unit 11 capital budgeting tool kit
TRANSCRIPT
-
8/8/2019 Unit 11 Capital Budgeting Tool Kit
1/10
1
2
3
4
5
6
7
8
910
11
12
13
14
15
16
1718
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
3738
3940
41
42
43
44
45
46
47
4849
50
51
A B C D E F G H I J K L M N O P Q R S T U V W
Unit 11
Project S
Year (t) Project S Project L 0 1 2 3 4
0 ($1,000) ($1,000) (1,000) 500 400 300 100
1 500 100
2 400 300 Project L
3 300 4004 100 600 0 1 2 3 4
(1,000) 100 300 400 600
Capital Budgeting Decision Criteria
Payback Period
Project S
Time period: 0 1 2 3 4
Cash flow: (1,000) 500 400 300 100
Cumulative cash flow: (1,000) (500) (100) 200 300 Click fx > Logical > AND > OK to get dialog box.
FALSE FALSE FALSE TRUE FALSE Use Logical "AND" to determine Then specify you want TRUE if cumulative CF > 0 but the previous CF < 0.
0.00 0.00 0.00 2.33 0.00 the first positive cumulative CF.There will be one TRUE.
Payback: 2.33 Use Logical IF to find the PaybackClick fx > Logical > IF > OK. Specify that if true, the payback is the previous year plus a fraction, if false, then 0.
Use Statistical Max function to Click fx > Statistical > MAX > OK > and specify range to find Payback.
Alternative calculation: 2.33 display payback.
Project L
Time period: 0 1 2 3 4
Cash flow: (1,000) 100 300 400 600
Cumulative cash flow: (1,000) (900) (600) (200) 400
Payback: 3.33 Uses IF statement.
In this file we use Excel to do most of the calculations explained in Chapter 10. First, we analyze Projects S and L,
whose cash flows are shown immediately below in both tabular and a time line formats. Spreadsheet analyses can be
set up vertically, in a table with columns, or horizontally, using time lines. For short problems, with just a few years,
we generally use the time line format because rows can be added and we can set the problem up as a series of income
statements. For long problems, it is often more convenient to use a tabular layout.
Here are the five key methods used to evaluate projects: (1) payback period, (2) discounted payback period, (3) net
present value, (4) internal rate of return, and (5) modified internal rate of return. Using these criteria, financial
'analysts seek to identify those projects that will lead to the maximization of the firm's stock price.
The payback period is defined as the expected number of years required to recover the investment, and it was the
first formal method used to evaluate capital budgeting projects. First, we identify the year i n which the cumulative
cash inflows exceed the initial cash outflows. That is the payback year. Then we take the previous year and add to
it unrecovered balance at the end of that year divided by the following year's cash flow. Generally speaking, the
shorter the payback period, the better the investment.
Tool Kit for The Basics of Capital Budgeting: Evaluating Cash Flows
Expected after-tax
net cash flows (CF t)
-
8/8/2019 Unit 11 Capital Budgeting Tool Kit
2/10
52
53
54
55
56
57
58
59
60
61
62
63
64
6566
67
68
69
70
7172
73
74
75
76
77
78
79
80
81
82
83
8485
86
87
8889
90
91
92
93
94
9596
97
98
99
100
101
102
103
104
105
A B C D E F G H I J K L M N O P Q R S T U V W
Discounted Payback Period
WACC = 10%
Project S
Time period: 0 1 2 3 4
Cash flow: (1,000) 500 400 300 100
Disc. cash flow: (1,000) 455 331 225 68 Cash Flows Discounted back at 10%.
Disc. cum. cash flow: (1,000) (545) (215) 11 79
Discounted Payback: 2.95 Uses IF statement.
Project L
Time period: 0 1 2 3 4
Cash flow: (1,000) 100 300 400 600
Disc. cash flow: (1,000) 91 248 301 410
Disc. cum. cash flow: (1,000) (909) (661) (361) 49
Discounted Payback: 3.88 Uses IF statement.
Net Present Value (NPV)
WACC = 10%
Project S
Time period: 0 1 2 3 4
Cash flow: (1,000) 500 400 300 100
Disc. cash flow: (1,000) 455 331 225 68
NPV(S) = $78.82 = Sum disc. CF 's. or $78.82 = Uses NPV function.
Project L
Time period: 0 1 2 3 4
Cash flow: (1,000) 100 300 400 600
Disc. cash flow: (1,000) 91 248 301 410
NPV(L) = $49.18 49.18$ = Uses NPV function.
Discounted payback period uses the project's cost of capital to discount the expected cash flows. The calculation of
discounted payback period is identical to the calculation of regular payback period, except you must base the
calculation on a new row of discounted cash flows. Note that both projects have a cost of capital of 10%.
The inherent problem with both paybacks is that they ignore cash flows that occur after the payback period mark.
While the discounted method accounts for timing issues (to some extent), it still falls short of fully analyzing projects.
However, all else equal, these two methods do provide some information about projects' liquidity and risk.
To calculate the NPV, we find the present value of the individual cash flows and find the sum of those discounted
cash flows. This value represents the value the project add to shareholder wealth.
The NPV method of capital budgeting dictates that all independent projects that have positive NPV should accepted.
The rationale behind that assertion arises from the idea that all such projects add wealth, and that should be the
overall goal of the manager in all respects. If strictly using the NPV method to evaluate two mutually exclusive
projects, you would want to accept the project that adds the most value (i.e. the project with the higher NPV).
Hence, if considering the above two projects, you would accept both projects if they are independent, and you wouldonly accept Project S if they are mutually exclusive.
Notice that the NPV function isn't really a Net present value.
Instead, it is the present value of future cash flows. Thus, you
specify only the future cash flows in the NPV function. To find the
true NPV, you must add the time zero cash flow to the result of the
NPV function.
-
8/8/2019 Unit 11 Capital Budgeting Tool Kit
3/10
106
107
108
109
110
111
112113
114
115
116
117
118
119
120121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138139
140
141
142
143
144
145
146
147
148
149
A B C D E F G H I J K L M N O P Q R S T U V W
Internal Rate of Return (IRR)
Year (t) Project S Project L
0 ($1,000) ($1,000) The IRR function assumes
1 500 100 IRR S = 14.49% payments occur at end of
2 400 300 IRR L = 11.79% periods, so that function does
3 300 400 not have to be adjusted.4 100 600
Expected after-tax
The internal rate of return is defined as the discount rate that equates the present value of a project's cash inflows to
its outflows. In other words, the internal rate of return is the interest rate that forces NPV to zero. The calculation
for IRR can be tedious, but Excel provides an IRR function that merely requires you to access the function and
enter the array of cash flows. The IRR's for Project S and L are shown below, along with the data entry for Project
S.
net cash flows (CF t)
The IRR method of capital budgeting maintains that projects should be accepted if their IRR is greater than the cost
of capital. Strict adherence to the IRR method would further dictate that mutually exclusive project s should bechosen on the basis of the greatest IRR. In this scenario, both projects have IRR's that exceed the cost of capital
(10%) and both should be accepted, if they are independent. If, however, the projects are mutually exclusive, we
would chose Project S. Recall, that this was our determination using the NPV method as well. The question that
naturally arises is whether or not the NPV and IRR methods will always agree.
When dealing with independent projects, the NPV and IRR methods will always yield the same accept/reject result.
'However, in the case of mutually exclusive projects, NPV and IRR can give conflicting results. One shortcoming of
the internal rate of return is that it assumes that cash flows received are reinvested at the project's internal rate of
return, which is not usually true. The nature of the congruence of the NPV and IRR methods is further detailed in a
latter section of this model.
Notice that for IRR you mustspecify all cashflows, including the time zerocash flow. This is in contrastto the NPV function, in whichyou specify only the futurecash flows.
-
8/8/2019 Unit 11 Capital Budgeting Tool Kit
4/10
150
151
152
153
154
155
156
157
158
159
160
161
162
163164165
166
167
168
169170
171
172
173
174
175
176
177
178
179
180
181
182183
184
185
186187
188
A B C D E F G H I J K L M N O P Q R S T U V W
Multiple IRR's
Consider the case of Project M.
Project M: 0 1 2
(1.6) 10 (10)
IRR M1
= 25.0%
IRR M2
= 400%
Project M: 0 1 2
(1.6) 10 (10)
r = 25.0%NPV = 0.00
The two solutions to this problem tell us that this project will have a positive NPV for all costs of capital between
'25% and 400%. We illustrate this point by creating a data table and a graph of the project NPVs.
Because of the mathematics involved, it is possible for some (but not all) projects that have more than one change of signs in the
set of cash flows to have more than one IRR. If you attempted to find the IRR with such a project using a financial calculator,
you would get an error message. The HP-10B says "Error - Soln", the HP-17B says '"Many/No Solutions, and the HP12C says
Error 3; Key in Guess" when such a project is evaluated. The procedure for correcting the problem isto store in a guess for the
IRR, and then the calculator will report the IRR that is closest to your guess. You can then use a different "guess" value, and
you should be able to find the other IRR. However, the nature of the mathematics creates a scenario in which one IRR is quite
extraordinary (often a few hundred percent).
We will solve this IRR twice, the first time using the default guess of 10%, and the second time we will enter a guessof 300%. Notice, that the first IRR calculation is exactly as it was above.
-
8/8/2019 Unit 11 Capital Budgeting Tool Kit
5/10
189
190
191
192
193
194
195
196
197
198
199
200
201
202203
204
205
206
207
208
209
210
211
212213
214
215
216
217
218
219
220
221
222223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241242
243
244
245
246
247
248
249
250
251
252
253
A B C D E F G H I J K L M N O P Q R S T U V W
NPV
r $0.0
0% (1.60)
25% 0.00
50% 0.62
75% 0.85
100% 0.90 Max.
125% 0.87
150% 0.80
175% 0.71
200% 0.62
225% 0.53
250% 0.44
275% 0.36300% 0.28
325% 0.20
350% 0.13
375% 0.06
400% 0.00
425% (0.06)
450% (0.11)
475% (0.16)
500% (0.21)
525% (0.26)550% (0.30)
NPV Profiles
Y ea r P ro jec t S P ro je ct L WACC = 10.0%
0 -$1 ,0 00 -$1 ,0 00 Project S Project L
1 $500 $100 NPV = $78.82 $49.182 $400 $300 IRR = 14.49% 11.79%
3 $300 $400 Crossover 7.17%
4 $100 $600
Data Table used to make graph:
S L
WACC $78.82 $49.18
0% $ 30 0.00 $ 40 0.00
5% $ 18 0.42 $ 20 6.50
7.17% $ 13 4.40 $ 13 4.40
10% $78.82 $49. 18
11.79% $46.10 $0.00
14.49% $ 0. 00 - $6 8. 02
15.0% - $8 .3 3 - $8 0. 14
20% -$83.72 -$187.50
25% -$149.44 -$277.44
Points about the graphs:
1. In Panel a, we see that if WACC < IRR, then NPV > 0, and vice versa.
2. Thus, for "normal and independent" projects, there can be no conflict between NPV and IRR rankings.
3. However, if we have mutually exclusive projects, conflicts can occur. In Panel b, we see that IRRS is
always greater than IRRL, but if WACC < 11.56%, then IRRL > IRRS, in which case a conflict occurs.
4. Summary: a. For normal, independent projects, conflict s can never occur, so either method can be used.
b. For mutually exclusive projects, if WACC > Crossover, no conflict, but if WACC < Crossover,
then there will be a conflict between NPV and IRR.
NPV profiles graph the relationship between projects' NPVs and the cost of capital. To create NPV profiles for
Projects S and L, we create data tables of NPV at different costs of capital.
Net Cash Flows
Project NPVs
-$2.00
-$1.50
-$1.00
-$0.50
$0.00
$0.50
$1.00
$1.50
-100% 0% 100% 200% 300% 400% 500%
Multiple Rates of Return
-$200
-$100
$0
$100
$200
$300
$400
0% 5% 10% 15% 20% 25%
NPV
WACC
Project S'sNPV Profile
-$400
-$200
$0
$200
$400
$600
0% 5% 10% 15% 20% 25%
NPV
WACC
Both Projects' Profiles
NPVsNPVL
Crossover= 7.17%IRRS = 14.49%
Accept Reject
ConflictNo conflict
-
8/8/2019 Unit 11 Capital Budgeting Tool Kit
6/10
254
255
256
257
258
259
260
261
262
263
264
265
266
267268269
270
271
272
273
274
275
276
277
278
279280
281
282
283
284
285
286287
288
289
290
291
292
293
294
295
296
297
298
299
A B C D E F G H I J K L M N O P Q R S T U V W
Expected after-tax
net cash flows (CF t) Cash flow Alternative: Use Tools > Goal Seek to find WACC when NPV(S) =
Year (t) Project S Project L differential NPV(L). Set up a table to show the difference in NPV's, which we
0 ($1,000) ($1,000) 0 want to be zero. The following will do it, getting WACC = 7.17%.
1 500 100 400 Look at B57 for the answer, then restore B57 to 10%.
2 400 300 100 NPV S = 78.82$
3 300 400 (100) NPV L = 49.18$4 100 600 (500) S - L = 29.64$
IRR = Crossover rate = 7.17%
Modified Internal Rate of Return (MIRR)
Previously, we had discussed that in some instances the NPV and IRR methods can give conflicting results. First, we
should attempt to define what we see in this graph. Notice, that the two project profiles (S and L) intersect the x-
axis at costs of capital of 14% and 12%, respectively. Not coincidently, those are the IRR's of the projects. If we
think about the definition of IRR, we remember that the internal rate of return is the cost of capital at which a
project will have an NPV of zero. Looking at our graph, it is a logical conclusion that the IRR of a project is defined
as the point at which its profile intersects the x-axis.
Looking further at the NPV profiles, we see that the two project profiles intersect at a point we shall call the
crossover point. We observe that at costs of capital greater than the crossover point, the project with the greater
IRR (Project S, in this case) also has the greater NPV. But at costs of capital less than the crossover point, the
project with the lesser IRR has the greater NPV. This relationship is the source of discrepancy between the NPV
and IRR methods. By looking at the graph, we see that the crossover appears to occur at approximately 7%.
Luckily, there is a more precise way of determining crossover. To find crossover, we will find the difference betweenthe two projects cash flows in each year, and then find the IRR of this series of differential cash flows.
The intuition behind the relationship between the NPV profile and the crossover rate is as follows: (1) Distant cash
flows are heavily penalized by high discount rates--the denominator is (1+r)t, and it increases geometrically, hence
gets very large at high values of t. (2) Long-term projects like L have most of their cash flows coming in the later
years, when the discount penalty is largest, hence they are most severely impacted by high capital costs. (3)
'Therefore, Project L's NPV profile is steeper than that of S. (4) Since the two profiles have different slopes, they
cross one another.
The modified internal rate of return is the discount rate that causes a project's cost (or cash outflows) to equal the
'present value of the project's terminal value. The terminal value is defined as the sum of the future values of the
'project's cash inflows, compounded at the project's cost of capital. To find MIRR, calculate the PV of the outflows
'and the FV of the inflows, and then find the rate that equates the two. Or, you can solve using the MIRR function.
G277
-
8/8/2019 Unit 11 Capital Budgeting Tool Kit
7/10
300
301
302
303
304
305
306
307
308
309
310
311
312
313314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
A B C D E F G H I J K L M N O P Q R S T U V W
WACC = 10% MIRRS = 12.11%
Project S MIRRL = 11.33%
10%
0 1 2 3 4
(1,000) 500 400 300 100
Project L
0 1 2 3 4
(1,000) 100 300 400 600
440.0
363.0
133.1
P V : (1,000) Terminal Value: 1,536.1
The advantage of using the MIRR, relative to the IRR, is that the MIRR assumes that cash flows received are
reinvested at the cost of capital, not the IRR. Since reinvestment at the cost of capital is more likely, the MIRR is a
'better indicator of a project's profitability. Moreover, it solves the multiple IRR problem, as a set of cash flows can
have but one MIRR .
Note that if negative cash flows occur in years beyond Year 1, those cash flows would be discounted at the cost of
capital and added to the Year 0 cost to find the total PV of costs. If both positive and negative flows occurred in
some year, the negative flow should be discounted, and the positive one compounded, rather than just dealing with
the net cash flow. This makes a difference.
Also note that Excel's MIRR function allows for discounting and reinvestment to occur at different rates. Generally,
MIRR is defined as reinvestment at the WACC, though Excel allows the calculation of a special MIRR where
reinvestment occurs at a different rate than WACC.
Finally, it is stated in the text, when the IRR versus the NPV is discussed, that the NPV is superior because (1) the
NPV assumes that cash flows are reinvested at the cost of capital whereas the IRR assumes reinvestment at the IRR,
and (2) it is more likely, in a competitive world, that the actual reinvestment rate is more likely to be the cost of
capital than the IRR, especially if the IRR is quite high. The MIRR setup can be used to prove that NPV indeeddoes assume reinvestment at the WACC, and IRR at the IRR.
B304:F304
B300
B300
-
8/8/2019 Unit 11 Capital Budgeting Tool Kit
8/10
336
337
338
339
340
341
342343
344345
346
347
348
349350
351
352
353
354
355
356357
358
359
360
361
362
363
364
365
366
367
368369
370
371
372
373
374
375
376
377
378
379
380
381
382
383
384
385
386
387
A B C D E F G H I J K L M N O P Q R S T U V W
Project S
WACC = 10%
0 1 2 3 4
(1,000) 500 400 300 100
330.0
484.0 Reinvestment at WACC = 10%
665.5PV outflows -$1,000.00 Terminal Value: 1,579.5
PV of TV $1,078.82NPV 78.82$ Thus, we see that the NPV is consistent with reinvestment at WACC.
Now repeat the process using the IRR, which is G118 as the discount rate.
Project S
IRR = 14.49%
0 1 2 3 4
(1,000) 500 400 300 100
343.5
524.3 Reinvestment at IRR = 14.49%
750.3
PV outflows -$1,000.00 Terminal Value: 1,718.1
PV of TV $1,000.00NPV $0.00 Thus, if compounding is at the IRR, NPV is zero. Since the
definition of IRR is the rate at which NPV = 0, this demonstrates
that the IRR assumes reinvestment at the IRR.
Profitability Index (PI)
For project S:
PI(S) = PV of future cash flows Initial costPI(S) = 1,078.82$ 1,000.00$
PI(S) = 1.079
For project L:
PI(L) = PV of future cash flows Initial cost
PI(L) = 1,049.18$ 1,000.00$
PI(L) = 1.049
PROJECTS WITH UNEQUAL LIVES
If two mutually exclusive projects have different lives, and if the projects can be repeated, then it is necessary to deal explicitly
with those unequal lives. We use the replacement chain (or common life) approach. This procedure compares projects of
unequal lives by equalizing their lives by assuming that each project can be repeated as many times as necessary to reach a
common life span. The NPVs over this life span are then compared, and the project with the higher common life NPV is chosen.
To illustrate, suppose a firm is considering two mutually exclusive projects, either a conveyor system (Project C) or a fleet of
forklift trucks (Project F) for moving materials. The firm's cost of capital is 12%. The cash flow timelines are shown below,
'along with the NPV and IRR for each project.
The profitability index is the present value of all future cash flows divided by the intial cost. It measures
the PV per dollar of investment.
-
8/8/2019 Unit 11 Capital Budgeting Tool Kit
9/10
388
389
390
391
392393
394395
396397
398
399
400
401402
403404
405
406
407
408
409
410
411
412
413
414
415
416
417
418
419
420421
422
423
424
425426
427
428429
430
431
432
433
434
435
436
437
438
439
440441
442
443
444
445
446
447
448
449
450
451
452
453
A B C D E F G H I J K L M N O P Q R S T U V W
Project C WA CC : 1 1. 5%
0 1 2 3 4 5 6
($40,000) $8,000 $14,000 $13,000 $12,000 $11,000 $10,000
NPV $7,165
IRR 17.5%
Project F
0 1 2 3
($20,000) $7, 000 $13,000 $12,000
NPV $5,391IRR 25.2%
Common Life Approach
Project C
0 1 2 3 4 5 6
($40,000) $8,000 $14,000 $13,000 $12,000 $11,000 $10,000
NPV $7,165IRR 17.5%
Project F
0 1 2 3 4 5 6
($20,000) $7, 000 $13,000 $12,000
($20,000) $7, 000 $13,000 $12, 000($20,000) $7,000 $13,000 ($8,000) $7,000 $13,000 $12,000
NPV $9,281IRR 25.2%
Equivalent Annual Annuity (EAA) Approach (See the Chapter 10 Web Extension for details.)
Here are the steps in the EAA approach.
1. Find the NPV of each project over its initial life (we already did this in our previous analysis).
NPVC= 7,165
NPVF= 5,391
2. Convert the NPV into an annuity payment with a life equal to the life of the project.
EE AC = 1 ,7 18 No te : w e us ed t he F unc ti on W iza rd f or t he P MT f unc ti on.
EEAF= 2,225
Project F has a higher EEA, so it is a better project.
ECONOMIC LIFE VS. PHYSICAL LIFE
On the basis of this extended analysis, it is clear that Project F is the better of the two investments (with both the
NPV and IRR methods).
Initially, it would appear that Project C is the better investment, based upon its higher NPV. However, if the firm chooses
Project F, it would have the opportunity to make the same investment three years from now. Therefore, we must reevaluate
Project F 'using extended common life of 6 years. The time lines are shown below. Note that only F's is changed.
End of Period:
End of Period:
End of Period:
Sometimes an asset has a physical life that is greater than its economic life. Consider the following asset
which has a physical life of three years. During its life, the asset will generate operating cash flows.
However, the project could be terminated and the asset sold at the end of any year. The following table
shows the operating cash flows and the salvage value for each year-- all values are shown on an after-tax
basis.
-
8/8/2019 Unit 11 Capital Budgeting Tool Kit
10/10
454
455
456
457
458
459
460
461
462
463464
465
466
467
468
469
470471
472
473
474475
476
477
A B C D E F G H I J K L M N O P Q R S T U V W
Year
Operating
Cash Flow
Salvage
Value
0 ( $4 ,8 00 ) $4 ,8 00
1 $2,000 $3,000
2 $2,000 $1,650
3 $1,750 $0
3-Year NPV = Intial Cost +
PV of
Operating
Cash Flow+
PV of
Salvage
Value
= ($4,800.00) + $4,785.88 + $0.00
3-Year NPV = ($14.12)
2-Year NPV = Intial Cost +
PV of
Operating
Cash Flow+
PV of
Salvage
Value
= ($4,800.00) + $3,471.07 + $1,363.64
2-Year NPV = $34.71
1-Year NPV = Intial Cost +
PV of
Operating
Cash Flow+
PV of
Salvage
Value
= ($4,800.00) + $1,818.18 + $2,727.27
1-Year NPV = ($254.55)
The asset has a negative NPV if it is kept for three years. But even though the asset will last three years,
it might be better to operate the asset for either one or two years, and then salvage it.
The cost of capital is 10%. If the asset is operated for the entire three years of its life, its NPV is: