unit 11 capital budgeting tool kit

Upload: tanira

Post on 09-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Unit 11 Capital Budgeting Tool Kit

    1/10

    1

    2

    3

    4

    5

    6

    7

    8

    910

    11

    12

    13

    14

    15

    16

    1718

    19

    20

    21

    22

    23

    24

    25

    26

    27

    28

    29

    30

    31

    32

    33

    34

    35

    36

    3738

    3940

    41

    42

    43

    44

    45

    46

    47

    4849

    50

    51

    A B C D E F G H I J K L M N O P Q R S T U V W

    Unit 11

    Project S

    Year (t) Project S Project L 0 1 2 3 4

    0 ($1,000) ($1,000) (1,000) 500 400 300 100

    1 500 100

    2 400 300 Project L

    3 300 4004 100 600 0 1 2 3 4

    (1,000) 100 300 400 600

    Capital Budgeting Decision Criteria

    Payback Period

    Project S

    Time period: 0 1 2 3 4

    Cash flow: (1,000) 500 400 300 100

    Cumulative cash flow: (1,000) (500) (100) 200 300 Click fx > Logical > AND > OK to get dialog box.

    FALSE FALSE FALSE TRUE FALSE Use Logical "AND" to determine Then specify you want TRUE if cumulative CF > 0 but the previous CF < 0.

    0.00 0.00 0.00 2.33 0.00 the first positive cumulative CF.There will be one TRUE.

    Payback: 2.33 Use Logical IF to find the PaybackClick fx > Logical > IF > OK. Specify that if true, the payback is the previous year plus a fraction, if false, then 0.

    Use Statistical Max function to Click fx > Statistical > MAX > OK > and specify range to find Payback.

    Alternative calculation: 2.33 display payback.

    Project L

    Time period: 0 1 2 3 4

    Cash flow: (1,000) 100 300 400 600

    Cumulative cash flow: (1,000) (900) (600) (200) 400

    Payback: 3.33 Uses IF statement.

    In this file we use Excel to do most of the calculations explained in Chapter 10. First, we analyze Projects S and L,

    whose cash flows are shown immediately below in both tabular and a time line formats. Spreadsheet analyses can be

    set up vertically, in a table with columns, or horizontally, using time lines. For short problems, with just a few years,

    we generally use the time line format because rows can be added and we can set the problem up as a series of income

    statements. For long problems, it is often more convenient to use a tabular layout.

    Here are the five key methods used to evaluate projects: (1) payback period, (2) discounted payback period, (3) net

    present value, (4) internal rate of return, and (5) modified internal rate of return. Using these criteria, financial

    'analysts seek to identify those projects that will lead to the maximization of the firm's stock price.

    The payback period is defined as the expected number of years required to recover the investment, and it was the

    first formal method used to evaluate capital budgeting projects. First, we identify the year i n which the cumulative

    cash inflows exceed the initial cash outflows. That is the payback year. Then we take the previous year and add to

    it unrecovered balance at the end of that year divided by the following year's cash flow. Generally speaking, the

    shorter the payback period, the better the investment.

    Tool Kit for The Basics of Capital Budgeting: Evaluating Cash Flows

    Expected after-tax

    net cash flows (CF t)

  • 8/8/2019 Unit 11 Capital Budgeting Tool Kit

    2/10

    52

    53

    54

    55

    56

    57

    58

    59

    60

    61

    62

    63

    64

    6566

    67

    68

    69

    70

    7172

    73

    74

    75

    76

    77

    78

    79

    80

    81

    82

    83

    8485

    86

    87

    8889

    90

    91

    92

    93

    94

    9596

    97

    98

    99

    100

    101

    102

    103

    104

    105

    A B C D E F G H I J K L M N O P Q R S T U V W

    Discounted Payback Period

    WACC = 10%

    Project S

    Time period: 0 1 2 3 4

    Cash flow: (1,000) 500 400 300 100

    Disc. cash flow: (1,000) 455 331 225 68 Cash Flows Discounted back at 10%.

    Disc. cum. cash flow: (1,000) (545) (215) 11 79

    Discounted Payback: 2.95 Uses IF statement.

    Project L

    Time period: 0 1 2 3 4

    Cash flow: (1,000) 100 300 400 600

    Disc. cash flow: (1,000) 91 248 301 410

    Disc. cum. cash flow: (1,000) (909) (661) (361) 49

    Discounted Payback: 3.88 Uses IF statement.

    Net Present Value (NPV)

    WACC = 10%

    Project S

    Time period: 0 1 2 3 4

    Cash flow: (1,000) 500 400 300 100

    Disc. cash flow: (1,000) 455 331 225 68

    NPV(S) = $78.82 = Sum disc. CF 's. or $78.82 = Uses NPV function.

    Project L

    Time period: 0 1 2 3 4

    Cash flow: (1,000) 100 300 400 600

    Disc. cash flow: (1,000) 91 248 301 410

    NPV(L) = $49.18 49.18$ = Uses NPV function.

    Discounted payback period uses the project's cost of capital to discount the expected cash flows. The calculation of

    discounted payback period is identical to the calculation of regular payback period, except you must base the

    calculation on a new row of discounted cash flows. Note that both projects have a cost of capital of 10%.

    The inherent problem with both paybacks is that they ignore cash flows that occur after the payback period mark.

    While the discounted method accounts for timing issues (to some extent), it still falls short of fully analyzing projects.

    However, all else equal, these two methods do provide some information about projects' liquidity and risk.

    To calculate the NPV, we find the present value of the individual cash flows and find the sum of those discounted

    cash flows. This value represents the value the project add to shareholder wealth.

    The NPV method of capital budgeting dictates that all independent projects that have positive NPV should accepted.

    The rationale behind that assertion arises from the idea that all such projects add wealth, and that should be the

    overall goal of the manager in all respects. If strictly using the NPV method to evaluate two mutually exclusive

    projects, you would want to accept the project that adds the most value (i.e. the project with the higher NPV).

    Hence, if considering the above two projects, you would accept both projects if they are independent, and you wouldonly accept Project S if they are mutually exclusive.

    Notice that the NPV function isn't really a Net present value.

    Instead, it is the present value of future cash flows. Thus, you

    specify only the future cash flows in the NPV function. To find the

    true NPV, you must add the time zero cash flow to the result of the

    NPV function.

  • 8/8/2019 Unit 11 Capital Budgeting Tool Kit

    3/10

    106

    107

    108

    109

    110

    111

    112113

    114

    115

    116

    117

    118

    119

    120121

    122

    123

    124

    125

    126

    127

    128

    129

    130

    131

    132

    133

    134

    135

    136

    137

    138139

    140

    141

    142

    143

    144

    145

    146

    147

    148

    149

    A B C D E F G H I J K L M N O P Q R S T U V W

    Internal Rate of Return (IRR)

    Year (t) Project S Project L

    0 ($1,000) ($1,000) The IRR function assumes

    1 500 100 IRR S = 14.49% payments occur at end of

    2 400 300 IRR L = 11.79% periods, so that function does

    3 300 400 not have to be adjusted.4 100 600

    Expected after-tax

    The internal rate of return is defined as the discount rate that equates the present value of a project's cash inflows to

    its outflows. In other words, the internal rate of return is the interest rate that forces NPV to zero. The calculation

    for IRR can be tedious, but Excel provides an IRR function that merely requires you to access the function and

    enter the array of cash flows. The IRR's for Project S and L are shown below, along with the data entry for Project

    S.

    net cash flows (CF t)

    The IRR method of capital budgeting maintains that projects should be accepted if their IRR is greater than the cost

    of capital. Strict adherence to the IRR method would further dictate that mutually exclusive project s should bechosen on the basis of the greatest IRR. In this scenario, both projects have IRR's that exceed the cost of capital

    (10%) and both should be accepted, if they are independent. If, however, the projects are mutually exclusive, we

    would chose Project S. Recall, that this was our determination using the NPV method as well. The question that

    naturally arises is whether or not the NPV and IRR methods will always agree.

    When dealing with independent projects, the NPV and IRR methods will always yield the same accept/reject result.

    'However, in the case of mutually exclusive projects, NPV and IRR can give conflicting results. One shortcoming of

    the internal rate of return is that it assumes that cash flows received are reinvested at the project's internal rate of

    return, which is not usually true. The nature of the congruence of the NPV and IRR methods is further detailed in a

    latter section of this model.

    Notice that for IRR you mustspecify all cashflows, including the time zerocash flow. This is in contrastto the NPV function, in whichyou specify only the futurecash flows.

  • 8/8/2019 Unit 11 Capital Budgeting Tool Kit

    4/10

    150

    151

    152

    153

    154

    155

    156

    157

    158

    159

    160

    161

    162

    163164165

    166

    167

    168

    169170

    171

    172

    173

    174

    175

    176

    177

    178

    179

    180

    181

    182183

    184

    185

    186187

    188

    A B C D E F G H I J K L M N O P Q R S T U V W

    Multiple IRR's

    Consider the case of Project M.

    Project M: 0 1 2

    (1.6) 10 (10)

    IRR M1

    = 25.0%

    IRR M2

    = 400%

    Project M: 0 1 2

    (1.6) 10 (10)

    r = 25.0%NPV = 0.00

    The two solutions to this problem tell us that this project will have a positive NPV for all costs of capital between

    '25% and 400%. We illustrate this point by creating a data table and a graph of the project NPVs.

    Because of the mathematics involved, it is possible for some (but not all) projects that have more than one change of signs in the

    set of cash flows to have more than one IRR. If you attempted to find the IRR with such a project using a financial calculator,

    you would get an error message. The HP-10B says "Error - Soln", the HP-17B says '"Many/No Solutions, and the HP12C says

    Error 3; Key in Guess" when such a project is evaluated. The procedure for correcting the problem isto store in a guess for the

    IRR, and then the calculator will report the IRR that is closest to your guess. You can then use a different "guess" value, and

    you should be able to find the other IRR. However, the nature of the mathematics creates a scenario in which one IRR is quite

    extraordinary (often a few hundred percent).

    We will solve this IRR twice, the first time using the default guess of 10%, and the second time we will enter a guessof 300%. Notice, that the first IRR calculation is exactly as it was above.

  • 8/8/2019 Unit 11 Capital Budgeting Tool Kit

    5/10

    189

    190

    191

    192

    193

    194

    195

    196

    197

    198

    199

    200

    201

    202203

    204

    205

    206

    207

    208

    209

    210

    211

    212213

    214

    215

    216

    217

    218

    219

    220

    221

    222223

    224

    225

    226

    227

    228

    229

    230

    231

    232

    233

    234

    235

    236

    237

    238

    239

    240

    241242

    243

    244

    245

    246

    247

    248

    249

    250

    251

    252

    253

    A B C D E F G H I J K L M N O P Q R S T U V W

    NPV

    r $0.0

    0% (1.60)

    25% 0.00

    50% 0.62

    75% 0.85

    100% 0.90 Max.

    125% 0.87

    150% 0.80

    175% 0.71

    200% 0.62

    225% 0.53

    250% 0.44

    275% 0.36300% 0.28

    325% 0.20

    350% 0.13

    375% 0.06

    400% 0.00

    425% (0.06)

    450% (0.11)

    475% (0.16)

    500% (0.21)

    525% (0.26)550% (0.30)

    NPV Profiles

    Y ea r P ro jec t S P ro je ct L WACC = 10.0%

    0 -$1 ,0 00 -$1 ,0 00 Project S Project L

    1 $500 $100 NPV = $78.82 $49.182 $400 $300 IRR = 14.49% 11.79%

    3 $300 $400 Crossover 7.17%

    4 $100 $600

    Data Table used to make graph:

    S L

    WACC $78.82 $49.18

    0% $ 30 0.00 $ 40 0.00

    5% $ 18 0.42 $ 20 6.50

    7.17% $ 13 4.40 $ 13 4.40

    10% $78.82 $49. 18

    11.79% $46.10 $0.00

    14.49% $ 0. 00 - $6 8. 02

    15.0% - $8 .3 3 - $8 0. 14

    20% -$83.72 -$187.50

    25% -$149.44 -$277.44

    Points about the graphs:

    1. In Panel a, we see that if WACC < IRR, then NPV > 0, and vice versa.

    2. Thus, for "normal and independent" projects, there can be no conflict between NPV and IRR rankings.

    3. However, if we have mutually exclusive projects, conflicts can occur. In Panel b, we see that IRRS is

    always greater than IRRL, but if WACC < 11.56%, then IRRL > IRRS, in which case a conflict occurs.

    4. Summary: a. For normal, independent projects, conflict s can never occur, so either method can be used.

    b. For mutually exclusive projects, if WACC > Crossover, no conflict, but if WACC < Crossover,

    then there will be a conflict between NPV and IRR.

    NPV profiles graph the relationship between projects' NPVs and the cost of capital. To create NPV profiles for

    Projects S and L, we create data tables of NPV at different costs of capital.

    Net Cash Flows

    Project NPVs

    -$2.00

    -$1.50

    -$1.00

    -$0.50

    $0.00

    $0.50

    $1.00

    $1.50

    -100% 0% 100% 200% 300% 400% 500%

    Multiple Rates of Return

    -$200

    -$100

    $0

    $100

    $200

    $300

    $400

    0% 5% 10% 15% 20% 25%

    NPV

    WACC

    Project S'sNPV Profile

    -$400

    -$200

    $0

    $200

    $400

    $600

    0% 5% 10% 15% 20% 25%

    NPV

    WACC

    Both Projects' Profiles

    NPVsNPVL

    Crossover= 7.17%IRRS = 14.49%

    Accept Reject

    ConflictNo conflict

  • 8/8/2019 Unit 11 Capital Budgeting Tool Kit

    6/10

    254

    255

    256

    257

    258

    259

    260

    261

    262

    263

    264

    265

    266

    267268269

    270

    271

    272

    273

    274

    275

    276

    277

    278

    279280

    281

    282

    283

    284

    285

    286287

    288

    289

    290

    291

    292

    293

    294

    295

    296

    297

    298

    299

    A B C D E F G H I J K L M N O P Q R S T U V W

    Expected after-tax

    net cash flows (CF t) Cash flow Alternative: Use Tools > Goal Seek to find WACC when NPV(S) =

    Year (t) Project S Project L differential NPV(L). Set up a table to show the difference in NPV's, which we

    0 ($1,000) ($1,000) 0 want to be zero. The following will do it, getting WACC = 7.17%.

    1 500 100 400 Look at B57 for the answer, then restore B57 to 10%.

    2 400 300 100 NPV S = 78.82$

    3 300 400 (100) NPV L = 49.18$4 100 600 (500) S - L = 29.64$

    IRR = Crossover rate = 7.17%

    Modified Internal Rate of Return (MIRR)

    Previously, we had discussed that in some instances the NPV and IRR methods can give conflicting results. First, we

    should attempt to define what we see in this graph. Notice, that the two project profiles (S and L) intersect the x-

    axis at costs of capital of 14% and 12%, respectively. Not coincidently, those are the IRR's of the projects. If we

    think about the definition of IRR, we remember that the internal rate of return is the cost of capital at which a

    project will have an NPV of zero. Looking at our graph, it is a logical conclusion that the IRR of a project is defined

    as the point at which its profile intersects the x-axis.

    Looking further at the NPV profiles, we see that the two project profiles intersect at a point we shall call the

    crossover point. We observe that at costs of capital greater than the crossover point, the project with the greater

    IRR (Project S, in this case) also has the greater NPV. But at costs of capital less than the crossover point, the

    project with the lesser IRR has the greater NPV. This relationship is the source of discrepancy between the NPV

    and IRR methods. By looking at the graph, we see that the crossover appears to occur at approximately 7%.

    Luckily, there is a more precise way of determining crossover. To find crossover, we will find the difference betweenthe two projects cash flows in each year, and then find the IRR of this series of differential cash flows.

    The intuition behind the relationship between the NPV profile and the crossover rate is as follows: (1) Distant cash

    flows are heavily penalized by high discount rates--the denominator is (1+r)t, and it increases geometrically, hence

    gets very large at high values of t. (2) Long-term projects like L have most of their cash flows coming in the later

    years, when the discount penalty is largest, hence they are most severely impacted by high capital costs. (3)

    'Therefore, Project L's NPV profile is steeper than that of S. (4) Since the two profiles have different slopes, they

    cross one another.

    The modified internal rate of return is the discount rate that causes a project's cost (or cash outflows) to equal the

    'present value of the project's terminal value. The terminal value is defined as the sum of the future values of the

    'project's cash inflows, compounded at the project's cost of capital. To find MIRR, calculate the PV of the outflows

    'and the FV of the inflows, and then find the rate that equates the two. Or, you can solve using the MIRR function.

    G277

  • 8/8/2019 Unit 11 Capital Budgeting Tool Kit

    7/10

    300

    301

    302

    303

    304

    305

    306

    307

    308

    309

    310

    311

    312

    313314

    315

    316

    317

    318

    319

    320

    321

    322

    323

    324

    325

    326

    327

    328

    329

    330

    331

    332

    333

    334

    335

    A B C D E F G H I J K L M N O P Q R S T U V W

    WACC = 10% MIRRS = 12.11%

    Project S MIRRL = 11.33%

    10%

    0 1 2 3 4

    (1,000) 500 400 300 100

    Project L

    0 1 2 3 4

    (1,000) 100 300 400 600

    440.0

    363.0

    133.1

    P V : (1,000) Terminal Value: 1,536.1

    The advantage of using the MIRR, relative to the IRR, is that the MIRR assumes that cash flows received are

    reinvested at the cost of capital, not the IRR. Since reinvestment at the cost of capital is more likely, the MIRR is a

    'better indicator of a project's profitability. Moreover, it solves the multiple IRR problem, as a set of cash flows can

    have but one MIRR .

    Note that if negative cash flows occur in years beyond Year 1, those cash flows would be discounted at the cost of

    capital and added to the Year 0 cost to find the total PV of costs. If both positive and negative flows occurred in

    some year, the negative flow should be discounted, and the positive one compounded, rather than just dealing with

    the net cash flow. This makes a difference.

    Also note that Excel's MIRR function allows for discounting and reinvestment to occur at different rates. Generally,

    MIRR is defined as reinvestment at the WACC, though Excel allows the calculation of a special MIRR where

    reinvestment occurs at a different rate than WACC.

    Finally, it is stated in the text, when the IRR versus the NPV is discussed, that the NPV is superior because (1) the

    NPV assumes that cash flows are reinvested at the cost of capital whereas the IRR assumes reinvestment at the IRR,

    and (2) it is more likely, in a competitive world, that the actual reinvestment rate is more likely to be the cost of

    capital than the IRR, especially if the IRR is quite high. The MIRR setup can be used to prove that NPV indeeddoes assume reinvestment at the WACC, and IRR at the IRR.

    B304:F304

    B300

    B300

  • 8/8/2019 Unit 11 Capital Budgeting Tool Kit

    8/10

    336

    337

    338

    339

    340

    341

    342343

    344345

    346

    347

    348

    349350

    351

    352

    353

    354

    355

    356357

    358

    359

    360

    361

    362

    363

    364

    365

    366

    367

    368369

    370

    371

    372

    373

    374

    375

    376

    377

    378

    379

    380

    381

    382

    383

    384

    385

    386

    387

    A B C D E F G H I J K L M N O P Q R S T U V W

    Project S

    WACC = 10%

    0 1 2 3 4

    (1,000) 500 400 300 100

    330.0

    484.0 Reinvestment at WACC = 10%

    665.5PV outflows -$1,000.00 Terminal Value: 1,579.5

    PV of TV $1,078.82NPV 78.82$ Thus, we see that the NPV is consistent with reinvestment at WACC.

    Now repeat the process using the IRR, which is G118 as the discount rate.

    Project S

    IRR = 14.49%

    0 1 2 3 4

    (1,000) 500 400 300 100

    343.5

    524.3 Reinvestment at IRR = 14.49%

    750.3

    PV outflows -$1,000.00 Terminal Value: 1,718.1

    PV of TV $1,000.00NPV $0.00 Thus, if compounding is at the IRR, NPV is zero. Since the

    definition of IRR is the rate at which NPV = 0, this demonstrates

    that the IRR assumes reinvestment at the IRR.

    Profitability Index (PI)

    For project S:

    PI(S) = PV of future cash flows Initial costPI(S) = 1,078.82$ 1,000.00$

    PI(S) = 1.079

    For project L:

    PI(L) = PV of future cash flows Initial cost

    PI(L) = 1,049.18$ 1,000.00$

    PI(L) = 1.049

    PROJECTS WITH UNEQUAL LIVES

    If two mutually exclusive projects have different lives, and if the projects can be repeated, then it is necessary to deal explicitly

    with those unequal lives. We use the replacement chain (or common life) approach. This procedure compares projects of

    unequal lives by equalizing their lives by assuming that each project can be repeated as many times as necessary to reach a

    common life span. The NPVs over this life span are then compared, and the project with the higher common life NPV is chosen.

    To illustrate, suppose a firm is considering two mutually exclusive projects, either a conveyor system (Project C) or a fleet of

    forklift trucks (Project F) for moving materials. The firm's cost of capital is 12%. The cash flow timelines are shown below,

    'along with the NPV and IRR for each project.

    The profitability index is the present value of all future cash flows divided by the intial cost. It measures

    the PV per dollar of investment.

  • 8/8/2019 Unit 11 Capital Budgeting Tool Kit

    9/10

    388

    389

    390

    391

    392393

    394395

    396397

    398

    399

    400

    401402

    403404

    405

    406

    407

    408

    409

    410

    411

    412

    413

    414

    415

    416

    417

    418

    419

    420421

    422

    423

    424

    425426

    427

    428429

    430

    431

    432

    433

    434

    435

    436

    437

    438

    439

    440441

    442

    443

    444

    445

    446

    447

    448

    449

    450

    451

    452

    453

    A B C D E F G H I J K L M N O P Q R S T U V W

    Project C WA CC : 1 1. 5%

    0 1 2 3 4 5 6

    ($40,000) $8,000 $14,000 $13,000 $12,000 $11,000 $10,000

    NPV $7,165

    IRR 17.5%

    Project F

    0 1 2 3

    ($20,000) $7, 000 $13,000 $12,000

    NPV $5,391IRR 25.2%

    Common Life Approach

    Project C

    0 1 2 3 4 5 6

    ($40,000) $8,000 $14,000 $13,000 $12,000 $11,000 $10,000

    NPV $7,165IRR 17.5%

    Project F

    0 1 2 3 4 5 6

    ($20,000) $7, 000 $13,000 $12,000

    ($20,000) $7, 000 $13,000 $12, 000($20,000) $7,000 $13,000 ($8,000) $7,000 $13,000 $12,000

    NPV $9,281IRR 25.2%

    Equivalent Annual Annuity (EAA) Approach (See the Chapter 10 Web Extension for details.)

    Here are the steps in the EAA approach.

    1. Find the NPV of each project over its initial life (we already did this in our previous analysis).

    NPVC= 7,165

    NPVF= 5,391

    2. Convert the NPV into an annuity payment with a life equal to the life of the project.

    EE AC = 1 ,7 18 No te : w e us ed t he F unc ti on W iza rd f or t he P MT f unc ti on.

    EEAF= 2,225

    Project F has a higher EEA, so it is a better project.

    ECONOMIC LIFE VS. PHYSICAL LIFE

    On the basis of this extended analysis, it is clear that Project F is the better of the two investments (with both the

    NPV and IRR methods).

    Initially, it would appear that Project C is the better investment, based upon its higher NPV. However, if the firm chooses

    Project F, it would have the opportunity to make the same investment three years from now. Therefore, we must reevaluate

    Project F 'using extended common life of 6 years. The time lines are shown below. Note that only F's is changed.

    End of Period:

    End of Period:

    End of Period:

    Sometimes an asset has a physical life that is greater than its economic life. Consider the following asset

    which has a physical life of three years. During its life, the asset will generate operating cash flows.

    However, the project could be terminated and the asset sold at the end of any year. The following table

    shows the operating cash flows and the salvage value for each year-- all values are shown on an after-tax

    basis.

  • 8/8/2019 Unit 11 Capital Budgeting Tool Kit

    10/10

    454

    455

    456

    457

    458

    459

    460

    461

    462

    463464

    465

    466

    467

    468

    469

    470471

    472

    473

    474475

    476

    477

    A B C D E F G H I J K L M N O P Q R S T U V W

    Year

    Operating

    Cash Flow

    Salvage

    Value

    0 ( $4 ,8 00 ) $4 ,8 00

    1 $2,000 $3,000

    2 $2,000 $1,650

    3 $1,750 $0

    3-Year NPV = Intial Cost +

    PV of

    Operating

    Cash Flow+

    PV of

    Salvage

    Value

    = ($4,800.00) + $4,785.88 + $0.00

    3-Year NPV = ($14.12)

    2-Year NPV = Intial Cost +

    PV of

    Operating

    Cash Flow+

    PV of

    Salvage

    Value

    = ($4,800.00) + $3,471.07 + $1,363.64

    2-Year NPV = $34.71

    1-Year NPV = Intial Cost +

    PV of

    Operating

    Cash Flow+

    PV of

    Salvage

    Value

    = ($4,800.00) + $1,818.18 + $2,727.27

    1-Year NPV = ($254.55)

    The asset has a negative NPV if it is kept for three years. But even though the asset will last three years,

    it might be better to operate the asset for either one or two years, and then salvage it.

    The cost of capital is 10%. If the asset is operated for the entire three years of its life, its NPV is: