an upper bound solution for retaining wall analysis by assuming a planar wedge failure
mechanism (Figure 2-1) and derived the limiting force as a function of depth behind the
wall. Coulomb's solution produces sufficiently accurate results despite the inaccurate
assumption that the wedge has a plane failure surface. More recent work in which the
lower part of the sliding wedge was assumed to have a curved boundary, as is observed in
model tests, produced equations that were considered overly complicated for practical use
(Terzaghi, 1943).
Rankine (1857) developed a lower bound solution by assuming that the earth pressures
acting on the wall held it at the limit of equilibrium. He derived limiting active and passive
earth pressure coefficients (Ka and Kp respectively), given by the ratio of effective
horizontal stress l, cr'h, to effective vertical stress, cr'v (Equation 2-1) and determined the
orientation of the surfaces of sliding. (The' at rest' or in situ earth pressure coefficient is
denoted by Ko.) The active state occurs when the rate of increase of horizontal earth
pressure is slower than for the vertical earth pressure (in absolute terms), in this case
behind a retaining wall, and the passive state occurs where the rate of increase of
horizontal earth pressure is faster than for the vertical earth pressure, e.g. in front of a
retaining walL Coulomb and Rankine's solutions are identical for a smooth wall with a
horizontal surface to the retained soil and a linear lateral pressure distribution.
, K = 0' h
0" v
Equation 2-1
Coulomb's method underestimates the active pressure and overestimates the passive
pressure, and hence may tend to an unsafe solution. Because Rankine's method relies on
static equilibrium it cannot take account of wall friction, unlike the Coulomb method, and
therefore overestimates the active pressure and underestimates the passive pressure,
producing an inherently safe (although unnecessarily costly) embedment depth. To
account for this, earth pressure coefficients have been developed which can be applied to
1 where effective stress is given by a' = a - u, where a is the total stress and u is the pore water pressure
10
K to take wall friction into consideration (British Standards Institution, 1995; Gaba el ai.,
2003).
Idealized stress distributions used in limit equilibrium analyses are shown in Figures 2-2
and 2-3. The fixed earth support method assumes that fixity develops close to the wall toe
so there is no lateral movement at this point. The free earth support method assumes that
the wall toe is free to move laterally. Unpropped embedded retaining walls rely entirely on
an adequate depth of embedment for their stability and so the fixed earth support method
must be used. Retaining walls propped at the crest tend to fail by rotation about the prop
level, so the free earth support method is usually used. It has been suggested that the fixed
earth support method can be used for analysis of propped walls: this is discussed in
Section 2-2-4.
2-2-3 Development of active and passive pressures
The limiting earth pressure coefficients for the active and passive states, Ka and Kp
respectively, are given in Equations 2-2 and 2-3, where ¢/ is the soil strength or angle of
friction and is given in degrees.2 (These equations are derived from consideration of the
Mohr circle of stress for a soil element on the verge offailure; see for example Powrie,
2004).
K = I-sin¢' a l+sin¢'
Equation 2-2
K =l+sin¢' p I-sin¢'
Equation 2-3
In order for active and passive pressures to be mobilized it is necessary for deformation or
displacement of the wall to take place. The amount of displacement necessary depends on
the type of soil and its overconsolidation ratio. 3
Soils such as sands and normally consolidated clays are close to their active limit at the in
situ state, i.e. the horizontal earth pressures are comparatively low (Ko < 0'7). In such
2 Tan ~ is analogous to the coefficient of friction, f..l, in the equation: F = f..l N where F is a force pushing against a normal force, N. 3 The overconsolidation ratio is given by: OCR = (J'y (max. preyious) / (J'y (current).
11
materials only a small movement of the structure is required to achieve full active
conditions behind the wall, but relatively large movements, which may be unacceptable
under working conditions, are required to achieve full passive conditions in front of the
wall. This was shown in large-scale model tests (Terzaghi, 1934) in which a wall was
rotated into and away from a bed of sand; the results are shown in Figure 2-4.
Overconsolidated clays (Ko > 1) have high horizontal earth pressures and are therefore
often closer to the passive limit of the soil, so only small movements of the structure are
needed to achieve passive conditions in front of the wall, but large, potentially
unacceptable movements are necessary to achieve active conditions behind the wall. Potts
& Fourie (1985) used finite element analysis to show that for an overconsolidated clay
with Ko = 2, a similar amount of movement is required to reach passive and active
conditions (see Figure 2-5). However bending moments measured in the field (Tedd e/ 0/.,
1984) and in centrifuge model tests (Bolton and Powrie, 1988) have not shown this to be
true in practice. In addition, Simpson (1992) argues that this study should be treated with
caution because it was carried out using a linear elastic soil model until it reached its
maximum shear strength, therefore not allowing for large stiffness at small strains (as
discussed by Burland et af., 1979).
Powrie et af. (1998) undertook triaxial tests on samples of overconsolidated kaolin to
investigate the total stress paths undertaken by elements of soil in front of and behind a
retaining wall during wall installation and excavation in front of the wall. They found that
the process of wall installation has a considerable influence in reducing the horizontal
stresses and therefore predicted that during excavation in front of a retaining wall, only
small movements of the wall are required to bring the earth pressure distribution close to
its active limit.
The factors that affect the extent to which passive or active pressures can be achieved are
still not well understood, particularly in the case of overconsolidated clay. In addition, the
distribution of stress on a retaining wall varies significantly from the idealised stress
distributions in Figures 2-2 and 2-3, as discussed in the following section.
2-2-4 Distribution of earth pressures
There has been considerable debate concerning the distribution of earth pressures on
retaining walls, both under working conditions and at collapse. Work by Terzaghi (1943,
12
1954), Tschebotarioff(1951) and Rowe (1952,1955 & 1956), studied the distribution of
pressure on retaining walls and the effect of wall flexibility on the bending moments and
prop/anchor loads.
As previously mentioned, some authors (e.g. Terzaghi, 1943) recommend the use of the
fixed earth support method for the design of propped walls, because the increased fixity at
the wall toe affects the distribution of pressure on the wall by raising the point of
application of the passive pressure, thereby decreasing the flexibility of the pile and hence
also the maximum bending moment. Terzaghi (1943) also suggested that for a flexible
retaining wall (particularly referring to steel sheet piles anchored near the top) and
assuming fixed earth support, there can be a further redistribution of earth pressure in
certain soils which causes an increase in pressure at the top of the wall around the position
of the restraint, and a decrease in pressure in the middle of the wall (see Figure 2-6). This
pressure distribution is a form of arching and is maintained solely by shear stresses.
Terzaghi stated that the bending moment calculated using the pressure distribution
indicated by the curved line in Figure 2-6(a) is less than half that calculated using the
linear pressure distribution.
Rowe (1952) undertook model tests with walls of varying flexibility in dense and loose
sand (Ko < 0·5) and compared the measured bending moments with those calculated from
a limit equilibrium calculation assuming free earth support and triangular pressure
distributions in front of and behind the wall. He showed that for the most flexible walls the
observed bending moments were much lower than the calculated values, and that as the
flexibility of the wall decreased the bending moment increased to that calculated by the
limit equilibrium analysis. This occurs because for a flexible wall the deflection at
excavation level is much larger than at toe level, and consequently more passive pressure
is mobilized at the top of the zone of soil in front of the wall than for a stiffer wall where e
the deflection at excavation level and the toe are similar (Figure 2-7). Rowe (1952) noted
that this effect also occurred with a rise in soil density (and hence soil stiffness).
Rowe (1952) studied the effect of a small anchor yield on the horizontal earth pressure
behind a retaining wall. He showed that an anchor yield of 0·1 % of the wall height led to a
breakdown in the arching that produces Terzaghi's pressure distribution and a return to the
triangular Coulomb pressure distribution. He concluded (and Terzaghi (1954) agreed) that
it was not justified to rely on the reductions indicated by the redistribution of pressure.
13
The debate on the use of the fixed earth support method for the analysis of propped or
anchored retaining walls has continued. Decreasing the flexibility of the pile decreases its
movement and therefore the ability of the soil to reach its active and passive limits. The
relatively old retaining wall design standard CIRIA 104 (Padfield and Mair, 1984-
discussed in Section 2-3) recommends against use of the fixed earth support method for
the design of propped walls embedded in clays, stating that it is not appropriate because of
the long-term deformation characteristic of the soil. However, the most recently published
guidance on embedded retaining wall design, CIRIA C580 (Gaba et at., 2003), states that
since modem support systems are somewhat stiffer it is now more likely that such a
pressure distribution could exist.
Since the development of active (and passive) pressures depends on the degree of wall
movement, there is some doubt that these pressures can be realised in overconsolidated
deposits with a stiff wall and propping system as little movement is likely to occur. The
work described above is, to some extent, of limited application to walls embedded in
overconsolidated deposits because it was based on the assumption that active conditions
would be met. In addition, the limit equilibrium methods used to calculate forces in
cantilever and singly propped walls can not be used for statically indeterminate multi
propped walls; these must be designed using iterative computer aided techniques which
give consideration to soil-structure interaction.
Potts & Fourie (1985) used finite element methods to investigate the influence of Ko on
bending moments and prop loads. They first carried out an analysis with a similar
geometry and soil profile to Rowe's, which produced results which were in good
agreement. They then ran further analyses using the same geometry but with a Ko of 2, and
found that increasing Ko produced very high bending moments, greater than the limit
equilibrium value. They also found that the bending moments increased further as the
stiffness of the wall increased. Potts & Bond (1994) also used finite element analysi s to
demonstrate that the bending moment and prop loads increase as wall stiffness and Ko
increase, and that for Ko > 0'5 the maximum bending moment and prop load are greater
than the values given by a limit equilibrium analysis. However, this study did not take into
consideration the effect of wall installation on horizontal earth pressures around a
retaining wall, which is discussed in the next section.
Richards & Powrie (1998) used finite element techniques to show that the construction
sequence can have an effect on ground movements behind the retaining wall during
14
excavation. They found that top down construction with early installation of a permanent
prop at the top ofthe wall, a temporary prop at the excavation mid-height and use of a
permanent prop at formation causes minimum ground movements behind the wall. This
may affect the amount of stress relief behind the wall and therefore the soil's ability to
achieve active pressures.
2-2-5 Change in horizontal earth pressure due to wall installation effects
The installation of a bored pile wall (or a diaphragm wall) in overconsolidated clay causes
stress changes in the ground by the following process. On boring, the horizontal stress (ail)
near the hole is reduced. If no support is used, ah at the edge of the borehole is reduced to
zero and in the short-term the borehole is held open by shear stresses in the soil. If the soil
is soft the hole may collapse quickly, so either a casing or bentonite slurry is used as
support until the concrete is poured into place. In this case, ah at the edge of the borehole
reduces to the value of the pressure exerted by either the casing or the bentonite slurry.
When concrete is poured, ah at the edge of the borehole will increase to the hydrostatic
pressure exerted by the wet concrete. During the curing process the heat of hydration
causes the concrete to expand, exerting an increased pressure on the edge of the borehole.
The concrete then cools, causing shrinkage, and a further pressure change can occur as the
soil may swell due to the changes in pore water pressure.
It is well known that the stress state in the soil surrounding an in situ retaining wall is
affected by the process of wall installation (Gunn et at., 1993; Symons & Carder, 1993;
Gourvenec & Powrie, 1999) and that the stress state of the adjacent soil following wall
installation may have a significant effect on the behaviour as calculated in a numerical
analysis (Potts & Fourie, 1984; Fourie & Potts, 1989; Powrie & Li, 1991). Wall
installation will affect the recent stress history of the soil and hence its subsequent stress
strain response (Atkinson et at., 1990; Powrie et at., 1998), and in soft soils may cause
significant ground movements in its own right (Stroud & Sweeney, 1977; Powrie &
Kantartzi, 1996).
Powrie (1985) discussed the change in horizontal pressure that might occur on
construction of a diaphragm-type retaining wall, and showed that a soil with Ko = 2 could
experience a reduction in horizontal stress that reduced Ko to just over 1. As previously
discussed in Section 2-2-3, Powrie et at. (1998) found that wall installation had a
significant influence on the horizontal soil stress, and that the recent stress history applied
15
by the excavation and concreting processes "move the stress state of the soil outside the
influence of its geological and pre-installation stress history." Furthermore Simpson and
Powrie (2001) noted that if the shear stresses that maintain a difference in the far-field and
near field horizontal stresses break down K will tend to no more than unity after
construction.
Tedd et al. (1984) reported results from instrumentation installed to monitor the behaviour
of a secant pile retaining wall during wall installation and excavation in front ofthe wall at
the Bell Common Tunnel on the M25. They found that ground movements during
installation of the retaining wall accounted for about 30% of the total movements that
occurred during the cut-and-cover tunnel construction, which indicates that stress relief
took place in the ground over this period. They also measured significant reductions in
horizontal earth pressure as a result of wall installation, although it was difficult to
establish the magnitude of these reductions due to difficulties arising from the construction
process.
During the field monitoring of other retaining walls in London Clay, Symons & Carder
(1993) measured changes in effective horizontal stress due to wall construction of 10% for
a bored pile wall (comprising 1·5 m diameter, 24 m long piles installed in London Clay)
and 20% for a diaphragm wall. Measurements of water pressure during excavation and
concreting showed that after an initial reduction, followed by an increase to levels
sometimes above pre-excavation levels, pore water pressures levelled out to values similar
to those measured prior to construction. This has also been observed in centrifuge model
tests of diaphragm wall installation processes (Powrie & Kantartzi, 1996).
Numerical analyses of in situ walls in which the effects of wall installation are neglected
generally give much higher bending moments and prop loads than both those obtained
using conventional limit equilibrium methods based on fully active pressures behind the
wall and those observed directly in the field (e.g. Potts & Fourie, 1984 and 1985; Tedd et
ai., 1984). Modelling wall installation by simply reducing the pre-excavation horizontal
stress across the entire mesh (Powrie & Li, 1991; Richards and Powrie, 1994) may reduce
the calculated wall bending moments. However, the process of wall installation in panels
or piles is three-dimensional and the magnitude, extent and longevity of the stress
reduction associated with in situ wall installation are all highly uncertain. Reducing the
horizontal earth pressure coefficient across the entire width of the finite element mesh is at
best a highly simplified approximation.
16
U sing a plane strain analysis to model the process of wall installation leads to over
predictions of the magnitude of soil displacements and the degree and extent of horizontal
stress relief (Gunn & Clayton, 1992; De Moor, 1994; Ng et at., 1995). Therefore some
authors have tried to model wall installation in three-dimensions. Ng (1992) modelled
vertical and horizontal sections of a retaining wall in plane strain in order to investigate
the three-dimensional nature of wall installation effects. He found that horizontal arching
plays an important role in restricting ground movements, and that if this effect is ignored
ground movements will be over-predicted. He also noted that in clays with very high
stiffness at small strains, much stress relief can occur with only a small movement. Using
three-dimensional finite element analysis techniques Gourvenic & Powrie (1999) showed
that the installation of a diaphragm wall panel affects the horizontal earth pressures on
adjacent panels. They also found that soil movements increase markedly for diaphragm
panel shape ratios (the vertical dimension (depth) to the dimension in the direction along
the wall (width)) ofless than 3, i.e. soil arching is best achieved with a deep, narrow panel
(the extreme of which is a pile) rather that a short, wide one.
A better understanding of the changes in stress that occur during installation of a retaining
wall could result in more realistic estimates of prop loads, wall bending moments and
ground movements than have been possible in the past. In this section the data collected
during wall installation are described and discussed, and conclusions are made regarding
the magnitude, pattern and longevity of horizontal stress changes due to the installation of
walls of this type.
2-2-6 Behaviour of embedded walls in the longer term
There is some concern that the high horizontal stresses in an overconsolidated deposit may
become re-established in the long-term, despite the reductions that occur during retaining
wall installation and subsequent excavation in front of the wall. This is thought to occur
because the shear stresses maintaining the difference in the far field and near field
horizontal stresses may break down. As pointed out by Simpson and Powrie (2001) it
seems unlikely, particularly in the design lifetime of the wall, that if the horizontal shear
stresses break down then the vertical shear stresses necessary to produce a Ko of more than
1 will not exist either. Therefore the long-term value of K can be no more than 1.
In order to determine the long-term stress state of the soil around a retaining wall, and
hence the longevity of the reduction in stress due to wall installation, studies have been
17
undertaken on walls that have been in service for a number of years. Analysis of the long
term behaviour of the Bell Common Tunnel (Symons & Tedd, 1989) showed insignificant
changes in earth pressure behind the wall and small decreases in earth pressure in front of
the wall in the four years after construction. Very small changes in pore water pressure
were measured on both sides of the wall.
Symons & Carder (1990) describe data obtained at two retaining wall sites: a cantilever
wall and a wall propped just below the carriageway, several years after construction was
completed. Measurements of total pressure and pore water pressure were taken in order to
determine whether equilibrium conditions had been reached. For the cantilever wall they
had, but for the propped wall pore water pressures were still gradually changing.
Measurements taken 150 m and 1·5 m from the cantilever wall showed that significant
stress reliefhad occurred due to construction/installation. However, for the propped wall,
measurements taken at 16 m and 1·5 m from the wall suggested no stress relief had
occurred in this case.
2-3 General overview of retaining wall design standards
A number of standards and guidelines regarding the design of embedded retaining walls
are in general use, and they sometimes provide conflicting advice on matters such as:
general approach to design, choice of soil parameters, choice of safety factors, estimation
of long-term pore water pressures, determination of wall bending moments and the
magnitude and distribution of horizontal earth pressure. Some of the guidance documents
currently used include:
• BS 8002, the British Standards Code of Practice for earth retaining structures
(British Standards Institution, 1994/2001);
• CIRIA 104 (the Construction Industry Research and Information Association
Report 104): Design of retaining walls embedded in stiff clay (Padfield & Mair,
1984);
• British Steel Piling Handbook (1997);
• The Highways Agency Design Manual for Roads and Bridges - Volume 2, Section
1, Part 2 - BD 42 Design of embedded retaining walls and bridge abutments
(Department of Transport, 2000);
18
• Eurocode 7. Geotechnical design, Part 1: General rules. (British Standards
Institution, 2004);
• elRIA C580, Embedded retaining walls: guidance for more economic design
(Gaba et al. 2003). This supersedes CIRIA 104.
CIRIA 104 has proved to be an extremely influential report which is used by 91 % of
design engineers (Gaba, 2002), usually in conjunction with one or more of the other more
recently released design guidelines. It was written strictly for the design of singly propped
or cantilever walls embedded in stiff overconsolidated clay, but its principles have been
applied to a wide range of wall types, including multi-propped embedded walls and non
embedded walls. It provides design guidance for permanent and temporary walls. As part
ofthe development work for Eurocode 7, designers from countries across Europe were
asked to design a retaining wall according to their country's normal design guidelines for a
specific project. The UK design, based on CIRIA 104, produced a longer wall than most
of the others, leading to questions regarding the severity ofthe recommended values for
the factor of safety on soil strength (Fs - described later in Section 2-3-2) in CIRIA 104.
BS 8002 is the second most popular guideline after CIRIA 104, being used by 70% of
design engineers. It was originally only applicable to retaining structures with a retained
height of up to 8 m, but its latest amendment (2001) has increased this to 15 m. Some
elements of the design specification in BS 8002 are thought to be rather onerous,
particularly the unplanned excavation and surcharge requirements. These are being revised
for a forthcoming version.
The Eurocodes are a set of standards which cover both structural and geotechnical design
requirements, where Eurocode 7 is the geotechnical constituent. The codes have been
written with the aim of allowing the design process to proceed fluidly from geotechnical to
structural design without difficulty or confusion. The Eurocodes were written to be a
consistent, internationally agreed set of codes for use throughout Europe and the rest of
the World, so that legal disputes over choices made in design can be avoided.
The British Steel Piling Handbook was primarily written for the design of permanent and
temporary sheet pile walls.
BD 42 covers the design of earth retaining structures where the "main stability is provided
by a significant length of wall stem embedded in the ground" and adopts limit state
19
principles. It states how to "use ... BS 8002 and CIRIA 104 in a way which is compatible
with ... BS 5400 (British Standard for steel, concrete and composite bridges, 2000)."
CIRIA C580 has been compiled with the intention of forming a comprehensive state-of.
the-art replacement for CIRIA 104, reducing the need for cross-referencing between
different design guidelines. It covers the design of temporary and permanent cantilever,
anchored, single and multi-propped walls which are embedded in stiff clay, and other tine
and coarse grained soils. Walls embedded in soft clay and rock are considered outside the
scope of the report.
2-3-1 Choice of soil parameters
Soil parameters for a particular site are determined from a combination of: previous
experience and publications; direct measurement of parameters from samples collected
during site investigation (usually expensive and therefore of limited number) and indirect
measurement of more easily and cheaply collected data for which correlations with the
required parameters have been suggested. The most commonly required parameters are the
undrained shear strength, cu, the effective angle of friction, <1/ and the effective cohesion,
cr. Determination of these parameters is a difficult process where the cost/output
relationship between the various sample and data collection techniques available must be
carefully balanced.
A designer should have a good understanding of the correlations between data collected
from difference sources, the factors that influence the values and the uncertainties and risk
associated with the often limited data. They can then use their 'engineeringjudgemenC to
select suitable parameters. The more recent design guidelines have attempted to advise on
this process and to make the designer think in terms of the probability of the parameter
having a certain value or range of values.
In CIRIA 104 two alternative design approaches are put forward; the designer can either
use 'moderately conservative' or 'worst credible' soil parameters (load and geometry are
also selected on these bases), with less conservative safety factors being applied for the
latter approach. 'Moderately conservative' is described as being a conservative best
estimate, and 'worst credible' is "the worst which a designer could realistically believe
might occur ... a value which is very unlikely to be exceeded". BD 42 requires the
20
consideration of moderately conservative and worst credible parameters in conjunction
with CIRIA 104.
BS 8002 requires consideration of the 'representative peak', which is generally considered
to be analogous with the moderately conservative and the critical state strength
parameters. The more onerous parameters are selected (after the relevant safety factors
have been applied) and only one design calculation is undertaken. Eurocode 7 uses
'characteristic' values for the geotechnical parameters, which are described as "a cautious
estimate ofthe value affecting the occurrence of the limit state".
The language varies, but in essence the emphasis is for a designer to use their experience
to balance low risk with economy.
2-3-2 Application of safety factors
Once the soil parameters have been given design values, a factor of safety, F, is applied to
one or more of the parameters in the ULS equation so that an adequate margin of safety is
supplied within the embedment depth. There are several different approaches to applying
this factor of safety: a factor on passive pressure, a factor on net pressure, a factor on
embedment depth andlor a factor on soil strength. Full details of how these different safety
factors compare with one another for different soil strengths are given by Burland el al.
(1981) - a summary is given below. They go on to suggest a revised definition of the
factor of safety for passive failure, Fr.
The factor on passive pressure method, Fp, (used in CP 2) employs a factor on Kp which is
commonly taken to be 2. This is based on the findings of Terzaghi (1934), as described in
Section 2-2-3, that (in sand) more wall movement is required to mobilize full passive
pressures than active pressures. Since overconsolidated clay is very likely to reach its
passive limit in front of the wall, it would be uneconomic to apply a factor of safety on
passive pressure in such a deposit.
The net pressure method, described in the British Steel Piling Handbook, uses the net
horizontal pressure distribution for walls propped at the crest. The depth of embedment is
chosen by equating the moment about the prop ofthe net pressure in front of the wall with
the moment of net pressure behind the wall factored by Fnp (normally 2). Burland el al.
(1981) showed that using this method a value of Fnp = 2 leads to a factor of safety on shear
strength of generally less than 1·1 for both drained and undrained conditions. CIRIA 104
21
expressly advises against the use of the net pressure method. Simpson and Powrie (2001)
state that the net pressure method is fundamentally unsound and potentially dangerous.
As indicated by the name, the factor on the depth of embedment, Fd, requires the
calculated wall depth to be increased (e.g. by a factor of 10%). CIRIA 104 advises that if
this method is used then because it is empirically based it should be checked against one
of the other design methods.
The use of a factor on soil strength, Fs, is consistent with the way in which factors of
safety are applied in structural design. A factor is applied to the main soil parameters: tan
¢l; the undrained shear strength, Cu; and the effective cohesion, c'; and in effect increases
the active pressure and reduces the passive pressure assumed in design. CIRIA 104
provides values for Fs. This method is thought to be the most appropriate approach to
design (Simpson & Powrie, 2000) and is the method recommended in CIRIA C580.
(CIRIA 104 additionally requires that an unplanned excavation is applied in front of the
wall, which should be the lesser of 10% of the retained height of the wall or 0·5 m, and
that a minimum surcharge of 10 kPa must be applied to the surface of the retained soil.
This produces a rather onerous loading condition that leads to uneconomical designs.)
BS 8002 focuses on serviceability requirements and in turn uses mobilization factors, M,
which are essentially analogous to Fs, but are designed to restrict displacements for the
serviceability limit state. The revised method devised by Burland et al. (1981) gives
results consistent with Fs, and so appears to give no real advantage over the use of Fs in
design.
Eurocode 7 uses limit state principles and partial factors with a design approach which is
expressed as:
The Effects of Actions must be Resisted.
In terms of a retaining wall, for example, the' actions' are the loads on the back of the
wall; the 'resistance' is the resistance provided by the ground in front of the wall and the
wall interface friction, etc.; and the 'effect' is the bending moment induced in the wall and
the prop loads. Eurocode 7 includes three design approaches which allow for partial
factors to be applied to different combinations ofthe Actions, Effects and/or Resistances.
It is expected that Design Approach 1 (DAl) will be recommended for use in Britain. In
DAI partial factors are generally applied to the primary variables, i.e. the ground strength,
22
however for piles and anchors the Resistances, e.g. bearing capacity, are factored.
Eurocode 7 also includes factors that allow for pile design from sensible interpretation of
load tests.
2-3-3 Calculation of design bending moments
There are two main methods in common practise for calculating the bending moment in a
wall in Britain. In the first, recommended in CIRIA 104, the wall length is calculated
without using safety factors, i.e. the wall embedment depth is found using a limit
equilibrium calculation with unfactored variables. The bending moment derived using this
depth of embedment is then multiplied by a safety factor of 1·4 or 1·5 for ULS design of
the wall section. In the second method, the wall length derived from using the factored
parameters for the stability calculation is used to calculate the bending moment, which is
then directly used for the ULS design. The second method often gives a higher bending
moment than the first, meaning that if the wall was ever called upon to use its full
embedment depth, its strength would not be sufficient to allow it, and it would fail in
bending. This inconsistency of length and strength means the walls are either longer than
they need to be, or not strong enough (Simpson & Powrie, 2000).
CIRIA C580 and Eurocode 7 use the same method for calculation of the SLS bending
moment as CIRIA 104, but Soil Structure Interaction (SSI) analyses may be used to
calculate the pressure on the retaining wall and therefore the redistribution of earth
pressures due to arching, etc. can be taken into account, in contrast to other methods that
use simple linear earth pressure distributions. In addition, CIRIA C580 requires that the
wall reinforcement must not be curtailed at the point of zero bending moment, but should
be extended to the bottom of the pile. Then, instead of applying a factor of safety to this
bending moment for the ULS design, the designer must use the greater of: the value
obtained from the most onerous soil parameters expected; a factor of 1'35 times the SLS
values and the values calculated in consideration of a progressive collapse.
2-3-4 Advice on wall installation effects
The most widely used guidelines for the design of embedded retaining walls (CIRIA 104,
BS 8002 and Eurocode 7) all agree that installation of a wall affects the stress state in the
soil and that these effects should be considered during design, although they do not give
23
specific guidance about what type of stress changes may occur. CIRIA 104 notes that the
installation of a diaphragm wall may reduce the horizontal stress in the soil from its
original value. BS 8002 does not give any specific guidance on the stress change that
might occur due to the installation process, it only mentions that the ratio of horizontal to
vertical stress for the soil at rest should not be used as it is affected by the installation
process.
CIRIA C580 goes further, giving guideline values for the reduction in the in situ
horizontal earth pressure coefficient due to wall installation of 10% for bored pile walls
and 20% for diaphragm walls installed in overconsolidated clays. These values are based
on the work by Symons & Carder (1993) described earlier. It is clear that without further
measurements of these stress changes in the field, considerable uncertainties remain and
economy of design may not be fully achieved. CIRIA C580 also recommends that for
linear elastic soil-structure interaction analyses a lateral earth pressure coefficient of 1 '"is
likely to give reasonably realistic bending moments and prop loads". This suggestion in
part relies on the fact that in such analyses the stiffness under unloading is generally
underestimated.
2-4 Use of spade cells to measure horizontal stress in overconsolidated clay
2-4-1 Background
Spade cells are increasingly used to measure horizontal soil stresses as they are relatively
cheap, easy to install and give reasonably reproducible readings. However, pushing a
spade cell into the ground generates high local stresses due to the displacement of the soil
as the cell is advanced. These stresses reduce over time as the excess pore water pressures
generated during the undrained loading dissipate (Tedd et ai., 1990). In natural and placed
soft clays, readings stabilize within a few days and there is considerable evidence to show
that realistic values of total stress can then be measured (Massarsch (1975); Massarsch et
ai. (1975); Tavenas et ai. (1975); Penman & Charles (1981)). The use of spade cells in
stiff clay was initially questioned, as it was thought that even if they could be pushed into
stiff clay, the soil disturbance might be so great that the stresses would be vastly over
estimated (Tedd and Charles, 1981).
24
Tedd & Charles (1981) showed that it was possible to push spade cells into stiff London
Clay deposits, but that a period of up to one month was needed for excess pore water
pressures to dissipate. They reported that spade cells gave far more reproducible results
than self-boring pressuremeter tests, but that the recorded stress following dissipation of
excess pore water pressure was significantly greater than the true in situ value.
Tedd & Charles (1983) compared readings from spade cells installed to measure vertical
stress in stiff clay with the overburden acting on them calculated from the bulk density of
the soil, and concluded that the amount by which a spade cell will over-read is dependent
on the soil stiffness. Owing to the difficulties in determining the appropriate soil stiffness,
a correlation between the spade cell over-read and the undrained shear strength (ell) of the
soil was proposed. This was considered reasonable as the undrained shear strength of a
stiff clay is related to its stiffness, and it is a commonly determined soil parameter and
therefore widely available. A simple empirical correction of 0'5 ell was suggested,
although Tedd & Charles noted that where possible a direct site specific determination of
the spade cell over-reading in stiff clay, for example by comparison with self-boring
pressuremeter tests or calculation of overburden on a vertically aligned cell, is advisable.
In an experiment similar to that carried out by Tedd & Charles (1983), Ryley & Carder
(1995) pushed several pressure cells horizontally into London Clay to measure the vertical
soil stress at different depths, and compared the readings with the calculated overburden.
They found that a correction of 0·8 ell gave a closer fit for the cells in firm clay
(40 kN/m2 < ell < 75 kN/m2) and stiff clay (75 kN/m2 < ell < 150 kN/m2). In very stiff clays
(ell> 150 kN/m2), the cell overestimated the stress by more than 1·0 ell' They concluded
that for very stiff clays, the correction factor might be as high as 2·0 eu, and that the degree
of over-read might be affected by local changes in the soil structure such as high clay
content and plasticity. At the Bell Common Tunnel, Tedd et al. (1984) used a correction
factor of 0·5 ell for London Clay, which gave a close correlation with self-boring
pressuremeter results, but a correction of O' 3 ell gave better agreement with the self-boring
pressuremeter results in the Claygate Beds. The results from some previous studies into
the spade cell over-reading are plotted in Figure 2-8.
25
2-5 Conclusion
In this chapter the components of retaining wall design and the choices that must be made
by the designer have been discussed, including the distribution of pressure on the walL the
expected effect of wall installation and the long-term behaviour of the wall. Work
undertaken towards the further understanding of the importance and impact of these issues
has been detailed. The design advice given by the most widely used guidelines has been
discussed. It is evident that more information is required to further understand the pressure
distribution on the wall, wall installation effects and the general wall stability in terms of
the factor of safety.
A better understanding of the changes in stress that occur on installation of a retaining
wall could result in better estimates of prop loads, wall bending moments and ground
settlements than are currently possible and consequently lead to more economical designs.
The results of previous studies into the over-reading seen by spade cells installed in
overconsolidated clays are rather scattered and show that a direct determination of the
over-reading at any particular site is desirable.
26
Coulomb's idealized failure surfaces
Failure surfaces observed in model tests
Figure 2-1: Failure surfaces arising from Coulomb's idealized earth pressure distribution
pressure
Active earth pressure
Passive earth pressure
Active earth -----L....l-__ ~ ___ ~ pressure
Rotation
Figure 2-2: Fixed earth support
Passive earth pressure __ ---,,..c:;....j_
p
Active earth pressure
Figure 2-3: Free earth support
27
10~----------~--------------------'
~ ~-::s
5
~ 2 ~ a.
..s::::: t:: co 1·0 Q.)
-c Q.) 0·5 '0 E Q.) o ()
0·2
I
------ -_ ...
,. ,. /
/ I
...... ,. ......... ... ------
Loose sand
Passive 8
hr:>: ~::>:
0·1~--~~--~~----~------~----~
0·004 o 0·02 0·04 0·06 Wall rotation, OIh
Figure 2-4: Relationship between earth pressure and wall rotation measured by Terzaghi for normally consolidated sand (different scales for active and passive
pressure) (modified by Simpson, 1992)
~
~ ::s If) If) Q.) .... a.
..s::::: t:: co Q.) -0 -c Q.) '0 tE Q.) 0 ()
4r-------------------r-----------------~
3
2
1
8 Active
\ ::::::::::::: \ :::::::::::::: m····· .. ········· ......... Passive
8
hl0 ...
o~--~----~--~----~--~----~--~--~ 0·04 0·02 o 0·02 0·04
Wall rotation, 5/h
Figure 2-5: Relationship between earth pressure and wall rotation computed by Potts and Fourie (1986) for overconsolidated clay
28
(a) Coulomb distribution - rotation
near base of wall
(b) Rotation at top of wall - (c) Fixed earth support -reduction in pressure at reduction in pressure towards
bottom of retained section top of retained section
Wall ,L~te.ral ~ressure movement ~ distribution
~ \/ , , I I I I I
Wall ---movement
, I I , I I , ~ movement I
\ '" Lateral pressure I distribution
Lateral pressure distribution
Figure 2-6: Influence of movement type on pressure distribution
Prop or anchor --t~---.:~~-- Prop or anchor _ ... ~-~~--
ctive
Factored passive
(a) Stiff wall
Factored passive
Full passive
(b) Flexible wall
Figure 2-7: Stress distributions behind and in front of (a) stiff and (b) flexible embedded walls (after Rowe, 1952)
29
A Reading, SBP, flat dilatometer (Carder and Symons, 1989) + Brent, SBP, Oedometer o Bell Common Tunnel, SBP (Tedd et ai, 1984) • Balham, Overburden (Tedd and Charles, 1983) • Heathrow, Overburden (Ryley and Carder, 1995)
500 .'
..... 1.5 C u
:
: ... • .. ' .
. ...... 0.8 C u
~ ... . '
.... ....... ·········0.3 C u
..•.....
100 200 300 Undrained shear strength, c u, kPa
Figure 2-8: Over-reading v CU. After Ryley and Carder, 1995.
30
3 CASESTUDY
3-1 Introduction
This chapter describes the geology of the field study site and details of the geometry and
construction sequence of the monitored retaining wall. It includes details of the
geotechnical design parameters obtained from the original site investigation for the soils at
the field study site together with an outline of the instrumentation scheme implemented to
measure loads within the structure and the stress changes within the ground adjacent to the
retaining wall.
3-2 Geology
Two specific locations at the site are referred to in this thesis and the variation in the
geology at these locations is detailed in this section. The locations are: a section of
retaining wall that forms part of a propped cutting, which has been comprehensively
instrumented as part of this project and is termed the 'instrumented section' and a drainage
31
sump next to the cut-and-cover tunnel, approximately 600 m to the north-west of the
instrumented section, termed the 'nadir sump'. An assessment ofthe performance of the
spade cells used in this study was undertaken at the nadir sump and is detailed in Chapter
5. The location of a self-boring pressuremeter (SBPM) test, refened to within this work
because it exists in an area with similar geological boundaries to the instrumented section.
is also noted (the relative positions of these locations are shown in Figure 3-1).
3-2-1 Geotechnical data and sample collection
Preliminary information regarding the nature of the geology at the CTRL site at Ashfc)]"(.i
and its geotechnical parameters was collected from: borehole records and laboratory tests
obtained as part of the main CTRL site investigation (the locations of useful boreholes in
the vicinity of the instrumented section and nadir sump are shown in Figure 3-1); the
CTRL Central Ashford Geotechnical Design Basis Report (GDBR - Union Railways,
1997); the regional geology guide for the district (HMSO, 1978); the Geological Memoir
(Smart et al., 1966); the 1 :50 000 British Geological Survey map for the area and from
Humpage & Booth (2000).
A characterization ofthe geology at the instrumented section was carried out to gain a
preliminary assessment of the nature and extent of the geological strata. Samples of
material were taken from within the cutting during excavation. Block sampling techniques
described by Heyman & Clayton (1999) were used to obtain undisturbed samples at the
instrumented section at levels determined by the characterization. A series of steps were
cut in the material with an excavation machine and blocks of approximately 0·3 x 0·3 x
0·3 m were then cut from the steps by hand. The blocks were wrapped in Clingfilm and
foil to preserve the natural moisture content.
In order to obtain further high quality soil samples and to characterise the geological
sequence, two wireline borehole cores were taken about 25 m from the instrumented
section in July 2001 (labelled BH1 and BH2 in Figure 3-1). Photos of the wireline
borehole equipment and logs of these boreholes are included in Appendix A. Samples
taken from these cores and from the block samples were tested in the laboratory at the
University of Southampton to determine the small strain stiffness behaviour of the clay
(Xu, 2005).
32
At the nadir sump the geological profile was estimated from boreholes taken during the
main site investigation and confirmed with observations made during excavation to form
the cutting at the instrumented section. Samples were obtained during excavation of the
nadir sump to provide additional bulk density data to compliment that reported in the main
CTRL site investigation. The geological profile at the location of the SBPM test was
obtained from adjacent borehole records (borehole reference PR3593, see Figure 3-1 ).
In Sections 3-2-3 and 3-2-4 descriptions ofthe reported and observed geology determined
from these combined sources is described.
3-2-2 Site location and history
The monitoring is located in the south-east of England at Ashford, Kent. The topography
of southern Kent, Sussex and part of Surrey is controlled by an anticline which can be
seen on the early 19th century geological map shown in Figure 3-2 (Mantell, 1833). The
stratum which overlies the Weald Clay, shown in Figure 3-2 as the Shanklin Sands, is now
known as the Lower Greensand. The Channel Tunnel Rail Link (CTRL) at Ashford has
been constructed along the side of the Weald of Kent valley on the basal layers of the
Lower Greensand,just above its boundary with the Weald Clay, as shown in Figure 3-2.
Construction of the CTRL included excavations which pass through the Lower Greensand
into the Weald Clay. The Weald of Kent valley was created by the removal of the upper
layers of material by denudation caused by the weakening of the material due to the
folding process which produced the anticline. The removal of the upper strata results in
the lower existing strata being overconsolidated, i.e. they were previously subjected to
much higher vertical loading than they are at present. This process may have also caused a
reduction in the effective horizontal stress in these deposits - this is discussed in more
detail in Section 3-2-4.
Previous land use
The 1876 1:10560 map of Ashford shows that the site of the instrumented section was a
(plant) nursery. A benchmark on this map indicates that the ground level close to the site
of the instrumented wall was 40·8 m AOD (metres above ordnance datum). Before
construction of the CTRL the ground level at the site was about 44 m AOD. Several
metres of made ground have been placed at the site and were observed during excavation
33
and in nearby boreholes. The area was also used as allotments over the years and more
recently has been the site of several warehouses.
3-2-3 Reported geology
Table 3-1 details the geological succession of the relevant deposits, and their approximate
ages.
Period and Succession
Age (Millions of Stratotype Thickness, m
Epoch years)
Lower ~1l2 Hythe Beds 25-90
Early Greensand 124 Atherfield Clay 6-28
Cretaceous Wealden up to 120 in mid
135 Weald Clay Formation Kent region
Table 3-1: Geological succession
The Weald Clay is generally a freshwater deposit, although the upper region is believed to
have been laid in brackish waters. It is generally a stiff to very stiff, brown to grey clay,
and in places it is thinly bedded with silt.
The overlying Lower Greensand was deposited in marine conditions. The basal layer of
the Lower Greensand is the Atherfield Clay, a deposit generally up to 15 m thick in the
Ashford region. The boundary between the Weald Clay and Atherfield Clay is sharply
defined by an undulose erosion surface which represents a slight unconformity, however
the bottom metre of the lower Atherfield Clay is sometimes confused for the top of the
Weald Clay. This band of clay differs distinctly from the underlying Weald Clay and often
contains a number oflarge oysters (Aetostreon or Exogyra) in the lowest 0·5 m, forming a
useful marker horizon (Roberts, 2003). The boundary is also often stained light brown.
The Atherfield Clay is a stiff to very stiff, closely fissured fairly fossiliferous clay and
consists of two distinct materials. The lower Atherfield Clay includes reddish brown or
chocolaty-brown clay. The upper layer (upper Atherfield Clay) is closely to extremely
closely bedded, greyish blue to brown, sandy and about 8 m thick. Humpage and Booth
(2000) reported that the Atherfield Clay weathers to a brown mottled orange and red silty
clay.
34
The GDBR notes that the Atherfield Clay has an "occasionally brecciated I structure"
within its high plasticity zone. The boundary between the brecciated and non-brecciated
clay is difficult to determine and for the purposes of design was taken to be the high
intermediate plasticity boundary. The GDBR also notes that there has been movement of
the Atherfield Clay: a shear zone was found in a borehole about 750 m from the
instrumented section, and cross-sections drawn through boreholes (using the high
intermediate plasticity boundary in the Atherfield Clay as a marker) show evidence of
dislocation in the area of the instrumented section.
The Hythe Beds overlying the Atherfield Clay outcrop over much of the CTRL Ashford
site and are approximately 1·5 m thick at the instrumented section. In general the Hythe
Beds consist of alternating layers of Rags tone, a hard, greyish blue glauconitic sandy
limestone and Hassock, a grey to brownish grey glauconitic, argillaceous, calcareous sand
or soft sandstone. The junction between Hythe Beds and the Atherfield Clay is not distinct
and as a result the top of the Atherfield Clay is sandy and glauconitic (HMSO, 1978). The
Hythe Beds are generally recorded as having a basal clayey sandy layer. Springs issue at
the junction of the Hythe Beds and the Atherfield Clay, hence at the Atherfield Clay
outcrop the land is commonly wet and boggy and it is not possible to get an impression of
the in situ state of the clay from its outcrops. In addition, the springs cause instability and
there have been movements of large blocks of limestone and sand, which have slipped on
the Atherfield Clay. The construction of the CTRL has provided an opportunity for the
Atherfield and Weald Clays to be viewed in greater detail than has previously been
possible.
From a study which included the Hythe Beds outcrop in the Weald of Kent near
Sevenoaks, Skempton & Weeks (1976) noted that the boundary between the Hythe Beds
and Atherfield Clay was difficult to determine, and that there is "probably a consistent
error in plotting the base of the Hythe Beds".
I Breccia: Geo!. A composite rock consisting of angular fragments of stone, etc., cemented together by some matrix, such as lime: sometimes opposed to conglomerate, in which the fragments are rounded and waterworn. (source: Oxford English Dictionary)
35
3-2-4 Observed geology
Weald Clay
The upper Weald Clay contains many silt laminations and occasional bands of siltstone,
about 100-200 mm thick, were recorded (see Appendix A). In some cases the silt
laminations were a few millimetres thick and there was proportionally more silt than clay
in the recovered core. These laminations generally dipped at approximately 20°.
Figure 3-3 shows the Weald Clay exposed by excavation at another part of the CTRL.
Layers in the Weald Clay can be clearly seen and are similar to those observed in the
wireline borehole core taken at the instrumented section.
Atherfield Clay
The erosion surface reported to exist between the Atherfield and Weald Clay was
observed in the cores taken close to the instrumented section (see Appendix A). The
surface was stained brown and about 2 mm of crumbly organic material existed between
the Atherfield and Weald clays.
The lower Atherfield Clay was chocolate-brown and very stiff. It is delineated by a
distinctive 400-500 mm thick band oflight brown material at the top, which was observed
in the nadir sump (Figure 3-4).
In the upper Atherfield Clay zones of thin silt partings, which become more frequent
towards the bottom of the stratum, were recorded. At the top of the upper Atherfield Clay
stratum the material consists of peds2 surrounded by a softer matrix. This is evidence of
the brecciation described in the GDBR (see Section 3-2-3). It also indicates weathering
(grade III - described as "stiffer, less weathered lumps of clay (lithorelics) in a matrix of
disturbed, softer clay" by Chandler, 2000). The size of the peds reduces with depth and the
soil becomes more consistent. Figure 3-5 shows a block sample of the upper Atherfield
Clay prior to removal. On cutting the material very hard peds up to 100 mm wide, which
can be seen in Figure 3-5, fell away. These peds are very hard and impossible to cut by
hand with field instruments and the action of attempting to cut the soil caused significant
disturbance and damage to the samples. The peds are surrounded by softer crumbly
2 Ped: an individual natural soil aggregate (US. Department of Agriculture Yearbook, 1958).
36
material, to which some smearing caused by the cutting process is evident in Figure 3-5.
This observation is consistent with the description of the Atherfield Clay near Ashford
given by Smart et al. (1966) as a, "grey clay that crumbles into cubical lumps" . These
lumps are caused by the opening up of fissures on unloading of the soil- a process likely
to provide drainage paths, thereby allowing easier movement of water than the measured
in situ permeability of the material might indicate.
Hythe Beds
The Hythe Beds was approximately 1·5 m thick at the instrumented section and consists of
stiff to very stiff yellow/grey mottled sandy clay (apart from the colour, it is very similar
in appearance to the top of the upper Atherfield Clay). At the transition between the
yellow/grey mottled material and the grey material there are peds of grey material within a
yellow matrix. Samples of the Hythe Beds taken during excavation were observed to
consist of firm to stiff mottled light brown and light grey sandy clay with pottery tile,
rotten wood fragments and large dark brown rootlets (Figure 3-6). Block sampling within
the Hythe Beds was found to be relatively straight forward, as the clay cut easily due to
the presence of fine sand, and the samples remained intact.
For the purposes of this work the boundary between the Hythe Beds and the Atherfield
Clay has been taken to exist where the colour of the clay changes from mottled
yellow/grey to grey, which coincides with a small increase in the plasticity index (due to a
reduction in the quantity of sand in the deposit). On this basis the upper Atherfield Clay
layer is 8·75 m thick at the instrumented section, which is generally consistent with
measurements from boreholes across the site.
Above the Hythe Beds is about 2 m of made ground, which is firm mottled dark
brown/grey organic sandy clay with pottery tile, rootlets and rotten wood fragments.
Figures 3-7 and 3-8 show the dark brown made ground, the yellow/light grey Hythe Beds
and the dark grey upper Atherfield Clay during excavation of the cutting.
General
There is evidence to suggest that there has been historic movement of the upper regions of
the Atherfield and possibly the Weald Clay in the area of the instrumented section. Figure
3-9 shows a shear plane observed in the excavation for the cutting 50 m to the west of the
instrumented section. The shear plane dips at 45° to the south-southwest with a strike of
37
approximately 0700 (east-northeast). Other shear planes have been observed within the
Atherfield Clay and Weald Clays formations. Figure 3-10 shows a sketch of a
discontinuity (possibly a shear plane) observed in the base of the excavation for the cutting
at the instrumented section before blinding was laid for the base slab (see Sections 3-4 and
3-5 for details of the construction and instrumentation layout). There was an apparent error
of approximately 1·5 m in the logging of the two wireline boreholes taken 25 m behind the
north wall at the instrumented section. The observed shear plane suggests that rather than
this being an actual error, this discrepancy may be due to disturbance/faulting between the
two borehole locations.
3-3 Geotechnical properties
3-3-1 Plasticity
Due to the variable silt content of the Weald Clay its plasticity index ranges between 10-
30%. The upper Atherfield Clay is generally of relatively high plasticity, with a plasticity
index of approximately 50%. The lower Atherfield Clay has a plasticity index of20-30%.
Profiles of the soil found from the wireline boreholes taken 25 m from the instrumented
section, including liquid limit, plastic limit and moisture content data, are shown in Figure
3-11. The moisture content is at or close to the plastic limit and there is a clear change in
plasticity from intermediate to low plasticity within the upper Atherfield Clay stratum,
about 2·3 m above the level ofthe boundary with the underlying lower Atherfield Clay.
This is explained by the increase in silt zones in the lower part of the upper Atherfield
Clay stratum.
A comparison of the geology at the instrumented section, the nadir sump and the location
of the pressuremeter test is shown in Figure 3-12. At the nadir sump the ground level was
reduced by approximately 8·2 m before construction.
3-3-2 Bulk density
Bulk density measurements from the main CTRL site investigation and samples obtained
during excavation ofthe nadir sump are shown (plotted in m AOD) in Figure 3-13.
38
3-3-3 Soil strength
The moderately conservative (see Section 2-3-1) value for the effective angle of soil
friction, rjJ', recommended in the GDBR for the Weald Clay is 23° with the effective
cohesion, c', equal to O. Further interpretation of the presented data indicates a rjJ' of 240
with c' = 0 may give a more appropriate 'average' value.
The moderately conservative rjJ' value recommended in the GDBR for the intermediate
plasticity Atherfield Clay is 21 ° with c' = 4 kPa. However, further interpretation of the
presented data indicates a value of 24° with c' = 0 may be a more appropriate 'average'
value. In addition, triaxial tests carried out at the University of Southampton by Xu (2005)
on samples of the lower Atherfield Clay collected from the rotary drilled cores (described
in Section 3-2-1) indicated a rjJ' for the lower Atherfield Clay of 26° with c' = 10 kPa
(Figure 3-14).
For the high plasticity Atherfield Clay the GDBR generally recommends a moderately
conservative rjJ' value of 24° with c' = 10 kPa for the non-brecciated and 29° with c' = 0 for
the brecciated region in the central Ashford area. However, the report notes that the
fissuring observed in the Atherfield Clay in the localised area of the instrumented section
is indicative of land movements (described in Sections 3-2-3 and 3-2-4) and therefore a
value relating to the remoulded state of the clay was used for design: ¢Jerit = 18°. This
value was later increased to 20° on reinterpretation of the data (Union Railways Ltd, 1997
B).
In the GDBR the value taken for the Hythe Beds as the moderately conservative soil
strength, ¢J, was 30° and c' = O. The limestone and soft sandstone that the Hythe Beds
generally consist of (see Section 3-2-3) would be responsible for much of this strength, but
were not present at the instrumented section: the lowest part of the Hythe Beds consists
only of sandy clay.
These soil strength parameters are summarised in Table 3-2.
39
Effective angle of soil Effective friction, til (moderately cohesion,
conservative),O c', kPa
Weald Clay 23 0
lower Atherfield Clay and GDBR
21 4 intermediate plasticity 24 0 upper Atherfield Clay
Xu (2005) 26 10
high plasticity upper non-brecciated 24 10 Atherfield Clay brecciated 29 0
remoulded 18/20 0
Hythe Beds 30 0
Table 3-2: Soil parameters of the Atherfield Clay and Weald Clay
Figure 3-15 shows the undrained shear strength (cu) as a function of depth, determined
from unconsolidated undrained triaxial tests on 100 mm samples and estimated from
standard penetration test (SPT) results. The SPT blowcount N multiplied by 4·5 (Stroud,
1974) correlates closely with the laboratory data for the Atherfield Clay, but gives values
generally in excess of the laboratory tests for the Weald Clay. This is consistent with
known sampling effects and in particular the disturbance to the microstructure, fabric and
mean effective stress caused by thick walled tube sampling in stiff clays (e.g. Hight &
Leroueil, 2003). In the Ashford site's Geotechnical Design Basis Report (Union Railways
Ltd, 1997) a value of 4·5 was used to factor the SPT data for the Atherfield clay and 3·5
was used for the Weald Clay. The best-fit line to all the data in the Atherfield Clay is
indicated, and is given by Equation 3-1. Figure 3-16 shows the undrained shear strength
found from the SBPM test PR3593 (for the location see Figure 3-1). The SBPM data
indicate slightly higher undrained shear strengths compared with the laboratory tests and
SPTs.
Cu (kPa) = 22 + 7 z (z in m below ground level) Equation 3-1
3-3-4 In situ horizontal stress
Figure 3-17 shows the in situ horizontal stress interpreted from the SBPM test. These data
imply an in situ earth pressure coefficient of approximately 1 (although they are
measurements of total rather than effective stress). This is rather less than would be
expected on the basis of the one-dimensional stress history of the deposit. Movement of
40
the soil by faulting or a landslide (described in Section 3-2-4) may reduce the in silll
horizontal earth pressure coefficient, Ko, to below that which might otherwise be expected
for a stiff overconsolidated clay on the basis of its stress history.
As previously mentioned, the geological folding that created the anticline shown in Figure
3-2 may also have had the effect of releasing horizontal stress as the soil stretched and
weakened. The London Clay (a much younger deposit than the Atherfield and Weald
clays), also seen on the section shown in Figure 3-2, was folded inwards by this process
which may have contributed to its relatively high in situ horizontal stress.
3-3-5 Permeability and Groundwater
Data from variable head permeability tests taken during the main site investigation are
shown in Figure 3-18. Due to the paucity of the data no firm conclusions can be drawn,
however, it appears that the Atherfield Clay has a very low permeability of about
1 x 10-8 mis, the Hythe Beds have a slightly higher permeability of about 1 x 10-7 mls and
the Weald Clay has a variable permeability of between 4 x 10-9 mls and 2 x 10-6 mls (the
variation is due to the silt laminations).
Roberts et al. (in print) state that reliable results from 5 tests in the Atherfield Clay and 20
in the Weald Clay carried out in the Central Ashford area gave an average permeability for
the Atherfield Clay of3 x 10-8 mls (with a range of2 x 10-9 mls to 9 x 10-8 m/s) and
1 x 10-8 mls for the Weald Clay (with a range of 1 x 10-9 mls to 3 x 10-7 m/s). Roberts et
at. state however that borehole permeability tests are known to be unreliable, often
underestimating the true permeability by an order of magnitude or more. They go on to
report the results of a pumping tests using ejector wells which indicated the permeability
of the Weald Clay to be in the order of 1 to 2 x 10-6 m/s.
The GDBR indicates that the in situ groundwater in the area of the instrumentation is
approximately 1 m below ground level. Extension of the best-fit line to the pore water
pressure data in the strata above and including the upper Atherfield Clay (Figure 3-19)
indicates the groundwater level to be at 42·7 m AOD (ground level is at 43·7 m AOD),
concurring with the GDBR. The water pressure distribution in these strata is represented
by Equation 3-2, where u is the pore water pressure and L is level in m AOD.
41
u = 8·28 x (42·706 - L), for L < 42·706. Equation 3-2
This equation indicates under-drainage of the Atherfield Clay (if the equation represented
a hydrostatic distribution of water pressure, the multiplier value 8·28 would be 9·81, the
density of water). This is probably due to the horizontal silt laminations in the underlying
Weald Clay acting as drainage paths, and the dewatering in a section of the CTRL
approximately 100 m from the instrumented section was shown to have an influence on
the groundwater regime up to 500 m away (Roberts et ai., in print). This dewatering
occurred over the period of wall installation at the instrumented section.
The data collected at the dewatered section approximately 100 m away from the
instrumented section indicates that the lower Atherfield and Weald clays have been
subjected to a drawdown of 5 m. This is consistent with the lower pore water pressures
measured in the lower Atherfield Clay. The water pressure profile produced by this
drawdown is shown in Figure 3-19, and given in Equation 3-3. The dotted line indicates
the likely water pressure profile in the lower Atherfield Clay.
u = 9·81 x (37·709 - L), for L < 37·709. Equation 3-3
3-4 Description of site and geometry of structure at the instrumented section
The instrumented section of the Channel Tunnel Rail Link (CTRL) is approximately
350 m northwest of Ashford International Station in Kent (Figure 3-20). It consists of a
propped contiguous bored pile retaining wall formed from 21 m long, 1·05 m diameter
piles spaced at 1·35 m centres. The piles at the instrumented section were installed in
November and December 1999. Figure 3-21 shows a cross-section of the instrumented
section. The cutting width is approximately 12 m and the excavation depth 10 m. The
walls are permanently supported at crest level by 1 m square reinforced concrete props
spaced at 4·5 m centres and at formation level by a reinforced concrete base slab. A corbel
was added to the retaining wall above the base slab at a later date to prevent slab uplift.
Temporary tubular steel props were employed during excavation to support the walls until
the base slab had been constructed.
In the Ashford area the CTRL follows a contour along a valley side, with the ground
sloping down from the northeast to the southwest. The construction is therefore not
symmetrical about the centreline of the excavation. Behind the south wall lies the London
42
to Dover main railway line and other local railway lines. The ground level behind the
south wall was reduced by several extra metres during construction of the CTRL to enable
construction of another railway line, as shown in Figure 3-22. Unfortunately access to the
south wall was not available due to site constraints and so it was not possible to monitor
its movement.
3-5 Construction sequence and installation of instrumentation
Approximately one month prior to installation of the contiguous piles, sixteen Soil
Instruments vibrating-wire push-in pressure cells with integral vibrating-wire piezometers
(spade cells) were installed adjacent to the line of the retaining wall. The spade cells
measured the in situ total horizontal stresses and pore water pressures and the subsequent
changes due to bored pile installation and further construction events. Figures 3-23 and
3-24 show the general arrangement of the spade cells in relation to the retaining wall. In
determining the positions of the spade cells, careful consideration was given to the
proximity of the individual bored piles allowing for pile installation tolerances (more
relevant to the deeper instruments) and the localised effect of pile installation on the
surrounding soil (Richards et al., acceptedfor publication). The spade cells were installed
at three different distances from the line of the wall, so that any variation in the influence
of wall installation effects with distance from the wall could be determined. The array of
instruments was spread out laterally along the wall owing to the need for a separate
installation borehole for each spade cell. The spade cell cables were sheathed in brightly
coloured sturdy plastic tubing near ground level behind the wall and to the depth of
formation level in front of the wall, in order to protect the cables and to provide a visual
marker during construction and excavation activities.
The dates ofthe main construction events are shown in Table 3-3, and details of the main
construction events are outlined below. For the purposes of this thesis all graphs and data
are referenced with respect to the number of days from the beginning of the project, with
the day the first spade cell was installed, 8th October 1999, being Day 1. The last
significant construction activity at the instrumented section occurred when the last
instrumented temporary prop was removed on Day 595.
43
Stage Name Schematic Day Date
1 Spade Cell see Figures 3- 1-13 8th_20th October 1999 Installation 23 and 3-24
2 Pile Installation 47-71 23 rd November to 1 i h
December 1999
3 Sand Drain i'W'~'" 349-352 20th_23 fd September 2000
Installation
d/~" .....
4 Capping Beam .=. .=. 440-442 approximately 20_22nd
iW /
A
'" Construction December 2000
.• '1'."".
5 RC (reinforced ~ 465 Props 1 & 2: 14th January concrete) Prop I'W'A' 467 2001 Construction Prop 3: 16th January 2001
u,~ ......
6 Excavation Phase 1 483-509 1 st_2ih February 2001 t 5:4 (no work ih_21 st Feb
~~ inclusive)
.• ,1:,,,,,.
7 Temporary Prop 512 Prop 1: 2nd March 2001 Installation
i'W'A' 522 Props 2 & 3: 1 i h March 2001
.• '1'.""'.
8 Excavation Phase 2 530-537 20th_2ih March 2001
13-7
I"w~ ",~,,,,,,,
9 Base Slab 579 8th May 2001 Construction
i~ ··'f,,,,,,"
10 Temporary Prop 581 Prop 1: 1 Oth May 2001 Removal 595 Props 2 & 3: 24th May 2001
I"~ ... ,r., ......
Table 3-3: Dates of main construction events
44
An essential component of this project was the full-time presence of the researcher on site
throughout the main construction period. This allowed the researcher to compile a detailed
diary of the construction events (and any other activities which may have affected the soil
stress or structural loads) and to link these changes with the collected measurements.
3-5-1 Pile installation
The lettering on the piles in Figure 3-23 indicates the sequence in which the piles were
installed and is detailed in Table 3-4. Appendix B contains more detailed information
regarding the pile installation period.
The pile installation process is shown in Figure 3-25 and illustrated in Figure 3-26, 3-27
and 3-28. In most cases, the uppermost 8 m ofthe pile bore was excavated on one working
day following which a casing was inserted to support the sides (this process took between
20 and 80 minutes, with an average duration of27 minutes). The remainder of the bore
was excavated on the next working day without any further form of support, although on
reaching the required depth bentonite slurry was introduced up to original ground level
(this took between 20 and 50 minutes, with an average of30 minutes). The reinforcement
cage was then lowered into the borehole and concrete was tremied in from the base at the
same rate that the bentonite was removed. (This process was implemented after
observation of trial boreholes left open for several days showed that those in the Atherfield
Clay would remain stable for at least 24 hours whereas deterioration occurred more
quickly in Weald Clay; Roscoe and Twine, 2001). The exception to this installation
sequence was a single pile in period Dl (see Figure 3-23 and Table 3-4) for which
excavation and concreting were carried out within one afternoon, immediately after period
D. It is also of note that certain piles were installed on a Friday (pm) and Monday (am), so
following excavation to 8 m the hole was left cased and open over the weekend.
45
.f::.. 0\
Installation Boring started Casing depth Boring restarted Pile completed, Concreting Concreting period reached, casing bentonite added started ended
inserted
Day Time Time Day Time Time Time Time
A 47 1510-1550 1540-1620 48 1155-1255 1235-1330 1420-1550 1453-1638
B 49 1440-1720 1600-1740 50 0805-0916 0845-1001 0916-1225 1002-1311
C 53 1459-1625 1520-1646 54 0800-0934 0835-1000 0955-1227 1032-1315
D 55 1518 1542 56 0910 1000 1109 1150
Dl 56 1220 1255 56 1255 1350 1626 1724
E 57 1150-1435 1218-1500 60 0906-1310 0941-1335 1112-1540 1156-1627
F 64 1040-1108 1130-1200 67 0810-0842 0842-0905 0950-1114 1036-1201
G 67 1715 1746 68 0848 0908 1058 1145
H 69 1631-1659 1657-1721 70 0810-0841 0840-0905 0933-1040 1006-1117
I 71 1135-1203 1200-1225 74 1120-1148 1146-1210 1430-1605 1545-1705 -- -- -
Table 3-4: Sequence of pile installation. Also see Figure 3-20
In each installation period, between 1 and 4 piles were installed. The times given represent the range including all piles
within each period
An inclinometer tube was installed within pile Z (see Figure 3-23) to measure the
deflected profile of the wall and to allow the bending moments to be estimated from the
deformed wall profile. (An inclinometer tube was also installed in the pile nearest to spade
cell 12 but the tube was damaged during construction and was unusable.) The inclinometer
tubing extended 10m into the natural ground below the toe of the pile thereby establishing
a fixed point and eliminating the need to rely on surveying the top of the wall to determine
its overall movement. Bending moments were also calculated from strains measured using
vibrating-wire embedment gauges installed in piles X and Y (Figure 3-23). Pairs of gauges
were situated at 1·5 m intervals down the piles (see Figures 3-29 and 3-30).
3-5-2 Sand drains
Sand drains were installed between the cutting walls to reduce the pore water pressures in
front of the retaining wall during construction. The retaining wall design was based on the
assumption that hydrostatic pore water pressures would exist on both sides of the wall:
from ground level behind the wall and from the bottom of the excavation in front of the
wall. However, there were concerns that the flow of water through the wall (or around the
toe) could result in higher pore water pressures in front of the wall. This could reduce the
passive effective stresses and therefore overstress the wall, or, depending on the
permeability of the Atherfield Clay, cause pore water pressures to build up in the Weald
Clay underneath the Atherfield Clay (due to the relatively high horizontal to vertical
permeability of the Weald Clay) which may cause the 'plug' of Atherfield Clay above to
be pushed upwards. The sand drains were therefore designed to relieve any pore water
pressure build up in front of the wall and ensure that the hydrostatic pore water pressure
profile assumed in design was achieved (Roscoe, 2005).
The 30 m deep sand drains were installed at 3 m ± 0·5 m centres in two lines, 3 m from
each wall. The sand drains in the vicinity of the instrumented section were installed over a
period of about 3 days. Each drain comprised a 150 mm diameter hole (bored without
casing) filled with 10 mm gravel. The line of sand drains near to the north wall fell
between most of the spade cells in front of the retaining wall, shown in Figure 3-23. A
0·5 m leeway in the position of the sand drains was used to ensure that spade cell 17 and
its cable were not endangered by the sand drain installation. Figure 3-31 shows the sand
drain nearest to spade cell 11 during excavation.
47
After excavation of the cutting to fonnation level a shallow channel (less than 200 nl111
deep) was excavated and filled with 10 mm gravel to link the sand drains under the base
slab. Drain holes were installed in the base slab so that water could drain through it,
thereby preventing the build up of pore water pressure under the base slab.
Data for the period immediately following sand drain installation is limited as construction
activities had commenced within the instrumented wall section and during this period
some of the gauge wires were broken; these activities included construction of a large slab
behind the wall and excavation around the wall for the capping beam construction (see
Section 3-5-7). Total horizontal stress and pore water pressure data collected prior to
construction of the capping beam are shown in Figure 3-32 (total stress measurements are
corrected by 0·35 eu to allow for spade cell installation effects: see Chapter 5). The figure
shows that installation of these drains appears to have had little effect on pore water
pressures and total stresses in the short-tenn.
3-5-3 Removal of pile tops
A month after installation ofthe sand drains (Days 382 to 384) the soil on either side of
the piles was excavated to a depth of approximately 2 m (Figure 3-33) in order that the
piles could be broken down to competent concrete, the pile tops removed and the capping
beam constructed. The pile tops were removed using the 'Elliot' method. This involves
drilling holes through the pile at the pile cut-off point and inducing a crack across the pile
section. Removal of the concrete pile top is aided by a foam covering on the reinforcement
bars above the cut-off point which restricts bonding between the reinforcement and the
concrete (Figure 3-34). The pile tops in the vicinity ofthe instrumentation were removed
in the days around Day 413 (23rd November 2000) (see Figure 3-35).
During removal of the pile tops it was necessary to release the vibrating-wire strain gauge
cables from the concrete. The cables were installed in a duct attached to the pile
reinforcement and extending down to the level of the pile cut-off (about 1 m) before the
pile concrete was poured, so that when the concrete was 'cut-off the cables were carefully
drawn through this ducting so that they exited the pile at the cut-off level. The pile gauge
cables were then run through ducting within the blinding for the capping beam, along with
the cables from the spade cells installed in front of the wall.
48
3-5-4 Capping beam
The capping beam had the dimensions shown in Figure 3-36 and can be seen in Figure
3-37. Around the time that the capping beam was constructed the ground level between
the tunnel walls was reduced by up to 1 m in preparation for the construction of the
reinforced concrete props. A 2 m high wall was built on the capping beam approximately
45 days after Temporary Prop Removal.
3-5-5 Reinforced concrete props
The reinforced concrete (RC) props were constructed on blinding approximately 75-100
mm thick. Plastic liner was used to separate the blinding form the poured concrete.
Blackjack was pained onto the capping beam at the locations of the forthcoming RC
props, as shown in Figure 3-38. There was no steel connection between the capping beam
and the RC prop. Shuttering was then erected, the pre-fabricated steel cage installed and
the concrete poured. During excavation under the props the blinding was removed.
Vibrating-wire embedment strain gauges were installed in three of the RC props to
measure axial loads. The locations of the monitored props in the instrumented section are
shown in Figures 3-39 and 3-40. Each RC prop was fitted with four gauges, 2 m from the
northern end. The prop load is calculated from the average of the outputs of the four
gauges at each cross-section to eliminate the effects of bending. In addition, bending was
measured in prop P2 using two further sets of 4 gauges located at 4 m and approximately
6 m (at the centreline ofthe excavation) from the northern end. The gauges are situated at
0°,90°, 180° and 270° on the cross-section of the prop and numbered as shown in Figure
3-29. The pre-instrumented reinforcement cage for RC prop P3 was erroneously placed in
the position ofRC prop 4: hence RC prop 3 is not instrumented.
3-5-6 Backfilling and material placement behind North wall capping beam
On Day 476 backfill was placed behind the capping beam on the north wall up to within
0·5-1·0 m of the western extent of the instrumentation. On Day 477 backfill was placed to
within 0·5-1·0 m of the eastern extent of the instrumentation. Backfill was placed behind
the capping beam at the instrumented section on Day 480 (Figure 3-41).
49
On Days 487 and 488 a large crane platform (1200 tonnes) was constructed behind the
wall close to the instrumented section, using 400 tonnes of ballast. (The crane was used to
lift a nearby footbridge into position.) Some time between Days 489 and 495
approximately 700-800 mm of hard core was placed and compacted directly behind the
wall over an area encompassing the whole length ofthe instrumented section to provide a
stable platform for the long-reach excavator on its return.
3-5-7 Excavation
As illustrated in Table 3-3, there were two main excavation phases: Excavation Phase 1
reduced the ground level within the cutting to just below temporary prop level (36·759 m
AOD) and Excavation Phase 2 reduced the ground to formation level (33·559 m AOD).
Figure 3-42 shows an elevation of the instrumented section indicating the dates on which
particular regions were excavated. The bulk of the material was removed with a long
reach excavator situated at ground level behind the wall (Figure 3-43). A more
manoeuvrable mini-digger located within the cutting was used to remove any remaining
material. In order to minimise instrument cable breakages the long-reach excavator
operator avoided the soil around the cables within the excavation and the mini-digger was
used to carefully remove this material at a later stage. A blinding layer was poured across
the base of the excavation within a few days of reaching final formation level.
3-5-8 Temporary props
The temporary props were hollow steel sections with an external diameter of 1016 mm, a
wall thickness of22·2 mm and a Young's modulus, E, of205 GN/m2• The load from the
wall was transferred to the temporary props by a concrete thrust block and waling beam
arrangement, as indicated in Figure 3-21 and Figure 3-44.
The load in three temporary props was measured with 12 vibrating-wire surface-mounted
strain gauges. Four gauges were fitted to each prop, 2 m from the northern end. The
gauges are welded onto the prop (see Figure 3-45) at 45°, 135°,225" and 315" on the prop
cross-section and were covered with insulated metal housings to minimize damage from
machinery and falling soil during excavation. The positions and numbering system are
shown in Figure 3-29.
50
3-5-9 Base slab
The dimensions of the base slab are shown in Figure 3-46. The base slab was constructed
in 11 m long segments. The instruments were installed such that they traversed the same
section of wall as Slab A4 (shown in Figures 3-23, 3-39 and 3-42 - note that the intension
was to monitor P3 instead ofP4: see Section 3-5-5). The base slab to the west (A3) was
poured on Day 571 and the slab to the east (A5) was poured on 590.
Eight vibrating-wire embedment strain gauges were attached between the reinforcement
steel in pairs along the centreline of the base slab, at 2 m intervals, to measure load in the
base slab. One gauge of each pair was at the top of the slab and the other at the bottom
(Figures 3-29 and 3-47). These gauges were connected to the datalogger on Day 575, four
days before the base slab was constructed, so that readings of strain and temperature could
be taken before and throughout the concrete pour.
The base slab gauges were irrecoverably lost on Day 1278 (ih April 2003) when the
tunnels were cleared out in preparation for installation of the over-head high-voltage
transmission lines.
3-5-10 Installation of storm drain
Six months after the main construction activities had been completed a storm drain was
installed approximately parallel to and behind the north wall on 9th November 2001 (see
Figure 3-48). The storm drain was about 0.5 m diameter and the distance between its
centreline and the edge of the wall was approximately 4 m. It was installed at an elevation
of approximately 41m AOD.
3-6 Data collection and vibrating-wire instrument technology
Vibrating-wire instruments were used because they are relatively easy to install and can be
monitored remotely and continuously using a datalogger. All of the instruments were
wired to a CRI0X Campbell Scientific datalogger with 2 vibrating-wire interfaces and 7
multiplexers (Figure 3-49). On collection the data was saved in both the datalogger and a
storage module to minimise data loss during data downloading. A photovoltaic cell and
inverter were connected to the datalogger battery to ensure continuous battery charging;
hence the system was effectively self-maintaining. A remote data collection system was
51
set up to collect and process the data (Richards et ai., 2003). This enabled data to be
automatically downloaded daily (via a modem) to several storage locations at the
University of Southampton, the raw data readings to be converted to AGS-M fOlmat
(CIRIA, 2002) and subsequently uploaded to a remote server where the data could be
viewed via a website within 24 hours of their collection.
For operational reasons (for example to allow any cable breakages occurring during
excavation and construction to be detected quickly) the datalogger was set up to take
readings of all instruments every 5 minutes so that at any time on accessing the datalogger
a reading obtained within the last 5 minutes could be viewed. Instrument readings were
stored in the datalogger at intervals of between 5 minutes and 2 hours, depending on the
level of activity on site.
All of the instrumentation used on site to monitor the structural loads, soil stresses and
pore water pressures used vibrating-wire transducer technology. Vibrating-wire
transducers contain a tensioned wire which is 'plucked' by a solenoid via a datalogger
instruction and the resulting frequency of vibration of the wire, which is proportional to
the strain in the gauge, is measured within the magnetic field of the solenoid (see Figure
3-50). As the length of the strain gauge (and therefore the wire within it) elongates or
contracts (depending on the stress patterns in the member in which it is installed), the
frequency at which the wire vibrates changes accordingly. The strain gauges also contain
thermistors for temperature measurement.
To obtain a strain reading from a vibrating-wire transducer the datalogger sends an electric
pulse which excites the solenoid within the instrument creating a magnetic field, causing
the wire to vibrate. The minimum and maximum frequencies of the 'sweep' are specified
by the user and depend on the type of gauge being used. The measured frequencies are
sent to the strain gauge sequentially starting with the lowest frequency and finishing with
the highest; this takes 150 ms. Although the wire vibrates at every frequency, the non
resonant frequencies die out quickly, leaving only the resonant frequency which remains
for a relatively long time. After waiting for the non-resonant frequencies to die out (20 ms)
the datalogger then measures the time taken for a user specified number of vibrations to
occur. This is used to find a value for the average frequency of vibration. The datalogger
then records the square ofthis frequency (expressed in units of kHz2 - see Equation 3-4,
where T is the period in milliseconds).
52
F 2 = _1_ 1 •
T-Equation 3-4
For this project the datalogger was set up to sweep between 800-1300 Hz and to obtain the
average frequency reading over 80 cycles for the concrete embedded and surface mounted
strain gauges and to sweep between 1600-30000 Hz and take readings over 100 cycles for
the spade cells and piezometers. These figures were based on the instrument and
datalogger manufacturers' advice.
At the reading interval specified in the datalogger (e.g. 5 minutes) readings are taken from
all instruments in succession. When using a large number of instruments in any
datalogging system it is important to ensure that the interval is long enough for all the
instrument readings to be obtained successfully.
Some instruments experienced periods of downtime due to inevitable cable breakages
caused by the machinery used during excavation. The full-time presence of the researcher
on site, working closely with the contractor during the construction period, kept these
losses and downtime to a minimum.
53
VI .j:>.
PRESSUREMETER TEST
I ~'PR 3593 (reference from
"" CTRL Site Investigation)
"'" SA4116
"'" " "'" ~/~
" "':?O/C SA 8428 ",,?a/JI,!
BH # - Wireline boreholes undertaken by University of Southampton
SA #### - Useful boreholes from CTRL Site Investigation
NORTH WALL
BH1 ~
~:2
••• TH} ...... ~12m SOU ••
WAL'o... 12 m ~ ..... SA849~ .... d··· ..
••••• 'Instrumente •••• ... ,
••••• section ••• ••• ••• •••
SAl 813.6: ~""
"'~:~I,! NADIR SUMP "'?~:~ll'
",,~IIJ,f
•••••
SA 8~1'40'", SA ~~~~""SA 6104
",," SA 6106 "" "
SA 8315~"T ~ 002
MAIN INSTRUMENTED SECTION N
+ "~)~A8497 1 1 I
o 100 m 200 m SA 9154" SA 8316A~"-
SA 8316"
Figure 3-1: Plan showing the locations ofthe areas described in this work
Vl Vl
,f ectlio7l/ rrtnlVJ.V c wn"C&v6Tb z:n,,·
CTRL at Ashford - Instrumented section
7f-19au .riO,.,.
Figure 3-1: Geology of the Weald of Kent (Mantell, 1833)
JJlflr ru ar INNdfloe
56
Figure 3-4: Light brown band derming the boundary between the upper and lower Atherfield Clay (observed in the nadir sump)
Figure 3-5: Showing the peds and softer matrix of the upper Atherfield Clay
57
Figure 3-6: In situ block sample of the Hythe Beds showing yellow/grey mottling and dark brown root material
58
Upper Atherfield Clay
Figure 3-7: Looking into the cutting between RC props during excavation
Figure 3-8: Elevation of the excavation face
59
Figure 3-9: Shear plane in the upper Atherfield Clay, 50 metres from the instrumented section (courtesy of Mark Roberts, Geological Specialist for Skanska
Technology Ltd.)
60
North wall 0 -rN
o Instrumented 00 section of wall
Material is smoother with very: 00 hard peds visible I 0
~ I 00
South wall 0 I Material is 0 o I more crumbly o I in appearance
00 :
o ~~O Line visible in base o of excavation
o
Figure 3-10: Sketch of discontinuity (possible shear plane) observed in the bottom of the excavation at the main instrumented section (plan view)
61
0\ tv
Moisture content, %
o 20 40 60 80 100 O +I--~+-~~--~~~~--~~
5
E 10
Qj > ~
'0 15 c: :::l
e C)
3= .E 20 (1) .0 J:: Q. (1)
o 25
30
35
Made Ground
. - 0 - • Hythe Beds (firm to stiff closely •• 00 • • fissured mottled light grey and
.a • light brown sandy CLAY) • • upper Atherfield Clay (stiff
• 0 • to very stiff fissured grey :: : sandy (fine) CLAY)
.0· 0 • · Change in PI 2.3 m above ..... ---;e---.. ---~ ------------ -.----- lip~iei-il6wer Atherfield boundary
~ . - ---- - -- -- - - - --o. • lower Atherfield Clay (stiff ~. .
to very stiff closely a • 1 c;: • fissured brown CLAY) a • o. •
~~ . F • •
---CJI •
o • •
Weald Clay (stiff to very stiff closely bedded grey CLAY with frequent sections containing sand (fine) laminations)
~ ---. - c ·-E Q) E .- ....... . -uc~ ._ 0 ._
- U :::l en CJ ~~= 0... ::::l -en
'0 E
Moisture content, %
o 20 40 60 80 100 o +I __ ~~-J __ +--L~~J--+ __ ~~
5
E 10
~ ~ '0 15 c: :::l
e C)
3= .E 20 (1) .0 J:: .... Q. (1)
o 25
30
35
o o
Made Ground
Hythe Beds o q
t · . } upper boundary to Atherfield CLAY
0: . . upper Atherfield Clay (stiff E • to very stiff fissured grey
• 0 • sandy (fine) CLAY) -------- --.:> --- . --- ----- ---- ------ --- --- -- --
.a. Change in PI 2.3 m above _ _ _ !k:(jI •• _____ ~ee.e!~~~t:r Atherfield boundary
c. • lower Atherfield Clay (stiff CJI • to very stiff closely fissured o. •
o. • brown CLAY)
o. • CJI •
o. • 0_ o. • ~ . o • •
o
Weald Clay (stiff to very stiff closely bedded grey CLAY with frequent sections contain ing sand (fine) laminations)
~
~(]} ....... E ..... C = .3 2 ~ '6 § ~ E U
0:::
Figure 3-11: Geotechnical profiles including liquid and plastic limit data from wireline boreholes BHl and BID (see Figure 3-1)
60
50
40
c ~ 30 E
20
10
Hythe Beds
upper Atherfield
Clay
lower Ath. Clay
.. -'" --...... -_ .. ------.. -----.. .. - .. ------- ... - ... -... --_ ..... -----------_ ... _--- .... -------------.. "" .. -----------.. ---.. ---.... -.. ------.... -----. ------------ ... -------- -------------~~~~~~:~ -:-:-: -:-:-: .. :-: -:-:-:-:------- -_ ... _ .... ----- ---------------------.. _-----------------------------------------------
Original ground level material removed i··· ···· ·· ··· ·· ····i before nadir sump
i Hythe Beds ! construction . i ~ -----------------i I
upper Atherfield
Clay lower Ath.
Clay ------... -.. -.. -.. -... -.. -.. ------~: .. :-:-: -: ... : .. :-:-:-:-: -:-.. -- ... ------------- ... ----_ .. _- --- ... ---- .. - .. _----- - ... --------- .. _-----------------------------------------.. -.. -.. ---.. -----.. -.. -------------- --- .. ------------- ... ---------~~~~!~~~i~-------------------- .. ----------- .. ------------------... _---------_ .. _ ... _-------_ ... -------------_ .. _--------"' .. '" --...... --... -----........... -" ... -... --------------------------------------------------------------------------------------------------_ .. _-
Hythe Beds
upper Atherfield
Clay
lower Ath . Clay
...... _ .. _- .. - ... ------- ... --.. _----- ----------------------_ .. ----. .... -.. -... -.. -.. -.. -.. -.. -... - ..... ------------- .. --------.. -... -... -... -... ---... ---... - -----
::wealEf:Gia~-:: _________ '1...
--------- .. -----_ ... _------..... __ ._-----_. ----.. -_ .. _-... ---.--------- .. .. -_ .. _-----..... _--- ---------,
Northwest 250 m 600 m South
o +-------------~------------~------------. self-boring
pressuremeter PR3593
nadir sump SA8313A
instrumented section
Figure 3-12: Comparison of geology at locations referred to in this study (see Figure 3-1 for locations)
63
Bulk density, Mg/m3
1.5 1.6 1.7 1.S 1.9 2.0 2.1 2.2 2.3 2.4 2.5 50 +t-------= .. -=--_-...... --J.'-.... -.-.... -1. ...... _ ..... _ .... --'----L----JL..---'---...L...--'----'
Ground level at/ + * Gr?und !evel and soil 45 nadir sump x -ttt profile at Instrumented
_______ .. _.. _:T" x /! section
40
35
30
c ~ 25 E
20
15
10
5
n
x :- Made ground
================{~==========B¥frliLBeds • x ~ • x W' ... ~. upper Atherfield
x ......... ~ Clay
x # -------------------------+--------_. x • lower ...
...... Atherfield Clay -----------------------.----------_.
...... +. Weald Clay
+ • ... +
+ ...
+ ... ...
... SAS315 - 71 m from instrumented section • SA9154 - 90 m from instrumented section x SA4116 - 590 m from instrumented section (nr. nadir sump) + SAS313A - 60S m from instrumented section (nr. nadir sump) • samples taken durin...9 excavation of the nadir sump
Figure 3-13: Bulk density with depth (see Figure 3-1 for relative borehole locations)
64
c;;-c... 6 (/) (/)
~ 1ii ro Q) .r: CJ)
400 ,---------~--------~----------~--------~--------~--------_,
, , , 300
, ,.. --- --- -- - --- ------ --:- ----------- -- ------ --------------------:--------------------:--------------------;--------------------
........ : " ...... :
200 ------------- ---- -- -1----- ----- - --------- --------------------r--- -- ---------------~------;?- --- -i----- - ____ a_awe_a.
, , , , , , , ,
:,.....
100
O +-------~_r---------+--~----~r_----~--+_--------_r--------__4
o 100 200 300 400 500 600
Mean effective stress s' (kPa) mid
Figure 3-14: Effective stress paths oflower Atherfield Clay specimens during monotonic shearing (Xu, 2005)
65
Undrained shear strength (CU)' kPa
o 100 200 300 400 500 600 700 O+----'---t--'---t------'--+-~_+-'--_t_-'--I__--'--____I
5
10
15
E
:S g.20 c
25
30
35
40
x x .... ~
• x
•
• I
x
x x ,......... 1013 kPa
~--------------------------~
• Cu found from 100 mm samples x SPT 'N' x 4.5
- best-fit line used for upper soil ..... best-fit line to Weald Clay SPT data
• • 38 mm tests from SA 8313A ... 38 mm tests from SA 8315
xx
approximate boundary between Atherfield Clay and Weald Clay
x
x
x x
• x x x ....
x
.... • x •
x
x x
x
"~
x
x
x
x
Figure 3-15: Undrained shear strength with depth found from 100 mm diameter laboratory samples and SPT results (38 mm test data are included for comparison)
66
5
10
15
E
:5 20 c. CI)
C
25
30
35
40
Undrained shear strength (c u), kPa
o 100 200 300 400 500 600 700
•
• • •
•
best-fit line found from laboratory samples (Figure 3-15)
•
• +--928
•
Figure 3-16: Undrained shear strength with depth measured with the self-boring pressuremeter
67
5
10
E
:515 c. CD C
20
25
30
Total horizontal stress, kPa o 100 200 300 400 500 600 700 800 900
, , , , , , , , , , , , . , , , , . " , , , , , ." ., , , ~ , . , ,
•
•
• •
'. , , , , , " . . \ , \-;--- overburden
\
• \ \
\ \ ,
\ , , ,
Figure 3-17: Total horizontal stress measured by self-boring pressuremeter
68
1.00E-09 1.00E-08
Permeability, m/s
1.00E-07 1.00E-06 1.00E-05 0+---~~-k~~4---~~~~~4----k~~~~~--~~~~~~
5 E
~ 10 ~ '"C
§ 15 e C)
~ 20 a; .c :5 25 Co CI)
c 30
35
•
Atherfield Clay •
•
•
•
•
Hythe Beds • • •
•
•
Weald Clay
\ trend line for Weald Clay data
y = -2.5364Ln(x) - 24.016
Figure 3-18: Permeability data
69
44
42
40
38 \
36
34
32
30
28
0 26
~24 E~22 ~20 CI)
...J 18
16
14
12
10
8
6
4
2
0
0
Ground level
Intercept = 42.7 m AOD Made Ground
_-========================8y~~=~~~~== \
\ \
\ \
./" Best-fit line through the measured pore water pressures (above 32 m AOD) u = 8.28 x (42.706 - Level (m AOD»
x\\x lower Atherfield Clay -------~-----------------------------
\ , Wall toe
Hydrostatic
, , , \ , , , ,
\ , , ,
/\\, groundwater profile based on 5 m drawdown from original ground
, \ , ,
Weald Clay
x pwp measurements 1.275 m from wall
, , \
\
water level \ u = 9.81 x (37.709 - Level (m AOD)\ , , , , ,
50 100 150 200 250 300 350 400 450 Pore water pressure, kPa
Figure 3-19: Pore water pressures: measurements and assumed profile
70
N
Instrumented section
@ CreoNn Copyri!~ht Ordnanee Survey. An EDI~tA. D igirnal','JISC supplied service .
Figure 3-20: Map of central Ashford showing the location of the instrumented section (Grid reference: 60081424)
71
South wall
mAOD
43.709 -.SZ.
37.259 _~ . -
/ I
I
I
North wall
Capping beam
Reinforced concrete prop I I
Thrust block ~
Temporary prop £&I --------- Waling beams ~
33.559 ...sz:.... r Base slab 1
Contiguous ~ bored pile wall
23.459
12.1 m
~ -
Figure 3-21: Cross-section of the cutting at the instrumented section
72
-.....) W
~
"""""" LMJ.. 1 I'ROI'05Il' ~
~. tDC£ _ _ "".."..,....,.. -i ~ Of. owe. Nroa. 4.JO-t)US- 08'H~-.£0920 6:21
~ ~.
II ~
if ;;
'" ~
&9,
~ 1000 -tJ~
11_ ft$)[ -pAPJ.PO ~AU.S
SOUTH WAll _J~_ 1.Q!l!t,
~.~_:.:-n .. _ ... -.... _. "'.
J 000.:'000 RD!'EDRCED COIIC>I£l£ __
PR(~ CONCReTE ORAlIMGE ~ NID I)I!I.INACE '!WET wnL rOf! l'II'ICJol. DEfNLS WU! '0 D¥I'G 'ios. OO-OUB- 088SO-409JO to 12
c.au- 00C1
2200
" 14~
t~ ..... I
lISlTy CCIHr.9Dt 111& SUoII
75- ntC. Sf ......,..; I.<VDI
4"!'O
~ $"'-...,M
..... ..... ~ .... -..
300 • 600 toHt1NUOuS RC COI!8EL (IYP.)
noo
=
+.~~
:l :. ~
~,
1'-- ~._. __ _
9" ~ .
§
1 ' J
n ~ ~ ~
l! ~
PR<lPOS(I) ...... It> Ll\IEl.
I~ CIA COHfQJOU5 ~ PU
Figure 3-22: Elevation illustrating the ground profile around the structure
I . ~IINOST_LOCP
~,~ '<7 •
I :r-'--______ L _________ _
000 IWJ.AST lNO 8'1"" C4J.4 COI'ITftltCTOft
6 7 8 9 10 -1100 ll5 - W 1100 1 - 2 3-_ _ _ ! i
- - - - -1800 Z X Y
-cr- @®®©@@@)®®®®© ®C;>CD©®®CD®® 1800 11 12 '
Dimensions in mm
N
~
- - : -11000
Extent of base slab A4
• Spade cell
(j) Pile and installation period
o Approx. sand drain positions
Z Inclinometer
X & Y Instrumented piles
Figure 3-23: Plan of the north wall in the instrumented section showing locations of instrumented piles, spade cells, sand drains and sequence of pile installation (see
Table 3-4)
Ground level
~ SZ 3.3 m bgl
~ sz 5.3 m bgl
Line denoting change Approx. ~J'. 316 8 in plasticity ~ casing depth ~~I/' ~ t ~ sz 8.3 m bgl
------------ -- ------ --- -- ---------------- ------------ --- ----- '. --- i-- ~-- -~ ------ - - - --- - -------13 11 ~ i ~SZ11.3mbgl
--~------~------------~--~~:~
Made ground
Hythe Beds
upper Atherfield Clay
lower 1:0 Atherfield Clay t sz 15.3 m bgl
20.3 m bgl sz ___ ____ ____ _
• Spade cell Horizontal dimensions in mm bgl- below ground level
18001800
:2200:
Weald Clay
: 2~00 : Dimensions in mm
Figure 3-24: Elevation of instrumented section showing spade cell locations
74
Day 1 - Bored Day 2(a) - Bored Day 2(b) - Filled Day 2(c) -open to 8 m then to 21 m with no with bentonite Concrete tremied casing inserted support support in from the base
CaSing!
Excavate to !
21m 1
Figure 3-25: Pile installation sequence
75
Figure 3-26: Pile boring
76
Figure 3-27: Installation of casing
77
Figure 3-28: Installation of reinforcement cage
78
North Centreline of wall excavation
mAOD These gauges only in RC prop P2 (see Figure 3-39)
43.709.5Z 1 Gauge reference
4EJ2 1 mAOD numbers
/ 3 B
Prop cross-sections .5Z 41 ·5 25 & 26 ~
showing positions of strain Strain gauges in gauges (facing north) the props
5L 40·0 23 & 24
~ ~ ~
5L 38·5 21 & 22
401
Temporary prop 5L 36·9 19 & 20
3 2 I
5L 35-4 17 & 18 ~
33.5595L Base slab 5L 33.9 15 & 16 ~
5L 32.5 13 & 14 ~
A pair of strain 5L 31 .0 11 & 12
gauges in the ~
base slab
5L 29.5 9 & 10 ~
5L 28.0 7&8
~ ~
Pairs of strain 5L 26.5 5&6 gauges in a pile ~
5L 25.0 3&4 ~
5L 24.0 1 & 2 23.459 'V ~
- -- ------- - --------------------------
Figure 3-29: Elevation of instrumented section showing strain gauge arrangement
79
00 o
Strain gauges ~~~~:
Figure 3-30: Strain gauges for measurement of pile bending moment
00 ........
Figure 3-31: Photo showing sand drain and cable for spade cell 11 (taken on 13th February 2001 - Day 495)
450 period of pile installation
1----.1
Beginning of main construction period
400 85-15.3~ :
~350 ~
t300 ~ .... (1)250 S c 2200 '': o .c 150 S ~100
50
1
812 "\r- l-/'
84 -~l ~1
O+OTT+r~~~"O+TT~"rhno~TT+r,,~~no~TT~~rhno~TT+r~
~150 ~
~100 ... Q. ... CI) 50 ;
o 28 56 84 112 140 168 196 224 252 280 308 336 364 392 420 448 Time in days
period of wall period of sand installation drain installation :~ -::-- P13-11.6m
P13 1 1 II 1 1 II I P11~~~ "~?-15.3m~ Pi? 1 : ~ P11-mm P12 : --~-v- ~-1"[3m
1 II 1 II
~ O+o"+OoT+>+r+r"r.rrrrrrhnrrl"""~"o+,,o+,,o+~.rrr.rrrrhno~ o c.. 0 28 56 84 112 140 168 196 224 252 280 308 336 364 392 420 448
Time in days
Figure 3-32: Changes in total horizontal stress and pore water pressure in front of the wall around the period of sand drain installation
82
00 w
Figure 3-33: Excavation either side of the north wall before break down to level of capping beam (taken on 1st November 2000 - Day 391)
Chains attached to pile with bolts
Figure 3-34: Pile top removal (south wall) (taken on 31st August 2000 - Day 329)
84
00 VI
Spade cell cables protected in plastic tubing
Figure 3-35: Wall before construction of capping beam (taken on 4th December 2000 - Day 424)
Wall was constructed here at a later date
t 850 500
Capping g Beam L!) T"""
150 Pile
I" • I 1050
Figure 3-36: Dimensions of capping beam (in mm)
Datalogger
Inclinometer • • tube
Figure 3-37: Capping beam (taken on 16th January 2001 - Day 467)
86
00 -....l
r·~aWlJl.;W;; V'ltJ:--·::·:---...!._' ''d ' ,.fI;~.~ """ , { .m!!iI·"t.l· .. ·l!I!!)!i!iii',·" .. :" ,. .* --------
Shuttering
Figure 3-38: Preparation for RC prop construction (taken on 16th January 2001- Day 467)
Direction of construction
Props P# - RC prop T# - Temporary prop
Shaded props are instrumented
Extent of base slab A4, 11 m
N
'x Pile
Z Inclinometer
X & Y Instrumented piles
Figure 3-39: Location of the instrumented props in relation to the instrumented piles
88
00 \0
Figure 3-40: Photo showing instrumented area before excavation (taken on 220d January 2001 - Day 473)
\0 o
Figure 3-41: Compacting backfill in the instrumented section (taken on 29 th January 2001 - Day 480)
\0 ......
Level, mAOD
43.709
42.209
Piles RC props
/ ~
Shaded props and piles are instrumented
Dates show when shaded areas of soil were removed
Piles X and Yare instrumented with strain gauges
Pile Z is instrumented with an inclinometer Capping
+-~~~L-______ ~-L ________ ~~ ______ -li~ ________ ~-L ______ ~~~ ______ -L~ ______ ~beam(see
:;:::;: Figure 3-36)
483-484 (Thu/Fri) ;;;:;:; I II I: I
!~m:'~i1rlU : : . Ir Tlcn) II Sli (Tue) 37.25~_\Z _ _ -_·_,·--·FJ-II III I,d ~ II ~ I !~:\ l i1.:>1 1 ~I ~::C 11 ® II]JJ~r~-J[ ~-n~ () Waling
beam
33.5~
I II II II II I nq TU ,'-,',), ...... .
by 524 "flied) .... ,', ,.,' .. , I-- \VY ... • ..
I II S~~b A~ ~ ins,~lIed : D~~~1 ! ~Iab A4 - installed .~ay 5!9 ~I~~e
If
wwwwwwwwwww~~ww~wwwwwwwww~
Figure 3-42: Elevation showing props and order of excavation. The shaded areas were excavated on the dates indicated, and the props and base slab were constructed on the dates indicated (excavation took place in 2001).
Figure 3-43: Excavation using long-reach excavator
Figure 3-44: Temporary prop with strain gauges
92
Figure 3-45: Temporary prop gauges welded onto prop
93
Corbel
2.5 % slope
~ I r---_____________ -+-____ B_a_s_e_s_la_b ______ -l
1600 4450
Figure 3-46: Elevation showing base slab arrangement (dimensions in mm)
Figure 3-47: Strain gauges wired onto base slab reinforcement (photo was taken looking down through base slab)
94
Figure 3-48: Storm drain installed behind north wall in November 2001 (Day 864)
95
Vibrating-wire interface
Storage module
" -,
Multiplexer
Modem
Battery
Figure 3-49: Datalogger set-up
~/ 2 Core Cable ~ ____ s~r
r--~~ (/ /"
Electro ~ " Magnet ,...
f "" .... _, t 1 \ \ , , \ , I , , \ •
INPUT PLUCK PULSE
(12 to 60 volts peak)
~ , , , ,
• f I \ , ___ ; I I 1 _ _
, • ______________ ~'~\~)~--~l ~I~I~-----------4 • • (" ., I I \
- , , , .-,~, ... - ..... -/-,- .- .... \' ; I , . ' ; " ,
" Magnetic Fleld---' , - - - - Piano Wire
Figure 3-50: Vibrating-wire gauge (Gage Technique)
96
4 STRUCTURAL MONITORING
4-1 Introduction
In this chapter, details of the instrumentation and the methods used to determine the
retaining wall displacement profile and the structural loads are presented. Data
representing the wall profile, wall bending moments and the prop loads at significant
stages of construction are presented and discussed. The instrumentation used to monitor
soil stresses and pore water pressures in the soil around the retaining wall (spade cells) is
described separately in Chapter 5.
97
4-2 Inclinometer
4-2-1 Description and Use
An inclinometer is a device for measuring inclination, or tilt. Inclinometers have been
used in numerous construction projects over at least the past 30 years to monitor ground
and structural movements, often as part of observational methods of construction (PecL
1969), e.g. The World Trade Centre (Saxena, 1975); Limehouse Link (Glass &
Powderham, 1994); Channel Tunnel Rail Link (Loveridge, 2000) and the Heathrow
Airside Road Tunnel (Hitchcock, 2003).
To find the retaining wall's deflected profile an inclinometer probe (Figure 4-1) is
manually lowered to the bottom of a tube installed within a pile. As the probe is pulled
back up, readings of the tilt angle are taken (using accelerometers) at 0'5 m intervals in
directions perpendicular and parallel to the wall. The inclinometer probe follows
longitudinal grooves in the tube to ensure that it does not rotate as it moves upwards. Base
readings are taken before the construction process being monitored begins (e.g.
excavation) and subsequent readings reveal changes that occur due to construction
activities.
To measure the absolute movement of the structure or ground mass being monitored,
either the tube must be extended below the structural component into ground known to be
stable (i.e. not affected by the construction process), or the top of the tube must be
surveyed at each reading. At the instrumented section the inclinometer tube extends 10m
into the ground beneath the pile toe to ensure fixity so that the absolute movements of the
wall can be determined. Further information regarding the use of inclinometers can be
found in Dunnicliff (1993).
Mikkelsen (2003) describes the types of errors that may occur when using an inclinometer
probe. In summary, these errors can be minimised by ensuring that:
• the same probe is used for all readings in a borehole;
• the same user takes the readings every time;
• the user is technically competent;
• the person who collects the data processes it; and
• the inclinometer probe is regularly calibrated.
98
These measures were taken by the monitoring team on the CTRL, who took inclinometer
readings across the site at Ashford (the data were mainly used for implementing the
Observational Method during construction).
In order to improve the accuracy of the inclinometer measurements two sets of data arc
collected for each profile: for the second set the inclinometer probe is rotated through
1800
• The difference between individual pairs of readings at a given level is called the I:lce
error or checksum. This is equal to twice the zero offset, or bias. The face errors are
displayed on the readout unit during data collection so that the user can check that these
errors are approximately constant throughout the survey. If the face errors are constant
there is no overall effect on the final inclinometer measurements. However, operator
technique, instrument performance and casing conditions (such as variability at joints or
dirt) can affect the face errors. For example, because the wheels on the inclinometer are
angled (Figure 4-1: they are sprung to ensure that the inclinometer runs in the tube
grooves), at tube joints the wheels may be resting on different sections of tubing and
therefore larger face errors may occur. In this case, larger face errors will exist in all
profile readings and can therefore be identified.
Ifthe face errors are randomly inconsistent, analysis ofthe individual readings can reveal
where the errors occur and the data can be altered accordingly. Figure 4-2 shows the face
errors from an inclinometer profile taken on Day 581 (after Base Slab Construction and
before Temporary Prop Removal). Some unusually large face errors are recorded at
various locations in the inclinometer tube. Table 4-1 shows the Face A and Face B
inclination readings at 41·593 m AOD and the calculated face errors for the data sets taken
on Day 581. At this reading location only the Face A reading was inconsistent. Having
identified the locations of these large face errors, comparison of the readings recorded at
these locations with those taken on the preceding and following days allows the rogue
readings to be identified and adjusted (amendments are shown in brackets).
Day 523 537 538 542 549
Face A 4·1 4·1 4·6 (4'1) 4·0 4·2
FaceB -2'4 -2,4 -2·5 -2·4 -2·3
Face error = (A+B)/2 0·85 0·85 1·05 (0'8) 0·80 0·95
Table 4-1: Example of inclinometer data analysis and correction using face errors: 41-593 m AOD
99
The original and amended profiles for readings taken on Day 581 are plotted in Figure -+-2.
The other data points highlighted in this plot were similarly analyzed and altered. For this
profile adjusting the data in this way 'moved' the top of the wall by 1·5 mm. This is about
8% of the overall movement at the top of the wall. All the inclinometer data were adjusted
in this way.
A further check on the accuracy of the data can be made by studying the wall toe
movement. Figure 4-3 shows the deflection of the wall toe with time (from the
inclinometer measurements). Although the data are scattered, those recorded before the
base slab was installed appear to show a general movement of the wall toe into the
excavation. The equation of the best-fit line to the readings taken before Base Slab
Construction is shown on the graph. (NB: The movement profile is not really linear as
different construction activities would produce more movement than others, however
since the total movement is so small (1'5 mm), the assumption of a linear movement
profile is justified.) Figure 4-4 shows (a) the as read profiles of the entire inclinometer
tube (adjusted for face errors as described above); (b) the corrected wall profiles assuming
a fixed toe; and (c) the corrected wall profiles assuming the toe moves according to the
equation found in Figure 4-3, for a small selection of the data taken during Excavation
Phase 1. Figure 4-4 shows that the adjustment described above produces much more
consistent data which is more easily viewed and analysed. The scale on which the
deflection data are plotted covers a small range of deflections, showing that in general
these errors are very small.
Less frequent inclinometer readings were taken after Base Slab Construction so it is more
difficult to infer the wall toe movement after this time. Figure 4-3 suggests that after Base
Slab Construction the wall returned to its original position and then slowly over the
following year moved back out into the excavation by a similar magnitude as during
excavation. This movement might seem reasonable; however Figure 4-5, which shows
inclinometer measurements taken within the entire inclinometer tube (i.e. including those
taken in the ground below the pile toe) following Base Slab Construction, shows that the
whole tube below the wall toe appears to be moving. This is highly unlikely because
movement of the wall toe would only be expected to cause movement of a metre or so of
the tube beneath. Therefore after this time the wall toe has assumed to have been
stationary.
100
Figure 4-6 shows all wall profile data found from the inclinometer data (adjusted for errors
as described above). Figure 4-6(d) shows the inclinometer profiles taken after Base Slab
Construction over this period corrected for zero movement of the toe. The profiles show
the top of the wall gradually moving into the excavation with time, with the exception of
the data taken in June and July where the wall moves very little. This behaviour would be
expected during and following Temporary Prop Removal. Therefore, the assumption that
the toe has remained in the same position as it was at the end of construction appears to be
valid. The inclinometer measurements show that the wall toe is in a similar position on
Days 585 Gust after Base Slab Construction) and 718 (over 4 months later).
The large deflections measured at the top of the wall are likely to be due to the
unsymmetrical geometry of the structure. The readings indicate that the structure has
swayed towards the south wall, where the ground level is lower than that behind the north
wall (Figure 3-22). This movement is described in more detail in Section 4-5-5.
The data taken below the toe of the pile can be used to determine the random errors
associated with the particular instrument and survey point. The maximum reading taken
over this section of inclinometer tube is 1·7 mm, indicating a maximum random error of
1·7 mm per 10m of inclinometer tubing.
Figure 4-7 shows the movement of the top of the wall with time. It shows gradual
movement into the excavation until Base Slab Construction after which the movement
reduces significantly. (It must be noted that this data is however based on the readings that
have been corrected for zero toe movement after Base Slab Construction. Therefore at a
minimum, the graph shows that there is little relative movement of the top of the wall to
its toe).
4-2-2 Calculation of bending moments from inclinometer data
Bending moments are frequently calculated from the bending strains measured using
vibrating-wire strain gauges embedded in concrete retaining walls (e.g. Tedd et al., 1984)
and piles (e.g. pile stabilized slopes: Smethurst, 2003). In order to estimate pile bending
moments from inclinometer readings, it is necessary to differentiate twice an equation
representing the deflected profile of the pile (measured with the inclinometer). To find an
equation for the wall's deflected profile, a curve (such as a polynomial) must be fitted to
the deflection data.
101
Ooi & Ramsey (2003) compared twelve methods for calculating bending moments from
inclinometer data including piecewise fitting of quadratic and cubic curves, and global
polynomial curve fitting. They noted that if using global polynomial curve fitting, the
lowest possible degree of polynomial that will "adequately" describe the data should
ideally be used. This will allow the main changes in wall shape to be modelled without
including small local errors in the inclinometer data. In general Ooi & Ramsey concluded
that piecewise fitting of cubic curves to windows of five points yielded "middle" values of
curvature and that when maximum curvature values found using this method were
compared to strain gauge data collected from laterally loaded piles the values were in good
agreement. For inclinometer data collected at the CTRL site global polynomial fitting has
been found to give good correlation with bending moments calculated from strain gauge
readings.
The second derivative of the equation representing the deflected wall profile yields an
expression for its curvature, K, of the wall, where K = liRe and Re is the radius of curvature
of the pile. The bending moment, M, is calculated from the product of the curvature and
the flexural rigidity of the pile, EI (Equation 4-1), where E is Young's modulus and I is
the second moment of area. For a circular cross-section with constant stiffness the second
moment of area is given by Equation 4-2, where r is the radius of the pile. The stiffness of
steel is approximately eight times that of concrete, therefore the flexural rigidity must be
calculated to include the effect ofthe steel in a reinforced section (see Section 4-3-3).
Equation 4-1
Equation 4-2
The pile concrete had 20 mm granite aggregate and a characteristic strength of 40 N/mm 2.
The mean 56 day cube strength of 61 cubes taken from the piles cast in the period the piles
in the instrumented section were cast was 73'0 N/mm2• It should be noted that this is
higher than might be expected, however it does refer to the 56 day cube strength (it is
more common practice to quote the 28 day strength for concrete).
The bending moment is defined as positive when the excavated side of the wall is in
tension.
102
It is important to carefully consider the degree of polynomial used to fit to the profile data.
A polynomial with a similar number of inflections as the shape of the profile should be
chosen, otherwise the bending moment plot produced will have too few/too many
inflections and indicate an inaccurate bending moment profile. A 5th order polynomial is
most suitable for representing the deflected shape of a wall which has a linear horizontal
pressure distribution acting on it (the pressure distribution is given by the 4th derivative of
the chosen polynomial). In reality the pressure distribution is unlikely to be perfectly
linear, and therefore both 5th and 6th order polynomial equations were fitted to the
deflected wall profile (determined by the inclinometer readings) before and after two
construction stages at which cracking appears to have occurred (described later). The
correlation coefficients for the curves were all greater than 0'997, which superficially I
indicates a high level of accuracy for the curve fit. Comparisons between the bending
moments calculated from the inclinometer and strain gauge measurements are made in
Section 4-4-5.
Factors that affect the stiffness of the pile and in tum affect the suitability of the curve
fitting include:
• changes in cross-sectional area of the element;
• changes in reinforcement stiffness; and
• concrete cracking.
These factors affect the continuity of the pile element and hence the mathematical
accuracy of the curve fit. It may be better to fit several curves to sections of the pile with
continuous properties. The reinforcement in the piles in the instrumented section reduced
from 50 mm to 40 mm diameter bars about 6 m above the pile toe (described in Section 4-
3-3). In addition, there was a bulge in the piles just below the level of the casing,
(described in Section 4-4-4). In this case however a better curve fit and bending moment
distribution was given by the curves fitted to the entire pile.
Cracking reduces the pile's cross-sectional area; therefore the value of I must be modified
to take account of this or the calculated bending moments will tend to be overestimated.
Further comments on fitting curves to inclinometer data are made in Section 4-4-5.
1 It is important to note that the correlation coefficient can be misleading: the higher the order of polynomial fitted to the data, the higher the correlation coefficient, but this does not necessarily mean the curve fit will give the best equation for the bending moment profile for the reasons already explained.
103
4-3 Vibrating-wire gauges
4-3-1 Use
Precautions that must be taken when using vibrating-wire gauges include the avoidance of
magnetic fields and magnetic particles. Since the railway was opened there has been no
obvious influence from passing trains on the data. It is also important to ensure that the
elasticity of the gauge approximates to the elasticity of the concrete for the period over
which the measurements are to be taken (British Standards Institution, 1986).
4-3-2 Method/or calculation o/prop loads/rom strain gauge measurements
In order to calculate prop loads and bending moments from strain gauges the strain in the
wire (and therefore the prop or pile), 8, is calculated from Equation 4-3 (where F\ is the
datum frequency of the wire equivalent to zero strain in the prop, F2 is a subsequent
reading and GF is the gauge or calibration factor, equal to 3·025 x 10-3 for the gauges used
in this project). The prop load, P, can then be found from Equation 4-4 (where A is the
cross-sectional area of the prop and E is the stiffness of concrete (for the RC props) or
steel (for the temporary props). The stiffness of steel has been taken as 205 MPa and a
value of25 MPa has been used for the stiffness of concrete (Mosley and Bungey, 1976).
This is a conservative value and the actual value may be higher (the concrete cube strength
data collected for the pile concrete is relatively high, however once load is applied creep
has a significant effect, effectively reducing the concrete stiffness). The calculated prop
loads and bending moments might therefore be underestimated.
Equation 4-3
P=& E A. Equation 4-4
Surface-mounted strain gauges are commonly used to measure temporary prop loads (e.g.
Richards et al., 1999; Batten & Powrie, 2000; Loveridge, 2000) as part of construction
monitoring (for example using the observational method: see Section 4-2). Many of the
issues concerning their use have been discussed by Batten et at. (1999), including
temperature and end effects and the influence of the instrument's location on the prop.
104
4-3-3 Method/or calculation o/bending moments/rom strain gauges
Bending moments in concrete retaining walls are calculated from strain measurements
obtained using embedment strain gauges placed in pairs at intervals up the concrete
section, with one at the front and one at the back of the wall at the same elevation (see
Figure 3-29). For an uncracked section of wall, the bending moment in the wall, lvI, is
calculated from the longitudinal bending strains &\ and &2 measured by the strain gauges at
the back and front of the wall respectively using Equation 4-5, (derived from Equations 4-
1 and 4-6) where y is the distance from the gauge to the neutral axis.
Equation 4-5
Y Rc =-. Equation 4-6 &
In the concrete piles used at Ashford there are 16 longitudinal reinforcement bars making
up 3·6% of the total cross-sectional area of the pile. The flexural rigidity (Elvalue) of the
pile has therefore been calculated to take the effect ofthe steel into account (see Appendix
C). The lower section ofthe pile (incorporating gauges 1-10: see Figure 3-29) has smaller
reinforcement bars and therefore a lower flexural rigidity. The flexural rigidity of the two
pile sections are given in Table 4-2.
Top of pile
Bottom of pile
Gauges
11-26
1-10
Flexural rigidity:
per pile, kNm2
2015300
1826600
per m run of wall, kNm2/m
1492800
1353000
Table 4-2: Flexural rigidity of concrete piles
For a circular section the flexural rigidity is proportional to the square of the cross
sectional area, A. (Equation 4-7: given that I = A 12, where k is the radius of gyration (for a
circle 12 = Y4 ? and A = 1t r2)). Therefore when the area decreases (for example when
cracking occurs) the flexural rigidity of the pile decreases rapidly.
EI= EA2 41Z"
Equation 4-7
105
Uncracked behaviour is usually assumed to exist in the calculation of bending moments
from strain gauge data (Tedd et al., 1984; Wood & Perrin, 1984; Hayward, 2000).
However, it is important to determine whether cracking has occurred because if so and the
value of the E1 is not adjusted accordingly, bending moments may be significantly over
estimated from gauge measurements. Details of how to calculate the cracked flexural
rigidity can be found in Branson (1977).
The cracking moment of the wall, Men is the moment corresponding to the maximum
tensile stress that the wall can accommodate (the modulus of rupture of concrete,.!,'.). The
most commonly used relationship between the modulus of rupture and cracking moment is
shown in Equation 4-8, wheref,. is given by Equation 4-9 (American Concrete Institute,
1992), Ig is the gross second moment of area of the pile (0·059666 m 4) and y, is the
distance from the centroid to the edge of the section. In Equation 4-9,!c' is the cylinder
compressive strength of concrete, and is taken to be 0·8!cu, where!cu is the 100 mm cube
compressive strength (Eurocode 2, 1992). On the basis of the analysis of the results from
over 12000 tensile strength tests, Raphael (1984) proposed Equation 4-10 for the
calculation off,..
Equation 4-8
Ir = O· 623.[l (in MPa). Equation 4-9
Ir =2.3/;2/3 (in psi). Equation 4-10
As stated in Section 4-2-2, cube tests of samples taken on site showed that the pile
concrete has a cube compressive strength of 73 MPa, giving the values for Mer listed in
Table 4-3. For these calculations Yt was taken as half the diameter of the pile.
Equationfr is calculated from
Equation 4-9
Equation 4-10
541
749
Table 4-3: The cracking moment of the wall, Mcr~ calculated by different methods
106
4-3-4 Correction for temperature effects
Structural elements expand and contract with temperature which causes changes in load
which are not induced by excavation or other structural loading. Temporary props are
particularly susceptible to changes in load due to temperature, as they are made of steel
which has a high thermal conductivity and therefore they absorb a great deal of heat
particularly when in direct sunlight. The relationship between temperature induced load
and temperature for temporary props is approximately linear (see Figure 4-8) and a
correction between temperature and load can be made based on this relationship.
However, it is important to remember that the readings represent actual loads in the props
which must be considered in design, and that the fluctuation of load with temperature can
be very large. During construction of the Canada Water underground station in London the
axial load varied by up to 50% during summer due to temperature effects (Batten e/ al.,
1999). The temperature versus load correction is therefore only made so that a comparison
can be made between design loads and loads calculated from back analysis of field
measurements.
The temperature corrected load, NT, is given by Equation 4-11, where N is the measured
load, To is the temperature of the gauge at installation (before any loading in the prop), TN
is the temperature at the time of reading Nand m is the gradient of the load versus
temperature relationship (for example m = 44·439 kN/oC in Figure 4-8).
Equation 4-11
4-4 Analysis of instrumentation data
4-4-1 Temporary prop data
The temporary prop loads uncorrected for temperature effects and the average temperature
measured by all gauges are shown in Figure 4-9. Before excavation there is very little
fluctuation in the readings because the gauge wire and body are composed of material
having the same coefficient of expansion as the prop and therefore there is no overall
change in tension in the wire as the prop and gauge expand and contract with temperature.
During excavation the prop loads are significantly affected by changes in temperature as
the ends of the props are restrained by the retaining walls.
107
The temporary prop loads corrected for temperature effects are shown in Figure 4-10. The
temperature correction has significantly reduced the variation in the readings with
temperature when load is recorded. However, before excavation, when there is no end
restraint to the props, the correction distorts the data so that it appears load is being
recorded. Hence, temperature correction is only appropriate when the props are restrained
to some degree.
The base readings for the temporary prop data (and the temperature correction) were taken
as the average of the readings from installation of the prop until the day before Excavation
Phase 2 began, over which time the readings were reasonably stable (this was 7 days for
TI and 6 days for T2 and T3). One ofthe gauges on TI (number 4) was broken during
excavation. Thereafter the load at the position of gauge 4 was taken to equal that measured
in gauge 3, as the loads had been similar up to this point, and the loads measured in gauges
3 and 4 of the other props are also similar.
4-4-2 Base slab data
Data from the base slab for the period from just before installation to approximately two
years later are shown in Figure 4-II(a). Set I relates to the pair of gauges to the north-west
of the instrumented section (closest to slab A3 which was constructed previously) and the
pairs are then equally spaced along centreline of the slab A4. Data collection began before
the concrete was poured so the fluctuation at the start of the graph (shown in detail in
Figure 4-II(b)) relates to the gauges expanding and contracting at a different rate to the
reinforcement to which they are attached. Zero readings for the strain calculation were the
average of the readings taken over the 72 hour period prior to concreting.
A large increase in load is indicated after the concrete was poured. The majority of this is
not load carried by the slab but a change in strain induced by the rise in temperature
caused by hydration of the cement as the concrete cures. The temperature increased to just
over 40°C, causing expansion ofthe gauge which is resisted by the setting concrete. There
is no similar decrease in load as the concrete cools which indicates that the gauge and the
concrete are cooling and contracting at the same rate. (It will be shown later in Section 4-
5-4 that the bending moments measured in the piles at the level of the base slab reduce at
the time of Base Slab Construction.)
108
Figure 4-12 shows the typical relationship between temperature and 'load' indicted by the
measured strain for a base slab gauge over the period of the concrete pour and after
temperature stabilization. There is no obvious relationship between load and temperature
for the period after temperature stabilization, and it is not possible to determine whether
the compressive strain indicated by the gauge is due to thermal effects or load being taken
up by the slab.
The temperature fluctuations experienced by the gauges in the base slab are small because
the slab is in contact with the ground at the bottom of the excavation which is at a
reasonably constant temperature (being generally out of direct sunlight).
Figure 4-13 shows the strain measured in the separate gauges for sets 1 to 4, where
compressive strain is positive. The strain behaviour is different in all sets and it is difficult
to distinguish a general pattern. Figure 4-13 shows that after ballast was placed on the base
slab between Days 998-1028 (July 2002), the daily fluctuations in temperature recorded
by the strain gauges became negligible.
4-4-3 Reinforced concrete prop data
When concrete cures it undergoes shrinkage due to the hydration process, and when load
is applied it is also subject to creep2. Analysis of reinforced concrete (RC) prop strain data
is therefore complicated because the strain measured is a combination of the strain due to
shrinkage, strain due to the applied load and strain due to the effects of creep. To illustrate
the possible magnitude of strain occurring due to creep effects, Neville (1970) states that a
typical creep deformation after a year under load is three times the deformation under that
load.
Concrete undergoes continual shrinkage as it ages, with the majority of this shrinkage
occurring in the first 28 days after the concrete is poured. It is possible to estimate the
amount of strain occurring due to shrinkage if measurements of strain are taken in the
immediate aftermath of the RC prop concrete pour and before any load is applied to the
prop. Any strain occurring during this period is due to shrinkage alone and therefore the
relationship between shrinkage and time can easily be established. A curve fitted to even
2 Creep is deformation occurring under, and induced by, a constant sustained stress (or applied load).
109
only a few weeks' of such data can provide a sound basis for estimating the strain due to
shrinkage that has occurred after any time period, even after load is applied to the prop.
The shrinkage due to creep is more difficult to quantify. Creep occurs when the strain
continues to increase after the application of load. This indicates that the stiffness, Ecollc • is
decreasing. It is possible to estimate the amount of creep that has OCCUlTed through
analysis of the data collected in the long-term, when the applied load is considered to be
relatively constant.
Calculation of strain due to shrinkage
The reinforced concrete prop strain data was not collected until 9 days after the last RC
prop concrete was poured, and it was then only another 7 days before Excavation Phase 1
commenced. It is therefore difficult to determine from the strain gauge data the rate of
shrinkage due to concrete curing and how much of the final shrinkage had occurred before
load was applied to the props. The strains measured in the concrete props over the period
of excavation (using for the zero strain reading the average of the readings taken over the
24 hours immediately before excavation under the props began) are shown in Figures
4-14,4-15 and 4-16 for props PI, P4 and P2 respectively. It appears from these figures
that the strain is increasing at a reasonably regular rate and the changes due to construction
events are difficult to identify.
The strains plotted in Figures 4-14 to 4-16 are a combination of strain due to shrinkage
and loading. To establish the effects of shrinkage it was proposed to cast a short section of
'prop' using the same concrete mix design and reinforcement detail, and to embed a
number of vibrating-wire strain gauges in it. Owing to site constraints this was not
possible, however it was possible to analyse strain data collected from RC props (with a
similar concrete mix and dimensions) cast elsewhere on site to estimate the concrete
shrinkage. These props were at chainage 89+205, approximately 700 m away from the
instrumented section.
Ross (1937) proposed the hyperbolic equation for concrete shrinkage given in Equation 4-
12, where Esh(t) is the shrinkage at time t and a and b are constants found from
experimental data, being the y-intercept and slope respectively of the linear relationship
between t I ESh(t) and time. This relationship was deduced for three instrumented props at
chainage 89+205. Strains in these props were monitored (using identical vibrating-wire
embedment gauges to those used at the instrumented section) throughout the concrete pour
110
and the period before excavation; a period of at least 28 days. It should be noted that at the
instrumented section the RC prop concrete was poured in January when temperatures were
3-8 DC, while at chainage 89+205 the concrete was poured in July when daily
temperatures ranged between 6-28 DC (measured by the thermistors in the RC prop
vibrating-wire gauges). The rate of curing and shrinkage is likely to be affected by the
ambient temperature at the time of the concrete pour and during curing, however the
resultant total shrinkage is considered to be independent of temperature.
t &s,,(t)=--·
a + bt Equation 4-12
Figure 4-17 shows a graph of t / &sh(t) against time for a typical strain response gauge at
chainage 89+205. The values for a and b calculated for all the gauges at chainage 89+205
are presented in Table 4-4, together with the maximum strain due to shrinkage indicated
by the data from each gauge using Equation 4-12.
Prop gauge a b r t 1 (. . ) Im--=- mlcrostram HOC! a+bt b
1 23170·8 4235·3 236·1
2 21346·9 4756·33 210·2 1 (Ch 89+205)
3 15583·5 5238·6 190·9
4 28178·6 4626·79 216·1
1 26562·5 4676·08 213·9
2 19539·1 4624·83 216·2 2 (Ch 89+205)
3 18549·1 4685·94 213·4
4 22791·9 4389-48 227·8
1 17151·9 4683·19 213·5
2 17198·8 4474·94 223·5 3 (Ch 89+205)
3 13626·8 5113·68 195·6
4 15783·0 4551·24 219·7
average 215 /-!E
Table 4-4: Values of a and b calculated for all gauges at chainage 89+205 m
The strain predicted by Equation 4-12 is compared with the measured strains (for the same
data plotted in Figure 4-17) in Figure 4-18. Using Equation 4-12, the strain measurements
from the RC prop gauges at chainage 89+205 predict that 215 /-!E of strain (with a range of
111
191-236 Ilf:) would have occurred in the long-term due to shrinkage, with 95% of this
strain occurring within 85 days of the props being cast. At the instrumented section this
was Day 552 (11 th April 2001); 15 days after Excavation Phase 2 and 27 days before Base
Slab Construction.
In Table 4-5 the following details are listed:
1. the length of time between construction and excavation directly underneath for the
props in the instrumented section,
2. the amount of shrinkage strain that would have occurred during excavation under
the props (calculated from the analysis on the props at chainage 89+205) and
3. the equivalent load that this strain would indicate if a correction was not made.
Prop PI P2 P4
Day constructed 465 465 467
Day Excavation Phase 1 began directly 483 487 505
underneath prop (see Figure 3-42)
Number of days between prop construction 18 22 38
and excavation directly underneath
Average strain at chainage 89+205 after this 160 166 202
length of time, Ilf:
Load indicated by this strain, kN 3989 4149 5049
Amount of shrinkage strain occurring in prop after excavation began directly 55 49 13 underneath, Ilf:
Equivalent load, kN 1379 1218 318
Table 4-5: amount of strain occurring due to shrinkage and equivalent load indicated by this strain for the props at the instrumented section
The calculations in Table 4-5 clearly indicate that if a correction is not made for concrete
shrinkage in cases where load is applied soon after prop construction, prop loads may be
significantly overestimated. Figure 4-19 shows the RC prop loads calculated using the
strains in Figures 4-14 to 4-16 and Figure 4-20 shows the loads calculated by reducing the
measured strains according to the analysis carried out on the readings from chainage
89+205. There are several points to make about these graphs regarding the shrinkage
correction:
112
1. The correction for shrinkage reduces the prop load by approximately 800 kN by
Day 552 (after which 95% of the shrinkage strain will have occurred).
2. The correction appears to have reduced the amount by which the readings increase
during periods when load is (apparently) not being applied, however there are still
periods where the load increases more than expected: during Excavation Phase 1
(particularly in PI and P2); before Excavation Phase 2; and after the temporary
props are removed.
Figure 4-21 shows the RC prop load data only up to the end of Excavation Phase 2. On
this graph the periods during Excavation Phase 1 when material directly under the RC
props was removed are indicated, and the corresponding increases in load are clear.
Another point of note is that after Tl was installed, the RC prop loads appear to decrease
when the temperature increases, and visa versa. This effect is particularly prominent at the
positions indicated by IT] and [2]. This may be because as the temporary props expand
with an increase in temperature the walls are pushed into the soil and the load in the RC
props is therefore reduced. It is also likely that because load is now being applied to the
RC props, creep is beginning to have an effect.
Calculation of strain due to creep
Equations representing the change in stiffness with time (due to the effects of creep) for
each prop have been estimated by assuming that the prop loads do not change after Day
607 (other than for seasonal and daily temperature variation). Day 607 was chosen
because it is 28 days after the base slab was poured and after the temporary props were
removed (on days 581 (Tl), 595 (T2 and T3) and 600 (T4)), and therefore it is assumed
there is no further change in load due to the preceding construction events. To remove the
effect of seasonal and daily variations, the load in the props has been assumed to be the
same as that recorded at 9 am on Day 607 as at the same time on the same day every year
following, i.e. on Days 972, 1337, 1702 and 2067. The variation in temperature recorded
at 9 am on these days by the thermistors in the gauges was only 3°C.
The Young's modulus, Econc, was found on each of these days using Equation 4-4,
assuming that the initial stiffness was 25 MPa. Equations with the form given in Equation
4-13, where N is the number of days and A, B, and C are constants, were then found (using
the least squares fitting method) to these data for each prop - see Figure 4-22. The
calculated values of A, Band C which provide the best-fit curves to the prop stiffness/time
113
relationship are given in Table 4-6. (Exponential expressions have commonly been used to
model creep behaviour in the past: see Neville, 1970.)
-N -
Econc = Ae B + C . Equation 4-13
PI P2 P4
A 12·756 12·971 14'741
B 12·222 11·981 10·222
C 558·12 816·98 606·20
Table 4-6: Values of constants for best-fit line to stiffness/time relationship (to 5 significant figures)
These equations were then used to calculate the stiffness used in the calculation of the RC
prop load from Day 607 onwards. As data collection is ongoing, in the future it will be
possible to get a better estimate of the creep behaviour.
Because the correction for creep has only been applied to the measurements taken after
Day 607, it only affects the long-term data, presented in Chapter 6. An adjustment for
creep should really be made as soon as load is applied, and therefore the reported RC prop
loads may be over-estimated (however the value of the initial Young's modulus is also an
estimate - see Section 4-3-2). In the first year after Day 607, 39 /-lE can be attributed to
creep. This is equivalent to 974 kN ofload, calculated using a Young's modulus of25
MPa. It was 4 months (or a third of this time) between the time excavation began under
the props (i.e. load began to be applied to the props) and Day 607. Although the strain due
to creep occurs at its fastest rate when load is applied, the load was initially small.
Therefore the creep occurring before the correction was made can be estimated to be a
maximum of 500 kN.
Effect of changes in temperature
The temperature versus load data for a typical RC prop strain gauge during periods when
no construction activities are taking place is shown in Figure 4-23. This figure shows that
there is no clear relationship between prop load and temperature which can be used for
correcting the daily and seasonal temperature induced fluctuation in load. However, the
RC props are not affected by temperature to the same degree as the temporary props and
are therefore more straightforward to analyse.
114
Further comments
There are a number of further comments that can be made regarding the reinforced
concrete prop data.
1. The load measured in prop P4 is significantly lower than that measured in props PI
and P2. The reason for this is uncertain, but may be due to anomalies in the
construction detailing such as a lack of fit at the prop wall interface.
2. The daily fluctuations in prop load in P4 are smaller than in props PI and P1. This
may be caused by variations in the concrete cover to the gauges, making them
more thermally insulated. This might have occurred if either P4 is larger than the
other props (which is unlikely but would also explain the smaller load recorded in
this prop as a larger surface area would indicate a larger load) or the gauges are
embedded further into the prop. Smaller strains would be expected to be measured
in either ofthese cases, as the gauges are proportionally closer to the neutral axis
of the prop.
3. A reduction in load was recorded in all 3 RC props on the removal of temporary
prop Tl, whereas an increase load in props PI and P2 was recorded when props T2
and T3 were removed, and similarly an increase was recorded in prop P4 when
prop T4 was removed. The base slab concrete reached its maximum strain and
temperature on the same day as Tl was removed, resulting in the decrease in load
measured by the other RC props, and masking the effect of the temporary prop
removal.
4-4-4 Pile data
Theoretically, if the neutral axis is in the middle of a pile section and there is no axial load
the bending strains at the front and back of the pile at any elevation will be equal and
opposite. In reality, as well as the self-weight of the pile and the capping beam, axial load
in the pile will be caused by wall friction on the front and back faces of the piled wall.
Figure 4-24 shows the difference in strain measured between the front and back of the pile
at each gauge pair elevation against time for piles X and Y (see Figure 3-29 for gauge
elevations). Figure 4-24 shows that for most gauge pairs the difference in strain between
the front and back ofthe pile is small. However, the values increase suddenly for gauge
pairs 15&16 and 17&18 in pile X at the start of Excavation Phase 2, and for 21&22 in pile
115
Y after Temporary Prop Removal. Figure 4-25 shows the strain measurements for these
individual gauges. Figure 4-25(a) shows that during the Excavation Phase 2 much larger
strains are measured by gauges X16 and X18 (even numbered gauges are at the front of
the pile) than by their partners, gauges X15 and X17 respectively. Figure 4-25(b) shows
that during Temporary Prop Removal a larger strain is measured by gauge Y22 than Y21.
These changes in strain are likely to be caused by to cracking in the piles. Figure 4-25(a)
also shows that following cracking of the pile during Excavation Phase 2, the response to
Temporary Prop Removal is much larger in the gauges at the front of the wall than the
gauges at the back.
Pile deflections measured with the inclinometer in Pile Z around the time of Excavation
Phase 2 and Temporary Prop Removal are shown in Figure 4-26. The elevations of gauges
15& 16, 17& 18 and 21 &22 are indicated. The figure shows that the points at which the
strains have increased to a greater degree at the front of the pile than the back of the pile
correspond with the points where the maximum deflections over the period have been
measured.
Table 4-7 lists the wall deflections and curvatures measured by the inclinometer for the
gauges at which the largest values were recorded before and after the two construction
activities that appeared to cause cracking (temporary prop removal and excavation phase
2). The changes in the values over these periods are included. The values relating to the
positions at which cracks occurred have been highlighted. As expected, the data show that
cracks occurred at positions where the largest changes in deflection and curvature
occurred, and indicate that the change may be more important than the degree of
deflection and curvature in initiating cracks. However, cracks do not appear to have
formed at the position of gauges 13&14 during Excavation Phase 2 and at gauges 23&24
during Temporary Prop Removal, where the changes in curvature that occurred were at
least as high as values at other locations where cracks did form. It is therefore likely that a
combination of the changes in deflection and curvature affects the propensity for cracking.
As previously noted, the bending moment in the pile may be affected by local changes in
the pile's cross-sectional area, which affects the flexural rigidity, EI, of the pile. Figure
4-27 shows a bulge in the pile just underneath the bottom of the casing used during
installation, indicating that overbreak has occurred at this level during excavation for the
piles, and the resulting cavity was consequently filled with concrete. This level
corresponds approximately with the level of gauges 17& 18 and 19&20, which indicate a
116
smaller bending moment than those calculated at the locations of gauges 15& 16 and
21&22 in the stages before cracking occurred, shown in Figure 4-29 (see next section).
This excess concrete was removed after construction was completed, some time between
August and October 2001.
Gauges 13&14 15&16 17&18 19&20 21&22 23&24
Elevation, m AOD 32·5 34 35·5 37 38·5 40
8, pre Exc. Phase 2 (Day 529) 7·5 8·7 9·7 10·3 10·6 10·8
8, post Exc. Phase 2 (Day 540) 16·9 18·6 19·1 18·8 18·1 17·3
Change in 8 9·4 9·9 9·4 8·5 7·5 6·5
8, pre TP Removal (Day 564) 18·3 20·2 20·7 20-4 19·5 18·6
8, post TP Removal (Day 617) 21·7 24·3 25·9 26·5 26·1 25·1
Change in 8 3·4 4·1 5·2 6·1 6·6 6·5
K, pre Exc. Phase 2 -0·065 -0·099 -0·125 -0·139 -0·139 -0·119
K, post Exc. Phase 2 -0·306 -0·344 -0·348 -0·312 -0·232 -0·102
Change in K -0·241 -0·245 -0·223 -0·173 -0·093 0·017
K, pre TP Removal -0·3 -0·343 -0·353 -0·321 -0·24 -0·101
K, post TP Removal -0·289 -0·402 -0·459 -0-446 -0·366 -0·231
Change in K 0·011 -0·059 -0·106 -0·125 -0·126 -0·13
Table 4-7: Changes in deflection, 8, (mm) (relative to the toe) and changes in curvature, K, ( X103m-l) (from the 5th order polynomial curve fit) over periods of pile
cracking. Positions where cracks have occurred are highlighted.
Figure 4-28 shows strains measured in Pile Y (see Figure 3-29 for the gauge elevations)
after excavation and before Base Slab Construction; (Days 542-571) therefore the ground
was at the level of the bottom of the base slab, just below gauges 15& 16. Over this period
the average temperatures measured in the temporary props ranged from 1 to 21°C, with an
average of 10°C. The figure shows that there is a linear relationship between temperature
and strain for the gauges at the front of the pile (odd numbers). The temperatures in these
gauges vary by 6°C; this was 30% ofthe temperature variation measured by the
temporary prop thermistors over the same period. This caused the strain to vary by
approximately 30-40 j.l8, which would indicate 66-89 kNm of bending moment. There is
no clear relationship with temperature for the gauges at the back of the pile, although the
temperature range experienced by these is much smaller due to the insulation provided by
the concrete and soil. Below excavation level the gauges at the front and back of the pile
are equally affected by temperature. Gauges 13&14 are affected slightly, gauges 11 & 12
117
even less so, and below this there is no relationship between strain and temperature. From
this, ambient changes in temperature can be assumed to only affect gauges within 2·5 m of
the excavation or ground level (excavation level minus the level of gauges 11 & 12).
4-4-5 Comparison between pile bending moments calculated/rom strain gauges and
inclinometer
Figures 4-29 and Figure 4-30 show bending moments calculated from the strain gauge and
inclinometer measurements at four instances; before and after Excavation Phase 2 (when
cracking occurred in Pile X: Figure 4-29) and before and after Temporary Prop Removal
(when cracking occurred in Pile Y: Figure 4-30). Data at points where cracking has been
shown to have occurred (in Figure 4-24 and Figure 4-2S) are highlighted on Figures 4-
29(b) and 4-30(b). Bending moments calculated from the Sth and 6th order polynomial
curve fits to the inclinometer data are shown. The upper and lower bounds for the cracking
moments, Mer (calculated in Section 4-3-3) are indicated on the figures. E1 values are all
based on uncracked concrete properties.
In Figure 4-29(a) and (b) there is close agreement between the bending moment data
derived from the wall profile and the strain gauges. In Figure 4-29(a) the measured
bending moments are all smaller than Men and there is little difference between the
bending moments calculated from the Sth and 6th order fits to the inclinometer data.
Figures 4-29(b) and 4-30(a) show that at some strain gauge locations the calculated
bending moments have exceeded Mer. The two highest of these are those where cracking
has been observed. At the other locations the section may be cracked but not specifically
at the strain gauge (the strain gauges are 140 mm long and at l'S m intervals). In general
there is close agreement between bending moments calculated from inclinometer readings
and strain gauge measurements for the middle section of the pile. However, at the pile toe
and the pile head the curves bear away from the strain gauge measurements. This is
obviously a mathematical problem with the curve fitting process, and is caused by
attempting to fit a polynomial curve to a wall profile which contains straight sections (the
bottom of the wall is straight below approximately 27·S m AOD - this was observed by
noting that the gradient of the pile is constant below 31· S m AOD, and that the strain
gauges measure zero bending moments below about 27·0 m AOD). Further analysis has
shown that polynomials fitted only to the curved parts of the pile (i.e. leaving out the
lowest few metres) produce very similar bending moment profiles but with the top and
118
bottom parts absent. It follows that the bending moments calculated for known straight
sections of the pile can simply be ignored.
Figure 4-30(b) shows the bending moment profiles found after Base Slab Construction and
Temporary Prop Removal. Again, at the pile toe and top the inclinometer derived bending
moments bear away from the strain gauge measurements. In Figure 4-30(b), unlike Figure
4-30(a), the inclinometer derived bending moments are larger than those measured using
the strain gauges around the position of the maximum bending moment.
4-5 Measured changes due to construction events
4-5-1 Temporary props
Figure 4-31 shows the individual temporary prop loads. It can be seen that approximately
800 kN ofload was recorded in temporary props T1 and T3 as a result of Excavation
Phase 2, and 1000 kN in T2. When the base slab in bay A3 (see Figure 3-42) was
constructed the load in the nearest temporary prop to it, T1, reduced by approximately
200 kN over the following 3 days. This is because the base slab concrete applied a lateral
load on the wall as a result of the weight of the wet concrete and the initial expansion of
the concrete due to curing. The combined load and expansion of the slab forced the wall
back into the soil for a short period, inducing a temporary decrease in the temporary prop
loads (in the piles a reduction in bending moment is measured in the gauges around the
level of the base slab when the base slab concrete is poured against them, see Section 4-5-
4). After the initial expansion of wet concrete it contracts while cooling and setting, and
therefore the load in the temporary props recovered to close to the original value over the
following 5 days, until the next base slab, at the instrumented section, was poured. This
caused the load in prop T1 to reduce by nearly 100 kN over the following 2 days, until it
was removed.
Temporary props T2 and T3 exhibited no change in load due to the installation of base
slab A3. Following construction of base slab A4, the base slab in the instrumented section
(i.e. directly below props T2 and T3), a reduction of approximately 200 kN was recorded
in both T2 and T3 over the following 2 days. Then only 2 days after casting slab A4, prop
T1 was removed and the load in prop T2 rose rapidly by approximately 200 kN. The load
in prop T2 continued to rise by approximately another 200 kN over the following 14 days,
119
until it was removed. There was no change in load in prop T2 when the next base slab, A5,
was constructed.
After base slab A4 was poured the load in prop T3 increased slowly over the following 9
days, by a total of approximately 80 kN, until the next base slab, A5, was installed. At this
point the load reduced by approximately 40 kN. The load in prop T3 was then reasonably
steady over the following 5 days until it was removed along with prop T2.
It is important to note that the changes in loads and bending moments due to the removal
of prop T1 are masked by the loads applied by the expansion and contraction of the base
slab concrete poured only 2 days earlier. Therefore the removal of props T2 and T3 might
be expected to have different consequences.
4-5-2 Base slab data
Although the temperatures indicated by the base slab gauges during the concrete pour
were very similar, Figures 4-11 and 4-13 shows that the strain rates were different. The
strain in set 1 rose much more quickly than the strains in set 4, and the strains in sets 2 and
3 rose at a very similar rate. Despite their different rates of strain during the concrete pour
and curing, sets 1-3 indicated a similar 'load' by Day 586 and set 4 by Day 596. The
difference in strain may be affected by the different frictional qualities of the boundaries to
the base slab: the previous concrete slab acts as a boundary near set 1 and there is
shuttering near set 4.
4-5-3 Reinforced concrete props
The changes in the reinforced concrete prop loads that occurred as a result of excavation
directly under the individual instrumented props are listed in Table 4-8 (also see Figure 4-
21). The loads measured at various construction stages are presented in Table 4-9.
120
Change due to excavation under:
PI P2 P4
PI 550 200 0
P2 400 500 0
P4 150 150 150
Table 4-8: Changes in RC prop load due to excavation directly under individual props
Load after excavation
Load after Load after construction was Temporary completed
Prop I year 2 years 3 years Removal
PI 1600 2700 3800 4500 5200
P2 1800 3100 4200 4900 6600
P4 900 1900 2700 3300 3900
Table 4-9: Load at specific stages of construction
4-5-4 Pile bending moments measured with strain gauges
Figures 4-32 and 4-33 show bending moments measured in Pile Y against time for the
gauges below and above the base slab respectively. For clarity only the data taken at 0900
each day is plotted to remove the fluctuations due to daily temperature changes. Figures
4-34 and 4-35 show similar data for Pile X.
Table 4-10 shows the different changes in bending moment that were experienced by
different parts of the pile as a result of specific construction activities. The information in
the table is representative of both piles, as they behaved similarly (although the
magnitudes of some of the changes differ).
Analysis ofthe data shows that the largest changes in bending moments occurred during
Excavation Phase 2, at the level of the base slab. This corresponds with the largest
changes in deflection and curvature shown in Table 4-6. Reductions in bending moment
were recorded during this construction event in the gauges near the top of the wall; this is
because rotation occurs around the temporary prop, the point of maximum bending moves
down the wall and therefore the top of the wall is under less stress (this rotation can be
seen in Figure 4-6 (a) and (b)). Before Excavation Phase 2, the maximum bending moment
was approximately at excavated ground level, i.e. about the location of the temporary prop
121
(gauges 21 &22). After Excavation Phase 2, the point of maximum bending moment was
approximately at formation (gauges 15& 16). The reduction in bending moments at the top
of the wall could also be partly due to redistribution of stresses in the wall resulting from
the cracking induced at this stage of construction.
The expansion and contraction of the base slab during its construction and the effect this
had on the wall induced a temporary decrease in the bending moments close to the level of
the base slab. The gauges near the top of the wall were not affected, probably because of
the presence of the temporary props, which restricted movement of the wall and therefore
load redistribution above its position.
As the heat generated in the base slab during the curing process dissipated the concrete
contracted, therefore the load being applied to the wall reduced and the bending moments
near the level of the base slab increased, as shown in Figures 4-32, 4-33, 4-34 and 4-35.
However, temporary prop T1 was removed only 2 days after the base slab was cast, and
therefore the change in bending moment is a combination of the loads occurring due to the
concrete setting and temporary prop removal. On removal of props T2 and T3, the bending
moment near the level of the base slab decreased. Therefore it is reasonable to assume that
the removal oftemporary prop T1 would also initiate a decrease in bending moment near
the level of the base slab, and if prop T1 had not been removed so soon following Base
Slab Construction the increase in bending moment in the following days may have been
substantially higher.
Temporary prop removal resulted in an increase in the bending moments in the top of the
wall and a decrease in those near the level of the base slab. The inclinometer
measurements in Figure 4-6 (d) show that the point of maximum deflection moved up the
wall after temporary prop removal (the last temporary props, T2 and T3, were removed on
Day 595).
122
....... tv w
Stage Top section of wall Middle section of wall Bottom of wall Max change Notes:
Exc. Phase 1 11&12-25&26: not applicable 1 &2-9& 10: decrease Increase at 21 &22 Approx. the same change increase recorded in 15& 16-19&20 and
23&24 due to second part of Exc. Phase 1.
Exc. Phase 2 21&22-25&26: 5&6-19&20: increase 1&2-3&4: no significant Increase at 15 & 16 Trend of changes generally decrease change continues for about 2 days after
Exc. Phase 2 has finished.
Base Slab 21&22-25&26: no 11&12-19&20: 1&2-9&10: small Decrease at 15&16 Construction significant change reduction increase/no significant
change
Removal of 23&24-25&26: small 13&14-21&22: slow 1&2-11&12: slow Increase at 15& 16 Tl increases over period increase over period of decrease over about 10
of 10 days/no about 10 days days. No significant significant change change in 1&2 and 3&4
Removal of 19&20-25&26: 17&18: no change; 1&2-7&8: no significant Increase at 21 &22 T2 and T3 increase (no change in 15&16-9&10: change
25&26 pile X) decrease -- -- --- - -- -
Table 4-10: Changes in bending moment for piles X and Y due to particular construction stages. Ranges are inclusive of gauge numbers quoted
4-5-5 Inclinometer data
The inclinometer readings illustrated in Figure 4-6 show that the wall moved consistently
into the excavation as construction progressed and that the majority of the movement
occurred during excavation phases 1 and 2. Further movement occurred at temporary prop
removal. The readings indicate that after temporary prop removal the wall continued to
move, with the top of the wall moving into the excavation by 4 mm over the following 1 1
months. However, Figure 4-7 shows that the movement was not in one direction and that
few readings were taken over a relatively long period of time, so the accuracy of these
measurements is questionable. It is possible that the wall movements may be affected by
yearly temperature changes, however the paucity of the readings prevents a definitive
conclusion.
As previously mentioned, the relatively high deflections measured at the top of the wall
lead to the conclusion that the cutting has swayed due to the difference in ground level
behind the north and south walls (see Figure 3-22). (N.B: A compression of 1 mm in the
RC prop would produce 25 000 kN of load; therefore the movement could not be due to
compressive loading.) Unfortunately it was not possible to monitor the south wall due to
access restrictions and very little is known about the progress of the construction 0 f the
'Maidstone loop', the line which was constructed behind the south wall, and the
corresponding changes in ground level. However from photographic evidence (Figure 3-
34 - taken 110 days before excavation activities began) the existing railway lines can be
seen and preparations for construction are being made, therefore the ground level must
have been reduced by this time.
In the early part of Excavation Phase 1 (Days 483-488: before work temporarily stopped)
the wall appears to be well propped at the top with excavation causing the wall to bend in
the middle. Figures 4-32, 4-33, 4-34 and 4-35 show that the bending moments induced at
this time were small. Later during Excavation Phase 1, the changes in deflection measured
at all points in the section of wall above temporary prop level were similar, indicating that
the wall was rotating and that the RC prop was not providing significant restraint. Figures
4-33 and 4-35 show that bending moments did not increase in either pile until the end of
Excavation Phase 1. The top of the wall moved approximately 7 mm during Excavation
Phase 1 and a further 3 mm before the start of Excavation Phase 2.
124
Between Days 530 and 533, at the beginning of Excavation Phase 2, the top ofthe wall
moved very little while lower down the wall the measured change in deflection was
approximately 5 mm. Days 534/535 were a weekend, after which excavation appears to
have produced similar changes in deflection in the top section of the wall, indicating little
restraint in the prop. The readings taken during Temporary Prop Removal also show the
whole top section of the wall moving.
4-6 Conclusions
At the CTRL site at Ashford, UK, wall deflection profiles have been found from
inclinometer measurements, inclinometer measurements and strain gauges have been used
to derive bending moments in a propped contiguous bored pile retaining wall, and strains
gauge measurements have also been used to measure temporary and reinforced concrete
prop loads. The following points can be made:
1. Use of vibrating-wire instruments and a datalogging system capable of taking
readings at up to 5 minute intervals has allowed (effectively) continuous data to be
collected on site at Ashford.
2. The implementation of rigorous procedures during data collection, thorough
analysis and error checking has produced good wall displacement profiles from the
inclinometer data.
3. It was not possible to infer load measurements from strain data collected in the
base slab, because the strains caused by changes in load could not be distinguished
from the strains caused by thermal effects arising from the concrete curing process.
4. The temporary prop data proved to be more straight-forward to analyse and was
corrected for temperature effects so that the average prop loads occurring due to
construction events could be determined.
5. Analysis of concrete shrinkage occurring in reinforced concrete props constructed
elsewhere at the Channel Tunnel Rail Link site has allowed prop loads at the
instrumented section to be estimated, despite the fact that excavation under the
props occurred very soon after the concrete pour while considerable shrinkage was
occurrmg.
125
6. Careful consideration ofthe mathematical restraints to curve fitting have allowed
wall bending moment profiles to be determined from inclinometer readings, and
these show good agreement with bending moment profiles found from vibrating
wire strain gauges. Identification of concreting cracking and an analysis of the
effect this has had on the bending moment profiles calculated from the
inclinometer measurements has explained the differences in bending moment plots
found by the two different methods after cracking had occurred.
126
E E C) c
= ::s CJ 0 ... . 5 ... c (1)
E (1)
> 0 E (1)
.s cu 3:
E E Cl c
= ::s CJ 0 ... c ... c (1)
E (1)
> 0 E (1)
.s cu 3:
2
Toe deflection = 0.0149 x Time in days - 7.0649
1.5 :-- Previous base slab construction (A3) .. -- Base slab construction (A4) j-- Next base slab construction (A5)
1
0.5
0 -.::t N 0 0 00 co -.::t N 0 00 co -.::t N ...... -.::t I'-- ...... (\') co 0) N LO I'-- 0 (\') co LO LO LO I'-- I'-- I'-- I'-- 00 00 00 0) 0) m
-0.5 Time in days
-1
(a)
2 y = 0.0149x - 7.0649
Exc. Ph. 1A Exc. Ph. 1B 1.5 ~:
::5-;
1
0.5
0 0) co (\') 0 I'-- -.::t ...... 00 LO N 0) co (\') 0 0 ...... N (\') (\') -.::t LO LO co I'-- I'-- 00 0) 0 LO LO LO LO LO LO LO LO LO LO LO LO LO co
-0.5 Time in days
-1
(b)
Figure 4-3: Movement of wall toe with time measured by the inclinometer (a) construction period and the following year (b) construction period only
128
N -0
c o « E CI)
> CI)
...J
-1
Readings taken on days 488,489,491
45
40
35
30
1
o
Readings taken on days 496,497,498,
501,502,503
1 2 3 Deflection, mm
(a)
4
c o « E
~ CI)
...J
-1
Readings taken on days
488,489,491
45
40
35
30
25
20
15
o
Readings taken on days 496,497,498,
501,502,503
Wall toe
1 2 3 Deflection, mm
(b)
4
c o « E
~ CI) ...J
-1
Readings taken on days
488,489,491
45 T r.
40
35
30
25
20
15
Readings taken on days 496,497,498,
501,502,503
~
Wall toe
o 1 2 3 Deflection, mm
(c)
Figure 4-4: Correction of inclinometer data: (a) As read, (b) adjusted for zero movement at the toe and (c) adjusted for movement at toe indicated by equation given in Figure 4-3
4
,..... w o
45
40
35 +
c 0 30 « E CI)
> 25 CI) ..J
20
15
-5 o
586
"M\~617 .
Exc. Phase "1" "Ievei
Exc. Phase "2 "Ievei 718
Wall toe
5 10 15 20 25 30 Deflection, mm
c 0 « E
CD > CI)
..J
28
26
634~~592
617
-5
2
2 JU !~ 585
14
o 5 Deflection, mm
(a) (b)
Wall toe
10 15
Figure 4-5: (a) Measured deflected profile of the wall and the bottom 10 m of tubing installed in the underlying soil. (b) Excerpt of (a) showing deflection ofthe bottom 10 m of inclinometer tubing
Days 496, Days 501, 497,498 502,503 Days 516,
45 / ~519,522 Days
488'40 489,
W-~~~--Day504
491
g 35 « E Q)
~ 30 ..J
25
,~-!H---Day 508
Days 510, ~511,512
Day 523
Wall toe
-5 0 5 10 15 20 25 30 Deflection, mm
45
40
(a)
Days 545,550,552, 558,560,564,566
~
Phase 1 o excavatiori"ievel o 35 Phase 2 « E excavation'Ievel
~ ..J 30
25 Wall toe
Days 580,581
-5 0 5 10 15 20 25 30 Deflection, mm
(c)
Days 524,525, 526,529,530
45 I Days 536,
/537,538, " 539,540
40
g 35 « E Q)
~ 30 ..J
25
Days 532 533
Wall toe
Phase 1 "exe, level
Phase 2 '''exe, level
-5 0 5 10 15 20 25 30
45
40
Deflection, mm
(b)
Days 718,719,747, 777, 862, 945
Days 585 -
Days 592--
Phase 1 excavatiori"ievel
00 35 « Phase 2 E excavation 'level
~ ..J 30
25 Wall toe
-5 0 5 10 15 20 25 30 Deflection, mm
(d)
Figure 4-6: Error adjusted inclinometer measurements taken during construction (2001): (a) around Excavation Phase 1 (Days 483-488), (b) around Excavation Phase
2 (Days 530-537), (c) around Base Slab Construction (Day 579) and (d) after Base Slab Construction
131
E E
25
C) c E 20 ~ (.)
.s c
E E C) C
E ~ (.)
0 .... c
(ij ~ -0 e. 0 .... -0 .... c CI)
E CI)
> 0
::E
0
25
20
15
10
5
0
-5
1.() ('f) ...... ...... oq- I'-oq- oq- oq-
0) I'-0) N oq- 1.()
t ro -00
...... ~ 0... ci x W
c: o • t5 ~ ..... -00 c: o ()
.0 JQ 00 ,: (1) " 00 :: ro " co ::
1.() ('f) 1.() ex) 1.() 1.()
a. 0 -00
...... ; .'
.!:: 0...: ci: x' w;
Removal of temporary prop T1
Removal of temporary props T2 and T3
...... 0) I'- 1.() ('f) ...... 0) I'- 1.() ('f) ...... 0) I'- 1.() ...... ('f) <0 0) N 1.() I'- 0 ('f) <0 0) ...... oq- I'-<0 <0 <0 <0 I'- I'- I'- ex) ex) ex) ex) 0) 0) 0)
Time in days
(a)
t ro t - "0 "0 00 ro ~
c: - c: "0 (1) 00 (1) (1)
N; N > ...... ...... 0
~ .' ~ E .!: .!: : "0:
0... 0... 0...: 0... (1): (1) ..... ..... ,
ci ci ci: ~, ...... x x x' 0: I-w w w; a.: a.
.0: 0 ro: ..... w; a. (1)' a. 00: E ro: (1)
co: l-
<0 oq- N 0 0 ('f) <0 0) 1.() 1.() 1.() 1.()
Time in days
(b)
Figure 4-7: Movement of the top of the wall (a) all measurements (b) excerpt of (a) showing construction phases only
132
2500
2000
z 1500 JII:
" CIS o
...J 1000
500
y = 44.439x + 1522.5
O+--r--.-~-'--+--r--.-~-'--+--r--.-~-'--+--r--.-~-'~
o 5 10 Temperature, °c
15 20
Figure 4-8: Typical relationship between load and temperature for temporary prop data taken over the 30 days between Excavation Phases 1 and 2, when no
construction activities were taking place.
133
....... w +:>.
2400
2200
2000
1800
1600
1400 +
i 1200 I .3 1000
800
600 ~
400
200
0 5
-200
t: co. en: ('\I: Q). en· co·
.£: • a...: 0: X· w:
T1
Temperature
-0; c· Q):
('\I.
Q): en. co·
.£:. a...:
535 542 549 556 563
Time in days
.0: co· Cii: Q)' en' co '-0 .0 :~ en':J :J'O
.Q :0. >'''-''' Q) '('1') ...... « a... :.......-
570
Figure 4-9: As measured temporary prop loads
40
30
20
10
0
-10 0 0
-20 ~ :::s -ca ~
-30 C1l Q.
E C1l
-40 ~
-50 .0'
'<to co: «: :-0 Cii'"O
T3 + -60 .0:
.Q) Q) : ~
. > en':J co . . 0 CO ' o Cii '"0 • E .0:0. + -70 Q) : ~ : Q) xfo en ' :J . ..... co ' 0 . T""" Q).« ca :o.:1- z.....-
I I I I I I I I I I I ~~8-80 577 584 591
-90
....... w VI
2400
2200
2000
1800
1600
1400
~ 1200 '0 co .3 1000
800
600
400
200
0 5
-200
t'
~ ~ N ' w: en, cu'
..c ' 0; 0 : x , w '
Temperature
-0 ' c ' w: N: w' en' cu '
..c ' 0.:
~T3 535 542 549 556 563
Time in days
.0 cu 00 : w ' en' cu ' -0 .0 : ~ en ' ::l ::l : 0 0 , Q. .;;' ''--'' w ,(V) L- ' « a.. : __
570
~: ' -0 « : 'w .0 ,-0 ' > cu , w : o oo:~:E w,o,w en ' Q. ' Lcu ' , T-
en : :1-
577
.0 cu 00 '
'-0 ~ : ~ cu ' ::l .0 ' 0
T2 x:;::
\
W ,L()
z ::5.
584 591
Figure 4-10: Temporary prop loads corrected for temperature effects
40
30
20
10
0
-1 0 (J 0
Q) -20 5 -co ... -30 ~
E w
-40 I-
-50
-60
-70
-80
5~8 -90
10000
8000
N 6000 .§ z ~
€4000 ::::I en en e
D.. 2000
2003
Probable time b9"ast
Set4 was laid on the s ab
O+-~.-.-~r-~~-.-+~-+-.-r-r-r,-.-.-+-.-.-r-~,,-.-+~
5 0 652 764 876 988 1100 1212 13
-2000 Time in days
(a)
10000 Base slab (A4) concrete poured
50
40
30
20 u
0
10 eli ... ::::I
0 ... C1l ... Q) c..
-10 E Q) I-
-20
-30
-40
-50
50
40
8000 : Next base slab (AS) concrete poured 30 ~
N 6000 E Z ~
€ 4000 ::::I en e
D.. 2000
I
Set 1 Pressures
o +-~~~AH~'-TO~-r,-r.-r.-ro-r~~-''-TO-+-r'-rT-r~ 5 4 588 595 602
-2000 Time in days
(b)
20 u
o 10 Q) ...
::::I
o 1U ... Q) c..
-10 E Q)
I-
-20
-30
-40
-50
Figure 4-11: (a) First 2 years of base slab readings. (b) Excerpt from (a), showing period including concrete pour
136
z ~
6000
5000
4000
3000
-g- 2000 increasing o ..J
1000 )()(xx
O+o-.~-r~~,,~~~-.~nrtw~x"~~-.~~r.'-rT~~~~~~~
-1000 x xJ5xrif20
concrete pour . \ dUring pour
25 30 35 40 45
-2000 Temperature, °c
Figure 4-12: Temperature versus load for a typical base slab gauge from before concreting to after stabilization of concrete temperature
137
138
0.0003
0.00025
0.0002
0.00015
c 'cu 0.0001 ... ... en
0.00005
0
-0.00005
-0.0001
0.0003
0.00025
0.0002
0.00015
c 'cu 0.0001 ... ... en
0.00005
0
-0.00005
-0.0001
N CD CD
N CD CD
"" t--t--
CD ex:> ex:>
(c)
CD ex:> ex:>
(d)
ex:> 0') 0')
Time in days
ex:> 0') 0')
Time in days
a ..--..--..--
-gauge 3A I
-gauge 3B I
N N N ..--
-gauge4A
-gauge4B
N N N ..--
Figure 4-13: Strains measured in the base slab gauges: (a) set 1, (b) set 2, (c) set 3 and (d) set 4
"" ('i') ('i') ..--
139
0.0003
0.0002
c: 'cu 0.0001 ... -en
-0.0001
0.0003
0.0002
(j)
c: 'cu 0.0001 ... -en
0.0000
-O.OOO j
Excavation Excavation phase 1 phase 2 1/\ CI I I 14+1 _ 0 I 1++1
I :';:;1 I I CUI I I =1 I
21 I ~I I
.-1 I oJ I 0 1 I
~ : · 1 I
112 I I I Q) I
:: 1-:-1
I
o N LO
CD I'LO
.;;t o CD
west east c.. blue e c.. black W purple
red
The zero reading is the average over 24 hours 2 weeks after concrete pour and the day before excavation
N ("I)
CD
o CD CD
co co CD
Time in days
Figure 4-14: Strains measured in PI
c.. blue west east Excavation Excavation C 0
0 ..... black M purple phase 1 C phase 2
:.;:; c.. u >-
1 /~llg ::::J ..... red l::; I I cu_ I~ 1++11 CUI 00 II ..... cu I I 1=1 C II 8.> I I 21 011 0 I I 001 U II l EE I I CI .a II----C: ~ Q) I I .~ CUll I ..... I I Cii II I
I el Q) II I I Cl.J 00 II I I ~ CU ll I I (!) I I ~I I I 0 1 I I Cl.J I EI I Q)I I f-I I I I The zero reading is the average over 24 I I I hours 2 weeks after concrete pour and I I I
I I the day before excavation I I
N 0 co CD .;;t N 0 co CD .;;t Q) N .;;t I'- 0 ("I) CD co ..- .;;t .;;t LO LO LO CD CD CD CD I'- I'-
Time in days
Figure 4-15: Strains measured in P4
140
CI.)
t:
0.0003
0.0002
'iii 0.0001 .... -en
-0.0001
0.0003
0.0002
t: 'iii 0.0001 .... -en
-0.0001
Excavation § phase 1 § I ;/" i\. II rol 1401 1_ I enl
I I I Cl I 11'-1 I II Oi I II el I I I o!
: :: b I I I COl I 1101
: :: ~ I II ~I : :: 1-1 I I I I I I I
o N L()
c Excavation 0
phase 1 g I ;/" i\. 11's1 1-..1 I_I (/)1 I I I .!: I
I % : el I Q..j
: ~ I ~I I 01 I Q..j I EI I Q) I I I I I I I I
o N L()
Excavation phase 2
I I I+-+f I I I I I I I I I I I I I I I
00 '>t L()
Excavation phase 2
I I 1+01 I I I I I I I I I I I I I I I I I I I I
a. blue west east c e o a. t5 ~ 21 1 ~ _
en l l 0 co C II a. > 01 1 I E °E () I I I .0 II-----C: ~ Q) co I I I ....
black W purple
red
Cii II I Q) I I I (/) I: :
The zero reading is the average over 24 hours 2 weeks after concrete pour and the day before excavation
'>t o CD
Time in days
(a) Gauge set A
ro ~~
II ~ E II 8. ~
.0 II I E a. ~:: :~ Q) e Q) II-r- I- a. (/) II I co I I I
OJ I I
N ('i) CD
o CD CD
00 00 CD
blue west east . black W purple
re ~ ~
The zero reading is the average over 24 hours 2 weeks after concrete pour and the day before excavation
'>t o CD
Time in days
N ('i) CD
o CD CD
00 00 CD
(b) Gauge set B
141
0.0003
0.0002
c 'IV 0.0001 ... -en
-0.0001
Excavation § Excavation phase 1 ~ phase 2
c o blue west east
1 ;/ \. I I I.. 1+01 1+->1
I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I I
o N lC)
:g ro 2 ~~ en
ll ~ E
§ I I 8. ~ 011 E Q. .0 II I Q) e ~ ::~f- Q. C/) II I
black E3 purple' ,
red ~
Q) II I ~ II
zero reading is the average over 24 hours 2 weeks after concrete pour and the day before excavation
<0 I'lC)
~ o <0
Time in days
(c) Gauge set C
N ('f)
<0
o <0 <0
00 00 <0
Figure 4-16: Strains measured in P2
142
400000
350000
300000 II) '0 I:
8 250000 Q) II)
.~ 200000 cu ... -~ 150000 E i=
100000
50000
0
0
y = 4624.83x + 19539.09 R2 = 0.99
Excavation began underneath props
7 14 21 28 35 42 49 56 63 70 77 84
Time in days (concrete pour on day 1)
Figure 4-17: Time/strain versus time for an RC prop gauge at chain age 89+205
400
350
300
II)
:::I. 250 I: cu ... 200 -II) 0 ... .~ 150 :!i
100
50
0
0
Excavation began underneath props
'. -' .. ' - ' .-'
Measured strain
.... -... .. .. -- --- _ ... . -I" -' _ . . • 0. ···· _.-I Strain predicted by : Equation 4-12 I I I Temperature
i \
7 14 21 28 35 42 49 56 63 70 77 84
Time in days (concrete pour on day 1)
150
130
110
u 90 0
Q) ... :::I
70 -cu ... Q) Q.
50 E Q) I-
30
10
Figure 4-18: Measured and calculated strain against time for an RC prop gauge at chain age 89+205
143
5000
4500
4000
3500
3000
-z 2500 ~ -"0 nJ .3 2000
1500
1000
500
0
-500
..........
.j:>.
.j:>.
Direction of construction ~Piles
ooooooo®®-oowoouoooo Props ~ ~ fj ~ " .,~ T \ ,' ,' " " " 'I~ P# - RC prop .;·i :;: . ;.;:;.;.:'.;.; . . : T# - Temp. prop ~ Z Inclinometer Temperature . ,:-: :.:".:. . :.;~?: "
X & Y Instrumented piles ,. "" " '. ; .. ': •. , ;.' . '---_ ________ -:---:--__ ----,-__ -----:-__ -,--'--_-\ .,. . ~ I I, ' ,, . , It ., ..
. ," I, I, '. II,," " ,, ',", I
I I I ,'r'· I . : I "
"~ .,, »1 I 'E I I ~ I I 8,1 I E
ClJI 2 tl 191
CIJ a. o ClJ
I ~I ClJI ~I 0..1 01 XI WI
I I I I I I I I I
..... CIJ
..... Q) CIJ co ..c 0..
I 1 I I ,... ........... .' . ' ,.; . ',' , . .••. 'I I I I :·· .... 1:··,·.:· ... I :'. I . ';',' ', :.,' ; " ':,:': '; ':'. ,.; ,' .,.; . ... I I
...... 1'" I I ' I ': '. I " "'1:' .... ' :'~' I I ... ," "{j; '1'," 1' , "0 I ':,, : I I I
-g' 1 "," ":' ~ I I I P2 AnJ1 ~ n l Q) I I 19 I I I
..... 1 I ~ I I I Q) I 1"0 .- I I I CIJ Q) ('i)
...... col l=ro f-I I Q)1..c1 I ..... ~I
~I ~I I .~ NI ..cl ~I I ..... f-0.. I W I I
~ co ..... CIJ
1
~
I
"0 Q) ..... CIJ' P4 u "01 ::J "0 a3 1
... Q) ..... CIJ >
N I c 0 0 "0 E Q)I u Q) Q)
ClJI .0 > ... ~ I co 0 ('i)
0..1 Ui E f-Q) Q)
~ CIJ
... co ..... N III f- f-
Il d llll ldllllld
l "\l U} I.U lTJ U r-- '<t ..... co ..... '<t '<t LO CD ,...... ,...... co CJ) CJ) LO LO LO LO LO LO LO LO LO LO
Time in days
Figure 4-19: Reinforced concrete prop loads uncorrected for effects of shrinkage
LO 0 CD
N ..... CD
30
25
20
15
10
5
o -5
5000
4500
4000
3500
3000
-z 2500 .lie: -'0 C'tI
.3 2000
1500
1000
500
0
-500
..... +:>. Vl
Direction of construction ~Piles
ooooooo~®ooooaoooooo
~o~~c prop ~ ~ rj ~ . ' . ,"' " ,,. • "" 1 • • ,' "
," II It, • I I:'~ .::', " .,,-. \',
T# - Temp. prop , Temperature Z Inclinometer I '
,It I " " " ". ,' 11 , I. -,, " " "", I
j I X & Y Instrumented piles I:',;, "'. ;'. '. :.;';': +J-+---+-------+---+--+-----+�---I�~-->'I '----I. I I " .. " • " I,. " " ~ " , I I ·1· I I .. .. ." .'~ •. .. ~. " ,' .' ' . • - ' ... ··1
.. .. .. , " I I ~ , \ I " I " '. II I' l ' II '" ' , ' . " .. .. ' _- r . I I I .... r.· .. ·· I ". I . . .. ' . .' , '. .- •.• • :.: I I , : I " . , " ' " ' ' . ,~ ' -. I I ' I ': '·. 1 ",( ., ,: ', :.. I
'l" I ,,' I ····· '1 ·:·\. . I .'1': I I ' - ' '' '.'. 00
I >,1 I 00 I I .. '0 I 001 '01 I I 'E I 00 I '0 I I ~ I 151 CI I I ~ I 15 I a5 I I J§ I til ~I I I ~I ti I ...... I I 00 I NI Q)I I I E I cD I Q) I I '0 .S: I Q) I 00 I I
el Q) I L.. I 00 I I ~ f'" I ~I ~I P2 I 21:;1 ...... I ~ I 00 I 0..1 Q) I 0.. I
...... 0 00 . <
Q)I ti I ~ I ~ I 1'- L...: I 01 XI Kl' ...... 1 0.. I 11,1 £1 Q)I u 0..1 00 I X
ul ~I W X I 0..1 WI ul
I X I I WI I I I I
I I I I
'0 I I .0211
I P4 .£Qg lI '0 00 L.. I I Q) I
I I
N ~ L{)
0> ~ L{)
to L{) L{)
Time in days
C") to L{)
Q)- > OO~II 0
~8 11 ...... ~ ,I,I.Ir,I, 'l,
0 I'- ~ I'- I'- co L{) L{) L{)
",/ , .' ,: ",'. ·"t· ".
...... co 0> 0> L{) L{)
-/ \ ,,',. ",0" " , '.:': '
L{) 0 to
Figure 4-20: Reinforced concrete prop loads corrected for effects of shrinkage using Equation 4-12
N ...... to
30
25
20
15
10
5
o -5
(,) -10 0
~ -15 .a
~ -20 Qj
Q.
E -25 Qj
I-
-30
-35
-40
-45
-50
-55
-60
-65
......... +:-0\
5000
4500
4000
3500
3000
~ 2500 -'0 III
.3 2000
1500
1000
500
(/)
t .s (/)
..-
>~
..-~ ..-o ..-
0)0. ~ 0) "0
KJE cu(/) KJ ~ .c2 .c t .c .s
0) a... (/) a... .s a... (/) (/) • 0. U (/) . ' (/) 'c ro 0 0 x' , 0,-0 I ._ " , .. .c X - wi 0) x C 1"- . a... W(/)I L.. WI 0) I-
.'1 I " ". I I U , r . , , '., • , r ' . , 'I . xI
" 'j""'" ," _,' ' r" " "" " wI I ' I I . " "I' " , , . " ", ' I I I I 111
' Temperature: I I ~ Exc. directly under P1
Exc. directly under P2
° r'~ . 4: .. 4
_5004 9 >" , . , 486 493 500 507 514
Time in days
"0 0)
m -(/) .~ C'? I-~ N l-
'. ·L,:. " ,
521
,.. ... ~
I ,I . . . , ,
• J • ~, :- .:~ ~ I L.::J en l NI 0)1
KJI .c l 0...1 UI ~ I
I I ~ , ' , ,
-'I:" " ,: (/)1 "gl 0)1
NI 0)1
KJI .cl 0... 1 UI x Wi
! I
:l
30
25
20
15
10
5
o -5
o -10 0
~ -15 .a
~ -20 Q)
Co E -25 Q) I-
-30
-35
-40
-45
-50
-55
528 535 5t 2-60
-65
Figure 4-21: Close up of Figure 4-20 showing reinforced concrete prop loads up to just after Excavation Phase 2
26 -- &- - P1 calcu lated stiffness
24 -- 0 - - P2 calculated stiffness
22 cu --~ --P4 calcu lated stiffness
Q.. 20 :iE - 18 " c:: 0
UJ" 16 iii 14 tfj CI) c 12 :=
P4 P1
:0:; 10 tfj Best-fit lines CI)
8 > :0:; cu
6 Qj 0:::
4
2 2001 2002 2003 2004 2005
0 452 817 1182 1547 1912 2277
Time in days
Figure 4-22: Stiffness calculated by assuming that there is no change in prop load after construction is completed and the calculated best-fit lines to these data
4000
3500
3000
2500
z 2000 ..=.::
~ 1500 o
..J 1000
500
-2 -500
-1000
No-work stage with in Excavation Phase 1
~D"B 10
/
0 aD a o DO
12 14 16 18
Before Excavation Phase 1 T t 0c empera ure,
readings taken in month after construction was completed
20 22 24 26 28 30 32
Figure 4-23: Temperature versus load for a typical RC prop gauge during periods when no construction activities are occurring
147
0.0003
0.0002
0.0001 Period of Excavation Phase 2
1 1
: Removal of T1: 1 -I 1 1
: Removal of T2:T3 1 • I I' --r---l
1 1
Difference in strain between other pairs of gauges
1 1
.~ ~~~~~~ ... 0 II)
.5 4 5 443 471 499 5211 555 ~83 639 ~ 1 g-0.0001 Time in days : ~ ~ 0-0.0002
-0.0003
-0.0004
-0.0005
0.0003
0.0002
0.0001 c
(a)
1 1 1 1 1
: X15&X16
Difference in strain between other pairs of gauges
~ 0 r~~~~~~~_~~!liiii~~ .5 4 5 443 471 499 527 1 555 639 ~ 1 1 u-0.0001 Time in days 1 1
C : : ~ 1 1
~-0.0002 Period of : : is excavation phase : :
2 in front of w=-=a""'II-';' 1:---;1_4
-
1 1 1 1 -0.0003 : : Removal of T1 1
1 1 :;:::.-L 1 1 1 Removal of T2,II 3 1 1 1 -'-l-..-I
-0.0004 1 1
-0.0005
(b)
'\ Difference in strain between gauges Y21 & Y22
Figure 4-24: Difference in strain measured for the pairs of strain gauges in (a) pile X and (b) pile Y over the period of construction
148
0.0003
0.0002
0.0001
Odd numbered gauges: back of pile (retained side)
0+-~~~~~~~~~~-+~-.~-+~~-r~~.-.-41~-'~'-+-'-'-~ 4 5 443 471 : 555 583:
-0.0001
-0.0002
-0.0003
-0.0004
-0.0005
0.0003
0.0002
0.0001
Even numbered gauges: front of pile (excavated side)
1 1 1 1 1 1 1 1 1 1
Period of excavation : in front of wall -:
Odd numbered gauges: back of pile (retained side)
(a)
1 1 1 1
: Removal of T1: : 1 • 1 1 : Removal of T2,T3 : I I _I
1 1 1 1 1 1
1 1 1 1
1
611 639
Time in days
O~~--~~~~~~~~~+T~~~~~~~~~~~
4 5
-0.0001
-0.0002
-0.0003
-0.0004
-0.0005
443
Even numbered gauges: front of pile (excavated side)
1 1 1 1 1 1 1 1 1 1 1
Period of excavation ~ front of wall :
(b)
1 1 1 1
1 1 1 1 1 1
Y22
1 1 1 1
1 1 1
Removal of T1 : -I
Removal of T2, T3 1 I .1 - 1 1 1 1 1 1 1 1 1 1 1 1 1 1
611 639
Time in days
Figure 4-25: Strain measurements over period of construction for (a) gauges X1S, X16, Xl7 and Xl8 and (b) gauges Y21 and Y22
149
44
42
40
38
36
c 0 34 c( E (j)
32 > CI)
...J
30
28
26
24
-5 o
DAY:
Wall toe
ro > o E ~ c.. e a.. ~ ~ o c.. E ~ ..... Q)
~
Exc. Phase 1 ...... ievel
Exc. Phase 2 ...... Iewel
Cracking occurred over the periods in which these movements took place
5 10 15 20 25 30 35 40 Deflection, mm
Figure 4-26: Deflections measured in pile Z with the inclinometer around the time of Excavation Phase 2 and Temporary Prop Removal. Readings taken in 2001.
150
......... VI .........
.. Instrumented piles
'---- ...
Figure 4-27: Photos showing bulge in concrete between the levels of the temporary prop and base slab. The concrete above the bulge was poured within the casing and is therefore very smooth .
1&2 20 3&4 20
18 18
16 16
.P 14 .P 14
~- 12 i 12 .a .a
10 l! 10 l! '" '" 8 0. 8 0. E E 6 .. 6 '" l-
I-4 4
2 2
-0 .0002 -0.0001 0 0.0001 0.0002 -0.0002 -0.0001 0 0.0001 0.0002 Strain (s) Strain (6)
5&6 20 7&8 20
18 18
16 ...l6 .P 14 .P 14
i 12 i 12 .a .a l! 10 l! 10
'" '" 0. 0. 8 E 8 E
'" '" 6 I- 6 I-
4 4
2 2
-0.0002 -0.0001 0 0.0001 0.0002 -0.0002 -0.0001 0 0.0001 0.0002 Strain (s) Strain (6)
9&1 0 20 11&12 20
18 18
16 16
.P - .P 14 14 i 12 i 12 :::J .a E 10 E 10 '" .. 0. 8 0. 8 E E ..
6 .. 6 l- I-
4 4
2 2
-0.0002 -0.0001 0 0.0001 0.0002 -0 .0002 -0.0001 0 0.0001 0.0002 Strain (s) Strain (6)
13&14 20 15&16 20
18 18
16 16 u { 14 .P 14 0 , i i .a 12 .a 12
E 10 I! 10 .. .. 0. 8
0. 8 E E .. ..
I- 6 I- 6
4 4
2 2
-0.0002 -0.0001 0 0.0001 0.0002 -0 .0002 -0.0001 0 0.0001 0.0002 Strain (s) Strain (e)
17&18 20 19&20 20
18 18
16 16
.P 14 u 14 0
i
I 12 i
I 12 .a .a
E 10 E 10
'" .. 0. 8 0. 8 E E
'" 6 .. 6 l- I-
4 4
2 2
I I
-0 .0002 -0 .0001 0 0.0001 0.0002 -0.0002 -0.0001 0 0.0001 0.0002 Strain (s) Stra in (e)
152
21&22 20 23&24 20
18 18
16 16
14
I 12
10 '%-8
6 " - 2
10
-- 8
6
4 4
2 2
-0.0002 -0 .0001 0 0.0001 0.0002 -0 .0002 -0.0001 0 0.0001 0.0002 Strain (s) Strain (s)
25&26 20
18
16
14-
j
6
4
2
-0.0002 -0 .0001 0 0.0001 0.0002 Strain (s)
Figure 4-28: Strains measured in Pile Y over the 30 days after excavation and before Base Slab Construction
153
VI +:>-
Top 9fwfill _44T Strain gauge readings I I o Pile Y b. Pile X I I I I I I
25&26! 4of\ I I I I
23&24: I I
111 21&22i 38 + t
19&20: 36
-I
17&181
34 15&16:
I _I
13&14: 32 I I
11&12: ~ Bending moment
9&10 I 11' : calculated from 5th
: : and 6th order fits I
7&8 fl I
c I
0 I 101
5&6 « 0) I "-1 ..,tf'1- E I I I I
'<t I '<t I CI CI a; _I I
2l
.QI.QI
3&4 I I > .... I +-' I I I C1I ro I ro I
-I I ...J ::J I ::J I 1&2 I I 0"1 0"1
I I WI WI
:Wall toe °L.I "L.I 01 UI ~I ~I
-1000 -500 0 500 1000 1500 2000
Top Qfw4i1l 44 ... I I
'l"" I I ,I I 1"1-, , I I "',42 I I
-I I ""-25&26 '
23&24 40
21&22 38
19&20 36
17&18
-I 34 15&16
13&14 32
11&12
9&10
7&8
5&6 I /
I " /
3&~: I "" 1/ I ) -I
1&2 I -I I I I
'¥Val! toe
-1000 -500
,
0
Strain gauge readings I
: 0 Pile Y b. Pile X I I I I I I
~ : Bending moment :~ calculated from 6th
c o « E
~ C1I
...J
: order fit I I I I I I I I
14,!\\ :
0+ I I
+1
+:T ° +1
f tl1i ~
I I
I ~I
Cracking has , occurred
~
.. I I / I I Bending moment
/ I I )~ calculated from 5th
/ I I order fit I
.0 0)1"
I I I '<t.'<t
I °L.I "L.I
01 0, ~I ~I
500 1000 1500 2000 Bending moment, kNm Bending moment, kNm
Figure 4-29: Bending moments calculated from inclinometer and strain gauge measurements before and after Excavation Phase 2
(a) Before Excavation Phase 2: Day 530 (20/03/01) (b) After Excavation Phase 2: Day 540 (30/03/01)
Top qfwCflIl 44 1 Strain gauge readings 1 Top ofw9" 44 1
Strain gauge readings 1 , , 1 1 1 1 o Pile Y ;:,. Pile X 1 1 1 o Pile Y ;:,. Pile X "'f 1 1 1 .- ....... 1 1 1
, 1
~ 1-_ 1 1
'""I 1 -.... -- 1
1 "-t..., 42 1 1 1 1 -""4Z 1
D. I: Bending moment 1 1 1 Bending moment 'f., -I 1 1
25&26 ,
: 1 calculated from 6th 25&26 : 1 ~ 1 calculated from 5th 1 1 1
1 order fit 1 1 o "'J:/ order fit 40 1 _I 1
23&24 1 23&24 : 1 4 to, 1 , , I 'i<,1
21&22 38 + o \J -I
~ "" 21&22 ! 38 1 1 , : + Cracking has
I c 0 C IZ1 : occurred 19&20 1 0 19&20 o 1
1 36 « 36 « 1 1 E E o : ,"'T 1 D. D.
17&18 1 Qj 17&18 Qj
I, 1 1+ 1 > > If} 1 34 Q) D. 34 Q) D.
15&16 1 -I 15&16 -I 1 v.(. : 1 1 Q'" ...: 13&14 1 13&14 1 32 32 1 1 1 1 1 1 1
11&12 1 D.I
11&12 1
1 1 1 1
30 1 Bending moment 1 1 1 1 1 1 calculated from 5th 1
9&10 1 1 9&10 1 1 1 order fit 1 1 1 1 1 28 1 1
7&8- 1 1 7&8- 1 1 1 1 Bending moment 1 1 1 1 01 ~: calculated from 6th
5&6-: 1 CJ) ..- 1 5&6
CJ) 1 I , 1 I ...t! order fit 1 '>t '>t, '>t 1 1
3&4 1 1 .f. 3&4 1 1 I _I 1 /24 1&2-1&2 1 1
1 1 1
I W911toe • ~I "L.-I }/Vall toe 1 'f;: 'f;: 0) 01
:2: 1 :2: 1 I , ,:, ,: I , ,2~ I I , ~I: ,:2:, :
-1000 -500 0 500 1000 1500 2000 -1000 -500 0 500 1000 1500 2000 Bending moment, kNm Bending moment, kNm
- Figure 4-30: Bending moments calculated from inclinometer and strain gauge measurements before and after Temporary Prop Removal VI VI (a) Before Temporary Prop Removal: Day 551 (10/04/01) (b) After Temporary Prop Removal: Day 617 (15/06/01)
2400 40
2200 Temperature 30
2000 20
1800 10
1600 N' '<t ' , 0 I
~ ~:-o -0 1 () Q)I Q) I 1400 (/)1 .0 I Q) --. 1 -1 0° ~
rol -0 ro I> :J I Z 00 01 0 0 1 .J:: I C ~ ':'::~1200 0..1 Q) Q) ol E c.. -20 ,a
·1 (/) 0-1 Q) ..-.I 't:l lOl C'CI U I ro I 1--' ~1000 Jj l I 1"- ~ I -30 ~ I II- '-1 Co ...J I .0 1
-40 ~ 800 I ro l 00 1 Q)I I-
600 (/)1 -50 ro l
400 .0 1
-60 I Xl
200 Q) I
-70 z: I
0 -80
-2005 535 542 549 556 563 570 577 584 591 5 8-90
Time in days
(a) Tl
2400 40
2200 Temperature 30
2000 20
1800 10
1600 0 I ()
1400 1ij : -1 0° z 00 : ~ ':'::J200 N I -20,a 't:l Q) I ... C'CI
C'CI (/) 1 01 000 ro I -30 Q) ...J .J:: I Co
0.. 1 -0 E 800 . : Q) -40 Q)
~ I ~ :; I-600 L!J II ro I 0 -50 .o l e.
I (/) I ~
400 II :J I~ -60 O l ~ '>:;; 200 ~ I ro -70 0.. 100
0+rt~~+n~~~+n~~~~~~+n~~~~~~~Tn+M~~-80
-2005 535 542 549 556 563 570 577 5 8-90
Time in days
(b) T2
156
2400
2200
2000
1800
Temperature
40
30
20
10
a 1600 1 ~ ~ ;~ ~; _I '" 10) 1 0» 00 1 U
1400 CUi ~ I:J I 0 0) I ~ -1 0° _ z 00: 0) :8.: E ~: :J ~ ~J 200 Nt ~ I I ~ ~: 8. -20 .a - 0)1 ~ ~II~ _ ... 001 IoU ....... X I --- ~ evo 1 000 CUi I I- 0) Il() -30 Q)
...J £1 I Zl~ C-800 0..: ,..-y-vvflVlt1I"""'""",,..r.nNll
l -40 !ii 01 I-XI
600 w: -50 I
400 : -60 I
200 -70
0+rtMrt~+n.rtTh~+n~Th~.rt~~+n~oH~.rtTh+n+n~+h~~-80
-2005 1 535 542 549 556 563 570 577 584 591 5 8-90
Time in days
(c) T3
Figure 4-31: Individual temporary prop loads
157
V1 00
1800
1600
1400
1200
E ~ 1000 ..;-c:: CD E
800 0 E C) c::
" 600 c:: CD m
400
200
0
4~6 -200
RC prop
Pile Y - Gauges below level of formation/base
slab Temp prop
Base slab
c 0
1:5 ::J .... -(/) c· -g I I -g 01 tl cil °1 1:5 I I 1:5 -EI .81 EI 2 II 2 (/)1 (/)1
ffil - - ............ (/) I I (/) 0) I 0)1
IlJI § II § 001 001 0>1 c..> I I c..> ~I ~I ·~I (\I I I -.::t 0...1 0...1 8::1 0... I I 0..._ c.31 c.31 col ...... I I ('I) XI XI °1 0... I I 0... wI wI
444 472
• 13 & 14 • 11 & 12 • 9 & 10 • 7 & 8 "0
c 0) • 5 & 6 (\I 0) (/)
co • 3 &4 l! 1 & 2
L: 0...
(/)
t. ti -ffi I "0 I I c I
0) I c I I .Q I -EI .... IO)llcrol
(/)
............ 0= (\II 0)10) II:;::::;-E I 0)1 (/)1 00 II~ 00 I 001 ~1~II]iEI ~I 0...10... II ~~ I 0...1 c.31 c.3 11- _I c.31 XI X 11"""(\11 Jjl WIWIII-I- I I
500 556 . 3&4 1&2
Time in days
Figure 4-32: Pile Y bending moments below the base slab plotted against time
c:: 0 15 ::J .... -(/) c 0 ° ro .0 > co 0
CI) E 0) 0::
co > 0 E 0) 0:: ('I)
l-N· 1-1
I
~
5&6
~3&14
9&10
7&8
612
Vl \0
1800
1600
1400
1200
E ~ 1000 ...;' s:: III E
800 0 E 0'1 s:: '0 600 s:: III m
400
200
0
4~6 -200
RC prop
• 25 & 26 Pile Y - Gauges above level of formation/base
slab Temp prop • 23 & 24
__________ • 21 & 22
C o U 2
+oJ I/) C o o E co ~I 0>1 .~ I §:I COl 0 1
I
C C o 0
U liu 2 112 ti I I ti § II § 0110 N I I '<t a.. I I a.. ~ I I C'? a.. I I a..
I I
-----------. 19 & 20 Base slab • 17 & 18 ___ --l. 15 & 16
t . ci.. ~1.81 1/)11/)1 ..... 1 ..... 1
~I~I ~I~I 0..10..1 cjlcjl XIXI wlw i
I I
~ co· til ~I
..... 1 0)1 Kli .!:I 0..1 cjl Lijl
I
c l 01
c ]11 o eo I
:;:; ti I -oIIJgCI C II co-0) I I ti ("') I
..... IIE ~I ~ II ..... ~I ~ III- I 0..11~
1-
444 472 500 528
Time in days
"C C 0) N 0) I/) co .!: a.. u x
W
556
Figure 4-33: Pile Y bending moments above the base slab plotted against time
I I I I
C I I 0 I I t5 I I ::s I I "-
+oJ
I -I I/) C I ~I 0 0 1 0 leo
§I .0 I> co 1 0 0:::1 en I§ ("')1 0) 10::: 1-1 I/)
co I ..... NI co .1- 1-1
584 612
0\ o
1800
1600
1400
1200
E ~ 1000 ..;-c: (II
E 800 0
E C) c: :c 600 c: (II
m
400
200
0
416
-200
Pile X - Gauges below level of formation/base
slab
C 0 t5 :J .... -en c· 01 01 EI rol ~I 0)1 .~I
8:1 rol 01
444
RC prop
Temp prop
Base slab
• 13 & 14
• 11 & 12
• 9 & 10
• 7&8
• 5&6
I: 3&4 1&2
en· c l I c I : I 1:1 I I CI .QII.Q 1: I ci.l 21 "0 I I 21 ul I u 21 SI ~I CII c ~ I 2112 en I en I .... 1 ~1I2 ~ I enl I en "'-1 "'-1 "'-1 <DIIJg~1 511 5 511 511 511 enl12 -I 0110 ro I ro I ~I ~II ~ ~ I NII~ it I it I a.. I a..11- _I a.. II a.. ·1 ·1 0 1 011 ~ ~ I ~I I C')- ~I ~I ~I ~II I a.. a.. ill ill ~--.~, 0 x
ill
~,~ I:?E:":;:':~ IUIIII ~ : A XVi!
472 500 till' .. • 556
Time in days
Figure 4-34: Pile X bending moments below the base slab plotted against time
::J .t. !:;I ~ II 011 o 11m .gll~ en II E <DII<D en I 10::
~ II~ I I
584
13&14
11&12
612
1800
1600
1400
1200
E ~ 1000 ..,.;-c: Q)
E 0 E
800
en c: "C 600 c: Q)
OJ
400
200
0
416
-200
........ 0\ ........
RC prop
Pile X - Gauges above ~125 & 26 I I I
level of formation/base 23 & 24 slab Temp prop ~ 21 & 22
19 & 20 Base slab 1+1 17 & 18
15&16 0:/: ;\; f~ .. ~ ~ I :If.. * .. .x 15& 16
c:: o
I I 1 Jj co I~ .j "
~ c:: 1 u 01 W'I _
2 ~ C::II ~ ~ c:: c:: 00 §JgI 811
ro 0 o .Q . . .Q t . a.. ~ . '0 . . ~ E:! I .0 I I > ~ o 1:5111:5 E:!1.81 00 1 a311~ ~I ClJII ~ 0:: E 2112 001001 0,)1 liro- I WIIO,) C")
CIJ 001100 T"'IT"'I ';:I~II~~I 0,)110:: I-
17&18
~ I § I I § ~ I ~ I 0,) I 00 I I - _I ~ I I T'"
0110 ClJIClJI 001 ~IIT"'NI OJIII-e> I £ £ CIJ ~ I- I- I 21 &22 £1 NII.q- a.. I a.. I £1a..11 II ~ 0. I a.. I I a.. . I . I a.. I " I I ,-
g- I ~ I I C")- ~ I ~ I d I I I II. . .A 23&24
o : IL:: IL W : W :,,,,,,,,,,~: t'V"~'1: "_..ad'!. ''--25&26
444 472 500 528 556 612
Time in days
Figure 4-35: Pile X bending moments above the base slab plotted against time
5 HORIZONTAL SOIL STRESS MEASUREMENT
5-1 Introduction
In this chapter the instrumentation used to study changes in the total horizontal stress and
pore water pressures around the retaining wall is described (push-in spade-shaped pressure
cells (spade cells)). A study carried out to determine the over-reading given by a spade cell
installed in overconsolidated clay is described in Section 5-4. This chapter also includes a
study of the stress changes measured in the soil around the retaining wall during
installation (Section 5-5) and data is presented which shows the changes in horizontal soil
stress measured due to excavation and construction of the cutting (Section 5-6).
5-2 Spade cell description
The spade cells used in this study were manufactured by Soil Instruments Ltd and
consisted of a pointed rectangular spade-shaped flat jack, approximately 7 mm thick and
100 mm wide, formed from two sheets of steel welded around the edge (Figure 5-1). The
162
narrow gap between the plates is filled with oil, and is connected to a vibrating-wire
pressure transducer by a short length of steel tubing forming a closed hydraulic system.
The spade cell body also houses an integral piezometer, in the form of a porous filter disc
connected to a second vibrating-wire transducer. The use of vibrating-wire transducers
allowed effectively continuous data to be obtained, as discussed in Section 4-6.
Tedd & Charles (1983) and Ryley & Carder (1995) used spade cells containing pneumatic
rather than vibrating-wire transducers. The vibrating-wire spade cell used in this study was
found to be unaffected by temperatures in the range expected to be exhibited in the ground
on site (9-24 degrees Centigrade) when unconfined. Readings from vibrating-wire
embedded strain gauges (incorporating temperature sensors) measuring strain in buried
concrete piles showed that the readings only became sensitive to ambient temperature
changes when the ground level was within 2·5 m of the cell (see Section 4-3-3).
5-3 Calibration
The spade cell used in the study to determine the spade cell over-reading was calibrated by
Soil Instruments. Figure 5-2 shows the equipment used for spade cell calibration. For total
stress measurement the spade cell is lowered into a compression chamber and readings
from the pressure transducer are taken as the pressure in the chamber is increased. During
this process plates are clamped over the ceramic disk (for pore water pressure
measurement) to protect it, as it has a smaller measurement range than the total stress
transducer.) To calibrate the pore water pressure transducer the clamp remains over the
ceramic disk and water pressure is applied to the transducer at its outlet point on the
transducer at the top of the spade cell. Again, transducer readings are taken as the pressure
acting on the transducer is changed.
5-4 Evaluation of spade cell over-reading
5-4-1 Introduction
Due to the considerable uncertainty regarding the magnitude of the over-reading and the
factors that may affect it (described in Section 2-4), a direct determination of the over
reading seen by spade cells installed in overconsolidated clays should be made wherever
163
possible until more data are available. The spade cell over-reading associated with the
geology at Ashford was evaluated by means of a field study in which a cell was installed
horizontally from the cut-and-cover excavation, aligned to measure the vertical stress, and
its readings were compared with the overburden acting on it. The soil above the spade ce II
was excavated in stages over a period of several weeks, and at each stage the overburden
was calculated and compared with the reading in the spade cell. Additionally,
measurements of in situ horizontal earth pressure taken with the spade cells in the
instrumented section have been compared with pressuremeter readings. In line with other
recent research, the values of over-reading have been expressed in terms of the undrained
shear strength of the soil.
5-4-2 Test procedure
The borehole into which the spade cell was installed was drilled horizontally and
perpendicular to the wall using a continuous flight auger (see Figure 5-3), to a point
approximately half a metre short of the centre of the nadir sump (see Figure 5-4). Owing
to the stiffness and undrained shear strength of the clay it was not necessary to line the
borehole. A jacking platform was then erected, tension bars installed into the piles on
either side of the installation point, and a reaction beam connected to the bars to allow the
spade cell to be pushed into position using a hydraulic jacking system. The installation
barrel was connected to the spade cell which was then moved to the end of the borehole,
so that zero readings could be taken. Considerable care was taken to ensure that the
borehole was horizontal and that the active faces of the spade cell were horizontal aligned.
To complete the installation, the borehole was backfilled and sealed using a cement grout.
The installation barrel was left in place to protect the cables. The exact location and
orientation of the spade cell were confirmed when it was uncovered during excavation
(Figure 5-5).
Prior to installation of the spade cell the instrument was kept submerged in water to
prevent the porous stone from de-saturating and so that it was close to ground temperature
before installation. As an added precaution, a period of fifteen minutes was allowed to
elapse between the transfer of the spade cell to the borehole and installation into the soil to
allow the spade cell temperature to equilibrate fully with the surrounding soil; readings
taken proved this to be the case.
164
The spade cell was pushed approximately 50 mm at each jack stroke during installation
and at each stroke a reading of total vertical stress was obtained using a hand-held
vibrating-wire readout meter. On completion, the transducers were connected to a
datalogger and readings were taken every 15 minutes. Figure 5-6 shows the spade cell
output during the installation phase and during excavation within the sump: the total stress
readings gradually stabilized over a period of approximately 2 weeks prior to excavation.
During excavation careful surveying of the level of the material within the sump at the end
of each day has enabled the overburden to be calculated. However, as excavation
proceeded after the ring beam had been installed access to the base of the excavation was
restricted due to the amount of machinery within the excavation. The excavation phases
are listed in Table 5-1 and the volume of material removed at each excavation phase is
shown schematically in Figure 5-7.
Stage Description Date Day
1 Excavation of3·8 m leaving steps cut in clay for Tues 26/06/01 628 access
2 Steps removed. Mini-digger lowered into Wed 27/06/01 629 excavation
3 Excavate another 2·65 m generally although Thurs 28/06/01 630 only 1 ·4 m directly over spade cell
4 Further excavation less than 1 m Fri 29/06/01 631
5 Excavation and levelling to ring beam formation Mon 02/07/01 634 level
6 Ring beam and wall installation and time for July 2001 633-concrete setting 663
7 Excavation restarted. 1·7 m of material below Wed 01/08/01 644 the ring beam removed.
8 Uncovered spade cell Mon 16:20 06/08/01 669
Table 5-1: Details of nadir sump excavation
5-4-3 Results and Discussion
Figure 5-6 shows that reductions in total stress were measured at every excavation stage
and an increase in total stress resulted from installation of the ring beam. At the end of the
test when there was no load on the spade cell the total stress readings returned to zero. The
pore water pressure was approximately zero throughout the test period.
165
Figure 5-8 shows the measured total vertical stress just prior to excavation and at the end
of each excavation stage plotted against the total vertical stress calculated from the depth
of overburden acting on the spade cell (calculated using a bulk density of 21 kN/m -': see
Chapter 3). Any discrepancy between the initial steady spade cell reading and the in silll
overburden stress must be due to the effect of inserting the cell. Figure 5-8 shows that the
initial overburden is 180 kPa, giving an over-read of 49 kPa or 0·35 x cu. As the
overburden is removed, further discrepancies may arise as a result of the differential
cell/soil stiffness (cell action factor effects), and/or the development of shear stresses
between the soil and the walls of the nadir sump, acting so as to resist heave.
In addition to an over-read of the in situ stress due to the effects of insertion, it is well
known that a pressure cell will generally either over-read or under-read changes in stress
depending on whether the cell is stiffer or less stiff than the soil within which it is
embedded. This was investigated by Peattie and Sparrow (1954) in terms of the relative
cell to soil stiffness. They provide guidance on the design of pressure cells to measure soil
pressures irrespective of the type or condition of the soil. Determination of the relative cell
to soil stiffness is complicated by the fact that, even for a given stress history, stress state
and load path, the stiffness of the soil may vary by several orders of magnitude as strain
occurs.
The data shown in Figure 5-8 suggest an under-read of the reduction in vertical stress,
which is consistent with a cell that is over-compliant (i.e. insufficiently stiff: Clayton &
Bica, 1993) and/or the mobilization of shear stress on the nadir sump walls. Measurement
of the change in thickness of the spade cell blade (by means of high resolution miniature
linear variable displacement transducers (L VDTs)) during calibration in a fluid filled cell
(Figure 5-9) indicated an effective cell stiffness (E) of 4·55 GPa. This is far in excess of
the measured small strain soil stiffness of the lower Atherfield Clay of270 MPa (Xu,
2002); thus over-compliance is not an issue, and the under-read of the reduction in vertical
stress must have been due to the mobilization of shear stresses on the nadir sump walls. To
confirm this, a plane strain undrained finite element analysis was carried out using the
continuum finite element program CRISP (Britto and Gunn, 1987), across the narrow
section of the nadir sump.
The analysis started with the walls already in place and a pre-excavation earth pressure
coefficient of 1. Excavation was modelled by the gradual removal of elements to a depth
of 6·7 m, corresponding to the level at which the intermediate concrete ring beam support
was constructed. The mesh used in the analysis is shown in Figure 5-10 and comprised
166
1904 non-consolidating linear strain triangular elements. The base boundary was fixed in
both the horizontal and vertical directions. The vertical mesh boundaries were fixed in the
horizontal direction only. An elastic-perfectly plastic soil model with a Tresca (undrained
shear strength) failure criterion in terms oftotal stresses, 'tmax = Cu was used for each soil
layer and the wall was modelled as a linear elastic material. An undrained soil stiffness
(Eu) profile was derived from the measured undrained shear strength profile (Figure 3-15
and Equation 3-1) using Eu =1500 cu. This is based on laboratory test data presented by
Jardine et al. (1984) for a variety of clays including London Clay, at a characteristic shear
strain of between 0·01 % and 0·1 % (Jardine et al., 1986; Mair, 1993).
An effective soil stiffness (E') profile was derived from the measured undrained stiffness
(Eu) profile using Equation 5-1, where Poisson's ratio (v') = 0·35.
E'= l+v' E • u·
1.5 Equation 5-1
The effective soil stiffness profile given by Equation 5-2 was used to derive the effective
bulk modulus of the soil (K').
E' K'=----
(3(1- 2v')) Equation 5-2
Undrained conditions were imposed by specifying the bulk modulus of water (Kw) as 100
times the effective bulk modulus ofthe soil (K').
Figure 5-11 shows the calculated total vertical stress as a function of overburden at an
integration point located at the same depth as the spade cell (approximately 8·5 m below
original ground level). The aspect ratio of the sump box (its breath, b, to length, I, ratio =
0·72) is high, suggesting that further arching effects would be expected across the longer
dimension of the box due to the shear stresses on the shorter walls. In very simple terms,
multiplying the calculated over-read by 1·72 gives an upper estimate ofthe possible error
due to arching between the sump walls.
The raw data from the finite element analysis were adjusted for comparison with the spade
cell data by:
• Multiplying the initially calculated over-read by 1·72 to allow for shear stresses on
the short sides of the sump as well, and
167
• Adding the over-read due to spade cell installation of 49 kPa.
Figure 5-11 shows that the adjusted finite element analysis results match closely the
measured data. This tends to confirm that the discrepancy between the calculated and
measured overburden may be accounted for by a combination of (a) spade cell over-read
of 0·35 Cu due to installation effects, and (b) the mobilization of shear stresses at the walls
of the nadir sump.
A simple equilibrium analysis of the mobilized soil/wall adhesion further supports this
conclusion. For an excavation of dimensions 1 x b in a soil of average undrained shear
strength Cu and unit weight y, a mobilized soil/wall adhesion of a clI
and a depth of soil
remaining (above the spade cell location) of h, the downward force acting on the soil in
addition to the weight is:
Equation 5-3
This is equivalent to an average increase in vertical stress of:
Equation 5-4
The undrained shear strength (cu) varies with height above the spade cell location (h) at a
rate of ~ kPa, and as previously stated in Section 3-6-3, the undrained shear strength at the
position of the spade cell Cu = 140 kPa. Thus the average undrained shear strength Gil in
the soil mass remaining above the spade cell is:
- f3h Cu = 140--.
2 Equation 5-5
Substituting equation 5-5 into equation 5-4 provides an indication of the error (over-read)
Err due to the mobilized shear stress on the sump wall perimeter as a function ofthe height
of the remaining soil above the spade cell:
E = (280ah _ aRh2 )(1 + b) . rr f/' lb Equation 5-6
Figure 5-12 shows the measured spade cell over-read and the calculated error (Err) for
adhesion factors (a) between 0 and 0-4. It can be seen that the measured discrepancy could
168
be accounted for by the mobilization of approximately 30% of the undrained shear
strength at the soil/wall interface as the overburden is removed.
Figure 5-13 shows the in situ total horizontal stresses measured at the instrumented
section, both raw and corrected for installation effects by subtracting 0'35 cu, and self ..
boring pressuremeter data obtained 250 m northwest of the nadir sump. The subtraction of
0·35 Cu to account for spade cell installation effects brings the spade cell data largely into
line with the self-boring pressuremeter test results. Consequently all total horizontal stress
measurements have been corrected by 0·35 Cu (unless otherwise stated).
5-5 Installation effects of a bored pile retaining wall in overconsolidated clay
5-5-1 Introduction
This section contains an analysis of the effects of wall installation on the soil surrounding
the contiguous bored pile retaining wall.
5-5-2 Calibration and installation of spade cells
The spade cells in the instrumented section were calibrated and installed by the Transport
Research Laboratory. Figure 5-14 shows the installation of one of these spade cells.
5-5-3 Stabilization of spade cells following insertion
Figure 5-15 shows the readings of total horizontal stress and pore water pressure during
spade cell insertion and for a period of one month afterwards (readings from spade cell or
piezometer number n are referred to as Sn and Pn respectively). The excess pore water
pressures induced during spade cell insertion had dissipated and readings of total
horizontal stress had stabilized prior to the installation of the bored pile wall.
5-5-4 In situ total horizontal stresses and pore water pressures
Figure 5 -16 shows the corrected, stabilized readings of total horizontal stress and pore
water pressure from all spade cells and piezometers, plotted against depth below original
ground level. The initial in situ pore water pressures were slightly less than hydrostatic
169
beneath a water table 1·2 m below the original ground surface in the upper Atherfield
Clay. In the lower part of the stratum the deviation of the pore water pressure from
hydrostatic was more pronounced. This distribution of pore water pressure with depth is
consistent with underdrainage of the Atherfield Clay into the underlying Weald Clay,
within which an ejector well pore pressure control system was in operation about 100m
from the instrumented section (see Section 3-3-5).
The variation of in situ total horizontal stress aho with depth z (below ground level) was
approximated by the linear function given in Equation 5-7.
aho (kPa) = 0·8 + 20·6 x z (z in m). Equation 5-7
5-5-5 Effective stress profile
The profile of effective horizontal stress cr'ho with depth (obtained by subtracting the
measured pore pressure from the total horizontal stress at each location) is shown in
Figure 5-17. The implied in situ earth pressure coefficient Ko (=a'ho/a'yo) is generally
within the range 0·9 to 1· 5 with an average of 1·1. This is rather less than would be
expected on the basis of the one-dimensional stress history of the deposit (as discussed in
Section 3-3-4).
5-5-6 Pore water pressure changes during and after wall installation
Figure 5-18 shows the variations in pore water pressure measured during the period of
wall installation, together with the periods of installation of each pile group. Detailed
interpretation ofthese data is complicated by the sequential nature of pile installation,
together with the fact that the spade cells could not all be installed at one cross section but
had to be spread along the length of the wall. However, the general response of each
transducer comprises a reduction in pore water pressure on excavation followed by an
overcompensating increase in pore water pressure on concreting. The pore water pressure
then gradually falls to the original value over a relatively short period of time (in this case
less than a day) as the concrete begins to set. This response is similar to that measured in
the field by Symons & Carder (1993) and in centrifuge model tests by Powrie & Kantartzi,
(1996). The magnitudes of the measured changes vary, but generally reduce with distance
from the pile being installed. The changes in pore pressure were consistently most
pronounced at piezometer P4. The reason for this is unknown.
170
Pile installation may be idealized as an expanding or contracting circular cylindrical
cavity. Analysis following Gibson & Anderson (1961; reproduced in Powrie, 2004) shows
that if it remains elastic, the soil surrounding the cavity deforms at constant volume and
constant average total stress p (= [O'r + O's + O'v]!3). In an elastic medium, deformation at
constant volume occurs at constant average effective stress pI; hence while p remains
constant there should be no change in pore water pressure. However, a reduction or
increase in cavity pressure (from the in situ condition) equal to the undrained shear
strength of the soil, cu, is sufficient to cause yield and hence potential changes in pore
water pressure. In the present case, the in situ total horizontal stress (given by Equation 5-
7, O'ho = 0·8 + 20·6 z) is greater than the undrained shear strength (given by Equation 3-1,
Cu = 22 + 7 z) for depths z greater than 1·6 m. Unloading the pile bore from an in situ total
horizontal stress O'ho to a cavity support pressure P (where [O'ho - P] ~ cu) will cause yield
of the surrounding soil within a plastic radius rp given by Equation 5-8, where R is the
cavity radius.
[a -c -P] r = R x exp ho u •
p 2c u
Equation 5-8
In the present case, taking the cavity support pressure P = 0, the cavity radius R = 0·525 m
and the profiles of in situ total horizontal stress and undrained shear strength with depth
given by Equations 5-7 and 3-1 respectively, the width of the plastic zone (r p - R) varies
from zero at a depth of 1·6 m to 0·6 m at the bottom of the pile bore.
Even the closest pore water pressure transducers were outside the theoretical plastic zone,
and might therefore have been expected to show no change in pore water pressure.
However, it is well known that soil does not behave as an ideal elastic material. Also, the
neglect in this simple analysis of both the potential for vertical load transfer to the soil
below the pile toe and the effect of any piles already installed introduces further degrees of
approximation. Nonetheless, the measured pore water changes are generally not large, and
decrease rapidly with distance from the wall as the effects of the approximations become
less significant.
For a wall constructed from diaphragm wall panels rather than individual piles, a greater
pore water pressure response would be expected. Excavation in plane strain results in a
reduction in average total stress p of half the reduction in horizontal pressure within the
trench, in the soil close to the trench (Powrie & Kantartzi, 1996). If the soil is again
171
assumed to deform elastically with p' = constant in undrained conditions, the change in
pore water pressure would be expected to be the same as the change in p, i.e. half the
reduction in horizontal stress within the trench. Powrie & Kantartzi (1996) report
centrifuge tests modelling diaphragm wall panel installation in which the measured
changes in pore water pressure clearly reduced with reducing panel length. However. the
difference in pore water pressure response between bored pile and diaphragm walls is not
so clear from the field observations described, but not presented in any great detail, by
Symons & Carder (1993).
Figure 5-19 shows the measured pore water pressures plotted against time for periods
before, during and 10 months after wall installation. When viewed in this way, the
fluctuations in pore water pressure due to pile excavation and concreting are little more
than noise, and the data show clearly that the overall net effect of wall installation on the
in situ pore water pressures was negligible. This is consistent with the observations of
Symons & Carder (1993) and Powrie & Kantartzi (1996), and confirms that, in an
overconsolidated clay, the overall effect of bored pile or diaphragm wall installation on the
in situ pore water pressures may reasonably be neglected. In the 10 months following wall
installation the pore water pressure slowly reduced at the positions of many of the spade
cells. The pore water pressure began to fall in March (approximately Day 150), probably
due to seasonal variations and/or construction dewatering being carried out about 500 m
from the instrumented section.
5-5-7 Total horizontal stress changes due to wall installation
Figure 5-20 shows the total horizontal stresses measured during installation of the wall. As
with the pore water pressures, interpretation is complicated by the sequential installation
ofthe piles and the staggered pattern of the spade cells along the length of the wall.
Nonetheless, the influence of pile construction on the individual traces (generally, a
reduction in total horizontal stress on excavating at least the lower portion of the pile and
an increase in total horizontal stress on concreting) is clear. Overall, pile installation
resulted in a reduction in total horizontal stress to below the in situ value, the magnitude of
the reduction generally decreasing with distance from and along the wall.
The changes in stress measured due to the installation of a single pile can be compared
with values calculated using an elastic analysis, assuming as an upper limit that the change
in stress at the pile bore is from the in situ stress to zero (as the pile was initially bored
172
with no support). The change in radial stress, ~()r, at a distance r from the centre of the
pile, is related to the change in stress at the pile bore, ~()PB, and the radius R of the pile
bore by Equation 5-9 (see for example Fjaer et ai., 1992).
Equation 5-9
The installation of any pile affects the stress state of the ground at the positions where
further piles are to be installed. Assuming that at the depth under consideration pile
installation results in a reduction in stress, then at the centres of piles yet to be installed,
the stress in the direction perpendicular to the wall increases (due to arching) and the
stress in the direction along the wall decreases. Calculation of the changes in stress seen
by a spade cell due to the installation of piles after the first pile is therefore more
complicated. A lower limit to the change in stress may be estimated by assuming that the
in situ stress at the positions ofthe piles not yet installed is reduced (as happens to the
stress in the direction along the wall). An upper limit may be estimated by assuming that
the in situ stress increases (as happens to the stress in the direction perpendicular to the
wall).
Consideration of the Mohr circle of stress shows that the change in horizontal stress acting
on the plane ofthe spade cell, ~crsc, due to the installation of any pile is given by Equation
5-10, where e is the angle between the normal to the wall and the line joining the pile to
the spade cell (Figure 5-21) and ~crr is the change in radial stress at the spade cell (as
given by Equation 5-9).
~crsc = ~crr X cos 28 Equation 5-10
Figure 5-22 shows the measured and calculated changes in stress, normalised with respect
to the in situ stress plotted as a function of the distance along the wall (in pile spacings)
between the spade cell and the nearest pile being installed in a particular pile installation
period. Due to the complexity of the installation sequence, the following rules have been
adopted:
1. Where two piles were installed simultaneously at an equal number of pile spacings
from a spade cell, the change in stress measured at the spade cell attributed to the
installation of a single pile was assumed to be halfthe total. For example two piles,
each four pile spacings from spade cell 3, were installed during Period A, so half
the measured total stress change has been attributed to each.
173
2. Where two piles were installed simultaneously at distances from a spade cell
differing by one or two pile spacings, the change in stress has been halved and
assigned to a pile at the average distance from a spade cell. For example piles were
installed 2 and 3 pile spacings from spade cell 12 in Period E, so half the measured
total stress change has been plotted as a change due to pile installation 2·5 pile
spacings away.
3. Where in any installation period the difference in the distance between the spade
cell and the nearest pile installed and the second nearest pile was more than two
pile spacings, the entire change in stress has been assigned to the nearest pile. For
example, the two piles installed in period A were two and six pile spacings from
spade cell 2, so the change measured at spade cell 2 during period A has been
plotted as a change due to a pile installation two pile spacings away.
The change in stress was calculated over the period from 2 hours before the pile
installation process began to 2 hours after it finished. Figure 5-22 shows that the reduction
in total horizontal stress measured on installation ofthe pile in line with a spade cell was
approximately 0 to 20% of the in situ value 1·275 m from the edge of the wall, 3 to 9%
2·375 m from the edge ofthe wall and 1 to 5% 3·475 m from the edge ofthe wall.
Figure 5-22 shows that the measured reduction in stress due to pile installation is generally
larger than that calculated using the simple elastic analysis - even assuming zero pressure
(rather than the pressure of bentonite or wet concrete) in the pile bore and an in situ stress
corresponding to the upper limit value resulting from the installation of previous piles.
This could be a result of shrinkage ofthe concrete (possibly due to thermal effects) as it
sets, andlor vertical arching and stress transfer below the bottom of the bore, which is not
taken into account in the simple analysis. The underestimation of the measured reductions
in horizontal stress is confirmed by Figure 5-23, which shows the calculated and average
measured reductions in stress (expressed as a percentage of the in situ value), for piles
directly opposite the spade cell (i.e. in Figure 5-21 a distance of zero pile spacings along
the wall).
Figure 5-24 shows the measured in situ and post-installation total horizontal stresses at a
distance of 1·275 m from the wall. The best-fit linear approximation to the in situ total
horizontal stress is given by Equation 5-7. The best-fit linear approximation to the post
installation total horizontal stress measured by the instruments 1·275 m from the wall is:
crh (kPa) = 7·4 + 16·7 z (m). Equation 5-11
174
On the basis of the best-fit linear approximations, the reduction in total horizontal stress
ranges from 10% at the top ofthe Atherfield Clay to 17% 15·3 m below ground level.
However, this masks the true nature of the variation with depth of the change in effective
horizontal stress, which is much greater (about 30%) at the mid-depth of the wall than at
ground level or at the toe (approximately 4%) as shown in Figure 5-25. This is consistent
with the transfer of lateral stress to the soil below the wall (sometimes referred to as
vertical arching), which results in an increase in horizontal stress below the toe as shown
by Ng et al. (1995). It also suggests that an attempt to quantify the effects of wall
installation as a uniform with depth percentage reduction may be too much of an over
simplification.
5-5-8 Effective stress changes due to wall installation
Figure 5-26 shows all the in situ effective horizontal stresses and the post installation
effective horizontal stresses measured 1·275 m from the wall. The best-fit linear
approximation to the in situ effective horizontal stress below the groundwater level of 1·2
m is given by Equation 5-12, and the best-fit linear approximation to the post-installation
effective horizontal stress below groundwater level is given by Equation 5-13.
cr'ho (kPa) = 15·3 (z - 1'2) + 10.86 (for z ~ 1'2 m). Equation 5-12
cr'h (kPa) = 11·6 (z - 1.2) + 5·52 z (m). (for z ~ 1·2 m). Equation 5-13
The change in effective horizontal stress calculated from the linear best-fit approximations
to the measurements is 30% 3·3 m below ground level, falling to 25% 15·3 m below
ground level (Figure 5-27). However, the linear approximations again mask the true
pattern, and the actual measurements show a similar trend to the total stress changes
(Figure 5-25) with the greatest reduction occurring at 8·3 m below ground level. The
percentage changes in effective stress are greater than the percentage changes in total
stress because there was no overall change in pore water pressures.
Current guidance given in CIRIA Report C580 (Gaba et al., 2003) is that installation of a
bored pile wall might be expected to reduce the in situ earth pressure coefficient by about
10%. This is largely based on work the work by Symons & Carder (1993) (see Section 2-
2-5) who measured a reduction in lateral earth pressure coefficient K from 2·1 to 1·9
(~1 0%). At Ashford the lateral earth pressure coefficient reduced from approximately 1·1
to 0·8 (~25%), on the basis ofthe linear idealizations to the data indicated in Figure 5-26.
175
Although there appears to be a large discrepancy between these changes when expressed
in percentage terms, they are consistent with a similar absolute reduction in total or
effective horizontal stress of about 0'25 yz in each case (where y is the unit weight of the
soil). This suggests that the likely reduction in earth pressure due to in situ wall
installation could be estimated in absolute terms. Given that the process might be expected
to be controlled by the boundary stresses at the pile bore this is perhaps surprising, but
may be more credible than an approach based on a reduction in Ko in percentage terms.
However, it has already been noted that idealisation of the percentage stress change as
uniform with depth may be inappropriate.
5-5-9 Total and effective horizontal stress changes after wall installation
Concern is sometimes expressed that the in situ horizontal stresses become re-established
in the long-term. In this case, measured total horizontal stresses showed no tendency to
change for a period of 10 months after wall installation (Figure 5-28), suggesting that the
reductions in horizontal stress due to wall installation are permanent. This is consistent
with long-term observations of horizontal pressures behind a number of in-service
retaining walls, which show no significant change in total horizontal stress over periods of
between 5 and 24 years after construction (Carder & Darley, 1998).
Although the in situ earth pressure coefficient of the Atherfield and Weald Clay at this site
is low relative to other overconsolidated clay deposits, the reduction in total horizontal
stress was similar to that for a clay with Ko = 2 excavated under bentonite, assuming a
water table at ground level.
5-6 Effect of excavation in front of the wall on horizontal earth stresses
The total horizontal stresses and pore water pressures measured by the spade cells over the
main cutting construction period are shown in Figures 5-29, 5-30 and 5-31 (for spade cells
1·275 m, 2·375 m and 3·475 m behind the wall respectively) and Figure 5-32 (in front of
the wall).
The Figures show that excavation of the cutting caused reductions in total horizontal stress
at all depths and distances behind the wall. Pore water pressures also reduced in all cases.
In front of the wall much larger reductions in total horizontal stress were measured. Base
176
Slab Construction, however, caused an increase in horizontal stress, particularly in spade
cells 11 and 13 which are located only 1·5 m below the base slab.
The compatibility of the total horizontal stress data, reinforced concrete prop loads and
bending moment data was investigated by analysing the data collected on Day 517, just
after Excavation Phase 1. Bending moments were calculated by taking moment up the
wall from the toe by consideration of it as a free body diagram. A spreadsheet was used to
find estimated values of total horizontal stress, within 10% of the spade cell
measurements, which gave a wall bending moment profile which was a best-fit to the
measured bending moment profile, using the least squares method (i.e. the sum of the
difference between the calculated and average measured bending moment squared was
minimised).
The measured and estimated horizontal stress profiles on Day 517 are shown in Table 5-2.
Table 5-3 and Figure 5-34 and the measured and computed bending moments in Piles X
and Y on Day 517 are shown in Table 5-4 and Figure 5-33.
Depth BGL, Spade cell Total horizontal stress, kPa Estimated/ m No. measured, (Yo
Measured Estimated
0 ground level
3.3 1 57 62 110
5.3 2 20 22 110
8.3 3 52 57 110
11.3 4 162 146 90
15.3 5 300 270 90
20.25 Wall toe 431.3
Table 5-2: Measured and estimated total horizontal soil stress behind the wall
177
Depth BGL, Spade cell Total horizontal stress, kPa Estimated/ m No. measured, 0/0
Measured Estimated
6.95 Exc level 0
8.3 82
11.6 11 (13) 101 (107) 111 110
15.3 (12) 17 (162) 331 329 99
20.25 Wall toe 386
Table 5-3: Measured and estimated total horizontal soil stress in front of the wall
Pile Depth, m Measured bending moments, kNm Calculated bending
gauges Pile X Pile Y Average moment, kNm
pile top 0.00 42.0
0.50 58.1
25&26 2.24 102.1 102.1 114.4
3.30 148.6
23&24 3.72 223.5 247.5 235.5 192.2
21&22 5.30 380.0 375.3 377.7 283.7
19&20 6.79 292.8 254.0 273.4 311.4
6.95 298.7
17&18 8.30 222.4 199.8 211.1 254.8
15&16 9.76 306.3 214.6 260.5 225.7
13&14 11.30 149.5 130.0 139.8 181.2
11.60 164.5
11&12 12.70 72.8 35.0 53.9 76.2
15.30 -129.8
9&10 14.20 -49.2 -49.2 -63.0
7&8 15.70 -165.7 -98.2 -131.9 -138.8
5&6 17.20 -94.8 -83.7 -89.3 -111.5
3&4 18.70 -43.7 -43.7 -41.5
1&2 19.70 6.0 -30.8 -12.4 -6.3
pile toe 20.25 0.0
Table 5-4: Measured and calculated bending moments
The RC prop load that would occur under the estimated horizontal soil stress profile
presented in Figure 5-33 can be found by analysis of the horizontal equilibrium, and yields
178
a load of 986 kN. The loads in the RC props indicated by the data presented in Section 4-
4-3 are listed in Table 5-5, along with the loads measured directly before and after the
period of 16 days during Excavation Phase 1 when no excavation was carried out in the
instrumented section. During this time the RC props loads increased by between 168 and
512 kN, and the majority of this apparent increase in load is probably attributable to creep.
Load after Load before Portion of Load excavation excavation load partially indicated after
phase lA, kN phase 1B, kN due to creep, Excavation kN Phase 1, kN
Day 489 503 - 517
PI 857 1250 393 1226
P2 555 1076 512 1406
P4 129 297 168 594
Table 5-5: Increase in prop load over period where no construction activities WCI'C
carried out during Excavation Phase 1
If the measured prop loads were reduced by the amount indicated by the increase in load
over the period of no activity at the instruemented section, the loads in RC props PI and
P2 would compare favorably with those calculated in the simple equilibrium analysis
carried out. The measurement ofRC prop loads is not straightforward and although further
refinements could possibly be made to these data, it is beyond the scope of this work.
5-7 Conclusions
Total stresses measured using push-in spade cells in Atherfield Clay may be corrected for
installation effects by subtracting 0·35 x the undrained shear strength, Cu. This is generally
less than corrections determined for spade cell installation effects in previous studies in
London Clay.
Laboratory calibration ofthe spade cell indicated a very high stiffness in comparison with
the surrounding soil, suggesting that errors due to over-compliance should not be
significant even in a stiff clay. In the experiment reported in this paper, discrepancies
between the measured vertical stress and the overburden could be accounted for by a
combination of cell installation effects and the mobilization of shear stresses on the nadir
sump chamber walls.
179
A comparison of total horizontal stresses measured in the self-boring pressuremeter tests
with spade cell measurements adjusted by 0·35 eu correction showed close agreement.
Measurement of the changes in total horizontal stress and pore water pressure during
installation of a contiguous bored pile retaining wall forming part of the Channel Tunnel
Rail Link at Ashford has shown that:
1. Pore water pressures fell during pile excavation and then increased during
concreting. The magnitude of the changes decreased with increasing distance from
the pile. In theory, the change in pore water pressure should be zero for a circular
cylindrical cavity if the surrounding soil behaves elastically. However, ditTerent
geometries would produce different theoretical results: e.g. in plane strain
l1u = 0·5 I1crh, close to the trench.
2. Overall, wall installation had no effect on pore water pressures, which rapidly
returned to their in situ values on completion of the process. This is in agreement
with previous observations for both diaphragm and bored pile walls. In contrast,
there was a very clear reduction in the effective horizontal stresses and lateral earth
pressure coefficients.
3. The in situ total horizontal stresses did not re-establish during the 10 months that
elapsed between wall installation and excavation in front of the wall.
4. Although the soil almost certainly yielded during installation, the size of the plastic
zone was small. However, the measured changes in horizontal stress due to
individual pile installation were generally greater than those calculated in a simple
elastic analysis, even assuming zero pressure at the pile bore rather than the
pressure of bentonite or wet concrete. This may have been due to shrinkage of the
concrete due to thermal effects, and/or vertical arching not taken into account in
the analysis.
5. The profiles of reduction in total and effective horizontal stress were not linear
with depth, but greatest at the mid depth of the pile. This is consistent with the
transfer of lateral stress to the soil below the wall (sometimes referred to as vertical
arching). In this case study, wall installation caused a reduction in total horizontal
stress varying from about 4% at the top and the bottom of the wall to
approximately 30% at mid-depth. Attempting to quantify the effects of wall
installation as a uniform with depth percentage reduction in total horizontal stress
may be an over-simplification.
180
Figure 5-1: Spade cell
181
Compression chamber
(a) Calibration equipment for total stress measurement
(b) Calibration equipment for pore water pressure measurement
Figure 5-2: Spade cell calibration equipment
182
Figure 5-3: Equipment for drilling horizontal borehole
183
N
+ spade cell
. ,
. ,
00 / SBPM test 00 I
location: 250 mOO /
/°0 cut-and-cover box
00 00
instrumented \0
" . nadir sump
.
section: 600 m \
,---0 , . ,
cut-and-cover box .
contiguous piled walls diameter = 1050
,,41.15 mAOD ----j,f---~
Upper Atherfield Clay
r--------------- ____ sz ~~~1 mAOD
'. ::g-~~_l\~~-.~ .. -,
, spade cell . , "
4 . ,
7500 4
,
T 13575
,
~
.
, .
,
f-------------
. ,
4 •
'---
lower Atherfield Clay
_ ___ __ \.Z 2?:~1 mAOD
Weald Clay
measure ments in mm herwise stated unless ot
Figure 5-4: Nadir sump plan and elevation
184
Figure 5-5: Spade cell: uncovered in excavation
185
......... 00 0'\
450
400
~ 350 .!II::
Q) ... ::s I/) 300 I/) Q) ... a. ... .$ 250 CIS 3: Q) ... &. 200
oI!S I/) I/)
~ 150 -I/) CIS (J
1:: 100 Q)
> n; -0 50 I-
Total stress
L I II II II
IIIIIII I II II II
J IILlII IIIIIII j IIIIII IIIIIII
. IIIIII Excavation 1 a-j I I II
I III III Excavation 2 - I .LII I I
I IIIIII
Excavation 3 I I II II I I I I"H I I
. I IIIIIII Excavation 4 ---LJ II II I I
Pore water I pressure
I TiTl"N I I I IIIII I I I IIIIII I I IIIIII I I IIIII I I IIIIIII I I IIIIII
II I~ II Excavation 5 II II II II
Increase in stress in response to ring beam installation
!~ I
o i j;:=;= ",,"" I" I~ I I Ii: ' 1.1
6 6 620 627 641 613 634 648 655 662 669 I
-50 ...L 11th June 2001
Time in days
Figure 5-6: Total vertical stress measured by spade cell in nadir sump
676
41.145
41.145
Excavation 1
'. //lL3L3§§_J7
! Spade cell 32.590
spade cell
r+~ 00000000~ o o 8
Excavation 4
36.860 3§.109 34.300 v: /7L _____ -I
I Spade cell 32.590
41.145
41.145
o spade cell
OQ/fooo 8 <:) o
~~ 8 ~ 0
00000000 o o o o
Excavation 2 Excavation 3 41.145
[ . .. , _~U42 _____ y-
, I 35.~05 _ 36.8~.: I
7777T/'L_" /:,1 34.698 !. !
! ! ,. ,
I'f Spade cell Spade cell I' : 32.590 32.590 i I
t·]
Q 0 o 0
go)f<000)-OO 8 ?;rooooo~~ 6 spade cell 6 b 0_ 0
8 tYA 8 S oooooo00tS'oB o· 06~s
G 0 o 0
8 8
Excavation 5 Installation of ring beam 41.145
__ ~4.~3.L ___
I Spade cell
I Spade cell
32.590 32.590
8 8 00000000008 00000000008 o 0 0 ........ "0
S 8 spade cellifj. 0 g O -----e-- . 0
- 0 :.'0 8 8 8···· . .'. '" ;',8 000000<00000 88000000000
o 0
8 8 o 0
all measurements in m AOD
.\'
.v
Figure 5-7: (a) Elevations and (b) plans detailing the excavation of material above spade cell in nadir sump
187
CIS D.. ~
Cii C)
CI) "C
250
200
[ 150 II)
c o II) II) e U;
S 100 .s "C e :::l II) CIS CI)
:E 50
o
after excavation 4 .. '
after excavatiofl' 5
LJ1 .' 1
excavatjon under ring beam
50 100
.'
before excavation
.'
150
over-read due to installation
200 250
Total stress acting on spade cell due to overburden, kPa
Figure 5-8: Measured total vertical stress versus overburden
188
0.0009
0.0008 ----------------,----------------- ----------------- ----------------- --------- -------,----.--- ....... .
E E 0.0007 en en CI)
~ 0.0006 CJ .=. -CI) "C ns
0.0005
~ 0.0004 a; CJ CI)
"C ns c. en
0.0003
.= 0.0002 CI) C) c ~ 0.0001 u
-0.0001
Calibration chamber fluid pressure, kPa
Figure 5-9: Nadir sump spade cell stiffness calibration
600
189
E C")
N V
50 m
Figure 5-10: Finite element analysis mesh
Position of spade cell
190
250
225
ca 200 a.. ..liI:
IIJ IIJ 175 Q) ~ -IIJ
ca (.) 150 1:: Q)
> '0
125 Q) -~ :::s
..=! ca 100 (.) ~
0 '0 ~ 75 :::s IIJ ca Q)
:!E 50
25
o
LJ1
25 50 75
-FEA
-A- Nadir sump spade cell
-+- Adjusted FEA
100 125 150 175 200 225 250
Overburden, kPa
Figure 5-11: Measured and calculated vertical stresses against overburden
191
150 Hmax
a=O.4 125
100 a=0.3 -ra a. ~ - 75 ... 0 ... a=O.2 ... w
50
a=0.1 25
a=O o ~~----~------~------~------~~-----.
o 2 4 6 8 10
Height of soil above spade cell (m)
Figure 5-12: Over-read error - measured and calculated from limit equilibrium analysis
192
5
25
30
Total horizontal stress, kPa
o 100 200 300 400 500 600 700 800 900
\ \ \ \ \
\ux. \ \
\ • . \ \ \ \
.~ \ \
\ \ \
,\~x
~ \ \ \ ...
\
.. ~ ... .&<x
• \.
\ \ \ \
\ \ . \
• • \ ~ Overburden
\
• • •
\ \ \ \ \ \ \ \ \ \
• Pressuremeter 3593 - 250 m from nadir sump ... in situ total stress (spade cell): corrected x in situ total stress (spade cell): uncorrected
Figure 5-13: Comparison between spade cell readings corrected by 0-35 Cn and selfboring pressuremeter test results
193
Figure 5-14: Spade cell installation
194
as D. ~
700
600
en 500 III ~ u; 400 S c ~ 300 'i: o = "i 200 '0 I-
100
85
810
810
84
no data for this period
812 817
\ -...
vlv ,,:: ......................................... -----___ 85
812 S13 89 1\ / 811 \ </. .......................................... _84 ____ _
1 .. ·8,-6· .. · .. :::::::::::::::" .. · .. · ...... ·· -~ 816
~~m-:::::::::::::::::::::::::::::::::::::::::::::==f-==~===== 815 ,...-v ~:--3~::!:
58 'S'~2 515 ;'~~"'::' "',::,' ,,:::::::::::: :::::::: ::~'~~89~~~8§1~~ S1
O~~rr~~rr~~"+.~-.r."-.rr,,~rr,,.-r.,,~-.ro~-.,,~
as 300 D. ~
~ 200 c. ... CI) .... ; 100 ~ 0
D. 0
o 5 10
0 5
15 20 25 30 Time in days
(a) Total horizontal stresses
no data for this period I
15 20 25 30 Time in days
(b) Pore water pressures
35 40 45
35 P1 40 45
50
P13 P3 -
50
Figure 5-15: Spade cell measurements taken between their installation and wall installation
195
0
0
1
2
3
4 (2 data points) 5
E 6
-a; 7 > 8 .9! "C 9 c 5 10 ... C» 11 == .E 12 CI)
.c 13 .c -g. 14 c 15
16
17
18
19
20
21
Total horizontal stress, kPa
100 200 300 400 500
¢ Total horizontal stress
t:. Pore water pressure
Hythe Beds
- - - - - -Sesf::fitlfrle -to -po-re water pressure data between 1.2 m and 11.6 m bgl
u = 8.6 z - 10.5
Best-fit line to total stress data aha = 20.6 z + 0.8
upper Atherfield Clay
lower Atherfield Clay
¢ ¢ ¢
Underdrainage Weald Clay
Wall toe
Figure 5-16: Stabilized readings of horizontal total stress and pore water pressure from all spade cells and piezometers, plotted against depth below original ground
level (before wall installation)
196
o Effective horizontal stress, kPa
100 200 300 400 500 O~~~~~~~~~~~~~~~~~
1
2
3
4
5
E 6 a; 7 ~ 8 -g 9
e 10 C) 11 ~ .2 12 Q)
.c 13 .c .. g. 14 C 15
16
17
18
19 20 21
o Effective stress
Hythe Beds
. Best-fit line to in situ effective
/ ·.ODD
o
Wall toe
stress data 0\0 = 15.3 (z - 1.2) + 10.9
upper Atherfield Clay
·· ... Iower Atherfield Clay
o 0 ".
~Weald Clay ..... ~
Figure 5-17: The profile of effective horizontal stress a' ho with depth (obtained by subtracting the measured pore pressure from the total horizontal stress at each
location)
197
CIS C. ~
150
i ;:100
e c. .. ~ 50
~ o c.
spade cell D.1 no. and /\ ,~, ,G,,Q,, , ..... 1;.... , ... f .... ,.Q. ,1-:1.. , ..... 1.. ... depth b.g.l~ : . .
P5-152!P'~: :: :~. : :::: : : :: :~~ 11..:jj a""': f'.+.....: Y·.: : .:.. ::: \ P5 - .j.UIEfE\""\·->~-----"':·- -;--:: --~ ---- :----~:.:--+~~-:---------""P11 P4 11 3 : . : :: :~:---- \ ---: ::: : :
- . Ol :: :: : : : : ::: :: . P4 P3-8.3m : .:: :..:: : : : ::.: :: : P3
"'-'---_." ~--.: : :'1 : : : : '.-. -.. -.. ~:.. ::: ~"""P12 12 153 . . ., . :- . .. . . ......... .. . ................ . ~: : :: : :: .:-< : ::.....: :: ~ ... ~ .. :: : P2
P2-5.3m : : :: ::: l:: .... : : :,:: :: ' P1 ---r:-:; :~', . -:-:-, ~ : P1-3.3m ::: :: ... :... ..
O+-~~-r~~~~~~~~~~~~~~~-r~~~~~~~~
150 CIS c. ~
as' .. ;:100 I/)
~ c. .. CI)
50 ... ; CI) .. 0 c.
0
150 CIS C. ~
i =100 I/) I/)
~ c.
43 50 57 64 71 78 Time in days
(a) 1-275 m from the wall
spade cell A )? ,G p~1 E F G H I no. and ' .... , , ... __ ...... ""--"'-''-'' i'- , ...........
, .. depth b.g.l: : ' .. , .. · .. ~:: ' .. , ..
' .. · .. ' .. ' .. · ..
P17-15.3rr1 ' .. , .. , ..
.. P16-8.3m 17 - .. 16 :
: P15-5.3m .. 15
"
43 50 57 64 71 78 Time in days
(b) 2-375 m from the wall
spade cell no. and ,.A.,.e D91
E ,'0;; i ...•.....• I ............ C
i"'
depth :: I •
~::
43 50 57 64 71 78 Time in days
(c) 3-475 m from the wall
Figure 5-18: Piezometer readings over the period of wall installation
198
period of wall installation
P1-3.3m :
beginning of main construction
~P5
: P4 ~P11
; P12 ~P3 ~P2
~P1 0~~4-~~~~~~~~~~-r~~~~~~~~~~~~~~~
ns 150 a.. ~
a) ... ;100 III ! c. ... CI) ... 50 ; CI) ... 0 a.. 0
... CI)
50 ... ; ! 0 a.. 0
4 32 60 88 116 144 172 200 228 256 284 312 340 368
4
4
period of wall installation
P16-8.3ri.1
P15-5.3m
32 60 88
period of wall installation
Time in days
(a) 1·275 m from the wall beginning of main
construction
~P17
~P16
~~P15
116 144 172 200 228 256 284 312 340 368 Time in days
(b) 2·375 m from the wall beginning of main
construction
~~~~;::;:::;.nh~~ru:::JI!!~~:::=::::::~;;:::::::. = P10
P8-8.3m; P7-5.3m; P6-3.3
32 60
: P13
~P8 ~P7
~P6
88 116 144 172 200 228 256 284 312 340 368 Time in days
(c) 3·475 m from the wall
Figure 5-19: Pore water pressures measured before, during and 10 months wall installation
199
450
400
~ 350 .lII::
~ 300 ~ ... II) 250 S c 2 200 'i: o J: 150 S ~ 100
50
6 7 8 9 10 -------------------------------.. -------.. -------.. -------e-------e-·
1100 15 16 ------------------------------.. ----------------e--------------------
1100 1 2 3 4 5 --------------------------e-------e-------e------... ------... ------
1800
@®®©@®@®®@@©®®0©®®0®® 1800 11 12
------------------------------.. ----------------.. ----------------------1100 __________________________________________________________________ ~---- • Spade cell
11 00 _______________________________________ ~--------------_________________ Dimensions in mm
spade cell A o. and :"':
depth b.g.l~ :
B c
8.1.?:~! .~:~~. ft· .~ ... j .......... : .. :: . " · ... I I " I :' , , I I , ,\
001 E F G H -_.--._-,". -----_ .. _- ... . , I •• , , , , II • , , • II • , . • II • , . • II • , , , .. , , , , ... , . • tl • , , · , .. , , · ,. , , , • t •• , , , ,. , . . I '" I.
85
: : :: : :r' -:' A::: . . . ..:: ., , 84-11.3m, , " , " ''', , , , .. ,' " .' 812 811 11 6 N.'
" , " ,," . ' ................... " .. ,,' '.' .. :' ...... . - . m ~, 'M'::: ,: .. ' : :: :~ ... : .. !' .. : ...•... :
------..-- ., ,. " , .. ~ , "." " ,
: J-~-\i-----~ -~- ; .. ;..... ! -f:-:! ~ : -r-- 84 83-8.3m, (. " " ~I-""----\ '-----'- ...... -.,..~" '--- 811
HJ' : :: : : : 1. : ~:------: :::: ~-:-----: .
81 33 ::: '~' , :: : : : :::: :: : 83 ---' _m : : : : : : " : : : ~ : 81
8=-2--=-5.-=-3m- : G f ~ ~~; . =4+-fF~ : :: 82 I • • • ". I, ,
I , , • ". I, ,
, , . ... '" ... , , . , .. , , .. • , , , .. I '. I • , • , .. I " I , .. , .. , ., ,
O+-.--r~~'-r'~·~'._-.~~~~,--r~~--~.-_r~"T'_,·~'~·_.~~._._~
43 50 57 64 71 78 Time in days
(a) 1,275 m from the wall
spade cell A B 450 o. and :"':
C 001 E F G H ----_ .. _.-_. _." .. __ .". __ .-- -._ .. -- .. _--.
depth b.g.l.
400 817-15. 3m-' -v-"""""'-""-"""""IJ'---':Il':---r---_, - ________ -i--~........;;.-v---:-""':-~ 817
~ 350 .lII::
~ 300 ~ ... II) 250 S c 2200 'i: o J: 150 S ~ 100
50
"
=816 : 815
816-8.3m
=~' [ffi::,' •• :. • •
815-5.3m. ; • ..;...' ___ : : : , . , ,. , I , , " " ,,' ,
"
O+-.--.~~--~~.-~-r~'+' ~--~~._~~~~--~+_.__r~~~
43 50 57 64 71 78 Time in days
(b) 2,375 m from the wall
200
450
400
~ 350 .:.::
~300 e -CI) 250 S c 2 200 'i: o J: 150 S ~ 100
50
6 7 8 9 10 ------------------------------.-------.-------.-------.-------.-.
1100 15 16 ------------------------------.----------------.--------------------
1100 1 2 3 4 5 -------------------------... ------... ------... ------... ------+------
11 12 ------------------------------.----------------.----------------------
11 00 __________________________________________________________________ ~---- • Spade cell
1100 13 Dimensions in mm ---------------------------------------.-------------------------------
spade cell A B C D D1 E F ,;~ H
o. and ;' ; .. .. . .. .. ; ;' .. " ..
depth b.g.l: : :
: : :
: : : :
: : : : :
: : : : :
: : :
: . . .. . '" , , ..., , . S13-11 6rrj : : : : : : :. : : : :::: : : S9~13'~;';' :-·:~j···i··,li .. l ......... d~~ ...... ~ .. ~ : :: .......... S13 . : ': :: : ~ : t : V: .-: '- ,,1:;"'; .. :" .:...... --
8-83m : : :: : : : :: : : : :::: : : S9 • -<----..,;" '\~i:: ' . """
S7-5.3m . . : ~ : r.---:- v.- ,~~ ., ,. S8
;::;;;::::;;:=~ ~, :,' :, :,:, :, :: =S7 S6-3.3m . , . " . ~ S6
, , I ., ,
, I I " I , , , II ,
, .... , , .... , , , I •• ,
I , , II ,
I • , II , ..... , • I , .. , ..
O+-~-.~~~~~_.~~~+_.__.~~,_~.__r~~~~.__r~_.~
43 50 57 64 71 78 Time in days
(c) 3·475 m from the wall
Figure 5-20: Total horizontal stress measurements taken during the period of wall installation
Any SP~]d~e~ r~, _._.-.-. ·_·-e-e·ee·-
Distance alo.ng wall,. I I I I number of pile spacings 0
2 3
--~r-~----~------~~~~cr
~crr ~cre
Figure 5-21: Pile installation sequence for the elastic analysis and Mohr circle showing calculation of correction for stress change measured on spade cell
201
0.5
.5 0.4 -In In
0.3 e In In .... CI) In a.. c .... ._ In 0.2
C =:s o:t::
:;::: II) (.) 0.1 :::l ~ CI) 0 0::
-0.1
0.5
.5 0.4 -In ~ In 0.3 !:; ~ In!:; C In 0.2 c,2 o '-:;::: II) 0.1 :::l
x
•
0
• •
•
o S1
• S2 x S3
• S4 • S5 + S11 x S12
--- average -- elastic solution
- ------;----x 3 4 5 6 t 8 9 10 11 12 Distance along wall (in pile spacings)
• S15 • S16 • S17
--- average --elastic solution
~ ~------~ 0~~~~~~~-4--~---+--~--~_r-_~ __ ~_~~~~~--'---' • o 1 2 3 4 567 8 9 10 11 12
-0.1 Distance along wall (in pile spacings)
0.5
.5 0.4 • S6 -• S7 • S8 x S13
--- average --elastic solution
o 1 234 5 6 7 8 9 10 11 12 -0.1 Distance along wall (in pile spacings)
Figure 5-22: Measured reduction in total horizontal stress normalised with respect to the in situ total horizontal stress (showing prediction from elastic analysis)
202
- 100 c 0
90 :;:; I '" measured I .!! Ci 80 -I/) .5 Ci~
70 ~ 0 ~
60 0 I/) -I/) Calculated maximum Q) ~
50 extent of plastic zone =-'C I/)
I/),a 40 I/) .-
Q) I/)
b c I/) .- 30 .5 c 20 0
:;:; CJ
10 = .. ~ 'C
'" Q) -.- ... -.- .. ~.- ..... r::t: 0 0 1 2 3 4
Distance from edge of pile, m
Figure 5-23: Reduction in total horizontal stress due to installation of pile nearest to spade cell only with distance from the wall compared with the elastic prediction
203
0
0
1
2
3
4
5
E 6
a; 7
~ 8 'C 9 c ::s
10 e tn 11 := .2 12 CI)
.Q 13
.s::. -g. 14 c 15
16
17
18
19
20
21
Total horizontal stress, kPa
100 200 300 400 500
¢ Before pile installation
• After pile installation
Hythe Beds
• ¢ Best-fit line to O"ha measurements ~ O"ha = 20.6 z + 0.8
Wall toe
Best-fit line to O"h measurements 1.275 m from wall after pile
•
installation O"h = 16.7 z + 7.4
upper Atherfield Clay
lower Atherfield Clay
Weald Clay
Figure 5-24: Total horizontal stresses measured by all spade cells before wall installation and by those 1.275 m from the edge of the wall after wall installation
204
0 0 1 2 3 4 5
E 6
Q; 7 > 8 .!!! "C 9 c e 10 CO) 11 ~ .2 12 CI)
.c 13 J:: ... g. 14 c 15
16 17 18 19 20 21
,
1> I
20
, , , ,
I I
I I
, , , I
I I
?
40 60 80 100
- Reduction from linear bestfit approximations
- ~- Reduction in total stress based on measurements
ythe Beds
upper Atherfield Clay ---~--------------------------------
I I
I I ~
I I
I
I
lower Atherfield Clay
Weald Clay
Wall toe
Figure 5-25: Change in total horizontal stress
205
0
1
2
3
4
5
(j) 6 > 7 .Sl! "0 8 c :::s 9 e C) 10 ~ .2 11 CI)
.c 12 E S£ 13 -g. 14 Q 15
16
17
18
19
20
21
0
Effective horizontal stress, kPa
100 200 300 400 500
a Before pile installation I', "
. \.. \. • After pile installation ' .. .... \. .'~ 0 Hythe Beds
" " -..::.- - ------------- - - - -------- - - --Best-fit line to cr'ho measurements
before pile installation cr'ho = 15.3(z -1.2) +10.9
Best-fit line to crh'
measurements 1.275 m from the wall after pile installation
cr'h = 11.6 (z -1.2) + 5.5
upper Atherfield Clay
.... lower Atherfield Clay '.
-----------~----~--------~----------o ll') Weald Clay
Wall toe
Figure 5-26: Effective horizontal stresses measured by all spade cells before wall installation and by those 1.275 m from the edge of the wall after wall installation
206
0 0 1 2 3 4 5
E 6
4i 7 > 8 ~
"C 9 c = 10 e C) 11 ~ ..2 12 Q)
,g 13 .c -g- 14 Q 15
16 17 18 19 20 21
20
, ,
40 60 80 100
- reductionfrom linear best-fit approximations
-i3- Reduction in effective stress based on measurements
Hythe Beds ------,-- --------------------------, ,
I _______ L
I I
I
rf
I I
I I
I
0, " ,
" " "
" " " " " "
Wall toe
"
"
" " " " " "
.P
upper Atherfield Clay
lower Atherfield Clay
Weald Clay
Figure 5-27: Change in effective horizontal stress
207
450 period of pile installation
1--1
Beginning of main construction period
400 85-15.3~ : 1 1 1 1
ns ~350
:2300 ~ .... ~250 S 5200 N 'i:
,g 150 C; 0100 I-
50
812-15.3m
84-11.3m
811-11.6m
~--~~----~-------------: 85 --------....--1-1 -1 1 1 1 1 1
1 812 -~--------~ ~
1
~J~t1-4 -~-------.; 811
1
:= ::::=::::: :~ 2 3
~-S-1 :-s2 O+.~~~r+~~~~~~+O~~~.+~~~~~~40~~~~~~
4
450
400 ns D..350 ..:.:::
:2300 ~ .... ~250 S 5200 N 'i:
,g150 ns 0100 I-
50
0
4
32 60 88 116 144 172 200 228 256 284 312 340 368
period of pile installation
1--1 1
1 1 1 1 1 1 1 1 1 1 1 1
S16-8.3m 1
Time in days
(a) 1·275 m from the wall
~ 15-5~:::'=:======: == I. 1
Beginning of main construction period
1 1
: 817 ----------<""1" ~
32 60 88 116 144 172 200 228 256 284 312 340 368 Time in days
(b) 2·375 m from the wall
208
450
400
CIS D..350 ~
~300 Q) ... +I
~250 JS 5200 N ';: ,g150
CIS cHoo I-
50
0
4
period of pile installation
1----.1 I I 1 1 I I 1 1 1 I 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
S13-11.6 : 1
--------------~--~----------
S7-5.3ml 1 1
S6-6.~:::· ::::::::::::::::::::::::::::::-:::.:::.:::::=:::::::::;:::;::::::::::~:;::::::::
Beginning of main construction period
1 I I 1 I 1 I 1 1 1 1 1 1 1 1 1 1
~ S13 -:---v-- _~ ~
S9 i S8 ~-
1 S7 ~---
1 -so 1 1
1
32 60 88 116 144 172 200 228 256 284 312 340 368 Time in days
(c) 3·475 m from the wall
Figure 5-28: Total horizontal stress measured before, during and 10 months after wall installation
209
400
350
50
.0 II ro II
- II Cf) ...... 11 Q) (/)11 (/) CII ro 011 coo
o +-~~-+~-.'-~r-r,~-r~~+-r.~-+-.,-.-~~~-r~.-~r.~-.~ 410 438 466 494 522 550 578 606 634 662
Time in days
(a)
(/) C 350 I CII C I I tl I 1091 I II
I .QII.Qtld ~~ I mltl II
I t)11 t)rold 1=1 rol'O II I ::J II ::Jii)Iii1 I rol ...... 1 C II ro
EI L..I Q.\ 1 ...... 1 (/)1 Q) 300 L..II L.. I 5 I ~INlN II > rolC ii) II ii)T"" 1"-; T""I..-I II 0 Q)lo Cll CQ)I~
Q)I ~ :p I -I Q)I Q) 511 ro E CO I.- 011 o (/)1 ~ ro ('1')1 (/)1 (/) .0 ._11 > Q)
It) ..... 1 0 0:: 0 ~:1l = 1-1 ro l ro ~ gl E 0:::
CIS 250 O'll ::J ..r::::1 J9 '01..r::::1..r:::: Il. .!: IlJ NII..;;ta..IO,J
a..:111 ~ c: a..:a.. Cf) lJ I Q) ('I')
~ 0.1 (/) a.. II a.. .1 I Q) ~: 0::: I-o.lC _II -ul (,) <ild rol UIU (/)
N ~200 rolO T""II ('I') XI ><l XI ><lIT"" NI XIX ro 01 T"" 010 a.. II a..WIW WIW l- I-! WIW co 0 I l- I-
~ I II I I I I I I I I/) I II I I I I I I I/) I II I I I I I I CI) I II I I I I I ~ 150 I II I I I I I
I II I I I I I ... I II I I I I I CI) ... I II I I I I I
; 100 P5-f'"V"1~r~ I I I I I I I
... ~ I e P4--I P5 0 I II
Il. 50 P3~ ------------ P4 I II
P2~ P3 0
P1 I II P2 1
4 0 438 466 494 522 550 578 606 634 662 -50
Time in days
(b)
Figure 5-29: Total pressure and pore water pressure measured 1·275 m from the back of the wall during the construction period
210
400 (/) C C C t 0 0 .Q t d CIl ~t
I 1:511 - CIlO iiil -gIl 1= I CIlI"O -'II 1-350 E:
::J II g enen ~I Q)II I~ I iii I ~ (/)11 ICIl l:; II !:; I I I IIC :~:N:N 511 I>
CIlIC (/)11 (/) '<"'j"-I "-1"-110 0 11 - 1 0 Q)IO CII C QlQl Q)I Q)II~ 1- I Q)I Q) II CIl IE ca OJ I+:;
011 0 ~~ ~I~II= I~I(/)I(/) .011 > IQ) c.. 300 ell (.) Oil 0 ..el..ell CIl I I CIlI CIl CIlIIO 10::: ~ CI2 Nil..,. a.;a.; 0....
10....
11 iii
1"0 l..el..e USII E I('t')
1$ '0.. I iii 0...._:: 0...._ ~~
I IIC IClo....lo.... Q)II~ :1-
~250 o.lC r,jI r,jIl- :~: ~:~ (/)11 CIllO ..-11 ('t') Xl Xl 1..- CIlII..- I -
IN ... 0:0 0.... 11 0.... WIW::I- :I-:W:W OJ:: I- II-.... II til II I II I I I II I
S200 II I II I I I II I II I II I I I II I
C II I II I I I II I 0 II I II I I I II I N II I II I I I II I
'§ 150 I II I II I I I II I
S1~ I II I I I II I .c II I I I I
S I II II I I I I I II I I I I I
0100 I II I I I- S1~-
I S16
50 I II I II S15 I II I II I II
0 410 438 466 494 522 550 578 606 634
Time in days
(a)
350 (/)
gO C 0 I :t .• 1 I c' I
0 0
I . :2 ~ I . CIlI II I d t l I I
I 10.-1"011 1._1 I "0 I I I (.)1 (.) 1.8 lGl CII I rol ~I C I I-
E: ::J I ::J rn. I (/) ,-I Q)II C I =1 (/)1 Q) I ICIl
300 .!:J I l:; ..-I I I> 1..- ..-1..-11 0 I CIlI N I N 1 0 CIl I C Ull (/) I I I 11._ I iiil I C 1-Q)I 0 Cil C ~ I Q) Q)I Q)I I ro I ci Q)I Q) 0 ICIl IE OJ I +:;
8:8~ I(/) (/)1(/)11_1_1 (/)1 (/) .0
1:5 I> IQ)
O'J(.) I CIl CIlI CIlII ro I ('t')1 CIlI CIl CIl 10
10::: ca 250 cI2 l..e ..el ..ell _ I 1-1 ..el ..e US ::J IE I('t') c.. ~: ~ 0..; 0.... '-
.~"@ 10.... 0....10....11 (/) I 10....1 - IQ) ~
Icj r,jIr,jIlEI~1 r,jI Q) (/)
10::: :1-I j cj (/) C e200 ~I cvi ~ I X Xl Xii ..- I N I Xl CIl 0 1..- I -CIlI
0 X IN 0 10 ~:o.... :w W:w:: 1-: 1-: w: W OJ 0 :1- II-:::s til I II I I I II I I I I I til I II I I I II I I I I I CI) I II I I I I I I I I I
5.150 I II I I I I I I I I II I I I I I I I ... I II I I I I I I I CI) I II I I I I I I I ....
; 100 I II I I I I I I I I II I I I I I I I I II I I I I I I I
CI) I II I I I I I I I ... P16 I II I I I I I I I 0 50 ~ I I I I I I c.. I II I I I I I
P15 I II I I I I I 1 ________ II P16 I II I I
0 4 0 438 466 494 522 550 578 606 63415
-50
Time in days
(b)
Figure 5-30: Total pressure and pore water pressure measured 2·375 m from the
back of the wall during the construction period
662
662
211
400
350
50
C t "0 ot"O 2 C:;:; 2 C en O).!Q en 0)
EI ...... 11...... c-rol~ enllen...-J.,-l..-I...-JloI2Ir...lN 0) '"' I ~ I 11._ I en I '"1
10) CIIC <U ~III~ICI <U 0) co I _ 0 II 0 ~ v, I I W I I ~ en 0)0 OliO ~I Irol~1 ~ cI2 NII-q- o..;n' 0.. 1 0..;1 t)11-1n:0.. 'gj ~ 0.. : : 0.. '"'1" I I C I I '"'"1
rolo ......... 11(1)~I~ ~:~::::~:~~ 0:0 0..::0.. Lij..,. ill :t:y: 1-:1-: t.Y ill
I ,.11 I I II I I
: S10:: : ::::: I II I I II I I I II I I II I I
S9 I II I I II I I ~~ .1.",,-,11 I III I I
I II I I II I I I II I I II I I I II I I II I I I II I I II I I
S8 ___ ....r,..,..11 1:1:1 : ::::: ~:~ II1I1 S7 --'""'- .~ll- '-/"~- II I I ~- I ------- --rr---- I I I
II
§ "ro .0 ._11 > roullo
- :::JIIE U) 'pliO)
~ ~::o:: ro 0 11 ..-co 0::1-
II II II I
I I I I I I I I I I I I
ro I> 1
0 IE 10) 10:: 1("1)
:1-
IN
:1-I I I I I I I I I I I I I I I I I II S6
~~~~~~~~~:~: --~~~~~:saS7 S6~
I II I II I II II
O+-,,-.~~-.~.-~~,L~-+,L~r+-..-~~~~r.-.,-r.-,~
410 438 466 494 522 550 578 606 634
350
300
~ 250 ~
2f 200 :I III III Q) c.. 150 ... ! ; 100
e £. 50
c.. § . ; I .91 :;:;tl d. : ~: g~:f1
EI Cil.... I VI rol en I t)"-I"<"i 0)1"0 Cli C 0)1 ill .01 0) QlI 0 enl iii ....l U a. 1 0 rol ro gl:::J II -q- .cI..l:J
._1 .... NI 0.. 0..10l 01- D..il .1 l r-o. enc 0 " ..... ~I (1) I....., rol 0 ..-jl 0.. illXI X 01 0 D..il I ill
I II I I I II I I I II I I I II I I I II I I I II I I I II I I I II I I
Time in days
(a)
. c .. I II 1011:1 1"011 1:;:;1 CUI "0 I CII I rol ~ C I 0)11 C I =1 v~ 0)
"-1..-IIOI2INN I II:;:; I enl aj
~I ~II.!Q I EI in ~ rol roll ro I ("1)1 CUI ro .cl.cl l _ II-I .0 .c 0..1 OJI en I 10..10..
.1 .II CI~I I 01 011 - I I d cj XI XII ..- I NI ><l X illilllll-ll-lWill
II I I II I I II I I II I I II I I II I I II I I II I I II I I P10 I II I I
___ ~:~ .r--",--I ~--- II I I I I I
I
II II II II
c"-0" ro .0 --II > ro UII 0E
- :::JII U) .PliO)
~ ~::o:: ro 011"-1-co Oil
II II
I 1-lro I> 10 IE 10)
:0:: 1("1) III • IN III I I I I I I I I I I I P9U"'1I.Jt r II
, I II ~ ____ --":_~I ---~-P1 0 P~~ :"''W ~ .. - - 159:
662
P I II I :
O~p~~~~~~~--~~~~~~~~~~±;~I ~~~=E~~~~;e~~~ 4 0
-50 438 466 494 522 550 578 606 662
Time in days
(b)
Figure 5-31: Total pressure and pore water pressure measured 3·475 m from the back of the wall during the construction period
212
400
350
50
ro >
S1~ ~ Exc,PI~ .Qll ro> I~ E: ~t:l 0. I:: ~ I ..0 0110 10) ml e .II. ro a I II I I I c75 ::JII E 10:: 1D:2 Cii:: Cii 1111 : 53:: e~ I '!:;II 0) 1«) oj g 5115"""""" IT""II.Q :u;:\ : 3l ~::o:: :1-_ e I '- 011 0 ..J..J I II ..... I I I ro 011 T"" IN ·-1..... II ±-1±-1 l..cll~ lEI I ID 0111- II- S17 g; ~ Nil <;t Q..jQ..j 100001Iro 1«)1 I :: ~ (010 0...110... 99 I .IICiiII-I :~ ~ 0:0 T""1:C'"it.Ljt.Lj :~::E:~: I II I
I 0...110... ~W::T"":N: : ::: S12~ ~ I I 1"1.111-11-1 I II I
I II I I (/)1 II I II I I II I I tl II: :::
S13 ,.! ~NI:~::: II I S12 ~I II I I (/)1 II II >...A ..... """""''W-\O;,\o S11~n ~III I II I I I II
I II I T"" I II I II I 0)1 II I II I (/)1 II I II I rol II I II I oCl II I II I 0...1 II I II I .1 II I II I 01 II I II I XI II I II I WI II
II II
"'rt\\I\~~#WII"'IIS13 .". S11
O+-~ro-+~-r,-~ro~~-r~~+-r.~-r-.,-~~-.~-r,-~~r.-,~
410 438 466 494 522 550
300
250
CIS 200
~ ~ 150 ~
~ Q)
Q. 100 ... Q) -; 50
~ o
Time in days
(a)
(/)
c·· e
~~ 15 II i 5i ti I 0110 I ~II:;:; ID "011 I .-1 J!ll "0 I 011 ° ell I rol Ie
EI 211 2 ~~ 1-1 0)11 I =1 (/)1 0)
ro:e +'II ..... ...-1..-1 ...-I T""II 5 I rol NI N
0) 0 ~:~ U I 0)11 :p I Ciil 0)1 0)
ID L- 0110 !(/)::~:E: (/):(/) I ..... OliO 0i10 ~II ro I «)1 ~I ~ el2 Nil <;t a.; 0..." Cii I 1-10...10... ·c..ICii 0...:: 0... II e I I I o.le
~~ ~ 011 - I ~I cil ci rolO ~I «)- Xii T"" I NI Xl X
0:0 0...:: 0... w:: I- : 1-1 w: W I II I I II I I I II I I II I I I II I I II I I I II I I II I I I II I I II I I
P17 I II I I I II I I ~~~II I I
P13~N I:: I I I I
P12------r ::: I ::: I I I I
I II I I I II I I II I I I II I
578 606 634 662
II i II I II l-II l ro
I> II 10
5 II ro IE ..0
._11 > 10) 011 0 ro ::JII E 10:: (ij .!:; II 0) 1«) 0) (/) II 0:: :1-(/) ell ro 0 1 T"" IN ID 0 I- II-
~ 0 +-~,,-+L,-.,-~ro~L+~~~~~Lo-r~~~~-,~-r,-~~-,-,~
4 0 -50
-100
438 466 494 662
P12 P17
Time in days
(b)
Figure 5-32: Total horizontal stress and pore water pressure measured in front of the wall during the construction period
213
-1000 o
Bending moment, kNm -500 0 500
~ Calculated 2 bending moment
0 PileY
4 " Pile X
IZ1
6
8
10
12
14
16 ~
-t-' c::::
18 Q)
E E
0 E
20 .c 0); - c:::: Co :so:: CD ()
C C\l L..
22 0
1000
Figure 5-33: Measured bending moments and bending moment calculated from horizontal soil stresses within 10% of those measured
214
Horizontal stress, kPa
800 600 400 200 o
2
4
6
8
10
12
14
16
18
20
22
+ Measured horizontal soil stress
-- --- Estimated horizontal soil stress •
+:
~:
E .s:: -c.. Q)
C
o 200 400 600 800
RC prop
Excavation level
.,
+ •
Figure 5-34: Measured and estimated total horizontal stresses
215
6 LONG TERM MONITORING
6-1 Introduction
In this chapter the long-term measurements of total horizontal stress and pore water
pressure in the soil around the wall, and the reinforced concrete prop loads and pile
bending moments in the structure, are presented and discussed.
6-2 Total horizontal stress and pore water pressure measurements
Figures 6-1 to 6-6 show the total horizontal stresses and pore water pressures measured
over the period from before pile installation to late 2005 by the spade cells 1,275,2'375
and 3·475 m behind the wall respectively. Figures 6-7 and 6-8 show the total horizontal
stresses and pore water pressures measured in front of the retaining wall over the same
period. These figures show that installation of the contiguous piled retaining wall and
excavation of the cutting caused the main significant changes in total horizontal stress and
pore water pressure. Since construction of the cutting was completed the total stress and
216
pore water pressure measurements have generally remained constant from year to year,
although a few spade cells have recorded small overall reductions.
Figures 6-1 to 6-8 show that in the years following construction of the cutting the total
stress measurements, and to a smaller extent the pore water pressure measurements,
experience seasonal variation with temperature, particularly those close to ground level
behind the wall and in front of the wall. The recorded loads are smallest in winter and
higher in summer for the spade cells 1·275 m behind the wall, with the highest readings
occurring between approximately July and October. The cells 2·375 m and 3·475 m behind
the wall lag behind this slightly, with the highest readings occurring between
approximately September and November. In front of the wall, the readings from the
shallowest spade cells (SII and S13) are highest between approximately September and
November and from the deeper cells between October and February.
The total stress cells appear to suffer from noise, probably due to temperature effects (the
deepest spade cells exhibit less noise). The pore water pressure transducers appear to be
less affected than the total stress transducers.
There have been a number of other significant changes worth noting. The readings from
total stress cell 4 appear to have shifted down by about 10 kPa over the period between
approximately Days 1630 to 1966 (Figure 6-1). Total stress cell 8 appears to have
malfunctioned (Figure 6-5) and total stress cell 12 performs unusually below about 160
kPa.
6-2-1 Installation of storm drain
Figures 6-1 to 6-6 show that before installation of the storm drain behind the instrumented
wall (see Section 3-5-6 and Figure 3-48) the pore water pressures measured in gauges P 1-
P4, P15-16 and P6-8 increased. This was during late October and early November and was
therefore probably due to seasonal rainfall. Installation of the storm drain generally caused
a fall in pore water pressure. Ever since the storm drain was installed the pore water
pressures have fluctuated very little by comparison. The total stress measurements in the
same gauges also increased over the period before the storm drain was installed, although
generally to a smaller degree, apart from the total horizontal stress measured in spade cell
1 which, if anything, dropped slightly over this period.
217
Over the period of storm drain installation, spade cell (SC) 1, 3·3 m below ground level
and therefore above the bottom of the storm drain trench, recorded a reduction in total
stress of about 15 kPa on excavation of the trench, and on backfilling the stress retmned to
its pre-trench excavation level. SC6, at the same depth as SC 1 but much closer to the
storm drain trench, recorded a reduction in total stress of approximately 50 kPa due to
trench excavation, recovering to 20 kPa. These changes can be seen more closely in
Figures 6-9, 6-10 and 6-11, and are essentially similar to the type of change exhibited as a
result of pile excavation.
6-3 Reinforced concrete prop loads
Figure 6-12 shows the reinforced concrete (RC) prop loads, calculated assuming the
Young's modulus of concrete is constant at 25 MPa, measured from before excavation
within the cutting to late 2005. The average temperature measured in the gauges is also
shown. The figure shows the load in the props increasing by between approximately 200
and 1000 kN each year.
Figure 6-13 shows the RC prop loads adjusted for the effects of creep (after Day 607) as
described in Section 4-4-3. The minimum load recorded each year is constant (in
approximately March to June), and the maximum load (recorded in October each year) is
reducing, showing that the seasonal variation in load is reducing each year.
As more data is collected in the long-term it should be possible to improve the correction
for the effects of creep.
6-4 Pile bending moments
Figures 6-14 to 6-17 show the pile bending moments measured over the period from
before excavation within the cutting to late 2005 by the gauges in Pile Y and Pile X
respectively. The buried gauges exhibit generally constant measurements with time but the
others vary significantly with temperature. Similar bending moments are exhibited in
gauges 15-24 in both piles, except in Pile Y gauges 21&22 and in Pile X 15&16 (and to
some extent 17&18) are higher, because the section is cracked at these locations.
218
6-5 Conclusions
The long-term spade cell measurements are showing generally constant total horizontal
stresses and pore water pressures over the years following construction of the cutting, and
in a few cases overall reductions being recorded. There are some seasonal and daily
variations in the readings, occurring more in the shallower spade cells than the deeper
ones, which are probably due to temperature.
Correction for creep in the reinforced concrete props has produced prop loads which are
generally constant from year to year. These loads vary seasonally like the spade cell data,
and the seasonal variation is reducing from year to year.
The bending moment data are generally constant with time and the effect of cracking on
the pile section is clear in the long-term data.
219
tv tv o
ctS D.. ~
400
350
300
en 250
~ .-I/)
ctS 1: 200 o .~ ... o
.s::. ~ 150 {:.
S5
S4: :
S1
100 t S2
50
2000
Pile installation period
2001 2002 2003
.. Base slab poure
Storm drain installed
~'lJ~ l' ~V~L . . .
o I .' .' \ I I . ' . I I I -50 11 8 286 454 622 790 958 1126 1294
Time in days
2004
1462 1630 1798
2005
S5
1~.J S4
1966 2134
S1 S3 S2
2302
Figure 6-1: Long-term total horizontal stress measured in spade cells 1·275 m behind the wall
tv tv >-'
C1l Il.. ~
eli ... :::l I/) I/)
~ Q. ... Q) ..... C1l 3: Q) ... 0 Il..
300
250
200 , Excavation
period ]--: :1-- ---l: '---150 ] " I , , 1 : . I " Base slab poure
100
~ P ~ P5
50
I ~~~::t:~~~~~~~~~~~ P4 ~ P3
o P1 ~r:::::::::+::::::~::t~:::=::::~±:=::::::::::: P2
P1
-50
2000 2001 2002 2003 2004 2005 -1 00 I I I I
-50 11 8 286 454 622 790 958 11 26 1294 1462 1630 1798 1966 2134 2302
Time in days
Figure 6-2: Long-term pore water pressure measured in spade cells 1·275 m behind the wall
tv tv tv
I'll a. .lII::
350
300
250
Ii 200 1/1 ~ -1/1
I'll 'E 150 o .~ ~
o .s::::: n; 100 -{:.
50
2000 2001
E~cavation period
.-.----
2002 2003
, .. Base slab poure
: .. I Storm drlain installed
2004 2005
~~~~~~~~~~~~~~~~~~MW~~ S16
S15
o ~ I I I I I I
-,·0 18 286 4$4 622 79 958 1126 1294 1462 1630 1798 1966 2134 2302
-50
Time in days
Figure 6-3: Long-term total horizontal stress measured in spade cells 2·375 m behind the wall
N N w
ca c..
350
300
250
~ 200 ~ ::l til til Q) a. 150 ... Q) .... ca ~
~ 100 o c..
50
o
2000
Pile i~stallation perio
-----.
2001
Excavation period
.-.--
2002 2003
.. Base slab poure
: .. I Storm driain installed
-50 I I I I
-50 11 8 286 454 622 790 958 11 26 1294
Time in days
2004 2005
"""t~....-.r-r----------..~_ ............ ~-_ P16
~P1 5
1462 1630 1798 1966 2134 2302
Figure 6-4: Long-term pore water pressures measured in spade cells 2·375 m behind the wall
N N .j:>.
300 ,
1
2000 J 2001 2002 2003 2004
Pile i
250 t peri? , ---+; :~ ,,, .
S10
2001 S9 : : '
m t 1 . . ." : I Base slab poured
--:,,_L'\~~ ' 't o ••
D. ' , : \ . : • . Storm drain inslalled ~ 150 S8::
"'~' I ~ .•. Ifj , : :: ~ .. Ifj , , Q) ,
: ~J~ : ... . 1ii ~7 ' , , .. '
III 100 -I: 0 ' .. 1 ......-~.A. ~ .. , ...... N '':: 0
.c:: III 50 + " I ' , 1 : ~. _ .. --liv-.L. ~._~J. ....... ...IIA..I -0 I- "I
1 :
' ,
1'1.. 0
- 0 18 286 4 4 622 79 95 1798 1966
-50
-100
Time in days
Figure 6-5: Long-term total horizontal stress measured in spade cells 3·475 m behind the wall
2005
,LIL~ 89
. • S7
S6
2134 2302
S8
N N VI
ctI c..
300 2000 :2001 2002
250 + : : I Pile installation period ,
~ '.<--- I " .. Base slab poured 1 : : ~ ..
200
.ll' 150 I , , I ---. , ____
~ ::s
2003
~ : .. I Storm drain installed
2004 2005
~100 ~~':: : CI) , , , ,
.... P9 1 '" , ! P8 : ' ' ~~ : ~'"r'" ' '''''''' ' .. _- ~" 1" -~~" r" P10 '- 50 ' , , " r" , '" -" ... P9 o P7 ' . ~' , ,
~lp6~~l O ~~ " ....... oII!eAt ........ "... P8
" , , " ·"~P7
P6
~ : : I I : -50
-100 I I I ,', I I
-50 118 286 454 622 790 958 11 26 1294 1462 1630 1798 1966 2134 2302
Time in days Figure 6-6: Long-term pore water pressures measured in spade cells 3·475 m behind the wall
tv tv 0'\
'" c.. ~
400
350
300
III~ 250 III ~ -III '" 'E 200 o
.!:! ... o
.£:
~ 150
r=.
100
50
1h :2001
Excavation period
, , , ,
\ , , , ,
'r-' hi • I-~ I~n: : • ~~ 11 ~i
, ,
~~
o I i 'i' l I I I I I
-50 11 8 286 454 622 790
2002 2003 2004
958 11 26 1294 1462 1630 1798 1966 Time in days
Figure 6-7: Long-term total horizontal stress measured in all spade cells in front ofthe wall
2005
S17
~S12
S13
S11
2134 2302
N N -....l
ca C. ~
~ ::s til til ~ Co ... Q) .... ~
300 I
250 +
200
150
100
' ' I 2000
: : I Pile installation period
--;- :-----
Excavati
p~
.1
410,
:2001 2002 2003 2004 2005
,. Base slab poured
,-- :--t---Storm dr+in installed
~ 50 o r-"" P13 P11 c. t
I~
o 1 :': 1 I : l: j . ......,.,,.,..~ . ~~_ ~L _::::;;;;l_ ,- P1 2
P17
-50
-100 I 1'1 I I 1'1 I I
-50 118 286 454 622 790 958 1126 1294 1462 1630 1798 1966 2134 2302
Time in days Figure 6-8: Long-term pore water pressure measured in all spade cells in front of the wall
400
350 datalogger was
refurbished
~300 n: ~ ~ ______________________ /---__ --______ --v ~ ______ ~S=5~
~ 250 ~ Storm drain -tJj
,s200 I: o N
excavation began
S4
'§ 150 . ~~-~--
J:
ca '0100 I-
50~============~==~~~ ~ ~ : S2
O~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
689 696 703 710 717 724 731 738 745 752 759 766 773 780
Time in days
(a)
300
250
-50
:-Storm drain
data logger was ~ refurbished :
excavation began
-100~~~~~~~~~~~~~rrn~ho~~~rlo~oh~~~~~~
689 696 703 710 717 724 731 738 745 752 759 766 773 780
Time in days
(b)
Figure 6-9: Total horizontal stress and pore water pressure measured 1·275 m behind the wall over period of storm drain installation
228
300
250 data logger was :
CIS refurbished ~.' Storm drain ~ 200
j 150 J.-________ -----------rk installed 89 I/)
~ 100 l: o N
~ 50 t:=::::.==:::::=~~=====:::=:::=:::::::::::::::::::==~:::::::~=::':::::;~-:::- :::=-::::: S7
~ S6 o O+-------------------------------------------~--------~ I-
-50
-100~~rtT~~~~~~~~~~hn~~~rrn~n.~~~n+~.rrnT~
689 696 703 710 717 724 731 738 745 752 759 766 773 780
Time in days
(a)
300
250
~ 200 ~- Storm drain ~
cD 5 150 data logger was: excavation
refurbished ~ began I/) I/) Q)
Q. 100 J-___________ ~~--~n~ ~---P-10
P7 -50
-100~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
689 696 703 710 717 724 731 738 745 752 759 766 773 780
Time in days
(b)
Figure 6-10: Total horizontal stress and pore water pressure measured 3·475 m behind the wall over period of storm drain installation
229
300
250
ns c.. 200 .:.I::
If) If) Q) 150 ~ -If) ns 100 -c 0 N .~
50 0 ..c C; - 0 0 I-
-50
-1 00 760
S9 ,e e e e e e e e e e e e e e e e e e. e e e .... 8 e I B 8 Gee e e a e e e e; 1 G I Geeea e a e e, e II a e G e De e s 8 8888 e e ee e e e eo e •• e e a e e 8. a eo. I.ee. eta ea ... I. ell .......... u a U
761
Excavation of trench on one day
762 763
Time in days
Further excavation on next day
764 765
+ S7
766
Figure 6-11: Immediate response of spade cells nearest to excavation of storm drain trench
230
L{) (")
o (")
L{) N
o N o L{)
I
o T"""
I
o N
I
L{) N
I
o (")
I
L{) (")
I
~~~~~~~~~~~~~~~~~~~~~~~~~~G£G
o o L{) (") T"""
~ .. --·1il.~~ -_.
--~~.reo_ - ~ . . .~~;.:,-. ~~~ Il)~-::. __ o · --:-.~
o .---~---.~~,
N .-~§f . -:..;::;ta:-: .. :..-- _ . . ~.~ . . •.
-.:t o o N
o o L{) N T"""
o o L{) ...... T"""
o o L{) o ......
o o L{) (j)
.--;:;~~. ~c.i?~--
o o L{) CO
o 0 0 o 0 0 L{) L{) L{) t- CD L{)
(N)!) peol
o o L{) '<t
o o L{) (")
o o L{) N
o o L{) ......
o o L{)
~LGG
S~GG
6S~G
£O~G
LPOG ~66~
S£6~
6LB~
£GB~
L9L~
~~L~
SS9~
o o L{)
I
231
13500 l T 35 2001 2002 2003 2004 2005
12500 30
11500 25
10500 20
9500 ~IJ 15
8500 ~~ J .J II IIII 10 u
[500 pI ' ' 1~~ " , ~1W'" Inrl'V ~"'V r 0 .
Temperature ~ ::::I
-g6500 o 10 0
-5 ! -' 5500
Q)
-l- -1 0
~
4500 ~ Co~struction Period
3500 -15
2500 -20
1500 -25 P4
500 -30
-500 ~ I.{) ..- "- (\') 0> I.{) ..- "- (\') 0> I.{) ..- "- (\') 0> I.{) ..- "- (\') 0> I.{) ..- "- (\') 0> I.{) ..- "- (\') 0> I.{) ..- ~ -35 (\') 0> ~ 0 I.{) ..- "- N co (\') 0> I.{) 0 CD ..- "- (\') co ~ 0> I.{) ..- CD N "- (\') 0> ~ 0 I.{) ..- "-~ I.{) I.{) CD "- "- co co 0> 0> 0 o ..- N N (\') (\') ~ ~ I.{) I.{) CD "- "- co co 0> 0> o ..- ..- N N (\')
..- ..- ..- ..- ..- ..- ..- ..- ..- ..- ..- ..- ..- ..- ..- ..- N N N N N N
Time in days tv Figure 6-13: Long-term reinforced concrete prop loads corrected for the effects of creep w tv
N W W
1800
1600
1400
1200
E z
Pile Y - Gauges below level of formation/base
slab .
II: J :Construe on Period
1 I ...
~ 1000 .... c: Q)
E 0 800 E en c: "C 600 c: Q)
OJ
400
200
o 1-~ ~ 2001
-200 416 528 640 752 864
2002
976 1088 1200
RC prop
,. Temp prop
Base slab
• 13 & 14 • 11 & 12 • 9 & 10 • 7 & 8 • 5 &6 • 3 &4 • 1 & 2
~ 13&14
:-
r-~~&4 7&8
'- 5&6 2003 2004 2005
i I I ill Iii iii iii I I iii I I I
1312 1424 1536 1648 1760 1872 1984 2096 2208 2320
Time in days
Figure 6-14: Long-term bending moments in Pile Y - gauges 1-14
N w ~
1800
Pile Y - Gauges above
1600 j. level of formation/base slab
1400 I :Construction Period
1200
E z .lII:: 1000 ~ c: Q)
E 0 800 E Ol c:
"C 600 c: Q)
m
400
200
o 1- ~ 2001
-200 416 528 640 752 864
RC prop • 25 & 26 • 23 & 24 • 21 & 22
. Temp prop ____ __ • 19 & 20 • 17 & 18
: Base slab • 15 & 16
. - - -
~ 21&22
15&16 ~--..,...~~~~~~~W' 17&18
19&20
2002 2003 2004 2005
976 1088 1200 1312 1424 1536 1648 1760 1872 1984 2096 2208 2320
Time in days
Figure 6-15: Long-term bending moments in Pile Y - gauges 15-26
tv W Vl
E z
1800
1600
1400
1200 j I bonstruclion Period
Pile X - Gauges below level of formation/base slab
RC prop
Temp prop
Base slab
• 13 & 14 • 11 & 12 • 9 & 10 • 7 & 8
J.I:: 1000 • 5 & 6 ..s c: Q)
E 0 E C) c: '0 c: Q)
m
• 3&4 • 1&2
800
i VP'l ~~ , ,
600
~ ~==~~~:~~ 400
200
:tf o+ptt'~ : _ ~: --== ,V-~p, , ~------------------~----------------
: 2001 : 2002 : 2003 2004 2005 -200 , ',' "
7&8 1&2 5&6
416 528 640 752 864 976 1088 1200 1312 1424 1536 1648 1760 1872 1984 2096 2208 2320
Time in days
Figure 6-16: Long-term bending moments in Pile X - gauges 1-14
tv w 0\
1800
1600
1400
1200
E ~ 1000 ...:-c Q)
E 0 800 E Ol c :c 600 c Q)
III
400
200
0
-200
Construdion Period Pile X - Gauges above level of formation/base
slab
RC prop
• 25 & 26 • 23 & 24 • 21 & 22
:ITemp prop====== ~. 19 & 20
• 17 & 18 :1 Base slab ===:j. 15 & 16
~ 15&16
I
Time in days
Figure 6-17: Long-term bending moments in Pile X - gauges 15-26
7 CONCLUSIONS AND RECOMMENDATIONS
The fieldwork described in this thesis represents one of the most extensively monitored
embedded retaining wall case studies undertaken, particularly outside the vicinity of the
London Clay. Total horizontal soil stress and pore water pressures have been logged
continuously since one month prior to installation of the contiguous bored pile wall,
throughout construction of the propped cutting and into the long-term (6 years to date).
The effects of wall installation, excavation ofthe cutting and the possibility of the in situ
stresses being re-established in the long-term have been assessed. Measurement of the pile
bending moments and the permanent and temporary prop loads has enabled the wall to be
analysed and the overall long-term stress state to be determined.
Detailed conclusions have been drawn at the end of chapters 4, 5, and 6; more general
conclusions arising from this research are stated below and recommendations for further
work arising from this fieldwork are made.
237
7-1 Conclusions
• This study is a complete case record linking the wall behaviour to the change in
horizontal stress in the soil, both behind and in front of the wall.
• There was no reinstatement of the total horizontal stress in the soil after either wall
installation or excavation of the cutting.
• The work undertaken in order to evaluate the spade cell over-read due to
installation in stiff overconsolidated clay adds significantly to the previous data as
spade cells have not previously been used in the Atherfield and Weald clays, and
the performance of a spade cell under a known changing load has not previously
been measured.
• The process of installing an in situ embedded retaining wall in overconsolidated
clay deposits produces a very clear reduction in the effective horizontal stresses
and lateral earth pressure coefficients. The reductions between 15 and 50% were
measured and the reduction was not linear with depth. This is a very significant
result for walls embedded in overconsolidated clays as they are regularly designed
to accommodate unnecessarily high horizontal stresses under working conditions.
• Identification of concreting cracking and analysis ofthe effect this has had on the
bending moment profiles calculated from the inclinometer measurements has
explained the differences in bending moment plots found by two different methods
after cracking had occurred.
• Structural monitoring is regularly used in construction of large projects to
minimise construction costs and maximise safety. Inclinometer measurements are
regularly taken to monitor wall movements. The success of the calculation of
bending moments and prop loads at the CTRL will provide confidence that
structural monitoring can be used more extensively than at present.
• The work undertaken to separate the strain due to shrinkage, creep and applied
load in the reinforced concrete props has allowed prop loads to be estimated which
agree with the measured wall bending moments and total horizontal soil stresses by
means of a simple equilibrium calculation.
238
• There has been no long term increase in the bending moments, reinforced concrek
prop loads or horizontal soil stress.
• Although continuous monitoring is demanding, the benefits of collecting
continuous data using vibrating-wire gauges connected to a datalogging system are
numerous and must form the basis of any future fieldwork studies.
7-2 Recommendations for further work
This research has highlighted several areas of further work which will build on the
important conclusions made above. Suggestions for this work are made in the following
paragraphs.
• Development of a data management system format that assimilates construction
events with the collected instrument responses would be highly desirable.
• The properties of the Atherfield Clay are not well understood. Further studies to
help define its geotechnical parameters would be most welcome. In particular, the
effect of the shear surfaces and fissuring on the permeability and the pore water
pressure changes should be addressed.
• Concrete shrinkage and creep have been studied extensively in the past, however
understanding the effect these factors have on the measurement of prop loads usi ng
embedded strain gauges is obviously crucial. Distinguishing the strain due to load
from the shrinkage strain and creep strain proved difficult in this case, particularly
because, due to the construction events, the props began to take up load very soon
after the concrete was poured. Analysis of the data still being collected will allow a
better understanding of the shrinkage due to creep to be attained.
• Further work should be undertaken to investigate the over-reading exhibited by
spade cells installed in overconsolidated clays. The connection made between the
over-read and the undrained shear strength could be improved upon.
• Measurement of the movement of the south wall would have been very valuable,
helping to answer questions regarding the amount of load taken up by the props,
the movement of the whole wall, issues surrounding the sway exhibited by the
structure and the ground settlement behind the monitored wall.
239
• There is a general requirement for further fieldwork to improve our understanding
of retaining wall behaviour.
• Finally, and possibly most importantly, the data collected in this field study should
be used for input and comparison of results for finite element analyses, not least to
study the overall performance of the wall; the three-dimensional nature of the
bored pile installation process and to investigate the transfer of stress under the
wall in the wall installation process which produced the non-linear stress reduction
observed in this study.
240
Appendix A
Figure A-1: Wireline borehole sample 'catch' mechanism
Figure A-2: Wireline borehole rig
241
Wireline borehole logs
borehole 1 page 1
BH 1
University of Southampton boreholes at the CTRL July 2001
note: stratum boundaries cannot be identified from this 44.99mAOD
80852.76E due to poor recoveries for the top runs. The other borehole is more reliable.
of borehole 200mm dark brown firm sandy CLAY (topsoil/made ground)
400mm brown firm sandy CLAY with rootets (topsail/made ground)
orange firm sandy CLAY with rootlets (made ground)
sandstone with shells and small black speckles
3.7-3.75 white/yellow and black/orange sandstone with shells and small black speckles
firm yellow/grey mottled sandy CLAY with a few pieces of gravel
stiff greylbrown mottled CLAY with some small orange marks
stiff to very stiff yellowish grey sandy CLAY
yellow grey/grey transtion zone. Some peds of very stiff grey CLAY with some yellow colouring. Peds have shiny surface.
stiff to very stiff closely bedded grey sandy CLAY with some small peds of very stiff material, mainly stiff crumbly matrix. Some fissure plains are shiny.
o Z ::J o c::: C> W o « :E
en o W III W J:
!;: J:
o ...J W u:: c::: W)J:« I-...J «(j c::: W 0. 0. ::J
242
Appendix A - borehole 1 page 2
c: OJ
.><
OJ 19 OJ a: 13 ~~ oil
en - c: " g-o ::;
(t!
en
6.45
82
10.35
11.5
12.5
13.5
14.75
15.75
BH 1
University of Southampton boreholes at the CTRL July 2001
44.99mAOD
80852.76E
22462.84N
very sliff grey extremely closely bedded sandy CLAY. Brown colouring 10 some parts • may be slaining from mud flush
very sliff grey extremely closely bedded sandy CLAY. Brown colouring 10 some parts· may be slaining from mud flush. Some of this run is softened and muddy.
very sliff closely laminaled sandy CLAY. Occasional brown slaining. iron pyrile nodules? Fissures (aboul20mm 10 50mm apart) with shiny faces.
12.3rn - some small black sandy stones which crumble under strong hand pressure. shells.
material here is more sandy than above. Very small pockets of fine white sand.
very sliff laminaled sandy CLAY
lighl brown band of very sliff lighl brown CLAY. chocolate colour.
very sliff grey CLAY. plaslic. not crumbly.
becoming very sliff grey/brown mottled CLAY
very sliff brown CLAY. choclaley appearance. Very closely fissured, moslly horizontally. but some in other directions. Some rare small hard inclusions «5mm). Homogeneous material.
><I: ...J U o ...J W u:: 0::: w ::c I<I: 0::: W Il. Il. :::l
><I: ...J U o ...J W u:: 0::: w ::c I<I: 0::: w ;: o ...J
243
Appendix A - borehole 1 page 3
University of Southampton boreholes at the CTRL July 2001
~~--------~------------------------------------------------------~ o(l
o ::;:
16.85
20.0
21.0
22.0
BH 1
}
A piece offtint was found in top of this run, about 15mm long.
16.7m - shear failure visible in core
16.85m-light grey/brown hd. rock
very stiff brown CLAY. choclatey appearance. Very closely fissured, mostly horizontally, but some in other directions. Some rare small hard inclusions «5mm). Homogeneous material.
bottom 200mm of this run is dark grey very stiff CLAY
top 50mm of this run is light brown CLAY, like the Ath I (it's been softened by drilling). There is a sudden change in colour below it to dark brown/grey very stiff closely fissured CLAY
Honogeneous matenal.
brown band of crumbly material (2mm), pass. organic remnant? Sparkley grains up to 1 mm dia. Under the brown there is a 30mm band of light greylbrown CLAY, which is hard in DISCONTINUITY
layers of shells, about 3 in this section (250mm). Other laminations of siltlfine sand.
very stiff dark grey CLAY
50mm at beginning of run - dk gry soft CLAY (softened by drilling?)
finm to stiff light grey CLAY with laminations of silt
19.4m - bed of mUdstone up to 10mm thick - not complete layer
mainly stiff but soft in places dark grey closely bedded CLAY. Core is stained brown on edges and in open cracks.
grey CLAY laminated with silt grey stiff CLAY laminated with silt.
finm SILT - with some clay. Silt is in bands and pockets up to 10mm wide with small amounts of clay inbetween. Silt is crumbly
stiff dark grey closely bedded CLAY brown band of CLAY about 2mm wide at 20.75 - brown hard layer about 1 Omm wide with small knobbles at 20.8 - band of brown silt about 1 Omm wide silt in pockets/lams w. some clay bet. Some small orange spots dk grey stiff CLAY. 21.03-21.05 - hd brown band -20mm wide made up of thin bands. Below is 40mm of brown hd MUDSTONE. In clay above hd band there v. thin silt lams, below it are silt particles distributed evenly thru the clay. 21.2-21.23 - white silt, 21.23-21.3 - green/grey very stiff CLAY w. silt lams 21.3-21.33 - dk grey very stiff CLAY w. white silt lams white closely bedded SILT w. very closely spaced lams of dk grey clay dk grey v. stiff CLAY w. infrequent silt lams. 21.6-21.65 silt lams close together
green/dk grey CLAY w. very frequent white silt laminations (v. close bedding) 21.9-22.03 - silt lams are less frequent
dk grey CLAY w silt lams and pockets. Much mud staining on the core.
lighter grey _ 22.5 - 22.58 light grey CLAY w silt lams ~ 22.58 - 22.66 very silty band - finm, closely bedded. Some clay. Stained brown.
22.66 - 22.73 dk grey stiff CLAY w les frequent silt lams 22.73 - 22.79 lighter grey with more silt 22.79 - 22.87 light grey CLAY w thin silt lams. Closely bedded. Brown staining
23.12 - 23.2 light grey CLAY with silt lams 23.2 - 23.23 closely bedded SILT light grey stiff closely bedded CLAY w silt lams brown staining
below sample: light grey CLAY laminated with silt
200mm band of white SILT
23.85 - 23.95 light grey CLAY laminated with silt
><t: ...J (.)
o ...J W u::: 0:: W J: I<t: 0:: W :!: o ...J
>-~ (.)
o ...J <t: w :!:
244
Appendix A - borehole 1 page 4
c: Q) j<!
Q) l'l 2 iii en 'iii
" 2 c: en E"0 III en
University of Southampton boreholes at the CTRL July 2001
~~------~--------------------------------------------------------~ o/l U ::;: BH 1
25.0
26.0
27.1
28.0
28.8 sample
29.7
light grey CLAY with silt lams. below 24.17 silt lams are wider. 2/3mm
Igt grey CLAY w. silt in pockets on bedding planes. Frequent but small
from 24.58 - silt in pockets on bedding planes less frequent
at 24.75 -layer of silt 3mm thick at 24.88 orange/brown crumbly layer v thin pass tree derived? very stiff dk grey CLAY with infreq. lams of silt at 24.96 v. thin lam of brown silt (?) with black speckles
dk grey CLAY v infreq white speckles also some infreq bedding planes with sparkles on. Closely bedded
200mm dk grey CLAY with some thin silt lams at 25.6m lump of mudstone 70 x 50mm dk grey circle markings on it. white/beige SILT laminated with clay v. closely bedded
dk grey very closely bedded stiff CLAY
finm - sftnd by drilling? Dk grey v closely bedded w pockets of hard silt
hard layer of brown closely bedded small knobles 15mm
dk greylbrownish (pass stained from mudflush) CLAY. some dk (whitelbrown) silt on bedding planes, but not much.
light grey CLAY closely bedded light grey clay - some v thin & infreq lams of silt
dk grey CLAY w infreq v thin white silt lams. Bedding is angled - 20'
dk grey v closely bedded CLAY with v. little silt
Igt grey CLAY. @28.30rge/brn ROCK - 2/3 dia. Of BH -100mm wide below rock: orange/brown rock fragments in soft clay missing material dk grey stiff closely bedded CLAY at 28.6 - some light grey/dark grey mottling
dk gry stiff v closely bedded CLAY w some silt pockets on bdg planes
at 28.9 - some silt lams one 2mm wide (at end of borehole section)
dk gry CLAY w some hard silt pockets. Some are quite large
at 29.23 - 29.35 - laminated SILT white/brown w. some clay grey CLAY w. lams (@ -20') and pockets of white and stained bm silt
dk grey v closely bedded CLAY at 29.65 - hard silt layer a few mm thick. Stained
>< -l U o -l < W ~
245
Appendix A - borehole 2 page 1
Q) 0 c ~ Q)
~ ~ en c :::J 0::
0
2
University of Southampton boreholes at the CTRL July 2001
44.83mAOD
soft sandy dark brown CLAY with gravel and cobbles (smelly)
firm to stiff mottled yellow/grey sandy (fine sand) CLAY (some orange staining). Brown speckles.
very stiff fissured mottled yellowish grey sandy CLAY with orange specks
very stiff grey sandy (fine) CLAY. with brown staining (of mud flush?) horizontally thinly laminated
o WZ O:::J <0 ::EO::
(!)
CJl o w m w :I: I>:I:
= o ..J w>-U::j ffiu :I: I<
246
Appendix A - borehole 2 page 2
BH 2
University of Southampton boreholes at the CTRL July 2001
Very stiff grey sandy (fine) CLAY. Less evidence of laminations. Clay is crumbly and has staining. Silty particles sparkle.
Round brown stain on core with a stone in the middle
RUns 1 and 2 very similar. In both runs large parts of the core has been affected by the drilling which has produced stained, softened and crumbly samples. The borehole was left open over the weekend before these runs were taken.
RUn 1 : large peds of very stiff sandy (fine) CLAY in matrix of sandy (fine) clay. There are fissures at intervals of about 50mm in all directions, the surfaces of which are wet and shiny and NOT stained with the mud flush. However much of this material seems to have been softened by the mud flush. Much brown staining. silty particles sparkle.
The bottom 100mm of this run is horizontally thinly laminated.
run 2 : very stiff crumbly silty CLAY with peds of very stiff silty clay Fissures are stained by mud flush.
very stiff grey CLAY. Slightly silty but less so than at lower positions in the stratum.
very stiff grey silty CLAY
Clay crumbles when cut. Lots of brown staining from the flush. The clay feels like it's softened.
First run of day after trouble with casing on day before. Top 25mm is yellow mush. Next 35mm is grey and has usual structure of Ath II but appears to have absorbed a lot of water and expanded.
Material after S 1 0 is very stiff grey silty CLAY.
material is greylbrown mottled above this line, so that the line corresponds to the point at which the clay stops being mottled.
S11 constitutes a light brown band that exists between the Ath I and II, which is very stiff light brown CLAY (choclatey appearance)
>-~ u o ...J W u:: 0:: w J: I<t: 0:: w a. a. ::::>
247
Appendix A - borehole 2 page 3
University of Southampton boreholes at the CTRL July 2001
BH2
}
s11 is part of a light brown band which exists at the top of the lower Atherfield Clay. Underneath it there is some light brown mottling to the core. Then the material is very stiff brown CLAY. It is chocolatey in appearance and is homogeneous.
darker - the top 350mm of run 3 is darker brown than the rest, but otherwise itis same: very stiff dark brown CLAY
occasional fragments of shell 3-4mm in size
very stiff fissured brown CLAY.
brown/dark grey very stiff closely fissured CLAY.
19.55 - 20.3 very stiff dark grey/brown closely fissured CLAY. Very dark at 20.3m, getting gradually lighter and browner as depth decreases.
60mm band of brown, very hard ROCK
grey very stiff closely fissured CLAY with some silt
light grey stiff CLAY with close silt laminations
300mm very stiff grey closely fissured CLAY
light grey CLAY with close silt laminations
dk grey stiff closely fissured CLAY
light grey stiff closely fissured CLAY with less frequent silt laminations
dk grey very stiff closely fissured CLAY with silt laminations
light grey very stiff closely fissured CLAY with silt laminations
grey very stiff closely fissured CLAY no silt laminations grey very stiff closely fissured CLAY silt laminations grey very stiff closely fissured clay CLAY no silt laminations band of grey ROCK, 100mm thick
dk grey very stiff closely fissured CLAY no silt laminations
200mm band light grey very stiff CLAY
dk grey very stiff closely fissured CLAY no silt laminations
very stiff grey CLAY with silt laminations
>« ...J u CI ...J W u. 0:: w J: I« 0:: w ~ o ...J
>« ...J U CI ...J « W ~
248
Appendix A - borehole 2 page 4
c: ~ University of Southampton boreholes at the CTRL July 2001 ttl (l) 0.:::
i ~ ~~--------~----------------------------------------------------------------~ ~ 5 ~ '" en
25.0
27.5
28.3
BH 2
very stiff closely laminated with silt grey CLAY. Some brown colour in laminations (mud flush?)
very stiff light grey closely laminated with silt CLAY.
dk grey closely fissured CLAY. V close silt laminations - 45° to horiz.
dark grey closely fissured CLAY.
dark grey closely fissured CLAY. With very close silt laminations 15° to the horizontal.
very stiff dark grey CLAY. With very close silt laminations 10-20° to the hOrizontal up to 3mm thick. Silt is greylwhite (or crushed fossils?)
above mudstone - very stiff greenish grey closely fissured CLAY
28.15 - Grey MUDSTONE about 4mm wide.
28.45 - silt lamination
very stiff dark grey horizontally closely fissured CLAY. Some fissures contain white silt but these layers are rare.
very stiff dark grey closely fissured CLAY. With peds about 10-20mm which are stiffer than the crumbly matrix. Some white silt (or crushed fossils?)
249
Appendix B - Piling diary
6 7 8 9 10 .. ~ ~ -- --1100 - - 16 - -1.? .. - -1100 .1 3 1 ~ 5
-1800 Z x y
+- 000000000000000000000 1800 G020 G021 G022 G023 G024G025 G026 G027 G028 G029 G030 G031 G032 G033 G034 G035 G036 G037 G038 G039 G040 .. --
N Dimensions in mm
~ • Spade cell o Pile and pile number
Figure B-1: Plan of piles showing pile reference numbers
Key - start and finish times for the following construction stages
ex. 1 = 1 st stage of excavation, 0 - 8 metres
ex.2 = 2nd stage of excavation, 8 - ~20 metres
Conc. = concrete pour
Date Time interval Pile no. and Procedure Time
Tuesday 23/11/1999 14:00
Wednesday 24/11/1999 10:00 12:00 14:00
Thursday 25/11/1999 14:00 16:00
Friday 26/11/1999 08:00
weekend
Monday 29/11/1999
10:00 12:00
14:00
16:00
G025 - ex.l G033 - ex.l
G025 - ex.2 G033 -ex.2 G025 - Conc. G025 - Conc.
G021 - ex.l G037 - ex.l G028 - ex.l
G021- ex.2 G028-ex.2 G021- Conc. G037 - ex.2 G037 - Conc. G028 - Conc.
G035 - ex.l G031 - ex.l G023 - ex.l
15:10 - 15:40 15:50 - 16:20
11 :55 - 12:35 12:55 - 13:30 14:20 - 14:53 15:50 - 16:38
14:40 - 16:00 16:50-17:10 17:20 - 17:40
08:05 - 08:45 O?:?? - 09:14 09:16 - 10:02 09:30 - 10:01 10:49 - 11 :30 12:25 - 13:11
14:59 - 15:20 15:55 -16:15 16:25 - 16:46
250
Date Time interval Pile no. and Procedure Time
Tuesday 30/1111999 08:00 0035 -ex.2 08:00 - 08:35 0031- ex.2 08:35 - 09:07 0023 - ex.2 09:34 - 10:00 0035 - Conc. 09:55 - 10:31
10:00 0023 - Conc. 11 :08 - 11 :46 12:00 0031- Conc. 12:27 - 13:15
Wednesday 01/12/1999 14:00 0030 - ex.1 15:18 - 15:42
Thursday 02/12/1999 08:00 0030-ex.2 09:10 - 10:00 10:00 0030 - Conc. 11:09 -11:50 12:00 0026 - ex. 1 &2 12:20 - 13:50 14:00 16:00 0026-Conc. 16:26 - 17:24
Friday 03/12/1999 10:00 0039 - ex.1 11:50 -12:18 12:00 0032 - ex.1 12:20 - 12:40
0027 -ex.l 12:50 -13:21 14:00 0022 -ex.l 14:35-15:00
weekend
Monday 06/12/1999 08:00 0022-ex.2 09:06 - 09:41 0027 -ex.2 09:44 - 10:14
10:00 0032-ex.2 11 :04 - 11 :40 0022-Conc. 11:12-11:56
12:00 0027 -Conc. 12:30 -13:15 0039- ex.2 13:10 -13:35
14:00 0032 - Conc. 14:20 - 15:15 0039-Conc. 15:40 - 16:27
Tuesday 07/12/1999
Wednesday 08/12/1999
Thursday 09/12/1999
Friday 10/12/1999 10:00 0040 - ex.1 10:40 - 12:00 0036-ex.1 11 :08 - 11 :30
weekend
Monday 13/12/1999 08:00 0036-ex.2 08:10 - 08:42 0040 - ex.2 08:42 - 09:05 0036-Conc. 09:50 - 10:36
10:00 0040-Conc. 11 :14 - 12:01 12:00 14:00 16:00 0029 - ex.l 17:15 - 17:46
Tuesday 14/12/1999 08:00 0029-ex.2 08:48 - 09:08 10:00 0029 - Conc. 10:58 - 11 :45
251
Date Time interval Pile no. and Procedure Time
Wednesday 1511211999 16:00 G020 - ex.l 16:31 - 16:57 G024 -ex.l 16:59-17:21
Thursday 08:00 G020-ex.2 08:10 - 08:40 G024-ex.2 08:41 - 09:05 G020-Conc. 09:33 - 10:06
10:00 G024 - Conc. 10:40-11:17
Friday 1711211999 10:00 G038 - ex.l 11 :35 - 12:00 12:00 G034 -ex.l 12:03 - 12:25
weekend
Monday 20/1211999 10:00 G038 -ex.2 11 :20 - 11 :46 G034-ex.2 11:48 -12:10
12:00 14:00 G038 - Conc. 14:30 - 15:45 16:00 G034-Conc. 16:05 - 17:05
252
Appendix C - Calculation of flexural rigidity (El) for pile
Upper part of pile (reinforcement bar diameter = 50 mm)
diameter of bar = Area of bar = Area of bar = second moment of area of bar, I = distance to neutral axis of furthest bar, YA = distance to neutral axis of 2nd furthest bar, YB = distance to neutral axis of 2nd nearest bar, Yc = distance to neutral axis of nearest bar, Yo = distance to neutral axis of bar on NA, YE = E (concrete) = E (steel) = I pile = assuming 70 mm cover to rebar
B o A
G
o c
50 mm 1963.5 mm~
0.0019635 m~ 3.0680E-07 m
4
0.43000 m 0.16455 m 0.30406 m
0.39727 m Om
25000000 kN/m~ 205000000 kN/m~
0.059666024 m4
no of bars x (I + Area x Y~ )
IA = 7.2671E-04 m4
18 = 0.000213897 m4
IC = 0.000727328 m4
ID = 0.001240758 m4
IE = 6.1 3592E-07 m4
TOTAL =
IE =
0.002909311 m4
(Ipile x Econc) - (Isteel x Econc) + (Isteel x Esteel) 2015326.594 kNm'
1492834.514 kNm'/m run of wall
Lower part of pile (reinforcement bar diameter = 40 mm)
diameter of bar = Area of bar = Area of bar = second moment of area of bar, I = distance to neutral axis of furthest bar, YA = distance to neutral axis of 2nd furthest bar, YB = distance to neutral axis of 2nd nearest bar, Yc = distance to neutral axis of nearest bar, Yo = distance to neutral axis of bar on NA, YE = E (concrete) = E (steel) = I pile = assuming 70 mm cover to rebar
B o A
o
G C
40 mm 1256.6 mm~
0.0012566 m~ 1.2566E-07 m
4
0.43000 m 0.16455 m
0.30406 m 0.39727 m
Om 25000000 kN/m~
205000000 kN/m~ 0.059666024 m4
no of bars x (I + Area x l) IA = 4.6496E-04 m
4
18 = 0.000136611 m4
IC = 0.000465207 m4
ID = 0.000793803 m4
IE = 2.51327E-07 m4
TOTAL = 0.001860828 m4
IE = (I pile x Econc) • (lsteel x Econc) + (Isteel x Esteel) 1826599.657 kNm'
1353036.783 kNm'/m run of wall
253
References
American Concrete Institute (ACI) (1992). Causes, evaluations and repair of cracks in
concrete structures (ACI 318/318R-89) ACI, Detroit, Mich.
Atkinson, J.H., Richardson, D. and Stallebrass, S.E. (1990). Effect ofrecent on the
stiffness of overconsolidated soils. Geotechnique 40(4): 531-540.
Batten, M. and Powrie, W. (2000). Measurement and analysis of temporary prop loads at
Canary Wharf underground station, east London Proc. Inst. Civ. Engrs. Geotech. Engng
143(July): 151-163.
Batten, M., Powrie, W., Boorman, R., Yu, H.-T. and Leiper, Q. (1999). Use of vibrating
wire strain gauges to measure loads in tubular steel props supporting deep retaining walls
Proc.lnstn. Civ. Engrs, 137(Jan): 3-13.
Bolton. M.D. and Powrie, W. (1987). The collapse of diaphragm walls retaining clay.
Geotechnique 37(3): 335-353.
Bolton. M.D. and Powrie, W. (1988). Behaviour of diaphragm walls in clay prior to
collapse. Geotechnique 38(2): 167-189.
Branson, D.E. (1977). Deformation of concrete structures. McGraw-Hill, New York.
British Standard Institution (1951). Code of Practice No.2: Earth retaining structures.
London: BSI.
British Standard Institution (1986). BS 1881-206: British Testing concrete - Part 206:
Recommendations for determination of strain in concrete, Milton Keynes: BSI.
British Standard Institution (1994). BS 8002: British Standards Institution Code of
practise for earth retaining structures, Milton Keynes: BSI.
British Standards Institution (2004). Eurocode 7: Geotechnical design Part 1, General
rules. EN1997-1 :2004.
British Steel Piling Handbook (1997). British Steel PIc. i h Edition.
Britto, A.M. and Gunn, M.J. (1987). Critical state soil mechanics via finite elements. Ellis
Horwood, Chichester.
254
Burland, J.B., Potts, D.M. and Walsh, N.M. (1981). The overall stability of free and
propped embedded cantilever walls, Ground Engineering 14(5): 28-38.
Burland, J.B., Simpson, B. and St John, H.D. (1979). Movements around excavations in
London Clay Proc. i h Eur. Con! on Soil Mech. and Found. Engng, Brighton. 1: 13-29.
Carder, D.R. and Symons, I.F. (1989). Long-term performance of an embedded cantilever
retaining wall in stiff clay. Geotechnique 39(1):55-75.
Carder, D.R. and Darley, P. (1998). The long term performance of embedded retaining
walls. TRL Report 381. Transport Research Laboratory, Crowthorne.
Carswell, I., Carder, D.R. and Gent, A.J.C (1993). Behaviour during construction of a
propped contiguous bored pile wall in stiff clay at Waltham stow. TRL Project Report 10.
Project Record E468A1BG.
Chandler, R.J. (2000). Clay Sediments in Depositional Basins: the Geotechnical Cycle.
Quarterly Journal of Engineering Geology and Hydrology, 33: 7-39.
Clayton, C.R.I. and Bica, A.V.D. (1993). The design of diaphragm-type boundary total
stress cells Geotechnique 43(4): 523-535.
Clayton, C.R.I. and Milititsky, J. (1983). Installation effects and the performance of bored
piles in stiff clay. Ground Engineering, March.
Coulomb (1776). Essai ... , Paris 7: 343-382.
De Moor, E.K. (1994). An analysis of bored pile/diaphragm wall installation effects.
Geotechinque 44(2): 341-347.
Department of Transport (2000). BD 42: Design manualfor roads and bridges, Vol. 2
Section 1 Part 2: Design of embedded retaining walls and bridge abutments, Department
of Transport, London: HMSO. Crown Copyright.
Dunnicliff, J. (1993). Geotechnical instrumentation for monitoring field performance
(with the assistance ofG.E. Green) Wiley, New York.
Eurocode 2 (1992) Design of concrete structures EN1992.
255
Fjaer, E., Holt, R.M., Horsrud, P., Raaer, RM. and Risnes, R (1992). Petroleum related
Rock mechanics, Elsevier.
Fourie, A.B. and Potts, D.M. (1989). Comparison of finite element and limiting
equilibrium analyses for an embedded cantilever retaining wall. Geotechnique 39(2): 175-
188.
Gaba, A.R. (2002). Presentation given at the ICE, London.
Gaba, A., Simpson, B., Powrie, W. and Beadman, D.R (2003). Embedded retaining
walls: guidance for more economic design Construction Industry Research and
Information Association Report C580. CIRIA, London.
Garrett, C. and Barnes, S.J. (1984). The design and performance of the Dunton Green
retaining wall. Geotechnique 34(4):533-548.
Gibson, RE. and Anderson, W.F. (1961). In situ measurement of soil properties with the
pressuremeter. Civil Engineering and Public Works Review 56(658): 615-618.
Glass and Powderham (1994). Application of the observational method at the limehouse
Link. Geotechnique 44(4):665-679.
Gourvenec, S.M. and Powrie, W. (1999). Three-dimensional finite-element analysis of
diaphragm wall installation Geotechnique 49(6): 801-823.
Gunn, M.J. and Clayton, C.RI. (1992). Installation effects and their importance in the
design of earth-retaining structures. Geotechnique 42(1): 137-141.
Gunn, M.J., Satkunananthan, A. and Clayton, C.RI. (1993). Finite Element modelling of
installation effects. Retaining structures. Thomas Telford, London.
Hayward, T. (2000). Field studies, analysis and numerical modelling of retaining walls
embedded in weak rock. Ph.D. thesis, University of Southampton, UK.
Heyman, G. and Clayton C.RI., (1999) Block sampling of soil: Some practical
considerations Geotechnicsfor developing Africa Wardle, Blight and Fourie, Balkema,
Rotterdam.
256
Hight, D.W. and Leroueil, S. (2003). Characterisation of soils for engineering purposes.
Characterisation and Engineering Properties of Natural Soils. Tan et al. (eds) A A
Balkema ISBN 90 C5809 537 1: 255-360.
Hitchcock, A.R. (2003). Elimination of temporary propping using the observational
method on the Heathrow airside road tunnel project Ground Engineering, May.
HMSO (1978) British Regional Geology - The Wealden District.
Humpage, A.J. and Booth K.A. (2000). The Lower Greensand in the Mid-Kent and
Ashford Contract Sectors of the Channel Tunnel Rail Link Construction Works. British
Geological Survey Commercial Report CRlOO/19.
Jardine, R.J., Symes, M.J. and Burland, J.B. (1984). The measurement of soil stiffness in
the triaxial apparatus. Geotechnique 34(3): 323-340.
Jardine, RJ., Potts, D.M., Fourie, A.B. and Burland, J.B. (1986). Studies of the influence
of non-linear stress-strain characteristics in soil-structure interaction, Geotechnique 36(3):
377-396.
Loveridge, F. (2000). Evaluation of prop loads at CTRL contract 430 Ashford Tunnels.
Ground Engineering
Mair, R.J. (1993). Developments in geotechnical engineering research, application to
tunnels and deep excavations. Proceedings of the Institution of Civil Engineers Civil
Engineering, 97(1): 27-41.
Mair, R.J. and Wood, D.M. (1987). In-situ Pressuremeter Testing: Methods, Testing and
Interpretation. Construction Industry Research and Information Association,
Butterworths, London.
Mantell, G.A. (1833). Geology of south-east England, Longman, London.
Massarsch, K.R. (1975). New method for measurement of lateral earth pressure in
cohesive soils. Can. Geotech. J. 12:142-146.
Massarsch, K.R., Holtz, R.D., Holm, B.G. and Fredriksson, A. (1975). Measurement of
horizontal in situ stresses. Proc. of Speciality Conf on in situ measurement of soil
properties, North Carolina, 1:266-286. American Society of Civil Engineers.
257
Mikkelsen, P.E. (2003). Advances in inclinometer data analysis. Symposium on Field
Measurements in Geomechanics, FMGM, Oslo Norway. September.
Mosley, W.H. and Bungey, J.H. (1976). Reinforced Concrete Design London, Macmillan.
Neville, A.M. (1970). Creep of concrete: plain, reinforced, and prestressed. North
Holland publishing Company, Amsterdam.
Ng, C.W.W. (1992). An Evaluation of Soil-structure Interaction Associated with a Multi
propped Excavation. PhD thesis, University of Bristol.
Ng, C.W.W., Lings, M.L., Simpson, B. and Nash, D.F.T. (1995). An approximate analysis
of the three-dimensional effects of diaphragm wall installation. Geotechnique 45(3):497-
507.
Ng, C.W.W. and Yan, R.W.M. (1999). Three-dimensional modelling ofa diaphragm wall
construction sequence. Geotechnique, 49(6): 825-834.
Ooi, P.S.K. and Ramsey, T.L. (2003). Curvature and bending moments from inclinometer
data, ASCE International Journal ofGeomechanics, 3(1):64-74.
Padfield, C.J. and Mair, RJ. (1984). Design of retaining walls embedded in stiff clays.
Report 104. London: Construction Industry Research and Information Association.
Peattie, K.R. and Sparrow, R.W. (1954). The fundamental action of earth pressure cells
Journal of the mechanics and physics of solids, 2: 141-155.
Penman, A.D.M. and Charles, J.A. (1981). Assessing the risk of hydraulic fracture in dam
cores. PRc. loth Int. Con! Soil Mech., Stockholm 1: 457-462.
Potts, D.M. and Bond, A.J. (1994). Calculation of Structural forces for propped retaining
walls. XIII ICSMFE, New Delhi, India.
Potts, D.M. and Fourie, A.B. (1984). The behaviour of a propped retaining wall: results of
a numerical experiment. Geotechnique, 34(3): 383-404.
Potts, D .M. and F ourie, A.B. (1985). The effect of wall stiffness on the behaviour of a
propped retaining wall. Geotechnique 35(3): 347-352.
Potts D. M. and Zdravkovic, L. (1999). Finite element analysis in geotechnical
engineering. Thomas Telford, London.
258
Powrie, W. (1985). Discussion on Perfonnance in propped and cantilever rigid walls.
Geotechnique 35(4): 546-548.
Powrie, W. (2004). Soil mechanics: concepts and applications (2nd edition). London: Spon
Press.
Powrie, W. and Kantartzi, C. (1996). Ground response during diaphragm wall installation
in clay: centrifuge model tests. Geotechnique 46(4): 725-739.
Powrie, W. and Li, E.S. (1991). Finite element analyses of an in situ wall propped at
fonnation level. Geotechnique 41(4): 499-514.
Powrie, W, Pantelidou H. and Stallebrass, S.E. (1998). Soil stiffness in stress paths
relevant to diaphragm walls in clay. Geotechnique 48(4): 483-494.
Raphael, J.M. (1984) Tensile strength of concrete ACI Journal, 81(2): 158-165.
Rankine, W. J. M. (1857). On the stability ofloose earth, Phil. Trans. Royal Society
147(2): 9-27.
Richards, D.J. Chandler, R.J. and Lock, A.C. (2003) Electronic data transfer systems for
field monitoring. Proc. Inst. Civ. Engrs 156(1): 47-55.
Richards, D.J., Clark, J., Powrie, W. and Heyman, G. (2005) An evaluation of total
horizontal stress measurements using push-in pressure cells in an overconsolidated clay
deposit. Proc. Inst. Civ. Engrs. Geotech. Engng accepted for publication.
Richards, D.J., Holmes, G. and Beadman, D.R. (1999). Measurement of temporary prop
loads at Mayfair car park. Proc. Inst. Civ. Engrs. Geotech. Engng 137(July): 165-174.
Richards, D.J. and Powrie, W. (1994). Finite element analysis of construction sequences
for propped retaining walls. Proc. Inst. Civ. Engrs, Geotech. Engng. 107(1994): 207-216.
Richards, D.J. and Powrie, W. (1998). Centrifuge tests on doubly propped embedded
retaining walls in overconsolidated kaolin clay, 48(6): 833-846.
Roberts, M. (2003). Private communication.
Roberts, T.O.L., Roscoe, H., Powrie, W. and Butcher, D. (2005). private communication.
Roscoe, H. (2005). Private communication.
259
Roscoe, H. and Twine, D. (2001). Design collaboration speeds Ashford tunnels. World
Tunnelling, 14(5): 237-241.
Ross, A.D. (1937). Concrete Creep Data. The Structural Engineer 15: 314-32.
Rowe, P.W. (1952). Anchored sheet-pile walls. Proc. Inst. Civ. Engrs. 1(1): 27-70.
Rowe, P.W. (1955). A theoretical and experimental analysis of sheet piled walls. Proc.
Inst. Civ. Engrs. 4(1): 32-69.
Rowe, P. W. (1956). Sheet piled walls at failure. Proc. Inst. Civ Engrs. 276-315.
Ryley, M.D. and Carder D.R. (1995). The performance of push-in spade cells installed in
stiff clay. Geotechnique 45(3): 533-539.
Saxena, S.K. (1975). Measured performance of a rigid concrete wall at the World Trade
Center, Proc. Conf. on Diaphragm Walls and Anchorages pp. 107-112.
Skempton, A.W. and Weeks, A.G. (1976) The Quaternary history of the Lower Greensand
escarpment and Weald Clay vale near Sevenoaks, Kent. Phil. Trans. R. Soc. Lond. A. 283:
493-526.
Simpson, B. (1992). Thirty-second Rankine lecture: Retaining structures: displacement
and design. Geotechnique 42(4): 541-576.
Simpson, B. and Powrie, W. (2000). Embedded retaining walls: theory, practise and
understanding. ISSMGE XVth International conference in Turkey.
Smart J.G.O., Bisson G. and Worssam B.C. (1966). Geology of the Country around
Canterbury and Folkestone. Her Majesty's Stationery Office, London.
Smethurst, J.A. 2003. The use of discrete piles for infrastructure slope stabilisation. PhD
thesis, University of Southampton, UK.
Stroud, M.A. (1974). The standard penetration test in insensitive clays and soft rocks
Proc. Eur. Symp. on Penetration Testing (ESOPTI) Volume 2:2, pp. 367-375, Swedish
Geological Society, Stockholm.
Stroud, M.A. and Sweeney, D.J., (1977). Discussion appendix in: A review of diaphragm
walls, pp. 142-148. London: Institution of Civil Engineers.
260
Symons, I.F. (1983). Assessing the stability of a propped, in situ retaining wall in
overconsolidated clay Proc. Inst. Civ. Engrs, 75(2): 617-633.
Symons, I.F. and Carder, D.R. (1990). Long term behaviour of embedded retaining walls
in over-consolidated clay. Geotechnical Instrumentation in Practice, TTL, London.
Symons, I.F. and Carder, D.R. (1992). Field measurements on embedded retaining walls.
Geotechnique 42(1): 117-126.
Symons, I.F. and Carder, D.R. (1993). Stress changes in stiff clay caused by the
installation of embedded retaining walls. Retaining structures Thomas Telford, London.
Symons, I.F. and Tedd, P. (1989). Behaviour ofa propped embedded retaining wall at Bell
Common Tunnel in the longer term. Geotechnique 34(4): 701-710.
Tavenas, F.A., Blanchette, G., Leroueil, S., Roy, M. and La Rochelle, P. (1975).
Difficulties in the in situ determination ofKo in soft sensitive clays Proc. of speciality
conference on in situ measurement of soil properties, North Carolina, 1:450-476. New
York, American Society of Civil Engineers.
Tedd, P., Chard, B.M., Charles, l.A. and Symons, I.F. (1984). Behaviour ofa propped
embedded retaining wall in stiff clay at Bell Common. Geotechnique 34(4): 513-532.
Tedd P. and Charles l.A. (1981). In-situ measurement of horizontal stress in
overconsolidated clay using push-in spade-shaped pressure cells. Geotechnique 31(4): 534
-538.
Tedd P. and Charles l.A. (1983). Evaluation of push-in pressure cell results in stiff clay.
Proceedings of the International Symposium on soil and rock investigation by in-situ
testing. Paris, Vol. 2, 579-584.
Tedd P., Powell lA., Charles l.A. and U glow I.M. (1990). In-situ measurement of earth
pressures using push-in spade-shaped pressure cells - 10 years experience. Geotechnical
Instrumentation in practice, Thomas Telford, London.
Terzaghi, K (1934). Theoretical Soil Mechanics, Wiley and Sons.
Terzaghi, K (1943). Large retaining wall tests, Engineering News Record 112: 36-140.
Terzaghi, K (1954). Anchored Bulk Heads, Trans. Am. Soc. Civ. Engrs 119: 1243-1280.
261
Tschebotarioff, G. (1951). Soil mechanics, foundations and earth structures, McGraw
Hill.
Union Railways Ltd (1997 A). Central Ashford - Geotechnical Design Basis Report
chainage 87+842 to 92+042. Report number 440-RUP-LCEEH-00043-AA.
Union Railways Ltd (1997 B). Ashford Tunnel Design Criteria. Report number 430-RUG
RLEEZ-00120-AA.
Weiler, W.A. and Kulhawy, F.H. (1982). Factors affecting stress cell measurements in
soil. J Geotechnical Engineering ASCE, 108, No. GT12 (December): 1529-1548.
Wood, L.A. and Perrin, A.J. (1984). Observations of a strutted diaphragm wall in London
clay: a preliminary assessment. Geotechnique, 34(4): 563-579.
Xu (2005). The behaviour of soil behind full-height integral abutments. PhD thesis,
University of Southampton.
262